Created byFuzzy Cloud

Supreme Court of India

SANJIT SINGH SALWAN & ORS.versusSARDAR INDERJIT SINGH SALWAN & ORS.

Citation
2025 INSC 988
Decided
14 August 2025
Disposal
Appeal(s) allowed

Holding

The respondents are estopped by their prior acceptance of the arbitral award and compromise decree and cannot claim the award is a nullity; the appeal is allowed and execution proceedings may be revived.

Summary

The appellants and respondents, both claiming to be trustees of a charitable trust, were involved in a dispute that led the respondents to file a suit for perpetual injunction. The trial court dismissed the suit under Section 92 of the CPC, prompting an appeal during which the parties agreed to arbitration and later accepted the arbitrator's award, filing a joint application to have the appeal disposed of on the basis of a compromise deed dated 02‑01‑2023. The award was later challenged by the respondents as a nullity on the ground that the matters were non‑arbitrable under Section 92, leading the Commercial Court and the High Court to reject the appellants' application under Section 9 of the Arbitration Act. The Supreme Court held that the respondents, having previously accepted the award and compromise deed, are estopped from now contesting its validity, as the doctrine of estoppel by conduct and election precludes a diametrically opposite stance. Consequently, the Court set aside the lower courts' orders and allowed the appellants to revive their execution proceedings. The appeal was therefore allowed.

Issues considered

  • Whether a party can raise a plea of estoppel in law after having previously accepted an arbitral award and compromise decree, thereby taking a contrary position.
  • Whether the arbitral award is a nullity under Section 92 of the Code of Civil Procedure and whether the doctrine of estoppel by conduct/election bars the respondents from raising that plea.

Legislation cited

Headnote

Issue for Consideration Issue arose as regards to whether a plea of estoppel in law can be permitted to be raised by a party ignoring its conduct that resulted in the other party altering its position to its detriment in view of such conduct. Headnotes† Code of Civil s.92 – Arbitration and Conciliation Act, 1996 – ss.9, 37 – Estoppel in law – Doctrine of estoppel by conduct – Doctrine of election – Appellants and the respondents claim to be trustees of a Charitable Trust – Dispute arose between them –

Subjects

Estoppel in lawDoctrine of estoppel by conductDoctrine of electionCompromise decreeConsent decreeArbitration award nullitySection 92 CPCSection 9 Arbitration ActSection 37 Arbitration ActCharitable trust dispute

Judgment

                 [2025] 8 S.C.R. 902 : 2025 INSC 988

                     Sanjit Singh Salwan & Ors.
                                   v.
                 Sardar Inderjit Singh Salwan & Ors.
                      (Civil Appeal No. 10653 of 2025)
                                14 August 2025
   [Augustine George Masih and Atul S. Chandurkar,* JJ.]


                            Issue for Consideration
       Issue arose as regards to whether a plea of estoppel in law can
       be permitted to be raised by a party ignoring its conduct that
       resulted in the other party altering its position to its detriment in
       view of such conduct.

                                   Headnotes†
       Code of Civil Procedure, 1908 – s.92 – Arbitration and
       Conciliation Act, 1996 – ss.9, 37 – Estoppel in law – Doctrine of
       estoppel by conduct – Doctrine of election – Appellants and the
       respondents claim to be trustees of a Charitable Trust – Dispute
       arose between them – Respondents filed a suit for perpetual
       injunction against the appellants – Trial Court rejected the
       plaint u/Or. VII r.11 holding that in view of s.92 of the Code,
       the suit was barred – Respondent filed appeal – During the
       pendency of the appeal, respondents moved an application
       in which it was stated that the parties had appointed a sole
       arbitrator to resolve their disputes – Sole Arbitrator passed
       an award – Thereafter, parties moved a joint application in the
       pending appeal seeking disposal of the appeal in terms of the
       award dated 30.12.2022 passed in arbitration – Accordingly,
       appeal was disposed of in terms of the award – Said award
       formed the part of the compromise decree – This decree was
       not challenged – Respondents allegedly failed to discharge
       their obligation under the award – Appellants filed for execution
       of compromise decree but, later withdrew to file application
       u/s.9 of the Arbitration Act – The Commercial Court went into
       the issue of arbitrability of the disputes between the parties
       and declared award as a nullity – High Court dismissed the
       appeal – Respondents contended that consent decree was
       not binding on them – Correctness:

* Author
[2025] 8 S.C.R.                                                             903

   Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


     Held: The issue is more about estoppel by conduct and election
     rather than estoppel in law – It would be impermissible for the
     respondents to take such opposite stand from the one that they
     had taken while initiating the proceedings – Having specifically
     pleaded that the suit filed by them was not hit by the provisions
     of s.92 of Code, it would not be now open for them to oppose the
     validity of the compromise deed dated 02.01.2023 by raising such
     ground – The pleadings of the respondents clearly indicate the
     conscious stand taken by them in the initial round of the present
     litigation – They had stated on more than one occasion that the
     proceedings initiated by them were maintainable and that the same
     were required to be decided on merits – They willingly had the
     matter referred for settlement and when the award was passed
     on 30.12.2022 they sought disposal of their appeal in terms of the
     compromise deed that was prepared on the basis of the award
     dated 30.12.2022 – The respondents therefore by their conduct
     are now estopped from taking an opposite stand – Therefore, on
     the doctrine of estoppel by conduct and election the respondents
     cannot be permitted to now raise a plea that the compromise
     deed based on the award dated 30.12.2022 was a nullity in view
     of the provisions of s.92 of the Code – Non-suiting the appellants
     on the ground that the award dated 30.12.2022 was a nullity in
     view of the objection raised by the respondents has resulted in
     grave injustice to the appellants – The justice of the case therefore
     requires that the appellants ought to be permitted to revive the
     execution proceedings that they had filed – Thus, the appellants
     are at liberty to revive the execution proceedings in the form of
     Miscellaneous Case. [Paras 14, 17, 19, 20, 21]

                              Case Law Cited
     Dhiyan Singh and Another v. Jugal Kishore and Another [1952]
     1 SCR 478 : AIR 1952 SC 145; R.N. Gosain v. Yashpal Dhir
     [1992] Supp. 2 SCR 257 : SLP(C) No. 4325 of 1992 (decided on
     23.10.1992) – relied on.
     Suzuki Parasrampuria Suitings Private Ltd. v. Official Liquidator
     of Mahendra Petrochemicals Limited & Ors. [2018] 12 SCR 906 :
     (2018) 10 SCC 707; Joint Action Committee of Air Line Pilots’
     Association of India (ALPAI) & Ors. v. Director General of Civil
     Aviation and Ors. [2011] 5 SCR 1019 : (2011) 5 SCC 435; Mumbai
904                                                                  [2025] 8 S.C.R.

                             Supreme Court Reports


       International Airport Private Ltd. v. Golden Chariot Airport and Anr.
       [2010] 12 SCR 326 : (2010) 10 SCC 422; Karam Kapahi and Ors. v.
       Lal Chand Public Charitable Trust and Anr. [2010] 4 SCR 422 :
       (2010) 4 SCC 753; Indore Development Authority v. Manoharlal &
       Ors. [2020] 3 SCR 1 : (2020) 8 SCC 129; Kavita Trehan & Anr. v.
       Balsara Hygiene Products Ltd. [1994] Supp. 1 SCR 340 : (1994)
       5 SCC 380; Vimal Kishor Shah and Others v. Jayesh Dinesh Shah
       and Others [2016] 7 SCR 102 : (2016) 8 SCC 788; Booz Allen &
       Hamilton Inc. v. SBI Home Finance Ltd. and Others [2011] 7 SCR
       310 : (2011) 5 SCC 532; Sunder Dass v. Ram Prakash [1977] 3
       SCR 60 : (1977) 2 SCC 662; Prem Singh and Ors. v. Birbal & Ors.
       [2006] Supp. 1 SCR 692 : (2006) 5 SCC 353; State of Rajasthan
       and Another v. Surendra Mohnot and Others [2014] 6 SCR 191 :
       (2014) 14 SCC 77 – referred to.

                                     List of Acts
       Code of Civil Procedure, 1908; Arbitration and Conciliation Act,
       1996.

                                 List of Keywords
       Estoppel in law; Doctrine of estoppel by conduct; Doctrine of
       election; Approbation and reprobation; Conduct of parties; Appellant
       left without any remedy; Compromise decree; Consent decree;
       Nullity of arbitral award; Issue of arbitrability of dispute; Diametrically
       opposite stand taken by respondent; De hors.

                                Case Arising From
       CIVIL APPELLATE JURISDICTION : Civil Appeal No. 10653 of 2025
       From the Judgment and Order dated 30.08.2024 of the High Court
       of Judicature at Allahabad in AUS37AACA No. 356 of 2024

                             Appearances for Parties
       Advs. for the Appellants:
       C. U. Singh, Sr. Adv., Punit Dutt Tyagi, Ms. Smriti Sahai, Shikhar
       Tyagi, Ms. Pragati Singh.
       Advs. for the Respondents:
       Gagan Gupta, Sr. Adv., Sanchit Garga, Amit Wadhwa, Shashwat
       Jaiswal.
[2025] 8 S.C.R.                                                            905

     Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


                  Judgment / Order of the Supreme Court

                                  Judgment

       Atul S. Chandurkar, J.

1.     Leave granted.
2.     The issue that arises for consideration in these proceedings is
       whether a plea of estoppel in law can be permitted to be raised by
       a party ignoring its conduct that resulted in the other party altering
       its position to its detriment in view of such conduct.
3.     Facts relevant for deciding the Civil Appeal are that the appellants and
       the respondents claim to be trustees of Guru Tegh Bahadur Charitable
       Trust (hereinafter referred to as ‘the Trust’). On disputes arising
       between the parties, the respondents claimed that the appellants
       had been removed as trustees. The respondents approached the
       Civil Court by filing a suit for perpetual injunction seeking to restrain
       the appellants from entering the school being conducted by the Trust
       and also from interfering with the functioning of the school. The
       appellants filed an application under provisions of Order VII Rule 11
       of the Code of Civil Procedure, 1908 (hereinafter referred to as ‘the
       Code’) seeking rejection of the plaint. The Trial Court on 13.04.2022,
       accepted the contentions of the appellants and rejected the plaint
       holding that in view of Section 92 of the Code, the suit was barred.
       The respondents being aggrieved by the dismissal of their suit filed
       an appeal before the District Court. During the pendency of the
       appeal, the respondents moved an application dated 07.07.2022 in
       which it was stated that the appellants as well as the respondents
       had appointed a sole arbitrator to resolve their disputes after which
       the process of arbitration had been undertaken. It was stated that the
       appeal filed by them be decided on the basis of the award passed
       by the sole arbitrator.
4.     On 30.12.2022, the sole arbitrator passed his award and made an
       arrangement between the parties as regards the manner of managing
       the affairs of the Trust. In view of the said award, the parties moved
       a joint application in the pending appeal before the District Court on
       02.01.2023 stating therein that they had accepted the award and
       that they would abide by it in true spirit. They sought disposal of the
       appeal in terms of the award. Accordingly, on 27.01.2023, the District
906                                                            [2025] 8 S.C.R.

                           Supreme Court Reports


       Court disposed of the appeal in terms of the award dated 30.12.2022.
       It was directed that the compromise deed recording the said award
       would form part of the decree. It is common ground that this decree
       passed by the District Court on 27.01.2023 was not challenged any
       further and the same continues to hold field even today.
5.     According to the appellants, they took various steps in terms of the
       award so as to comply with their part of obligations. It was their
       grievance that the respondents however failed to discharge their
       obligations under the award. Ultimately, on 23.11.2023 the appellants
       filed Miscellaneous Case No.122 of 2023 seeking to execute the
       aforesaid compromise decree. The said proceedings however
       were withdrawn by the appellants on 08.12.2023, after which the
       appellants filed an application under Section 9 of the Arbitration and
       Conciliation Act, 1996 (hereinafter referred to as “the Act of 1996”). In
       the said proceedings, the appellants sought various interim measures
       in terms of the arbitral award. This application was opposed by
       the respondents. The learned Judge of the Commercial Court on
       24.05.2024 went into the issue of arbitrability of the disputes between
       the parties and on finding that the disputes pertained to the affairs
       of the Trust held that in view of the provisions of Section 92 of the
       Code, the arbitrator could not have gone into the same. It was held
       that the award dated 30.12.2022 was a nullity and hence there was
       no question of its enforcement. Accordingly, the application filed by the
       appellants under Section 9 of the Act of 1996 came to be rejected.
       The appellants, being aggrieved, filed an appeal under Section 37 of
       the Act of 1996. The High Court declined to interfere with the order
       passed by the Commercial Court and affirmed the finding that the
       dispute was non-arbitrable. The High Court accordingly dismissed
       the said appeal on 30.08.2024. The appellants being aggrieved by
       the aforesaid decision have approached this Court.
6.     Mr. C.U. Singh, learned Senior Advocate for the appellants submitted
       that the parties having accepted the award passed by the arbitrator
       on 31.10.2022 which thereafter resulted in a consent decree being
       passed by the District Court on 27.01.2023, it was not permissible
       for the respondents to disregard the same and contend that the
       consent decree was not binding upon them. In fact, the consent
       decree had become final and therefore the appellants were justified
       in seeking interim measures on that basis under Section 9 of the Act
       of 1996. The appellants in accordance with the terms of the consent
[2025] 8 S.C.R.                                                           907

     Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


       decree had complied with their obligations by taking necessary
       steps but no reciprocal steps were taken by the respondents. The
       respondents had consented to the passing of the consent decree in
       the suit filed by them. Hence, by their conduct they were estopped
       from questioning the validity of the consent decree and raising the
       ground of non-arbitrability. In this regard reliance was placed on the
       decisions of this Court in Suzuki Parasrampuria Suitings Private
       Ltd. v. Official Liquidator of Mahendra Petrochemicals Limited
       & Ors., (2018) 10 SCC 707, Joint Action Committee of Air Line
       Pilots’ Association of India (ALPAI) & Ors. v. Director General of
       Civil Aviation and Ors., (2011) 5 SCC 435, Mumbai International
       Airport Private Ltd. v. Golden Chariot Airport and Anr., (2010)
       10 SCC 422 and Karam Kapahi and Ors. v. Lal Chand Public
       Charitable Trust and Anr., (2010) 4 SCC 753. The conduct of
       the respondents disentitled them to oppose the enforcement of the
       consent decree as it had become final.
       Without prejudice to the aforesaid contentions, it was urged that
       even if it was to be held that in view of Section 92 of the Code, the
       disputes were non-arbitrable, the appellants were entitled to the fruits
       of the consent decree. The appellants had in fact filed execution
       proceedings but the same were withdrawn so as to invoke the
       provisions of Section 9 of the Act of 1996. As a result of the impugned
       orders, the appellants were left without any remedy whatsoever
       despite the existence of a consent decree that had attained finality.
       Reference in this regard was made to the decisions of this Court
       in Indore Development Authority v. Manoharlal & Ors., (2020) 8
       SCC 129 and Kavita Trehan & Anr. v. Balsara Hygiene Products
       Ltd., (1994) 5 SCC 380. It was thus urged that this Court ought to
       exercise jurisdiction so as to enable the appellants to enjoy the fruits
       of the consent decree.
7.     On the other hand, Mr. Gagan Gupta, learned Senior Advocate for the
       respondents while opposing the appeal submitted that notwithstanding
       the passing of the consent decree, the Commercial Court was justified
       in holding the award dated 30.12.2022 to be a nullity. The issues
       dealt with by the sole arbitrator related to affairs of the Trust. In
       view of Section 92 of the Code, the same could not have been the
       subject matter of arbitration. It was submitted that the award dated
       30.12.2022 and the subsequent order passed by the District Court
       could not be treated to be a consent decree. The appeal was merely
908                                                           [2025] 8 S.C.R.

                           Supreme Court Reports


       disposed of on the joint application of the parties. The Commercial
       Court therefore rightly held the award to be a nullity which could not
       be executed. Since the arbitrator had dealt with an issue over which
       he had no jurisdiction, this aspect went to the root of the matter and
       could be raised at any point of time. The Commercial Court therefore
       in proceedings filed under Section 9 of the Act of 1996 rightly refused
       to grant any interim measures under Section 9 of the Act of 1996.
       Reliance was placed on the decisions of this Court in Vimal Kishor
       Shah and others v. Jayesh Dinesh Shah and others, (2016) 8
       SCC 788 and Booz Allen & Hamilton Inc. v. SBI Home Finance
       Ltd. and others, (2011) 5 SCC 532. It was also urged that the
       appellants having themselves withdrawn the execution proceedings
       for invoking the jurisdiction under Section 9 of the Act of 1996, they
       could not be now permitted to contend that they should be permitted
       to execute the consent decree. In any event, since the award had
       been held to be a nullity there was no question of it being executed.
       Reliance was placed on the decisions of this Court in Sunder Dass v.
       Ram Prakash, (1977) 2 SCC 662 and Prem Singh and Ors. v.
       Birbal & Ors., (2006) 5 SCC 353. To urge that there could be no
       estoppel against law, reliance was placed on State of Rajasthan
       and another v. Surendra Mohnot and others, (2014) 14 SCC 77.
       It was thus submitted that the appellants had been rightly denied
       the relief and the impugned orders did not warrant any interference.
8.     We have heard the learned counsel for the parties at length and
       with their assistance we have also perused the documentary
       material on record. At the outset, it would be necessary to refer
       to certain admitted facts on record. The Trust deed in question is
       dated 15.10.1979 which indicates various objects of the Trust. The
       same include providing for educational facilities in various fields by
       establishing and maintaining institutions of learning. Various other
       ancillary objects have been stated therein. The respondents being
       aggrieved by the alleged interference of the appellants in the affairs
       of the Trust approached the Civil Court by filing a suit for perpetual
       injunction seeking to restrain the appellants from entering the premises
       of the school being run by the Trust and also from interfering with
       the functioning of the said school. In paragraphs 19A to 19C of the
       plaint, the respondents pleaded as under:
            “19A. That the relief claimed in the present suit does not
            fall within the ambit and scope of Sec. 92 CPC. Provisions
[2025] 8 S.C.R.                                                             909

     Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


            of Section 92 CPC in the matter of dispute is not at all
            attracted. The suit has not been filed, seeking relief
            pertaining to any matter enumerated in Section 92 CPC.
            19B. That the suit is not barred by any of the Provisions
            of Arbitration & Conciliation Act 1996, because the subject
            matter and relief of the suit does not tantamount to dispute
            which can be referred to Arbitration. The terms of the Trust
            Deed do not attract any Arbitration Clause. The present
            parties to the suit were not signatories of the Trust Deed.
            19C. That this Hon’ble Court u/S. 9 CPC has jurisdiction
            to hear and decide the suit.”
                                                    (Emphasis supplied)

9.     It was the appellants who sought to raise an objection to the jurisdiction
       of the Civil Court by raising a ground that the suit was barred by law
       in view of Section 92 of the Code. This application was opposed by
       the respondents asserting that the suit was legally tenable. The Trial
       Court by its order dated 13.04.2022 proceeded to hold that in view
       of Section 92 of the Code, the Civil Court had no jurisdiction to try
       the same. The plaint was accordingly rejected under provisions of
       Order VII Rule 11 of the Code. The respondents being aggrieved,
       challenged the said order by filing an appeal under Section 96 of the
       Code. During pendency of the said appeal, the respondents moved
       an application dated 07.07.2022 stating therein that the respondents
       as well as the appellants had decided to have their disputes resolved
       mutually. In the said application it was averred as under:
            “In this appeal appellants as well as respondents have
            mutually decided to get their matter resolved out of the
            Court under arbitration of Shri Vipin Sodhi, Advocate,
            Meerut. The appellants have appointed Shri Vipin Sodhi,
            Advocate, 105, Carriappa Street, Meerut Cantt as their
            sole arbitrator in all or any dispute pertaining to Guru
            Tegh Bahadur Charitable Trust and its school at 227,
            West End Road, Meerut Cantt etc. Partnership firm M/s
            Sri Guru Tegh Bahadur Public School, Delhi Road, Meerut
            or any other connected matters, on 27.5.2022. Shri Vipin
            Sodhi, Advocate, has accepted to be an arbitral tribunal
            to decide all disputes and to give his final award. Shri
910                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


          Vipin Sodhi has entered upon the Reference of arbitration
          and various sittings have already taken place. As per oral
          submissions of appellant Arbitrator has taken into points
          in dispute. Version of the appellants has been recorded.
          Entire disputes raised by the appellants have been taken
          into consideration and the arbitration is in process.
          It Is, therefore, very humbly prayed that this appeal should
          be decided from the outcome of final award passed by the
          Arbitrator Shri Vipin Sodhi, Advocate, Meerut.”
                                                 (Emphasis supplied)

10. The sole arbitrator on 30.12.2022 passed his award and issued
    various directions. Both the parties thereafter filed a joint application
    before the Appellate Court on 02.01.2023 praying that the appeal
    be disposed of in terms of the award dated 30.12.2022. In the said
    joint application it was stated as under:
          “Both the parties humbly submits as under:
          That the Learned Arbitral Tribunal Sole Arbitrator Shri
          Vipin Sodhi, Advocate Meerut has passed the Award dated
          30.12.2022 in our matter. Copy of the Award is enclosed.
          We both parties accept the Award and it shall be binding
          on us. We shall not challenge the award and will abide
          by it in true sense and spirits.
          That the Appeal be decided accordingly in terms of award.
          It is, therefore, prayed that in view of award enclosed this
          appeal be disposed of as per law.”
                                                 (Emphasis supplied)

11. The Appellate Court noted the aforesaid and took on record the
    compromise deed dated 02.01.2023. The same was marked as
    Document No. 25C. On 27.01.2023, the Appellate Court disposed
    of the appeal in terms of the compromise deed which was to form
    part of the decree. The said order reads as under:-
          1. Challenge in this civil appeal is to the judgment and
          decree dated 13.04.2022 passed by learned Civil Judge
          (Sr. Div.) Meerut, which was passed by him in O.S. No.
[2025] 8 S.C.R.                                                         911

   Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


           227 of 2022 Guru Tegh Bahadur School and others versus
           Sardar Sanjt Singh Salwan and others.
           2. During pendency of this appeal, good sense prevailed
           between the parties and their dispute has been decided
           by sole Arbitrator Shri Vipin Sodhi, Advocate who has
           passed an award on 30.12.2022 and all the parties have
           accepted, the same. They filled compromise deed 25C on
           02.01.2023, wherein they accepted passing and finalization
           of the award. Compromise deed read over and explained
           to the parties on 06.01.2023, and they accepted the
           contents thereof.
           3. In opinion of this court, the said compromise is lawful.
           Hence, it would be proper to decide this appeal in terms
           of compromise deed/application 25C.
                                      Order
           This civil appeal is decided in terms of compromise deed/
           application 25, which shall form part of decree.
           The parties shall bear their own respective costs
           throughout.”
                                                 (Emphasis supplied)

12. From the aforesaid material on record, it becomes clear that it was
    the respondents who invoked the jurisdiction of the Civil Court by
    filing suit for perpetual injunction against the appellants. It was their
    case that the suit as filed was not barred by the provisions of Section
    92 of the Code. Thereafter, in the appeal preferred by them, the
    respondents moved an application dated 07.07.2022 stating therein
    that they along with the appellants had decided to end their disputes
    by having the matter resolved out of Court. The parties again jointly
    sought disposal of the respondents’ appeal in terms of the award
    dated 30.12.2022. This request was accepted by the Appellate
    Court and the respondents’ appeal was disposed of in terms of the
    compromise deed at Document No. 25C.
     These admitted facts clearly indicate that the respondents had taken a
     conscious stand that the suit filed by them was not barred by Section
     92 of the Code and that on the basis of the compromise deed in the
     form of the award dated 30.12.2022, a decree was passed in the
912                                                          [2025] 8 S.C.R.

                          Supreme Court Reports


       appeal preferred by them. These facts assume importance since
       they reflect on the conduct of the parties, especially the respondents.
13. After the initial round of litigation when the appellants sought to rely
    upon the consent deed and filed an application under Section 9 of
    the Act of 1996 for seeking interim measures, the respondents took
    a completely opposite stand and raised a plea that the compromise
    deed in the form of award dated 30.12.2022 was a nullity in view
    of Section 92 of the Code. They persisted with this stand which
    found favour with the Commercial Court and thereafter in appeal
    before the High Court. The question therefore to be considered is
    whether the respondents could be permitted to take a diametrically
    opposite stand from the one taken by them in the earlier stage of
    the proceedings initiated by them so as to leave the appellants
    without any remedy.
14. In our view, it would be impermissible for the respondents to take
    such opposite stand from the one that they had taken while initiating
    the proceedings. Having specifically pleaded that the suit filed by
    them was not hit by the provisions of Section 92 of Code, it would
    not be now open for them to oppose the validity of the compromise
    deed dated 02.01.2023 by raising such ground. The pleadings of the
    respondents referred to hereinabove clearly indicate the conscious
    stand taken by them in the initial round of the present litigation.
    They had stated on more than one occasion that the proceedings
    initiated by them were maintainable and that the same were required
    to be decided on merits. They willingly had the matter referred for
    settlement and when the award was passed on 30.12.2022 they
    sought disposal of their appeal in terms of the compromise deed
    that was prepared on the basis of the award dated 30.12.2022.
    The respondents therefore by their conduct are now estopped from
    taking an opposite stand.
15. This position is fortified by the decision of this Court in Mumbai
    International Airport Private Ltd. (supra). It was held therein as
    under:
            “44. Is an action at law a game of chess? Can a litigant
            change and choose its stand to suit its convenience and
            prolong a civil litigation on such prevaricated pleas?
            45. The common law doctrine prohibiting approbation
            and reprobation is a facet of the law of estoppel and well
[2025] 8 S.C.R.                                                           913

   Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


           established in our jurisprudence also. The doctrine of
           election was discussed by Lord Blackburn in the decision
           of the House of Lords in Scarf v. Jardine [(1882) 7 AC
           345 : (1881-85) All ER Rep 651 (HL)] wherein the learned
           Lord formulated: (AC p. 361)
                “… a party in his own mind has thought that he would
                choose one of two remedies, even though he has
                written it down on a memorandum or has indicated
                it in some other way, that alone will not bind him;
                but so soon as he has not only determined to follow
                one of his remedies but has communicated it to the
                other side in such a way as to lead the opposite
                party to believe that he has made that choice, he
                has completed his election and can go no further;
                and whether he intended it or not, if he has done an
                unequivocal act … the fact of his having done that
                unequivocal act to the knowledge of the persons
                concerned is an election.”
           46. In Tinkler v. Hilder [(1849) 4 Exch 187] Parke, B. stated
           that where a party had received a benefit under an order,
           it could not claim that it was valid for one purpose and
           invalid for another. (See p. 190.)
           47. In Clough v. London and North Western Railway Co.
           [(1861-73) All ER Rep 646] the Court referred at All ER
           p. 651 F to Comyn’s Digest, wherein it has been stated:
                “If a man once determines his election, it shall be
                determined forever.”
           50. Ashutosh Mookerjee, J. speaking for the Division Bench
           of the Calcutta High Court in Dwijendra Narain Roy v.
           Joges Chandra De [AIR 1924 Cal 600] , held that it is an
           elementary rule that a party litigant cannot be permitted
           to assume inconsistent positions in court, to play fast and
           loose, to blow hot and cold, to approbate and reprobate to
           the detriment of his opponent. This wholesome doctrine,
           the learned Judge held, applies not only to successive
           stages of the same suit, but also to another suit than
           the one in which the position was taken up, provided the
           second suit grows out of the judgment in the first. 53. This
914                                                           [2025] 8 S.C.R.

                        Supreme Court Reports


         Court in C. Beepathuma case [AIR 1965 SC 241 : (1964)
         5 SCR 836] at AIR p. 246, para 17 also took note of the
         principle stated in White & Tudor’s Leading Case in Equity,
         Vol. 18th Edn. at p. 444, wherein it is stated:
              “Election is the obligation imposed upon a party by
              courts of equity to choose between two inconsistent
              or alternative rights or claims in cases where there is
              clear intention of the person from whom he derives
              one that he should not enjoy both … That he who
              accepts a benefit under a deed or will must adopt
              the whole contents of the instrument.”
         54. In New Bihar Biri Leaves Co. v. State of Bihar [(1981)
         1 SCC 537] this Court observed that it is a fundamental
         principle of general application that if a person of his own
         accord, accepts a contract on certain terms and works
         out the contract, he cannot be allowed to adhere to and
         abide by some of the terms of the contract which proved
         advantageous to him and repudiate the other terms of the
         same contract which might be disadvantageous to him. The
         maxim, qui approbat non reprobat (one who approbates
         cannot reprobate), applies in our laws too.”
16. Reference can also be made to the following observations in R.N.
    Gosain vs. Yashpal Dhir, SLP(C) No. 4325 of 1992 decided on
    23.10.1992:
         “Law does not permit a person to both approbate and
         reprobate. This principle is based on the doctrine of
         election which postulates that no party can accept and
         reject the same instrument and that “a person cannot say
         at one time that a transaction is valid and thereby obtain
         some advantage, to which he could only be entitled on the
         footing that it is valid, and then turn round and say it is
         void for the purpose of securing some other advantage”.
         [see: Verschures Creameries Ltd. V. Hull and Netherlands
         Steamship Co. Ltd., (1921), 2 R.B. 608, at p.612, Scrutton,
         L.J]. Accoring to Halsbury’s Laws of England, 4th Edn., Vol.
         16, “after taking an advantage under an order (for example
         for the payment of costs) a party may be precluded from
         saying that it is invalid and asking to set it aside. (para 1508)”
[2025] 8 S.C.R.                                                            915

   Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


17. We would now deal with the contention of the respondents that the
    award as passed by the sole arbitrator was a nullity since it dealt
    with issues that fell within the purview of Section 92 of the Code. The
    invalidity of the award could thus be set up at any stage to prevent
    its execution and that there could be no estoppel against law. This
    plea as raised by the respondents found favour with the Commercial
    Court as well as the High Court.
     The contention though attractive cannot enable the respondents
     the surmount the equitable hurdle of estoppel. Having lulled the
     appellants in having the disputes resolved through arbitration and
     thereafter seeking disposal of their appeal on the strength of the
     said award, the respondents are definitely estopped from now setting
     up its invalidity. The issue is more about estoppel by conduct and
     election rather than estoppel in law.
     In Dhiyan Singh and another v. Jugal Kishore and another,
     AIR 1952 SC 145, a family dispute in relation to certain ancestral
     and self-acquired properties was sought to be resolved through
     arbitration. Before the Courts it was urged that not only had the
     arbitrator travelled beyond the terms of his reference by awarding
     absolute interest in the property to one party when she had limited
     interest therein, it was also urged that on factual aspects also he was
     incorrect. It was however found that the other party had accepted
     the award and by such conduct had induced the former party from
     parting with a share in her property.
     Vivian Bose, J. (as his Lordship then was) held as under:
           “It was urged, among other things, that the arbitrator had
           travelled beyond the terms of his reference in awarding
           Mst. Mohan Dei an absolute interest. It was also urged
           that even if Brijlal was bound, his son Kishan Lal, who did
           not claim through him but who had an independent title
           as reversioner to Shanker Lal, would not be bound, and
           it was contended that if Kishan Lal was not bound, the
           plaintiffs would not be either. But we need not examine
           these points because we do not need to proceed on the
           binding nature of the award. Even if the award be invalid
           we are of the opinion that the plaintiffs’ claim is completely
           answered by the plea of estoppel.
916                                                        [2025] 8 S.C.R.

                      Supreme Court Reports


       Now it can be conceded that before an estoppel can arise,
       there must be, first, a representation of an existing fact
       as distinct from a mere promise de futuro made by one
       party to the other; second, that the other party, believing
       it, must have been induced to act on the faith of it; and
       third, that he must have so acted to his detriment.
       It is true that in one sense a question of title is one of law
       and it is equally true that there can be no estoppel on a
       question of law. But every question of law must be grounded
       on facts and when Brijlal’s conduct is analysed it will be
       found to entail an assertion by him that he admitted and
       recognised facts which would in law give Mst. Mohan Dei
       an absolute interest in the lands awarded to her. It was
       because of that assertion of fact, namely, his recognition
       and admission of the existence of facts which would give
       Mst. Mohan Dei an absolute interest, that she was induced
       to part with about one-third of the property to which Brijlal,
       on a true estimate of the facts as now known, had no right.
       There can be no doubt that she acted to her detriment
       and there can, we think, be equally no doubt that she was
       induced to do so on the faith of Brijlal’s statements and
       conduct which induced her to believe that he accepted all
       the implications of the award. But in any event, we are
       clear that Brijlal would have been estopped. The nature
       of the dispute and the description of it given in the award
       show that there was considerable doubt, and certainly much
       dispute, about the true state of affairs. Even if the arbitrator
       was wholly wrong and even if he had no power to decide
       as he did, it was open to both sides to accept the decision
       and by their acceptance recognise the existence of facts
       which would in law give the other an absolute estate in
       the properties they agreed to divide among themselves
       and did divide. That, in our opinion, is a representation of
       an existing fact or set of facts. Each would consequently
       be estopped as against the other and Brijlal in particular
       would have been estopped from denying the existence
       of facts which would give Mst. Mohan Dei an absolute
       interest in the suit property.”
                                        (Emphasis supplied by us)
[2025] 8 S.C.R.                                                         917

   Sanjit Singh Salwan & Ors. v. Sardar Inderjit Singh Salwan & Ors.


18. In our view, the ratio of the aforesaid decision is a complete answer
    to the defence raised by the respondents on the plea of estoppel
    against law. It is only because the respondents consented to have
    the disputes resolved through the arbitration of Mr. Vipin Sodhi that
    the compromise deed was executed and the respondents’ appeal
    was disposed of accordingly. The appellants thereafter acted in
    accordance with the terms of the consent deed and altered their
    position to their detriment. They took steps to withdraw the First
    Information Report and also parted with substantial amounts as
    required by the consent deed. All these facts are sufficient to hold that
    after the parties accepted the consent deed, the appellants acted in
    accordance with its terms and altered their position. The respondents
    thus by their conduct of accepting the compromise deed based on
    the award of the arbitrator are now precluded from questioning its
    validity. As held in Dhiyan Singh (supra), the issue of invalidity of
    the award, as a question of law, cannot be considered de hors the
    conduct of parties. In these facts, the ratio of decisions relied upon
    by the respondents do not further their case. Hence, this contention
    of the respondents fails.
19. We therefore find that on the doctrine of estoppel by conduct and
    election the respondents cannot be permitted to now raise a plea
    that the compromise deed based on the award dated 30.12.2022
    was a nullity in view of the provisions of Section 92 of the Code.
    On this count, we do not deem it necessary to go into the legality
    of the award dated 30.12.2022 as was done by the Courts in the
    impugned orders.
20. It can be seen from the order passed by the Commercial Court on
    24.05.2024 and thereafter by the High Court on 30.08.2024 that
    the effect of the compromise deed resulting into a decree has not
    been given its due importance. The conduct of the respondents
    of approbation by first accepting the award and having the appeal
    disposed of on that basis and thereafter of reprobation by setting up
    its invalidity has been lost sight of. The compromise deed was not
    challenged at any point of time by the respondents. The appellants
    sought to execute the decree as passed initially by filing execution
    proceedings on 23.11.2023. The same were however withdrawn
    on 08.12.2023. Thereafter jurisdiction under Section 9 of the Act of
    1996 was invoked by the appellants. In our view, non-suiting the
    appellants on the ground that the award dated 30.12.2022 was a
918                                                          [2025] 8 S.C.R.

                              Supreme Court Reports


       nullity in view of the objection raised by the respondents has resulted
       in grave injustice to the appellants. If the impugned adjudication
       is accepted, the respondents would reap benefit from their act of
       approbation and reprobation. The respondents having succeeded in
       having a decree being passed on the strength of the arbitral award
       dated 30.12.2022 now cannot be permitted to contend that the
       award itself was a nullity. The justice of the case therefore requires
       that the appellants ought to be permitted to revive the execution
       proceedings that they had filed being Miscellaneous Case No. 122
       of 2023. These proceedings were withdrawn shortly after being filed
       to enable the appellants to file the application under Section 9 of the
       Act of 1996 and there was no adjudication of the same on merits.
       In our view, the appellants cannot be left remediless especially in
       the backdrop of the fact that the compromise decree was passed
       in the respondents’ appeal which remained unchallenged by them.
21. For aforesaid reasons, the order passed by the Commercial Court
    in Arbitration Suit No.25 of 2023 dated 24.05.2024 as well as the
    judgment of the Division Bench in Appeal No.356 of 2024 dated
    30.08.2024 are set aside. The appellants are at liberty to revive the
    execution proceedings in the form of Miscellaneous Case No.122
    of 2023. The execution proceedings shall be decided on their own
    merits and in accordance with law. The civil appeal is allowed in
    aforesaid terms leaving the parties to bear their own costs.

       Result of the case: Appeal allowed.




       †
           Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Estoppel in law"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

SANJIT SINGH SALWAN & ORS. versus SARDAR INDERJIT SINGH SALWAN & ORS. — 2025 INSC 988 - Legal Desk AI