SRI NRIPATI GHOSHAL, FIRST LAND ACQUISITION COLLECTOR AND ORS.versusPREMAVATL KAPUR (DEAD) BY LRS. AND ORS. ETC.
- Citation
- 1996 INSC 775
- Decided
- 23 July 1996
- Disposal
- Appeal(s) allowed
- Bench
- K RAMASWAMY
Holding
The acquisition of the premises was for a bona‑fide public (defence) purpose and therefore not mala fide.
Summary
The premises at 7 Chapel Road, Calcutta, were requisitioned in 1971 under the West Bengal Premises Requisition and Control (Temporary Provisions) Act, 1947 for defence purposes during the Bangladesh war, and the Indian Navy took possession. The respondents challenged the requisition, and the government later initiated acquisition proceedings under the Land Acquisition Act, 1894, publishing a notification in 1981 and a declaration in 1982, culminating in a final award in September 1983. A single High Court judge held that there was no public purpose for the requisition but allowed time for the award, while a Division Bench later set aside that finding, declaring the acquisition mala fide. The Supreme Court examined whether the acquisition was indeed for a bona‑fide public purpose, noting that the defence purpose had crystallised before the award became final, and held that the acquisition was lawful and not mala fide. It also criticised the Government’s delay in filing appeals and directed the creation of a central legal cell to ensure timely prosecution of such matters. Consequently, the Court allowed the appeals without costs, overturning the Division Bench’s decision.
Issues considered
- Whether the requisition of the premises under the West Bengal Premises Requisition and Control (Temporary Provisions) Act, 1947 was for a public purpose.
- Whether the subsequent acquisition of the premises under the Land Acquisition Act, 1894 was bona‑fide or mala fide.
- Whether the procedural delays and failure to deliver possession affected the validity of the acquisition.
Legislation cited
- Land Acquisition Act, 1894s. 11, s. 12, s. 4, s. 5-A, s. 6
- West Bengal Premises Requisition and Control (Temporary Provisions) Act, 1947s. 3(1)
Subjects
Judgment
\
A SRI NRIPATI GHOSHAL, FIRST LAND ACQUISITION
COLLECTOR AND ORS.
v.
PRE!v!AVATl KAPUR (DEAD) BY LRS. AND ORS. ETC.
JULY 23, 1996
B
iK RAMASWAMY AND G.B. PATTANAIK, JJ.]
VVest Bengal Preniiscs Requisition and Control (Tcn1jJora1y Provisions)
1947: Section 3( 1).
•
c Land Acquisition Act, 1894: Section 4, SA, 6, 11 and 12.
Land-Acquisition and Requisition-Validity of-Premises requisi-
tioned under !Vest Bengal Act for defence p1upose--Pre111ises in possession
of Indian Nai:v-W!it challenging requisition-in the 111eanivhile acquisition
D proceedings initiated under the Land Acquisition Act-High Cowt holding
that there 11.•as no public ]Jlll]JOse in requisition-In view of acquisition
proceeding alreac(v initiated 1-iizh Cotat a'vvarding four nionths' ti111e to coni-
plete enquhy and pass a1vard-Direction to hand over possession in case of
default-In the 111ea11tin1e acquisition beco111ingfi11al-Another tt-·1it by respon-
dent-Dismissal by single J11dge--Division Bench holding that there was no
E public purpose and that the acquisition was ma/a fide-Appeal-Held
notification and declaration became final before the single Judge passed its
orde1~P11b/ic pwpo.ce viz. defence pwpose got Cl)'Stalized before the judgment
ivas rendered by High Cciu11-There were no n1ala fidcs in acquisition-Ac-
quisition was for p11b/ic µwpose.
F
Govemment litigation-Delay in preferring appeals by govern-
111ent-Deprecation of-Suggestion by Suprenze Coi:11 that Cabinet Conunittee
should constitute a legal Cell centralising all cases to decide whether appeal
should be filed-Fixing responsibility of officers for delay.
G CIVIL APPELLATE JURISDICTION : Civil Appeal No. 227 of
1992 Etc.
From the Judgment and Order dated 31.7.90 of the Calcutta High
Court in Appeal from Original Order No. T. 3734 of 1986.
H S. Muralidhar and Rathin Das for Appellants in C.A. No. 227/92.
850
,. NRIP AT! GHOSHAL v. PREMi\VAT! KAPUR 851
Parveen Swamp, Ms. A. Subhashini, NP, for Union of India in C.A. A
No. 3790/92.
A:K. Ganguli, Parag P. Tripathi, Rana Mukherjee, Ms. Sumita Muk-
herjee, lndeevar Goodwill and Abha R. Sharma for the Respondents.
The following Order of the Court was delivered : B
Delay condoned.
Substitution allowed.
These appeals by special leave arise from the order of the Division c
Bench of the Calcutta High Court dated July, 31, 1990 made in Appeal
from Original Order No. T.3734/86.
The undisputed facts arc that the premises bearing No. 7, Chappel
Road, Haslings, Calcutta \Vas requisitioned on Novcn1ber 29, 1971 under D
Section 3(1) of the West Bengal Pren1ises Requisition and Control (Tem-
pon1ry Provisions) Act, 1947 (for short, 'the Bengal Act') due to
Bangladesh war. The Indian N.avy had taken possession thereof and has
remained in possession of the said prcn1ises. Subsequently, it \VOtild appear,
the respondents had filed Matter No. 1295179 in the Calcutta High Court
questioning the legality of the requisition. It would appear that proceedings E
were initiated as early as in 1975 for acquisition of the property and the
correspondence between various Departments \Vas going on. Notification
under Section 4(1) of the Land Acquisition Act, 1894 (1of1984) (for short,
the 'Act') was published on November 26, 1981. Enquiry under Section 5-A
was conducted. Thereafter, declaration under Section (, was published on F
November 25, 1982. The writ petition pending in the High Court came up
for hearing. A learned single judge by his order dated April 8, 1983 had
held that though there was no public purpose for requisition under the
Bengal Act, since the acquisition \Vas initiated under the Act, four months'
time ;vas granted for completing the award enquiry and to pass the award; G
in case of default, he directed the appellants to hand over possession of
the premises to the respondents. In the meanwhile, the acquisition
proceedings were completed by making award on September 21, 1983.
Notice under Section 12 was issued to the respondents on Septen1ber 23,
1983. Thus the acquisition under the Act had become final. An oral\._
application came to be made before the learned Judge for extension of H
'
852 SUPREME COURT REPORTS [1996] SUPP. 3 S.C.R.
A time on July 22, 1983 since the time was to expire on August 8, 1983. But
the learned Judge declined lo extend the time by his order dated August
2, 1983. Since the possession was not delivered, the respondents had filed
another writ petition in the High Court which the learned single Judge had
dismissed on November 12, 1986. On appeal, in the impugned order the
Division Bench set aside the order of the learned single Judge am! issued
B
mandamus as indicated in the order. The primary findings recorded by the
Division Bench were that there was no public purpose and that the acquisi-
tion was ma/a fide.
The question, therefore, is : whether the lwo findings recorded by
C the Division Bench are correct in la\v? Shri Ganguli, learned senior counsel
for the respondents, sought to support the findings of the Division Bench
on the ground that there arc no bona fides on the part of the appellants in
pursuing the mailer. In fact, when the respondent had pointed out in the
High Court that there was no public purpose in requisitioning the property,
D they came forward with the acquisition under the Act; when the learned
single Ju<lge ha<l <lirected the appellants to have the a\vard en4uiry com-
pleted and the award made within four months, the same were not done
within the prescribed time. In spite of initiation of contempt proceedings,
the possession \Vas not delivered. These circumstances could be considered
lo show that the acquisition was ma/a fide and that, therefore, in the light
E of the above background, the High Court was right in reaching the con-
clusion. We find no force in the contentions.
H is seen that the acquisition proceedings under the Act were
initiated no doubt after the first writ petition was filed challenging the
F requisition under the West Bengal Act. But the notification under Section
4( l) and the declaration published under Section 6 of the Act became final
before the learned single judge had passed the order on April 8, 1983.
Thereby the public purpose, namely, defence purposes, got crystalised
before the judgment was rendered by the learned single Judge. The learned
single .Judge accepting the legal position, quite rightly, had given time to
G complete the award enquiry and to pass the award. unfortunately, due to
lethargy on the part of the authorities to have the funds made available,
award could nol be made for non- depositing of the amount. The question,
therefore, emerges; .\vhether the acquisition is n1ala fide? So long as the
public purpose subserves, the finding that the acquisition is ma/a fide is
H cx-facie unsustainable. No doubt there are !aches on the part of the
NRIPATIGHOSHALv. PREMAVATIKAPUR 853
authorities, hut so long as the acquisition proceedings were legal and the A
defence personnel remain in possession of the pren1ises for the defence
purpose, the acquisition is for public purpose. Therefore, it cannot be
characterised to be ma/a fide. It is seen that by the time the second writ
petition, which is the subject n1atter ulti1natcly in this appeal, came to be
filed) the acquisition ha<l bccon1c final; the a\vard had become final and
B
the compensation was tendered. Under those circumstances, the High
Court, without going into the validity in that behalf, was not right in setting
aside the acquisition on the specious finding that it is ma/a fide. Therefore,
the High Court has not properly considered that aspect in the correct
perspective in deciding the matter.
c
Pursuant to the interim direction granted by this Court appellants
have deposited rent at the rate of Rs. 7500 per month beginning from
1.l.92. Shri Ganguli has brought to our notice that the payments were not
alleged to have been paid for the earlier period of requisition. It is also
brought to our notice that the a1nount of con1pensation was not received
D
_, by the respondents. Under these circumstances, it would be open to the
Land Acquisition Collector to vary an<l, if found correct, to adjust the
amounts, deposited as per the orders of the Court, to\vards the an1ount
payable, if not already paid for the period of requisition. If there is any
further amount due, that amount may also be directed to be paid to the
respondents within a specified time. The amount deposited pursuant to E
orders of this court, if found excess, may be adjusted towards the amount
payable as compensation for the acquired premises.
It is unfortunate that in spite of peremptory direction to pass av.ard
and on non-compliance of order to deliver possession of the building, no F
prompt action has been taken. The officers have not shown diligence
required in this case. Even though the conten1pt proceedings were initiated
for non-delivery of possession, yet no steps had been taken even to file
appeal in this Court within the prescribed limitation. That would show
apathy or absolute indifference on the part of the concerned officers in
pursuing the proceedings. It would be obvious that since they do not have G
personal interest in the Governmental matters, they do not show the
required dispatch. It is our sad experience that invariably, all cases of the
Government, 1;c that of Government of India or State Governments, except
presently in the case of the Government of Punjab, are being filed \Vith
abnormal delay. It would, therefore, be high time that all the Governments H
(
854 SUPREME COURT REPORTS [1996] SUPP. 3 S.C.R.
A should necessarily streamline the process of taking decision in time to file
appeals. The lack of responsibility and indifference further gets com-
pounded from the fact that though the writ petitioner (3rd respondent in
this case) died on September 18, 1993 and notice was given by her counsel
to the counsel for the Union on October 4, 1993, no steps were taken to
B bring the legal representatives on record till August 19, 1994. In August
1994 the application for substitution came to be filed but unaccompanied
by the application to condone the delay which came to be filed in septem-
ber 1994 but still without any explanation. These facts do indicate the
absolute lack of diligence and apathy or indifference in pursuing the
matters on behalf of the Union of India.
c It is unfortunate that we have come across that even the State
Governments adopt the same indifferent attitude in pursuing the public
causes in filing the appeals in this Court as well as in the High Courts and
the courts below. It is high time for the Government of India through the
Cabinet Secretary to constitute a legal cell centralising all the cases to
D decide whether appeals should be !!led and if so have them filed in time
or with utmost dispatch. The officers responsible should be made account-
able for the delay. Same process is equally required to be adopted in case
of appeals to be filed in this Court or in the High Courts by the respective
State Governments and/or the Union of India.
E The Registry is directed to communicate this order to the Cabinet
Secretary and also to all the Chief Secretaries of the State Governments;
so also to the Attorney General of India and the Advocates General of the
concerned States so that appropriate measures could be taken in this
behalf.
F
The appeals are accordingly allowed, but, m the circumstances
\vithout costs.
T.N.A. Appeals allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.