Created byFuzzy Cloud

Supreme Court of India

STATE OF MADHYA PRADESHversusSHEETLA SAHAI & ORS.

Citation
2009 INSC 997
Decided
4 August 2009
Disposal
Dismissed

Holding

Sanction for prosecution under Section 197 of the CrPC was required; the appeal is dismissed.

Summary

The Supreme Court examined the prosecution of several senior officials, including the former Water Resources Minister of Madhya Pradesh, for alleged criminal conspiracy and misconduct under the Prevention of Corruption Act in connection with the Hasdeo Bango dam project. The respondents were accused of sanctioning extra payments for stone quarrying beyond contract terms. The key issue was whether prosecution required prior sanction under Section 197 of the Code of Criminal Procedure, given that the officials acted in their official capacity or purport to do so. The Court held that Section 197 applies whenever a public servant acts or purports to act in discharge of official duties, irrespective of whether they were still in office, and that the material on record did not establish a criminal conspiracy. Consequently, the appeal seeking to set aside the High Court’s order was dismissed, confirming that sanction was required and that the case lacked sufficient basis for charges.

Issues considered

  • Whether sanction for prosecution under Section 197 of the Code of Criminal Procedure is required when the accused are public servants who acted or purport to act in official capacity.
  • Whether the alleged acts constitute criminal misconduct under Sections 13(1)(d)(ii-iii) and 13(2) of the Prevention of Corruption Act, 1988.
  • Whether there is sufficient evidence to establish a criminal conspiracy under Section 120A and 1208 of the Indian Penal Code.
  • Whether the respondents, some of whom had ceased to hold public office, are covered by Section 197.
  • Whether the High Court erred in its approach to framing charges and evaluating the material on record.

Legislation cited

Subjects

criminal conspiracyprevention of corruption actsection 197 crpcpublic servantofficial dutysanction for prosecutionevidenceframing of chargedam projectextra lead payment

Judgment

                        [2009] 12 S.C.R. 1048


A                  STATE OF MADHYA PRADESH
                                    v.
                      SHEETLA SAHAI & ORS.
                 (Criminal Appeal No. 1417 of 2009)
                           AUGUST 4, 2009
B
             [S.B. SINHA AND CYRIAC JOSEPH, JJ.]

         CODE OF CRIMINAL PROCEDURE, 1973:

c         Section 197 - Sanction for prosecution - Whether public
    servants act in their official capacity or purport to act in their
    official capacity such action would attract the provisions of
    Section 197 - Thus sanction for prosecution was required to
    be obtained - Prevention of Corruption Act, 1988 - Sections
    13, 19.
D
      In this appeal on the basis of the facts of the case
  and contentions raised on both sides, the main question
  that arose for consideration was whether sanction for
  prosecution in terms of Section 197 Cr.P.C. was required
E to be obtained.

        Dismissing the appeal, the Court                                 \'   -
      HELD: 1.1. Criminal conspiracy is an independent
  offence. It is punishable separately. Prosecution,
F therefore, for the purpose of bringing the charge of
  criminal conspiracy read with the relevant provisions of
  the Prevention of Corruption Act was required to
  establish the offence by applying the same legal
  principles which are otherwise applicable for the purpose
G of bringing a criminal misconduct on the part of an
                                                                         •    -<
                                                                                   -
  accused. A criminal conspiracy must be put to action
  inasmuch as so long a crime is generated in the mind of
  an accused, it does not become punishable. What is

H                                 1048
            STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1049
                             & ORS.

            necessary is not thoughts, which may even be criminal          A
 --'-·      in cli.aracter, often involuntary, but offence would be said
            to have been committed thereunder only when that take
            concrete shape of an agreement to do or cause to be
            done an illegal act or an act which although not illegal by
            illegal means and then if nothing further is done the          B
            agreement would give rise to a criminal conspiracy.
            [Paras 50 and 51] [1078-C-F]

                 1.2. What is necessary is to show meeting of minds
 ..,,       of two or more persons for doing or causing to be done
            an illegal act or an act by illegal means. While saying so,
                                                                           c
            this Court is not oblivious of the fact that often
            conspiracy is hatched in secrec~r and for proving the said
            offence substantial direct evidence may not be possible
            to be obtained. An offence of criminal conspiracy can also
            be proved by circumstantial evidence. [Paras 51 and 52]        D
    ,.1,-   [1078-H; 1079-A-B]

                1.3. Ex facie, there is no material to show that a
            conspiracy had been hatched by the respondents. [Para
            52]                                                            E
                 Soma Chakravarty v. State Through CBI (2007) 5 SCC
--"'-!      403; K.N. Sathyapalan (Dead) by LRs. v. State of Kera/a &
            Anr. (2006) 12 SCALE 654; Kehar Singh and Ors. v. State
            (Delhi Administration), 1988 (3) SCC 609; State (NCT) of
                                                                           F
            Delhi v. Navjot Sandhu @ Afsan Guru (2005) 11 SCC 600;
            Ram Narayan Popli v. CBI (2003) 3 SCC 641 and Yogesh
            @ Sachin Jagdish Joshi v. State of Maharashtra (2008) 6
            SCALE 469, referred to.

                2. The Minister in his note dated 4.11.1991 did not        G
            make any recommendation. He merely lamented the
 '-1
            manner in which the former Secretary acted as prior
            thereto, the said authority himself for all intent and
            purport had accepted the recommendations of the
            authorities incharge of construction of the dam including      H
    1050     SUPREME COURT REPORTS              [2009) 12 S.C.R.


A the Chief Engineer. He constituted a committee. He
  obtained the opinion of the Financial Adviser. If upon
  consideration of the entire materials on record,
  independent opinion had been rendered and
  recommendations were made, it is difficult to
B comprehend as to how that by itself would constitute a
  criminal misconduct or leads to the conclusion of
  hatching any criminal conspiracy. Recommendations
  made by the Committee or the opinion rendered by an
  independent officer like Financial Adviser need not be
c acted upon. It was for the State to take a decision. Such
  a decision was required to be taken on the basis of the
  materials available. [Para 53) [1080-H; 1081-A-C]

        Inspector Prem Chand v. Govt. of N. C. T. of Delhi & Ors.
    2007 AIR SCW 2532, referred to.
D
       3. Even under the Prevention of Corruption Act, an
  offence cannot be said to have been committed only
  because the public servant has obtained either for
  himself or for any other person any pecuniary advantage.
E He must do so by abusing his position as public servant
  or holding office as a public servant. In the latter category
  of cases, absence of any public interest is a sine qua non.
  The materials brought on record do not suggest in any
  manner whatsoever that the respondent Nos. 1 to 7
F either had abused their position or had obtained
  pecuniary advantage for the respondent Nos. 8, 9 and 10,
  which was without any public interest. [Para 54) (1082-
  E-F]

       4.1. There cannot be any doubt whatsoever that the
G tests for the purpose of framing of charge and the one
  for recording a judgment of conviction are different. A
  distinction must be borne in mind that whereas at the time
  of framing of the charge, the court may take into
  consideration the fact as to whether the accused might
H have committed the offence or not; at the time of
                 STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1051
                                  & ORS.

      __..;...   recording a judgment of conviction, the prosecution is          A
                 required to prove beyond reasonable doubt that the
                 accused has committed the offence. [Para 58) [1084-B-C]

                     · 4.2. In this case, the probative value of the materials
                 on record has not been gone into. The materials brought         B
                 on record have been accepted as true at this stage. It is
                 true that at this stage even a defence of an accused
                 cannot be considered. But, this Court is unable to agree
       ~"i·      with the submission that where the entire materials
                 collected during investigation have been placed before
                 the court as part of the ch'argesheet, the court at the time
                                                                                 c
                 of framing. of the charge could only look to those
                 materials whereupon the prosecution intended to rely
                 upon and ignore the others which are in favour of the
                 accused. The question as to whether the court should
                 proceed on the basis as to whether the materials brought        D
       A·
                 on record even if given face value and taken to be correct
                 in their entirety disclose commission of an offence or not
                 must be determined having regard to the entirety of
                 materials brought on record by the prosecution and not
4                on a part of it. If such a construction is made, Sub-section    E
                 (5) of Section 173 of the Code of Criminal Procedure shall
    -- "'!       become meaningless. [Para 59) [1084-D-G]

                       5. The prosecution, having regard to the right of an
                 accused to have a fair investigation, fair inquiry and fair     F
                 trial as adumbrated under Article 21 of the Constitution
                 of India, cannot at any stage be deprived of taking
                 advantage of the materials which the prosecution itself
                 has placed on record. If upon perusal of the entire
                 materials on record, the court arrives at an opinion that
    .. ..,,      two views are possible, charges can be framed, but if only
                                                                                 G

                 one and one view is possible to be taken, the court shall
                 not put the accused to harassment by asking him to face
                 a trial. [Para 59] [1084-G-H; 1085-A-B]
                                                                                 H
    1052      SUPREME COURT REPORTS              (2009] 12 S.C.R.


A       State of Maharashtra and Others v. Som Nath Thapa and
    Others (1996) 4 SCC 659, relied on.
                                                                      •-...   .
         Centre for Public Interest Litigation and Another v. Union
    of India and Another (2005) 8 SCC 202, referred to.
B        6.1. Be he an Executive Engineer, Superintending
    Engineer, Chief Engineer, Engineer-in-Chief, Secretary or
    Deputy Secretary, matters were placed before them by
    their subordinate officers. They were required to take
    action thereupon. They were required to apply their own
C   mind. A decision on their part was required to be taken
    so as to enable them to oversee supervision and
    completion of a government project. The Minister having
    regard to the provisions of the Rules of Executive
    Business was required to take a decision for and on
D   behalf of the State. Some of the respondents were
    required to render their individual opinion required by
    their superiors. They were members of the Committee
    constituted by the authorities, viz., the Minister or the
    Secretary. At that stage, it was not possible for them to
E   refuse to be a Member of the Committee and/ or not to
    render any opinion at all when they were asked to
    perform their duties. They were required to do the same
    and, thus, there cannot be any doubt whatsoever that
    each one of the respondent Nos. 1 to 7 was performing
F   his official duties. [Para 62] [1087-D-H]

       6.2. For the purpose of attracting the provisions of
  Section 197 of the Code of Criminal Procedure, it is not
  necessary that they must act in their official capacity but
  even where a public servant purports to act in their
G official capacity, the same would attract the provisions of
  Section 197 of the Code of Criminal Procedure. Thus, in
  the instant case, sanction for prosecution in terms of
  Section 197 of the Code of Criminal Procedure was

H
        STATE OF MADHYA PRADESH v. SHEETLA SAHAl1053
                         & ORS.
       required to be obtained. (Paras 63 and 66) (1088-A-B;   A
_,..   1092-F]

           Sankaran Moitra v. Sadhna Das and Another (2006) 4
       SCC 584; Matajog Dobey v. H. C. Bhari AIR 1956 SC 44 :
       1955 (2) SCR 925; 8. Saha v. M.S. Kochar (1979) 4 SCC B
       177; R. Balakrishna Pillai v. State of Kera/a and Another
       (1996) 1 SCC 478; Rakesh Kumar Mishra v. State of Bihar
       and Others (2006) 1 SCC 557; Parkash Singh Badal v. State
       of Punjab and Others (2007) 1 SCC 1 and State of Karantaka
-~     v. Ameerjan (2007) 11 SCC 273, relied on.
                                                               c
                         Case Law Reference:
           (2007) 5 sec 403        referred to       Para 34

           (2006) 12 SCALE 654     referred to       Para 35
                                                               D
           1988 (3) sec 609        referred to       Para 52
 ~-

           (2005) 11 sec 600       referred to       Para 52
           (2003) 3 sec 641        referred to       Para 52
           (2008) 6 SCALE 469      referred to       Para 52   E

           2001 AIR sew 2532       referred to       Para 53
~
           (1996) 4 sec 659        relied on         Para 59
           (2005) 8 sec 202        referred to       Para 60   F
           (2006) 4 sec 584        relied on         Para 63
           AIR 1956 SC 44 :
           1955 (2) SCR 925        relied on         Para 63
                                                               G
           (1979) 4 sec 111        relied on         Para 63
;1
           (1996) 1 sec 478        relied on         Para 63
           (2006) 1 sec 557        relied on         Para 63
                                                               H
    1054     SUPREME COURT REPORTS              [2009] 12 S.C.R.


A       (2001) 1 sec 1              relied on            Para 64
        (2007) 11 sec 213           relied on            Para 65

        CRIMINAL APPELLATE JURISDICTION: Criminal Appeal
    No. 1417 of 2009.
B
         From the Judgment & Order dated 12.01.2006 of the High
    Court of Madhya Pradesh, Jabalpur in Criminal Revision Nos.
    75, 126, 127, 147, 161, 242 of 1999 and 734 of 1997.

       K.T.S. Tulsi, Ravinder Singh, Puneet Jain, Sushi! Kumar
C Jain, Ashwin V. Kotemath for the Appellant.

         Vivek K. Tankha, Ajay Mishra, Uday Umesh Lalit, B.K.
    Satija, Siddharth Gupta, Mohit Nayak, Akshat Shrivastava, P.P.
    Singh, lnderjeet Yadav for the Respondents.
D
        The Judgment of the Court was delivered by

        S.B. SINHA, J. 1. Leave granted.

      2. Appellant is before us being aggrieved by and
E dissatisfied with a judgment and order dated 12.01.2006
  passed by a learned Single Judge of the Madhya Pradesh High
  Court allowing the criminal revision applications filed by the
  respondents herein arising out of the orders dated 21.12.1998
  and 13.05.1997 passed by the Special Judge, Bhopal in
F Special Case No. 6 of 1997.

     • 3. The respondents herein were proceeded against for
  commission of offences under Section 13(1)(d)(2)(ii-iii) read
  with Section 13(2) of the Prevention of Corruption Act, 1988
  (for short "the Act") and Section 1208 of the Indian Penal Code,
G 1860.
                                                                     f   •
        4. Before proceeding further, we may notice the positions
    held by the respondents herein. Respondent No. 1 Sheetla
    Sahai was Minister for Water Resources of the State of Madhya
H
          STATE OF MADHYA PRADESH v. SHEETLA SAHA! 1055
                     & ORS. [S.B. SINHA, J.]

 .
__       Pradesh. Respondent No. 2 D.V.S.R. Sarma and the                    A
         respondent No. 7 S.W. Mohgoankar were the Secretary to the
         Government of Madhya Pradesh. Respondent No. 3 P.V.
         Srinivasaiyah was the Engineer-in-Chief and the respondent
         No. 4 A.S. Laxminarsimhaiya was\the Deputy Secretary in the
         Government of Madhya Pradesh. Respondent No. 5 V.R.B.               B
         Gopal and the respondent No. 6 M.N. Nadkarni were the Chief
         Engineers, Hasdeo Bango Project. Respondent No. 11 R.P.
         Khare was the Secretary, Control Board for Major Projects.
-:l\
              5. Appellant under the aegies of the World Bank
         undertook construction of the Hasdeo Bango Masonry dam
                                                                             c
         project. For the aforementioned purpose, the respondent Nos.
         8, 9 and 10 herein, viz.,M/s Progressive Constructions Pvt. Ltd.,
         M/s Prasad & Company, M/s SEW Construction Co.
         (hereinafter referred to as "the contractors") were awarded
         contracts in terms whereof they were required to excavate           D
 £,;Jr   stones etc. from Therma Pahar Quarry, which was situate at
         only 12 kms. away from the site, for use of the stone to be
         extracted therefrom for construction of masonry spillway.

             6. One of the terms of the said contract is as under:           E

             " .. :The tenderer should satisfy himself regarding
,•v          availability of the required quality and quantity of the
             materials, if any quarry is changed for any reason
             whatsoever, no claim shall be entertained on this account."
                                                                             F
              In addition to the guidelines, a plan was also supplied to
         the contractors containing the following note:

                   "the contractor shall extract materials from the
             approved sources and quarry areas to be designated by           G
             the engineer-in-charge for their particular contract group.
~·~'
             They shall have no claim for any material collected
             elsewhere without having obtained the prior approval in
             writing of the engineer in charge. Such material shall
             become the property of the department unless approval to
                                                                             H
    1056     SUPREME COURT REPORTS               [2009] 12 S.C.R.


A       use the same is subsequently accorded by the engineer-
        in-charge, in which case, however, the contractor shall not
        be entitled for any extra rate or lead."

       7. However, on the premise that whereas eight lakh cubic
  meters of stones of the requisite specification were required
8
  for masonry work, only one lakh cubic meter stone was
  available from the Therma Pahar Quarry, permission was
  sought for by the contractors to excavate stones, rubbles and
  other materials from a quarry known as Katghora Quarry which
  was situated at a distance of 22 kms. from the dam.                      !--
C
        8. The question was considered by the concerned
  engineers. The District Mining Officer and the Additional
  Collector Korba, having regard to the fact that the mining leases
  in respect of the said quarries were to be granted, asked them
D not to do so as the stones in the hillocks of villages Katghora,
  Hunkra and Maheshpur were found to be suitable for the
  masonry work of the dam, as would appear from a letter dated
  14.07.1983 issued by the Executive Engineer to the Additional
  Collector, Korba.
E
        9. The Superinteoding Engineer, respondent No. 7 herein
    also by his letter dated 28.07.1983 addressed to Shri R.C.
    Gupta, the then Executive Engineer stated:

        "I am informed that Rampura quarry near Katghora on
F       Kathora Ambikapur road, may also yield good masonary
        stones. You may also explore this possibility and let me
        know if the stones were got tested. If not, the samples from
        this quarry may also be tested. Case could also be moved
        to obtain lease for this quarry."
G
         10. A request was also made to the Mining Officer of
    Bilaspur to the same effect by Shri R.C. Gupta, the then
    Executive Engineer by a letter dated 16.10.1983, stating:
                                                                       '    .
        " ... Adequate quantity of rubble is not available from
H       Therma quarries of Forest Department acquired for this
         STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1057
                    & ORS. [S.B. SINHA, J.]
              purpose and Geologist, Geological Survey of India had            A
              intimated that about one lakh cum. of rubble can only be
              extracted from Therma quarries. For completion of this
              major dam about ten lakh cum. rubble & metal are needed.
              Out of which 1 lakh cum. can be extracted from Therma
              quarry, about three lakh cum. can be used out of the stone       B
              received from excavation of foundation of dam, remaining
              6 (six) lakh cum. is required from adjacent stone quarries
              like Katghora, Hukra & Maheshpur. Hence, I have
- ..\-
   .          requested in my letter cited above (copy enclosed) to
              additional Collector, Korba, to reserve rubble quarries in       c
              the surroundings of the above villages so that rubble from
              these quarries can be extracted for completion of the
              Bango Dam in time.

                    Now I understand that you have proposed the above
              quarries for auction on 20th & 21st Oct.'83. I request to        D
              delete the rubble quarries situated in the surrounding of
              Katghora, Hukra & Maheshpur from the purview of auction
              and transfer to Irrigation Department. Depending upon the
              quantity of rubble required by each agency executed
              masonry works at Bango Dam, allotment of individual              E
              quarries will be made by us after the agenCies deposit the
              royalty charges which will be refundable to them after
              awarding the certificate of utilizing the material in bonafide
              Government works.
                                                                               F
                    Till the formalities are over for transfer of the above
              quarries to Irrigation Department, I request to delete the
              following quarries from the purview of auction.

         S.No. Name of        PC No.     Name of Khasra No.         Area
               Village                   material                              G

         1.       Hukra       47         Stone       347/1    17.396 Hee.

         2.       Maheshpur 31-A         Stone       1/1-K    30.425Hec." '•
                                                                               H
    1058      SUPREME COURT REPORTS                [2009) 12 S.C.R.


A        11. The Additional Collector (Mining Section), Korba in
    response thereto by a letter dated 22.11.1983 addressed to
    the Executive Engineer reserved the aforementioned quarries
    for extraction of stones departmentally, subject to the conditions
    mentioned therein.
B
         12. Yet again, the Executive Engineer by a letter dated
    05.12.1984 addressed to the Superintending Engineer brought
    to his notice that alternative sites for quarrying operations for
    extraction of stones were necessary, inter alia, stating:
c       "2. The quarrying operations for extraction of stones was
        started in the real sense during 82-83 working season, i.e.,
        prior to the area was ready for starting the masonry. The
        contractors after the start of quarry operations, repeatedly
        wrote, regarding the non availability of sufficient stones of
D       requisite quality. They had also brought out that the yield
        of even this small quantity of stone was very much less. In
        consultations with the department and the resident
        geologist, they have opened more number of quarry faces,
        but this did not result yields. This office has also carried
E       out case studies which has established the yield of useful
        stone to be very much less. The details enclosed at
        Annexure A. Even the quantum of stone available is less,         'f •
        when compared to the requirement.

        3. It was reported that the quantum of useful rubble
F       available in the entire Therma Pahad Hills is to the tune of
        one lakh cum. against the total requirement of 8 lakh cum.
        for the entire dam. This was based on the detailed
        investigations and report of the Resident Geologist. Even
        this quantity can be extracted with much difficulty. Therma
G       Pahad Quarry on the visual appearance and the random
        bore holes, initially appeared to be good. As such this was      ' '
        declared as quarry for masonry stone and accordingly
        estimates prepared and designated as the specified
        quarry in the quarry map enclosed along with the
H       agreements. The contractors naturally could not have
              STATE OF MADHYA PRADESH v. SHEETLA SAHA! 1059
                         & ORS. [S.B. SINHA, J.]

      ,-k        investigated the quarry by actual opening/ operation, and       A
                 have inspected the quarry with the data available to them.
                 Therefore neither department nor the contractor could have
                 foreseen the non availability of useful stone in the required
                 quantity from the designated quarry."
                                                                                 B
                 It was requested:

                 "It is therefore requested that the sanction may be obtained
      ·~
                 for payment of additional leads and communicated.
                 However, the payment towards additional wasteful
                 expenditure incurred in therma quarries as claimed by           c
                 contractors is recommended for rejection."

                   13. The Superintending Engineer brought the same to the
...          notice of the Chief Engineer by a letter dated 18.12.1984 stating
             that there had always been a controversy regarding the use of D
       ~*    those stones as rubble in masonry dam. A question was also
             raised as to whether the department would permit additional
             payment due to change in the quarry. If such a step is not taken,
             the contractor may put an end to the contract and, thus, inter
             alia requested that payment of additional leads from Katghora
                                                                               E
             quarry may be allowed.
      <Y          14. It appears that even the Central Water Commission of
             the Government of India by a letter dated 04.05.1984 informed
             the Chief Engineer of the project to the following effect:
                                                                                 F
                 "Please refer to your letter on the above mentioned subject.
                 You have proposed to use stone from Therma Pahar
                 quarry for the construction of the dam. Though the stone
                 from this quarry has been approved as Granite, the

      . '(
                 Compressive strength of the stone from this quarry varies
                 from 289 kg/cm to 373 kg/cm, which is very .low. It is
                 necessary that the reasons for such low strength for the
                                                                                 G

                 Granite are investigated before deciding to use the same
                 for the construction of the dam."
                 15. By a letter dated 7.06.1983, the Executive Engineer         H
    1060      SUPREME COURT REPORTS               (2009] 12 S.C.R.


A of the Quality Control Division brought the following to the notice
  of the Superintending Engineer of the Quality Control                          "       .>



  Department:

        "Thus, it is noticed the mica existing in the rocks under
        question varies from 7% to 11%. No mention of the
B
        permissible percentage of mica is given in IS codes or
        other books. Only Hand book on civil engineering by PN
        Khanna, reveals that 2% of mica is permissible. In view of
        the above it is submitted that the pigmetite band stones             j   •


        are not fit for use in masonry dam from quality control unit
c       Machadoli's point of view. This is, however, continuously
        used in masonry on dam blocks 16, 17, 18, 19, 25, 26,
        27, 28, 29, 35, 37 in which work continuously in progress.
        If the higher authority deems it fit, that use of pigmetite is               ....
        to be continued by overruling the opinion of the
D       undersigned clear written instructions may kindly be issued      "I:
        to this office for guiding the A.R.Os. Quality Control
        deployed on Quality control work of masonry dam. Early
        reply is solicited."

E       16. In view of the aforementioned development, the Chief
    Engineer of the Project brought the same to the notice of the
    Secretary of the Major, Medium and Minor Irrigation                  "(          -
    Department, Bhopal by a letter dated 11.01.1985 inter alia
    making the following recommendations:
F       "(i) Permitting the Chief Engineer for declaring Katghora
        quarry as an additional quarry for balance quantity of
        rubble quarry for rubble for masonry dam other than one
        lakh cubic meter of rubble, as assessed by the geologist
        to be extracted by the contractors from Therma Pahad
G       quarry as far as possible in the contracts mentioned in this
        letter.
                                                                         ;       .
        (ii) To allow payment of additional leads from Katghora
        quarry for cum of masonry at the rates detailed in table at
H       para 5.3 above."
                STATE OF MADHYA PRADESH v. SHEETLA SAHAl1061
                           & ORS. [S.B. SINHA, J.]

·..---+             Along with the said letter, various other documents were     A
               enclosed as specified therein including a letter dated
               4.05.1990, wherein it was inter alia stated:

-                  "10. In view of the above, the Chief Engineer submitted
                   proposals on 4.07.85 for Government Orders. According         B
                   to the above proposals sanction to pay extra lead
                   amounting to Rs. 1,23,23,767/- has been sought. This
                   amount is about 3% of the total amount of contract of Rs.
     -*            41. 77 crores. The Chief Engineer had also sought the
                   opinion of the World Bank, and the World Bank gave a
                   suggestion to deal the issue with in the contractual
                                                                                 c
                   provisions. Similar problem has been raised by th.e
                   contractors in Bansagar Project also, and the Executive
~.
                   Committee had recommended approval of lead payment.

          -r       11. According to the Chief Engineer's report, the Executive   D
                   Engineers had reported that only 30% to 35% useful
                   stones can be extracted which was not economical. This
                   project is under construction with the World Bank
                   assistance, will have to be completed on time, to supply
                   water to the National Thermal Power Corporation, and also     E
                   to the M.P.E.B. Power Stgtion. In view of this stones have
    ~     v
                   been brought from Katghora quarry situated at 22 Km.
                   where sufficient quality of stones are available.

                   In case, due to above reasons had the Agreements drawn
                                                                                 F
                   been cancelled and new tenders recalled the cost would
                   have been more. Further, precious time would have been
                   lost in this process which would have affected the works
                   and it would not be possible to supply water to N.T.P.C.
                   and M.P.E.B."
                                                                                 G
     ;.   '        17. In a letter dated 14.02.1985 addressed to the Chief
               Engineer, the World Bank stated:

                   "We note you have referred the matter to the Secretary,
                   Irrigation Department, Bhopal for decision. We suggest
                                                                                 H
    1062     SUPREME COURT REPORTS               [2009] 12 S.C.R.


A       that the matter be resolved within contractual limits."

        18. Pursuant thereto and in furtherance thereof, even the
    Progress Review Committee observed in its note dated
    14.05.1985 as follows:
B       "27. Chief Engineer (HBP) explained his proposal
        submitted through his memo No. 1916/HB/84 dated 29/3/
        85. He gave the background of the change of quarry, in
        view of unexpectedly low yield of useful stone from the
        Therma Pahad quarry, approved in the technically
c       sanctioned, sanctioned estimate and also on which basis
        tenders had been invited and contractors' rates accepted.
        He informed the Committee that the total extra
        commitment for the various contracts worked out to Rs.
        1.23 crores - approximately 3% of the total contract value.
D
        28. Financial Adviser observed that he had no offered any
        comments on the merit of the case, as then appeared to
        him essentially a claim case. PRC does not deal such
        claim cases.
E       29. The Committee observed that the World Bank too vide
        their letter of 14/2/85 had suggested that'the matter be
        resolved within contractual limits.

        30. In view of the above, the Committee did not examine
F       the proposal of Chief Engineer and refrained from giving
        any comments in the matter at this stage."
        19. However, the contractors invoked the arbitration
    agreement contained in the said contract in the year 1987 and
    an ad hoc settlement was proposed.
G
        20. The matter was placed before the Financial Adviser.·
                                                                      ,.
  The Financial Adviser in his note dated 4.01.1991 to the
  Secretary, while stating that the Financial Adviser functions as
  a consultant offering comments on cases referred to him in the
H light of his background, experience and expertise and going
1



                                                                                         ---..
                 STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1063
                            & ORS. [S.B. SINHA, J.]

         -"     by the facts placed before him which may not be treated as a         A
                substitute for vetting by the Finance Department wherever such
                vetting is required under the rules of governmental business,
                inter alia made the following comments:

                    "... However, since the whole contract action was based          B
                    on the presumption that the required quantity of material
                    of required specification would be available from a quarry
                    with in 12 KM of the work site, it can be reasonable
       ->           assumed that the contractors have quoted their rates on
                    this assumption. The departmental estimates were also
                    based on this assumption. Since, later on, this assumption
                                                                                     c
                    was found to be invalid and majority of the material had to
                    be obtained from a quarry with an average lead of 22 KM
                    from the work site as against 12 KM in respect of the
                    contemplated quarry, the contractors have a reasonable
       _.,.._       case for additional payment on account of extra lead of the      D
                    material brought by them from this second quarry. Thus,
                    their claim is based on consideration of equity rather than
                    there of law."

                    In regard thereto, the Financial Adviser opined:                 E
..Ao   ·y           "4. Since the proposed settlement will amount to extra-
                    contractual payment, it has to be ensured that the proposed
                    settlement is acceptable to the contractors concerned. In
                    other words, the settlement has to be a negotiated
                    settlement and should not leave room for further disputes        F
                    with the various contractors. Since the purpose of the
                    whole exercise is to avoid arbitration it could even be
                    ascertained if there are any other disputed issues in these

.      ~
                    contracts. If an overall settlement of all the disputes could
                    be attempted and a sort of package deal is evolved in
                    respect of each contract so that the contracts are finalized
                                                                                     G

                    once for all leaving no scope for arbitration on the other
                    hand if the contractors intend to take resort to arbitration
                    for other issues, this issue could also go in for arbitration.
                    A package approach would allow negotiation in a spirit or        H
    1064      SUPREME COURT REPORTS               [2009] 12 S.C.R.


A        give and take for an over-all settlement of all disputes."

       21. The then Secretary (Irrigation) Shri M.S. Billore
  constituted a committee comprising of the Engineer-in-Chief
  P.V. Srinivasaiyah, the Chief Engineer, the Financial Adviser,
  Secretary (Control Board) and the Deputy Secretary, some of
8
  whom are Accused Nos. 3, 4,5 and 11.

        22. The said Committee submitted a report in respect
    whereof the Secretary made a note that the same be critically     ~ _
    examined.
c
         The Officer on Special Duty noticed the recommendations
    of the Committee, which are as under:

        "(i) As the quarry has been changed by the Department
        due to Technical reasons the contractors cannot be held
D       responsible.

        (ii) When the Department itself did not know about the
        quarry's unsuitability it will be unfair to expect the
        contractors to bring stones from the changed quarry at the
E       same rates.

        (iii) Payment to the extent of actual quantity brought from   .,.. ~
        the quarries be made."

      The proposals of the Chief Engineer, the quantities under
F each agreement, the rate and the amount were also noticed. It
  was proposed:
        "Therefore, it is proposed to approve payment for actual
        quantity and the Chief Engineer may be informed to take
G       undertakings from the contractors before making the
        payment."                                                     (   .
         The Financial Adviser was asked to examine the said
    proposal in details. Some discussions apparently were held and
    it was found necessary to obtain the following information
H
I
0



                  STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1065
                             & ORS. [S.B. SINHA, J.]
        _,.....   before taking decision at the government level:                      A

                       "1. After the inspection of the Geologists how much quantity
                       has been brought from Therma Pahad by each contractor.

                       2. How much quantity has been brought from Katghora
                       quarry.                                                         B

                       3. How the records are kept by the Department about the
                       quantity of stones brought from different quarries."
        - }.
                       A draft letter was also prepared.                               c
                        23. On or about 6.04.1991, one Shri Uday Shinde in his
                  note· stated that the Chief Engineer had not sent any detail in
                  regard to Block 31-38 as in the agreement only Therma Pahar
                  quarry had been shown for the balance work and as the original
                  file was sent to the Hon'ble Minister, it was not possible to deal   D
          -+-
                  with the case. The file was re-submitted and the amount payable
                  to the contractor for additional lead was again put up for
                  administrative approval. Yet again, the Engineering in-Chief
                  Committee was asked to examine the matter.
                                                                                       E
                       24. In a note to the Secretary dated 27.04.1991, the salient
    ... --r       features in respect of the aforementioned matter were placed
                  again to which Shri M.S. Billore by his note dated 1.05.1991
                  opined :

                       "Since government decision has already been informed to         F
                       the Chief Engineer, Hasdeo Bango Project through
                       government letter No: 9/CP/B/31/89/319, Bhopal dated
                       28.2.89. Hence, any action at government level is not
                       pending in this case and Chief Engineer to take action in
                       this case as per government order."                             G
    •       )j

                       25. Allegedly, the respondent No. 1 who was Minister at
                  the relevant point of time sat over the file for a period of about
                  six months. He on 4.11.1991 noted:
                                                                                       H
    1066     SUPREME COURT REPORTS               [2009] 12 S.C.R.


A       "I have studied the case. Whenever any opinion has been
        sought by the Secretary, from whichever authority, they
        gave their opinion as per their wisdom. Every time the
        Secretary has been seeking the opinion from one after
        another officer. In this process he spent a period of one
B       year between 3.5.90 to 1.5.91. In accepting the opinion or
        recommending any action, it was expected from the
        Secretary to take into consideration the fact that the
        opinions had been given as per their wisdom. Therefore,
        question does not arise to take any action against the
c       subordinate officers.
       No basis appears for the Secretary to take a totally
       different view than the unanimous opinions. Therefore, it
       is necessary to investigate the basis on which the
       Secretary Shri Billore had rendered his opinion.
D
       The new Secretary to study the case and give opinion."

      26. Pursuant thereto or in furtherance thereof, the
  respondent No. 2 Shri D.V.S.R. Sarma submitted a report upon
E constitution of a Committee, stating:

       "(i) Due to technical reasons, the department has changed
       the quarry. Therefore, its liability should not be upon the
       contractors.

F      (ii) When the Department had not any knowledge about the
       quarry, and to expect this that even under the changed
       quarry the contractor should fetch/ transport the stones at
       the same rate, is also not proper.
       (iii) Where &Where (sic) and for that much of the quantities,
G      the materials have been brought from a quarry at more
       distance, it is proper to make payment for that much
       excess distance."

      27. The respondent No.1 approved the said note of the
H respondent No. 2 on or about 20.01.1992 whereupon the
            STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1067
                       & ORS. [S.B. SINHA, J.]

            amount in question was sanctioned.                                  A
     /~
                28. Thereafter, the accounts were audited and one Shri
            G.K. Shukla, Deputy Accountant General reported:

                "(a) The clause of the agreement noted above and the
                quarry chart clearly bring out that in the event of change of   B
                quarry on whatever reasons no claim will be entertained
                and contractor should before quoting rates, visit the quarry
                site and satisfy himself regarding quantity and quality of
     ->         the material available. Thus, the sanction appears a
                negotiated settlement beyond the contractual provisions,        c
                for which concurrence of Finance Department ought to
                have been obtained.

                (b) The PRC considered this as a claim case which was
                to be decided by Arbitrator under M. P. Adhikaran               D
      ~~·
                Adhiniyan, 1983.

                (c) The Member, World Bank suggested to resolve the
                matter within the contractual limits.

                (d) The Secretary Irrigation had earlier rejected the case      E
                as it was not admissible.
    > '-1
                (e) The rates quoted by the contractors were inclusive of
                all lead and lift, being item rate tender."

-               The Auditor General of India also took note of the said         F
            report, stating:

                "Therefore, in spite of the report of the Geologist that the
                good quality of stone was available in sufficient quantities
                in the upper portion of the quarry situated in the hill         G
    >. )'       mentioned in the agreement and in spite of there being
                specific provision in the agreements that no additional
                payment would be acceptable in the event of change in
                leads or change in quarry, the payments made to the
                contractors were irregular and resultantly made additional      H
     1068       SUPREME COURT REPORTS             [2009] 12 S.C.R.


A        gains of Rs. 102.46 lacs to them."
                                                                        ~.

       29. Pursuant thereto or in furtherance thereof, a complaint
  was lodged. The matter was investigated by the Special Police
  Establishment. They collected all the materials and filed a
  chargesheet in the Court of learned Special Judge on
B
  27.03.1997. The case was registered as Special Case No. 6
  of 1997.

        30. By an order dated 13.05.1997, the learned Special
    Judge took cognizance of the case, opining:                         ~   -
c
         (i)    As none of the accused is a public servant, no
                sanction was required to be obtained in terms of
                Section 19 of the Act.

         (ii)   Criminal misconduct relating to corrupt practice
D               under Section 13(1)(d)(ii-iii) of the Act has nothing
                to do with normal activity and work under               +-
                government duty of any public servant at any time.

       31. In the year 1997, the respondent Nos. 1and2 had filed
E a revision application before the High Court.
        32. The Special Judge framed charges against the
                                                                        y•
    respondents on or about 29.07.1999; a sample copy whereof
    reads as under:
F       "You were working as Minister In-charge, Ministry of Water
        Resources, Government of Madhya Pradesh from June
        1990 to September 1992 .. On the recommendatory note
        of Shri D.V.S.R. Sharma ignoring the letter dated 14.02.85
        of the Finance Branch of World Bank and earlier decision
G       dated 18.02.85 according to which the case of extra lead
        was to be decided within the ambit of the contract in           1    4

        respect of payment of extra lead to the concerned Tender
        Contractors for transportation of stones used in
        construction work of masonry non-flow dam upstream in
H       Hasdeo Bango Project. You in conspiracy with the
       STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1069
                  & ORS. [S.B. SINHA, J.]
           employees and Tender Contractors accorded                         A
           administrative sanction and payment of one crore two lac
           forty six thousand two hundred rupees was made to the
           Contractors towards extra lead. Hence, you while holding
           the post of public servant misusing the position of the post
           provided financial benefit to the Tender Contractors without      B
           public interest.

                   Your above act being offence under Section
            13(1)(D)(ii-iii), the Prevention of Corruption Act, 1988 is
            punishable under Section 13(2) the Prevention of                 C
            Corruption Act, 1988. In the alternative, you in criminal
            conspiracy with Shri D.V.S.R. Sharma, Secretary! working
            in the Ministry of Water Resources, Government of Madhya
            Pradesh and other employees and contractors acted as
            mentioned above, which is punishable under Section
            13(1)(D)(ii and iii) read with Section 1208 iPC, which is        D
            within the jurisdiction of this Court.

                  Hence, I hereby direct that you will be tried for the
            offence mentioned above by this Court."
                                                                             E
            33. Aggrieved by and dissatisfied therewith, the
       respondents filed revision applications before the High Court,
       which by reason of the impugned order have been allowed. The
       State is, thus, before us.

           34. Mr. K.T.S. Tulsi, learned senior counsel appearing on         F
       behalf of the appellant, in support of the appeal, inter alia would
       submit:

             (i)    The High Court committed a serious error in opining
                    that an order of sanction in terms of Section 197        G
                    of the Code of Criminal Procedure was required to
~ "'                be obtained despite the fact that the respondent
                    Nos. 1 to 7 were no longer holders of public
                    office(s).

             (ii)   While exercising its revisional jurisdiction, the High   H
    1070       SUPREME COURT REPORTS              [2009] 12 S.C.R.


A               Court could not enter into the question of
                appreciation of evidence as also the probative
                value of the materials brought on record, contrary
                to the tests laid down by this Court in Soma
                Chakravarty v. State Through CBI [(2007) 5 SCC
B               403] as the tests for framing of charge are different
                from the tests for recording a judgment of acquittal
                against an accused insofar as whereas in the
                former, strong suspicion would be sufficient, in the
                latter proof beyond any reasonable doubt is
c               necessary.

       (iii)   The prosecution agency being a special agency
               constituted under the Madhya Pradesh Special
               Police Establishment Act, which functions under the
               jurisdiction of the Lokayukata, only because all
D              materials have been made part of the chargesheet,
               the same could not have been relied upon by the
               High Court as the only materials upon which the
               prosecution would rely upon for proving its case
               would be the terms of the contract, the note sheets,
E              the letters dated 4.08.1983, 11.08.1983,
               16.08.1983, 17.08.1983, 10.07.1984, 14.11.1984
               and 2.03.1988, in terms whereof the contractors
               were categorically informed that they would not be
               entitled to any extra amount towards additional lead
F              or otherwise.

       (iv)    The World Bank having opined that stones from
               alternative sources may be obtained within the
               budgeted amount, the extra amount could not have
               been sanctioned by the respondents.
G
       (v)     By reason of the acts of the respondents, the State      ., •
               has suffered a loss to the extent of Rs. 1.02 crores
               and in that view of the matter, the High Court should
               not have passed the impugned order.
H
         STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1071
                    & ORS. [S.B. SINHA, J.]

              (vi)   As none of the accused is a public servant, the          A
, .,;.               question of obtaining sanction in terms of Section
                     19 of the Act did not arise.

              (vii) Criminal misconduct relating to corrupt practices
                    under Section 13( 1)(d)(ii-iii) of the Act cannot be      B
                    mingled with the normal activity and duties of the
                    public servant at any time, and, thus, no order of
                    sanction was required to be obtained even under
                    Section 197 of the Code of Criminal Procedure,
-~                  1973.
                                                                              c
              (viii) The Indian Institute of Technology having tested the
                     rocks excavated from Therma Pahar Quarry and
                     having opined that they can safely be used for
                     rubble masonry as well as for coarse and fine

   ..                aggregate, any opinion rendered contrary theret.o
                     or inconsistent therewith should have been ignored .

             35. Mr. U.U. Lalit and Mr. Vivek Tankha, learned senior
                                                                              D



         counsel appearing on behalf of the respondents, on the other
         hand, urged :
                                                                              E
              (i)    The court at the stage of framing of charge and
> ·~
                     consequently the High Court in exercise of its
                     jurisdiction under Sections 397 and 401 of the
                     Code of Criminal Procedure were entitled to
                     consider the entire materials on record for the          F
                     purpose of arriving at a finding as to whether the
                     contents thereof, even if taken to be correct in their
                     entirety, constituted a prima facie case against the
                     accused or not.
                                                                              G
              (ii)   It would not be correct to contend that although all
~.                   the documents collected during investigation form
                     part of the final report submitted by the Special
                     Police Establishment in terms of Sub-section (5) of
                     Section 173 of the Code of Criminal Procedure, for
                                                                              H
    1072           SUPREME COURT REPORTS              [2009] 12 S.C.R.
                                                                                         •

A                   the purpose of framing of charge or otherwise the
                    prosecution can rely only on a few of them so as to       ;..   .
                    make a distinction between the documents which
                    are in favour of the prosecution and those which are
                    in favour of the accused.
8
           (iii)   The materials brought on record clearly show that
                   the concerned authorities found it necessary to
                   explore the possibility of procuring stones of
                   requisite quality from other sources as they had
                   proceeded on a wrong premise that stone of                1-
c                  requisite quality to the extent of 8 lakh cubic meters
                   would be available in the quarry in question.

       (iv)        Although the contract could be considered to show
                   that no claim for any material collected elsewhere,
D                  without obtaining the prior approval of the Engineer
                   lncharge, as was contended by the prosecution,
                   was admissible, on a close reading of the terms of
                   the contract it would appear that a contingency of
                   this nature, viz., that the parties entered into a
E                  contract on a mistaken fact was not contemplated
                   as the contractors cannot be asked to take upon
                   themselves the financial burden in respect of matter
                   for which they were not responsible.                      ~      ..
       (v)         A decision having been taken by the highest
F                  authority not only upon taking into consideration the
                   opinion of all concerned, viz., from Executive
                   Engineer to the Minister concerned but also in view
                   of the opinion of the Government of India and on the
                   basis of two reports of the Committee, viz., reports
G                  by respondent No. 2 D.V.S.R. Sarma Committee
                   and respondent No. 3 P.V. Srinivasaiyah
                   Committee, no interference with the impugned
                                                                            ,, ,.
                   judgment is warranted.

H      (vi)        The documents relied upon by the prosecution, even
                   STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1073
                              & ORS. [S.B. SINHA, J.]
                              if given face value and tak~n to be correct in their    A
           ~.A                entirety, do not disclose commission of any offence
                              under the Prevention of Corruption Act as no
                              allegation had been made as regards misuse or
                              abuse of office.
-"'(                                                                               B
                      (vii)   The State having acted within its jurisdiction in
                              taking a decision in regard to making of extra
                              payment by way of novation of the original contract,
                              no exception thereto can be taken as the situation
           - t-               was unforeseen. Even the arbitral tribunal having
                              passed an award in favour of the contractor which
                                                                                      c
                              is in consonance with a decision of this Court in
                              K.N. Sathyapalan (Dead) by LRs. v. State of
                              Kera/a & Anr. [(2006) 12 SCALE 654], the
   ,.                         respondents cannot be said to have committed any
                              offence .                                            D
            . -t
                      (viii) In any view of the matter, no evidence has been
                             brought on record to show that any conspiracy was
                             entered into by the respondents inter se.
                                                                                      E
                      (ix)    Assuming that the respondents have arrived at a
                              wrong conclusion, the same would only constitute
       ~    ~                 an error of judgment and not a criminal misconduct.

                      (x)     The malafide attitude on the part of the State would
                              be evident from the fact that the respondents herein    F
                              who were members of the Committee have also
                              been roped in although they had made fair, proper
                              and impartial recommendations which could have
                              been accepted or rejected. Even the respondent
                              No. 1 in his note dated 4.11.1991 did not issue any     G
                              direction to make payment but merely asked the
       "     'f
                              respondent No. 2 to have a re-look at the entire
                              matter as prior to the purported opinion of Mr.
                              Billore, as contained in his note dated 1.05.1991
                              he had opined otherwise, viz., not in the tune of the   H
    1074          SUPREME COURT REPORTS            [2009) 12 S.C.R.


A                  recommendations made by the Quality Control
                   Department: i.e., in favour of the contractors.       c>--,

           (xi)    There is nothing on record to show that the
                   respondent Nos. 1 to 7 herein have done any act
B                  which was beyond their official duty and hence, the
                   impugned judgment is unassailable.

        36. The question raised before us is required to be
    determined on the backdrop of factual matrix involved herein.
    We have taken into consideration in details the background            ~     -
c   materials only with a view to consider as to whether the High
    Court was right in opining that no case for framing of charges
    against the re$pondents was made out.

       The fact that the State entered into contracts with the
D respondent Nos. 8, 9 and 10 is not in dispute. The basic terms
  of the contract, which we have taken note of, are also not in
                                                                         i' .
  dispute. What is in dispute is the interpretation and application
  thereof.

       37. The contract contained an arbitration clause. The
E respondents herein invoked the said arbitration agreement, as
  noticed hereinbefore, as far back in the year 1987. Indisputably,
  an award had been made in their favour on the basis of a                )>     ..._
  settlement arrived at by and between the parties. Such a
  settlement was arrived at on the basis of the stand taken by
F the authorities of the State of Madhya Pradesh upon entering
  into detailed deliberations.
       38. The learned counsel for the parties took us through the
  entire agreement to raise rival contentions as to whether
G despite the apparent rigours contained therein, the contractors
  could have been paid any additional amount towards extra
                                                                          f
  lead.                                                                          A,



       39. We think a construction of the terms of contract in the
  light of the factual matrix of the matter to which we have
H adverted to heretobefore, as has been argued by the
                  STATE OF MADHYA PRADESH v. SHEETLA SAHAl1075
                             & ORS. [S.B. SINHA, J.]

 .        ,.~   · respondents, is possible. It is, however, not necessary for us        A
                  to delve deep into the matter inasmuch as we are concerned
                  only with the question as to whether the materials brought on
                  record form sufficient basis for framing of charges under
-~                Section 13(1)(d)(ii-iii) of the Act read with Section 13(2) thereof
                  read with Section 1208 of the Indian Penal Code or not.               B
                    40. At the outset, however, we must place on record that
               construction of the dam over river Hasdeo Bango became
       -t necessary for the purpose of supply of water to the National
               Thermal Power Corporation. It was a World Bank project. The
               project was required to be completed within a time frame.                c
               Stones required to be used for the construction of the. dam, as
             , of necessity, were required to be of sufficient strength. The
     ..        opinion of the Indian Institute of Technology, referred to by Mr.
               Tulsi, is not on record. Correspondences as also the opinion
         -·+ of the Central Water Commission, Government of India,                      D
               however, point out that stones of requisite strength were not
               available at Therma Pahar Quarry. The quantum of stone
               required was eight lakh cubic meters and only one lakh cubic
               metres was available thereat. The balance seven lakh cubic
               meters of stone was, thus, required to be obtained from the              E
               quarries situated at villages villages Katghora, Hunkra and
      f- -t-
               Maheshpur.

                      41. Stone is a minor mineral within the meaning of the
                 provisions of the Mines and Minerals (Regulation and
                                                                                        F
                 Development) Act, 1957 and the Minor Mineral Concession
                 Rules framed by the State. Lease and/ or licence for extraction
                 thereof is to be granted by the Collector. Although the Mines
                 Department of the State intended to grant 'Quarry lease' in
                 favour of others having regard to the requirements of the State,
      ~   ...    the said quarries were reserved, subject to certain conditions.        G

                      42. The respondent Nos. 8 to 10, in view of the provisions
                 of the Mines and Mineral (Regulation and Development) Act,
                 1957 and the Madhya Pradesh Minor Mineral Concession
                 Rules could not have on their own undertaken mining operation          H
    1076     SUPREME COURT REPORTS               [2009] 12 S.C.R.


A for the purpose of extracting the said minor mineral. They could
  have done so only on a licence granted in their favour by the
  Collector/State. However, as the hillocks of the villages in
  question were reserved for departmental use, only by reason
  thereof the contractors could carry on mining operation thereat
8 and not otherwise. It was, therefore, a conscious decision on
  the part of the competent authorities of the State.

       43. The contract itself suggests that there was a possibility
  of dispute in regard to allocation of the parts of the quarries. A
  dispute resolution mechanism by creating a forum viz. the Office
C of the Superintending Engineer was created.

       44. The intra-departmental and inter-departmental
  correspondences and notesheets to which we have adverted
  to heretobefore clearly go to show that the authorities incharge
o of construction of the dam were aware of the difficulties which
  were being faced by the contractors. Their apprehension was
  that in the event the contractors were not permitted to mine
  stones from Katghora Quarry and other Quarries, they may
  leave the job as a result whereof the entire project might come
E to a stand-still.

       45. The representations made by the contractors for the
  aforementioned purpose, even if to be ignored, the intra-
  departmental and inter-departmental correspondences cannot
  be. They clearly point out a clear picture as regards necessity
F for explaining the possibilities of extracting stones from some
  other mines for being used in the construction of dam.

        46. We would proceed on the basis that two divergent
  opinions on the construction of the contract in the light of the
G stand taken by the World Bank as also the earlier decision
  taken by the State was possible. That, however, would not
  mean that a fresh decision could not have been taken keeping
  in view the exigencies of the situation. A decision to that effect
  was not taken only by one officer or one authority. Each one of
H the authorities was ad idem in their view in the decision making
                  STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1077
                             & ORS. [S.B. SINHA, J.]

     ....   ~
                  process. Even the Financial Adviser who was an independent           A
                  person and who had nothing to do with the implementation of
                  the project made recommendations in favour of the contractors
                  stating that if not in law but in equity they were entitled to the
                  additional amount.
                                                                                       B
                       47. From the materials available on record, it is crystal
                  clear that the decision taken was a collective one. The decision
                  was required to be taken in the exigency of the situation. It may
     ~      ·'    be an error of judgment but then no material has been brought
                  on record to show that they did so for causing any wrongful gain
                  to themselves or to a third party or for causing wrongful loss to
                                                                                       c
                  the State

.                      48. Section 13 of the Act provides for criminal misconduct
                  by a public servant. Such an offence of criminal misconduct by
                  a public servant can be said to have been committed if in terms D
            -t    of Section 13(1)(d)(ii-iii) a public servant abuses its position
                  and obtains for himself or for any other person any valuable
                  thing or pecuniary advantage; or while holding office as a public
                  servant, obtains for any person any valuable thing or pecuniary
                  advantage without any public interest. Sub-section (2) of E
                  Section 13 provides that any public servant who commits ·
j,          +     criminal misconduct shall be punishable with imprisonment for
                  a term which shall be not less than one year but which may
                  extend to seven years and shall also be liable to fine.
                                                                                       F
                       49. Criminal conspiracy has been defined in Section 120A
                  of the Indian Penal Code, 1860 to mean:

                      "When two or more persons agree to do, or cause to be
                      done,--

.           ...       ( 1) an illegal act, or
                                                                                       G

                      (2) an act which is not illegal by illegal means, such an
                      agreement is designated a criminal conspiracy:

                      Provided that no agreement except an agreement to                H
    1078          SUPREME COURT REPORTS               [2009] 12 S.C.R.


A       commit an offence shall amount to a criminal conspiracy              ·t--.....         •
        unless some act besides the agreement is done by one
        or more parties to such agreement in pursuance thereof.

        Explanation.--lt is immaterial whether the illegal act is the
        ultimate object of such agreement, or is merely incidental
B
        to that object."

        Section 1208 of the Indian Penal Code provides for
    punishment for criminal conspiracy.                                      ~ '

c      50. Criminal conspiracy is an independent offence. It is
  punishable separately. Prosecution, therefore, for the purpose
  of bringing the charge of criminal conspiracy read with the
  aforementioned provisions of the Prevention of Corruption Act
  was required to establish the offence by applying the same legal
D principles which are otherwise applicable for the purpose of
  bringing a criminal misconduct on the part of an accused.                  ~         -

        51. A criminal conspiracy must be put to action inasmuch
  as so long a crime is generated in the mind of an accused, it
  does not become punishable. What is necessary is not
E thoughts, which may even be criminal in character, often
  involuntary, but offence would be said to have been committed
                                                                                 :r-       ~
  thereunder only when that take concrete shape of an agreement
  to do or cause to be done an illegal act or an act which although
  not illegal by illegal means and then if nothing further is done
F the agreement would give rise to a criminal conspiracy.

        Its ingredients are

           (i)     an agreement between two or more persons;
G          (ii)    an agreement must relate to doing or causing to be
                   done either (a) an illegal act; (b) an act which is not
                                                                              ..
                   illegal in itself but is done by illegal means.

       What is, therefore, necessary is to show meeting of minds
H of two or more persons for doing or causing to be done an
                   STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1079
                              & ORS. [S.B. SINHA, J.]

    /    __.,,,   illegal act or an act by illegal means.                           A

                       52. While saying so, we are not oblivious of the fact that
                  often conspiracy is hatched in secrecy and for proving the said
                  offence substantial direct evidence may not be possible to be
                  obtained. An offence of criminal conspiracy can also be proved    B
                  by circumstantial evidence.

                      In Kehar Singh and Ors. v. State (Delhi Administration),
    .     .)..    [1988 (3) SCC 609 at 731), this Court has quoted the following
                  passage from Russell on Crimes (12th Edn. Vol 1):
                                                                                    c
                      "The gist of the offence of conspiracy then lies, not in doing
                      the act, or effecting the purpose for which the conspiracy
                      is formed, nor in attempting to do them, nor in inciting
                      others to do them, but in the forming of the scheme or
                      agreement between the parties. Agreement is essential. D
        --t-          Mere knowledge, or even discussion, of the plan is not, per
                      se enough"
/


                       In State (NCT) of Delhi v. Navjot Sandhu @ Afsan Guru
                  [(2005) 11 SCC 600), this Court stated the law, thus:
                                                                                 E
                      "101. One more principle which deserves notice is that the
                      cumulative effect of the proved circumstances should be
                      taken into account in determining the guilt of the accused
                      rather than adopting an isolated approach to each of the
                      circumstances. Of course, each one of the circumstances F
                      should be proved beyond reasonable doubt. Lastly, in
                      regard to the appreciation of evidence relating to the
                      conspiracy, the Court must take care to see that the acts
                      or conduct of the parties must be conscious and clear
,
                      enough to infer their concurrence as to the common design G
    •    -~           and its execution."
                       We may also notice that in Ram Narayan Pop/i v. CBI
                  [(2003) 3 sec 641], it was held:
                      "... Law making conspiracy a crime is designed to curb        H
    1080     SUPREME COURT REPORTS               [2009] 12 S.C.R.


A       immoderate power to do mischief which is gained by a
                                                                        'I- '
        combination of the means. The encouragement and
        support which co-conspirators give to one another
        rendering enterprises possible which, if left to individual
        effort, would have been impossible, furnish the ground for
B       visiting conspirators and abettors with condign
        punishment. .. "

       In Yogesh @ Sachin Jagdish Joshi v. State of
    Maharashtra [(2008) 6 SCALE 469], this Court opined:                 ~ ~



c       "23. Thus, it is manifest that the meeting of minds of two
        or more persons for doing an illegal act or an act by illegal
        means is $ine qua non of the criminal conspiracy but it may
        not be possible to prove the agreement between them by
        direct proof. Nevertheless, existence of the conspiracy and
D       its objective can be inferred from the surrounding
        circumstances and the conduct of the accused. But the           -t -

        incriminating circumstances must form a chain of events
        from which a conclusion about the guilt of the accused
        could be drawn. It is well settled that an offence of
E       conspiracy is a substantive offence and renders the mere
        agreement to commit an offence punishable even if an
        offence does not take place pursuant to the illegal
        agreement."

      Ex facie, there is no material to show that a conspiracy had
F been hatched by the respondents.

       53. Mr. Tulsi would suggest that the very fact that the
  respondent No. 1 being a Minister kept the file with him for a
  period of six months so as to see that the then Secretary Mr.
G M.S. Billore retires so as to enable him to obtain opinion of
  another officer would prima facie establish that he intended to        r
                                                                                •
  cause pecuniary gain to the respondent Nos. 8, 9 and 10.

        We have noticed hereinbefore that the Minister in his note
    dated 4.11.1991 did not make any recommendation. He merely
H
                    STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1081
                               & ORS. [S.B. SINHA, J.]

            ,.,Jr
                    lamente.d the manner in which the former Secretary Mr. M.S. A
                    Billore acted as prior thereto, the said authority himself for all
                    intent and purport had accepted the recommendations of the
                    authorities incharge of construction of the dam including the
                    Chief Engineer. He constituted a committee. He obtained the
                    opinion of the Financial Adviser. If upon consideration of the B
                    entire materials on record, independent opinion had been
                    rendered and recommendations were made, it is difficult to
                    comprehend as to how that by itself would constitute a criminal
            ,. ),
                    misconduct or leads to the conclusion of hatching any criminal
                    conspiracy. Recommendations made by the Committee or the            c
                    opinion rendered by an independent officer like FinandaL
                    Adviser need not be acted upon. Jt was for the State toJakefa
                    decision. Such a decision was required to be takenon the
                    basis of the materials available.

                             In Inspector Prem Chand v. Govt. of N. C. T. of Delhi D
            ----                                 /

                        & Ors. [2007 AIR SCW/2532], this Court observed:

                             "In State of Punjab and Ors. vs. Ram Singh Ex.
                        Constable [1992 (4) SCC 54], it was stated:
                                                                                        E
                              "Misconduct has been defined in Black's Law
                        Dictionary, Sixth Edition at page 999, thus:

                              'A transgression of some established and definite
                        rule of action, a forbidden act, a dereliction from duty,
                        unlawful behaviour, wilful in character, improper or wrong      F
                        behaviour, its synonyms are misdemeanor, misdeed,
                        misbehavior, delinquency, impropriety, mismanagement,
__...,...               offense, but not negligence or carelessness.'

                        Misconduct in office has been defined as:                       G
                              "Any unlawful behaviour by a public officer in relation
                        to the duties of his office, willful in character. Term
                        embraces acts which the officer holder had no right to
                        perform, acts performed improperly, and failure to act in
                        the face of an affirmative duty to act."                        H
                                                                                            /
    1082     SUPREME COURT REPORTS              [2009] 12 S.C.R.

A       In P. Ramanatha Aiya~s Law Lexicon, 3rd edition, at page     Jo,~,

        3027, the term 'misconduct' has been defined as under:

             "The term 'misconduct' implies, a wrongful intention,
        and not a mere error of judgment.
B            Misconduct is not necessarily the same thing as
        conduct involving moral turpitude.

             The word 'misconduct' is a relative term, and has to
        be construed with reference to the subject matter and the    "' '
c       context wherein the term occurs, having regard to the
        scope of the Act or statute which is being construed.
        Misconduct literally means wrong conduct or improper
        conduct."

        [See also Bharat Petroleum Corpn. Ltd. vs. T.K. Raju,
D
        r2oos (3) sec 143]."                                         <!- -


       54. Even under the Act, an offence cannot be said to have
  been committed only because the public servant has obtained
  either for himself or for any other person any pecuniary
E advantage. He must do so by abusing his position as public
  servant or holding office as a public servant. In the latter
  category of cases, absence of any public interest is a sine qua     1"

  non. The materials brought on record do not suggest in any
  manner whatsoever that the respondent Nos. 1 to 7 either had
F abused their position or had obtained pecuniary advantage for
  the respondent Nos. 8, 9 and 10, which was without any public
  interest.

       55. Whether, on the one hand, the dam should be
  constructed within a time frame fixed by the World Bank is a
G public interest or whether sticking to the terms of the contract
  which may lead to abandonment of work by the contractors
  would be a public interest is a matter over which a decision
  was required to be taken, particularly when the authorities
  proceeded on the basis that they had made advertisements
H and called for the tender on a wrong premise, viz., the stones
                  STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1083
                             & ORS. [S.B. SINHA, J.]
                  available in the quarry in question for supply of requisite quality   A
      ,..~        of stone was not in requisite quantity.

                       56. It is also interesting to notice that the prosecution had
                  proceeded against the officials in a pick and choose manner.
                  We may notice the following statements made in the counter-           B
                  affidavit which had not been denied or disputed to show that
                  not only those accused who were in office for a very short time
                  but also those who had retired long back before the file was
                  moved for the purpose of obtaining clearance for payment of
          >- ),
                  additional amount from the government, viz., M.N. Nadkami who
                  worked as Chief Engineer till 24.03.1987 and S.W.
                                                                                        c
                  Mohogaonkar, Superintending Engineer who worked till
                  19.06.1989 have been made accused but, on the other hand,
                  those who were one way or the other connected with the
                  decision, viz., Shri J.R. Malhotra and Mr. R.D. Nanhoria have
                  not been proceeded at all. We fail to understand on what basis        D
          - -+-   such a discrimination was made.

~
                       57. In Soma Chakravarty (supra), whereupon strong
                  reliance has been placed by Mr. Tulsi, this Court opined:
                                                                                  E
                      "23. In a case of this nature, the.learned Special Judge
                      also should have considered the question having regard
  )         +         to the "doctrine of parity" in mind. An accused similarly
                      situated has not been proceeded against only because,
                      the departmental proceedings ended in his favour.
.._
                      Whether an accused before him although stands on a F
                      similar footing despite he having not been departmentally
                      proceeded against or had not been completely exonerated
                      also required to be considered. If exoneration in a
' ~·                  departmental proceeding is the basis for not framing a
                      charge against an accused person who is said to be G
      ~               similarly situated, the question which requires a further
             '        consideration was as to whether the applicant before it
                      was similarly situated or not and/or whether the exonerated
                      officer in the departmental proce.eding also faced same
                      charges including the charge of being a party to the larger H
    1084      SUPREME COURT REPORTS               [2009] 12 S.C.R.


A        conspiracy."
                                                                         ;.    .
          58. There cannot be any doubt whatsoever that the tests
    for the purpose of framing of charge and the one for recording
    a judgment of conviction are different.
B        A distinction must be borne in mind that whereas at the
    time of framing of the charge, the court may take into
    consideration the .fact as to whether the accused might have
    committed the offence or not; at the time of recording a

c
    judgment of conviction, the prosecution is required to prove
    beyond reasonable doubt that the accused has committed the
                                                                         ".
    offence.

         59. In this case, the probative value of the materials on
    record has not been gone into. The materials brought on record
D   have been accepted as true at this stage. It is true that at this
    stage even a defence of an accused cannot be considered.
                                                                        -t •
    But, we are unable to persuade ourselves to agree with the
    submission of Mr. Tulsi that where the entire materials collected
    during investigation have been placed before the court as part
    of the chargesheet, the court at the time of framing of the
                                                                                   -
E
    char.ge could only look to those materials whereupon the
    prosecution intended to rely upon and ignore the others which
    are in favour of the accused. The question as to whether the         ~         •
    court should proceed on the basis as to whether the materials
    brought on record even if given face value and taken to be
F   correct in their entirety disclose commission of an offence or
    not must be determined having regard to the entirety of
    materials brought on record by the prosecution and not on a
    part of it. If such a construction is made, Sub-section (5) of

G
    Section 173 of the Code of Criminal Procedure shall become
    meaningless.
                                                                               ·-
                                                                         ;     <
       The prosecution, having regard to the right of an accused
  to have a fair investigation, fair inquiry and fair tri.al as
  adumbrated under Article 21 of the Constitution of India, cannot
H at any stage be deprivea of taking advantage of the materials
                    STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1085
                               & ORS. [S.B. SINHA, J.]

                   which the prosecution itself has placed on record. If upon          A
      ~--'I        perusal of the entire materials on record, the court arrives at
                   an opinion that two views are possible, charges can be framed,
                   but if only one and one view is possible to be taken, the court
                   shall not put the accused to harassment by asking him to face
                   a trial.                                                            B

                       {See State of Maharashtra and Others v. Som Nath
                   Thapa and Others [(1996) 4 SCC 659]} .
      ..-,),             60. This leaves us with the question as to whether an order
                   of sanction was required to be obtained. There exists a             c
                   distinction between a sanction for prosecution under Section
               I
                   19 of the Act and Section 197 of the Code of Criminal
                   Procedure. Whereas in terms of Section 19, it would not be
                   necessary to obtain sanction in respect of those who had
                   ceased to be a public servant, Section 197 of the Code of           D
      .   ~        Criminal Procedure requires sanction both for those who were
                   or are public servants.

                        61. Strong reliance has been placed by Mr. Tulsi on a
                   judgment of this Court in Centre for Public Interest Litigation
                                                                                       E
                   and Another v. Union of India .and Another [(2005) 8 SCC 202).
                   In that case, it was held:
,,      -+

                       "9. The protection given under Section 197 is to protect
                       responsible public servants against the institution of
                       possibly vexatious criminal proceedings for offences            F
                       alleged to have been committed by them while they are
                       acting or purporting to act as public servants. The policy
                       of the legislature is to afford adequate protection to public
>..                    servants to ensure that they are not prosecuted for anything
                       done by them in,tb~ discharge of their official duties          G
                       without reasonable cause, and if sanction is granted, to
 • ~
                       confer on the Government, if they choose to exercise it,
                       complete control of the prosecution. This protection has
                       certain limits and is available only when the alleged act
                       done by the public servant is reasonably connected with         H
    1086    SUPREME COURT REPORTS                  [2009] 12 -S.C.R.


A      the discharge of his official duty and is not merely a cloak
       for doing the objectionable act. If in doing his official duty,    "· ~
       he acted in excess of his duty, but there is a reasonable
       connection between the act and the performance of the
       official duty, the excess will not be a sufficient ground to
B      deprive the public servant from the protection. The
       question is not as to the nature of the offence such as
       whether the alleged offence contained an element
       necessarily dependent upon the offender being a public
       servant, but whether it was committed by a public servant
                                                                          .A '
c      acting or purporting to act as such in the discharge of his
       official capacity. Before Section 197 can be invoked, it
       must be shown that the official concerned was accused of
       an offence alleged to have been committed by him while
       acting or purporting to act in the discharge of his official
       duties. It is not the duty which requires examination so
D
       much as the act, because the official act can be performed
       both in the discharge of the official duty as well as in           "'" .
       dereliction of it. The act must fall within the scope and
       range of the official duties of the public servant concerned.
       It is the quality of the act which is important and the
E      protection of this section is available if the .act falls within
       the scope and range of his official duty. There cannot be
       any universal rule to determine whether there is a                  .-     "-
       reasonable connection between the act done and the
       official duty, nor is it possible to lay down any such rule.
F      One safe and sure test in this regard would be to consider
       if the omission or neglect on the part of the public servant
       to commit the act complained of could have made him
       answerable for a charge of dereliction of his official duty.

G
       If the answer to this question is in the affirmative, it may
       be said that such act was committed by the public servant
       while acting in the discharge of his official duty and there        ,.
                                                                                  ·-
                                                                                  •
       was every connection with the act complained of and the
       official duty of the public servant. This aspect makes it clear
       that the concept of Section 197 does not get immediately
H      attracted on institution of the complaint case.
                                STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1087
                                           & ORS. [S.B. SINHA, J.]
                                    10. Use of the expression "official duty" implies that the act     A
               ···""                or omission must have been done by the public servant in
                                    the course of his service and that it should have been in
                                    discharge of his duty. The section does not extend its
                                    protective cover to every act or omission done by a public
                                    servant in service but restricts its scope of operation to         B
                                    only those acts or omissions which are done by a public
                                    servant in discharge of official duty.

                                    11. If on facts, therefore, it is prima facie found that the act
              1.-       ~·
                                    or omission for which the accused was charged had
                                    reasonable connection with discharge of his duty then it
                                                                                                       c
                                    must be held to be official to which applicability of Section
                                    197 of the Code cannot be disputed."

     ,                             62. Were the respondent Nos. 1 to 7 required to act in the
                               matter as a part of official duty?                                      D
              >         -+-
                                     Indisputably, they were required to do so. Be he an
                                Executive Engineer, Superintending Engineer, Chief Engineer,
                                Engineer-in-Chief, Secretary or Deputy Secretary, matters were
                                placed before them by their subordinate officers. They were
                                                                                                 E
                                required to take action thereupon. They were required to apply
     ,•                        their own mind. A decision on their part was required to be
          ~     --..           taken so as to enable them to oversee supervision and
                               completion of a government project. The Minister having regard
                               to the provisions of the Rules of Executive Business was
                               required to take a decision for and on behalf of the State. Some F
                               of the respondents, as noticed hereinbefore, were required to
                               render their individual opinion required by their superiors. They
                               were members of the Committee constituted by the authorities,
                              viz., the Minister or the Secretary. At that stage, it was not
                              possible for them to refuse to be a Member of the Committee G
          ~       .I.         and/ or not to render any opinion at all when they were asked
                              to perform their duties. They were required to do the same and,
-~
                              thus, there cannot be any doubt whatsoever that each one of
                              the respondent Nos. 1 to 7 was performing his official duties.
                                                                                                 H
        1088      SUPREME COURT REPORTS                [2009] 12 S.C.R.


A      63. For the purpose of attracting the provisions of Section              ,.._
  197 of the Code of Criminal Procedure, it is not necessary that
  they must act in their official capacity but even where a public
  servant purports to act in their official capacity, the same would
  attract the provisions of Section 197 of the Code of Criminal
B Procedure. It was so held by this Court in Sankaran Moitra v.
  Sadhna pas and Another [(2006) 4 SCC 584].

            The question came up for consideration before this Court
        in Matajog Dobey v. H.C. Bhari [AIR 1956 SC 44 : 1955 (2)               ~    .
        SCR 925] wherein it was held:
c
            "17. Slightly differing tests have been laid down in the
            decided cases to ascertain the scope and the meaning
            of the relevant words occurring in Section 197 of the Code;
            "any offence alleged to have been committed by him while
            acting or purporting to act in the discharge of his official
D
            duty". But the difference is only in language and not in            ...
            substance. The offence alleged to have been committed
            must have something to do, or must be related in some
            manner with the discharge of official duty. No question of
E            sanction can arise under Section 197, unless the act
             complained of is an offence; the only point to determine
             is whether it was committed in the discharge of official               ,, '-
             duty. There must be a reasonable connection between the
             act and the official duty. It does not matter even if the act
             exceeds what is strictly necessary for the discharge of the
 F
              duty, as this question will arise only at a later stage when
              the trial proceeds on the merits. What we must find out is
              whether the act and the official duty are so inter-related that                ,:s;-;
              one can postulate reasonably that it was done by the
              accused in the performance of the official duty, though
 G            possibly in excess of the needs and requirements of the
               situation. In Hori Barn Singh v. Crown Sulaiman, J.
                                                                                    •    •
               observes:
                                                                                             r
               "The section cannot be confined to only such acts as are
    H          done by a public servant directly in pursuance of his public
                 STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1089
                            & ORS. [S.B. SINHA, J.]

      r><            office, though in excess of the duty or under a mistaken          A
                     belief as to the existence of such duty. Nor is it necessary
                     to go to the length of saying that the act constituting the
                     offence should be so inseparably connected with the
                     official duty as to form part and parcel of the same
                     transaction."                                                     B

                     The interpretation that found favour with Varadachariar, J.
                     in the same case is stated by him in these terms at p. 187:
      r- Jr          "There must be something in the nature of the act
                     complained of that attaches it to the official character of
                     the person doing it." In affirming this view, the Judicial
                                                                                       c
                     Committee of the Privy Council observe in Gill case: "A
                     public servant can only be said to act or purport to act in ·
.,.                  the discharge of his official duty, if his act is such as to lie
                     within the scope of his official duty ... The test may well
          ' -t       be whether the public servant, if challenged, can D
  '
                     reasonably claim that, what he does, he does in virtue of
                     his office." Hori Ram case is referred to with approval in
                     the later case of Lieutenant Hector Thomas Huntley v.
                     King-Emperor but the test laid down that it must be
                     established that the act complained of was an official act E
                     appears to us unduly to narrow down the scope of the
      >    ...       protection afforded by Section 197 of the Criminal
                     Procedure Code as defined and understood in the earlier
                     case. The decision in Meads v. King does not carry us
                     any further; it adopts the reasoning in Gill's case."            F

                     The said principle has been reiterated by this Court in ;:
                 Saha v. M.S. Kochar [(1979) 4 SCC 177] in the foilowi1,g
                 terms:

                     "17. The words "any offence alleged to have been                  G
      I      ~
                     committed by him while acting or purporting to act in the
                     discharge of his official duty" employed in Section 197(1)
                     of the Code, are capable of a narrow as well as a wide
                     interpretation. If these words are construed too narrowly,
                     the section will be rendered altogether sterile, for, "it is no   H
    1090      SUPREME COURT REPORTS                 [2009] 12 S.C.R.


A        part of an official duty to commit an offence, and never can           :.. -..
         be". In the wider sense, these words will take under their
         umbrella every act constituting an offence, committed in the
         course of the same transaction in which the official duty is
         performed or purports to be performed. The right approach
B       to the import of these words lies between these two
        extremes. While on the one hand, it is not every offence
        committed by a public servant while engaged in the
        performance of his official duty, which is entitled to the
        protection of Section 197(1), an act constituting an offence,          "     '

c       directly and reasonably connected with his official duty will
        require sanction for prosecution under the said provision.
        As pointed out by Ramaswami, J., in Baijnath v. State of
        M.P., "it is the quality of the act that is important, and if it
        falls within the scope and range of his official duties, the
        protection contemplated by Section 197 of the Criminal
                                                                                             ....
D
        Procedure Code will be attracted".                                 t     .


        18. In sum, the sine qua non for the applicability of this
        section is that the offence charged, be it one of
        commission or omission, must be one which has been
E       committed by the public servant either in his official
        capacity or under colour of fhe office held by him."
                                                                           ,.
        [See also R. Balakrishna Pillai v. State of Kera/a and
                                                                                         "
    Another [(1996) 1 SCC 478]
F        In Rakesh Kumar Mishra v. State of Bihar and Others
    [(2006) 1 SCC 557], this Court held:
        "12. It has been widened further by extending protection
        to even those acts or omissions which are done in
G       purported exercise of official duty; that is under the colour
        of office. Official duty, therefore, implies that the act or       • •
        omission must have been done by the public servant in the
        course of his service and such act or omission must have
        been performed as part of duty which further must have
H       been official in nature. The section has, thus, to be
            STATE OF MADHYA PRADESH v. SHEETLA SAHAI 1091
                       & ORS. [S.B. SINHA, J.]

                construed strictly, while determining its applicability to any   A
...   ;(
                act or omission in the course of service. Its operation has
                to be limited to those duties which are discharged in the
                course of duty. But once any act or omission has been
                found to have been committed by a public servant in the
                discharge of his duty then it must be given liberal and wide     B
                construction so far its official nature is concerned. For
                instance a public servant is not entitled to indulge in
                criminal activities. To that extent the section has to be
 »·· ·t·        construed narrowly and in a restricted manner. But once it
                is established that an act or omission was done by the           c
                public servant while discharging his duty then the scope
                of its being official should be construed so as to advance
                the objective of the section in favour of the public servant.
                Otherwise the entire purpose of affording protection to a
                public servant without sanction shall stand frustrated. For
                instance a police officer in the discharge of duty may have
                                                                                 p
  ~    -t
                to use force which may be an offence for the prosecution
                of which the sanction may be necessary. But if the same
                officer commits an act in the course of service but rtot in
                the discharge of his duty and without any justification
                therefor  then the bar under Section 197 of the Code is not      E
                   .                                                        .
                attracted ... "
      ...
                64. Reliance has been placed by Mr. Tutsi on Parkash
            Singh Badal v. State of Punjab and Others [(2007) 1 SCC 1]
            wherein this Court held:                                             F

                "38. The question relating to the need of sanction under
                Section 197 of the Code is not necessarily to be
                considered as soon as the complaint is lodged and on the
                allegations contained therein. This question may arise at
                                                                                 G
                any stage of the proceeding. The question whether
+ ·~            sanction is necessary or not may have to be determined
                from stage to stage."

               In that case, the appellant therein was charged for
            commission of an offence of cheating under Section 420 and           H
    1092        SUPREME COURT REPORTS                 [2009] 12 S.C.R.


A Sections 467, 468, 471 and 1208 of the Indian Penal Code.

           In the factual matrix involved therein, it was held:
                                                                             )..   .
           "29. The effect of sub-sections (3) and (4) of Section 19
           of the Act are of considerable significance. In sub-section
B          (3) the stress is on "failure of justice" and that too "in the
           opinion of the court". In sub-section (4), the stress is on
           raising the plea at the appropriate time. Significantly, the
           "failure of justice" is relatable to error, omission or
           irregularity in the sanction. Therefore, mere error, omission     f     '
c          or irregularity in sanction is (sic not) considered fatal
           unless it has resulted in failure of justice or has been
           occasioned thereby. Section 19(1) is a matter of procedure
           and does not go to the root of jurisdiction as observed in
           para 95 of Narasimha Rao case. Sub-section (3)(c) of
D          Section 19 reduces the rigour of prohibition. In Section
           6(2) of the old Act [Section 19(2) of the Act] question
           relates to doubt about authority to grant sanction and not       +- '
           whether sanction is necessary."

         65. In State of Karantaka v. Ameerjan [(2007) 11 SCC
E
    273], it was held that an. order of sanction is required to be
    passed on due application of mind.
                                                                            .,
       66. Thus, in this case, sanction for prosecution in terms of
  Section 197 of the Code of Criminal Procedure was required
F to be obtained.

         67. For the reasons aforementioned, there is no merit in
    this appeal which is dismissed accordingly.

    G.N.                                           Appeal dismissed.

                                                                            •          ~


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "criminal conspiracy"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.