Created byFuzzy Cloud

Supreme Court of India

STATE OF RAJASTHANversusM/S. NAV BHARAT CONSTRUCTION CO.

Citation
2005 INSC 479
Decided
4 October 2005
Disposal
Disposed off

Holding

The umpire was not proven biased, must confine his award to the claims actually referred, need not give reasons unless the contract requires, and his award of claims contrary to the contract constitutes misconduct, warranting its setting aside and remand to a new umpire.

Summary

The State of Rajasthan awarded a construction contract to Nav Bharat Construction Co., which later terminated the contract for delay. The contractor filed multiple claims, of which the district court initially referred only one claim to arbitration; the High Court later ordered all four claims to be referred. Subsequent applications led to 28 claims being referred, but the arbitrators received 39 claims. A difference of opinion between the two arbitrators led to the appointment of an umpire, V.K. Gupta, who awarded all 39 claims. The State challenged the umpire on grounds of bias, excess jurisdiction, failure to give reasons, and awarding contrary to contract terms. The Supreme Court held that bias was not proved, the umpire should have confined the award to the claims actually referred, and under the Arbitration Act 1940 reasons are not mandatory unless the contract requires them. Since the umpire awarded claims beyond the contract, he mis‑conducted himself. The Court set aside the award and remitted the matter to an independent umpire, disposing of the appeals.

Issues considered

  • Whether the umpire was biased against the State of Rajasthan.
  • Whether the umpire exceeded his jurisdiction by deciding claims not referred to arbitration.
  • Whether the umpire was required to give a reasoned award under the Arbitration Act, 1940.
  • Whether the umpire mis‑conducted himself by awarding amounts contrary to the terms of the contract.
  • Whether the award should be set aside on the grounds of bias, excess jurisdiction, or misconduct.

Legislation cited

Subjects

ArbitrationUmpireBiasJurisdictionReasoned awardArbitration Act 1940Construction contractAward set asideMisconduct

Judgment

A                              STATE OF RAJASTHAN
                                            V.

                    MIS. NA V BHARAT CONSTRUCTION CO.

                                  OCTOBER 4, 2005

B                [S.N. VARIAVA AND TARUN CHATTERJEE, JJ.]


           Arbitration:

          ·contract-Dispute-Reference of claims to arbitration-Reference of
C 28 claims-Decision of 39 claims-Difference of opinion between two
     arbitrators-Dispute referred to Umpire arbitrator-Award by Umpire
     challenged on the grounds that the Umpire was biased; that decision of 39
     claims were wrong as only 28 claims were referred; and that the umpire had
     misconducted himself by not giving reasoned award and by passing the award
D    contrary to the terms of the contract-Held: In the facts of the case bias not
     proved-Umpire should have confined its award only to the claims made in
     the applications-The Act does not require giving reasons unless the contract
     so requires-An arbitrator cannot go beyond the terms of the contract-The
     majority of the claims in the present case are against the terms of the contract-
     Award is not set aside on the ground of misconduct as it would cause hardship
E    to the party who had got contract-Hence award set aside and matter referred
     to independent Umpire appointed by this Court-Arbitration Act, 1940.
            A contract for construction was awarded by appellant to the
     respondent. Despite extension of time, respondent was not able to complete
     the work within stipulated time. The contract was terminated and the
F    balance work was completed by some other contractor. Various claims of
     respondents were rejected by appellants. The respondent moved
     application u/s.20 of Arbitration Act, 1940 for reference of 4 claims to the
     Arbitrator. District Judge referred only one claim and refused to refer
     other three claims as not referable. In appeal, High Court directed that
G    all the four claims be referred to arbitration. In the meantime, respondent
     had filed another application· u/s 20 of the Act seeking reference of 24 more
     claims and the same was allowed. Disputes were referred to two
     arbitrators. Due to difference of opinion between the two arbitrators,
     dispute was referred to an Umpire arbitrator. Appellant filed application
     seeking removal of the Umpire on the ground of bias and the same was
fl                                         988
            STATE OF RAJASTllAN "· NAV BHARAT CONSTRUCTION CO.         989
dismissed. Revision against the same was also dismissed. Umpire passed        A
the award. Appellants' objection was dismissed by trial court. The cross-
appeals of the appellants and respondents were dismissed by High Court.
Hence the present cross-appeals.

     It was contended that the Umpire was biased; that the Umpire had
wrongly decided 39 claims as only 28 claims were referred; that as one of     B
the Arbitrators out of the two, had given reasoned and speaking order,
the Umpire by not giving reasoned award had misconducted himself; that
the Umpire had also misconducted himself inasmuch as he had awarded
contrary to the terms of the contract.

      Disposing of the appeals, the Court                                     c
      HELD: 1. It cannot be said that the Umpire was biased against the
appella~ts inasmuch as he was the person, who regularly appeared for the
respondent in arbitration matters and assisted the respondent in their
arbitration cases. On this ground the Appellant had earlier filed an
application for removal of the Umpire. That application came to be            D
rejected and an appeal against that order was also dismissed. Having failed
in their attempt to remove the Umpire, this ground is no longer available
to the appellants. Even otherwise except for making bare averments no
proof has been produced to substantiate the averments. If, this Umpire
was appearing for and/or regularly assisting the respondents there would      E
be documents showing his name/appearance. None have been produced.
                                                          [994-F; 995-A-BJ

      Ran)it Thakur v. Union of India and Ors., [1987) 4 SCC 611 and Jiwan
Kumar Lohia and Anr. v. Durga Dutt Lohia and Ors., [1992] 1 SCC 56,
referred to.                                                                  F
      2. If any claim did not form part of the two applications the same
cannot be arbitrated upon and the Umpire will confine the reference to
the claims made in the two applications. It prima facie appears that the
two applications were for referring, in all, 28 claims to arbitration.        G
                                                         (995-F-G; 995-C(

    Orissa Mining Corporation Ltd v. Prannath Vishvanath Rawlley, [1977)
3 SCC 535 and H.L. Batra and Co. v. State of Haryana and Anr.. (1999] 9
sec 188, relied on.
                                                                              H
    990                    SUPREME COURT REPORTS [2005] SUPP. 3 S.C.R.

A        3. Under the Arbitration Act 1940, unless the contract so required,
    reasons were not required to be given. The mere fact that two Arbitrators
    had differed and that the matter was required to be dealt with by an
    Umpire does not mean that the Umpire should give reasons for his Award.
                                                                   (996-C-D]

B        Raipur Development Authority and Ors. v. Mis. Chokhamal Contractors
    and Ors., (1989] 2 SCC 721, followed.

         4.1. An arbitrator cannot go beyond the terms of the contract
    between the parties. In the guise of doing justice he cannot award contrary
C   to the terms of the contract. If he does so he will have misconducted
    himself. Of course if an interpretation of a term of the contract is involved
    then the interpretation of the arbitrator must be accepted unless it is one
    which could not be reasonably possible. However where the term of the
    contract is clear and unambiguous the arbitrator cannot ignore it.
                                                                     (1008-C-D]
D
          4.2. In this case the award itself states that the award is against claims
    l to 39, except claim no. 30. Therefore this award is in respect of claims
    covered by the contract and to that extent the Umpire has misconducted
    himself. (1009-A]

E         4.3. The Contract is very specific. The majority of the claims are
    against the terms of the Contract. However, there are also other claims,
    which are not against the terms of the Contract. To merely set aside the
    Award on ground of misconduct would work hardship on the Respondent
    as they would then be depriyed of claims which may be maintainable. The
F   correct course would be to set aside the award and refer the matter back
    to an independent Umpire appointed by this Court. The Umpire will fix
    his own terms and conditions. However it is clarified that only those claims
    covered by the two applications will be considered. [1009-E; 1010-C-D[

          4.4. The Umpire will also decide whether the Respondent had agreed
G to do the contracted work done during the extended period at the same
    rates and/or whether the Respondent is entitled to increased rates and if
    so at what rate. The Umpire shall decide only on the basis of the materials
    already placed before the earlier Arbitrators and the earlier Umpire.
                                                                      [1010-E]
H
...:..,         STATE OF RAJASTHAN v. NAY BHARAT CONSTRUCTION CO. [VARIAVA, J.]    991
                4.5. It is clarified that this is not a new reference but a continuation   A
          of the earlier proceedings and thus the Arbitration Act 1940 shall continue
          to apply. (1011-AI

                Paradip Port Trust and Ors. v. Unique Builders, AIR (2001) SC 846,
          distinguished.
                                                                                           B
                Bharat Coking Coal Ltd. v. L.K. Ahuja and Co., (2001) 4 SCC 86;
          Continental Constructions Co. Ltd. v. State of M.P., (1988) 3 SCC 82;
          Hindustan Steel Works Construction Ltd v. C. Rajasekhar Rao, [1987) 4 SCC
          93; S. Harcharan Singh v. Union of India, AIR (1991) SC 945; Hindustan
          Constructions Co. Ltd. v. State of J & K, AIR (1992) SC 2192; Continental
          Construction Ltd. v. State of U.P. 12003) 8 SCC 4; Mis. Sudarsan Trading         c
          Co. v. State of Kera/a, AIR (1989) SC 890; P.M Paul v. Union of India, AIR
          (1989) SC 1034; Build India Construction System v. Union of India, (2002)
          5 SCC 433 and Tarapore and Co. v. State of M.P., (1994) 3 SCC 521,
          referred to.

                CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2500 of 200 I.             D
               From the Judgment and Order dated 10.12. 99 of the Rajasthan High
          Court in S.B.C.M.A. No. 1091 of 1996.

               V.A. Mohta, Aruneshwar Gupta, Naveen Kumar Singh and Nilakanta
          Nayak with him for the appellant in C.A. No. 2500/200 I and Respondent in        E
          C.A. No. 2501/2001.

                Moolchand Luhadia, Respondent In-person in C.A. No. 2500/200 I and
          appellant-in-person In C.A. No. 2501/2001.

               The Judgment of the Court was delivered by
                                                                                           F
              S.N. VARIA VA, J. These Appeals are against the Judgment dated I 0th
          December 1999 of the Rajasthan High Court.

               Briefly stated the facts are as follows.

                The Appellants invited tenders for construction of Bhimsagar Dam.
          Pursuant thereto, various tenders were received. Ultimately the tender of the    G
          Respondent was accepted. A contract was awarded to the Respondent on
          18th January 1979. Under the contract, the work was to be started on 16th
          November 1978 and to be completed by 15th May 1981. The work was not
          completed within this time and time was extended. It appears that the work
•
          was not completed within the extended time also. The Appellants terminated       H
    992                    SUPREME COURT REPORTS [2005] SUPP. 3 S.C.R.

A the contract and got the balance work completed from some other contractor.
           The Respondent raised various claims which were rejected by the
    Appellants. The Respondent, therefore, moved an application under Section
    20 of the Arbitration Act, 1940 for referring the claims mentioned therein to
    arbitration. By an Order dated 11th November 1982, the District Judge held
B   that only one claim was referable to arbitration and refused to refer the other
    three claims to arbitration.

          The Respondent filed an Appeal before the High Court. The High
    Court by its Order dated 7th June 1984 held that it was for the Arbitrator to
    decide whether the claims were to be awarded or not. The High Court held
C   that reference could not be refused and, therefore, directed that all the four
    claims be referred to arbitration.
          Even before the High Court passed the Order dt. 7th June 1984, the
    Respondent had, on 31st March 1983, filed another application under Section
    20 of the Arbitration Act, 1940. By this application the Respondent sought
D   reference of 24 more claims. The District Judge by an Order dated I st March
    1985 allowed the application.
          The disputes were referred to two Arbitrators. One Shri M.K. Gambhir
    was appointed by the Appellants and Shri Leeladhar Aggarwal was appointed
    by the Respondent. The Respondent, however, filed 39 claims amounting to
E   Rs. 42,59,155.56 before the Arbitrators.
          Parties led oral and documentary evidence. There was a difference of
    opinions between the two Arbitrators. Therefore, the Arbitrators referred the
    disputes to an Umpire viz. one Shri V. K. Gupta.
F         The Appellants filed an application under Section 11 of the Arbitration
    Act, 1940 for removal of Shri V. K. Gupta as an Umpire on the ground of
    bias. This application was dismissed on 16th November 1993 inter a/ia on
    the ground that there was no evidence to show that there was any bias. The
    Appellants filed a Revision which also came to be dismissed by the High
    Court in January 1995.
G        The Umpire entered into the reference and gave an Award on 29th May
    1995. The operative part of the Award reads as follows:-
            " ...... And having carefully considered the oral evidence, the
            documents, site topographical conditions, analysis of rates, technical
            specifications, other exhibits filed by the parties, the operations
H
       STATE OF RAJASTHAN 1·. NA V BHARAT CONSTRUCTION CO. [VARIA VA. J.]   993
        required for various items of existing B.S.R. and newly approved          A
        rates for Bhim Sagar Dam, Schedule 'C' the conditions of the contract,
        P. W.F.A.R. and various case laws cited by the parties, I make the
        award as under:-

            I award an amount of Rs. 29,96,060/- (Rupees Twenty nine lacs
        Ninety-six thousand and sixty only) payable by the Respondents to         B
        the Claimants against claim Nos. 1 to 39 except Claim No. 30 (as
        awarded below separately) and enumerated under paras 15 and 16 of
        the statement of claims of the Claimants.

            I further award refund/release of the Bank F.D.R.S. amounting to
        Rs. 2,84,000/- (Rupees two lacs eighty-four thousand only) being          C
        security deposit by the Respondents in favour of Claimants as claimed
        under para 17 of the Claim statement.

            I award an interest difference of (18% - F.D.R. interest rate on
        F.D.R. amount w.e.f. 15.12.82 till released to the Claimants or decreed
        whichever is earlier however the interest already accrued from 17.11.78   D
        upto 14.12.82 is to be reduced from the final calculated sum.

           I also award an interest @ 18% per annum from 15.12.82 to
       14.7.83 on total amount of claims except F.D.R. amount payable to
       Claimants as prior to reference.
                                                                                  E
           I further award an interest@ 18% p.a. from 15.7.83 to 29.5.95
       on total amount of Claims except F.0.R. amount payable to Claimants
       as pendente lite interest.

           I further award an interest @ 18% p.a. on total amount of Claims
       except F.0.R. amounts beyond 29.5.95 upto the date of payment or           F
       decree of the Court whichever is earlier.

           I further award that the Respondents shall pay a part of the cost
       of arbitration and part of fees of arbitrator and Umpire to the extent
       of Rs.20,000 to the Claimants."
                                                                                  G
      The Appellants filed objections under Sections 30 and 33 of the
Arbitration Act 1940, which were dismissed by the Trial Court or, !6th July
1996. The Appellants filed an Appeal before the High Court and the
Respondent filed a Cross-Appeal claiming compound interest. The High Court
by the impugned Judgment dismissed both the Appeals. Civil Appeal No.2500
of 200 I is by the Appellants who are aggrieved by the dismissal of their
                                         \
                                                                                  H
    994                   SUPREME COURT REPORTS [2005) SUPP. 3 S.C.R.

A objections. Civil Appeal No.250 I of 200 I is by the Respondents against
    dismissal of their claim for compound interest.

          Mr. Mohta has assailed the Award on five grounds:

           (I) that the Umpire was biased against the Appellants inasmuch as
B               he was person, who regularly appeared for the Respondent in
                arbitration matters and assisted the Respondent in their arbitration
                cases;
           (2) that the Court had referred only 28 claims yet all the 39 claims
               have been allowed by the Umpire. It was submitted that in respect
c              of the claim which had not been referred to arbitration the Umpire
               had no jurisdiction to arbitrate and the Award in respect of those
               claims had to be set aside;
           (3) that as there had been a difference of opinion between the two
               Arbitrators and, one of the Arbitrators namely, Mr. Gambhir,
               had given a speaking and reasoned Award, the Umpire was also
D
               bound to pass a reasoned Award. It was submitted that by not
               giving a reasoned Award the Umpire had misconducted himself;
           (4) that the Umpire had misconducted himself inasmuch as he had
               not applied his mind to the terms of the contract and had awarded
               contrary to the terms of the contract; and
E
           (5) that the interest awarded is very high and that in an identical
               matter between the same parties, reported in (2002] I SCC 659,
               this Court has reduced interest to 6%.

          Mr. Mohta first submitted that the Umpire was biased against the
F Appellants inasmuch as he was the person, who regularly appeared for the
  Respondent in arbitration matters and assisted the Respondent in their
  arbitration cases. Mr. Mohta relied on the case of Ranjit Thakur v. Union of
  India and Ors., reported in [l987j 4 SCC 611. In this case it has been held
  that the test of real likelihood of bias is whether a reasonable person in
G possession of relevant information would have thought that bias was likely
  and whether the authority concerned was likely to be disposed to decide the
  matter only in a particular manner. It is held that what is relevant is the
  reasonableness of the apprehension in that regard in the mind of the party.
  Mr. Mohta also relied on the case of Jiwan Kumar lohia and Anr. v. Durga
  Dutt lohia and Ors., reported in [ 1992] I SCC 56 wherein also the same
H principles have been reiterated. We see no substance in this first ground of
       STATE OF RAJASTHAN "· NAV BHARAT CONSTRUCTION CO. [VARIAVA, J.]       995
challenge. On the ground now urged the Appellant had earlier filed an              A
application for removal of the Umpire. That application came to be rejected
on 16th November 1993 and an Appeal against that Order was also dismissed
in January 1995. Having failed in their attempt to remove the Umpire, in our
view, this ground is no longer available to the Appellants. Even otherwise
except for making bare averments no proof has been produced to substantiate
the averments. If, as claimed, this Umpire was appearing for and/or regularly
                                                                                   B
assisting the Respondents there would be documents showing his name/
appearance. None have been produced.

        So far as the second ground is concerned, we have seen the two
 applications made by the Respondent. It prima facie appears that the two C
 applications were for referring, in all, 28 claims to arbitration. The Respondent
then made 39 claims before the Arbitrators. The Umpire has awarded in
 respect of all the 39 claims. If claims not referred to Arbitration have been
 dealt with and awarded the Umpire would have exceeded his jurisdiction.
 However Mr. Moolchand Luhadia, partner of the Respondent who appeared
 in person, contended that all the claims were referred to the Arbitrators by D
the Order dt. !st March 1985. He submitted that this is clear from the directions
to the Arbitrators to decide all disputes arising between the parties. We are
unable to accept this submission. The Order dt. I st March 1985 allows
"application dt. 9th April 1983 as part of application dt. 5th October 1981 ".
It is in the context of claims raised in these two applications that the Arbitrators E
are instructed to decide all disputes between the parties. Mr. Lohadia then
submitted that all claims were included in the two applications made by
them. It was submitted that in the applications some of the claims were
clubbed together but whilst filing the statement of claims they were segregated
and separated. As we are proposing to refer the matter back to an Umpire,
we do not propose to go into the question as to whether or not the 39 claims F
were part of the two applications filed by the Respondent. In our view, this
is a question which can be decided by the Umpire. All that we need to clarify
is that if any claim did not form part of the two applications the same cannot
be arbitrated upon and the Umpire will confine the reference to the claims
made in the two applications. It must be mentioned that in the case of Orissa G
Mining Corporation Ltd. v. Prannath Vishvanath Rawlley, reported in (1977]
3 SCC 535 this Court has held that when an agreement is filed in Court and
an order of reference is made, then the claim as a result of the order of
reference is limited to that relief and the arbitrator cannot enlarge the scope
of reference and entertain fresh claims without a further order of reference.
It must also be mentioned that Mr. Lohadia had relied upon the case of H. H
    996                     SUPREME COURT REPORTS [2005) SUPP. 3 S.C.R.

A L. Batra & Co. v. State of Haryana and Anr. Reported in (1999] 9 SCC 188.
    In this case the award of the arbitrator was set aside and a new arbitrator was
    appointed. The order stated that the new arbitrator was appointed "for settling
    disputes between the parties". Before the new arbitrator 7 additional claims,
    over and above the 30 claims originally made, were made. It was held that
    the award was not vitiated as the terms of reference did not confine the
B   second reference to only 30 claims. This authority is of no assistance to the
    Respondent as it does not lay down that the arbitrator can entertain claims
    not referred to him.

          We, however, see no substance in the third ground i.e. that reasons
C   should have been given by the Umpire. It is settled position that under the
    Arbitration Act 1940, unless the contract so required, reasons were not required
    to be given. A Constitution Bench of this Court in the case Raipur Development
    Authority and Ors. v. Mis Chokhamal Contractors and Ors., reported in
    (1989] 2 SCC 721, has held that it is not necessary. to give reasons and that
    an Award cannot be set aside merely because it is a non-speaking Award.
D   The mere fact that two Arbitrators had differed and that the matter was
    required to be dealt with by an Umpire does not mean that the Umpire should
    give reasons for his Award. We further clarify that the Umpire now being
    appointed by us need not give reasons.

          Mr. Mohta had next contended that the Umpire has misconducted himself
E   inasmuch as he had ignored the terms of the contract and awarded contrary
    to the terms of the contract. To this objection, the Respondent had submitted
    that such a point had neither been urged before the District Judge nor before
    the High Court. We, however, find that this point has in fact been urged both
    before the District Judge as well as before the High Court. This point, therefore,
F   requires to be considered.

          In order to consider this point, some of the terms and conditions of the
    tender documents and the contract are required to be set out.

          The Respondent has given a declaration which inter-alia reads as
G follows:
            "I. I/We have visited the Site and fully acquainted myself/ourselves
            the local situation regarding materials, labour and other factors
            pertaining to the work before submitting this order.

            2. !/We carefully studied the N.1.T. conditions of contract,
H
      STATE OF RAJASTHAN '" NA V BHARAT CONSTRUCTION CO. [VARIA VA.J.]    997
        specification, additional instructions, general rules and directions and A
        other documents related to this work and I/We agree to execute the
        work accordingly.



       I/We do hereby tender for the execution for the Rajasthan Government B
       of the work specified as above within the time specified in Schedule
       'F' and at the rates entered in Schedule 'G '. The work will be carried
       out in accordance in all respects with the detailed specifications,
       designs, drawings and instructions referred to in the attached Schedule
       sheet."

      The relevant terms of the tender document (which is part of the contract)
                                                                                  c
and the contract reads as follows;

       "7. HOUSES:-

       No local housing is likely to be available and the contract should D
       arrange for suitable housing for the staff and labour. Land for the
       same will be granted free of charge for temporary use during the
       period of contract.



       12. SUPPLY OF PETROL AND DIESEL:-                                          E
       The contractor has to make his own arrangements for the supply of
       petrol and diesel and lubricants. The nearest place from where it can
       be obtained is Jhalawar.

                                                                                  F
       Clause 12-The Engineer-in-Charge shall have power to make any
       alterations in or additions to the original specifications, drawings,
       designs and instructions, that may appear to him be necessary or
       advisable during the progress of the work and the contractor shall be
       bound to carry out the working in accordance with any instruction G
       which may be given to him in writing signed by the Engineer-in-
       Charge and such alteration shall not invalidate the contract and any
       additional work which the Contractor may be directed to do in the
       manner above specified as part of the work shall be carried out by
       the contractor on the same conditions in all respects 011 which he         H
    998                   SUPREME COURT REPORTS [2005] SUPP. 3 S.C.R.

A         agreed to do the main work, and at the same rates as are specified
          in tender for the main work. The time for the completion of the work
          shall be extended in the proportion that the additional work bears to
          the original contract work, and the certificate of the Engineer-in-
          Charge shall be conclusive as to such proportion. And if the additional
          work includes any class of work for which rate is specified in this
B         contract then such class of work shall be carried out at the rates
          entered in the schedule of rates of the district if it exists and such last
          mentioned class of work is not entered in the schedule of rates of the
          district, then the contractor shall, within seven days of the date of this
          receipt of the order to carry out the work, inform the Engineer-in-
c         Charge of the rate which it is his intention to charge for such class
          of work and if the Engineer-in-Charge does not agree to this rate he
          shall, by notice in writing, be at liberty to cancel his order to carry
          out such class of work and arrange to carry it out in such manner as
          he may consider advisable, provided always if the contractor shall
          commence work or incur any expenditure in regard thereto before the
D         rates shall have been determined as lastly herein before mentioned,
          then and in such case he shall only be entitled to be paid in respect
          of the work carried out or expenditure incurred by him prior to the
          date of the determination of the rate as aforesaid according to such
          rate or rates as shall be fixed by the Engineer-in-Charge. In the event
E         of a dispute, the decision of the Chief Engineer will be final.



          Clause 23-Except where otherwise specified in the contract the decision
          of the Chief Engineer of the Government of Rajasthan for the time
          being shall be final, conclusive, and binding on all parties to the
F         contract upon all questions relating to the meaning of the specifications,
          designs, drawings and instructions herein before mentioned and as to
          the quality of workmanship, or materials used on the work or as to
          any other question, claim, rights, matter, or thing whatsoever in any
          way arising out of, or relating to, the contract, designs, drawings,
G         specifications, estimates, instructions, order, these conditions or
          otherwise concerning the works, or the execution or failure to execute
          the same, whether arising during the progress of the work, or after
          the completion or abandonment thereof, or the contract by the
          contractor shall be final, conclusive and binding on the contractor.

H
     STATE OF RAJASTl·IAN v. NAV BHARAT CONSTRUCTION CO. [VARIAVA. J.]    999
.'    Clause 36-The Sales Tax or any other tax on materials issued in the        A
      process offulfilling contract payable to the Government under rules
      in fo'tce will be paid by the contractor himself



      Clause 38-Fair Wages Clause:-{a) The contractor shall pay not less         B
      than fair wage to labourers engaged by him on the work.

      Explanation:- {'fair wages' means minimum wages for time on piece
      work fixed or revised by the State Govt. under the minimum Wages
      Act, 1948.}

      (b) The contractor shall not withstanding the prov1s1ons C
      of... .................contract to the contrary cause to be paid fair wages to
      labourers indirectly engaged on the work including any labour engaged
      by him, his sub-contractors in connection with the said work as if the
      labourers has been immediately or directly employed by him.

      (c) In respect of all labourers indirectly or directly employed on the     D
      work for the purpose of the contractor's part of this agreement, the
      contractor shall comply with or cause to be complied with the P.W.D.
      contractor's labour regulation made way of that be made by the
      Government from time to time in regard to payment of wages period,
      deductions, maintenance of wages register, wage card, publications         E
      and submission of wages periodical returns in all other matters of like
      nature.

      (d) The Executive Engineer-in-Charge shall have the right to deduct
      from the money due to the contractor may sum required to estimate
      to be required for making good the loss suffered by a worker by            F
      reasons of non-fulfillment of the conditions of the contract for the
      benefit of the worker or workers non-payment of wages or deductions
      made therefor which are not justified by the tenns of contract or as
      a result of non-observance of the aforesaid regulations.

     (e) Vis-a-vis the Government of Rajasthan the contractor shall be           G
     primarily liable for all payments to be made and for the observance
     of the regulations aforesaid without prejudice to his right to claim
     indemnity from his sub-contract.

     (t) The regulations aforesaid shall be deemed to be part of this contract
      and breach thereof shall be deemed to be breach of contract."              H
    1000                     SUPREME COURT REPORTS [2005] SUPP. 3 S.C.R.

A          Special Conditions of the contract inter-alia provide as follows:              ·'
           "31 LABOUR CONDITIONS:-
            (a) The contractor shall comply with the labour laws viz. Contractor
                Labour Regulation Act, Minimum Wages Act. Workman's
B               Compensation Act, Industrial Disputes Act, etc. as may be current
                and shall furnish the returns and information as any required and
                be specified from time to time. The contractor will have to carry
                out registration with the office or Regional Labour Commissioner,
                and obtain a valid licence for employing labour.

c           (b) The contractor shall as far as possible, obtain his requirements of
                labour, skilled and unskilled from the local area. No person below
                the age of 12 years shall be employed as labour.
            (c) The contractor shall pay fair and reasonable wages (whether or
                not such wages are controlled by any Laws existing at the time)
                to the workmen employed by him for the work. In the event of
D
                any disputes arising between the contractor and his workmen on
                the grounds that the wages paid are not fair and reasonable the
                dispute shall in the absence of legal or other relief to the workmen,
                be referred to the Engineer who shall decide the same the decision
                of the Engineer shall be conclusive and binding on the contractor
E               but such decision or any decision in this behalf that the
                contractor's workmen may obtain by resource to law or other
                legal means available to them, shall not, in any way, affect the
                condition in the contract regarding payment to be made by Govt.
                to the contractor only at the rate accounted in this contrtact.
F           (d) The contractor shall not employ animals suffering from source,
                lameness, or emaciation or which are immature nor shall treat
                them in a way that may be considered in human.
            (e) The Engineer shall have the authority to remove from the work
                any animal or workmen that, in his opinion which shall be
G               conclusive, he may consider unfit or undesirable and no
                responsibility shall be accepted by the Government for any delay
                or extra expenses caused towards the completion of the work
                such removal.
            (t)   While employing skilled or un-skilled labourers piece workers
H                 the contractor sh al I be first preference to the person certified to
                                                                                          \.
         STATE OF RAJASTHAN r. NA V BHARAT CONSTRUCTION CO. [VARIA VA, J ] J00]

.   "          him by the Engineer, or his duly authorized representative as A
               persons who are adversely affected by the Bhimsagar submergence
               and are suitable for employment and shall be minimum fair wages
               not below the minimum which has been fixed to this
               implementation of this work sited by the Engineer, whose decision
               shall be final, binding on the piece worker/contractor.
                                                                                    B
         (g) The contractor shall employ any famine, convict or other labour
              of a particular class or kind if ordered in writing to do so by the
              Engineer.
         (h) Should Government declare a state of famine to exist in any
             village within I 0 miles of the work, the contractor shall employee    c
             upon such parts of the works are suitable for unskilled labour,
             any persons certified to him by the Engineers or by a duly
             authorized agent of the Engineers, in writing to be in need or
             relief and the contractor shall pay to such persons wages not
             below the minimum which the Government may have fixed in
             this behalf. Any disputes which may arise in the implementation D
             of this provision shall be decided by the Engineer whose decision
             shall be final and binding on the contractor.
         (i)   The contractor shall provide reasonable facilities to the satisfaction
               of the Engineer, for the labour employed by him, where no such
               natural facilities exists. The usual facilities are weather proof E
               shelter for rest and supply or whole some drinking water, facilities
               for obtaining food reasonable washing and sanitary facilities
               special facilities for women workers, suitable residential
               accommodation, recreation and cultural activities, general sanction
               and health measures etc.
                                                                                    F
         U) The implementation of any provision of this clause shall, in no
             way, entitle the contractor to claim compensation or rates higher
             than tendered in his contract.

         "'""'"'''''''''''"'"'n"""'"''''''''''''"'''''''''''''''''

                                                                                    G
          (57) The quantities given in Schedule 'G' are approximate and
          payments will be made on measurement of actual quantities of different
          items of work executed by the contractor.

             The rates quoted shall be for the committed item in the schedule.
          The contractor is advised to see the site fully and investigate in detail H
    .t
    1002                  SUPREME COURT REPORTS [2005] SUPP. 3 S.C.R.

A          as to the source of materials availability of labour means of approach
           and carrying quarries to be put stocking of materials putting tools and
           plants in use and other site conditions such of flood levels etc. He is
           expected to have investigated as site the execution of work and quote
           his tender accordingly. No claim on 11is account shall be accepted. ft
           shall be assumed that his rates quoted in 'G' Schedule cover all
B          possible eventualities that may be not within the course of execution
           of this work.



           60. Owning to difficulty in obtaining certain materials in the open
c          market the Government has undertaken to supply materials specified
           in the schedules of the tender form. There may be delay in obtaining
           materials by the Department and the contractor is therefore required
           to keep in touch with the day to day position of supply of material
           from the Engineer-in-Charge need to so adjust the progress of the
           work that their labour may not remain idle not there may be no other
D
           claim due to or arising from delay in obtaining materials. It should
           be clearly understood that no monetary claim whatsoever shall be
           entertained by the Government on account of delay in supplying way.

           61. Under no circumstances shall any claim for compensation from
           the Government on any account be considered unless the contractor
E
           shall have informed the reasons for the claim in writing to the
           Engineer-in-Charge within 7 days of occurrence of cause of such
           claim. Similarly any hindrances to the work which may cause extension
           of period of completion of work shall be immediately informed in
           writing to the Engineer for his consideration."
F
           Schedule 'G' to the contract lists the estimated quantities of items of
           work and the rates payable for such work. At the end of this Schedule
           a lead statement and some notes appear, the relevant portion of which
           reads as follows:

G                                "LEAD STATEMENT

           s.    Items                Source            Lead in      Total
           No                                            Kms.         Km.
           I.    Stone Ballast        Local             I km         I km.
           2.    Sand                 Piplia river      46 km.       46 km.
H
                                                                                     \
       STATE OF RAJASTHAN 1·. NAY BHARAT CONSTRUCTION CO. [VARIAVA, J.] 1003

        (1) Any extra items if involved will be paid on the basis of the B.S.R. A
        1975 of Ajmer Irrigation on which 'G' Schedule is prepared plus the
        tendered premium of the Contractor.

        (2) If any construction material is not available at the sources indicated
        in the Lead Statement and has to be obtained from other sources
        intimated in writing by the Executive Engineer and if such other             B
        sources are nearer or further than the original source indicated recovery
        or extra payment will accordingly be made for the leaser or greater
        distance involved as per B.S.R. on which 'G' Schedule is based plus
        the premium tendered by the contractor."(emphasis supplied)

Thus the Respondents had fully acquainted themselves with the local conditions C
and had agreed to execute the work as per specifications and at the rates
specified in Schedule 'G'. It is only in respect of additional work that the
Respondents were entitled to be paid at rates set out in B.S.R. 1975. Clause
12 provides that the Respondents had to make their own arrangements for
petrol, diesel and lubricants. Clause 31 of the special conditions provides that D
the Respondent shall pay fair wages and comply with labour laws. The contract
provides that the fact that the contractor had to pay fair/minimum wages and
comply with labour laws would not entitle the contractor to claim compensation
or rates higher than those tendered in the contract. Clause 57 of the special
conditions provides that the rates quoted in Schedule G cover all possible
eventualities and that no claim can be made in respect of items like source E
of material, availability of labour, means of approach etc.

At this stage it becomes necessary to set out a summary of the claims made
by the respondent. They are as under:

 s.                                                              Amount              F
 No Claim No.               Claim                                  (Rs.)
      Claim No. I       Amount of Final Bill                         2,00,000.00

 2 Claim No. 2          (I) For Chisel Dressed Face Stone            2,78,737.92

                        (2) Cost of C.R. Stone
                                                                                     G

 3 Claim No. 3          Cost of R. R. Stone                          2,71,282.00

 4 Claim No. 4          Rehandling of Sand                           I, 18,559.82

 5 Claim No. 5          Rehandling of Stone                            15,743.59 H
    1004                 SUPREME COURT REPORTS [2005] SUPP. 3 S.C.R.
                                                                                    .; ,
A    6 Claim No. 6       Extra lead of stone                         15,743.59

     7 Claim No. 7       Extra lead of Rubble Stone                   I l,123.19

     8 Claim No. 8       Preparation of Foundation for slides      1,49,955.00

     9 Claim No. 9       Final excavation of sides                   18,556.57
B
     10 Claim No. IO     Carriage of porus pipes                       2,662.90

     11 Claim No. 11     Finishing of the concrete                     5,861.16

     12 Claim No. 12     R.C.C. in inspection gallery and sluice     32,000.00
c    13 Claim No. 13     Rock cutting by line drilling chiseling     25,947.31

     14 Claim No. 14     Mechanical mixing of cement mortar        1,82,990.72

     15 Claim No. 15     Cleaning of surface by air & water daily 66,079.74

D    16 Claim . No. 16   Shuttering of stair case in Galleries         2,231.60

     17 Claim No. 17     Cement concrete in saturated condition      29,223.81

     18 Claim No. 18     Shuttering at the junction of the
                         Dam heel and the Down stream
E                        protection                                    5,126.49

     19 Claim No. 19     Mechanical mixing of cement concrete          2,463.26

     20 Claim No. 20     Carriage of Air vent pipe                     2,497.50

     21 Claim No. 21     Crusher broken aggregate                    33,669.00
F
     22 Claim No. 22     Cleaning the foundation surface
                         handed over by the department               28,092.00

     23 Claim No. 23     Increased in rates of royalty                17,216.87

     24 Claim No. 24     Increased in rates of Diesel               1,22,604.36
G
     25 Claim No. 25     Increased in minimum labour wages         5,27,638.60

     26 Claim No. 26     Increased in minimum labour wages
                         and increase in price in the rates        I0,52, 797 .30
                                                                                    ~
H    27 Claim No. 27     Loss of profit                             3,07,038,00
      STATE OF RAJASTHAN 1·. NAY BHARAT CONSTRUCTION CO. [VARIAVA, J.] 1005


 28 Claim No. 28        Due to unlawful withdraw! of the                           A
                        running work                               1,58,904.85

 29 Claim No. 29        Over establishment and
                        overheads beyond 16.5.81
                        (stipulated date of completion)            4,33,347.00
                                                                                   B
 30 Claim No. 30        Difference of interest of F.D.R.             56,800.00

 31 Claim No. 31        Wrong recovery from bills for sand
                        department & extra carriage
                        (6364.71 + 23206.90                          29,571.61

 32 Claim No. 32        Recovery of labour                            2,730.30
                                                                                   c
 33 Claim No. 33        Recovery of Storage charges                  22,549.30

 34 Claim No. 34        Material remain unused                        5,856.00

 35 Claim No. 35        Electric charges                             10,205.20     D
 36 Claim No. 36        Excess charges of hire charges of machine

 37 Claim No. 37        Recoveries to be final

 38 Claim No. 38        For screening of sand                         4, 165.00
                                                                                   E
 39 Claim No. 39        Royalty charges on departmental
                        material                                      6,243.30

       Mr. Mohta relied upon the case of Bharat Coking Coal Ltd. v. L. K.
Ahuja & Co., reported in (2001] 4 sec 86, wherein it has been held that if         F
an Arbitrator has not applied his mind to important terms of the contract
between the parties and has not applied such terms in making his award,
then, even though the award is a non-speaking award. This error is apparent
on the face of the award, the entire lump sum award is required to be set
aside. He also relied upon the case of Continental Constructions Co. Ltd. v.
State ofM. P., reported in (1988] 3 sec 82. In this case also it has been held     G
that if an Arbitrator. awards extra costs on account of changes in circumstances
such as price rise, in spite of a provision in the Contract to the contrary, it
would amount to the Arbitrator mis-conducting himself and that such an
award would be required to set aside.

                                                                                   H
    1006                   SUPREME COURT REPORTS (2005] SUPP. 3 S.C.R.

A          Mr. Mohta took us through a number of claims and pointed out that
    under most of the claims additional/higher amounts were being claimed in
    respect of works covered by the Contract. He submitted that there were a
    number of claims where, for doing the contracted work during the extended
    period, higher rates were claimed and the Umpire has awarded those claims
B   not on the basis of contracted price but on basis of rates given to the new
    contractor who was appointed to complete the work left unfinished by the
    Respondent. Mr. Mohta submitted that the letters extending time categorically
    provided that the work would be done at the contracted rate. He submitted
    that this had been accepted by the Respondent. As we propose to remit the
    matter back to an Umpire we do not deal with each instance pointed out by
C   Mr. Mohta. Only by way of example we refer to two claims.

         As set out hereinabove claim no. 2 is in a sum of Rs.2,78,737.92 and
  it is for chisel dressed face stones. Under this claim, the Respondents have
  claimed extra amounts for chiseling the stones on all four sides when, under
  the Contract, they are supposed to do this work at the rates specified for such
D work in Schedule G. Mr. Mohta pointed out Clause 5.1 l(iii) of the Technical
  Specifications the relevant portion of which reads as follows:

            "xxx                   xxx                    xxx

            Dressing:- The face stone shall be squared on all joints and beds. The
E           beds shall be hammer dressed true and square for at least 7.5 ems.
            Back, from the face and the side joints for atleast 7.5 ems. The faces
            of the stones shall be single line chisel dressed and bushing shall not
            project by more than 3.75 ems. No pinnings will be allowed on the
            face. All side joints shall be vertical and beds horizontal and no joint
            shall be more than 12 mm. in thickness. Stones shall break joints in
F           courses above and below by at least half the height of the courses.
            The joint in face work shall not be thicker than 12 mm. for single line
            chisel dressed stones.                                                          -
            "xxx                   xxx                    xxx''

G He submitted that this was the work which was required to be done under the
  Contract at the rate specified in Schedule G and yet the claim had been made
  at higher rates. He submitted that the Umpire had not rejected the claim. He
  submitted that even though the award was a lump sum award it was also in
  respect of claim No. 2. Mr. Mohta also referred to claim No. 26 which was
H for Rs. 10,52, 797.30 for increase in minimum labour/wages and increase in           -{
                                                                                            ,-'

                                                                                       I
      STATE OF RAJASTHAN i·. NAV BHARAT CONSTRUCTION CO. [VARIAVA, J.) 1007

prices. He pointed out that this claim was contrary to Clause 38 of the           A
Contract and Clause 31 of the Special Conditions of the Contract which
specifically provided that the contractor would not be entitled to claim
compensation or higher rates because he had to implement labour laws or
pay fair wages.

      In the same manner, Mr. Mohta took us through a large number of             B
other claims to show that they were contrary to the terms of the Contract. As
stated above it is not necessary, for the purposes of this Judgment, to set out
in detail the submission of Mr. Mohta in respect of other claims referred to
by him.

       On the other hand, Mr. Luhadia submitted that this was a non-speaking C
lump sum award and therefore the grounds on which this Court can interfere
with such an award are very limited. In support of his submission he relied
upon a number of authorities including the cases of Hindustan Steel Works
Construction Ltd. v. C. Rajasekhar Rao, reported in [1987] 4 SCC 93. In this
case it has been held that it is only in a speaking award that the Court can D
look into the reasoning of the award. It is held that it is not open to the Court
to probe the mental process of the arbitrator and speculate, where no reasons
are given, as to what impelled the arbitrator to arrive as to his conclusions.
He also relied on the cases of S. Harcharan Singh v. Union of India, _reported
in AIR (1991) SC 945; Hindustan Constructions Co. Ltd. v. State ofJ. & K.,
reported in AIR (1992) SC 2192 and Continental Construction Ltd. v. State E
of U. P., reported in (2003] 8 SCC 4. In these cases the question was regarding
interpretation of the terms of the contract. It was held that the Court cannot
substitute its own interpretation to that of the arbitrator so long as the
interpretation of the arbitrator is a possible one. Reliance was also placed
upon the case of M/s. Sudarsan Trading Co. v. State of Kera/a, reported in F
AIR (1989) SC 890. In this case also it has been held that it is for the
arbitrator to interpret terms of the contract and that if the view taken by the
arbitrator is a possible view then the court would not interfere. In the case of
P. M. Paul v. Union of India, reported in AIR (1989) SC 1034 the questions
referred to the arbitrator were (a) who was responsible for the delay; (b) what
are the repercussions of the delay and (c) how to apportion •he consequences. G
The arbitrator gave a reasoned award holding the Union of India responsible
for the delay and awarded escalation in costs to the contractor. It must
immediately be mentioned that there was no provision in the contract which
permitted or barred grant of escalation. This Court held that the arbitrator had
not exceeded his jurisdiction nor misconducted himself. In the case of Build H
    1008                    SUPREME COURT REPORTS [2005) SUPP. 3 S.C.R.

A India Construction System v. Union of India, reported in [2002] 5 SCC 433
    after the contract was entered into it was amended to provide that in cases
    where the claim is more than 1 lakh a reasoned award should be given. The
    arbitrator gave an unreasoned award. The challenge to it on the ground that
    the award was unreasoned was not accepted as this point was taken for the
B   first time in the high court and also on the ground that a contract cannot be
    unilaterally altered.

        There can be no dispute to the well established principle set out in these
  cases. However these cases do not detract from the law laid C:Jwn in Bharat
  Coking Coal Ltd's case or Continental Construction Co. Ltd's case (supra).
C An arbitrator cannot go beyond the terms of the contract between the parties.
  In the guise of doing justice he cannot award contrary to the terms of the
  contract. If he does so he will have misconducted himself. Of course if an
  interpretation of a term of the contract is involved than the interpretation of
  the arbitrator must be accepted unless it is one which could not be reasonably
  possible. However where the term of the contract is clear and unambiguous
D the arbitrator cannot ignore it.
                                                                                      ;
           Mr. Luhadia submitted that the respondents had made claims totaling
    Rs. 4556155.56p. He submitted that claims for damages were to the tune of
    Rs. 27.50 lacs. He submitted that the -tlaim for final bill was for Rs. 2 lacs.
    He submitted that the claims for extra items were for Rs. 1598495. He
E   submitted that the Umpire had only awarded Rs. 2996060. He submitted that
    as the award is a non speaking award, even presuming without admitting that
    some claims were covered by the terms of the contract, it still could not be
    said that the Umpire has awarded towards claims covered by the contract. He
    submitted that thus the award could not be set aside. In support of this
F   submission he relied upon the case of Paradip Port Trust and Ors. v. Unique
    Builders, reported in AIR (200 I) SC 846. In this case the claim had been for
    Rs. 1293260. The arbitrator awarded as follows:

            "Mis Unique Builders Ltd. the claimant is entitled to receive from
            Paradeep Port Trust a sum of Rs. 851315 with interest .............. "
G
  It was contended in that case that claims 2 and 7 (therein) could not have
  been awarded. This Court held that as the award was a lump sum award and
  as only Rs. 851315 had been awarded against a claim of Rs. 1293260 it was
  not possible to say whether any amounts had been awarded against claims 2
  and/or 7, relying on this Mr. Lohadia submitted that even in this case it
H cannot be said whether any amounts have been awarded against claims alleged


                                                                                      I
      STATE OF RAJASTHAN 1·. NAV BHARAT CONSTRUCTION CO. [VARIAVA, J.] J 009

to be covered by the contract. We are unable to accept this submission. In A
this case the award itself states that the award of Rs. 29,96,060 is against
claims 1 to 39, except claim no. 30. Therefore this award is in respect of
claims covered by the contract and to that extent the Umpire has misconducted
himself. Even otherwise the claim for damages is not in a sum of Rs. 27.50
lacs as claimed. Claims 27 and 28 which deal with damages are for Rs.
3,07,038 and Rs. 1,58,904.85. The other claims, included in the figure of Rs. B
27.50 given to this Court appear to be claims at enhanced rates for the
contracted work done during the extended period. Mr. Lohadia denied that
Respondents had agreed to do work during the extended period at the
contracted rate. Thus at this stage, unlike in Paradip Port Trust's case (supra),
it does appear on the face of the record that higher rates for items covered C
by the contract have been awarded.

       As regards claim No. 2 Mr. Luhadia fairly admitted that Clause 5. I l(iii)
of the Contract requires chiseling of stones on all sides. He however submitted
that the rates given in Schedule G were only for chiseling of stones on one
side. He submitted that this was clear from Note 1 under Schedule G which D
stated that Schedule G was based on B.S.R. 1975. He submitted that B.S.R.
 1975 showed that such rates were only for chiseling stones on one side. He
submitted that when the stone has to be chiseled on all sides the rates given
in B·.S.R. 1975 were to be applied. He submitted that claim No. 2 was based
on those rates. We are unable to accept this submission of Mr. Luhadia. The E
Contract is very specific. The work specified in the Contract has to be done
at the rates specified in Schedule 'G'. Even though Schedule G may be based
on B.S.R. 1975 it is not exactly as B.S.R. 1975. Where in respect of a work
specified in the contract the rate has been given in Schedule G that work
could only be done at that rate. Works specified in the Contract does not
become extra work. It is only in respect of extra work that rates specified in F
B.S.R. 1975 can be applied. To us it is clear that the claim No. 2 is contrary
to the terms of the Contract. It is barred by Clauses 57, 60 and 61 of the
Contract. As regards claim No. 26, Mr. Luhadia relied upon the case of
Tarapore & Co. v. State of M.P., reported in [1994] 3 SCC 521. In this case,
the question was whether the contractor was entitled to claim extra amounts G
because he had to pay increased wages to his workers. This Court has held
that the contractor would have tendered on the basis of the then prevailing
wages and as the contract required the contractor to pay the minimum wages
if the minimum wages increased it was an implied term of the contract that
he would not be entitled to claim the additional amount. However, it must be
noted that, in this case, there was no term in the contract which prohibited H
    1010                   SUPREME COURT REPORTS [2005) SUPP. 3 S.C.R.

A any extra claims being made because of the increase in wages. Clause 31 of
    the Special Conditions of the Contract, which has been reproduced
    hereinabove, specifically bars the contractor from claiming any compensation
    or an increase in rate under such circumstances. Not only that but the
    Respondents had with their initial tender put in a term which provided that
B   ifthere was any increase in the minimum wages by the Government the rates
    quoted by him would be increased by the same percentage. At the time of
    negotiation this clause was dropped. Thus, the Respondents had themselves
    specifically agreed not to claim any compensation or increase by reason of
    increase in wages. This claim could therefore not have been granted.

C       It prima-facie appears that the majority of the claims are against the
  terms of the Contract. However, there are also other claims which are not
  against the terms of the Contract. To merely set aside the Award on ground
  of misconduct would work hardship on the Respondent as they would then
  be deprived of claims which may be maintainable. In our view the correct
  course would be to set aside the award and refer the matter back to an
D independent Umpire appointed by this Court. The Umpire will fix his own
  terms and conditions. We however clarify that only those claims covered by
  the two applications will be considered. Of course the Umpire will decide
  how many of the 39 claims formed part of the claims made in the two
  applications. Needless to state that the terms of the contract will be kept in
E mind and claims contrary to terms of the contract will undoubtedly not be
  allowed. The Umpire will also decide whether the Respondent had agreed to
  do the contracted work done during the extended period at the same rates
  and/or whether the Respondent is entitled to increased rates and if so at what
  rate. The Umpire shall decide only on the basis of the materials already
  placed before the earlier Arbitrators and the earlier Umpire.
F
          Under the circumstances and for reasons set out hereinabove, we set
    aside the Award and appoint Justice N. Santosh Hegde, a retired Judge of this
    Court, as the Umpire. The Umpire, Mr. V. K. Gupta, shall forthwith forward
    all papers and documents to Justice N. Santosh Hegde at his residence, i.e.,
    9, Krishna Menon Marg, New Delhi. The parties shall appear before Justice
G   N. Santosh Hegde on 6.10.2005 at 5.00 P.M. at 9, Krishna Menon Marg,
    New Delhi. Justice N. Santosh Hegde shall fix his fees which shall be borne
    by both the parties equally. Justice N. Santosh Hegde is requested to fix the
    schedule and give his award within a period of 4 months from the date of
    receipt of all the papers and documents from the outgoing Umpire Mr. V. K.
H   Gupta. The award to be filed in this Court. We leave the questi<>r t>fgrant



                                                                                    (
      STATE OF RAJASTHAN v. NAV BHARAT CONSTRUCTION CO. [VARIAVA.J.] 101 J

of interest open to be decided by the Umpire in accordance with law.                A
      Lastly, it is clarified that this is not a new reference but a continuation
of the earlier proceedings and thus the Arbitration Act 1940 shall continue
to apply.

      The Appeals stand disposed off accordingly. There will be no order as B
to costs.

K.K.T.                                                    Appeals disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.