Created byFuzzy Cloud

Supreme Court of India

STEEL AUTHORITY OF INDIA LTD.versusJ.C. BUDHARAJA, GOVERNMENT AND MINING CONTRACTOR

Citation
1999 INSC 375
Decided
1 September 1999
Disposal
Appeal(s) allowed

Holding

An arbitrator must act within the contractual limits and cannot award relief prohibited by the contract, and a claim barred by the Limitation Act is outside his jurisdiction, making the award illegal and subject to setting aside.

Summary

The Steel Authority of India Ltd. (appellant) challenged an arbitral award that granted damages for delay in handing over a work site, which the contract expressly prohibited. The appellant also argued that the claim was barred by the three‑year limitation period under the Limitation Act, 1963. The Supreme Court held that an arbitrator derives his authority from the contract and cannot award relief that the contract excludes; such a grant is a jurisdictional error rendering the award illegal. It further held that the cause of action arose on the date of the contractor’s notice in August 1979, making the claim time‑barred, and that the award was a speaking award, allowing the court to examine its reasoning. Consequently, the award and the lower courts’ orders were set aside. The appeal was allowed with costs.

Issues considered

  • Whether the arbitrator exceeded his jurisdiction by awarding damages prohibited by the contract clauses.
  • Whether the claim for damages was barred by the limitation period under the Limitation Act, 1963.
  • Whether the award is a speaking award that can be scrutinised by the court.
  • Whether interest awarded by the arbitrator was justified.

Legislation cited

Subjects

ArbitrationJurisdictionLimitation periodSpeaking awardContractual prohibitionArbitrator misconductInterest award

Judgment

              STEEL AUTHORITY OF INDIA LTD.                                       A
                           v.
   J.C. BUDHARAJA, GOVERNMENT AND MINING CONTRACTOR

                           SEPTEMBER 1, 1999

                 [D.P. WADHWA AND M.B. SHAH, JJ.]                                 B

      Arbitration Act, 1940: Section 30.

       Misconduct-Jurisdictional error-Contract stipulated that no claim
 would be tenable for delay in handing over the work site-Contract only           C
provided extension of time for completion in case of such delay-Despite
such prohibition, award given for losses due to delay in handing over work
 site-Held: Arbitrator has to function within the limits of the agreement and
cannot exceed his jurisdiction-Whether or not the arbitrator has so functioned
 would be a jurisdictional fact and required to be gone into by the court-        D
Arbitrator may have jurisdiction to entertain a claim but does not have
jurisdiction to pass award in respect 'of prohibited items of contract-I/ he
does so it will be a jurisdictional error-Hence, the said award is, on the face
of it, illegal.
        Arbitration-Disputes-Reference to-Period of limitation-Cause of
 action-Arising of-Contractor gave notice on 29-8-1979 demanding a E
 certain sum-No response and no payment from company-Contractor's right
 to receive damages not kept alive in subsequent supplementary agreement-
 Instead contractor agreed to complete work within the stipulated time on a
 higher rate-Company wrote letter in [on 3.9.1983} repudiating the claim
 made by the contractor-No action to refer the dispute for arbitration taken p
 by contractor within 3 years from 29-8-1979-When dispute with regard to
 second agreement [dated 20.12.1980} arose in 1985 contractor gave notice
for appointment of arbitrator and the matter was referred to arbitration-In
 that reference contractor raised the dispute pertaining to the first agreement-
 Arbitrator appointed in December I 985 with reservation that the claim was
 barred by the period of limitation-Held: Cause of action arose on G
 29-8-1979, the date of notice of demand-Hence, Claim before the arbitrator
 in December 1985 barred by period of limitation-:-Letter written in 1983
 would not give fresh cause of action because on that date cause of action
for recovering the amount was barred by the period of three years prescribed
under Art. 137 of the Limitation Act-Under S. 3 of the Limitation Act it was H
                                     155
                                        Cl




           156                     SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.

      A the duty of the arbitrator to reject the claim as it was, on the face of it, barred
           by limitation-Limitation Act, 1963, Art. 13 7 and S. 3.

               Arbitration-4ward-Speaking or non-speaking-Contractor claimed
          damages for delay in handing over the work site-Arbitrator awarded damages
          and also gave reasons for it-Held: The reasons clearly reveal that the
      B   award is a speaking award-Hence, court can go behind it.

                The predecessor of the appellant executed a contract with the
          predecessor of the respondent for certain construction within a wild life
          sanctuary. The agreement stipulated that no claim for delay in giving the
      C   entire site or giving it gradually would be tenable and in such cases the
          appellant was only obliged to extend the time for completion of the work.

                The respondent raised a dispute on 29-8-1979 for losses incurred due
          to delay in handing over the work site but there was no response from the
          appellant and no payment was made. Thereafter a supplementary agreement
     D    was executed between the appellant and the respondent in which it was
'\
          nowhere stated that the respondent's .alleged right of getting payment for
          damages or losses suffered was kept alive. On the contrary, the respondent
          had agreed to complete the work within the time stipulated in the second
          agreement by charging some higher rate. The respondent had not sought
     E    any reference of the aforesaid dispute within three years from the date when
          cause of action arose i.e., 29-8-1979. However, the appellant wrote a letter
          in 1983 repudiating the respondent's claim on account of damages or losses
          suffered by him.

                 When a dispute arose with regard to the second agreement the
     F respondent gave a notice on 2-12-1985 to appoint an arbitrator and the
          matter was referred to arbitration. In that reference, the respondent raised
          certain claims relating to the work done under the first agreement. The
          appellant appointed an arbitrator with a specific reservation regarding the
          tenability, maintainability and validity of reference as also on the ground that
     G    the claim was barred by the period of limitation and it pertained to excepted
          matters in the terms of the general conditions of the contract.

             The arbitrator awarded damages for losses incurred by the respondent
       "for the reasons" of delay in handing over the work site to the respondent
       under the first agreement. The award was made rule of the Court and the
     H appeal filed against it was dismissed by the High Court. Hence this appeal.
               STEEL AUTHORITY OF INDIA LTD. v. J.C. BUDHARAJA. GOVT. AND MINING CONTRACTOR   157
            On behalf of the appellant it was contended that the award passed by                    A
..,.   the arbitrator was without jurisdiction and that the claim made by the
       respondent was barred by the period of limitation.

            On behalf of the respondent it was contended that the award was non-
       speaking and, therefore, the courts below rightly refused to interfere with
       ~                                                                                            B
             Allowing the appeal, the Court

             HELD: 1.1. It is settled law that arbitrator derives his authority from
       the contract and if he acts in manifest disregard of the contract, the award
       given by him would be an arbitrary one. Further, the Arbitration Act, 1940                   C
       does not give any pol,Ver to the arbitrator to act arbitrarily or capriciously.
       His existence depends upon the agreement and his function is to act within
       the limits of the said agreement. [165-G-H; 166-B-C]

              1.2. To find out whether the arbitrator has travelled beyond his
       jurisdiction and acted beyond the terms of the agreement between the parties,                D
       the agreement is required to be looked into. It is true that interpretations
       of a particular condition in the agreement would be within the jurisdiction
       of the arbitrator. However, in cases where there is no question of interpretation
       of any term of the contract, but of solely reading the same as it is and still
       the arbitrator ignores it and awards the amount despite the prohibition in                   E
       the agreement, the award would be arbitrary, capricious and without
       jurisdiction. Whether the arbitrator has acted beyond the terms of the
       contract or has travelled beyond his jurisdiction would depend upon facts,
       which however would be jurisdictional facts, and are required to be gone into
       by the court. Arbitrator may have jurisdiction to entertain the claim and yet
       he may not have jurisdiction to pass award for particular items in view of                   F
       the prohibition contained in the contract and, in such cases, it would be a
       jurisdictional error. For this limited purpose reference to the terms of the
       contract is a must. [166-F-H; 167-A)

            Continental Construction Co. Ltd. v. State of MP., [1988) 3 SCC 82;
       New Indi~ Civil Erectors (P) Ltd. v. Oil and Natural Gas. Corporation, G
       (1997) 11 SCC 75; H.P. State Electricity Board v. R.J. Shah and Company,
       [1994) 4 SCC 214 and Associated Engineering Co. v. Government of A.P.,
       [1991) 4 sec 93, relied on.

             1.3. In the instant case, the award passed by the arbitrator is against
       the conditions agreed by the contacting parties and is in conscious disregard                H
     158                      SUPREME COURT REPORTS (1999] SUPP. 2 S.C.R.

 A of stipulations of the contract from which the arbitrator derives his authority.
     His appointment as a sole arbitrator itself was a conditional one. Despite this
     he has ignored the stipulations and conditions between the parties. Hence,
     the said award is, on the face of it, illegal. [168-G-H; 169-A-B)

           2. Right to refer the dispute to the arbitrator arose in 1979 when the
B   contractor gave a notice demanding t~e amount and there was no response
    from the appellant and the amount was not paid. The cause of action for
    recovery of the said amount arose from the date of the notice. The contractor
    cannot wait indefinitely and is required to take action within the period of
    limitation. Hence, the cl.aim before the arbitrator in December 1985 was
C   barred by the period of limitation. Letter written in 1983 by the appellant
    repudiating the respondent's claim on account of damages or losses sustained
    by him would not give a fresh cause of action. On that date cause of action
    for recovering the said amount was barred by the period of three years
    prescribed under Article 137 of the Limitation Act, 1963. Under Section 3
    of the Limitation Act, it was the duty of the arbitrator to reject the claim as
D   it was, on the face of it, barred by the period of limitation.
                                                              (171-G-H; 173-C-D]

         State ofOrissa v. Damodar Das, (1996) 2 SCC 216 and Panchu Gopal
    Bose v. Board of Trustees for the Port of Calcutta, (1993) 4 SCC 338, relied
    on.
E
        Major (Retd) Inder Singh Rekhi v. Delhi Development Authority, [1988)
    2 sec 338, referred to.

         3. The reasons, which are specifically mentioned in the award for
    granting damages, clearly reveal that the arbitrator has passed a speaking
F   award. Hence the Court could go behind it.

            CIVIL APPELLATE JURISDICTION: Civil Appeal No. 507 of
    1992.

            From the Judgment and Order dated 11.9.91 of the Patna High Court in
G M.A. NQ. 621 of 1990.
            Dhruv Mehta and M.P. Vinod for the Appellant.                              I
           G.L. Sanghi and Raj Kumar Mahta for the Respondent.

H          The Judgment of the Court was delivered by
  STEEL AUTHORITY OF INDIA LTD. v. JC. BUDHARAJA, GOVT. AND MINING CONTRACTOR [SHAH, J.]   159
      SHAH, J. This appeal is filed against the judgment and order dated                         A
11th September, 1991 passed by the Patna High Court, Ranchi Bench in
Miscellaneous Appeal No.621of1990 under Section 39(1)(vi) of the Arbitration
Act, 1940 (hereinafter referred to as "the Act"). The High Court dismissed the
appeal filed by the appellant and confirmed the order dated 2nd April, I 990
passed by the Subordinate Judge, 1st Court, Chas in Arbitration Suit No. 28                      B
of 1988 by which award is made rule of Court with 8 per cent per annum
interest from the date of the decree.

      It is undisputed that the National Mineral Development Corporation,
predecessor of the Steel Authority of India Limited on l .8.1977 executed a
contract with the respondent for construction of tailing-cum-storage reservoir                   C
at Kundi for Megha Taburu Iron Ore Project. As per the terms of the contract,
the work was to be completed within a period of two years. During this period,
Public Sector Iron and Steel Companies (Re-structuring and Miscellaneous
Provisions) Act, 1978 was passed and Steel Authority of India Limited became
the employer in place of National Mineral Development Corporation. Further,
the contractor, N.C. Budharaja also died and was succeeded by the present                        D
respondent.

       After two years of contract period, on 29th August, 1979, respondent
raised the claim of about 18 lakhs as damages for delay in handing over work
sites and allied reasons. On 20th December, 1980, a supplementary agreement
was executed between the appellant and the respondent for the same work                          E
at an increased rate. The relevant part of the said agreement is as under:

        "The Supplementary agreement made this twentieth day of December,
        1980 between Steel Authority of India Limited having its registered
        office at Hindustan Times House, 18/20, Kasturba Gandhi Marg, New                        F
        Delhi - l l 0 00 l and having one of its units at Bokaro Steel Plant at
        Bokaro Steel City (hereinafter referred to as the (Employer) which
        expression shall include its successors and assigns) of the one part
        and Mis N.C. Budharaja Govt. and Mining Contractor, at Jharpada,
        P.O. Budheswari Colony, Bhubaneswar (hereinafter referred to as the
        "Contractor") which expression shall include its successors and assigns                  G.
        of the other part.

            WHEREAS the contractor entered into an agreement dt. lst August
        1977 with Mis National Mineral Development Corporation Limited in
        regard to the work of "Constructions of Tailing-cum-Storage Reservoir"
        at Meghahatuburu Iron Ore Project relating to their Meghahatuburu                        H
      160                     SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.
                                                                    .      '

A            Iron Ore Project.

                 AND-,WHEREAS the-said--unit of the National Mineral
             Development Corporation Limited after the coming into force of the
             Public Sector Iron and Steel Companies (Restructuring and
             Miscellaneous Provisions) Act, 1978 was transferred to Steel Authority
B            of India Limited and declared as a captive unit for the Bokaro Steel
             Plant of Steel Authority of India Limited.

                 AND WHEREAS pursuant to the provisions of Section 23 of the
             Restructuring Act aforesaid, the agreement entered into by and between
             Mis National Mineral Development Corporation Ltd. in respect of
c            Meghahatuburu unit of Mis National Mineral Development Authority
             Ltd. became fully enforceable and effective against or in favour of
             Steel Authority of India Limited.

                 AND WHEREAS the Contractor is yet to execute a considerable
             portion of the work more particularly described in the schedule to this
D            agreement.

                AND WHEREAS the contractor has agreed to complete the said
            balance work as on 12.3.80 the estimated quantity of which is set out .·
            in document specified at 2(d) on the terms and conditions hereinafter
            enumerated."
E
            Further clauses 3 and 4 of the said agreement read as under:

             "3. In consideration of the payments to be made by the employer to
            the Contractor as hereinafter mentioned the contractor hereby
            covenants with the employer to construct, complete and maintain the
F
            works in conformity with the provisions of contract in all respect.

            4. The employer hereby covenants to pay to the contractor in
            consideration of the construction, completion ancl maintenance of the
            works the contract price at the time and in the manner prescribed by
G           the contract."

          Despite the aforesaid fact that the supplementary agreement was
    executed for the same work at an increased rate, it is stated that the appellant
    wrote letter dated 3.9.1983 repudiating claim of 18 lakhs on account of damages
    for any loss sustained by the contractor as claimed by him by his letter dated
H   29th August, l 979.

                                                                                       /
       STEEL AUTHORITY OF rNDIA LTD. 1·. J.C. l!UDHARAJA, GOVT. AND MINING CONTRACTOR (SHAH. J ]   161

              Thereafter, dispute arose in the year 1985 for the work with regard to                     A
    ·. second agreement dated 20th December, 1980 and the matter \:Vas referred to
       arbitration. In that Reference, respondent raised certain claims relating to the
       work done under the first agreement. On 2{ld December, 1985, the appellant
       raised an objection that the claim could not be decided by the Arbitrators as
       the s!)me was pertaining to previous agreement. Thereafter respondent gave                        B
       notice dated 2nd December, 1985 to the appellant to appoint sole arbitrator
       as provided for under the first agreement. On 10th December, 1985, the
       appellant appointed sole arbitrator "with reservation regarding the tenability,
       maintainability and validity of the Reference as also on further grounds that
       the claim was barred by the period of limitation and that it pertained to
       excepted matters of general conditions of the contract".                                          c
             On 11th July, 1986, the arbitrators gave an award pertaining to the
     dispute under the agreement dated 20.12.1980. Against the claim of Item No. l
     of Rs.17 lakhs and odd pertaining to first agreement, the arbitrators awarded
     'Nil'; this award has been made rule of the Court by the High Court of Delhi.
                                                                                                         D
             Meanwhile, the appellant challenged the jurisdiction of the sole arbitrator
      by filing Miscellaneous Case No. 22 of 1987. Finally, the High Court dismissed
      the Revision Application on 22nd August, 1988. Thereafter on 18th November,
      1988, the sole arbitr~tor made an award granting damages to the tune of
      Rs.11,26,296 as principal sum (unliquidated damages) and a further sum of
      Rs.12,06,000 as interest on the above principal amount from 29th August, 1979                      E
     till the date of the Reference, i.e., 15th December, 1985. The arbitrator also
     awarded future interest at the rate of 17 per cent from the date of the award
     to the date of payment or the date of decree whichever is earlier.           order    s/
     dated 2nd April, 1990, the learned Sub-Judge made the award rule of the court
     with a modification for the payment of interest from the date of the decree                         F
     at the rate of 8 per cent on the principal t:tmount or unpaid part till the date
     of actual payment. The appeal filed before the High Court against the said
     judgment and decree was also dismissed. Hence this appeal.

           At the time of hearing, the learned counsel for the appellant submitted
     that the award passed by the arbitrator is                                                          G
              (a)     without jurisdiction,

l             (b)    The claim made by the respondent was on the face of it barred
                     by the period of limitation, and

              (c)    Award of interest is wholly unjustified and illegal.                                H
     162                      SUPREME COURT REPORTS [1999) SUPP. 2 S.C.R.

A         The learned counsel for the respondent supported the order passed by
     the High Court. He submitted that:

            (I)    The award is non-speaking. Hence, courts below rightly refused
                  to interfere with.

            (2)   The question, whether claim made by the contractor was within
B                 period of limitation or not, was required to be decided by the
                  arbitrator, and

            (3)   There is no prohibition for awarding interest from the date of the
                  claim till the date of reference and thereafter.

C          For deciding the controversy, it would be necessary to refer to the
     material part of the award dated 18th November, 1988 which is as under:

                "The claimant has put forth a claim amounting to Rs.18,10,014.48
            plus interest on the same amount at 30 per cent per annum from
            29.8.79 till date of payment.
D
                The amount of interest at the above rate on the claim amount from
            29.8.79 till l 8.l l.88, i.e., date of"A WARD" worked out to Rs.33,39,351.00
            (Rupees Thirty three lakhs thirty nine thousand three hundred fifty
            one only).

E               Thus the total amount of claims including interest up to the ·date
            of "AWARD" works out to Rs.5 l ,49,365.48 (Rupees fifty one Iakhs
            forty nine thousand three hundred sixty five and paise forty eight
            only).

                On perusal of all documents filed by both parties and relied upon
F·          by the parties and keeping in view oral and written submissions and
            chain of arguments of both parties relating to factual and legal, I am
            convinced that the claimant sustained losses on account of the
            following reasons:-
            (a)   The work site is located in the wild-life sanctuary of Saranda
G                 Reserve forest. The project authorities issued work .order without
                  completing the departmental formalities in obtaining permission
                  of the Forest Department for executing the work inside wild-life
                  sanctuary.
            (b)   The project authorities could not obtain permission of Forest
H                 Department to take men and machinery to the work site as and
        STEEL AUTHORITY OF INDIA LTD. v. J.C. BUDHARAJA, GOVT. AND MINING CONTRACTOR [SHAH, J.)   163

                      when necessary for executing the work.                                            A
               (c)   The project authorities could not obtain permission of Forest
                     Department in time for making hutments at work site and could
                     not hand over the ~ite in time.
               (d)   The project authority could not remove forest growths from the
                     working area before issue of work order.                                           B
               (e)   The project authorities could not obtain permission of Forest
                     Department for transporting the required machinery and materials
                     for blasting operation and executing drilling and blasting work
                     inside the wild-life sanctuary till March 1979.
               (f)   Delay in payment of legitimate dues of the claimant for more
                                                                                                        c
                     than nine years.

              After recording the aforesaid reasons; the arbitrator held that in
      consideration of the documents, submissions and arguments of both the
      parties, contractor was entitled to be paid by the Steel Authority of India                       D
      Limited a sum ofRs.l l,26,296 as principal amount and a sum ofRs.12,06,000
      as interest from 29th August, 1979 till 15th August, 1985, in all Rs.23,32,296.
      The Arbitrator also awarded future interest at the rate of 17 per cent on the

...   principal sum of Rs.11,26,296 from the date of award till the date of payment
      or the date of decree whichever is earlier.
                                                                                                        E
            Learned counsel for the appellant submitted that the award is a speaking
      one and the Arbitrator has awarded the damages for the reasons that
      department failed to obtain various permissions from the forest depai:tJnent.
      The reasons which are specifically mentioned in the award for grantirig aamages
      clearly reveal that the arbitrator has passed a speaking award. He pointed out                    p
      the terms of the contract and submitted that it is apparent that arbitrator has
      awarded the amount for the items for which there is prohibition in the contract
      and thereby he has travelled beyond his jurisdiction. For this purpose, learned
      counsel for the appellant referred to conditions which are referred to by the
      learned Single Judge and the trial court. They are as under:
                                                                                                        G
              "Clause 25: No claim if work is abandoned or postponed-

                  The successful tenderer shall have no claim whatsoever against
              the Corporation if the work or any part thereof covered by these
              tender documents if postponed to any later date or abandoned in the
              overall interest of the Corporation or for any other reason. The                          H
     164                      SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R.

A            Corporation's decision in the matter shall be final and binding on the
             contractor.

             Clause 32: Site for execution of work:

                 Site for execution of work will be available as soon as the work
            is awarded. In case it is not possible for the Corporation to make the
B
            entire site available on the award of work the contractor will have to
            arrarrge his working programme.accordingly. No claim whatsoever for
            not giving the entire site on award of work and for giving the site
            gradually will be tenable.

c           Clause 39: (Force majeruo):

                No failure or omission to carry out the provisions of the contract
            shall give rise to any claim by the Corporation and the contractor,
                                                                                          --
            one against the other, if such fa,ilure ommission arises from an act of
            God, which shall include natural calamities such as fire, t:Jood,
D           earthquake, hurricane or any postilence, or from civil strike, compliance
            with any statute or regulation of Government, lockouts and strikes,
            or from any political or other reasons beyond the control or either
            the Corporation or the Contractor, including war whether declared
            or not, Civil war or state of insurrection.

E           Clause 5 (iv): General Conditions of Contract (Time for Completion
            of work covered by the Contract):

           Failure or delay by the Corporation to hand over to the contractor
           possession of the lands necessary fo_r the execution of the work, or·
           to give the necessary drawings instructions or any other .delay by the
F          Corporation which due to any other cause whatsoever shall in no way
           affect or vitiate the contract or alter the character thereof or entitle the
           contractor to damage or compensation therefor provided that the
           Corporation may extend the time for completion of the work by such
           period as it may consider necessary and proper.
G         Before the learned Sub-Judge and the High Court, it was submitted that
    in view of the aforesaid conditions which are laid down in the contract which
    prohibited award of damages or compensation, it was not open to the arbitrator
    to award damages for the alleged losses sustained on account of not obtaining
    or delay in obtaining various permissions required to be taken under the law
H   or rules from the Forest Department.
.             STEEL AUTHORITY OF INDIA LTD. v. J.C. BUDHARAJA, GOVT. AND MINING CONTRACTOR [SHAH, J.]   165
                  Re: Lack of Jurisdiction of the Arbitrator                                                  A

-                 From the Award quoted above, it is apparent that damages are granted
            by the arbitrator for delay in obtaining pennission from the Forest Department:

                     (a)    for executing the work inside the wildlife sanctuary;
                     (b)   to take man and machinery to the worksite in the forest;                           B
                     (c)   for making hutments at the work site and failure to hand over
                           site in time;
                     (d) failure to remove Forests growths from working area before
                         issue of work order; and
                                                                                                              c
...                  (e)   for transporting the required machinery and materials for blasting
                           operation and executing the drilling and blasting work inside the
                           wild-life sanctuary till March, 1979.

                     Clause 32 of the agreement specifically stipulates that no claim
             whatsoever for not giving the entire site on award of work and for giving the D
             site gradually will be tenable and the contractor is required to arrange his
            working programme accordingly. Clause 39 further stipulates that no failure
             or omission to carry out the provisions of the contract shall give rise to any



-
            claim by the Corporation and the contractor, one against the other, if such
            failure or omission arises from compliance with any statute or regulation of E
            Government or other reasons beyond the control of either the Corporation or
            the Contractor. Obtaining permission from Forest Department to carry out the
            work in wild life sanctuary depends on statutory regulations. Clause (vi) of
            General condition of the contract also provides that failure or delay by the
            Corporation to hand over to the Contractor possession of the lands necessary
            for the execution of the work or any other delay by the Corporation which F
            due to any other cause whatsoever would not entitle the ~ontractor to damage
            or compensation thereof; in such cases, the only duty of the Corporation was
            to extend the time for completion of the work by such period as it may think
            necessary and proper. These conditions specifically prohibit granting claim
      ...   for damages for the breaches mentioned therein. It was not open to the G
            arbitrator to ignore the said conditions which are binding on the contracting
            parties. By ignoring the same, he has acted beyond the jurisdiction conferred


--
            upon him. It is settled law that arbitrator derives the authority from the
            contract and if he acts in manifest disregard of the contract, the award given
            by him would be arbitrary one. This deliberate departure from the contract
            amounts not only to manifest disregard of the authority or misconduct on his H
      166                      SUPREME COURT REPORTS [1999) SUPP. 2 S.C.R.

.A part, but it may tantamount to mala fide action. In the present case, it is
     apparent that awarding of damages of Rs. 11 lakhs and more for the alleged
     lapses or delay in handing over work site is, on the face of it, against the
     terms of the contract.

            Further, the Arbitration Act does not give any power to the arbitrator
 B   to act arbitrarily or capriciously. His existence depends upon the agreement
     and his function is to act within the limits of the said agreement. In Continental
     Construction Co. Ltd. v. State of Madhya Pradesh, [1988] 3 SCC 82, this
     Court considered the clauses of the contract which stipulated that contractor
     had to complete the work in spite of rise in the prices of materials and also
C    rise in labour charges at the rates stipulated in the contract. Despite this, the
     arbitrator partly allowed contractor's claim. That was set aside by the Court
     and the appeal filed against that was dismissed by this Court by holding that
     it was not open to the contractor to claim extra costs towards rise .in prices
     of material and labour and that arbitrator misconducted himself in not deciding
     the specific objection regarding the legality of extra claim. In that case, the
D    Court referred to the various decisions and succinctly observed:

             "If no specific question of law is referred, the decision of the arbitrator
             on that question is not final however much it may be within his
             jurisdiction and indeed essential for him to decide the question
             incidentally. The arbitrator is not a conciliator and cannot ignore the
E            Jaw or misapply it in order to do what he thinks is just and reasonable.      ..--
             The arbitrator is a tribunal selected by the parties to decide their
             disputes according to law and so is bound to follow and apply the
             law, and if he does not he can be set right by the court provided his
             error appears on the face of the award."

F        It is to be reiterated that to find out whether the arbitrator has travelled
  beyond his jurisdiction and acted beyond the terms of the agreement between
  the parties, agreement is required to be looked into. It is true that interpretation
   of a particular condition in the agreement would be within the jurisdiction of
  the arbitrator. However, in cases where there is no question of interpretation
G of any term of the contract, but of solely reading the same as it is and still
  the arbitrator ignores it and awards the amount despite the _prohibition in the
  agreement, the award would be arbitrary, capricious and without jurisdiction.
  Whether the arbitrator has acted beyond the. terms of the contract or has
  travelled beyond his jurisdiction would depend upon facts, which however
  would be jurisdictional facts, and are required .to be gone into by the court.
H Arbitrator may have jurisdiction to entertain claim and yet he may not have
                                                                                           -
  STEEL AU1110RITY OF INDIA LTD. v. J.C. BUDHARAJA, GOVT. AND MINING CONTRACTOR (SHAH, J.)   167
jurisdiction to pass award for particular items in view of the prohibition                         A
contained in the contract and, in such cases, it would be a jurisdictional error.
For this limited purpose reference to the terms of the contract is a must.
Dealing with similar question this Court in New India Civil Erectors (P) Ltd.
v. Oil and Natural Gas Corporation, [1997) 11 SCC 75 held thus:

        "It is axiomatic .that the arbitrator being a creature of the agreement,                   B
        must operate within the four comers of the agreement and cannot
        travel beyond it. More particularly, he cannot award any amount
        which is ruled out or prohibited by the terms of the agreement. In this
        case, the agreement between the parties clearly says that in measuring
        the built-up area, the balcony areas should be excluded. The arbitrators                   C
        could not have acted contrary to the said stipulation and awarded any
        amount to the appellant on that account".

      However, the learned Counsel for the Respondent submitted that the
award being non-speaking one, the learned Sub-Judge and the High Court
have rightly refused to go behind the award or interfere with. In our view, this                   D
submission is without any substance. It is apparent that the Arbitrator has
awarded Rs. 11,26,296 for the losses sustained for the reasons stated therein
which we have incorporated in the previous paragraph. These reasons only
pertained to non-obtaining or delay in obtaining permission from the Forest
Department as the work site was located in the wild-life sanctuary of Saranda
reserve forest. The Arbitrator in his award in terms mentioned "/am convinced                      E
that the claimant sustained losses on account of following reasons" and
thereafter reasons are recorded. Therefore, it cannot be said that the award
is a non-speaking one.

      Further even if such reasons are not recorded, the claim itself for such
prohibited items was not entertainable by the Arbitrator. In the agreement                         F
between the parties, there is specific bar to raising of such claims. Hence the
decision of the arbitrator is without jurisdiction. This·aspect is also dealt with
by this Court in H.P. State Electricity Board v. J{J. Shah and Company,
[ 1999] 4 SCC 214. In paragraph 26, the Court held as under:
                                                                                                   G
        "In order to determine whether the arbitrator has acted irr excess of
        jurisdiction what has to be seen is whether the claimant could raise
        a particular dispute or claim before the arbitrator. If the answer is in
        affirmative, then it is clear that arbitrator would have the jurisdiction
        to deal with such a claim. On the other hand if the arbitration clause
        or a specific term in the contract or the law does not permit or give H
        168                      SUPREME COURT REPORTS [1999) SUPP. 2 S.C.R.

. ·A            the arbitrator the power to decide or to adjudicate on a dispute raised
                by the claimant or there is a specific bar to the raising of a particular
                dispute or claim, then any decision given by the Arbitrator in respect
                thereof would clearly be in excess of jurisdiction."

              The Court further held that in order 'to find out whether the Arbitrator
  B     has acted in excess of the jurisdiction, the Court may have to look into some
        documents including the contract as well as the reference of the dispute made
        to the Arbitrator limited for ~e purpose of seeing whether the Arbitrator has
        the jurisdiction to decide the claim made in the arbitration preceedings.

              Further dealing with the similar condition in the contract, such as no
  C claim for price escalation other than those provided therein shall be entertained
        and "the Contractor will not be entitled for any extra rate due to change in
        sel~ction of querries", this Court in Associated Engineering Co. v. Government
        of Andhra Pradesh and Anr., [1991] 4 SCC 93, observed that four claims
       mentioned therein. were not payable under the contract, in fact, it prohibited
  D    such payment and for this purpose. The Court held "this conclusion is
       reached not by construction of the contract but by merely looking at the
       contract". The Court further observed that the Arbitrator could not act
       arbitrarily, irrationally, capriciously or independently of the contract; his sole
       fiJnction is to arbitrate in terms of the contract. The Court further held thus:

  E            "An arbitrator who acts in manifest disregard of the contract acts
               without jurisdiction. His authority is derived from the contract and is
               governed by the Arbitration Act which embodies principles derived
               from a specialised branch of the law of agency (see Mustill and
               Boyd's Commercial Arbitration, 2nd edn., p. 641 ). He commits
               misconduct if by his award he decides matters excluded by the
  F            agreement (see Halsbury's Laws of England, Volume II, 4th edn., para
               622). A delibera~e departure from contract amounts to not only manifest
               disregard of his authority or a misconduct· on his part, but it may
               tantamount to a' mala fide action. A conscious disregard of the law or
               the provisions of the contract from which he has derived his authority
 G             vitiates the award."

              In view of the aforesaid settled law, the award passed by the arbitrator
       is against the conditions agreed by the contracting parties and is in conscious
       disregard of stipulations of the contract from which the arbitrator derives his
       authority. His appointment as a sole arbitrator itself was conditional one and
 H     he was informed that the same was "with reservation regarding the tenability,
  STEEL AUTHORITY OF INDIA LTD. v. J.C. BUDHARAJA, GOVT. AND MINING CONTRACTOR[SHAH, J.)   169
maintainability and validity of the Reference as also on further grounds that                    A
the claim was barred by the period of limitation and that it pertained to
excepted matters of general conditions of the contract". Despite this he has
ignored the stipulations and conditions between parties. Hence, the said
award is, on the face of it, illegal.

      Re: LIMITATION                                                                             B

      Our next question is of limitation. The period of limitation is required
to be considered on the basis of the arbitration clause between the parties
which is as under:

      "All disputes or differences whatsoever which shall at any time arise
                                                                                                 c
between the parties hereto touching or concerning the works or the execution
meaning operation or effect thereof or to the rights or liabilities of parties or
arising out of or in relation thereto, whether during or after completion of the
contract, or whether before or after determination, foreclosure or breach of the
contract (other that those in respect of which the decision of any person is ·D
by the contract expressed to be final and binding) shall after written notice
by either party to the contract to the other of them and to the M.D./Chairman
of the Corporation (who will be the appointing Authority) be referred for
adjudication to be sole Arbitrator to be appointed as hereafter. provided.
                                                                                                 E
       The Appointing Authority will send within thirty days of the receipt of
notice a panel of three names of persons not directly connected with the work
of the contractor who will select any one of the persons named to be appointed
as a sole Arbitrator within thirty days of receipt of the names. If the Contractor
fails to select the name from the panel and communicate within 30 days, the
appointing authority shall appoint one out of the panel as sole Arbitrator.                      F

       If the Appointing Authority fails to send to the contn~ctor the panel of
three names, as aforesaid, within the period specified, the Contractor shall
send to the Appointing Authority a panel of three names of persons who
shall all be unconnected with the organisation by which the work is executed.                    G
The Appointing Authority shall on receipt of the names as aforesaid select
any one of the persons named and appoint him as the Sole Arbitrator, if the
appointing authority fails to select the person and appoint him as the Sole
Arbitrator within 30 days of receipt of the panel and inform the contractor
accordingly, the Contractor shall be entitled to invoke the provisions of the
Indian Arbitration Act, 1940 and any statutory modification thereof."                            H
     170                      SUPREME COURT REPORTS [1999],SUPP. 2 S.C.R.

A         In view of the aforesaid arbitration clause, even though the claim made
    by the contractor was time barred, the dispute was required to be referred to
    the arbitrator. However, the reference was subject to the condition that it was
    barred by the period of limitation. In that context, the learned counsel for the
                                                                                       <
    appellant submitted that it is settled law that application under Section 20 or
    notice for appointment of arbitrator is to be filed within three years from the
B date when 'cause of action' arises as provided in Article 137 of the Limitation
   Act, 1963. The application filed by the contractor in December 1985 was, on
   the face of it, time barred because the cause of action to recover the amount
   arose, according to the contractor, in August 1979 when he demanded the
   alleged damages for loss suffered by him because of the delay in handing
C over the worksites. He further submitted that, in the present case, in year 1980
   for the same work, the Contractor has executed a supplementary agreement
   for the completion of the work within the stipulated time and at a higher rate.     •
   This would also show that Contractor waived his alleged right of asking for
   appointment of Arbitrator as provided in arbitration clause. He referred to the
   arbitration clause and pointed out that within 30 days of the receipt of the
D notice, arbitrator is required to be appointed by the Managing Director. If
   arbitrator is not appointed· then Contractor has option to send the panel of
   three names from which arbitrator is required to be appointed. He contended
  that after the supplementary agreement, there was no question of adjudicating
  the so- called demand made by the contractor in the year 1979. In any case,
E he submitted that the Contractor ought to have approached the Court under
   Section 20 or ought to have demanded arbitration within three years from the
  date of the notice demanding the amount for loss suffered by him. As against
  this, learned Counsel for the respondent submitted that the cause of action
  to refer the matter to the arbitrator arose only in 1983 when respondent denied
  contractors' claim.
F
          For deciding this controversy, we would first refer to the decision of
    this Court in the State o/Orissa & Ors. v. Damodar Das, [1996] 2 SCC 216
    wherein this Court held that Section 3 of the Limitation Act, 1963, enjoys the
    power to consider the question of limitation whether it is pleaded or not. The
G   Court in paragraph 5 held as under:

           "Russell on Arbitration by Anthony Walton (19th Edn.) at pp. 4-5
           states that the period of limitation for commencing an arbitration runs
           from the date on which the "cause of arbitration" accrued, that is to
           say, from the date when the claimant first acquired either a right of
H          action or a right to require an arbitration take place upon the dispute

                             .
                             ~.
  STEEL AUTHORITY OF INDIA LTD. v. J.C. BUDHARAJA, GOVT. AND MINING CONTRACTOR [SHAH, J.]   171
         concerned. The period of limitation for the commencement of an                           A
         arbitration runs from the date on which, had there been no arbitration
         clause, the cause of action would have accrued:

         "Just as in the case of actions the claim is not to be brought after the
         expiration of a specified number of years from the date on which the
         cause of action accrued, so in the case of arbitrations, the claim is not                B
         to be put forward after the expiration of the specified number of years
         from the date when the claim accrued."

         Even if the arbitration clause contains a provision that no cause of
         action shall accrue in respect of any matter agreed to be referred to
         until an award is made, time still runs from the normal date when the                    C
         cause of action would have accrued if there had been no arbitration
         clause."

     The Court also referred to the earlier decision in Panchu Gopal Bose
v. Board of Trustees for Port of Calcutta, (1993] 4 SCC 338, where the Court
~~as~                                                                                             D
        "The Period of limitation for commencing an arbitration runs from the
        date on which the cause of arbitration accrued, that is to say, from the
        date when the claimant first acquired either a right of action or a right
        to require that an arbitration takes place upon the dispute concerned.
                                                                                                  E·
        Therefore, the period of limitation for the commencement of an
        arbitration runs from the date on which, had there been no
        arbitration clause, the cause of action would have accrued. Just as
        in the case of actions the claim is not to be brought after the expiration
        of a specified number of years from the date on which the cause of                        F
        action accrued, so in the case of arbitrations, the claim is not to be
        put forward after the expiration of the specified number of years from
        the date when the claim accrued."

      Applying the aforesaid ratio in the present case, right to refer the
dispute to the arbitrator arose in 1979 when Contractor gave a notice demanding                   G
the amount and there was·no response from the appellant and the amount was
not paid. The cause of action for recovery of the said amount arose from the
date of the notice. Contractor cannot wait indefinitely and is required to take
action within the period of limitation. In the present case, there was
supplementary agreement between the parties. Supplementary agreement
nowhere provides that so-called right of the contractor to recover damages                        H
     172                      SUPREME COURT REPORTS [1999) SUPP. 2 S.C.R.

A was in any manner saved. On the contrary, it specifically mentions that
     contractor was yet to execute a considerable portion of the work more
     particularly described in the schedule to the agreement. And that the contractor
     has agreed to complete the said balance work on the terms and conditions
     enumerated in the agreement. Now, in this set of circumstances, contractor
     cannot wait and approach the authority or the court for referring the dispute
B    to the arbitrator beyond the period oflimitation. Section 37 of the Arbitration
     Act specifically provides that provisions of the Indian Limitation Act shall
     apply to the arbitrations as they apply to proceedings in the Court.

           Learned counsel for the respondent relied upon the decision of this
C   Court in Major (Retd.) Inder Singh Rekhi v. Delhi Development Authority,
    [1988] 2 SCC 338 for contending that cause of action for referring the claim
    arises only when the appellant disputed the right of the respondent to recover
    the damages claimed by him. In the said case, the Court h_as observed that
    on completion of the work, the right to get payment would clearly arise, but
    wherein the final bills have not been prepared and when the assertion of the
D   claim was made on 28th February, 1983 and there was non-payment, the cause
    of action arose from that date. In that case, application under Section 20· was
    filed in January 1986. The Court also observed that:
             "it is true that the party cannot postpone the accrual of cause of
             action by writing reminders or sending reminders but where the bill
E            had not been finally prepared, the claim made by a claimant is the
             accrual of the cause of action. A dispute arises where there is a claim
             and a denial and repudiation of the claim. The existence of dispute is
             essential for appointment of an arbitrator under Section 8 or a reference
            under Section 20 of the Act. See Law ofArbitration by RS. Bachawat,
            first edition, page 354. There should be dispute and there can only
F           be a dispute when a claim is asserted by one party and denied by the
            other on whatever grounds. Mere failure or inaction to pay does not
             lead to the inference of the existence of dispute. Dispute entails a
            positive element and assertion of denying, not merely inaction to
            accede to a claim or a request. Whether in a particular case a dispute
G           has arisen or no~ has to be found out from the facts and circumstances.
            of the case. "

          In the present case, as stated above, on 29th August, 1979, the contractor
    wrote letter making certain claims. Thereafter, the supplementary agreement
    was executed on 20th December, 1980. In that agreement it is nowhere stated
H   that contractors alleged right of getting damages or losses suffered by him
  STEEL AUTHORITY OF INDIA LTD. 1•. J.C. BUDHARAJA, GOVT. AND MINING CONTRACTOR [SHAH, J.]   }   73

was kept alive. On the contrary, he has agreed to complete the work within A
the time stipulated in the second agreement by charging some higher rate.
Contractor has not sought any reference within three years from the date
when cause of action arose, i.e., from 29th August, 1979. Only in 1985 when
dispute arose with regard to the second agreement, respondent gave notice
on 2nd December, 1985 to appoint sole arbitrator. The sole arbitrator was B-
appointed with a specific reservation regarding the tenability, maintainability
and validity of reference as also on the ground that claim was barred by the
period of limitation and it pertained to excepted matters in terms of general
conditions of the contract. From these facts, it is apparent that claim before
the arbitrator in November-December 1985 was apparently barred by period
of limitation. Letter dated 3rd September, 1983 written by the appellant C
repudiating the respondent's claim on account of damages or losses sustained
by him would not give fresh cause of action. On that date cause of action
for recovering the said amount was barred by the period of three years
prescribed under Article 13 7 of the Limitation Act, 1963. Under Section 3 of
the Limitation Act, it was the duty of the arbitrator to reject the claim as it
was on the face of it, barred by the period of limitation.                      D
       In the present case, in view of the aforesaid findings, it is not necessary
to discuss the contention with regard to the award of interest prior to coming
into force of the Interest Act, 1978 or that no interest could be awarded on
the unliquidated damages. It is also not necessary to discuss whether                                 E
arbitration agreement provided in first agreement executed in 1977 would
survive after execution of the second agreement in December, .1980.

       In the result, the appeal is allowed with costs. The impugned order
passed by the Patna High Court, Ranchi Bench in Miscellaneous Appeal No.
621 of 1990 and the order dated 2nd April, 1990 passed by the Subordinate_                            F
Judge, 1st Court, Chas in Arbitration Suit No. 28 of 1988 are quashed and set.
aside.

V.S.S.                                                                      Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.