STEEMAN LTD.versusSTATE OF HIMACHAL PRADESH
- Citation
- 1997 INSC 236
- Decided
- 6 March 1997
- Disposal
- Dismissed
- Bench
- A S ANAND
Holding
The court cannot interfere with the arbitral award on the raised grounds; the award stands and the application is dismissed.
Summary
The petitioners, Steeman Ltd., were contracted to construct the Sitla Bridge in Himachal Pradesh. Disputes over progress and payments led to the imposition of a penalty and rescission of the contract, which the petitioners successfully appealed, allowing work to continue and the matter to be referred to arbitration. After several arbitrators were appointed, the final arbitrator awarded a modest sum with interest at 6% despite the petitioners’ claim for 18% interest, and the petitioners challenged the award on four grounds: failure to answer a prior question of law, a non‑speaking award suggesting the arbitrator did not consider the claim, denial of a reasonable opportunity to present their case, and the low interest rate. The Supreme Court held that the questioned law was not framed as an issue by the arbitrator, that the new arbitrator’s award superseded the earlier question, that detailed minutes showed the parties were given full opportunity, and that the interest rate decision fell within the arbitrator’s discretion and not within the limited grounds for court interference under Section 30 of the Arbitration Act, 1940. Consequently, the Court dismissed the interlocutory application and the special leave petition, leaving the award untouched.
Issues considered
- Whether the arbitrator was obliged to answer a question of law raised before the predecessor arbitrator.
- Whether a non‑speaking award indicates the arbitrator failed to apply his mind to the claim.
- Whether the petitioner was denied a reasonable opportunity to present his case.
- Whether the award of interest at 6% contrary to the claimed 18% is a ground for court interference under Section 30 of the Arbitration Act, 1940.
- Whether the court has jurisdiction to interfere with the arbitral award on these grounds.
Legislation cited
- Arbitration Act, 1940s. 13(b), s. 30
Subjects
Judgment
A STEEMAN LTD.
v.
STATE OF HIMACHAL PRADESH
MARCH 6, 1997
B (DR .. A.S. ANAND AND K. VENKATASWAMI, JJ.]
Arbitration Act, 1940: Section 30.
Award--Cliallenge of-Grounds-Arbitrator failed to answer question
C of law raised before predecessor arbitrato1~From the non-speaking award it '
was not possible to find out whether the arbitrator had applied his mind to a
pmt of claim-Arbitrator had not given reasonable opportunity of meeting the
-
case-Interest awarded was at too low a rate of 6% whereas claim was for
18%---Held : No such question of law framed as an issue by arbitrato~Al
legation of Company's properties being forcibly taken possession of by
D State-No separate claim made in the amended claim-Reasonable oppor-
tunity of meeting the case-Giving of-Proved by the detailed minutes of the
Arbitrator drawn at the sittings hi!,ld by him-No good reason to think that
the Arbitrator had awarded interest at 6% without taking into account the
relevant facts and circumstances of the case-Jurisdiction of the Court to
E inteifere with the award confined to matters enumerated in S.30.
The applicant/petitioner was awarded the work of construction of a
Bridge. As there was some dispute between the parties regarding the
progress of the work and payments for the same, the petitioner submitted
disputes/differences for adjudication by an arbitrator. However, the
F respondents imposed a penalty in addition to rescinding the contract.
Against the order rescinding the contract and imposing penalty, the
petitioner successfully appealed to the State Government. Consequently,
the petitioner was allowed to proceed with the work and the disputes were
referred to an arbi\rator. The arbitrator entered upon the reference. While
G the arbitration proceedings were going on, the respondents again res-
cinded the contract finally.
The petitioner submitted additional claims before the arbitrator
consequent upon the rescinding of the contract finally. The petitioner also
raised a question of law before the arbitrator. The arbitrator referred that
H question for opinion of the High Court under Section 13 (b) of the Arbitra-
770
STEEMAN LTD. v. STATE 771
tion Act, 1940. While that was pending a new arbitrator was appointed. A
-- The High Court while setting aside the removal of the previous arbitrator
-
did .not continue with the new arbitrator. Since, no orders were passed by
the High Court for proceeding further with the arbitration matter, the
petitioner filed a Transfer Petition before this Court. This Court disposed
of the Transfer Petition by appointing an arbitrator. The said arbitrator B
duly entered upon the reference, held as many as 10 sittings/hearings and
•. drew minutes of every meeting in. detail. Based on that an award was
passed and filed in this Court. The petitioner had filed an application
challenging the award.
On behalf of the petitioner it was contended that the arbitrator failed C
to answer the question of law raised' before predecessor arbitrator, that
since the arbitrator had made a non-speaking award it was not possible
to find out whether he had applied his mind to a part of the claim; that
the arbitrator had not given a reasonable opportunity of meeting the case;
and that the interest awarded was at too low a rate as the claim was for
18% and the award was at 6%. D
Dismissing the application, this Court
HELD : 1. By consent of both the parties, the arbitrator framed
issues for adjudication and the question of law now being raised was not E
one of the issues. Further the so-called question of law loses its relevance,
after the appointment of the new arbitrator by the Court, as indeed no act
of rescinding the contract took place after this Court appointed the
Arbitrator. Therefore, there is no substance in the first point. [775-B]
2. The Arbitrator as quite justified in not awarding any amount F
under a separate head for the property of the Company forcibly taken
possw;sion of in the light of the amended claims presented before him.
There is thus no substance in the argument that the claim as originally
put forward regarding company property allegedly taken possession of by
the respondent illegally and forcibly, was not. separately considered by the G
Arbitrator. In fact, no such separate claim was made by the petitioner in
the amended claim. [777-E-F]
a
3. The contention that the petitioner was not given reasonable
in
opportunity of meeting the case is not acceptable view of the detailed
minutes of the Arbitrator drawn at the sittings which extended to 10 in . H
'
772 SUPREME COURT REPORTS [1997) 2 S.C.R.
A number. (777-G]
Suresh Ragho Desai & Anr. v. Smt. Vijaya Vi11ayak Ghag, (1988] 4
B
SCC 591 and Rajpur Development Authority & Ors. v. Mis. Chokhamal
Contractors & Ors., [1989] 2 SCC 721, referred to.
4. There is no good reason to think that the Arbitrator has awarded
-
interest at 6% as against 18% claimed without taking into account the
relevant facts and circumstances of the case. Further the jurisdiction of
the Court to interfere with the award is confined to matters enumerated
in Section 30 of the Arbitration Act, 1940 and the point regarding interest
C would not fall within the ambit of Section 30 of the Act. (779-A-B]
CIVIL APPELLATE JURISDICTION: Interlocutory Application.
No. 1.
IN
D Transfer Petition (C) No. 233 of 1980.
WITH
Special Leave Petition (C) No. 15978 of 1986.
E From the Judgment and Order dated 3.7.86 of the Himachal Pradesh
High Court in C.R. No. 5 of 1973.
M.L. Verma and S.K. Gambhir for the Applicant/Petitioner.
B. Dutta, L.R. Nath and J.S. Attri for the Respondents.
F
The Judgment of the Court was delivered by
VENKATASWAMI, J. On a close and careful scrutiny of the facts we
find that the dispute in these matters lies in a very narrow compass, but
longwinding arguments were addressed by referring to matters which have
G no real relevance to the actual disputes in these matters.
Brief facts leading to the filing of these two matters are the following:
The work of construction of Sitla Bridge over river Ravi at Champa
was awarded after negotiation to the applicanUpetitioner (Mis Steeman
H Ltd.) on 31.12.1969. We are not giving details as they are not necessary. As
STEEMANLTD.¥. STATE[VENKATASWAMI,J.] 773
. there was some dispute between the parties regarding the progress of the A
work and payments for the sa~e. The petitioner Company submitted
-
disputes/differences for adjudication by an arbitrator as per clause 29 of
the agreement. While so, the Executive Engineer, Champa Division im-
posed penalty of Rs. 63,000 in addition to rescinding the contract on
5.7.1971. Against the order rescinding the contract and imposing penalty, B
the petitioner Company successfully appealed to the Government- of
Himachal Pradesh. Consequently,. the Company was allowed to proceed
with the work and the disputes were referred to an arbitrator.
As Arbitrator originally appointed was not acceptable to the
· . petitioner company one, Mr. R.K. Sarkar was appointed as arbitrator oy C
· mutual consent of parties. The said arbitrator entered upon the reference.
While the arbitration proceedings were going on, the respondents
again rescinded the contract finally on 7.6.1972.
On 7.10.1972, the petitioner Company submitted additional claims D
before the arbitrator consequent upon the rescinding of the contract finally.
The petitioner Company also raised a question of law before the arbitrator,
namely, 'whether the respondent was competent to rescind the contract on
the ground of slow progress when the matter in dispute was subjudice
before the arbitrator during the pendency of the case'. The arbitrator
referred that question for opinion of the Himachal Pradesh High Court E
under Section 13(b) of the Indian Arbitration Act. While that was pending,
it appears that in the place of Mr. R.K. Sarkar one Mr. O.B. Sablok was
appointed as arbitrator. The petitioner challenged the substitution of the
arbitrator before the High Court. The High Court while setting aside the
removal of Mr. R.K. Sarkar and the appointment of Mr. O.B. Sablok as
arbitrator, did not continue Mr. R.K. Sarkar as arbitrator. Since, no orders F
were passed by the High Court for proceeding furthr.r with the arbitration
matter, the petitioner Company moved this Court by filing Transfer Peti-
tion No. 233 of 1980 for transfer of the cases to some other High Court.
This Court disposed of the Transfer Petition on 12.3.1984 by appointing
one Mr. G.N. Ramaswamiah, Chief Engineer (IPH) H.P. FWD. with the G
mutual consent of the parties with a direction to the said arbitrator to enter
upon the reference and directing both the parties to appear before him on
·3.9.1984.
The said arbitrator duly entered upon the office, held as many as 10
sittings/hearings and drew minutes of every meeting in detail. Based on that · H
774 SUPREME COURT REPORTS (1997] 2 S.C.R.
A an award' has been passed on 14.6.1985.
The High Court (before which the question of law above mentioned,
was referred to by Mr. R.K. Sarkar, the previous Arbitrator) disposed of
the matter on 3. 7.1986 stating that since the successor Arbitrator had made
the award, there was no need to answer the question. On that view, the
B High Court dismissed the reference matter. Aggrieved by that the above
special leave petition has been filed.
When we asked the learned Senior Counsel appearing for the
petitioner whether anything survives in the special leave petition not only
C in view of the issues raised before the Arbitrator for adjudication but also
having regard to the arbitrator appointed by this Court passing the award,
the leaned counsel frankly submitted that the special leave petition has
become infructuous. Accordingly, we dismiss the same as having become
infructuous.
D Award has been filed in this Court. Petitioner has filed objections to
the award.
Challenging the award as such, the learned counsel raised four
points.
E The first point raised is that the arbitrator should have answered the
question of law raised before the predecessor arbitrator and the failure to
do so vitiates the award.
Secondly, the arbitrator has made a non-speaking award and, there- ,
fore it is not possible to find out whether he has applied his mind to that
F part of the claim amounting to rupees two lakhs eighteen thousand which
represented the goods seized after rescinding the contract.
Thirdly, the arbitrator has not given reasonable opportunity of meet-
irig the case of the respondents and also in establishing the petitioner's
G case. In support of this contention he placed reliance on Suresh Ragho
Desai and Another v. Smt. Vijaya Vinayak Ghag, [1988] 4 SCC 591 and
Rajpur Development Authority & Others v. M/s. Chokhamal Contractors &
Others, [1989) 2 SCC 721.
And the last point is that the interest awarded was at too low a rate
H as_ the claim was for 18% and the award was at 6%.
STEEMANLTD. v. STATE[VENKATASWAMI,J.] 775
So far as the first point is concerned, we do not think that the said A
question arises out of the present arbitration proceedings inasmuch as this
Court appointed the present arbitrator to go into the disputes between the
parties and the parties were directed to place before the arbitrator their
respective disputes. As a matter of fact by consent of both the parties. The
arbitrator framed issues for adjudication and it does not appear from the B
issues that the question of law now being raised was one of the issues.
Further the so-called question of law ioses its relevance, after the appoint-
ment of the new arbitrator by this Court, as indeed no act of rescinding
the contract took place after this court appointed the Arbitrator. There-
fore, there is no substance in the first point.
c
Regarding the second point, the facts a1 e like this. The petitioner
company's demand in the original claim under clauses I & II read as
follows:-
(in round figure
of 1000 rupees) D
I. The work done by the company
upto 16.9.1972 when it was forcibly
dispossessed, approximately 12,00,000.00
Less value received from H.P. E
PWD, in the shape of cash or
material (-) 3,00,000.00
9,00,000
Plus for property of the company F
illegally & forcibly taken over on
16.9.72 by the Department ( +) 4,18,000.00
Less value of material handed
over to company (-) 2,00,000.00 G
11,18,000.00
- Total amount on account of work
down and property forcibly taken
over plus interest @'i8% p.a. from H
776 SUPREME COURT REPORTS
.
[1997} 2 S.C.R .
A 16-9-72 to 15-9-84, i.e. for 12 years ( +) 24,15,000.00
The total sum to which the
company is entitled as on 15-9-84
under this head 32,33,000.00
B II. Damages on account of criminal
breach of trust, fabricating false
evidence, mischief, forgery, cheating,
with intent to cause injust loss and
injury to the petitioner. The company ·
c claims a sum equal \o the money
it was illegally deprived of 11,18,000.00
The above claims were modified before the present Arbitrator which
read as follows :-
Claims prefemd by the Petitioner :-
D
I (a) Claim on works done by the
Company upto 16.9.72 Rs. 11,18,000.00
(b) Interest on the amount under
E I(a) @ 18% per annum for a period
of 12 years. Rs. 24,15,000.00
II. Claims made by the company
under for reasons whatsoever as
per clause of the agreement Rs. 11,18,000.00"
F
[Other clauses omitted as not relevant)
The Arbitrator has passed the award on the basis of the amended
claim as follows :-
Claims preferred Amount
G S. No. Awarded amount
by the petitioner claimed (Rs.)
I. (a) Claim on works 11,18,000.00 I award Rupees Forty two
done by the thousand Nine hundred
company upto Forty Nine and Sixty Three
16.9.72 paisa only. (Rs. 42,949.63)
H
S1EEMANL1D. v. STA1E[VENKATASWAMI,J.) 777
(b) Interest on the 24,15,000.00 I award simple interest of A
amount under I(a) six percent for 12 years
upto this date amounting
to Rupees Thirty
Thousand Nine Hundred
Twenty Three and seventy B
three paisa only. (Rs.
30,923.73)
II. Claims made by 11,18,000.00 I award Rupees Twenty
the company on Three Thousand Two
damages (This is Hundred Twenty Five lying
amended claim m deposit with
c
from the earlier Respondent. Further I
item" for reasons award Rupees Fifty
whatsoever as per Thousand on i.1ventory of
clause of the stores etc. totalling Seventy
agreement), and Three Thousand Two D
amount 1s the hundred twenty Five only).
same (23,225 + 50,000 =
73,225.00)."
The Arbitrator was in our opinion quite justified in not awarding any
amount under a separate head for the property of the Company forcibly E
taken possession in the light of the amended claims presented before him.
There is thus no substance in the argument that the claim as originally put
forward regarding company property allegedly taken possession of by
respondent illegally and forcibly, was not separately considered by the
Arbitrator. Answer is obvious viz. no such separate claim was made by the F
petitioner in the amended claim. Hence we have no hesitation to reject the
second point also.
So far as the third point is concerned, namely that the petitioner was
not given reasonable opportunity to substantiate the case, we do not think
that we can accept that contention after perusing the detailed minutes of G
the Arbitrator drawn at the sittings which extended to 10 in number. As a
matter of fact, we find that the Arbitrator had called upon the petitioner
Company time and again to furnish documents to support the claims. But, ,
the petitioner has only partly compiled with the directions of the Ar-
bitrator. The Arbitrator had given full and reasonable opportunity to both H
778 SUPREME COURT REPORTS (1997] 2 S.C.R.
A parties to put forward their respective claims. At the last sitting dated
5.4.85, the Arbitrator observed as follows :-
'As far as oral hearing is concerned, it is closed but in case any
clarifications are needed by the court after receipt of final reply
from both the parties ~thin the dates stipulated above, the parties
B may be summoned at short notice to seek such clarifications
needed by the court.'
Pursuant to the above, it appears the Arbitrator sent letters to both
parties seeking certain clarifications. Taking advantage of that, learned
C counsel for the petitioner argued that the Arbitrator has not given
reasonable time to the petitioner to clarify the doubts. The learned counsel
also invited our attention to a post-script found at the concluding part of
the proceedings dated 30.5.85. The post-script reads as follows :-
'That during the course of hearing, petitioner requested for an
D interval to see the documents and give clarifications. Accordingly,
the court adjourned for half an hour during the course of the
proceedings.'
According to the learned counsel, the time given Arbitrator was
totally inadequate to. clarify the doubts and therefore, there was no
E reasonable opportunity. As pointed out earlier, after going through the
minutes of the Arbitrator drawn during the sittings, we do not think that
there is any substance in the argument. Further neither of the counsel was
in a position to explain as to who made the post -script and when was it
entered in the proceedings of the Arbitrator. The decisions cited by the
F learned counsel for the petitioner in support of his argument that want of
reasonable opportunity would vitiate the award may not come to his aid as
we are satisfied on the facts of the case, from the record including the
minutes drawn meticulously, that the Arbitrator had given full and
reasonable oportunity to both parties. Accordingly we find no force in this
G point as well.
As regards the last point concerning the interest, we are informed
that there is no clause in the agreement regarding interest. Before the
Arbitrator both parties appear to have agreed on the rate of interest at
18%. However, the Arbitrator in the facts and circumstances of the case
H awarded interest at 6%. The agreement between the parties does not mean
STEEMAN LTD. v. STATE [VENKATASWAMI, J.] 779
that the Arbitrator was bogged down to that rate irrespective of other facts A
and circumstances of the case on hand. We have no good reason to think
that· the Arbitrator has awarded interest at 6% as against 18% claim
without taking not account the relevant facts and circumstances of the case.
Further the jurisdiction of the Court to interfere with the award is confined
to matters enumerated in Section 30 of the Arbitration Act. We do not B
think that the last point raised before us would fall within the ambit of
Section 30 to interfere with the award. ·
In the result the Interlocutory Application 1/96 in Transfer Petition
(Civil) No. 233/80 as well as Special leave petition (Civil) No. 15978/86
stand dismissed. However, .there will be no order as to costs. C
v.s.s. Appeal and petition dismissed.
,•
·-
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.