Created byFuzzy Cloud

Supreme Court of India

SUNDARAM FINANCE LTD.versusNEPC INDIA LTD.

Citation
1999 INSC 10
Decided
13 January 1999
Disposal
Disposed off

Holding

A court may entertain an application under Section 9 of the Arbitration and Conciliation Act, 1996 and grant interim relief even before arbitral proceedings commence, provided a valid arbitration agreement exists and the applicant demonstrates a manifest intention to refer the dispute to arbitration.

Summary

Sundaram Finance Ltd entered into a hire‑purchase agreement for two wind‑turbine generators with NEPC India Ltd, which contained an arbitration clause. After the respondent defaulted on payments, the appellant sought interim custody of the equipment under Section 9 of the Arbitration and Conciliation Act, 1996, and the trial court granted the order. The High Court set aside the order, holding that Section 9 could not be invoked before arbitral proceedings were pending. The Supreme Court held that Section 9 expressly allows a court to grant interim measures before or during arbitral proceedings, provided a valid arbitration agreement exists and the applicant shows a manifest intention to arbitrate, and that a notice under Section 21 is not a prerequisite. The Court also emphasized the need for High Courts to frame procedural rules under Section 82. Consequently, the High Court judgment was set aside and the trial court's interim order restored.

Issues considered

  • Whether Section 9 of the Arbitration and Conciliation Act, 1996 authorises a court to grant interim relief before the commencement of arbitral proceedings.
  • Whether a notice invoking the arbitration clause under Section 21 is a condition precedent to filing an application under Section 9.
  • Whether the existence of a valid arbitration agreement and a manifest intention to arbitrate suffice for jurisdiction under Section 9.
  • Whether High Courts should make rules under Section 82 to regulate applications under Section 9.

Legislation cited

Subjects

ArbitrationInterim reliefSection 9Arbitration and Conciliation Act 1996Arbitration clauseHire‑purchase agreementManifest intention to arbitrateUNCITRAL Model Law

Judgment

             t-




                                        SUNDARAM FINANCE LTD.                                        A
         ~
                                                  v.
                                           NEPC INDIA LTD.

                                              JANUARY 13, 1999

                             (SUJATA V. MANOHAR AND B.N. KIRPAL, JJ.)                                B
     \

                        Arbitratio11 a11d Conciliatio11 Act, 1996: Sectio11s 9 and 21.

                         Interim orde1~Seeking of-Before co111111e11ceme11t of arbitra-
                  tion-Held, Court ca11 pass interim order eve11 before comme11ceme11t of c
                  wbitral proceedings-It is not necessary to issue a 11otice invoking arbitration
                  clause to the opposite party before filing application u11der S. 9 for interim
                  relief-However, before passi11g the interim order court must be satisfied that
                  there exists a valid arbitration agree111e11t a11d that the applicant inte11ds to
                  take the dispute to arbitration-Court may pass a co11ditio11al order with a
                  view to seei11g that effective steps are take11 by the applicant for comme11ci11g D
                  the arbitral proceedi11gs-Arbitratio11 Act, 1940, Ss.41(c), 20 a11d Sch.
                  Il--{f11ited Nations Commissio11 on Intemational Trade Law-Model Law
                  011 I11tematio11al Commercial Arbitration adopted in 1985, .Art.9.

                         Sections 9 and 22-Rules u11der-Maki11g of-By High Courts-Held,              E
                  High Cuurts should make rules u11der S.82 consistent with the Act providing
                  for the manner of fili11g the application, the documents which should accom-
                  pany the same and the manner of dealing with the same under S.9.

                        Provisio11s-/11terpretation of-Held, Should be construed i11de-
                  pe11dently without refere11ce to the principles underlying the repealed-Arbitra-   F
                  tion Act, 1940-Should be co11strued with reference to the UNCITRAL Model
                  Law.

                        Interpretation of Statutes:
                                                                                                     G
                        Basic Rules--fl.ule of Literal Construction-adopting of.
-«   ,_
                        Words and Phrases:

                        "Before''-Mea11i11g of-/n the co11text of S.9 of the Arbitration a11d
                  Conciliation Act, 1996.                                                     H
                                                      89
    90                    SUPREME COURT REPORTS                   [1999] 1 S.C.R.

A          The respondent had entered into a hire-purchase agreement with the       ~
    appellant in respect of two wind turbine generators along with all acces-
    sories. The terms of agreement contemplated payments being made in
    instalments by the respondent. However, the respondent paid the first
    fifteen instalments and thereafter committed default and payment was not
    made in spite of several demands being made by the appellant.
B
           The purchase agreement contained an arbitration clause and, there-
    fore, the appellant filed an application under Section 9 of the Arbitration
    and Con~iliation Act, 1996 before the Trial Court for interim custody of
    the hire-purchase equipment. The Trial Court passed an interim order to
c   that effect.

          The respondent filed a petition before the High Court challenging
    the aforesaid order of the Trial Court. The High Court allowed the petition
    on the ground that as no arbitration proceedings were pending and even
D   the arbitrator had not been appointed, an application under Section 9 of
    the 1996 Act for getting interim relief alone was not maintainable and,         "
    therefore, the Trial Court had no jurisdiction to entertain such an applica-
    tion. Hence this appeal.

          Disposing of the appeal, this Court
E
          HELD: 1.1. Under the Arbitration and Conciliation Act, 1996 the
    Court can pass interim orders under Section 9. Arbitral proceedings
    commence only when the request to refer the dispute is received by the
    respondent as per Section 21 of the Act. The material words occurring in
F   Section 9 are "before or during the arbitral proceedings". This clearly con-
    templates two stages when the Court can pass interim orders, i.e:, during
    the arbitral proceedings or before the arbitral proceedings, There is no
    reason as to why Section 9 of the 1996 Act should not be literally construed.
    Meaning has to be given to the word "before" occurring in the said section.
G   The only interpretation that can be given is that the Court can pass interim
    orders before the commencement of arbitral proceedings. The Court has
                                                                                    ~   ~-
    jurisdiction to entertain an application under Section 9 either before
    arbitral proceedings or during arbitral proceedings or after the making of
    the arbitral award but before it is enforced in accordance with Section 36
H   of the Act. [98-G-H; 99"A·D]
r

                SUNDARAM FINANCE LTD. v. NEPC INDIA LTD.                       91

           1.2. However, when a party applies under Section 9 of the 1996 Act        A
    it is implicit that it accepts that there is a final and binding arbitration
    agreement in ·existence. It is also implicit that a dispute must have arisen
    which is referable to the arbitral tribunal. Section 9 further contemplates
    arbitration proceedings taking place between the parties. When an applica-
    tion under Section 9 is filed before the commeucement of the arbitral
    proceedings there has to be manifest intention on the part of the applicant
                                                                                     B
    to take recourse to the arbitral proceedings if, at the time when the
    application under Section 9 is filed, the proceedings have not commenced
    under Section 21 of the 1996 Act. In order to give full effect to the words
    "before or dwing arbitral proceedings', occurring in Section 9 it would not
    be necessary that a notice invoking the arbitration clause must be issued        C
    to the opposite party before an application under Section 9 can be filed.
    The issuance of a notice may, in a given case, be sufficient to establish the
    manifest intention to have the dispute referred to arbitral tribunal; but a
    situation may so demand that a party may choose to apply under Section
    9 for an interim measure even before issuing a notice contemplated by            D
    Section _21 of the said Act. If an application is so made the Court will first
    have to be satisfied that there exists a valid arbitration agreement and the
    applicant intends to take the dispute to arbitration. Once it is so satisfied
    the Court will have the jurisdiction to pass orders under Section 9 giving
    such interim protection as the facts and circumstances warrant. While
    passing such an order and in order to ensure that effective steps are taken      E
    to commence the arbitral proceedings, the Court while exercising jurisdic-
    tion under Section 9 can pass conditional order to put the applicant to
    such terms as it may deem fit with a view to see that effective steps are
    taken by the applicant for commencing the arbitral proceedings. What is
    apparent, however, is that the Court is not debarred from dealing with an
                                                                                     F
    application under Section 9 merely because no notice has been issued
    under Section 21 of the 1996 Act. [102-C-H]

          Channel Tunnel Group Ltd. v. Balfour Betty Co11strnctio11 Ltd. [1992)
    2 LLR, referred to.
                                                                                     G
         Russel 011 Arbitration 21st Edn. P .386, referred to.

          2.1. The 1996 Act does not contain a provision similar to Section 20
    of the Arbitration Act, 1940. Nor is Section 9 or Section 17 similar to
    Section 41 (b) and the Second Schedule to the 1940 Act. Section 8 of the         H
     92                     SUPREME COURT REPORTS                  [1999] 1 S.C.R.
 A    new Act is not in pari materia with Section 20 of the 1940 Act. It is only if
      in an action, which is pending before the Court that a party applies that       'ff
      the matter is the subject of an arbitration agreement does. the Court get
      jurisdiction to refer the parties to arbitration. The said provision does not
      contemplate, unlike Section 20 of the 1?40 Act, a party applying to a Court
 B   •for appointing an arbitrator when no matter is pending before the Court.
      Under the 1996 Act appointment of arbitrator/s is made as per the
      provision of Section 11 which does not require the Court to pass a judicial       !
      order appointing arbitrator/s. [98-D-F]

           Sant Ram & Co. v. State of Rajasthan, [1997) 1 SCC 147, held
· C inapplicable.

           2.2. Further, Section 82 of the 1996 Act gives the High Court power
     _to make rules consistent with the Act. All the High Courts have not so far
     made rules. Whereas Section 84 gives the Central Government power to
     make rules to carry out the provisions of the Act, the High Courts should
 D   also, wherever necessary, make rules. It would be helpful if such rules deal
     with the procedure to be followed by the Courts while exercising jurisdic-         ><
     tion under Section 9 of the Act. The rules may provide for the manner in
     which the application should be filed, the documents which should accom-
     pany the same and the manner in which such applications will be dealt
 E   with by the Courts. The High Courts are, therefore, requested to frame
     appropriate rules as expeditiously as possible so as to facilitate quick and
     satisfactory disposal of arbitration cases. [103-A-C]

         3. The 1996 Act is very different from the Arbitration Act, 1940. The
   provisions of the Act have, therefore, to be interpreted and construed
 F independently and in fact reference to 1940 Act may actually lead to
   misconstruction. In other words the provisions of 1996 Act have to be
   interpreted being uninfluenced by the principles underlying the 1940 Act.
   In order to get help in construing these provisions it is more relevant to
   refer to the UNCITRAL (United Nations Commission on International
 G Trade Law) Model Law rather than the 1940 Act. [96-C-D]

            CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 141-143
      of 1999.                                                                         -r !"

            From the Judgment and Order dated 22.6.98 of the Madras High
 H Court itJ. C.R.P. No. 1421-23 and C.t.f.P. Nos. 6698-6701of1998.
     SUNDARAM FINANCE LTD. v. NEPCINDIALTD. [KIRPAL, J.)                    93
      Harish Salve and K. Swami for the Appellant.                                A
     Gopal Subramaniam, Gopal Jain, Arvind Kumar, A Choudhary,
(R.Karanjawala) for Mrs. M. Karanjawala for the Respondent.

      The Judgment of the Court was delivered by
                                                                                  B
      KIRPAL, J. Leave granted.

      An important question which arises for consideration in these cases
is whether under Section 9 of The Arbitration and Conciliation Act, 1996
(hereinafter referred to as 'the 1996 Act') the. Court has jurisdiction to pass
interim orders even before arbitral proceedings commence and before an            c
arbitrator is appointed.

      . The relevant facts which are necessary for the consideration of the
p_oint in issue are that the respondent had entered 1into a hire-purchase
agreement with the appellant herein in respect of supply of two wind D
turbine generators along with all accessories. The terms of the agreement
contemplated payments being made in instalments by the respondent, the
first instalment was payable on 29th September, 1995 and the last was due
by 25th August, 1998. In all the payment was to be made by 36 instalments.

        According to the appellant the respondent paid the first fifteen          E
instalments and thereafter committed default and payment was not made
i;i spite of several demands being made by the appellant. The hire-purchase
agreement contained an arbitration clause which reads as follqws :

        "All disputes, differences and/or claims, arising o.ut of this hire F
        purchase agreement whether during its subsistence or thereafter
        shall be settled by arbitration in accordance with the provision of
        Indian Arbitration Act, 1940 or any statutory amendments thereof
        and shall be referred to the sole arbitration of an arbitrator
        nominated by the Managing Director of the owner. The award G
        given by such an arbitrator shall be final and binding on all the
        parties to this agreement.

        It is a term of this agreement that in the event of such an arbitrator
        to whom the matter has been originally referred doing or being
        unable to act for any reason, the Managing Director of the owner, H
    94                   SUPREME COURT REPORTS                    [1999) 1 S.C.R.

A           at the time of such death of the arbitrator or his inability to act as
            arbitrator shall appoint another person to sit as arbitrator. Such a
            person shall be entitled to proceed with the reference from the
            stage at which it was left by his predecessor".

    When the appellant came to know that other litigation was pending against
B the respondent it filed an application under Section 9 of the 1996 Act
    before the City Trial Court, Chennai, praying for the appointment of an          '
    Advocate Commissioner to take custody of the hire-purchase
    machinery/equipment and restore .the same to the interim custody of the
    appellant herein. This application was taken up for hearing on 7th April,
c   1998 and the Trial Court passed an interim order appointing a Commis-
    sioner to take possession of the turbines with the help of the police.

         The aforesaid order of the Trial Court was challenged with the
  respondent filing a petition under Article 227 of the Constitution before
  the High <;:ourt at Madras. One of the main contentions urged on behalf
D of the respondent was that as no arbitration proceedings were pending and          .,<.
  even the arbitrator had not been appointed, an application under Section
  9 of the 1996 Act for getting interim relief alone was not maintainable. On
  merits it was contended that the ex parte order which was passed by the
  trial court was uncalled for. While. supporting the order of the Trial Court
  the appellant herein had submitted before the High Court that interim
E
  order could be passed even before the commencement of the arbitral
  proceedings.

          By it's judgment dated 22nd June 1998, the High Court allowed the·
    respondent's petition. In it's judgment, after referring to the provisions of
F   Section 41 of the Arbitration Act, 1940 and the relevant provisions of the       ·•
    1996 Act, the High Court observed as follows :

             "Second Schedule to the 1940 Act is the powers of the Court and
             item No. 4 is "interim injunction or the appointment of a receiver".
             Therefore, there is no virtual difference between Section 41 read
G            with Schedule 2 and present Section 9 of the Arbitration Act.
             Moreover, if an interpretation such as the one contended by the         -f' I
             Learned Counsel for the appellant is to be given to Section 9 the
             very object of the Act would be defeated. Any party, who has an
             agreement for arbitration with another can rush to Civil Court and
H            straight away get an order under Section 9 and thereafter keep
    I

             SUNDARAM FINANCE LTD. v. NEPCINDIALTD. [KIRPAL,J.]                      95

                 quiet without referring the matter to Arbitration. That will have a       A
                 very serious consequence on the provisions of the Act. It could not
                 have been the intention of the legislature in enacting the present
                 Arbitration Act. Further, the very fact that Section 9 comes after
                 Section 8 which deals with the reference of disputes to Arbitration,
                 the only interpretation that could be given to Section 9 is that it
                                                                                           B
                 could be availed of when an arbitration proceedings is pending
~
                 before the Arbitral Tribunal or is at the reference stage before the
                 Court or after the Arbitral award has been made."

        While coming to the conclusion that the application under Section 9 of the
        1996 Act before the trial court was misconceived, as no effort had at the          c
        time of filing of such an application, being made by the appellant to have
        an arbitrator appointed, the High Court chose not to consider the merits
        of the trial court's order as in its opinion the trial court had no jurisdiction
        to entertain such an application. Hence these appeals by special leave.

               Under the provisions of the Arbitration Act, 1940, the powers of the        D
        Court to pass interim orders were derived from Section 4l(b) read with
        2nd Schedule to the Arbitration Act, 1940. Mr. Gopal Subramaniam,
        learned senior counsel appearing for the respondent, placed reliance on
        Sant Ram & Co. v. State of Rajasthan and Others, [1997) 1SCC147 wherein
        at page 150 it was observed that "The initiation of pendency of any proceed-
                                                                                           E
        ings in the Coult in relation to the arbitration proceedings would, therefore,
        be a precondition for the exercise of the power by the civil co ult under the
        Second Schedule of the Act." Even if this be the position under the 1940
        Act we still have to examine whether there has been any change in the law
        with the promulgation of The Arbitration and Conciliation Act, 1996.
                                                                                           F
               Prior to the promulgation of the 1996 Act the law on arbitration in
        India was substantially contained in three enactments, namely, The Ar-
        bitration Act, 1940, the Arbitration (Protocol and Convention) Act, 1937
        and the Foreign Awards (Recognition and Enforcement) Act, 1961. In the
        Statement of Objects and Reasons appended to the Bill it was stated that
        the 1940 Act, which contained the general law of arbitration, had become G
        outdated. The said objects and reasons noticed that the United Nations
~

        Commission on international Trade Law (UNCITRAL) adopted in 1985
        the Model Law on International Commercial Arbitration. The General
        Assembly had recommended that all countries give due consideration to
        the said Model Law which, along with the rules, was stated to have H
    96                    SUPREME COURT REPORTS                    [1999) 1 S.C.R.
A   harmonised concepts on arbitration and conciliation of different legal
    systems of the world and thus contained provisions which were designed
    for universal application. The above said Statement of Objects and Reasons
    in para 3 states that "Though the said UNCITRAL Model Law and rnles are
    intended to deal with international commercial arbitration and conciliation,
B they could, with appropriate modifications, serve as a model for legislation
    on domestic arbitration and conciliation. The present Bill seeks to consolidate
    and amend the law relating to domestic arbitration, international commercial
    arbitration, enforcement of foreign arbitral awards and to define the law
    relating to conciliation, taking into account the said UNCITRAL Model Law
    and Rules."
c
          The 1996 Act is very different from the Arbitration Act, 1940. The
    provisions of this Act have, therefore, to be interpreted and construed
    independently and in fact reference to 1940 Act may actually lead to
    misconstruction. In other· words the provisions of 1996 Act have to be
    interpreted being uninfluenced by the principles underlying the 1940 Act.
D   In order to get help in construing these provisions it is more relevant to        "
    refer to the UNCITRAL Model Law rather than the 1940 Act.

          Some of the provisions of the 1996 Act which are relevant in the
    present case are Sections 2( d), 9, 17 and Section 21. Section 2( d) defines
E   an Arbitral Tribunal to mean a sole arbitrator or a panel of arbitrators.
    Section 9 of the_ 1996 Act, which gives power to the Court to pass interim
    orders, and with the interpretation of which we are concerned in the
    present case, reads thus :

             "9. Interim measures by court - A party may, before or during
F            arbitral proceedings or at any time after the making of the arbitral
             award but before it is enforced in accordance with section 36,
             apply to a court :

             (i) for the appointment of a guardian for a minor or a person of
             unsound mind for the purposes of arbitral proceedings; or
G
             (ii) for an interim measure of protection in respect of any of the
             following matters, namely :

              (a) the preservation, interim custody or sale of any goods which·
H             are the subject-matter of the arbitration agreement;
               SUNDARAMFINANCELTD. v. NEPCINDIALTD. [KIRPAL,J.]                      97
                  (b) securing the amount in dispute in the arbitration;                   A
                  (c) the detention, preservation or inspection of any property or
                  thing which is the subject-matter of the dispute in arbitration, or
                  as to which any question may arise therein and authorising for any
                  of the aforesaid purposes any person to enter upon any land or
                                                                                           B
                  building in the possession of any party, or authorising any samples
                  to be taken or any observation ~o be made, or experiment to be
                  tried, which may be necessary or expedient for the purpose of
                  obtaining full information or evidence;

                  (d) interim injunction or the appointment of a receiver;                 c
                  (e) such other interim measure of protection as may appear to the
                  court to be just and convenient,

     ;.
                  and the Court shall have the same power for making order as it D
                  has for the purpose of, and in relation to, any proceedings before
                  it."

          As this section refers to ''Arbitral Tribunaf' the same has to be read along
          with Section 21 which relates to the commencement of the arbitral
          proceedings and reads as follows :                                               E

                   "21. Commencement of arbitral proceedings - Unless otherwise
                   agreed by the parties, the arbitral proceedings in respect of a
                 . particular dispute commence on the date on which a request for
                   that dispute to be referred to arbitration is received by the respon-   F
                   dent."

                The Arbitral Tribunal has also been given jurisdiction to pass interim
          orders by Section 17 of the said Act which reads as follows:

                  "17. Interim measures ordered by arbitral tribunal :                     G
'·    '           (1) Unless otherwise agreed by the parties, the arbitral tribunal
                  may at the request of a party, order a party to take any interim
                  measure of protection as the arbitral tribunal may consider neces-
                  sary in respect of the subject-matter of the dispute.              H
    98                   SUPREME COURT REPORTS                  (1999] 1 S.C.R.

A            (2) The arbitral tribunal may require a party to provide ap-
             propriate security in connection with a measure ordered under
             sub-section (1)."

         The reading of Section 21 clearly shows that the arbitral proceedings
  commence on the date on which a request for a dispute to be referred to
B
  arbitration is received by the respondent. It is in this context that we have
  to examine and interpret the expression "before or during arbitral proceed-
  ings" occurring in Section 9 of the 1996 Act. We may here observe that
  though Section 17 gives the arbitral tribunal the power to pass orders the
  same cannot be enforced as orders of a Court. It is for this reason that
C Section 9 admittedly gives the Court power to pass interim orders during
   the arbitration proceedings.

        The position under the Arbitration Act, 1940 was that a party could
                                                                                            ~
  commence proceedings in Court by moving an application under Section
  20 for appointment of an arbitrator and simultaneously it could move an
D                                                                                           ~
  application for interim relief under the Section Schedule read with Section
                                                                                  ""'
  41(b) of the 1940 Act. The 1996 Act does not contain a provision similar
  to Section 20 of the 1940 Act. Nor is Section 9 or Section 17 similar to
  Section 41(b) and the Second Schedule to the 1940 Act. Section 8 of the
  new Act is not in pari materia with Section 20 of the 1940 Act. It is only if
E in an action which is pending before the Court that a party applies that the
  matter is the subject of an arbitration agreement does the Court get
  jurisdiction to refer the parties to arb~tration. The said provision does not
  contemplate, unlike Section 20 of the 1940 Act, a party applying to a Court
  for appointing an arbitrator when no matter is pending before the Court.
F Under th_e 1996 Act appointment of arbitrator/s is made as per the              .,-
  provision of Section 11 which does not require the Court to pass a judicial
  order appointing arbitrator/s. The High Court was, therefore, wrong in                    ·-'
  referring to these provisions of the 1940 Act while interpreting Section 9
  of the new Act.

G        Under the 1996 Act the Court can pass interim orders under section-
  9. Arbitral proceedings, as we have seen, commence only when the request        i     /
  to refer the dispute is received by the respondent as per Section 21 of the
  Act. The material words occurring in Section 9 are "before or during the_
  arbitral proceedings". This clearly contemplates two stages when the Court
H can pass interim orders, i.e., during the arbitral proceedings or before the
                  SUNDARAM FINANCE LTD. v. NEPCINDIALTD. [KIRPAL,J.]                 99

       ·~    arbitral proceedings. There is no reason as to why Section 9 of the 1996 A
             Act should not be literally construed. Meaning has to be given to the word
             "before" occurring in the said section. The only interpretation that can be
             given is that the Court can pass interim orders before the commencement
             of arbitral proceedings. Any other interpretation, like the one given by the
             High Court, will have .the effect of rendering the word "before" in Section
             9 as redundant. This is clearly not permissible. Not only does the language
                                                                                           B
             warrants such an interpretation but it was necessary to have such a
             provision in the interest of justice. But for such a provision no party would
             have a right to apply for interim .measure before notice under Section 21
             is received by the r.espondent. It is not unknown when it becomes difficult
             to serve the respondents. It was, therefore, necessary that provision was    c
             made in the Act which could enable a party to get interim relief urgently
             in order to protect it's interest. Reading the section as a whole it appears
             to us that the Court has jurisdiction to entertain an application under
             Section 9 either before arbitral proceedings or during arbitral proceedings
             or after the making of the arbitral award but before it is enforced in
_,,   ...                                                                                  D
             accordance with Section 36 of the Act.

                 Section 9 of the said Act corresponds to Article 9 of the UNCITRAL
             Model Law which is as follows :

                     "It is not incompatible with an arbitration agreement for a party    E
                     to request, befpre or during arbitral proceedings, from a court an
                     interim measure of protection and for a court to grant such
                     measure."


      .,..   This article recognises, just like Section 9 of the 1996 Act, a request being F
             made before a Court for an interim measure of protection before arbitral
             proceedings. It is possible that in some countries if a party went to the
             Court seeking interim measure of protection that might be construed under
             the local law as meaning that the said party had waived its right to take
             recourse to arbitration. Article 9 of the UNCITRAL Model Law seeks to
             clarify that merely because a party to an arbitration agreement requests the G
             Court for an interim measure "before or during arbitral proceedings" such
             recourse would not be regarded as being incompatible with an arbitration
             agreement. To put it differently the arbitration proceedings can i::ommence
             and continue notwithstanding a party to the arbitration agreement having
             approached the Court for an order for interim protection. The language H
    100                   SUPREME COURT REPORTS                  (1999] 1 S.C.R.
A of Section 9 of the 1996 Act is not identical to Article 9 of the UNCITRAL
    Model Law but the expression "before or during arbitral proceedings" used
    in Section 9 of the 1996 Act seems to have been inserted with a view to
    give it the same meaning as those words have in Article 9 of the UN-
    CITRAL Model Law. It is clear, therefore, that a party to an arbitration
    agreement can approach the Court for interim relief not only during the
B   arbitral proceedings but even before the arbitral proceedings. To that
    extent Section 9 of the 1996 Act is similar to Article 9 of the UNCITRAL
    Model Law.

          It will also be useful to refer to a somewhat similar provision in the
C Arbitration Act, 1996 of England. Section 44 of this Act gives the Court
  powers which are exercisable in support of the arbitral proceedings. Sub-
  section (3) of Section 44 permits, in the case of urgency, the Court to make
  an order contemplated by sub-section (2) even on an application by a
  ''proposed party to the amitral proceedings". The expression used in this sub-
D section ''party or proposed party to the arbitral proceedings" shows that where
  arbitral proceedings have commenced then the application will obviously
  be of a party to the said proceedings but where the arbitral proceedings
  have not commenced a ''proposed party" has been given the right to ap-
   proach the Court. A proposed party to the arbitral proceedings would,
   therefore, be one who is party to an arbitration agreement and where
E disputes have arisen but the arbitral proceedings have not commenced.
   While referring to Section 44 of the English Act in ddi'ling with the
   question of grant of interim injunctions in support of arbitral proceedings
   Russell on Arbitration (21st Edition) at page 386 has stated as under :

F            "The Court may exercise its power to grant an interim injunction
             before there has been any request for arbitration or the appoint-
             ment of arbitrators, provided that the applicant intends to refer
             the dispute to arbitration in due course.

G            The power to grant an interim injunction under Section 44 of the
             Act extends to the granting of a Mareva injunction in appropriate
             cases. It may also include granting an interim mandatory injunc-
             tion, although the court will be slow to grant an injunction which
             provides a remedy of essentially the Sjlme kind as is ultimately
H            being sought from the arbitral tribunal.
          SUNDARAMFINANCELTD. v. NEPCINDIALTD. [KIRPAL,J.]                     101
.,         In our opinion this view correctly represents the position in law,         A
     namely, that even before the commencement of arbitral proceedings the
     Court can grant interim relief. The said provision contains the same
     principle which underlies Section 9 of the 1996 Act.

           Our attention was also drawn to the case of (171e Channel Tunnel
~    Group Ltd. and France Manche SA. v. Balfour Betty Constrnction Ltd. and          B
     Others, [1992) 2 Lloyd's Law Reports) dealing with question of the juris-
     diction of the England' Court to grant an interim injunction in a case where
     the parties have agreed that the disputes shall be settled by arbitration. The
     Court of Appeal referred to Section 12 (6) of the Arbitration Act, 1950
     which provided as follows :                                                      c
             "The High Court shall have, for the purpose of and in relation to
             a reference, the same power of making orders in respect of - (h)
             interim injunctions or the appointment of a receiver; as it has for
             the purpose of and in relation to an action or matter in the High
             Court... ..                                                              D

     Construing this Staughton L.J observed as under :

             "In my view this power cai:t be exercised before there has been any
             request for arbitration or the appointment of arbitrators, provided
                                                                                      E
             that the applicant intends to take the dispute to arbitration in due
             course. Whatever the meaning of "reference" to s.12(6)(h) (and it
             is not always_ easy to determine the precise meaning of the word
             in arbitration_ statutes) I would hold that the power of the Court
             in such a case would be exercised for the purpose of and in relation
             to a reference."                                                         F

     We are in respect agreement with the aforesaid observations which are in
     conformity with the view which we have taken in construing Section 9 of
     the 1996 Act.

           It was submitted by Mr. Subramaniam that even if the Court can             G
     exercise jurisdiction under Section 9 before the arbitral proceedings have
'    commenced the party seeking to invoke Section 9 must express a manifest
     intention to arbitrate. The learned counsel submitted that this intention can
     take the following forms : (a) In an application under Section 9, the party
     would have to state that it unequivocably relies on the arbitration agree-       H
    102                   SUPREME COURT REPORTS                  (1999] 1 S.C.R.
                                                                                    ~
A   ment and makes an averment that it would invoke the arbitration clause;
    (b) At the time when the Court passes an interim order under Section 9,
    an express undertaking is given by the party before the Court that it would
    invoke the arbitration clause forthwith and within a fixed period; and ( c)
    a notice invoking arbitration clause should have been issued k the opposite
    party. It was contended that mere filing of an application Ul).der Section 9
B   was not sufficient to establish manifest intention to this extent.              ,,
         When a party applies under Section 9 of the 1996 Act it is implicit
  that it accepts that there is a final and binding arbitration agreement in
  existence. It is also implicit that a dispute must have arisen which is
c referable to the arbitral tribunal. Section 9 further contemplates arbitration
  proceedings taking place between the parties. Mr. Subramaniam is, there-
  fore, right in submitting that when an application under Section 9 is filed
  before the commencement of the arbitral proceedings there has to be
  manifest intention on the part of the applicant to take recourse to the
D arbitral proceedings if, at the time when the application under Section 9 is
  filed, the proceedings have not commenced under Section 21 of the 1996
  Act. In order to give full effect to the words "be/ore or during arbitral
  proceedings" occurring in Section 9 it would not be necessary that a notice
  invoking the arbitration clause must be issued to the opposite party before
  an application under Section 9 can be filed. The issuance of a notice may,
E iri a given case, be sufficient to establish the manifest intention to have the
  dispute referred to arbitral tribunal, but a situation may so demand that a
  party may choose to apply under Section 9 for an interim measure even
  before issuing a notice contemplated by Section 21 of the said Act. If an
  application is so made the Court will first have to be satisfied that there
F exists a valid arbitration. agreement and the applicant intends to take the       T
   dispute to arbitration. Once it is so satisfied the Court will have the
  jurisdiction to pass orders under Section 9 giving such interim protection
   as the facts and circumstances warrant. While passing such an order and
   in order to ensure that effective steps are taken to commence the arbitral
   proceedings, the Court while exercising jurisdiction under Section 9 can
G pass conditional order to put the applicant to such terms as it may deem
   fit with a view to see that effective steps are taken by the applicant for
   commencing the arbitral proceedings. What is apparent, however, is that
                                                                                    1
                                                                                         ~
   the Court is not debarred from dealing with an application under Section
   9 merely because no notice has been issued under Section 21 of the 1996
H Act.
         SUNDARAMFINANCELTD. v. NEPCINDIALTD.[KIRPAL,J.]                 103

      There is another aspect which calls for our attention. Section 82 of      A
the 1996 Act gives the High Court power to make rules consistent with the
Act. We were informed that all the High Courts have not so far made rules.
Whereas the Section 84 gives the Central Government power to make rules
to carry out the provisions of the Act, the High Court should also, wherever
necessary, make rules. It would be helpful if such rules deal with the
procedure to be followed by the Courts while exercising jurisdiction under
                                                                                B
Section 9 of the Act. The rules may provide for the manner in which the
application should be filed, the documents which should accompany the
same and the manner in which such applications will be dealt with by the
Courts. The High Courts are, therefore, requested to frame appropriate
rules as expeditiously as possible so as to facilitate quick and satisfactory   c
disposal of arbitration cases.

      In view of the aforesaid discussions it follows that the High Court
erred in coming to the conclusion that the trial court had no jurisdiction
in entertaining the application under Section 9 because arbitration
proceedings had not been initiated by the appellant.                            D
      We accordingly set aside the judgment of the High Court but as the
High Court has not considered the merits of the case, it is directed that
the petition filed by the respondent, challenging the order of the Trial
court, be decided on merits. The appeals are disposed of accordingly.
There will be no order as to costs.                                             E

v.s.s.                                                 Appeals disposed of.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.