TAMIL NADU ELECTRICITY BOARD AND ANR.versusN. RAJU REDDIAR AND ANR.
- Citation
- 1996 INSC 582
- Decided
- 24 April 1996
- Disposal
- Appeal(s) allowed
- Bench
- K RAMASWAMY
Holding
A written contract governs its terms; no oral evidence or later insertions can vary those terms, and the handwritten addition was a subsequent interpolation, so payment is on a single‑slab basis.
Summary
The respondents (plaintiffs) sued the T.N. Electricity Board for Rs. 46,08,820, claiming that the freight rates for transporting iron and steel were to be paid on a multi‑slab basis as indicated in a handwritten addition to a letter appended to their tender. The High Court Division Bench accepted this claim, holding that the handwritten portion was part of the contract and that the conduct of some Superintending Engineers, who had passed bills on a multi‑slab basis, supported the claim. The Supreme Court held that the contract was a written agreement and, under Sections 91 and 92 of the Evidence Act, 1872, oral evidence or later insertions cannot vary its terms. It found that the handwritten addition was a subsequent interpolation lacking any signature and that no documentary evidence showed the parties agreed to a multi‑slab rate. Consequently, the claim for multi‑slab payment failed and the decree of the Single Judge (single‑slab basis) was affirmed, setting aside the Division Bench’s decision.
Issues considered
- The handwritten portion of the letter appended to the tender – whether it formed part of the contract or was a later interpolation.
- Whether oral evidence or post‑tender discussions can be admitted to vary the terms of a written contract under the Evidence Act.
- Whether the conduct of Superintending Engineers in passing some bills on a multi‑slab basis creates an estoppel or right to such payment.
- Whether the freight rates under the contract were to be calculated on a multi‑slab or single‑slab basis.
Legislation cited
- Indian Evidence Act, 1872s. 91, s. 92
Subjects
Judgment
TAMIL NADU ELECTRICITY BOARD AND ANR. A
v.
N. RAJU REDDIAR AND ANR.
APRIL 24, 1996
[K. RAMASWAMY AND G.B. PATTANAIK, JJ.] B
Evidence Act, 1872-Ss. 91, 92-Written agreement-Proof of-Where
agreement contains whole tenns of the contract-Parties not entitled to lead
oral or other documentary evidence ascertaining intention of parties.
The respondents-plaintiffs filed a suit for recovery of a sum of Rs.
c
46,08,820 with interest alleging that the defendants· appellants invited
tenders for transportation of iron and steel materials; that the Plaintiff 1
submitted his tender, his offer was accepted and an agreement was entered
into; that the plaintiffs carried the material and delivered the same at
various destinations but when bills were submitted, the defendants instead D
of making payments in accordance with the terms of the contract
postponed the payment of the bills.
The defendants in their written statement stated that the plaintiffs
were not entitled to claim multi slab basis as the multi slab rates had never E
been accepted and not covered by the agreement executed by the parties
and the plaintiffs raised this issue only after the contract was over and
that the plaintiffs had not delivered the materials correctly at some des·
tinations.
Single Judge of the High Court held that rates ,,;n have to be F
calcnlated on single slab basis and not on multi slab basis and that the
words in the letter enclosed to the tender form, written in ink as 'I have
c1uoted my rates for each slab and add for every extra one and part thereof,
were there at the time of submission of the tender but the expression 'for
each slab' did not mean that the tender was not on multi slab basis and
that the shortages alleged by the defendants had not been established. G
While holding that there was considerable delay in the matter of payment
of bills, the suit was decreed in part. In appeal the Division Bench of the
High Court relying upon the hand written portion of the letter and the
conduct of the Superintending Engineer in passing the plaintiff's bills on
multi slab basis helct that the plaintiffs were entitled to freight charges on H
739
740 SUPREME COURT REPORTS [1996] SUPP.1 S.C.R.
A multi slab basis. Hence this appeal.
The appellants contended that the hand written portion in the
plaintill's letter was a subsequent interpolation; that the acceptance of the
tender by the contractor indicated that it was on single slab basis; that the
bills were submitted during the extended period of the contract which
B indicated an obvious illegal design and that passing of some bills by some
of the Superintending Engineers on multi slab basis was not determinative
of the terms and conditions of the contract particularly when the contract
was a written one.
c whetherThehand
respondents urged that there was no issue on the question as to
written portion was subsequently inserted; that after sub-
mission of the tender, the contractor explicitely expressed to have the work
done on multi slab basis and that the defendants in fact accepted and acted
on multi slab basis and that the single slab system was on the face of it
wholly unreasonable.
D
Allowing the appeal, this Court
HELD : 1.1. The agreement between the parties was a written agree-
ment and therefore the parties were bound by the terms and conditions of
the agreement. Once a contract is reduced to writing, by operation of
E Section 91 of the Evidence Act it is not open to any of the parties to seek
to prove terms of the contract with reference to some oral or other
documentary evidence to find out the intention of the parties. Under
Section 92 of the Evidence Act where the written instrument appears to
contain the whole terms of the contract then parties to the contract are
F not entitled to lead any oral evidence to ascertain the terms of the contract.
It is only when the written contract does not contain the whole of the
agreement between the parties and there is any ambiguity then oral
evidence is permissible to prove the other conditions which also must not
be inconsistent with the written contract. In the instant case the plaintiffs
being conscious of this position along with the tender appended a letter
G and in that letter inserted certain terms by writing in ink to establish the
case that the acceptance of the plaintiffs' tender would tantamount to the
acceptance to the terms contained in the letter in which there was insersion
in writing to the effect that it was on multi slab basis. This question as to
whether such hand written portion was originally there or was sub-
H sequently inserted was considered by the trial Judge and a finding was
T.N. ELECTRICITY BD. v. N.R. REDDIAR 741
given in favour of the plaintiffs. The said finding, however, on the face of A
it appeared to be wholly unsustainable. There was no signature either by
the persons submitting the tender or by the persons receiving the same on
the hand wr_itten portion of the letter. The trial Judge had noticed that the
certified copy which was issued by the Board on 11.7.1978 of the aforesaid
letter clearly contained the hand written portion and therefore he came to
the conclusion that the hand written portion was there at the time of
B
submission of the tender. The tender itself was submitted on 12.7.1978 and
how the Board could grant a certified copy of the letter on 11.7.1978 when
the plaintiffs' case itself was that along with the tender he had appended
the letter in c1uestion. Therefore, hand written portion was not there at the
time of submission of the tender but was subsequently inserted obviously c
with the connivance of the officers of the Board. The Board in its rejoinder
affidavit filed in this court had stated that the attested copy was actually
received on 28.12.1978, much later than the finalisation of the tenders and
agreement and in order to build up a case the aforesaid interpolation had
been made. In the facts and circumstances of the present case the aforesaid D
stand of the Board was wholly justified and that the hand written portion
was not there initially and bad been inserted subsequently. The main basis
of the plaintiffs' case on which a multi slab rate was claimed therefore fail.
A
The written agreement between the parties nowhere indicated that the
rate to be paid to the plaintiffs was on multi slab basis and the terms
and conditions of the written contract was not snsceptible of such a E
construction. [747-D-H; 748-A-E]
1.2. DW-1 as witness of the defendants in his evidence bad admitted
that after snbmission of tender there was certain discussions between the
contractor and the authorities and in that discussion contractor had p
expressed to charge for the job on multi slab basis and same was accepted
by the authorities. A decree could not be granted in favour of the plaintiffs
on the aforesaid statement since the contract in hand was a written one.
There was no document whatsoever in support of the aforesaid so called
'after tender discussion' and the acceptance of the terms in the said
discussion to the effect that rate would be charged on multi slab basis. G
Then again if the plaintiff had appended the letter to the tender indicating
that he would be charging on multi slab basis there was no occasion to
have any 'after tender discussion' or to raise the issue of rate being
'accepted on multi slab basis. The so called statement of DW-1 therefore
was wholly unacceptable and could not be taken into account to vary the H
742 SUPREME COURT REPORTS [1996] SUPP. 1 S.C.R.
A terms of the written contract [747F-H; 748-A]
1.3. Some of the Superintending Engineers passed some of the bills
on multi slab basis and further when complaints were received and the
matter was investigated into by vigilance to absolve the concerned otlicers
from liability, a recommendation had been made to grant the rate on multi
B slab basis. But such a recommendation or such passing of bills on one
count on multi slab basis could not be construed to have conferred a right
on the plaintiffs to get the payments on multi slab basis, until and unless
it was proved by the plaintiff that the defendants agreed under the written
contract to pay on multi slab basis. The plaintiffs had utterly failed to
C establish the same. [748-C-E]
CIVIL APP~LATE JURISDICTION : Civil Appeal No. 7496 of
1996.
From the Judgment and Order dated 6.9.95 of the Madras High
D Court in O.S.A. No. 112 of 1987.
V.R. Reddy, Additional Solicitor General and A. Mariarputham for
the Appellants.
S. Sivasubramaniam and V. Balachandran for the Respondents.
E
The Judgment of the Court was delivered by
PATIANAIK, J. Leave granted.
This appeal by special leave is directed against the Judgment of the
F Division Bench of the Madras High Court dated 6.9.1995 in O.S.A. No. 112
of 1987. The palintiffs who are the respondents in this appeal filed the suit
on the original side of the High Court for recovery of a sum of Rs. 46,08,820
together with interest at 18% per annum. It was alleged in the plaint that
the defendants who are appellants in this appeal invited tenders for
transportation of iron and steel materials including unloading, weighment
G and stocking from various stockyards of the suppliers to the destination
stores during the period 1.9.1978 to 31.8.1979. In pursuance of the aforesaid
advertisement the Plaintiff No. 1 submitted his tender on 12.7.1978 and
along with tender submitted, a letter was also enclosed. This offer of the
plaintiff was accepted and an agreement was entered into. In accordance
H with the agreement the plaintiff furnished a bank guarantee and deposited
T.N. ELECTRICITY BD. v. N.R. REDDIAR [PATTANAIK,J.] 743
the necessary earnest money and commenced the work of transport of A
materials. It was further alleged that the palintiffs carried the material and
di;livered the same at various destinations as per the direction given from
time to time by the defendants. In all a total quantity of 1, 73, 78, 821 metric
tonnes of iron and steel were transported and the necessary bills were
submitted in November, 1979. But the defendant instead of making the B
payments in accordance with the terms of the contract postponed the
payment of the bills. It was averred in the plaint that the defendant agreed
to pay no on multi slab basis which is apparent from letter of the plaintiff
attached to the tender submitted by him and that was also the trade
practice. The plaintiff finally issued a notice on 28.3.1980 calling upon the
defendants to settle the bills but the defendants replied on 7.5.1980 making C
several misleading averments. As the plaintiffs' bills were not settled, the
suit was filed for recovery of the amount as already stated.
The defendants in their written statement denied the allegations
made in the plaint. The specific stand taken in the written statement was D
that the plainiffs are not entitled to claim multi slab basis and on the other
hand they are entitled to single slab basis. It was stated that the multi slab
rates had never been accepted and not covered by the agreement executed
by the parties. It was also stated that on the basis of instructions from
headquarters the Superintending Engineer5 have been passing the bills on
E
single slab basis and the plaintiffs remained silent during the entire tenure
of the contract period but raised this issue after the contract period was
over. The defendant further averred that the plaintiffs have not delivered
the materials correctly at some destinations. In reply to the aforesaid
written statement the plaintiffs also filed a reply statement denying the
allegations made in the written statement and reiterated the stand taken in F
the plaint. On these pleadings the learned Single Judge framed three issues
and on Issue No. 1 came to hold ,, that the rates mentioned in Exhibit D-8
will have to be calculated on single slab basis and not on multi slab basis
as contended by the plaintiffs. So far as the letter Exhibit P-1 dated
11.7.1978 which was enclosed to the tender from Exhibit P-2, the learned G
Single Judge negatived the contention of the defendant and came to hold
that the words written in ink in Exhibit P-1 were ai the time of submission
of the tender. The words were "! have quoted my rates for each slab and
add for every extra one and part thereof'. The plaintiffs' case is essentially
based on the aforesaid expression in the letter which was enclosed to the H
744 SUPREME COURT REPORTS [1996\ SUPP.1 S.C.R.
A tender and which according to the plaintif!S was ultimately accepted. The
learned Single Judge, however, construed the expression "for each slab"
mentioned in Exhibit D-6 and came to hold that the tender was not on
multi slab basis. The learned Judge also held that merely because the
tender conditions are not clear one cannot accept the contention of the
B plaintiff that the rates agreed upon is on multi slab basis. Further taking
into account the terms and conditions of Exhibit D-1 the learned Judge
came to hold that the irresistible conclusion is that what was intended is
only a single slab basis. The learned Judge also examined several other
tenders and then negatived the plaintifrs contention that the agreement
was on multi slab basis. On an analysis of the pattern of the working of the
C rates in several tenders the learned Judge rejected the plaintiffs' contention
that the contract was on multi slab basis. Though the plaintiffs relied upon
several recommendations of the Superintending Engineer but the learned
Judge on consideration of the same came to hold that those recommenda-
tions will have to be rejected. It was also held that the terms and conditions
D of a contract have to be decided on its own and production of other
contracts will not be of any help in deciding what are the terms of the
present contract. He also held that the defendants failed to produce any
other contemporarious contract which has been granted on multi slab basis.
On issue No. 2 the learned Singler
Judge on
.
consideration of entire evidence
E on record came to hold that the shortages alleged by the defendants had
not been established. On Issue No. 3 the learned Single Judge came to hold
that there is considerable delay in the matter of payment of bills though
such delay had occasioned on account of difference in the interpretation
of the terms of the contract and the delay is on the part of the defendants
in settling the bills. With these conclusions and on calculating on single slab
F
basis the learr.ed Single Jugde passed a decree for Rs. 9,31,157.63 witb
interest at 12% per annum from 1.1.1980 till the date of decree and
thereafter at 6% per annum. The suit was thus decreed in part. The
plaintiffs challenged the decree by filing an appeal and the defendants also
filed a cross-objection challenging that part of the decree in favour of the
G plaintiffs. The Division Bench of the High Court relying upon the hand
written portion of Exhibit P-1 and the conduct of the Superintending
Engineer in passing the palintiffs' bills on multi slab basis as well as relying
upon some other contracts came to hold that the plaintiffs are entitled to
freight charges on multi slab basis. The Division Bench also held that the
H interpretation of the learned Single Judge of the expression 'for each slab'
T.N. ELECTRICITYBD. v. N.R. REDDIAR [PATTANAIK,J.] 745
is wholly erroneous and it could only mean that the rate was on multi slab A
basis. With these conclusions the Division Bench allowed the plaintiffs'
appeal and dismissed the defendant's cross-objection and hence the
present appeal by the special leave.
Mr. V.R. Reddy, the learned Additional Solicitor General appearing
for the appellants contended that the hand written portion in the plaintiffs
B
letter Exhibit P-1 dated 11.7.1978 which was enclosed to the tender form
Exhibit P-2 is nothing but a subsequent interpolation inasmuch as neither
there is any signature either of the plaintiff or of the receiving officer on
the same and further it was really astonishing that though the tender was
submitted on 12.7.1978 but according to the plaintiff an attested copy of C
the letter could be obtained from the departmental officer on 11.7.1978.
Mr. Reddy further argued that the acceptance of the tender by the con-
tractor clearly indicates that it was on single slab basis as the nute to the
same states "only one rate should be quoted for various lengths and sizes
and not different rates for different lengths". Mr. Reddy further urged that D
the very fact that the plaintiffs did not submit any bills till the end of the
contract period and started .to submit the bills during the extended period
of the contract would indicate that with an obvious illegal design the bills
were not being submitted in time. Repelling the reasonings advanced by
the Division Bench of the High Court Mr. Reddy urged that passing of
some bills by some of the Superintending Engineers on multi slab basis is E
not determinative of the terms and conditions of the contract particularly
when the contract is a written one and consequently the Division Bench
erred in law that the contract was on multi slab basis.
We find sufficient force in each of the contentions advanced by th.e F
learned counsel for the appellants.
Mr. Sivasubramanaim, the learned senior counsel appearing for the
respondents, repelling the contentions advanced by Mr. Reddy urged that
there was no issue at all on the question as to whether hand written portion
was subsequently inserted with the connivance of the officers of the Board G
·and therefore it would not be appropriate for this Court to interfere with
the same at this stage. The learned counsel also contended that the very
admission of DW-1, one of the witnesses of the defendants to the effect
that after submission of the tender, discussions were made with the con-
tractor and the contractor eXplicitely expressed to have the work done on H
746 SUPREME COURT REPORTS {l996J SUPP. 1 S.C.R.
A multi slab basis, clinches the matter and it is not open for the defendants
to give a go bye to the said admission of the witness. The learned counsel
also urged that the defendants in fact accepted and acted on multi slab
basis as is apparent from the letter Exhibit P-39 dated 18.4.80 from the
Superintending Engineer, General Construction Circle/South. Tirunelvalli
to the Chief Engineer, Materials Management, whereunder not only the
B
Superintending Engineer has candidly admitted that the system of payment
of multi slab basis has been in vogue in several circles but also stated that
the single slab system will not give a workable practical solution. Learned
counsel lastly urged that the single slab system is on the face of it wholly
unreasonable and to SU$lain the said argument placed before us certain
c calculations made in different documents. We arc unable to persuade
ourselves to agree with the contentions advanced by the learned counsel
for the respondents.
At the outset it must be borne in mind that the agreement between
D the parties was written agreement and therefore the parties are bound by
the terms and conditions of the agreement. Once a contract is reduced to
writing, by operation of Section 91 of the Evidence Act it is not open to
any of the parties to seek to prove the terms of the contract with reference
to some oral or other documentary evidence to find out the intention of
the parties. Under Section 92 of the Evidence Act where the written
E instrument appears to contain the whole terms of the contract then parties
to the contract are not entitled to lead any oral evidence to ascertain the
terms of the contract. It is only when the written contract does not contain
the whole of the agreement between the parties and there is any ambiguity
then oral evidence is permissible to prove the other conditions which also
F must not be inconsistent with the written contract. The case in hand has to
be adjudged bearing in mind the aforesaid principles and the plaintiffs
being conscious of this position along with the tender appended a letter
and in that letter inserted terms bv writing in ink to establish the case that
the acceptance of the plaintiffs' tender would tantamount to lhe acceptance
to the terms contained in the letter in which there was insersion is writing
G to the effect that it was on multi slab basis. It is in this context the question
whether such hand written portion was originally there or was subseqnently
inserted assumes great significance. We are unable to accept the stand
taken by the learned counsel for the respondents that there was not such
issue on this question inasmuch as this question was considered by the
H learned Trial Judge while discnssing Issue No. 1 on the basis of evidence
T.N.ELECTRICITYBD.v. N.R. REDDIAR [PATTANAIK,J.] 747
laid and the Trial Judge had given a finding in favour of the plaintiffs. The A
said finding, however, on the face of it appears to us to be wholly unsus-
tainable. As has been stated earlier there was no signature either by the
persons submitting the tender or by the persons receiving the same on the
h•nd written portion of the letter. The learned Trial Judge had noticed that
the certified copy which was issued by the Board on 11. 7.1978 of the
aforesaid letter clearly contains the hand written portion and therefore he
B
came to the conclusion that the hand written portion was there at the time
of submission of the tender. The tender itself was submitted on 12.7.1978
and we fail to understand how the Board could grant a certified copy of
the letter on 11.7.1978 when the plaintiffs' case itself is that along with the
tender he had appended the letter in question. On this ground alone it can C
be safely held that hand written portion in Exhibit P-1 was not there at the
time of submission of the tender but was subsequently inserted obviously
with the connivaces of the officers of the Board. The Board in its rejoinder
affidavit filed in this Court has stated that the attested copy was actually
received on 28.12.1978, much later than the finalisation of the tenders and D
agreement and in order to build up a case the aforesaid interpolation has
been made. In the facts and circumstances of the present case the aforesaid
stand of the Board appears to us to be wholly justified and at any rate we
have no hesitation to come to the conclusion that the hand written portion
in Exhibit P-1 was not there initially and has been inserted subsequently.
The main basis of the plaintiffs' case on which a multi slab rate was claimed E
therefore fails. The written agreement between the parties nowhere indi-
cates that the rate to be paid to the plaintiffs was on multi slab basis. and
the terms and conditions of the written contract is not susceptible of such
a construction.
F
It is no doubt true that DW-1 a witness of the defendants in his
evidence had admitted that after submission of tender there was certain
discussions between the contractor and the authorities and in that discus-
sion contractor had expressed to charge for the job on multi slab basis and
same was accepted by the authorities. We are afraid a decree cannot be
granted in favour of the plaintiffs on the aforesaid statement since the G
·contract in hand was a written one. There is no document whatsoever in
support of the aforesaid. so called after tender discussion and the accep-
tance of the terms in the said discussion to the effect that rate would be
charged on multi slab basis. Then again if the plaintiff had appended the
letter to the tender indicating that he would be charging on mnlti slab basis H
748 SUPREME COURT REPORTS [1996[ SUPP.1 S.C.R.
A there was no occasion to have any after tender discussion or to raise the
issue of rate being accepted on multi slab basis. The so called statement
of DW-1 therefore is wholly unacceptable and in the eye of law also cannot
be taken into account to vary the terms of the written contract. The
Division Bench of the High Court committed obvious error in allowing
variance of the terms of written contract relying upon such statement of
B DW-1 and granted the decree on multi slab basis.
The only other question which survives for consideration is whether
the conduct of some of Superintending Engineers in passing some of the
bills on multi slab basis can be pleaded as an estoppcl against the defen-
c dants and can form the basis of plaintiffs' case. The answer to this question
must be in the negative. It transpires that some of the Superintending
Engineers passed some of the bills on multi slab basis and further when
complaints were received and the matter was investigated into by vigilance
to absolve the concerned officers from liability, a recommendation has
D been made to grant the rate on multi slab basis. But such a recommenda-
tion or such passing of bills on one count or multi slab basis cannot be
construed to have conferred a right on the plaintiffs to get the payments
on multi slab basis, until and unless it is provided by the plaintiff that the
defendants agreed under the written contract to pay on multi slab basis.
The plaintiffs have utterly failed to establish the same. A particular officer
E for various reasons may pass a bill on multi slab basis or a contractor may
be able to get one of his bills passed at a rate other than the rate given in
written contract in connivance with the passing authority. But when a
dispute arises and the matter comes to court for adjudication no decree
can be granted to the plaintiffs on that basis and the plaintiffs would be
F required to establish that the defendants in written contract agreed to grant
the rate on multi slab basis. That has not been establish in the case in hand.
Therefore, in our considered opinion the Division Bench of the High Court
wholly erred in law in allowing the plaintiffs' appeal and granting that
decree accepting plaintiffs' claim that the rate has to be paid on. multi slab
basis. In the aforesaid premises the impugned judgment and decree of the
G Division Bench is set aside and that of the learned Single Judge is affirmed.
This appeal is allowed, but in the circumstance-' there will be no order as
to costs.
R.A. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.