Created byFuzzy Cloud

Supreme Court of India

TARAPORE & COMPANYversusCOCHIN SHIPYARD LTD. COCHIN & ANR.

Citation
1984 INSC 55
Decided
6 March 1984
Disposal
Appeal(s) allowed

Holding

A specific question of law referred to the arbitrator is binding on the parties, and the award cannot be set aside on the ground of an apparent error of law; the compensation claim is covered by the arbitration clause.

Summary

Tarapore & Co. entered into a works contract with Cochin Shipyard Ltd. for the construction of a building dock, which included a clause (Clause 40) referring all disputes to a sole arbitrator. The contractor later claimed compensation for the increased cost of imported pile‑driving equipment and technical know‑how, and the dispute was referred to the arbitrator, who awarded Rs. 99 lakhs with interest. The respondent challenged the award on the grounds of insufficient stamp duty and alleged that the arbitrator exceeded his jurisdiction by mis‑interpreting Clause 40. The High Court set aside the award, but the Supreme Court held that the parties had specifically referred a question of law concerning the arbitrator's jurisdiction to the arbitrator, making his decision binding and not subject to being set aside on the basis of an apparent error of law. The Court also found that the compensation claim fell within the wide‑ranged arbitration clause. Consequently, the appeal was allowed, the High Court’s order was reversed, and the award was restored as a rule of the court.

Issues considered

  • Whether a specific question of law referred to an arbitrator is binding on the parties and precludes the court from setting aside the award on the ground of an apparent error of law.
  • Whether the claim for compensation for the increase in cost of imported pile‑driving equipment and technical know‑how is covered by Clause 40 of the General Conditions of Contract.
  • Whether the award was insufficiently stamped under the Kerala Stamp Act.
  • Whether the arbitrator exceeded his jurisdiction by misconstruing Clause 40.

Legislation cited

Subjects

ArbitrationSpecific question of lawJurisdiction of arbitratorAward set‑asideError of law apparent on the faceWorks contractCompensation claimClause 40Without prejudiceStamp duty

Judgment

           i18
  A                                 TARAPORE.& COMPANY
                    ·.
                                                   . v,

                         COCHIN SHIPYARD LTD. COCHIN & ANR.
  B
                                             March 6, 1984

                         . [D.A. DBSAI AND 0. CHINNAPPA REDUY, JJ.J                            -~   .

  c
                 Arbitration Act 1940 (Act X of 1940) section 16(/)(c), 30 and 33.
                                     .
                Arbitration-Works conlract~Construction of BNilding Dock and Repair
                                                                                     .
           Dock-Reference _of specific question 'of law to arbitrator-Arbitrator framing
           "issue-Parties agreeing to· issue being decided-=-Award 1f could be set aside on
           ground of error. of law on. face of award.

                 Interpretation:.
 D
               Agreement-Works contracr ·of large magnitude-Over-Simplification of
          clauses impermissib/e.-Agreement predicated upon and agreed fact silllation-
          Situation ceasing to exist-Agreement to that extent rendered irrelevant and
          otiose.

               Words & PhraseJ:
 E
              .'Without prejudice'-Meaning of-'claim arising out of contract'-'Relating
          to the contract'-Meaning of___.;.C/auie 40 General Conditions of Contract.

                The appelJant and the resi;>ondents entered into a contract for the cons-
           truction of Building 1)ock; ·CJ a use 40 _of the General Conditions of Contract
 F        entered into between -the parties, provided that "all questions and dispute\
          relating to the meaning of the Specifications Estimates Instructions, Designs,
          Drawing-----~nd the quality of the workmenship or materials used in tlte
          work or its to any Other questions, claim, right, matter or thing whatsoever in
          any way <irising out_ of or relating to the" contract or otherwise concerning the
          execution whether arising during the progress of the work or ofter completion-
          ---shall ·be-referred to the Sole Arbitrator etc~" During the. implefilentation
 G        of the works contract, disputes arose between the parti~s-in respect of a ~laim
          for compensation on account of the increase in the cost of imported pile-d~iving
          equipment and teclmic31 know-how fees. Correspondence was exchanged 'bet·
          ween the Appellant and Respondent No. 1 and the dispute was referred to the
          Sole Arbitrator. The polnt referred were: (1) Whether the c1airn of compen·
          sation for increase in the cqst of im-portcd pile driving equipinent and technical
          know-bow fees would fall within the purview of the first para of clause 40 of the
.ff       General .Conditions of COntract ; and (2), if it does, the quantum of con1pen-       .,
          sati~n. if aQy~ to which the appeUallt would be ·entitled to. The arbitrator
          entered upon the reference and after· hearing the parties. gave bis award. The

      •
                                                     •


               TARAPORE CO. JI. COCHIN SHIPYARD                                 119
arbitrator hel,d that the appellant was entitled to compensation for the increase
in the cost of in1ported pile drawing equipment and technical know-how fees by
a sum of Rs. 99 lakhs which amount shall be payable with interest@ 9'J/2%
The award was typed orl stamp paper of the value of Rs. 150/-. The arbitratC!r
forwarded the award to both the parties .

    . The appellant moved 3. petition under'sections 14 and 17 of the Arbitration
Act, in the Court.Of the Sub.orCinate Judge for filing the award and for making         B
it a rule of the Court, while the respondent moved a petition ,under sections 30
and 33 for setting aside the award contending that: (-1) the aw"ard was insuffi-
ciently stamped, and (2) the arbjtrator had exceeded his jurisdiction by miscon..
struing clause 40. The s'ubordinate Judge negatived both the coil.tentions. Jt.
was held that the respondent having submitted the question ,..,hether the dispute
raised by the appellant was covered by the arbitration clituse ; could not con-
trovert the jurisdiction of the Arbitrator to decide the dispute ; and the aw~rd of     c
the arbitrator was modified in the matter of interest frOm 9'1 /2 per "cent as awar-
ded by the ar'Qitrator to 6 per cent, and the award was made a fuie of the
Court.

     The respondent preferred an appeal to the Rish Court, and a Division
Bench, agreed· with the Subordinate Judge on the question of insufficiency of
stamp. It however held that the question ·whether th~ dispute was arbitrable or         D
not could not be finally decided ~Y the arbitrator because it was a matter relating
to-his jurisdiction, and that the arbitrator cannot by an erroneous interpretation
or construction of the ~clau:e confer jurisdiction on himself and that the court
can go into the qµestion whether the matter in dispute between the parties was
covered by the arbitration clause_. It finally held tha,t even though the arbitration
clause was very wide, the dispute as to compensation for increase in the cost of
impo_rted pile diiving equipment and technic3.I know-how fees could not be cove-
                                                                                        ·E
red by the arbitration clause because under clause 26 every plant, machinery
and equipment had to be provided by the contractor and any ·rise or escalation
in the price Of suCh equip!nent or machinery, cannot be the subject matter of
compensation. by the respondent. The apt)e_al wai therefore allowed, and,.the
trial court's order, ma_kiog the award a rule of the court was set aside and
dir~ted that the award be returned to the parties.                                       F
     In. the appeal to this Court it was contended on beh'l)f of the appellant,
that though Sec. 16( l)(e) of the Arbitrlllion Act may permit the court to remit
or set aside-the award on the ground that there is an error of law ,ap193.rent on
the face of it, yet where a specific question of law has been referred to the
arbitrator for deci~ion, the fact that the-deci~ion is 'ei-roneous does not make the
award bad on its face so as tO permit its being set aside.. As a specific question       G
of law touching upon the jurisdiction of the ·arbitrator was speficially referred to         •
the arbitrator for his decision, the decision of the arbitrator is binding on the
parties and the court cannot proceed to inquire whether upon a true construction
of the arbitration clause, the dispute referred to the arbitrator for arbitration
would be covered by the arbitration clause so as to clothe the arbitrator with the
jurisdiction to arbitrate upon the dispute.
                                                                                         H
     On behalf of the respondent, it was contended that the jurisdiction or the
 arbitrator cannot be left to the decision of the arbitrator so as to be binding on
                                            •

              iio           ,   SUPREME COURT REPORTS                             [1984] 3 s.c.R..
              the parties and it is always for the court to decide whether the arbitrator had
              jurisdiction to decide the dispute, and that the arbitrator cannot by a miscon-
             , structioo of the, arbitration agreement clothe himsClf with or confer upon himself
               the jurisdiction to decide the dispute.



        B
                    Allowing the Appeal ;
                                                    ..
                   HELD : 1. A specific question of law touching the jurisidiction of the
              arbitratOr was specifically referred to the arbitrator and therefore the arbitrator's
               decision is binding on ~}le parties and the award cannot be s.et aside on the sole
              .ground that there· was an error of law apparent on the face of the award. 1t is
                                                                                                         ..
                                                                                                      . --\.

               also established that the claim for compensation made by the contr~ctor which
               led to the dispute VflS covered by the arbitration clause. The quantum of com~
    ·C        pensation awarded by the arbitrator .was never disputed nor questioned. [170E·Fl

                   2. A question of law may fi~ure before an "Brbitrator in two wiys. It may
              arise as an incidental point "'.hile deciding the main disput~ referred to the
              ar"itratOr or in a given case parties may refer a specific question of law to· the ·
              arbitrator for his decision. [137G·H]

    D             Russel : Law of Arbitration. Twentieth Edition p. 22 ,· Halsbury's Laws of
                  England Vol. 2 Para 623 4th Edition referted to.

                  3. Arbitration has been considered a civilised. way of resolving disputes
              avoiding court proceedings. There is no reason why the parties should be
             precluded from .referring a specific question of law to an ar bitratoi for his
             decision and agree to be bound by the same. This approach manifests faith
    E        of parties ill the capacity of·the tribunal of their choice to decide even a pllre
             question of law. If they do so, with eyes wide open, and there is nothing to •
             preciude the parties from doing. sq. then there is no reason why the 'court s4ould
             iry to impose its view of law· superseding the view of the Tribunal whose
             decision the parties agreed to. abide by. On-principle it appears distinctly clear
            that wben a specific question of la"w is referred ~o an arbitrator for -bis decision
    F       including the one. touching upon the jurisdiction of the arbitrator. the decision of
            the arbitrator would be bindi'ng on both the pa'rties and it would not be open
            to any of the two pafties to wriggle out of it by contendiOg that the arbitrator
            cannot clutch at.or confer jurisdictiOn upon himself by mis-construing the arbi..
            tration agree!llent. [I 38E' GJ .                      ·

                  4. If a question 'of law is specifically 1eferred and it becomes- evident
    G       · th;t the parties desired to have a decision on the f!'ecific question from the
•             arbitrator rather than one from the cOurt, then the court will not i[herferf with
             the award of the arbitrator on the ground that there is an error or law apparent
              on the face of the award even if the view of law taken. by the arbitrator does not
              accord with the view of the court. [147F]

    B           Kelantan Government v. Duff Development Co. Ltd. 1923 All E.R. 349: Re
            Kins and Duveen, [1913]-2 K.B. 32: F.R. Absa/om Ltd. v. Great Western
            (London)Garden Village Society Ltd., (1933] All E.R. 616; Durga Prasad Chamria
                                    TARAPORB'co. v. COCHIN SHIPYAjtD                            121
              . and Anr. v. Sewkishendas Bhattar and Ors: AIR 1949 Privy Council 334; Seth·
                                                                                                       A
                ThawardasPherumalv. The Union of ludia; (1955] 2 S.C.R. 48; M/s. Alopi
               ·Parshad & Sons Ltd. v. Tbe Union of India, (1960] 2 S.C.R. 783; Champsey
                Bhara and Company v. Jivraj Balloo Spinning and Wea~ing Company· Ltd. : Law
                Report 50 J.B. 324; Union ofJndia v. A.L. Rallia "Ram., (1%4] 3 S.C.R. 164;
                Mis. Kapoor NiloJc.heri., Co-op. Dairy Farm Society Ltd. v. Union of lndia and
..              Others., AIR 1973 S.C. 1338; N. Chellappafl v. Secretary, Kewla State Electricity
                Board & Anr., [1975] 2 S.C.R. 811; Produce Brok@rs Co. Ltd. v. Olympia Oil             B
                and Cake Co. ltd., (1914-15] All E.R. 133; Attorney General For Manitoba
                v: Kelly and Others.. (1922) Hll E.R. 68; Hirji Mulji v. CJieong Yue Steamship
"    )-   I
                Co.Ltd., (1926] All E.R. 51; lfeyman & Anr. v. Dmwins Ltd., (1942] 1 All E.R._
                337; Jivarajbhai Ujamshi Sheth & Ors. v. Chiniamanrao Balaji & Anr., (1954] 5
                S.C.R. 480; Dr. S.B. Dutt v. University of Delhi., [195,8] S.C.R. 1236; referred
                to.
                                                                                                       c
                    5. The expression 'Without prejudice' carries a technical meaning depen-
               ding upon the context in which it is used. An action taken without prejudice
               to· one's right cannot" necessarily mean that the entire action1 can be ignored, by
               the party taking the same. [148F-G]

                    In the instant case, i'n the context in which the expressio·a iwithout prejudice
                                                                                                   9



               is used, it would only mean that the respondent reserved the right tO contend
                                                                                                       D
               before the arbitrator that the dispute is not covered by ihe arbitration clause .. Jt
               does not appear that. what was a contention ·that no specific question \\;3-S
               specifically referred to the arbitrator, On a. proper reading of the correspori-
               dence, and in the setting in which the term 'wiihout prejudice' is used; it only
               means that the respondent reseived to itself the right to contend before the
               arbitrator that a dispute raised or ,the claim made by the contractor was not           E
               covered by the arbitration clause. N9 other me" '1•.ng :can be assigned to it.·
               [1480-E]

                     6. In works contract of such magnitude, and which have been ·undertaken
                by an Indian Contractor for the first time negotiations prior to the finalisation of
                the contact and the correspondence leading to the formation of cOntract supply
               the basis· on which the contract was finally entered into. Undoubtedly, if in the       F
                final written contract, .thei:,.e is something contrary to the basic understanding
              _ during the formative stage of the contract, the written contract would prevail.
               Buf if the co"ntract does not indicate to the contary and the assumptions appear-
                ed to be the found{ltion of the contract, that aspect cannot be overlooked while
                determining what were the obligations· undertaken the formal contract.
                [151U-!52Bl
                                                                                                       G
                   7. Over-simplification of the clauses of the contract involving works of
               large magnitude is impermissible. kThe whole gamut of discussions, negotiations
               and correspondence must be taken into consideration to arrive at a true nicaning
               of what was agreed to between the parties. [156F]

                    In the instant case, there is no room for doubt that the parties agreed that       H
               the investment of the contractor under this head would be Rs. 2 crores and the
               tendered rates were predicated upon and co-related _to this understanding. [156G]
      Iii               SUPREME COURT REPORTS                           [1984] 3 s.c.R..
A          8. When ~ri agreeme~t is predicated. upon an agreed fact situati~n, if the
      latter cea5es to exist the agreement to that extent becomes irrelevant of otiose.
      [1560]


           9. Phrases suGh as 'claim arising out of contract' ot. 'relating to the con·-
      tract'· or 'Concerniti:g the cotract' -on proper construction would mean that if                ..
B     whiie·intertaining or rejecting the claim or ihe dispute in relation to claim ma:Y
     be entertained or rejected after reference 10 the contract, it is a claim arising out
     of contract. The· language of clause 40 shows that. any claim arising out of the         -'> •
     contract -iri relation to estimates made in the contract would be covered by the
     arbitration clause. If it becomes necessary to have recolirse to th6 contract to ·
     settle the di~pllte One way or the other then certainly it can be said that it is a
c    dispute arising out of the con"act. [157F-G]


           In the instant case, the .arbitration clause is so widely worded as disputes
      arising out of .the contract. or in relation tq the cont'ract or execution of the·
     works that "it would comprehend, within its cOmpass a claim for cOmp·en-
     sation related to estimates and arising out of the cOntract: [157H]                     ·"""'(

D
          10· (i) A dispute, the determination of which turns on the true construction
     of the contract,.. wou!d also seem to. be a dispute under arisin~ out or.:or concer-
     ning the contract. The test is tf\at if in setling a dispUt~, a reference to the
     contract is necessary, such a dispute would be covered by. the arbitration
     clause. [158D-E]

E
          A.M. Mair & Ca. v. Gordhandas Sqgarmu/l., [1950] S.C.R, 792; Ruby
     Gef!eral Insurance Co. Ltd. v. Pearey' Lal Kumar And Another; [1952] S.C.R.
     501; referred to.


          ii. Where the parties .are at one· in asserting that they entered into a
F    bindin.s contract, but a difference has aris~n between them whether there bas
     been a breach by one side or the other, or whether circumstances hnve arisen
     which have dischar.ged ·one ··or both parties from ~further petformance; such
    .differences should be "regarded as differences which have arisen 'in.respect of' or
     'With regard to' of 'under' the contract, and an arbitration clause which uses
     these, or similar expressions should be contrue~ acc0rdingly. "[1~9B-~]

G
        Union of India v. Salween Timber Construction (India) & Ors., [1969] 2
    S.C.R. 224; Heyman & Anr. v. Darwins Ltd., [1942] A.C. 356 at 366; Astro
    Vencedor Co1npania Naviora S.A. of. Panan1a v. Mabanaft G.M.8.H. The
    Diamianos., [1971] 2 Q.B. 588; Gunter Henck v. Andre & CIE. S.A., [1970] 1
    Lloyd's Law Repoi:ts 235; referred to

          In the instant case, from the pleadings, it clearly transpires that both the
     parties had recoutse to the contract. It is satisfactorily established that the.
    claim made by the contractor would be covered by the arbitration clause. [160B]
                        tARA!'oRE Co. V•COCHIN SHIPYARD (Desai J.)           123

                    CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3023 of
            1980.                                                                    A


           • . Appeal by Special leave from the Judgment and Order dated
            the 21st August, 1980 of the Kt;rala High Court in M.F.A. No. 409
'           of 1979.
                                <
    ' ,          F.S. Nariman, A.N. Haksar, · T. Raghvan, R.F. Nariman,              B
'    ./
            V.A. Bobde & K.R. Nambiar, foi"the Appellant.

                    G.B. Pai,   P.K.   Kumar,   A.K. Sharma,   As/wk Mathur and
            Pa~veen Kumar for the Respondent.
                    The Judgment of the Court was .delivered by                      c
                  DESAI, J. In this appeal by. special I.eave a very interesting
    .,_     question ih the field oflaw of arbitration which 'honest man dread
            more, than the dreaded law suits' arises for our c~nsideration.

                    First respondent Cochin Shipyard Limited ('respondent' for       D
             short) invited tenders for construction of Building Dock at Cochin.
             As there was only one ~tender that of Tarapore & . Company,· the
             appellant, the respondent called fresh tenders somewhere in July,
            1971. In December, 1971; the respondent invited tenders for cons-
            truction of a Repair Dock also at Cochin. There were two. tenders        E
            for Building Dock; namely, one of the appellant and one by
            M/s National Building Construcfion Corpbration, a Government
            oflndia undertaking, the value of the tender Of the latter being ·
            double that of the appellant. For the construction of the Repair
          • Dock, the only tender was of the appellant. 1n view or th~ limited
            nuinber of tenders. received, · the appellant was invited to negotiate   F   •
            the terms of tender. The v_alue of the works to be executed was
    .      ·over Rs. 24 crores. In view of the huge investment in the project,
     '      the tenders were examined by a committee called the Tender Com-
            mittee conslituied in accordance with the approval of the Ministry
            of Shipping and Transport for examining and evaluating the tenders
            r~ceived for the Building Dock and the Repair Dock. The Tender           G
            Committee taking note of the poor response to the invitation to
            tender and costiy affair decided to accept the tender of the appel-
            lant inter alia for the ·reasons (i) that works of such complexity and
            magnitude have not bee.n undertaken before by any Indian contrac-;       H
            tor, (ii) that the plant and equipment required for the work are not
            available indigenously, (iii) that if the contractor is to procure the
             124                 ~UPREME COURT REPORTS                (19s4j 3 s.c.a.
A             specialised equipment · r~quired for this work, there ·is hardly any             >   -,..,




              assurance that after these works are over, he would find any sub-
              stantial use for the sai:ne, (iv) that excavation. and subsequent cons-·
              tructio~ involve de-watering which introduces considerable ·amount
              of uncertainty and th~t during the discussions; the apprehension of
              the tenders of this kind was· voiced and noticed by' the Committee,

..
B            .and (v) that RCC Piling also requires .highly skilled and complex
              technical . operations and it involves .. a large eiement of risk and
             uncertainty in the· work.     Both the tenders of the appellant were
        . accepted, and contracts were entered into between the parties." Both
          the parties while entering into contracts. were aware anc\ conscious
      ~ of the fact that equipment and technical know-how would. have to
c be imported involving a huge outlay of foreign exchange. Appellant-
          contractor quoted rates .on t.wo aiternative basis depending-upon
          whether it had to import equipment and know-how at its cost invol- .
          ving Rs. 2 crores in foreign exchange or the equipment ·and know-
          how wer.e tci be imported by the respondent at.its ·cost and made
D         available for use of the appellant in which case the appellant would
          be liable t.o pay hire charges for the pile. driving plant at the rate of
          Rs. 23/- per metre of ·600 mm· dia. RCC cast-in-situ pipe' and
          Rs. 16/- per metre of 500 mm di:\. RCC cast-in-situ pipe and at the.
          rate of 300 per .tonne, of steel sheet· piies driven to be recovered
      ' from the running bills payable to the appellant.contractor. The -
E · ·. appellant was gjven to understand b:t a. note in the invitation to
      • tender that foreign exchange in yen credit to th;: tune of Rs. 38        lacs
          is earmarked for the purchase of construction equipment, accessories
          etc. from Japan for works of Building Dock, Repair Dock1 the three
          Quays etc. On January 24, 1973, work· order for Building Dock
          and Repair Dock was .issued. by the respondent in favour of appel-
F      . !ant and in this .work order as recommended by the Tender Commit-
          tee, the respondent adopted the' alternative B as set out iri the ten-·
          der, namely, that the contractor was to procure the equipment and
          know-how at a cost of about Rs. 2 crores in foreign exchange. In
          order.to make this aspect specific, ·additional condition No. 31 was
          incorporated in the works order in order to provide for the expense
       · to be illcurred and the amount of foreign exchange needed for im~
          porting equipmept and technical kllow-how, relevant portion . of
         .wl!ich reads as under :                                '
     .   '             "Requisite foreign exchange, for importing piling plant ·. ··
H              >>and machinery, spares, technicaf, know-how· and> hiring of
                experts necessary for both the.Dock Works vide Work Order ·.
                No. 130l9/l/71-W-II dated Janual'J 24, 1973 for Building.
                                                                                         ...
                                                                              J

                   TARAPORECO. v. COCHIN SHIPYARD (Desai J.)              125

           Dock etc. and· Work Order No. 13012/15/71-W-II dated                    A
           January. 24, 1973 for Repair Dock. etc., amounting to about
           Rs 2.00 crores in all wiUbe made availa\>le to the contractor
           f~om the 11th Yen Credit subject to his getting indigenous              •
           clearance and providing detailed justification. The details
           of such procurement shall be·fnrnished by the t:ontractor as
           soon as they are finalised."                                            B

•   f                              •   •
                 In view of the huge investment, it was agre.ed that the respon-
         dent would make an.advance payment of75% of the value of old
        . machinery and 90% of the value of new machinery brought to site
          by the Contractor and in -0rder to secure this advance payment,          c
          equipment would be hypothecated by the Contractor (o the respon- ·
          dent and the advanoe payment were to carry interest at 9.1/2% p.a.
          on the outstanding balance of advance. The mode of recovery was
          also specified. The formal contract was signed on January 29, 1973
          which included an arbitration clause to which we would turn a
          little later.                                                            b

               · It so happened that the required pile driving equipment includ-
         ing the technical know-how against 1lth Japanese Yen credit were
         not available. The respondent also made inqulres in this behalf,
         but without 'success. Ultimately, International Foundation Group,         E
         Holland agreed to provide the rate of equipment conforming more
         or less to the same specification for which clearance.was sought and
         received. from the Government of India. After the respondent •
         certified that the equipment and know-how ofiei:ed by International
         Foundation Group. Holland conform to the earlier cleara11ce and
          that the same equipment being not indigenously available or against
          11th Japanese Yen Credit, the respondent requested the Govern-               '
          ment of India to give necessary clearance to the appellant to import
         the equipmeat. This approval was received on Septembet 1, 1973
          and the foreign exchange to the extent or Rs 211.80 lakhs equal to
          9,4%2.700. Dutch Florins was released in favour of the appellant.
          The entire imported equipment was received in four consignments
          between March/July 1974. During the intervening period, there
          were variations in the rate· of exchange and therefore the foreign
          exchange cost of equipment alone in· terms of rupees worked ~ut at
          Rs. 177.50 lakhs and of the technical know-how fees payable in 11
           instalments worked out at Rs. 105 lakhs. The custom duty went           H
           up by .Rs. 21 lakhs as a consequence of the increase in rupe_e value
         • 0 f the imported equipment in terins of Dutch F 1orlu,
          .  .         .      '  .                       .     . .
                        SUPREME COURT REPORTS                  [1984] 3 S.C.R.
A              The appellant made .a tentative claim in the amount of
        Rs. 61.27 lakhs from the·respondent on account of increase in cost
        of pile driving equipment and technical know-how fees on the
..    ·ground that the contracto{ was entitled to be compensated by the
        respondent foi,)he same. In. the letter dated May 28,1975, the
        appellant bas stated that the 'tendered rates were. based on certain
B
        total cost of machines which has since gone up considerably render-
        ing the rates no longer workable. The l&l'Pellant' had .provided for
        a cost of I 50 lakhs of rupees for the equipment and ihe life of the
        equipment was !akin as 12,000 hours and its probable period of
        engagement on this job was taken as 8,000 hours. ·On this basis'
c       two-thirds of the cost of the equipment will be written off by way
        of depreciation on this job.' ·It was also stated that there is an
        increase in the fees for the technical know-how. The letter con-
        cluded by saying that the loss sustain.ed by the appellant upto May
         15,1975 on account of variation in the rate of foreign· exchange was
         Rs. 61,27,'3!7 and requested the'.respondent to compensate the loss
D       aileast upto the tune of Rs. 45 lakhs which is approximately 75%
        of the loss suffered by the contractor in this behalf. The respondent
       'responded to this letter as per its letter daied July 2,1975 saying
     · that the letter dated July 14,1972 of the appellant which forms part
        of the contract documents clearly recites that the total foreign ex-·
        change required by the contractor for the equipment, spares, techni-
E       cal know-bow. and hiring of exp~rts, was expected to be about Rs. 2
        crores and that the expenditure incurred by the contractor in this
        behalf. so· far has been less· than Rs. 2 crores and in the circum-
      .stancesit was found difficult to accept the position that the tender
        was based on the assumptions indicated in the letter under reply
        and that the rates for the pile driving should for the future he revis-
F
        ed. there ensued further correspondence between the parties.
        Ultimately, the appellant by its letter dated March 1, 1976 informed
        the respondent that its claim for compensation for increase in the
     . cost of imported pile driving eqµipment and technicai know-how
         fees has not been entertained for over a year. It was further stated
G       that 'inasmuch as the dispute has thus arisen between us re&ardiflg
         the above claim, we are invoking the provisions for arbitration in
         our contracts and ret;erring this dispute to arbitration.' On March
        ·17, 1976 Chief Engineer of the respondant replied saying that the
         matter as set out in the letter dated March 1,1976 invoking arbitra-
                                                                                  .~.
         tion clause is receiving tlieir immediate attention and the appellant
H        will hear shortly in this be))alf. On March 29,1976, the respondent
         wrote to the .appellant denying the claim for compensation of the
         appellant. Simultaneously the 'respondent framed three point8
                                      . .
            •
                              TARAPORE co. v. COCHIN SHIPYARD (Desai J.)             127

                  covering the dispute so raised for reference to and decision by the
                                                                                            A
                  arbitrator. The letter also sets out as required by Clause 40 a panel
                  of three names from which anyone can be chosen by the.appellant
                 as the sole arbitrator. The appellant by its letter dated April
                   1~19_76 :Vhile refuting the contention of the respondent that the dis-
                  pute would not be covered by Clause 40 i.e. arbitration clause in         B
                  the contract, stated that the proper course would be to.refer the
                · dispute that has arisen betwee.n the parties' to the decisfon of the
                   a.rbitrator a11d not any particular issue or issues. Ultimately froni
'   )
                  amongst the three names indifated by the respondent the appellant
        •         selected .Shri C. Srinivasa Rao, Chief Bridge· Engineer, Southern
                  Railway, Madras to be the Sole Arbitrator to tlecide the dispute.         c
                   On receipt of this letter the respondent referred the dispute to Shri
                   C. Srinivasa Rao as Sole Arbitrator. While referring the dispute to
                   the sole arbitration of Shri C. Srinivasa Rao, the respondent retain-
                   ed the three points of reference set out in the letter dated March
    y              29,1976 but added one more. The· Arbitrator entered upon the re-
                   ference on June 2,1976. On being called upon by the Arbitrator,          D
                   the appellant filed its statement of claim on June 19,1976. The
                   appellant claimed Rs. 2,03,47,.266 ·as per th., Schedule to the State-
                   ment of Claim on account of increase in the cost of·eq'uipment and
                   technical know-how fees. The respondent filed its reply to the
                   Statement of Claim on July 19,197,,
                                                                                            E
                                                  '
                       The·points/disputes referred by the parties to the sole arbitra-
                 tor read as under ;


                            "!. Does the claim ·of Messrs. Tarapore & Co. on                F
                     Cochin Shipyard Ltd., for compensation for increase in the
                     cost of im,Ported pile driving equipment and technical know-
                     how fees referred to in clauses (2) and (3) hereunder fall
                     within the purview of the first paragraph of Clause 40 of the
                     General Conditions of Contract entered into between the two
                     parties ?                                                              c
                                      /
                             2. If the answer to (1) above is in the affirm~tive, in
                      terms of the provisions· of the contract are Messrs .. Tarapore
                      & Co. entitled to compensation for increase in the cost of im-
                    . ported pile driving equipment and technical know-how fees
                      to be paid to them by Cochin Shipyard Ltd.? If so, what ~s
                       the amo11nt ~
             128             SUPR~ME COURT REPORTS                    [1984] 3 S.C.R.

                       3. The dis1mte t.hat has arisen between Messrs. Tara-
                pore & Co., and Cochin Shipyard Ltd.· regarding the claim
               ·of M/s. Tara pore & Co., for compensation for increase in
                the cost of the imported pile driving equipment and the tech-
                nical know-how fees.
     B
                                                                                 •                    •
                       ,4.   "Costs'~
                                                                                             'r-
                 Parties appeared before the Arbitrator through their respective                 J.
            counsel. The Abitrator gave its Awatd on July 6,1977. On Point
            No. 1, the Arbitrator' held as under:                                       • '·
     c                         •
                       "The claim· of Messrs. Tarapore and Company on
                Cochin Shipyard Limited for compensat.ion for increase in
                the cost of imported pile driving equipment and technical
                know-how fees falls within the purview of the first paragraph
                of Clause 40 of the General Conditions of Contract entered·                      y
    'I>.        into between the parties."

                    On Point No.· 2, the Arbitrator . held that the appellant.
             'Messrs. Tarapore and Company are: entitled to compensation by
             the Cochin Shipyard Limited for the increase in the cpst of i111por-
             ted pile driving equipment and the.. technical know-how fees by a
             sum of Rs. 99·1akhs only which amount shall be payable with in-
             terest at 9.1/2% per 'annum from this date till date of payment or
            decree, whichever i~ earlier'. On Point No. 3, the decision recorded
            was 'that it jg covered by the decision on Points (1) and (2)'. On
            Point No. 4, on the question of costs, the Arbitrator having deter-
    F       mined his fees and incidental expenses directed both the parties to
           ·bear the same eq:ually. '(he Award was typed on a stamp paper of
            the valµe of Rs .. 150/- at Madras. j3y his letter·dated Nil July, 1977,
            the Sole Arbitrator foFWarded the award to both the parties."


    G               The appellant moved a petition under Secs. 14 and 17 of the
            Arbitration Act in the Court of the Subordinate Judge, Ernakulam
           for filing the award and for making it a .·rule of the court. On
           October 7;1977 the respondent moved O.P. 81 of 1977 being a com-
           bined petition under Secs. 30 and 33 of the Arbitratioo Act before
           the Subordinate Judge, Ernakulam praying for setting aside the
    H      award. · The prayer for setting aside the award was fonnded on two                    ,
           groui1\ls; {l) that the award is insufficien!lY stamped and (2) that the      .   '
            fl,r1;>itrator has exceeded ·bis iuriuliction by misconstruin(l Clause 40

'
                                                                                      •


                                      .                  .
                    TARAPORE co. v. COCHIN SHIPYARD (Desai J.)              129

         of the General Conditions of Contract (Arbitration clause for
         short),

                The learned Subordinate Judge noted the fact that the award
         was originaJly engrossed on a stamp paper     of  Rs. 150/- but before
         filing the ·award in the court on 'August 4, 1977, the Arbitrator on · B
         August f,1977 affixed additional stamp of Rs. 14,722.50 p. which
         would be the requisite stamp under Art. 12 read with Art. J 4 of the
.   )-    Kerala Stamp Act. .The learned Subordinate Judge accordingly
          negatived the contention of the .respondent that the award was
          insufficiently stamped. On the second point, the learned J~dge held ·
          that the respondent having subn:iitted the question whether the dis-' C.
          pute raised by the appellant was covered by the arbitration clause
          cannot be permitted to controvert lhe jurisdiction of the Arbitrator
         .to decide this dispute and accordingly, negatived the. contention of
          the respondent. The learned Judge after modifying the award of
          t,he Arbitrator in the matter of int,rest from 9.1/2% as awarded by • D
          the Arbitrator to 6% granted the application of the applicant and .
           made the award a rule of the cpurt.
                                                                                          •
                  The respondent preferred M.F.A. 409 of 1979 in, the High ·
           Court of Kerala at Ernakulam. A Division .Bench of the High
           Court agreed with the learned Subordinate Judge on the question of        ·E
           insufficiency of stamp.· The Division Bench however, after exl?res-
           sing- its displeasure about not making a reasoned award by the
           Arbitrator proceeded to examine the C()ntent.ion whethei; the arbitra-
           tion claUfe covers the dispnte. The court held that the question
           whether the dispute is arbitrable or not cannot be finally decided by
         · the arbitrator because it is a matter relating to his .jurisdiction. It
            was further held that the arbltrawr cannot by an erroneous inter-
           pretation or construction of the clause confer jurisdiction on him-
            self and the court c.an go into the question whether the matter in
            disp)lte between the parties is covered by the arbitration clause.
          · The specific contention ort behalf of the appellant that once a speci-
            fic question of law is referred to the arbitrator, the parties are       G
            bound by the de.cision of the arbitrator was negatived by the ·High
            Court ·and it was held that as the reiipondent has joined arbitration
            under protest, it was not estopped from contestinjl the question and
            the award is not binding Qn it if it can be shown that the arbitration
            agreement did not cov.er the dispute raised by the appellant. The        ·H
            court finally held that even though the arbitration clause was very
             wide, the dispute as to the compensation for increase in the cost of.
             imported pile driving equipment an<l technical kn_ow·how fees woutd·
               130               ~\!PREME COURT REPORTS ·              [1984}3 S.C.R.
    A
                 not be covered by the arbitration clau>e inter.alia on the ground
                that by Cl. 26 of the General Conditions of Contract every plant, .
                 machinery and equipment had to be provided by the contrator and
                any rise nr escalation in the price of su.ch equipment or machinery
                cannot be the subject matter of compensation by the respondent.
                Accordingly, the appeal of the respondent was allowed and the
     B
              )ud$ment and order of the trial court making the award rule of the
                court was set aside. The court directed that the award be returned
                to the parties: Hence this appeal by the contractor by special          "'-   .
              · Jeave.

     c               Before we advert to the rival contentions, it would be advan-
               tageous to refer .to the arbitration clause being Clause 40 ~of the
               General Conditions of Tender subject to which the contract ;vas
               entered into, the relevant portion of which reads as Ul)der ;
         •
    D                      "Clause 40. Except where otherwise provided in the
•                   contract, all questions and disputes relating to the meaning
                    of the· Specifications, Instructions, designs Drawings herein-
                   before mel)tioned and as .to the quality or workmanship or
                   materials used on the work or as to any other questions,
                   claim, right, matter or thing whatsoever in any way arising
    E
                   out of or relating to the Contract, Designs, Drawings, Speci,
                  ficatioqs, Estimates, Instructions, Orders or these conditions
                  or otherwise concerning
                 .·                   .                                  .
                                             the works or the execution or failure
                  to execut.e the same,. whethe.r arising during the progress of
                  the work Qr after completion or abandonment thereof shall,
                  after. written notice by eitJ;ier party to the contract, to the
                  either of them, be referred to the .Sole Arbitration of a per-
                  son appointed by the Chief Project ,Officer of the Cochin
                 Shipyard Project or the Administrative Head of the Cochin
                 Shipyard Project at.Jhe time of such appointment by what-
                 ever designation known, from a panel of names given in
    _G           Annexure II."
                                               •
                     Over and above the extfacted portion, ·the clause provides for
               the manner and metho'd of appointing tlie sole arbitrator, the conti-
               nuance ofthe work during progress of arbitration proceedings, the
    H         .time and place of holding the arbitration proceedings, the power to ·
               enlarge the period for making the award and finality to be attached            .'
             · to the award of the Arbitrator.
                                          .'
•
             •
                     TARAPORE co. v. COCHiN SHIPYARD (Desai J.)                  131

                    When the arbitration clause was invoked by the appellant, the         A
           respondfnt did contend that 'the dispute raised by the appellant was
            not covered 1!J the arbitration clause. After. specifying its demur,
           the respondent formulated the points in dispute on which the
            arbitration was invited to give his award. Undoubtedly, the respon-
           dent proceeded to formulate the points in dispute betwee.n the
           parties on which the Arbitrator was to be invited to give his award            B
            without prejudice to its right to contend that the dispute is "not
          . covered by-the arbitration clause and that the appellant is .not enti-
           ~led to any compensation in respect of the increase in the cost of
            imported pile driving equipment and technical know-how fees. What
            is the eifect of referring the specific question of law to arbitration
            without prejudice to one's right to co(itehd to the contrary will be
                                                                                          c
            presently examined. The fact remains that on the. dispute arising
            out of a claim for compensation on account of the increase in the
            cost of imported pile driving equipme~t. and technical know-how
            fees, the respondent agreed to refer the dispute under two specific
            heads to the Arbitrator. The dispute so raised have already been              D
            extracted. Briefly stated they are : (1) whether the claim for com-
            pen~tion would fall within the pµrview of the first para of the
             arbitration clause and (2) if it does the quantum of compensation,
             if any, to which the appellant would be entitled. Analysin~ the dis,
             puies, let it be made distinctly c!eAr th~t the appellant asserted that
             its claim for compensation would be governed by the arbitration              E
             clause and the same wa• specifically denied by the respondent saying
             that t\Je claim would be beyond the pµrview of the arbitration
             claus;.· On these rival positions, the specific issue was framed
             whether the claim for compensation would fall within the purview
             of the first part of the arbitratoin clause. This:was the specific dispute
             referred to the arbitrator inviting him specifically to decide this          F
             dispute. If this issue specifically .raises a question as to jurisdiction
    ,'       of the arbitrator to arbitrate upon the dispute set out in Point No.
              2, it appears to have 'been specifically referred t.o the Arbittator for
             his decision. Parties, therefore, agreed to submit the specific ques- ·
         • tion even with· regard to ·the scope, ambit, width and the construction
                                                                                          .G
             'of the arbitration clause so as to define its parameters and contours
              with a view to ascertaining· whether the claim advanced by the                   ·•   .
             -appellant and disputed by the respondent would be covered by the ·
            . arbitration clause. Whether. upon its true construction.the arbitra-
    ,.        tion clause would include within its· compass the dispute thus raised
              between the parties was specifically put in issue because parties were      H
              at varian~e about i\. 'Appellant asserted that its claim to compensa-
              tion would form the subject matter] of ·arbitration under Clause 40
                                          ,.



                                                                                                 •
               132             SUPREME COURT REPORTS                    (1984] 3 S.C.R.

        A       and the respondent contending to the contrary. · While deciding
                this dispute, as to th~ scope, width and ·ambit of arbitration clause
                vis:a•vis the dispute raised, it is not necessary to decide whether the
                Claim was tenable justified or had any substance in it. 'fhat would
                fall within the second point of reference to the arbitra,tot which
               opens with a sp~ific 'clause that it needs onJy to be de.cided if the
    B·         answe.r to the first point of reference, namely jurisdiction· of the
               arbitrator under Clause 40 is in the affirmative meaning thereby
               that the.dispute so,;aised and sub~isting between the Nrties-would
               be covered by the arbi~ration agreement. In other words, if the
               dispute is covered by)he arbitration agreement, the arbitrator was
               further required to decide whether there was any substanc;, in the
    c          claim made, and if he found some substance in the disputed claim,
              to ascertain what amount the appellant would be entitled to recover
              as and by way of compensation from the-respondent. The arbitrator
              was thus required and called up 0n first to decide whether the dispute
              is arbitrable as falling witlfin the width and ambit •or the arbitration .
              agreement. If the answer is in the affirtnative, then alone the second,
    D
              point need be examined. If the answer to the first point ofreference

        ..   is in the negative in that if the arbitraior weie of the opinion that
             the dispnte is not arbitrable as it would not fa II within the sc't>pe,
             width afld ambit,· of• the arbitration agreement, it would not be
             necessary for him to determine wiether the l>ppellant was entitled
    E        to recover anything by way of compensation. This aspect is be~g
                                                          .
             analysed in depth to point out that the parties specificall~. referred.
             the question of construction . of arbitratio·n agreement, its ~idth,
             ambit and parameters vis-a-vis the dispute raised so as to decide
             whether the dispute w~uld fall within· the purview of the arbitration
             agreement, in. other w~rds the jurisdiction of the arbitrator..
    F
                     Correspondence placed on record would unmistakably show.
               that a specific question- as to the jurisdiction of the arbitr.ator was
               specifically referred by the parties to the arbitrator. Appellant-
             . contractor by his letter dated March .J, 1976 to the Chief Engit1:eer
               of the respondent invited his attention to the claim for compeµsation
    G          for.increase in cost of pile driving equipment and technical know-how
               fees raised about a year.ago and further invited his attention to the
•              Jetter dated 6th October, 197~ of the respondent infprming the
               appellant that the claim cannot' be entertained. The app2Jlant
                                                                                           )'i. '•
               proceeded further to state as under: _
                        .                       '                                          ·"'
    H                    "Inasmuch as a dispute has. thus arisen between us
                · regarding the above claim, we are invokills die provisions for ·
                  •
                                                                         •
                  hRAPORE co. v. COCHIN SHIPYARD (Desai     f)           133

           arbitration in our contracts and referring this dispute to           A
           arbitration." ~

              The respondent by bis letter dated March 17, 1976 informed
        the appellant that the matter.raised in the letter dated March 1,1976
        in the matter of compensation is receiving their immediate attention
        and the appellant will shor\ly hear f1om them in this connection.
        Thereafter the respondent by his letter dated March 29,1976 informed
•• >    the appellant as under;
                                        •
                  "We have dealt with the merits of your claims in the .
           previous correspo!ltlence on the'· subject and we reitera!e that
           no amounts whatever are ·dve to you in respect of these
                                                                                c
           claims. It is also our view that such claim does not fall
          ·within the purview-of Clause 40 of the General Conditions
           of Contract and hence does not qualify for arbitration.

                  However, in view of your insistence and without               D·
           prejudice to our position, we propose that, the following be
           the issues to be referred to arbitration: '

                  1.   Does the claim of M/s Tarapore & Co., on Cochin
           Shipyard Ltd., for compensation for increase in the cost of
           imported pile driving equipment and technical know-how fees          E
           fall within the purview of the first para of CJause-40 of the
           General Conditions of Contract entered into between the two ·
           parties?

                ' 2. If the answer to I is in the affirmative in terms of
                  •
           the provisions. of the · concerned contract, are Messrs.
                                                                                F
           Tarapore ~ Co. entitled to compensation for .increase in the
  .;       cost of imported rile driving equipment and technical know-
           how fees to be paid to them py Cochin Shipyard,Ltd.? If so,
           what is the amount?                           ·
                                                                                G'
                  3. "Costs."

               The respondent proceeded to notify the panel of names and
         invited the appellant to choose the arbitrator as agreed to between
         the parties and set out in clause 40. The appellant by his letter
         dated April 19,·1976 whil~ reasserting that the claim made by it       H
       · would be covered by Clause 40 further stated that the proper course
         would be to refer the dispute that has arisen between thep arties on
                •
              134             SUPREME COURT REPORTS                  [1984i 3 s.c.R..

     A        the matter of compensation to the decisio11 of the arbitrator and not
              any partfoular issue or issues. It was also sugg<;sted that framing
              of the issues will be- the funttio11 of the arbitrator after he enters
              upon the reference and after he has the pleadings of both the partie3
              before
                 .    him. The ·appellant
                                  .         also
                                             . suggested what dispute should be
              referred to the arbitrator and set it out as under:
 B
                         "The decision of the dispute that has arisen between
•                 M/s Tarapore & Co., and the Cochin Shipyard Limited,
                  regarding the claim of Mfs Tan.ore & Co., for compensation
                • for the increase in the cost of t\Ie imported pile driving
                . equipment and of the technical know-how fees."
 c
                  The appellant proceeded to ;uggest that Shri C. Srinivasa Rao
          · from amongst the panel be appointed· as the Sole Arbitrator .. The
            respondent by his letter dated ·April 27/28, 1976 annexing ihree
            earlier letters dated March I, 1976, March 29, 1976 and April 19,
D           1976 referred the four points herein before set out for the decision of
         .. the arbitrator.                                   \

                   This correspondence would unmistakably show that while the
             appellant wanted· a general reference about its claim, it was the
             respondent w_ho now contests that no specific question of law was
E          . specifically referred to the .arbitrator for his decision was specific
             about the points to be ·referred for· the decision of the Arbitrator.
          · T~e first ,roint extracted hereinabove would clearly show that the
-.          specific question about the jurisdiction of the· arbitrator to arbitrate
         , .\ipon the dispute set out in points Nos. 2, 3 and 4 was specifically
            refe~red to the arbitrator .. On the first point, the arbitrator_ had to
I'          decide whether the claim made by the appellant and disputdd by the
            respondent would be covered by Clause"40 i.e. the.arbitration clause.
            In other words, the specific question referred to the Arbitrator was
            about" his jurisdiction. to arbitrate upon the disputes covered by
            points Nos. 2, 3-.nd 4, if and only"if,_upon a true construction of the
            arbitration clause that is first paragraph of Clause 4_0, would cover
G
            the disputed claim for. compensation he can enter into the merits of
            the dispute and _decide it. It is upon the decision on point No. I that
            the arbitrator would have jurisdiction to decide the dispute involved
            in points Nos. 2, 3 and 4. The1 first point of reference is clearly a
            specific question of law touching upon the jurisdiction · of the
H           arbitrator and this was framed anp referred to by none other than,
            despite the initial objection of the petitioner, the respondent. There-
            fore, the respondent invited the arbitrator by the specific point of -
                                          J
                         ,

                       TARAPORE co. v. COCHIN Sl{IPYARD (Desai, J.)            135

          reference which involves a •specific question of, law touching upon
          the jurisdiction of the arbitrator to decide the same. This becomes
          further clear from the. fact that both the learned counsel appearing
          before the arbitrator submitted agreed draft issues for the decision
          of the arbitrator. The first issue amongst the agreed draft issues
          reads as under:
                                                                                      B .
                    "Does the claim of the claimant fall within the purview
             of the purview of the firs\ para of Clause 40 of the General
             Conditions of Contract entered into between the two parties? .

                 This point was not to be incidentally decided· while deciding
          the .dispute referred io the arbitrator his jurisdiction to entertain the   G.
          dispute js questioned. In fact, hereby : the reference of the specific
          point of law touching upon the jurisdiction of the arbitrator the
          parties invited the arbitrator to decide this specific question. It was
          he who was asked by the submission or terms of reference to decide
          his jurisdiction first and then proceed to decide the dispute on
          merits. We referred to Issue No: 1 in the agreed draft issues only          D
          to l:iuttress the conclusion that it was at the. instance of the respen-
          dent that the arbitrator was called upon to decide · the question of
          the scope, ambit and width of arbitration clause the decision on
          wh\Ch would confer jurisdiction upon him to decide the· dispute as
          to compensation. In this context it would be advantageous to refer
          to paragraphs 11 and 12 of the counter statement filed by the res-
          pondent before the arbitrator which reads as under:

                       "11. It is submitted that the claim in question
     I.
               relating to the increase in the cost of machinery and equip·
               ment as also technical know-how fees payble by the
               contractors/claimants is· fully outside the purview of the.
                                                                                      .,
               contract. There is no liability on the part of the respondent•
               to procure the machinery and equipment or technical know-
~-             how required by the contractor nor was there any liability to
               pay any part of the cost, whether it .be the original assumed
               cost or the increased cost. The claim thus is completely               G
               outside the purview of the ·contract and it is submitted,
           · · therefore, that the same does not fall within the purview of
               the first para)lfaph of Clause 40 of the General Conditions of
               Contract and thus not arbitrable .
•                12. It is submittedthat the question of arbitrability of the
'         ·.dispute should be 'decided as a preliminary· point before proceeding
          with the other issues."
                                                              •
       136            SUPREMB?COURT REPORTS                   (1984] 3 s.c.R..
A             The formulation of the specific question of law by the respon·
      dent along with its suggestion to dec.ide it as a preliminary issue and
      .becoming a party to the agreed draft issue No .. I would conclusively
    · establish. that the specific question of law touching upon the ·
      jurisdiction of the arbitrator was referred to the arbitrator for his
      de~ision. Therefore, the conclusion is lnescapable that a specific
B     question of law touching upon the jurisdiction of the arbitrator which
      is indisputably a question construction of Cl. 40 and therefore a
      question 6f law was specifically referred by the parties to the
      arbitrator for his decision and by the terms of Clause 40 agr~ed to '
                                     0




      abide by his decision as final andibinding.
c            Mr. F.S. Nariman, learned counsel for the- appellant urged "that
       Sec. 16(1) (c) may permit the court to remit or set aside the award
       on the ground that there is an error of law apparent on the face of
       it, yet where a specific question of law has been referred to the
       arbitrator for decision, the fact that the decision is erroneous do·es
       not make the award bad on its face so as to permit its being set"aside.
      Expanding the submission, it was urged that a decisibn on a question
       of law by an arbitrator may be given in two · different and distinct
      situations; firstly where while deciding a dispute referred to him
       incidentally. a question of law may arise which an arbitrator )llay
      decide in order to dispose of the refefence and if in such a situation
E     any error of law appears- on the face of the award, the c~urt can
      interfere with the award. But.there is an altogether an independent
      and a distinct situation in which a question of law might arise such
    . as where the parties to the dispute may frame the specific question of
      iaw and refer it to the Arbitrator for his decision. In the later          \
      situation, it was urged that the decision of the Arbitrator even if
F     err~neous would not permit the court to interfere with the award.
      Proceeding along it was urged that in thi.s case. a specific question of
      Jaw touching upon the jurisdiction of the arbitrator was specifically
      referred to the Arbitrator for his decision and therefore, the decision
     of the Arbitrator is binding on the parties and the court cannot
      proceed to inquire whether upon a true construction of the arbitra·
G
      tion clause. · the dispute referred .to the Arbitrator for arbitration
      would be covered by the" arbitration clause so as to clothe the
      arbitrator with the jurisdiction to arbitrate upon.the ;disl'ute.

           Mr. Pai, lear11ed counsel for the respondenfcountered by saying
H    that jurisdiction oNhe arbitrator cannot be left to the decision of
     tbe "arbitrator so ~s to be binding on the parties and it is always for
    the court to decide whether the arbitrator has jurisdiction to decid.e
                                                    I


                                         .
                          TARAl>OkE co. l'· COCHIN SHIPYARD (Desai, J.)
                                                                   .             1~1

              the dispute. Alternatively, it was submittec\ .that the arbitrator          A
              cannot by a misconstruction of the arbitration agreement clothe
              ,himself with or .confer upon himself the jurisdiction to decide the
               dispute. The court it was said has always retains to itself the
               jurisdiction to look at the arbitration agreement to determine its
'   '
               scope and ambit ·and if it. is found that the dispute referred to the,
               arbitrator does not fall within the arbitration agreement,. the court
             . must interfere on the ground that the award disclosed an error of law
                                                                                          •
    • .>        apparent on the face of it.

                   The contention may be examinecJ. both on principle.and on the
              precedents.                                                                 C

                     Complexity of rights and obligations in national and inter-
              national trade and commerce would certainly generate disputes
              between tjl.e parties and treated as a normal incident of commercial
              life artd till· commercial arbitration came to be· s:cognised as a          D
              civilised way of resolving such disputes, prolix and time-consuming
              litigation was the only method of resolving such disputes. As an
              alternative ,to court proceedings, arl;>itration as a method ofresolving
              <\isputes by domestic tribunal constituted by the choice of parties
              became acceptable. The basic difference between -the court procee-
               dings and the arbitration is the choice of the tribunal. Ordinarily,       E
               all matters in which relief can be claimed from the court may become
               subject ·matter of arbitration. Now if in a iaw court incidental
               questions of law arise in the course of proceeding, the court has an
               obligation to decide those questions of law. But when it came to a
               tribunal not endowed, with the judicial power of the State but by   0


               conferment by the. parties to the dispute or• which acquir.es jurisd ic-   F
               tion by a submission of the parties to the dispute to invite the
               decision by the forum of their choice and to be bound by it a que.stion
               arose whether a pure question of law if at afl can be referred to an
               arbitrator for his decision and even· if he_ decides, can the decisiop
               be questioned on the ground that there is an error apparent on the
               face of the award in deciding the questipn. Now as stated a short·
                                                                                          ·c
               while ago, a question of law may figure before an arbivator in two
               ways. It may arise as an incidental point while deciding the main
               dispute referred to the a~bitrator or in a given case parties may refer

        ..
        l
                a specific question of law to the arbitrator for his decision. There
               is no more gainsaying the fact l!.at a pnre .question of law may and       H.
                can be referred t'o an arbitrator for his decision. Russel on the Law
                of Arbitration Twentieth Edition at page 22 states
                                                                .
                                                                      as under·I
      i~s                     SUPJ(EME COURT REPORTS          . (1984) 3 S.C.R.
A                 "A pure 'question of law ·may be referred to an
          arbitrator; and where such a question is specifically referred
          his award win not be set asjde merely upon the ground that
          his decision is wrong."

           In Halsbury's Laws bf· England Vol. 2 Para 623 4th Edition
B.   the statemept of law reads as under:

                  "If 'a specific question of law 'is submitted to the             ....(_   ...
          arbitrator for his decision and he decide it, the fact that the
          decision is erroneous does not make tlie award bad on its face
c         so as to . permit its being 'set ·aside; and w.here the question
          referred for arbitration is· a question of construction, which is,
          gencraUy ,speaking, a _question of law, the arbitrator's decision
          cannot be set aside only because the court would itself have
          come to a different conclusion."

                     •
             With the ever widenings ·expansion of international trade and·
      commerce, complex question of private International Law, effect of
      local laws on contracts between parties belonging to different.nations
      are certainly bound to crop up. l\rbitration has been considered a
      civilised way of resolving such dispute~ avoiding court proceedings'.
     There is no reason why the parties should be precluded from referring
      a specific question of law to an arbitrator for his decision and agree·
     to be bound by the same. This approach manifests faith of parties
     in the capacity of the tribunal of their choice to decide even pure a
     question of law. If they do so, with eyes wide open, ~nd there is
     nothing to preclude the 'parties from doing so, then there is no reason
                                .
     why the court should try to impose its view of law superseding the
      '




     -viey; of the Tribun;tl whose decision the parties agreed to abide by.
                                                                           .
     Therefore, on principle it appears distinctly clear that when a specific
     question oflaw is referred io   an arbitrator for his decision including
     the one touching upon the jurisdiction of the arbitrator, th~ decision'
     o\'the arbitrator would be binding on both the parties and it would
G    not be open to any of the two parties to. wriggle out of it by conten·
     ding that the arbitrator cannDt clutch at or confer jurisdiction upon.
     himself by rllis-construing the arbitration agreement.                  ·

          This conclusion is borne out by a long' line of decisions both,
     Indian and foreign to which we would now turn.                               ...
H
                                            .   .
            The earliest case to which we would ref~f is the decision of the
                                                                                  -,,1
                      TARAPO;E co. v. COCHIN SHIPYARD (Desai,};)                  1~9
                                                                       •
          House of Lords in KeTanten Government v. Duff Development Co.                 A
          Ltd.' in which Lord Trevethin in his speech said as uuder:

                      "lf your Lordships should be of opinion that the award
               is bad in law upon its face, it should be set aside, for ihis is
              not in my view, a submission to arbitration of such a nature

.   ,
              that, although the law is bad upon the face of the awan;j, the
              decision cannot be questioned. That happens only wheri the
           ·. submission is of a sp1cific question of law and is such that it
                                                                                        B


              can be fairly construed to show that' the parties intended to
              give up their rights td re~ort to the King's courts and in ·Jieu
              thereof to submit that question to the decision of a tribunal
            . of their own."                                                            c

                 Same distinction was also· brought out"y Lord Parmoor when
           he said that 'the principle applicable where a specific question of
           law has been-submitted to the decision of arbitration is well expressed
           by Channell, J., in Re King and Duveen, 2 in which it was said that
           where a·specific question of 'law is referred to an arbitrator for nis
           decision, the award cannot be set asid.e. on the ground of an error
           apparent. on the face of the award because the question ?f Jaw was
           wrongly decided.' At .a later stage, it was observed that if the· court,
           before which it is sougqt to impeach the award, comes to the conclu-
           sion that the alleged error in law even if it can be maintained, arises      E
           in the decision of a question ot .law directly submitted to the,
        •arbitrator for his decision, t.hen '.he principle stated by-Channel, J.,
           in Re. King and Duv~en apphes, 1s attracted and the parties having               •
           chosen their tribunal, and not having applied successfully to the
           court under;either s. 4 ors. 19 of the Arbitration Act, 1889, are not in
           a position to .question the award or to maintain a claim to set it           F
           aside.' This decision is an authority of the propositidn tha.t where'
        . ·a question of construction is the very point referred fo~ arbitration;
           then the decis.ion of the arbitrator upon thai point cannot be set
           aside by the court only because the court would itself have come·to a
           different conclusion.           ·

               In F,R. Absalom ltd. v. Great Western (London) Garden Village
          Society Ltd.' the contention was that the award was bad by reason
          of an error in law appearing on the face of it. 'l;he submission was


               (!) [1923) All E.R. 349
             . (2) [1913) 2 K.B. 32
               (3) [1933] AU E.R. 616
         140 -
                                                         •
                           . St!PRBMB Coukt REPORtS             (1984] 3 s.c.k .
                    •
        not before the court and a reference to the pleadings had to be made.
        for the purpose of ascertaining whether any specific question of law
     • was in dispute, and Wa3 referred io the arbitrator for his decision.
        The pleadings disclosed that the whole dispute between parties was         "
        as to the am.ount due to the contractor in respect of the value of the
        work done and of the materials ·on the site urio and including a
B      certain pate. In tlie background of this fact, Lord Warrington in
       his speech said that no specific question of construction arose. In
       order to. decide whether.the ii.ward was bad It\! reason of an error of
       Jaw on the face of it, Lord Russel in his ~peech pointed out at page
       621 that it is essential to keep the case where disputes are referred
c     Jo an arbitrator 1n the decision of ,which a question of law. becomes
•      material distinct from the case in which a ~pecific question oflaw
      has been referred to him /or decision.' Thereafter he proceeded to
       state:                .

                   "The authorities make a clear distinction between
         ~these two cases and as they appear to me, . they decide that
           in the former case the court can interfere. if and when any
           error of law appears on the' face of the award; but that in the
           latt~r case no such interference is._ possible upon the· ground
•          that it so appears that the decision upon the question of law
           is an erroneous one.
E
             In reaching this conclusion;' the decision in Ke Ian tan Govern·
       ment v. Duff Development Co. Ltd. was affirmed. On the facts, ·ff·
       it was found that no specific question of law ~as referred to ·tlie
       arbitrator for his decision.

F             In /Jurga Prasad Chamria _and Anr. v. Sewkishendas Bhattar
        !ind Ors'; the award was sought to be set aside inter alia on the          •
       ground that t!11l award was bad on account of an error of law.
       appar,ent on the face' of it. The errors 'of law relied upon were; (a)
       the arbitrator J:iad •admitted as evidence the family settlement and
       the partnership arrangement of 1916, neither of which, though each'
G
       related (it was said) to immoveable property, had been registered
       as required by the Indiaµ Registration Act, and (b) the arbitrator.
    • ought to have held that Anardeyi's suit was in any event barred by
     · limitation. The Privy Council first noticed the issues settled by
       fanckridge. J.; amongstthem were ·the two following:


         (I) A.I.R, 1949 (P.C.) 334
                  TARAPORE co.iv. COCHIN SHIPYARD (Desai, J.)                141

                    "l(b) Is' the agreement dated 16th November, 1916,             A
            relating to the alleged family settlement valid or admissible
            in evidence? .
                    (9) Is the plaintiff's ··claim or any portion thereof
            barred Jjy limitation?,,
               After tnese issues had been settled, the parties agteed to refer
                                                                                   B
        to arbitration "the outstanding matters in the suit." In a motion for
• >
        setting aside the awardjt was urged that there was an error of law
        apparent on the face of the award both with regard as to the
        admissibility of the alleged fa~ily settlement and about the suit of
                                                                                        ..
        Anardeyi being barred by limitation. Rejecting the motion, the Privy
       'council observed as under,
            •
                   ·"However, tl:iat may be, their Lordships are satisfied
            that the two points oflaw as to which it is said the arbitrators
            error vitiates the award were specfically referred to him to
            decid~ and if this' is so, it would be <:ontrary to well-establis-
            hed principles such as are laid down in re King and Duveen              D
            and F.R. Absa/om Ltd. v. Great West (London) Garden Village
            Society Ltd., for a Court of law to interfere with the award
            even if tlie Court itself would have taken a different view of
            either·ofihe points of iaw had they been before it."
              Turning to the decisions of our Court, reference may first be         E
        made to Seth Thaward1~ Pherumal v. The Union of India'. Jn that
        case, the question was_ whether the award was -bad on account of
        error of law apparent on the face of it, as provided in Sec. 16(!) (c)
      . of the Arbitration Act. Examining this contention, ·this Court
        observed as under:           ·
                   "This covers cases in which in errOi of law appears on
                                                                                    r
          ,the face of the award. But in determinin!!'what such an error
           is, a distinction must'be drawn between cases in which a ques-
                                                         .
           tion of law is specifically referred and those in which a decision·
           on a question oflaw is incidentally material (however neces-
                                                                           .



           sary) in order to decide the question actually referred. If a
                                                                                   G'
                                                                                   :1
           question of law is'specifcally referred and it is evident that•'
           the parties desire to have a decision from the arbitrator about
           that rathei'then one from the Courts, then the Courts will not
         , interfere, though even there, there is authority for the view
         · that the courts will interfere if it is apparent that the arbitrator
                                                                                   ff.
         (I) [1955] 2 S.C.R. 48
                                                             '
       142            SUPREME COURT REPORTS                        [1984) 3 S.C.R.

 A          has. acted illegally in reaching his decision, th~t is to say, if
           he has decided on foadmissible evidence or on principles of
         · construction that the law does 1,1ot contenance o,r· something
           of that nature. See the speech of Viscount Cave in Ke/antan
           Government v. Duff Development Co. at page 409. But that
           is not a matter which arises in this case.
B
                    The law about this is, in our opinion the same in
          ·England as here and the pril)ciples that govern this class of
            case have been reviewe.d at length and set out with clarity by
          . the House of Lords in F.R. Absalom Ltd. v. Great Western
            (London) Garden Village Society and in Ke/antan Govern-
·C          ment v'. Duff De~efopment Co. In Duiga Prasad v. Sewkiii.·
            hendas · the Privy Council applied the, law expounded in ·
            Absa/om's case tci India; see also Chainpsey Bhara & Co. v.
            Jivraj Ba/loo Spinning and.Weaving Co. and Saleh Mahomed
            Umer Dossa/ v. Nathooma/ Kessamal. The wider language
         · used· by Lord Macnaghten in Ghu/am Jiliini v. M uh~mmad
           .Hassan<b.aci reference to the revisionail ·powers of the. High
            Court under the Civil Procedure Code and must be. confined
            to the facts of that case where the question of !aw· involved
            there, namely, limitation, was spec!ficaUy referred. An
           arbitrator is not a conciliator and cannot ignore the law or
E           mi;apply it in.order to do what he thinks is just and reasonable.
            He is a tribunal sel~cted by the parties to decide their disputes
           according to law and so is b01md to follow, and apply the Jaw,
         · and ifhe does not he can be set right by the Courts provided
           his er•or appears on.the fact of' the .•award. The single ex-
           ception to this is when the. parties choose specifically to refer
F          a question of law l\S a seperate and distinct matter."
                              •   p                       -    .
                The Court fl)rther proceeded to examine whether in the facts .
       'Of that . case, the arbitrator was speci'fically asked to construe
        clause ·6 of the contr>ll:t or any part of the"contract or whether any
         question of law was specifically referred. The Court emphasised .
G       the word 'specifically' by pointing out tha_t, parties who made
      a reference to arbitration have the right fo insist that the Tribunal
       of their choice shall decide their dispute according to Jaw, so
       before the 'right.,i:an be denied to them in any particufar matt_er, the ·
       court must be very sure that both sides wanted the decision of the
       arbitrator on a point of Jaw rather than that of the Courts 'and that
     · they wanted his decision on that point to be final. . The Conrt then
       proceeded to examine the various clauses of the contract and held
        tllat tl1is is not the kind of specific reference on a point of law that
                         TARAPORE.CO. v. COClflN SlflPYARD (Desai, J.)    •       143
            _ the law of ar~itration requires. The C_ourt held that when a. ques-          A-
               tion of law is the point at issue, unless both sides specifically agree
             . to refer it and agree "to be bound by the arbitrator's decision, the
               jurisdiction of the Courts to set an arbitration right when the error
               is apparent on the face of the award is not _ousted. The mere faCt
•           , that both parties submit incidental arguments about a point of law -
             · in the course of the proceedings is no~ enough. This decision is an
.
t
    ;
        '
               authority for the proposition that where the parties specifically agree .
               to refer a specific question of law for the decision of the arbitratot,
               and agree to be bound by it, the _Cciurt cannot set aside the award on
               the ground of an error oflaw apparent on the face of it even though
               the decision of the arbitrator may not acsord with the law as under-
               stood by the C"ourt. If on the other hand, the question of law is           c
               incidentally decided by the arbitrator, it is not enough to oust the
               jurisdiction of the Court to set aside the award on the ground that
               there is an error apparent on the face of the award.          ·

                      In M/s Alopi Par shad & Sons .Ltd. v. The Union 'of India'
               the Court reiterated the observation in Seth Thawardas's case and           'D
               observed that if a specific question is submitted to the arbitrato~-
               and he answers it, the. fact that the answer involves an erron~ous
               decision in point of law, does-not make the award bad on its_ face
               so as io permit of its being set aside. _In the facts of the case, this
               Court agreeing with the High Court held that ther'e is no founda-
               tion-for the view that a specific reference, submitting a question of
               law for the adjudication of the arbitrators, was made. It may be
               st3cted in passing that a brief reference to the claim put forward
               before the arbitator on behalf of.the appellants in th.at case, set out
             . at page 798 of the report, would clearly, show that no specific
               question -of law was referred by the parties for .the decision of the
              arbitrator. Mr. Pai learned counsel for the respondent pointed out
               that the Court has also observed following the deCision, of the Privy
-~
            , Council in Chatnpsey Bhara and Company v. Jiv.aj Bal/60 Spinning
               and Weaving Company Ltd'., that 'the- extent of the jurisdiction of
               the court to set aside an award on the grouµd of an error in making
               the award is well-defined. The award of an arbitrator may be set,           G
             . aside on the ground of an etror on the face thereof only when in
               the award 011in any document incorporated with it, as for instance,
               a note appended by the . arbitrators, stating the reasons for_ his
               decision, there is found some legal proposition which is the basis of
               the award and which is erroneous. This observation does not help

                (I) J[1960]'2 S.C.R. 793    __
                (2) Law Report$Q l-A· 324
                                                                                               1-



                                  ..
      • 144                 SUPREME COURT REPORTS                 (19&4) 3 S.C.R •
                                                         •
A         in deciding the point under discussion and just after this statement,
          there follows the obsevation about the effect of referring a specffic-
          question of Jaw for the decision of the airbitrator and the jurisdic-
          tion-of the Co~rt to set aside 'the award on the grol!nd 'that !herds


B
     ..   an error of law apparent on the face of it.
                                                                     '
             .In Union of India- v: A.L. Ra//ia Ram1 this Court after referring
       to the decision in Champs.y '/Jhara and Coinpany reaffirmed that,
       the rule in that decision does not apply where questions of law
       are-specifically referred to the arbitrator for hii decision; the award
       of the arbitrator on those questions is binding upon the parties, for
       by referring specific questions tlw parties desire to -have a decision
-c     from the arbitrator on tho§e questipns raiher than frqm the Court and
       the Court will not, unless it is satisfied that the arbitr.ator had procee-
       ded illegally interfere with the decision. After referring .to the decl-
     . sion hereinabove examined by' us, the Court came to the conclusion
       that no specific question of Jaw wer.e referred to the arbitrator's            ·-,,,_
       the decision whereof is binding upon the parties.                          .
0
              In M/s Kapoor Nilokheri ·Co-op. Dairy Farm Society Ltd. v. •
     • Union of India and Others• the Court agreed with the submission
       .on behalf of the respondent Government of India that the appellants
        having specifically stated that their clai~s are b~sed on the agree-
        ment and on '.nothing else and all that the arbitrator bad to decide
E     . was as to the effect of the agreement, the arbitrator bad really to
        decide a question . of law, i.e. of interpreting the document, the
        agreement dated May 6, 1953 and therefore the decision is not
        open to Challenge. In fact, this decision is hardly of any assistance
        and we leave it' at that.
F            In N' Chellappan v. Secretary, Kera/a State Electricity Board
       & Anr•. by a consent order, the umpire was _appointed as the sole                       •
      arbitrator, and the respondent-Board without a demur participated
      in the proceedings before the umpire and took the chance of an
      award in its favour, this Court said ~hat it cannot turn round and say
G     that the umpire. bad no inherent jurisdicti6n and therefore its parti-
      cipation in the proceedings before the, um.pi re is of no avail. This deci-
      sion is not of much assistance on the point!undet discussion. Mr. Pai
       on the other band urged that the jl/risdiction of the afbitator could
      not be determined by him nor can he arrogate jurisdiction to himself

             (I) (1964] 3 S.C.R. 164
            (2) A.LR. 1973 S.C. 1338
            (3) (1975) 2 S.C,R:1*!1
•I
-
~                      •     TARAPORB co. v. COCHIN sHiPYARD (Desai, J.)
                               ,
                  by mis-construction of the contract and thereby clutch at jurisdiction
                   and in such a situation, the court always retains to itself to set at
                   naught.the award on the ground of an error of law apparent on the
                                                                                          145,




                   face of the award. 111 terms, he stated that the issue about the
                   jurisdiction of the arbitrator has never been parted with by . the
                   Court-Generally speakings, common law courts were very reluctant
                                                                                                   B
                 . to part with its jurisdiction to' set at naught an award on the ground
                 ·that-the_ arbitrator had no jurisdiction to entertain ·and. decide the
                   dispute. The Court went so far as to say that the arbitrator cannot
                   confer jurisdiction upon himseif by deciding in ·its own favour some
                   preliminary points upon which its jurisdiction rests. In fact, that is
                   a non-issuse. It cannot be dispute.d that even the question of jurisdic-        Cl
                    tion of an arbitrator can be the aubject matter of a specific reference.
                    If.the parties agree to refer the specific question w)lether th~ dispute
                    raiseq is covered by the arbitration agreement, it becomes a
                    specific question of law even if it involves the jurisdjction of the
                    arbitraor _and if it is so, a. decision of.the arbitrato_r on specific ques-
                    tion referred to him for decision even if it appears to be erroneous           D
                  . to the Court is binding on the.parties.· The decisions relied upon by
                    Mr. Pai do not derogate from this legal position... We may briefly
                    r~fer to those decision

                         In Produce Brokers Co. Ltd~ v. Olympia Oil aniJCake Co. Ltd.,1
                  it was held that "if the question which the arbitrator takes upon                E
                  himself to decide is not in fact within the' submission the awa_rd is a
         . >,.    nullity. The arl/itr~tor ~annot make his award binding by. holding
                  contrary to the true fac.ts when the question which he !lffects ·to
                                                                                                        i
                  determine is within the submiision." Let us emphasise the ratio of
                   the decision that the arbitrator takes upon himself to decide a
                   question not within the submission. · This would mean that the                   F

    ..             question of law was not specifically referred to thy arbitrator for his
                   decision but it was incidentally raised. In fact, nowhere .it was
                   contended that ariY specific question of law was referred to the
                   arbitrator and if so what would be its effect on the binding character
                   of the d.ecision was. ever raised in that case. In that cllse after an·
                   answer was returned to the Special Case submitted for the opinion                E
                   of the court, the Committee of Appeal unreservedly accepted the
                    said answers upon the construction of the contract as a matter of
                    law·apart from the custom of.the trade, but proceeded further to
                    hold that there was a long established and well-recognised custom of
                    the trade .in cases of re-sales that buyers under the forrn of contract
                                                                                                       H

                       (I) [1914-!Sl AU ~·R· 133
        146                    SUPREME COURT REPORTS             [1984] 3 S.C.R,               ~··
                                                                          •
        in question impliedly' agreed with their sellers tlrat they would accept
        the original Shipper's appropriation if passed on without delay. On
        a motion by the buyers to have the award. set aside, of which notice
                                    .                     .
        was glven, the Divisional Court held that the arbitrators had no
        jurisdiction to find conclusively the existence of a trade custom, and
        the Court of Appeal on the authority of prr.cedents bui against their ·
    B   own opinion, affirmed the decision. The appellant-seller's company
                                                                                         . 4'.,
        appealed to the House of Lords. ,Lotd Loreburn in his speech -
        observed that 'these men of business made contracts and therein
        agreed to arbitrate· upbn all disputes arising ·out of 'their contracts.
                                                                                   ' '
                                                                                   . '     i
        Yet there Iiave already been seven distinct stages of argument and·
        decision, four of them in courts of law, upon a dispute arising on
    c   those contracts, and the end is not .yet. I do not know how many
        more stages there will be. Pa1ties have a right to prefer .what some
        may consider the imperfect though expeditious wisdom of arbitrators
        to the slower and more .costly justice of His Majesty's courts. ·It is
         to be regretted when they have to encounter the inconveniences of
    D   both methods· with the advantage 01. neither." Approaching the
        matter from this angle, the appealwa:s allowed and the decision of.
        the 9ommittee of Appeal, taking note of the custom of th~ trade,
        allowed the award to stand. This decision can in no way help the
         respondent.

              In Attorney Oeneral For Manitoba v. Kelly and Others1 it was
        observed that "Whenever therels. a difference of opinion between
'       the parties as to the. authorify cqnferred oh an ·umpire or arbitrator
        under an agreed submission the decision rests ultimately with the
        court and not with the umpire or arbitrator." · This is predicated
        upon a proposition that common ll!w courts were reluctant to part
        with their jurisdiction to set,at·naught an award if th~ arbitrator
                                                                                                  '
         confers jurisdiction upon himself by deciding in his own favour some
         preliminary point 'Upon which his jurisdiction rests.
              Mr. Pai also referred to the decisions of.the Privy Council in
        Champsey Bhara & Co, and Hirji Mu/ji v. Cheong Yue Steamship Co.
    G   Ltd.• Both these decisions. are of no assistance on the question
        about the reference of a specific question of law touching upon the
        jurisdiction of the arbitrator f~r his deeision and its effect. Jn fact.
        the decision in Champsey Bhara' s case clearly turns upon as to what
        constitutes an error of Jaw apparent on the face of the award .
              •
    H
         (1) [1922] All. E.R. 69
         (2) [1926] All. E·R· SJ
                         TARAPORE co. y. COCHIN SHIPYARD (Desai, J.)              141
                  The next case referred to was Heyman & Anrs. v. Darwins Ltd. 1         A
            It reasserts that as a rule the arbitrator cannot clothe himself with
            jurisdiction.                                         ~-

                     Turning to the decisions of this Court, .reference was first made
             to Jivarajbhai Ujamshi Sheth & Ors. v. Chintamanrao Balaji & Anr.•
•'           Shah, J. speaking for himself and Jilstice Sarkar at page 499 observed      'a
           . that 'this is not a case in which the arbitrator Jias committed a mere
             error of fact or law in -reaching his conclusio11 on the disputed
• >•        ·question >Submitted for his adjudication. It is a case of assumption
             of jurisdiction not poss_essed by him, and that renders the award 1 tci
             the extent to which it is beyond the arbitrator's jurisdiction, invalid".
             It may be pointed out that these observations are in the context of
              tlie facts of that case and there was no contention before the cou.rt
              that any specific qu,estion of law touching upon the jurisdiction of
              the arbitrator was referred to-for his:decision by the parties.
                   The last decision in this context referred to was Dr. S:B. Dutt
            v. University q{ Delhi. 8 In that case the .arbitrator gave by his           D
             award a direction to enforce the contract ·of personal service. · This
           _ wautated as an error of law apparent on the face of the award and·
             the award was set aside. Again it may be pointed out that tpe
             reference to the the point set out in the .letter of reference extracted
             at page 1240 clearly spells out that no specific question oflaw
             touching upon the jurisdiction of the arbitrator was referred to the         E
             arbitrator for his decision.

                   ' On a conspectus of these decisions, it clearly transpires that if
             a question of law is specificially referred .and it becomes evident that
                                                                                              ,,
             the parties desired to have a decision on the specific question from _
             th_e arbitrator about 'that rath~r than one from court, then the court      -F
             will noi interfere with the award of the arbitrator on the ground that
             th'ere is an error of law apparent on the face of the award even if
             the view of ·taw taken by the. arbitrator does not.accord with the
     --~
             view of the court. This view of law taken in England was stated by
             this Court to be the same in this country and since the decision in
             Seth Thawardas's· case which follows earlier decisions in England            c
            ·and India, it has not been departed from. Th_e view canvassed for
             by Mr. Pai that common law courts were very reluctant to part with
              its jurisdiction has hardly any relevance where a specific qu,estion of


              (I) [1942! (I) All E.R. 337.                                                H
              (Q) [1964] S SCR 480.
              (3) (195?1 SCR 1236'
    •     148                    . SUPREME COURT REP ORTS            [1984) 3 s.C.R.

         . law including the one touching the jurisdiction of the arbitrator ·is
            referred to the arbitrator for his decision. Even if the decision of
         · the arbitrator doi'l not ac.cord with the view of the court, the award
          . cannot be set aside on the sole ground that there is an error of law
            apparent on the face of it.
B                  Before we· conclude on this 'pojnt we must take note 6f a
            contention of Mr. Pa.i that the respondent cannot be 'estopped from
            ·contending that the arbitrator had ·no jurisdiction lo entertain the
            dispute as the respond~nt agreed to the submission without prejudice
            to its rights to contend t,o _the contrary.. It is undoubtedly true that
         'in the letter dated March 29,1976.by which the respondent agreed
c           to refer the dispute to the arbitrator. it was in ternis stated that the
            reference is ·being made without prejudice to the positi.on of the
            resppndent as adopted in the l~tter meaning thereby without prejudice
            to its rights to contend that the claim of the appellant is not covered
             by the arbitration clause. In the context in which the expression
D           'without prejudice' is us.ed, it would only mean that the respondent
             reserved the right to contend before the arbitratpr that the dispute
            is not covered by the arbitration clause. It does not· appear that
            what was reserved ~as a contention that, no specific question of law
            was specifically referred· to the arbitrator. It is difficult to spell out
           ,such a contention from the letter. ·And the respondent did raise the
E           contention before the arbitrator .that he had no jurisdiction to
            entertain the dispute as it would not be covered ·by the arbitration·
            clause. Apatt from the technical meaning which the expression
            'without prejudice' carries depending upon the context in which it is
            used, in the. present case on a l?roper reading of the _correspondence
           .and-in· the setting in which the term is used, it only means that the
F
            re.spondent reserved~to itself the right to contend before the arQ,jtartor
            that a dispute raised or the claim made by the 'contractor was not .
            covered by the arbitration ·clause. No other meaning can· be as'signed
            to it. An action taken wi~hout prejudice to one's right cannot
        • necess.arily mean that the entire action can be ignored by the party
          ·taking the same. In this case, the respondent referred the specific
         . question of )aw to the qrbitrator. This WflS ·according to .the
            respondent without ptejudice to its right to. contend that the c.Jaim
            or the dispute. is not covered by the arbitration clause. The
            contention was to be before the arbitrator. If the respondent warited
            to ~sscrt that it had reserved t9 itself the right 'to con!e.nd that no
H           specific question of law was referred to the arbitrator, in .the first
            instance, it should not have made the reference in the terms in which
             it is made but should have agreed to the proposal of tile appellant
                       tARAPORE   co. v. COCHIN SHIPYARD (Desai, J,)           149

         to make a general reference. If the ·appellant insisted on the                   A
         reference of a sp~cifi:c .question which error High Court appears to
         have committed, it could have declined to make .the reference <Of a
         specilkquestion of iaw touching his jurisdiction and should have
         taken recourse to the. court by making an appi'ication under Sec.
•        33 of the Arbitration· Act to have the. effect of the arbitration agree-
                                                                                          B
         ment determined by the court. Not only the re'spondent did not
    I    have recourse to an application under Sec .. 33 of the Arbitration Act,
• >
         but ofits own it referred a specific question of Jaw to the arbitrator
         for his decision, participated. in the arbitration proceeding in~i(ed,
        ·the arbitrator to decide the spedfic question and fook a chance of a
         decision. It cannot therefore, now be permitted to turn round. and
                                                                                      c
         contend to the contrary on the nebulous plea that it had referred
        ·the, claim/dispute to the sole arbitrator without prejudice to its right .
         to contend to the contrary. Therefore, there is no merit in the
                      of
         contention Mr. Pai.                                                    •

               , In this case, as earlie~ pointed out a _specific question as to      D
           whether the claim of compe!lsation made by the appellant-contractor
         · and demurred arid disputed by the respondent wQuld be covered
           within the scope, ambit and width of the arbitratioi. clause, wa~
           specifically referred by the parties for the decision of\the arbitrator.
           Therefore, it is a case where a specific question 'of law touching upon
        ,Jhe jurisdiction of the arbitrator was referred for the decision of the          E
           arbitartor by the parties.' Even if the view taken by the arbitrator
           may qot accord with the view of the.court about the scope, ambit
           and· wi<!!h of the arbitration clause, the award cannot be set aside       •
           on the ground that there is an efror of law apparent on the face of
           the award. The view taken by the High Court is palpably untenable
           a.nd has to be reversed. On this short paint, the appeal can be                F
           all6wed ... However, it was strenuously urged by both the sides that
           the dispute arising out of the claim for compensation made by. the
           appellant on account of the increase in the cost of the piie driving
           equipment and technical know-how fees would or would not, be
          covered by the first Pilragraph of Clause 40, we would briefly examine
           the same to point out that it would be covered.                            G

                In order to ascertain whether 'the claim for compensation for
          incr_ease iu the price of pile driving· equipment and technical know-
          h9w fees would be covered by the arbitration clause, it is necessary
        · briefly to refer .to the negotiations and discussions leading to the
                                                                                      H
          formation of the contract for construction of the Repair Dock and
          the Building Dock. The value of the works to be executed was
        150                 SUPREME'couRT REPo~'rs                [1984j ~ s.C.R.
   . A over Rs 24 crores. In respect of the construction of Repair Oock,
          there was only the tender of .the appellant land. in respect of the
           Building Dock,. there were two tenders:· one of the appellant and
           another by M/s National mji!ding Construction Corporation, the
           tendered valueo of the latter being· double . that of. the former.
           Indisputably, tqe respondent had a very limited or realistically no
                                                                                       .. '
  .• B choice. In such a situation the Tender Committee took notice of
           the fact of the. pol:lr response to the invitation to tender. The
           Committee took notice of such salient features of the work being the
                                                                                       ~'   .
           complexity and magnitude· of the works to be undei'taken by any
        · Indian Contra9tor and the non-availability of plant and equipment
     C required for the works and, more especially that if the contractor· ·
           was to procure the specialised ·equipment required for the works,
•          there  was hardly any assurance that after the works were over, the
           machinery would be so much depreciated to have a11y substantial
     · •use or utility to the contractor. Iri the 'invitation to te.nder, it was
           indicated that requisite foreign exchange for importing pile driving
           equipment and machinery, spares and technical know-how amounting
           to about Rs 2 crores in all would be made available to the contractor
           from the 11th Yen Credit from Japan, subject to his getting indi:
           genous cloorance and providing·d.etailed justdication. Annexure IV
           to the General Conditions of Contract clearly. specifies that the
           tendereis while quoting shall give separately the full details' of the
     E ·equipment for which they would be requiting foreign exchange
        · assistance. And they shall also i~dicate the financial implication if
           any, . for providing not providing the foreign exchange assistance
           indicated for th~ various equipments. Two things emerge from
           recital of the facts' herein enumerate<;l i'n the course of formation of.
           tbe contract: (1) that the pile driving equipment will have to be
     F ·imported from outside India and technical know-how fees will. have
           to be paid both in foreign currency and (2) this would necessitate
           investment of about Rs 2 crores by the contractor. The_ contractor
           in his letter dated July 14,1972 specifically invited the rospondent to
            confirm the modifications in the terms of contract as set out therein.
     G Jn paragraph 31 (E) (!),the contractor states that all foreign exchange-
            for the equipment, spares, technical know-how and hiring of experts
           shall be provided to the contractor and that the total foreign
         · exchange on all these accounts will be about Rs 2 crores. A sort of
            an assurance was thus extended to the contractor thatthe same
            wquld .be made available to him from the 11th Yen credit from
   H Japan. This is.not disputed. It is also an admitted position that
          ,the neeessary equipment, machinery, spares and technical know-how
            were not available from Japan and the availability of the I Ith
l                                    •




                    !AkAl>oRilcp. ~. cocit1N sarPYARD (Desai, J.)                          151

Yen credit from Japan lost all significance. Further the respondent                              A
by its letter dated January 24, 1973 to the appellant while accepting
the tender of the appellant.on behalf of Cochin Shipyard Limited
specifically stated as under:

              ''You shall provide at your cost all construction' plant
       and machinery (including that requiring import) for all items                             B
       of work including RCC piling and Steel Sheel Piling Works.
     1
       Departmental machinery likely to be made. available for issue
       to the Contractor shall be as -in Annexure IV of the General
       Conditions of Tender.

              You shall furnish an inventory. of all plant and                                   c
       machinery propos.ed to be used. on the works including items
       of imported machinery with probable date of their availability
       at site for use or! the work. This should match with the
       Detailed Working Programme indicated as above."

           At this stage· a reference to the.addition~! Terms and Condi-                         Q
    tions/Modifications to the General Conditions and Specifications of
    t~~ Departmental Tender Documents, \(ould be advantageous. It
    _reads as under:           •                     ·

                  "All Piling Equipment shall . be procured by the
       Contractor ........................ .... 1• ........... ; ......................... .     E
        ............. Selection of equipment will be done by the Contractor
       i11 consultation . with the Cochin Shipyard authorities. No
       hire charges for the equipment procured by the. Contractor is
       payble to the Shipyard .................................................. ..
        ................ Requisite foreign exchange, for importing piling
       plant and machinery, spares, technicai know'-how and hiring                               F
       of experts necessary for both the Dock Works,videWork
       Order ........ for Repair Dock etc., amounting to about Rs 2.00
       crores in.all will be m1de available to ·the Contractor from
       the ! Ith Yen credit subject to his getting indige~ous clearance
       and proyiding detailed.justification"                                           .
                                                                                                 G
        It is thus unquestionably established that the appellant whose
  tender was accepted after negotiations and scrutiny by the Tender
  Commitee was expected to invest Rs 2 crores in importmg pile
  driving equipme)Jt and technical know-how fees. The tender was
  accepted and a formal contract was entered into on his basis. 1n"                              ff·
  works contract of such magnitude, the value whereof was over Rs. 24
· crores, and which was being undertaken by an Indian contractor for
                                                •



       152                   SUPREME COURT REPORTS             [1~84] 3 s.c.R..     · ~j
A     the first time negotiations prior to the finalisation of the contract
      and tlie correspondence leading to the formation of contract supply
      the basis on which contract was finally entered into. Undoubtedly,
   . if in th'e final written contract, there . is something contr~ry to the
      basic understanding during the formative stage of the contract, the
      written ~oiltract would. prevail. But if the contract does· not indicate
                                                                                1
B     to the contray and the assumptions appeared to be the foundation·
                                                                                     ' .
      of the contract obviously that aspect cannot be overlooked while
      determining what were the obligation undertken under th, formal
      contract. It may be recalled that the two alternative rates were .
    ·quoted.by the_ contractor: (i) the respondent were to Import the. pile··
      driving equipment and technical _know-how for its optration, the
c     same would be leased to the contractor at negotiated fates or (ii)
      the contractor were to impor.t the same the rates be paid to the con-
      tractor. The second alternative was accepted· by the parties on the
      f1mdamental assumption that the investment in this behalf. would be
      Rs 2 crores. This is the agreed position on which contract was
D   . entered into. To continue the narrative, it may be pointed out that
      this fundamental foundation of the contract not left to guess work,
      but is specifically referred to in the.notice inviting tender and in Ille
   · specification$ and modifcations as addenda to the General Comli-
      tions of Contract. It was clearly understood between .the parties
      that the contractor has to· invest roughly Rs. 2 · crares in foreign, ·'
E·    exchange for i~porting pile driving equipment and technical know-
      how fees without which this work could never have been .undertaken
      and without which it wonld not have been entrusted . to the
      contractor. The contractor when be quote his terms must obvimrsly ·.
      have made appropriate calculations, one of which in this case
      appears to. be that it will have to invest Rs. 2 crores in foreign
F     exchange and this fact flies in the face that aftrer the work w~s over
      the imlJor"ted machinery would depreciate to this extenfthat it would
      h.ave h~rdly any use of utility to the contractor ~s noticed by the
      Tender· Committee. The rates quoted by the contractor were
      obviously interrelated to the basic assumption. The fact that such
      was also also the understanding of the respondent may now be
G
      pointed out.
             The respondent by its letter dated July 31, 1973 to Industrial
       Adviser (HME), Directorate General of Technical Development
       requested him .to issue· necessary clearance to the appellant fot
     · import of the equipment set out in the Annexure to the letter on the
H
       ground that the appellant tried its level best to get the equipment
       from the Japaneses sources, butthey could not get positive resitive .
                                '             . '
                        TARAPORE   co. v. cocillN SHIPYARD (Desai, J.)         153
             response for such equipments. They had also tried their best to get       A
           .s~itable offers from U. K., U. S. A., USSR, Canada,           West Ger-
             many and Holland. It l"as also pointed aut that the respondent itself
             also made independent enqujries in· Japan for getting suitable offers
             for tl1e above equipment without success. Thus it . becomes clear'
             that to the knowledge of the respondent, the 11th Yen Credit
•         · became irrelevapt. The Government of India by its letter dated             B
     j       September 1,1973 to the respondent conv(>yed its approval to the
            release of;the foreign exchange in favour of the appellant to the
             extent of Rs 2 ILSO lakhs (Rupees two crores eleven lakhs and eighty
            thousand only) equivalent to DFL 9, 442, 7.00 at the specified exc-
            hange rate. Therafer the appellant by its letter. dated May 28,1975
             amongst others requested tjie responde.nt to take note of the fact that
             the tendered tales were based ou certain total cost of machfoes which
                         .
            Iias since gone up considerably  "
                                                   rendering the rates' no longer ·
            workable; The contractor proceeded to point out the utter irre-
            levancy of the rates in view of the higher outlay of imported.
            machinery and technical know-how. It pointed out the loss sustained        D.
            by the contractor and requested fqr compensatfon in this behalf.
            This was followed by the letter dated Jnly I, 1975 by the contractor
            io the respondeht, emphasising the- fact that ihe tendered rates had
            become - unwofkable and unrealistic owing to the incre~se in the cost
            of equipment. know-how etc. as a result of the increase in the foreign·
            exchange rate of Dutch Guilders as related to the Rupee. In response
            to the last letter the respondent replied by. its, letter dated July 2,
            1975, relevant portion of which may be extracted:

                      "In this connection, a kind reference is invited to your ·
              letter dated the 14lh July, 1972 (which forms a part of the
               contract documents) wherein you had indicated that the rota/            F
              foreign exchang~. required by you for the equipment; spares,                  •
J
             'technical know-how and hiring of experts, was expected to be
    "'\        about Rs 2 crores. From the d.ata enclosed with your . letter
              under reply, it is seen that the foreign exchange.expenditure
               incurred by you SO· far in connection With this Contract had
                                                                                       G
              been less than Rs 2 crores. In the circumstances; it is difficult
              to accent the position that your tender was based on assum-
              ptions indicated by you and that the rates for pile driving
              should now be revised.:'

                This letter furnishes proof, if one was needed that parties were
                                                                                       H
          ad idem that the investment for imported pile driving equipment
          and foreign exchange know-how would be about Rs 2 crores. The
                         SUPR~ME COURT REPORTS                  [19&4i 3 s.c.k. •

A       respondent does not .contest the claim for ~ompensation under this
        head as is npw sought to. be done on the ground that as the contrac-
        tor had to provide imported pile drivjng equipment and technical

 .     know-how, the respondent is not entitled to compensation even _if
       the initial estimate has been found to - be unrealistic .. On the
       contrary the claim for compensation 1s disputed and controverted on
B.     the'gr0und that the foreign exchange expenditure ·incµrred by the'·
       contractor so far in connection with imported pile driving equipment
      ·and technical know-how has been less than Rs 2 crores. From this
       correspondence, it. wolud emerge that both the parties were agreed
       that the.contractor wonld have to invest Rs 2· crores in foreign ex-
       change for importing pile driving equipment and· technical know-how
c      wh.ich could only be used after approval of the same by. the respon-
       dent. The appellant by its letter August 9; 1975 contended. that
       escalation of expenditure under this head is taken care of in the
       contract .and more speCifically in clauses 13 and ~ 6 o( the works
       order: W'e would have occasion t~ refer to these clauses. a little latet.
       The respondent by its letter dated· August 29, 1975 reasserted its
D       position· that the foreign exchange element of the expenditure
       incurred by the contractor works-out to Rs 1.96 crores, ·which is
       foss than the figure of Rs. 2 crore.s that was expected to be invested
       in foreign ·exc4ange-which was to be provided by the contracto.r, .
       The respondent.also referred to th~ assessm~nt of e.<penditure made
     · by the contractor as per its letter dated July 14,1972. This has
       already been referred to by us. The respondeni further asserted that
        the estimate so ma'!te till that date has not been exceeded and tJ1eie-
        fore, any argument based on fluctuation in the exchaqge rate is not
        valid or tenable. It may be repeated that the refusal to entertain the
        claim for compensation was ·predicated upon. the. estimates having
         not exceeded the basic. minimum of Rs. 2 crores by the contractor on
I'      which rates were worked out and agreed, and not· that such claim
        cannot be entertained under the contract. By its Jetter dated Sep-
        tember 18;1975, the contractor reiterated it~· position; In its letter
         dated October 6, 1975, the respondent when it was faced with the
         situation that the expenditure incurred under this head in foreign ex- ·
G
         change had risen to Rs 214.33 lacs i. e. it had exceeded the expected
          investment of Rs. 2 crores·under this head, took !I summerasult ;rnd ·
        stated that the·respondent had at no stage stated that the contractor
        was 'not entitled to'any claim because the amount of foreign exchange
        has not yet exceeded Rs 200 Iak!).s'. One has merely to call attention
        to the two letters dated July '2, 1975 and August 29 1975 to reach
B       the conclusion that tJie respondent has gone back upon its original
       vositio11 and having found that the expenditure under this head has
                           •


                 'rARAPORB co. Y. COCHIN SHIPYARD (Desai, J.)                 BS
                                                                          •
        tgone up beyond the estimated expenditure made a volte face, the two            A.
         positions. so adopted being entirely inconsistent with' each other
         Tl;tereafter, the matter was referred to arbitration. .

                  From the commencement i.e. from tl\e stage of inviting tenders
          and through the negotiations and the finalisation of the contract, at
          every stage, the respondent assured that foreign exchange would be            B
          made available from 11th Yen Credir. As the equipm3nt was not
          available from Jap11'n, the availabilty of Yen Credit becqme otios"
          .from the contractor's point of view. At the instanc,e of and with the
          active participation of the respondent, the contractor made enquiries
        · in various countries and ultimately procured the necessary equipment
                                                                                        c
          and technical know--how which was approved by the respondent and
           imported the same. In the time lag, the price as well as the foreign
           exchange rates in relation to rupee underwent an upward change,
           with the result. that the contractor had to invest, as made out by it
           and not seriously controverted before the arbitrator in all· Rs. 275.40
           lakhs for imported pile driving equipment and spares and Rs. 18,64,          D
           337.61 on technical services-cum-know-how fees and a further
           sum for higher custom duty. Details of the claim have been set out
            in Annexures 1 and 2 reSf>ectivel~ to the statement of claim submitted
            by 'the appellant to the arbitrator. The respondent in its counter-
             statement did not controvert the details of the claim and the expen-
           diturejnvolved under the two heads-_ The whole of the counter·               B
            claim' was concerned with the denial of its liability io compensate
           the contractvr coupled with the contention that the claim would not
           be covered by the arbitration agreement and therefore,· ihe arblt~ator ,
            had no jurisdiction to entertain and adjudicate the claim. ·· It may
            also be mentioned that at,no time since the award, the res;))n1~n t·
                                                                                        F
            ever disputed or questioned the amount awarded "by the arbitrator.·
            It is thus satisfactorily established that the contractor had to invest
- j
            something far in excess of Rs. 2 crores ·which it was expected to
  -1.       invest. ih foreig~ exchange for imported pile drivijig equipment and
            techmcal know-ho_w fe~s. The whole contract was concluded on
            this understanding. Being aware of the fluctuating position in this         G
            b_ehalf, the contractor l:ad tendered two alternative rates for comple·
             hon of the, work as pomted earli~r ; one based on equipment being
             im~orted by the respondent and leased to the appellalJt and alter-
             na~1~ely rat~s on the basis that the contractor would import pile
             dnvmg equrp,ment and technical know-how. In respect of the second
             alternative, which was ultillllitely agreed to between the parties ·1      H
             was clearly and ·unmistakably understood between. the partiest h~l    ..
                                                     •                  •
                                SuPREME COURT REPORTS              · [! 984] 3 s.c.k
 ·A       the contractor would have to invest Rs. 2 crores and the rates were
          co-related to this investment with the knowledge of the fact that
          when work was completed, the equipment would' depreciate to the
          tnne of 75% of its capability and WQnld be hardly of an¥ use to the
          contractor. · The estimated expenditure having far exceeded, a claim
          for compensation would certainly be tefiable .at the instance of the
            .
          contractor. .

                  The High Court quoted  •
                                            clauses 16, 26 hnd 31 in its judament
                                                                             0
            but did nof dilate upon the provisions of the clauses so a:; to co-
                                                                                        ~




                                                                                            .   . 1.


                                                                                                  '

            relate them with Its decisiatl. Clause 16 envisaged a situation where ..
            since the formation of the 'contract any fresh law is enacted which
:.Cl.       has the bearing on the price of materials incorporated in the works
            and/or wages oflabour, the terms of contract shall accordingly be
            varied. Clause 26 provided for supply of materials, plants, tools, ·
            appliances etc. by the contractor. Clause 2 provides for the liability
            of the contractor to supply construction, plant 'and machinery
         .. including the items .to be imported and a further obligation. is cast
D
            on the contractor to Juruish inventory of the same. Clause 3·1
            amongst others, provided that the pile driving equipment shall be
           p·rocured by the contractor, and the selection of equipment shall be
           done by the contractor, in consultation with the responden·t. These
           clauses were presumably referred to in the context of. an arguwent
                                                                                       •,
           that the pnce escalationdause does not cover the claim for compen-
.E
           sation for ~dditional expenditure on imported plant and machinery            . '
                                                                                            x
           and technic)ll know-how because the contract substantially provides
          for the s.ame- to bl supplied by the contractor.' In our opinion, this
           over-simplification of the clauses of the contract involving works pf
          such magnitude is impermissible. The whole gamut of discussions,
          negotiations and'correspondence must be taken into consideration
           to arrive at a true meaning of what was ·agreed to between the
          parties. And in this case there is no room for doubt that the parties
          agreed, that the investment of the. contractor under this head would
          be Rs,. 2 crores and the tendered rate& were predicated upon and
          co-related_ to t)lis undt!standing. When an . ag,eement is predicated
          upon ati agreed fact situation, if the latter ceases to exist the agree-
          ment to that extent becomes irrelevant or otiose. The rat.es j'lay-
          able to J,he contractor were r.elated to ·the investment of Rs 2 crores
          under this head by the contractor. Once the rates bec!lme irrelevant
          on account of circumstances· beyond the control of the contractor,
          it was open to, the. contractor to make a claim for compensation.
          Therefore, it appears satisfactorily est4blished that-the claim arose .
        · while iWplementing t.he contract and in_ relation to the contract.
                  TAR.I.PORE co. v. cocl!iN sHiPYARD (Desai, J.)                157
            •The next question is whetherlhis claim made by the contractor              A
       and disputed by the respondent wpuld be ccivered by the arbitratfon
       clause. The arbitration clause has already been extracted. Even the
       High Court admits th<1t clause 40 is very widely worded. It inter
       alia provides that.all questions and disputes relating to the meaning
     · of the Specifications Estimates, InstructiOns, Designs. Drawings
       bereinbefore mentioned and as to the quality of the Workmanship                  B

t
       or matelials. used on the work or as to the any other questions claim,
       right, matter or thing whatsoever .in any. way arising out of or relat-
       ing to the contract---:--..._-:-_ or otherwise concerning the
     . works or the execution---'---whether arising during the
       progress of the work or after completion----'--;---shall be                     -c
      ·referred to the Sole Arbitrator etc." The scope; width and the ambit
       of the Arbitration clause is of widest amplitude and any claim arising
       out of or relating to the contract or otherwise concerning the works
       or the execution thereof would be covered by the· arbitration clause.
       The material portion of clause 40 which would assist us in deciding
       the questions is .'claim' right matter or thing whatsoever in any way           D
       arising out of or relating to the contract~---------·--­
     . estimates or otherwise concerning the works or-the execution. etc."
         Briefly stated any claim arising out of or relating to the contract,
         estimates or otherwise concerning the works or the execution thereof
         would be covered by the arbitration clause. The question to be, posed
         is ."does the claim made by the contractor arise outof or relates to
         the contract, estimates, or is otherwise <:oncerning works for execution
         thereof? Phrases such as 'claim ·arising out of contract' or "relating
         to the contract' ,or 'concerning t~e contract' on proper constrnction
                                                  •
         would mean that if while entertaining or rejecting the claim or the
         dispute in relation to C:1;tim may be entertained or rejected after
                                                                                        F
    . ,, reference to the contract, it is a claim arising out of contract. Again
         the· language of cl. 40. shows that any claim arising out of the
         contract in relation to estimate made in the contract would be cover-
         ed by the arbitration clause. If it becomes necessary to have recourse
         to the ·contract .to settle the dispute one way or the bther than
         certainly it can be -said that it is a dispute arising out of the contract.   G
         And in this case the arbitration· clause so widely worded as disputes
         arising out of the contract or in relation !o the contract or execution
         of the.works would comprehend. Within its compass a claim for
         compensation related to estimates .and ·arising out ofthe'contract.
         The test is whether it is necessary to have recourse to the contract
         to settle.the dispu.te that'has arise.n.'

       VJ (See Russel onJ\rbitration 20th ed. pag< 85/
                                               •
      158                        SUPREME COURT RllPORTS         [1~84] 3 S.C~R.
A              We may now tum to some. decision to which our attention was
        drawn. The first case we would like to.refer to is A. M. Mair & Co. v.
        Gordhanda.•s Sagarmull.' The Court was concerned with the arbitra·
        tio.n clause drawn up as ; "all matters, question, disp~tes, differences •
        and/or claims, arising out of and/or concerning, and/or in connec-
        tion and/or in consequence of, or relating · fo, the contract etc."
·B      The question arose whether the due date·uJJder the contract was
        extended within the time, earlier reserved. The arbiirator held that
        the due date of the contract has been extend.ed by a mutual agree·
        ment and the respondents were held liable to pay a sum of .Rs. 4,116
        together with .interest at the rates specified in the award. It was
c       contended that the,dispute is not covered by the arbitration clause.
        This Court whilli holding that the dispute is covered by the arbi.trar
        tion clause observed that looking to the rival contentions, ·such a
        dispute, the determination of which turns on the true coristr-uction of
        the contract, would also seem to be a dispute. under or arising out
      · of or concerning the contract. The· test formulated .was that if in
D     . settling a dispute, a reference to the contract is necessary, such   a
        dispute would be cove.red by the arbitration clause: •

              In Ruby General lns.urance Co. Ltd v. Pearey Lal Kumar AIJa
      .Another, this Court was concerned with the ·clause in a. policy of
       insurance .which provided that differences .arising out of the policy
E     .11hall be referred to the decision of the arbitrator. In construing this
       clause, this Court observed as under:.

                  "The test is whether recourse to the contract by wh.ich
            the parties are bound is necessary for the purpose of
            determining the matter .in dispute between them .. If such
 F          recourse to the contract is necessary, then the matter must·
            come within the scope of the arbitr~tor's jurisdiction."

              In Union af India v. Salween Timber Cou;truction (lndia) &
        Ors.• this Court observed that the test for determining the question
        is whether recpurse to the contract by .which both the parties are
 G      bound is necessary for the purpose of determining whether the claim
        of the respondent.firm is justified or'otherwise. If it is necessary to
      . take recourse to the terms of the contract for the purpose of deci-
        ding the matter in dispute, it must be held that the matter is within


 ff    · (1) [i950]S.C.R. 792.
        (2} ]19521 S.C.R. 501. .
        (3) [1%9] 2 S.C.\l. µ4,
                    TAll.APORB CO. v. COCHIN SHIPYARD (Desai, J.)         159

        the scope of the arbitratron clause and the aiitrators have jurisdiction A
        to decide the same. In so stating the proportion of [aw, reliance was
        placed on Heyman & Anr. v. Danvins Ltd.'. in which it was held
        that 'where the parties are atone in asserting that they entered into
    . • a' binding contract, but a difference l!as arisen between them whether
        there has been a breach by one side or the other, or whether circum- B
        stances have arisen which have discharged ·one or both parties froln
        further performance, such differences should be regarded as differe-
         nces which have arisen in resp\'Ct of or 'with .regard to, or 'under'
j        the contract, .and an arbitration clause whicl\ uses these, or. similar
         expressions should be construed accordingly. The Court affirme.a,.
         the decision in Ruby General lnsurance Co. Ltd. case.                   c

             In Astro Vencedor Compania Naviera S. A. of Panama v. ·
       Mabanaft G. M. B. H. ·The J)iamianos' a question arose whether a
       claim in tort would be covered by the arbitration clause? It was
       admitted that "1'e claim for wrongful arres\ is a claim in tort. And D
       it was contended that a claim in to1 t cannot come within the arbitra-
       tion clause. The Court of Appeal speaking through Lord Denning
       held that the claim in tort would be co".ered by the arbitration
       clause, if the claim or the issue has a sufficiently close connection
        with the claim under the contract.
                                                                              E

              In Gunter ilenck v. Andre & ClE. S. A.' the Court (Queen's
       'BenchDivisb n (Commerci'al Court) help thit the words 'arising out
        of clearly extend the mooning than would otherwise be applied to the
        clause were it limited: to 'all disputes ·arising under the ~onfract. F


              In                                            t
                 the facts before .us, th~ respond en~ ~n para of its counter•
        slatement filed before 'the arbitrator spec1f1ca!ly referred to clause.
        16 of the General Conditions of Contract and to the AaditiOnal
        Terms and Conditions Modifications forming part of 'the contract G
        document. In paragarph II, it was stated that th~ claim of the appel-
        lant was completely outside the purview of the contract and the same
        does not fall within the purview of the first paragraph of Clause 40


           O> [19421 A.c. 3S6 @ 366.
           (2) (19711 2 Q.B, 588.
                                                                                 H
                              ..
           (3) (1970) I Lloyd's Law Reports 235,
                                ·-.:   .. : .. L




        160                  SUPREME CO:URT REPORTS               (1984) 3 S.C.l\o
  '
 ·A
      . it was further stated in paragraph 13 that contract provides for
          escalation in certain respects and that is the only escalation which is
         admissible in terms of. the contract ~d the claim made by the
         appellant does not ·come within the escalation clanse nor in the
         agreed. formula relating· to such escalatjon. The contratcor relied
  B
      - upon Clause 13 of 'the .Additional Terms and Co~ditions Modfications
        .which form part of the contract document to sustain its claim. From
         the pleadings, it cl~arly transpires that both the parties had recourse         '
         to the contract which is admittedly entered into in support. of. the
. C      rival contentions and ,therefore, the ,claim made by the ·appellant
      . would be covered by the arbitration clause, which is of the widest
        .amplitud.e, It is thus satisfactorily esfablished that the claim made
        by tlie contractor would be covered by the arbitration clause.


 D
             Mr. Nariman also wanted us to examine whether ihe claill)
       made by the arbitrator would•. be admissible on the principle of
      quantu#i meriut. lt is not necessary to ex~mine this aspect at all° in
      ·the view which we are taking.

 E
              He also wanted us to adopt an approach that the effort of the
       court must be to uphold the award and not to reject it. We, consider
       it llnnecessary to dilate upon it .

 F
              The discussion leads to the .ine.scapable conclusion that a
      specific question.if law touching the jurisdiction of the arbitrator
      was specifically referred to the arbitrator and therefore the arbitrator
      decision is binding on the parties and the award cannot be s~t aside .
 G
      on the sole ground that there was an erro~ Qf law apparent on . the
      face of the award. It is also established that the claim for compensa-
      tion made by the arbitrator which led to the dispute was covered by
      the arbitration clause. The quantum of compensation awarded by

 H
      the arbitrator was never disputed nor qU:estioned. Therefore, the
      High Court was clearly in error reversing the decision of the trial            ,...;
                                                                                     ~ ~.
      901,1rt.
                          TARAPORE CO. v. COCHIN SHIPYARD (De~i, J.)        161

                  Accordingly this appeal succeeds and is allowed and the Judg-
             ment of the High Court is set aside and the Judgment atid order of
             the Subordinate Judge, Ernakulam dated March 30, 1979 is restored
             with costs throughout-


                                                                                       B
•            N.V.K.                                             'Appeal gllowed.
.   _\
                           •




    y




         •


                                                                              -    ;



                                                                              ' j      •·


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.