U.P. ELECT. BOARD THROUGH ITS CHAIRMAN AND ANR.versusM/S. TRIVENI ENGG. WORKS LTD.
- Citation
- 1996 INSC 515
- Decided
- 12 April 1996
- Disposal
- Appeal(s) allowed
- Bench
- K RAMASWAMY
Holding
The Board may charge the industrial consumer under HV‑2 rates for the disputed period, as LMV‑10 was deleted and no substitute exists, and LMV‑2 is not applicable to industrial loads.
Summary
The U.P. Electricity Board (appeal) and M/s Triveni Engineering Works Ltd (respondent) entered into an agreement for electricity supply of 104 kW, which allowed the Board to revise tariffs under Section 48 of the Electricity Supply Act, 1948. The Board revised tariffs on 13 July 1986, deleting the LMV‑10 schedule without providing a substitute, and applied the HV‑2 schedule for large industrial loads. The respondent increased its load to 404 kW on 10 October 1989 and entered a separate contract for the new rates. The dispute concerned which tariff applied for consumption between 1 August 1986 and 9 October 1989; the respondent argued that, after LMV‑10’s deletion, it should be charged under the commercial LMV‑2 schedule, not HV‑2. The High Court held the agreement effective only from October 1989, absolving the respondent of liability for the earlier period. The Supreme Court reversed, holding that the industrial consumer must be charged under HV‑2 rates after LMV‑10’s deletion, as LMV‑2 is for commercial establishments, and directed the Board to revise the bill for the earlier period (Feb‑July 1986) at the pre‑revision rates. The appeal was allowed and no costs were awarded.
Issues considered
- Whether the deletion of the LMV‑10 tariff schedule entitles an industrial consumer to be charged under the commercial LMV‑2 schedule.
- Whether the Board, under Section 48 of the Electricity Supply Act, 1948, can apply the HV‑2 tariff to the respondent for the period between August 1986 and October 1989.
Legislation cited
Subjects
Judgment
A U.P. ELECT, BOARD THROUGH ITS CHAIRMAN AND ANR.
v.
M/S. TRIVENI ENGG. WORKS LTD.
APRIL 12, 1996
B [K. RAMASWAMY AND G.B. PATTANAIK, JJ.]
Elect1icity Supply Act, 1948 :
S.48-Revision of Tmiffi-Under an agreement between the respondent
C indusoy and the U.P. Electricity Board, the Board revised tamffs and deleted
LMV-1(}-He/d, on deletion of LMV-10 w.e.j: July 31, 191!6, and the respon-
dent being an industlial unit, the respondent is liable to pay the charges for
electiicity consumed between August 1986 and October 9, 1989 under HV-2
rates.
D CIVIL APPELLATE JURISDICTION : Civil Appeal No. 7468 of
1996.
From the Judgment and Order dated 4.5.95 of the Allahabad High
Court in C.M.W.P. No. 23865 of 1990.
E B. Sen and Pradeep Misra for the Appellants.
Sanjeev Anand for the Respondents.
The following Order of the Court was delivered :
F Leave granted.
We, have heard learned counsel for the parties.
This appeal by special leave arises from the judgment and order
dated May 4, 1995 made in W.P. No. 23865/90 by the High Court of
G Allahabad. The admitted facts are that the respondents had entered into
an agreement for the supply of electrical energy, initially of 104 KW. The
load was mixed type load for industrial purpose as well as for light and
fans of the factory under clause (8) of the agreement. Section 48 of the
Electrical Supply Act, 1948 empowers the Board to revise the tariffs from
H time to time. One of the conditions under clause (8) read as under :
290
U.P. ELECT. BD. v. TRIVENI ENGG. WORKS LTD. 291
"8(a) The Consumer shall pay for the supply of electric energy at A
the rates enforced by the Supplier from time to time as may be
applicable to the Consumer.
Provided that in the event of alternative rates being available for
that category of load, the consumer shall have the option to choose
the tariff that suit him best. B
(b) The rate Schedule applicable to the consumer at the time of
execution of this agreement is annexed hereto as Annexure.
(c) The rate schedule above mentioned met at the discretion of C
the Supplier, be revised by the Supplier from time to time and in
the case of revision the rate schedule so revised shall be applicable
to the consumer from such date as may be general or special order
be notified by the Supplier."
Under clause (8) read writ Section 48, the appellant-Board has the D
power to revise the tariffs from time to time for supply of electrical energy.
In exercise thereof, on July 13, 1986 the Board revised the tariffs and
deleted LMV-10 and substituted various items for the deleted tariffs. As
far LMV-10 is concerned, there is no corresponding substitution under the
amended tariffs. By operation of rate schedule, for HV-2, "large and heavy E
powcr 1, it is provided for any other power consumption to enter under any
1
other rate "schedule" HV-2 becomes applicable.
It is an admitted position that on October 10, 1989, at the request of
the respondent, 104 KW of electrical energy was increased to 404 KW and
a separate contract was entered into for payment of rates under the tariff. F
The above revised rates would apply from that date. The only dispute is
with reference to the rate applicable for the electricity supplied between
August 1, 1986 to October 9, 1989. It is the contention of the respondent-
industry that in view of the deletion of LMV-10, the rate of schedule must
be LMV-2. As a consequence, the appellant has no power to charge the
respondent at the HV-2 rate. That contention found favour with the High G
Court. The High Court came to the conclusion that the agreement had
become effective from October 10, 1989, the respondent had no right to
charge for the previous supply. It is not covered under the agreement. The
High Court was not right in reaching the conclusion. It is seen that under
the contract entered into by the respondent, they are liable to charge H
292 SUPREMECOURTREPORTS (1996] SUPP. lS.C.R.
A consumption of the electrical energy as per the rates provided in LMV-10.
On its deletion w.e.f. July 31, 1986 for the electricity consumed by the
respondent, one of the rates applicable should be as provided in the tariff.
It is seen that LMV-2 is only for commercial establishments. Since the
respondent is an industrial unit, obviously HV-2 would stand applicable
only. Since there is no express contract between the parties, the residuary
B
power in HV-2 stands attracted. Accordingly the respondent is liable to
pay the charges for the electricity consumed between August 1, 1986 and
October 9, 1989 under HV-2 Rates. We are informed that from February,
1986 till July 31, 1986, the bill also has been given for the payment of the
charges under HV-2 rates. This is obviously incorrect. They are liable to
c charge only at the previous rates from the period from February 1986 till
July 31, 1986, the date on which the revision was effected. The appellant
is, therefore, directed to revise the bill accordingly and make a fresh
demand for payment. On demand so made, the respondent is at liberty to
pay the same within a period of six months from the date of the receipt of
D the demand.
The appeal is accordingly allowed. No costs.
R.P. Appeal Allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.