Created byFuzzy Cloud

Supreme Court of India

UNITED INDIA INSURANCE CO. LTD. & ANR.versusHYUNDAI ENGINEERING AND CONSTRUCTION CO. LTD. & ORS.

Citation
2018 INSC 732
Decided
21 August 2018
Disposal
Appeal(s) allowed

Holding

An arbitration clause that is conditioned on the insurer’s admission of liability is ineffective where the insurer repudiates the claim, rendering the dispute non‑arbitrable.

Summary

The Supreme Court examined whether clause 7 of a Contractor's All Risk insurance policy constituted a valid arbitration clause. The clause stipulated that arbitration would apply only if the insurer admitted liability and a dispute arose over the quantum payable. The insurer, United India Insurance, had repudiated the claim, denying any liability, and communicated this to the insured. The Court held that because the insurer did not admit liability, the pre‑condition for triggering arbitration was not satisfied, making the dispute non‑arbitrable. Consequently, the High Court’s appointment of an arbitrator was set aside and the respondents were directed to pursue a civil suit. The appeal by the insurer was allowed.

Issues considered

  • Whether clause 7 of the insurance policy is a valid arbitration clause or is conditioned on the insurer's admission of liability.
  • Whether a dispute arising from the insurer's repudiation of a claim falls within the scope of the arbitration clause.
  • Whether the High Court erred in appointing an arbitrator under Section 11(4) & 11(6) of the Arbitration and Conciliation Act, 1996.
  • How an arbitration clause must be interpreted under the Arbitration and Conciliation Act, 1996.

Legislation cited

Subjects

arbitration clauseconditional arbitrationinsurance policyrepudiation of claimnon‑arbitrable disputeArbitration and Conciliation Actinterpretation of arbitration agreementpre‑condition of liability admission

Judgment

                         [2018] 12 S.C.R. 1085                             1085


        UNITED INDIA INSURANCE CO. LTD. & ANR.                             A
                              v.
       HYUNDAI ENGINEERING AND CONSTRUCTION
                      CO. LTD. & ORS.
               (Civil Appeal No. 8146 of 2018)
                                                                           B
                          AUGUST 21, 2018
      [DIPAK MISRA, CJI, A. M. KHANWILKAR AND
             DR. D.Y. CHANDRACHUD, JJ.]
       Arbitration and Conciliation Act, 1996 – s.11(4) and s.11(6)
– Arbitration clause – Examination of – Respondent No.3 awarded            C
a contract for design, construction and maintenance of bridge to a
Joint Venture (JV) constituted by the Respondent Nos.1 and 2 –
After commencement of work, an insurance policy was obtained
from the appellants-insurer covering the entire project – During
construction, an accident occurred causing significant loss to the
                                                                           D
contractor – A detailed claim for a sum was submitted by the JV to
the appellants – Appellants found the claim not payable – Dispute
arose between the parties – Respondent Nos.1 and 2 filed a
petition u/s. 11(4) & 11(6) of the Act for appointment of arbitrator,
which was allowed by the High Court – On appeal, held: The
subject clause 7 of the insurance policy was hedged with a                 E
pre-condition expressly predicating that no difference or dispute
shall be referable to arbitration, if the appellants disputed or did
not accept its liability under or in respect of the policy – Arbitration
clause has to be interpreted strictly and such an arbitration clause
will get activated or kindled only if the dispute between the parties
                                                                           F
is limited to the quantum to be paid under the policy and liability
should be unequivocally admitted by the insurer – That is the
pre-condition and sine qua non for triggering the arbitration
clause – On facts, the appellants completely denied their liability
and repudiated the claim of the JV in the communication to the JV
– Thus, the dispute in question is non-arbitrable.                         G
       Allowing the appeal, the Court
       HELD: 1. The arbitration clause has to be interpreted
strictly. The subject clause 7 is a conditional expression of intent.
Such an arbitration clause will get activated or kindled only if the
dispute between the parties is limited to the quantum to be paid           H
                                 1085
1086            SUPREME COURT REPORTS                     [2018] 12 S.C.R.


 A     under the policy. The liability should be unequivocally admitted
       by the insurer. That is the pre-condition and sine qua non for
       triggering the arbitration clause. To put it differently, an
       arbitration clause would enliven or invigorate only if the insurer
       admits or accepts its liability under or in respect of the concerned
       policy. That has been expressly predicated in the opening part
 B
       of clause 7 as well as the second paragraph of the same clause.
       Thus there can be no arbitration in cases where the insurance
       company disputes or does not accept the liability under or in
       respect of the policy. [Para 13] [1098-C-E]
              2. The appellants completely denied their liability and
 C     repudiated the claim of the JV (respondent Nos.1 & 2) in the
       communication to them. The reasons mentioned in the
       communications are specific. No plea was raised by the
       respondents that the policy or the said clause 7 was void. The
       appellants repudiated the claim of the JV and denied their
 D     liability in toto under or in respect of the subject policy. It was
       not a plea to dispute the quantum to be paid under the policy,
       which alone could be referred to arbitration in terms of clause 7.
       Thus, the plea taken by the appellants is of denial of its liability
       to indemnify the loss as claimed by the JV, which falls in the
       excepted category, thereby making the arbitration clause
 E     ineffective and incapable of being enforced, if not non-existent.
       It is not actuated so as to make a reference to arbitration. In
       other words, the plea of the appellants is about falling in an
       excepted category and non-arbitrable matter within the meaning
       of the opening part of clause 7 and as re-stated in the second
 F     paragraph of the same clause. Thus, the dispute in question is
       non-arbitrable and Respondent Nos.1 & 2 ought to have resorted
       to the remedy of a suit. [Paras 14 and 15] [1099-C-F]
             Oriental Insurance Company Limited v. Narbheram
             Power and Steel Private Limited (2018) 6 SCC 534
 G           – relied on.
             Duro Felguera, S.A. v. Gangavaram Port Limited
             (2017) 9 SCC 729 ; Jumbo Bags Ltd. v. New India
             Assurance Co. Ltd. 2016 SCC OnLine Mad 9141 ;

 H
UNITED INDIA INSURANCE CO. LTD. v. HYUNDAI ENGINEERING 1087
              AND CONSTRUCTION CO. LTD.

         Vulcan Insurance Co. Ltd. v. Maharaj Singh and Anr.                 A
         (1976) 1 SCC 943 : [1976] 2 SCR 62 – referred to.
                            Case Law Reference
         (2017) 9 SCC 729               referred to            Para 1
         (2018) 6 SCC 534               relied on              Para 12       B
         [1976] 2 SCR 62                referred to            Para 11


      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 8146
of 2018.
                                                                             C
      From the Judgment and Order dated 30.11.2017 of the High Court
of Judicature at Madras in O. P. No. 537 of 2017.
       P. P. Malhotra, Ms. Meenakshi Arora, Sr. Advs., Mohit Paul, Vineet
Malhotra, Yasir Rauf, Vishal Gohri, Anugrah Niraj Ekka, Shubhendu
Kaushik, Aneesh Mittal, Ms. Shreya Sharma, Ms. Anupama Kaul,                 D
S. Ravi Shankar, Ms. Yamunah Nachiar, Ms. Bhanu Kapoor, Advs.
for the appearing parties.
         The Judgment of the Court was delivered by
       A. M. KHANWILKAR, J. 1. The conundrum in this appeal is
whether clause 7 of the subject Insurance Policy dated 5th September,        E
2007 posits unequivocal expression of the intention of arbitration or is
hedged with a conditionality? The learned Single Judge of the High
Court of Judicature at Madras vide impugned judgment and order dated
30th November, 2017 in O.P. No.537/2017 had held that post amendment
of the Arbitration and Conciliation Act, 1966 (for short, “the Act”), with   F
effect from 23rd October, 2015 by insertion of sub-section 6A in Section
11 of the Act, the limited mandate of the Court is to examine the factum
of existence of an arbitration agreement. No more and no less. The
learned Single Judge placed reliance on the two-Judge Bench decision
of this Court in Duro Felguera, S.A. Vs. Gangavaram Port Limited,1
and another decision of its own High Court in Jumbo Bags Ltd. Vs.            G
New India Assurance Co. Ltd.2 The appellants, however, placed
reliance on a three-Judge Bench decision of this Court in Oriental

1
    (2017) 9 SCC 729
2
    2016 SCC OnLine Mad 9141 : (2016) 3 CTC 761 : (2016) 2 LW 769            H
1088               SUPREME COURT REPORTS                          [2018] 12 S.C.R.


 A     Insurance Company Limited Vs. Narbheram Power and Steel
       Private Limited,3 where this Court had an occasion to construe a similar
       clause of an insurance policy as in the present case. Relying on this
       decision, it is urged that the impugned judgment cannot be countenanced
       and that the High Court ought to have dismissed the original petition filed
 B     by the respondents under Sections 11(4) & 11(6) of the Act read with
       Rule 2 of the Appointment of Arbitrators by the Chief Justice of Madras
       High Court Scheme, 1996, to declare the arbitrator nominated by the
       respondents herein as the sole arbitrator; or in addition, appoint one
       arbitrator on behalf of the appellants herein so as to adjudicate all the
       disputes inter se between the parties in terms of the Act.
 C
              2. Shorn of unnecessary facts, be it noted that the respondent
       Nos.1 and 2 constitute a Joint Venture (“JV”). Respondent No.3 awarded
       a contract on 29th September, 2006 for design, construction and
       maintenance of a bridge across the River Chambal, which was to be
       completed within a period of 40 months and was commenced on
 D     5th December, 2007 by the JV after respondent No.3 handed over the
       site to it. After commencement of the work, a Contractor All Risk
       Insurance Policy (“CAR Policy”) dated 5 th December, 2007 was
       obtained from the appellants covering the entire project, valued at
       Rs.2,13,58,76,000/-. The policy contained clause 7, which reads thus:
 E              “7. If any difference shall arise as to the quantum to be paid
                under this Policy (liability being otherwise admitted) such
                difference shall independently of all other questions be referred
                to the decision of an arbitrator to be appointed in writing by the
                parties in difference, or if they cannot agree upon a single
 F              arbitrator to the decision of two disinterested persons as
                arbitrators of whom one shall be appointed in writing by each of
                the parties within two calendar months after having been required
                so to do in writing by the other party in accordance with the
                provisions of the Arbitration Act, 1940, as amended from time to
                time and for the time being in force in case either party shall
 G              refuse or fail to appoint arbitrator within two calendar months
                after receipt of notice in writing requiring an appointment the other
                party shall be at liberty to appoint sole arbitrator and in case of
                disagreement between the arbitrators, the difference shall be

       3
           (2018) 6 SCC 534
 H
UNITED INDIA INSURANCE CO. LTD. v. HYUNDAI ENGINEERING 1089
   AND CONSTRUCTION CO. LTD. [A.M. KHANWILKAR, J.]

      referred to the decision of an umpire who shall have been             A
      appointed by them in writing before entering on the reference and
      who shall sit with the arbitrators and preside at their meetings.
      It is clearly agreed and understood that no difference or
      dispute shall be referable to arbitration as herein before
      provided, if the Company has disputed or not accepted                 B
      liability under or in respect of this Policy.
      It is hereby expressly stipulated and declared that it shall be a
      condition precedent to any right of action or suit upon this policy
      that the award by such arbitrator, arbitrators or umpire of the
      amount of the loss or damage shall be first obtained.                 C
      It is also hereby further expressly agreed and declared that if the
      Company shall disclaim liability to the insured for any claim
      hereunder and such claim shall not within 3 calendar months
      from the date of such disclaimer have been made the subject
      matter of a suit in a court of law, then the claim shall for all      D
      purpose be deemed to have been abandoned and shall not
      thereafter be recoverable hereunder.”
                                                    (emphasis supplied)
       3. During the construction of the bridge, on 24th December, 2009,
an accident occurred causing significant loss to the contractor. A          E
detailed claim for a sum of Rs.1,51,59,94,543/- was submitted by the JV
to the appellants, in response to which the appellants appointed one
Mr. S. Ananthapadmanabhan, Surveyor and Loss Adjuster, for
assessing the loss caused to the contractor. A final report was submitted
by the Surveyor on 28 th February, 2011 assessing the loss as               F
Rs.39,09,92,828/-, however, with the finding that the damage was on
account of the faulty design and improper execution of the project and
not payable under the policy. Besides the stated report, a Committee of
Experts was set up by the Ministry of Road Transport and Highways,
Government of India, to enquire into the accident which then submitted
its report on 7th August, 2010.                                             G
       4. The appellants took into account both these reports and vide
communication dated 21st April, 2011, intimated the respondents that the
claim put forth by the JV, was found to be not payable, and accordingly,
stood repudiated. The said communication reads thus:
                                                                            H
1090      SUPREME COURT REPORTS                        [2018] 12 S.C.R.


 A     “UNITED INDIA INSURANCE COMPANY LIMITED
       Divisional Office:010700          Post Box No.4528
       Ist Floor, Silingi Building Gram UNDIVSEVEN
       134, Greams Road                  Phone:28290845/846
       Chennai-600 006                   Telefax:044-28290844
 B     Ref.:010700/CAR Claim/2011                21st April, 2011
       REGISTERED POST WITH ACKNOWLEDGE DUE

       M/s National Highways of Authority of India
       1-C-10 SFS Colony
 C     Talwandi, Kota
       Rajasthan-324 005
       Dear Sirs
       Kind Attn: Mr. Anoop Kulshreshtha, Project Director

 D     Re: Claim under Contractor’s All Risk Policy No.011900/44/07/
       03/60000001- Our Claim No.010703/44/09/03/90000007-Collapse
       of Cable Stayed Bridge at Kota, Rajasthan.
       We refer to the above claim lodged by you under your Contractor’s
       All Risk Policy in respect of collapse of portion of bridge under
       construction on 24.12.2009.
 E
       You are aware that immediately on intimation of the occurrence,
       our Company had deputed Mr. S Ananta Padmanabhan, a duly
       licensed and well experienced civil engineer surveyor for detailed
       survey as required by Insurance Act. The surveyor had visited
       the site on various occasions and was in contact and
 F
       correspondence with you when various particulars, information
       and records were obtained. Besides enquiries with you the surveyor
       had also made other enquiries for information including the
       Government, Police Authorities and gathered reports of the
       respective agencies. After detailed survey, the surveyor had
 G     submitted his Final Report dated 28.2.2011 in respect of the claim.
       Besides the Survey Report, it also found that the occurrence was
       the subject matter of enquiry by a Special Committee constituted
       by the Ministry of Road Transport and Highways, Govt. of India
       which had also submitted a detailed report dated 7.8.2010.
 H
UNITED INDIA INSURANCE CO. LTD. v. HYUNDAI ENGINEERING 1091
   AND CONSTRUCTION CO. LTD. [A.M. KHANWILKAR, J.]

    We find that there had been a collapse of the lateral span P3-P4,       A
    P4 Pylon and main span structures from S1-S10 segments which
    fell into the river.
    On a careful study of the records it is found that the collapsed
    portion was affected entirely due to faulty design, besides defective
    workmanship and materials in execution of the project. A few of         B
    the relevant factors are observed as under:-
    In execution of the project it is found that the junction at Pylon P4
    was most critical and vulnerable which had to be handled with
    due care and diligence. An instable equilibrium had been caused
    at this junction, due to shearing of the slab in the lateral span       C
    P3-P4 about 15 mts. From the P4 junction, which caused the
    tilting of the pylon, dragging with it the spans P3-P4, P3-P2 and
    Piers P3, P4. The release of restraints on the movement of the
    bearings at P4 had not been performed in manner necessary,
    contributing to a massive failure. Lack of coordination and planning
    between various consultants and failure to properly oversee the         D
    execution had been found.
    There had been change of allocation of work among various joint
    venture partners which had played a key role in the quality of
    workmanship. Even at the affected P4 location, construction of
    Pier P4 was the responsibility of Hyundai Engg. & Construction          E
    Co. Whereas it was found to have been carried out by Gatnmon
    India.
    There had also been change in the sequence of operations in
    construction to make up for lost time, which adversely affected
    the stability of the P4 joint.                                          F
    The summary of the findings of the Enquiry committee is that the
    collapse was caused, inter alia, by 1) absence of stability devices
    during construction, 2) shortfall in design and 3) deficient
    workmanship.
                                                                            G
    The Enquiry Committee have more particularly observed that
    a)     the contractors are responsible for all during the structure
    to reach a vulnerable stage, without taking adequate precautions
    with respect to stability and robustness of the partially completed
    structure and shortfall in the design.
                                                                            H
1092      SUPREME COURT REPORTS                      [2018] 12 S.C.R.


 A     b) Since they have been shortfalls at the design responsibility
       also lies with.
       The available records and documents clearly reveal that
       the loss has occurred due to faulty design and defective
       workmanship.
 B     We find that national Highways Authority of India have in fact
       initiated action by issue of show cause notice against the
       Contractors.
       The Kota Police had lodged FIR against various employees of
       the Contractors/Sub contractors and submitted final report which
 C     supports the above observations.
       The policy does not cover the loss in the above
       circumstances. In fact the policy specifically excludes any
       loss/damage caused by faulty design, defective
       workmanship/material. Further, the revelations of the
 D     expert body and the surveyors indicate willful acts/
       negligence in execution of work of such nature resulting in
       the occurrence.
       In view of the above, we regret to inform you that the claim
       is found to be not payable and accordingly stands repudiated.
 E
       Insurers reserve their right to rely upon any further or other
       materials/terms in support of the above conclusion and the above
       circumstances are not exhaustive of the basis for the above
       decision.
       Thanking You
 F
       Yours faithfully
       Sd/-
       Senior Divisional Manager

 G     Copy to:
       1) M/s Hyundai Engineering & Construction Co. Ltd & Gammon
       India Ltd., Chambal Bridge Project. Behind Tilam Sangh, Rawat
       Bhata Road, Kota Rajasthan-324010.
       2) Regional Office-Technical-Engineering Dept.
 H
UNITED INDIA INSURANCE CO. LTD. v. HYUNDAI ENGINEERING 1093
   AND CONSTRUCTION CO. LTD. [A.M. KHANWILKAR, J.]

      3) Head Office-Technical-Engineering Dept.                               A
      Regd. & Head Office: 24, Whites Road,
      Chennai-600 014.”
                                             (emphasis supplied)
       5. The JV nevertheless entered into correspondence with the
appellants to reopen and re-assess its decision of repudiation of the claim.   B
Finally, the appellants informed the respondents that it was unable to
“reconsider” the claim which has already been repudiated. The said
communication reads thus:
      “UNITED INDIA INSURANCE COMPANY LIMITED
           HEAD OFFICE 24, WHITES ROAD CHENNAI                                 C
                    CIN:U93090TN1938GOI000108
       Ref:No.UIIC/ENGG/CLAIMS/17-18/01 Dt:17.04.2017
      To
                       KA: Mr. Anupam Gupta
      The Project Director                                                     D
      M/s National Highways Authority of India
      Project Implementation Unit
      A-575, Talwandi, Kota (Rajasthan)-324005
      Subject: CAR Insurance Policy
                                                                               E
      No.011900/44/07/03/60000001.
      Settlement of Contractors claim No.010703/44/096/03/90000007.
      Dear Sir,
      We refer to your letter Ref:17011/27/2006-Kota/CAR/RJ-05/3909
      dt. 18.01.2017 and Contractor letter Ref: HZ-6718, dated                 F
      04.02.2017 and also the subsequent meeting held at our office
      Chennai. On perusal of the documents provided, we find that no
      further points have emerged in support of the claim.
      In view of the above we regret our inability to reconsider
the claim which was repudiated.                                                G
      Yours faithfully


      (D. Nagalakshmi)
      Dy. General Manager
                                                                               H
1094             SUPREME COURT REPORTS                          [2018] 12 S.C.R.


 A           CC: KA: Mr. Haeng Kwon Kang
             The Chief Project Manager
             Hyundai Engineering & Construction Co. Ltd.
             Chambal Bridge Project, Behind Tilam Sangh
             Rawat Bhata Road, Kota Rajasthan-324 010"
 B                                                    (emphasis supplied)
             6. As a sequel, the JV vide its letter dated 29 th May, 2017
       informed the appellants that disputes had arisen between the appellants
       and the JV and in view thereof it was invoking the arbitration clause
       No.7 contained in the Insurance Policy and had nominated Dr. V.K.
 C     Agrawal as its Arbitrator. The appellants were also called upon to either
       accept the name of the sole arbitrator or nominate its own arbitrator
       within 30 days from the date of receipt of the communication.
       Eventually, respondent Nos.1 & 2 filed a petition under Sections 11(4) &
       11(6) of the Act before the High Court of Judicature at Madras being
       O.P. No.537/2017.
 D
              7. The said petition was resisted by the appellants. It was urged
       that the subject clause 7 of the policy was hedged with a pre-condition
       expressly predicating that no difference or dispute shall be referable to
       arbitration, if the appellants disputed or did not accept its liability under
       or in respect of the policy. In other words, in case of repudiation of the
 E     claim by the appellants, the remedy of the insured was to file a suit
       within 3 months of such disclaimer. It was asserted that the appellants
       had repudiated the liability vide letter dated 21st April, 2011. That is an
       indisputable fact. The communication sent by the appellants on 17th April,
       2017 was a mere reiteration and confirmation of the repudiation already
 F     communicated vide letter dated 21st April, 2011. It was specifically
       denied that the said letter dated 17th April, 2017 was a final repudiation
       for the purpose of calculating limitation as alleged by the applicants
       (respondent Nos.1 & 2). It was urged that the dispute raised was not
       one of quantum to be paid under the policy but on the very factum of
       alleged loss not covered under the policy. By virtue whereof, the agree-
 G     ment specifically excluded making a reference to arbitration.
              8. Notwithstanding the stand taken by the appellants, the learned
       Single Judge of the High Court by the impugned judgment allowed the
       petition filed by respondent Nos.1 & 2 and appointed Mr. Justice P.

 H
UNITED INDIA INSURANCE CO. LTD. v. HYUNDAI ENGINEERING 1095
   AND CONSTRUCTION CO. LTD. [A.M. KHANWILKAR, J.]

Jyothimani, Former Judge, High Court of Judicature, Madras to act as            A
an Arbitrator in the matter, having opined that arbitration agreement
existed in the form of clause 7 of the Insurance Policy, by relying mainly
on the decision in Duro Felguera, (supra) and Jumbo Bags Ltd.,
(supra).
      9. We have heard Mr. P.P. Malhotra, learned senior counsel                B
appearing for the appellants and Ms. Meenakshi Arora, learned senior
counsel appearing for the respondents.
      10. The clause similar to the subject clause 7 of the Insurance
Policy came up for consideration before a three-Judge Bench of this
Court in Oriental Insurance Company Limited (supra). After analysing            C
the legal principle expounded in a host of decisions, including the
decision in Jumbo Bags Ltd. (supra), the Court opined as follows:
       “23. It does not need special emphasis that an arbitration clause is
       required to be strictly construed. Any expression in the clause
       must unequivocally express the intent of arbitration. It can also        D
       lay the postulate in which situations the arbitration clause
       cannot be given effect to. If a clause stipulates that under
       certain circumstances there can be no arbitration, and they
       are demonstrably clear then the controversy pertaining to
       the appointment of arbitrator has to be put to rest.
                                                                                E
        24. In the instant case, Clause 13 categorically lays the postulate
that if the insurer has disputed or not accepted the liability, no difference
or dispute shall be referred to arbitration…..”
                                                      (emphasis supplied)
    While adverting to the observation in paragraphs 28 and 32 of the           F
Jumbo Bags Ltd. (supra), the Court observed thus:
       “19. We may presently refer to the decision of the Madras High
       Court in Jumbo Bags Ltd. In the said case, the learned Chief
       Justice was interpreting clause 13 of the policy conditions.
       Referring to Vulcan Insurance Co. Ltd., he has held thus:                G
       (Jumbo Bags Ltd. case, SCC OnLine Mad para 28)
          ‘28. …The dispute which is not referable to arbitration, being
          not covered by the clause cannot be over the subject-matter

                                                                                H
1096               SUPREME COURT REPORTS                         [2018] 12 S.C.R.


 A                 of arbitration, and the remedy of the insured in this case is only
                   to institute a suit.’
       And again : (SCC OnLine Mad para 32)
                ‘32. I am of the view that the remedy of arbitration is not
                available to the petitioner herein in view of the arbitration clause
 B              specifically excluding the mode of adjudication of disputes by
                arbitration, where a claim is repudiated in toto. The remedy would
                thus only be of a civil suit in accordance with law.’
                We concur with the said view.”

 C                                                             (emphasis supplied)
              11. The other decision heavily relied upon by the High Court and
       also by the respondents in Duro Felguera (supra), will be of no avail.
       Firstly, because it is a two-Judge Bench decision and also because the
       Court was not called upon to consider the question which arises in the
 D     present case, in reference to clause 7 of the subject Insurance Policy.
       The exposition in this decision is a general observation about the effect
       of the amended provision and not specific to the issue under
       consideration. The issue under consideration has been directly dealt with
       by a three-Judge Bench of this Court in Oriental Insurance Company
       Limited (supra), following the exposition in Vulcan Insurance Co. Ltd.
 E     Vs. Maharaj Singh and Anr.4, which, again, is a three-Judge Bench
       decision having construed clause similar to the subject clause 7 of the
       Insurance Policy. In paragraphs 11 & 12 of Vulcan Insurance Co.
       Ltd. (supra), the Court answered the issue thus:
                “11. Although the surveyors in their letter dated April 26, 1963
 F              had raised a dispute as to the amount of any loss or damage
                alleged to have been suffered by Respondent 1, the appellant at
                no point of time raised any such dispute. The appellant
                company in its letter dated July 5 and 29, 1963 repudiated
                the claim altogether. Under clause 13 the company was not
                required to mention any reason of rejection of the claim
 G
                nor did it mention any. But the repudiation of the claim could
                not amount to the raising of a dispute as to the amount of
                any loss or damage alleged to have been suffered by
                Respondent 1. If the rejection of the claim made by the

 H     4
           (1976) 1 SCC 943
UNITED INDIA INSURANCE CO. LTD. v. HYUNDAI ENGINEERING 1097
   AND CONSTRUCTION CO. LTD. [A.M. KHANWILKAR, J.]

      insured be on the ground that he had suffered no loss as a                A
      result of the fire or the amount of loss was not to the extent
      claimed by him, then and then only, a difference could have
      arisen as to the amount of any loss or damage within the
      meaning of clause 18. In this case, however, the company
      repudiated its liability to pay any amount of loss or damage as
                                                                                B
      claimed by Respondent 1. In other words, the dispute raised by
      the company appertained to its liability to pay any amount of
      damage whatsoever. In our opinion, therefore, the dispute raised
      by the appellant company was not covered by the arbitration
      clause.
      12.     As per clause 13 on rejection of the claim by the                 C
      company an action or suit, meaning thereby a legal
      proceeding which almost invariably in India will be in the
      nature of a suit, has got to be commenced within three
      months from the date of such rejection; otherwise, all
      benefits under the policy stand forfeited. The rejection of the           D
      claim may be for the reasons indicated in the first part of clause
      13, such as, false declaration, fraud or wilful neglect of the claimant
      or on any other ground disclosed or undisclosed. But as soon as
      there is a rejection of the claim and not the raising of a dispute as
      to the amount of any loss or damage, the only remedy open to the
      claimant is to commence a legal proceeding, namely, a suit, for           E
      establishment of the company’s liability. It may well be that after
      the liability of the company is established in such a suit, for
      determination of the quantum of the loss or damage reference to
      arbitration will have to be resorted to in accordance with clause
      18. But the arbitration clause, restricted as it is by the use            F
      of the words ‘if any difference arises as to the amount of
      any loss or damage’, cannot take within its sweep a dispute
      as to the liability of the company when it refuses to pay any
      damage at all.”
                                                      (emphasis supplied)       G
      Again in paragraph 22, after analysing the relevant judicial
precedents, the Court concluded as follows:
      “22. The two lines of cases clearly bear out the two distinct
      situations in law. A clause like the one in Scott v. Avery bars any
                                                                                H
1098             SUPREME COURT REPORTS                             [2018] 12 S.C.R.


 A            action or suit if commenced for determination of a dispute covered
              by the arbitration clause. But if on the other hand a dispute
              cropped up at the very outset which cannot be referred to
              arbitration as being not covered by the clause, then Scott v.
              Avery clause is rendered inoperative and cannot be pleaded
              as a bar to the maintainability of the legal action or suit for
 B
              determination of the dispute which was outside the
              arbitration clause.”
                                                               (Emphasis supplied)
              13. From the line of authorities, it is clear that the arbitration clause
 C     has to be interpreted strictly. The subject clause 7 which is in pari
       materia to clause 13 of the policy considered by a three-Judge Bench in
       Oriental Insurance Company Limited (supra), is a conditional
       expression of intent. Such an arbitration clause will get activated or kindled
       only if the dispute between the parties is limited to the quantum to be
       paid under the policy. The liability should be unequivocally admitted by
 D     the insurer. That is the pre-condition and sine qua non for triggering the
       arbitration clause. To put it differently, an arbitration clause would
       enliven or invigorate only if the insurer admits or accepts its liability
       under or in respect of the concerned policy. That has been expressly
       predicated in the opening part of clause 7 as well as the second
 E     paragraph of the same clause. In the opening part, it is stated that the
       “(liability being otherwise admitted)”. This is reinforced and re-stated in
       the second paragraph in the following words:
              “It is clearly agreed and understood that no difference or dispute
              shall be referable to arbitration as herein before provided, if the
 F            Company has disputed or not accepted liability under or in
              respect of this Policy.”
             Thus understood, there can be no arbitration in cases where the
       insurance company disputes or does not accept the liability under or in
       respect of the policy.
 G            14. The core issue is whether the communication sent on
       21st April, 2011 falls in the excepted category of repudiation and denial
       of liability in toto or has the effect of acceptance of liability by the
       insurer under or in respect of the policy and limited to disputation of

 H
UNITED INDIA INSURANCE CO. LTD. v. HYUNDAI ENGINEERING 1099
   AND CONSTRUCTION CO. LTD. [A.M. KHANWILKAR, J.]

quantum. The High Court has made no effort to examine this aspect at            A
all. It only reproduced clause 7 of the policy and in reference to the
dictum in Duro Felguera (supra) held that no other enquiry can be
made by the Court in that regard. This is misreading of the said decision
and the amended provision and, in particular, mis-application of the three-
Judge Bench decisions of this Court in Vulcan Insurance Co. Ltd.
                                                                                B
(supra) and in Oriental Insurance Company Ltd. (supra).
       15. Reverting to the communication dated 21st April, 2011, we
have no hesitation in taking the view that the appellants completely
denied their liability and repudiated the claim of the JV (respondent Nos.1
& 2) for the reasons mentioned in the communication. The reasons are
specific. No plea was raised by the respondents that the policy or the          C
said clause 7 was void. The appellants repudiated the claim of the JV
and denied their liability in toto under or in respect of the subject policy.
It was not a plea to dispute the quantum to be paid under the policy,
which alone could be referred to arbitration in terms of clause 7. Thus,
the plea taken by the appellants is of denial of its liability to indemnify     D
the loss as claimed by the JV, which falls in the excepted category,
thereby making the arbitration clause ineffective and incapable of being
enforced, if not non-existent. It is not actuated so as to make a
reference to arbitration. In other words, the plea of the appellants is
about falling in an excepted category and non-arbitrable matter within
the meaning of the opening part of clause 7 and as re-stated in the             E
second paragraph of the same clause.
       16. In view of the above, it must be held that the dispute in
question is non-arbitrable and respondent Nos.1 & 2 ought to have
resorted to the remedy of a suit. The plea of respondent Nos.1 & 2
about the final repudiation expressed by the appellants vide                    F
communication dated 17th April, 2017 will be of no avail. However,
whether that factum can be taken as the cause of action for institution
of the suit is a matter which can be debated in those proceedings. We
may not be understood to have expressed any opinion either way in that
regard.                                                                         G
       17. Accordingly, we allow this appeal and set aside the impugned
judgment and order and further dismiss the original petition No.537/2017
filed by respondent Nos.1 & 2 before the High Court of Judicature at

                                                                                H
1100            SUPREME COURT REPORTS                          [2018] 12 S.C.R.


 A     Madras, with liberty to the said respondents to take recourse to a civil
       suit for mitigation of its grievances, if so advised. We are not expressing
       any opinion either way on the merits of the issues to be answered in the
       said proceedings.
             18. The appeal is allowed in the aforementioned terms with no
 B     order as to costs.


       Ankit Gyan                                                   Appeal allowed.



 C




 D




 E




 F




 G




 H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "arbitration clause"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.