Patna High Court

Suman Singh @ Suman SharmaversusThe State of Bihar

Decided
Disposal
DISMISSED

Holding

The Court held that the acquisition complied with all statutory requirements, including issuance of notice under Section 11(i) of the 2013 Act, and therefore dismissed the writ petition.

Summary

The petitioners, a group of land owners in Patna district, challenged the acquisition of their lands for the Mukhyamantri Gramin Sadak Yojana, seeking to quash the notice published on 09.05.2023 and the awards under Section 37(2) of the RFCTLARR Act, 2013, and to restrain possession. They alleged that the mandatory notice under Section 11(i) of the 2013 Act was never issued, violating the right to notice and hearing recognised by the Supreme Court in Kolkata Municipal Corporation v. Vimal Kumar Shah. The State contended that a notice dated 02.09.2022 was served, the award was lawfully made, compensation was paid, and the acquisition served a public purpose. The Court examined the statutory requirements, the Supreme Court principles, and the record of notice, finding that the respondents had complied with the procedural mandates. Consequently, the Court held that the petition lacked merit and dismissed the writ petition. The status‑quo order was merged with the dismissal order.

Issues considered

  • Whether a valid notice under Section 11(i) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 was issued to the petitioners.
  • Whether the land acquisition complied with the principles of notice, hearing, reasoned decision, public purpose, fair compensation and expeditious procedure as laid down by Supreme Court precedent.
  • Whether the awards under Section 37(2) of the 2013 Act can be quashed on the ground of procedural irregularity.
  • Whether the respondents can be restrained from taking possession of the acquired land.

Legislation cited

Subjects

  • land acquisition
  • right to notice
  • fair compensation
  • public purpose
  • RFCTLARR Act
  • writ petition
  • property rights
  • Article 300A

Judgment

         IN THE HIGH COURT OF JUDICATURE AT PATNA
                   Civil Writ Jurisdiction Case No.11917 of 2023
     ======================================================
1.    Suman Singh @ Suman Sharma Son of Late Ram Akbal Sharma Resident of
      Village-Bherharia, P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
2.   Binay Singh Son of Late Chandradeo Singh Resident of Village-Bherharia,
     P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
3.   Arun Kumar Tiwari Son of Siddeshwar Tiwari @ Chini Tiwari Resident of
     Village-Bherharia, P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
4.   Rabindra Sharma Son of Late Alakhdeo Sharma Resident of Village-
     Bherharia, P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
5.   Nawlesh Sharma Son of Bachchu Sharma Resident of Village-Bherharia,
     P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
6.   Surya Nath Singh @ Sharma Son of Late Rajju Singh Resident of Village-
     Bherharia, P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
7.   Laxman Tiwari Son of Raj Bahadur Tiwari Resident of Village-Bherharia,
     P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
8.   Bimal Kumar Tiwari Son of Ram Pratap Tiwari Resident of Village-
     Bherharia, P.O.-Siyarampur, P.S.-Paliganj, District-Patna.
                                                                ... ... Petitioner/s
                                       Versus
1.   The State of Bihar through the Additional Chief Secretary, Department of
     Revenue and Land Reforms, Govt. of Bihar, Patna.
2.   The Distirct Magistrate-Cum-Collector, Patna.
3.   The Distirct Land Acquisition Officer, Patna.
4.   The Commissioner, Patna Division, Patna.
5.    The Executive Engineer, Rural Engineer Organization, Patna Division,
      Patna.
                                                         ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :      Mr. Neeraj Kumar, Advocate
     For the Respondent/s   :      Mr. Md. Khurshid Alam, AAG-12
     ======================================================
     CORAM: HONOURABLE MR. JUSTICE RAJIV ROY
     ORAL JUDGMENT
     Date : 06-07-2026

                    Heard Mr. Neeraj Kumar, learned counsel for the

      petitioner and the State.

                  2. The present petition has been preferred for the

      following relief/s:

                                               i)      for      issuance        of

                                   appropriate writ, order or direction
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           2/29




                                        specially in the nature of certiorari for

                                        quashing the notice dated 09.05.2023

                                        published in Hindi Newspaper "Dainik

                                        Bhaskar"        under    Section    19    (1)

                                        whereby Collectorate, Patna (District

                                        Land       Acquisition     Branch)       has

                                        declared that for the project G.T.S.N.Y.

                                        and       for     Mukhya-Mantri         Gram

                                        Sampark Yojna (G.T.S.N.Y.) Lands

                                        from Guran Bigha Road to Bherari

                                        Siyarampur Road) is required for

                                        construction of Road, and area of

                                        0.6760 Acres vide Thana No. 328

                                        Revenue Thana No. Bikram, Anchal-

                                        Paliganj, District- Patna.

                                                       ii) for quashing the Award

                                        No. 1, 2, 4 and 5 issued under Section

                                        37(2)      of     the    Right     to    Fair

                                        Compensation and Transparency in

                                        Land Acquisition, Rehabilitation and

                                        Re-settlement Act, 2013 given to the

                                        petitioners.
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           3/29




                                                       iii) For a direction to the

                                        Respondent authorities not to take

                                        possession of land to be acquired.

                                                       iv) Any other relief or reliefs

                                        to which the petitioners are entitled in

                                        the facts and circumstances of this

                                        case.

                     3. The matter relates to a piece of land details of

         which is/are incorporated in paragraph no.4 of the petition and

         read as under:

                                        (i) Plot No. 1314, 1315 of Petitioner

                                        No.1 Suman Sharma

                                        (ii) lands of Petitioner No.2, Binay

                                        Singh vide Khata No. 368, S. Plot No.

                                        1317 an area of 0.046 acres

                                        (iii)     Rabindra Sharma vide Khata

                                        No. 357 S. Plot No. 1412 an area of

                                        0.18 acres

                                        (iv) Chini Tiwari vide Khata No. 334,

                                        S. Plot No. 1425 an area of 0.1150

                                        acres

                                        (v) lands of Surya Nath Singh @
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           4/29




                                        Sharma, vide Khata No. 2585, S. Plot

                                        No. 1762 an area of 0.055

                                          (vi) lands of Bimal Tiwari, Laxman

                                        Tiwari, Nawlesh Sharma are also

                                        going to be acquired (details not

                                        given).

                     4. The respondent proposed to acquire the land under

         ‘Mukhyamantri Gramin Sadak Yojana’ (henceforth for short

         ‘the Yojana’).

                     5. Though not incorporated in this writ petition, the

         submission put forward by the learned counsel for the petitioner

         is/are that the mandatory notice under Section 11(i) of Land

         Acquisition,      Rehabilitation         and   Resettlement Act, 2013

         (henceforth for short ‘the 2013 Act’) was never issued and

         instead, the respondents straight away made the award

         declaration.

                     6. Aggrieved, the present writ petition. Learned

         counsel for the petitioners submits that the least that is expected

         from the respondents is/are to issue notice to the petitioners

         about their intention to acquire the property which must be

         clear, cogent and meaningful.

                     7. In support of the case, learned counsel for the
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           5/29




         petitioner, took this Court to an order of the Hon’ble Supreme

         Court in the case of Kolkata Municipal Corporation and

         another vs Vimal Kumar Shah and Ors. reported in 2024 (3)

         (SC) (97) with specific reference to paragraphs 24, 25, 27 and

         30 which read as under:

                                           24. the Right to property: A net of

                                           intersecting rights: There is yet

                                           another aspect of the matter. Under

                                           our         constitutional       scheme,

                                           compliance with a fair procedure of

                                           law before depriving any person of

                                           his immovable property is well

                                           entrenched. We are examining this

                                           issue in the context of Section 352 of

                                           the Act which is bereft of any

                                           procedure        whatsoever          before

                                           compulsorily       acquiring         private

                                           property.     Again,      assuming      that

                                           Section 363 of the Act provides for

                                           compensation,                compulsory

                                           acquisition        will      still       be

                                           unconstitutional if proper procedure
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           6/29




                                           is not established or followed before

                                           depriving a person of their right to

                                           property. We find it compelling to

                                           clarify that a rather undue emphasis

                                           is     laid     on        provisions          of

                                           compensation to justify the power of

                                           compulsory          acquisition,       as     if

                                           compensation         by      itself    is    the

                                           complete procedure for a valid

                                           acquisition;

                                           25. while it is true that after the 44th

                                           Constitutional Amendment, the right

                                           to property drifted from Part-III to

                                           Part-XII of the Constitution, there

                                           continues to be a potent safety net

                                           against arbitrary acquisitions, hasty

                                           decision-making              and        unfair

                                           redressal mechanisms. Despite its

                                           spatial placement, Article 300A

                                           which declares that "no person shall

                                           be deprived of his property save by

                                           authority      of      law       has        been
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           7/29




                                           characterised       both        as     a

                                           constitutional and also a human

                                           right10.     To      assume          that

                                           constitutional     protection        gets

                                           constricted to the mandate of a fair

                                           compensation       would        be     a

                                           disingenuous reading of the text and,

                                           shall we say, offensive to the

                                           egalitarian spirit of the Constitution.

                                           27. What then are these sub-rights or

                                           strands      of     this     swadeshi

                                           constitutional fabric constituting the

                                           right to property? Seven such sub-

                                           rights can be identified albeit non-

                                           exhaustive. These are: (i) duty of the

                                           State to inform the person that it

                                           intends to acquire his property-the

                                           right to notice, (ii) the duty of the

                                           State to hear objections to the

                                           acquisition-the right to be heard,

                                           (iii) the duty of the State to inform

                                           the person of its decision to acquire
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           8/29




                                           the right to a reasoned decision, (iv)

                                           the duty of the State to demonstrate

                                           that the acquisition is for public

                                           purpose-the duty to acquire only for

                                           public purpose, (v) the duty of the

                                           State to restitute and rehabilitate the

                                           right       of   restitution     or    fair

                                           compensation, (vi) the duty of the

                                           State to conduct the process of

                                           acquisition efficiently and within

                                           prescribed       timelines       of     the

                                           proceedings-the right to an efficient

                                           and expeditious process, and (vii)

                                           final conclusion of the proceedings

                                           leading to vesting the right of

                                           conclusion.

                                           30.     Following     are      the    seven

                                           principles:



                                           30.1. The Right to notice: (i) A prior

                                           notice informing the bearer of the

                                           right that the State intends to
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                           9/29




                                           deprive them of the right to property

                                           is a right in itself; a linear extension

                                           of the right to know embedded in

                                           Article 19(1)(a). The Constitution

                                           does not contemplate acquisition by

                                           ambush. The notice to acquire must

                                           be clear, cogent and meaningful.

                                           Some of the statutes reflect this right.

                                           (ii) Section 4 of the Land Acquisition

                                           Act, 1894, Section 3 (1) of the

                                           Requisitioning and Acquisition of

                                           Immovable       Property      Act,   1952,

                                           Section 11 of the Right to Fair

                                           Compensation and Transparency in

                                           Land Acquisition, Rehabilitation and

                                           Resettlement Act, 2013, and Section

                                           3A of the National Highways Act,

                                           1956 are examples of such statutory

                                           incorporation of the right to notice

                                           before      initiation   of    the    land

                                           acquisition proceedings.

                                           (iii) In a large number of decisions,
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          10/29




                                           our     constitutional       courts     have

                                           independently recognised the right

                                           to notice before any process of

                                           acquisition is commenced.

                                           30.2. The Right to be heard: (i)

                                           Following the right to a meaningful

                                           and     effective    prior     notice     of

                                           acquisition, is the right of the

                                           property-bearer to communicate his

                                           objections and concerns to the

                                           authority acquiring the property.

                                           This right to be heard against the

                                           proposed      acquisition       must      be

                                           meaningful and not a sham.

                                           (ii)   Section      5A   of    the     Land

                                           Acquisition Act, 1894, Section 3 (1)

                                           of the Requisitioning and Acquisition

                                           of Immovable Property Act, 1952,

                                           Section 15 of the Right to Fair

                                           Compensation and Transparency in

                                           Land Acquisition, Rehabilitation and

                                           Resettlement Act, 2013, and Section
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          11/29




                                           3C of the National Highways some

                                           statutory Act, 1956, embodiments of

                                           this    right.   are   some   statutory

                                           embodiments of this right.

                                           iii) Judicial opinions recognizing the

                                           importance of this right are far too

                                           many to reproduce. Suffice to say

                                           that that the enquiry in which a land

                                           holder would raise his objection is

                                           not a mere formality.

                                           30.3. The Right to a reasoned

                                           decision: (i) That the authorities

                                           have heard and considered the

                                           objections is evidenced only through

                                           a reasoned order. It is incumbent

                                           upon the authority to take an

                                           informed decision and communicate

                                           the same to the objector.



                                           Act, 1894, Section 3 (2) of the (ii)

                                           Section 6 of the Land Acquisition

                                           Requisitioning and Acquisition of
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          12/29




                                           Immovable       Property        Act,    1952,

                                           Section 19 of the Right to Fair

                                           Compensation and Transparency in

                                           Land Acquisition, Rehabilitation and

                                           Resettlement Act, 2013 and Section

                                           3D of the National Highways Act,

                                           1956,         are        the       statutory

                                           incorporations of this principle.

                                           (iii) Highlighting the importance of

                                           the declaration of the decision to

                                           acquire, the Courts have held that

                                           the declaration is mandatory, falling

                                           which, the acquisition exceedings

                                           will cease to have effect.

                                           30.4. The Duty to acquire only for

                                           public      purpose:      (i)    That     the

                                           acquisition must be for a public

                                           purpose is inherent and an important

                                           fetter on the discretion of the

                                           authorities         to   acquire.        This

                                           requirement, which conditions the

                                           purpose of acquisition must stand to
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          13/29




                                           reason with the larger constitutional

                                           goals       of   a    welfare     state   and

                                           distributive justice.

                                           (ii) Sections 4 and 6 of the Land

                                           Acquisition Act, 1894, Sections 3(1)

                                           and 7(1) of the Requisitioning and

                                           Acquisition of Immovable Property

                                           Act, 1952, Sections 2(1), 11(1), 15(1)

                                           (b) and 19(1) of the Right to Fair

                                           Compensation and Transparency in

                                           Land Acquisition, Rehabilitation and

                                           Resettlement Act, 2013 and Section

                                           3A(1) of the National Highways Act,

                                           1956         depict         the     statutory

                                           incorporation of the public purpose

                                           requirement            of         compulsory

                                           acquisition.



                                           (iii) The decision of compulsory

                                           acquisition of land is subject to

                                           judicial review and the Court will

                                           examine and determine whether the
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          14/29




                                           acquisition is related to public

                                           purpose. If the court arrives at a

                                           conclusion that that there is no

                                           public purpose involved in the

                                           acquisition, the entire process can be

                                           set-aside. This Court has time and

                                           again reiterated the importance of

                                           the         underlying       objective      of

                                           acquisition of land by the State to be

                                           for a public purpose.

                                           30.5. The Right of restitution or fair

                                           compensation: (i) A person's right

                                           to hold and enjoy property is an

                                           integral part to the constitutional

                                           right         under        Article       300A.

                                           Deprivation or extinguishment of

                                           that right is permissible only upon

                                           restitution, be it in the form of

                                           monetary                     compensation,

                                           rehabilitation        or     other   similar

                                           means. Compensation has always

                                           been considered to be an integral
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          15/29




                                           part of the process of acquisition.

                                           (ii)   Section   11   of    the    Land

                                           Acquisition Act, 1894, Sections 8

                                           and 9 of the Requisitioning and

                                           Acquisition of immovable Property

                                           Act, 1952, Section 23 of the Right to

                                           Fair          Compensation          and

                                           Transparency in Land Acquisition,

                                           Rehabilitation and Resettlement Act,

                                           2013, and Sections 3G and 3H of the

                                           National Highways Act, 1956 are the

                                           statutory incorporations of the right

                                           to restitute a person whose land has

                                           been compulsorily acquired.

                                           (iii) Our courts have not only

                                           considered that compensation is

                                           necessary, but have also held that a

                                           fair and reasonable compensation is

                                           the sine qua non for any acquisition

                                           process.

                                           30.6. The Right to an efficient and

                                           expeditious      process:    (i)    The
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          16/29




                                           acquisition process is traumatic for

                                           more        than     one      reason.        The

                                           administrative delays in identifying

                                           the land, conducting the enquiry and

                                           evaluating the objections, leading to

                                           a final declaration, consume time

                                           and energy. Further, passing of the

                                           award, payment of compensation

                                           and taking over the possession are

                                           equally      time     consuming.        It     is

                                           necessary for the administration to

                                           be efficient in concluding the process

                                           and within a reasonable time. This

                                           obligation must necessarily form

                                           part of Article 300A.

                                           (ii) Sections 5A(1), 6, 11A and 34 of

                                           the Land Acquisition Act, 1894,

                                           Sections      6(1A)     and     9      of     the

                                           Requisitioning and Acquisition of

                                           Immovable          Property     Act,        1952,

                                           Sections 4(2), 7(4), 7(5), 11(5), 14,

                                           15(1), 16(1), 19(2), 25, 38(1), 60(4),
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          17/29




                                           64 and 80 of the Right to Fair

                                           Compensation and Transparency in

                                           Land Acquisition, Rehabilitation and

                                           Resettlement Act, 2013 and Sections

                                           3C(1), 3D(3) and 3E(1) of the

                                           National      Highways    Act,     1956,

                                           prescribe for statutory frameworks

                                           for the completion of individual

                                           steps in the process of acquisition of

                                           land within stipulated timelines.

                                           (iii) On multiple occasions, upon

                                           failure to adhere to the timelines

                                           specified in law, the courts have set

                                           aside the acquisition proceedings.

                                           30.7. The Right of conclusion: (i)

                                           Upon conclusion of process of

                                           acquisition     and      payment      of

                                           compensation,     the    State     takes

                                           possession of the property in normal

                                           circumstances. The culmination of

                                           an acquisition process is not in the

                                           payment of compensation, but also
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          18/29




                                           in taking over the actual physical

                                           possession of the land. If possession

                                           is not taken, acquisition is not

                                           complete. With the taking over of

                                           actual possession after the normal

                                           procedures        of        acquisition,     the

                                           private holding is divested and the

                                           right, title and interest in the

                                           property, along-with possession is

                                           vested in the State. Without final

                                           vesting,      the        State's,     or      its

                                           beneficiary's right, title and interest

                                           in the property is inconclusive and

                                           causes      lot     of      difficulties.    The

                                           obligation to conclude and complete

                                           the process of acquisition is also

                                           part of Article 300A,



                                           (iⅱ)    Section        16     of    the     Land

                                           Acquisition Act, 1894, Sections 4

                                           and 5 of the Requisitioning and

                                           Acquisition of Immovable Property
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          19/29




                                           Act, 1952, Sections 37 and 38 of the

                                           Right to Fair Compensation and

                                           Transparency in Land Acquisition,

                                           Rehabilitation and Resettlement Act,

                                           2013, and Sections 3D and 3E of the

                                           National    Highways     Act,    1956,

                                           statutorily recognise this right of the

                                           acquirer.

                                           (iii) This step of taking over of

                                           possession has been a matter of

                                           great judicial scrutiny and this Court

                                           has endeavoured to construe the

                                           relevant provisions in a way which

                                           ensures non-arbitrariness in this

                                           action of the acquirer 20. For that

                                           matter, after taking over possession,

                                           the process of land acquisition

                                           concludes with the vesting of the

                                           land with the concerned authority.

                                           The culmination of an acquisition

                                           process by vesting has been a matter

                                           of great importance. On this aspect,
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          20/29




                                           the courts have given a large

                                           number of decisions as to the time,

                                           method      and   manner     by    which

                                           vesting takes place.



                     8. Accordingly, the contention is that having not

         followed the mandatory provision of the issuance of notices, the

         first principle of the right to notice having been breached, the

         decision taken by the respondents have to be interfered with.

                     9. A counter affidavit has come on behalf of the

         respondent no. 2 and 3 duly signed by the Additional District

         Land Acquisition Officer, Patna and learned State counsel has

         taken this Court to paragraph no.9 to 16 which read as under:

                                            9. that preliminary notification

                                            under      section   11   (1)    of   the

                                            RFCTLARR Act, 2013 has been

                                            issued vide letter no-2113, dated-

                                            02.09.2022 and Declaration vide

                                            letter no-1011, dated-03.05.2023.

                                            The possession has been handed

                                            over to Requisitioning Authority the

                                            on 27.01.2024;
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          21/29




                                            10. that the rate fixation of the land

                                            has been done after considering the

                                            higher value of the average value of

                                            the sale deeds preceding three

                                            years from the notification and

                                            MVR has been considered.

                                                  The average of the sale deed

                                                  has been found to be Rs.-

                                                  17,58,288.00 per acre whereas

                                                  the MVR of the land in question

                                                  which is agriculture in nature

                                                  has   been     fixed   to    be

                                                  17,50,000.00 per acre. Thus the

                                                  higher rate of Rs.-17,58,288.00

                                                  per acre has been considered

                                                  for the calculation of the

                                                  compensation amount to the

                                                  land owners.    Further     60%

                                                  solatium amount to those land

                                                  owners who have given their

                                                  land on their own and addition

                                                  of additional damages has been
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          22/29




                                                  added. The rate fixation report

                                                  dated-12.06.2023           which   has

                                                  been approved by the Collector,

                                                  Patna.

                                                  11. That the Award No-01, 02,

                                                  03, 04 and 05 (Annexure 05

                                                  series of the writ petition) has

                                                  been prepared in the name of

                                                  Sharma (Petitioner), Sharma,

                                                  Kamata Suman Ravindra Singh

                                                  and Chini Tiwari and issued

                                                  under section-37 (2) of the

                                                  RFCTLARR            Act,    2013    in

                                                  accordance with calculation as

                                                  law as per the mentioned in the

                                                  aforesaid paragraph.

                                                  12.That the land owners did not

                                                  turn     up   for     receiving    the

                                                  compensation amount inspite of

                                                  several notices sent to them and

                                                  paper publication also made in

                                                  this regard. There has been no
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          23/29




                                                  application filed by the land

                                                  owners         for     compensation

                                                  amount receiving even the after

                                                  10      days      of   new      paper

                                                  publication made in Hindustan

                                                  and Dainik Jagaran dated-

                                                  01.12.2023.

                                                  13.     That      accordingly     the

                                                  District       Land      Acquisition

                                                  passed order Officer, Patna has

                                                  Memo vide No-119, dated-

                                                  13.01.2024 whereby direction

                                                  has been made for depositing

                                                  the        100%        compensation

                                                  amount before the Learned

                                                  Court of the Land Acquisition

                                                  Rehabilitation and Resettlement

                                                  Authority, Patna under section-

                                                  77 (2) of the RFCTLARR Act,

                                                  2013.

                                                  14. That it is humbly submitted

                                                  that earlier in the aforesaid
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          24/29




                                                  order, due to typing mistake the

                                                  total compensation amount has

                                                  been inadvertently mentioned

                                                  as Rs. 1 28,72,796.00 instead of

                                                  Rs.-48,72,796.00.        The     said

                                                  amount of Rs-28,72,796.00 has

                                                  been earlier sent vide Cheque

                                                  No-086647,      dated-25.01.2024

                                                  to the Learned Court of the

                                                  Land Acquisition Rehabilitation

                                                  and      Resettlement     Authority,

                                                  Patna.



                                                  Thus an amended order vide

                                                  Memo          No-304,          dated-

                                                  29.01.2025 has been issued by

                                                  the District Land Acquisition

                                                  Officer, Patna whereby order

                                                  has been passed directing the

                                                  Nazir of the Land Acquisition

                                                  District Office, Patna to send

                                                  the   remaining         amount     of
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          25/29




                                                  Rs.20,00,000.00 to the Learned

                                                  Court of the Land Acquisition

                                                  Rehabilitation and Resettlement

                                                  Authority,      Patna.     The       said

                                                  amount of Rs.-20,00,000.00 has

                                                  been sent to the Authority vide

                                                  Cheque         No-300536,         dated-

                                                  30.01.2025.

                                                  15. That it is apparent from the

                                                  aforesaid        facts     that       the

                                                  answering        respondents         have

                                                  taken     needful         action       in

                                                  accordance with law in the

                                                  aforesaid matter.

                                                  16.     That     in    view     of    the

                                                  aforesaid       facts,    the     notice

                                                  dated-09.05.2023 under section

                                                  19 (1) of the RFCTLARR Act,

                                                  2013 issued by the Collector,

                                                  Patna     with        regard    to    the

                                                  aforesaid project is justified in

                                                  the eyes of law.
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          26/29




                     10. Learned State counsel submits that contrary to the

         stand taken by the petitioners (not in the affidavits in the writ

         petition) that no notice was issued prior to the declaration of the

         award, it clearly reflects from the paragraph no.9 of the counter

         affidavit that vide letter no.2113 dated 02.09.2022 notice under

         Section 11(i) of         ‘the 2013 Act’ has issued and when no

         objection was received with regard to the land in question, only

         thereafter, the declaration vide letter no. 10011 dated 02.05.2023

         came into existence.

                     11.Learned State counsel submits that 80% the work

         already stands completed but due to the petitioner putting spoke

         in the wheels, the entire work could not be completed yet.

                     12. Having heard the parties and pursuing the records,

         the facts that emerges is/are that the petitioners knocked the

         doors of the High Court with the prayer not to acquire their

         lands which they are cultivating. In the entire writ petition, no

         where it records that the notice under Section 11(i) of ‘the 2013

         Act’ was not issued thus breaching the first principle mandated

         by the Hon’ble Supreme Court in the case of Kolkata

         Municipal Corporation (Supra).

                     13. Further, the matter was first heard by a coordinate

         bench on 09.01.2025 and while directing the respondents to file
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          27/29




         affidavits, it was observed that status quo as existing today to be

         maintained.

                     14. The affidavits of the respondents came to be filed

         on 04.02.2025 after service of copy to the learned counsel for

         the petitioners. It recorded issuance of notice under Section

         11(i) of ‘the 2013 Act’ vide letter no. 2113 dated 02.09.2022.

         The petitioners chose not to file any reply to the counter

         affidavit rebutting the stand of the respondents despite receiving

         the affidavit on 04.02.2025 till the matter has been taken up for

         hearing. In between, adjournments were sought for and granted

         by another coordinate bench on 31.10.2025, 11.11.2025 and

         18.11.2025.

                     15. When the matter was lastly taken up on

         16.06.2026, once again prayer for adjournment was made but a

         stand was taken by the learned counsel that he intends to

         converse with the petitioners regarding compensation on the

         receipt of compensation amount as 80% of the work stands

         completed. This court thus adjourned the matter.

                     16. However, today, learned counsel for the petitioner

         has taken up the non issuance of notice under Section 11(i) of

         ‘the 2013 Act’ to interfere with the decision. This Court repeats

         that no reply to counter affidavit(dated 04.02.2025) has been
Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                          28/29




         filed by the petitioners rebutting the stand of the respondents

         that notice was indeed issued which followed the award.

                     17. This Court is thus satisfied that the respondents

         have followed the legal process in the said acquisition process

         which includes issuance of notice under Section 11(i) of ‘the

         2013 Act’ to the declaration of award.

                     18. Regarding the Hon’ble Supreme Court’s

         judgement in the Kolkata Municipal Corporation (Supra)

         cited by the petitioners, this Court observes that it no way

         applies in the case of the petitioners as they failed to rebut the

         specific stand taken by the respondents about the issuance of

         notice.

                     19.This Court further holds that the records show that

         the respondents followed the principles required in the case of

         acquisition as mandated in Kolkata Municipal Corporation

         (Supra). The petitioner never put forward their objection

         pursuant to the said notice and as such cannot claim that they

         were not heard.

                     20. Further, the acquisition has been made for ‘the

         Yojana’ which is definitely in public purpose.Thus, the second

         principle also was fulfilled, further, it is not the case of the

         petitioner that they have not been given fair compensation as
             Patna High Court CWJC No.11917 of 2023 dt.06-07-2026
                                                       29/29




                      mandated in Kolkata Municipal Corporation(Supra).

                                  21.The respondents have further taken efficient and

                      expeditious process and have concluded the acquisition

                      proceeding following all the legal procedure, thus, all the

                      principles mandated in Kolkata Municipal Corporation

                      (Supra).

                                  22. Lots of water has flown down the ganges and now

                      the time has come for the respondents to complete the project

                      which is pending since last 3-4 years. The petitioners, if so want

                      can receive the compensation amount after presenting their

                      respective documents.

                                  23. The aforesaid facts have been incorporated. This

                      takes the Court to only one conclusion. The writ petition lacks

                      merit and is accordingly dismissed. The status quo order passed

                      earlier gets merged with the order of dismissal.

                                  24. Let the copy of the order be sent to the office of

                      the Collector, Patna for his perusal/needful.




                                                     (Rajiv Roy, J)
Ravi/-Ankita
AFR/NAFR                AFR
CAV DATE
Uploading Date          08.07.2026
Transmission Date


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.