Holding
The arbitration appeals are dismissed because the lower court had jurisdiction and the claims are time‑barred.
Summary
The case involved three identical arbitration appeals filed by the Godavari Marathwada Irrigation Development Corporation against contractor S.S. Deshmukh concerning a renovation contract for a canal. The contractor had obtained an arbitration award, which was subsequently challenged under Section 34 of the Arbitration and Conciliation Act, 1996, and the matter passed through several courts before reaching the High Court. The appellant argued that the lower court lacked jurisdiction because the dispute value was below the Rs 50 lakh threshold for a commercial court, and that the claim was time‑barred under Article 18 of the Limitation Act, 1963. The respondent contended that the principal district judge was competent to hear the matter and that the limitation period began only after the final bill was paid on 1 September 1999. The High Court held that the principal district judge had proper jurisdiction as the dispute value was below Rs 50 lakh and that the limitation period had indeed expired, rendering the claims barred. Consequently, all three arbitration appeals were dismissed.
Issues considered
- Whether the Principal District Judge, Aurangabad, had jurisdiction to entertain the Section 34 application despite the commercial court notification and the monetary value of the dispute.
- Whether the arbitration award is barred by limitation under Article 18 of the Limitation Act, 1963, given the dates of final bill payment and notice of arbitration.
Legislation cited
- Arbitration and Conciliation Act, 1996 — s. 21, 33, 34, 37
- Commercial Courts Act, 2015 (as amended 2018) — s. 3-A
- Limitation Act, 1963 — s. Article 18
Subjects
- arbitration
- jurisdiction
- commercial court
- limitation
- Section 34 challenge
- public works contract
- interest
- security deposit
Judgment
2026:BHC-AUG:20987
1 Arba30.2021+
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
ARBITRATION APPEAL NO. 29 OF 2021
. GODAVARI MARATHWADA
IRRIGATION DEVELOPMENT
CORPORATION, AURANGABAD,
Through the Executive Engineer,
Jayakwadi Irrigation Division (North),
Paithan, District: Aurangabad .. Appellant
(Original Respondent)
VERSUS
. S. S. DESHMUKH,
Dnyanai, Plot No.25,
Saraswati Colony No.2, Georai,
Dist. Beed .. Respondent
(Original Claimant)
...
Advocate for Appellant : Mr. Sudhir Govind Bhalerao
Advocate for Respondent : Mr. Amol K. Gawali
...
WITH
ARBITRATION APPEAL NO. 30 OF 2021
GODAVARI MARATHWADA IRRIGATION DEVELOPMENT
CORPORATION THR EXECUTIVE ENGINEER JAYAKWADI
VERSUS
S. S. DESHMUKH
…
Advocate for Appellant : Mr. Sudhir Govind Bhalerao
Advocate for Respondent : Mr. Amol K. Gawali
WITH
ARBITRATION APPEAL NO. 31 OF 2021
GODAVARI MARATHWADA IRRIGATION DEVELOPMENT
CORPOATION THR EXECUTIVE ENGINEER JAYAKWADI
VERSUS
S. S. DESHMUKH
…
Advocate for Appellant : Mr. Sudhir Govind Bhalerao
2 Arba30.2021+
Advocate for Respondent : Mr. Amol K. Gawali
WITH
CIVIL APPLICATION NO. 7008 OF 2021
IN ARBA/30/2021
GODAVARI MARATHWADA IRRIGATION DEVELOPMENT
CORPORATION THR EXECUTIVE ENGINEER JAYAKWADI
VERSUS
S. S. DESHMUKH
…
Advocate for Applicant : Mr. Sudhir Govind Bhalerao
Advocate for Respondent : Mr. Amol K. Gawali
WITH
CIVIL APPLICATION NO. 7007 OF 2021
IN ARBA/29/2021
GODAVARI MARATHWADA IRRIGATION DEVELOPMENT
CORPORATION AURANGABAD THR EXECUTIVE ENGINEER
JAYAKWADI
VERSUS
S.S. DESHMUKH
…
Advocate for Applicant : Mr. Sudhir Govind Bhalerao
Advocate for Respondent : Mr. Amol K. Gawali
WITH
CIVIL APPLICATION NO. 7009 OF 2021
IN ARBA/31/2021
GODAVARI MARATHWADA IRRIGATION DEVELOPMENT
CORPORATION THR EXECUTIVE ENGINEER JAYAKWADI
VERSUS
S. S. DESHMUKH
…
Advocate for Applicant : Mr. Sudhir Govind Bhalerao
Advocate for Respondent : Mr. Amol K. Gawali
...
CORAM : ARUN R. PEDNEKER, J.
DATE : 08.05.2026
3 Arba30.2021+
JUDGMENT:
1. Heard Mr. Sudhir Govind Bhalerao, learned counsel for
the Appellant and Mr. Amol K. Gawali, learned counsel for the
Respondent.
2. The matters are identical and involves similar issue, so
also, to avoid rigmarole are taken up together.
3. The facts are taken up from Arbitration Appeal No.30 of
2021. Facts giving rise to the Arbitration Appeal are that the
tender notice bearing No.1/1995-96 was issued by the Executive
Engineer, Jayakwadi Irrigation Division (North), Paithan, Dist.
Aurangabad, for execution of work for renovation and
improvement of minor and sub-minor of distributory-10 of Paithan
Left Bank Canal between Km.8.00 to 12.00. The estimated cost of
tender was Rs.6,82,505/- and the work was to be completed within
06 months from issuance of date of work order. In all the
Arbitration Appeals the work relates to renovation, improvement
of minors and sub-minors of distributary of P.L.B.C. canal from
from different Kilometers.
4. On 26.02.1996, the claimant was accepted as the lowest
and most competent bidder who had accepted to execute the work
at estimated cost of Rs.6,82,505/-. Work order was issued in favour
4 Arba30.2021+
of the claimant on deposit of earnest amount of Rs.13,650/- and
Rs.34,125/- in the form of initial security deposit.
5. On 31.12.1998, one time extension was granted. Final
bill payment was made on 01.09.1999.
6. On 28.10.1999, the contractor called upon the Chief
Engineer, with copy to the Executive Engineer and Superintending
Engineer seeking settlement of various claims raised in the letter
under different heads.
7. On 19.02.2000, notice under Section 21 invoking
arbitration clause i.e. Clause No.53 of the tender condition was
issued seeking appointment of Arbitrator.
8. On 02.05.2000, Shri. D. B. Murkute, (Sole Arbitrator),
Retired Superintending Engineer was appointed as Sole Arbitrator
by the claimant contractor.
9. On 06.06.2001, Shri. D.B. Murkute (Sole Arbitrator)
along with a forwarding letter addressed to the Executive
Engineer, sent a copy of Arbitration Award which was passed by
him in favour of the claimant contractor.
5 Arba30.2021+
10. The Arbitration Award passed by Shri. D. B. Murkute
(Sole Arbitrator) was challenged under Section 34 of Arbitration
and Conciliation Act, 1996 by the appellant (Department) by filing
MARJI No. 201/2021 on 30.08.2001 and the learned Principle
District Judge Shri. T. V. Nalawade on 17.08.2009 allowed the
Application, thereby setting aside the Arbitration Award.
11. On 09.08.2010, the Hon'ble High Court (Coram: Shri. B.
R. Gawai J.) by common judgment and order passed in Arbitration
Appeal No.14/2009, 18/2009 and 19/2009 partly allowed the
appeals thereby set aside the Judgment dated 17.08.2009 passed
by the Principle District Judge setting aside the Arbitration Award,
and also set aside the Arbitration Awards. The Hon'ble High Court
appointed Shri. A. S. More (Superintending Engineer and
Administrator, Command Area Development Authority, Jalgaon) to
act as Sole Arbitrator and decide the Arbitration within 06 months
from the date of appearance.
12. On 24.08.2010, Claim Statement were filed by the
claimant contractor.
13. On 23.09.2010, Written Statement was filed by the
appellant /original opponent Department.
6 Arba30.2021+
14. On 15.11.2010, Rejoinder was filed by the claimant
contractor.
15. Since the Sole Arbitrator Shri. A. S. More could not
deliver the Arbitration Award within 06 months as directed by the
Hon'ble High Court, and his mandate had been terminated by efflux
of time, in exercise of powers under Sec. 11 (6) the Hon'ble High
Court appointed Hon'ble Shri. N. P. Chapalgaonkar, Retired High
Court Judge as Sole Arbitrator.
16. On 10.10.2012, pursis was filed by both the parties
adopting the pleadings filed before the earlier Arbitrator Shri. A. S.
More. Affidavit of Examination in Chief was filed by the claimant
Shri. S. S. Deshmukh in support of his claim.
17. On 12.11.2012, the Executive Engineer Jayakwadi
Irrigation Division (North), Paithan, Dist. Aurangabad filed
affidavit of examination in chief in support of his defense.
18. On 19.05.2013, both the claimant and the respondent
filed their written notes of argument before the Hon'ble Sole
Arbitrator.
19. On 10.07.2013, the Hon'ble Sole Arbitrator declared the
Arbitration Award. On an application under Section 33 a corrected
7 Arba30.2021+
final award was declared on 08.08.2013. The Sole Arbitrator had
considered and decided the following claims:
Claim No.1- Relates to non payment of cost of clearing and
removing bushes, shrubs and jungle from site work, claiming
Rs. 45,000/-. The claim of Rs. 45,000/- was allowed under
this head.
Claim No.2- The said claim relates to three items of Schedule-
B quantity for which higher rates were demanded as per
tender conditions for quantities executed above 130%.
1) Item No.3- excavation of soil, silt and soft murum. The
Arbitrator rejected the claim under this head.
2) Item No.9- In respect of construction of embankment in
casing zone, including transportation of material with leads.
The Arbitrator awarded Rs. 22,170.40 under this head.
Claim No.3- The claimant had claimed Rs. 3,00,000/- for
repairs which he was required to carryout from 04.07.1997
till 31.03.1999 as per the direction of the respondent
Department. The Sole Arbitrator based on evidence
before him recorded that, the claimant was required to
maintain the work and continuously carryout the repair
work till 31.03.1999, since the Department was making
inquiry about the finalization of bill. The Sole Arbitrator
granted Rs. 1,50,000/- under this head.
8 Arba30.2021+
Claim No.4- For refund of security deposit amounting to Rs.
53,639/- towards initial security deposit. The Hon'ble Sole
Arbitrator awarded Rs. 53,639/-.
The Sole Arbitrator granted 18% interest from
31.03.1997 on the awarded amount (Total Rs. 2,70,809.40)
i.e. Rs. 6,75,643.30. Thus the Sole Arbitrator awarded
amount of Rs. 9,46,425/- to be paid before 10.07.2013 and in
the eventuality of non payment directed that, the same would
carry at the rate of interest @ 18% till realization. By virtue of
the corrected award dated 08.08.2023 the Sole Arbitrator
rejected the objection as to jurisdiction raised by the
respondent.
20. On 25.11.2013, MARJI No.596/2013 was filed by the
appellant Department challenging the Arbitration Award under
Section 34 of the Arbitration Act. The paragraph No.9 of the
Appeal Memo records that, for the purpose of court fees and
jurisdiction the claim is valued at Rs. 11,31,441/-.
On 22.02.2016, the challenge to the Arbitration Award
under Section 34 of the Arbitration and Conciliation Act, 1996, in
the form of MARJI No. 596/2013 was rejected by the Learned
Principle District Judge, Aurangabad.
9 Arba30.2021+
21. On 23.01.2020, by common judgment and order passed
by the Hon'ble High Court (Coram: Shri. Rohit B. Deo J.) in
Arbitration Appeal No. 5/2017, 6/2017 and 7/2017, while hearing a
appeal under Section 37 of the Arbitration and Conciliation Act,
1996, the same was partly allowed, remitting the matters to the
Principle District Judge, Aurangabad to decide the Arbitration
Application under Section 34 on its own merits within a period of
90 days from date of appearance. The amount of Rs. 60,00,000/-
which was deposited by the appellant Department, out of which
50% was allowed to be withdrawn by the respondent on
undertaking. The undertaking given by the Contractor to
reimburse the said amount was continued till decision of
application under Section 34.
22. On 04.01.2021, the learned Principle District Judge,
Aurangabad as per directions of the Hon'ble High Court reheard the
advocate for both the parties and decided the Civil Misc.
Application No. 596/2013.
23. In March-2021, the judgment and decree dated
04.01.2021 passed by the Principal District Judge, Aurangabad in
Civil Misc. Application No. 596/2013 was challenge by filing
Arbitration Appeal No. 30/2021 i.e. the present Arbitration Appeal
10 Arba30.2021+
before the Hon'ble High Court under section 37 of the Arbitration
and Conciliation Act, 1996.
{1} JURISDICTION:
A) Contention of Advocate for Appellant:-
24. The Principal District Judge, Aurangabad while passing
impugned judgment dated 04.01.2021, while deciding the Civil
Miscellaneous Application No. 596/2013 did not have jurisdiction
to decide the same, since the Arbitration Award under challenge
under Section 34, being in the nature of commercial dispute, ought
to have been placed before the commercial court, which had
exclusive jurisdiction to decide the Civil Miscellaneous Application
No. 596/2013.
25. Thus, in the light of the fact that, by placing reliance on
the Government Notification dated 03.07.2019, issued by the Law
and Judiciary Department, whereby in exercise of power conferred
under Section 3-A of the Commercial Courts Act, 2015 (as amended
in 2018), the District Judge-1 at the District Head Quarter, was
recognized as 'Commercial Court' in Maharashtra, the jurisdiction
of the Principal District Judge, Aurangabad was impliedly barred.
The impugned judgment was therefore passed without jurisdiction.
11 Arba30.2021+
B) Submissions of Advocate for the Respondent :-
26. The Advocate for the respondent placed on record the
notification dated 03.07.2019 issued by the Law and Judiciary
Department under the signature of the Secretary Legal Advisor
Cum Joint Secretary to the Government, which was issued under
powers conferred under Section 3 (1A) of the Commercial Courts
Act, 2015 (as Amended in 2018), wherein the Government of
Maharashtra in consultation with the High Court of Bombay had
specified the pecuniary value of the Commercial Courts as Rs.
50,00,000/-within whole of Maharashtra.
27. He has further placed a office order issued by the
Principal District and Sessions Judge, Aurangabad bearing No. B-2
(10/2019), dated 22.08.2019, wherein the learned Principal
District Judge exercising administrative power in furtherance of
the above notification has bestowed the power of Commercial Court
on the Civil Judge, Senior Division (Senior most), Aurangabad to
decide Commercial Dispute at District Level of specified value
above Rs. 50,00,000/- (Rupees Fifty Lacs) and upto and inclusive
of Rs. 1 Crore.
28. The Advocate for the respondent Contractor pointed out
from the Appeal Memo of MARJI No. 596/2013 that the valuation
for the purpose of court fees and jurisdiction in the present appeal
12 Arba30.2021+
is Rs.11,31,441/- (Rupees Eleven Lacs Thirty One Thousand Four
Hundred Forty one), which is below Rs. 50,00,000/-lacs.
Similarly, the claim in MARJI No. 594/2013
(Arbitration Appeal No.29 of 2021) is valued at Rs.10,56,107/- and
in MARJI No. 595/2013 (Arbitration Appeal No.31 of 2021) is
valued at Rs.11,87,541/-, which is also below Rs. 50,00,000/-lacs.
29. This court finds that in view of the Notification dated
03.07.2019 issued by Law and Judiciary Department and
administrative order passed by the Learned Principal District
Judge on the administrative side, ‘the commercial dispute’ of
specified value above Rs. 50,00,000/- are to be decided by the
Commercial Court. Since the value of the dispute in the Arbitration
Appeal under challenge is much below Rs. 50,00,000/-, the regular
court i.e. the Principal Court of civil jurisdiction i.e. the Principal
District Judge had the jurisdiction to decide the Arbitration
Application under Section 34.
30. Thus the impugned judgment and order does not suffer
any jurisdictional error, since it is passed by a court having
jurisdiction to pass the impugned judgment and order.
02. Limitation:-
13 Arba30.2021+
A) Contention of the Advocate for the appellant Department:
31. The Advocate for the appellant Department by placing
reliance on the unreported Judgment passed in Arbitration Appeal
No. 6/2007 (State of Maharashtra V/s Hindustan Construction
Company and others), wherein this Hon'ble Court (Coram: Shri. R.
D. Dhanuka, J.) had pronounced the judgment on 01.02.2013,
contended that, the limitation would be governed by Article 18 of
the Limitation Act, which reads as under-
Article Description of application Period of Time from which
limitation period begins to
run
18 For the price of work done by Three years When the work
the plaintiff for the defendant is done.
at his request, where no time
has been fixed for payment.
32. Placing reliance on the above Judgment it was
contended that, the last extension was granted to the contract
awarded to the respondent was 31.12.1998, therefore the
Arbitration Proceedings initiated by the claimant are barred by
limitation, and therefore, the award deserves to be set aside.
33. It is his contention that, neither the learned Sole
Arbitrator nor the Learned District Judge has considered the
objection as to limitation which had been raised by the appellant
Department.
14 Arba30.2021+
B) Submissions of Advocate for the Respondent :-
34. The Advocate for the respondent, pointed out that, it is
a admitted fact that, the final bill has been paid on 01.09.1999.
35. The Advocate for the respondent by drawing attention
of the court to the discussion while granting Claim No.3 (Para No.
12 of the Arbitration Award, Page No. 17 to 19 of the Appeal
Memo), pointed out that, the Sole Arbitrator had held that, in
absence of final bill the contractor was required to work beyond the
contract period (including extensions) from 04.07.1997 to
31.03.1999 and the Arbitrator under this head had paid Rs.
1,50,000/- to the contractor.
36. It was also pointed out from the record that, the notice
under section 21 invoking Arbitration Clause was issued on
19.02.2000.
37. He has placed reliance on several Judgments, which lay
down that, the limitation would start from the date of final bill,
since the point of dispute would only arise after the contractor
becomes aware of the fact that, his claims have been finally
rejected on account of non payment of the same in the final bill.
15 Arba30.2021+
38. This court in the case of Executive Director, G.M.I.D.C.
and others Vs. M/s Gurunanak Industries and another, dated
17.01.2026, at Paragraph No.40, has observed as under:
“40. Article 18 of the Schedule to the Limitation Act, 1963
would apply only where the amount payable is known and
becomes payable on completion of work. However, in the
present case, although the physical work may have been
completed on 30/06/2013, the measurement of the work
and the escalated price was yet to be computed. The final bill
was required to be prepared after joint measurement and
after working out the escalation under the contractual
clause. Therefore, limitation would commence only upon
denial or partial payment of the final bill which occurred on
12/04/2016. The suit is filed on 21/12/2017 and is within
three years of payment of partial final bill and is thus within
limitation and would be covered under Article 55, of the
Limitation Act.”
39. In Arbitration Appeal No.30 of 2021, the date of
payment of final bill is 01.09.1999 and the notice under Section 21
was issued on 19.02.2000 and on 02.05.2000 the Arbitrator was
appointed.
In Arbitration Appeal No.29 of 2021, no final bill was
prepared or paid and the notice under Section 21 was issued on
19.02.2000 and on 02.05.2000 the Arbitrator was appointed.
In Arbitration Appeal No.31 of 2021, no final bill was
prepared or paid and the notice under Section 21 was issued on
19.02.2000 and on 02.05.2000 the Arbitrator was appointed.
As such, the claims filed before the Arbitrator are in
limitation.
16 Arba30.2021+
40. In view of the above, the Arbitration Appeals are
dismissed.
[ARUN R. PEDNEKER, J.]