Bombay High Court
NASHIK INFRASTRUCTURE DEVELOPERS PVT LTDversusMANAGING DIRECTOR MAHARSHTRA STATE ROAD DEVELOPMENT CORPORATION LTD
- Decided
- Disposal
- Disposed Off
Holding
The petition is to be treated as filed on the original side and the arbitral tribunal's mandate is extended for six months under Section 29-A.
Summary
The petitioner, Nashik Infrastructure Developers Pvt. Ltd., filed an arbitration petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of the arbitral tribunal's mandate which had expired on 31 January 2026. The respondent, Managing Director of Maharashtra State Road Development Corporation Ltd., contested that the petition was incorrectly filed in the appellate side, arguing that the seat of arbitration was Mumbai. The Court held that the petition should be treated as filed on the original side, given the seat of arbitration. Both parties jointly requested a six‑month extension, considering the advanced stage of the proceedings. The Court granted the extension, extending the tribunal's mandate until 31 July 2026, and ordered compliance upon posting of the order on the Court’s website.
Issues considered
- Whether the arbitration petition filed on the appellate side is maintainable when the seat of arbitration is Mumbai
- Whether an extension of the arbitral tribunal's mandate can be granted under Section 29-A of the Arbitration and Conciliation Act, 1996
Legislation cited
- Arbitration and Conciliation Act, 1996 — s. 29-A
Subjects
- Arbitration
- Extension of mandate
- Section 29-A
- Original side filing
- High Court of Bombay
Judgment
23-ARP-19-2026.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
ARBITRATION PETITION NO. 19 OF 2026
CHAITANYA
ASHOK
JADHAV
Digitally signed by
CHAITANYA ASHOK
Nashik Infrastructure Developers Pvt. Ltd. …Petitioner
JADHAV
Date: 2026.02.06
12:14:50 +0530
Versus
Managing Director Maharashtra State Road Devel-
opment Corporation Ltd. …Respondents
Mr. Aniruddha A. Garge, i/b Adv. Jitendra H. Oak, for the
Appellant.
Adv. Joshua D’souza, a/w Chirag Sancheti, Saad Memon i/b
Bulwark Solicitors, for the Petitioner.
CORAM : SOMASEKHAR SUNDARESAN, J.
DATE : FEBRUARY 2, 2026
ORDER :
1. Learned Advocate for the parties submit that the Petition has
wrongly been filed in the Appellate Side, since the seat of Arbitration is
Mumbai.
2. In these circumstances, the Petition be treated as a Petition
filed on the Original Side.
3. This is a Petition under Section 29-A of the Arbitration and
Conciliation Act, 1996, seeking an extension of mandate of the Arbitral
Tribunal, which expired on January 31, 2026.
Page 1 of 2
February 2, 2026
Chaitanya
23-ARP-19-2026.doc
4. Today, when the matter is called out, Learned Counsel for the
parties jointly request for an extension of mandate by a period of six
months, bearing in mind the stage at which the arbitral proceedings are
placed.
5. In these circumstances, taking into account the stage at
which the Arbitral proceedings are placed, this Petition is finally
disposed of extending the mandate of the Arbitral Tribunal for a
period of six months i.e., until July 31, 2026.
6. All actions required to be taken pursuant to this order shall
be taken upon receipt of a downloaded copy as available on this Court’s
website.
[ SOMASEKHAR SUNDARESAN, J.]
Page 2 of 2
February 2, 2026
Chaitanya