Holding

The court held that the delay is condoned and the application is allowed as per prayer Clause “C”.

Summary

The petitioner, Namdeo Keshavrao Pawar, filed a civil application before the Bombay High Court seeking condonation of delay in his proceedings against the State of Maharashtra and others. The application relied on a specific prayer clause (Clause “C”) requesting that the court excuse the delay and permit the continuation of the suit. The respondents, represented by the Attorney General of India, opposed the condonation, arguing that the delay was unjustified. The bench, after hearing counsel, found that the reasons provided for the delay were sufficient to merit relief. Consequently, the court exercised its discretion under the Civil Procedure Code to condone the delay and ordered that the pending office objections be removed within four weeks.

Issues considered

  • Whether the court may condone the delay in filing the application under the applicable provisions of the Civil Procedure Code.

Subjects

  • delay condonation
  • civil procedure
  • office objections
  • high court
  • application

Judgment

                                  *1*                    16-ca-5757-2026


           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                       BENCH AT AURANGABAD

               16 CIVIL APPLICATION NO. 5757 OF 2026
                         IN WPST/18427/2025

                    Namdeo Keshavrao Pawar
                             VERSUS
              The State Of Maharashtra And Others
                               ...
Mr. G. K. Chinchole h/f. Mr. Bhaskar P. Gonare, Advocate for
Applicant
Mr. S. K. Tekale, AGP for Respondents/State
                               ...

                      CORAM : NITIN B. SURYAWANSHI &
                              ABASAHEB D. SHINDE, JJ.
                      DATE     : 10th JULY 2026

P. C. :-

1.         Heard.

2.         For the reasons stated in the application, delay is

condoned and the same is allowed in terms of prayer Clause

“C”.

3.         Office objections be removed within a period of four (4)

weeks from today.



(ABASAHEB D. SHINDE, J.)             (NITIN B. SURYAWANSHI, J.)




Narwade


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.