Bombay High Court

CONSO FEEDSversusALFA LAVAL (INDIA) PVT.LTD

Decided
Disposal
DISMISSED

Holding

The High Court dismissed the Section 34 petition, upholding the arbitrator’s award and finding no ground for interference.

Summary

The petitioner, Conso Feeds, purchased a fishmeal plant from Alfa Laval (India) and paid Rs. 4.94 crore, securing a performance bank guarantee of Rs. 2.45 crore. The plant could not be commissioned due to alleged design and equipment defects, leading the petitioner to invoke arbitration under the Arbitration and Conciliation Act, 1996. The sole arbitrator awarded a refund of Rs. 4.45 crore for the purchase price but held that claims 15(2) to 15(8) – covering excise duty, taxes, freight, accommodation, infrastructure upgrades, raw material costs, interest and loss of business – were barred by Clause 10(a) and 10(b) of the Techno‑Commercial Agreement and capped at the amount of the bank guarantee. The petitioner challenged this award via a Section 34 petition, arguing that the clauses should not exclude direct losses, that interest pendente lite was wrongly denied, and that the award was perverse and violative of public policy. The High Court held that the arbitrator’s interpretation of the contract was a plausible view, not patently illegal or perverse, and that Section 34 does not permit substitution of the court’s view for that of the arbitrator. Consequently, the petition was dismissed, leaving the award intact.

Issues considered

  • The applicability of Clause 10(a) and 10(b) of the Techno‑Commercial Agreement to exclude claims 15(2)‑15(8).
  • Whether the arbitrator erred in interpreting the warranty clause and its precedence over Clause 10.
  • The entitlement to interest pendente lite under Section 31(7) of the Arbitration Act.
  • Whether the award is perverse, patently illegal or violative of public policy, warranting interference under Section 34.
  • The scope of judicial review of an arbitral award under the Arbitration and Conciliation Act, 1996.

Legislation cited

Subjects

  • Arbitration
  • Section 34 petition
  • Contract interpretation
  • Consequential damages
  • Limitation of liability
  • Performance bank guarantee
  • Interest pendente lite
  • Public policy
  • Breach of contract
  • Fishmeal plant

Judgment

2026:BHC-OS:17613

                                                                    CARBP-1267-2018 (final).doc


                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
                                       IN ITS COMMERCIAL DIVISION

                         COMMERCIAL ARBITRATION PETITION NO. 1267 OF 2018

                Conso Feeds                                  ]
                Eara P.O., Neelamperoor, Alappuzha,          ]
                District 686534, represented by its Managing ]
                Partner                                      ]
                                                                 ...Petitioner

                         Versus

                Alfa Laval (India) Pvt. Ltd.                   ]
                Registered Office at Mumbai-Pune Road,         ]
                Dapodi, Pune – 411012,                         ]
                Through its Managing Director                  ] ...Respondent
                                               ——————
                Mr. Anil D’souza, Mr. Akash Rebello, Mr. Paras Gosar and Mr. Nadeem Shama for
                the Petitioner.
                Mr. Sharan Jagtiani, Senior Advocate a/w Mr. Rohil Bandekar, Mr. Nitin Khare,
                Mr. Ritwik Kulkarni and Mr. Akhil Khupade for the Respondent.
                                               ——————
                                                       Coram : Sharmila U. Deshmukh, J.
                                                       Reserved on : 10th July, 2026.
                                                       Pronounced on : 6th August, 2026.
                Judgment :
                1.        The present Petition filed under Section 34 of the Arbitration

                and Conciliation Act, 1996 is at the instance of the original Claimant

                being partly aggrieved by the impugned Award to the extent that the

                Claims 15(2) to 15(8) have been held to be barred by Clauses 10 (a) and

                (b) of Techno Commercial Agreement dated 10 th September, 2014 and

                capped by the Arbitrator to the extent of the amount of the Bank



                Sairaj                            1 of 36
                                                  CARBP-1267-2018 (final).doc


Guarantee which is invoked and encashed by the Claimant.

2.       The arbitration agreement was invoked by the Claimant seeking

resolution of disputes which arose between the parties under an

Agreement of 10th September, 2013 executed between the Claimant

and the Respondent for the purchase and installation of fishmeal

plant.

3.       The Petition sets out that by purchase order of 11 th September,

2013 read with Techno Commercial Agreement dated 10 th September,

2013, the Claimant had purchased fishmeal plant from the

Respondent, which the Respondent was required to supply, erect and

commission. Despite various attempts, the plant could not be

commissioned solely due to the faulty design and equipment supplied

by the Respondent and the Claimant called upon the Respondent to

take back the plant. As there was no refund of the price of the plant as

initially claimed by the Claimant, arbitration was invoked. In the Section

11 application, the learned Sole Arbitrator came to be appointed by

this Court.

4.       The statement of the claim (SOC) sets out that the pursuant to

the discussions and negotiations, on 10th September, 2013, the

Respondent submitted the final quotation with detailed payment

terms and in response thereof, on 11th September, 2013, the Claimant

issued the purchase order, which was confirmed. The entire payment of


Sairaj                            2 of 36
                                                  CARBP-1267-2018 (final).doc


the purchase order was paid in time aggregating to Rs. 4,94,49,669/-

and Bank guarantee was issued in favor of the Respondent in the sum

of Rs. 2.45 crores representing the balance payment and performance

guarantee was given by the Respondent in favor of the Claimant. As

per the Agreement, the erection and the commissioning of the fish

meal plant was to be completed by 31 st March, 2014, which was

delayed for reasons attributable to the Respondent. On 5 th September,

2014, the Respondent invoked the Bank guarantee which would have

expired only on 24th September, 2014. On 19th September, 2014, the

first trial run of the plaint was conducted, which failed. The email

correspondences are relied upon to substantiate that the subsequent

eight production trials till 12th December, 2014 also failed.

5.       The Claimant had availed financial assistance to the tune of

7,06,75,777/- from Federal Bank in addition to incurring huge interest

amount to the tune of Rs. 2,01,41,515/-. The claim under various heads

was for sum of Rs. 17,64,81,771/-.

6.       In its Written Statement-cum-Counterstatement of claim, the

Respondent claimed that the Respondent could not erect and install

the plant immediately as the site was not ready. The provisions of

utilities could be made only in September, 2014 when the first trial was

conducted. The Claimant failed to supply sufficient quantity of raw

material to run the plaint at its optimum level. The commercial


Sairaj                           3 of 36
                                                  CARBP-1267-2018 (final).doc


operation of the plant commenced on 12 th November, 2014 without

any interruption and that there was non-compliance of the conditions

imposed by the Kerala Pollution Control Board for operating the said

plant, which was violated resulting in pollution. The Claimant in

collusion with the ICICI Bank got the performance bank guarantee

encashed fraudulently much before the expiry date and further sent a

legal notice on 21st October, 2015 demanding                 sum of Rs.

16,46,34,828/-. There was successful and satisfactory commission and

performance trial of the fishmeal plant giving no cause of action for

any liability upon the Respondent. The counter claim of the

Respondent was for a sum of Rs. 44,50,000/- plus interest at the rate of

15% per annum being encashment of performance bank guarantee by

the claimant.

7.       The Learned Arbitrator held that there was breach of contract by

the Respondent and the Claimant had performed its part of obligation

under the Techno Legal Commercial Agreement dated 10 th September,

2013 and Purchase Order dated 11th September, 2013. It further held

that the Claimant had rightly invoked the performance bank guarantee

and answered the counter claim against the Respondent. Insofar as the

claim for Rs 17,64,81,771/- is concerned, the learned Arbitrator

directed refund of purchase price of Rs. 4,45,00,000/- with interest

therein at the rate of 9% p.a. from the date of Award till the payment


Sairaj                            4 of 36
                                                 CARBP-1267-2018 (final).doc


and realization and upon such payment, the Respondent was entitled

to take back its supplies and equipment from the Claimant’s site of the

fishmeal plant, within a period of six months from the date of payment.

The claims from 15(2) to 15(8) were held to fall within the ambit of

Clause 10(a) and (b) of the general terms and conditions in Section VI of

the Techno Commercial Agreement and held to be limited to amount

of the bank guarantee which was invoked and encashed by the

Claimant.

8.       Mr. D’souza, learned counsel appearing for the Petitioner would

point out that the claims 15(2) to (7) were in respect of excise duty,

sales tax, freight charge, etc. which were incurred by the Claimant

towards the installation of the plant. He would further point out the

relevant Issue No 5 as to the entitlement of the Claimant to the sum of

Rs.17,64,81,771/- or any part thereof. He submits that as the Arbitrator

has directed the refund of the purchase price of the plant, it is

accepted that there is a breach of contract by the Respondent. He

would submit that as the breach has been admitted, there was no

question of application of clause 10(a) and 10(b) of the Agreement to

direct losses. He submits that the claims raised by the claimant were

not indirect, but actual expenses incurred and not a claim based on

reimbursement of actual expenses. He submits that the defense of the

claims being barred by Clause 10(a) is not the pleaded case of the


Sairaj                            5 of 36
                                                 CARBP-1267-2018 (final).doc


Respondent and therefore the Claimant did not have an opportunity of

dealing with the same.

9.       He would submit that there is an inherent contradiction in the

Award by pointing out that the learned Arbitrator while rejecting other

claims held it to be barred by Clause 10(a) of the Techno Commercial

Agreement contrary to its own finding that Clause 10(a) was attracted

only after the machinery was supplied and commissioned. He submits

that as the Tribunal has held that the plant has not commissioned,

there is no question of clause 10(a) being applied to the present case.

He has taken this Court in detail through the findings of the Arbitrator

in paragraph 126 to 136 and 147 of the Award. He submits that the

claim towards payment of interest under Claim 15(7) cannot be

construed to be an indirect or consequential damage or liability as

provided in Clause 10 and according to him, there is error in not

awarding interest from date of payment of purchase price and

pendente lite. He submits that by the clarificatory order passed under

Section 33 of Arbitration Act, the Arbitrator has clarified that interest

pendente lite has not been granted. He submits that once the

Arbitrator comes to a conclusion that damages are payable due to

failure to commission the plant, damages by way of interest from date

of payment of purchase price and pendente lite has to follow. He

submits that the Claimant is entitled to interest on all the claims as


Sairaj                           6 of 36
                                                  CARBP-1267-2018 (final).doc


provided in Section 31(7) of the Arbitration Act and the refusal to

award such interest is against the public policy of India and liable to be

set aside.

10.      He submits that Claims 15(2) to 15(7) cannot be treated as

consequential damage or loss of profit as a matter of fundamental and

substantive law of India. He submits that it is not        a question of

interpretation of contract, but a matter of application of substantive

law. He submits that any finding to the contrary will be perverse,

patently illegal as well as violative of public policy. He submits that the

loss on account of payment of excise duty, sales tax, freight charges,

etc. were clearly direct and not consequential loss and once the

Arbitrator arrives at a conclusion that Clause 10(a) relates only to

consequential damages, he could not have excluded Claims 15(1) to

15(7). He submits that the claims being direct damages were not

capable of being excluded by Clause 10(a) and ought have been

allowed.

11.      He would further submit that upon plain reading of the

Agreement, clause 10(a) and (b) is superseded by warranty clause and

offer letter dated 10th September, 2014 by virtue of clause 10(h) as per

the general terms and conditions. He submits that the warranty clause

makes it clear that the Respondent is not responsible for any

consequential or indirect damages and by providing an express clause


Sairaj                           7 of 36
                                                  CARBP-1267-2018 (final).doc


for damages in the main Agreement, Clause 10(a) and (b) stands

excluded.

12.      He submits that the Petitioner’s claim is for expenses as well as

loss of profits which are direct damages and Claim 15(8) which is loss of

business opportunity is a direct damage and not an indirect damage.

He submits that the Arbitrator erred in rejecting the arguments of the

Claimant that the rule of contra proferentem must apply to the

interpretation of clause 10(a). He submits that the contract must be

interpreted against the person who has drafted the contract and in the

present case, the offer sheet has been prepared by the Respondent

and must be interpreted against the Respondent.

13.       He submits that the reading of the Tribunal of Clause 10(a)

amounts to rewriting of the contract between the parties and is an

error apparent on the face of record, perverse and illegal. He submits

that the interpretation of the Arbitrator of clause 10(a) of the contract

is an impossible interpretation which would warrant interference under

Section 34 of Arbitration Act.

14.      He would further submit that the written statement of the

Respondent does not speak of limitation of liability and despite

thereof, the Arbitrator has limited the liability to the extent of bank

guarantee. He submits that the claims set out in paragraph 130 of the

Award have been accepted by the Arbitrator, however, the Arbitrator


Sairaj                            8 of 36
                                                  CARBP-1267-2018 (final).doc


has limited the same to the amount of Bank guarantee, which is a

perverse finding. In support, he relies upon the following decisions :

             Deepak Fertiliser and Petrochemical Corporation vs.
             Davy Mckee (London) Ltd.1

             Union of India vs. Saraswat Trading Agency2

             South East Asia Marine Engineering               and
             Constructions Ltd. vs. Oil India Ltd.3

             Delhi Metro Rail Corporation Ltd. vs. Delhi Airport
             Metro Express Pvt. Ltd.4

15.      Per contra, Mr. Jagtiani, learned Senior Advocate appearing for

the Respondent would submit that the apart from refund of purchase

price, the other claims were in the nature of damages for the breach of

the contract. He submits that the contention that the Respondent has

not taken the defence of Claims 15(2) to 15(8) being excluded by

Clause 10, cannot be entertained by Section 34 Court as it would

amount to re-appreciation of evidence. He submits that it is well

settled that the Arbitrator is the best judge of the quality and quantity

of evidence. He further points out that the Respondent has specified

that its liability as per the agreed terms is restricted to the

performance guarantee and the Claimant had sufficient notice about

denial of its claim by reason of Clause 10(a) of the Agreement.

16.      He would further submit that the entire submissions of Mr.
1     (1998) EWCA Civ 1753.
2     (2009) 16 SCC 504.
3     (2020) 5 SCC 164.
4     (2024) 6 SCC 357.



Sairaj                            9 of 36
                                                 CARBP-1267-2018 (final).doc


D’souza is to assail the interpretation of the contract by the Arbitrator,

which is impermissible in Section 34 Petition. He submits that the view

taken by the Arbitrator being a possible view cannot be interfered and

substituted by view of this Court.    He has taken this Court to Clause

10(a) of the Agreement to contend that the same is divided in two

parts and in the first part damages on account of the specified

eventualities are excluded from the Respondent’s liability and second

part capped the liability of the Respondent at the value of

performance bank guarantee. He submits that it is also a possible

interpretation that the warranty clause does not supersede Clause 10

of general terms and condition. He submits that the Award is founded

on interpretation of the terms of the contract and there is no issue of

violation of fundamental and substantive law of India.

17.      He would further submit that power of the Arbitrator to award

pre-reference interest, pendente lite interest, and post award interest

under Section 31(7) is well settled and the relief sought in the present

case was to award future interest and costs against the Respondent.

He submits that the Arbitrator by the additional award has declined the

Claimant’s relief of grant of pendente lite interest. He submits that

discretion has been rightly exercised by the arbitrator, no interference

is warranted. To support his contentions, reliance is placed on the

following decisions:


Sairaj                          10 of 36
                                                                  CARBP-1267-2018 (final).doc


            Securitrans India Pvt. Ltd. vs.                       FIS   Payment
            Solutions and Services Pvt. Ltd.5

            United India Insurance Company Ltd. vs. UPL
            Limited6

             Thermax Ltd.            vs.    Rashtriya        Chemicals        and
             Fertilizers7

             Associate         Builders       vs.      Delhi       Development
             Authority8

             Oil and Natural Gas Corporation Ltd. vs. Saw Pipes
             Ltd.9

              Sangyong Engineering and Construction Company
              Ltd. vs. National Highways Authority of India10

              Larsen Air Conditioning and Refrigration Company
              vs. Union of India11

              Batliboi Environmental Engineers Ltd.                            vs.
              Hindustan Petroleum Corporation Limited12

             Reliance Infrastructure Limited vs. State of Goa13

             S. V. Sundaram vs. State of Karnataka14

             Rajasthan State Mines and Minerals Ltd. vs.
             Eastern Engineering Enterprises15

             Associated Engineering Co. vs. Government of
             Andhra Pradesh16


5    Judgment dated 23.12.2023 passed in CARBP No. 750 of 2024.
6    2026 SCC OnLine Bom 2679.
7    2025 SCC Online Bom 5010.
8    (2015) 3 SCC 49.
9    (2003) 5 SCC 705.
10   (2019) 15 SCC 131.
11   2023 SCC OnLine SC 982.
12   (2024) 2 SCC 375.
13   (2024) 1 SCC 479.
14   (2024) 3 SCC 623.
15   (1999) 9 SCC 283.
16   (1991) 4 SCC 93.



Sairaj                                     11 of 36
                                                 CARBP-1267-2018 (final).doc


            Ramnath International Construction (P) Ltd. vs.
            Union of India17

            Vilayati Ram Mittal (P) Ltd. vs. Reserve Bank of
            India18

            John Peter Fernandes vs. Saraswati Ramchandra
            Ghanate since deceased and Others19

            Pam Developments Private Limited vs. State of
            West Bengal20

            UHL Power Company Limited vs. State of Himachal
            Pradesh21

            Dyna Technologies Private Limited vs. Crompton
            Greaves Limited22

            Parsa Kente Collieries Limited vs. Rajasthan Rajya
            Vidyut Utpadan Nigam Limited23

            Rashtriya Ispat Nigam Limited vs. Dewan Chand
            Ram Saran24

            South East Asia Marine Engineering               and
            Constructions Limited vs. Oil India Limited25

            Morgan Securities and Credits Private Limited vs.
            Videocon industries Limited26

            Hyder Consulting (UK) Limited vs. Governor, State
            of Orissa through Chief Engineer27

            Secretary, Irrigation Department, Government of

17   (2007) 2 SCC 453.
18   2017 SCC OnLine Bom 8479.
19   2023 SCC OnLine Bom 676.
20   2024 SCC OnLine SC 2247.
21   (2022) 4 SCC 116.
22   (2019) 20 SCC 1.
23   (2019) 7 SCC 236.
24   (2012) 5 SCC 306.
25   (2020) 5 SCC 164.
26   (2023) 1 SCC 602.
27   (2015) 2 SCC 189.



Sairaj                           12 of 36
                                                   CARBP-1267-2018 (final).doc


              Orissa vs. G. C. Roy28

              NHAI vs. M. Hakeem29

              S. V. Sundaram vs. State of Karnataka30

18.      In rejoinder, Mr. D’souza would submit that there is a patent

illegality as Clause 10(a) does not include interest and therefore, the

Arbitrator could not have limited the claim for interest while capping

the liability. He submits that the Award is severable as claim 15(1) has

been granted and claim 15(2) to 15(8) has been rejected, which are

different heads of the claim and therefore, good part of the Award can

be retained while severing the bad part of the Award. He submits that

the decision in the case of OPG Power Generation Private Limited vs.

Enexio Power Cooling Solutions India31 will apply when the ultimate

conclusion is not disturbed and not when there is an inherent

contradiction and ultimate conclusion would change. He would further

distinguish the judgment on interest cited by Mr. Jagtiani to contend

that the bank interest claimed is pendente lite interest and Section

31(7) discretion has not been exercised. He submits that the bank

interest is raised as claim only to show what has been paid as interest.

19.      Rival contentions now fall for determination.

20.      At the heart of controversy is Clause 10(a) and (b) and Warantee

28    (1992) 1 SCC 508.
29    (2021) 9 SCC 1.
30    (2024) 3 SCC 623.
31    2024 INSC 711.



Sairaj                                 13 of 36
                                                  CARBP-1267-2018 (final).doc


Clause of the Techno-Commercial Agreement dated 10 th September,

2013. In so far as refund of purchase price is concerned, the Learned

Arbitrator has held that there is breach of contract by the Respondent

and had awarded refund of purchase price and rejected Claims 15(2) to

15(8). Claims 15(2) and 15(3) are claims for amounts of excise duty,

state tax, freight and insurance charges. Claim 15(4) is a claim for

expenses incurred for accommodation of Respondent’s engineers and

officials. Claim 15(5) is a claim for expenses incurred for upgradation of

infrastructure to suit contracted plant and supporting machinery

including drier. Claim 15(6) is claim for raw material cost for seven

trials. Claim 15(7) claims bank interest upto 31 st October, 2016 and

Claim 15(8) is damage suffered on account of business opportunity

loss, mental agony and loss of reputation.

21.      In paragraph no. 15 of the SOC, the Claimant has set out various

claims against the Respondent, as under:

  1. Price of the Plant                            Rs. 4,45,00,000.00
  2. Excise Duty, Sales Tax                        Rs. 49,49,669.000
  3. Freight charges and insurance                 Rs. 4,33,608.000
  4. Expenses for accommodation of Alfalaval’s
     Engineers and Officials                       Rs. 4,15,250.000
  5. For up-gradation of infrastructure to suit
     contracted Plant and supporting machinery
     including drier                               Rs. 2,61,27,517.000
  6. Raw Materials cost for seven trial runs       Rs. 18,22,335.000
  7. Bank interest upto 31.10.2016                 Rs. 2,26,83,392.000
  8. Damage suffered on account of business


Sairaj                           14 of 36
                                                       CARBP-1267-2018 (final).doc


         loss’ opportunity loss, mental agony and loss
         of reputation limited to                      Rs. 8,00,00,000.00
                                   Total               Rs. 18,09,31,771.00

         Less : Amount of performance Guarantee
         enforced to mitigate the loss without
         prejudice to any of the claims as above        Rs. 44,50,000.00
                                Balance Payable         Rs. 17,64,81,771.00


22.       The Learned Arbitrator has held that Claims 15(2) to 15(8) fall

within the ambit of Clause 10(a) and capped the same to the limit of

bank guarantee. The general terms and conditions are contained in

Clause 10(a), 10(b), 10(h) of the Agreement dated 10 th September, 2013

and reads as under :

              “10. General

              a) Consequential Damages

              We shall not be liable for any consequential damages,
              loss of profit, costs and/or expenses if any incurred by
              you or by any other person employed by you or
              representing you directly or indirectly, any third party
              obligations entered into by you or any statutory / legal
              obligation, awards, damages, statutory or legal action,
              costs or expenses in relation to the performance or any
              other feature of the plant supplied and / or erected
              and / or commissioned by us. Our obligation in this
              contract including all causes and any representations
              made by us to you shall not exceed the value of the
              performance bank guarantee/corporate guarantee or
              any other compensation agreed by us in the contract and
              shall be applicable only to faults noticed and not
              corrected in the performance of the equipment during
              the warranty period. All the obligations under the
              warranty period given by us shall be subject to your
              operating the plant and equipment as per the agreed
              method         of       operation      as       normally
              understood/specifically    mentioned     by    us.   The


Sairaj                               15 of 36
                                                     CARBP-1267-2018 (final).doc


            performance warranty obligations are strictly subject to
            the battery limits, exclusions and output parameters
            mentioned in the contract.

            b) Secondary Liability

            Secondary liability such as indemnification for any loss
            caused by stoppage of the plant or due to any other
            reasons concerning this contract will under no
            circumstances be acceptable to us and we shall not be
            responsible for such losses.

            h) Order of Precedence

            Wherever any clauses as mentioned in this Contract are
            partly or fully at variance with the General Terms and
            Conditions of Sale, the printed form of which is
            enclosed, then clauses specifically entered into as part
            of this Contract shall have precedence and shall override
            the corresponding clauses in the General Terms and
            Conditions of Sale.”

23.      The Respondent in paragraph 8 of its written statement cum

counterstatement of claim specifically denied the liability for any

consequential      damages      or    any   secondary    liability,    including

indemnification for any reason concerning the contract and capping of

the liability to the value of performance bank guarantee referrable to

Clause 10(a) and (b) of the contract. The impugned Award records at

paragraph 123, the case of the Respondent that the claims made in

paragraph 15 of SOC are in teeth of Clause 10(a) and (b) and in nature

of damages without any averments in support thereof by relying on

Section 73 of Contract Act. In paragraph 124, the submission of

Respondent is recorded that claims would be limited to warranty




Sairaj                               16 of 36
                                                       CARBP-1267-2018 (final).doc


clause and there is no clause for refund. The defence of the

Respondent was that none of the claims could be granted by the

Learned Arbitrator as Clause 10(a) and 10(b) of the contract excluded

the claims. The Respondent denied even Claim 15(1) seeking refund of

purchase price.

24.      In the background of such submission, the Learned Arbitrator

considered whether Clause 10(a) and (b) can be pressed into service by

the Respondent to oppose the claims made by the Claimant and held in

paragraph no. 126 as under:

         “126. The next question, then is, whether Clause 10 (a) and
         (b) forming part of the General Terms and Conditions in
         Section V of the Techno Commercial Agreement dated
         10.9.2013 and the clause relating to Warantee in Section IV
         of the said document relating to Price Schedule &
         Commercial Terms and Conditions can be pressed into
         service by the Respondent to oppose the claims made by the
         Claimant. In my opinion, a reading of the two clauses, it will
         be seen that the clause relating the Consequential Damages
         and Secondary Liability would apply in the event of the fish
         meal plant being supplied as contracted and it being
         commissioned by the Respondent and got ready for
         commercial operations without any defects or operational
         glitches. It is not material that the plant was not operated at
         the fullest capacity for any reason, but in the present case
         the plant was not able to function satisfactorily and certainly
         not demonstrated to be fit for commercial operations, free
         from any defect or deficiencies, which were found in one
         area or the other. Clause 10(a) of the Agreement dated
         10.9.2013 dealing with Consequential Damages relates to
         indirect damages and not damages or compensation arising
         out of the direct consequences of the Respondent's failure
         to perform its obligations under the contract of supplying a
         functional fishmeal plant which can be taken to smooth


Sairaj                              17 of 36
                                                        CARBP-1267-2018 (final).doc


         commercial operations. At the highest, Clause 10(a) of the
         Techno Commercial Agreement will restrict only to the
         consequential or indirect damages or the damages
         mentioned in the said clause. However, this clause is also
         inclusive of certain foreseeable losses mentioned therein
         (which can be termed as direct consequences) and have been
         factored in by the parties for the purpose of exclusion. In my
         opinion, the claims of the Claimant on account of loss of
         profit, costs and expenditure incurred on the provision of
         raw materials for the trials, etc would fall within the ambit of
         this clause, since notwithstanding the fact they are included
         under the clause relating to consequential damages, they
         find place in the limitations on liability covered by the said
         clause and are intended to be part of the limited liability of
         the Respondent. Damages on account of direct consequence
         of the breach of the contract or non-performance of the
         contract which fall outside the specified consequences or
         other than those specified only will not fall within the ambit
         of either of the clauses 10(a) and 10(b). The claimant will
         therefore be entitled to claim only such damages for direct
         losses or compensation as is warranted and not specifically
         excluded on account of breach of contract and the failure to
         perform the contract by the Respondent. I do not agree with
         the submission of the Counsel for the Claimant, that the
         doctrine of contra-proferentum should be applied in the
         facts of the present case to interpret the contract against
         the Respondent, or to hold that the Claimant was not aware
         of this clause in the agreement, it not having been brought
         to its notice, as there is no material on record to support this
         argument.



25.      It would also be apposite to reproduce paragraph 129 and 130

of the Award which reads as under:

            “129. As mentioned before the Claimant has claimed
            a total amount Rs. 17,64,81,771.00 from the
            Respondent as a sum total of the various heads of
            claim. The first claim of Rs. 4,45,00,000/- being the
            price of the plant. There is no dispute that the


Sairaj                               18 of 36
                                                 CARBP-1267-2018 (final).doc


         Respondent has received the said amount from the
         Claimant. Having held that the Respondent has
         failed to supply, erect, commission and provide a
         fishmeal plant as contemplated under the Contract
         between the parties, Claimant is presently saddled
         with the equipment which it is not in a position to
         use or operate. The Respondent having failed to
         provide a plant as per the contract, the Claimant will
         be entitled to compensatory damages as a direct
         result of its failures. I do not read the Clauses in the
         agreement relating to consequential damages and
         warrantee to hold that such compensation is barred
         or excluded and there is no specific bar (as was in the
         case law relied upon by the Counsel for the
         Respondent) to the grant of compensation for the
         direct loss arising on the failure of the Respondent.
         In my view, the loss of price paid for the defective
         and deficient supply, erection and defaults in setting
         up and commissioning the fish meal plan is a direct
         consequence of the Respondent's failure and the
         Claimant is entitled to be compensated for it. I
         therefore hold that the Respondent is liable to pay
         to the Claimant the amount of Rs.4,45,00,000/ as
         compensation. The claimant will be entitled to
         interest at the rate of 9% p.a. from the date of the
         Award till payment and realisation.

         130. The claims under the other heads viz. Claim of
         Rs. 49,49,669/ towards of payment of excise duty,
         sales tax etc i.e. claim 15(2); Claim of Rs. 4,33,608/
         towards freight charges and insurance i.e. Claim 15
         (3); Claim of Rs. 4,12,250 towards expenses for the
         accommodation of Alfa Laval's engineers and
         officials i.e. Claim 15 (4); Claim of Rs. 2,61,27,517/
         towards upgradation of infrastructure to suit
         contracted plant and supporting machinery; Claim of
         Rs. 18,22,335/ towards raw materials for the cost of
         seven trial runs i.e. Claim 15(6); claim of
         Rs.2,26,83,392/ towards bank interest upto
         31.10.216 i.e. Claim 15(7); and Rs.8,00,00,000/
         towards damage suffered on account of business
         loss, opportunity loss, mental agony, and loss of
         reputation i.e. Claim 15(8), would, in my opinion, all


Sairaj                          19 of 36
                                                    CARBP-1267-2018 (final).doc


            fall within the ambit of Clause 10(a) and (b) of the
            General Terms and Conditions in Section VI of the
            Techno Commercial Agreement. These claims are
            limited to the amount of the bank guarantee which
            is invoked and encashed by the Claimant.”


26.      The learned Arbitrator has interpreted Clause 10(a) to be

restricted to consequential or indirect damages, damages specified

therein and even direct consequences for purpose of exclusion. Clause

10(a) specified loss of profits, cots/expenses, statutory obligation

apart from consequential/indirect damages. The latter portion of

Clause 10(a) restricted the liability to extent of performance

guarantee. By reason of specific mention of loss of profits, costs and

expenses, etc. in clause 10(a), though under the heading of

consequential damages, the learned Arbitrator has held that the Claims

15(2) to 15(8) fall within ambit of Clause 10(a) and capped to the limit

of performance       bank   guarantee.      The   learned   Arbitrator    has

interpreted Clause 10(a) as an agreement between the parties

specifying certain liabilities of the Respondent to be limited to the

extent of performance bank guarantee.

27.      A case of inconsistency in paragraph 126 of the Award is sought

to be raised by Mr. D’souza contending that in first part of paragraph

126, the Learned Arbitrator has held that Clause 10(a) and (b) do not

apply to the present case on account of non commissioning of the



Sairaj                           20 of 36
                                                CARBP-1267-2018 (final).doc


plant as contracted, whereas in the second part of paragraph 126, the

Arbitrator has denied the claims of Claimant by taking recourse to

Clause 10(a). A conjoint reading of paragraph 126, 129 and 130 would

disclose that the Learned Arbitrator has first put all claims in the

basket of Clause 10(a) and (b) of contract in view of the defence that

none of the claims can be granted by reason of the said Clause.

Thereafter by an interpretative process, the Learned Arbitrator has

analysed the claims in the context of Clause 10(a) and (b) to hold that

Claim 15(1) pertaining to refund of purchase price is a direct result of

the failure of Respondent to provide the plant and would not be

covered by the contract clauses relating to consequential damages and

warrantee to hold that such compensation is barred or excluded.

Though a contention was raised about Section 73 of Contract Act, the

Learned Arbitrator has granted Claim 15(1) by interpreting Clause 10(a)

for its exclusion from the said clause. The learned Arbitrator has not

applied the principles of Section 73 of Contract Act to grant Claim

15(1), but has interpreted Clause 10(a) to hold that the claim 15(1) is

direct result of failure which will not be covered by clause of

consequential damages and warantee. It is pertinent to note that there

is no sequiter to the finding in the first part of paragraph 126. The

Claimant is a beneficiary of the interpretation of Clause 10(a) as the

learned Arbitrator has ruled that the claim for refund of purchase price


Sairaj                         21 of 36
                                                    CARBP-1267-2018 (final).doc


does not form part of consequential damages and is direct result of the

failure.

28.      The second portion of paragraph 126 of the Award read with

paragraph 129 and 130 makes it abundantly clear that Clause 10(a) is

held to be applicable to the claims raised by the Claimant. If the Award

is read as a whole, the same clearly proceeds on the applicability of

clause 10(a) and renders findings on various claims raised by the

Claimant.      The interpretation placed by the learned Arbitrator on

Clause 10(a) as recorded in second part of paragraph 126 is not only a

possible interpretation but it appeals to this Court. In the case of

Securitrans India Pvt. Ltd. vs. FIS Payment Solutions and Services

Pvt. Ltd. (supra), the Co-ordinate Bench has held that the Award has to

be read in its entirety and finding of perversity can be recorded when

there are absolutely no reasons for reaching the conclusion. Such is not

the case here.

29.      The first part of Clause 10(a) of contract excludes the liability of

Respondent in respect of (a) consequential damage (b) loss of profit (c)

costs and/or expenses incurred by the Claimant (d) statutory obligation

(e) awards, (f) damages (g) statutory or legal action and (g) costs or

expenses in relations to performance or any other feature of the plant

supplied and/or erected. The learned Arbitrator has interpreted this

clause to grant Claim 15(1) and to cap Claim 15(2) to 15(8) to the


Sairaj                             22 of 36
                                                 CARBP-1267-2018 (final).doc


extent of performance bank guarantee.

30.      The rejection of Claim 15(2) to 15(8) to the fullest extent is

assailed as being violative of fundamental and substantive law. In Vijay

Karia and Others vs Prysmian Cavi E Sistemi SRL and Others 32, the

Hon’ble Apex Court has held that the fundamental policy of Indian law

must amount to breach of some legal principle or legislation which is

so basic to Indian law that it is not susceptible of being compromised.

“Fundamental Policy” refers to the core values of India’s public policy

as a nation, which may find expression not only in statutes but also

time-honoured, hallowed principles which are followed by Courts.

31.      It is therefore not permissible for the Court to interfere even

when there is breach of substantive law and it must be shown that the

law so breached forms bedrock of Indian law. The present case is a case

of interpretation of terms of the contract and whether the claims

stands excluded by an agreement between the parties. Even accepting

for the moment that the Claimant, under the law, would be entitled to

such claims in the event of breach by the Respondent, it is open for the

parties to arrive at an arrangement by which, the liability is excluded

and limited. This is precisely the interpretation of Clause 10(a) of

contract by learned Arbitrator. Mr. D’souza would contend that claims

of the Claimant were not indirect but actual expenses incurred. The

32 AIR 2020 SC 1807.


Sairaj                           23 of 36
                                                  CARBP-1267-2018 (final).doc


submission would require this Court to interpret the nature of claims,

whether consequential or direct, and substitute its own interpretation

with the      interpretation   of the   Learned   Arbitrator, which is

impermissible. It is within the jurisdiction of the Learned Arbitrator to

interpret the terms of the contract and the view taken is a possible

view that Claims 15(2) to 15(8) are covered by Clause 10(a) to the

extent of performance guarantee. Clause 10(a) specifically mentions

loss of profit, costs and/or expenses, statutory obligations for purpose

of exclusion and limits it only to the performance guarantee. Section 5

of Arbitration Act must be given its full effect to minimise judicial

intervention when the view cannot be said to be impossible. It is not

only a plausible view, but a possible view which is required to be

upheld.

32.      In the case of Vilayati Ram Mittal (P) vs. Reserve Bank of India

(supra), the Hon’ble Division Bench of this Court has held that it is for

the Arbitrator to decide the effect of the clause and deal with the

same. In that case by virtue of the clause, the contractor was not held

to be entitled for any loss suffered on account of delay and the Hon’ble

Division Bench has held that this clause binds both the parties and it is

not open for the Appellant therein to construe clause 18 so as to seek

the benefit and contend that the clause is binding between the parties

but do not bind the Arbitrator or the Court. It further held that if the


Sairaj                           24 of 36
                                                       CARBP-1267-2018 (final).doc


clause specifically prohibits any claim on the account of delay, by

ignoring the said clause, the Arbitrator cannot travel beyond his

jurisdiction as that would constitute the jurisdictional error.

33.      In the case of UHL Power Company Limited vs. State of H. P.

(supra), the Hon’ble Apex Court has held in paragraph 18, 19 and 22 as

under :

           “18. It has also been held time and again by this Court that
           if there are two plausible interpretations of the terms and
           conditions of the contract, then no fault can be found, if
           the learned arbitrator proceeds to accept one
           interpretation as against the other. In Dyna Technologies
           (P) Ltd. v. Crompton Greaves Ltd. [Dyna Technologies (P) Ltd.
           v. Crompton Greaves Ltd., (2019) 20 SCC 1], the limitations
           on the Court while exercising powers under Section 34 of
           the Arbitration Act has been highlighted thus : (SCC p. 12,
           para 24)

                “24. There is no dispute that Section 34 of the
                Arbitration Act limits a challenge to an award
                only on the grounds provided therein or as
                interpreted by various Courts. We need to be
                cognizant of the fact that arbitral awards
                should not be interfered with in a casual and
                cavalier manner, unless the Court comes to a
                conclusion that the perversity of the award
                goes to the root of the matter without there
                being a possibility of alternative interpretation
                which may sustain the arbitral award. Section
                34 is different in its approach and cannot be
                equated with a normal appellate jurisdiction.
                The mandate under Section 34 is to respect the
                finality of the arbitral award and the party
                autonomy to get their dispute adjudicated by
                an alternative forum as provided under the law.
                If the Courts were to interfere with the arbitral
                award in the usual course on factual aspects,
                then the commercial wisdom behind opting for
                alternate dispute resolution would stand
                frustrated.”



Sairaj                              25 of 36
                                                    CARBP-1267-2018 (final).doc




         19. In Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut
         Utpadan Nigam Ltd. [Parsa Kente Collieries Ltd. v.
         Rajasthan Rajya Vidyut Utpadan Nigam Ltd., (2019) 7 SCC
         236 : (2019) 3 SCC (Civ) 552] , adverting to the previous
         decisions of this Court in McDermott International Inc. v.
         Burn Standard Co. Ltd. [McDermott International Inc. v.
         Burn Standard Co. Ltd., (2006) 11 SCC 181] and Rashtriya
         Ispat Nigam Ltd. v. Dewan Chand Ram Saran [Rashtriya
         Ispat Nigam Ltd. v. Dewan Chand Ram Saran, (2012) 5 SCC
         306], wherein it has been observed that an Arbitral
         Tribunal must decide in accordance with the terms of the
         contract, but if a term of the contract has been construed
         in a reasonable manner, then the award ought not to be
         set aside on this ground, it has been held thus : (Parsa
         Kente Collieries case [Parsa Kente Collieries Ltd. v.
         Rajasthan Rajya Vidyut Utpadan Nigam Ltd., (2019) 7 SCC
         236 : (2019) 3 SCC (Civ) 552] , SCC pp. 244-45, para 9)

              “9.1. … It is further observed and held that
              construction of the terms of a contract is
              primarily for an arbitrator to decide unless the
              arbitrator construes the contract in such a way
              that it could be said to be something that no
              fair-minded or reasonable person could do. It
              is further observed by this Court in the
              aforesaid decision in para 33 that when a court
              is applying the “public policy” test to an
              arbitration award, it does not act as a court of
              appeal and consequently errors of fact cannot
              be corrected. A possible view by the arbitrator
              on facts has necessarily to pass muster as the
              arbitrator is the ultimate master of the
              quantity and quality of evidence to be relied
              upon when he delivers his arbitral award. It is
              further observed that thus an award based on
              little evidence or on evidence which does not
              measure up in quality to a trained legal mind
              would not be held to be invalid on this score.

              9.2. Similar is the view taken by this Court in
              NHAI v. ITD Cementation India Ltd. [NHAI v. ITD
              Cementation India Ltd., (2015) 14 SCC 21 :
              (2016) 2 SCC (Civ) 716], SCC para 25 and SAIL v.
              Gupta Brother Steel Tubes Ltd. [SAIL v. Gupta
              Brother Steel Tubes Ltd., (2009) 10 SCC 63 :



Sairaj                            26 of 36
                                                         CARBP-1267-2018 (final).doc


                  (2009) 4 SCC (Civ) 16] , SCC para 29.”
                                               (emphasis supplied)

             22. In the instant case, we are of the view that the
             interpretation of the relevant clauses of the
             implementation agreement, as arrived at by the learned
             sole arbitrator, are both, possible and plausible. Merely
             because another view could have been taken, can hardly
             be a ground for the learned Single Judge to have
             interfered with the arbitral award. In the given facts and
             circumstances of the case, the appellate court has rightly
             held that the learned Single Judge exceeded his
             jurisdiction in interfering with the award by questioning
             the interpretation given to the relevant clauses of the
             implementation agreement, as the reasons given are
             backed by logic.”

34.      The scope of interference under Section 34 of the Arbitration Act

is well-settled. In Associate Builders vs. Delhi Development Authority

(supra), the Hon’ble Apex Court has held in paragraph 42.3, 44 and 45

as under :

             “42.3. (c) Equally, the third subhead of patent illegality is
             really a contravention of Section 28(3) of the Arbitration
             Act, which reads as under:

                 “28.Rules applicable to substance of dispute.
                 —(1)-(2)***
                 (3) In all cases, the Arbitral Tribunal shall decide
                 in accordance with the terms of the contract
                 and shall take into account the usages of the
                 trade applicable to the transaction.”
                 This last contravention must be understood
                 with a caveat. An Arbitral Tribunal must decide
                 in accordance with the terms of the contract,
                 but if an arbitrator construes a term of the
                 contract in a reasonable manner, it will not
                 mean that the award can be set aside on this
                 ground. Construction of the terms of a contract
                 is primarily for an arbitrator to decide unless
                 the arbitrator construes the contract in such a
                 way that it could be said to be something that
                 no fair-minded or reasonable person could do.


Sairaj                                27 of 36
                                                    CARBP-1267-2018 (final).doc




          In MSK Projects (I) (JV) Ltd. v. State of Rajasthan [(2011)
         10 SCC 573 : (2012) 3 SCC (Civ) 818] , the Court held : (SCC
         pp. 581-82, para 17)

              “17. If the arbitrator commits an error in the
              construction of the contract, that is an error
              within his jurisdiction. But if he wanders
              outside the contract and deals with matters
              not allotted to him, he commits a jurisdictional
              error. Extrinsic evidence is admissible in such
              cases because the dispute is not something
              which arises under or in relation to the contract
              or dependent on the construction of the
              contract or to be determined within the award.
              The ambiguity of the award can, in such cases,
              be resolved by admitting extrinsic evidence.
              The rationale of this rule is that the nature of
              the dispute is something which has to be
              determined outside and independent of what
              appears in the award. Such a jurisdictional error
              needs to be proved by evidence extrinsic to the
              award. (See Gobardhan Das v. Lachhmi Ram
              [(1954) 1 SCC 566 : AIR 1954 SC 689], Thawardas
              Pherumal v. Union of India [AIR 1955 SC 468],
              Union of India v. Kishorilal Gupta & Bros. [AIR
              1959 SC 1362], Alopi Parshad & Sons Ltd. v.
              Union of India [AIR 1960 SC 588] , Jivarajbhai
              Ujamshi Sheth v. Chintamanrao Balaji [AIR 1965
              SC 214] and Renusagar Power Co. Ltd. v. General
              Electric Co. [(1984) 4 SCC 679 : AIR 1985 SC
              1156] )”
                                         (emphasis supplied)

          In Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran
         [(2012) 5 SCC 306] , the Court held : (SCC pp. 320-21,
         paras 43-45)

              “43. In any case, assuming that Clause 9.3 was
              capable of two interpretations, the view taken
              by the arbitrator was clearly a possible if not a
              plausible one. It is not possible to say that the
              arbitrator had travelled outside his jurisdiction,
              or that the view taken by him was against the
              terms of contract. That being the position, the
              High Court had no reason to interfere with the



Sairaj                           28 of 36
                                               CARBP-1267-2018 (final).doc


         award and substitute its view in place of the
         interpretation accepted by the arbitrator.

                                 (emphasis supplied)

         44. The legal position in this behalf has been
         summarised in para 18 of the judgment of this
         Court in SAIL v. Gupta Brother Steel Tubes Ltd.
         [(2009) 10 SCC 63 : (2009) 4 SCC (Civ) 16] and
         which has been referred to above. Similar view
         has been taken later in Sumitomo Heavy
         Industries Ltd. v. ONGC Ltd. [(2010) 11 SCC 296 :
         (2010) 4 SCC (Civ) 459] to which one of us
         (Gokhale, J.) was a party. The observations in
         para 43 thereof are instructive in this behalf.

         45. This para 43 reads as follows : (Sumitomo
         case [(2010) 11 SCC 296 : (2010) 4 SCC (Civ) 459]
         , SCC p. 313)

         ‘43. … The umpire has considered the fact
         situation and placed a construction on the
         clauses of the agreement which according to
         him was the correct one. One may at the
         highest say that one would have preferred
         another construction of Clause 17.3 but that
         cannot make the award in any way perverse.
         Nor can one substitute one's own view in such a
         situation, in place of the one taken by the
         umpire, which would amount to sitting in
         appeal. As held by this Court in Kwality Mfg.
         Corpn. v. Central Warehousing Corpn. [(2009) 5
         SCC 142 : (2009) 2 SCC (Civ) 406] the Court
         while considering challenge to arbitral award
         does not sit in appeal over the findings and
         decision of the arbitrator, which is what the
         High Court has practically done in this matter.
         The umpire is legitimately entitled to take the
         view which he holds to be the correct one after
         considering the material before him and after
         interpreting the provisions of the agreement. If
         he does so, the decision of the umpire has to be
         accepted as final and binding.”

                                      (emphasis supplied)




Sairaj                     29 of 36
                                                       CARBP-1267-2018 (final).doc


35.       The settled position in law prohibits Section 34 Court from

substituting its own view in place of Arbitrator’s interpretation. The

error in construction is considered as an error within jurisdiction, which

does not warrant interference. In my view, the interpretation of Clause

10(a) of the contract by the impugned Award cannot be said to be an

impossible view.

36.      In so far as the supersession of Clause 10 by warrantee clause is

concerned, the learned Arbitrator held in paragraph nos. 127 as under :


            127. In so far as the clause of Warantee is concerned, it
            will not apply in the present case as the plant is
            admittedly not commissioned or handed over to the
            Claimant. Respondent has never called upon the Claimant
            to take over the plant and as asserted by the Claimant in
            its mails, the responsibility in supplying the plant
            remained with the Respondent. The contract between
            the parties is not for the supply of individual parts or only
            equipment. In my opinion the clause of Warantee will
            apply only after the commissioning of the plant as agreed
            by the parties, which has not happened. This will also
            include handing over an operational plant to the
            Claimant. I find this because the warrantee is subject to
            certain conditions which show that the plant should be in
            the entire charge and operations of the purchaser i.e. the
            Claimant. This clause also reiterates that the Respondent
            shall not be responsible for any consequential or indirect
            damages only and does not cover direct damages. These
            clause do not, in my reading, absolve the Respondent on
            liability arising on account of direct damages or
            compensation on account of direct consequences.”

37.      The warrantee clause warrantee all equipment offered by

Respondent against the material, workmanship, manufacturing defects

for period of 12 month and that Respondent shall not be responsible



Sairaj                              30 of 36
                                                CARBP-1267-2018 (final).doc


for any consequential or indirect damages. The contention is that there

is an express clause for damages in the main agreement and therefore

Clause 10(a) and (b) stands excluded by virtue of Clause 10(h) of the

contract as the warantee clause excludes only consequential damages.

The warantee clause binds the Respondent against defects specified

i.e. against material, workmanship and manufacturing defects for

particular period. The clause being a warantee clause, the Learned

Arbitrator has held that the same would not apply as the plant is not

commissioned and handed over, which cannot be interfered with.

38.      Insofar as the claim on account of interest is concerned, the

submissions are conflated in as much the interest sought as Claim 15(7)

is characterised as interest pendente lite as well as a direct

consequence of the breach suffered by the Respondent. Mr. D’souza

would contend that the Claim 15(7) which is Bank interest upto 31 st

October, 2016 paid on financial loan which has been obtained by the

Claimant, should have been granted as interest pendente lite. The

concept of interest pendente lite is different from interest claimed as

head of loss and as a direct consequence of breach. In the present case,

Claim 15(7) is claimed as head of loss and not as interest pendente lite

and the award of interest pendente lite would constitute interest for

the period from filing of the statement of claim till the Award of

Arbitrator. In the application under Section 33, the claim was for


Sairaj                          31 of 36
                                                   CARBP-1267-2018 (final).doc


payment of interest pendente lite, which has been declined by Learned

Arbitrator in exercise of its jurisdiction which meets the parameters of

Section 31(7) of the Arbitration Act. The Learned Arbitrator has

considered the claim of interest as indirect loss and has capped it

within the limited liability clause.

39.      As far as the award of interest pendente lite is concerned, in the

case of Morgan Securities and Credits Private Limited vs. Videocon

Industries Limited (supra), the Hon’ble Apex Court considered the

expression “unless the Award otherwise directs“ in Section 31(7)(b) of

the Act to hold that wide discretion is conferred upon the Arbitrator to

determine the rate of reasonable pre-award interest.

40.      Dealing with the citations relied upon by Mr. D’souza, in the case

of Deepak Fertiliser and Petrochemical Corporation vs. Davy Mckee

(London) Ltd. (supra), the England and Wales Court of Appeal was

considering an appeal arising under the Commercial Court in respect of

the contractual claims raised in that case. While dealing with the issue

as to whether the losses claimed are excluded from recovery by virtue

of clause 6.8 of the contract therein which provided that the party shall

not be liable for loss of anticipated profits, catalyst, raw-material and

products or for indirect or consequential damages by reason of which

all heads of claims against the party were held to be excluded. It was

held that direct and natural result of the destruction of plant was that


Sairaj                            32 of 36
                                                  CARBP-1267-2018 (final).doc


the party was left without a methanol plant, wasted overheads

incurred during the reconstruction of the plant, as well as profits lost

during that period, which are no more remote as losses than the cost of

reconstruction. It held that the costs incurred cannot be categorized as

an indirect or consequential loss or damage nor could its cost be

categorized as constituting a loss of profit.

41.      The distinguishing feature, in the present case, is the limited

powers vested in Section 34 Court, once the Arbitrator has interpreted

the terms of the contract which view cannot be said to be an

impossible view. In that case the proceedings arose out of Commercial

Court litigation which leaves the field wide open for the Appellate

Court to re-appreciate the findings.

42.      In the case of Union of India vs. Saraswat Trading Agency and

Others (supra), the Hon’ble Apex Court considered the question of

interest for pre-reference period and dealt with the power of

arbitrator to award interest pendente lite and if so on what principles. It

held that the Arbitrator has the power to award interest pendente lite.

There is no quarrel with the said decision however, in the present case,

as discussed above, the claim for interest is claimed as a head of loss

and not as interest pendente lite. Further, Arbitrator in his discretion

declined to grant interest pendente lite.

43.      In the case of South East Asia Marine Engineering and


Sairaj                           33 of 36
                                                 CARBP-1267-2018 (final).doc


Constructions Limited vs. Oil India Limited (supra), the Hon’ble Apex

Court considered the scope of Section 34 of the Arbitration Act.

Pertinently, the Court noted the case of Dyna Technologies (P) Ltd. vs.

Crompton Greaves Limited33 and held that where two views are

possible, the Court cannot interfere in the plausible view taken by the

Arbitrator supported by reasoning. In the facts of that case, the

Hon’ble Apex Court did not subscribe the reasons provided by

Arbitrator or High Court as it failed to apply the standard of

consideration of all clauses of contract while interpreting clause 23 of

the contract therein. In that case, clause in question was in respect of

change in law which results in additional costs/reduction in cost to

contractor and which was required to be reimbursed. The Arbitral

Tribunal had held that clause must be liberally construed and any

circular of government circular would result in change in law. The High

Court reasoned that clause 23 is akin to force majeure clause. In such

facts, the Hon’ble Apex Court considered that the wide interpretation

by Arbitral Tribunal cannot be accepted and that document forming

the written contract shall be read as whole which was the basic rule

ignored by the Arbitral Tribunal while interpreting the contract. The

decision turned on the terms of the contract contained therein, which

is rendered in a different factual scenario. The decision cannot be cited

33 (2019) 20 SCC 1.


Sairaj                          34 of 36
                                                    CARBP-1267-2018 (final).doc


as a proposition that even if the view taken is possible view, it is open

for Section 34 Court to substitute its own view.

44.      In the case of Delhi Metro Rail Corporation Limited vs. Delhi

Airport Metro Express Pvt. Ltd. (supra), the Hon’ble Apex Court

considered the scope of interference with the Arbitral Award, with

which there is no quarrel.

45.      The grounds on which the Award can be set aside are set out in

Section 34 of the Arbitration Act. The learned Arbitrator has

interpreted the terms of the contract to hold that claims 15(2) to 15(8)

of the claims raised by the Claimant are covered by clause 10(a) and are

capped at the limited liability of performance guarantee. The view

being possible view cannot be said to be patently illegal or so perverse

that no reasonable person could have arrived at the same. Perversity as

is settled is a finding based on no evidence and arrived at by ignoring

the vital evidence, which would be liable to be set aside under the head

of patent illegality. The error, if any, in construction of contract, is an

error within jurisdiction incapable of being corrected in Section 34

jurisdiction.

46.      In light of the discussion above, I do not find the impugned order

to suffer from perversity or patent illegality or such as violates the

fundamental policy of Indian law.

47.      Resultantly, the Arbitration Petition fails and stands dismissed.


Sairaj                             35 of 36
                                                 CARBP-1267-2018 (final).doc


48.      Nothing survives for consideration in pending Applications, if

any, and the same stand disposed of.



                                            [Sharmila U. Deshmukh, J.]




Sairaj                           36 of 36


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.