Holding
The Court held that the petitioner had made out a prima facie case for interim relief and granted the relief, ordering the respondent to comply with the prayer clause and the petitioner to constitute the arbitral tribunal within 90 days.
Summary
IIFL Finance Ltd. granted a term loan of Rs.11,78,826 to the respondents, who later defaulted on repayments. IIFL issued a demand notice for the outstanding amount of Rs.9,38,401, which the respondents ignored, and alleged that they were attempting to transfer assets. IIFL filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim protection pending arbitration. The Court examined the loan agreement, the demand notice, and the statement of account, finding a prima facie case for interim relief and noting the existence of an arbitration clause. It held that the balance of convenience favored the petitioner and ordered the respondents to comply with the prayer clause and the petitioner to constitute an arbitral tribunal within 90 days. The petition was disposed with the interim relief granted.
Issues considered
- Whether the petitioner has made out a prima facie case for interim relief under Section 9 of the Arbitration and Conciliation Act, 1996.
- Whether an arbitration agreement exists between the parties, permitting the Court to entertain the Section 9 petition.
- Whether the balance of convenience favors granting interim protection to the petitioner.
Legislation cited
Subjects
- loan default
- arbitration
- interim relief
- Section 9
- balance of convenience
- asset transfer
- recall notice
- commercial loan
Judgment
36-carbp234-2026.doc
AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMM ARBITRATION PETITION NO.234 OF 2026
IIFL Finance Limited … Petitioner
V/s.
Ashit Baran Bose & Another … Respondents
Mr. Jitesh Mundhwa with Ms. Shital Londhe and Ms.
Varsha Singh for the petitioner-IIFL.
CORAM : AMIT BORKAR, J.
DATED : JULY 2, 2026
P.C.:
1. The present petition has been filed under Section 9 of the
Arbitration and Conciliation Act, 1996. By this petition, the
petitioner is seeking interim reliefs against the respondent pending
the commencement of arbitration proceedings.
2. The case of the petitioner, in brief, is that the respondent was
in need of financial assistance for expanding its business and for
obtaining a term loan. For that purpose, the respondent
approached the petitioner by submitting an online application
seeking financial help. After considering the request made by the
respondent and after discussions between the parties, the
petitioner agreed to grant a business term loan. Accordingly, a loan
facility of a maximum amount of Rs.11,78,826/- was sanctioned in
favour of the respondent on the terms and conditions contained in
1
36-carbp234-2026.doc
the loan agreement executed between the parties.
3. After execution of the loan agreement, the petitioner
disbursed the loan amount to the respondent in accordance with
the agreed terms. Under the loan agreement, the respondent was
required to repay the loan in monthly instalments. Each instalment
was to include interest calculated on the reducing balance of the
loan together with a part payment towards the principal amount.
4. According to the petitioner, the respondent initially made
repayments for a few months. However, thereafter the respondent
stopped making the payments as required under the loan
agreement. Because of this failure, the respondent committed
default in repayment of the loan. The petitioner states that several
requests and reminders were given to the respondent to clear the
outstanding dues. In spite of those requests, the respondent failed
to make the necessary payments.
5. As a final attempt before taking legal action, the petitioner,
through its Advocates, issued a demand notice calling upon the
respondent to pay an amount of Rs.9,38,401/- which was stated to
be outstanding as on 1 January 2026, within seven days from the
date of receipt of the notice. Even after receiving the notice, the
respondent did not make the payment or comply with the demand
made therein. The petitioner has also placed on record the
foreclosure statement and the statement of account showing the
amount alleged to be due and payable by the respondent.
6. The petitioner submits that, in view of Clauses 12 and 13 of
the loan agreement, an Event of Default has occurred. According
2
36-carbp234-2026.doc
to the petitioner, it has therefore become entitled to enforce the
terms of the agreement and to take appropriate steps for recovery
of the outstanding amount. It is the petitioner's case that, as on 22
December 2025, the respondent is liable to pay a sum of Rs.
9,38,401/-under the loan facility.
7. The petitioner further contends that the respondent has
failed to perform its obligations under the loan agreement as well
as the other transaction documents. It is also stated that the
petitioner has reason to believe that the respondent does not
intend to honour those obligations and is attempting to dispose of
or transfer its assets. According to the petitioner, if such transfers
are permitted, recovery of the outstanding dues may become
difficult and the petitioner may suffer serious loss. On this
apprehension, the present petition has been filed seeking urgent
interim protection under Section 9 of the Arbitration and
Conciliation Act, 1996.
8. Though the respondents were duly served with notice of the
present proceedings, none appeared on their behalf.
9. I have considered the pleadings, the documents placed on
record and the submissions made on behalf of the petitioner. Since
none has appeared for the respondent despite service, this Court
has examined the material available on record with due care. At
this stage, the Court is not expected to decide the disputes
between the parties. However, it is required to see whether the
petitioner has shown a prima facie case for grant of interim
protection on the basis of the available material.
3
36-carbp234-2026.doc
10. Clause 26 of the loan agreement contains an arbitration
clause agreed between the parties. From the documents placed on
record, it appears that both sides had accepted that any dispute
arising out of the loan transaction would be referred to arbitration.
Therefore, at this stage, it cannot be said that there is no
arbitration agreement between the parties. Since the agreement
itself provides for resolution of disputes through arbitration, the
petitioner is entitled to invoke the jurisdiction of this Court under
Section 9 of the Arbitration and Conciliation Act for seeking
interim protection before the Arbitral Tribunal is constituted.
11. It is also not in dispute that the petitioner has already issued
a recall notice calling upon the respondent to repay the entire
outstanding loan amount. The petitioner has placed a copy of the
said notice on record. Despite such notice, there is nothing on
record to show that the respondent has cleared the dues or replied
disputing the demand. Though the mere issuance of a recall notice
may not by itself establish the entire claim of the petitioner, it does
indicate that the petitioner has called upon the respondent to
make payment before approaching this Court.
12. The statement of account produced along with the petition
also shows the amount which, according to the petitioner, remains
due and payable from the respondent. At this stage, the Court is
not required to examine the correctness of every entry in the
statement of account or determine the liability. Those issues can be
examined in the arbitral proceedings after both sides place their
evidence. However, for the limited purpose of considering interim
relief, the statement of account provides prima facie support to the
4
36-carbp234-2026.doc
petitioner's claim that some amount is stated to be outstanding
against the respondent.
13. The petitioner has further made a statement on oath that the
respondent is attempting to transfer or alienate its assets. Such
statement has been made in the petition after verification by the
petitioner. Though this allegation will have to be examined in
before the learned Arbitral Tribunal if disputed, at this stage there
is no material placed by the respondent to contradict the said
assertion, as the respondent has chosen not to appear. If the assets
are transferred during the pendency of the dispute and the
petitioner succeeds in arbitration, recovery of the awarded amount
may become difficult. Therefore, such apprehension expressed by
the petitioner cannot be ignored while considering the prayer for
interim protection.
14. Having considered the pleadings and the documents placed
on record, I am of the opinion that the petitioner has made out a
prima facie case for grant of interim protection in terms of prayer
clause (e). The balance of convenience also appears to be in favour
of granting such relief. Accordingly, the petition can be disposed of
by passing the following order:
(a) The respondent shall comply with prayer clause (e) of
the petition;
(b) The petitioner shall take necessary steps for
constitution of the Arbitral Tribunal within a period of ninety
days from today.
5
36-carbp234-2026.doc
15. The arbitration petition is accordingly disposed of in the
above terms. There shall be no order as to costs.
(AMIT BORKAR, J.)
6