Bombay High Court

THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD THR GMIDC AURANGABADversusNAGNATH BABU DHUMAL THR LRS RUKMINIBAI RAMLING BIDWE AND ANR

Disposal
PARTLY ALLOWED AND PARTLY DISMISSED

Holding

The Court held that, in the interest of justice, the compensation rates awarded in LAR No. 432/2011 (Rs 3000 per R for irrigated land and Rs 1500 per R for dry land) are applicable to the present appeals, thereby partially allowing both the acquiring body’s and the claimants’ appeals and modifying the awards accordingly.

Summary

The Court heard multiple first appeals challenging the compensation awards in land acquisition proceedings for the Wadala Tank project. The Special Land Acquisition Officer had initially awarded Rs 150‑225 per R, which the reference court enhanced to Rs 940 per R. The acquiring body argued that the reference court’s enhancement was unwarranted, while the original claimants contended that the compensation remained inadequate. Relying on a prior judgment (LAR No. 432/2011) that awarded Rs 3000 per R for irrigated land and Rs 1500 per R for dry land, the Court held that the same rates should apply to the present appeals. It partially allowed the appeals of both the acquiring body and the claimants, modified the awards accordingly, and ordered interest and statutory benefits under Section 34 of the Land Acquisition Act. The impugned judgments were modified and pending civil applications were disposed of.

Issues considered

  • Whether the compensation rates awarded by the reference court can be aligned with rates granted in another land acquisition reference for the same project.
  • Whether the acquiring body's appeal challenging the reference court's enhanced compensation should be allowed.
  • Whether the original claimants are entitled to the higher compensation rates of Rs 3000 per R for irrigated land and Rs 1500 per R for dry land with statutory benefits.
  • Application of interest under Section 34 of the Land Acquisition Act as per State of Maharashtra v. Kailas Shiva Rangari.

Legislation cited

Subjects

  • land acquisition
  • compensation
  • reference court
  • interest under Section 34
  • precedent
  • Wadala Tank project
  • statutory benefits
  • appellate jurisdiction

Judgment

2026:BHC-AUG:31909

                                                                FA 770/13 & Ors
                                            1

                        IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   BENCH AT AURANGABAD

                              22 FIRST APPEAL NO. 770 OF 2013

                             KASHINATH VISHWANATH BAMANKAR
                                          VERSUS
                                 THE STATE OF MAH AND ANR
                                             ...
                                           WITH
                               FIRST APPEAL NO. 2926 OF 2017

               THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD
                                  THR GMIDC AURANGABAD
                                          VERSUS
                               SOPAN RAMANNA MANU AND ANR
                                             …
                                           WITH
                               FIRST APPEAL NO. 2928 OF 2017

               THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD
                                  THR GMIDC AURANGABAD
                                          VERSUS
                            MEENAKSHI APPARAO DHUMAL AND ANR
                                             …
                                           WITH
                               FIRST APPEAL NO. 2927 OF 2017

               THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD
                                   THR GMIDC AURANGABAD
                                           VERSUS
                NAGNATH BABU DHUMAL THR LRS RUKMINIBAI RAMLING BIDWE AND
                                             ANR
                                              …
                                             WITH
                                FIRST APPEAL NO. 748 OF 2014
                                             WITH
                             CIVIL APPLICATION NO. 7080 OF 2018
                                        IN FA/748/2014

                GODAVARI MARATHWADA IRRIGATION DEVELOPMENT CORPORATION,
                          MINOR IRRIGATION DIVISION, OSMANABAD
                                         VERSUS
                      KASHINATH VISHWANATH BAMANKAR AND ANOTHER
                                            …
                                          WITH
                              FIRST APPEAL NO. 2023 OF 2015

                 EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD
                                          VERSUS
                          BABASAHEB GUNDAPPA PATIL AND ANOTHER
                                                           FA 770/13 & Ors
                                     2

                                   …
                                 WITH
                     FIRST APPEAL NO. 1147 OF 2017
                                 WITH
                   CIVIL APPLICATION NO. 150 OF 2025

     THE EXECUTIVE ENGINEER, LOWER TERNA CANAL DIVISION-2,
                     OSMANABAD AND ORS.
                            VERSUS
             ABHAY KALYANRAO DESHPANDE AND ORS.
                               …
                              WITH
                 FIRST APPEAL NO. 2159 OF 2017

   THE MAHARASHTRA KRUSHNA VALLY DEVELOPMENT CORPORATION
                                 VERSUS
                       MOHAMMAD RASHID SHAIKH
                                     …
Advocates for Appellants in respective matters : Mr. Anand V. Patil-Indrale,
   Mr. P.S. Shinde, Mr. A.N. Gaddime, Mr. A.M. Gaikwad, Mr. S.C. Arora
         AGP for Respondent/State in all matters : Mr. S.S. Dande
Advocate for Respondents/claimants in respective matters : Mr. V.V. Ingale,
           Mr. Sanjay Wakure, Mr. R.P. Adgaonkar, Mr. L.C. Patil
  Advocate for Respondent No. 2. in FA 770/13 : Ms. Geeta Deshpande
                                     …

                    CORAM        : SIDDHESHWAR S. THOMBRE, J.
                    Dated        : July 27, 2026

PER COURT :-

1.    First Appeal Nos. 2023/2015, 1147/2017 and 2159/2017 are not on

board. Taken on board.

2.    Admit.

3.    Heard finally with the consent of learned counsel Mr. Anand V. Patil-

Indrale, Mr. P.S. Shinde, Mr. A.N. Gaddime, Mr. A.M. Gaikwad, Mr. S.C.

Arora, Mrs. Geeta Deshpande appearing for appellants/acquiring body in

respective matters, Mr. S.S. Dande, learned AGP for State, Mr. V.V. Ingale,

Mr. Sanjay Wakure, Mr. R.P. Adgaonkar and Mr. L.C. Patil, for original

claimants.

4.    By the present appeals, the acquiring body as well as the original
                                                            FA 770/13 & Ors
                                      3

claimants challenge the judgments and awards passed by the learned

reference court in different land acquisition references.

5.    The lands of the claimants involved in the present appeals were

acquired for the project Wadala Tank from different villages. The

notification under section 4 of the Land Acquisition Act came to be

published on 25.2.1993. Possession was taken over on 30.12.1992. The

Special Land Acquisition Officer (SLAO) passed the award dated 8.11.1996

and granted compensation at the rate of Rs. 9000/- per Acre and Rs.

6600/- per Acre. The claimants being aggrieved by the inadequate

compensation, preferred land acquisition references wherein the reference

court enhanced the compensation at the rate of Rs. 37,600/- per Acre i.e.

940/- per R. for their acquired lands. Being aggrieved by the same, the

acquiring body as well as the original claimants filed the present appeals.

6.    The learned counsel for the acquiring body in respective matters

submit that SLAO has granted compensation at the rate of RS. 150/- per

R. and Rs. 225/- per R. and same was enhanced by the reference court by

granting Rs.940/- per R. He submits that the SLAO has already considered

the comparable sale instances from the adjoining villages and rightly

granted compensation, but the reference court without considering the

same has enhanced the compensation which needs to be set aside by

allowing the appeals filed by the acquiring body.

7.    In support of the above contentions, Mrs. Geeta Deshpande, learned

counsel for the acquiring body placed reliance on the judgment and order

dated 21.10.2024 passed by the Hon’ble Supreme Court in Civil Appeal of

2024 arising out of SLP © No. 7963/2023 (Horrmal (Deceased) through his

L.Rs. And others Vs. State of Haryana and Others).
                                                          FA 770/13 & Ors
                                    4

8.    Per contra, the learned counsel appearing for the original claimants

submits that the SLAO has granted very meager compensation and

therefore, the references were filed. They relied on the sale deed Exhs. 29

and 30 and also on 7/12 extracts Exhs. 19, 24 and 28. They submit that

the acquiring lands though dry lands, the SLAO has granted very meager

compensation, the reference court without considering the sale instances

has granted very inadequate compensation though they are entitled to

receive more enhancement.

9.    The learned counsel for the original claimants have tendered the

copy of the order dated 11.3.2026 passed by this Court in First Appeal No.

1918/2020 (The Ex. Engineer, Minor Irrigation Div. Osmanabad and Ors.

Vs. Mohan Maruti Dhole) in which judgment and award dated 18.8.2015

passed by the Civil Judge, Senior Division, Osmanabad in LAR No.

432/2011 is under challenge.   They submits that the above matter arise

from the same project and the reference court enhanced the compensation

by granting rate of Rs. 3000/- per R. for irrigated lands. They submit that

the said order was challenged by the acquiring body before this Court by

filing First Appeal No. 1918/2020 and this court vide order dated

11.3.2026 maintained the rate granted by the reference court, but

modified the award to the extent of interest u/s. 34 of the Act in view of

the law laid down by the Full Bench of this Court in the case of State of

Maharashtra Vs. Kailas Shiva Rangari, reported in 2016 (3) Mh.L.J. 457.

Therefore, they submit that when this court confirmed the award passed in

LAR No. 432/2011, the appeals filed by the acquiring body needs to be

dismissed and compensation needs to be enhanced in view of the above

judgment in LAR No. 432/2011 passed by the reference court which is also
                                                             FA 770/13 & Ors
                                       5

confirmed by this court in FA No. 1918/2020.

10.     Having heard the learned counsel for the respective parties, I have

gone through the record and proceedings and also the judgment and

award of the reference court. There is no dispute about the fact that lands

in the present first appeals are acquired from village Patoda and other

villages. As regards the order on which claimants have placed reliance, the

lands are from village Bamani and the lands from the village Patoda and

Bamani are acquired for Wadala Tank by way of two different notifications.

However, the fact remains that the lands from different villages were

acquired for the same project. In view of the above, though different

notifications are issued, the lands were acquired from different villages for

the same project, I find that in the interest of justice, the rate granted in

LAR No. 432/2011 by the reference court can be considered for

enhancement in appeals filed by the original claimants though it cannot be

considered as binding precedent. Therefore, in my view the claimants from

the present appeals are also entitled to get the same rate as was granted

in LAR NO. 432/2011, which is confirmed by this Court in First Appeal No.

1918/2020. Hence, I pass the following order

                                  ORDER

(i)     The appeals filed by the acquiring body are partly allowed.

(II)    The appeals filed by the original claimants are also partly allowed

and the claimants are entitled to receive compensation at the rate of

Rs.3000/- per R. for irrigated lands, Rs. 1500/- per R. for dry land as

classified by the reference court, with all the statutory benefits available

under the Land Acquisition Act.

(III)   As regards interest and statutory benefits under the Act is
                                                              FA 770/13 & Ors
                                       6

concerned, the claimants are entitled to receive the interest in view of the

law laid down by the Full Bench of this Court in the case of         State of

Maharashtra Vs. Kailas Shiva Rangari (supra).

(IV)   The impugned judgments and awards are modified accordingly.

(V)    The claimants to pay the deficit court fees, if any, for enhanced

compensation.

(VI)   Pending Civil Applications, if any, are disposed of.



                                           ( SIDDHESHWAR S. THOMBRE, J. )

ssc/
