Created by Fuzzy Cloud

Bombay High Court

RAJENDRA GAJANAN PATILversusTHE STATE OF MAHARASHTRA THROUGH PUBLIC WORK DEPT. AND ORS

Decided
Disposal
Allowed

Holding

The writ petition is allowed; respondents must acquire the land, compute and pay compensation within six months.

Summary

The petitioner claimed that the State, through the Public Works Department, took possession of his land in 2010 for a road‑widening project and, despite issuing notices in 2011 and 2013, failed to pay any compensation. He invoked Article 300A of the Constitution and sought acquisition, computation and payment of compensation under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, along with damages. The respondents admitted the possession, acknowledged that compensation had not been paid, and stated they were ready to pay, but pointed to a terminated contract with a private contractor (Respondent No.7). The Court, relying on Supreme Court precedent that the right to property remains a constitutional and human right, held that the petition deserved relief. Accordingly, the writ petition was allowed and the respondents were directed to complete acquisition and pay compensation within six months.

Issues considered

  • Whether the State's taking of possession of the petitioner's land without payment of compensation violates Article 300A of the Constitution.
  • Whether the petition under the 2013 Land Acquisition Act is maintainable despite the involvement of a private contractor.
  • Whether the respondents are liable to acquire the land and pay compensation as directed by the Court.

Legislation cited

Subjects

  • Right to property
  • Article 300A
  • Land acquisition
  • Compensation
  • Writ petition
  • Public Works Department
  • Contract breach

Judgment

                                                                                         20_WP_5637_21.doc



                                       IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                               CIVIL APPELLATE JURISDICTION
                                              WRIT PETITION NO. 5637 OF 2021

                            Rajendra Gajanan Patil                                …      Petitioner
                                  vs.
                            The State of Maharashtra,
                            Through the Public Works Department & others          …      Respondents

                            Mr. Anilkumar K. Patil a/w. Mr. Laxmikant Patil and Mr. Digvijay Patil for
                            petitioner.
                            Mr. M. M. Pabale, AGP for respondent Nos.1 to 6 – State authorities.

                                                               CORAM :      MANISH PITALE &
                                                                            SHREERAM V. SHIRSAT, JJ
                                                               DATE     :   27th JULY, 2026
                            P.C. :


                            .        The petitioner is aggrieved by the action of respondents in
                            taking possession of the subject land of petitioner located in Gat
                            No.86, Village Kalamkhand, Taluka Wada, District Palghar, in the
                            year 2010 for widening of an existing road. It is the case of the
                            petitioner that despite possession having been taken as far back as in
                            the year 2010 and notices having been issued in the year 2011,
                            offering compensation by negotiation and agreement, no further
                            steps were taken by the respondents to pay just, fair and reasonable
                            compensation to the petitioner.


                            2.       It is submitted that therefore, this is a case of violation of the
                            petitioner’s right to property under Article 300A of the Constitution
                            of India. In that context, the petitioner seeks direction against the
                            respondents to take steps for acquisition of the subject land,
                            computation of compensation and payment thereof, under the
                            provisions of The Right to Fair Compensation and Transparency in
         Digitally signed
         by PRIYA
PRIYA    KAMBLI
         Date:
KAMBLI   2026.07.27
         18:15:52
         +0530
                                                                                                       1/4
                                                          20_WP_5637_21.doc



Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Act of
2013). The petitioner also prays for compensation and damages for
having taken illegal possession of the subject land as far back in the
year 2010.


3.    Respondent Nos.1 to 6 are represented by the learned AGP.
Reply affidavit dated 21.04.2025 has been filed on behalf of
respondent No.4. The relevant portion of the said affidavit reads as
follows:


     “5) I say that accordingly, the joint measurement was
         conducted and its reports was prepared on
         6.12.2010. As per the joint measurement report, it is
         reflected that the Petitioner land bearing S.No. 86
         area admeasuring 1690.00 Square Metre land is
         acquired. Hereto annexed and marked as Exhibit 4
         is the copy of joint measurement report.

     6)    I say that since the land of Petitioner was taken into
           possession for said project, public notices were
           issued on 27.4.2011, 2.6.2011 and 26.2.2013 in
           local newspaper and on 4.3.2014 in Sakal
           newspaper. By and under the Public Notice dated
           4.3.2014, the Petitioner alongwith other occupants
           were informed to contact with this Respondents and
           Respondent No.7 for claiming of compensation
           amount. Hereto annexed and marked as Exhibit 5
           Colly. are the copies of notices dt. 27.4.2011,
           2.6.2011 and 26.2.2013.

     7)    I say that as per the BOT agreement and work order
           it was primary responsibility of the Respondent No.7
           to acquire land of the Petitioner by entering into
           agreement/sale deed and to pay compensation
           accordingly. However, it appears from the record
           that the Respondent No.7 failed to do so for the
           reason best known to him.

     8)    I say that since the Respondent No.7 committed
           breach of contract and the Work Order and failed to

                                                                        2/4
                                                        20_WP_5637_21.doc



          comply with the condition of repairing and
          maintenance of the road, his contract is terminated
          on 11.10.2019.

     9)   I say that as per the new G.R. dated 12.05.2015 and
          30.09.2015 the Petitioner's land can be taken
          through private negotiation, therefore, this
          Respondent is ready and willing to pay the
          compensation amount for the acquired possession of
          the Petitioner's land for the said project through
          private negotiation. Hereto annexed and marked as
          Exhibit '6' Colly are copies of G.R., dated
          12.05.2015 and 30.09.2015.

     10) I say that this Respondent is reserved his right for
         recovery of amount of compensation for acquisition
         of Petitioner's land from the Respondent No. 7 by
         adopting appropriate procedure.

     11) I say that as per the Order of this Hon'ble Court
         dated 09.04.2025, the present affidavit is supposed
         to be filed on or before 17.04.2025, however, due to
         non availability of the documents there is delay in
         filing the present affidavit for which the Respondent
         is sincere apology to this Hon'ble Court.”


4.    A perusal of the above-quoted contents of the reply affidavit
clearly shows that while respondent No.4 was engaged for
completing the work of road-widening, the work order was
cancelled. The said fact is irrelevant for deciding the present writ
petition. What is more relevant and crucial is that respondent Nos.1
to 6 have not denied the fact that the possession was indeed taken in
the year 2010 and till date, compensation has not been paid. As a
matter of fact, the said respondents have stated in the above-quoted
portion of the affidavit that they are ready to pay compensation to
the petitioners.


5.    The Supreme Court, in a number of cases, including in the case
of Kolkata Municipal Corporation and another vs. Bimal Kumar Shah

                                                                      3/4
                                                                   20_WP_5637_21.doc



     and others, (2024) 10 SCC 533, has held that although the right to
     property is no longer a fundamental right, it is indeed a
     constitutional and human right, which cannot be trampled upon by
     the State authorities. In the present case, in the light of the admitted
     position on facts that the petitioner is deprived of the said land since
     the year 2010 and till date, compensation has not been paid, the writ
     petition deserves to be allowed.


     6.        In view of the above, the writ petition is allowed.
     Consequently, respondent Nos.1 to 6 are directed to immediately
     take steps for acquisition of the said land of the petitioner,
     computation and payment of compensation in terms of the provisions
     of the Act of 2013. The aforesaid entire process, including payment
     of compensation shall be completed within a period of 6 months
     from the date of this order.


     7.        Pending applications, if any, also stand disposed of.




     (SHREERAM V. SHIRSAT, J.)                            (MANISH PITALE, J.)




Priya Kambli




                                                                                 4/4


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.