Allahabad High Court
TATA PROJECTS LIMITED A COMPANYversusUTTAR PRADESH POWER TRANSMISSION CORPORATION LIMITED
- Decided
- Bench
- PIYUSH AGRAWAL
Holding
The Court appointed Justice Pankaj Mithal as the sole arbitrator under Section 11(6) of the Arbitration & Conciliation Act.
Summary
Tata Projects Ltd entered into an EPC contract with Uttar Pradesh Power Transmission Corporation Ltd for a GIS sub‑station. Owing to COVID‑19 and alleged project‑management failures, the work was delayed, leading the contractor to claim Rs 33.99 cr and the respondent to reject the claim. The parties could not agree on an arbitrator despite an arbitration clause (clause 38) in the contract, prompting Tata Projects to invoke Section 21 of the Arbitration & Conciliation Act and file an application under Section 11(6) for the court to appoint a sole arbitrator. The High Court, relying on Supreme Court decisions interpreting Section 11(6A) post‑2015 amendment, held that the existence of an arbitration agreement suffices and the court may appoint an arbitrator when parties fail to do so. Justice Pankaj Mithal was appointed as the sole arbitrator, and the application was disposed of.
Issues considered
- Whether the High Court can appoint a sole arbitrator under Section 11(6) of the Arbitration & Conciliation Act when parties fail to agree on an arbitrator.
- Whether the existence of an arbitration clause in the contract is sufficient to trigger appointment under Section 11(6).
- Interpretation of Section 11(6A) after the 2015 amendment in the context of appointing an arbitrator.
Legislation cited
- Arbitration and Conciliation Act, 1996 — s. 11(6), 11(6A), 21
- Companies Act
Subjects
- Arbitration
- Section 11 appointment
- Arbitration clause
- EPC contract
- Delay and retention
- Supreme Court precedent
- Arbitration agreement
Judgment
HIGH COURT OF JUDICATURE AT ALLAHABAD
ARBITRATION AND CONCILI. APPL.U/S11(4) No. - 96 of 2026
Tata Projects Limited A Company
.....Applicant(s)
Versus
Uttar Pradesh Power Transmission Corporation Limited
.....Opposite Party(s)
Counsel for Applicant(s) : Kundan Rai, Uday Pratap Singh
Counsel for Opposite Party(s) : Pranjal Mehrotra
Court No. - 7
HON'BLE PIYUSH AGRAWAL, J.
1. Heard the learned counsel for the parties.
2. The instant application has been preferred under Section 11(6) of the Arbitration &
Conciliation Act, 1996 for appointment of a sole Arbitrator.
3. Learned counsel for the applicant submits that the applicant is a company
incorporated under the provisions of Companies Act. He submits that the opposite
party has invited bids for designing supply of erection, civil works, testing and
commissioning of 400/220/132/kv GIS Sub Station on an EPC basis at Basti, Uttar
Pradesh in which the applicant being the successful bidder awarded the contract and in
pursuance thereof an agreement was signed between the parties on 26.12.2018. He
submits that in January, 2019, the applicant after completing the pre-construction
activities, has requested the respondent to issue Form V (Labour License) so that work
force could be deployed at the side and in pursuance thereof FORM V has been issued
on 4.7.2019 extending the period of 6 month. He submits that in the meantime, due to
COVID 19 pandemic the construction could not be completed, therefore, the applicant
again applied for extension of time on 4.7.2020, which was allowed but the
respondent issued a letter on 10.7.2023 stating that there was total delay of 776 days in
completing the project to which the applicant responded through letter dated 1.8.2023
stating that due to the said delay, the applicant was suffered financial cost of Rs. 14.73
cr. and thereafter again sent a letter dated 13.9.2023 requesting to release the retention
amount of Rs. 16.87 Cr. Thereafter some dispute arose between the parties and the
applicant raised total claim of Rs. 33,99,08,572/- under the various heads arising out
of contract agreement which was rejected by the respondent on 16.1.2025. Aggrieved
to the said rejection, the applicant issued notice dated 11.2.2025 under Section 21 of
the Arbitration and Conciliation Act invoking arbitration clause no. 38 of the contract
agreement but no consented arbitrator could be appointed by the parties. Hence the
present application.
4. Per contra, learned counsel for the opposite party has vehemently opposed the
ARCO No. 96 of 2026
2
submissions made by learned counsel for the applicant. He submits that the applicant
utterly failed to adhere to the contractual timelines and the project suffered inordinate
delays solely due to the applicant's poor project management, slow mobilization of
resources and failure to execute the work with due diligence. However, learned
counsel for the opposite party does not dispute about the existence of dispute between
the parties.
5. Having heard learned counsel for the parties, the scope of the present proceedings
under Section 11 of the Act does not require any elaboration in view of that position in
law having been made crystal clear by a recent three judge decision of the Supreme
Court in the case of M/S Mayavati Trading Pvt. Ltd. Vs. Pradyuat Deb Burman,
Civil Appeal No. 7023 of 2019, decided on 05.09.2019 in which it has been held as
below:
"This being the position, it is clear that the law prior to the 2015 Amendment that has
been laid down by this Court, which would have included going into whether accord
and satisfaction has taken place, has now been legislatively overruled. This being the
position, it is difficult to agree with the reasoning contained in the aforesaid judgment
as Section 11(6A) is confined to the examination of the existence of an arbitration
agreement and is to be understood in the narrow sense as has been laid down in the
judgment Duro Felguera, S.A. (supra) -- see paras 48 & 59."
6. While laying down that law, the Supreme Court had itself referred to paragraph nos.
48 & 59 of its earlier decision in the case of Duro Felguera, S.A. Vs. Gangavaram
Port Ltd., (2017) 9 SCC 729.
7. That position in law has been reiterated in a recent decision of the Supreme Court in
GOQII Technologies Pvt. Ltd. Vs. Sokrati Technologies Pvt. Ltd., (2025) 2 SCC
192.
8. In the facts of the present case, on prima facie basis, it has to be accepted that there
exists an arbitration clause, between the parties. Also, it is clear that the parties have
not been able to appoint consented arbitrator and therefore, the appointing authority
has to be assumed by this Court upon the present application.
9. At the same time, no final conclusion is being drawn as may affect the merits of the
claim. That matter would remain to be considered by the appropriate forum at the
appropriate stage, upon claim, objection, challenge or appeal being filed. Thus,
amongst others it would remain open to the opposite party to raise all objections as the
Act permits.
10. Leaving that course completely open to the respective parties, at present, only a
forum is being provided for adjudication of a claim proposed to be raised and resisted,
in accordance with the law.
ARCO No. 96 of 2026
3
11. Accordingly, with the consent of learned counsel for the parties, Hon'ble Mr.
Justice Pankaj Mithal, (a Former Judge of the Supreme Court), resident of R-29,
Ground Floor, South Extension - II, New Delhi - 110 049, Mobile No. 9415216238
(Email ID: [email protected]), is hereby appointed as an
Arbitrator, who shall adjudicate the matter and settle all the dispute between the
parties in accordance with law.
12. The Arbitrator shall be entitled to his fees and expenses as may be agreed between
the parties.
13. In view of the above, the present arbitration application stands disposed of.
14. Office to intimate this order to the Arbitrator through normal mode as well as e-
mail.
September 24, 2026
Rahul Dwivedi/-
(Piyush Agrawal,J.)
Digitally signed by :-
RAHUL DWIVEDI
High Court of Judicature at Allahabad
Checking your session…