Created byFuzzy Cloud

Supreme Court of India

A.P. POWER COORDINATION COMMITTEE & ORS.versusMIS. LANCO KONDAPALLI POWER LTD. & ORS.

Citation
2015 INSC 1033
Decided
16 October 2015
Disposal
Dismissed

Holding

A claim before the Commission cannot be entertained if barred by the ordinary limitation period, but the period may be excluded under s.14 of the Limitation Act, and the MAT claim is covered by Article 3.8 of the PPA.

Summary

The dispute involved the A.P. Power Coordination Committee and related entities (appellants) and M/s. LanCo Kondapalli Power Ltd. (respondent) over capacity‑charge bills and a claim for reimbursement of Minimum Alternate Tax (MAT) under their Power Purchase Agreement (PPA). The key questions were whether the Limitation Act, 1963 applies to proceedings before the Andhra Pradesh Electricity Regulatory Commission (the Commission) under s.86(1)(f) of the Electricity Act, 2003, whether the Appellate Tribunal for Electricity (APTEL) was correct in allowing the exclusion of the arbitration period under s.14 of the Limitation Act, and whether the MAT claim falls within Article 3.8 of the PPA. The Supreme Court held that a claim before the Commission is barred by the ordinary limitation period unless a period is excluded under s.14, and that APTEL correctly applied s.14. It also held that MAT is covered by Article 3.8 and is recoverable. Consequently, the appeals were dismissed and the Commission was directed to pass a consequential order on the MAT claim.

Issues considered

  • Whether the Limitation Act, 1963 (s.3, s.14 and Schedule) applies to actions instituted before the Commission under s.86(1)(f) of the Electricity Act, 2003.
  • Whether the order of APTEL permitting the application of principles under s.14 of the Limitation Act is contrary to law.
  • Whether the claim for reimbursement of Minimum Alternate Tax is covered by Article 3.8 of the Power Purchase Agreement and therefore enforceable.

Legislation cited

Subjects

Electricity ActLimitation ActAPTELCommissionArbitrationCapacity chargesMinimum Alternate TaxPower Purchase AgreementSection 86Section 14Statutory tribunal

Judgment

                   [2015] 12 S.C.R. 447


   A.P. POWER COORDINATION COMMITTEE & ORS.                   A
                             v.
    MIS. LANCO KONDAPALLI POWER LTD. & ORS.
              (Civil Appeal No. 6036 of 2012)
                                                              B
                   OCTOBER 16, 2015
   [VIKRAMAJIT SEN AND SHIVA KIRTI SINGH, JJ.]
      Electricity Act, 2003 - s. 86(1 )(f), 174 - Limitation Act,
1963 - ss. 3, 14, Schedule - Disputes between /icencees c
and power generating company- Bill for capacity charges-
Claim for reimbursement of minimum alternate Tax (MAT) -
Whether the Limitation Act, s. 3 and the Schedule would
apply to any action instituted before the Commission uls.
86(1)(f) - Whether the impugned order passed by APTEL D
permitting application of principles emerging from s. 14, is
against law - Whether the claim for reimbursement of MAT
is in contravention of relevant terms and conditions of the
Power Purchase Agreement (PPA) - Held: A claim coming
before the Commission cannot be entertained or allowed if it E
is barred by limitation prescribed for an ordinary suit before
the civil court - However, in appropriate case, a specified
period may be excluded on account of principle underlying
salutary provisions like s. 5 or 14 - Further, such limitation
upon the Commission would be only in respect of its judicial F
power uls. 86(1 )(f) and not in respect of its other powers or
functions which may be administrative or regulatory - As
regards order passed by APTEL, in law, the APTEL could
grant exclusion of certain period on the basis of principles ul G
s. 14 - On facts, APTEL adopted a just and lawful approach
in examining the relevant facts and in excluding the entire.
period claimed by respondent which starts from the notice
for arbitration dated 8.9.2003 given by the respondent, till
 the application of the respondent u/s. 11 of the Arbitration H
448       SUPREME COURT REPORTS                 [2015] 12 S.C.R.

A Act before the High Court was finally disposed of on
   18. 3. 2009 - Challenge to impugned order in respect of views
  taken on the issue of limitation in the light of principles of s.
   14 fails - As regards the claim for reimbursement, entire
  phraseology used in Article 3.8 of the PPA clarifies that
B parties were aware that tax regime keeps changing and
  therefore any advance income tax payable for the income
  from the project only had to be reimbursed by the Board -
  As a successor of the Board the appeliant cannot avoid the
  liability to reimburse advance income tax paid by_ the
C respondent, on the ground that MAT was a new variety of tax
  concept introduced subsequently in which minimum tax
  became payable on the basis of mere book profits of even
  power generating companies - It cannot be said that such,
  tax is not on income from the project and thus, not covered
0
  by Article 3.8- Taxable income became amenable to MAT
  on account of s. 115JB - Claim for MAT covered by Article
  3. 8 and payable as such when requisite conditions stand
      ~~~d                                            .
E        Dismissing the appeals, the Court

        HELD: 1.1 There is no possibility of any difference
  of opinion in accepting that on account of judgment of
  this Court in Gujarat Urja the Commission has been
F elevated to the status of a substitute for the Civil Court
  in respect of all disputes between the licencees and
  generating companies. Such dispute need not arise from
  the exercise of powers under the Electricity Act. Even
  claims or disputes arising purely out of contract like in
G the instant case have to be either adjudicated by the
  Commission or the Commission itself has the discretion
  to refer the dispute for arbitration after exercising its
  power to nominate the arbitrator. A statutory authority
H like the Commission is also required to determine or
   A.P. POWER COORDINATION COMMITTEE v. LANCO                   449
                KONDAPALLI POWER LTD.

decide a claim or dispute either by itself or by referring it   A
to arbitration only in accordance with law and thus
Section 174 and 175 of the Electricity Act assume
relevance. Since no separate limitation has been
prescribed for exercise of power under Section 86(1)f)
nor this adjudicatory power of the Commission has been          B
enlarged to entertain even the time barred claims, there
is no conflict between the provisions of the Electricity
Act and Limitation Act to attract the provisions of Section
174 of the Electricity Act. In such a situation on account
of provisions in Section 175 of the Act or even otherwise       C
the power of adjudication and determination or even the
power of deciding whether a case requires reference to
arbitration must be exercised in a fair manner and in
accordance with law. In the absence of any provision in         o·
the Electricity Act creating a new right upon a claimant.
to claim even monies barred by law of limitation, or taking
away a right of the other side to take a lawful defence of
limitation, in the light of nature of judicial power
conferred on the Commission, claims coming for                  E
adjudication before it cannot be entertained or allowed
if it is found legally not recoverable in a regular suit or
any other regular proceeding such as arbitration, on
account of law of limitation. This view is taken not only
because it appears to be more just but also because             F
unlike Labour laws and Industrial Disputes Act, the
 Electricity Act has no peculiar philosophy or inherent
 underlying reasons requiring adherence to a contrary
view. [Para 29] [489-B-D, H; 490-A-F]
                                                            G
     1.2Aclaim coming beforethe Commission cannot
be entertained or allowed if it is barred by limitation
prescribed for an ordinary suit before the civil court. But
in appropriate case, a specified period may be excluded
on account of principle underlying salutary provisions H
450          SUPREME COURT REPORTS               [2015] 12 S.C.R.

A like Section 5 or 14 of the Limitation Act. Further, such
  limitation upon the Commission on account of the
  decision in V.R.Kal/iyanikutty would be only in respect
  of its judicial power under clause (f) of sub-section (1) of
  s. 86 of the Electricity Act, 2003 and not in respect of ifs
B other powers or functions which may be administrative
  or regulatory. [Para 30] [491-C-E]

        1.3 The respondent rightly appreciated the hurdle
  of limitation in its way when such an objection was taken
C by the appellant and it rightly chose to seek exclusion
  of the period it was pursuing arbitration proceeding
  before the High Court, on the basis of principles
  underlying Section 14 of the Limitation Act. [Para 31] [491-
      F-G]
D
            1.4 In law, the APTEL could grant exclusion of
      certain period on the basis of principles under Section
      14 in view of law laid down or clarified in M.P. Steel
      Corporation. On facts, there is no difficulty in holding that
E     APTEL has adopted a just and lawful approach in
      examining the relevant facts and in excluding the entire
      period claimed by the respondent which starts from the
      notice for arbitration dated 8.9.2003 given by the
      respondent, till the application of the respondent under
F     Section 11 of the Arbitration Act before the High Court
      was finally disposed of on 18.3.2009. The issue whether
      the first notice dated 8.9.2003 or the next notice dated
      26.3.2004 should be treated as notice for arbitration for
      the purpose of Section 21 of the Arbitration Act was
G     rightly not pursued further by the counsel. But since this
      issue was touched, the entire Article 14 of the PPA as
      well as the notice dated 8.9.2003 is looked at and there
      is no difficulty in holding it as the notice for arbitration
      which amounted to initiation of arbitral proceedings as
H     contemplated by Section 21 of the Arbitration Act. The
   A.P. POWER COORDINATION COMMITTEE v. LANCO                451
              KONDAPALLI POWER LTD.

submission on behalf of appellant that after the judgment A
of this Co.urt in Gujarat Urja on 13.3.2008, the
continuance of the arbitral proceedings before the High
Court at the instance of the respondent should not be
accepted as bona fide and that the commission was
justified in not excluding this period of about one year B
on the ground that it was not bona fide and in such facts
APTEL should not have taken a contrary view, cannot
be accepted. [Para 32] [492-A-E]

      1.5 The appellant had notice of the arbitral C
proceeding and after judgment in. Gujarat Urja, the
appellant also took no steps to get the application under
Section 11 listed and disposed of earlier to 18.3.2009.
The averments and the materials are not sufficient to
establish the claim of the appellant that the proceeding D
ceased to be bona fide after 13.3.2008. As a
consequence thereof, the challenge to impugned order
in respect of views taken on the issue of limitation in the
light of principles of Section 14 of the Limitation Act fails.
[Para 32][493-C-D]                                             E

      1.6 The issue whether MAT is covered by Article 3.8
of the PPA was clearly covered by Arbitration notice. The
filing of upto date claims through amendment or
otherwise before the Arbitral Tribunal could not happen F
for the obvious reason that application under Section
11 of the Arbitration Act itself remained pending till
18.03.2009 before the High Court and thereafter before
the Commission. [Para 33] [494-A-B]
                                                          G
      1.7 The claim for reimbursement of MAT for the
period 2001-2005 was rejected by the Commission on
the ground of limitation and after impugned order by
APTEL reversing such order, that claim stands remitted.
to the Commission for passing a consequential order. H
452        SUPREME COURT REPORTS              [2015] 12 S.C.R.

A     The claims for other periods have been allowed by the
      Commission. On account of the view indicated earlier
      upholding the order of APTEL on the issue of limitation,
      the claim of MAT for 2001-2005 cannot be treated as
      barred by limitation. Thus the claim of MAT for entire
 B    concerned period that is from 2001-2012 will be covered
      by the decision on Merits of Claim relating to MAT. The
      submission that MAT cannot be covered by the
      provisions in Article 3.8 of the PPA providing for claims
      for taxes on income because the appellant had not
C     foreseen such eventuality in view of the then prevailing
      tax regime under which income from such power
      projects stood exempted, is noticed only to be rejected.
      The entire. phraseology used in Article 3.8 of the PPA
      leaves no manner of doubt that parties were aware that
0
      tax regime keeps changing and therefore any advance
      income tax payable for the income from the project only
      had to be reimbursed by the Board. As a successor of
      the Board the appellant cannot avoid the liability to
E     reimburse advance income tax paid by the respondent,
      on the ground that MAT was a new variety of tax concept
      introduced subsequently in which minimum tax became
      payable on the basis of mere book profits of even power
      generating companies. The argument that such tax is
F     not on income from the project and thus, not covered
      by Article 3.8 of the PPA is without any substance.
      [Para 34] [494C-H; 495-A]
       1.8 The objective of levying MAT, as declared by the
G Income Tax Department is to bring into the tax net "Zero
  Tax Companies" which inspite of having earned
  substantial book profits and having paid handsome
  dividends, do not pay any tax due to various tax
  concessions and incentives provided under the Income
H Tax Law. It is no body's case that in fact the respondent
   AP. POWER COORDINATION COMMITTEE v. LANCO                 453
             KONDAPALLI POWER LTD.

had not generated income from the project during the         A
relevant years. The taxable income, of course, became
amenable to MAT on account of Section 115JB. The
legislative changes in respect of MAT show that it came
into force initially with e·ffect from 1.4.1988 by
introduction of Section 115J in the Income Tax Act, 1961     B
but this provision was amended to exempt power
generating companies with.effect from 1.4.1989 and from
1.4.1991 MAT became inapplicable because of deletion
of Section 115J which was reintroduced with effect from
1.4.1997 by insertion of Section 115JA. But it was not       C
made applicable ~o power generating companies till
31.3.2001. However, Section 115JAwas withdrawn and
Section ·115JB was inserted with effect from 1.4.2001 to
make MAT applicable to all targeted corporate entities
                                                             0
including power generating companies. The submission
on behalf of the appellant that Section 115JB is a tax not
on profit but of different character is based on
misconception. No doubt this Section has a special
provision for payment of tax by certain companies on         E
the basis of its book profit which is deemed to be the
total income of the assessee and is subjected to income
tax at a specified rate. The provisions of Sections 115JA
and 11 SJB have been also construed as a self-contained
code But that does not change the basic nature of the        F
provision. It remains a provision under the Income Tax
Act and what is levied is income tax on the assessment
of income as per such a special provision. [Para 35]
[495-B-H; 496-A]
                                                             G
     1.9 Article 1.4 of the PPA provides inter alia that
reference to any 'Law' shall be construed as a reference
to such Law as from time to time amended or re-enacted.
This general provision in our view is sufficient to take
care of all the taxes on income under Article 3.8 of the H
454         SUPREME COURT REPORTS              [2015] 12 S.C.R.

A PPA notwithstanding different rates of income tax or
  other changes which may be brought about in the
  Income Tax Act. This view commends itself because
  such change in Law relating to Income Tax does not
  require any additional claim to be raised by the power
B generating companies. There is no specific amount-or
  rate which is to be reimbursed by the Board. Rather, the
  entire advance income ·tax payable requires
  reimbursement on account of Article 3.8 of the PPA
  provided of course that the accounts are maintained in
C the manner required by the Agreement so that tax is only
  on the basis of income from the project. No such dispute
  has been raised in the instant case. (Para 36] (496-B-D]
            1.10 The claim of the appellant that liability of MAT
D     is on account of change in Law and therefore required
      the respondent to adopt the procedure for making claims
      under Article 11.4 of the PPA does not appeal for the
      aforesaid reasons. The entire stipulation in Article 11.4
      of the PPA is in respect of additional or reduced
E     expenditures or costs which have not been catered for
      and arise later due to change in Law. The burden on
      account of income tax as per Article 3.9 of the PPA cannot
      be treated as additional or reduced burden because the
      entire actual advance income tax payable for the project
F     is required to be reimbursed by the Board. It is immaterial
      whether the income tax payable is high or low in any
      particular year. When there is already a special provision
      in respect of entire payable taxes on income under Article
      3.8 of the PPA, that should have precedence over the
G     general provisions in Article 11.4 of the PPA. [Para 37]
      (496-E-H]
        1.11 Section 2(43) defines 'Tax' to mean income tax
  chargeable under the provisions of Income Tax Act and
H 'Total Income' has been defined with reference to Section
   A.P. POWER COORDINATION COMMITTEE v. LANGO               455
              KONDAPALLI POWER LTD.

5 which enlarges the scope of total income not only to A
income received. or accrued but also deemed to be
received or deemed to be accrued in India (for a resident).
Simply because the exemption earlier granted to power
generating companies has been withdrawn so as to
subject them to income tax liability under a special B
provision, cannot lead to any inference as suggested
on behalf of the appellant that it is not an income tax but
some other tax which is levied under s.115JB of the
Income Tax Act. Hence the claim for MAT covered by
Article 3.8 of the PPA and payable as such when C
requisite conditions stand satisfied. [Para 38] [497-B-D]

     M.P Steel Corporation v. Commissioner of Central
     Excise (2015) 7 SCC 58; State of Kera/av. V.R.
     Kalliyanikutty 1999 (2) SCR 372: (1999) 3 SCC          D
     657 - relied on.

     Gujarat Urja Vik as Nigam Ltd. v. Essar Power Ltd. ·
     2008 (4) SCR 822: (2008) 4 sec 755; Tamil
     Nadu Generation & D[stribution Corpn. Ltd. v.          E
     PPN Power Generating Co. (P) Ltd. 2014 (4)
     SCR 667: (2014) 11 SCC 53; Hans Raj Gupta v.
     Dehra Dun-Mussoorie Electric Tramway Co. Ltd.
     AIR 1933 PC 63; New Delhi Municipal Committee
     v. Ka/u Ram 1976 (0) Suppl. SCR 87:(1976) 3            F
     SCC 407; Kihoto Hallahan v. Zachillhu 1992 (1)
     SCR 686: 1992 Supp. (2) SCC 651; Thakur Jugal
     Kishore Sinha v. Sitamarhi Central Co-operative
     Bank Ltd. 1967 (3) SCR 163; Brajnandan Sinha
     v. Jyoti Narain AIR 1956 SC 66: 1955 SCR 955;          G
     P Sarathy v. State Bank of India 2000 (1) Suppl.
     SCR 402: (2000) 5 SCC 355; Commissioner of
     Sa/es Tax v. Parson Tools and Plants (1975)4
     SCC 22; Ujjam Bai v. State of U.P AIR 1962 SC
                                                            H
456        SUPREME COURT REPORTS                [2015] 12 S.C.R.


A         1621 :1963 SCR 778; Jagannath Prasad v. State
          of UP AIR 1963 SC 416: 1963 SCR 850; Mukri
          Gopalan v. Cheppilat Puthanpurayil Aboobacker
          1995 (2) Suppl. SCR 1: (1995) 5 sec 5;
          Consolidated Engg. Enterprises v. Irrigation Deptt.
B         2008 (5) SCR 1108: (2008) 7 SCC 169; Trans
          Mediterranean Airways v. Universal Exports 2011
          (14) SCR 47: (2011) 10 SCC 316; Henry
          Hauenstein v. John.A. Lynham 100 U.S. 483; Re.
          Jarvis (Deceased) Edge v. Jarvis (1958) 2 All.ER
c         336; Bombay Gas Co. Ltd. v. Gopal Bhiva 1964(3)
          SCR 709; Hindustan Times Ltd. v. Union of India
          1998 (1) SCR 4:(1998) 2 SCC 242; State of
          Gujarat · v. Patil Raghav Natha 1970
          (1) SCR 335:(1969) 2 SCC 187; Ram Chand v.
D
          Union of India 1993 (2) Suppl. SCR 558: (1994)
          1 SCC 44; Bombay Dyeing & Manufacturing Co.
          Ltd. v. The State of Bombay AIR 1958 SC
          328:1958 SCR 1122; Mis. Tilokchand and
E         Motichand v. H.B. Munshf (1969) 1 SCC 110;
          Ajanta Pharma Limited vs. CIT 2010 (11)
          SCR 404:2010 (9) SCC 455- referred to.
                          Case Law Reference

F     2008 (4) SCR 822               Referred to.     Para 5

      2014 (4) SCR 667               Referred to.     Para 14

      1999 (2) SCR 372               Referred to.     Para 17

      AIR 1933 PC 63                 Referred to.     Para 17
G
      1976 (0) Suppl. SCR 87         Referred to.     Para 18

      1992 (1) SCR 686               Referred to.     Para 19

      1967 (3) SCR 163               Referred to.     Para 19
H
   A.P. POWER COORDINATION COMMITTEE v. LANCO                     457
                 KONDAPALLI POWER LTD.

1955 SCR 955                      Referred to.     Para 19        A

2000 (1) Suppl. SCR 402           Referred to.     Para 20

(2015) 1 sec 58                   Relied on.       Para 20

(1975) 4 sec 22                   Referred to.     Para 20        B
1963 SCR 778                      R~ferred to.     Para 20

1963 SCR 850                      Referred to.     Para 20

1995 (2) Suppl. SCR 1             Referred to.     Para 20        c
2008 (5) SCR 1108                 Referred to.     Para 20

2011 (~4) SCR 47                  Referred to.     Para 21

100 U.S. 483                      Referred to.     Para 26
                                                                  D
(1958) 2 All.ER 336               Referred to.     Para 26

1964(3) SCR 709                   Referred to.     Para 26

1998 (1) SCR 4                    Referred to.     Para 26
                                                                  E
1970 (1) SCR 335                  Referred to.     Para 26

1993 (2) Suppl. SCR 558           Referred to.     Para 26

1958 SCR 1122                     Referred to.     Para 27
                                                                  F
(1969) 1sec110                    Referred to.     Para 27

2010 (11) SCR 404                 Referred to.     Para 35
     CIVIL APPELLATE JURISDICTION: Civil Appeal No.
6036 of 2012                                                      G

      From the Judgment and Order dated 02.07.2012 of the
Appellate Tribunal for Electricity, New Delhi in Appeal No. 129
of 2011
                               WITH                               H
458        SUPREME COURT REPORTS                  [2015] 12 S.C.R.


A         C. A. Nos. 6061and6138 of 2012

          C. A. No. 9304 of 2013 and C. A. No. 6835 of 2015

          V. Giri,A. Subba Rao, ManavVohra, Svadha Shankar,
  K. L. D. S. Vinober, P. Siva Rao, Rakesh K. Sharma, Anand
8 K. Ganesan, Swapna Sheshadri, K. V. Balakrishnan, K. V.
  Mohan for the Appellants.

         C. A. Sundaram, Jayant Bhushan, Vikas Singh, S. B.
  Upadhyay, Sakya Singha Chaudhuri, Avijeet Lala, Kanika
C Chugh, Saloni Tangri, Rohini Musa, Zafar lnayat, D. Bharathi
  Reddy, Shivani Khandekar, Sakya Singha Chaudhuri, Vishrov
  Mukehrjee, Apoorva Misra, ·Rohit Venkat, Deipika Kalia, Sum it
  Kumar Vats, Pukhrambam Ramesh Kumar, Pawan Upadhyay,
  Kaustav P. Pathak, Sarvjit Pratap Singh, Sharmila Upadhyay
D for the Respondents.

          The Judgment of the Court was delivered by

         SHIVAKIRTI SINGH, J.1. The leading matter -
E C.A.No.6036 of 2012 as well as C.A.No.6061 of 2012 are
  statutory appeals arising out of a common order dated
  2. 7.2012 passed by Appellate Tribunal for Electricity (for short,
  'APTEL') whereby pleas under Section 14 of the Limitation
  Act, 1963 to explain the alleged delay in preferring claims by
F the common respondent- M/s. Lance Kondapalli Power Ltd.
  (for brevity referred to as 'M/s. LAN CO') a power generating
  company before the Andhra Pradesh Electricity Regulatory
  Commission (hereinafter referred to as 'the Commission') has
  been accepted and as a result the main claim in the leading
G matter relating to Bill for Capacity Charges and in the other
  appeal for Minimum Alternate Tax (MAT) for 2001-2005 have
  been remanded for a follow up order by the Commission on
  the actual claims and interest. In respect of MAT, a concession
  on merits was recorded in respect of period 2006-2009 and
H
   A.P. POWER COORDINATION COMMITTEE v. LANCO                     459
     KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

for the earlier period (2001-2005) the contest was confined       A
 only to issue of limitation, as evidenced by Original Order of
 Commission dated 13.6.2011. Hence, through a SLP leading
 to C.A.No.6835 of 2015, the Appellant has chosen to make a
 direct challenge to aforesaid order to explain and overcome
.the alleged concession in respect of claim for reimbursement     B
 of MAT for the entire period of 2001-2009. C.A. No.6138 of
 2012 is a statutory appeal to again challenge MAT for 2006-
 2009 but directed against appellate order dated 20.7.2012
 by APTEL. The last matter, C.A.No.9304 of 2013 arises out
 of a SLP against the original order of Commission dated          C
 8.8.2013 relating to MAT claim for the period 2009-2012.
 Since issues are same or similar between the same appellant
 and respondent in all these appeals, they have been heard
 together and shall be governed by this common judgment.
                                                                  0
 Unless otherwise indicated the facts·have been noted from
 the records of the main matter, i.e., C.A.No.6036 of2012.

      2. Instead of merits of bills raised by M/s. LANCO for
capacity charges the issue of limitation has assumed greater
significance and has thrown up two important points. First, E
whether the Limitation Act is applicable to a claim before the
Commission and if the answer is in positive, then second,
whether APTEL's order reversing the views of Commission.
and accepting claim under Section 14 of the Limitation Act is F
in accordance with law or not. ft is not in dispute that if the
order of APTEL is upheld, the issue of correctness or validity
of capacity charges will stand remanded for decision by the
Commission in accordance with law. So far as claim of M/s.
LANGO for reimbursement of MAT for the period 2001-2005 G
is concerned, it shall stand rejected if APTEL's order on the
issue of limitation is reversed, otherwise such claim for the
aforesaid period as well as for later period upto 2012 will be
governed by the present judgment on the issue of legality and
admissibility of claim for MAT.                                 H
460          SUPREME COURT REPORTS                   [2015] 12 S.C.R.


A            3. Before adverting to the issues noticed above and the
      rival contentions, it will be useful to notice the essential facts
      relevant for deciding the issues. M/s. LANGO is engaged in
      the generation and sale of electricity. Its Registered Office is
      at Hyderabad and it has set up its power project at Kondapalli
B     Industrial Development Area in Krishna District of Andhra
      Pradesh. A.P. Power Co-ordination Committee, the appellant
      no.1, as the name suggests, was constituted on 07.06.2005
      to ensure coordination between the four distribution
      companies of Andhra Pradesh who are appellant nos.3 to 6.
C     M/s. Transmission Corporation of Andhra Pradesh
      (APTRANSCO) is the second appellant. At the relevant time
      the appellant no.2 was engaged in procurement of power for
      the Distribution Companies. In the first phase of power sector
D     reforms, Andhra Pradesh State Electricity Board was
      unbundled into Generation and Transmission Corporation and
      subsequently the four Distribution Companies were notified
      by the Government on 31.3.2000 on account of unbundling of
      the Transmission Corporation in the subsequent phase of
E     reforms.

         4. There is no dispute between the parties that the
   erstwhile A. P. State Electricity Board had invited bids for short
  ,gestation power projects. M/s. LANCO also submitted its bid
F which was accepted by the Board and approved by the
   Government of Andhra Pradesh leading to a Power Purchase
   Agreement (for brevity, 'PPA') dated 31.3.1997. M/s. LANCO
   then set up a 355 MW (ISO) Combined Cycle Gas Power Plant.
   The completion of the plant took more than the scheduled
G period of 16 months. It is not necessary to go into reasons for
   the delay in the present proceeding. It will suffice to note that
   Mis. LA NCO declared 25.10.2000 as the date of
   commissioning of their project but this was not accepted as
   the Commercial Operation Date (COD) by APTRANSCO.
H However, M/s. LANCO continued to generate power and
    A.P. POWER COORDINATION COMMITTEE v. LANGO                       461
     KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

delivered it to grid. It raised bills from 19.9.2000. While the      A
charges for the energy delivered were accepted, the bill for
capacity charges was disallowed on the ground that it was not
in accordance with the PPA. On 8.9.2003 M/s. LANCO issued
a notice of arbitration under Article 14 of the PPA. There is
some dispute as to whether this notice was only for invoking         B
the mechanism for informal dispute resolution or also a notice
for resolution of dispute by Arbitration. The appellants through
a reply dated 24.9.2003 requested for an ordinary meeting to.
discuss pending problems before considering the request for
arbitration. On 14.10.2003 Mis. LANCO wrote a letter                 C
intimating the nomination of its Company's Secretary as its
representative to participate in the proceeding for informal
dispute resolution required by Article 14.1. It requested the
other side to designate their representative and to intimate
                                                                     0
the date and venue of the meeting. The appellants through a
letter dated 25.11.2003 designated their Chief General
Manager to act as their representative but the meeting
scheduled could not take place. On 26.3.2004, M/s. LANCO
issued another notice for arbitration and intimated the name         E
of Justice B.P. Jeevan Reddy as its arbitrator. Through a letter
dated 8.4.2004, APTRANSCO raised various grounds in
support of its stance that the arbitration clause was not
enforceable, particularly in the light of Section 86(1 )(f) of the
Electricity Act, 2003.                                               F

       5. M/s. LANCO did not accept the stand of appellants
arid filed an Arbitration Application bearing No.31 of 2004 on
27.4.2004 before the High Court of Andhra Pradesh at
Hyderabad under Section 11(4) of the Arbitration and G
Conciliation Act, 1996 seeking appointment of arbitrator for
APTRANSCO so that the disputes raised by it could be
resolved through arbitration. APTRANSCO contested the
maintainability of arbitration proceedings on various grounds
including Section 86(1 )(f) of the Electricity Act, 2003. While H
462        SUPREME COURT REPORTS                 [2015] 12 S.C.R.


A the matter before the High Court was still pending, the scope
  and effect of Section 86( 1)(f) of the Electricity Act was decided
  by a judgment of this Court dated March 13, 2008 in the case
  of Gujarat Urja Vikas Nigam Ltd. v. Essar Power Ltd.
  (2008) 4 SCC 755. This Court held that all disputes between
B the licencee such as the appellants and generating companies
  such as Mis. LANGO require adjudication only by the State
  Commission which is alone competent to either adjudicate
  the disputes or refer them for arbitration and to appoint
  arbitrator. It was clearly held that it is the State Commis~ion or
C its nominee under Section 86(1 )(f) of the Electricity Act, 2003
  and not the Chief Justice cir his nominee under Section 11 of
  the Arbitration and Conciliation Act, 1996 who will have the
  authority to appoint an arbitrator if it decides to refer the
  disputes to arbitration. This Court further clarified that except
0
  the power of appointing arbitrator getting shifted to the State
  Commission, conduct of arbitration even under Section 86(1 )(f)
  of the Electricity Act would be governed by provisions of the
  Arbitration and Conciliation Act, 1996. Only in cases of conflict
E the Electricity Act would prevail.

         6. In view of law settled by the judgment in the case of
   Gujarat Urja (supra), the Arbitration Application No.31 of 2004
   was closed by the High Court on 18.3.2009 with liberty to M/s.
 F LANCO to approach the Commission under Section 86(1 )(f)
   of the Elec~ricity Act. M/s. LANCO filed O.P.No.33 of 2009
   before the Commission on 5.6.2009 to claim capacity charges
   on the basis of bills raised from 15.9.2000 onwards to
   11.1.2001. The appellants resisted the claim inter a/ia on the
 G ground of limitation. The appellants preferred a specific
   application for rejecting the O.P.No.33 of 2009 on the ground
   of limitation. M/s. LANCO preferred a reply in which Section
   14 of the Limitation Act was invoked for seeking exclusion of
   time when the arbitration proceeding had remained pending
 H with the High Court in the form of Arbitration Application No.31
   A.P. POWER CCORDINATION COMMITTEE v. LANGO                   463
    KONDAPALLI POWER LTD. [SHIVA KIRTI SINGH, J.]

of 2004. The Commission rejected the claim by order dated A
13.6.2011 on the ground of limitation by holding that the time.
spent in the arbitration proceedings did not merit exclusion
under Section 14 of the Limitation Act because it had not been
pursued in good faith. M/s. LAN CO preferred Appeal No.129
of 2011 before APTEL. That appeal was allowed by the B
impugned judgment presently under appeal, dated 2.7.2012.
APTEL reversed the findings of the Commission on the issue
of limitation and directed the Commission to pass appropriate
follow up order on the actual claims and interest.
                                                                 c
        7. So far as claim of M/s. LAN CO for reimbursement of
 MAT for various periods is concerned, the claim for the period
2001-2005 was rejected by the Commission on the ground of
limitation but it got revived on account of common appellate
order by APTEL dated 2.7.2012 and after the remand only a D
consequential order is required to be passed by the
Commission. For other periods, the claim for reimbursement
of MAT has been allowed in favour of M/s. LANCO. The
Commission allowed the claim for the periods 2006-2009 and
2009-2012 on account of its earlier order in respect of similar E
claim in another case which elicited a concession by the
counsel for the appellants, although in the written statement
before the Commission the appellants had seriously contested
such claim on merits. It is contended by Mr. V. Giri, learned F
senior counsel for the appellant that the concession was
misconceived and unauthorized. Learned senior counsel for
M/s. LANCO, Mr. Sundaram, fairly conceded that the issue
relating to claim for reimbursement of MAT may be heard and
decided by us on merits and accordingly the parties have been G
heard in detail on the merits of such claim for the entire period,.
i.e., from 2001to2012. But in case the claim of MATfor2001-
2005 is held by us to be barred by limitation, it will not be
considered on merits.
                                                                 H
464        SUPREME COURT REPORTS                  [2015] 12 S.C.R.


A        8. Appearing for the appellants, learned senior advocate
  Mr. V. Giri pointed out that in the impugned on;ler under appeal
  APTEL has not considered the claim of capacity charges on
  merits and therefore this Court is not required to go into facts
  for deciding the merits of bills for capacity charges. On the
B issue of limitation he contended that there was no issue raised
  before the Commission that bar of limitation as per Limitation
  Act is not applicable to the proceedings before the
  Commission. He referred to the arguments advanced on
  behalf of Mis. LAN CO before APT EL to highlight that even in .
C appeal it claimed exclusion of time spent in arbitration
  proceedings under Section 14(2) of the Limitation Act and
  hence this Court should not allow Mis. LANCO to now urge
  that the Limitation Act cannot apply and hence there will be no
  bar of any limitation in preferring a claim before the State
0
  Commission. We have noticed that in para 28 of the judgment
  under appeal APTEL has noted that the appellant no.1 (M/s.
  LANCO) does not seriously dispute the fact that the Limitation
  Act would be applicable to the present case. But learned
E counsels have conceded that the issue whether Limitation Act
  is applicable or not is one of law and accordingly the parties
  have advanced detailed submissions on this issue. Hence
  we propose to consider these submissions also.

 F         9. From the above stand of the parties, the following
      issues emerge for our consideration and adjudication :-

           (i) Whether the Limitation Act, 1963, particularly Section
           3 and the Schedule will apply to any action instituted
           before the Commission under Section 86(1)(f) of the
G          Electricity Act, 2003?

           (ii) Whether the impugned order passed by APTEL
           permitting application of principles emerging from
           Section 14 of the Limitation Act, is against Law so as to
H          warrant interference?
   AP. POWER COORDINATION COMMITTEE v. LANCO                        465
     KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

     (iii) And whether on merits the claim for reimbursement        A
     of MAT is in contravention of relevant terms and
     conditions of the Power Purchase Agreement (PPA)?

     10. At this juncture, relevant provisions or articles of PPA
need to be noticed. They are as follows:                            B

     "Article 3.8 - Claims for Taxes on Income

       Any advance Income tax payable for the Project in any
     month supported by a certificate of a chartered
     accountant approved by the Board (such approval not to         C
     be unreasonably withheld or delayed) shall be
     reimbursed by the Board. After the tax assessment is
     completed for any year: and the liability thereon is
     determined by the taxation authorities in India, the excess
                                                                    0
     or shortfall in the tax liability so determined will be
     adjusted in the supplementary bill (as defined in Article
     5.5) for the succeeding month or on the due date of
     paymentthereof, whichever is later, subject to Article 3.9.
     Tax to be reimbursed will be calculated on the income          E
     from the project only, and calculated on the assumption
     that the Company is engaged solely in the ownership,
     design, financing, construction, operation and
     maintenance of the Project and will not include tax
     reimbursements of the previous year.                           F

     5.5.     - Supplementary Bills

     For payments due to the Company for reimbursement of
     taxes on income, incentives or taxes and duties levied
     on generation and/or sale of electricity, payments for G
     periods of political Force Majeure affecting either Party
     or Non-Political Force Majeure affecting tile Board or
     any other adjustments or payments due to the Company
     hereunder, the Company shall present a supplementary H
466   SUPREME COURT REPORTS                     [2015] 12 S.C.R.


A     bill, in such form as may be mutually agreed upon by the
      Board and the Company, (duly supported by supporting
      data). Each supplementary bill shall be payable by the
      Board on the Due Date of Payment, except in case of
      supplementary bill for taxes on income. At least thirty
B     (30) days prior to the date when income tax is required
      to be paid by the Company, the Company shall submit to
      the Board a supplementary bill for the same. This bill
      shall be payable by the Board within twenty-five (25) days
      of its presentation to the Board by the Company or at
c     least five (5) days before the date on which the tax is
      required to be paid by the Company, whichever is later.

      5.7      - Billing Disputes

D     Notwithstanding any dispute as to all or any portion of
      any bill submitted by the company to the Board, the Board
      shall pay the full amount of the bill provided that the amount
      of the bill is based on (a) a meter reading that has either
      been signed by both Parties or certified by the Company
E     with respect to the Board's refusal to sign within three
      (3) days of the meter reading date and (b) the provisions
      of this Agreement. The Board shall notify the Company
      of any disputed alllount, and the Company shall rectify
      the defect or otherwise notify its rejection of the disputed
 F    amount, with reasons, within five (5) days of the reference
      by the Board, falling agreement on which the provisions
      of Article 14 shall apply with respect thereto. If the
      resolution of any dispute requires the Company to
      reimburse the Board, the amount to be reimbursed shall
G     bear interest at the Working Capital Rate applicable to
      the Board from the date of payment by the Board to the
      date of reimbursement. The Board may not dispute any
      amount after sixty (60) days following the Due Date of
      Payment therefor.
H
A.P. POWER COORDINATION COMMITTEE v. LANGO                         467
 KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

 11.1     - Definition of Law                                      A
 For the purposes of this Agreement, "Law" means the
 constitution of India and any act, rul~, regulation, directive,
 notification, order or instruction having the force of Law
 enacted or issued by any competent legislature, or                8
 Government Agency.

 11.2     - Definition of Change in Law

 For the purposes of this agreement, "Change in Law"
 means                                                             c
 (i) any enactment or issue of any new Law,

 (ii) any amendment, alteration, modification or repeal of
 any existing Law or any new or modified directive or
 order thereunder,                                         D

 (iii) any change in the application or interpretation of any
 Law by a competent legislature or GovernmentAgency
 in India which is contrary to the existing accepted
 application or interpretation thereof, in each case coming        E
 into effect after the date of this Agreement, provision for
 which has not been made elsewhere in the Agreement.

 11.4 - Additional/Reduced Expenditures or Other
 Increased/Reduced Costs due to a Change in Law                    F
 or Change in Permits

 (a) Within sixty (60) days after the COD of the first
 Generating Unit or the end of any Tariff Year, the Company
 shall determine after accounting for the net economic G
 effects on the Company during the period prior to the
 COD of the first Generating Unit or, as the case may be,
 such Tariff Year of any Changes in Law or Cha.nges in
 Permits, based on an accounting conducted by an
 independent chartered accountant reasonably H
468   SUPREME COURT REPORTS                   [2015] 12 S.C.R.


A     acceptable to the Board. If as a result of such accounting,
      the company suffers an increase in costs or a reduction
      in after-tax cash flow or any other net economic burden
      which it would not nave experienced but for such changes
      in Law or Changes in Permits (taking into account the
B     reasonable costs offinancing of any capital improvement
      in the period prior to the COD of the first Generating Unit
      or, as the case may be, such Tariff Year), the aggregate
      economic affect of which exceeds the equivalent of
      Rupees three (3) crores per 100 MW or pro-rata for any
c     part thereof during the period prior to the COD of the
      first generating unit and Rupees one (1) crore per 100
      MW or pro-rata for any part thereof during the period after
      the COD of the first Generating Unit, during any Tariff
      Year (excluding cost adjustments in respect of Changes
D
      in Law or Changes in Permits from any prior period), the
      Company may notify the Board of any proposed
      amendments to this Agreement required to put the
      Company in the same economic position it would have
 E    occupied in the absence of such cost increase reduction
      in the net after-tax cash flow or any other economic
      burden. Such notice shall be accompanied by a
      certification of the Company's independent chartered
      accountant and a reasonably detailed explanation of
 F    certification of any officer of the Company respecting the
      basis for such net economic burden increase. The
      amount of an net economic burden claimed by the
      Company shall be net of any insurance proceeds
      received in respect thereof.
G
      (b) Within sixty (60) days after the COD of the first
      Generating Unit or the end of any Tariff Year, if after
      accqunting as provided in subsection (a) for the net
      economic effects on the Company during the period prior
 H    to the COD of the first Generating Unit or as the case
A.P. POWER COORDINATION COMMITTEE v. LANCO                         469
 KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

   may be, such tariff year of any changes in law or               A
   Changes in Permits, the Company experiences a
   reduction in costs or an increase in after-tax cash flow or
   any other net economic benefit which it would not have
   experienced but for such Changes in Law or Changes in
   Permits, the aggregate economic effect of which                 B
   exceeds the equivalent of Rs.3 crore per 100 MW or pro-
   rata for any part thereof during the period prior to the
   COD of the first Generating Unit or Rupees one (1) crore
   per 100 MW or pro-rata for any part thereof, following
   the COD of the first Generating Unit, during any tariff Year,   C
   the Company shall provide to the Board results of such
   accounting together with a certificate of the Independent
   chartered accountant and the Board, in response thereto
   may notify the company of any proposed amendments               D
   to this Agreement required in its good faith judgment to
   put the Company in the same economic position it would
   have occupied in the absence of such cost reduction,
   increase in the net after-tax cash flow or any other
   economic benefit. Such notice shall be accompanied              E
   by a reasonably detailed explanation of a certification of
·. an officer of the Company respecting the basis for such
   decrease.

 (c) Only increased costs which are necessarily and F
 unavoidably incurred in complying with or as a direct result
 of the Changes in Law or Changes in Permits taking into
 account, all reasonable steps which may be taken by the
 Company to minimize such increased costs, shall be
 considered as increased costs for the purposes of this G
 Article.

 (d) As soon as practicable during the period prior to the
 COD of the first Generating Unit or any Tariff Year after
 the Company becomes aware of any Change in Law or H
470   SUPREME COURT REPORTS                   [2015] 12 S.C.R.


A     Change in Permits which could reasonably be expected
      to give rise to an increase/reduction in costs or reduction/
      increase in after-tax cash flow pursuant to paragraph (a)
      and (b), the Company shall provide an interim notice
      thereof to the Board describing, to the extent possible,
 B    the expected effect on the costs and the cash flow of the
      Company. The Company shall consult with the Board
      regarding such increased expenditures and the
      Company shall use all reasonable efforts to implement
      the Board's recommendations, if any, to minimize such
c     increased expenditures consistent with Prudent Utility
      Practices and the Company's obligations under this
      Agreement. If prior to the end of any Tariff year the
      Company demonstrates on the basis of a certification of
      its chartered accountant that any Change in Law or
 D
      Change in Permits would result in the Company's being
      unable to meet its payment obligations to its lenders under
      the Financing Documents on a current basis, then in
      addition to the Company's right under sub-section (a)
 E    but notwithstanding the time period for exercising such
      rights specified therein, the Company shall be entitled to
      propose amendments to this Agreement as provided in
      sub-section(a) and the Parties shall consider such
      proposal as provided in subsection (e) below, provided
 F    that any benefits which the Company is eligible to receive
      under subsection (a) shall be reduced by any benefits
      received by the Company prior to the end of the relevant
      period under this subsection.

G     (e) Within thirty (30) days after receiving any proposal
      pursuant to paragraph (a), (b) or (d), the Parties shall
      meet and agree on either amendments to this Agreement
      or alternative arrangements to implement the foregoing.
      If no such agreement has been reached within ninety (90)
H     days after any meeting pursuant to Article 11.3(a), (b) or
A.P. POWER COORDINATION COMMiTTEE v. LANGO                      471
  KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

   (d), as the case may be, the proposals of the Parties        A
 . shall be submitted to the Independent chartered
   accountant referred to in paragraphs (a), (b) and (d), as
  the case may be.

 14.1      - Informal Dispute Resolution                        B
 (a) Each Party shall designate in writing to the other Party
 a representative who shall be authorized to resolve any
 dispute arising under this Agreement in an equitable
 manner.                                                        c
 (b) If the designated representatives are unable to resolve
 a dispute under this Agreement within fifteen (15) days,
 such dispute shall be referred by such representatives
 to a senior officer designated by the Company and a
                                                                0
 senior officer designated by the Board, respectively, who
 shall attempt to resolve the dispute within a further period
 of fifteen (15) days.

 (c) The Parties hereto agree to use their best efforts to
 attempt to resolve all disputes arising hereunder              E
 promptly, equitably and in good faith, and further agree
 to provide each other with reasonable access during
 normal business hours to any and all non-privileged
 records, information and data pertaining to any such           F
 dispute.

 14.2      -Arbitration

 (a) In the event that any dispute is not resolved between
 the Parties pursuant to Article 14.1, then such disputes G
 shall be settled exclusively and finally by arbitration. It is
 specifically understood and agreed that any dispute that
 cannot be resolved oetween the Parties, including any
 matter relating to the interpretation of this Agreement,
 shall be ·submitted to arbitration irrespective of the H
472         SUPREME COURT REPORTS                    [2015] 12 S.C.R.


A          magnitude thereof, and the amount in dispute or whether
           such dispute would otherwise be considered justiciable
           or ripe for resolution by any court or arbitral tribunal. This
           Agreement and the rights and obligations of the Parties
           hereunder shall remain in full force and effect pending
 B         the award in such arbitration proceedings, which award
           shall determine whether and when termination of this
           Agreement if relevant shall become effective."

              11. Although, we were taken through various other
C     Articles of PPA but it is not imperative to reproduce all such
      provisions. Article 3.1 provides for capacity charge which is
      required to be computed as per Article 3.2 and is meant to be
      paid by the Board. This is in respect of the Cumulative
      Available Energy provided by the Project in respect of any tariff
D     year, upto (but not exceeding) an amount calculated on the
      basis of Prescribed Plant Load factor. Since the issue of
      capacity charge is not required to be addressed by us on
      merits, further details need not detain us. Clause 3.8 has
      been read over again and again because it is of immense
E     significance in deciding the issue relating to MAT. Article 5
      contains various sub-articles relating to billing and payment.
      They provide for monthly tariff bills which are payable by the
      Board or the licensee on the Due Date of Payment. The
 F    supplementary bills are covered by Article 5.5. They cover
      different items and are required to be supported by supporting
      data. Such bills are also payable on the Due Date of Payment,
      except the supplementary bill for taxes on income which is to
      be submitted at least 30 days prior to the time when the income
G     tax is required to be paid by the generating company. Such
      bill is payable by the Board within 25 days of presentation or
      at least 5 days before the date on which the tax is required to
      be paid by the company, whicheveJ is later.
        12. Article 5.7 relates to billing disputes and it refers to
H the provisions of Article 14 which governs Arbitration including
   A.P. POWER COORDINATION COMMITTEE v. LANCO                       473
     KONDAPALLI POWER LTD. [SHIVA KIRT! SINGH, J.)

Informal Dispute Resolution. Article 11 caters to the effects of    A
Change in L~w 1Jpon the rights and liabilities of the parties.
This has assumed relevance in the present context on account
of stand taken by the appellant that MAT does not fall under
Article 3.8 governing claims for Taxes on Income but under
Article 11.4 which provides an altogether different procedure       B
for making claim for additional costs by the company on
account of any Change in Law etc. In this contex· it may usefully
be noted that Article 1 of PPA contains definitions fo.r the
purposes of the agreement. Article 1.2 adopts definition of
several terms as defined in the Indian Electricity (Supply Act)     C
1948 and set out in Schedule B to the Agreement. Article 1.4
contains various general provisions such as - unless the context
otherwise requires, the singular shall include plural etc. and
vice versa and that " ....... a reference to any Law shall be
                                                                    0
construed as a reference to such Law as from time to time
amended or re-enacted."

      13. Mr. Giri drew our attention to various provisions of
the Electricity Act, 2003 particularly to Section 86 providing
for various functions of a State Commissi·on which include the      E
function under clause (f) in Sub-Section (1) empowering the
Commission fo "adjudicate upon the disputes between the
licensees and generating companies and to refer any dispute
for arbitration." He also referred to Section 94 which vests the    F
Commission, for purposes of any inquiry or proceedings under
this Act, with same powers as are vested in Civil Court under
the Code of Civil Procedure, 1908 in respect of various matters
such as summoning and enforcing the attendance of any
person and examining him on oath; discovery and production          G
of any document etc; receiving evidence on affidavit;
requisitioning of any public record; issuing commission forthe
examination of witnesses; reviewing its decisions, directions
and orders; and any other matter which may be prescribed by
the Commission. The Commission shall also have powers to            H
474          SUPREME COURT REPORTS                    (2015] 12 S.C.R.


A pass suitable interim order and authorize any suitable person
   to represent the interest of the consumers in the proceedings
  ,before it. Section 95 declares that all proceedings before the
   Commission shall be deemed to be judicial proceedings within
   the meaning of Sections 193 and 228 of the Indian Penal Code
B and it shall be deemed to be a Civil Court for the purposes of
   Sections 345 and 346 of the Code of Criminal Procedure,
   1973. Section 158 is a solitary provision in Part XVI which
   provides for arbitration under the heading "Dispute Resolution".
   According to Section 158, any matter directed to be
C determined by Arbitration, unless there is expressed provision
   to the contrary in the license of a licensee, shall be determined
   by such person or persons as the Commission may nominate
   in that behalf on the application of either party; but in all other
D respects the Arbitration shall be subject to the provisions of
   the Arbitration and Conciliation Act, 1996.

             14.0n the basis of powers and functions of the
      Commission highlighted above and on account of law declared
      in Gujarat Urja (supra) as well as in Tamil Nadu Generation
E     & Distribution Coipn. Ltd. v. PPN Power Generating Co.
      (P) Ltd., (2014) 11SCC53, the contention of Mr. Giri is that in
      discharge of its functions to adjudicate all disputes between
      the licensees and generating companies and/or in referring a
F     dispute to arbitration under Section 86(1 )(f) of the Electricity
      Act, the Commission deserves to be treated as a substitute
      and therefore equivalent of civil court for the purpose of
      attracting the bar of limitation provided under the Limitation
      Act, 1963. According to him the law laid down by this Court
G     that Limitation Act applies only to civil courts in the strict sense
      of the term requires reconsideration in an appropriate case
      but in the present matter, since in the case of PPN Power
      Generating Co. (P) Ltd.(supra) it has been categorically held
      that the State Commission discharges judicial functions and
H     judicial power of far reaching effect and has essential trapping
    A.P. POWER COORDINATION COMMITTEE v. LANGO                            475
      KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

of the Courts, the same should be sufficient to make the A
Limitation Act applicable to petitions or applications that come
before the Commission requiring adjudication even of matters
arising purely out of contract like in the present case and not
from the statutory provisions of the Electricity Act. He also
advanced a supplementary or alternative submission that there B
is nothing in the Electricity Act, 2003 to restore to any party the
right to sue for a cause which has already become barred by
law of Limitation, rather under the mandate of Section 175 of
the Electricity Act, the Limitation Act has to be given full respect
as a law for the time being in force unless any provision of the C
Limitation Act is found to be inconsistent with the Electricity
Act. Only in a situation of conflict, the electricity Act will have a
superior or overriding force by virtue of Section 174 of the
Electricity Act.
                                                                      D
       15. Yet another submission of Mr. Giri is that the matter
does not attract Section 2(4) oftheArbitration and Conciliation
Act, 1996 (for brevity 'Arbitration Act') rather Section 43 of the
Arbitration Act shall govern the rights of the parties and it
mandates that the Limitation Act, 1963 shall apply to arbitrations·       E
as it applies to proceedings in courts. It may however be noted·
here that in the case of PPN Power Generating Co. (P) Ltd.
(supra) in para 65, the Court held that the Limitation Act would
not be applicable in such matters for various reasons including           F
Section 2(4) of the Arbitration Act which was extracted to
highlight that sub-section (1) of Section 40, Sections 41 and
43 all in Part I of the Arbitration Act, would not apply to arbitration
under any other enactment. Only rest of the Limitation Act
would be applicable to the extent not inconsistent with the other         G
enactment or any Rule made thereunder. On that basis in
Paragraph 66 it was held that the provisions with regard to
Limitation Act under Section 43 of the Arbitration Act would
not be applicable to statutory arbitrations conducted under the
Electricity Act, 2003.                                                    H
476         SUPREME COURT REPORTS                   [2015] 12 S.C.R.


A            16. In fairness to the submission of Mr. Giri, it is noted
      that in the PPN Power Generating Co. (P) Ltd.(supra), in
      Paragraphs 64 and 68, this Court was satisfied on facts itself
      that the principle of delay and !aches was not attracted. Further,
      the provisions in the PPA in that case provided that the seat of
 B    Arbitration shall be in London and that alone made part I of the
      Arbitration Act inapplicable to the arbitration proceeding and
      ruled out applicability of Section 43 also.

             17. Mr. Giri has placed considerable reliance upon a
C     jt,Jdgment by three Judges of this Court in State of Kera la v.
      V.R. Kalliyanikutty (1999) 3 SCC 657. The question of law
      in that case was whether a debt which is barred by the law of
      limitation can be recovered by resorting to recovery
      proceedings under the Kera la Revenue Recovery Act of 1968.
D     The High Court held that in the absence of any provision in the
      aforesaid Kerala Act creating a substantive right to recover
      time barred debts, such debts could not be recovered through
      the summary proceedings under that Act. As per Section 71
      of the Kerala Act the Government could issue a notification
 E    making the provisions of the Act applicable to the recovery of
      "amounts due" from any person or class of persons to any
      specified institution or any class of institutions. The say of
      State Government and the State Financial Corporation was
      that the words "amounts due" will encompass time barred claims
 F
      also. This Court placed reliance upon judgment of the Privy
      Council in the case of Hans Raj Gupta v. Dehra Dun-
      Mussoorie Electric Tramway Co. Ltd. AIR 1933 PC 63. It
      found that the Kerala Act did not create any new right rather it
G     only provided a process for speedy recovery of moneys due.
      Therefore the person claiming recovery cannot claim amounts
      which are not legally recoverable nor can a defence of limitation
      available to a debtor in a suit or other legal proceeding be
      taken away under the provisions of the Kera la Act. The State
 H    supported its stand by highlighting the settled legal principle
    A.P. POWER COORDINATION COMMITTEE v. LANCO                    477
      KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

  that the statute of limitation merely bars the remedy without A
  touching the right. But such submission did not cut any ice.
·Relevant provisions of the KeralaAct led to a conclusion that ·
. although the necessity offiling a suit stood avoided, the claim
  which could be legally recovered was not enlarged. In para 16
  this Court concluded thus:                                      B

      " ......... An Act must expressly provide for such
     ·enlargement of claims which are legally recoverable,
      before it can be interpreted as extending to the recovery
      of those amounts which have ceased to be legally C
      recoverable on the date when recovery proceedings are
      undertaken ...... "

        In fact this Court looked to the scheme of the Kerala
Act to come to a conclusion that "amounts due" are those          o
amounts which the creditor could have recovered had he filed
a suit.

      18. It is noteworthy that besides drawing relevant
inference from the provisions of the Kera la Act, in paragraph    E
11 the Court acted cautiously in interpreting the words
"amounts due" in view of Article 14 of the Constitution. It
expressed its views thus :

      " ..... Moreover, such a wide interpretation of "amounts F
      due" which destroys an important defence available to a
      debtor in a suit against him by the creditor, may attract.
      Article 14 against the Act. It would be ironic if an Act for
      speedy recovery is held as enabling a creditor who has
      delayed recovery beyond the period of limitation to G
      recover such delayed claims."

      In para 12 the Court referred to and relied upon judgment
in the case of New Delhi Municipal Committee v. Kalu
Ram (1976) 3 SCC 407 wherein this Court had similarly             H
478         SUPREME COURT REPORTS                      [2015] 12 S.C.R.


A interpreted Section 7 of the Public Premises (Eviction of
   Unauthorised Occupants) Act, 1958. The words "arrears of
 . rent payable" were given a limited meaning by holding thus:

           " ..... In the context of recoverY of arrears of rent under
 B         Section 7, this Court said that if the recovery is barred
           by the law of limitation, it is difficult to hold that the Estate
           Officer could still insist thatthe said amount was payable.
           When a duty is cast on an authority to determine the
           arrears of rent the determination must be in accordance
C          with law. .... "

                                                     (emphasis added)

            19. Mr. Giri referred to paragraphs 98 and 99 of the
      judgment in the case of Kihoto Hollohan v. Zachillhu 1992
0
      Supp. (2) SCC 651 to highlight the attributes of a "Court" and
      those of a Tribunal and also the relevant tests which led the
      court to hold that the Speaker while deciding certain disputes
      is a Tribunal. Similarly in the case of Thakur Jugal Kishore
E     Sinha v. Sitamarhi Central Co-operative Bank Ltd. 1967
      (3) SCR 163, this Court held that the Assistant Registrar of
      Co-operative Societies was a court within the meaning of the
      Contempt of Courts Act, 1952. This inference was based on
      the pronounced view that the subordination for the purpose of
 F    Section 3 of the Contempt of Courts Act means judicial
      subordination under the constitutional provisions and not
      subordination under the usual hierarchy of courts as per Civil
      Procedure Code or the Criminal Procedure Code. The next
      case in this series is that of Brajnandan Sinha v. Jyoti
G     Narain AIR 1956 SC 66. In this case it was found that the
      Commissioner appointed under the Public Servants (Inquiries)
      Act 1850 (Act 37 of 1850) is not a court within the meaning of
      the term under Section 3 of the Contempt of Courts Act. This
      view found favour largely because the Commissioner did not
H     have the legal capacity under that Act to deliver "definitive
   A.P. POWER COORDINATION COMMITTEE v. LANGO                        479
    KONDAPALLI POWER LTD. [SHIVA KIRTI SINGH, J.)

judgment". Mr. Giri has however sought to highlight paragraphs A
 14 to 18 of the judgment which deal with the essential attributes
of a Tribunal so as to clothe it with the status of a court. Those
paragraphs are as follows :

     "(14) The pronouncement of a definitive judgment is thus B
     considered the essential 'sine qua non' of a Court and
     unless and until a binding and authoritative judgment can
     be pronounced by a person or body of persons it cannot
     be predicated that he or they constitute a Court.
                                                                     c
     (15) The Privy Council in the case of 'Shell Co. of Australia
     v. Federal Commissioner of Taxation', 1931AC275 (A)
     thus defined 'Judicial Power' at p.295:

        'Is this right? What is 'Judicial power'? Their
                                                                     0
        Lordships are of opinion that one of the best definitions
        is that given by Griffith C.J. in - 'Huddart, Parker &
        Co. v. Moorehead', (1909) 8 CLR 330 at p.357 (B)
        where he says: 'I am of opinion that the words 'judicial
        power' as used in S.71 of the Constitution mean the E
        power which every sovereign authority must of
        necessity have to decide controversies between its·
        subjects, or between itself and its subjects, whether
        the rights relate to life, liberty or property. The exercise
        of this power does not begin until some tribunal which F
        has power to give a binding and authoritative decision
        (whether subject to appeal or not) is called upon to
        take action'.

     Their Lordships further enumerated at p.297 certain G
     negative propositions in relation to this subject:

        '1. A tribunal is not necessarily a Court in this strict
        sense because it gives a final decision;

        2. Nor because it hears witnesses on oath;                   H
480    SUPREME COURT REPORTS                   [2015] 12 S.C.R.


A        3. Nor because two or more contending parties
         appear before it between whom it has to decide;

         4. Nor because it gives decisions which affect the
         rights of subjects;
B
         5. Nor because there is an appeal to a Court;

         6. Nor because it is a body to which a matter is
         referred by another body.

C     See 'Rex v. Electricity Commissioners' 1924-1 KB
      171(C)'

      and observed at page 298:

         'An administrative tribunal may act judicially, but still
D
         remain an administrative tribunal as distinguished from
         a Court, strictly so-called. Mere externals do not make
         a direction to an administrative officer by an ad hoc
         tribunal an exercise by a Court of judicial power.'
E     ( 16) The same principle was reiterated by this Court in -
      'Bharat Bank Ltd. v. Employees of Bharat Bank Ltd.',AIR
       1950 SC 188 (D); and - 'Meqbool Hussain v. State of
      Bombay', AIR 1953 SC 325 (E), where the test of a
      judicial tribunal as laid down in a passage from - 'Cooper
F
      v. Willson', 1937-2 KB 309 (F) at p.340, was adopted by
      this Court:

        'A true judicial decision presupposes an existing
        dispute betyveen two or more parties, and then
G       involves four requisites: - (1) The presentation (not
        necessarily orally) of their case by the parties to the
        dispute, (2) ifthe dispute between them is a question
        of fact, the ascertainment of the fact by means of
        evidence adduced by the parties to the dispute and
H
   A.P. POWER COORDINATION COMMITTEE v. LANCO                  481
     KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

        often with the assistance of argument by or on behalf A
        of the parties on the evidence; (3) if the dispute
        between them is a question of law, the submission of
        legal arguments by the parties; and (4) a decision
        which disposes of the whole matter by a finding upon
        the facts in dispute and an application of the law of B
         '         .
        the land to the facts so found, including where required
        a ruling upon any disputed question of law'.

     (17) 'Maqbool Hussain's case (E)', above referred to,
     was followed by this Court in - 'S.A. Venkataraman v. C
     Union of India', AIR 1954 SC 375 (G), where a
     Constitution Bench of this Court also laid down that both
     finality and authoritativeness were the essential tests of
     a judicial pronouncement.
                                                                D
     (18) It is clear, therefore, that in· order to constitute a
     Court in the strict sense of the term, an essential condition
     is that the Court should have, apart from having some of
     the trappings of a judicial tribunal, power to give a
     decision or a definitive judgment which has finality and E
     authoritativeness which are the essential tests of a
     judicial pronouncement."

       20. On behalf of appellants reliance was next placed upon
case of P. Sarathy v. State Bank of India (2000) 5 SCC F
355. A Bench of two Judges considered the scope of the word
"Court" occurring in Section 14 of the Limitation Act and held
that any authority or tribunal having trappings of a court is
covered because "Court" does not necessarily have to be a
civil court. On such reasonings the appellate authority under G
Section 41 of Tamil Nadu Shops and Establishments Act was
held to be a court. One must notice here only that the judgment
in the case of P. Sarathy (supra) has been considered in a
recent judgment of this Court rendered by a Bench of two
Judges in the case of M.P. Steel Corporation v. H
482         SUPREME COURT REPORTS                  [2015] 12 S.C.R.


A      Commissioner of Central Excise (2015) 7 SCC 58. In this
       case it was held that although the Limitation Act including
       Section 14 thereof would not apply to appeals filed before a
      quasi-judicial tribunal such as the Collector (Appeals)
       mentioned in Section 128 of the Customs Act, 1962 but the
 B     principles underlying Section 14 of the Limitation Act would
       nevertheless apply as they advance the cause of justice. The
      Court repelled the submission that Section 128 of the Customs
      Act excludes the application of the principles underlying
       Section 14 of the Limitation Act. In order to reach the
C      conclusion that only principles underlying Section 14 and not
      the very Section itself can apply to tribunals having attributes
      of Court, in M.P. Steel Corporation (supra) the Court
      analysed the precedents and the Limitation Act 1963. It
      concluded that a quasi-judicial Tribunal will suffer Limitation
0
      Act only as per the statutory scheme under which it is created
      and functions. On the other hand, on its own the Limitation Act
      is applicable in respect of proceedings before courts proper,
      i.e., courts as understood in the strict sense of being part of
E     the Judicial Branch of the State. In support of this principle
      several judgments of this Court were noted such as a three-
      Judge Bench judgment in Commissioner of Sales T~x v.
      Parson Tools and Plants (1975)4 SCC 22 in which reliance
      was placed upon Ujjam Bai v. State of U.P. AIR 1962 SC
F      1621. For the same purpose reliance was also placed upon
      judgment in the case of Jagannath Prasad v. State of U.P.
      AIR 1963 SC 416. A contrary view taken by a two-Judge Bench
      in the case of Mukri Gopalan v. Cheppilat Puthanpurayil
      Aboobacker (1995) 5 SCC 5 was therefore held to be at
G     variance with at least five earlier binding judgments and also
      at odd with a lclter judgment in the case of Consolidated Engg.
      Enterprises v. Irrigation Deptt. (2008) 7 SCC 169. The latter
      judgment was considered in detail because the three-Judge
      Bench examined the provisions of the Arbitration and
H     Conciliation Act 1996 and held that provisions of Section 14
   A.P. POWER COORDINATION COMMITTEE v. LANCO                     483
     KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

of the Limitation Act 1963 would be applicable to an A
application under Section 34 of the 1996 Act filed before a
Civil Court for setting aside an Arbitral Award. This view in
Consolidated Engg.(supra) has been further clarified by
Ravindran, J. (as he then was) in his separate but concurring
judgment, particularly in paragraph 44.                       B

      21. In an attempt to shJwthatthe word "Court" has been
interpreted differently in context of different statutes, Mr. Giri
referred to the case of Trans Mediterranean Airways v.
Universal Exports (2011) 10 SCC 316. In paragraphs 44 C
and onwards a number of precedents were noticed as to the
meaning and interpretation of the word "Court" and in paragraph
57 it was held that the word "Court" in Rule 29 of the Second
Schedule of the Carriage by Air Act 1972 has been borrowed
from the Warsaw Convention and had not been used in the D
strict sense as used in the procedural laws of this country. The
word "Court" was, therefore, held to include the consumer
forums. In para 58 it was. reiterated that in legislations like the
Consumer Protection Act the word "Court" cannot be given a
strict meaning.                                                     E

     22. In reply on this issue, learned senior advocate Mr.
Sundaram took a frontal stand that Limitation Act does not
apply to a proceeding before the Commission because it is
not a court stricto-sensu. For this proposition he relied upon F
judgments in the case of PPN Power Generating Co. (P)
Ltd. (supra) and M.P. Steel Corporation (supra). He however
floated a suggestion that even when no period of limitation is
app!icable for initiating action before the Commission, if this
Court finds it nec~ssary and in the interest of justice, then a G
reasonable period may be indicated by this Court for the
aforesaid purpose. He hastened to add that such reasonable
period can only be as an illustration and not as a fixed period.
According to him, a reasonable illustrative period indicated H
484         SUPREME COURT REPORTS                     [2015] 12 S.C.R.



A     by the court, in practical application, can vary from case to
      case as per facts of each case. He also contended that even
      if a definite limitation period is found to be attracted, in view of
      law laid down clearly in M.P. Steel Corporation (supra), the
      principles underling Section 14 will be applicable and the same
 B    has been rightly applied by APTEL while rendering the
      impugned order under appeal.

           23. Mr. Sundaram referred to PPN Power Generating
      Co. (P) Ltd. (supra) and placed reliance upon a solitary
C     sentence at the end of paragraph 64 which reads thus :

            "In any event, the Limitation Act is inapplicable to
            proceeding before the State Commission."

            He also placed reliance upon paragraph 65 which is as
0
      follows:

           "65. The submission of the appellant that the Limitation
           Act would be available in case the reference was to be
           made to arbitration, in our opinion, is also without merit.
E          Firstly, the State Commission exercised its jurisdiction
           to decide the dispute itself. The matter was not referred
           to arbitration, therefore, the Limitation Act would not be
           applicable. Secondly, Section 43 of the Arbitration and
           Conciliation Act would not be applicable even if the
F
           matter was referred to arbitration by virtue of Section 2(4)
           of the Arbitration Act, 1996. Section 2(4) of the Arbitration
           Act reads as under:

               '2(4) This Part except sub-section (1) of Section 40,
G              Sections 41 and 43 shall apply to every arbitration
               under any other enactment for the time being in force,
               as if the arbitration were pursuant to an arbitration
               agreement and as if that other enactment were an
               arbitration agreement, except insofar as the
H
   A.P. POWER COORDINATION COMMITTEE v.. LANCO                      485
     KONDAPALLI POWER LTD. [SHIVA KIRTI SINGH, J.]

        provisions of this Part are inconsistent with that other A
        enactment or with any rules made thereunder."

       24. Mr. Sundaram placed reliance upon judgment in the
case of M.P. Steel Corporation (supra) to support his
submission that Limitation Act applies only to courts stricto-      s
sensu and not to quasi-judicial tribunals. It may be noted here
that the matter in M.P. Steel Corporation (supra) had arisen
from proceedings under the Customs Act and hence in that
case there was no occasion to consider the issue whether the
Limitation Act is applicable to an action initiated before the      C
Commission by virtue of provisions of the Electricity Act, 2003.
However, this judgment does help the respondents to an extent
by holding that principles underlying Section 14 of the
Limitation Act will be applicable even in matters filed before a
quasi-judicial tribunal such as the Commission. But the moot        D
question remains to be answered -whether the bar of limitation
is required to be respected by the Commission on the ground
that there is no provision in the Electricity Act conferring
additional rights upon a party moving the Commission for relief
so as to claim even such reliefs which stand barr~d by limitation   E
before the Civil Court or even for-arbitral proceedings. The
other ancillary issue required to _be answered is -whether by
virtue of provisions of the Electrici~y Act 2003 the Limitation
Act has been made applicable to an action before the                F
Commission by express provision or even by necessary
intendment.

      . 25. Before answering the aforesaid two issues and then
 adverting to the question whether principles of Section 14 were
rightly applied by APTEL (in case any period of limitation is G
 held to be attracted), it will be proper to note some relevant
 contentions advanced by learned senior advocate Mr. Jayant
 Bhushan who has appeared for some of the respondents.
                                                                    H
486         SUPREME COURT REPORTS                   [2015] 12 S.C.R.


A            26. Mr. Bhushan pointed out that Commission is a
      creature of Statute and hence it cannot reject a claim on the
      ground of limitation unless limitation is found to be applicable
      by virtue of the provisions of the Electricity Act 2003. According
      to him if Limitation Act does not apply, courts cannot import
 B    limitation and the exceptional cases where this Court has
      introduced principles of delay and !aches relate to proceedings
      before quasi-judicial tribunals which are vested with
      discretionary or suo motu jurisdiction like revisional power; the
      other exception being courts having extraordinary or equity
C     jurisdiction such as writ jurisdiction vested in the High Courts
      or the Supreme Court. In support of the limited and exceptional
      applicability of principles of delay and !aches as distinguished
      from limitation, Mr. Bhushan placed reliance upon an old
      judgment of Supreme Court of United States in the case of
0
      Henry Hauenstein v. John A. Lynham 100 U.S. 483 and
      also upon extracts from Halsbury's Laws of England and a
      judgment of Chancery Division in the case of Re. Jarvis
      (Deceased) Edge v. Jarvis (1958) 2 All.ER 336. Since the
 E    principle noted above is well settled, the above authorities need
      not be discussed particularly when this Court has taken similar
      view in the case of Bombay Gas Co. Ltd. v. Gopal Shiva
       1964(3) SCR 709 and Hindustan Times Ltd. v. Union of
      India (1998) 2 SCC 242. In the latter case the issue under
 F    consideration was of delay in passing order levying damages
      under Employees Provident Funds and Miscellaneous
      Provisions Act, 1952. The Court distinguished long line of
      cases such as State of Gujarat v. Patil Raghav Natha (1969)
      2 SCC 187 and Ram Chand v. Union of India (1994) 1 SCC
G     44 by pointing out that same principles will not apply to moneys
      withheld by a defaulter when he actually holds the money in
      Trust for the beneficiaries. Paragraph 19 of that judgment
      highlights that the concerned Statute does not contain any
      provision prescribing a period of limitation either for
 H    assessment or recovery and although the moneys payable into
    A.P. POWER COORDINATION COMMITTEE v. LANCO                   487
      KONDAPALLI POWER LTD. [SHIVA KIRTI SINGH, J.)

 the Fund are for the ultimate benefit of the employees but there A
 is no provision by which the employees can directly recover
 the due amounts. The power of recovery is vested in the
 statutory authorities to be exercised in the manner provided
 by the Statute and not by way of suit.
                                                                   B
       27. Mr. Bhushan also referred to some judgments in
 support of the principle that Statute of limitation only bars a
 remedy through ordinary suit and not a remedy provided under
 a special Statute such as the Industrial Disputes Act which must
 be given effect to on the basis of various provisions contained C
therein. For this purpose he relied upon a Constitut'on Bench
judgment in the case of Bombay Dyeing & Manufacturing
 Co. Ltd. v. The State of Bombay AIR 1958 SC 328. He
 sought to explain the Constitution Bench judgment in the case
of M/s. Tilokchand and Motichand v. H.B. Munshi (1969) D
 1sec    110 by pointing out that delay and laches were held to
 be applicable to a petition under.Article 32 of the Constitution
of India for the reason that such jurisdiction was always
 recognized and held to be a discretionary one.
                                                                   E
       28. Coming back to the issues relating to limitation, in
view of law noticed above and for the reasons noted in M.P.
Steel Corporation (supra), we respectfully concur and hold
that by itself the Limitation Act will not be applicable to the
Commission under the Indian Electricity Act 2003 as the F
Commission is not a Court stricto sensu. Further stand of the
respondents that the Commission being a statutory tribunal,
cannot act beyond the four walls of the Electricity Act also does
not brook any exception. In the case of PPN Power
Generating Co. (P) Ltd. (supra) this Court examined the issue G
of limitation in a very summary manner and without referring to
the relevant provisions of the Electricity Act 2003, at the end of
para 64 it was observed in a single sentence that the Limitation
Act is inapplicable to proceeding before the State H
488          SUPREME COURT REPORTS                    [2015] 12 S.C.R.


A Commission. But in view of detailed discussion in the case of
  M.P. Steel Corporation (supra), we have held above that by
  itself the Limitation Act is inapplicable to proceeding or action
  brought before the State Commission. However, the Electricity
  Act 2003 requires a further scrutiny to find out whether by virtue
B of Section 175 of the Electricity Act or otherwise it can be
  inferred that the provisions of Limitation Act will govern or curtail
  the powers of the Commission in entertaining a claim under
  Section 86(1 )(f) of the Electricity Act. Section 175 reads thus:

C           "175. Provisions. of this Act to be in addition to and
            not in derogation of other laws. - The provisions of
            this Act are in addition to and not in derogation of any
            other law for the time being in force."

o              A plain reading of this Section leads to a conclusion
       that unless the provisions of the Electricity Act are in conflict
       with any other law when this Act will have overriding effect as
       per Section 174, the provisions of Electricity Act will not
       adversely affect any other law for the time being in force. In
E     other words, as stated in the Section the provisions of the
       Electricity Act will be additional provisions without adversely
      affecting or substracting anything from any other law which may
      be in force. Such provision cannot be stretched to infer
      adoption of the Limitation Act for the purpose of regulating the
F     varied and numerous powers and functions of authorities under
      Electricity Act 2003. In this context it is relevant to keep in view
      that the State Commission or the Central Commission have
      been entrusted with large number of diverse functions, many
      being administrative or regulatory and such powers do not invite
G     the rigours of the Limitation Act. Only for controlling the quasi
      judicial functions of the Commission under Section 86(1 )(f), it
      will not be possible to accept the contention of the appellant
      that by Section 175 the Electricity Act, 2003 adopts the
H      Limitation Act either explicitly or by necessary implication.
   A.P. POWER COORDINATION COMMITTEE v. LANCO                      489
     KONDAPALLI POWER LTD. [SHIVA KIRT! SINGH, J.]

       29. The only other weighty contention of Mr. Giri that there A
is nothing in the Electricity Act 2003 to create a right in a suitor
before the Commission to seek claims which are barred by
law of limitation merits a serious consideration. There is no
possibility of any difference of opinion in accepting that on
account of judgment of this Court in Gujarat Urja (supra) the B
Commission has been elevated to the status of a substitute
for the Civil Court in respect of all disputes b.etween the
licencees and generating companies. Such dispute need hot
arise from the exercise of powers under the Electricity Act.
Even claims or disputes arising purely out of contract like in C
the present case have to be either adjudicated by the
Commission or the Commission itself has the discretion to
refer the dispute for arbitration after exercising its power to
nominate the arbitrator. It is in view of such far reaching judicial
                                                                     0
powers vested in the Commission that in the case of PPN
Power Generating Co. (P) Ltd. (supra) this Court advised
the State to exercise enabling power under Section 84(2) to
appoint a person who is/has been a Judge of a High Court as
Chairperson of the State Commission. In such a situation it E
falls for consideration whether the principle of law enunciated
in State of Kerala v. V.R. Kalliyanikutty (supra) and in the
case of New Delhi Municipal Committee v. Kalu Ram
(supra) is attracted so as to bar entertainment of claims which
are legally not recoverable in a ~uit or other legal proceeding F
on account of bar created by the Limitation Act. On behalf of ·
respondents those judgments were explained by pointing out
that in the first case the peculiar words in the statute- "amount
due" and in the second case "arrears of rent payable" fell for
interpretation in the context of powers of concerned tribunal G
and on account of aforesaid particular words of the statute
this Court held that the duty cast upon the authority to determine
what is recoverable or payable implies a duty to determine
such claims in accordance with law. In our considered view a
statutory authority like the Commission is also required to H
490       SUPREME COURT REPORTS                  [2015) 12 S.C.R.


A determine or decide a claim or dispute either by itself or by
   referring it to arbitration only in accordance with law and thus
  Section 174 and 175 of the Electricity Act assume relevance.
  Since no separate limitation has been prescribed for exercise
  of power under Section 86(1 )f) nor this adjudicatory power of
B the Commission has been enlarged to entertain even the time
  barred claims, there is no conflict between the provisions of
  the Electricity Act and Limitation Act to attract the provisions
  of Section 174 of the Electricity Act. In such a situation on
  account of provisions in Section 175 of the Electricity Act or
C even otherwise the power of adjudication and determination
  or even the power of deciding whether a case requires
  reference to arbitration must be exercised in a fair manner
  and in accordance with law. In the absence of any provision in
D the Electricity Act creating a new right upon a claimant to claim
  even monies barred by law of limitation, or taking away a right
  of the other side to take a lawful defence of limitation, we are
  persuaded to hold that in the light of nature of judicial power
  conferred on the Commission, claims coming for adjudication
E before it cannot be entertained or allowed if it is found legally
  not reco'1erable in a regular suit or any other regular proceeding
  such as arbitration, on account of law of limitation. We have
  taken this view not only because it appears to be more just but
  also because unlike Labour laws and Industrial Disputes Act,
F the Electricity Act has no peculiar philosophy or inherent
  underlying reasons requiring adherence to a contrary view.

        30. We have taken the aforesaid view to avoid injustice
  as well as possibility of discrimination. We have already.
G extracted a part of paragraph 11 of the judgment in the case of
  State of Kerala v. V.R. Kalliyanikutty (supra) wherein Court
  considered the matter also in the light of Article 14 of the
  Constitution. In that case the possibility of Article 14 being
  attracted against the statute was highlighted to justify a
H particular interpretation as already noted. It was also observed
    A.P. POWER COORDINATION COMMITTEE l LANCO                           491
      KONDAPALLI POWER LTD. [SHIVA KIRTI SINGH, J.)

  that it would be ironic if in the name of speedy recovery             A
  contemplated by the statute, a creditor is enabled to recover
. claims beyond the period of limitation. In this context, it would
  be fair to infer that the special adjudicatory role envisaged
  under Section 86(1 )(f) also appears to be for speedy resolution
  so that a vital developmental factor - electricity and its supply     B
  is not adversely affected by delay in adjudication of even
  ordinary civil disputes by the Civil Court. Evidently, in absence
  of any reason or justification the legislature did not contemplate
 to enable a creditor who has allowed the period of limitation to
  set in, to recover such delayed claims through the Commission.        C
  Hence we hold that a claim coming before the Commission·
  cannot be entertained or allowed if it is barred by limitation
  prescribed for an ordinary suit before the civil court. But in
  appropriate case, a specified period may be excluded on
                                                                        0
  account of principle underlying salutary provisions like Section
  5 or 14 of the Limitation Act. We must hasten to add here that
  such limitation upon the Commission on account of this
  decision would be only in respect of its judicial power under
  clause (f) of sub-section,(1) of Section 86 of the Electricity Act,   E
  2003 and not in respect of its other powers or functions which
  may be administrative or regulatory.

      31. In the light of above there can be no difficulty in
appreciating that M/s. LANGO rightly appreciated the hurdle F
of limitation in its way when such an objection was taken by
the appellant and it rightly chose to seek exclusion of the period
it was pursuing arbitration proceeding before the High Court,
on the basis of principles underlying Section 14 of the
Limitation Act.                                                    G
      32. The issue as to whether the impugned order by
APTEL permitting application of principles on Section 14 of
the Limitation Act is in accordance with law or warrants
interference now requires to be answered on the basis of law            H
492       SUPREME COURT REPORTS                 [2015] 12 S.C.R.


A as well as facts. In law, the APTEL could grant exclusion of
  certain period on the basis of principles under Section 14 in
  view of law laid down or clarified in M.P. Steel Corporation
  (supra). On facts, although the parties have argued at length,
  we find no difficulty in holding thatAPTEL has adopted a just
B and lawful approach in examining the relevant facts and in
  excluding the entire period claimed by Mis. LAN CO which starts
  from the notice for arbitration dated 8.9.2003 given by Mis.
  LANGO, till the application of Mis. LANGO under Section 11
  of the Arbitration Act before the High Court was finally disposed
C of on 18.3.2009. The issue whether the first notice dated
  8. 9.2003 or the next notice dated 26.3.2004 should be treated ·
  as notice for arbitration for the purpose of Section 21 of the
  Arbitration Act was rightly not pursued further by Mr. Giri after
  some initial arguments. But since this issue was touched, we
0
  have looked at the entire Article 14 of the PPA as well as the
  notice dated 8.9.2003 and we find no difficulty in holding it as
  the notice for arbitration which amounted to initiation of arbitral
  proceedings as contemplated by Section 21 of the Arbitration
E Act. A spirited argument was advanced on behalf of appellant
  that after the judgment of this Court in Gujarat Urja (supra) on
  13.3.2008, the continuance of the arbitral proceedings before
  the High Court at the instance of Mis. LANGO should not be
  accepted as bona fide and that the commission was justified
F in not excluding this period of about one year on the ground
  that it was not bona fide and in such facts APTEL should not
  have taken a contrary view. Having considered submissions
  of the parties we find no merit in the aforesaid contention
  advanced on behalf of appellant. The view which we are going
G to take has been indicated by this Court in several judgments
  including M.P. Steel Corporation (supra). But the point
  requires no debate in view of clear stipulation in explanation
  (a) to sub-section (3) of Section 14 of the Limitation Act. This
  explanation reads as follows:
H
   A.P. POWER COORDINATION COMMITTEE v. LANGO                     493
    KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.)

     "Explanation- For the purposes of this section, -            A

     (a) in excluding the time during which a former civil
     proceeding was pending, the day on which that
     proceeding was instituted and the day on which it ended
     shall both be counted ........... "                     B

         The same conclusion is inevitable even on other relevant
facts. The· appellant had notice of the arbitral proceeding and
after judgment in Gujarat Urja (supra), the appellant also took
no steps to get the application under Section 11 listed and C
disposed of earlier to 18.3.2009. The averments and the
materials are not sufficient to establish the claim of the appellant
that the proceeding ceased to be bona fide after 13.3.2008.
As a consequence of aforesaid discussion, the challenge to
impugned order in respect of views taken on the issue of o
limitation in the light of principles of Section 14 of the Limitation
Act fails.

      Issues relating to MAT

       33.The notice of Arbitration dated 8.9.2003, .inter alia, · E
made a demand for reimbursement of ir1~ome tax payment
made by M/s. LANCO, as per Article 3.8 of the PPA. -No doubt
the claim on this head for the subsequent years was not and
could not be in this notice but the difference between the parties F
on the issue had already arisen. In the notice claims for
advance income tax for the period 1.4.2001 to 15.6.2003
amounting to Rs.13.14 crores were included under the heading
"General Nature of Claims" and under the heading "Relief
Sought", Mis. LANGO claimed - "a declaration that the claimant G
is entitled to reimbursement of advance income tax paid by
the claimant". Under the same heading M/s. LAN CO mentioned
that it reserves its rights to seek such other reliefs or amend/
supplement the reliefs in the Statement of Claim as it may deem
appropriate whenever the same is filed before the Arbitral H
494        SUPREME COURT REPORTS                 [2015] 12 S.C.R.


A Tribunal. Thus the issue whether MAT is covered by article
  3.8 of the PPA was clearly covered by Arbitration notice. The
  filing of upto date claims through amendment or otherwise
  before theArbitral Tribunal could not happen for the obvious
  reason that application under Section 11 of the Arbitration Act
B itself remained pending till 181h March, 2009 before the High
  Court and thereafter before the Commission.

           34. It has already been noted that the claim for
     reimbursement of MAT for the period 2001-2005 was rejected
C · by the Commission on the ground of limitation and after
     impugned order by APTEL reversing such order, that claim
    stands remitted to the Commission for passing a
    consequential order. The claims for other periods have been
    allowed by the Commission. On account of our view indicated
D earlier upholding the order of APTEL on the issue of limitation,
    the claim of MAT for 2001-2005 cannot be treated as barred
    by limitation. Thus the claim of MAT for entire concerned period
    that is from 2001-2012 will be covered by our decision on
    Merits of Claim relating to MAT. The argument of Mr. Giri that
E MAT cannot be covered by the provisions in Article 3.8 of the
    PPA providing for claims for taxes on income because the
    appellant had not foreseen such eventuality in view of the then
    prevailing tax regime under which income from such power
F projects stood exempted, is noticed only to be rejected. The
    entire phraseology used in Article 3.8 of the PPA leaves no
    manner of doubt that parties were aware that tax regime keeps
    changing and therefore any advance income tax payable for
    the income from the project only had to be reimbursed by the
G Board. As a successor of the Board the appellant cannot avoid
    the liability to reimburse advance income tax paid by the M/s.
    LANCO, on the ground that MAT was a new variety of tax
    concept introduced subsequently in which minimum tax
    became payable on the basis of mere book profits of even
H power generating companies. The argument that such tax is
   A.P. POWER COORDINATION COMMITTEE v. LANCO                      495
    KONDAPALLI POWER LTD. [SHIVAKIRTI SINGH, J.]

not on income from the project and therefore, not covered by A
Article 3.8 of the PPA is also found to be without any substance.

      35. The objective of levying MAT, as declared by the
Income Tax Department is to bring into the tax net "Zero Tax
Companies" which inspite of having earned substantial book         B
profits and having paid handsome dividends, do not pay any
tax due to various tax concessions and incentives provided
under the Income Tax Law. It is no body's case that in fact M/
s. LAN CO had not generated income from the project during
the relevant years. The taxable income, of course, became          C
amenable to MAT on account of Section 115JB. The.
Legislative changes in respect of MAT show that it came into
force initially with effect from 1.4.1988 by introduction of
Section 115J in the Income Tax Act, 1961 but this provision
was amended to exempt power generating companies with              D
effect from 1.4.1989 and from 1.4.1991 MAT became
inapplicable because of deletion of Section 11 SJ which was
reintroduced with effect from 1.4.1997 by insertion of Section
115JA. But it was not made applicable to power generating
companies till 31.3.2001. However, Section 115JA was               E
withdrawn and Section 115JB was inserted with effect from
1.4.2001 to make MAT applicable to all targeted corporate
entities including power generating companies. The
submission on behalf of the appellant that Section 115JB is a      F
tax not on profit but of different character is based on
misconception. No doubt this Section has a special provision
for payment of tax by certain companies on the basis of its
book profit which is deemed to be the total income of the.
assessee and is subjected to income tax at a specified rate.       G
The provisions of Sections 115JA and 115JB have been also
construed as a self-contained code in Ajanta Pharma Limited
vs. CIT, 201 O(9) sec 455 and in several other judgments as
stand alone sections. But that does not change the basic
nature of the provision. It remains a provision under the Income   H
496        SUPREME COURT REPORTS                  [2015] 12 S.C.R.


A Tax Act and what is levied is income tax on the assessment of
  income as per such a special provision.
          36. Article 1.4 of the PPA provides inter alia that reference
    to any 'Law' shall be construed as a reference to such Law as
8 . from time to time amended or re-enacted. This general
    provision in our view is sufficient to take care of all the taxes
    on income under Article 3.8 of the PPA notwithstanding different
    rates of income tax or other changes which may be brought
    about in the Income Tax Act. This view commends itself to us
c because such change in Law relating to Income Tax does not
    require any additional claim to be raised by the power
    generating companies. There is no specific amount - or rate
    which is to be reimbursed by the Board. Rather, the entire
    advance income tax payable requires reimbursement on
D account of Article 3.8 of the PPA provided of course that the .
    accounts are maintained in the manner required by the
    Agreement so that tax is only on the basis of income from the
    project. No such dispute has been raised in the present case.
E       37. The claim of the appellant that liability of MAT is on
  account of change in Law and therefore required M/s. LANCO
  to adopt the procedure for making claims under Article 11.4 of
  the PPA does not appeal to us for the aforesaid reasons. The
  entire stipulation in Article 11.4 of the PPA is in respect of
F additional or reduced expenditures or costs which have not
  been catered for and arise later due to change in Law. The
  burden on account of income tax as per Article 3.9 of the PPA
  cannot be treated as additional or reduced burden because
  the entire actual advance income tax payable for the project is
G required to be reimbursed by the Board. It is immaterial
  whether the income tax payable is high or low in any particular
  year. When there is already a special provision in respect of
  entire payable taxes on income under Article 3.8 of the PPA,
  that should have precedence over the general provisions in
H Article 11.4 of the PPA.
    A.P. POWER C00RDINATION COMMITTEE v. LANCO                     497
     KONDAPALLI POWER LTD. [SHIVA KIRT! SINGH, J.]

      38. We have also considered other relevant provisions A
of the Income Tax su~h as definition of income, total income,
tax and find that they do not help the case of the appellant in
any manner. Section 2(43) defines 'Tax' to mean income tax
chargeable under the provisions of Income Tax Act and 'Total
Income' has been defined with reference to Section 5 which ·B
enlarges the scope of total income not only to income received
or accrued but also deemed to be received or deemed to be.
accrued in India (for a resident). Simply because the exemption
earlier granted. to power generating companies has been
withdrawn so as to subject them to income tax liability under a C
special provision, cannot lead to any inference as suggested
on behalf of the appellant that it is not an income tax but some
other tax which is levied under Section 115JB of the Income
Tax Act. Hence we hold the claim for MAT covered by Article
                                                                 0
3.8 of the PPAand payable as such when requisite conditions
stand satisfied.

      39. In the final conclusion, we find no scope to interfere
with the impugned order in these appeals. The appeals are
dismissed but without any order as to costs.                     E

Nidhi Jain                                    Appeals dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Electricity Act"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.