Created byFuzzy Cloud

Supreme Court of India

ALEMBIC PHARMACEUTICALS LTD.versusROHIT PRAJAPATI & ORS.

Citation
2020 INSC 326
Decided
1 April 2020
Disposal
Appeal(s) allowed

Holding

The Court held that the 2002 circular is not a Section 3 measure, the NGT has jurisdiction to review it, ex‑post‑facto clearances are impermissible, the industries are not covered by the Clause 8 exemption, and the NGT’s closure order is disproportionate, directing only a compensation deposit.

Summary

Three pharmaceutical units in Ankleshwar began operations without obtaining the prior environmental clearance (EC) mandated by the 1994 Environmental Impact Assessment (EIA) notification. The Ministry of Environment and Forests issued a 2002 circular allowing defaulting units to obtain an ex‑post‑facto EC, which the National Green Tribunal (NGT) struck down as illegal. The Supreme Court examined whether the circular could be treated as a "measure" under Section 3 of the Environment (Protection) Act, 1986 and whether the concept of ex‑post‑facto EC violated the precautionary principle and the statutory requirement of prior clearance. The Court held that the circular was a purely administrative decision, not a Section 3 measure, and therefore the NGT was within its jurisdiction to review its vires. While confirming that the industries had operated without valid ECs, the Court found the NGT’s order to revoke the ECs and close the units disproportionate and instead directed each unit to deposit Rs 10 crore as compensation for environmental damage. The judgment was delivered under Article 142 of the Constitution, allowing the Court to modify the NGT’s orders.

Issues considered

  • The 2002 circular granting ex‑post‑facto environmental clearances is a "measure" within the meaning of Section 3 of the Environment (Protection) Act, 1986.
  • Whether the National Green Tribunal has jurisdiction to strike down the circular.
  • Whether ex‑post‑facto environmental clearance is permissible under the 1994 EIA notification and environmental jurisprudence.
  • Whether the exemption under Clause 8 of the explanatory note to the 1994 EIA notification applies to the three industries.
  • Whether the NGT’s directions to revoke the ECs and order closure of the units are proportionate.

Legislation cited

Subjects

environmental clearanceex post facto clearanceprecautionary principleproportionalityNational Green TribunalEIA notification 1994environmental jurisprudencesustainable developmentcompensationindustrial pollution

Judgment

                        [2020] 10 S.C.R. 677                             677


                ALEMBIC PHARMACEUTICALS LTD.                             A
                                   v.
                    ROHIT PRAJAPATI & ORS.
                   (Civil Appeal No. 1526 of 2016)
                           APRIL 01, 2020
                                                                         B
         [DR. DHANANJAYA Y CHANDRACHUD AND
                       AJAY RASTOGI, JJ.]
       Environment (Protection) Act 1986 – s.3 – 1994 Environmental
Impact Assessment (EIA) notification mandated prior Environmental
Clearance (EC) for setting up and expansion of industrial units
falling within thirty categories – Deadline extended by various          C
circulars – 2002 Circular while further extending the deadline
allowed for ex post facto ECs – Quashed by National Green Tribunal
(NGT) – On appeal, held: Concept of an ex post facto EC is in
derogation of the fundamental principles of environmental
jurisprudence – It is an anathema to the 1994 EIA notification –         D
Allowing for an ex post facto clearance would essentially condone
the operation of industrial activities without the grant of an EC – It
would be contrary to both the precautionary principle as well as
the need for sustainable development – 2002 circular alters the
application of the 1994 EIA notification which has a statutory
character – Being an administrative decision, it is beyond the scope     E
of s.3 – It cannot be said to be a measure for protecting and
improving the quality of environment and is not protected by s.3 –
No jurisdictional bar on NGT to enquire into its vires – In case of
the three industries in question, no ECs were sought before the
commencement or expansion of operations, as mandated by the 1994         F
EIA notification – They continued to operate in the teeth of the said
notification – Further, none of these industries are entitled to the
benefit of the exemption contained in Clause 8 to the explanatory
note of the 1994 notification – However, NGT’s directions for
revocation of the ECs and closure of the units do not accord with
the principle of proportionality – Industries to deposit compensation    G
of ` 10 crores each, in addition to the amount directed by NGT –
Environment (Protection) Rules 1986 – Constitution of India –
Art.142.
       Environment (Protection) Act 1986 – Rules/Regulations under
– Jurisdiction of NGT to strike down – Discussed.                        H
                                 677
678            SUPREME COURT REPORTS                    [2020] 10 S.C.R.


A            Allowing the appeals, the Court
             HELD: 1. Section 3(1), Environment (Protection) Act 1986
      is an enabling provision for the Central Government to undertake
      all such measures as it deems necessary or expedient for the
      purpose of protecting and improving the quality of the
B     environment and preventing, controlling and abating
      environmental pollution. This limb of the submission of the
      Additional Solicitor General is crucial to the issue as to whether
      the NGT has exceeded its jurisdiction since the decision in Sterlite
      holds that the NGT, while exercising its appellate jurisdiction,
      “cannot strike down rules or regulations made under this Act”.
C     To demonstrate that the NGT did not have the jurisdiction to
      strike down the circular dated 14 May 2002, it was urged that
      the circular was issued by the MoEF pursuant to its powers under
      Section 3 of the Environment Protection Act 1986. There is an
      inherent difficulty in accepting the submission. Before this Court,
D     the Union of India has not pleaded the case that the circular dated
      14 May 2002 is a measure which is traceable to the provisions of
      Section 3. On the contrary, in its pleadings the Union of India
      construed it as a “purely administrative decision”. The omission
      in the appeal to make any attempt to sustain the circular dated
      14 May 2002 with reference to the provisions of Section 3 of the
E     Environment Protection Act 1986 is significant. For an action of
      the Central government to be treated as a measure referable to
      Section 3 it must satisfy the statutory requirement of being
      necessary or expedient “for the purpose of protecting and
      improving the quality of the environment and preventing,
F     controlling and abating environment pollution”. The circular dated
      14 May 2002 in fact does quite the contrary. The EIA notification
      of 1994 has been issued under the provisions of the Environment
      Protection Act 1986 and the Environment Protection Rules 1986,
      with the object of imposing restrictions and prohibitions on setting
      up of new projects or expansion or modernisation of existing
G     project. The measures are based on the precautionary principle
      and aim to protect the interests of the environment. The circular
      dated 14 May 2002 allowed defaulting industrial units who had
      commenced activities without an EC to cure the default by an ex
      post facto clearance. Being an administrative decision, it is beyond
      the scope of Section 3 and cannot be said to be a measure for the
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                       679
                   & ORS.

purpose of protecting and improving the quality of the                 A
environment. The EIA notification of 1994 mandates a prior
environmental clearance. The circular substantially amends or
alters the application of the EIA notification of 1994. The
administrative circular is not a measure protected by Section 3.
Hence there was no jurisdictional bar on the NGT to enquire into
                                                                       B
its legitimacy or vires. Moreover, the administrative circular is
contrary to the EIA Notification 1994 which has a statutory
character. The circular is unsustainable in law. [Paras 20, 21][697-
C-F; 698-A-E; 699-C]
       Tamil Nadu Pollution Control Board v. Sterlite Industries
       (I) Ltd. [2019] 3 SCR 777 – referred to.                        C
       2.1 The concept of an ex post facto EC is in derogation of
the fundamental principles of environmental jurisprudence and
is an anathema to the EIA notification dated 27 January 1994. It
is detrimental to the environment and could lead to irreparable
degradation. The reason why a retrospective EC or an ex post           D
facto clearance is alien to environmental jurisprudence is that
before the issuance of an EC, the statutory notification warrants
a careful application of mind, besides a study into the likely
consequences of a proposed activity on the environment. An EC
can be issued only after various stages of the decision-making
process have been completed. Requirements such as conducting           E
a public hearing, screening, scoping and appraisal are components
of the decision-making process which ensure that the likely
impacts of the industrial activity or the expansion of an existing
industrial activity are considered in the decision-making calculus.
Allowing for an ex post facto clearance would essentially condone      F
the operation of industrial activities without the grant of an EC.
In the absence of an EC, there would be no conditions that would
safeguard the environment. Moreover, if the EC was to be
ultimately refused, irreparable harm would have been caused to
the environment. In either view of the matter, environment law
cannot countenance the notion of an ex post facto clearance. This      G
would be contrary to both the precautionary principle as well as
the need for sustainable development. In the case of all the three
industries, ECs were applied for nearly a decade after the
introduction of the EIA notification 1994. In the meantime, the
industries had been set up and had commenced production. The           H
680           SUPREME COURT REPORTS                     [2020] 10 S.C.R.


A     documents disclosed by the three industries demonstrate that
      no ECs as mandated by the EIA notification of 1994 were sought
      before the commencement or expansion of operations. The terms
      of the EIA notification of 1994 envisage that expansion or
      modernisation of any activity (if the pollution load is to exceed
      the existing one) or a new project listed in Schedule – I shall not
B
      be undertaken unless it has been granted an EC. In the present
      case, all the three industries continued to operate in the teeth of
      the EIA notification 1994. [Paras 23, 25][700-F-H; 701-A-C; 706-
      G-H; 707-E-F]
            Common Cause v. Union of India (2017) 9 SCC 499 :
C           [2017] 13 SCR 361– relied on.
            2.2 Before the exemption contained in Clause 8 applies, it
      was necessary for projects listed in Schedule - I to obtain all
      relevant clearances from the State government including an NOC
      from the State Pollution Control Board. It was not sufficient to
D     merely obtain an NOC from the State Pollution Control Board.
      The exemption which was carved out in the explanatory note
      was to ensure that activities which had received all required
      clearances at the state level, following the acquisition of land
      should be protected. In fact, many of them would also involve the
      commencement of production prior to 27 January 1994. The
E     explanatory note stated that where production had not yet
      commenced, the IAA would have to be intimated. The EIA
      notification 1994 is a significant instrument in effectuating the
      implementation of the precautionary principle. The burden lies
      on the project proponent who seeks to alter the state of the
F     environment or to impact on the environment to demonstrate
      that the terms on which an exemption has been granted have
      been fulfilled. An exemption must be construed in its strict sense
      according to its plain terms. None of the three industries before
      the Court have furnished an exhaustive catalogue of what were
      the “relevant clearances from the State government” that had to
G     be obtained under the provisions of the law as it then stood. With
      this background, it will now be assessed individually whether the
      industries in question qualified for the exemption provided by
      Clause 8 to the explanatory note.

H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                    681
                   & ORS.

       Alembic Pharmaceuticals Limited                              A
       (i) Darshak Private Limited (API - I)
       The material produced on the record indicates that on 17
July 1992, Gujarat Pollution Control Board (GPCB) had issued
an NOC to establish an industrial unit and manufacture two
pharmaceuticals products. However, the NOC for manufacturing        B
additional items was issued only on 11 June 1997 subsequent to
the EIA notification dated 27 January 1994. The language used
in the NOC makes it clear that obtaining consents and
authorisations under various environment related legislations was
a mandatory pre-condition and not merely directory. The evidence
produced on the record by Darshak Private Limited indicates         C
that it did not have the requisite consents and authorisations
under the Air Act, Water Act and Hazardous Waste Rules prior
to the EIA notification 1994. Many of the consents and
permissions were obtained subsequently and not prior to the EIA
notification of 1994. Accordingly, the manufacturing unit of        D
Darshak Private Limited (API – I) is not covered under the
exemption under Clause 8 to the explanatory note of the EIA
notification of 1994.
       (ii) Nirayu Private Limited (API – II)
       A factory license was issued on 12 July 1984 to API – II.    E
On 24 May 1985, GPCB issued a water consent order under the
Water Act. This was valid only for the manufacture of anaesthetic
Ether. GPCB issued a site clearance certificate on 9 October
1991 for the manufacture of CIMC Chloride and Cloxacillin
Sodium. An NOC to establish an industrial unit and to manufacture
products was issued on 12 May 1993 and one for expansion on 4       F
December 1995. The NOC dated 12 May 1993 issued to Nirayu
Private Limited (API – II) also mandates that the project
proponent “shall be required to obtain” from the board “prior to
commencement of production” requisite consents and
authorisations under the Air Act, Water Act and Hazardous Waste     G
Rules from GPCB. All consents and permissions had not been
obtained prior to the EIA notification of 1994. Accordingly, the
manufacturing unit of Nirayu Private Limited (API – II) is not
covered under the exemption under Clause 8 to the explanatory
note of the EIA notification of 1994.
                                                                    H
682            SUPREME COURT REPORTS                    [2020] 10 S.C.R.


A            United Phosphorous Limited
             No material has been produced to indicate that all relevant
      clearances from the State government including the NOC from
      GPCB had been obtained prior to the EIA notification 1994.
      Accordingly, they cannot be granted the benefit of the exemption
B     under Clause 8 to the explanatory note of the EIA notification of
      1994.
             Unique Chemicals Limited
             It is evident from the table enlisting the list of relevant
      permissions, consents and authorisations that all permissions
C     were received after the EIA notification 1994 was issued. Clearly,
      Unique Chemicals Limited is not entitled to the benefit of the
      exemption contained in Clause 8 of the explanatory note to the
      EIA notification 1994. [Paras 28-32][708-E-F, G-H; 709-A-B, C-
      D; 710-D, F-H; 711-A-C, D-F; 712-A-D]
             2.3 From the material placed on the record by the industries,
D     it becomes evident that there has been a gross abdication of
      responsibility by all the three industries in terms of obtaining
      timely consents and authorisations from the GPCB. There exists
      a distinction between obtaining relevant clearances and consents
      from the State Pollution Control Board and obtaining an
E     environmental clearance in accordance with the procedure laid
      down under the EIA notification of 1994. A consent order issued
      by the State Pollution Control Board allows an industry to operate
      within the prescribed emission norms. However, the consent
      orders do not account for the social cost and impact of undertaking
      an industrial activity on the environment and its surroundings. A
F     holistic analysis of the environmental impact of an industrial
      activity is only accounted for once all the steps listed out in EIA
      notification of 1994 are followed. The purpose of setting in place
      specific requirements such as public hearing, screening, scoping
      and appraisal is to foster deliberative decisions and protect
G     environmental concerns. The detailed process listed out in the
      EIA notification of 1994 for obtaining an EC allows for minimising
      the adverse environmental impact of any industrial activity and
      improving the quality of the environment. One must adopt an
      ecologically rational outlook towards development. Given the
      social and environmental impacts of an industrial activity,
H     environment compliance must not be seen as an obstacle to
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                       683
                   & ORS.

development but as a measure towards achieving sustainable             A
development and inter-generational equity. None of the three
industries were entitled to the benefit of the exemption contained
in Clause 8 of the explanatory note to the EIA notification of
1994. [Paras 33, 34][712-D-H; 713-A]
      2.4 The MoEF had issued a circular on 5 November 1998            B
permitting applications for ECs to be filed by 31 March 1999,
which was extended subsequently to 30 June 2001. On 14 May
2002, the deadline was extended until 31 March 2003 subject to
a deposit commensurate to the investment made. Though the
three industries operated without an EC for several years after
the EIA notification of 1994, each of them had subsequently            C
received ECs including amended ECs for expansion of existing
capacities. These ECs have been operational since 14 May 2003
(in the case of Alembic Pharmaceuticals Limited), 17 July 2003
(in the case of United Phosphorous Limited), and 23 December
2002 (in the case of Unique Chemicals Limited). In addition, all       D
the three units have made infrastructural investments and
employed significant numbers of workers in their industrial units.
The directions of the NGT for the revocation of the ECs and for
closure of the units do not accord with the principle of
proportionality. At the same time, the Court cannot be oblivious
to the environmental degradation caused by all three industries        E
units that operated without valid ECs. The breach by the
industries cannot be left unattended by legal consequences. The
three industries are directed to deposit compensation quantified
at ` 10 crores each. The amount shall be deposited with GPCB
and duly utilised for restoration and remedial measures to improve     F
the quality of the environment in the industrial area in which the
industries operate. This deposit shall be in addition to the amount
directed by the NGT. The impugned judgment of the NGT is set
aside in so far as it directed the revocation of the ECs and closure
of the industries as well as the order in review. [Paras 36, 38 and
39][713-G; 714-A; 716-C-D, E-F, G-H; 717-B-C]                          G
      Lafarge Umiam Mining Pvt Ltd v. Union of India (2011)
      7 SCC 338 : [2011] 7 SCR 954; Electrotherm Ltd v.
      Patel Vipulkumar Ramjibhai (2016) 9 SCC 300 – relied
      on.
                                                                       H
684            SUPREME COURT REPORTS                     [2020] 10 S.C.R.


A           Goa Foundation v. Union of India (2005) 11 SCC 559;
            Techi Tagi Tara v. Rajendra Singh Bhandari & Ors.
            (2018) (11) SCC 734 : [2017] 12 SCR 956; Bharat
            Sanchar Nigam Limited v. Telecom Regulatory Authority
            of India (2014) 3 SCC 222 : [2013] 12 SCR 999 –
            referred to.
B
                             Case Law Reference
      [2017] 12 SCR 956                  referred to           Para 15
      (2005) 11 SCC 559                  referred to           Para 15
      [2011] 7 SCR 954                   relied on             Para 15
C     (2016) 9 SCC 300                   relied on             Para 15
      [2017] 13 SCR 361                  relied on             Para 16
      [2019] 3 SCR 777                   referred to           Para 18
      [2013] 12 SCR 999                  referred to           Para 18
            CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1526
D     of 2016.
            From the Judgment and Order dated 08.01.2016 of the National
      Green Tribunal (Western Zone) Bench, Pune in Application No. 66 (THC)
      of 2015 (WZ) Special Civil Application No. 17417 of 2003.
            With
E
            C.A. No. 3175 of 2016, C.A. No. 6604-6605 of 2016, C.A. No.
      1555 of 2017.
            A.N.S. Nadkarni, ASG, Kapil Sibal, Huzefa Ahmadi, Devang
      Nanavati, C.U. Singh, Dr. Abhishek M. Singhvi, Parag P. Tripathi,
      Sr. Advs., Ms. Ruby Singh Ahuja, Ms. Deepti Sarin, Ms. Kritika
F     Sachdeva, Ashutosh P. Shukla (for M/s. Karanjawala & Co.), Sandeep
      Narain, Ankit Virmani, M. Chandra Sekhar, Joyti Prakash Sahu (for
      M/s. S. Narain & Co.), Mahesh Agarwal, Rishi Agrawala, Ankur Saigal,
      Anirudha Bhatia, Rohan Talwar, E. C. Agrawala, D.L. Chidanand, S.S.
      Rebello, Arzu Paul, Neeleshwar Pavani, Ms. Riya Soni, Gurmeet Singh
G     Makker, Siddharth Seem, Satya Mitra, Ms. Hetvi Patel, A.P. Mayee, A.
      Rajarajan, Sanjeev Kr. Choudhary, Mrs. Hemantika Wahi, Ms. Jesal
      Wahi, Ms. Puja Singh, Ms. Ruchi Kohli, Ms. Nidhi Jaswal, Ms. Manyaa
      Chandok, Ajay Marwah, Advs. for the appearing parties.


H
    ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                 685
                      & ORS.

       The Judgment of the Court was delivered by                                   A
       DR. DHANANJAYA Y CHANDRACHUD, J.
       1. By a judgment dated 8 January 2016, the Bench of the National
Green Tribunal1 for the Western Zone held that a circular issued by the
Union Ministry of Environment and Forests2 on 14 May 2002 is contrary
to law. The circular envisaged the grant of ex post facto environmental             B
clearances. The NGT issued a slew of directions including the revocation
of environmental clearances and for closing down industrial units operating
without valid consents. On 17 May 2016, the NGT dismissed an
application for review filed by one of the affected industrial units. The
industrial units and MoEF are in appeal3.                                           C
                                                         4
       2. The Environmental Impact Assessment notification of 27
January 1994 mandated prior Environmental Clearances5 for setting up
and expansion of industrial projects falling within thirty categories. The
deadline for obtaining an EC under the EIA notification of 1994 was
extended by various circulars to 31 March 1999 and thereafter to 30                 D
June 2001. By the circular of 14 May 2002, which was quashed by the
NGT, MoEF extended the period till 31 March 2003 for those industrial
units which had gone into production without obtaining an EC under the
EIA notification of 1994 to apply for and obtain an ex post facto EC.
The circular indicated that it had been decided:
                                                                                    E
       “... to extend the deadline upto 31 March 2003 so that defaulting
       units could avail of this last and final opportunity to obtain ex-
       post-facto environmental clearance...”
       3. The circular of 14 May 2002, allowed for ex post facto ECs,
subject to a graded contribution into an earmarked fund based on the                F
investment cost of the project. The first and the second respondents
challenged the circular of 14 May 2002 before the High Court of Gujarat.
The proceedings were subsequently transferred to the NGT. The NGT
by its decision dated 8 January 2016 held that the law did not permit the
grant of an ex post facto clearances and that the circular of 14 May
1
                                                                                    G
  “NGT”
2
  “MoEF”
3
  Civil Appeal no 1526 of 2016 (Alembic Pharmaceuticals Limited); Civil Appeal no
3175 of 2016 (United Phosphorus Limited); Civil Appeal nos 6604-6605 of 2016
(Unique Chemicals); and Civil Appeal no 42756 of 2016 (Union of India)
4
  “EIA”
5
  “EC”                                                                              H
686                SUPREME COURT REPORTS                         [2020] 10 S.C.R.


A     2002 was an internal communication and did not override the provisions
      of the EIA notification dated 27 January 1994 which had been issued in
      exercise of statutory powers conferred by Section 3 of the Environment
      (Protection) Act 19866.
            4. Having held that the concept of an “ex post facto environmental
B     clearance” was not sustainable with reference to any provision of law,
      the NGT issued the following directions:
               (i) The authorities of the Union of India, including the MoEF,
                   State of Gujarat, Gujarat Pollution Control Board7 and District
                   Collectors shall not grant consent for an industrial activity
C                  covered by the EIA notification of 1994 without the steps
                   mandated by the notification such as screening, scoping, public
                   hearing and decision being fulfilled;
               (ii) The ECs granted to the industrial units of the sixth to ninth
                    respondents shall be revoked;
D              (iii) All the industrial activities which were being operated without
                     a valid EC and consent to operate shall be closed down within
                     one month;
               (iv) Each of the units shall deposit a compensation of ` 10 lakhs
                    for having caused environmental degradation;and
E
               (v) The amount deposited shall be used for the restoration of the
                   environment in and around the industrial area of Ankleshwar
                   in the State of Gujarat.
             5. The private respondents before the NGT who were affected
      by the above directions are:
F
               (i) United Phosphorous Ltd - the sixth respondent;
               (ii) Unique Chemicals - the seventh respondent;
               (iii) Darshak Private Limited - the eight respondent; and

G              (iv) Nirayu Private Limited - the ninth respondent.
             The private respondents are engaged in the manufacture of
      pharmaceuticals and bulk drugs at the industrial area of Ankleshwar in
      the State of Gujarat. Alembic Pharmaceuticals Limited is the appellant
      6
          “Environment Protection Rules”
      7
H         “GPCB”
    ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                            687
       & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

in the lead appeal before this Court. Darshak Private Limited merged           A
with the appellant in 2002 pursuant to a scheme of amalgamation
sanctioned by the High Court of Gujarat. Nirayu Private Limited was
acquired by the appellant under a slump sale on 1 January 2008. Following
this exercise, the manufacturing units of erstwhile Darshak Private
Limited and Nirayu Private Limited have come to be known as API – I
                                                                               B
and API – II, respectively.
         EIA Notification of 1994
       6. The EIA notification was issued by the MoEF on 27 January
1994, in exercise of its powers under Section 3(1) and clause (v) of
Section 3(2) of the Environment Protection Act 1986 read with Rule             C
5(3)(d) of the Environment (Protection) Rules 19868. The EIA notification
stipulated that:
         “…on and form the date of publication of this notification in the
         Official Gazette, expansion or modernization of any activity (if
         pollution load is to exceed the existing one) or new project listed   D
         in Schedule I to this notification, shall not be undertaken in any
         part of India unless it has been accorded environmental clearance
         by the Central Government in accordance with the procedure
         hereinafter specified in this notification.”
       7. The EIA notification stipulated that any person who desired to       E
undertake a new project, or the expansion or modernisation of an existing
industry, listed in Schedule-I shall submit an application to the Secretary,
MoEF. Entry 8 of Schedule - I includes industries engaged in
manufacturing bulk drugs and pharmaceuticals. The application had to
be accompanied by a project report including, inter alia, an EIA report
and an environmental management plan prepared in accordance with               F
the guidelines issued by the Union Government through the MoEF from
time to time. The notification spelt out the procedure to be followed
upon the submission of the application including an evaluation and
assessment by a stipulated agency. Clause 3(a)9 provided that:
         “...no construction work primarily or otherwise relating to the       G
         setting up of the project may be undertaken till the environmental
         and site clearances is obtained.”

8
    “Environment Protection Rules”
9
    Which was (substituted on 4 May 1994)                                      H
688             SUPREME COURT REPORTS                          [2020] 10 S.C.R.


A           8. On 10 April 1997, the EIA notification of 1994 was amended
      by making a public hearing mandatory for thirty categories of activities
      which required an EC. On 5 November 1998, the MoEF issued a circular
      recording that though the EIA notification of 1994 was in effect since 27
      January 1994, units covered by the notification had been set up without
      obtaining prior ECs. The GPCB had despite the advice of the MoEF
B
      allowed units to operate without valid ECs. In this backdrop, the circular
      of 5 November 1998 provided that:
            “Since number of such proposals are large in number and many
            of the units have not applied for environmental clearance genuinely
            out of ignorance it has been decided to consider their case for
C           environmental clearance on merits. This will apply only to those
            proposals which are received in the Ministry till 31st March 1999.
            Simultaneously State Pollution Control Boards have also been
            advised to issue requisite notices to the units to apply for
            environmental clearance. In case of those units which have already
D           started production, we may consider the proposals on merits and
            if necessary suggest additional mitigative measures. A formal
            environmental clearance will be issued in these cases after approval
            by the competent authority.”
             9. By a circular dated 27 December 2000, the MoEF directed all
E     state pollution control boards to issue fresh notices to all defaulting units
      and extended the deadline to obtain ECs from 31 March 1999 to 30 June
      2001. Inspite of this, there were delinquent units which had either failed
      to apply for an EC or had failed to complete the requirement of a public
      hearing before the extended date. By the circular of 14 May 2002, the
      deadline was extended to 31 March 2003. The circular stated that:
F
            “Keeping the foregoing in view, it has been decided to extend the
            deadline upto 31 March 2003 so that defaulting units could avail
            of this last and final opportunity to obtain ex-post- facto
            environmental clearance.This would apply to all such units, which
            had commenced construction activities/operations without obtaining
G           prior environmental clearance in violation of the EIA Notification
            of 27 January 1994.”
           10. In terms of the circular, those defaulting units seeking an
      expansion were to earmark a separate fund for “eco-development
      measures including community development measures in Indian projects
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                             689
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

areas” on a graded scale linked to the investment in the project. This       A
was indicated in a tabulated form which read thus:
        A   Projects with investment upto 1 % of the project cost with a
            ` 100 crores                  minimum of ` 50,000
        B   Projects with investment      0.5% of the project cost subject
            beyond ` 100 crores and upto to a minimum of ` 1 crore and a
            ` 1,000 crores                maximum of ` 2.5 crores            B

        C   Projects with investment      0.25 % of the project cost
            exceeding ` 1000 crores       subject to a maximum of
                                          ` 5 crores


      Units which failed to comply with the extended deadline were to        C
be proceeded against.
       The challenge to the ex post facto circular dated 14 May
2002
       11. A petition was instituted under Article 226 of the Constitution
by the first and second respondents in the present lead appeal before the    D
High Court of Gujarat challenging the circular dated 14 May 2002 and
seeking the revocation of the clearances which were granted to the
industrial units in question. The case was transferred to the Western
Zonal Bench of the NGT by the High Court of Gujarat on 21 April
2015.The NGT by its judgment dated 8 January 2016 set aside the circular     E
dated 14 May 2002 and issued consequential directions which have been
noted in the earlier part of this judgment. Unique Chemicals Limited, the
seventh respondent before the NGT, preferred a review petition against
the judgment of the NGT which was dismissed. The affected industrial
units and the MoEF are in appeal before this Court.
                                                                             F
      12. The issue to be adjudicated is whether in view of the
requirement of a prior EC under the EIA notification of 1994, a provision
for an ex post facto EC to industrial units could be validly made by
means of the circular dated 14 May 2002.
      13. During the course of the submissions, Mr Kapil Sibal, learned      G
Senior Counsel appearing on behalf of Alembic Pharmaceuticals Limited
has urged the following submissions:
       (i) The issue is academic as both the units of the appellant have
           been granted an EC for subsequent expansion to a much higher
           capacity after conducting a public hearing and upon               H
690                SUPREME COURT REPORTS                       [2020] 10 S.C.R.


A                  consideration of all material factors. The relevant details in
                   support of the submission arethus:
                   Darshak Private Limited (API - I)
              (a) An EC was granted on 14 May 2003 for a capacity of 15 MT
                  per month;
B
              (b) An EC was granted on 16 April 2008 for expansion of capacity
                  from 15 MT per month to 25 MT per month;and
              (c) An EC was granted on 31 January 2017 for a further
                  expansion of capacity from 25 to 75 MT per month.
C             Nirayu Private Limited (API – II)
                   (a)   An EC was granted on 14 May 2003 for a capacity of
                         47 MT per month; and
                   (b)   An EC was granted on 20 December 2016 for an
                         expanded capacity of 300 MT permonth.
D
              (ii) The EIA notification of 1994 omits the expression “prior”.
                   This is contrasted with the EIA notification dated 14 September
                   2006 which stipulates the requirement of a “prior” EC. While
                   a prior EC is mandatory under the notification dated 14
                   September 2006, it was not under the earlier notification dated
E                  27 January 1994;
              (iii) Once an EC has been granted for a much larger capacity
                    after conducting a prior public hearing, the question as to
                    whether the first EC for a lesser capacity was valid, is of no
                    significance. Since both the units have an EC for a larger
F                   capacity, the satisfaction for granting an EC for a lesser
                    capacity would be subsumed;
              (iv) The EIA notification of 1994 did not apply to the two units of
                   the appellant (API – I and API – II). Clause 8 of the
                   explanatory note to the EIA notification of 1994 provides that
G                  where a no objection certificate 10 from GPCB has been
                   obtained before 27 January 1994, an EC is not required. In
                   this context it has been submitted that:


      10
H          “NOC”
     ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                         691
        & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

        (a) On 17 July 1992, GPCB granted an NOC to establish and            A
            manufacture to the manufacturing unit of API - I;
        (b) On 29 May 1997 and 27 July 1998, GPCB granted an
            authorisation to operate under the Air (Prevention and Control
            of Pollution) Act 198111 to API - I;
        (c) On 11 October 1999, GPCB granted API – I an authorisation        B
            to operate under the Water (Prevention & Control of Pollution)
            Act 197412;
        (d) On 24 May 1985,GPCB granted API - II a consent order
            under the Water Act;
                                                                             C
        (e) On 9 October 1991, GPCB granted a site clearance certificate
            to API – II;
        (f) On 12 May 1993,GPCB granted an NOC to API - II to
            establish and for the manufacture drugs;
        (g) On 23 September 1993 and 13 November 1999, GPCB                  D
            granteda consent under the Water Act to API -II;
        (h) On 14 December 2001, GPCB granted an authorisation to
            API - II to operate under the Hazardous Waste (Management
            and Handling) Rules 198913; and
        (i) On 1 September 1999, 14 December 2001 and 7 March 2008,          E
            GPCB granted a consolidated consent and authorisation to
            API -II.
        (v) A public hearing was not mandatory under the EIA notification
            of 1994.
                                                                             F
            Clause 4 of the explanatory note confers a discretion to call
            for a hearing in case of projects that may cause large scale
            displacement or with severe environmental ramifications;
        (vi) If the order of the NGT prevails, the appellant would be
             prejudiced and suffer an irreparable loss.The appellant has     G
             made an investment of over ` 293 crores and employed a
             labour force of over 1000 workers; and

11
   “Air Act”
12
   “Water Act”
13
   “Hazardous Waste Rules”                                                   H
692            SUPREME COURT REPORTS                        [2020] 10 S.C.R.


A           (vii) The first respondent who was the petitioner before the NGT
                  chose to target only the appellant and two others out of over
                  ninety different entities which were granted similar
                  clearances. This cherry picking of certain select units
                  demonstrates the mala fide nature of the proceedings.
B            14. During the course of his submissions, Mr C U Singh, learned
      Senior Counsel appearing on behalf of United Phosphorus Limited has
      urged the following submissions:
            (i) The circular dated 5 November 1998, by which the deadline
                for obtaining ECs under the EIA notification of 1994 was
C               extended to 30 June 2001 was not challenged. The circular
                dated 5 November 1998 specifically noted that the State
                Pollution Control Board had despite the advice of the MoEF
                allowed units to operate without valid ECs;
            (ii) United Phosphorus Limited had all requisite ECs that were
D                granted by GPCB for the existing and expanded capacity. In
                 this context it has been submitted:
                 (a) An EC was granted on 17 July 2003 for manufacturing
                     Phorate and Terbuphose (300 MT per month combined)
                     and Acephate (80 MT per month);
E                (b) An EC was granted on 15 April 2008 for the expansion
                     of capacity for manufacturing pesticides and
                     intermediate products. Production of Phorate and
                     Terbuphose was increased from 300 MT per month to
                     500 MT per month, and production of Acephate was
F                    increased to 1000 MT per month;
                 (c) An EC was granted on 10 January 2020 for an enhanced
                     capacity of 9546 MT per month;
            (iii) The complainant, the first respondent in the lead appeal,
                  attended the public hearing held on 16 January 2002 prior to
G                 the grant of an EC on 17 July 2003 and raised no objections;
            (iv) If the order of the NGT prevails, the appellant would be
                 prejudiced and suffer an irreparable loss. The appellant has
                 employed approximately 400 permanent and contract workers
                 at its manufacturing unit;and
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                 693
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

         (v) The challenge by the first and second respondents was to the        A
             EIA notification 1994 which did not apply to the manufacturing
             unit of the appellant. At the relevant time, the appellant was
             exempted from obtaining an EC since it had all requisite
             permissions. In this context it has been submitted:
              (a) On 3 October 1992, GPCB granted an NOC to the                  B
                  appellant for setting up a manufacturing unit;
              (b) On 17 November 1995 and 2 April 1996, GPCB granted
                  NOCs for expansion and manufacturing additional
                  products;
              (c) On 27 August 2009, GPCB granted a consolidated                 C
                  consent and authorisation to the appellant s
                  manufacturingunit;
              (d) On 25 July 2012, GPCB issued an NOC for the
                  expansion of the appellant s manufacturing unit;and
              (e) On 11 May 2015 and 27 May 2017,GPCB granted a                  D
                  consolidated consent and authorisation for expanded
                  operations.
      15. Appearing for Unique Chemicals Limited, Dr Abhishek Singhvi,
learned Senior Counsel urged the following submissions:
         (i) The NGT did not have the jurisdiction to entertain the petition     E
             filed by the first and second respondents in view of the decision
             of this Court in Techi Tagi Tara v Rajendra Singh Bhandari
             & Ors14;
         (ii) The EC granted in 2007 superseded the earlier EC granted in
              2002.                                                              F
         Therefore, the question of validity of the earlier EC does not arise.
         In this context it has been submitted:
         (a) An EC was granted on 23 December 2002 for a capacity of
             78.02 MT per month for manufacturing bulk drugs
             andintermediates;                                                   G

         (b) An EC was granted on 8 August 2007 for an increase in
             manufacturing capacity from 78.02 MT per month to 116.12
             MT per month; and
14
     2018 (11) SCC 734                                                           H
694             SUPREME COURT REPORTS                         [2020] 10 S.C.R.


A            (c) An EC was granted on 30 June 2018 for an increase in the
                 manufacturing capacity to 290 MT per month. On 10 April
                 2019, the above EC was amended allowing an increase in the
                 number of products permitted to be manufactured by the
                 appellant.
B            (iii) The ex post facto clearance granted to the appellant cannot
                   be set aside by the order of the NGT in terms of the decision
                   of this Court in Goa Foundation v Union of India15, where
                   95 industrial projects were accorded ex post facto clearances
                   in terms of the circular dated 14 May 2002. Accordingly, no
                   question of closing down the manufacturing units of the
C                  appellants can arise;
             (iv) The requirement of an ex post facto public hearing was
                  introduced by an amendment in 1997 to the EIA notification
                  of 1994. The legality of an ex post facto public hearing has
                  been upheld by this Court in Lafarge Umiam Mining Pvt
D                 Ltd v Union of India16;
             (v) In various cases where there has been a violation of law, this
                 court has not ordered the closure considering the significant
                 investment and expansion undertaken by the industry. In
                 Electrotherm Ltd v Patel17, this Court did not order closure
E                of the plant since a significant expansion had already taken
                 place and the industry was functioning;
             (vi) If the order of the NGT prevails, the appellant would be
                  prejudiced and suffer an irreparable loss. The appellant has
                  employed approximately 400 employees at its manufacturing
F                 unit;
             (vii) The EIA notification 1994 did not apply to the manufacturing
                   unit of the appellant. The manufacturing unit of the appellant
                   was exempt from obtaining an EC as it had all the requisite
                   permissions. In this context it has been submitted:
G
             (a) On 30 September 1995, GPCB issued an ‘air consent order’
                 under the Air Act;

      15
         (2005) 11 SCC 559
      16
         (2011) 7 SCC 338
      17
H        (2016) 9 SCC 300
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                 695
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

         (b) On 9 January 1996 GPCB issued an authorisation under the            A
             Hazardous Waste Rules;
         (c) On 16 April 1996 GPCB issued a ‘water consent order’ under
             the Water Act;
         (d) On 15 April 2009 GPCB granted a consolidated consent and
             authorisation to the manufacturing unit of the appellant;           B

         (e) On 11 June 2010 and 26 June 2012, GPCB amended the
             consolidated consent and authorisation granted to the appellant
             on 13 April 2009;
         (f) On 30 May 2011, GPCB granted consent to set up a gas-               C
             based power generation plant having a capacity of 400 KW
             at the manufacturing unit of the appellant;
         (g) On 2 November 2013, GPCB granted a fresh consolidated
             consent and authorisation to the manufacturing unit of the
             appellant; and                                                      D
         (h) On 25 January 2019 and 25 October 2019, GPCB granted a
             fresh and revised consolidated consent and authorisation,
             respectively for an increase in the number of products
             permitted to be manufactured at the manufacturing unit of
             the appellant.
                                                                                 E
       16. Appearing for the first and second respondents, Mr Siddharth
Seem, learned counsel has urged the following submissions before this
Court:
         (i) The circular dated 14 May 2002 is illegal because environmental
              jurisprudence does not recognise any concept of ex post facto      F
              clearances. Any ex post facto approval is void and the benefit
              of the circular cannot be given to such an industry. In this
              regard, reliance was placed upon the decision of this Court in
              Common Cause v Union of India18;
         (ii) The circular dated 14 May 2002 does not mention its source         G
              or authority of law. The source of the circular is not traceable
              to Section 3 of the Environment Protection Act 1986 because
              the circular does not protect or improve the quality of the
              environment. The circular allows defaulters to get ex post
18
     (2017) 9 SCC 499                                                            H
696             SUPREME COURT REPORTS                            [2020] 10 S.C.R.


A                 facto clearances and does not encourage compliance with
                  the law;
             (iii) The Comprehensive Environmental Pollution Index report by
                   the Central Pollution Control Board indicates that the air, water
                   and soil parameters in and around the industrial area of
B                  Ankleshwar in the State of Gujarat, where the three industrial
                   units are located, are among the most critical in India: and
             (iv) Even if this court were to hold that the closure of the industries
                  should not be ordered, compensation should be directed to be
                  paid by them for restoration of the environment. These
C                 industries have brazenly operated for years without
                  environmental clearances.
             17. The rival submissions fall for our consideration.
              18. We first address the challenge to the jurisdiction of the NGT
      to strike down rules or regulations made under the Environment Protection
D     Act 1986. In Tamil Nadu Pollution Control Board v Sterlite
      Industries (I) Ltd19 (“Sterlite”) this Court analysed the adjudicatory
      functions which have been entrusted to the NGT under the National
      Green Tribunal Act 201020. Justice R F Nariman, speaking for a two
      judge Bench held that while exercising its jurisdiction under Section 16,
E     the NGT cannot strike down rules or regulations made under the
      Environment Protection Act 1986. In coming to this conclusion, the Court
      relied on the decision in Bharat Sanchar Nigam Limited v Telecom
      Regulatory Authority of India21, where the appellate power contained
      in Section 14 of the Telecom Regulatory Authority of India Act 22 1997
      was interpreted. After adverting to this decision, Justice R F Nariman
F     concluded that:
             “53…the NGT has no general power of judicial review akin to
             that vested under Article 226 of the Constitution of India possessed
             by the High Courts of this country.”
           19. While placing reliance on the above decision, Mr ANS
G
      Nadkarni, learned Additional Solicitor General made an attempt to
      demonstrate that the power to issue the circular dated 14 May 2002 that
      19
         2019 SCC Online SC 221 / Civil Appeal nos 4763-4764 of 2013
      20
         “NGT Act”
      21
         (2014) 3 SCC 222
      22
         “TRAI Act”
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                              697
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

extended the deadline for defaulting units to avail of an ex post facto       A
clearance until 30 March 2003 could well be traceable to Section 3 of
the Environment Protection Act 1986. Section 3, to the extent relevant,
provides thus:
      “Section 3. Power of central government to take measures to
      protect and improve environment.- (1) Subject to the provisions         B
      of this Act, the Central Government, shall have the power to take
      all such measures as it deems necessary or expedient for the
      purpose of protecting and improving the quality of the environment
      and preventing controlling and abating environmental pollution.”
       20. Section 3(1) is an enabling provision for the Central              C
Government to undertake all such measures as it deems necessary or
expedient for the purpose of protecting and improving the quality of the
environment and preventing, controlling and abating environmental
pollution. This limb of the submission of the Additional Solicitor General
is crucial to the issue as to whether the NGT has exceeded its jurisdiction
since the decision in Sterlite holds that the NGT, while exercising its       D
appellate jurisdiction, “cannot strike down rules or regulations made under
this Act”. In the present case, to demonstrate that the NGT did not
have the jurisdiction to strike down the circular dated 14 May 2002, it
was urged that the circular was issued by the MoEF pursuant to its
powers under Section 3 of the Environment Protection Act 1986. There          E
is an inherent difficulty in accepting the submission. Before this Court,
the Union of India has not pleaded the case that the circular dated 14
May 2002 is a measure which is traceable to the provisions of Section 3.
On the contrary, in its pleadings the Union of India construed it as a
“purely administrative decision”. Ground (iii) in paragraph 3 of the memo
of appeal states the position of the Union government:                        F

      “Because the Hon ble Tribunal failed to appreciate that after the
      EIA, Notification 1994 the opportunity to seek ex-post facto
      environmental clearance was given to industries in background of
      far reaching impact in terms of direct loss of livelihood in the
      employees working in the units which also supply inputs to other        G
      units and their indirect employment. It was submitted to the
      Hon’ble High Court of Gujarat that issuance of circular
      dated 14/05/2002, based on which environmental clearance
      was given, was purely an administrative decision before
      taking string entaction.”                                               H
                                                     (Emphasis supplied)
698             SUPREME COURT REPORTS                          [2020] 10 S.C.R.


A             21. The omission in the appeal to make any attempt to sustain the
      circular dated 14 May 2002 with reference to the provisions of Section
      3 of the Environment Protection Act 1986 is significant. For an action of
      the Central government to be treated as a measure referable to Section
      3 it must satisfy the statutory requirement of being necessary or expedient
      “for the purpose of protecting and improving the quality of the environment
B
      and preventing, controlling and abating environment pollution”. The
      circular dated 14 May 2002 in fact does quite the contrary. It purported
      to allow an extension of time for industrial units to comply with the
      requirement of an EC. The EIA notification dated 27 January 1994
      mandated that an EC has to be obtained before embarking on a new
C     project or expanding or modernising an existing one. The EIA notification
      of 1994 has been issued under the provisions of the Environment
      Protection Act 1986 and the Environment Protection Rules 1986, with
      the object of imposing restrictions and prohibitions on setting up of new
      projects or expansion or modernisation of existing project. The measures
      are based on the precautionary principle and aim to protect the interests
D
      of the environment. The circular dated 14 May 2002 allowed defaulting
      industrial units who had commenced activities without an EC to cure the
      default by an ex post facto clearance. Being an administrative decision,
      it is beyond the scope of Section 3 and cannot be said to be a measure
      for the purpose of protecting and improving the quality of the environment.
E     The circular notes that there were defaulting units which had failed to
      comply with the requirement of obtaining an EC as mandated. The circular
      provided for an extension of time and inexplicably introduced the notion
      of an expost facto clearance. In effect, it impacted the obligation of the
      industrial units to be in compliance with the law. The concept of ex post
      facto clearance is fundamentally at odds with the EIA notification dated
F
      27 January 1994. The EIA notification of 1994 contained a stipulation
      that any expansion or modernisation of an activity or setting up of a new
      project listed in Schedule – I “shall not be undertaken in any part of India
      unless it has been accorded environmental clearance”. The language of
      the notification is as clear as it can be to indicate that the requirement is
G     of a prior EC. A mandatory provision requires complete compliance.
      The words “shall not be undertaken” read in conjunction with the
      expression “unless” can only have one meaning : before undertaking a
      new project or expanding or modernising an existing one, an EC must be
      obtained. When the EIA notification of 1994 mandates a prior EC, it
      proscribes a post activity approval or an ex post facto permission. What
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                             699
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

is sought to be achieved by the administrative circular dated 14 May         A
2002 is contrary to the statutory notification dated 27 January 1994. The
circular dated 14 May 2002 does not stipulate how the detrimental effects
on the environment would be taken care of if the project proponent is
granted an ex post facto EC. The EIA notification of 1994 mandates a
prior environmental clearance. The circular substantially amends or alters
                                                                             B
the application of the EIA notification of 1994. The mandate of not
commencing a new project or expanding or modernising an existing one
unless an environmental clearance has been obtained stands diluted and
is rendered ineffective by the issuance of the administrative circular
dated 14 May 2002. This discussion leads us to the conclusion that the
administrative circular is not a measure protected by Section 3. Hence       C
there was no jurisdictional bar on the NGT to enquire into its legitimacy
or vires. Moreover, the administrative circular is contrary to the EIA
Notification 1994 which has a statutory character. The circular is
unsustainable in law.
        22. Mr Kapil Sibal, learned Senior Counsel appearing on behalf of    D
Alembic Pharmaceuticals Limited sought to urge that the EIA notification
dated 27 January 1994 contains an omission of the expression “prior”
and contrasted this with the EIA notification dated 14 September 2006
which stipulates the requirement of a “prior” EC. This, in his submission
is an indicator that a prior EC is mandatory under the notification dated
14 September 2006 but was not so under the earlier notification dated 27     E
January 1994. This interpretation was not supported by Mr ANS
Nadkarni, learned Additional Solicitor General who categorically submitted
that the requirement under the notification dated 27 January 1994 was
of a prior EC. We are unable to accept the submission of Mr Kapil
Sibal. The terms of the EIA notification dated 27 January 1994 leave no      F
manner of doubt that a prior EC was mandated before a new project
was commenced or before undertaking any expansion or modernisation
of an existing project. The absence of the expression “prior” in the EIA
notification dated 27 January 1994 makes no difference since the words
“shall not be undertaken…unless” postulate the requirement of a prior
EC. Speaking for a two judge Bench of this Court in Common Cause             G
v Union of India 23 (“Common Cause”), Justice Madan B Lokur
rejected the submission which was urged on behalf of mining lease holders
that:

23
     (2017) 9 SCC 499                                                        H
700            SUPREME COURT REPORTS                          [2020] 10 S.C.R.


A           “108… the possibility of getting an ex post facto EC was a signal
            to the mining leaseholders that obtaining an EC was not mandatory
            or that it if was not obtained, the default was retrospectively
            condonable.”
            Disagreeing with the submission, the Court held:
B           “125. We are not in agreement with the learned counsel for the
            mining leaseholders. There is no doubt that the grant of an
            EC cannot be taken as a mechanical exercise. It can only
            be granted after due diligence and reasonable care since
            damage to the environment can have a long-term impact.
C           EIA 1994 is therefore very clear that if expansion or
            modernisation of any mining activity exceeds the existing
            pollution load, a prior EC is necessary and as already held
            by this Court in M.C. Mehta [M.C. Mehta v. Union of
            India, (2004) 12 SCC 118] even for the renewal of a mining
            lease where there is no expansion or modernisation of any
D           activity, a prior EC is necessary. Such importance having
            been given to an EC, the grant of an ex post facto
            environmental clearance would be detrimental to the
            environment and could lead to irreparable degradation of
            the environment. The concept of an ex post facto or a
E           retrospective EC is completely alien to environmental
            jurisprudence including EIA 1994 and EIA 2006. We make
            it clear that an EC will come into force not earlier than the date of
            itsgrant.”
                                                           (Emphasis supplied)
F            23. The concept of an ex post facto EC is in derogation of the
      fundamental principles of environmental jurisprudence and is an anathema
      to the EIA notification dated 27 January 1994. It is, as the judgment in
      Common Cause holds, detrimental to the environment and could lead
      to irreparable degradation. The reason why a retrospective EC or an ex
G     post facto clearance is alien to environmental jurisprudence is that before
      the issuance of an EC, the statutory notification warrants a careful
      application of mind, besides a study into the likely consequences of a
      proposed activity on the environment. An EC can be issued only after
      various stages of the decision-making process have been completed.

H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                                           701
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

       Requirements such as conducting a public hearing, screening,                                        A
scoping and appraisal are components of the decision-making process
which ensure that the likely impacts of the industrial activity or the
expansion of an existing industrial activity are considered in the decision-
making calculus. Allowing for an ex post facto clearance would
essentially condone the operation of industrial activities without the grant
                                                                                                           B
of an EC. In the absence of an EC, there would be no conditions that
would safeguard the environment. Moreover, if the EC was to be
ultimately refused, irreparable harm would have been caused to the
environment. In either view of the matter, environment law cannot
countenance the notion of an ex post facto clearance. This would be
contrary to both the precautionary principle as well as the need for                                       C
sustainable development.
       24. In order to enable the Court to assess the status of compliance,
the material which has been produced on the record by (i) Alembic
Pharmaceuticals Limited; (ii) United Phosphorous Limited; and (iii)
Unique Chemicals Limited has been compiled in a tabulated form for                                         D
each of the three industries. For Alembic Pharmaceuticals Limited, the
data for its two industrial units - Darshak Private Limited (API – I) and
Nirayu Private Limited (API – II) - has been analysed separately. For
each of the three industries, Table A below consists of the list of
permissions, consents and authorisations obtained by the industry from
various authorities. Table B contains a list of ECs which were granted                                     E
from time to time to each industrial unit. The position as tabulated below
is based on the material which has been disclosed on the record of these
proceedings:
                Table A: List of permissions, consents and authorisations granted to Alembic
                                          Pharmaceuticals Limited
                                              Darshak (API–I)                                              F
                     Date                           Permission/Consent/Authorisation Granted
           17 July 1992                GPCB issued a no objection certificate to establish an industrial
                                       unit
                                       for the manufacture of the followi ng items at API–I: (i)
                                       Ciprofloxacin (1.25 MT pm); and (ii) Norfloxacin (2.5 MT pm)
           11June 1997                 GPCB granted noobjectioncertificate              for
                                       manufacturingaddi tional
                                       items at API–I
           29 May 1997                 GPCB issued air consent order authorising to operate API–I          G
           11 July 1997,               GPCB granted no objection certificate for manufacturing of
           12 July 1997 and 27 July    additional items at API–I
           1998
           31 March 1999               GPCB issued air consent order authorising to operate API–I
           11     October              GPCB issued water consent order authorising to operate AP–I
           1999
           Between 27 September        GPCB issued various consents under the Air Act, Water Act
           2002    –    23             and Hazardous Waste Rules.
           December 2011
                                                                                                           H
702            SUPREME COURT REPORTS                                         [2020] 10 S.C.R.


A          Table A: List of permi ssions, consents and authorisations granted to Alembic
                                      Pharmaceuticals Limited
                                          Darshak (API–I)
                Date                             Permission/Consent/Authorisation Granted
      17 July 1992                 GPCB issued a no obj ection certificate to establish an industrial
                                   unit
                                   for the manufacture of the followi ng items at API–I: (i)
B                                  Ciprofloxacin (1.25 MT pm); and (ii) Norfloxacin (2.5 MT pm)
      11June 1997                  GPCB granted noobjectioncertificate              for
                                   manufact uringadditional
                                   items at API–I
      29 May 1997                  GPCB issued air consent order authorising to operate API–I
      11 July 1997,                GPCB granted no objection certificate for manufacturing of
      12 Jul y 1997 and 27 July    additional items at API–I
C     1998
      31 March 1999                GPCB issued air consent order authorising to operate API–I
      11     October               GPCB issued water consent order authorising to operate AP–I
      1999
      Between 27 September         GPCB issued various consents under t he Air Act, Water Act
      2002    –    23              and Hazardous Waste Rules.
      December 2011
D
                                  Nirayu Private Limited(API–II)
            Date                        Permission/Consent/Authorisation Granted
      12 July 1984        Factory license was issued in favour of Nirayu Private Limited
      24 May 1985         GPCB issued water consent order authorisi ng to operate API–II

E     9 October 1991      GPCB issued a site clearance certificate to establish an industrial
                          unit
                          and manufacture the following items at API–II: (i) CIMC
                          chloride (2000 kgs pm); and (ii) Cloxacillin sodium (500 kgs pm)
      12 May 1993         GPCB granted a no objection certificate to establish an industrial
                          unit and manufacture the following items: (i) Acetone
                          thiosemicarbazone
                          (2MTpm);(ii)2Mercapta(5MTpm);(iii)Methoxyorthoxymethyl
F                         chloride (0.3 MT pm); and (iv) Solvent ether (7 MT pm)
      1    September      GPCB issued authorisation to operate API–II under the Hazardous
      1993                Waste Rules
      23 September        GPCB issued water consent order authorisi ng to operate API–II
      1993
      4    December       GPCB granted no objection certificate for manufacturing
G     1995                additional
                          items at API–II
      4 October 1996      GPCB issued air consent order to operate API–II
      and 17 April
      1998


H
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                             703
   & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

 1 September 1999            GPCB granted consolidated consent and authorisation to         A
                             operate API–II
 12 November 1999            GPCB issued water consent order to operate API–II
 14     December 2001        GPCB issued authorisation to operate API–II under the
                             Hazardous Waste Rules
 Between 27 September        GPCB issued various consents under the Air Act, Water
 2002 – 6 January 2015       Act and Hazardous Waste Rules.                                 B


      Table B: List of environmental clearances granted to Alembic Pharmaceuticals
                                         Limited
                                     Darshak(API–I)
   Date of          Date of             EC for Expansion              Date EC Granted
                     Public                (Quantity)
                                                                                            C
  Application
                    Hearing
 21        July 30 January 2002    Manufacturing of various         14 May 2003 as per
 2001                              bulk drugs and intermediate      the      1994     EIA
                                   products with a total capacity   notification
                                   of
                                   15 MT pm
 8 December      9 October 2007    Expansion of total capacity of 16 April 2008 as per
                                                                                            D
 2006                              bulk drugs from 15 to 25 MT    the      2006      EIA
                                   pm                             notification
 16              12 June 2015      Expansion of total capacity of 31 January 2017 as per
 September                         active         pharmaceutical the        2006     EIA
 2015                              ingredients from 25 to 75 MT notification
                                   pm                                                       E
                             Nirayu Private Limited(API–II)
   Date of       Date of Public        EC for Expansion               Date EC Granted
  Application        Hearing                (Quantity)
 20       July 30 January 2002     Manufacturing of various         14 May 2003 as per
 2001                              bulk        drugs        and     the      1994     EIA
                                   intermediate products with       notification            F
                                   a total capacity of
                                   47 MT pm
 28      March 12 June 2015        Expansion        of     total    20 December 2016 as
 2016                              capacity       of      active    per the 2006 EIA
                                                        pharma      notification
                                   ceutical          ingredients
                                   andintermediates                                         G
                                   from 47 to 300 MT pm




                                                                                            H
704          SUPREME COURT REPORTS                                                [2020] 10 S.C.R.


A          Table A: List of permissions, consents and authorisations granted
                                       to United
                                 Phosphorus Limited
                                    Unit no 2 - Plot no 3405 and 3406

                 Date                 Permission/Consent/Authorisation
                                      Granted
B     31       January Gujarat Industrial Development Corporation granted
      1992             land to the
                       appellant to establish and run unit no 2
      9 March 1992     GPCB issued no objection certifi cate for operation of
                       unit no 2 in
                       relation to manufacturing of various products
      3 October 1992   GPCB issued no objection certificate to set up a unit to
C                      manufacture the following items at unit no 2: (i)
                       Carbendazim; (ii) Quinalphos; and
                       (iii) Paraquat
      1993             Unit no 2 commenced manufacturing activities
      17    November   GPCB granted no objection certificate for expansion of
      1995             unit no 2 for manufacturing of two additi onal products –
D                      Phorate and Terbuphose
                       (300 MT pm combined)
      2 April 1996     GPCB granted no objection certificate for expansion of
                       unit no 2 for
                       the manufacture of Acephate (80 MT per month)
      27 August 2009   GPCB granted a consolidated consent and authorisation
                       to unit no 2
E
      25 July 2012     GPCB issued consent to establish (NOC) for expansion
                       of unit no 2
      11 May 2015 GPCB granted a consolidated consent and authorisation
      and    27 April for the expanded operations
      2017

       Tab le B : Lis t of enviro nmental clearances g ranted to Un ited P hos phorus L imited
F                                     U nit no 2 - P lot no 3 40 5 and 3 40 6

        D a te o f           D a te of       EC fo r E xpansio n (Q uantity)      Da te EC Gra nted
       Applica tio n          P ubli c
                             H ea ring
      21     Au gu st   1 6 Jan uary 20 02   Man ufacturing of Phorate and       1 7 Jul y 2003 as per
      2 00 2                                 Terbu phos e (3 00 M T p m          E IA no tification of
                                             co mb ined ) and A cephate (80      1 994
                                             MT per month)
G     2 0 Octo ber                           Ex pansion o f p esticides an d     April 15 20 08 as per
      2 00 7                     -           intermed iat e p ro ducts.          E IA no tification of
                                             - Prod uctio n o f Phorate an d     2 006
                                             Terbu phos e to be in creased to
                                             50 0 MT pm comb in ed
                                             - Produ ctio n o f A ceph at et o
                                             be increased to 1 00 0 MT pm
             -                   -           En han ced cap aci ty of 9546 M T   1 0 Jan uary 20 20 as
H                                            per m on th (as per written         p er E IA no tification
                                             sub mis sions)                      o f 2 00 6
ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                      705
   & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

    Table A: List of permissions, consents and authorisations granted to             A
                        Unique Chemicals Limited
                              Unit at plot no 5

       Date                     Permission/Consent/Authorisation Granted
14 August 1995     GPCB issued a no objection certificate to establish and run a
                   unit                                                              B
                   (site clearance) at plot no 5
30 September       GPCB issued air consent order authorising to operate unit at
1995               plot no 5
25   December      GPCB issued a no objection certificate to set up and
1995               manufacture the following items at the unit at plot no 5: (i)
                   Dichlotofenance sodium (6 MT pm); (ii) Nifedipine (2 MT
                   pm); (iii) Indolinone (6.9 MT pm); and
                                                                                     C
                   (iv) Pefloxacin (3 MT pm)
9 January 1996     GPCB issued authorisation under the Hazardous Waste Rules
16 April 1996      GPCB issued water consent order authorising to operate unit
                   at plot
                   no 5
24 April 1996      Unit at plot no 5 commenced manufacturing activities              D
15 April 2009      GPCB granted a consolidated consent and authorisation to the
                   unit at
                   plot no 5
11 June 2010       GPCB amended the consolidated consent and authorisation
and 26 June        to the unit at plot no 5 granted on 15 April 2009
2012
                                                                                     E
30 May 2011        GPCB granted no objection certificate to set up a gas-based
                   power
                   generation plant of a capacity of 400 KW at the unit at plot no
                   5
2    November      GPCB granted a fresh consolidated consent and authorisation
2013               to the
                   unit at plot no 5 for manufacturing of bulk drugs and             F
                   intermediates
1 July 2016        The appellant was cert ified as a zero liquid discharge unit
25       January   GPCB granted a new consolidated consent and authorisation
2019               to the
                   unit at plot no 5
25      October    GPCB issued a revised consolidated consent and
                   authorisation for
                                                                                     G
2019
                   increase in t he number of products that were permitted to be
                   manufactured at the unit at plot no 5




                                                                                     H
706              SUPREME COURT REPORTS                                                [2020] 10 S.C.R.


A          Table B: List of environmental clearances granted to Unique Chemicals Limited
                                               Unit at pl ot no 5

               Date of        Date of Public           EC for Expansion                   Date EC
             Application        Hearing                (Quantity)                         Granted
          30 June 2001       25 January 2002       Total capacity 78.02 MT 23 December 2002 as
                                                   pm of bulk drugs and per EIA not ification
                                                   intermediates.                   1994
                                                   Manufacturing         of     (i)
B                                                  Diclofenac              sodium
                                                   intermediates and derivates
                                                   (40      MT       pm);      (ii)
                                                   Nifedipine           and     its
                                                   intermediates (2 MT pm);
                                                   (iii) Indelinone (7 MT pm);
                                                   (iv) Pefloxacin and its
                                                   intermediates (3 MT pm);
                                                   (v) 2 methyl imldazole (15
C                                                  MT pm); (vi) Phentolamine
                                                   HCL (10 MT pm); (vii)
                                                   Diltazem HCL (1MT
                                                   pm); and (viii) other co-
                                                   products
          12 January 2007    Exempt            –   For      an    i ncrease      in 8 August 2007 as per
                             proposed project      manufacturing of bulk drugs EIA notification 2006
                             located in notified   and intermediates from a
                             industrial area       total capacity from 78.02
D                                                  MT pm to
                                                   116.12 MT pm
                                                   For      an    increase       in
                                                   manufacturing        of     co-
                                                   products from a total
                                                   capacity of 103 MT pm to
                                                   297 MT pm
                                                   For setting up a captive
E                                                  power plant with 1.3 MW
                                                   capacity
          16 March 2018      Exempt            –   For      an      i ncrease   in   30 June 2018 as per EIA
                             proposed project      manufacturing of bulk drugs       notification2006
                             located in notified   and intermediates from a
                             industrial area       total capacity from 78.02
                                                   MT pm to
                                                   290 MT pm by
                                                           setti ng       up of
F                                                  synthetic organic chemicals
                                                   manufacturing plant
                                                   Amendment to the EC dated         10   April 2019
                                                   30
                                                   June 2018 increasing the          as per the 2006
                                                   number of
                                                   products           permitted      EIA notification
                                                   manufactured by the
                                                   appellant at the
G                                                  unit at plot no 5


             25. The position that emerges from the record is that in the case
      of all the three industries, ECs were applied for nearly a decade after
      the introduction of the EIA notification 1994. In the meantime, the
H     industries had been set up and had commenced production. GPCB issued
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                 707
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

a notice to United Phosphorus Limited on 30 April 2001 directing them            A
to apply for an EC. On 9 December 2000, GPCB issued a notice to
Darshak Private Limited (API – I) and Nirayu Private Limited (API –
II) directing them to apply for and obtain an EC in accordance with the
EIA notification of 1994. Darshak Private Limited (API – I) of Alembic
Pharmaceuticals Limited, applied for an EC on 21 July 2001 which it
                                                                                 B
was granted on 14 May 2003. Subsequent applications for expansion of
capacity were submitted on 8 December 2006 and 16 September 2015
for which ECs were granted on 16 April 2008 and 31 January 2017,
respectively. Nirayu Private Limited (API – II), initially applied for an
EC on 20 July 2001 and the EC was granted on 14 May 2003. The
application for the grant of an EC for an extended capacity was submitted        C
on 28 March 2016 and the EC was granted on 20 December 2016. In
the case of United Phosphorous Limited, the initial EC was sought on 21
August 2002 and it was granted on 17 July 2003. An application for
expansion of capacity was submitted on 20 October 2007 and it was
granted on 15 April 2008. An EC for the further expansion of capacity
                                                                                 D
was granted on 10 January 2020. In the case of Unique Chemicals Limited,
the initial application for an EC was submitted on 30 June 2001 and it
was granted on 23 December 2002. Subsequent applications for
expansion in capacity were submitted on 12 January 2007 and 16 March
2018 for which ECs were granted on 8 August 2017 and 30 June 2018,
respectively. An amendment to the EC dated 30 June 2018 was granted              E
on 10 April 2019. The documents disclosed by the three industries
demonstrate that no ECs as mandated by the EIA notification of 1994
were sought before the commencement or expansion of operations. The
terms of the EIA notification of 1994 envisage that expansion or
modernisation of any activity (if the pollution load is to exceed the existing
                                                                                 F
one) or a new project listed in Schedule – I shall not be undertaken
unless it has been granted an EC. In the present case, all the three
industries continued to operate in the teeth of the EIA notification 1994.
        26. Learned counsel appearing for the three industries have relied
on a range of additional measures adopted, such as the installation of
latest pollution capturing technologies, recent consents from GPCB and           G
certification of “zero discharge” units. These measures adopted
subsequently will not cure the failure to obtain ECs before the projects
commenced operation. These measures are simply to ensure compliance
with the pollution standards and requirements of law that exist as of
date. These submissions have no bearing on determining whether the               H
708             SUPREME COURT REPORTS                          [2020] 10 S.C.R.


A     industrial units were in the past operating in compliance with the requisite
      environmental standards. These measures cannot act as correctives for
      historical wrongs and cannot compensate for the damage already caused
      to the environment as a result of manufacturing activities which were
      carried on without ECs.
B            27. Learned counsel for the three industries urged that the EIA
      notification of 1994 did not apply to their manufacturing units as they
      were covered by the exemption in terms of Clause 8 of the explanatory
      note. The issue which needs to be considered is whether the industries
      were covered by the exemption and were not required to obtain ECs.
      Clause 8 to the explanatory note to the EIA notification of 1994 states
C     thus:
            “8. Exemption for projects already initiated
            For projects listed in Schedule – I to the notification in respect of
            which the required land has been acquired and all relevant
D           clearances of the State Government including NOC from the
            respective State Pollution Control Board have been obtained before
            27th January 1994, a project proponent will not be required to
            seek environmental clearance from the IAA. However, those units
            who have not as yet commenced production will inform the IAA”

E            28. Before the exemption contained in Clause 8 applies, it was
      necessary for projects listed in Schedule - I to obtain all relevant
      clearances from the State government including an NOC from the State
      Pollution Control Board. It was in other words not sufficient to merely
      obtain an NOC from the State Pollution Control Board. The exemption
      which was carved out in the explanatory note was to ensure that activities
F     which had received all required clearances at the state level, following
      the acquisition of land should be protected. In fact, many of them would
      also involve the commencement of production prior to 27 January 1994.
      The explanatory note stated that where production had not yet
      commenced, the IAA would have to be intimated. In order to be covered
G     within the scope of the exemption, the burden is on the industry to
      demonstrate before this Court that they fulfilled conditions spelt out in
      Clause 8 of the explanatory note. The EIA notification 1994 is a significant
      instrument in effectuating the implementation of the precautionary
      principle. The burden lies on the project proponent who seeks to alter
      the state of the environment or to impact on the environment to
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                            709
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

demonstrate that the terms on which an exemption has been granted           A
have been fulfilled. An exemption must be construed in its strict sense
according to its plain terms. None of the three industries before the
Court have furnished an exhaustive catalogue of what were the “relevant
clearances from the State government” that had to be obtained under
the provisions of the law as it then stood.
                                                                            B
       29. With this background, we will now assess individually whether
the industries in question qualified for the exemption provided by Clause
8 to the explanatory note.
      30. Alembic Pharmaceuticals Limited
      (i) Darshak Private Limited (API -I)                                  C

      The material produced on the record indicates that on 17 July
1992, GPCB had issued an NOC to establish an industrial unit and
manufacture two pharmaceuticals products. However, the NOC for
manufacturing additional items was issued only on 11 June 1997
subsequent to the EIA notification dated 27 January 1994. The NOC           D
dated 17 July 1992 issued by GPCB clearly states:
      “We would like to inform you that the proposed location for this
      industrial plant is acceptable to us provided that you will
      implement the following measure for the prevention and
      control of environmental pollution:-                                  E
      (A)
      (B)
      (C)
      (D) Adequate arrangement for the management and handling of           F
      hazardous waste shall be made:
      IMPORTANT NOTE
      (1)
      (2)                                                                   G
      (3) The applicant/entrepreneur shall be required to obtain the
      following from the Board prior to commencement of
      production:
      (a) Consent under the Water (Prevention and Control of Pollution)
      Act 1974.                                                             H
710            SUPREME COURT REPORTS                          [2020] 10 S.C.R.


A           (b) Consent under the Air (Prevention and Control of Pollution)
            Act 1981.
            (c) Authorisation under the Hazardous Waste (Management and
            Handling) Rules 1989 under the Environment (Protection) Act
            1986.”
B                                                          (Emphasis supplied)
              GPCB while granting the NOC to establish an industrial unit
      required the project proponent to undertake certain measures for the
      prevention and control of environmental pollution including installation of
      treatment plants, discharge of effluents within prescribed limits and the
C     creation of a green belt around the industrial unit. One of the points
      under the “Important Note” states that the project proponent “shall be
      required to obtain” from the board “prior to commencement of production”
      requisite consents and authorisations under the Air Act, Water Act and
      Hazardous Waste Rules. The language used in the NOC makes it clear
D     that obtaining consents and authorisations under various environment
      related legislations was a mandatory pre-condition and not merely
      directory. In the present case, the authorisation under the Air Act was
      issued only on 29 May 1997 and 31 March 1999. The authorisation under
      the Water Act was issued on 11 October 1999. Clause 8 of the explanatory
      note states that for the exemption to apply, it was necessary for projects
E     listed in Schedule - I to have obtained all relevant clearances from the
      State government including an NOC from the State Pollution Control
      Board. The evidence produced on the record by Darshak Private Limited
      indicates that it did not have the requisite consents and authorisations
      under the Air Act, Water Act and Hazardous Waste Rules prior to the
F     EIA notification 1994. Many of the consents and permissions were
      obtained subsequently and not prior to the EIA notification of 1994.
      Accordingly, the manufacturing unit of Darshak Private Limited (API –
      I) is not covered under the exemption under Clause 8 to the explanatory
      note of the EIA notification of 1994.

G           (ii) Nirayu Private Limited (API –II)
            A factory license was issued on 12 July 1984 to API – II. On 24
      May 1985, GPCB issued a water consent order under the Water Act.
      This was valid only for the manufacture of anaesthetic Ether. GPCB
      issued a site clearance certificate on 9 October 1991 for the manufacture
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                             711
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

of CIMC Chloride and Cloxacillin Sodium. An NOC to establish an              A
industrial unit and to manufacture products was issued on 12 May 1993
and one for expansion on 4 December 1995. It is relevant to note that
the NOC dated 12 May 1993 issued by GPCB to Nirayu Private
Limited(API – II) is worded in exactly the same manner as the NOC
dated 17 July 1992 issued to Darshak Private Limited (API – I). The
                                                                             B
NOC dated 12 May 1993 issued to Nirayu Private Limited (API – II)
also mandates that the project proponent “shall be required to obtain”
from the board “prior to commencement of production” requisite consents
and authorisations under the Air Act, Water Act and Hazardous Waste
Rules from GPCB. In the case of Nirayu Private Limited (API – II),
authorisation under the Hazardous Waste Rules was issued on 1                C
September 1993. Consent to operate API – II under the Water Act was
issued on 12 November 1999. GPCB issued consolidate consent and
authorisation to operate API – II on 14 December 2010. From the above
narration which is based on the disclosures made by Nirayu Private
Limited, it is evident that all consents and permissions had not been
                                                                             D
obtained prior to the EIA notification of 1994. Accordingly, the
manufacturing unit of Nirayu Private Limited (API – II) is not covered
under the exemption under Clause 8 to the explanatory note of the EIA
notification of 1994.
      31. United PhosphorousLimited
                                                                             E
       On 31 January 1992, Gujarat Industrial Development Corporation
granted land to the appellant to establish and run its unit. On 9 March
1992 and 3 October 1992, GPCB issued an NOC for the operation of
the unit. The unit commenced manufacturing in 1993. It is relevant to
note that the NOC dated 3 October 1993 also mandates that the project
proponent “shall be required to obtain” from the GPCB “prior to              F
commencement of production” requisite consents and authorisations
under the Air Act, Water Act and Hazardous Waste Rules. United
Phosphorous Limited has not disclosed the dates on which it received
authorisations under the relevant environmental legislation. It has placed
on record a consolidated consent and authorisation that was issued much      G
later on 27 August 2009 under the Air Act, Water Act and Hazardous
Waste (Management, Handling and Trans boundary Movement) Rules



                                                                             H
712            SUPREME COURT REPORTS                          [2020] 10 S.C.R.


A     2008. The disclosures which have been made are patently incomplete.
      No material has been produced to indicate that all relevant clearances
      from the State government including the NOC from GPCB had been
      obtained prior to the EIA notification 1994. Accordingly, they cannot be
      granted the benefit of the exemption under Clause 8 to the explanatory
      note of the EIA notification of 1994.
B
            32. Unique ChemicalsLimited
             The material produced on the record indicates that GPCB issued
      an NOC to establish and run the manufacturing unit on 14 August 1995.
      It is evident from the table enlisting the list of relevant permissions,
C     consents and authorisations that all permissions were received after the
      EIA notification 1994 was issued. Clearly, Unique Chemicals Limited is
      not entitled to the benefit of the exemption contained in Clause 8 of the
      explanatory note to the EIA notification1994.
             33. From the material placed on the record by the industries, it
D     becomes evident that there has been a gross abdication of responsibility
      by all the three industries in terms of obtaining timely consents and
      authorisations from the GPCB. There exists a distinction between
      obtaining relevant clearances and consents from the State Pollution
      Control Board and obtaining an environmental clearance in accordance
      with the procedure laid down under the EIA notification of 1994. A consent
E     order issued by the State Pollution Control Board allows an industry to
      operate within the prescribed emission norms. However, the consent
      orders do not account for the social cost and impact of undertaking an
      industrial activity on the environment and its surroundings. A holistic
      analysis of the environmental impact of an industrial activity is only
F     accounted for once all the steps listed out in EIA notification of 1994 are
      followed. The purpose of setting in place specific requirements such as
      public hearing, screening, scoping and appraisal is to foster deliberative
      decisions and protect environmental concerns. The detailed process listed
      out in the EIA notification of 1994 for obtaining an EC allows for
      minimising the adverse environmental impact of any industrial activity
G     and improving the quality of the environment. One must adopt an
      ecologically rational outlook towards development. Given the social and
      environmental impacts of an industrial activity, environment compliance
      must not be seen as an obstacle to development but as a measure towards
      achieving sustainable development and inter-generational equity.
H
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                               713
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

       34. We have therefore come to the conclusion that none of the           A
three industries were entitled to the benefit of the exemption contained
in Clause 8 of the explanatory note to the EIA notification of 1994.
       35. The issue which must now concern the Court is the
consequence which will emanate from the failure of the three industries
to obtain their ECs until 14 May 2003 in the case of Alembic                   B
Pharmaceuticals Limited, 17 July 2003 in the case of United Phosphorous
Limited, and 23 December 2002 in the case of Unique Chemicals Limited.
The functioning of the factories of all three industries without a valid EC
would have had an adverse impact on the environment, ecology and
biodiversity in the area where they are located. The Comprehensive
Environmental Pollution Index24 report issued by the Central Pollution         C
Control Board for 2009-2010 describes the environmental quality at 88
locations across the country. Ankleshwar in the State of Gujarat, where
the three industries are located showed critical levels of pollution25. In
the Interim Assessment of CEPI for 2011, the report indicates similar
critical figures26 of pollution in the Ankleshwar area. The CEPI scores        D
for 201327 and 201828 were also significantly high. This is an indication
that industrial units have been operating in an unregulated manner and in
defiance of the law. Some of the environmental damage caused by the
operation of the industrial units would be irreversible. However, to the
extent possible some of the damage can be corrected by undertaking
measures to protect and conserve the environment.                              E

        36. Even though it is not possible to individually determine the
exact extent of the damage caused to the environment by the three
industries, several circumstances must weigh with the Court in determining
the appropriate measure of restitution. First, it is not in dispute that all
the three industries did obtain ECs, though this was several years after       F
the EIA notification of 1994 and the commencement of production.
Second, subsequent to the grant of the ECs, the manufacturing units of
all the three industries have also obtained ECs for an expansion of capacity
from time to time. Third, the MoEF had issued a circular on 5 November
1998 permitting applications for ECs to be filed by 31 March 1999, which       G

24
   “CEPI”
25
   CEPI score - 88.50
26
   CEPI score - 85.75
27
   CEPI score - 80.93
28
   CEPI score - 80.21                                                          H
714                SUPREME COURT REPORTS                        [2020] 10 S.C.R.


A     was extended subsequently to 30 June 2001. On 14 May 2002, the
      deadline was extended until 31 March 2003 subject to a deposit
      commensurate to the investment made. The circulars issued by the MoEF
      extending time for obtaining ECs came to the notice of this Court in Goa
      Foundation (I) v Union of India29. Fourth, though in the context of the
      facts of the case, this Court in Lafarge Umiam Mining Private Limited
B
      v Union of India30 (“Lafarge”) has upheld the decision to grant ex
      post facto clearances with respect to limestone mining projects in the
      State of Meghalaya. In Lafarge, the Court dealt with the question of
      whether ex post facto clearances stood vitiated by alleged suppression
      of the nature of the land by the project proponent and whether there
C     was non-application of mind by the MoEF while granting the clearances.
      While upholding the ex post facto clearances, the Court held that the
      native tribals were involved in the decision-making process and that the
      MoEF had adopted a due diligence approach in reassuring itself through
      reports regarding the environmental impact of the project. Chief Justice
      SH Kapadia speaking for the three judge Bench observed:
D
               “119. The time has come for us to apply the constitutional
               “doctrine of proportionality” to the matters concerning
               environment as a part of the process of judicial review in
               contradistinction to merit review. It cannot be gain said
               that utilization of the environment and its natural resources
E              has to be in a way that is consistent with principles of
               sustainable development and intergenerational equity, but
               balancing of these equities may entail policy choices. In the
               circumstances, barring exceptions, decisions relating to utilization
               of natural resources have to be tested on the anvil of the well-
F              recognized principles of judicial review. Have all the relevant
               factors been taken into account? Have any extraneous factors
               influenced the decision? Is the decision strictly in accordance with
               the legislative policy underlying the law (if any) that governs the
               field? Is the decision consistent with the principles of sustainable
               development in the sense that has the decision-maker taken into
G              account the said principle and, on the basis of relevant
               considerations, arrived at a balanced decision? Thus, the Court
               should review the decision-making process to ensure that the
               decision of MoEF is fair and fully informed, based on the correct
      29
           (2005) 11 SCC 559
H     30
           (2011) 7 SCC 338
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                  715
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

         principles, and free from any bias or restraint. Once this is ensured,   A
         then the doctrine of “margin of appreciation” in favour of the
         decision-maker would come intoplay.”
                                                         (Emphasis supplied)
       37. After adverting to the decision in Lafarge, another Bench of
three learned judges of this Court in Electrotherm (India) Limited v              B
Patel Vipulkumar Ramjibhai31, dealt with the issue of whether an EC
granted for expansion to the appellant without holding a public hearing
was valid in law. Justice Uday Umesh Lalit speaking for the Bench held
thus:
         “19…the decision-making process in doing away with or in granting        C
         exemption from public consultation/public hearing, was not based
         on correct principles and as such the decision was invalid and
         improper.”
       The Court while deciding the consequence of granting an EC
without public hearing did not direct closure of the appellant's unit and         D
instead held thus:
         “20. At the same time, we cannot lose sight of the fact that in
         pursuance of environmental clearance dated 27-1-2010, the
         expansion of the project has been undertaken and as reported by
         CPCB in its affidavit filed on 7-7-2014, most of the                     E
         recommendations made by CPCB are complied with. In our
         considered view, the interest of justice would be subserved if that
         part of the decision exempting public consultation/public hearing
         is set aside and the matter is relegated back to the authorities
         concerned to effectuate public consultation/public hearing.              F
         However, since the expansion has been undertaken and
         the industry has been functioning, we do not deem it
         appropriate to order closure of the entire plant as directed
         by the High Court. If the public consultation/public hearing results
         in a negative mandate against the expansion of the project, the
         authorities would do well to direct and ensure scaling down of the       G
         activities to the level that was permitted by environmental clearance
         dated 20-2-2008. If public consultation/public hearing reflects in
         favour of the expansion of the project, environmental clearance
         dated 27-1-2010 would hold good and be fully operative. In other
31
     (2016) 9 SCC 300
                                                                                  H
716             SUPREME COURT REPORTS                           [2020] 10 S.C.R.


A            words, at this length of time when the expansion has already
             been undertaken, in the peculiar facts of this case and in
             order to meet ends of justice, we deem it appropriate to
             change the nature of requirement of public consultation/
             public hearing from pre-decisional to post-decisional. The
             public consultation/public hearing shall be organised by the
B
             authorities concerned in three months from today.”
                                                             (Emphasis supplied)
             38. Guided by the precepts that emerge from the above decisions,
      this Court has taken note of the fact that though the three industries
C     operated without an EC for several years after the EIA notification of
      1994, each of them had subsequently received ECs including amended
      ECs for expansion of existing capacities. These ECs have been
      operational since 14 May 2003 (in the case of Alembic Pharmaceuticals
      Limited), 17 July 2003 (in the case of United Phosphorous Limited), and
      23 December 2002 (in the case of Unique Chemicals Limited). In
D     addition, all the three units have made infrastructural investments and
      employed significant numbers of workers in their industrial units.
             39. In this backdrop, this Court must take a balanced approach
      which holds the industries to account for having operated without
      environmental clearances in the past without ordering a closure of
E     operations. The directions of the NGT for the revocation of the ECs and
      for closure of the units do not accord with the principle of proportionality.
      At the same time, the Court cannot be oblivious to the environmental
      degradation caused by all three industries units that operated without
      valid ECs. The three industries have evaded the legally binding regime
F     of obtaining ECs. They cannot escape the liability incurred on account
      of such non- compliance. Penalties must be imposed for the disobedience
      with a binding legal regime. The breach by the industries cannot be left
      unattended by legal consequences. The amount should be used for the
      purpose of restitution and restoration of the environment. Instead and in
      place of the directions issued by the NGT, we are of the view that it
G     would be in the interests of justice to direct the three industries to deposit
      compensation quantified at ` 10 crores each. The amount shall be
      deposited with GPCB and it shall be duly utilised for restoration and
      remedial measures to improve the quality of the environment in the
      industrial area in which the industries operate. Though we have come to
H     the conclusion, for the reasons indicated, that the direction for the
 ALEMBIC PHARMACEUTICALS LTD. v. ROHIT PRAJAPATI                                 717
    & ORS. [DR. DHANANJAYA Y CHANDRACHUD, J.]

revocation of the ECs and the closure of the industries was not warranted,       A
we have issued the order for payment of compensation as a facet of
preserving the environment in accordance with the precautionary
principle. These directions are issued under Article 142 of the Constitution.
Alembic Pharmaceuticals Limited, United Phosphorous Limited and
Unique Chemicals Limited shall deposit the amount of compensation
                                                                                 B
with GPCB within a period of four months from the date of receipt of
the certified copy of this judgment. This deposit shall be in addition to the
amount directed by the NGT. Subject to the deposit of the aforesaid
amount and for the reasons indicated, we allow the appeals and set
aside the impugned judgment of the NGT dated 8 January 2016 in so far
as it directed the revocation of the ECs and closure of the industries as        C
well as the order in review dated 17 May 2016.
      Pending application(s), if any, shall stand disposed of.


Divya Pandey                                                  Appeals allowed.
                                                                                 D




                                                                                 E




                                                                                 F




                                                                                 G




                                                                                 H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "environmental clearance"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.