Created byFuzzy Cloud

Supreme Court of India

ARABIAN EXPORTS PRIVATE LIMITEDversusNATIONAL INSURANCE COMPANY LTD.

Citation
2025 INSC 630
Decided
6 May 2025
Disposal
Appeal(s) allowed

Holding

The Supreme Court held that the dispute is arbitrable and the High Court was wrong to refuse appointment of an arbitrator, as questions of duress and adequacy of the settlement fall within the arbitral tribunal’s jurisdiction.

Summary

Arabian Exports Private Limited (the appellant) claimed insurance proceeds for flood damage amounting to Rs 5,71,69,554 against National Insurance Company Ltd. (the respondent). After a long delay, the respondent offered a much lower sum of Rs 1,88,14,146, which the appellant accepted by signing an undated voucher and encashing the cheque, citing financial duress. The appellant later invoked the arbitration clause in the policies to recover the balance and filed applications under Section 11 of the Arbitration and Conciliation Act, 1996. The Bombay High Court dismissed the applications, holding that the voucher constituted a full and final settlement (accord and satisfaction) barring arbitration. The Supreme Court examined the doctrine of accord and satisfaction, the effect of economic duress, and the limited role of courts under Section 11, concluding that the existence of an arbitration agreement suffices to refer the dispute to arbitration. Consequently, the Court set aside the High Court order, allowed the appeals, and appointed a sole arbitrator.

Issues considered

  • Whether a dispute arising after the execution of a full and final discharge voucher can be referred to arbitration under the arbitration clause.
  • Whether a voucher signed under economic duress bars the applicability of the arbitration agreement.
  • Whether the doctrine of accord and satisfaction precludes arbitration when the settlement is contested on grounds of duress or inadequacy.

Legislation cited

Headnote

Issue for Consideration Whether a dispute raised by an insured after giving a full and final discharge voucher to the insurer can be referred to arbitration. Headnotes† Arbitration and Conciliation Act, 1996 – s.11 – Appellant claimed loss and damages under the insurance – After a considerable delay, a grossly inadequate amount was offered by the respondent – Due to financial strain, appellant signed the undated and standardized voucher/advance receipt – Pursuant thereto, appellant received the cheque issued by the respondent –

Subjects

Insurance policiesFull and final discharge vouchersAccord and satisfactionRes integraUndated and standardized voucher/advance receiptFinancial duressBilateral negotiated settlementArbitrable disputesPlea of coercionDoctrine of kompetenz-kompetenzMinimum judicial intervention

Judgment

                  [2025] 5 S.C.R. 798 : 2025 INSC 630

                    Arabian Exports Private Limited
                                   v.
                   National Insurance Company Ltd.
                  (Civil Appeal No(s). 6372-6373 of 2025)
                                  06 May 2025
                [Abhay S. Oka and Ujjal Bhuyan,* JJ.]


                            Issue for Consideration
       Whether a dispute raised by an insured after giving a full and final
       discharge voucher to the insurer can be referred to arbitration.

                                   Headnotes†
       Arbitration and Conciliation Act, 1996 – s.11 – Appellant
       claimed loss and damages under the insurance policies taken
       from the respondent – After a considerable delay, a grossly
       inadequate amount was offered by the respondent – Due to
       financial strain, appellant signed the undated and standardized
       voucher/advance receipt – Pursuant thereto, appellant received
       the cheque issued by the respondent – Later, appellant
       invoked arbitration clause to settle the balance amount being
       the difference between the claim lodged by the appellant and
       the amount paid by the respondent – Respondent denied any
       liability and refused to accept arbitration – Appellant filed
       applications u/s.11 of the Act for appointment of arbitrator –
       High Court held that no arbitrator could be appointed in view
       of acceptance of the amount in full and final settlement –
       Correctness:
       Held: High Court was wrong in rejecting the s.11(6) applications
       of the appellant – The question as to whether the appellant was
       compelled to sign the standardized voucher/advance receipt
       forwarded to it by the respondent out of economic duress and
       whether notwithstanding receipt of Rs. 1,88,14,146.00 as against
       the claim of Rs. 5,71,69,554.00 the claim to arbitration is sustainable
       or not are clearly within the domain of the arbitral tribunal – Thus,
       impugned order set aside. [Paras 41, 42]
       Arbitration and Conciliation Act, 1996 – Invocation of arbitration
       after settlement between the parties – Concept of ‘accord and
       satisfaction’ – Discussed. [Paras 33-39]

* Author
[2025] 5 S.C.R.                                                           799

 Arabian Exports Private Limited v. National Insurance Company Ltd.


     Arbitration and Conciliation Act, 1996 – Doctrine of kompetenz-
     kompetenz firmly embedded in arbitration jurisprudence in
     India – Discussed. [Para 40]

                             Case Law Cited
     National Insurance Company Limited v. Boghara Polyfab Private
     Limited [2008] 13 SCR 638 : (2009) 1 SCC 267; Nathani Steels
     Ltd. v. Associated Constructions (1995) Supp. 3 SCC 324; Duro
     Felguera, S.A. v. Gangavaram Port Ltd. [2017] 10 SCR 285 :
     (2017) 9 SCC 729; Vidya Drolia v. Durga Trading Corporation
     [2020] 11 SCR 1001 : (2021) 2 SCC 1; Oriental Insurance
     Company Ltd. v. Dicitex Furnishing Ltd. [2019] 14 SCR 389 :
     (2020) 4 SCC 621; SBI General Insurance Co. Ltd. v. Krish
     Spinning SBI General Insurance Co. Ltd. v. Krish Spinning [2024]
     7 SCR 840 : 2024 SCC OnLine SC 1754; Aslam Ismail Khan
     Deshmukh v. Asap Fluids Pvt. Ltd. [2024] 12 SCR 108 : (2025)
     1 SCC 502 – referred to.

                                List of Acts
     Arbitration and Conciliation Act, 1996.

                             List of Keywords
     Insurance policies; Full and final discharge vouchers; Accord and
     satisfaction; Res integra; Undated and standardized voucher/
     advance receipt; Financial duress; Bilateral negotiated settlement;
     Arbitrable disputes; Plea of coercion; Doctrine of kompetenz-
     kompetenz; Minimum judicial intervention.

                            Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No(s). 6372-6373
     of 2025
     From the Judgment and Order dated 02.12.2011 of the High Court
     of Judicature at Bombay in AA Nos. 186 and 187 of 2011

                         Appearances for Parties
     Advs. for the Appellant:
     Kavin Gulati, Sr. Adv., Ms. Surekha Raman, Amarjit Singh Bede,
     Shreyash Kumar, Mohit Shivkumar, Dushyant Sharma, Abhinav
     Mathur (for M/S. K J John and Co.)
800                                                          [2025] 5 S.C.R.

                           Supreme Court Reports


       Advs. for the Respondents:
       Manish Singhvi, Sr. Adv., Vishnu Mehra, Ms. Manjeet Chawla,
       Mrs. Usha Pant Kukreti, Kunal Malhotra.

                  Judgment / Order of the Supreme Court

                                  Judgment

       Ujjal Bhuyan, J.

       Leave granted.

2.     These appeals by special leave are directed against the order dated
       02.12.2011 passed by the High Court of Judicature at Bombay in
       Arbitration Application Nos. 186-187 of 2011.
3.     In this case, delay was condoned and notice was issued on
       11.05.2012.
4.     The short issue for consideration in these appeals is whether a
       dispute raised by an insured after giving a full and final discharge
       voucher to the insurer can be referred to arbitration.
5.     As we shall deliberate upon, this issue is no longer res integra.
6.     However, for a proper perspective, relevant facts may be briefly noted.
7.     Appellant is a company incorporated under the provisions of the
       Companies Act, 1956. It is engaged in the business of exporting
       meat and meat products. For this purpose, appellant used to process
       the meat and store the same at its factory premises at Taloja in the
       State of Maharashtra.
8.     On 08.10.2004, appellant took a comprehensive Standard Fire and
       Special Perils Policy bearing No. 260301/11/04/3100585 from the
       respondent towards insuring the meat processing and cold storage
       unit as also the building, plant and machinery, furniture, fixtures and
       fittings in the Taloja plant for an amount of Rs.3,28,55,000.00 which
       was for the period from 09.10.2004 to 03.10.2005.
9.     Appellant also took a Fire Declaration Policy bearing No.
       260301/11/04/3301441 insuring all its stock-in-trade and finished
       products stored in the cold storage facility at its factory premises
       at Taloja. This policy was for an amount of Rs.5,76,85,000.00 and
       covered the period from 15.03.2005 to 15.03.2006.
[2025] 5 S.C.R.                                                        801

 Arabian Exports Private Limited v. National Insurance Company Ltd.


10. It is stated that appellant had paid the insurance premium towards
    both the insurance policies.
11. On 26.07.2005, there was very heavy and unprecedented rainfall in
    several parts of Maharashtra including at Taloja. Because of such
    unprecedented and very heavy rainfall, the factory premises at Taloja
    was completely flooded and got submerged under water for several
    hours. It is stated that all communication lines had broken down and
    there were no means of communication to and fro the Taloja plant
    leaving the incident unnoticed till 28.07.2005. It is further stated
    that appellant had suffered severe loss due to the damage caused
    to the factory building, plant and machinery, furniture, fixtures and
    accessories as well as the stock lying at the Taloja plant.
12. Appellant had informed the respondent on 29.07.2005 regarding the
    damage suffered at the Taloja plant and requested the respondent to
    depute a surveyor to assess the damage. Appellant claimed loss and
    damage to the plant and machinery etc. under the Standard Fire and
    Special Perils Policy for an amount of Rs. 56,07,027.00. Appellant
    also claimed loss and damage qua the stock in cold storage under
    the Fire Declaration Policy for an amount of Rs. 5,15,62,527.00.
13. It is stated that on 28.07.2005, Dr. A.S. Patil (it is not stated who he
    was or who had authorized him) had inspected the factory premises
    at Taloja and after inspecting the stock-in-trade certified that the
    same was unfit for human consumption. On 29.11.2005, Chempro
    Inspection Private Limited, the surveyor appointed by the respondent,
    conducted a survey at the Taloja plant. In its report dated 29.11.2005,
    the surveyor acknowledged the loss suffered by the appellant.
14. Unfortunately, despite repeated requests and reminders by the
    appellant, respondent failed to settle the claims of the appellant.
15. After a considerable delay, appellant was presented with an
    undated and standardized voucher/advance receipt for a sum of Rs.
    1,88,14,146.00 sometime in December, 2008.
16. Due to financial strain caused by the delay on the part of the
    respondent to settle the claims coupled with the pressure exerted
    by various bankers and creditors, appellant was left with no other
    option but to sign and submit to the respondent the said undated and
    standardized voucher/advance receipt on 12.12.2008 for an amount
    of Rs. 1,88,14,146.00 being claimed under the Fire Declaration
802                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


       Policy. Pursuant thereto, appellant received the cheque issued by
       the respondent for a sum of Rs. 1,88,14,146.00 on 19.12.2008.
17. It may be mentioned that the two insurance policies had identically
    worded arbitration clause.
18. On 24.12.2008, appellant while reserving its right to invoke the
    aforesaid arbitration clause called upon the respondent to settle and
    pay the balance amount of Rs. 3,83,55,408.00 being the difference
    between the claim lodged by the appellant and the amount paid by
    the respondent. Appellant also sought for a copy of the surveyor’s
    report.
19. By letter dated 21.03.2009, respondent provided the appellant with
    a copy of the surveyor’s report giving details of the respondent’s
    assessment of the appellant’s claim.
20. Though the appellant made repeated attempts to resolve the matter
    but the respondent did not cooperate. Consequently, appellant
    addressed letter dated 17.04.2009 to the respondent invoking the
    arbitration clause contained in the insurance policy and at the same
    time nominated Mr. Ramakant W. Gudal, a retired Joint Commissioner
    and Controlling Authority, Food and Drugs Administration, Maharashtra
    as the sole arbitrator. It is stated that this letter was hand delivered
    to the respondent on 20.04.2009.
21. Respondent issued letter dated 18.05.2009 to the appellant through
    its lawyer denying its liability and refusing to accept arbitration and
    failed to nominate an arbitrator in terms of Clause 30 of the insurance
    policy. Respondent vide further letter dated 12.10.2009 stated that
    it was not agreeable to refer the matter to arbitration.
22. Thereafter, appellant filed applications under Section 11 of the
    Arbitration and Conciliation Act, 1996 (briefly, ‘the 1996 Act’
    hereinafter) before the High Court of Judicature at Bombay for
    appointment of an arbitrator to arbitrate the claims of the appellant.
    Thus two arbitration applications were filed in respect of the two
    policies which were registered as arbitration application Nos. 186
    of 2011 and 187 of 2011.
23. Learned Single Judge of the High Court of Judicature at Bombay
    (briefly, ‘the High Court’ hereinafter) observed that the amount paid
    by the respondent was accepted by the appellant in full and final
    settlement of the claim. It was accepted without any demur and
[2025] 5 S.C.R.                                                              803

 Arabian Exports Private Limited v. National Insurance Company Ltd.


     after encashing the cheque, the dispute was raised on 24.12.2008.
     Therefore, vide the impugned order dated 02.12.2011, learned
     Single Judge held that no arbitrator could be appointed in view
     of acceptance of the amount in full and final settlement. Both the
     arbitration applications were accordingly dismissed.
24. Mr. Kavin Gulati, learned senior counsel for the appellant has drawn
    our attention to the relevant facts and submits that learned Single
    Judge had rejected the applications under Section 11 of the 1996 Act
    on the ground that the discharge voucher signed by the appellant
    in favour of the respondent constituted full accord and satisfaction
    having accepted the amount paid by the respondent without demur.
     24.1. Learned senior counsel submits that in the present case,
           ‘accord and satisfaction’ is not voluntary but under compulsion.
           Appellant was under financial duress on account of the huge
           loss caused by the rainwater and flooding; additionally, there
           was long delay on the part of the respondent in processing
           the claim. That apart, appellant was pressurized by the banks
           and creditors for repayment of credit. In such circumstances,
           appellant had no other option but to sign the undated and
           standardized voucher/advance receipt for a wholly inadequate
           amount of Rs. 1,88,14,146.00 against the bona fide claim of
           Rs. 5,71,69,554.00. In this connection, learned senior counsel
           has drawn the attention of the Court to the letter dated
           24.12.2008 and the pleadings in the applications under Section
           11 of the 1996 Act which reads thus:
                The fact that the voucher relating to payment of our
                claim under the Standard Fire and Special Perils
                Policy refers to article/property “stolen” clearly
                establishes the complete non application of mind
                and disregard by your company to our repeated
                representations and the nature of our loss. Looking
                to the financial strain cast on us by virtue of the willful
                delay on the part of your organization in settlement at
                our claims coupled with the pressure exerted by our
                bankers and creditors, we were left with no option
                but to sign and submit to you the said undated and
                standardized voucher on December 12th 2008, for the
                grossly inadequate amount of Rs. 1,88,14,146.00.
804                                                          [2025] 5 S.C.R.

                              Supreme Court Reports


       24.2. Learned senior counsel submits that the case of the appellant
             is squarely covered by the decision of this Court in National
             Insurance Company Limited Vs. Boghara Polyfab Private
             Limited1. He has also distinguished the decision of this Court in
             Nathani Steels Ltd. Vs. Associated Constructions2 relied upon
             by the respondent. He submits that in Nathani Steels (supra),
             there were negotiations between the parties culminating in
             a voluntary negotiated settlement of all pending disputes.
             Contract was thus discharged by ‘accord and satisfaction’.
             This is not so in the present case. He further submits that
             issue in question is covered by the decision of this Court in
             Boghara Polyfab (supra).
       24.3. In any event, the discharge voucher was in relation to only
             one policy i.e. Fire Declaration Policy. It did not cover the
             Standard Fire and Special Perils Policy. Learned senior counsel
             has referred to and relied upon the circular dated 24.09.2015
             issued by the Insurance Regulatory and Development Authority
             of India clarifying that execution of vouchers as full and final
             discharge did not foreclose the rights of the policy holders
             to seek higher compensation before any judicial fora or any
             other fora established by law. This has been endorsed and
             reiterated vide subsequent circular dated 07.06.2016 issued
             by the Insurance Regulatory and Developmentary Authority of
             India. He, therefore, submits that learned Single Judge erred
             while rejecting the applications for appointment of arbitrator.
             Therefore, the impugned order is liable to be set aside.
25. Per contra, Dr. Manish Singhvi, learned senior counsel for the
    respondent submits that a three Judge Bench of this Court in Nathani
    Steels (supra) has clearly held that once a dispute or difference
    between the parties arising out of a contract is amicably settled by
    the parties, unless such settlement is set aside in proper proceedings,
    it is not open to one of the parties to the settlement to further seek
    arbitration. According to him, this case is squarely covered by Nathani
    Steels Ltd. (supra).



1   (2009) 1 SCC 267
2   (1995) Supp (3) SCC 324
[2025] 5 S.C.R.                                                            805

 Arabian Exports Private Limited v. National Insurance Company Ltd.


     25.1. Learned senior counsel submits that Nathani Steels Ltd.
           (supra) is a decision of a three Judge Bench whereas Boghara
           Polyfab (supra) is by a two Judge Bench. Therefore, the conflict
           between Nathani Steels (supra) and Boghara Polyfab (supra)
           needs to be resolved by referring the matter to a larger Bench.
     25.2. He submits that in so far the present case is concerned, there
           is no question of any fraud. In fact, there was no pleading
           and argument as regards fraud. There is also no pleading as
           to duress or coercion. Mere citation of the expressions fraud,
           duress or coercion will not make it a case of fraud, duress or
           coercion. There has to be adequate pleadings. That apart,
           appellant has not produced any document to even prima-
           facie show that the appellant was being pressurized by the
           respondent to enter into a settlement.
     25.3. In so far letter of the appellant dated 24.12.2008 is concerned,
           learned senior counsel submits that the said letter mentioned
           about the policies but did not contain any statement to the
           effect that the settlement was only for one policy. Respondent
           had processed the claim of the appellant on the basis of the
           report of the surveyor. The figure of Rs. 1.88 crores was not
           an imaginary or illusory figure but based on the assessment
           of the surveyor.
     25.4. Dr. Singhvi also argued an alternative prayer. If the Court is of
           the opinion that the High Court had not considered the aspect
           of duress and coercion, then the matter may be referred back
           to the High Court. In that event the High Court would consider
           the aspect of duress and coercion. Otherwise, no case for
           arbitration is made out. Therefore, he seeks dismissal of the
           appeals.
26. Submissions made by learned counsel for the parties have received
    the due consideration of the Court.
27. The two insurance policies contain an identically worded arbitration
    clause which read as follows:
           13. If any dispute or difference shall arise as to the quantum
           to be paid under this policy liability being otherwise
           admitted such difference shall independently of all other
806                                                        [2025] 5 S.C.R.

                         Supreme Court Reports


          questions be referred to the decision of sole arbitrator to
          be appointed in writing by the parties to or if they cannot
          agree upon a single arbitrator within 30 days of any party
          invoking arbitration, the same shall be referred to a panel
          of three arbitrators, comprising of two arbitrators, one
          to be appointed by each of the parties to the dispute/
          difference and the third arbitrator to be appointed by such
          two arbitrators and arbitration shall be conducted under
          and in accordance with the provisions of the Arbitration
          and Conciliation Act, 1996.
          It is clearly agreed and understood that no difference or
          dispute shall be referable to arbitration as hereinbefore
          provided, if the Company has disputed or not accepted
          liability under or in respect of this policy.
          It is hereby expressly stipulated and declared that it shall
          be a condition precedent to any right of action or suit upon
          this policy that the award by such arbitrator/arbitrators of
          the amount of the loss or damages shall be first obtained.
28. In its letter dated 24.12.2008 addressed to the respondent, appellant
    stated that after an inordinate delay of 42 months, a grossly inadequate
    amount of Rs.1,88,14,146.00 was offered by the respondent in
    response to the bona fide and genuine claim of the appellant for
    the aggregate sum of Rs.5,71,69,554.00. Appellant further stated
    that because of the financial strain caused due to the delay on
    the part of the respondent in settling its claims coupled with the
    pressure exerted by its bankers and creditors, appellant was left
    with no other option but to sign and submit to the respondent the
    undated and standardized voucher forwarded by it on 12.12.2008
    for Rs.1,88,14,146.00. Appellant further stated that it received a
    cheque for the aforesaid amount on 19.12.2008. Referring to the
    arbitral clause in the insurance policies, appellant stated that there
    is an arbitrable dispute in the context of the quantum of claim, the
    liability being admitted by the respondent. Appellant called upon the
    respondent to pay the balance amount of Rs.3,83,55,408.00 with
    interest at the rate of 18 percent. Respondent was put to notice
    that if the said amount was not paid, appellant would invoke the
    arbitration clause not only claiming the balance amount but also
    damages and compensation.
[2025] 5 S.C.R.                                                         807

 Arabian Exports Private Limited v. National Insurance Company Ltd.


29. Finally, appellant through its advocate issued notice to the respondent
    on 17.04.2009 invoking the arbitration clause and nominated
    Mr. Ramakant W. Gudal, retired Joint Commissioner and Controlling
    Authority, Food & Drugs Administration, Maharashtra as the Sole
    Arbitrator. Respondent was called upon to concur with the said
    nomination or alternatively to nominate its own arbitrator in which event
    the two nominated arbitrators would appoint a presiding arbitrator.
30. However, respondent informed the appellant vide letter dated
    12.10.2009 that it was not agreeable to refer the matter to arbitration
    as the appellant had accepted the amount offered in full and final
    settlement which amounted to ‘accord and settlement’.
31. It was thereafter that appellant approached the High Court by filing
    applications under Section 11 of the 1996 Act. The relevant pleadings
    have already been extracted and noted.
32. Learned Single Judge vide the impugned order observed that the
    amount offered by the respondent was accepted by the appellant in
    full and final settlement of the claim. The acceptance was not without
    prejudice to the rights and contentions of the appellant or reserving
    the right to challenge the amount that was being paid. The payment
    was made on 19.12.2008. It was accepted without any demur and
    after encashing the cheque the dispute was raised on 24.12.2008.
    Learned Single Judge referred to one of his previous orders where
    he had taken a view that if such a receipt is issued which accepts
    the payment in full and final settlement, then a dispute cannot be
    raised. He therefore held that no arbitrator can be appointed in view
    of acceptance of the amount in full and final settlement.
33. In Nathani Steels (supra), a three-Judge Bench of this Court opined
    that once the parties reach a settlement in respect of any dispute
    or difference arising under a contract and that dispute or difference
    is amicably settled by way of a final settlement by and between the
    parties, unless that settlement is set aside in proper proceedings
    it cannot lie in the mouth of one of the parties to the settlement to
    spurn it on the ground that it was a mistake and thereafter proceed
    to invoke the arbitration clause.
     33.1. Of course the Bench held that unless the settlement is set
           aside in proper proceedings, it would not be open to one of the
           parties to the settlement to invoke arbitration. But at the same
808                                                           [2025] 5 S.C.R.

                           Supreme Court Reports


              time, it needs to be pointed out that this view was taken in the
              context of an amicable settlement arrived at between the parties
              in the presence of a third party and reduced to writing. If there
              is an amicable settlement of the dispute between the parties
              unless such settlement is set aside in proper proceedings, it
              would not be open to one of the parties to invoke arbitration.
              Therefore, the crucial expression here is ‘amicable settlement’.
34. This decision was explained by this Court in Boghara Polyfab (supra).
    A two-Judge Bench of this Court noted that in Nathani Steels (supra)
    this Court on examination of the facts of that case was satisfied that
    there were negotiations leading to voluntary settlement between the
    parties in all pending disputes. Thus the contract was discharged by
    ‘accord and satisfaction’. The Bench categorized such claims under
    two categories. In the first category there would be cases where there
    is bilateral negotiated settlement of pending disputes, such settlement
    having been reduced to writing either in the presence of witnesses or
    otherwise. Nathani Steels (supra) falls in this category. In the second
    category of cases, there would be ‘no dues/claims certificate’ or ‘full
    and final settlement discharge vouchers’ insisted upon and taken,
    either in a printed format or otherwise, as a condition precedent
    for release of the admitted dues. In the latter group of cases, the
    disputes are arbitrable. Mere execution of a full and final settlement
    receipt or a discharge voucher cannot be a bar to arbitration even
    when validity thereof is challenged by the claimant on the ground of
    fraud, coercion or undue influence. The Bench further distinguished
    Nathani Steels (supra) by clarifying that the observations made that
    unless the settlement is set aside in proper proceedings, it would not
    be open to a party to the settlement to invoke arbitration was with
    reference to a plea of ‘mistake’ taken by the claimant and not with
    reference to allegations of fraud, undue influence or coercion. Further,
    the said decision was rendered in the context of the provisions of
    the Arbitration Act, 1940. The perspective of the 1996 Act is different
    from the Arbitration Act, 1940.
35. In Duro Felguera, S.A. Vs. Gangavaram Port Ltd.3, a two-Judge
    Bench of this Court examined Section 11(6) of the 1996 Act as well as
    Section 11(6A) inserted in the 1996 Act by way of the Arbitration and


3   (2017) 9 SCC 729
[2025] 5 S.C.R.                                                            809

    Arabian Exports Private Limited v. National Insurance Company Ltd.


       Conciliation (Amendment) Act 2015 and concluded that courts should
       look into only one aspect: existence of an arbitration agreement.
       Already the width of jurisdiction under Section 11(6) of the 1996 Act
       was considerably wide following judicial dicta but post the aforesaid
       amendment, all that the courts need to see is whether an arbitration
       agreement exists – nothing more, nothing less. The legislative policy
       and purpose is essentially to minimize the court’s intervention at the
       stage of appointing the arbitrator.
36. A three-Judge Bench of this Court in Vidya Drolia Vs. Durga Trading
    Corporation4 held that subject matter qua arbitrability cannot be
    decided at the stage of Sections 8 or 11 of the 1996 Act unless it
    is a clear case of dead wood. The court under Sections 8 and 11
    has to refer a matter to arbitration or to appoint an arbitrator, as the
    case may be, unless a party has established a prima facie case of
    non-existence of a valid arbitration agreement. The court should
    refer a matter if the validity of the arbitration agreement cannot be
    determined on a prima facie basis. The rule should be: when in
    doubt, do refer.
37. In Oriental Insurance Company Ltd. Vs. Dicitex Furnishing Ltd.5, a
    two-Judge Bench of this Court considered the objection of the insurer
    about maintainability of the application under Section 11(6) of the
    1996 Act in which the High Court had appointed an arbitrator. The
    objection was that the claimant had signed the discharge voucher
    and had accepted the amount offered, thus signifying ‘accord and
    satisfaction’ which in turn meant that there was no arbitrable dispute.
    This Court rejected the objection of the insurer and held thus:
             26. An overall reading of Dicitex’s application [under
             Section 11(6)] clearly shows that its grievance with respect
             to the involuntary nature of the discharge voucher was
             articulated. It cannot be disputed that several letters —
             spanning over two years—stating that it was facing financial
             crisis on account of the delay in settling the claim, were
             addressed to the appellant. This Court is conscious of the
             fact that an application under Section 11(6) is in the form
             of a pleading which merely seeks an order of the court,


4    (2021) 2 SCC 1
5    (2020) 4 SCC 621
810                                                             [2025] 5 S.C.R.

                              Supreme Court Reports


             for appointment of an arbitrator. It cannot be conclusive
             of the pleas or contentions that the claimant or the party
             concerned can take in the arbitral proceedings. At this
             stage, therefore, the court which is required to ensure
             that an arbitrable dispute exists, has to be prima facie
             convinced about the genuineness or credibility of the
             plea of coercion; it cannot be too particular about the
             nature of the plea, which necessarily has to be made
             and established in the substantive (read : arbitration)
             proceeding. If the court were to take a contrary approach
             and minutely examine the plea and judge its credibility or
             reasonableness, there would be a danger of its denying
             a forum to the applicant altogether, because rejection of
             the application would render the finding (about the finality
             of the discharge and its effect as satisfaction) final, thus,
             precluding the applicant of its right even to approach a
             civil court. There are decisions of this Court (Associated
             Construction v. Pawanhans Helicopters Ltd. and Boghara
             Polyfab) which upheld the concept of economic duress.
             Having regard to the facts and circumstances, this Court is
             of the opinion that the reasoning in the impugned judgment
             cannot be faulted.
       37.1. Thus, this Court held that at the stage of Section 11(6) of the
             1996 Act, court is required to ensure that an arbitrable dispute
             exist; it has to be prima facie convinced about the genuineness
             or credibility of the plea of coercion; it cannot be too particular
             about the nature of the plea which naturally has to be made and
             established in the arbitral proceeding. If the courts were to take
             a contrary approach, there would be the danger of denying a
             forum to the claimant altogether. This Court upheld the concept
             of economic duress and held that notwithstanding signing of
             discharge voucher and accepting the amount offered, the
             dispute is still arbitrable. Pleading in a Section 11(6) application
             cannot be conclusive whether there is fraud, coercion or undue
             influence or otherwise.
38. A three-Judge Bench of this Court in SBI General Insurance Co.
    Ltd. Vs. Krish Spinning6 held that even if the contracting parties in


6   2024 SCC OnLine SC 1754
[2025] 5 S.C.R.                                                               811

    Arabian Exports Private Limited v. National Insurance Company Ltd.


       pursuance to a settlement agree to discharge each other of any
       obligations arising under the contract it is does not ipso facto mean
       that the arbitration agreement too would come to an end, unless the
       parties expressly agree to do the same. The Bench also explained
       the concept of ‘accord and satisfaction’ under Section 63 of the
       Indian Contract Act, 1872. Any dispute pertaining to the full and final
       settlement itself by necessary implication being a dispute arising out
       of or in relation to or under the substantive contract would not be
       precluded from reference to arbitration as the arbitration agreement
       contained in the original contract continues to be in existence even
       after the parties have discharged the original contract by ‘accord
       and satisfaction’. This Court held thus:
             53. Thus, even if the contracting parties, in pursuance of a
             settlement, agree to discharge each other of any obligations
             arising under the contract, this does not ipso facto mean
             that the arbitration agreement too would come to an end,
             unless the parties expressly agree to do the same. The
             intention of the parties in discharging a contract by “accord
             and satisfaction” is to relieve each other of the existing or
             any new obligations under the contract. Such a discharge
             of obligations under the substantive contract cannot be
             construed to mean that the parties also intended to relieve
             each other of their obligation to settle any dispute pertaining
             to the original contract through arbitration.
             54. Although ordinarily no arbitrable disputes may subsist
             after execution of a full and final settlement, yet any
             dispute pertaining to the full and final settlement itself, by
             necessary implication being a dispute arising out of or in
             relation to or under the substantive contract, would not be
             precluded from reference to arbitration as the arbitration
             agreement contained in the original contract continues to
             be in existence even after the parties have discharged the
             original contract by “accord and satisfaction”.
39. Again, in the case of Aslam Ismail Khan Deshmukh Vs. Asap Fluids
    Pvt. Ltd.7, a three-Judge Bench of this Court reiterated the above
    proposition and held as under:


7    (2025) 1 SCC 502
812                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


          51. It is now well-settled law that, at the stage of Section
          11 application, the referral courts need only to examine
          whether the arbitration agreement exists - nothing more,
          nothing less. This approach upholds the intention of the
          parties, at the time of entering into the agreement, to refer
          all disputes arising between themselves to arbitration.
          However, some parties might take undue advantage of
          such a limited scope of judicial interference of the referral
          courts and force other parties to the agreement into
          participating in a time-consuming and costly arbitration
          process. This is especially possible in instances, including
          but not limited to, where the claimant canvasses either
          ex facie time-barred claims or claims which have been
          discharged through “accord and satisfaction”, or cases
          where the impleadment of a non-signatory to the arbitration
          agreement is sought, etc.
          52. In order to balance such a limited scope of judicial
          interference with the interests of the parties who might be
          constrained to participate in the arbitration proceedings, the
          arbitral tribunal may direct that the costs of the arbitration
          shall be borne by the party which the tribunal ultimately
          finds to have abused the process of law and caused
          unnecessary harassment to the other party to the arbitration
40. Thus, the doctrine of Kompetenz-Kompetenz is now firmly embedded
    in the arbitration jurisprudence in India. This doctrine is based on
    the principle that an arbitral tribunal is competent to rule on its
    own jurisdiction including on the issue of existence or validity of an
    arbitration agreement. The object is to minimize judicial intervention
    which is an acknowledgment of the concept of party autonomy.
41. In view of the clear legal proposition, we have no hesitation in
    holding that the High Court was wrong in rejecting the Section
    11(6) applications of the appellant. The question as to whether the
    appellant was compelled to sign the standardized voucher/advance
    receipt forwarded to it by the respondent out of economic duress and
    whether notwithstanding receipt of Rs.1,88,14,146.00 as against the
    claim of Rs. 5,71,69,554.00 the claim to arbitration is sustainable or
    not are clearly within the domain of the arbitral tribunal.
42. That being the position, the impugned order of the High Court dated
    02.12.2011 is set aside.
[2025] 5 S.C.R.                                                     813

 Arabian Exports Private Limited v. National Insurance Company Ltd.


43. Having regard to the long lapse of time we are of the view that it
    would be appropriate for this Court to appoint a retired Judge of the
    Bombay High Court as the sole arbitrator. Accordingly, we appoint
    Justice (Retd.) Suresh Chandrakant Gupte (Mobile No.- 9821010104)
    as the sole arbitrator. Parties to report to the sole arbitrator by
    15.05.2025.
44. Appeals are accordingly allowed. However, there shall be no order
    as to costs.

     Result of the case: Appeals allowed.




     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Insurance policies"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

ARABIAN EXPORTS PRIVATE LIMITED versus NATIONAL INSURANCE COMPANY LTD. — 2025 INSC 630 - Legal Desk AI