CONSOLIDATED CONSTRUCTION CONSORTIUM LIMITEDversusSOFTWARE TECHNOLOGY PARKS OF INDIA
- Citation
- 2025 INSC 574
- Decided
- 28 April 2025
- Disposal
- Dismissed
- Bench
- ABHAY S OKA
Holding
The Supreme Court held that the Single Judge exceeded the limited jurisdiction of Section 34 and that the award could not be set aside on grounds beyond those enumerated, thereby upholding the Division Bench’s restoration of the award.
Summary
The appellant, Consolidated Construction Consortium Ltd., was contracted by the respondent, Software Technology Parks of India, to construct a building. The contract stipulated liquidated damages for delay, but the respondent granted several extensions of time before finally deducting Rs. 82,43,499 as liquidated damages. An arbitrator upheld the deduction, but the appellant challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, and a Single Judge set aside the award, holding that the work was completed within the extended period. The respondent appealed under Section 37, and the Division Bench of the High Court restored the award, finding the Single Judge had exceeded his jurisdiction. The Supreme Court affirmed that a court may interfere with an arbitral award only on the limited grounds listed in Section 34 and that the Single Judge’s reasoning went beyond those grounds, thereby upholding the Division Bench’s decision and dismissing the appeal.
Issues considered
- The scope of judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996 in setting aside an arbitral award.
- Whether the High Court Single Judge exceeded his jurisdiction in setting aside the award on grounds not enumerated in Section 34.
- The applicability of Section 37 of the Act to overturn a Section 34 order.
- The validity of the deduction of liquidated damages despite extensions of time under the contract.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 2A, s. 33, s. 34, s. 37
- Contract Act, 1872s. 55, s. 73, s. 74
Headnote
Issue for Consideration Issue arose as regards the correctness of the order passed by the Division Bench of High Court upholding the arbitral award. Headnotes† Arbitration and Conciliation Act, 1996 – ss.34 and 37 – Application for setting aside arbitral awards – regarding delay in completion of the construction contract – Respondent-contracting authority deducted liquidated damages from the contractual dues of the appellant-contractor, along with other deduction and paid balance amount to appellant – Initiation of arbitral proceedings by
Subjects
Judgment
[2025] 4 S.C.R. 1846 : 2025 INSC 574
Consolidated Construction Consortium Limited
v.
Software Technology Parks of India
(Civil Appeal No. 5383 of 2024)
28 April 2025
[Abhay S. Oka and Ujjal Bhuyan,* JJ.]
Issue for Consideration
Issue arose as regards the correctness of the order passed by
the Division Bench of High Court upholding the arbitral award.
Headnotes†
Arbitration and Conciliation Act, 1996 – ss.34 and 37 –
Application for setting aside arbitral awards – Dispute
between the parties regarding delay in completion of the
construction contract – Respondent-contracting authority
deducted liquidated damages from the contractual dues of
the appellant-contractor, along with other deduction and paid
balance amount to appellant – Initiation of arbitral proceedings
by the appellant challenging deduction of liquidated damages –
Arbitral award by the arbitrator upholding the deduction of
liquidated damages – Petition u/s.34 by the appellant to set
aside the arbitral award – Allowed by the Single Judge of the
High Court setting aside the award holding that the appellant
had completed the work during the extended time granted
by the respondent, thus there was no delay – However, the
Division Bench set aside the judgment of the Single Judge –
Correctness:
Held: An arbitral award is not liable to be interfered with only on
the ground that the award is illegal or is erroneous in law which
would require re-appraisal of the evidence adduced before the
arbitral tribunal – If two views are possible, no scope for the court
to re-appraise the evidence and to take the view other than the
one taken by the arbitrator – View taken by the arbitral tribunal
is ordinarily to be accepted and allowed to prevail – Scope of
interference in arbitral matters is only confined to the extent
* Author
[2025] 4 S.C.R. 1847
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
envisaged u/s.34 – Proceedings u/s.34 are summary in nature and
not like a full-fledged civil suit or a civil appeal – Award cannot be
touched unless it is contrary to the substantive provisions of law
or s.34 or the terms of the agreement – Role of the court u/s.34
is a restrictive jurisdiction and has to be invoked in a conservative
manner – Arbitral autonomy must be respected and judicial
interference should remain minimal otherwise it will defeat the very
object of the 1996 Act – There was an ex post facto approval on
the part of the respondent – Appellant continued with the contract
work even after the extended period had expired – All throughout
respondent had put the appellant to notice that notwithstanding
extension of time it reserved the right to levy liquidated damages –
Single Judge went beyond the grounds provided in s.34 to set aside
the arbitral award and exceeded jurisdiction – No justification for
setting aside the arbitral award by taking a different view which is
certainly a possible and plausible view – Different interpretation
of the clause of the contract other than the one taken by the
arbitral tribunal is possible but that will not bring the challenge to
the arbitral award within the four corners of s.34 – Division Bench
justified in reversing the order of Single Judge u/s.37 – Contract
Act, 1872 – ss.55, 73, 74. [Paras 22-24, 28]
List of Acts
Arbitration and Conciliation Act, 1996, Contract Act, 1872.
List of Keywords
Arbitral award; Challenge to arbitral award; Delay in completion
of construction project; Liquidated damages; Deduction of
liquidated damages; Scope of interference u/s.37 of Arbitration
and Conciliation Act; Scope of interference u/s.34 of Arbitration
and Conciliation Act; Extension of time; Ex post facto approval;
Consequences of breach of contract; Appellate provision; Award
illegal or erroneous in law; Restrictive jurisdiction; Invoked in
conservative manner; Minimal judicial interference; Judge exceeded
jurisdiction; Arbitral autonomy.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 5383 of 2024
From the Judgment and Order dated 08.08.2019 of the High Court
of Judicature at Madras in OSA No. 157 of 2019
1848 [2025] 4 S.C.R.
Supreme Court Reports
Appearances for Parties
Advs. for the Appellant:
S.S. Rajesh, K.S. Mahadevan, Ms. Swati Bansal, Rangarajan R.,
Aravind Gopinathan, Rajesh Kumar.
Advs. for the Respondent:
Vinay Mohan Sharma, Ravinder Kumar Yadav, Mrs. Arti Anupriya,
Kartikey, Paras Juneja, Vineet Yadav, Amir Yadav, Vinay Kumar
Sharma, Ms. Bhawana Gadpandey.
Judgment / Order of the Supreme Court
Judgment
Ujjal Bhuyan, J.
This appeal by special leave is directed against the judgment and
order dated 08.08.2019 passed by the High Court of Judicature at
Madras in O.S.A. No. 157 of 2019.
2. Be it stated that by the judgment and order dated 08.08.2019
(‘impugned judgment’ hereinafter), Division Bench of the High Court
of Judicature at Madras (briefly ‘the High Court’ hereinafter) allowed
the appeal of the respondent filed under Section 37 of the Arbitration
and Conciliation Act, 1996 (briefly ‘the 1996 Act’ hereinafter) by
setting aside the judgment and order dated 02.01.2019 passed by
the learned Single Judge of the High Court in O.P. No. 433 of 2010
which was filed by the appellant under Section 34 of the 1996 Act
setting aside the arbitral award dated 05.01.2010.
3. Relevant facts may be briefly noted.
4. Software Technology Parks of India i.e. the respondent following
a tender process had awarded a contract to M/s Consolidated
Construction Consortium Ltd. i.e. the appellant for construction of
office building, incubation centre etc. of the respondent. As per the
Letter of Intent dated 09.03.2006 issued by the respondent, the
total cost of the project was Rs. 16,48,69,970.00. The scheduled
date for completion of construction was 15.01.2007. Appellant could
complete the construction only by 30.11.2007. There was thus a
delay of about 10 months.
[2025] 4 S.C.R. 1849
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
4.1. Appellant after handing over the project site to the respondent
claimed a sum of Rs. 1,40,12,786.00 including retention
money and interest thereon. However, because of the delay
in completion, respondent levied and deducted liquidated
damages to the tune of Rs. 82,43,499.00 by invoking clause
26 of the contract agreement entered into between the parties.
Respondent also made other deductions. After such deductions,
balance amount of Rs. 3,70,992.00 was paid to the appellant
by the respondent.
4.2. Aggrieved appellant invoked the arbitration clause of the
contract agreement and initiated arbitral proceedings challenging
deduction of liquidated damages by the respondent and also
lodged other claims. Respondent also lodged counter claims.
4.3. Learned arbitrator vide the award dated 10.05.2010 upheld the
deduction of liquidated damages by the respondent. That apart,
learned arbitrator dismissed the claims and counter claims of
the parties. Learned arbitrator held that he did not find any of
the claims or counter claims to have been established and,
therefore, declared the award as nil against all the claims and
counter claims.
5. Appellant filed a petition before the High Court under Section 34 of
the 1996 Act to set aside the award which was registered as Original
Petition (O.P.) No. 433 of 2010. A learned Single Judge of the High
Court vide the judgment and order dated 02.01.2019 held that there
was extension of the work period. Appellant had completed the work
during the extended period of time. Therefore, deduction of liquidated
damages was not justified. Consequently, the arbitral award dated
10.05.2010 was set aside.
6. Aggrieved by the aforesaid judgment and order dated 02.01.2019,
respondent preferred an appeal before the High Court under Section
37 of the 1996 Act which was registered as O.S.A. No. 157 of 2019.
A Division Bench of the High Court vide the impugned judgment and
order dated 08.08.2019 opined that learned Single Judge was not
justified in setting aside the award. The award was set aside purely on
assumptions and surmises. Grounds on which the award was set aside
were beyond the scope of Section 34 of the 1996 Act. Accordingly,
the judgment and order of the learned Single Judge dated 02.01.2019
was set aside, thereby allowing the appeal of the respondent.
1850 [2025] 4 S.C.R.
Supreme Court Reports
7. Aggrieved thereby appellant had filed the related special leave petition
on which notice was issued on 05.02.2021. When the matter was
heard on 23.04.2024, leave was granted.
8. Learned counsel for the appellant submits that Division Bench of the
High Court was not at all justified in exercising power under Section
37 of the 1996 Act by reversing the decision of the learned Single
Judge passed under Section 34 of the 1996 Act. He submits that
scope of interference under Section 37 is extremely limited and,
therefore, the Division Bench committed a manifest error in setting
aside the order passed under Section 34 of the 1996 Act. In the
process, the Division Bench committed a further error by restoring
the award which had upheld deduction of liquidated damages by
the respondent.
8.1. Learned Single Judge had rightly exercised power within the
broad parameters of Section 34 of the 1996 Act while setting
aside the award in question. It is the Division Bench which acted
like an appellate court beyond the scope of Section 37 of the
1996 Act while setting aside the order passed under Section
34 of the 1996 Act and restoring the award.
8.2. Learned counsel submits that the respondent had extended
the time for completion of the contractual work. Appellant had
completed the construction within the extended period. Therefore,
there was no delay in the contractual performance. Extension of
time and levy of liquidated damages cannot go hand-in-hand.
In the circumstances, respondent was not justified in deducting
liquidated damages from the contractual dues of the appellant.
8.3. He submits that the instant contract between the appellant and
the respondent was a contract relating to construction. In such
a contract, time is never of the essence. Such a contract is
governed by the principles laid down in Sections 55, 73 and 74
of the Indian Contract Act, 1872. In any view of the matter, the
employer would be entitled to liquidated damages to compensate
for the delay provided the delay had caused loss or damage
to the employer. No such deduction can be made if the delay
does not cause any loss or damage.
8.4. Division Bench had ignored the letter dated 26.09.2008 issued by
the respondent to the appellant extending the time to complete
the contract upto 30.11.2007. This letter of extension was written
[2025] 4 S.C.R. 1851
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
pursuant to the application of the appellant dated 14.12.2007
seeking such extension. Thus, appellant had completed the work
within the extended time granted by the respondent. Therefore,
there was no delay in executing the contract. Further, no loss
ensued to the respondent which would justify any deduction
on account of liquidated damages.
8.5. That being the position, there was no justification for invoking
clause 26 of the contract agreement by the respondent.
8.6. Learned counsel submits that learned Single Judge had rightly
noted that appellant could not complete the contract work within
the initial time frame because of reasons which were beyond its
control. When the respondent had extended the time frame, it was
obvious that the delay could not be attributed to the appellant.
Extension of time to complete the contract does not imply a
delay in execution. No loss was suffered by the respondent.
8.7. Learned counsel submits that when the respondent recognized
the difficulties faced by the appellant in executing the contract
it extended the time limit for completion of the contract till
30.06.2007. When the appellant was still unable to complete the
contract by 30.06.2007, respondent had allowed the appellant
to carry on with the work and to complete the contract by
30.11.2007 which was accepted by the respondent, of course,
reserving its right to levy liquidated damages. Learned counsel
further submits that on the one hand respondent had allowed
the appellant extended time to complete the construction
work, but on the other hand levied liquidated damages on the
appellant by invoking clause 26 of the contract agreement.
However, no advance notice was issued to the appellant
indicating any intention on the part of the respondent to levy
liquidated damages.
8.8. Lastly, learned counsel submits that in any view of the matter,
the impugned order is wholly unsustainable in law as well as
on facts and, is, thus liable to be appropriately interfered with.
9. On the other hand, learned counsel for the respondent submits that
liquidated damages were rightly levied by the respondent. Such
liquidated damages are in conformity with Section 55 of the Indian
Contract Act, 1872 (briefly ‘the Contract Act’ hereinafter). Respondent
was presented with such a situation by the appellant that it had no
1852 [2025] 4 S.C.R.
Supreme Court Reports
other option but to grant extension of time on account of appellant’s
admitted inability to complete the work within the stipulated time. In the
review meeting held on 18.12.2006, just twenty eight days before the
stipulated date for completion of the work i.e. 15.01.2007, appellant
expressed its inability to complete the work within the stipulated date.
Respondent was left with no option other than to fix a revised date
for completion of the work and grant extension of time.
9.1. Pursuant to the review meeting dated 18.12.2006, respondent
vide letter dated 12.01.2007 had granted the first extension
of time for completion of the contract work upto 28.02.2007.
However, appellant failed to complete the work within this
extended period of time. As a result, respondent was compelled
to grant further extensions of time to the appellant upto
30.06.2007 in order to have the contract work completed. This
was because of appellant’s continued failure to meet even the
revised timelines despite repeated requests and warnings from
the respondent and its architect.
9.2. Learned counsel for the respondent submits that in the review
meeting held on 18.12.2006, appellant was unequivocally
forewarned that grant of extension of time for completion of
the contract work would be without prejudice to the right of
the respondent to recover liquidated damages. Each time
extension was granted it was made clear to the appellant that
such extension of time was without prejudice to the right of the
respondent to recover liquidated damages. Therefore, appellant
had full prior notice of the respondent’s intention to levy liquidated
damages. In the circumstances, it is not open to the appellant
to now contend that the respondent is not entitled to recover
liquidated damages on the ground that time for performance
of the contract was extended.
9.3. Learned counsel has refuted the contention of learned counsel
for the appellant that time was not the essence of the contract.
On the contrary, he asserts that time was very much of essence
for performance of the contract. Because of admitted inability
of the appellant to complete the contract work within time,
respondent was compelled to grant multiple extensions of time
but each time, appellant was forewarned that such extension
of time was without prejudice to the right of the respondent to
recover liquidated damages.
[2025] 4 S.C.R. 1853
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
9.4. Learned counsel has also denied the contention of learned
counsel for the appellant that respondent could not furnish or
show any loss or damage suffered by it because of the delay
in execution of the contract. He submits that the arbitral tribunal
had minutely examined this aspect of the matter and after
considering the evidence on record rejected such contention
of the appellant. Arbitral tribunal held that liquidated damages
were validly deducted; the quantum was fair and reasonable.
9.5. Learned counsel for the respondent, therefore, submits that
the appellate court i.e. Division Bench of the High Court had
rightly set aside the order of the learned Single Judge thereby
restoring the award. Learned Single Judge had set aside the
award in complete disregard to Section 34 of the 1996 Act. He
submits that there is no merit in the appeal. Consequently, the
appeal should be dismissed.
10. Submissions made by learned counsel for the parties have received
the due consideration of the Court.
11. Let us first deal with the award. In this case, the arbitral tribunal
comprised of a sole arbitrator Shri K. Srinivasan. He was appointed as
the arbitrator on 05.01.2009. In the arbitral proceedings, as many as
five claims were made on behalf of the appellant. On the other hand,
the respondent made three counter claims. In so far the appellant is
concerned, the major claim was relating to refund of Rs. 82,43,499.00
deducted by the respondent as liquidated damages. This claim was
framed as issue No. 3 by the arbitral tribunal. In so far respondent
is concerned, it raised counter claims relating to reimbursement of
rent paid by it for the period of delay in completion of the contract
work as well as for loss of rent in the new complex due to delayed
construction. As alluded to hereinabove, issue No. 3 pertains to
claim of the appellant for refund of Rs. 82,43,499.00 deducted by the
respondent as liquidated damages i.e. as compensation for the delay
in execution of the contract. Both appellant and the respondent had
submitted their relied upon documents and advanced their respective
contentions. Arbitral tribunal had framed two questions:
(i) Whether the delay had occurred due to default on
the part of the claimant(appellant)? and
(ii) Whether the respondent was entitled in terms of the
contract to levy liquidated damages for the delay?
1854 [2025] 4 S.C.R.
Supreme Court Reports
11.1. After going through the materials on record, arbitral tribunal
held that respondent had produced documents to show that
the delay in moving to the new premises had caused them
direct financial loss in two ways:
(i) in having to continue to pay rent for ten and half
months in the old premises; and
(ii) in having lost ten and half months in letting out
portions of the new premises on rent.
11.2. Such a loss was on account of the breach of contract by the
appellant. Respondent had established that the loss suffered
by it indeed occurred due to delay in handing over the new
premises. Clause 26 of the contract agreement permitted the
respondent to levy liquidated damages. It also provided as
to how the quantum of liquidated damages should be arrived
at. According to the arbitral tribunal, the quantum was at the
rate of 0.5% per week of delay. Delay in this case was more
than ten months. Bulk of the delay was for reasons within
the control of the appellant. The figure of Rs. 82,43,499.00
was correctly quantified and deducted as liquidated damages
by the respondent. Therefore, the arbitral tribunal held that
the liquidated damages were legally and contractually valid.
It was reasonable compared to the loss occasioned to the
respondent due to default by the appellant. Therefore, arbitral
tribunal held as under:
In view of all that has been stated above I conclude
that recovery of LD was valid contractually and
legally. It was levied by a competent authority and the
levied amount was fair and reasonable. I therefore
award Nil amount against this claim.
11.3. Thereafter, the arbitral tribunal rejected the other claims of
the appellant as well as the counter claims of the respondent.
Summary of the award dated 10.05.2010 reads as under:
In sum therefore I do not find that any of the claims
by the claimant or counter claims by the respondents
have been established and the award is NIL against
all the claims and counter-claims.
[2025] 4 S.C.R. 1855
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
12. Clause 26 of the contract agreement deals with liquidated damages.
Clause 26 reads thus:
26. Liquidated damages
If the contractor fails to complete the work by the date
stated in the Appendix or within any extended time under
clause 28 hereof the contractor shall pay or allow the
employer to deduct the sum named in the Appendix as
“Liquidated Damages” for the period during which the
said works shall remain incomplete and the employer may
deduct such damages from any money due or that may
become due to the contractor.
12.1. Thus, what clause 26 says is that if the contractor fails to
complete the work within the stipulated period or within the
extended time as provided under clause 28 then the employer
shall be entitled to deduct the sum named in the Appendix as
liquidated damages for the period during which the contract
work remained incomplete. The employer may deduct such
liquidated damages from any money due or that may become
due to the contractor.
12.2. In the Appendix, the time for completion was provided as 10
months from the 10th day of the written order to commence
work or after the date on which the site was handed over to
the contractor whichever was later. In so far determination
of liquidated damages is concerned, it was mentioned in the
Appendix that the same would be calculated at the rate of
Rs. 0.5 percent of the contract value per week subject to a
maximum of 5 percent of the value of the contract.
13. Clause 27 provides for extension of time. Clause 27 reads as under:
27. Extension of time
If the contractor shall desire an extension of time for
completion of the work on the grounds of his having been
unavoidably hindered (a) by force majeure or (b) by reason
of any exceptional inclement weather or (c) reason of
any proceedings taken or threatened by or dispute with
adjoining or neighbouring employers or public authorities
arising otherwise than through the contractor’s own
defaults or (d) by the work or delays of other contractors
1856 [2025] 4 S.C.R.
Supreme Court Reports
or tradesmen engaged or nominated by the employer
or the architect and not referred to in the Schedule of
Quantities and/or specifications or (e) by strikes or lockout
affecting any of the building trades or (f) by reason of
delays in the supply of materials stipulated to be supplied
by the employer he shall apply in writing to the architect/
employer within 15 days of such hindrance on account
of which he desires such extension as aforesaid and the
architect/employer, if in his opinion reasonable grounds
have been shown therefor, may make a fair and reasonable
extension of time for completion of the contract works,
but the contractor shall nevertheless constantly use his
endeavours to prevent delay and shall do all that may
reasonably be required of him to proceed with the work
expeditiously provided.
(a) that the contractor shall have no claim other than
extension of time for the delay in completion of the
work due to such hindrance and nothing else and
(b) that the contractor shall suspend the works whenever
called upon to do so in writing by the architect/
employer and shall be allowed reasonable extension
of time for completion of work due to such suspension
of work and nothing else.
13.1. What clause 27 provides for is that if the contractor wants an
extension of time for completion of the work on the ground
that the work has been unavoidably hindered:
(i) by force majeure; or
(ii) by reason of any exceptional inclement weather; or
(iii) by reason of any proceedings taken or dispute etc. with
neighbours otherwise then the contractor’s own default; or
(iv) due to the work or delay of other contractors or tradesmen
engaged or nominated by the employer or the architect; or
(v) by strike or lock out affecting any of the building trades; or
(vi) by reason of delay in supply of materials stipulated to be
supplied by the employer; or
[2025] 4 S.C.R. 1857
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
(vii) if the contractor wanted extension of time, he was required
to apply to the employer/architect for such extension
within the period specified and if the employer/architect
was of the opinion that reasonable grounds were shown,
it would make a fair and reasonable extension of time for
completion of the contract work.
14. Since, there is a reference to clause 28 in clause 26, we may as
well consider clause 28. It deals with consequence of failure of the
contractor to comply with the instructions of the architect or the
employer. Clause 28 reads thus:
28. Failure of contractor to comply with Architect’s/
Employer’s Instructions
If the contractor after receipt of written notice from the
architect/employer requiring compliance within ten days
fails to comply with such further drawings and/or architect/
employer’s instructions the employer may employ and pay
other persons to execute any such work whatsoever that
may be necessary to give effect thereto, and all costs
incurred in connection therewith shall be recoverable from
the contractor by the employer on the certificate of the
architect as a debt or may be deducted by him from any
money due to or become due to the contractor.
15. From a conjoint analysis of clauses 26, 27 and 28 it is evident that if
the contractor fails to complete the work within the stipulated period
or within the extended time as may be provided, he would be liable
to pay liquidated damages which may be deducted by the employer
from any due to be paid by the employer to the contractor. How the
liquidated damages is to be determined is provided in the Appendix
as noted above. If the contract work is hindered beyond the control
of the contractor such as the examples given in clause 27, the
contractor may seek extension of time and if the same is found to be
reasonable, the employer may make a fair and reasonable extension
of time. On a combined reading of the above clauses, a plausible
view may be taken that clause 26 is not controlled by clause 27.
16. What the arbitrator noted in this case is that on a number of occasions,
appellant had sought for time. On each occasion respondent was
compelled to allow the appellant to carry on with the work beyond
1858 [2025] 4 S.C.R.
Supreme Court Reports
the extended time period by granting further extension, reserving its
right to levy liquidated damages. It has come on record that in the
review meeting held on 18.12.2006, respondent had put the appellant
to notice that grant of extension of time for completion of the contract
work would be without prejudice to the right of the respondent to
recover liquidated damages. Though the first extended time limit was
till 28.02.2007, further time had to be granted by the respondent on
a number of occasions thereafter till 30.06.2007, on each occasion
reserving the right to levy liquidated damages.
17. At this stage we may mention that appellant had continued execution
of the work beyond 30.06.2007 and completed the same only
on 30.11.2007 though the last extended period had expired on
30.06.2007. It was only after completion of the contract work that the
appellant wrote letter dated 14.12.2007 to the respondent seeking
extension of time. Respondent issued letter dated 26.09.2008 granting
extension of time. So it was an ex post facto approval on the part
of the respondent. Thus, appellant had continued with the contract
work even after the extended period had expired on 30.06.2007.
Be it stated that all throughout respondent had put the appellant to
notice that notwithstanding extension of time it reserved the right to
levy liquidated damages.
18. Section 55 of the Indian Contract Act says that when a party to a
contract promises to do a certain thing within a specified time but fails
to do so, the contract or so much of it as has not been performed,
becomes voidable at the option of the promisee if the intention of
the parties was that time should be of the essence of the contract.
If time is not the essence of the contract, the contract does not
become voidable by the failure to do such thing on or before the
specified time but the promisee is entitled to compensation from the
promisor for any loss occasioned to him by such failure. Further, if
in case of a contract voidable on account of the promisor’s failure to
perform his promise within the time agreed and the promisee accepts
performance of such promise at any time other than that agreed,
the promisee cannot claim compensation for any loss occasioned
by the non-performance of the promise at the time agreed, unless,
at the time of such acceptance he gives notice to the promisor of
his intention to do so.
19. Sections 73 and 74 deal with consequences of breach of contract.
Heading of Section 73 is compensation for loss or damage caused
[2025] 4 S.C.R. 1859
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
by breach of contract. When a contract is broken, the party who
suffers by such breach is entitled to receive from the party who has
broken the contract compensation for any loss or damage caused to
him thereby which naturally arose in the usual course of things from
such breach or which the parties knew when they made the contract
to be likely to result from the breach of it. On the other hand, Section
74 deals with compensation for breach of contract where penalty
is stipulated for. When a contract is broken, if a sum is mentioned
in the contract as the amount to be paid in case of such breach or
if the contract contains any other stipulation by way of penalty, the
party complaining of the breach is entitled whether or not actually
damage or loss is proved to have been caused thereby, to receive
from the party who has broken the contract reasonable compensation
not exceeding the amount so named or the penalty stipulated for.
20. A conjoint reading of Sections 55, 73 and 74 would indicate that in
a contract whether time is of the essence or not, if the contractor
fails to execute the contract within the specified time, the contract
becomes voidable at the option of the promisee and the promisee
would be entitled to compensation from the promisor for any loss
occasioned to him by such failure. However, in case of a contract
where time is of the essence, the contract becomes voidable on
account of the contractor’s failure to execute the contract within the
agreed time. The promisee cannot claim compensation for any loss
occasioned by such breach of the contract unless he gives notice
to the promisor of his intention to claim compensation. This is made
more specific in Section 73. Section 74 contemplates a situation where
penalty is provided for and quantified as compensation for breach
of contract. In such a case, the party complaining of the breach is
entitled to compensation whether or not actual damage or loss is
proved to have been caused thereby but such compensation shall
not exceed the quantum of penalty stipulated.
21. Before we deal with the order of the learned Single Judge dated
02.01.2019 passed under Section 34 of the 1996 Act, it would be
apposite to advert to Section 34 of the 1996 Act which is as follows:
34. Application for setting aside arbitral award- (1)
Recourse to a court against an arbitral award may be
made only by an application for setting aside such award
in accordance with sub-section (2) and sub-section (3).
1860 [2025] 4 S.C.R.
Supreme Court Reports
(2) An arbitral award may be set aside by the court only if—
(a) the party making the application [establishes on the
basis of the record of the arbitral tribunal that]—
(i) a party was under some incapacity; or
(ii) the arbitration agreement is not valid under the
law to which the parties have subjected it or, failing
any indication thereon, under the law for the time
being in force; or
(iii) the party making the application was not given
proper notice of the appointment of an arbitrator or
of the arbitral proceedings or was otherwise unable
to present his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of
the submission to arbitration, or it contains decisions
on matters beyond the scope of the submission to
arbitration:
Provided that, if the decisions on matters
submitted to arbitration can be separated from
those not so submitted, only that part of the
arbitral award which contains decisions on
matters not submitted to arbitration may be
set aside; or
(v) the composition of the arbitral tribunal or the arbitral
procedure was not in accordance with the agreement
of the parties, unless such agreement was in conflict
with a provision of this part from which the parties
cannot derogate, or, failing such agreement, was not
in accordance with this part; or
(b) the court finds that—
(i) the subject-matter of the dispute is not capable of
settlement by arbitration under the law for the time
being in force, or
(ii) the arbitral award is in conflict with the public
policy of India.
[2025] 4 S.C.R. 1861
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
[Explanation 1.—For the avoidance of any doubt, it is
clarified that an award is in conflict with the public policy
of India, only if,—
(i) the making of the award was induced or affected
by fraud or corruption or was in violation of Section
75 or Section 81; or
(ii) it is in contravention with the fundamental policy
of Indian law; or
(iii) it is in conflict with the most basic notions of
morality or justice.
Explanation 2.—For the avoidance of doubt, the test as
to whether there is a contravention with the fundamental
policy of Indian law shall not entail a review on the merits
of the dispute.]
[(2-A) An arbitral award arising out of arbitration other than
international commercial arbitration, may also be set aside
by the court, if the court finds that the award is vitiated
by patent illegality appearing on the face of the award:
Provided that an award shall not be set aside merely
on the ground of an erroneous application of the law
or by reappreciation of evidence.]
(3) An application for setting aside may not be made after
three months have elapsed from the date on which the
party making that application had received the arbitral
award or, if a request had been made under Section 33,
from the date on which that request had been disposed
of by the arbitral tribunal:
Provided that if the court is satisfied that the applicant
was prevented by sufficient cause from making the
application within the said period of three months it
may entertain the application within a further period
of thirty days, but not thereafter.
(4) On receipt of an application under sub-section (1), the
court may, where it is appropriate and it is so requested
by a party, adjourn the proceedings for a period of time
1862 [2025] 4 S.C.R.
Supreme Court Reports
determined by it in order to give the arbitral tribunal an
opportunity to resume the arbitral proceedings or to take
such other action as in the opinion of arbitral tribunal will
eliminate the grounds for setting aside the arbitral award.
[(5) An application under this section shall be filed by a
party only after issuing a prior notice to the other party and
such application shall be accompanied by an affidavit by the
applicant endorsing compliance with the said requirement.
(6) An application under this section shall be disposed
of expeditiously, and in any event, within a period of one
year from the date on which the notice referred to in sub-
section (5) is served upon the other party.]
22. Sub-section (1) of Section 34 provides that an application may be
made to the competent court for setting aside an arbitral award. This
is the only remedy available for setting aside an arbitral award. The
conditions for setting aside an arbitral award are mentioned in sub-
sections (2) and (2A). Sub-section (2) provides for situations such
as the agreed party was under some incapacity or the arbitration
agreement is not valid under the law or the aggrieved party did not
receive proper notice regarding appointment of arbitrator or of the
arbitral proceedings which prevented it from presenting its case
or the arbitral award deals with a dispute not contemplated by or
not falling within the terms of arbitration or the composition of the
arbitral tribunal or the procedure adopted in arbitration were not in
accordance with the agreement of the parties or the subject matter
of dispute is not capable of settlement by arbitration or the arbitral
award is in conflict within the public policy of India. In terms of sub-
section (2A), an arbitral award may also be set aside on the ground
of patent illegality appearing on the face of the award. Sub-section (3)
provides for the time limit for filing of an application for setting aside
arbitral award. Therefore, the grounds on which an arbitral award
can be set aside are clearly mentioned in Sections 34(2) and 34(2A)
of the 1996 Act. An arbitral award cannot be set aside on a ground
which is beyond the grounds mentioned in sub-sections (2) and (2A)
of Section 34.
23. Scope of Section 34 of the 1996 Act is now well crystallized by a
plethora of judgments of this Court. Section 34 is not in the nature of
[2025] 4 S.C.R. 1863
Consolidated Construction Consortium Limited v.
Software Technology Parks of India
an appellate provision. It provides for setting aside an arbitral award
that too only on very limited grounds i.e. as those contained in sub-
sections (2) and (2A) of Section 34. It is the only remedy for setting
aside an arbitral award. An arbitral award is not liable to be interfered
with only on the ground that the award is illegal or is erroneous in
law which would require re-appraisal of the evidence adduced before
the arbitral tribunal. If two views are possible, there is no scope for
the court to re-appraise the evidence and to take the view other
than the one taken by the arbitrator. The view taken by the arbitral
tribunal is ordinarily to be accepted and allowed to prevail. Thus,
the scope of interference in arbitral matters is only confined to the
extent envisaged under Section 34 of the Act. The court exercising
powers under Section 34 has perforce to limit its jurisdiction within
the four corners of Section 34. It cannot travel beyond Section 34.
Thus, proceedings under Section 34 are summary in nature and
not like a full-fledged civil suit or a civil appeal. The award as such
cannot be touched unless it is contrary to the substantive provisions
of law or Section 34 of the 1996 Act or the terms of the agreement.
24. Therefore, the role of the court under Section 34 of the 1996 Act
is clearly demarcated. It is a restrictive jurisdiction and has to be
invoked in a conservative manner. The reason is that arbitral autonomy
must be respected and judicial interference should remain minimal
otherwise it will defeat the very object of the 1996 Act.
25. Keeping the above in view, let us now deal with the order of the
learned Single Judge dated 02.01.2019 passed under Section 34
of the 1996 Act.
26. In the aforesaid order, learned Single Judge noted that the contract
work was required to be executed within a period of 10 months.
Appellant could not complete the work within the contract period
due to land slides and rains. Ultimately, appellant could complete the
work on 30.11.2007 by seeking extension of time which was granted
by the respondent. There is no complaint about the construction.
Learned Single Judge also noted that there were rains and land
slides during the contract period which is not in dispute. Thereafter,
learned Single Judge observed as under:
If the building had been erected and there were landslides,
it would affect the building constructed and there would
not only have been loss of money, but also loss of lives
1864 [2025] 4 S.C.R.
Supreme Court Reports
and that the 1st respondent should thank the stars that no
untoward event took place.
27. Learned Single Judge also observed that clause 26 of the contract
agreement could not be read in isolation without reference to clause
27. The fact that appellant was allowed to carry on the contract work
and to subsequently complete the same cannot be denied. Once there
is extension of time, there cannot be a narrow interpretation to clause
26. Purpose of extension of time was only for completion of work.
Extension of time and levy of liquidated damages cannot go hand
in hand. Contention of the respondent would have been acceptable
had there been no extension in time or the work remained incomplete
even after the extended period. In such an event, respondent would
have been justified to levy and recover liquidated damages. Once
the appellant had completed the work during the extended period
of time, claim of liquidated damages by the respondent could not
be accepted. Therefore, the arbitral award dated 10.05.2010 was
set aside.
28. We are afraid learned Single Judge had clearly gone beyond the
grounds provided in Section 34 of the 1996 Act to set aside the
arbitral award. Learned Single Judge exceeded the jurisdiction under
Section 34 of the 1996 Act. There was no justification for setting
aside the arbitral award by taking a different view. View taken by the
arbitral tribunal is certainly a possible and plausible view. A different
interpretation of clause 26 other than the one taken by the arbitral
tribunal is possible but that will not bring the challenge to the arbitral
award within the four corners of Section 34. In any view of the matter,
mere setting aside of the arbitral award did not confer any benefit to
the appellant. In the circumstances, the Division Bench was justified
in reversing the order of the learned Single Judge under Section 37
of the 1996 Act.
29. That being the position, we do not find any merit in this appeal.
Consequently, the appeal is dismissed. However, there shall be no
order as to cost.
Result of the case: Appeal dismissed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.