Created byFuzzy Cloud

Supreme Court of India

DELHI ELECTRICITY REGULATORY COMMISSIONversusTATA POWER DELHI DISTRIBUTION LIMITED

Citation
2026 INSC 461
Decided
7 May 2026
Disposal
Appeal(s) allowed

Holding

Depreciation for tariff purposes is confined to the period approved in the PPA and cannot be recovered beyond the operational period, as consumer welfare under s.61(d) of the Electricity Act overrides the technical useful life of the asset.

Summary

The Delhi Electricity Regulatory Commission (Commission) approved a power purchase agreement (PPA) for the Rithala Combined Cycle Power Plant with a six‑year operational period, after which the plant ceased supplying electricity in March 2018. Tata Power Delhi Distribution Limited (TPDDL) later sought to recover the remaining capital cost of the plant by claiming depreciation over its technical useful life of fifteen years, invoking Regulation 6.32 of the 2011 DERC Regulations. The Appellate Tribunal for Electricity (APTEL) allowed this claim, setting aside the Commission’s order that limited depreciation to the six‑year period. The Supreme Court held that tariff determination must balance cost recovery with consumer welfare, and that depreciation cannot be charged beyond the period approved in the PPA. It interpreted Regulation 6.32 harmoniously with Regulation 4.1 and Section 61(d) of the Electricity Act, concluding that the generating utility does not have an absolute right to recover depreciation when the asset is no longer supplying power. Consequently, the Court set aside the APTEL judgment and restored the Commission’s order, limiting depreciation to the six‑year operational period.

Issues considered

  • Whether depreciation under the applicable tariff regulations must necessarily be allowed over the entire technical useful life of an asset irrespective of the period during which the asset is actually utilised for supply of electricity?
  • Whether Regulation 6.32 of the 2011 DERC Regulations confers an absolute right upon the generating utility to recover entire capital cost over the useful life of the asset, even where the asset ceases to supply electricity to the consumer?
  • Whether the APTEL erred in law in disregarding the regulatory framework and approval conditions which limited the operational and recovery period of the Plant to six years?

Legislation cited

Headnote

Issue for Consideration Whether the depreciation under the applicable tariff regulations must necessarily be allowed over the entire technical useful life of an asset irrespective of the period during which the asset is actually utilised for supply of electricity; 2011 Regulations confers an absolute right upon the generating utility to recover entire capital cost over the useful life of the asset, even where the asset ceases to supply electricity to the consumer; whether the APTEL erred in law in disregarding the regulatory framework and approval

Subjects

depreciationtariff determinationconsumer welfarepower purchase agreementgenerating utilitytechnical useful lifeelectricity regulationDERC RegulationsAPTELDelhi Electricity Regulatory Commissioncapital cost recovery

Judgment

                  [2026] 5 S.C.R. 441 : 2026 INSC 461

              Delhi Electricity Regulatory Commission
                                  v.
               Tata Power Delhi Distribution Limited
                        (Civil Appeal No. 6388 of 2025)
                                   07 May 2026
    [Pamidighantam Sri Narasimha and Alok Aradhe,* JJ.]


                             Issue for Consideration
       Whether the depreciation under the applicable tariff regulations
       must necessarily be allowed over the entire technical useful life
       of an asset irrespective of the period during which the asset is
       actually utilised for supply of electricity; whether Regulation 6.32
       of 2011 Regulations confers an absolute right upon the generating
       utility to recover entire capital cost over the useful life of the asset,
       even where the asset ceases to supply electricity to the consumer;
       whether the APTEL erred in law in disregarding the regulatory
       framework and approval conditions which limited the operational
       and recovery period of the Plant to six years.

                                    Headnotes†
       Electricity Act, 2003 – ss.61(d), 62 – DERC (Terms and
       Conditions for Determination of Generation Tariff) Regulations,
       2011 – Regulations 6.30-6.32, 4.1 – APTEL set aside the order
       passed by the Delhi Electricity Regulatory Commission and
       directed that entire capital cost of Rithala Combined Cycle
       Power Plant at Rithala, Delhi (the Plant) be recovered through
       depreciation over a period of fifteen years notwithstanding the
       admitted fact that the Plant ceased to supply electricity to the
       consumers from and after March-2018 – Challenge to – Whether
       the depreciation under the applicable tariff regulations must
       necessarily be allowed over the entire technical useful life of
       an asset irrespective of the period during which the asset is
       actually utilised for supply of electricity:
       Held: Tariff determination is not merely a mathematical exercise
       but a regulatory balancing act – The object of enabling reasonable
       cost recovery for utilities must be weighed against and calibrated
       with, paramount obligation to safeguard consumer interest – In
* Author
442                                                              [2026] 5 S.C.R.

                            Supreme Court Reports


       the instant case, admittedly, electricity has not been supplied to
       the consumers beyond March-2018 – The consumers cannot be
       required to pay for a service which they no longer received – Under
       the PPA, TPDDL (Tata Power Delhi Distribution Limited) had to
       supply electricity only for a period of six years – The Commission
       had clarified to the Managing Director of TPDDL that the plant could
       be treated as a merchant generator which is free to sell the power
       anywhere other than to the distribution utilities in Delhi or outside
       the State or to captive consumers within the State – There was no
       legal impediment to either sale of the Plant or sale of electricity as
       a merchant generator – Therefore, TPDDL cannot be permitted to
       burden the consumers with tariff charges beyond March-2018 –
       Therefore, the first substantial question of law is answered in the
       negative – Impugned judgment passed by the APTEL is set aside,
       order passed by the Commission is restored. [Paras 20, 23]

       Electricity Act, 2003 – ss.61(d), 62 – DERC (Terms and
       Conditions for Determination of Generation Tariff) Regulations,
       2011 – Regulations 6.30-6.32, 4.1 – Whether Regulation 6.32 of
       2011 Regulations confers an absolute right upon the generating
       utility to recover entire capital cost over the useful life of the
       asset, even where the asset ceases to supply electricity to
       the consumer:
       Held: No – Regulation 6.32 of 2011 Regulations prescribes the
       methodology of calculating depreciation over the useful life of
       the asset – No provision has to be read in isolation – Regulation
       6.32 of 2011 Regulations must be construed harmoniously with
       Regulation 4.1 of 2011 Regulations, which mandates that the tariff
       for supply of electricity by a generating company to a distribution
       licensee is to be determined in accordance with PPA or any other
       arrangement for such period as may be approved or adopted by the
       Commission, to the extent of existing installed capacity contained
       in the PPA – Regulation 4.1 of 2011 Regulations confines tariff
       entitlement to the period approved in the PPA – The order dated
       31.08.2017 fixed the operational and recovery framework of the
       plant up to March-2018 – The 2011 Regulations have to be read in
       conjunction with s.61(d) of the 2003 Act which places the consumer
       interest at the centre of tariff Regulation – Thus, Regulation 6.32 of
       the 2011 Regulations does not, and cannot, override the broader
       statutory and regulatory framework and the same does not confer
[2026] 5 S.C.R.                                                                443

               Delhi Electricity Regulatory Commission v.
                 Tata Power Delhi Distribution Limited

     an absolute and unconditional right upon the generating utility to
     recover depreciation from the consumers even for a period when
     the asset is free to supply electricity. [Para 21]

     Electricity Act, 2003 – ss.61(d), 62 – DERC (Terms and
     Conditions for Determination of Generation Tariff) Regulations,
     2011 – Whether the APTEL erred in law in disregarding the
     regulatory framework and approval conditions which limited
     the operational and recovery period of the Plant to six years:
     Held: GNCTD granted permission on a temporary basis for
     a period 5 to 6 years – The TPDDL was directed to obtain all
     necessary regulatory approvals before commencing generation –
     The Commission in its order dated 31.08.2017, which was not
     challenged by TPDDL, approved the PPA only for a period of six
     years from the date of commercial operation till March-2018 –
     APTEL ought to have appreciated that distinction between 15
     years technical useful life and 6 years regulatory recovery period
     is not merely semantic but the tariff framework drew the distinction
     clearly – APTEL’s approach is inconsistent with the order dated
     31.08.2017, which was accepted by TPDDL and had attained
     finality – The True-up proceedings are intended to give effect to
     tariff framework and not to reopen or reconfigure it – APTEL erred,
     therefore, in disregarding the regulatory framework and conditions
     of approval – Therefore, the third substantial question of law, is
     answered in the affirmative – The substantial questions of law which
     arise for consideration in this appeal, are answered in favour of the
     Commission and against the TPDDL – Impugned judgment dated
     10.02.2025 passed by the APTEL is set aside and order dated
     11.11.2019 passed by the Commission is restored. [Paras 22, 23]

     Electricity Act, 2003 – s.61 – Tariff Determination – Consumer
     welfare, a central and guiding statutory principle:
     Held: s.61 of the 2003 Act governs the determination of tariff – s.61(d)
     specifically provides that in specifying the terms and conditions
     for the determination of tariff, the Appropriate Commission shall
     be guided, inter alia, by the object of safeguarding consumers’
     interests and at the same time, recovery of the cost of electricity
     in a reasonable manner – This provision establishes consumer
     welfare not as a peripheral consideration but as a central and
     guiding statutory principle in tariff determination. [Para 15]
444                                                             [2026] 5 S.C.R.

                            Supreme Court Reports


                                Case Law Cited
       BSES Rajdhani Power Ltd. & Anr. v. Union of India & Ors.,
       2025 SCC OnLine SC 1637 – referred to.

                                  List of Acts
       Electricity Act, 2003, DERC (Terms and Conditions for Determination
       of Generation Tariff) Regulations, 2011; Code of Civil Procedure,
       1908.

                               List of Keywords
       Depreciation under applicable tariff regulations; Entire technical
       useful life of an asset; Rithala Combined Cycle Power Plant at
       Rithala, Delhi; Plant ceased to supply electricity to the consumers;
       Sections 61(d), 62, Electricity Act, 2003; Generating utility; Entire
       capital cost; Useful life of the asset.

                              Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6388 of 2025
       From the Judgment and Order dated 10.02.2025 of the Appellate
       Tribunal for Electricity at New Delhi in AN No. 33 of 2020.

                           Appearances for Parties
       Advs. for the Appellant(s):
       Jayant K. Mehta, Sr. Adv., Dhananjay Baijal, Ms. Mansvini Jain,
       Tilak Singh.
       Advs. for the Respondent(s):
       Kapil Sibal, Sr. Adv., Amit Kapur, Anupam Varma, Rahul Kinra, Aditya
       Gupta, Girdhar Gopal Khattar, Yash Srivastava, Pukhrambam
       Ramesh Kumar, Karun Shamra, Ms. Anupama Ngangom,
       Ms. Rajkumari Divyasana.

                  Judgment / Order of the Supreme Court

                                   Judgment

       Alok Aradhe, J.

1.     This appeal under Section 125 of the Electricity Act, 2003, (2003 Act)
       preferred by Delhi Electricity Regulatory Commission (Commission)
[2026] 5 S.C.R.                                                             445

               Delhi Electricity Regulatory Commission v.
                 Tata Power Delhi Distribution Limited

     challenges the correctness and legality of the judgment and order
     dated 10.02.2025 passed by the Appellate Tribunal for Electricity
     (APTEL). By the impugned judgment, APTEL has set aside the
     order dated 11.11.2019 passed by the Commission and issued the
     direction that entire capital cost of Rithala Combined Cycle Power
     Plant at Rithala, Delhi (the Plant) be permitted to be recovered
     through depreciation over a period of fifteen years notwithstanding
     the admitted fact that the Plant ceased to supply electricity to the
     consumers from and after March-2018.
2.   The facts giving rise to this litigation though substantially not in dispute,
     are required to be set out, in order to appreciate the competing legal
     submissions advanced before us.

     FACTUAL MATRIX
3.   The respondent, Tata Power Delhi Distribution Limited (TPDDL) is a
     joint venture entity between the Tata Power Company Limited and
     Delhi Power Company Limited. On 11.06.2007, TPDDL moved a
     proposal for allotment of land at Rithala for setting up a temporary
     108-megawatts Gas-based Power Plant with operational tenure
     expressly limited to 5 to 6 years, following which the land would
     revert to the Delhi Development Authority (DDA). The genesis of
     the project lay in the pressing and urgent need to augment power
     supply in the National Capital Territory of Delhi in the lead-up to the
     Commonwealth Games 2010. The Plant was conceived as a short-
     term measure to address peak demand and accordingly, approval
     was structured within a limited operational horizon. On 24.07.2007,
     TPDDL addressed the letter to the DDA seeking change of land use
     specifically for a short-term 5 to 6 years operational span of the Plant.
4.   On 17.05.2008, TPDDL intimated Commission of its intention to
     establish and operate the Plant. The Commission sometime in
     April-2009 granted in principle approval for the scheme based on
     TPDDL’s proposal submitted in the year 2008. On 27.07.2009,
     Generation and Distribution divisions of TPDDL executed an intra
     company “Terms and conditions for sale and purchase of power
     for the Plant”. The TPDDL on 21.08.2009 filed a petition namely,
     petition no. 11 of 2009, before the Commission under Section 62
     read with Section 86 (1)(b) of the 2003 Act, seeking approval of the
     said terms and conditions. A second petition namely, petition no. 7
     of 2010, was filed on 26.02.2010, seeking approval for the use of
446                                                            [2026] 5 S.C.R.

                           Supreme Court Reports


       6 acres land for setting up 108-megawatts Power Generation Plant
       at Rithala, New Delhi. A third petition namely, petition no. 6 of 2013,
       was filed by TPDDL on 23.11.2012, seeking determination of the
       final generation tariff from the Plant.
5.     The Plant achieved commercial operation in open cycle mode
       on 04.02.2011 and in combined cycle mode on 04.09.2011. The
       Commission disposed of all the three petitions filed by TPDDL by a
       common order dated 31.08.2017, the details of which are as follows:
       (i)    The Commission allowed petition no. 11 of 2009 to the extent of
              permission granted by Government of National Capital Territory
              of Delhi (GNCTD) for a period of six years from the year of
              commissioning of the Plant in combined cycle mode, thereby
              fixing the operation and supply period up to March-2018.
       (ii)   The Commission allowed petition no. 7 of 2010 subject to the
              condition that any profits from the Plant would be governed
              by provisions of DERC (Treatment of Income from Other
              Business of Transmission Licensee and Distribution Licensee)
              Regulations, 2005.
       (iii) The Commission allowed petition no. 6 of 2013 and approved
             the fixed charges and operational parameters required for
             computation of energy charges and directed the TPDDL to
             file true-up petitions for finalisation of generation tariff for the
             respective years.
6.     The Commission by its order dated 31.08.2017, determined the
       capital cost of the Plant at ₹197.70 crores after applying appropriate
       benchmarking and prudence checks as against the TPDDL’s claimed
       capital cost of ₹320.17 crores. It is noteworthy that the said capital
       cost determination was made in the backdrop of six years operational
       framework. The Commission accepted a technical useful life of the
       Plant of fifteen years based on experts certification, and it restricted
       the operational and tariff recovery framework to a period of six years.
       The Plant was thus allowed to operate for supply purposes only till
       March-2018. The TPDDL did not challenge the aforesaid order by
       way of an appeal and therefore the order dated 31.08.2017 has
       become final and binding inter-parties.
7.     Subsequently, TPDDL filed a petition namely, petition no. 51 of 2017,
       seeking true-up of expenditure for Financial Years 2010-2011 to 2016-
[2026] 5 S.C.R.                                                        447

               Delhi Electricity Regulatory Commission v.
                 Tata Power Delhi Distribution Limited

     2017 and the annual requirements for Financial Year 2017-2018. The
     Commission, by an order dated 11.11.2019, allowed depreciation at
     the rate of 6% per annum in respect of the Plant only up to Financial
     Year 2017-2018 resulting in cumulative depreciation of ₹83.34 crores.
     The remaining capital cost of approximately ₹94.59 crores together
     with carrying cost, was not allowed to be passed through in tariff,
     on the ground that Plant has ceased to supply electricity to the
     consumers after March-2018.
8.   The aforesaid order of the Commission was challenged by TPDDL
     in an appeal. The APTEL by an order dated 10.02.2025 inter alia
     held that the Commission itself had fixed the useful life of the Plant
     at fifteen years and had computed the capital cost on that basis.
     Therefore, the depreciation cost cannot be restricted only to six
     years. The APTEL further held that Regulation 6.32 of the DERC
     (Terms and Conditions for Determination of Generation Tariff)
     Regulations, 2011 (2011 Regulations) mandated depreciation over
     the useful life and did not admit of any exception. The APTEL,
     therefore, set aside the order of the Commission and remanded
     the matter to it with a direction to allow recovery of entire capital
     cost of the Plant by way of depreciation over the useful life of the
     Plant for fifteen years.
9.   Aggrieved by the said judgment the Commission has preferred the
     present appeal.

     SUBMISSIONS
10. Learned senior counsel for the Commission submitted that APTEL
    erred in not appreciating that TPDDL cannot recover the capital cost
    of the Plant either from the distribution licensee or from the retail
    consumers of Delhi, in respect of electricity not supplied and to fasten
    the liability on the consumers for a period beyond March-2018 is
    contrary to Section 61 (d) of the 2003 Act. It is contended that APTEL
    misapplied Regulation 6.32 of 2011 Regulations and ought to have
    appreciated that TPDDL was free to exploit the Plant beyond six
    years to recover its capital cost. It is, therefore, submitted that the
    impugned order be set aside and the appeal be allowed.
11. Learned senior counsel for the TPDDL, on the other hand, submitted
    that TPDDL is entitled to recover depreciation in terms of Regulation
448                                                                        [2026] 5 S.C.R.

                               Supreme Court Reports


       6.32 of 2011 Regulations, as the same does not restrict depreciation
       only to the operational life or the duration of the Power Purchase
       Agreement (PPA). It is contended that TPDDL is only seeking to
       recover balance recovery of depreciable capital cost of the Plant.
       It is urged that Commission must abide by and implement the
       directions of APTEL to secure accountability and disproportionate
       increase and long pending regulatory asset depict a regulatory
       failure which has serious consequences on all stakeholders and
       the ultimate burden is only on the consumer1. It is urged that
       the order of the APTEL does not call for any interference in this
       appeal.

       ISSUES
12. We have considered the rival submissions on both sides and have
    perused the record. Section 125 of the 2003 Act provides for a
    remedy of appeal to an aggrieved person from the decision or order
    of APTEL to this Court, on any one or more of the grounds specified
    in Section 100 of the Code of Civil Procedure, 1908.
13. Upon consideration of the pleadings, the record of the proceedings
    before the Commission and APTEL, and the submissions of learned
    counsel for the parties, following substantial questions of law arise
    for determination in this appeal:
       (i)    Whether the depreciation under the applicable tariff regulations
              must necessarily be allowed over the entire technical useful life
              of an asset irrespective of the period during which the asset is
              actually utilised for supply of electricity?
       (ii)   Whether Regulation 6.32 of 2011 Regulations confers an
              absolute right upon the generating utility to recover entire capital
              cost over the useful life of the asset, even where the asset
              ceases to supply electricity to the consumer?
       (iii) Whether the APTEL erred in law in disregarding the regulatory
             framework and approval conditions which limited the operational
             and recovery period of the Plant to six years?




1   BSES Rajdhani Power Ltd. & Anr. v. Union of India & Ors., 2025 SCC OnLine SC 1637
[2026] 5 S.C.R.                                                          449

               Delhi Electricity Regulatory Commission v.
                 Tata Power Delhi Distribution Limited

     STATUTORY FRAMEWORK
14. Before proceeding further, it is useful to set out the statutory and
    regulatory provisions that have bearing on the questions which arise
    for consideration in this appeal.
15. Section 61 of the 2003 Act governs the determination of tariff.
    Section 61(d) specifically provides that in specifying the terms and
    conditions for the determination of tariff, the Appropriate Commission
    shall be guided, inter alia, by the object of safeguarding consumers’
    interests and at the same time, recovery of the cost of electricity in a
    reasonable manner. This provision establishes consumer welfare not
    as a peripheral consideration but as a central and guiding statutory
    principle in tariff determination.
16. Section 62 of the 2003 Act empowers the Commission to determine
    tariff for supply of electricity by a generating company to a distribution
    licensee, in accordance with the provisions of the 2003 Act and the
    Regulations made thereunder.
17. Regulations 6.30 to 6.32 of the DERC (Terms and Conditions for
    Determination of Generation Tariff) Regulations, 2011 provides as
    follows:
           “6.30 Depreciation shall be calculated for each year of
           the Control Period, on the amount of Capital Cost of the
           Fixed Assets as admitted by the Commission; Provided
           that depreciation shall not be allowed on assets funded
           by any capital subsidy/grant.
           6.31 Depreciation for each year of the Control Period shall
           be determined based on the methodology as specified in
           these Regulations along with the rates and other terms
           specified in Appendix-1 of these Regulations.
           6.32 Depreciation shall be calculated annually, based on
           the straight line method, over the useful life of the asset.
           The base value for the purpose of depreciation shall be
           capital cost of the asset as admitted by the Commission.
           Provided that, the remaining depreciable value as on 31st
           March of the year closing after a period of 12 years from
           the date of commercial operation shall be spread over the
           balance useful life of the assets.”
450                                                          [2026] 5 S.C.R.

                           Supreme Court Reports


18. Regulation 4.1 of the 2011 Regulations mandates that the tariff for
    supply of electricity by the generating company to the distribution
    licensee shall be in accordance with the PPA or any other
    arrangement for such period as may be approved or adopted by
    the Commission, to the extent of the existing installed capacity as
    contained in the PPA.

       ANALYSIS AND FINDINGS

       Question No. (i)
19. The Commission while computing the capital cost of the Plant for
    determination of final generation tariff, by an order dated 31.08.2017,
    found that useful life of the Plant is fifteen years. However, the
    Commission vide order dated 31.08.2017, approved the PPA which
    restricted the period of operation and supply up to March-2018, i.e.,
    for a period of six years. Admittedly, a sum ₹83.34 crores has been
    approved as depreciation for the aforesaid period of six years.
20. The tariff determination is not merely a mathematical exercise but
    a regulatory balancing act. The object of enabling reasonable cost
    recovery for utilities must be weighed against and calibrated with,
    paramount obligation to safeguard consumer interest. In the instant
    case, admittedly, electricity has not been supplied to the consumers
    beyond March-2018. The consumers cannot be required to pay for a
    service which they no longer received. Under the PPA, TPDDL had
    to supply electricity only for a period of six years. It is also pertinent
    to note that the Commission on 04.09.2012, had clarified to the
    Managing Director of TPDDL that the plant could be treated as a
    merchant generator which is free to sell the power anywhere other
    than to the distribution utilities in Delhi or outside the State or to
    captive consumers within the State. There was no legal impediment to
    either sale of the Plant or sale of electricity as a merchant generator.
    Therefore, TPDDL cannot be permitted to burden the consumers with
    tariff charges beyond March-2018. Therefore, the first substantial
    question of law is answered in the negative.

       Question No. (ii)
21. Regulation 6.32 of 2011 Regulations prescribes the methodology
    of calculating depreciation over the useful life of the asset. It is a
    settled canon of statutory interpretation that no provision has to
[2026] 5 S.C.R.                                                         451

               Delhi Electricity Regulatory Commission v.
                 Tata Power Delhi Distribution Limited

     be read in isolation. Regulation 6.32 of 2011 Regulations must be
     construed harmoniously with Regulation 4.1 of 2011 Regulations,
     which mandates that the tariff for supply of electricity by a generating
     company to a distribution licensee is to be determined in accordance
     with PPA or any other arrangement for such period as may be
     approved or adopted by the Commission, to the extent of existing
     installed capacity contained in the PPA. Regulation 4.1 of 2011
     Regulations confines tariff entitlement to the period approved in the
     PPA. The order dated 31.08.2017 fixed the operational and recovery
     framework of the plant up to March-2018. The 2011 Regulations
     have to be read in conjunction with Section 61(d) of the 2003 Act
     which places the consumer interest at the centre of tariff Regulation.
     Thus, Regulation 6.32 of the 2011 Regulations does not, and cannot,
     override the broader statutory and regulatory framework and the
     same does not confer an absolute and unconditional right upon the
     generating utility to recover depreciation from the consumers even
     for a period when the asset is free to supply electricity. For the
     aforementioned reasons, the substantial question of law no. (ii) is
     also answered in the negative.

     Question No. (iii)
22. The GNCTD granted permission on a temporary basis for a period 5
    to 6 years. The TPDDL was directed to obtain all necessary regulatory
    approvals before commencing generation. The Commission in its
    order dated 31.08.2017, which was not challenged by TPDDL,
    approved the PPA only for a period of six years from the date of
    commercial operation till March-2018. The APTEL ought to have
    appreciated that distinction between 15 years technical useful life
    and 6 years regulatory recovery period is not merely semantic
    but the tariff framework drew the distinction clearly. The APTEL’s
    approach is inconsistent with the order dated 31.08.2017, which
    was accepted by TPDDL and had attained finality. The True-up
    proceedings are intended to give effect to tariff framework and
    not to reopen or reconfigure it. The APTEL erred, therefore, in
    disregarding the regulatory framework and conditions of approval.
    Therefore, the third substantial question of law, is answered in the
    affirmative.
23. For the foregoing reasons, the substantial questions of law which
    arise for consideration in this appeal, are answered in favour of
452                                                       [2026] 5 S.C.R.

                              Supreme Court Reports


       the Commission and against the TPDDL. The impugned judgment
       dated 10.02.2025 passed by the APTEL is set aside and order dated
       11.11.2019 passed by the Commission is restored.
24. In the result, appeal is allowed. There shall be no order as to costs.

       Result of the case: Appeal allowed.




       †
           Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "depreciation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.