Created byFuzzy Cloud

Supreme Court of India

JAIPUR VIDYUT VITRAN NIGAM LTD. & ORS.versusADANI POWER RAJASTHAN LTD. & ANR.

Citation
2025 INSC 770
Decided
23 May 2025
Disposal
Dismissed

Holding

The Coal India notification is a change in law event under Article 10.2.1, entitling the generator to compensation from the date of the notification, and Article 10.5.1(ii) does not apply; the appeal is dismissed.

Summary

The dispute arose from a Coal India notification dated 19‑12‑2017 imposing Evacuation Facility Charges (EFC) on coal dispatches, which the power generator (Adani Power Rajasthan Ltd.) claimed constituted a "change in law" under the Power Purchase Agreement (PPA) with the Rajasthan distribution companies. The generator sought compensation and carrying cost from the date of the notification, while the appellants argued that the change should be treated under Article 10.5.1(ii) and that a supplementary bill should have been raised earlier. The Supreme Court held that the CIL notification is a change in law event under Article 10.2.1, entitling the generator to compensation from the notification date, and that Article 10.5.1(ii) does not apply because there is no judicial interpretation involved. The Court further affirmed that a supplementary bill may be raised after adjudication and rejected the appellants' claim for denial of carrying cost. Consequently, the appeal was dismissed.

Issues considered

  • Whether the Coal India notification imposing Evacuation Facility Charges amounts to a "change in law" under Article 10 of the PPA.
  • Whether Article 10.5.1(ii) of the PPA applies to the present facts, i.e., whether the change is due to a judicial or governmental interpretation.
  • Whether the generator is entitled to compensation and carrying cost (Late Payment Surcharge) from the date of the notification.
  • Whether a supplementary bill must be raised before the entitlement to compensation can be enforced.

Legislation cited

Headnote

Issue for Consideration Issue pertains to whether the notification by the Coal India imposing Evacuation Facility Charges constituted a change in law under the Power Purchase Agreement; and as regards the interpretation of Article 10.2.1 vis-à-vis Article 10.5 of the PPA with Headnotes† Electricity Act, 2003 – Power Purchase Agreement – Art.10 – Principles for computing impact of Change in Law – Tariff Adjustment Payment on account of Change in Law – Power Purchase Agreement between the appellants-Discoms and respondent

Subjects

Evacuation Facility ChargesChange in lawPower Purchase AgreementPrinciples for computing impact of Change in LawTariff Adjustment PaymentElectricity Regulatory CommissionLate Payment Surcharge ratesAdditional chargesCompensationRestitutionary principleCut-off datePrinciple of restitutionMonthly tariff paymentSupplementary bill

Judgment

                 [2025] 5 S.C.R. 2486 : 2025 INSC 770

               Jaipur Vidyut Vitran Nigam Ltd. & Ors.
                                  v.
                 Adani Power Rajasthan Ltd. & Anr.
                       (Civil Appeal No. 4336 of 2025)
                                 23 May 2025
              [M.M. Sundresh* and Rajesh Bindal, JJ.]


                            Issue for Consideration
       Issue pertains to whether the notification by the Coal India imposing
       Evacuation Facility Charges constituted a change in law under the
       Power Purchase Agreement; and as regards the interpretation
       of Article 10.2.1 vis-à-vis Article 10.5 of the PPA with specific
       reference to 10.5.1(ii).

                                   Headnotes†
       Electricity Act, 2003 – Power Purchase Agreement – Art.10 –
       Principles for computing impact of Change in Law – Tariff
       Adjustment Payment on account of Change in Law – Power
       Purchase Agreement between the appellants-Discoms and
       respondent No.1-Power Generator for the supply of 1200 MW
       power – Issuance of Notification by Coal India imposing a levy
       of Evacuation Facility Charges – Next day, respondent No.1
       informed appellants that the Notification constituted a ‘change
       in law’ event – Respondent no.1 then filed a Petition before
       the Electricity Regulatory Commission – Some reliefs allowed,
       and against refusal of some of the claims, the respondent
       No.1 filed an appeal – Appellate tribunal allowed the delay in
       filing and re-filing of the appeal – Appellate tribunal held that
       the Notification would amount to a change in law, and the
       respondent No.1 would be entitled to the grant of compensation
       from the date of the Notification along with carrying cost at
       Late Payment Surcharge rates and remanded the matter to the
       Commission for computation of the amounts – Challenge to:
       Held: All such additional charges which are payable on account
       of orders, directions, notifications, regulations, etc. issued by the
       instrumentalities of the State, after the cut-off date, will have to



* Author
[2025] 5 S.C.R.                                                                 2487

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                    Adani Power Rajasthan Ltd. & Anr.

     be considered to be “change in law” events – Generators would
     be entitled to compensation on the restitutionary principle on such
     changes occurring after the cut-off date – Art.10.2.1 in the PPA was
     incorporated based on the principle of restitution, to compensate the
     affected party in order to restore it to the same economic position,
     but for the change in law – This particular provision is a substantive
     one, which in a normal circumstance, has to be given effect to in
     letter and spirit – Under Art.10.5.1(i) of the PPA, the adjustment in
     monthly tariff payment shall become effective from the date notified
     in the change in law – Art. 10.5.1(ii) of the PPA emerge where there
     is an adjudication by way of an order/judgment of a competent
     Court or Tribunal or an Indian Governmental Instrumentality, is not
     applicable to the facts of the instant case since there is no change
     in law which has occasioned by way of an interpretation given by
     a Court or a Tribunal or an Indian Governmental Instrumentality –
     Thus, no reason to interfere with the impugned judgment – Liability
     has been fastened upon the appellants under the agreement –
     Submission that the supplementary bill ought to have been raised
     earlier and, thus, the payment can only be made thereafter has
     neither a factual basis nor a legal one. [Paras 18, 21-25, 28]

                                Case Law Cited
     GMR Warora Energy Ltd. v. CERC [2023] 8 SCR 183 : (2023) 10
     SCC 401; Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power
     Ltd. [2019] 4 SCR 487 : (2019) 5 SCC 325; Uttar Haryana Bijli
     Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd. [2022] 11 SCR
     102 : (2023) 2 SCC 624 – relied on.
     Prem Cottex v. Uttar Haryana Bijli Vitran Nigam Ltd. [2021] 8 SCR
     645 : (2021) 20 SCC 200 – referred to.

                                  List of Acts
     Electricity Act, 2003; Code of Civil Procedure, 1908.

                               List of Keywords
     Evacuation Facility Charges; Change in law; Power Purchase
     Agreement; Principles for computing impact of Change in Law;
     Tariff Adjustment Payment; Electricity Regulatory Commission;
     Late Payment Surcharge rates; Additional charges; Compensation;
     Restitutionary principle; Cut-off date; Principle of restitution; Monthly
     tariff payment; Supplementary bill.
2488                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


                           Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4336 of 2025
     From the Judgment and Order dated 18.04.2024 of the Appellate
     Tribunal for Electricity at New Delhi in AN No. 237 of 2023

                        Appearances for Parties
     Advs. for the Appellants:
     Shyam Divan, Sr. Adv., Kartik Seth, Ms. Shriya Gilhotra, Raghav
     Sharma, Saurabh Chaturvedi, Chiranjeev Sharma, M/S. Chambers
     of Kartik Seth.
     Advs. for the Respondents:
     Dr. A.M. Singhvi, Sr. Adv., Mahesh Agarwal, Amit Kapur,
     Ms. Poonam Sengupta, Arshit Anand, Shashwat Singh, Saunak
     Rajguru, Subham Bhut, Siddharth Seem, E. C. Agrawala.

                Judgment / Order of the Supreme Court

                                Judgment

     M.M. Sundresh, J.

1.   Admit.
2.   We have heard the learned Senior Counsel, Mr. Shyam Divan and
     learned Counsel, Mr. Karthik Seth appearing for the appellants and
     the learned Senior Counsel, Dr. Abhishek Manu Singhvi appearing
     for the respondent No. 1, at length. All the relevant documents,
     including the written submissions of the parties, have been perused.
3.   In pursuance of the Letter of Intent issued to Adani Power Rajasthan
     Ltd. (respondent No.1-Power Generator), on 17.12.2009, a Power
     Purchase Agreement (hereinafter referred to as the “PPA”) dated
     28.01.2010 was entered into between appellant Nos.1, 2 and 3,
     who are the Rajasthan Discoms engaged in the distribution and
     supply of electricity, on one side and respondent No.1 on the other,
     for the supply of 1200 MW Aggregate Contracted Capacity at a
     levelized tariff of Rs.3.238 per unit. The same was duly approved
     by respondent No.2.
4.   While the agreement was in operation, a Notification came to be
     issued at the instance of M/s. Coal India Limited (hereinafter referred
[2025] 5 S.C.R.                                                      2489

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                   Adani Power Rajasthan Ltd. & Anr.

     to as “CIL”), dated 19.12.2017, imposing a levy of Evacuation
     Facility Charges (hereinafter referred to as the “EFC”) with effect
     from 20.12.2017. Immediately, on the very next day i.e. 20.12.2017,
     respondent No.1 informed appellant No. 4 that the Notification dated
     19.12.2017 constituted a ‘change in law’ event. The Notification dated
     19.12.2017 is extracted below:

           “COAL INDIA LIMITED
           A Maharatna Company
           (A Govt. of India Enterprise)
           COAL BHAWAN
           Sales & Marketing Division
           Ground & Floor, Premises No, 04 MAR, Plot No. AF-III,
           Action Area -1A
           Rajarhat, New Town, Kolkata - 700156
           Phone: 033-71104143, Fax: 033-23244229, Website:
           ………………………………
           CIN: L23 L09WB1973GO1028844

           PRICE NOTIFICATION: CIL:S&M: GM(F)Pricing 2017/
           1005 dated 19th Dec. 2017
           Charge of Rs. 50 (Fifty) per tonne shall be levied as
           ‘Evacuation Facility Charges’ on all despatches except
           despatch through rapid loading arrangement. This is
           effective from 00:00 hour of 20” Dec. 2017. This issues
           with the approval of the competent authority.
                                           General Manager (M&S)
                                               Marketing & Sales”

5.   On its failure in eliciting a suitable reply, respondent No.1 filed a
     Petition bearing No.1373/2018 before the Rajasthan Electricity
     Regulatory Commission (hereinafter referred to as the “RERC”),
     invoking Section 86 of the Electricity Act, 2003 (hereinafter referred
     to as the “2003 Act”) read with Article 10 of the PPA. While rejecting
     some of the reliefs, the RERC did allow some of the other prayers
2490                                                       [2025] 5 S.C.R.

                        Supreme Court Reports


     sought for by respondent No.1. Against the refusal of some of the
     claims, the respondent No. 1 filed an appeal before the Appellate
     Tribunal for Electricity (hereinafter referred to as the “APTEL”).
6.   The appeal under Section 111 of the 2003 Act was so made along
     with an application seeking condonation of delay of 332 days in filing.
     Another application was filed seeking to condone the delay of 236
     days in re-filing the appeal. Upon hearing both sides, the aforesaid
     applications were allowed and, thereafter, the appeal was decided on
     merits. It is pertinent to note that the common order by the APTEL,
     dated 23.01.2023, condoning the delay on both counts, has attained
     finality for want of further challenge.
7.   The APTEL, inter alia, held by its judgment dated 18.04.2024, after
     elaborately considering the submissions made by both sides, that the
     Notification dated 19.12.2017 would amount to a change in law, and
     the respondent No. 1 would be entitled to the grant of compensation
     from the date of the Notification, by taking note of the decision
     rendered by this Court in GMR Warora Energy Ltd. v. CERC (2023)
     10 SCC 401 (hereinafter referred to as “GMR Warora”) which, in
     turn, also placed reliance upon the earlier decisions of this Court.
     While doing so, it also took into consideration, the fair submission
     made on behalf of the appellants that the principal issue of levy of
     EFC, and consequently, the date from which the respondent No. 1
     would be entitled to the grant of compensation, is covered by the
     aforementioned judgement. Further reliance was placed on the said
     decision by the APTEL, for the purpose of granting carrying cost at
     the rate of Late Payment Surcharge (hereinafter referred to as “LPS”),
     on a compounding basis, which is to be reckoned from the date of
     the Notification. The submission made by the appellants before the
     APTEL that a supplementary bill is mandatory before seeking relief
     for the LPS was also considered and rejected. Once again, the
     impact of delay was argued and considered with specific reference
     to carrying cost. Accordingly, the following conclusion was arrived at:

          “X.CONCLUSION:
          The Appellant shall, in terms of what has been indicated
          hereinabove, be entitled for the benefit of the change in law
          event on account of evacuation facility charges from the
          date on which the notification, issued by Coal India Limited,
          was made applicable to them. The sum representing this
[2025] 5 S.C.R.                                                          2491

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                   Adani Power Rajasthan Ltd. & Anr.

           benefit shall be paid by Respondents 2 to 5 to the appellant
           along with carrying cost at LPS rates. While the Appellant
           shall not be entitled for carrying cost (much less at LPS
           rates), for the delay of 332 days in filing the Appeal, they
           shall be given credit for the sum of Rs.5 lakhs paid by them
           earlier as a condition for condoning the delay in filing the
           Appeal, since they are now being denied carrying cost for
           the said period of delay. The matter is remanded to the
           Respondent-Commission to compute the amounts which
           the Appellant is entitled to in terms of this Judgment. The
           Appeal is disposed of accordingly.”
8.   When the appeal was filed before this Court, it was entertained,
     limiting its scope only to the interpretation of Article 10.2.1 vis-à-vis
     10.5 of the PPA, with specific reference to 10.5.1 (ii). The following
     is the order passed by this Court on 09.09.2024:
           “We have heard learned senior counsel for the parties
           at length.
           Most of the issues raised in the present matter are covered
           by earlier decisions of this Court in ‘GMR Warora Energy
           Ltd. v. CERC & Ors.’, (2023) 10 SCC 401, ‘UHBVNL v.
           Adani Power (Mundra) Limited’, (2023) 2 SCC 624,
           ‘UHBVNL v. Adani Power Limited’, (2019) 5 SCC 325 and
           ‘MSEDCL v. MERC & Ors.’, (2022) 4 SCC 657. We may
           note that the delay in refiling has been duly considered
           earlier by the APTEL while condoning it. The said order
           has attained finality.
           The only issue which might arise for consideration
           in this appeal pertains to the interpretation of Article
           10.2.1 vis-à-vis Article 10.5 of the PPA with specific
           reference to 10.5.1 (ii).
           Learned senior counsel for the respondents seeks and is
           granted two weeks’ time to file a counter affidavit.
           Rejoinder affidavit shall be filed within a period of two
           weeks thereafter.
           List on 26.11.2024.”
                                                  (emphasis supplied)
2492                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


     SUBMISSIONS ON BEHALF OF THE APPELLANTS
9.   Notwithstanding the aforesaid order passed on 09.09.2024, the
     learned Senior Counsel and learned Counsel appearing for the
     appellants, made elaborate submissions on the other issues as well.
     It is submitted that the delay has occasioned only due to the fault
     of respondent No.1 through the litigation process and, therefore,
     what is to be applied is Article 10.5.1 (ii). The APTEL was wrong in
     condoning the delay by allowing the applications filed by respondent
     No.1. There is no basis for awarding carrying cost at the rate of LPS,
     and the APTEL ought not to have awarded the same as the LPS is
     granted only when there is a delay in the payment of a supplementary
     bill. The learned Senior Counsel placed substantial reliance on the
     PPA to contend that it is respondent No.1 who did not raise the
     supplementary bill at the earliest point of time, as mandated under
     Article 8 of the PPA. The decision rendered by this Court in GMR
     Warora (supra) does not apply to the case of respondent No.1,
     considering that in the said case, a supplementary bill was indeed
     raised. Unless a demand is raised, there is no question of payment
     that would arise, as there is a clear distinction between the liability to
     pay, as against an obligation to pay. In support of his contention, the
     learned Senior Counsel has also placed reliance upon the decision
     of this Court in Prem Cottex v. Uttar Haryana Bijli Vitran Nigam
     Ltd., (2021) 20 SCC 200.

     SUBMISSIONS ON BEHALF OF THE RESPONDENTS
10. The learned Senior Counsel Dr. Abhishek Manu Singhvi appearing
    for the respondent No. 1, submits that there exists a preliminary
    objection as arguments have been made by the appellants beyond
    the scope of not only the present appeal but also the order, dated
    09.09.2024, of this Court. The issues sought to be raised by the
    appellants have already been settled by this Court in not only GMR
    Warora (supra) but also in two other decisions of this Court in Uttar
    Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd., (2019) 5 SCC
    325 (hereinafter referred to as “UHBVNL 2019”) and Uttar Haryana
    Bijli Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd., (2023) 2
    SCC 624 (hereinafter referred to as “UHBVNL 2023”).
11. There is no question of raising a supplementary bill earlier, in view
    of the definite stand taken by the appellants on the notification
[2025] 5 S.C.R.                                                              2493

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                    Adani Power Rajasthan Ltd. & Anr.

     made by respondent No.1 on 20.12.2017. It is nobody’s case that
     the appellants were going to honour the bill if raised at the earliest
     point of time, as contended by them. The APTEL itself has held that
     respondent No.1 is not entitled to carrying cost for the period of delay
     in filing the appeal. The orders passed on that count have attained
     finality. The appellants are making a futile attempt at reopening the
     issues which are closed. Thus, it is a fit case where the appeal has
     to be dismissed with costs, particularly when appropriate orders have
     been passed by the RERC in pursuance of the order of remand
     made by the APTEL.
12. Before we deal with the submissions made by the parties, we deem
    it appropriate to discuss and elaborate on the scope of appeals
    under the 2003 Act.

     SCOPE OF APPEALS UNDER THE ELECTRICITY ACT, 2003
13. Whenever a statute provides for an appeal, a Court is expected to
    restrain itself to the contours of the powers conferred under it. The
    nature and status of the Court loses its significance as it only draws
    its powers from the statute alone, and not beyond. After all, judicial
    restraint and sobriety, when consciously restricted by the Legislature,
    forms an integral part of the duties and functions of the Court.

     Section 111 of the 2003 Act
           “111. Appeal to Appellate Tribunal.— (1) Any person
           aggrieved by an order made by an adjudicating officer
           under this Act (except under Section 127) or an order
           made by the Appropriate Commission under this Act may
           prefer an appeal to the Appellate Tribunal for Electricity:
           Provided that any person appealing against the order of
           the adjudicating officer levying any penalty shall, while filing
           the appeal, deposit the amount of such penalty:
           Provided further that where in any particular case, the
           Appellate Tribunal is of the opinion that the deposit of such
           penalty would cause undue hardship to such person, it may
           dispense with such deposit subject to such conditions as it
           may deem fit to impose so as to safeguard the realisation
           of penalty.
2494                                                         [2025] 5 S.C.R.

                       Supreme Court Reports


        (2) Every appeal under sub-section (1) shall be filed
        within a period of forty-five days from the date on which
        a copy of the order made by the adjudicating officer or
        the Appropriate Commission is received by the aggrieved
        person and it shall be in such form, verified in such manner
        and be accompanied by such fee as may be prescribed:
        Provided that the Appellate Tribunal may entertain an
        appeal after the expiry of the said period of forty-five days
        if it is satisfied that there was sufficient cause for not filing
        it within that period.
        (3) On receipt of an appeal under sub-section (1), the
        Appellate Tribunal may, after giving the parties to the
        appeal an opportunity of being heard, pass such orders
        thereon as it thinks fit, confirming, modifying or setting
        aside the order appealed against.
        (4) The Appellate Tribunal shall send a copy of every order
        made by it to the parties to the appeal and to the concerned
        adjudicating officer or the Appropriate Commission, as the
        case may be.
        (5) The appeal filed before the Appellate Tribunal under
        sub-section (1) shall be dealt with by it as expeditiously
        as possible and endeavour shall be made by it to dispose
        of the appeal finally within one hundred and eighty days
        from the date of receipt of the appeal:
        Provided that where any appeal could not be disposed of
        within the said period of one hundred and eighty days, the
        Appellate Tribunal shall record its reasons in writing for
        not disposing of the appeal within the said period.
        (6) The Appellate Tribunal may, for the purpose of
        examining the legality, propriety or correctness of any
        order made by the adjudicating officer or the Appropriate
        Commission under this Act, as the case may be, in relation
        to any proceeding, on its own motion or otherwise, call for
        the records of such proceedings and make such order in
        the case as it thinks fit.”
[2025] 5 S.C.R.                                                            2495

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                    Adani Power Rajasthan Ltd. & Anr.

     Section 125 of the 2003 Act
           “125. Appeal to Supreme Court.—Any person aggrieved
           by any decision or order of the Appellate Tribunal, may,
           file an appeal to the Supreme Court, within sixty days
           from the date of communication of the decision or order
           of the Appellate Tribunal, to him, on any one or more of
           the grounds specified in Section 100 of the Code of Civil
           Procedure, 1908 (5 of 1908):
           Provided that the Supreme Court may, if it is satisfied that
           the appellant was prevented by sufficient cause from filing
           the appeal within the said period, allow it to be filed within
           a further period not exceeding sixty days.”

     Section 100 of the Code of Civil Procedure, 1908
           “100. Second appeal.— (1) Save as otherwise expressly
           provided in the body of this Code or by any other law for
           the time being in force, an appeal shall lie to the High
           Court from every decree passed in appeal by any Court
           subordinate to the High Court, if the High Court is satisfied
           that the case involves a substantial question of law.
           (2) An appeal may lie under this section from an appellate
           decree passed ex- parte.
           (3) In an appeal under this section, the memorandum of
           appeal shall precisely state the substantial question of law
           involved in the appeal.
           (4) Where the High Court is satisfied that a substantial
           question of law is involved in any case, it shall formulate
           that question.
           (5) The appeal shall be heard on the question so formulated
           and the respondent shall, at the hearing of the appeal,
           be allowed to argue that the case does not involve such
           question:
           Provided that nothing in this sub-section shall be deemed
           to take away or abridge the power of the Court to hear, for
           reasons to be recorded, the appeal on any other substantial
2496                                                         [2025] 5 S.C.R.

                          Supreme Court Reports


           question of law, not formulated by it, if it is satisfied that
           the case involves such question.”
14. Under Section 111 of the 2003 Act, the APTEL is vested with all the
    powers that can possibly be exercised by the Regulatory Commission.
    In other words, it is the final Court of fact and law.
15. However, under Section 125 of the 2003 Act, the powers expected
    to be exercised by this Court is circumscribed and controlled by the
    pari materia provision contained under Section 100 of the Code of
    Civil Procedure, 1908 (hereinafter referred to as “the CPC”). Thus,
    it is axiomatic that an appellant has to raise a substantial question
    of law, which if the Court finds to be in existence, shall accordingly
    frame it in whatever manner it deems fit and proper, and put it to the
    other side to respond. It is for this Court to ultimately consider the
    existence of a substantial question of law and if it does so, answer it
    accordingly. We will only clarify that there is no bar for this Court to
    add any number of substantial questions of law even after framing
    one earlier, in which case the respondents will have to be given due
    notice of the same.
16. Section 100 of the CPC, after its amendment in the year 1978,
    consciously concerns itself with a question of law which shall be
    substantial in nature. Therefore, a mere question of law would not
    be sufficient enough to entertain an appeal under Section 125 of
    the 2003 Act. Added to that, it should be such that the substantial
    question of law, if answered in the affirmative in favour of the appellant,
    shall have the effect of reversing the decision of the APTEL. While
    deciding a substantial question of law, this Court shall do so, based
    upon the findings of fact rendered by the APTEL, unless by way of an
    exception, a perversity is found thereunder. In a case where a finding
    is rendered contrary to the records, without assigning any reason,
    and/or on a total misconception of the fact seen apparently on the
    face of the record, may in a given case, give rise to a substantial
    question of law. Suffice it is to state that a substantial question of law
    has to be framed by this Court in exercise of the power under Section
    125 of the 2003 Act and, thereafter, to be answered accordingly.
17. In the facts of the instant case, we have indeed framed only
    one substantial question of law vide order dated 09.09.2024, as
    aforementioned. Though we did permit the appellants to raise all the
    other issues and considered them as not feasible, the fact remains
    that they do not constitute substantial questions of law.
[2025] 5 S.C.R.                                                           2497

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                   Adani Power Rajasthan Ltd. & Anr.

     DISCUSSION
18. The issue with respect to change in law over a notification issued by
    a public authority and the resultant date to be reckoned has indeed
    attained finality pursuant to the judgments delivered by this Court
    in GMR Warora Energy Ltd. (supra), UHBVNL 2019 (supra) and
    UHBVNL 2023 (supra).

     GMR Warora Energy Ltd. v. CERC (2023) 10 SCC 401
           “95. For appreciating the rival submissions, we will have
           to construe the term “Law”, which has been defined in the
           PPAs, which reads thus:
                “ “Law” means, in relation to this Agreement,
                all laws including Electricity laws in force in
                India and any statute, ordinance, regulation,
                notification or code, rule, or any interpretation
                of any of them by an Indian Governmental
                Instrumentality and having force of law and
                shall further include all applicable rules,
                regulations, orders, notifications by an Indian
                Governmental Instrumentality pursuant to
                or under any of them and shall include all
                rules, regulations, decisions and orders of
                CERC and MERC.”
           96. Perusal of the definition of the term “Law” itself would
           clearly show that the term “Law” would mean all laws
           including Electricity laws in force in India and any statute,
           ordinance, regulation, notification or code, rule, or any
           interpretation of any of them by an Indian governmental
           instrumentality and having force of law. It would further
           reveal that the term “Law” shall also include all
           applicable rules, regulations, orders, notifications by
           an Indian governmental instrumentality and shall also
           include all rules, regulations, decisions and orders of
           CERC and MERC.
           97. In any case, the issue as to what would amount
           to “Law” is no more res integra. This Court, in Energy
           Watchdog [Energy Watchdog v. CERC, (2017) 14 SCC
2498                                                    [2025] 5 S.C.R.

                      Supreme Court Reports


        80 : (2018) 1 SCC (Civ) 133] , has observed thus : (SCC
        p. 131, para 57)
             “57. Both the letter dated 31-7-2013 and the
             revised Tariff Policy are statutory documents
             being issued under Section 3 of the Act and
             have the force of law. This being so, it is clear
             that so far as the procurement of Indian coal is
             concerned, to the extent that the supply from
             Coal India and other Indian sources is cut down,
             the PPA read with these documents provides
             in Clause 13.2 that while determining the
             consequences of change in law, parties shall
             have due regard to the principle that the
             purpose of compensating the party affected
             by such change in law is to restore, through
             monthly tariff payments, the affected party
             to the economic position as if such change
             in law has not occurred. Further, for the
             operation period of the PPA, compensation for
             any increase/decrease in cost to the seller shall
             be determined and be effective from such date
             as decided by the Central Electricity Regulation
             Commission. This being the case, we are of
             the view that though change in Indonesian law
             would not qualify as a change in law under the
             guidelines read with the PPA, change in Indian
             law certainly would.”
        98. The aforesaid view of this Court taken in Energy
        Watchdog [Energy Watchdog v. CERC, (2017) 14 SCC 80 :
        (2018) 1 SCC (Civ) 133] has been approved by a Bench
        of three learned Judges of this Court in Adani Rajasthan
        case [Jaipur Vidyut Vitaran Nigam Ltd. v. Adani Power
        Rajasthan Ltd., (2021) 18 SCC 478] and also followed by
        this Court when the two linked matters out of this batch of
        appeals were decided by this Court in Maharashtra State
        Electricity Distribution Co. Ltd. v. Adani Power Maharashtra
        Ltd. [(2023) 7 SCC 401] It cannot be denied that CIL
        is an instrumentality of the Government of India and
        its orders, insofar as price of fuel is concerned, are
        binding on all its subsidiaries.
[2025] 5 S.C.R.                                                           2499

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                   Adani Power Rajasthan Ltd. & Anr.

                                     ***
           100. As discussed hereinabove, the term “Law”
           would also include all applicable rules, regulations,
           orders, notifications issued by an Indian governmental
           instrumentality.
           101. It would thus be clear that all such additional
           charges which are payable on account of orders,
           directions, notifications, regulations, etc. issued by the
           instrumentalities of the State, after the cut-off date, will
           have to be considered to be “change in law” events.
           The generators would be entitled to compensation on
           the restitutionary principle on such changes occurring
           after the cut-off date.
                                     ***
           111. Undisputedly, EFC was imposed by CIL vide its
           Circular dated 19-12-2017.
           112. As already discussed hereinabove, CIL is an
           instrumentality of the State. It is thus clear that, on the
           cut-off date, there was no requirement of EFC, which
           has been brought into effect only on 19-12-2017. As
           such, the circular of CIL dated 19-12-2017 would also
           amount to “change in law”.
                                     ***
           117. For considering the rival submissions, it will be
           apposite to refer to the following articles, which are almost
           common in most of the PPAs:
                “11. Billing and payment.—
                                     ***
                11.3. Payment of monthly bills.—
                                     ***
                11.3.4. In the event of delay in payment of a
                monthly bill by any procurer beyond its due
                date, a late payment surcharge shall be payable
                by the procurer to the seller at the rate of two
2500                                                     [2025] 5 S.C.R.

                      Supreme Court Reports


             (2) per cent in excess of the applicable SBAR
             per annum, on the amount of outstanding
             payment, calculated on a day-to-day basis (and
             compounded with monthly rest), for each day
             of the delay.
                                 ***
             11.8. Payment of supplementary bill.—
             11.8.1. Either party may raise a bill on the
             other party (“supplementary bill”) for payment
             on account of:
             (i) Adjustments required by the Regional Energy
             Account (if applicable);
             (ii) Tariff payment for change in parameters,
             pursuant to provisions in Schedule 5; or
             (iii) Change in law as provided in Article 13 and
             such bill shall be paid by the other party.
                                 ***
             11.8.3. In the event of delay in payment of a
             supplementary bill by either party beyond one
             month from the date of billing, a late payment
             surcharge shall be payable at same terms
             applicable to the monthly bill in Article 11.3.4.”
        118. A perusal of Article 11.3.4 of the PPA would reveal
        that in the event of delay in payment of a monthly bill
        by any procurer beyond its due date, a late payment
        surcharge shall be payable by the procurer to the seller
        @ of 2% in excess of the applicable State Bank Advance
        Rate (“SBAR” for short) per annum, on the amount of
        outstanding payment, calculated on a day-to-day basis
        (and compounded with monthly rest), for each day of
        the delay. Article 11.8 of the PPA deals with payment
        of supplementary bill. It enables either party to raise a
        supplementary bill on the other party for payment on
        account of certain events. Clause (iii) of Article 11.8.1 of
        the PPA deals with “change in law” as provided in Article
[2025] 5 S.C.R.                                                             2501

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                    Adani Power Rajasthan Ltd. & Anr.

           13. It requires the bill to be paid by the other party. Article
           11.8.3 of the PPA also provides that in the event of delay in
           payment of a supplementary bill by either party beyond one
           month from the date of billing, a late payment surcharge
           shall be payable at same terms applicable to the monthly
           bill in Article 11.3.4.
                                      ***
           120. It could thus be seen that this Court in Adani Power
           [Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power
           Ltd., (2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657] has
           held that insofar as the “operation period” is concerned,
           compensation for any increase/decrease in revenues or
           costs to the seller is to be determined and effected from
           such date as is decided by the appropriate Commission.
           It has further been held that the compensation is only
           payable for increase/decrease in revenue or cost to the
           seller if it is in excess of an amount equivalent to 1% of
           the letter of credit in aggregate for a contract year. It has
           been held that restitutionary principles apply in case
           a certain threshold limit is crossed. It has been held
           that an inbuilt restitutionary principle compensates
           the party affected by such “change in law” and the
           affected party must be restored through monthly tariff
           payment to the same economic position as if such
           “change in law” had not occurred.
           121. From the perusal of para 9 of Adani Power [Uttar
           Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd., (2019)
           5 SCC 325 : (2019) 2 SCC (Civ) 657], it would also be
           clear that in case the “change in law” happens to be
           by way of adoption, promulgation, amendment, re-
           enactment or repeal of the law or “change in law”,
           it has to be effected from the date on which such
           change occurs.
           122. In this respect, it will also be apposite to refer to the
           following observations of this Court in Maharashtra State
           Electricity Distribution Co. Ltd. v. Maharashtra Electricity
           Regulatory Commission [(2022) 4 SCC 657] : (SCC pp.
           719-20, paras 173-78)
2502                                                    [2025] 5 S.C.R.

                      Supreme Court Reports


        “173. APTEL correctly found that: (Maharashtra Pradesh
        Electricity Regulatory Commission case [Maharashtra State
        Electricity Distribution Co. Ltd. v. Maharashtra Pradesh
        Electricity Regulatory Commission, 2021 SCC OnLine
        APTEL 13], SCC OnLine APTEL para 13)
             ‘13. … On the contrary, there is a conscious exclusion
             regarding any suo motu change in the rate to be
             applied while calculating LPS, it being incorrect to
             argue on the assumption that the contract permits
             automatic change in system.’
        174. This Court is unable to accept Mr Singh’s submission
        that the conclusion of APTEL that LPS is not tariff is
        erroneous. The meaning of the expression tariff has to be
        considered, and has rightly been considered by APTEL
        in the context of the relevant provision of the power
        purchase agreements. The dictionary meaning of tariff
        may be charge. However, in Article 13 of Stage 1 and
        Article 10 of Stage 2 power purchase agreements, tariff
        means monthly tariff and tariff adjustment consequential
        to change in law, is of monthly tariff in respect of supply
        of electricity.
        175. As argued by the respondent power generating
        companies appearing through Mr Rohatgi, Mr Singhvi,
        Mr Mukherjee and Ms Anand respectively, LPS is only
        payable when payment against monthly bills is delayed
        and not otherwise.
        176. The object of LPS is to enforce and/or encourage
        timely payment of charges by the procurer i.e. the
        appellant. In other words, LPS dissuades the procurer
        from delaying payment of charges. The rate of LPS
        has no bearing or impact on tariff. Changes in the
        basis of the rates of LPS do not affect the rate at
        which power was agreed to be sold and purchased
        under the power purchase agreements. The principle
        of restitution under the change in law provisions
        of the power purchase agreements are attracted in
        respect of tariff.
[2025] 5 S.C.R.                                                           2503

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                   Adani Power Rajasthan Ltd. & Anr.

           177. LPS cannot be equated with carrying cost or actual
           cost incurred for the supply of power. The appellant has
           a contractual obligation to make timely payment of the
           invoices raised by the power generating companies,
           subject, of course, to scrutiny and verification of the same.
           Mr Mukul Rohatgi has a point that if the funding cost was
           so much lesser than the rate of LPS, as contended by the
           appellant, the appellant could have raised funds at a lower
           rate of interest, made timely payment of the invoices raised
           by the power generating companies, and avoided LPS.
           178. The proposition that courts cannot rewrite a
           contract mutually executed between the parties, is well
           settled. The Court cannot, through its interpretative
           process, rewrite or create a new contract between
           the parties. The Court has to simply apply the terms
           and conditions of the agreement as agreed between
           the parties, as observed by this Court in Shree Ambica
           Medical Stores v. Surat People’s Coop. Bank [(2020)
           13 SCC 564] , para 20, cited by Ms Divya Anand. This
           appeal is an attempt to renegotiate the terms of the PPA,
           as argued by Ms Divya Anand as also other counsel. It is
           well settled that courts cannot substitute their own view of
           the presumed understanding of commercial terms by the
           parties, if the terms are explicitly expressed. The explicit
           terms of a contract are always the final word with regard to
           the intention of the parties, as held by this Court in Nabha
           Power Ltd. v. Punjab SPCL [(2018) 11 SCC 508 : (2018)
           5 SCC (Civ) 1] , paras 45 & 72, cited by Ms Anand.”
                                                (emphasis in original)

           123. This Court has clearly held in Maharashtra State
           Electricity Distribution Co. [Maharashtra State Electricity
           Distribution Co. Ltd. v. Maharashtra Electricity Regulatory
           Commission, (2022) 4 SCC 657] that the DISCOMS have
           a contractual obligation to make timely payment of the
           invoices raised by the power generating companies,
           subject to scrutiny and verification of the same. This
           Court has rejected the contention that the funding cost
2504                                                       [2025] 5 S.C.R.

                       Supreme Court Reports


        was much lesser than the rate of LPS. This Court has
        reiterated the proposition that the courts cannot rewrite
        a contract which is executed between the parties. This
        Court has emphasised that it cannot substitute its own
        view of the presumed understanding of commercial terms
        by the parties, if the terms are explicitly expressed. It has
        been held that the explicit terms of a contract are always
        the final word with regard to the intention of the parties.
        124. As already discussed hereinabove, Article 11.8 of the
        PPA entitles either party to raise a supplementary bill on
        the other party on account of “change in law” as provided
        in Article 13 and such bills are required to be paid by the
        either party. Article 11.8.3 of the PPA specifically provides
        that in the event of delay in payment of a supplementary bill
        by either party beyond one month from the date of billing,
        a late payment surcharge shall be payable at the same
        terms applicable to the monthly bill in Article 11.3.4. Article
        11.3.4 of the PPA specifically provides a late payment
        surcharge to be paid by the procurer to the seller @ of
        2% in excess of the applicable SBAR per annum on the
        amount of outstanding payment calculated on day-to-day
        basis (and compounded with monthly rest), for each day
        of the delay.
                                   ***
        126. It is thus clear that this Court has reiterated
        in Adani Power (Mundra) [Uttar Haryana Bijli Vitran
        Nigam Ltd. v. Adani Power (Mundra) Ltd., (2023) 2 SCC
        624 : (2023) 1 SCC (Civ) 31] that once carrying cost
        has been granted, it cannot be urged that interest on
        carrying cost should be calculated on simple interest
        basis instead of compound interest basis. It has been
        held that grant of compound interest on carrying cost
        and that too from the date of the occurrence of the
        “change in law” event is based on sound logic. It has
        been held that it is aimed at restituting a party that
        is adversely affected by a “change in law” event and
        restore it to its original economic position as if such
        a “change in law” event had not taken place.
[2025] 5 S.C.R.                                                             2505

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                    Adani Power Rajasthan Ltd. & Anr.

           127. The argument that there is no provision in the
           PPAs for payment of compound interest from the date
           when the “change in law” event had occurred, has
           been specifically rejected by this Court.
           128. In view of this consistent position of law and application
           of restitutionary principles and privity of contractual
           obligations between the parties as contained in the PPAs,
           we do not find that the view taken by the learned APTEL
           with regard to carrying cost warrants interference.
                                      ***
           177. It is further to be noted that this Court in Uttar Haryana
           Bijli Vitran Nigam Ltd. v. Adani Power Ltd. [(2019) 5 SCC
           325 : (2019) 2 SCC (Civ) 657], has specifically observed
           that the “change in law” events will have to accrue
           from the date on which rules, orders, notifications
           are issued by the instrumentalities of the State. Even
           in spite of this finding, the DISCOMS are pursuing
           litigations after litigations.
           178. We find that, when the PPA itself provides a
           mechanism for payment of compensation on the
           ground of “change in law”, unwarranted litigation,
           which wastes the time of the Court as well as adds to
           the ultimate cost of electricity consumed by the end-
           consumer, ought to be avoided. Ultimately, the huge
           cost of litigation on the part of DISCOMS as well as
           the generators adds to the cost of electricity that is
           supplied to the end-consumers.”
                                                   (emphasis supplied)

     Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power (Mundra)
     Ltd. (2023) 2 SCC 624
           “20. It is clear that the restitutionary principles
           encapsulated in Article 13.2 would take effect for
           computing the impact of change in law. We see no
           reason to interfere with the impugned judgment [Adani
           Power (Mundra) Ltd. v. CERC, 2021 SCC OnLine APTEL
2506                                                      [2025] 5 S.C.R.

                       Supreme Court Reports


        67] , wherein it has been held by the Appellate Tribunal that
        Respondent 1 Adani Power had started claiming change in
        law event compensation in respect of installation of FGD
        unit along with carrying cost, right from the year 2012 and
        that it has approached several fora to get this claim settled.
        Respondent 1 Adani Power finally succeeded in getting
        compensation towards FGD unit only on 28-3-2018, but
        the carrying cost claim was denied. The relief relating to
        carrying cost was granted to Respondent 1 Adani Power by
        the Appellate Tribunal vide order dated 13-4-2018 [Adani
        Power Ltd. v. CERC, 2018 SCC OnLine APTEL 5] which
        was duly tested by this Court and upheld on 25-2-2019
        [Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power
        Ltd., (2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657]. Once
        carrying cost has been granted in favour of Respondent
        1 Adani Power, it cannot be urged by the appellants
        that interest on carrying cost should be calculated on
        simple interest basis instead of compound interest
        basis. Grant of compound interest on carrying cost
        and that too from the date of the occurrence of the
        change in law event is based on sound logic. The idea
        behind granting interest on carrying cost is not far to
        see, it is aimed at restituting a party that is adversely
        affected by a change in law event and restore it to its
        original economic position as if such a change in law
        event had not taken place.
        21. In the instant case, Respondent 1 Adani Power had
        to incur expenses to purchase the FGD unit and install
        it in view of the terms and conditions of the environment
        clearance given by the Ministry of Environment and
        Forests, Union of India, in the year 2010. For this, it had
        to arrange finances by borrowing from banks. The interest
        rate framework followed by scheduled commercial banks
        and regulated by Reserve Bank of India mandates that
        interest shall be charged on all advances at monthly
        rests. In this view of the matter, Respondent 1 Adani
        Power is justified in stating that if the banks have
        charged it interest on monthly rest basis for giving
        loans to purchase the FGD unit, any restitution will
[2025] 5 S.C.R.                                                           2507

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                   Adani Power Rajasthan Ltd. & Anr.

           be incomplete, if it is not fully compensated for the
           interest paid by it to the banks on compounding basis.
           22. We are of the opinion that interest on carrying
           cost is nothing but time value for money and the
           only manner in which a party can be afforded the
           benefit of restitution in every which way. In the facts
           of the instant case, the Appellate Tribunal was justified in
           allowing interest on carrying cost in favour of Respondent
           1 Adani Power for the period between the year 2014, when
           the FGD unit was installed, till the year 2021. There was
           no justification for the Central Commission to have
           excluded the period between 2014 and 2018 and grant
           relief from the date of the passing of the order i.e.
           from 28-3-2018 [Adani Power Ltd. v. Uttar Haryana Bijli
           Vitran Nigam Ltd., 2018 SCC OnLine CERC 8] to 2021;
           nor is there any logic to such a segregation of timelines,
           particularly when Respondent 1 Adani Power was prompt
           in raising a claim on the appellants and pursuing its legal
           remedies.
           23. We are not persuaded by the submission made on
           behalf of the appellants that since no fault is attributable
           to them for the delay caused in determination of the
           amount, they cannot be saddled with the liability to pay
           interest on carrying cost; nor is there any substance
           in the argument sought to be advanced that there is
           no provision in the PPAs for payment of compound
           interest from the date when the change in law event
           had occurred.
           24. The entire concept of restitutionary principles
           engrained in Article 13 of the PPAs has to be read in
           the correct perspective. The said principle that governs
           compensating a party for the time value for money,
           is the very same principle that would be invoked and
           applied for grant of interest on carrying cost on account
           of a change in law event. Therefore, reliance on Article
           11.3.4 read with Article 11.8.3 on the part of the appellants
           cannot take their case further. Nor does the decision in
2508                                                      [2025] 5 S.C.R.

                       Supreme Court Reports


        Priya Vart case [Priya Vart v. Union of India, (1995) 5
        SCC 437] have any application to the facts of the present
        case as the said case relates to payment of compensation
        under the Land Acquisition Act and the interest that would
        be payable in case of delayed payment of compensation.”
                                               (emphasis supplied)

    Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd. (2019)
    5 SCC 325
        “9. It will be seen that Article 13.4.1 makes it clear
        that adjustment in monthly tariff payment on account
        of change in law shall be effected from the date of
        the change in law [see sub-clause (i) of clause 4.1],
        in case the change in law happens to be by way of
        adoption, promulgation, amendment, re-enactment
        or repeal of the law or change in law. As opposed to
        this, if the change in law is on account of a change
        in interpretation of law by a judgment of a Court or
        Tribunal or governmental instrumentality, the case
        would fall under sub-clause (ii) of clause 4.1, in which
        case, the monthly tariff payment shall be effected from
        the date of the said order/judgment of the competent
        authority/Tribunal or the governmental instrumentality.
        What is important to notice is that Article 13.4.1 is subject
        to Article 13.2 of the PPAs.
        10. Article 13.2 is an in-built restitutionary principle
        which compensates the party affected by such change
        in law and which must restore, through monthly tariff
        payments, the affected party to the same economic
        position as if such change in law has not occurred.
        This would mean that by this clause a fiction is created,
        and the party has to be put in the same economic
        position as if such change in law has not occurred i.e.
        the party must be given the benefit of restitution as
        understood in civil law. Article 13.2, however, goes on
        to divide such restitution into two separate periods. The
        first period is the “construction period” in which increase/
        decrease of capital cost of the project in the tariff is to be
        governed by a certain formula. However, the seller has to
[2025] 5 S.C.R.                                                             2509

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                    Adani Power Rajasthan Ltd. & Anr.

           provide to the procurer documentary proof of such increase/
           decrease in capital cost for establishing the impact of
           such change in law and in the case of dispute as to the
           same, a dispute resolution mechanism as per Article 17
           of the PPA is to be resorted to. It is also made clear that
           compensation is only payable to either party only with
           effect from the date on which the total increase/decrease
           exceeds the amount stated therein.
           11. So far as the “operation period” is concerned,
           compensation for any increase/decrease in revenues or
           costs to the seller is to be determined and effected from
           such date as is decided by the appropriate Commission.
           Here again, this compensation is only payable for increase/
           decrease in revenue or cost to the seller if it is in excess
           of an amount equivalent to 1% of the Letter of Credit in
           aggregate for a contract year. What is clear, therefore,
           from a reading of Article 13.2, is that restitutionary
           principles apply in case a certain threshold limit is
           crossed in both sub-clauses (a) and (b). There is no
           dispute that the present case is covered by sub-clause
           (b) and that the aforesaid threshold has been crossed.
           The mechanism for claiming a change in law is then
           set out by Article 13.3 of the PPA.
                                      ***
           13. A reading of Article 13 as a whole, therefore, leads
           to the position that subject to restitutionary principles
           contained in Article 13.2, the adjustment in monthly tariff
           payment, in the facts of the present case, has to be from
           the date of the withdrawal of exemption which was done
           by administrative orders dated 6-4-2015 and 16-2-2016.
           The present case, therefore, falls within Article 13.4.1(i).
           This being the case, it is clear that the adjustment in
           monthly tariff payment has to be effected from the
           date on which the exemptions given were withdrawn.
           This being the case, monthly invoices to be raised by the
           seller after such change in tariff are to appropriately reflect
           the changed tariff. On the facts of the present case, it is
           clear that the respondents were entitled to adjustment in
           their monthly tariff payment from the date on which the
           exemption notifications became effective. This being the
2510                                                         [2025] 5 S.C.R.

                         Supreme Court Reports


          case, the restitutionary principle contained in Article 13.2
          would kick in for the simple reason that it is only after the
          order dated 4-5-2017 [Adani Power Ltd. v. Uttar Haryana
          Bijli Vitran Nigam Ltd., 2017 SCC OnLine CERC 66] that
          CERC held that the respondents were entitled to claim
          added costs on account of change in law w.e.f. 1-4-2015.
          This being the case, it would be fallacious to say that the
          respondents would be claiming this restitutionary amount
          on some general principle of equity outside the PPA. Since
          it is clear that this amount of carrying cost is only relatable
          to Article 13 of the PPA, we find no reason to interfere
          with the judgment of the Appellate Tribunal.”
                                                  (emphasis supplied)

19. Notwithstanding the aforesaid clear pronouncements of this Court, we
    would like to throw a little more light on what constitutes a ‘change in
    law’ event, in view of the persuasive submissions made by Mr. Shyam
    Divan, the learned Senior Counsel appearing for the appellants.
20. While Article 10 of the PPA, with specific reference to Article 10.2,
    deals with application and principles for computing impact of change
    in law, Article 10.5, being a facet of Article 10.2 of the PPA, concerns
    itself with tariff adjustment payment on account of change in law.
    Article 10.2 and Article 10.5 of the PPA are extracted as below:
          “10.2 Application and Principles for computing impact of
          Change in Law
          10.2.1 While determining the consequence of Change
          in Law under this Article 10, the Parties shall have due
          regard to the principle that the purpose of compensating
          the Party affected by such Change in Law is to restore
          through monthly Tariff Payment, to the extent contemplated
          in this Article 10, the affected Party to the same economic
          position as if such Change in Law has not occurred.
                                     ***
          10.5 Tariff Adjustment Payment on account of Change
          in Law
          10.5.1 Subject to Article 10.2, the adjustment in monthly
          Tariff Payment shall be effective from:
[2025] 5 S.C.R.                                                        2511

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                   Adani Power Rajasthan Ltd. & Anr.

           (i) the date of adoption, promulgation, amendment, re-
           enactment or repeal of the Law or Change in Law; or
           (ii) the date of order/ judgment of the Competent Court
           or tribunal or Indian Governmental Instrumentality, if the
           Change in Law is on account of a change in interpretation
           of Law.
           10.5.2 The payment for Change in Law shall be through
           Supplementary Bill as mentioned in Article 8.8. However,
           in case of any change in Tariff by reason of Change in
           Law, as determined in accordance with this Agreement, the
           Monthly Invoice to be raised the Seller after such change
           in Tariff shall appropriately reflect the changed Tariff.”
21. As held by this Court in the decisions referred to supra, Article
    10.2.1 in the instant PPA was incorporated based on the principle of
    restitution. The idea of this principle is to compensate the affected
    party in order to restore it to the same economic position, but for the
    change in law. This particular provision is a substantive one, which in
    a normal circumstance, has to be given effect to in letter and spirit.
22. Article 10.5 of the PPA deals with tariff adjustment payment occasioned
    on account of change in law. Under Article 10.5.1 (i) of the PPA, the
    adjustment would start from the date of change in law. Therefore,
    as a matter of course, the adjustment in monthly tariff payment shall
    become effective from the date notified in the change in law.
23. Article 10.5.1 (ii) of the PPA might emerge in a factual scenario where
    there is an adjudication by way of an order/judgment of a competent
    Court or Tribunal or an Indian Governmental Instrumentality, as the
    case may be. Rendering of an order/judgement would require an
    interpretation of law. When there is a change in the interpretation
    of law in rendering the order/judgement, the date of such an order/
    judgment would constitute a ‘change in law’ under Article 10.5.1 (ii)
    of the PPA.
24. Hence, a mere difference in the understanding of a ‘change in law’
    by one party to the PPA, does not, by itself, preclude the other party
    from deriving a benefit by invoking Article 10.5.1 (i) of the PPA. In
    other words, a different understanding would not result in a different
    interpretation of law, that would bar entitlement under Article 10.5.1
    (i) of the PPA and, therefore, such a situation would not fall within
    the purview of Article 10.5.1 (ii) of the PPA.
2512                                                           [2025] 5 S.C.R.

                          Supreme Court Reports


25. To make this position clear, Article 10.5.1 (ii) of the PPA is not applicable
    to the facts of the instant case since there is no change in law which
    has occasioned by way of an interpretation given by a Court or a
    Tribunal or an Indian Governmental Instrumentality. Recognising a
    change in law is different from interpreting a notification as the one
    applicable to the parties. We are only clarifying the position that
    there is no change in the interpretation of law involved in the case
    at hand, particularly when the said issue was not before the APTEL,
    for which the author of the change in law should have been made a
    party to the proceedings, in order to defend it. The Notification, dated
    19.12.2017, and its application are not in dispute. What is in dispute
    is whether it constitutes a change in law or not. So long as there is
    no interpretation on the Notification with respect to its applicability
    to the parties before us, Clause (ii) of Article 10.5.1 of the PPA will
    have no application.
26. Article 10.5.2 of the PPA kicks in thereafter. Hence, a supplementary
    bill has to be raised only after due adjudication by the competent
    forum. Our view is fortified on a proper reading of Article 8 of the PPA.
           “ARTICLE 8: BILLING AND PAYMENT
                                       ***
           8.3 Payment of Monthly Bills
           8.3.1 The Procurers shall pay the amount payable under
           the Monthly Bill on the Due Date to such account of the
           Seller, as shall have been previously notified by the Seller
           in accordance with Article 8.3.4 below.
           8.3.2 All payments made by the Procurer(s) shall be
           appropriated by the Seller in the following order of priority:
           i) towards Late Payment Surcharge, if any;
           ii) towards the earlier unpaid Monthly Bill(s), if any; and
           iii) towards the then current Monthly Bill.
                                       ***
           8.3.5 In the event of delay in payment of a Monthly Bill
           by the Procurers beyond its Due Date, a Late Payment
           Surcharge shall be payable by such Procurers to the Seller
           at the rate of two percent (2%) in excess of the applicable
           SBAR per annum, on the amount of outstanding payment,
[2025] 5 S.C.R.                                                           2513

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                    Adani Power Rajasthan Ltd. & Anr.

           calculated on a day to day basis (and compounded with
           monthly rest), for each day of the delay. The Late Payment
           Surcharge shall be claimed by the Seller through the
           Supplementary Bill.
                                      ***
           8.6 Disputed Bill
           8.6.1 If a Party does not dispute a Monthly Bill, Provisional
           Bill or a Supplementary Bill raised by the other Party by
           the Due Date, such Bill shall be taken as conclusive.
           8.6.2 If a Party disputes the amount payable under a
           Monthly Bill, Provisional Bill or a Supplementary Bill, as
           the case may be, that Party shall, within thirty (30) days
           of receiving such Bill, issue a notice (the “Bill Dispute
           Notice”) to the invoicing Party setting out:
           i) the details of the disputed amount;
           ii) its estimate of what the correct amount should be; and
           iii) all written material in support of its claim.
                                      ***
           8.8 Payment of Supplementary Bill
           8.8.1 Either Party may raise a bill on the other Party
           (“Supplementary Bill”) for payment on account of:
           i) Adjustments required by the Regional Energy Account
           (if applicable);
           ii) Tariff Payment for change in parameters, pursuant to
           provisions in Schedule 4; or
           iii) Change in Law as provided in Article 10,
           and such Supplementary Bill shall be paid by the other
           Party.
                                      ***
           8.8.3 In the event of delay in payment of a Supplementary
           Bill by either Party beyond its Due Date, a Late Payment
           Surcharge shall be payable at the same terms applicable
           to the Monthly Bill in· Article 8.3.5.”
2514                                                            [2025] 5 S.C.R.

                             Supreme Court Reports


     It is not in dispute that a supplementary bill is not a monthly bill. Article
     8 of the PPA deals with billing and payment alone. Under Article 8.8, the
     other party is duty-bound to make the payment when a supplementary
     bill is raised due to a change in law event having occurred, as provided
     under Article 10 of the PPA. This can happen only after due adjudication
     by the competent forum, has taken place. For more clarity, one has to
     read Article 10.5.2 along with Article 8.8 of the PPA. It is only thereafter
     that Article 8.6 of the PPA might come into the picture when there exists
     a dispute on the quantum of amount claimed in the supplementary bill
     raised after the completion of due adjudication by the competent forum,
     on the issue pertaining to the change in law.
27. The incidental issue raised with respect to carrying cost at the rate
    of LPS has also been dealt with in the decisions referred to in GMR
    Warora Energy Ltd. (supra), UHBVNL 2019 (supra) and UHBVNL
    2023 (supra) and, therefore, any fresh consideration would only be
    an academic exercise. We also find that the decision relied upon by
    the learned Senior Counsel appearing on behalf of the appellants,
    have no application to the facts of the case.
28. For the aforesaid reasons, we find absolutely no reason to interfere
    with the impugned judgment. Liability has been fastened upon
    the appellants under the agreement. The contention that the
    supplementary bill ought to have been raised earlier and, therefore,
    the payment can only be made thereafter has neither a factual basis
    nor a legal one. We would only point out the fact that respondent
    No.1 did notify the change in law event immediately on the very
    next day of the notification having been issued. In any case, we
    have been informed that in pursuance of the order of remand made
    by the APTEL, further orders have been passed by the RERC on
    19.06.2024, which has not been challenged before this Court.
29. In view of the aforesaid analysis, we find no merit in this appeal.
    The appeal stands dismissed, accordingly.
30. Pending application(s), if any, shall stand disposed of.

     Result of the case: Appeal dismissed.




     †
         Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Evacuation Facility Charges"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

JAIPUR VIDYUT VITRAN NIGAM LTD. & ORS. versus ADANI POWER RAJASTHAN LTD. & ANR. — 2025 INSC 770 - Legal Desk AI