Created byFuzzy Cloud

Supreme Court of India

JAIPUR VIDYUT VITRAN NIGAM LTD. & ORS.versusMB POWER (MADHYA PRADESH) LIMITED & ORS.

Citation
2024 INSC 23
Decided
8 January 2024
Disposal
Appeal(s) allowed

Holding

The State Commission is empowered under Section 63, read with Section 86(1)(b) and the Bidding Guidelines, to reject bids not market‑aligned and to consider consumer interest, and the High Court’s mandamus was unlawful.

Summary

The Rajasthan Electricity Regulatory Commission (State Commission) was asked to approve the procurement of 1,000 MW of power through a competitive bidding process. After negotiations, the Commission approved only 500 MW and adopted the tariffs of the lowest bidders, while the higher‑priced bids of L‑4 and L‑5 were rejected as not market‑aligned. The Appellate Tribunal for Electricity (APTEL) held that the State Commission could not consider market alignment, a view later upheld by the High Court which issued a mandamus directing the procurers to purchase 200 MW from MB Power at its higher tariff. The Supreme Court held that under Section 63 of the Electricity Act, read with Section 86(1)(b) and the Bidding Guidelines, the State Commission does have the power to reject bids not aligned with market prices and must consider consumer interest, rendering the High Court’s mandamus erroneous. Consequently, the Supreme Court quashed the High Court’s order and the APTEL’s decision, allowing the appeals and directing costs.

Issues considered

  • The scope of power of the State Commission under Section 63 of the Electricity Act to consider whether tariffs are market‑aligned.
  • Whether the State Commission may reject bids on the ground of lack of market alignment under Clause 5.15 of the Competitive Bidding Guidelines.
  • The correctness of the High Court’s mandamus directing procurement from MB Power at its quoted tariff.
  • The applicability of the rule of alternate remedy and the maintainability of the writ petition under Article 226.
  • The interpretation of the words ‘any’ and ‘all’ in Clause 5.15 of the Bidding Guidelines.

Legislation cited

Subjects

ElectricityState Electricity Regulatory CommissionAppellate Tribunal for ElectricityBid Evaluation CommitteeRequest for ProposalPower Purchase AgreementReduction of quantum of powerTest of filling the bucketTariffs not aligned to the prevailing market pricesConsumers’ interestCompetitive Bidding GuidelinesAdoption of tariffDetermination of tariff by bidding processFunctions of State CommissionFunctions of Central Electricity Regulatory CommissionMandamusContract harmful to the public interestInterpretation of statutesLiteral interpretationPurposive constructionRegulation of tariffAlternate remedyJudicial reviewUnreasonableness or arbitrarinessAward of contractCommercial transactionCommercial considerationsJudicial scrutiny

Judgment

                   [2024] 1 S.C.R. 909 : 2024 INSC 23

             Jaipur Vidyut Vitran Nigam Ltd. & Ors.
                                v.
           MB Power (Madhya Pradesh) Limited & Ors.
                       (Civil Appeal No. 6503 of 2022)
                                08 January 2024
           [B. R. Gavai* and Prashant Kumar Mishra, JJ.]

                            Issue for Consideration
       State Commission held that the tariffs offered by the L-4 and L-5
       bidders were not aligned to the prevailing market prices. In appeal
       by L-5, APTEL held that the State Commission had to necessarily
       adopt the tariff and had no power to consider whether the tariff was
       aligned to market prices. Impugned judgment of the High Court
       relying on the said judgment of the APTEL and the earlier orders
       of this Court concluded that applying the test of “filling the bucket”,
       the procurers were bound to take supply from the respondent No.1
       at the rates quoted by it and it had a right to supply power since
       there was a gap of 300 MW between the power procured by the
       procurers and the ceiling of 906 MW determined by this Court. High
       Court whether justified in issuing mandamus directing the appellants
       to take supply of 200 MW power from the respondent No.1 at the
       rates quoted by it. Power of the State Commission to go into the
       question as to whether the prices quoted are market aligned or not
       and to take into consideration the aspect of consumers’ interest.

                                    Headnotes
       Electricity Act, 2003 – ss.63, 86 – Rajasthan Rajya Vidyut
       Prasaran Nigam Limited (RVPN) filed Petition before the State
       Commission seeking approval for procurement of 1000 MW
       of power by a competitive bidding process – RFP was issued
       – Eventually, in consonance with the LoI, PPAs were signed
       with the L-1, L-2 and L-3 bidders – State Commission held that
       the quantum of only 500 MW power was liable to be approved
       considering the demand in the State as recommended by the
       EAC and it approved the tariff quoted by the L-1 to L-3 bidders
       – Appeals filed by L-2 and L-3 bidders before APTEL, allowed
       – Challenged by the appellants – Subsequently, Civil Appeals
       were filed by L-5 bidder also– Disposing of the appeals, State
       Commission was directed to go into the issue of approval for
       adoption of tariff with regard to L-4 and L-5 bidders– Further,
* Author
910                                                              [2024] 1 S.C.R.

                        Digital Supreme Court Reports


       vide order dtd.19.11.18, State Commission was directed to
       go into the issue of adoption of tariff – State Commission
       held that the tariffs offered by the L-4 and L-5 bidders were
       not aligned to the prevailing market prices – Appeal filed by
       L-5 bidder, allowed by APTEL – Writ petition was filed by the
       respondent No.1 – Allowed by impugned judgment:
       Held: Unlike s.62 r/w ss.61 and 64, under the provisions of s.63,
       the appropriate Commission does not “determine” tariff but only
       “adopts” tariff already determined u/s.63 – Such “adoption” is only
       if such tariff has been determined through a transparent process
       of bidding, and this transparent process of bidding must be in
       accordance with the guidelines issued by the Central Governments
       – s.86(1)(b) gives ample power to the State Commission to regulate
       electricity purchase and procurement process of distribution
       licensees – It also empowers the State Commission to regulate
       the matters including the price at which electricity shall be procured
       from the generating companies, etc. – Further, orders relied upon
       by the APTEL, specifically the order dtd. 19.11.2018, clarified
       that the State Commission was to decide the tariff u/s.63 having
       regard to the law laid down both statutorily and by this Court – As
       such, the State Commission was bound to take into consideration
       the Bidding Guidelines notified by the Central Government, and
       specifically clause 5.15 thereof – State Commission justified in
       considering the Clause 5.15 of the Bidding Guidelines which
       specifically permits to reject all price bids if the rates quoted are
       not aligned to the prevailing market prices – APTEL grossly erred
       in holding that the State Commission has no power to go into the
       question, as to whether the prices quoted are market aligned or not
       and also not to take into consideration the aspect of consumers’
       interest – It cannot be read from the orders of this Court that the
       State Commission was bound to accept the bids as quoted by
       the bidders till the bucket was filled – No such direction can be
       issued by this Court de hors the provisions of ss.63 and 86(1)(b)
       and the Bidding Guidelines – Since the decision-making process
       adopted by the Bid Evaluation Committee approved by the State
       Commission, was in accordance with the law laid down by this
       Court, the same ought not to have been interfered with by the
       APTEL – High Court could not have issued a mandamus to the
       instrumentalities of the State to enter into a contract harmful to the
       public interest inasmuch as, if the power was to be procured by
       the procurers at the rates quoted by the respondent No.1, which
       was even higher than the rates quoted by the L-5 bidder, then the
[2024] 1 S.C.R.                                                               911

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     State would have to bear financial burden in thousands of crore
     rupees, which in turn would have passed on to the consumers
     – Impugned judgment quashed and set aside – Cost imposed.
     [Paras 67, 71, 73-75, 78, 83, 104, 105]
     Electricity – Competitive Bidding Guidelines notified by the
     Government of India u/s.63 – Respondent No.1 contended
     that the procurer is bound to accept all the bids emerged in
     a competitive bidding process once the bidding process was
     found to be transparent and in compliance with the Bidding
     Guidelines:
     Held: If the contention is to be accepted it will do complete violence
     to clause 5.15 of the Bidding Guidelines itself – If that view is
     accepted, the DISCOMS will be compelled to purchase electricity
     at a much higher rate as compared with other suppliers – The
     said higher rate will be passed on to the consumers – As such,
     accepting the contention of the respondent No.1 would result in
     adversely affecting the interests of the consumers and, in turn,
     would be against the larger public interest. [Para 77]
     Electricity Act, 2003 – s.63 – General Clauses Act – s.13(2)
     – “all”, “any” – Principle of literal interpretation – Principle
     of purposive construction – “all” used in clause 5.15 of
     the Bidding Guidelines r/ws.86(1)(b) – Competitive Bidding
     Guidelines notified by the Government of India u/s.63 – It was
     contended that the power under clause 5.15 of the Bidding
     Guidelines can be exercised only when the bidding process
     is found to be not in compliance with the Bidding Guidelines
     and is not transparent in respect of all the bidders and not in
     respect of some of the bidders is concerned:
     Held: The contention is without substance – Words “all” or “any” will
     have to be construed in their context taking into consideration the
     scheme and purpose of the enactment – What is the meaning which
     the legislature intended to give to a particular statutory provision
     has to be decided by the Court on a consideration of the context
     in which the word(s) appear(s) and in particular, the scheme and
     object of the legislation – The word “all” used in clause 5.15 of
     the Bidding Guidelines, read with the legislative policy for which
     the Electricity Act was enacted and r/ws.86(1)(b), will have to be
     construed to be the one including “any” – Applying the principle of
     literal interpretation, the evaluation committee/BEC would be entitled
     to reject only such of the price bids if it finds that the rates quoted
912                                                              [2024] 1 S.C.R.

                        Digital Supreme Court Reports


       by the bidders are not aligned to the prevailing market prices – It
       does not stipulate rejection of all the bids in the bidding process
       – If the contention that clause 5.15 of the Bidding Guidelines will
       come into play, which permits the Evaluation Committee to reject
       “all” price bids and not “any” one of them is accepted, it will lead
       to absurdity – The Court, while interpreting a particular provision,
       will have to apply the principles of purposive construction – Such
       an interpretation would result in defeating one of the main objects
       of the enactment, i.e., protection of the consumer. [Paras 84, 87,
       88 and 91]
       Interpretation of Statutes – Principle of purposive construction
       – Discussed.
       Electricity Act, 2003 – ss.62, 63, 79(1)(b):
       Held: The non-obstante clause advisedly restricts itself to s.62,
       there is no reason to put s.79 out of the way altogether – Either
       u/s.62, or 63, the general regulatory power of the Commission
       u/s.79(1)(b) is the source of the power to regulate, which includes
       the power to determine or adopt tariff – ss.62 and 63 deal with
       “determination” of tariff, which is part of “regulating” tariff – In a
       situation where the guidelines issued by the Central Government
       u/s.63 cover the situation, the Central Commission is bound by
       those guidelines and must exercise its regulatory functions, albeit
       u/s.79(1)(b), only in accordance with those guidelines. [Para 68]
       Alternate remedy – Electricity Act, 2003 – Constitution of
       India – Article 226 – Judicial review – Scope:
       Held: The Electricity Act is an exhaustive code on all matters
       concerning electricity – Under the Electricity Act, all issues dealing
       with electricity have to be considered by the authorities constituted
       under the said Act – The State Electricity Commission and the
       APTEL have ample powers to adjudicate in the matters with
       regard to electricity – These Tribunals are tribunals consisting of
       experts having vast experience in the field of electricity – In the
       present case, the High Court erred in directly entertaining the writ
       petition when the respondent No.1-the writ petitioner before the
       High Court had an adequate alternate remedy of approaching the
       State Electricity Commission – Although, availability of an alternate
       remedy is not a complete bar in the exercise of the power of judicial
       review by the High Courts but, recourse to such a remedy would
       be permissible only if extraordinary and exceptional circumstances
       are made out – While exercising its power of judicial review, the
[2024] 1 S.C.R.                                                              913

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     Court can step in where a case of manifest unreasonableness or
     arbitrariness is made out – There was not even an allegation with
     regard to that effect – In such circumstances, recourse to a petition
     under Article 226 of the Constitution of India in the availability of
     efficacious alternate remedy under a statute which is a complete
     code in itself was not justified. [Paras 93-95]
     Contract – Award of contract, a commercial transaction –
     Judicial Scrutiny – Scope:
     Held: The award of a contract, whether by a private party or by
     a public body or the State is essentially a commercial transaction
     – In arriving at a commercial decision, considerations which are
     paramount are commercial considerations – State can choose its
     own method to arrive at a decision – It can fix its own terms of
     invitation to tender and that is not open to judicial scrutiny – State
     can enter into negotiations before finally deciding to accept one of
     the offers made to it – Price need not always be the sole criterion
     for awarding a contract – State may not accept the offer even
     though it happens to be the highest or the lowest – However, the
     State, its corporations, instrumentalities and agencies are bound
     to adhere to the norms, standards and procedures laid down
     by them and cannot depart from them arbitrarily – Though that
     decision is not amenable to judicial review, the court can examine
     the decision-making process and interfere if it is found vitiated by
     mala fides, unreasonableness and arbitrariness – Only when the
     Court comes to a conclusion that overwhelming public interest
     requires interference, the court should intervene. [Para 102]

                              Case Law Cited
           PTC India Limited v. Central Electricity Regulatory
           Commission, Through Secretary [2010] 3 SCR 609 :
           (2010) 4 SCC 603; Vivek Narayan Sharma and others
           v. Union of India and others [2023] 1 SCR 1 : (2023)
           3 SCC 1 – followed.
           Energy Watchdog v. Central Electricity Regulatory
           Commission and others [2017] 3 SCR 153 : (2017)
           14 SCC 80; GMR Warora Energy Limited v. Central
           Electricity Regulatory Commission (CERC) & Ors. [2023]
           8 SCR 183 : 2023 SCC Online SC 464 – relied on.
           R.Viswanathan and others v. Rukn-ul-Mulk Syed Abdul
           Wajid since deceased and others [1963] 3 SCR 22 :
914                                                                 [2024] 1 S.C.R.

                         Digital Supreme Court Reports


             AIR 1963 SC 1; Deccan Paper Mills Company Limited
             v. Regency Mahavir Properties & Ors. [2020] 13 SCR
             427 : (2021) 4 SCC 786; Tata Power Company Limited
             Transmission v. Maharashtra Electricity Regulatory
             Commission & Ors. [2022] 19 S.C.R. 620 : 2022 SCC
             Online 1615; Tata Cellular v. Union of India [1994]
             2 Suppl. SCR 122 : (1994) 6 SCC 651; Rajasthan
             Housing Board and another v. G.S. Investments and
             another [2006] 7 Suppl. SCR 868 : (2007) 1 SCC 477;
             Laxmikant and others v. Satyawan and others [1996] 3
             SCR 532 : (1996) 4 SCC 208; Reliance Infrastructure
             Limited v. State of Maharashtra and others [2019] 1 SCR
             886 : (2019) 3 SCC 352; Radha Krishan Industries v.
             State of Himachal Pradesh and others [2021] 3 SCR
             406 : (2021) 6 SCC 771; South Indian Bank Ltd. and
             others v. Naveen Mathew Philip and another [2023] 4
             SCR 18 : 2023 SCC OnLine SC 435; Air India Ltd. v.
             Cochin International Airport Ltd. and others [2000] 1
             SCR 505 : (2000) 2 SCC 617 – referred to.

                                    List of Acts
       Electricity Act; RERC (Power Purchase & Procurement Process
       of Distribution Licensee) Regulations 2004; Constitution of India;
       General Clauses Act.

                                   List Keywords
       Electricity; State Electricity Regulatory Commission; Appellate
       Tribunal for Electricity; Bid Evaluation Committee; Request for
       Proposal; Power Purchase Agreement; Reduction of quantum of
       power; Test of filling the bucket; Tariffs not aligned to the prevailing
       market prices; Consumers’ interest; Competitive Bidding Guidelines/
       Process; Approval for adoption of tariff; Determination of tariff
       by bidding process; Functions of State Commission; Functions
       of Central Electricity Regulatory Commission; Bid Evaluation
       Committee; Mandamus; Contract harmful to the public interest;
       Interpretation of Statutes; Principle of literal interpretation; Principle
       of purposive construction; Determination of tariff, Regulating
       tariff; Alternate remedy; Judicial review; Unreasonableness
       or arbitrariness; Award of contract; Commercial transaction;
       Commercial considerations; Judicial Scrutiny.
[2024] 1 S.C.R.                                                        915

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

                           Case Arising From

     CIVIL APPELLATE JURISDICTION : Civil Appeal No. 6503 of 2022.
     From the Judgment and Order dated 20.09.2021 of the High Court
     of Judicature for Rajasthan Bench at Jaipur in D.B. Civil Writ Petition
     No.14815 of 2020.
     With
     Civil Appeal Nos. 6502 of 2022 And 4612 of 2023.
                        Appearances for Parties
     P. Chidambaram, Sr. Adv., Anand K Ganesan, Amal Nair, Ms. Shivani
     Verma, Nitin Saluja, Nikunj Dayal, Ms. Kritika Khanna, Advs. for the
     Appellants.
     Vikramjit Banerjee, A.S.G., Dr. A.M. Singhvi, Prag Tripathi, C.S.
     Vaidhyanathan, Sr. Advs., Atul Shanker Mathur, Mahesh Agarwal,
     Rishi Agrawala, Vaibhav Mishra, Dr. Rajeshwar Singh, Avishkar
     Singhvi, Ms. Priya Singh, Prabal Mehrotra, Shubhankar, Ankur
     Saigal, Karan Verma, Apoorv Agarwal, E. C. Agrawala, Atul Shankar
     Mathur, Buddy Rangnathan, Umang Katariya, Ms. Mishika Bajpai,
     Ms. Apoorva Agrawal, Sidharth Seem, M/s. Khaitan & Co., Jayant
     Mohan, Zoheb Hossain, P.V. Yogeshwaran, Siddhartha Sinha, Ms.
     Megha Saxena, Aditya Kashyap, Ms. Vanshja Shukla, Nring C.
     Zeliang, Gurmeet Singh Makker, Saurabh Mishra, Ms. Prerna Singh,
     Guntur Prabhakar, Ravi Kishore, Guntur Pramod Kumar, Umesh
     Kumar Khaitan, Advs. for the Respondents.

                Judgment / Order of the Supreme Court
                                  Judgment
     B. R. Gavai, J.

     CIVIL APPEAL NO. 6503 OF 2022 AND CIVIL APPEAL NO. 6502
     OF 2022
1.   These appeals challenge the judgment and order dated 20th September
     2021, passed by the Division Bench of the High Court of Judicature
     for Rajasthan, Bench at Jaipur, in D.B. Civil Writ Petition No. 14815
     of 2020, thereby allowing the said writ petition filed by MB Power
     (Madhya Pradesh) Limited (hereinafter referred to as “MB Power”),
     respondent No.1 herein. By the impugned judgment and order, the
916                                                            [2024] 1 S.C.R.

                       Digital Supreme Court Reports


       High Court held that the respondent Nos. 1 to 5 therein (appellants
       herein and the State of Rajasthan) are bound to purchase a total of 906
       MW electricity from the successful bidders. It, therefore, directed the
       writ petitioner- MB Power (respondent No.1 herein) and respondent
       No.7 - PTC India Ltd. (hereinafter referred to as “PTC India”) in the
       said writ petition (respondent No.2 in the present appeals) to supply
       200 MW electricity to the respondents therein (appellants herein)
       within the limit of 906 MW. It also directed the writ petitioner-MB Power
       and PTC India, respondent No.7 in the said writ petition, to file an
       appropriate application before the respondent Nos. 1 to 5 in the said
       writ petition, within two weeks from the date of the order, complying
       with the necessary requisite conditions, including bank guarantee
       etc., as required in terms of the Request for Proposal (hereinafter
       referred to as “the RFP”). It further directed the respondent Nos. 1
       to 5 in the said writ petition, for issuance of Letter of Intent (“LoI”
       for short) in respect of bid filed through PTC India for supplying 200
       MW power from the power generating station of the writ petitioner
       i.e. MB Power at levelized tariff of Rs.5.517/Kwh, being in terms of
       their bid qualified by the Bid Evaluation Committee (“BEC” for short)
       and ranked L-7. It further directed the respondents No.1 to 5 in the
       said writ petition, to immediately within two weeks thereafter, execute
       the Power Purchase Agreement (“PPA” for short) with PTC India for
       procuring 200 MW power from the power generating station of MB
       Power, and then to start procuring power in accordance with law.
       As an interim measure, it directed that the tariff to be actually paid
       by the procurer-respondents before it, shall be the interim tariff i.e.
       Rs.2.88 per unit, as specified by this Court in its interim order dated
       28th September 2020, passed in I.A. No.83693 of 2020 in Civil Appeal
       No.2721 of 2020. It further held that the final adoption of tariff to be
       paid to PTC India (respondent No.7 before it) under the PPA shall
       be subject to the final outcome of the said Civil Appeal No. 2721 of
       2020, pending before this Court.

       BRIEF FACTS:
2.     The facts leading to the filing of these two appeals, as mentioned
       in Civil Appeal No. 6503 of 2022, are as under:
       2.1 The Government of India vide Notification dated 19th January
           2005, notified the Competitive Bidding Guidelines (hereinafter
           referred to as “the Bidding Guidelines”) under Section 63 of the
[2024] 1 S.C.R.                                                           917

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

           Electricity Act, 2003 (hereinafter referred to as “the Electricity
           Act”). The objective of the said Bidding Guidelines is for
           introduction of competition and protection of consumer interest.
      2.2 On 21st September 2009, Rajasthan Rajya Vidyut Prasaran
          Nigam Limited (hereinafter referred to as “RVPN”) filed Petition
          No.205 of 2009 before the Rajasthan Electricity Regulatory
          Commission (hereinafter referred to as “the State Commission”)
          seeking approval for procurement of 1000 MW of power by a
          competitive bidding process.
      2.3 On 28th May 2012, RVPN issued an RFP, inviting sellers to
          participate in the competitive bidding for procurement of 1000
          MW under the Bidding Guidelines.
      2.4 In the month of February 2013, bids were received from the
          bidders.
      2.5 On 4th April 2013, based on the preliminary evaluation of the
          non-financial bids by the BEC, 7 bidders were declared as
          qualified for opening of the financial bids. The respondent
          No.1-MB Power herein was not a bidder in the above process.
          Respondent No.2-PTC India herein had submitted a bid for 1041
          MW, which it was to procure from five different generators. PTC
          India is a power-trading licensee company, which had procured
          the bid document after depositing a Bid Bond.
      2.6 In the various meetings held between 17th April 2013 and 22nd
          April 2013, the BEC had placed the bids received in ascending
          order, from lowest to the highest tariff as follows:

Rank       Qualified    Levelized Tariff Capacity Cumulative     Average
         Bidder Name      (Rs/kWh)       Offered   Capacity     Cumulative
                                                   Offered        Tariff
                                                                (Rs/ kWh)
L-1     PTC – Maruti        4.517          195         195         4.517
        Clean Coal
        and Power
        Limited
L-2     PTC – DB            4.811          311         506         4.698
        Power Limited
918                                                         [2024] 1 S.C.R.

                         Digital Supreme Court Reports



L-3      LPL – Lanco           4.943       100        606         4.738
         Babandh
         Power Limited
L-4      PTC – Athena          5.143       200        806         4.839
         Chhattisgarh
         Power Ltd
L-5      SKS Power             5.300       100        906         4.890
         Generation
         (Chhattisgarh)
         Limited
L-6      LPL – Lanco           5.490       100        1006        4.949
         Vidarbha
         Thermal
         Power Limited
L-7      PTC – MB              5.517       200        1206        5.043
         Power
         (Madhya
         Pradesh) Ltd.
L-8      KSK                   5.572       475        1681        5.193
         Mahanadi
         Power
         Company
         Limited
L-9      Jindal Power          6.038       300        1981        5.321
         Limited
L-10     LPL – Lanco           7.110       100        2081        5.407
         Amarkantak
         Power Ltd



       2.7 In the 216th Meeting of the Board of Directors of RVPN, it
           was decided to take an opinion from the BEC as to whether
           negotiations should be held to reduce tariff keeping in view of
           the long-term impact and quantum of the amounts involved.
       2.8 On 4th June 2013, the BEC gave its opinion that since the rates
           quoted vary considerably, negotiations could be held with the
           bidders.
       2.9 Vide Resolution dated 4th June 2013, the Board of the RVPN
           decided to hold negotiations with the qualified bidders.
       2.10 In the negotiations, the following offers were received:
[2024] 1 S.C.R.                                                          919

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                MB Power (Madhya Pradesh) Limited & Ors.

            “
            •    L-1/Maruti Clean Coal & Power Ltd. offered an
                 additional capacity of 55 MW, aggregating to a total
                 of 250 MW.
            •    L-2/DB Power Limited, inter-alia, agreed to provide
                 additional quantum of power to the tune of 99 MW,
                 aggregating to a total of 410 MW.
            •    Similarly, L-3/Lanco Power Ltd. offered an additional
                 capacity of 250 MW, aggregating to a total of 350 MW.”
       2.11 The Board of Directors of the RVPN, in its meeting held on 27th
            September 2013, directed that, LoI be issued in favour of the
            L-1, L-2 and L-3 bidders as under, subject to the approval of
            the State Commission while adopting the tariff.

 “S.                Bidder            Quoted       Capacity     Additional
 No.                                   Tariff      offered in   Capacity
                                       (Rs. /      Bid (MW)      Offered
                                       kWh)                       (MW)
1       M/s PTC India Ltd              4.517          195           55
        (through developer M/s
        Maruti Clean Coal and
        Power Limited)
2       M/s PTC India Ltd (through     4.811          311           99
        their developer M/s DB
        Power Limited)4.811
3       M/s Lanco Power Limited        4.892          100           250
        (Generation Source – M/s
        Lanco Babandh Power
        Limited)
        Total                                         606           404
G. Total (A+B)                                          1010 MW”
       2.12 In consonance with the LoI, on 1st November 2013, PPAs were
            signed with the L-1, L-2 and L-3 bidders. Thereafter, RVPN
            filed Petition No.431 of 2013 before the State Commission
            under Section 63 of the Electricity Act read with clause 5.16
920                                                        [2024] 1 S.C.R.

                      Digital Supreme Court Reports


             of the Bidding Guidelines for adoption of tariff for purchase
             of long-term base load power of 1000 MW (±10%) as quoted
             by the successful bidders (being L-1, L-2 and L-3) under the
             Case-I bidding process.
       2.13 The Energy Assessment Committee (“EAC” for short),
            constituted by the Government of Rajasthan pursuant to
            Regulation 3 of the Power Procurement Regulations, in its
            4th meeting held on 29th January 2014, recommended that
            there was no requirement for long term procurement of 1000
            MW (±10%) power under Case-I for which PPAs had been
            executed and tariff adoption petition had been filed before the
            State Commission.
       2.14 In the meantime, the L-4 and L-5 bidders filed Writ Petitions
            being CWP No. 19437 of 2013 and CWP No.18699 of 2013
            respectively, before the High Court, seeking to strike down
            the negotiations process and the higher quantum awarded
            to L-1, L-2 and L-3 bidders.
       2.15 The High Court vide judgment dated 7th February 2014, refused
            to entertain the writ petitions and relegated the parties to the
            State Commission. The said order dated 7th February 2014
            came to be challenged by the L-4 and L-5 bidders by way
            of writ appeals being DB Special Appeals (Writ) Nos. 538 of
            2014 and 604 of 2014. The said appeals also came to be
            dismissed by the High Court vide judgment and order dated
            18th April 2014.
       2.16 Subsequently, in its 5th meeting held on 21st May 2014, the
            EAC recommended that as against the quantum of 1000 MW
            power, for which PPAs had been executed and tariff adoption
            petition had been filed, a demand of 600 MW power ought to
            be considered, on account of availability of power from various
            sources and to meet future contingencies.
       2.17 The Government of Rajasthan, therefore, vide its letter dated
            25th July 2014, issued to the RVPN, approved the purchase of
            a quantum of 500 MW power on long term basis as against
            the quantum of 1000 MW for which PPAs had already been
            executed.
[2024] 1 S.C.R.                                                        921

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     2.18 On the basis of the decision/recommendation of the EAC
          and the direction issued by the Government of Rajasthan,
          RVPN filed an application under Regulation 7 of the RERC
          (Power Purchase & Procurement Process of Distribution
          Licensee) Regulations 2004 (hereinafter referred to as “RERC
          Regulations 2004”) in Petition No.431 of 2013, to bring on
          record the EAC decision/recommendation and the Government
          of Rajasthan approval. In the said application, inter alia, it
          was prayed for adoption of tariff and approval of the reduced
          quantum of 500 MW of power to be purchased as against the
          original 1000 MW of power for which PPAs had already been
          executed with the successful bidders.
     2.19 Vide order dated 22nd July 2015 in Petition No.431 of 2013,
          the State Commission held that the quantum of only 500 MW
          power was liable to be approved considering the demand in
          the State as recommended by the EAC. The State Commission
          also approved the tariff quoted by the L-1 to L-3 bidders.
     2.20 Aggrieved by the reduction of quantum by the State
          Commission, the L-2 and L-3 bidders preferred appeals
          before the learned Appellate Tribunal for Electricity (hereinafter
          referred to as “the learned APTEL”) being Appeal Nos. 235 of
          2015 and 191 of 2015 respectively.
     2.21 Two separate appeals were also preferred by the L-4 and
          L-5 bidders, being Appeal No. 264 of 2015 and Appeal No.
          202 of 2015 respectively, wherein apart from challenging the
          reduction of quantum by the State Commission from 1000
          MW to 500 MW, the increase in quantum granted to the L-1,
          L-2 and L-3 bidders was also challenged.
     2.22 Vide order dated 2nd February 2018, the learned APTEL allowed
          the Appeal Nos. 191 of 2015 and 235 of 2015, filed by the L-3
          and L-2 bidders, holding that the reduction of quantum by the
          State Commission from 1000 MW to 500 MW was incorrect. It,
          therefore, directed the State Commission to pass consequential
          orders for approving the PPAs for the L-2 and L-3 bidders for
          the higher quantum which was negotiated.
     2.23 The order of the learned APTEL dated 2nd February 2018,
          was challenged by the present appellants before this Court by
922                                                         [2024] 1 S.C.R.

                      Digital Supreme Court Reports


             way of Civil Appeal Nos. 3481-3482 of 2018, on the ground
             that the RFP quantum cannot be restored from 500 MW to
             1000 MW. Subsequently, Civil Appeal Nos. 2502-2503 of 2018
             also came to be filed by L-5 bidder- SKS Power Generation
             (Chhattisgarh) Limited (hereinafter referred to as “SKS Power”),
             on the ground that the State Commission could not have
             permitted the procurement of higher quantum by the L-2 and
             L-3 bidders.
       2.24 Vide order dated 25th April 2018, the said Civil Appeals were
            disposed of by this Court, upholding the decision of the learned
            APTEL, setting aside the reduction of quantum of procurement
            from 1000 MW to 500 MW after the bidding process was
            over. However, this Court held that the decision of the learned
            APTEL on the quantum to be procured from individual bidders
            was liable to be reversed and that the quantum originally
            offered by the bidders in the bidding process has to be taken
            into consideration and increase in quantum by means of
            negotiation was not permissible. Insofar as L-4 and L-5 bidders
            are concerned, since the tariff quoted was not considered at
            any stage by either the procurer, or by RVPN or by the State
            Commission, this Court directed the State Commission to go
            into the issue of approval for adoption of tariff with regard to
            L-4 and L-5 bidders.
       2.25 Subsequent to the judgment and order dated 25th April 2018,
            passed by this Court, the BEC came to a finding that the
            tariffs quoted by the L-4 and L-5 bidders were not aligned to
            the prevailing market prices.
       2.26 In the meantime, vide order dated 19th November 2018, this
            Court, on an application filed by RVPN, directed the State
            Commission to go into the issue of adoption of tariff in terms
            of Section 63 of the Electricity Act and the law laid down by
            this Court under the said provision.
       2.27 Vide order dated 26th February 2019, the State Commission
            held that the tariffs offered by the L-4 and L-5 bidders were
            not aligned to the prevailing market prices.
       2.28 Being aggrieved by the same, SKS Power (L-5 bidder)
            challenged the above order dated 26th February 2019 before
            the learned APTEL by way of Appeal No.224 of 2019.
[2024] 1 S.C.R.                                                              923

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     2.29 Vide the judgment and order dated 3rd February 2020, the
          learned APTEL allowed the appeal of the L-5 bidder – SKS
          Power and held that the State Commission had to necessarily
          adopt the tariff, and had no power to consider whether the
          tariff was aligned to market prices.
     2.30 Aggrieved by the same, the present appellants have filed Civil
          Appeal No. 1937 of 2020 and Civil Appeal No.2721 of 2020.
          Initially, the present appeals were tagged along with the said
          appeals. However, vide order dated 10th October 2023, the
          same have been de-tagged.
     2.31 On an interlocutory application being I.A. No.83693 of 2020
          filed by L-5 bidder-SKS Power in Civil Appeal No. 2721 of 2020,
          an interim order 28th September 2020, came to be passed by
          this Court, holding that the L-5 bidder was entitled to supply
          power to the appellants at the tariff of Rs.2.88 per unit.
     2.32 It appears that subsequently thereafter on 14th December 2020,
          a writ petition being Writ Petition No. 14815 of 2020 came to
          be filed by the respondent No.1-MB Power before the High
          Court, seeking following relief:
            “(a) Issue appropriate Writ or order or direction in the
                 nature of declaration or certiorari or any other writ
                 or direction declaring Rule 69(2)(b) of the RTPP
                 Rules as ultra vires Article 14, 19(1)(g) and 21 of
                 the Constitution of India as well as Section 63 of
                 the Electricity Act, 2003;
            (b)     Issue appropriate Writ or order or direction in the
                    nature of mandamus directing the Respondent
                    Nos. 1-4 to immediately issue a Letter of Intent in
                    favour of the Petitioner, sign the power Purchase
                    Agreement with the Petitioner as per its bid tariff,
                    take steps for adoption of tariff of the Petitioner and
                    immediately commence supply of power;
            (c)     Pass such further order(s) as this Hon’ble Court may
                    deem fit and proper in the facts and circumstances
                    of the instant case in the interest of justice.”
924                                                        [2024] 1 S.C.R.

                      Digital Supreme Court Reports


       2.33 In the appeals filed by the present appellants, i.e., Civil
            Appeal Nos. 1937 of 2020 and 2721 of 2020, respondent
            No.1-MB Power filed an application for impleadment, on
            the ground that the issue of role of the State Commission
            in adoption of tariff being decided by this Court in the said
            appeals would have an impact on the writ petition filed by it
            before the High Court.
       2.34 Vide order dated 19th April 2021, this Court directed the said
            application for impleadment to be considered at the stage of
            hearing of the said appeals.
       2.35 By the impugned judgment and order, the said writ petition
            filed by MB Power has been allowed by the High Court in
            terms of the aforesaid directions.
       2.36 Hence the present appeals.

       CIVIL APPEAL NO. 4612 OF 2023
3.     This appeal filed by Rajasthan Urja Vikas Nigam Limited (hereinafter
       referred to as “RUVNL”) challenges the order dated 1st June 2023,
       passed by the learned APTEL, whereby the learned APTEL has
       stayed the operation of the order dated 31st March 2023, passed by
       the State Commission in Petition No.RERC-2097 of 2023.
4.     The facts, in brief, leading to the filing of Civil Appeal No.4612 of
       2023, are as under:
       4.1 In the year 2022, the RUVNL had proposed the procurement of
           294 MW of power on long term basis and for that purpose had
           filed Petition No.2017 of 2022 before the State Commission.
       4.2 Vide order dated 2nd November 2022, the State Commission
           rejected the procurement of power on long term basis.
       4.3 Thereafter, considering the assessment and requirement of
           power, the RUVNL filed Petition No.RERC-2097 of 2023 before
           the State Commission, seeking approval for procurement of
           160 MW of power on medium term basis i.e., for a period of 5
           years and not for 25 years on long term basis.
[2024] 1 S.C.R.                                                       925

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     4.4 Vide order dated 31st March 2023, the State Commission granted
         approval to the distribution licensees in the State of Rajasthan
         for procurement of 160 MW round-the-clock fuel agnostic power
         on medium term basis by way of a competitive bidding process.
     4.5 Aggrieved thereby, the respondent No.1 herein, i.e., MB Power
         (Madhya Pradesh) Limited filed Appeal No. 466 of 2023 before
         the learned APTEL against the order dated 31st March 2023
         passed by the State Commission, along with I.A. No.1004 of
         2023 for the stay of the order.
     4.6 Vide impugned order dated 1st June 2023, the learned APTEL
         stayed operation of the order passed by the State Commission
         and directed that in the bidding process for procurement of 160
         MW of power on medium term basis the bid shall neither be
         finalized nor shall any Letter of Intent be issued pursuant to
         the opening of the bids.
     4.7 Aggrieved thereby, the RUVNL has filed the present appeal.
5.   Vide order dated 26th September 2023, this Court had permitted the
     appellant to proceed further with the tender process for procurement
     of 160 MW of power for 5 years on the basis of model bidding
     documents for medium term procurement.
6.   Vide order dated 10th October 2023, this Court had been informed
     that pursuant to the aforesaid order dated 26th September 2023,
     bids had been opened and the lowest bid was at Rs.5.30 per unit.
     As a result, this Court had clarified that the pendency of the present
     appeal would not come in the way of the appellant in finalizing the
     tender and executing power purchase agreement with the successful
     bidders and the appellant would be at liberty to do so in order to
     overcome the difficulty of power shortage.
7.   The order of the learned APTEL dated 1st June 2023 basically relies
     on the judgment of the Division Bench of the High Court of Judicature
     for Rajasthan, bench at Jaipur, passed in D.B. Civil Writ Petition No.
     14815 of 2020, which is a subject matter of challenge in Civil Appeal
     Nos. 6503 of 2022 and 6502 of 2022. As such, the result of Civil
     Appeal No.4612 of 2023 would depend upon the outcome of Civil
     Appeal Nos. 6503 of 2022 and 6502 of 2022.
926                                                         [2024] 1 S.C.R.

                           Digital Supreme Court Reports


       SUBMISSIONS OF THE APPELLANTS
8.     We have heard Shri P. Chidambaram, learned Senior Counsel
       appearing for the appellants, and Dr. A.M. Singhvi and Shri
       C.S. Vaidyanathan, learned Senior Counsel appearing for the
       respondents.
9.     Shri Chidambaram, at the outset, submits that the writ petition, filed
       by the respondent No.1-MB Power, was not maintainable before
       the High Court in its original jurisdiction under Article 226 of the
       Constitution of India. It is submitted that, if the respondent No.1-MB
       Power had any grievance, it could have either approached the State
       Commission or the learned APTEL.
10. He submits that this Court in the case of PTC India Limited v. Central
    Electricity Regulatory Commission, Through Secretary1 has held
    that the Electricity Act is an exhaustive code on all matters concerning
    electricity. The Electricity Act provides for the forum for adjudication
    of all disputes between a generator and the procurer/licensee. As
    such, the respondent No.1-MB Power, if had any grievance, ought
    to have filed an application before the State Commission or the
    learned APTEL and it could not have approached the High Court
    directly in its writ jurisdiction.
11. Shri Chidambaram further submitted that though L-1 to L-5 bidders
    have continuously been litigating their grievances from 2013
    onwards, the respondent No.1-MB Power, since it was not short-
    listed, had taken no steps from 2013 onwards. It is submitted that,
    as a matter of fact, the bid of L-7 bidder was returned and on 6th
    January 2015, the Bid Bond bank guarantee was also directed to
    be not extended. Still, it kept silent for about 6 years. He further
    submits that even after the judgment and order was passed by
    this Court on 25th April 2018, respondent No.1-MB Power did not
    take any steps for about two years, and for the first time, on 14th
    December 2020, it filed a writ petition before the High Court. As such,
    it is clear that the respondent No.1-MB Power had acquiesced the
    direction by the appellants dated 6th January 2015 not to renew the
    Bid Bond bank guarantee. Shri Chidambaram, therefore, submits
    that the writ petition was liable to be dismissed on the ground of
    delay and laches itself.


1    [2010] 3 SCR 609 : (2010) 4 SCC 603=2010 INSC 146
[2024] 1 S.C.R.                                                          927

                 Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                MB Power (Madhya Pradesh) Limited & Ors.

12. Shri Chidambaram further submits that the term “successful bidder”
    has been defined in the RFP. It is submitted that the bidder(s)
    selected by the procurer/authorized representative, pursuant to the
    RFP for supply of power by itself or through the project company
    as per the terms of the RFP, and to whom a LoI has been issued,
    can only be termed as the “successful bidder”. Since no LoI was
    issued to the respondent No.1-MB Power, it could not be construed
    as a “successful bidder”.
13. Shri Chidambaram submits that the theory of “filling the bucket”, as
    put forth by the respondent No.1-MB Power, has no basis either in
    the RFP or in the Bidding Guidelines. It is further submitted that the
    said theory is a dangerous proposition inasmuch as, it is expected
    that the procurer would be obliged to accept the bids of lower ranked
    financial bids, irrespective of the exorbitant tariff quoted by them.
    Shri Chidambaram has given an illustration to that effect that, if in
    a bid to procure 1000 MW, 2 bidders can be put forward as stalking
    horses who would bid lower tariffs and are ranked as L-1 and L-2.
    Thereafter, L-3 onwards can quote exorbitant tariffs which are not
    aligned to market prices. He submits that this specious theory of
    “filling the bucket”, which would oblige the procurer to go to the last
    bidder, irrespective of their tariffs being completely exorbitant, is very
    dangerous. It is submitted that, in any case, clause 3.5.12 of the
    RFP enables the procurer to reject any bid where the quoted tariff
    is not aligned to market prices.
14. Shri Chidambaram further submits that the directions issued by this
    Court vide order dated 25th April 2018, were specifically restricted
    to L-1 to L-5 bidders, which were litigating. It is submitted that the
    contention of the respondent No.1-MB Power that the order of this
    Court dated 25th April 2018 was an order in rem is erroneous.
15. Relying on the judgment of this Court in the case of R. Viswanathan
    and others v. Rukn-ul-Mulk Syed Abdul Wajid since deceased
    and others2, Shri Chidambaram submits that the judgment in rem
    settles the destiny of the res itself. Whereas an order in personam
    determines the rights of persons before the Court and binds only


2   (1963) 3 SCR 22=AIR 1963 SC 1=1962 INSC 205
928                                                          [2024] 1 S.C.R.

                          Digital Supreme Court Reports


       the parties to the lis. Reliance in this respect is also placed on the
       judgment of this Court in the case of Deccan Paper Mills Company
       Limited v. Regency Mahavir Properties & Ors.3
16. Shri Chidambaram further submits that the reliance by the
    respondents on the certificate, which certified the bid evaluation
    process was carried out in conformity with the provisions of the RFP,
    and, therefore, it is not permissible to go into the determination of
    tariff is incorrect. He submits that the certificate is not certifying that
    L-7 was qualified to be selected as a “successful bidder” or it had
    earned a right to have his bid accepted irrespective of the quoted
    tariff. He submits that if the quoted tariff of L-4 bidder of Rs.5.143
    and L-5 bidder of Rs.5.300 were misaligned, then, most certainly,
    the quoted tariff of L-7 bidder of Rs.5.517 was also misaligned.
17. The learned Senior Counsel submits that the jurisdiction under
    Section 63 of the Electricity Act is not that of a mere post office.
    The State Commission has a power to reject the adoption of tariff
    if it is not aligned to market prices. In this respect, he refers to the
    judgments of this Court in the cases of Tata Power Company Limited
    Transmission v. Maharashtra Electricity Regulatory Commission
    & Ors.4 and Energy Watchdog v. Central Electricity Regulatory
    Commission and others5.
18. Shri Chidambaram submits that the State Commission while adopting
    the tariff is bound to take into consideration the protection of consumer
    interest. Reliance in this respect has been placed on the judgment
    of this Court in the case of GMR Warora Energy Limited v. Central
    Electricity Regulatory Commission (CERC) & Ors.6, wherein this
    Court has emphasized the need for balancing the interest of the
    consumers with that of the generators.
19. Shri Chidambaram further submits that in view of clauses 2.15.1 and
    3.5.12 of the RFP and clause 5.15 of the Bidding Guidelines, the
    appellants had the power to reject all price bids if the rates quoted
    are not aligned to the prevailing market prices.



3   [2021] 13 SCR 786 : (2021) 4 SCC 786=2020 INSC 497
4   [2022] 19 SCR 620 : 2022 SCC Online 1615=2022 INSC 1220
5   [2017] 3 SCR 153 : (2017) 14 SCC 80=2017 INSC 338
6   [2023] 8 SCR 183 : 2023 SCC Online SC 464=2023 INSC 398
[2024] 1 S.C.R.                                                                  929

                  Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                 MB Power (Madhya Pradesh) Limited & Ors.

20. Shri Chidambaram lastly submitted that the bidders have no vested
    right to contract. Article 226 of the Constitution of India cannot be
    used to award a contract in favour of the bidder. In this respect, he
    refers to the following judgments of this Court:
     i.     Tata Cellular v. Union of India7
     ii.    Rajasthan Housing Board and another v. G.S. Investments
            and another8
     iii.   Laxmikant and others v. Satyawan and others9
21. Shri Chidambaram, therefore, submits that the impugned judgment
    and order is not sustainable and is liable to be set aside.

     SUBMISSIONS OF THE RESPONDENTS
22. Dr. A.M. Singhvi, learned Senior Counsel, per contra, submits that
    unlike Section 62 read with Sections 61 and 64 of the Electricity Act,
    under Section 63 of the Electricity Act, the appropriate Commission
    only “adopts” tariff and does not “determine” tariff. However, in cases
    under Section 63 of the Electricity Act, the Central Commission is
    bound by the guidelines issued by the Central Government and it
    is required to exercise its regulatory functions, albeit under Section
    79(1)(b) only in accordance with those guidelines. In this respect, he
    relies on the judgment of this Court in the case of Energy Watchdog
    (supra) and Tata Power Company Limited Transmission (supra).
23. Dr. Singhvi submits that two issues that can be considered in a case
    under Section 63 of the Electricity Act by the Commission are:
     (1)    as to whether the bidding process was transparent; and
     (2)    as to whether the bidding process was held in accordance with
            the guidelines issued by the Central Government.
24. He submits that once the tariff is an outcome of the bidding process
    and the bidding process is transparent and held in accordance with
    the Bidding Guidelines, the appropriate Commission is mandated
    to adopt such tariff and it does not have a discretion to go into the
    question as to whether it is market aligned or not.


7   [1994] 2 Supp. SCR 122 : (1994) 6 SCC 651 (para 94)= 1994 INSC 283
8   [2006] 7 Supp. SCR 868 : (2007) 1 SCC 477 (para 8, 9 and 11)= 2006 INSC 766
9   [1996] 3 SCR 532 : (1996) 4 SCC 208=1996 INSC 409
930                                                        [2024] 1 S.C.R.

                     Digital Supreme Court Reports


25. Dr. Singhvi further submits that while adopting an already determined
    tariff by the bidding process as per Section 63 of the Electricity Act,
    the issue of market alignment of respondent No.1’s bid does not and
    cannot arise for consideration in these proceedings.
26. Without prejudice to the aforesaid submissions, Dr. Singhvi submits
    that it is not permissible for the State Commission to go into the
    question of market alignment. He submitted that the respondent
    No.1’s quoted tariff was market aligned not only in the year 2013
    but also today. Dr. Singhvi submits that in the recent tender for
    procurement of 160 MW electricity, conducted in pursuance to the
    permission granted by this Court, the lowest bid for 1st year tariff
    discovered and approved by the appellants is at Rs.5.30 per unit. It
    is submitted that there is a vast difference between “1st year tariff”
    and “levelized tariff”. Dr. Singhvi submits that however, if this offer
    for supply in the first year of the bid is to be levelized for 25 years,
    it would come to Rs.7.91 per unit, which is around 50% higher than
    the 1st year tariff of the said bidder itself.
27. Dr. Singhvi submits that M/s Deloitte is a common consultant insofar
    as the appellants and the Uttar Pradesh Power Corporation Limited
    (“UPPCL” for short). He submits that, in fact, BEC of UPPCL, in
    March 2013, accepted tariff up to Rs. 5.849 per unit i.e., a tariff
    much higher than that of respondent No.1-MB Power. It is submitted
    that the bidding period in the present case as well as in the case
    of UPPCL is the same. It is submitted that, however, in 2018, the
    Rajasthan BEC mischievously and selectively considered tariff only
    up to 2012 and compared bids of Andhra Pradesh and Kerala, which
    were, in fact, discovered in 2015 and 2014 respectively. It is submitted
    that similarly, in the State of Tamil Nadu, for the same period, the
    equivalent levelized tariff was determined by M/s Deloitte at Rs.5.75
    per unit for 25 years and the same was accepted. It is, therefore,
    submitted that, considering the aforesaid, the levelized tariff of the
    respondent No.1-MB Power for 25 years at Rs.5.517 per unit is
    indisputably market aligned even as on 2012-2013.
28. Dr. Singhvi, relied on the following charts to show that the levelized
    tariff for 25 years, as quoted by the respondent No.1-MB Power, is
    very much market aligned.
[2024] 1 S.C.R.                                                            931

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.


     “Market Price as of 2012-13 – at the time of Rajasthan Bid

Procurer State             1st Year          Levelized      PPA Duration
                           Quoted           Tariff for 25
                            Tariff             years

Rajasthan – L5 (i.e.        3.976              5.300            25 years
SKS)

Rajasthan – L7              4.137              5.517            25 years
(i.e. R1 – MB
Power Bid)

UP – 2013 Tariff             4.36              5.849            25 years
approved by
BEC (Deloitte as
consultant)

TN – Approved               4.117               5.75            15 years
Tariff



  Prices discovered in Rajasthan Medium Term Tender in Sept /
                            Oct 2023

Procurer State                  1st Year         Levelized         PPA
                                Quoted          Tariff for 25    Duration
                                 Tariff            years
Rajasthan – 2023                    5.30            7.91          5 years
Rajasthan – R1 (i.e. L7 –           4.137          5.517         25 years”
MB Power 2012 Bid)



29. Dr. Singhvi, the learned Senior Counsel, relying on clause 3.5.9 of
    the RFP, submits that, no negotiations were permissible in spite of
    the specific clause in the RFP and the opinion to the contrary given
    by the consultant. It is submitted that the appellants tried to negotiate
    the prices with L-1 to L-3 bidders, which decision has been finally
    set aside by this Court vide order dated 25th April 2018.
932                                                         [2024] 1 S.C.R.

                     Digital Supreme Court Reports


30. Dr. Singhvi submits that in view of the specific certificate dated 4th
    June 2013, issued by the BEC, certifying that the bidding procedure
    for the bids in question had been carried out by the appellants in
    conformity with the provisions of the RFP and the Bidding Guidelines
    issued by the Government of India, it is not permissible for the
    appellants to take a contradictory stand.
31. Dr. Singhvi submits that what this Court had directed by order dated
    25th April 2018, was to adopt the tariff with regard to L-4 and L-5
    bidders. By the subsequent order dated 19th November 2018, this
    Court clarified and directed to decide the tariff under Section 63 of
    the Electricity Act having regard to the law laid down both statutorily
    and by this Court. It is submitted that the only scrutiny that could
    be done by the Commission was only with regard to the following
    of the twin requirements as observed by this Court in the case of
    Energy Watchdog (supra).
32. Dr. Singhvi submits that the power to reject the bids is in respect of
    all price bids. He submits that if it is found that the bidding process
    was not transparent and the Guidelines were not followed or the
    bids are not market aligned, then the appellants would be entitled
    to reject all bids and not individually and selectively some bids. He
    submits that if the interpretation as placed by the appellants is to be
    accepted, it will vest an arbitrary power with the procurer of energy
    to arbitrarily reject the bid of any of the bidders. It is submitted that
    such an unfettered and unchecked discretion cannot be permitted to
    be exercised by the appellants/distribution companies (“DISCOMS”).
33. Dr. Singhvi submits that insofar as the aspect with regard to
    “consumer’s interest” is concerned, the learned APTEL has squarely
    covered the same. It has been held by the learned APTEL that the
    consumers’ interest is a broad term and among others, involves
    reliable, quality and un-interrupted power on long term basis besides
    being competitive.
34. The learned Senior Counsel submits that the State of Rajasthan
    needed 1000 MW of power when it invited the bids in question. He
    submits that the DISCOMS have even fairly admitted that they are
    still in need of power and as such, filed an Interlocutory Application
[2024] 1 S.C.R.                                                        933

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     being I.A. No. 150366 of 2023 in Civil Appeal No.4612 of 2023
     (for permission to file additional documents) seeking permission
     to procure power for medium term from the State Commission. It
     is, therefore, submitted that even in the larger public interest and
     consumer interest, the appellants should procure the power from the
     respondent No.1-MB Power. Dr. Singhvi submits that the appellants
     are bound to procure 906 MW of power in view of the orders passed
     by this Court on 25th of April 2018. He submits that the RFP provides
     for bucket filling. It is, therefore, submitted that the appellants are
     required to procure the power going down the ladder from the bidders
     starting from L-1 to the one till procurement of 906 MW of power is
     complete. It is submitted that since many of the bidders had now
     gone into insolvency, it is only 3 bidders, which are left in the fray.
     L-1 bidder is supplying 195 MW power and L-2 is supplying 311 MW
     power. It is submitted that even in the event, this Court permits L-5
     bidder to supply 100 MW power and 160 MW power for medium term
     in pursuance to the order passed by this Court on 26th September
     2023, still the total would not be beyond 766 MW. Still the balance
     of 140 MW power would remain.
35. Dr. Singhvi submits insofar as contention of the appellants with regard
    to delay and laches is concerned, the same is without substance.
    He submits that only after the respondent No.1 came to know about
    the incapacity of L-3, L-4 and L-6 bidders to honour their offered
    capacity, the occasion to revalidate the claim of the respondent
    No.1 arose. The learned Senior Counsel, relying on clause 3.5.6 of
    the RFP, submits that the selection process shall continue till the
    requisitioned capacity has been achieved through the summation
    of the quantum offered by the “successful bidders” or when the
    balance of the requisitioned capacity is less than the minimum bid
    capacity. It is submitted that since there is still a gap of 140 MW, to
    comply with this Court’s order dated 25th April 2018, the appellants
    are bound to enter into PPAs with the qualified bidders until the
    entire requisitioned capacity of 906 MW is met.
36. Dr. Singhvi relied on the following chart to show that the prices
    discovered in all medium and long term bids are much higher than
    the levelized price quoted by the respondent No.1-MB Power.
934                                                      [2024] 1 S.C.R.

                    Digital Supreme Court Reports



 “Prices discovered in all medium and long term bids since 2022

Procurer State              1st Year      Levelized      PPA Duration
                            Quoted       Tariff for 25
                             Tariff         years
Adani Mumbai– 2022            5.98           8.78          2.1 years
Uttarakhand–2023              5.41           7.93          1.5 years
Noida Power – 2022            5.15           7.46           3 years
Mundra SEZ– 2023              5.00           6.69          15 years
Haryana – 2022            5.70 to 5.75       8.36           3 years
J & K – 2023                  6.05           8.22           5 years
Haryana – 2023                6.05           8.22           5 years
NDMC – 2023                   6.05           8.22           5 years
Madhya Pradesh–2023           6.05           8.22           5 years
Haryana – 2023                5.79           8.49           5 years
Gujarat – 2023            5.18 to 5.69       6.81          15 years
Uttarakhand–2023              7.97           11.72         3.5 years
Noida Power – 2023            6.30           9.18          3 years”

37. Dr. Singhvi, therefore, submits that, if the directions as issued by
    the High Court are maintained, it will be in the interests of the
    consumers, who will be getting the electricity at lesser prices than
    what has recently been emerged as a levelized price in the bidding
    process. He submits that this is specifically so when indisputably
    even according to the appellants they are in dire need of power.
    Dr. Singhvi, therefore, prays for dismissal of the present appeals.
38. Shri C.S. Vaidyanathan, learned Senior Counsel also addressed
    similar arguments and prayed for dismissal of the present appeals.

       CONSIDERATIONS
39. For considering the rival submissions, it will be necessary to refer
    to some of the provisions of the Electricity Act, which are as under:
          “63. Determination of tariff by bidding process. -
          Notwithstanding anything contained in section 62, the
          Appropriate Commission shall adopt the tariff if such
[2024] 1 S.C.R.                                                             935

                  Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                 MB Power (Madhya Pradesh) Limited & Ors.

           tariff has been determined through transparent process
           of bidding in accordance with the guidelines issued by the
           Central Government.”
                                    xxx xxx xxx
           79. Functions of Central Commission.-(1) The Central
           Commission shall discharge the following functions,
           namely:-
           (a)    ………………………………………
           (b)    to regulate the tariff of generating companies other
                  than those owned or controlled by the Central
                  Government specified in clause (a), if such generating
                  companies enter into or otherwise have a composite
                  scheme for generation and sale of electricity in more
                  than one State;
                                    xxx xxx xxx
           “86. Functions of State Commission.- (1) The State
           Commission shall discharge the following functions,
           namely: -
           (a)    …………….
           (b)    regulate electricity purchase and procurement
                  process of distribution licensees including the price at
                  which electricity shall be procured from the generating
                  companies or licensees or from other sources through
                  agreements for purchase of power for distribution and
                  supply within the State;”
40. It will also be relevant to refer to part of the preamble of the Bidding
    Guidelines notified by the Union of India vide Resolution dated 19th
    January 2005, which is as under:
           “These guidelines have been framed under the above
           provisions of section 63 of the Act. The specific objectives
           of these guidelines are as follows:
           1.     Promote competitive procurement of electricity by
                  distribution licensees;
936                                                        [2024] 1 S.C.R.

                     Digital Supreme Court Reports


          2.    Facilitate transparency and fairness in procurement
                processes;
          3.    Facilitate reduction of information asymmetries for
                various bidders;
          4.    Protect consumer interests by facilitating competitive
                conditions in procurement of electricity;
          5.    Enhance standardization and reduce ambiguity and
                hence time for materialization of projects;
          6.    Provide flexibility to suppliers on internal operations
                while ensuring certainty on availability of power and
                tariffs for buyers.”
41. It will also be relevant to refer to certain clauses of the RFP, which
    are as under:
       2.15     Right to withdraw the RFP and to reject any Bid.
       2.15.1   This RFP may be withdrawn or cancelled by the
                Procurer/ Authorized Representative at any time
                without assigning any reasons thereof. The Procurer/
                Authorized Representative further reserves the right,
                at its complete discretion, to reject any or all of the
                Bids without assigning any reasons whatsoever and
                without incurring any liability on any account.”
                                     xxx xxx xxx
       “3.5     STEP IV- Successful Bidder(s) Selection
       3.5.1    Bids qualifying in Step III shall only be evaluated in
                this stage.
       3.5.2    The Levelized Tariff calculated as per Clause 3.4.8
                for all Financial Bids of Qualified Bidders shall be
                ranked from the lowest to the highest.
       3.5.3    The Bidder with the lowest Levelized Tariff shall be
                declared as the Successful Bidder for the quantum
                of power (in MW) offered by such Bidder in its
                Financial Bid.
       3.5.4    The selection process of the Successful Bidder as
                mentioned above in Clause 3.5.3 shall be repeated for
[2024] 1 S.C.R.                                                         937

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

                all the remaining Financial Bids of Qualified Bidders
                until the entire Requisitioned Capacity is met or
                until the time when the balance of the Requisitioned
                Capacity is less than the Minimum Bid Capacity.
      3.5.5     At any step in the process in Clause 3.5.4, in case
                the Requisitioned Capacity has not been achieved
                and the offered capacity of the Bidder with the lowest
                Levelized Tariff amongst the remaining Financial Bids
                is larger than the balance Requisitioned Capacity, any
                fraction or combination of fractions offered by such
                Bidder shall be considered for selection, towards
                meeting the Requisitioned Capacity.
      3.5.6     The selection process shall stand completed once
                the Requisitioned Capacity has been achieved
                through the summation of the quantum offered by
                the Successful Bidders or when the balance of the
                Requisitioned Capacity is less than the Minimum
                Bid Capacity.
                Provided however in case only one Bidder remains
                at any step of the selection process and the balance
                Requisitioned Capacity exceeds the Minimum Bid
                Capacity, Financial Bid(s) of such Bidder shall be
                referred to Appropriate Commission and the selection
                of the Bidder shall then be at the sole discretion of
                the Appropriate Commission.
      3.5.7     At any step during the selection of Successful
                Bidder(s) in accordance with Clauses 3.5.2 to 3.5.6,
                the Procurer / Authorized Representative reserves
                the right to increase / decrease the Requisitioned
                Capacity by up to ten percent (10%) of the quantum
                indicated in Clause 1.3.1 to achieve the balance
                Requisitioned Capacity and select the Successful
                Bidder with the lowest Levelized Tariff amongst
                the remaining Bids. Any increase / decrease in the
                Requisitioned Capacity exceeding ten percent (10%)
                of the quantum in Clause 1.3.1. can be made only
                with the approval of the Appropriate Commission.
938                                                           [2024] 1 S.C.R.

                      Digital Supreme Court Reports


       3.5.8    The Letter(s) of Intent shall be issued to all such
                Successful Bidder(s) selected as per the provisions
                of this Clause 3.5.
       3.5.9    There shall be no negotiation on the Quoted Tariff
                between the Authorized Representative/ Procurer
                and the Bidder(s) during the process of evaluation.
       3.5.10   Each Successful Bidder shall unconditionally accept
                the LOI, and record on one (1) copy of the LOI,
                “Accepted Unconditionally”, under the signature of
                the authorized signatory of the Successful Bidder
                and return such copy to the Procurer/ Authorized
                Representative within seven (7) days of issue of LOI.
       3.5.11   If the Successful Bidder, to whom the Letter of Intent
                has been issued does not fulfill any of the conditions
                specified in Clauses 2.2.8 and 2.2.9, the Procurer /
                Authorized Representative reserves the right to annul
                the award of the Letter of Intent of such Successful
                Bidder. Further, in such a case, the provisions of
                Clause 2.5 (b) shall apply.
       3.5.12   The Procurer / Authorized Representative, in its own
                discretion, has the right to reject all Bids if the Quoted
                Tariff are not aligned to the prevailing market prices.”
42. It will also be relevant to refer to clause 5.15 of the Bidding Guidelines,
    which is as under:
           “5.1 The bidder who has quoted lowest levellised tariff as
                per evaluation procedure, shall be considered for the
                award. The evaluation committee shall have the
                right to reject all price bids if the rates quoted
                are not aligned to the prevailing market prices.”
                                                   [emphasis supplied]
43. Successful bidder has been defined in the RFP as under:
           “Successful Bidder(s)” shall mean the Bidder(s)
           selected by the Procurer/ Authorized Representative, as
           applicable pursuant to this RFP for supply of power by
           itself or through the Project Company as per the terms of
[2024] 1 S.C.R.                                                        939

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

           the RFP Documents, and to whom a Letter of Intent has
           been issued;”
44. The impugned judgment of the High Court is basically based on the
    judgment of the learned APTEL dated 3rd February 2020 in the case
    of SKS Power and orders passed by this Court as already observed
    herein above. After the bids were received for procurement of 1000
    MW, the BEC decided to accept the bids of L-1, L-2 and L-3 bidders.
    However, as the State government had recommended reduction of
    purchase to only 500 MW power, RVPN filed an application under
    Regulation 7 of the RERC Regulations 2004, for adoption of tariff
    of L-1 to L-3, so also allowing it to purchase only 500 MW of power
    as against 1000 MW. The said application was allowed by the State
    Commission. The State Commission also adopted the tariff determined
    through the bidding process for purchase of 500 MW power vide its
    order dated 22nd July 2015. The said order of the State Commission
    was challenged before the learned APTEL by M/s D.B. Power Ltd
    [L-2 bidder] and by M/s Lanco Power Ltd. [L-3 bidder] by way of
    Appeal Nos. 235 of 2015 and 191 of 2015 respectively.
45. The learned APTEL in the said appeals, vide judgment and order
    dated 2nd February 2018, set aside the order of the State Commission
    dated 22nd July, 2015, and passed the following directions:
                                   “ORDER
           Hence, the Appeal Nos. 235 of 2015 and 191 of 2015
           are allowed and the State Commission’s order dated
           22.07.2015 is set aside. The State Commission is directed
           to pass consequential order in accordance with the law
           keeping in view our observations made above as well as the
           judgments of this Tribunal rendered earlier on the aspects
           of the scope of Section 63 of the Act as expeditiously as
           possible, preferably, within 2 months from today. No order
           as to costs.”
46. After the learned APTEL passed the aforesaid order, M/s D.B. Power
    Ltd. (L-2 bidder) filed an Interlocutory Application before the State
    Commission, praying for passing forthwith consequential orders in
    terms of the judgment of the learned APTEL. It also sought a direction
    to DISCOMS to start procuring power from it to the extent of 410
    MW as per the PPA dated 1st November 2013.
940                                                         [2024] 1 S.C.R.

                     Digital Supreme Court Reports


47. When the matter was heard by the State Commission on 8th March
    2018, it was noticed that appeals against the order of the learned
    APTEL were pending before this Court.
48. This Court disposed of the said appeals vide judgment and order
    dated 25th April 2018, and issued the following directions:
          “We are in agreement with the earlier conclusion of the
          APTEL. We are of the view that the direction of reduction
          of capacity from 1000 mw to 500 mw by the State
          Commission was correctly set aside. Since L-1 to L-5 were
          represented before this Court, we direct that they shall be
          entitled to supply of power in terms of the originally offered
          amount, mentioned above, in accordance with para 3.5
          of the Request for Proposal. The power supply will now
          be reduced to a total of 906 mw. The State Commission
          may now go into the issue of approval for adoption of tariff
          with regard to L-4 and L-5. All Letters of Intent (LOIs) shall
          stand modified in terms of the above. All the appeals shall
          stand disposed of in terms of the above order.”
49. Consequent to the orders passed by this Court, the State Commission
    vide its order dated 29th May 2018, directed RVPN/DISCOMS to file an
    appropriate application/petition in relation to L-3, L-4 and L-5 bidders.
50. RVPN accordingly filed an application on 27th August 2018 before
    the State Commission, submitting therein that the tariff of L-4 and
    L-5 bidders was very high and not aligned to market prices and,
    therefore, sought not to be adopted in terms of the competitive
    bidding guidelines and documents.
51. In the meantime, a Contempt Petition came to be filed before this
    Court by SKS Power. This Court vide order dated 20th September
    2018, in the said Contempt Petition, issued the following directions:
          “We are of the view that there is no doubt whatsoever
          that now the PPA has to be signed between the parties.
          However, the State Commission, may, as per our order,
          go into the issue of approval of adoption of tariff with
          regard to L-5, who is the party before us, and will decide
          the same within a period of six weeks from today.
[2024] 1 S.C.R.                                                          941

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

           PPA is to be signed immediately thereafter.”
                                                 [emphasis supplied]
52. Thereafter, SKS Power filed an Interlocutory Application on 5th October
    2018, praying for adoption of its tariff as per the orders of this Court
    dated 25th April 2018 and 20th September 2018.
53. It was contended before the State Commission by SKS Power that
    the State Commission was bound to adopt tariff as quoted by it.
    However, per contra, it was contended by the RVPN and DISCOMS
    that since the tariff quoted by SKS Power was not market aligned,
    it could not be adopted. In view of the counter submission, the
    State Commission vide its order dated 16th October 2018, gave an
    opportunity to the RVPN to file an amended application or seek
    direction on the issue from this Court.
54. Accordingly, RVPN filed a Miscellaneous Application before this
    Court. This Court vide order dated 19th November 2018, passed
    the following order:
           “Having heard learned counsels for both the parties,
           we only clarify that the Rajasthan Electricity Regulatory
           Commission [the State Commission) is to decide the tariff
           under-Section 63 of the Electricity Act, 2003 having regard
           to the law laid down both statutorily and by this Court.
           The State Commission to finalise the aforesaid prices
           within a period of eight weeks from today.
           The MAs are disposed of accordingly.”
55. A review application was also filed on behalf of the SKS Power. The
    said review application was disposed of by this Court vide order
    dated 21st January 2019, with the following directions:
           “------. We find that as per the Standard Bidding Guidelines
           the PPA is first to be signed after which the question of
           adoption of tariff has to be taken up.
           With this clarification of the 20.09.2018 order, we dispose
           of the review and the M.A.
           The State Commission which has reserved its judgment
942                                                         [2024] 1 S.C.R.

                     Digital Supreme Court Reports


          on 16.01.2019 will hear the parties within a period of two
          weeks from today and will pass orders after taking into
          account the order that we have passed today.”
56. In accordance with the directions issued by this Court, the State
    Commission considered the rival submissions of the parties and
    came to a conclusion that the tariff quoted by SKS Power was not
    market aligned. The State Commission also found that, adoption of
    such high rate would be against the consumer interest. The State
    Commission, therefore, vide order dated 26th February 2019, decided
    not to adopt the tariff quoted by L-4 and L-5 bidders.
57. The said order dated 26th February 2019 of the State Commission
    was challenged before the learned APTEL by SKS Power by way
    of Appeal No.224 of 2019. The learned APTEL framed the following
    three issues in the said appeal:
         “ISSUE NO.1:      Whether the Respondent Commission
                           could reject the tariff/bid of the Appellant,
                           in terms of Section 63 of the Electricity
                           Act, 2003 and the directions issued by the
                           Hon’ble Supreme Court?
         ISSUE NO.2:       Whether there was a sufficient proof to
                           show that the bid of the Appellant was
                           market aligned?
         ISSUE NO.3:       Whether the argument of Consumer interest
                           be advanced by the Rajasthan Discoms in
                           the facts of the present Appeal?”
58. The learned APTEL while answering the first issue, came to the
    conclusion that the State Commission, while adopting tariff under
    Section 63, has to only consider that the Bidding Guidelines issued
    by the Central Government providing for tariff structure were complied
    with or not. The learned APTEL also held that the State Commission
    cannot exercise its powers de hors such guidelines. It further held that
    the State Commission has no power to reject the tariff of a bidder.
59. Insofar as the second issue is concerned, the learned APTEL came
    to a finding that, since the bid of SKS Power was already evaluated,
    and the subsequent certificates were issued by the BEC confirming
[2024] 1 S.C.R.                                                       943

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     the transparency of the bid, it was not open for the State Commission
     to go into the question, as to whether the tariff quoted by SKS Power
     was market aligned or not. It further held that, after the order dated
     25th April 2018 was passed by this Court, it was not open for the
     State Commission to re-evaluate the bid.
60. Insofar as the third issue with regard to consumers’ interest is
    concerned, the learned APTEL held that the said issue cannot be
    raised again at that stage when the same had been dealt with in
    detail by the learned APTEL vide order dated 2nd February 2018
    and also considered by this Court before passing the order dated
    25th April, 2018.
61. Accordingly, the appeal was allowed by the learned APTEL vide order
    dated 3rd February 2020 and the order dated 26th February 2019 of
    the State Commission was set aside. The learned APTEL directed
    that the tariff of SKS Power, as offered in its bid, shall be adopted.
    The parties were directed to revive and implement the PPA dated 4th
    February 2019. This order dated 3rd February 2020, passed by the
    learned APTEL has been challenged by the DISCOMS and RVPN
    before this Court by way of Civil Appeal No.1937 of 2020 and Civil
    Appeal No. 2721 of 2020 respectively.
62. The respondent No.1 in the present proceedings rests its claim on
    the aforesaid orders passed by this Court and the order dated 3rd
    February 2020, passed by the learned APTEL.
63. Basically, it is the contention of the respondent No.1-MB Power that
    after the orders were passed by this Court, RVPN and the DISCOMS
    were bound to procure electricity/power from the bidders going down
    the ladder until the entire 906 MW power was exhausted. It is their
    contention that once it is certified that the bid evaluation process
    has been complied with as per the Bidding Guidelines issued by the
    Central Government, it is presumed that the process was transparent
    and it is not permissible for the State Commission to go into the
    question of market aligned tariff and also the consumer interest. It is
    their contention that without considering the question, as to whether
    the tariff was market aligned or not, the procurers were bound to
    accept supply from the bidders at the rates quoted by them. It is
    their submission that the power under Section 63 of the Electricity
944                                                         [2024] 1 S.C.R.

                      Digital Supreme Court Reports


       Act restricted the scrutiny only to two aspects, viz., (1) whether the
       Bidding Guidelines framed by the Union of India under Section 63
       of the Electricity Act were followed; and (2) whether the bidding
       process was transparent or not.
64. The High Court in the impugned judgment, relying on the observations
    of the learned APTEL and the earlier orders of this Court has come
    to a conclusion that, applying the test of “filling the bucket”, the
    procurers were bound to take supply from the respondent No.1-MB
    Power at the rates quoted by it. On the basis of the judgment of the
    learned APTEL, the High Court held that the respondent No.1-MB
    Power had a right to supply power since there was a gap of 300
    MW between the power procured by the procurers and the ceiling
    of 906 MW determined by this Court. In these premises, the High
    Court issued a mandamus directing the appellants to take supply
    of 200 MW electricity/power from the respondent No.1-MB Power
    at the rates quoted by it.
65. We, therefore, find that, before deciding the correctness or otherwise
    of the impugned judgment, it will be necessary for us to examine
    the correctness of the judgment and order dated 3rd February 2020,
    passed by the learned APTEL in the case of SKS Power.
66. We have already reproduced Section 63 of the Electricity Act. The
    provisions of Section 63 of the Electricity Act fell for consideration
    before this Court in the case of Energy Watchdog (supra). It will
    be apposite to refer to paragraphs 19 and 20 of the said judgment,
    which are as under:
            “19. The construction of Section 63, when read with the
            other provisions of this Act, is what comes up for decision
            in the present appeals. It may be noticed that Section
            63 begins with a non obstante clause, but it is a non
            obstante clause covering only Section 62. Secondly, unlike
            Section 62 read with Sections 61 and 64, the appropriate
            Commission does not “determine” tariff but only “adopts”
            tariff already determined under Section 63. Thirdly, such
            “adoption” is only if such tariff has been determined
            through a transparent process of bidding, and, fourthly,
            this transparent process of bidding must be in accordance
            with the guidelines issued by the Central Government.
[2024] 1 S.C.R.                                                            945

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

           What has been argued before us is that Section 63
           is a standalone provision and has to be construed
           on its own terms, and that, therefore, in the case of
           transparent bidding nothing can be looked at except
           the bid itself which must accord with guidelines issued
           by the Central Government. One thing is immediately
           clear, that the appropriate Commission does not
           act as a mere post office under Section 63. It must
           adopt the tariff which has been determined through a
           transparent process of bidding, but this can only be
           done in accordance with the guidelines issued by the
           Central Government. Guidelines have been issued under
           this section on 19-1-2005, which guidelines have been
           amended from time to time. Clause 4, in particular, deals
           with tariff and the appropriate Commission certainly has
           the jurisdiction to look into whether the tariff determined
           through the process of bidding accords with Clause 4.
           20. It is important to note that the regulatory powers of
           the Central Commission, so far as tariff is concerned, are
           specifically mentioned in Section 79(1). This regulatory
           power is a general one, and it is very difficult to state
           that when the Commission adopts tariff under Section
           63, it functions dehors its general regulatory power under
           Section 79(1)(b). For one thing, such regulation takes
           place under the Central Government’s guidelines. For
           another, in a situation where there are no guidelines or in
           a situation which is not covered by the guidelines, can it
           be said that the Commission’s power to “regulate” tariff is
           completely done away with? According to us, this is not a
           correct way of reading the aforesaid statutory provisions.
           The first rule of statutory interpretation is that the statute
           must be read as a whole. As a concomitant of that rule,
           it is also clear that all the discordant notes struck by the
           various sections must be harmonised. Considering the fact
           that the non obstante clause advisedly restricts itself to
           Section 62, we see no good reason to put Section 79 out
           of the way altogether. The reason why Section 62 alone
           has been put out of the way is that determination of tariff
           can take place in one of two ways — either under Section
946                                                          [2024] 1 S.C.R.

                     Digital Supreme Court Reports


          62, where the Commission itself determines the tariff in
          accordance with the provisions of the Act (after laying
          down the terms and conditions for determination of tariff
          mentioned in Section 61) or under Section 63 where the
          Commission adopts tariff that is already determined by a
          transparent process of bidding. In either case, the general
          regulatory power of the Commission under Section 79(1)
          (b) is the source of the power to regulate, which includes
          the power to determine or adopt tariff. In fact, Sections
          62 and 63 deal with “determination” of tariff, which is part
          of “regulating” tariff. Whereas “determining” tariff for inter-
          State transmission of electricity is dealt with by Section
          79(1)(d), Section 79(1)(b) is a wider source of power
          to “regulate” tariff. It is clear that in a situation where
          the guidelines issued by the Central Government under
          Section 63 cover the situation, the Central Commission is
          bound by those guidelines and must exercise its regulatory
          functions, albeit under Section 79(1)(b), only in accordance
          with those guidelines. As has been stated above, it is only
          in a situation where there are no guidelines framed at all
          or where the guidelines do not deal with a given situation
          that the Commission’s general regulatory powers under
          Section 79(1)(b) can then be used.”
                                                  [emphasis supplied]
67. It could thus be seen that it has been held by this Court that unlike
    Section 62 read with Sections 61 and 64, under the provisions of
    Section 63 of the Electricity Act, the appropriate Commission does
    not “determine” tariff but only “adopts” tariff already determined under
    Section 63. It has further been held that, such “adoption” is only if
    such tariff has been determined through a transparent process of
    bidding, and that, this transparent process of bidding must be in
    accordance with the guidelines issued by the Central Government.
    It was sought to be contended before this Court in the said case
    that Section 63 is a standalone provision and has to be construed
    on its own terms, and that, therefore, in the case of transparent
    bidding nothing can be looked at except the bid itself which must
    accord with guidelines issued by the Central Government. However,
    rejecting the said contention, this Court observed that the appropriate
[2024] 1 S.C.R.                                                            947

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
               MB Power (Madhya Pradesh) Limited & Ors.

     Commission does not act as a mere post office under Section 63.
     It has been observed that, Clause 4, in particular, deals with tariff
     and the appropriate Commission certainly has the jurisdiction to look
     into whether the tariff determined through the process of bidding
     accords with Clause 4.
68. This Court in the said case, in paragraph 20, further observed that
    the entire Act shall be read as a whole. It has been held that, all the
    discordant notes struck by the various sections must be harmonized.
    It has been held that, considering the fact that the non obstante
    clause advisedly restricts itself to Section 62, there is no reason to
    put Section 79 out of the way altogether. It has been held that, either
    under Section 62, or under Section 63, the general regulatory power
    of the Commission under Section 79(1)(b) is the source of the power
    to regulate, which includes the power to determine or adopt tariff. It
    has been held that, Sections 62 and 63 deal with “determination” of
    tariff, which is part of “regulating” tariff. It has further been held that,
    in a situation where the guidelines issued by the Central Government
    under Section 63 cover the situation, the Central Commission is bound
    by those guidelines and must exercise its regulatory functions, albeit
    under Section 79(1)(b), only in accordance with those guidelines. It
    has further been held that, it is only in a situation where there are
    no guidelines framed at all or where the guidelines do not deal with
    a given situation that the Commission’s general regulatory powers
    under Section 79(1)(b) can be used.
69. The aforesaid view of this Court in the case of Energy Watchdog
    (supra), which is a judgment delivered by two Judge Bench, has
    been approved by three Judge Bench of this Court in the case of
    Tata Power Company Limited Transmission (supra).
70. We have already referred to Section 86(1)(b) of the Electricity Act,
    which is analogous to Section 79 of the Electricity Act. Section 79
    determines the functions of Central Commission, whereas Section 86
    provides for the functions of the State Commission. Section 86 of the
    Electricity Act empowers the State Commission to regulate electricity
    purchase and procurement process of distribution licensees including
    the price at which electricity shall be procured from the generating
    companies or licensees or from other sources through agreements
    for purchase of power for distribution and supply within the State.
948                                                          [2024] 1 S.C.R.

                      Digital Supreme Court Reports


71. It can thus be seen that Section 86(1)(b) of the Electricity Act gives
    ample power on the State Commission to regulate electricity purchase
    and procurement process of distribution licensees. It also empowers
    the State Commission to regulate the matters including the price at
    which electricity shall be procured from the generating companies, etc.
72. It will also be relevant to refer to the Bidding Guidelines notified by
    the Central Government vide Resolution dated 19th January 2005. The
    preamble of the Bidding Guidelines specifically states that, one of the
    objectives of the said Bidding Guidelines is to facilitate transparency
    and fairness in procurement processes and protection of consumer
    interests by facilitating competitive conditions in procurement of
    electricity.
73. Clause 5.15 of the Bidding Guidelines is an important clause. It
    provides that, the bidder who has quoted lowest levelized tariff as
    per evaluation procedure, shall be considered for the award. It also
    provides that the evaluation committee shall have the right to reject
    all price bids if the rates quoted are not aligned to the prevailing
    market prices.
74. It is thus amply clear that the evaluation committee is empowered to
    consider, as to whether the rates quoted are aligned to the market
    price or not, and that the evaluation committee shall have the right to
    reject all the price bids if it finds that the rates quoted are not aligned
    to the prevailing market price. The orders which are relied upon by
    the learned APTEL, specifically the order dated 19th November 2018
    of this Court, had specifically clarified that the State Commission
    was to decide the tariff under Section 63 of the Electricity Act having
    regard to the law laid down both statutorily and by this Court.
75. In this background, the State Commission was justified in considering
    clause 5.15 of the Bidding Guidelines, which specifically permits to
    reject all price bids if the rates quoted are not aligned to the prevailing
    market prices.
76. The contention that this Court has ordered that the bids quoted by
    the bidders are to be accepted without going into the question of it
    being market aligned or not, in our view, is without substance.
77. If the contention of the respondent No.1-MB Power that the procurer
    is bound to accept all the bids emerged in a competitive bidding
[2024] 1 S.C.R.                                                         949

                Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
               MB Power (Madhya Pradesh) Limited & Ors.

     process once the bidding process was found to be transparent and in
     compliance with the Bidding Guidelines is to be accepted, in our view,
     it will do complete violence to clause 5.15 of the Bidding Guidelines
     itself. If that view is accepted, the DISCOMS will be compelled to
     purchase electricity at a much higher rate as compared with other
     suppliers. The said higher rate will be passed on to the consumers.
     As such, accepting the contention of the respondent No.1 would
     result in adversely affecting the interests of the consumers and,
     in turn, would be against the larger public interest. For example,
     if in a bidding process for 1000 MW power, 10 persons emerged
     as “qualified bidders”. L-1 bidder quotes Rs.2 per unit for 100 MW
     power and L-2 bidder quotes Rs.2.25 per unit for another 100 MW
     power and from L-3 bidder onwards, they start quoting Rs.10 per
     unit and above for balance 800 MW power, could the public interest
     be subserved by compelling the procurer to buy balance 800 MW
     power at Rs.10 per unit and above when the prices quoted are totally
     not aligned to market prices.
78. We are, therefore, of the considered view that the learned APTEL
    has grossly erred in holding that the State Commission has no power
    to go into the question, as to whether the prices quoted are market
    aligned or not and also not to take into consideration the aspect of
    consumers’ interest.
79. When the Bidding Guidelines itself permit the BEC to reject all price
    bids if the rates quoted are not aligned to the prevailing market prices,
    there is no question of the State Commission being not in a position
    to go into the question, as to whether the rates quoted are market
    aligned or not, specifically, in the light of ample powers vested with
    the State Commission under Section 86(1)(b) of the Electricity Act,
    which also includes the power to regulate the prices at which electricity
    shall be procured from the generating companies, etc. The finding
    of the learned APTEL, in our view, therefore, is totally erroneous.
80. In the case of SKS Power, the BEC, consisting of following 6 members,
    has considered the levelized tariff quoted by L-4 and L-5 bidders:
     (i)    Shri R.K. Jain, Chief Engineer (NPP & RA), RVPN, Jaipur;
     (ii)   Shri Manish Saxena, Chief Controller of Accounts, RVPN, Jaipur;
     (iii) Shri M.M. Ranwa, Chief Engineer, RUVNL, Jaipur;
     (iv) Shri K.L. Meena, Addl. Chief Engineer (Fuel), RVUN, Jaipur;
     (v)    Shri S.K. Mathur, Chief Engineer (HQ), JVVNL, Jaipur; and
950                                                       [2024] 1 S.C.R.

                     Digital Supreme Court Reports


       (vi) Shri Tarun Agarwal, CA, Partner M/s Shyamlal Agrawal & Co.,
            Jaipur
81. It can be seen that the said Committee consisted of 4 technical
    members of the rank of Chief Engineer/Additional Chief Engineer.
    It consisted of the Chief Controller of Account, RVPN, Jaipur. It also
    consisted of a Chartered Accountant, who is an expert in financial
    matters. After due deliberations, the BEC consisting of experts found
    that the prices quoted by L-4 and L-5 bidders were exorbitantly
    high and it would result in additional financial burden of more than
    Rs.1715 crore on the consumers of the State as compared to the
    tariff of L-1 bidder.
82. The State Commission after considering the detailed analysis of the
    BEC had come to the considered conclusion that the prices offered
    by SKS Power (L-5 bidder) were not market aligned, and therefore,
    not in the consumers’ interest. We, therefore, find that the learned
    APTEL has grossly erred in reversing the well-reasoned order passed
    by the State Commission, which was, in turn, based on the decision
    of the BEC in accordance with clause 5.15 of the Bidding Guidelines.
83. We further find that it cannot be read from the orders of this Court
    that the State Commission was bound to accept the bids as quoted
    by the bidders till the bucket was filled. Firstly, no such direction
    can be issued by this Court de hors the provisions of Section 63
    and 86(1)(b) of the Electricity Act and the Bidding Guidelines. In
    any event, vide order dated 19th November 2018, this Court had
    specifically directed the State Commission to decide the tariff under
    Section 63 of the Electricity Act having regard to the law laid down
    both statutorily and by this Court. As such, the State Commission
    was bound to take into consideration the Bidding Guidelines and
    specifically clause 5.15 thereof.
84. With regard to the contention that the power under clause 5.15 of the
    Bidding Guidelines can be exercised only when the bidding process
    is found to be not in compliance with the Bidding Guidelines and
    is not transparent in respect of all the bidders and not in respect of
    some of the bidders is concerned, in our view, the same is without
    substance.
85. We may in this respect refer to Section 13(2) of the General Clauses
    Act, which reads thus:
[2024] 1 S.C.R.                                                            951

                   Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                  MB Power (Madhya Pradesh) Limited & Ors.

             “13. Gender and number.—In all Central Acts and
             Regulations, unless there is anything repugnant in the
             subject or context,—
             (1) …………………; and
             (2) words in the singular shall include the plural, and vice
             versa.”
86. Apart from that, the Constitution Bench of this Court in the case of
    Vivek Narayan Sharma and others v. Union of India and others10
    had an occasion to consider the question, as to whether the word
    “any” would include “all” and vice versa. The Constitution Bench of
    this Court observed thus:
          “113. It is strenuously urged by the learned Senior Counsel
          appearing on behalf of the petitioners that the word “any” used
          in sub-section (2) of Section 26 of the RBI Act will have to be
          given a restricted meaning to mean “some”. It is submitted that if
          sub-section (2) of Section 26 of the RBI Act is not read in such
          manner, the very power available under the said sub-section
          will have to be held to be invalid on the ground of excessive
          delegation. It is submitted that it cannot be construed that
          the legislature intended to bestow uncanalised, unguided and
          arbitrary power on the Central Government to demonetise the
          entire currency. It is, therefore, the submission of the petitioners
          that in order to save the said section from being declared void,
          the word “any” requires to be interpreted in a restricted manner
          to mean “some”.
          114. Per contra, it is submitted on behalf of the respondents
          that the word “any” under sub-section (2) of Section 26 of the
          RBI Act, cannot be interpreted in a narrow manner and it will
          have to be construed to include “all”.
          Precedents construing the word “any”
          115. A Constitution Bench of this Court in Chief Inspector of
          Mines v. Lala Karam Chand Thapar [Chief Inspector of Mines
          v. Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC


10   [2023] 1 SCR 1 : (2023) 3 SCC 1=2023 INSC 2
952                                                      [2024] 1 S.C.R.

                   Digital Supreme Court Reports


       838] was considering the question as to whether the phrase
       “any one of the Directors” as found in Section 76 of the Mines
       Act, 1952 could mean “only one of the Directors” or could it
       be construed to mean “every one of the Directors”. In the said
       case, all the Directors of the Company were prosecuted for the
       offences punishable under Sections 73 and 74 of the Mines Act,
       1952. The High Court had held [Lala Karam Chand Thapar v.
       State of Bihar, 1958 SCC OnLine Pat 30] that any “one” of the
       Directors of the Company could only be prosecuted.
       116. The Constitution Bench of this Court observed thus : (Lala
       Karam Chand Thapar case [Chief Inspector of Mines v. Lala
       Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838],
       AIR pp. 847-48, paras 29-34)
         “29. It is quite clear and indeed not disputed that in some
         contexts, “any one” means “one only it matters not which
         one” the phrase “any of the Directors” is therefore quite
         capable of meaning “only one of the Directors, it does
         not matter which one”. Is the phrase however capable
         of no other meaning? If it is not, the courts cannot look
         further, and must interpret these words in that meaning
         only, irrespective of what the intention of the legislature
         might be believed to have been. If however the phrase
         is capable of another meaning, as suggested viz. “every
         one of the Directors” it will be necessary to decide which
         of the two meanings was intended by the legislature.
         30. If one examines the use of the words “any one”
         in common conversation or literature, there can be no
         doubt that they are not infrequently used to mean “every
         one” — not one, but all. Thus we say of any one can
         see that this is wrong, to mean “everyone can see that
         this is wrong”. “Any one may enter” does not mean that
         “only one person may enter”, but that all may enter. It is
         permissible and indeed profitable to turn in this connection
         to Oxford English Dictionary, at p. 378, of which, we find
         the meaning of “any” given thus:‘In affirmative sentences,
         it asserts, concerning a being or thing of the sort named,
         without limitation as to which, and thus collectively of
[2024] 1 S.C.R.                                                            953

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

           every one of them’. One of the illustrations given is — “I
           challenge anyone to contradict my assertions”. Certainly,
           this does not mean that one only is challenged; but that
           all are challenged. It is abundantly clear therefore that
           “any one” is not infrequently used to mean “every one”.
           31. But, argues Mr Pathak, granting that this is so, it must
           be held that when the phrase “any one” is used with the
           preposition “of”, followed by a word denoting a number
           of persons, it never means “every one”. The extract from
           Oxford Dictionary, it is interesting to notice, speaks of an
           assertion “concerning a being or thing of the sort named”;
           it is not unreasonable to say that, the word “of” followed
           by a word denoting a number of persons or things is just
           such “naming of a sort” as mentioned there. Suppose, the
           illustration “I challenge any one to contradict my assertions”
           was changed to “I challenge any one of my opponents
           to contradict my assertion”. “Any one of my opponents”
           here would mean “all my opponents” — not one only of
           the opponents.
           32. While the phrase “any one of them” or any similar
           phrase consisting of “any one”, followed by “of” which is
           followed in its turn by words denoting a number of persons
           or things, does not appear to have fallen for judicial
           construction, in our courts or in England — the phrase “any
           of the present Directors” had to be interpreted in an old
           English case, Isle of Wight Railway Co. v. Tahourdin [Isle
           of Wight Railway Co. v. Tahourdin, (1883) LR 25 Ch D 320
           (CA)] . A number of shareholders required the Directors
           to call a meeting of the company for two objects. One
           of the objects was mentioned as ‘To remove, if deemed
           necessary or expedient any of the present Directors, and
           to elect Directors to fill any vacancy on the Board’. The
           Directors issued a notice to convene a meeting for the
           other object and held the meeting. Then the shareholders,
           under the Companies Clauses Act, 1845, issued a notice
           of their own convening a meeting for both the objects in
           the original requisition. In an action by the Directors to
954                                                        [2024] 1 S.C.R.

                    Digital Supreme Court Reports


         restrain the requisitionists, from holding the meeting, the
         Court of Appeal held that a notice to remove “any of the
         present Directors” would justify a resolution for removing all
         who are Directors at the present time. “Any”, Lord Cotton,
         L.J. pointed out, would involve “all”.
         33. It is true that the language there was “any of the present
         Directors” and not “any one of the present Directors” and
         it is urged that the word “one”, in the latter phrase makes
         all the difference. We think it will be wrong to put too much
         emphasis on the word “one” here. It may be pointed out in
         this connection that the Permanent Edition of Words and
         Phrases, mentions an American case Front & Huntingdon
         Building & Loan Assn. v. Berzinski [Front & Huntingdon
         Building & Loan Assn. v. Berzinski, 130 Pa Super 297 :
         196 A 572 (Superior Court of Pennsylvania 1938)] where
         the words “any of them” were held to be the equivalent
         of “any one of them”.
         34. After giving the matter full and anxious consideration,
         we have come to the conclusion that the words “any one
         of the Directors” is ambiguous; in some contexts, it means
         “only one of the Directors, does not matter which one”, but
         in other contexts, it is capable of meaning “every one of
         the Directors”. Which of these two meanings was intended
         by the legislature in any particular statutory phrase has to
         be decided by the courts on a consideration of the context
         in which the words appear, and in particular, the scheme
         and object of the legislation.”
                                                 (emphasis supplied)
       117. The Constitution Bench in Lala Karam Chand Thapar case
       [Chief Inspector of Mines v. Lala Karam Chand Thapar, (1962)
       1 SCR 9 : AIR 1961 SC 838] found that the words “any one”
       have been commonly used to mean “every one” i.e. not one,
       but all. It found that the word “any”, in affirmative sentences,
       asserts, concerning a being or thing of the sort named, without
       limitation. It held that it is abundantly clear that the words “any
       one” are not infrequently used to mean “every one”.
[2024] 1 S.C.R.                                                            955

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

        118. It could be seen that the Constitution Bench in Lala Karam
        Chand Thapar case [Chief Inspector of Mines v. Lala Karam
        Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838], after giving
        the matter full and anxious consideration, came to the conclusion
        that the words “any one of the Directors” was an ambiguous
        one. It held that in some contexts, it means “only one of the
        Directors, does not matter which one”, but in other contexts, it
        is capable of meaning “every one of the Directors”. It held that
        which of these two meanings was intended by the legislature in
        any particular statutory phrase has to be decided by the courts
        on consideration of the context in which the words appear, and
        in particular, the scheme and object of the legislation.
        119. After examining the scheme of the Mines Act, 1952, the
        Constitution Bench of this Court further observed thus : (Lala
        Karam Chand Thapar case [Chief Inspector of Mines v. Lala
        Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838],
        AIR pp. 848-49, paras 36-38)
           “36. But, argues Mr Pathak, one must not forget the
           special rule of interpretation for “penal statute” that if the
           language is ambiguous, the interpretation in favour of
           the accused should ordinarily be adopted. If you interpret
           “any one” in the sense suggested by him, the legislation
           he suggests is void and so the accused escapes. One
           of the two possible constructions, thus being in favour of
           the accused, should therefore be adopted. In our opinion,
           there is no substance in this contention. The rule of strict
           interpretation of penal statutes in favour of the accused
           is not of universal application, and must be considered
           along with other well-established rules of interpretation.
           We have already seen that the scheme and object of the
           statute makes it reasonable to think that the legislature
           intended to subject all the Directors of a company owning
           coal mines to prosecution and penalties, and not one only
           of the Directors. In the face of these considerations there
           is no scope here of the application of the rule for strict
           interpretation of penal statutes in favour of the accused.
           37. The High Court appears to have been greatly
           impressed by the fact that in other statutes where the
956                                                         [2024] 1 S.C.R.

                    Digital Supreme Court Reports


         legislature wanted to make every one out of a group or a
         class of persons liable it used clear language expressing
         the intention; and that the phrase “any one” has not
         been used in any other statute in this country to express
         “every one”. It will be unreasonable, in our opinion, to
         attach too much weight to this circumstance; and as for
         the reasons mentioned above, we think the phrase “any
         one of the Directors” is capable of meaning “every one
         of the Directors”, the fact that in other statutes, different
         words were used to express a similar meaning is not of
         any significance.
         38. We have, on all these considerations come to the
         conclusion that the words “any one of the Directors”
         has been used in Section 76 to mean “every one of the
         Directors”, and that the contrary interpretation given by
         the High Court is not correct.”
                                                 (emphasis supplied)
       120. It could thus be seen that though it was sought to be
       argued before the Court that since the rule of strict interpretation
       of penal statutes in favour of the accused has to be adopted
       and that the word “any” was suffixed by the word “one”, it
       has to be given restricted meaning; the Court in Lala Karam
       Chand Thapar case [Chief Inspector of Mines v. Lala Karam
       Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838] came to
       the conclusion that the words “any one of the Directors” used
       in Section 76 of the Mines Act, 1952 would mean “every one
       of the Directors”. It is further to be noted that the word “any”
       in the said case was suffixed by the word “one”, still the Court
       held that the words “any one” would mean “all” and not “one”.
       It is to be noted that in the present case, the legislature has
       not employed the word “one” after the word “any”. It is settled
       law that it has to be construed that every single word employed
       or not employed by the legislature has a purpose behind it.
       121. On the very date on which the judgment in Chief Inspector
       of Mines v. Lala Karam Chand Thapar [Chief Inspector of Mines v.
       Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838]
       was pronounced, the same Constitution Bench also pronounced
       the judgment in Banwarilal Agarwalla [Banwarilal Agarwalla v.
[2024] 1 S.C.R.                                                           957

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

        State of Bihar, (1962) 1 SCR 33 : AIR 1961 SC 849], wherein
        the Constitution Bench observed thus : (Banwarilal Agarwalla
        case [Banwarilal Agarwalla v. State of Bihar, (1962) 1 SCR 33
        : AIR 1961 SC 849], AIR p. 850, para 3)
           “3. The first contention is based on an assumption that
           the word “any one” in Section 76 means only “one of
           the Directors, and only one of the shareholders”. This
           question as regards the interpretation of the word “any
           one” in Section 76 was raised in Criminal Appeals Nos. 98
           to 106 of 1959 (Chief Inspector of Mines [Chief Inspector
           of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9
           : AIR 1961 SC 838], etc.) and it has been decided there
           that the word “any one” should be interpreted there as
           “every one”. Thus under Section 76 every one of the
           shareholders of a private company owning the mine, and
           every one of the Directors of a public company owning
           the mine is liable to prosecution. No question of violation
           of Article 14 therefore arises.”
                                                  (emphasis supplied)
        122. Another Constitution Bench of this Court in Tej Kiran Jain
        [Tej Kiran Jain v. N. Sanjiva Reddy, (1970) 2 SCC 272] was
        considering the provisions of Article 105 of the Constitution of
        India and, particularly, the immunity as available to the Member
        of Parliament “in respect of anything said … in Parliament”.
        The Constitution Bench observed thus : (SCC p. 274, para 8)
           “8. In our judgment it is not possible to read the provisions
           of the article in the way suggested. The article means what
           it says in language which could not be plainer. The article
           confers immunity inter alia in respect of “anything said …
           in Parliament”. The word “anything” is of the widest import
           and is equivalent to “everything”. The only limitation arises
           from the words “in Parliament” which means during the
           sitting of Parliament and in the course of the business of
           Parliament. We are concerned only with speeches in Lok
           Sabha. Once it was proved that Parliament was sitting and
           its business was being transacted, anything said during the
           course of that business was immune from proceedings in
           any Court this immunity is not only complete but is as it
           should be. It is of the essence of parliamentary system of
958                                                      [2024] 1 S.C.R.

                   Digital Supreme Court Reports


         Government that people’s representatives should be free
         to express themselves without fear of legal consequences.
         What they say is only subject to the discipline of the rules
         of Parliament, the good sense of the members and the
         control of proceedings by the Speaker. The Courts have
         no say in the matter and should really have none.”
                                               (emphasis supplied)
       123. This Court held in Tej Kiran Jain case [Tej Kiran Jain v.
       N. Sanjiva Reddy, (1970) 2 SCC 272] that the word “anything”
       is of the widest import and is equivalent to “everything”. The
       only limitation arises from the words “in Parliament” which
       means during the sitting of Parliament and in the course of the
       business of Parliament. It held that, once it was proved that
       Parliament was sitting and its business was being transacted,
       anything said during the course of that business was immune
       from proceedings in any court.
       124. This Court, in LDA [LDA v. M.K. Gupta, (1994) 1 SCC 243],
       was considering clause (o) of Section 2(1) of the Consumer
       Protection Act, 1986 which defines “service”, wherein the word
       “any” again fell for consideration. This Court observed thus :
       (SCC p. 255, para 4)
         “4. … The words “any” and “potential” are significant.
         Both are of wide amplitude. The word “any” dictionarily
         means “one or some or all”. In Black’s Law Dictionary it
         is explained thus, ‘word “any” has a diversity of meaning
         and may be employed to indicate “all” or “every” as well
         as “some” or “one” and its meaning in a given statute
         depends upon the context and the subject-matter of the
         statute’. The use of the word “any” in the context it has
         been used in clause (o) indicates that it has been used
         in wider sense extending from one to all.”
       125. This Court held in LDA case [LDA v. M.K. Gupta, (1994)
       1 SCC 243] that the word “any” is of wide amplitude. It means
       “one or some or all”. Referring to Black’s Law Dictionary, the
       Court observed that the word “any” has a diversity of meaning
       and may be employed to indicate “all” or “every” as well as
       “some” or “one”. However, the meaning which is to be given
       to it would depend upon the context and the subject-matter of
[2024] 1 S.C.R.                                                             959

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

        the statute.
        126. In K.P. Mohammed Salim [K.P. Mohammed Salim v. CIT,
        (2008) 11 SCC 573], this Court was considering the power of
        the Director General or Chief Commissioner or Commissioner
        to transfer any case from one or more assessing officers
        subordinate to him to any other assessing officer or assessing
        officers. This Court observed thus : (SCC p. 578, para 17)
           “17. The word “any” must be read in the context of the
           statute and for the said purpose, it may in a situation of this
           nature, means all. The principles of purposive construction
           for the said purpose may be resorted to. (See New India
           Assurance Co. Ltd. v. Nusli Neville Wadia [New India
           Assurance Co. Ltd. v. Nusli Neville Wadia, (2008) 3 SCC
           279 : (2008) 1 SCC (Civ) 850] .) Thus, in the context of a
           statute, the word “any” may be read as all in the context
           of the Income Tax Act for which the power of transfer
           has been conferred upon the authorities specified under
           Section 127.”
                                                   (emphasis supplied)
        127. The Court in K.P. Mohammed Salim [K.P. Mohammed
        Salim v. CIT, (2008) 11 SCC 573] again reiterated that the
        word “any” must be read in the context of the statute. The
        Court also applied the principles of purposive construction to
        the term “any” to mean “all”.
        128. In Raj Kumar Shivhare [Raj Kumar Shivhare v. Directorate
        of Enforcement, (2010) 4 SCC 772 : (2010) 3 SCC (Civ) 712],
        an argument was sought to be advanced that since Section 35
        of the Foreign Exchange Management Act, 1999 uses the words
        “any decision or order”, only appeals from final order could be
        filed. Rejecting the said contention, this Court observed thus :
        (SCC pp. 779-80, paras 19-20 & 26)
           “19. The word “any” in this context would mean “all”. We
           are of this opinion in view of the fact that this section
           confers a right of appeal on any person aggrieved. A right
           of appeal, it is well settled, is a creature of statute. It is
960                                                          [2024] 1 S.C.R.

                    Digital Supreme Court Reports


         never an inherent right, like that of filing a suit. A right of
         filing a suit, unless it is barred by statute, as it is barred
         here under Section 34 of FEMA, is an inherent right (see
         Section 9 of the Civil Procedure Code) but a right of appeal
         is always conferred by a statute. While conferring such
         right a statute may impose restrictions, like limitation or
         pre-deposit of penalty or it may limit the area of appeal to
         questions of law or sometime to substantial questions of
         law. Whenever such limitations are imposed, they are to be
         strictly followed. But in a case where there is no limitation on
         the nature of order or decision to be appealed against, as
         in this case, the right of appeal cannot be further curtailed
         by this Court on the basis of an interpretative exercise.
         20. Under Section 35 of FEMA, the legislature has
         conferred a right of appeal to a person aggrieved from
         “any” “order” or “decision” of the Appellate Tribunal. Of
         course such appeal will have to be on a question of law.
         In this context the word “any” would mean “all”.
         ***
         26. In the instant case also when a right is conferred on a
         person aggrieved to file appeal from “any” order or decision
         of the Tribunal, there is no reason, in the absence of a
         contrary statutory intent, to give it a restricted meaning.
         Therefore, in our judgment in Section 35 of FEMA, any
         “order” or “decision” of the Appellate Tribunal would mean
         all decisions or orders of the Appellate Tribunal and all such
         decisions or orders are, subject to limitation, appealable
         to the High Court on a question of law.”
                                                  (emphasis supplied)
       129. While holding that the word “any” in the context would mean
       “all”, this Court in Raj Kumar Shivhare [Raj Kumar Shivhare v.
       Directorate of Enforcement, (2010) 4 SCC 772 : (2010) 3 SCC
       (Civ) 712] observed that a right of appeal is always conferred
       by a statute. It has been held that, while conferring such right,
       a statute may impose restrictions, like limitation or pre-deposit
       of penalty or it may limit the area of appeal to questions of law
[2024] 1 S.C.R.                                                        961

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

        or sometime to substantial questions of law. It has been held
        that whenever such limitations are imposed, they are to be
        strictly followed. It has been held that in a case where there
        is no limitation, the right of appeal cannot be curtailed by this
        Court on the basis of an interpretative exercise.
        130. Shri P. Chidambaram, learned Senior Counsel relied on
        the judgment of this Court in Union of India v. A.B. Shah [Union
        of India v. A.B. Shah, (1996) 8 SCC 540 : 1996 SCC (Cri) 688].
        In the said case, the High Court was considering an appeal
        preferred by the Union of India wherein it had challenged the
        acquittal of the accused by the learned trial court, which was
        confirmed in appeal by the High Court. The learned trial court
        and the High Court had held that the complaint filed was beyond
        limitation. This Court reversed the judgments of the learned trial
        court and the High Court.
        131. This Court while interpreting the expression “at any time”
        observed thus : (A.B. Shah case [Union of India v. A.B. Shah,
        (1996) 8 SCC 540 : 1996 SCC (Cri) 688], SCC p. 546, para 12)
           “12. If we look into Conditions 3 and 6 with the object
           and purpose of the Act in mind, it has to be held that
           these conditions are not only relatable to what was
           required at the commencement of depillaring process,
           but the unstowing for the required length must exist
           always. The expression “at any time” finding place in
           Condition 6 has to mean, in the context in which it has
           been used, “at any point of time”, the effect of which is
           that the required length must be maintained all the time.
           The accomplishment of object of the Act, one of which
           is safety in the mines, requires taking of such a view,
           especially in the backdrop of repeated mine disasters
           which have been taking, off and on, heavy toll of lives
           of the miners. It may be pointed out that the word “any”
           has a diversity of meaning and in Black›s Law Dictionary
           it has been stated that this word may be employed to
           indicate “all” or “every”, and its meaning will depend
           “upon the context and subject-matter of the statute”. A
           reference to what has been stated in Stroud’s Judicial
962                                                          [2024] 1 S.C.R.

                      Digital Supreme Court Reports


          Dictionary, Vol. I, is revealing inasmuch as the import of
          the word “any” has been explained from pp. 145 to 153
          of the 4th Edn., a perusal of which shows it has different
          connotations depending primarily on the subject-matter
          of the statute and the context of its use. A Bench of
          this Court in LDA v. M.K. Gupta [LDA v. M.K. Gupta,
          (1994) 1 SCC 243], gave a very wide meaning to this
          word finding place in Section 2(1)(o) of the Consumer
          Protection Act, 1986 defining “service”. (See para 4)”
                                                (emphasis supplied)
        132. Shri Chidambaram rightly argued that the word “any” will
        have to be construed in its context, taking into consideration
        the scheme and the purpose of the enactment. There can
        be no quarrel with regard to the said proposition. Right from
        the judgment of the Constitution Bench of this Court in Chief
        Inspector of Mines v. Lala Karam Chand Thapar [Chief Inspector
        of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR
        1961 SC 838], the position is clear. What is the meaning which
        the legislature intended to give to a particular statutory provision
        has to be decided by the Court on a consideration of the context
        in which the word(s) appear(s) and in particular, the scheme
        and object of the legislation.”
87. From the perusal of the various judgments, which have been referred
    to in detail by the Constitution Bench, it will be clear that the words
    “all” or “any” will have to be construed in their context taking into
    consideration the scheme and purpose of the enactment. What is
    the meaning which the legislature intended to give to a particular
    statutory provision has to be decided by the Court on a consideration
    of the context in which the word(s) appear(s) and in particular, the
    scheme and object of the legislation. We have no hesitation to hold
    that the word “all” used in clause 5.15 of the Bidding Guidelines, read
    with the legislative policy for which the Electricity Act was enacted
    and read with Section 86(1)(b) of the Electricity Act, will have to be
    construed to be the one including “any”. As such, the contention in
    that regard is to be rejected.
88. In any case, applying the principle of literal interpretation, the
    evaluation committee/BEC would be entitled to reject only such of
    the price bids if it finds that the rates quoted by the bidders are not
[2024] 1 S.C.R.                                                              963

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     aligned to the prevailing market prices. It does not stipulate rejection
     of all the bids in the bidding process. For example, if in a bidding
     process, which is in accordance with the Bidding Guidelines and is
     transparent, 5 bidders emerged. Out of the said bidders, the rates
     quoted by only 3 bidders are market aligned and the rates quoted
     by rest of the 2 bidders are not market aligned. In accordance with
     the Bidding Guidelines, the BEC would be entitled to recommend
     acceptance of the bids of the first 3 bidders and reject the bids of
     rest of the 2 bidders whose quoted rates/prices are not found to be
     market aligned. We, therefore, reject the contention in this behalf.
89. We further find that the Court, while interpreting a particular provision,
    will have to apply the principles of purposive construction. The
    Constitution Bench of this Court in the case of Vivek Narayan Sharma
    (supra) after surveying various judgments on the issue has held thus:
           “148. It is thus clear that it is a settled principle that the
           modern approach of interpretation is a pragmatic one, and
           not pedantic. An interpretation which advances the purpose
           of the Act and which ensures its smooth and harmonious
           working must be chosen and the other which leads to
           absurdity, or confusion, or friction, or contradiction and
           conflict between its various provisions, or undermines, or
           tends to defeat or destroy the basic scheme and purpose
           of the enactment must be eschewed. The primary and
           foremost task of the Court in interpreting a statute is to
           gather the intention of the legislature, actual or imputed.
           Having ascertained the intention, it is the duty of the
           Court to strive to so interpret the statute as to promote
           or advance the object and purpose of the enactment.
           For this purpose, where necessary, the Court may even
           depart from the rule that plain words should be interpreted
           according to their plain meaning. There need be no meek
           and mute submission to the plainness of the language. To
           avoid patent injustice, anomaly or absurdity or to avoid
           invalidation of a law, the court would be justified in departing
           from the so-called golden rule of construction so as to
           give effect to the object and purpose of the enactment.
           Ascertainment of legislative intent is the basic rule of
           statutory construction.”
964                                                          [2024] 1 S.C.R.

                      Digital Supreme Court Reports


90. It could thus be seen that it is a settled principle that the modern
    approach of interpretation is a pragmatic one, and not pedantic. An
    interpretation which advances the purpose of the Act and which
    ensures its smooth and harmonious working must be chosen and the
    other which leads to absurdity, or confusion, or friction, or contradiction
    and conflict between its various provisions, or undermines, or tends
    to defeat or destroy the basic scheme and purpose of the enactment
    must be eschewed.
91. If the contention that clause 5.15 of the Bidding Guidelines will come
    into play, which permits the Evaluation Committee to reject “all” price
    bids and not “any” one of them is accepted, it will lead to nothing
    else than resulting in absurdity. Suppose, if L-1 bidder quotes Rs.3
    per unit and L-5 bidder quotes Rs.7 per unit, requirement to reject
    the bid of L-1 bidder, whose bid is found market aligned along
    with that of L-5 bidder, which is not market aligned, would lead to
    an anomalous situation. Could the consumer be deprived of the
    electricity to be procured from L-1 at a market aligned price only
    because some of the bidders have quoted much higher prices and
    are not market aligned. In our view, such an interpretation would
    result in defeating one of the main objects of the enactment, i.e.,
    protection of the consumer.
92. It is needless to state that this Court, time and again, in various
    judgments including the one in the case of GMR Warora Energy
    Limited (supra) has recognised the requirement of balancing the
    consumers’ interest with that of the interest of the generators. It will
    not be permissible to take a lopsided view only to protect the interest
    of the generators ignoring the consumers’ interest and public interest.
93. We find that the High Court was not justified in entertaining the
    petition. The Constitution Bench of this Court in the case of PTC
    India Limited (supra) has held that the Electricity Act is an exhaustive
    code on all matters concerning electricity. Under the Electricity
    Act, all issues dealing with electricity have to be considered by the
    authorities constituted under the said Act. As held by the Constitution
    Bench of this Court, the State Electricity Commission and the learned
    APTEL have ample powers to adjudicate in the matters with regard
    to electricity. Not only that, these Tribunals are tribunals consisting of
    experts having vast experience in the field of electricity. As such, we
[2024] 1 S.C.R.                                                           965

                   Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                  MB Power (Madhya Pradesh) Limited & Ors.

      find that the High Court erred in directly entertaining the writ petition
      when the respondent No.1, i.e., the writ petitioner before the High
      Court had an adequate alternate remedy of approaching the State
      Electricity Commission.
94. This Court in the case of Reliance Infrastructure Limited v. State
    of Maharashtra and others11 has held that while exercising its power
    of judicial review, the Court can step in where a case of manifest
    unreasonableness or arbitrariness is made out.
95. In the present case, there is not even an allegation with regard
    to that effect. In such circumstances, recourse to a petition under
    Article 226 of the Constitution of India in the availability of efficacious
    alternate remedy under a statute, which is a complete code in itself,
    in our view, was not justified.
96. No doubt that availability of an alternate remedy is not a complete bar
    in the exercise of the power of judicial review by the High Courts. But,
    recourse to such a remedy would be permissible only if extraordinary
    and exceptional circumstances are made out. A reference in this
    respect could be made to the judgments of this Court in the cases
    of Radha Krishan Industries v. State of Himachal Pradesh and
    others12 and South Indian Bank Ltd. and others v. Naveen Mathew
    Philip and another13.
97. We may gainfully refer to the observation of this Court in the case
    of Radha Krishan Industries (supra), wherein this Court has laid
    down certain principles after referring to the earlier judgments:
          “24. The High Court has dealt with the maintainability of the
          petition under Article 226 of the Constitution. Relying on the
          decision of this Court in CCT v. Glaxo Smith Kline Consumer
          Health Care Ltd. [CCT v. Glaxo Smith Kline Consumer Health
          Care Ltd., (2020) 19 SCC 681 : 2020 SCC OnLine SC 440],
          the High Court noted that although it can entertain a petition
          under Article 226 of the Constitution, it must not do so when the


11   [2019] 1 SCR 886 : (2019) 3 SCC 352=2019 INSC 63
12   [2021] 3 SCR 406 : (2021) 6 SCC 771=2021 INSC 266
13   [2023] 4 SCR 18 : 2023 SCC OnLine SC 435 =2023 INSC 379
966                                                         [2024] 1 S.C.R.

                     Digital Supreme Court Reports


       aggrieved person has an effective alternate remedy available
       in law. However, certain exceptions to this “rule of alternate
       remedy” include where, the statutory authority has not acted in
       accordance with the provisions of the law or acted in defiance
       of the fundamental principles of judicial procedure; or has
       resorted to invoke provisions, which are repealed; or where an
       order has been passed in violation of the principles of natural
       justice. Applying this formulation, the High Court noted that the
       appellant has an alternate remedy available under the GST Act
       and thus, the petition was not maintainable.
       25. In this background, it becomes necessary for this Court, to
       dwell on the “rule of alternate remedy” and its judicial exposition.
       In Whirlpool Corpn. v. Registrar of Trade Marks [Whirlpool
       Corpn. v. Registrar of Trade Marks, (1998) 8 SCC 1], a two-
       Judge Bench of this Court after reviewing the case law on this
       point, noted : (SCC pp. 9-10, paras 14-15)
         “14. The power to issue prerogative writs under Article 226
         of the Constitution is plenary in nature and is not limited
         by any other provision of the Constitution. This power can
         be exercised by the High Court not only for issuing writs
         in the nature of habeas corpus, mandamus, prohibition,
         quo warranto and certiorari for the enforcement of any
         of the Fundamental Rights contained in Part III of the
         Constitution but also for “any other purpose”.
         15. Under Article 226 of the Constitution, the High Court,
         having regard to the facts of the case, has a discretion
         to entertain or not to entertain a writ petition. But the
         High Court has imposed upon itself certain restrictions
         one of which is that if an effective and efficacious
         remedy is available, the High Court would not normally
         exercise its jurisdiction. But the alternative remedy has
         been consistently held by this Court not to operate as
         a bar in at least three contingencies, namely, where the
         writ petition has been filed for the enforcement of any
         of the Fundamental Rights or where there has been a
         violation of the principle of natural justice or where the
         order or proceedings are wholly without jurisdiction or
[2024] 1 S.C.R.                                                              967

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

           the vires of an Act is challenged. There is a plethora
           of case-law on this point but to cut down this circle of
           forensic whirlpool, we would rely on some old decisions
           of the evolutionary era of the constitutional law as they
           still hold the field.”
                                                    (emphasis supplied)
        26. Following the dictum of this Court in Whirlpool [Whirlpool
        Corpn. v. Registrar of Trade Marks, (1998) 8 SCC 1], in
        Harbanslal Sahnia v. Indian Oil Corpn. Ltd. [Harbanslal Sahnia
        v. Indian Oil Corpn. Ltd., (2003) 2 SCC 107], this Court noted
        that : (Harbanslal Sahnia case [Harbanslal Sahnia v. Indian Oil
        Corpn. Ltd., (2003) 2 SCC 107], SCC p. 110, para 7)
           “7. So far as the view taken by the High Court that the remedy
           by way of recourse to arbitration clause was available to
           the appellants and therefore the writ petition filed by the
           appellants was liable to be dismissed is concerned, suffice
           it to observe that the rule of exclusion of writ jurisdiction by
           availability of an alternative remedy is a rule of discretion
           and not one of compulsion. In an appropriate case, in
           spite of availability of the alternative remedy, the High
           Court may still exercise its writ jurisdiction in at least three
           contingencies : (i) where the writ petition seeks enforcement
           of any of the fundamental rights; (ii) where there is failure
           of principles of natural justice; or (iii) where the orders or
           proceedings are wholly without jurisdiction or the vires of
           an Act is challenged. (See Whirlpool Corpn. v. Registrar of
           Trade Marks [Whirlpool Corpn. v. Registrar of Trade Marks,
           (1998) 8 SCC 1] .) The present case attracts applicability
           of the first two contingencies. Moreover, as noted, the
           appellants’ dealership, which is their bread and butter,
           came to be terminated for an irrelevant and non-existent
           cause. In such circumstances, we feel that the appellants
           should have been allowed relief by the High Court itself
           instead of driving them to the need of initiating arbitration
           proceedings.”
                                                    (emphasis supplied)
968                                                         [2024] 1 S.C.R.

                     Digital Supreme Court Reports


       27. The principles of law which emerge are that:
       27.1. The power under Article 226 of the Constitution to
       issue writs can be exercised not only for the enforcement of
       fundamental rights, but for any other purpose as well.
       27.2. The High Court has the discretion not to entertain a writ
       petition. One of the restrictions placed on the power of the High
       Court is where an effective alternate remedy is available to the
       aggrieved person.
       27.3. Exceptions to the rule of alternate remedy arise where
       : (a) the writ petition has been filed for the enforcement of a
       fundamental right protected by Part III of the Constitution; (b)
       there has been a violation of the principles of natural justice;
       (c) the order or proceedings are wholly without jurisdiction; or
       (d) the vires of a legislation is challenged.
       27.4. An alternate remedy by itself does not divest the High
       Court of its powers under Article 226 of the Constitution in an
       appropriate case though ordinarily, a writ petition should not be
       entertained when an efficacious alternate remedy is provided
       by law.
       27.5. When a right is created by a statute, which itself prescribes
       the remedy or procedure for enforcing the right or liability, resort
       must be had to that particular statutory remedy before invoking
       the discretionary remedy under Article 226 of the Constitution.
       This rule of exhaustion of statutory remedies is a rule of policy,
       convenience and discretion.
       27.6. In cases where there are disputed questions of fact, the
       High Court may decide to decline jurisdiction in a writ petition.
       However, if the High Court is objectively of the view that the
       nature of the controversy requires the exercise of its writ
       jurisdiction, such a view would not readily be interfered with.
       28. These principles have been consistently upheld by this
       Court in Chand Ratan v. Durga Prasad [Chand Ratan v. Durga
       Prasad, (2003) 5 SCC 399], Babubhai Muljibhai Patel v. Nandlal
       Khodidas Barot [Babubhai Muljibhai Patel v. Nandlal Khodidas
       Barot, (1974) 2 SCC 706] and Rajasthan SEB v. Union of India
       [Rajasthan SEB v. Union of India, (2008) 5 SCC 632] among
       other decisions.”
[2024] 1 S.C.R.                                                            969

                   Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
                  MB Power (Madhya Pradesh) Limited & Ors.

98. This Court has clearly held that when a right is created by a statute,
    which itself prescribes the remedy or procedure for enforcing the
    right or liability, resort must be had to that particular statutory remedy
    before invoking the discretionary remedy under Article 226 of the
    Constitution of India.
99. Recently, this Court in the case of M/s South Indian Bank Ltd. &
    Ors. (supra) has also taken a similar view.
100. There is another ground on which the High Court ought to have refused
     to entertain the petition. The bid of L-7 bidder was returned and the
     Bid Bond bank guarantee was also directed not to be extended vide
     the communication dated 6th January 2015. The judgment and order
     passed by this Court, on which reliance is placed by respondent No.1,
     is also delivered on 25th April 2018. However, the respondent No.1
     did not take any steps from 6th January 2015 and in any case, from
     25th April 2018 till 14th December 2020, on which date the petition
     came to be filed before the High Court. No doubt that the petition
     need not be dismissed solely on the ground of delay and laches.
     However, if petitioner approaches the Court with delay, he has to
     satisfy the Court about the justification for delay in approaching the
     Court belatedly. In our considered view, the High Court ought not to
     have entertained the petition also on the ground of delay and laches.
101. In any case, we find that the High Court was not justified in issuing
     the mandamus in the nature which it has issued. This Court in the
     case of Air India Ltd. v. Cochin International Airport Ltd. and
     others14 has observed thus:
             “7. The law relating to award of a contract by the State,
             its corporations and bodies acting as instrumentalities
             and agencies of the Government has been settled by
             the decision of this Court in Ramana Dayaram Shetty v.
             International Airport Authority of India [(1979) 3 SCC 489],
             Fertilizer Corpn. Kamgar Union (Regd.) v. Union of India
             [(1981) 1 SCC 568], CCE v. Dunlop India Ltd. [(1985) 1
             SCC 260 : 1985 SCC (Tax) 75], Tata Cellular v. Union of
             India [(1994) 6 SCC 651], Ramniklal N. Bhutta v. State of
             Maharashtra [(1997) 1 SCC 134] and Raunaq International


14   [2000] 1 SCR 505 : (2000) 2 SCC 617=2000 INSC 39
970                                                         [2024] 1 S.C.R.

                     Digital Supreme Court Reports


          Ltd. v. I.V.R. Construction Ltd. [(1999) 1 SCC 492] The award
          of a contract, whether it is by a private party or by a public
          body or the State, is essentially a commercial transaction.
          In arriving at a commercial decision considerations which
          are paramount are commercial considerations. The State
          can choose its own method to arrive at a decision. It can
          fix its own terms of invitation to tender and that is not open
          to judicial scrutiny. It can enter into negotiations before
          finally deciding to accept one of the offers made to it.
          Price need not always be the sole criterion for awarding
          a contract. It is free to grant any relaxation, for bona fide
          reasons, if the tender conditions permit such a relaxation.
          It may not accept the offer even though it happens to be
          the highest or the lowest. But the State, its corporations,
          instrumentalities and agencies are bound to adhere to the
          norms, standards and procedures laid down by them and
          cannot depart from them arbitrarily. Though that decision is
          not amenable to judicial review, the court can examine the
          decision-making process and interfere if it is found vitiated
          by mala fides, unreasonableness and arbitrariness. The
          State, its corporations, instrumentalities and agencies have
          the public duty to be fair to all concerned. Even when some
          defect is found in the decision-making process the court
          must exercise its discretionary power under Article 226 with
          great caution and should exercise it only in furtherance
          of public interest and not merely on the making out of a
          legal point. The court should always keep the larger public
          interest in mind in order to decide whether its intervention
          is called for or not. Only when it comes to a conclusion
          that overwhelming public interest requires interference,
          the court should intervene.”
102. It could thus be seen that this Court has held that the award of
     a contract, whether it is by a private party or by a public body or
     the State, is essentially a commercial transaction. In arriving at
     a commercial decision, considerations which are paramount are
     commercial considerations. It has been held that the State can
     choose its own method to arrive at a decision. It can fix its own
     terms of invitation to tender and that is not open to judicial scrutiny.
     It has further been held that the State can enter into negotiations
[2024] 1 S.C.R.                                                          971

               Jaipur Vidyut Vitran Nigam Ltd. & Ors. v.
              MB Power (Madhya Pradesh) Limited & Ors.

     before finally deciding to accept one of the offers made to it. It has
     further been held that, price need not always be the sole criterion for
     awarding a contract. It has been held that the State may not accept
     the offer even though it happens to be the highest or the lowest.
     However, the State, its corporations, instrumentalities and agencies
     are bound to adhere to the norms, standards and procedures laid
     down by them and cannot depart from them arbitrarily. Though that
     decision is not amenable to judicial review, the court can examine
     the decision-making process and interfere if it is found vitiated by
     mala fides, unreasonableness and arbitrariness. It has further been
     held that even when some defect has been found in the decision-
     making process, the court must exercise its discretionary power
     under Article 226 with great caution and should exercise it only in
     furtherance of public interest and not merely on the making out of a
     legal point. The court should always keep the larger public interest
     in mind in order to decide whether its intervention is called for or
     not. Only when it comes to a conclusion that overwhelming public
     interest requires interference, the court should intervene.
103. As has been held by this Court in the case of Tata Cellular (supra),
     the Court is not only concerned with the merits of the decision but
     also with the decision-making process. Unless the Court finds that
     the decision-making process is vitiated by arbitrariness, mala fides,
     irrationality, it will not be permissible for the Court to interfere with
     the same.
104. In the present case, the decision-making process, as adopted by the
     BEC was totally in conformity with the principles laid down by this
     Court from time to time. The BEC after considering the competitive
     rates offered in the bidding process in various States came to a
     conclusion that the rates quoted by SKS Power (L-5 bidder) were
     not market aligned. The said decision has been approved by the
     State Commission. Since the decision-making process adopted by
     the BEC, which has been approved by the State Commission, was
     in accordance with the law laid down by this Court, the same ought
     not to have been interfered with by the learned APTEL.
105. In any case, the High Court, by the impugned judgment and order,
     could not have issued a mandamus to the instrumentalities of the
     State to enter into a contract, which was totally harmful to the public
972                                                        [2024] 1 S.C.R.

                       Digital Supreme Court Reports


       interest. Inasmuch as, if the power/electricity is to be procured by
       the procurers at the rates quoted by the respondent No.1-MB Power,
       which is even higher than the rates quoted by the SKS Power (L-5
       bidder), then the State would have been required to bear financial
       burden in thousands of crore rupees, which would have, in turn,
       passed on to the consumers. As such, we are of the considered
       view that the mandamus issued by the Court is issued by failing
       to take into consideration the larger consumers’ interest and the
       consequential public interest. We are, therefore, of the view that
       the impugned judgment and order passed by the High Court is not
       sustainable in law and deserves to be quashed and set aside.

       CIVIL APPEAL NO. 6503 OF 2022 AND CIVIL APPEAL NO. 6502
       OF 2022
106. The appeals are, therefore, allowed. The impugned judgment and
     order of the Division Bench of the High Court of Judicature for
     Rajasthan, Bench at Jaipur dated 20th September 2021 in D.B.
     Civil Writ Petition No. 14815 of 2020 is quashed and set aside. The
     respondent No.1-M.B. Power (Madhya Pradesh) Limited is directed
     to pay costs, quantified at Rs.5,00,000/- (Rupees Five Lakh) in each
     case to the appellants.
107. Pending applications, if any, shall stand disposed of.

       CIVIL APPEAL NO. 4612 OF 2023
108. Since we have already set aside the judgment and order of the
     High Court dated 20th September 2021 in D.B. Civil Writ Petition
     No.14815 of 2020 and the order impugned in the present appeal
     is based on the said order of the High Court dated 20th September
     2021, the present appeal is also allowed. The judgment and order
     of the learned APTEL dated 1st June 2023 is quashed and set aside.
109. Since we have saddled the costs in Civil Appeal Nos. 6503 of 2022
     and 6502 of 2022, there shall be no order as to costs in the present
     appeal.
110. Pending applications, if any, shall stand disposed of.


       Headnotes prepared by: Divya Pandey               Result of the case:
                                                           Appeals allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Electricity"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

JAIPUR VIDYUT VITRAN NIGAM LTD. & ORS. versus MB POWER (MADHYA PRADESH) LIMITED & ORS. — 2024 INSC 23 - Legal Desk AI