Created byFuzzy Cloud

Supreme Court of India

JINOFER KAWASJI BHUJWALAversusTHE STATE OF GUJARAT

Citation
2020 INSC 441
Decided
19 June 2020
Disposal
Appeal(s) allowed

Holding

The appellant is entitled to bail; the alleged threat to national security is not substantiated, and the expired six‑month period without trial commencement warrants his release on bail.

Summary

The appellant, a director of Aatash Norcontrol Limited (ANL), was arrested in connection with alleged financial irregularities in a Build‑Own‑Operate‑Transfer project for a Vessel Traffic and Port Management System (VTPMS) in the Gulf of Khambhat. While the dispute over capital costs was referred to arbitration, the Gujarat Maritime Board lodged a FIR against eight persons, including the appellant, under several IPC sections and the Prevention of Corruption Act. The appellant’s bail applications were repeatedly rejected, but the Gujarat High Court allowed a fresh application if the trial did not commence within six months—a period that subsequently expired without trial. The State argued that the case involved national security, warranting denial of bail. The Supreme Court held that the national‑security claim could not be sustained because the project had been operational since 2010 and the dispute arose only in 2018 over financial matters, and because the arbitral tribunal’s interim measures stayed any termination of the concession, allowing the project to continue under police supervision. Consequently, the Court granted bail to the appellant, subject to conditions, and allowed the appeal.

Issues considered

  • Whether the appellant is entitled to bail despite serious charges and the State's claim of national security concerns.
  • Whether the lapse of the six‑month period for trial commencement justifies granting bail.
  • Whether the interim measures ordered by the arbitral tribunal affect the bail considerations.
  • Whether national‑security considerations can override the presumption of bail in this case.

Legislation cited

Subjects

bailnational securityarbitrationinterim measuresconcession agreementVTPMSPrevention of Corruption ActIPCstay of terminationsenior citizentrial delay

Judgment

                        [2020] 5 S.C.R. 383                              383


                 JINOFER KAWASJI BHUJWALA                                A
                                  v.
                    THE STATE OF GUJARAT
                 (Criminal Appeal No. 460 of 2020)
                           JUNE 19, 2020                                 B
            [ASHOK BHUSHAN, M.R. SHAH AND
               V. RAMASUBRAMANIAN, JJ.]
       Bail – A Company ‘ANL’ was issued a Letter of Intent for
Construction and development of Vessels Traffic and Port
                                                                         C
Management System (VTPMS) in the Gulf of Khambhat, on Build
Own Operate and Transfer basis – It was followed by a Concession
Agreement, entered into between the Gujarat Maritime Board, ANL
and the Government of Gujarat – Dispute arose regarding the
Capital Cost incurred by ANL – On basis of a preliminary inspection
report, the Gujarat Maritime Board claimed that ANL made an extra        D
income of Rs. 134.38 crores – ANL moved the Commercial Court
u/s.9 of the Arbitration and Conciliation Act, 1996 as there was
threat of termination of the Concession Agreement and thereafter
matter was referred to Arbitration – The Gujarat Maritime Board
lodged a complaint and on basis of the said complaint FIR was
                                                                         E
registered against 8 accused, including A-1, A-2 and A-3 u/ss. 406,
409, 420, 465, 468, 471 and 120 B IPC and s. 13(1)(d) of the
Prevention of Corruption Act – A-1(Appellant) and A-2 his son were
arrested – Ever since then, the appellant is in judicial custody – His
bail application was rejected several times – However, the High
Court gave liberty to the appellant to file a fresh application before   F
the trial Court if the trial could not commence within a period of six
months – Incidentally, this period of six months has expired and
trial has not commenced yet – Also, the Arbitral Tribunal passed
interim measures and financial interests of the Maritime Board were
protected – In the background of the above facts, the appellant
                                                                         G
sought bail – Per contra, the respondent-State contended that the
matter involved national security, which stands threatened by the
activities of the appellant – Held: The potential threat to national
security, cannot be sustained, for two reasons – The first reason is
that the project became operational in August 2010 and the disputes
                                                                         H
                                 383
384            SUPREME COURT REPORTS                      [2020] 5 S.C.R.


A     started between the parties in 2018 that too with regard to financial
      matters – The second reason, by virtue of interim measures of
      protection granted by the Arbitral Tribunal u/s. 17, the termination
      of Concession Agreement stands stayed – Therefore, the Company
      of which the appellant is the head, continues to operate the VTPMS
      Project – The Arbitral Tribunal has also permitted the State Police
B
      to be there at the Project and allowed Maritime Board to depute a
      competent person, familiar with the project in question, to supervise
      and monitor the functioning of the Project – Also, the period of six
      months within which the High Court hoped the trial to commence,
      has expired as on date – Therefore, appellant is entitled to bail and
C     is directed to be released on bail.
            Allowing the appeal, the Court
            HELD: 1. The period of six months within which the High
      Court hoped the trial to commence, has expired as on date. The
      appellant, who is admittedly 62 years of age has already spent
D     nearly a year in judicial custody. A period of nine months has
      passed from the date of filing of the charge sheet. Though the
      Solicitor General contended that the sanction to prosecute has
      already been issued as against Government Officials, the fact
      remains that charges have not been framed and the trial has not
E     commenced as yet. [Para 20][389-F]
             2. The arguments revolving around the potential threat to
      national security, cannot be sustained, for two reasons. The first
      reason is that the project became operational in August-2010
      and the disputes between the parties started only in 2018 and
F     that too with regard to financial matters. The second reason is
      that by virtue of the interim measures of protection granted by
      the Arbitral Tribunal (comprising of a former Judge of this court,
      a former Judge of the High court and a Senior Advocate) in terms
      of section 17 of the Arbitration and Conciliation Act, 1996, the
      termination of the Concession Agreement stands stayed.
G     Therefore, the Company of which the appellant is the head,
      continues to operate the VTPMS Project. In any case, the Arbitral
      Tribunal has not merely protected the economic interests of the
      State, but also permitted the State Police to be there at the project
      site. The Tribunal has also allowed the Maritime Board to depute
H
    JINOFER KAWASJI BHUJWALA v. STATE OF GUJARAT                           385


a competent person, familiar with the project in question, to              A
supervise and monitor the functioning of the project. Therefore,
this contention cannot be accepted blind fold. [Para 21]
[389-G-H; 390-A-B]
       3. Though much is said about the tempering of witnesses,
it is seen from the material on record that the prosecution rests          B
mainly on documents. In any case, the prosecution is not
remedyless, if a person enlarged on bail, indulges in certain
activities. [Para 22][390-C]
       4. Therefore, this Court is of the view that the appellant is
entitled to bail. Hence, the appeal is allowed and the appellant is        C
directed to be released on bail, subject to such terms and
conditions as the Sessions Court may deem fit and appropriate in
the facts and circumstances of the case, including a condition for
the surrender of the passport, which shall be subject to orders
passed by the Trial Court from time to time. [Para 23][390-D]
                                                                           D
      CRIMINAL APPELLATE JURISDICTION: Criminal Appeal
No. 460 of 2020.
      From the Judgment and Order dated 09.12.2019 of the High Court
of Gujarat at Ahmedabad in CRLMA No. 19125 of 2019.
      Tushar Mehta, SG, Harish Salve, Siddhartha Dave, Mukul Rohatgi,      E
Sr. Advs., A.R. Gupta, Mohit Chaudhary, Aditya A. Gupta, Kunal
Sachdeva, Ms. Puja Sharma, Omar Ahmad, Jaspal Singh, Balwinder
Singh Suri, Anup Kumar Mishra, M/s. Kings and Alliance Llp , Aniruddha
P. Mayee, Gursharan H. Virk, Ms. Misha Rohatgi, Nakul Mohta,
Ms. Shubhangi Rathore, Advs. for the appearing parties.                    F
      The Order of the Court was passed by
      V. RAMASUBRAMANIAN. J.
      1. Leave granted.
      2. Aggrieved by the dismissal of his bail application by the High    G
Court of Gujarat at Ahmedabad, a person who is cited as A-1 in the First
Information Report in Crime No.I-I/5/2019 dated 26.06.2019 for alleged
offences under Sections 406, 409, 420, 465, 468, 471 and 120B of the


                                                                           H
386            SUPREME COURT REPORTS                          [2020] 5 S.C.R.


A     Indian Penal Code and Section 13(1)(d) of the Prevention of Corruption
      Act, 1988, has come up with the above appeal.
            3. We have heard Mr. Harish Salve and Mr. Siddhartha Dave,
      learned Senior Counsel appearing for the appellant; Mr. Tushar Mehta,
      learned Solicitor General appearing for the State of Gujarat and
B     Mr. Mukul Rohatgi, learned Senior Counsel appearing for Gujarat Maritime
      Board.
            4. Pursuant to an invitation to offer floated in November-2006
      and the assessment of the proposals received from interested parties, a
      company by name Aatash Norcontrol Limited (for short “ANL”), was
C     issued with a Letter of Intent on 26.02.2007 for the construction and
      development of Vessels Traffic and Port Management System
      (hereinafter referred to as “VTPMS”) in the Gulf of Khambhat, on
      Build Own Operate and Transfer (BOOT) basis. It was followed by a
      Concession Agreement dated 30.09.2007 entered into between the
      Gujarat Maritime Board, ANL and the Government of Gujarat.
D
             5. As per the Concession Agreement, Aatash Norcontrol Limited
      is obliged to install Key Radar Stations at 7 places in the Gulf of Cambay
      and repeater Radar Stations at 2 places, with the master control being
      set up at Dumas. The object of setting up the Radar Stations is to monitor
      the vessels entering the Gulf of Khambhat and to ensure Coastal and
E     National Security.
            6. VTPMS for the Gulf of Khambhat became operational in
      August, 2010 after a completion certificate was issued by the Gujarat
      Maritime Board. But in 2018 disputes arose regarding the capital cost
      incurred by ANL. An expert committee was appointed under Clause 18
F     of the agreement and they submitted a report indicating a particular
      amount as the capital cost.
            7. But Gujarat Maritime Board claimed, on the basis of a
      preliminary inspection report of the Principal Accountant General that
      ANL made an extra income of Rs. 134.38 crores during the financial
G     years 2015-16 and 2017-18 and that the said amount should be paid by
      ANL.
             8. ANL moved the commercial court at Ahmedabad under section
      9 of the Arbitration and Conciliation Act, 1996, as there was a threat of
      termination of the Concession Agreement. The disputes were also referred
H     to arbitration. Before the Arbitral Tribunal constituted on 01.03.2019,
    JINOFER KAWASJI BHUJWALA v. STATE OF GUJARAT                                387
              [V. RAMASUBRAMANIAN. J.]

both parties (ANL and Gujarat Maritime Board) moved applications                A
under section 17 of the Arbitration and Conciliation Act.
       9. However, on 01.05.2019, the Gujarat Maritime Board lodged a
complaint with the CID Crime, Gandhi Nagar Zone, alleging that ANL
was guilty of (1) inflation of cost (2) non execution of certain works (3)
creation of shell companies and carrying out work through them (4)              B
siphoning and round tripping of funds through those companies (5) not
carrying out construction on the lands allotted for Master Control Room
(6) raising of false bills and forged invoices (7) managing the issue of
completion certificate through the then Superintending Engineer and Chief
Nautical Officer of the board and (8) entering into a conspiracy with
each other to exceed the expenditure of the project upto Rs. 100 crores         C
and committing criminal breach of trust.
      10. On the basis of the above complaint, a FIR bearing no. I-I/5/
2019 was registered on 26.6.2019 against eight named accused, for
alleged offences under sections 406, 409, 420, 465, 468, 471 and 120B
of IPC and section 13(1)(d) of the Prevention of Corruption Act. The            D
appellant herein and his son and daughter were cited as A-1, A-2 and
A-3 respectively, as they happen to be the Directors of the Companies.
       11. On 27.6.2019, the appellant and his son were arrested. After
being in police custody under orders of court, the appellant was sent to
judicial custody on 2.7.2019. Ever since then, the appellant is in judicial     E
custody. His bail application was first rejected by the Sessions Court on
6.7.2019. Though the appellant moved the High Court, he withdrew the
application on 6.8.2019 with liberty to move a fresh application after the
filing of the charge sheet. But, it is relevant to note that the two officers
of the Maritime Board who were also implicated, were granted bail by            F
the High Court.
      12. A charge sheet was filed by the Investigating Officer on
21.9.2019, as against the appellant and the others. However, no charge
sheet was filed against the Officers of the Maritime Board, as orders of
sanction from the Government were awaited at that time.                         G
       13. In view of the filing of the charge sheet, the appellant moved
a bail application before the Sessions Court but the same was rejected
on 3.10.2019. Therefore, the appellant moved the High Court of Gujarat,
which, by the order impugned in the appeal, dated 09-12-2019, dismissed
the application. However, the High Court gave liberty to the appellant to
                                                                                H
388            SUPREME COURT REPORTS                           [2020] 5 S.C.R.


A     file a fresh application before the Trial Court if the trial could not
      commence within a period of six months. Incidentally, this period of six
      months has now expired and the trial has not commenced as yet.
             14. Before proceeding further, it is to be noted that on 7.8.2019,
      the Arbitral Tribunal passed orders on the applications under section 17
B     of the Arbitration Act (1) granting a stay of the termination notice (2)
      directing ANL to deposit the entire amount generated out of the VTPMS
      project in an escrow account and to file a monthly report regarding the
      details of deposits so made (3) permitting ANL to withdraw 25% of the
      gross amount so deposited, to meet the overheads and to run the project
      (4) permitting the State Police Personnel deputed at the project site to
C     continue without any interference with the day to day functioning of the
      project except overseeing safety aspects (5) permitting the Maritime
      Board to depute a competent person to supervise and monitor the
      functioning of the project (6) directing ANL not to encumber or dispose
      of the plant and machinery and other valuable items and (7) directing
D     ANL to pay Rs. 16,43,44,227/- to the Maritime Board payable for the
      month of July, 2019.
            15. As a result of the aforesaid interim measures ordered by the
      Arbitral Tribunal, ANL continues to operate the project under the
      Concession Agreement and the financial interests of the Maritime Board
E     stand protected by those directions.
             16. In the background of the above facts, it is contended by the
      learned Senior Counsel appearing for the appellant (1) that a cloak of
      criminality has been given to a dispute of purely civil nature (2) that the
      economic interests of the Board stand protected by the interim measures
F     granted by the Arbitral Tribunal (3) that the appellant is a senior citizen
      having medical complications and (4) that since the charge sheet has
      been filed and the trial has not commenced, the continued incarceration
      of the appellant is unjustified.
              17. The prayer for bail is opposed by the State and the Maritime
G     Board, on the ground inter alia (1) that the very object of the Concession
      Agreement was to establish Radar Stations to monitor and identify
      infiltration by non-State vessels involved in anti-national activities (2)
      that what is on hand is not just a civil dispute but a huge financial scam
      (3) that the appellant is the brain behind such a scam involving round
      tripping of funds through a maze of shell companies (4) that the matter
H
    JINOFER KAWASJI BHUJWALA v. STATE OF GUJARAT                             389
              [V. RAMASUBRAMANIAN. J.]

involves national security, which now stands threatened by the activities    A
of the appellant and the companies managed by him (5) that the appellant
has already started influencing the witnesses, by sending gifts to the
senior officers of the Maritime Board (6) that under his pressure, two
Chartered Accountants who had earlier given statements, retracted (7)
that even before the report of the Forensic Sciences Laboratory could
                                                                             B
reach the Investigating Officer, the appellant exhibited knowledge of its
contents, thereby showing his influence and power (8) that one of the
co accused is absconding and (9) that since many witnesses for the
prosecution are either the former or present employees of the appellant
or retired Government Officials, they are vulnerable and hence the
appellant’s request for bail should be rejected.                             C
      18. We have carefully considered the pleadings, the documents,
the written notes of submissions and the issues involved.
      19. At the outset, we should point out that the impugned order of
the High Court is dated 9.12.2019. The operative portion of the order of
the High Court is extracted as follows:                                      D

      “In view of the aforesaid discussion, I am not inclined to
      exercise the discretion in favour of the present applicant.
      Application is, therefore, dismissed. However, liberty is
      reserved to the applicant to file fresh application before the
      concerned trial Court if the trial is not commenced within a           E
      period of six months”.
        20. Obviously, the period of six months within which the High
Court hoped the trial to commence, has expired as on date. The appellant,
who is admittedly 62 years of age has already spent nearly a year in
judicial custody. A period of nine months has passed from the date of        F
filing of the charge sheet. Though the learned Solicitor General contended
that the sanction to prosecute has already been issued as against
Government Officials, the fact remains that charges have not been framed
and the trial has not commenced as yet.
       21. The arguments revolving around the potential threat to national   G
security, cannot be sustained, for two reasons. The first reason is that
the project became operational in August-2010 and the disputes between
the parties started only in 2018 and that too with regard to financial
matters. The second reason is that by virtue of the interim measures of
protection granted by the Arbitral Tribunal (comprising of a former Judge
                                                                             H
390                SUPREME COURT REPORTS                         [2020] 5 S.C.R.


A     of this court, a former Judge of the High court and a Senior Advocate) in
      terms of section 17 of the Arbitration and Conciliation Act, 1996, the
      termination of the Concession Agreement stands stayed. Therefore, the
      Company of which the appellant is the head, continues to operate the
      VTPMS Project. In any case, the Arbitral Tribunal has not merely
      protected the economic interests of the State, but also permitted the
B
      State Police to be there at the project site. The Tribunal has also allowed
      the Maritime Board to depute a competent person, familiar with the
      project in question, to supervise and monitor the functioning of the project.
      Therefore, we cannot accept this contention blind fold.
            22. Though much is said about the tempering of witnesses, it is
C     seen from the material on record that the prosecution rests mainly on
      documents. In any case, the prosecution is not remedyless, if a person
      enlarged on bail, indulges in certain activities.
             23. Therefore, we are of the view that the appellant is entitled to
      bail. Hence, the appeal is allowed and the appellant is directed to be
D     released on bail, subject to such terms and conditions as the Sessions
      Court may deem fit and appropriate in the facts and circumstances of
      the case, including a condition for the surrender of the passport, which
      shall be subject to orders passed by the Trial Court from time to time.

E
      Ankit Gyan                                                     Appeal allowed.




F




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "bail"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.