Created byFuzzy Cloud

Supreme Court of India

M.D., M/S. RAMAKRISHNA POULTRY P. LTD.versusR. CHELLAPPAN & ORS.

Citation
2009 INSC 753
Decided
8 May 2009
Disposal
Appeal(s) allowed

Holding

The Court held that the transmission line must be raised to provide a clearance of at least 40 ft (56 m) and that the appellant is entitled to compensation under Section 10(d) of the Telegraph Act, 1885.

Summary

M/s. Ramakrishna Poultry Ltd., a poultry farmer, purchased land and erected sheds while the Power Grid Corporation was surveying a 400 kV transmission line that would pass over the sheds. The company claimed that the high‑voltage lines would harm its birds and sought a realignment or increased tower height. The Madras High Court directed the matter to the District Magistrate, who ordered a deviation, which was set aside by the High Court. On appeal, the Supreme Court balanced the appellant’s grievance against the technical and public‑interest considerations, noting that the poultry farm was established after the line’s route was already being surveyed and that a deviation over a third party’s land was not feasible. The Court directed the corporation to raise the clearance of the line to 56 m (40 ft) and held that the appellant is entitled to compensation under Section 10(d) of the Telegraph Act, 1885.

Issues considered

  • Whether the District Magistrate/Collector can order deviation or alteration of a transmission line under Section 16 or Section 17 of the Telegraph Act, 1885.
  • Whether the appellant is entitled to compensation under Section 10(d) of the Telegraph Act for use of its land.
  • Whether technical feasibility and public interest justify raising tower height instead of realigning the line.
  • Whether the appellant had knowledge of the transmission line project and thus cannot claim exclusive rights over the land.
  • Whether the increased clearance of 40 ft satisfies the requirement of equity between individual grievance and public interest.

Legislation cited

Subjects

Telegraph ActCompensationTransmission linePoultry farmPublic interestClearanceDeviationHigh voltageElectromagnetic fieldLand acquisition

Judgment

                                [2009] 8 S.C.R. 1055

    ,;              M.D., M/S. RAMAKRISHNA POULTRY P. LTD.                  A·

-                                          v.
                              R. CHELLAPPAN & ORS.
                           (Civil Appe<1I No. ?,41 ~ gf 2009)
                                     MAY 8, 2009
                                                                            B
                  [ALTAMAS KABIR AND CYRIAC JOSPEH, JJ.]
         ~

                  Telegraph Act, 1885:

                    ss. 16, 17 and 10 (d) - Erection of transmission towers c
              and laying the High voltage transmission lines - High Voltage
             wires passing over poultry sheds - Likely to affect
             performance and health of layer birds - Held: Purchase of
             /,:ind and starting poultry business were effected when survey
             fOr route of transmission line was being undertaken - In view D
             of stand of Power Grid Corporation that deviation in
             transmissipn linfJ§ could not be practically achieved,
             Corporation would r[Jise the height of the lowest point of sag
             of transmission lines between two towers on either sides of the
             poultry shed from 46. 5 meters to 56 meters raising the
                                                                             E
             clearance to 40' between the lowest point of sag and the
             highest point of poultry shed - Company would be entitled to
             oompensation on account of erection of tower for carrying
             transmission lines over poultry farm in accordance with
             provisions of s. 10 (d) of the Act- Equity- Balance between
             grievance of individual and public interest.                    F

                 The appellant company which was engaged in
             poultry farming, purchased land and constructed poultry
             sheds thereon, at about the same time when respondent
             No. 3, the Power Grid Corporation of India Ltd., started       G
.. ,-        survey in the area for erecting transmission towers for
             carrying High Voltage electricity current transmission
             wires at various locations. The appellant company
             apprehending that High voltage transmission wires over
                                         1055                               H
    1056      SUPREME COURT REPORTS [2009] 8 S.C.R

A the poultry sheds would adversely affect the performance
  and health of layer birds, filed a writ petition before the
  High Court seeking a realignment of the transmission
  lines so that either the poultry sheds could be avoided
                                                                    -
  or the height of the tower could be raised. The High Court
B directed the petitioner company to file objection before
  the District Magistrate, who directed the Corporation to
  realign the transmission power line. Since the proposed
  realignment was to pass over a portion of the land of         +
  respondent No. 1, he filed a writ petition challenging the
c order of the District Magistrate. The Division Bench of the
  High Court set aside the order of the District Magistrate.
  Aggrieved, the company carrying on poultry farming filed
  the appeal.

       Allowing the appeal in part, the Court
D
      HELD: 1.1. On consideration of the rival submissions
  made on behalf of the respective parties, a balance will
  have to be achieved between the appellant's grievance
  and both the technical as well as techno ecological
E feasibility of altering the route of the transmission lines
  in keeping with the directions given by the District
  Collector. [Para 26) [1067-A-B]
                                                                .
       1.2. The purchases of the land by the appellant-
  company for starting the poultry business and the
F erection of the poultry sheds were effected at a point of
  time when the process of identifying the route of the
  transmission lines was already in progress and survey
  work was being unclertaken. It cannot be said that the
  appellant-company did not have knowledge of the
G ongoing project, which is for the benefit of a large
  number of people of the area as against the interest of a     •   ..
  single individual. [Para 27] [1067-G-H; 1068-A]

      1.3. In view of the objections on behalf of the Power
H Grid Corporation that the deviation in the transmission
             IVl.D., M/S. RAMAKRISHNA POULTRY P. LTD. v. R. 1057
                            CHELLAPPAN & ORS.

           lines, as suggested on behalf of the appellant-company,        A
_,,
    •      ce>uld not be practically achieved, the next best solution
           that can be resorted to is to increase the clearance
           b1?tween the lowest point of the sag of the transmission
           cable and the top most portion of the appellant's poultry
           sheds. From the point of the sag on both sides the cable       B
           moves upwards and the clearance becomes even greater
           on both sides of the lowest spot. [Para 27] [1068-A-C]
       ~

                1.4. The Power Grid Corporation had already
           accepted the alternate suggestion made on behalf of the
           appellant-company and raised the height of the lowest
                                                                          c
           point of sag of the transmission lines between the two
           towers on either side of the poultry sheds of the
 ·-·       appellant-company from 46.5 metres, to 52 metres, which
           in practical terms means a clearance of 30 ft. between the
           l1>west point of the sag and the highest point of the          D
           poultry shed. In the Circumstances, the Corporation is
           directed to further increase the clearance from 52 meters
           to 56 meters so that the clearance between the lowest
           point of the sag of the cable and the top most portion of
           tlhe poultry shed is not less than ·40 ft. The Order of the    E
           Division Bench of the High Court is set aside. [Para 26
           and 28] [1067-D-E; 1068-D-F]

                2. The appellant-company will be entitled to
           compensation in accordance with the provision of s.10(d)       F
           of the Telegraph Act, 1885, for use of its lands or the
           damage caused thereto on account of the erection of the
           tower/pylon for carrying the transmission lines over the
           poultry farm. [Para 29] [1068-F-G]
                CIVIL APPELLATE JURISDICTION : Civil Appeal No.           G

- •        :~413 of 2009 .

               From the Judgment & Order dated 29.08.2008 of the High
           Court of Madras, Madurai Bench in W.A. (MD) No. 522 of 2008.
                                                                          H
    1058        SUPREME COURT REPORTS [2009] 8 S.C.R.


A       S. Ganesh, Prasarith P., V. Vasudevan and K.V. Bharathi              ).

    Upadhyaya for the Appellants.
                                                                                  "'
     Parag Tripathi, A.T.M. Ranga Ramanujam, V. Prabhakar,
  Ramjee Prasad, Revathy Raghavan, Nitih Thukral,
  Yashodharan Anand, Kuna! Bahri (for Parekh & Co.) R.
B
  Nedumaran and P. Soma Sundaram for the Respondents.
         The Judgment of the Court was delivered by                     .,

c
         ALTAMAS KABIR, J. 1. Leave granted.
       2. The appellant is a Private Limited Company engaged
                                                                                   -
  in the business of poultry farming which is confined to tpe
  production of eggs. It has constructed three separate sheds on                  -~
  Survey Nos.242/2 and 249/3 in Nanniyur Pudur Village in Karur
  District in the State of Tamil Nadu for accommodating about
D 1.25 lakh layer birds. It is the case of the appellant that it had
  invested a sum of about Rs.6 crores in acquiring the lands,
  erecting the sheds thereupon and acquiring the birds for the
  purpose of starting the poultry farm.

E        3. At this juncture, it may be noted that the lands on which
    the poultry farm was started by the appellant, had been acquired
    in two stages. About 11 acres of land were acquired by the
    appellant- Company on 23rd June, 2004 and about 4 acres
    were acquired on 19th November, 2004.
F      5. At about the same time, the 3rd respondent, The Power
  Grid Corporation of India Ltd. (hereinafter referred to as 'the
  Corporation') took up the work of construction of a 400 KV
  Perambalur - Pugalur DIC Line as part of the Neyveli Thermal
  Station Expansion Project for evacuation of electricity
G generated therein. In the process, transmission towers were
  required to be installed in various locations, some of which were
  private lands, including the Patta lands of the appellant, where
                                                                        ~
                                                                                  --
  its poultry farm is situated.
        6. On 8th October, 2006, the appellant sought an opinion
H
                       M.D., M/S. RAMAKRISHNA POULTRY P. LTD. v. R. 1059
                         CHELLAPPAN & ORS. [ALTAMAS KABIR; J.]

          A
                     from the Assistant Director, Department of Animal Husbandry,           A

-                    regarding the effect on the layer birds on account of emission
                     of electro magnetic fields from the High Voltage Transmission
                     Lines passing over the poultry sheds. According to the said
!
                     authority, the passing of High Voltage Electricity Current
                     ltansmission Wires over the poultry sheds would adversely              B
                     affect the performance and health of the birds in the long run.


-   ':.
          'f              7. The appellant thereupon filed Writ Petition No.6850/06
                     before the High Court, seeking a re- alignment of the
                     transmission lines so that either the appellant's poultry sheds
                     could be avoided or the height of the tower/pylon could be             c
                     raised. Relying on an earlier order dated 18th January, 2007,

-         ...
                     passed by a learned Single Judge of the Madras High court in
                     Writ Petition No.49172/06, the learned Single Judge of the
                     Madras High Court by his judgment and order dated 31st
                     January, 2007, disposed of the said Writ· Petition, along with         D
                     other connected writ petitions, with liberty to the writ petitioners
                     to submit their objections, if any, to the District Magistrate
                     concerned, within a period of two weeks from the date of the
                     order. The District Magistrate was directed to consider the
                     same in the light of the order passed by the Court and pass            E
                     an order on merits and in accordance with law, after affording
                     an opportunity to the petitioners, as well as the respondents,
              ~
                     to make out their respective cases, within a period of six weeks
                     thereafter.
='\                                                                                         F
                            8. Pursuant to the aforesaid order, the District Magistrate
                     issued notice to the appellant and the Corporation to file
                     objections, if any. The appellant filed its objections indicating
                     the damage that would be caused to the poultry farm, if the
                     transmission line was not shifted to avoid the poultry sheds. The
                     appellant asked for a small deviation of the route of the power        G
                'i   linei in the eastward direction, within his lands, so that minimum
                     damage was effected to the poultry farm. On the other hand,
                     the Corporation submitted that no deviation of the transmission
                     linei from the approved route of alignment was feasible. After a
                                                                                            H
                  M.D., M/S. RAMAKRISHNA POULTRY P. LTD. v. R. 1061
                    CHELLAPPAN & ORS. [ALTAMAS KABIR, J.)

        ;. .    e11gaged in the business of supplying electricity under the Act,      A
                any of the powers which the Telegraph Authority possesses
                under the Telegraph Act with respect to the placing of telephonic
               lines or posts for the purpose of a telephone established or
               maintained by the Government or to be so established or
               maintained. On behalf of the appellant it was submitted that the       B
               Division Bench was wrong in holding that under Section 16 of
               the Telegraph Act, the District Magistrate had no power to
               change the alignment and that the Division Bench had failed
               t() notice that the order of the District Magistrate was not under
               Section 16, but under Section 17(3) of the said Act.                   c
                    12. Another ground of challenge was that the impugned
               c1rder of the Division Bench was contrary to the earlier order
               elated 31st January, 2007, directing the Corporation to
               approach the District Magistrate concerned in each case for
        .      permission to deal with the objections raised by the petitioners       D
    •          with the further direction that the said District Magistrate would
               consider the objections and pass orders in accordance with the
               provisions which have been indicated in the said order. It was
               i~lso urged that since the same had become final between the
               parties, there was no scope for a contrary order to be passed,         E
               1!iS has been done in terms of the impugned order of the
               Division Bench in Writ Appeal No.522/08, holding that under
               Section 16 of the Te•egraph Act the District Collector was not
               empowered to change the alignment.
                                                                                      F
                     13. The last ground of challenge was that the Division
               Bench had lost sight of the fact that the Corporation had, in fact,
               accepted the order passed by the District Magistrate and has
               even acted thereupon, as it had stated in its Counter Affidavit
               filed in response to the writ petition filed by R. Chellappan.
                                                                                      G
        '            14. Mr. S. Ganesh, learned Senior counsel appearing for
               the appellant, submitted that Sections 10 and 17 of the
               Telegraph Act have to be read pragmatically to meet a situation
               where the transmission line had already been erected and even
.   '          if the alternative prayer made by the appellant in its writ petition   H
    1062       SUPREME COURT REPORTS (2009] 8 S.C.R.


A was to be granted, the same would not lessen the danger of
  the Electromagnetic Waves created by the high power
  transmission lines damaging the health of the birds in the poultry
  farm and adversely affecting their egg-laying capacity. Mr.
  Ganesh urged that such a prayer had been made without the
B assistance of the opinion of an expert, who has subsequently
  indicated in no uncertain terms that even if the height of the
  transmission lines was raised to double the height to which it        ¥
  had been raised, it would still adversely affect the egg-laying
  capacity of the birds.
c      15. Mr. Ganesh vehemently submitted that the application
  of the appellant being under Section 17 of the ·Telegraph Act,
  it was within the power and jurisdiction of the District Magistrate
  to direct a small deviation of the transmission line over the
  appellant's own lands, the expenses wherefor would be borne
D by the appellant, so as to avoid its passing directly over the        ~



  poultry sheds. Mr. Ganesh also submitted that since the
  Corporation was ready and willing to make a deviation over the
  adjoining land belonging to Respondent No.1, except for the
  alleged damage as may be caused to the coconut trees and
E the temple on its revised route, there was no reason why the
  same could not be adopted in order to save the huge
  investment which the appellant had already made in the poultry
  farm, the loss whereof would completely cripple the appellant's
  business, particularly, when the poultry farm was already in
F operation  before the evacuation project from the Neyveli dam
  had even been contemplated or started.
       16. Learned counsel appearing for the Respondent No.1
  supported the order of the District Collector but contended that
  since the interest of the public at large relating to supply of
G electricity was involved, it was necessary for the dispute to be
  set at rest so that the transmission line could be commissioned       •
  at the earliest opportunity.
       17. On behalf of the Corporation, Mr. Parag Tripathi,
H learned Additional Solicitor General contended that the order
            M.D., MIS. RAMAKRISHNA POULTRY P. LTD. v. R. 1063
              CHl::LLAPPAN & ORS. [ALTAMAS KABIR, J.J

 I.       of the District Magistrate directing change in alignment of the      A
          transmission line did not take into consideration various factors,
          namely, that the transmission line which would pass over the
          contiguous plot belonged to the Respondent No.1 and
          bordered the plot of the appellant.
                                                                            B
                 18. Mr. Tripathi submitted that the electricity to be
           generated by the Neyveli Thermal-II Expansion in the State of
      "    Tamil Nadu has to be distributed by the construction of a 400
           KV DIC transmission line from Neyveli to Pugalur comprising
           of 57€1 towers with a length of 198 kms. connecting the Neyveli
           Thermal Power Station II to Pugalur 400 KV Sub-station. The         c
           estimated cost of the project was set at Rs.691.83 crores. He
           also submitted that on 24th December, 2003, the Government
           of India had, in exercise of its powers conferred under Section
           164 of the Electricity Act of 2003, passed an order authorizing
...        the Corporation to exercise all the powers vested in the D
           Telegraph Authority under Part Ill of the Indian Telegraph Act,
           1885 in respect of the electrical lines and electrical plants
           established or maintained, or to be so established or
           maintained for transmission of electricity or for the purpose of
           telephonic or telegraphic communication necessary for the E
          proper coordination of work. Further more, Mis. Shyama Power
          (India) Private Ltd. had already been issued the Works Order
.         for dEitailed survey on 9th June, 2004 and such work had been
          completed in the year 2004 itself. He submitted that the local
          public was taken into confidence during the consultation F
          programmes organized by the Corporation on 2nd October,
          2004 and only thereafter, on completion of the survey works,
          the route alignment was marked along with vital landmarks,
          including the crossing of the Cauveri river and the locations on
          which the towers were to be erected. Mr. Tripathi contended G
          that despite having knowledge that the area was marked for
~
          an overhead transmission line over Survey Nos.24911 to 2491
          11 and 242 of Nanniyur Village, the petitioner went on to
          purchase the lands on which the poultry farm was established
          on 23rd June, 2004 and 19th November, 2004. The learned H
    1064       SUPREME COURT REPORTS [2009] 8 S.C.R.


A Additional Solicitor General also submitted that the work of the
  project had advanced to a stage where out of the total number
  of 576 locations, the foundation work for erection of towers had
  been completed in respect of 568 locations and towers had
  already been erected at 553 locations. Furthermore, out of the
B length of 198 kms., the stringing work of the transmission lines
  had been completed upto 171 kms. and, although, the
  transmission line should have been commissioned on or
  before the month of October, 2007, the same had been delayed
  due to the present litigation. The learned Additional Solicitor
C General also submitted that the representation made by the
  appellant- Company had been disposed of by the Corporation
  on 7th May, 2005 on the ground that at the time of the survey
  work, there was no poultry farm in existence and that it was not
  techno-economically feasible to realign the transmission line at
  the advanced stage of implementation. Mr. Tripathi urged that
0
  the fact that the Managing Director of the appellant-Company
   was a local man would also be evident from the fact that the
   Certificate of Incorporation of the appellant-Company indicates
   the plots in question to be the address of the Company and it
   is difficult to accept that the Managing Director of the Company
E did not have any knowledge of the ongoing project, which
   included large scale survey work for finalizing the alignment and
   the route to be taken, including the construction of towers/        +
   pylons for carrying the transmission lines.
F       19. It was also submitted that the alternate prayer made
  on behalf of the appellant-Company had been duly considered
  and acted upon and the height of the transmission towers in
  question had been raised from 46.5 meters to 52 meters so
  that the gap between the highest point of the construction and
G the lowest point of the sag in the transmission line was 30 ft.
  The same having been done, the appellant should not have any
  further cause for complaint.
       20. Mr. Tripathi submitted that while passing the order,
  purporting to be an order under Section 17 of the Telegraph
H Act, the District Magistrate had failed to take into consideration
          M.D., MIS. RAMAKRISHNA POULTRY P. LTD. v. R. 1065
            CHELLAPPAN & ORS. [ALTAMAS KABIR, J.]

        that an order under Section 17 could only be passed after the         A
        erection of the towers and that too for altering the alignment
        within the same land. Further more, the alternate plea of raising
        the height of the towers, as also the technical feasibility
        regarding the crossing of the transmission lines at the Highway
        crossing and also the river Cauveri, together with the higher         B
        cost provision for realignment and the ecological aspect had
        not been taken into consideration by the District Collector, who
        passEid the order on 30th April, 2007 in a purely mechanical
        manner without giving any thought to the various consequences
        that such order was bound to give rise to.                            c
             21. Mr. Tripathi referred to the Full Bench decision of the
        Kerala High Court in Mammoo Vs. State of Kera/a & Anr. tAIR
        1980 Kern!a 18], where it was held that while Section 16(1) of
        the 1elegraph Act vested the District Magistrate with certain
•       authority which he would be entitled to exercise in his discretion,   D
        such functions were only of an administrative or executive
        nature. In effect, it was held that the District Magistrate, while
        exercising power under Section 16(1) of the above Act, did not
        act as a Court, but in a purely administrative capacity.
                                                                              E
        :22. Reference was also made to the decision of the Kerala
  High Court in Moidu alias Kunnippa Vs. The District
• Magistrate and District Collector, Ma/appuram and Ors.
  [MANU/KE/0410/1998], in support of the submission that in
  order to attract Section 17 of the aforesaid Act, the telegraph             F
  line or post in question would have had to be installed and
  would have had to be shifted from one portion to another portion
  of th19 same property.

             23. Mr. Tripathi submitted that having regard to the prayers
        made by the appellant in its Writ Petition (MD) No.6850/06            G
    l   before the Madurai Bench of the Madras High Court, the
        alternate prayer for raising the height of the tower has been
        acted upon by the Corporation and the appellant could not,
        themfore, have any further grievance against the Corporation
        with regard to the carriage of the transmission lines over the        H
     1066       SUPREME COURT REPORTS [2009] 8 S.C.R.


A appellant's property.

        24. Appearing for R. Chellappan, the Respondent No.1,
  Mr. A.T.M. Ranga Ramanujam, learned Senior counsel
  adopted Mr. Tipathi's submissions and submitted that if the
  order of the District Collector was accepted as having been
B
  passed under Section 17 of the Indian Telegraph Act, then any
  realignment of the transmission line would have to be effected
  within the plot of the person at whose instance such realignment         •
  is sought. The proposed alternate alignment through the land
  of the Respondent No.1 was not, therefore, permissible and
c such proposed alternate alignment was liable to be rejected.
         25. On the other hand, Mr. R. Nedumaran, learned counsel
   appearing for the State of Tamil Nadu, while supporting the
   order passed by the District Collector, urged that the erection
D of the towers for carrying the transmission lines was for the            i'

   benefit of the public at large who stood to benefit from the
   energising of the target area for the improvement of the lot of
   the people of the area. Mr. Nedumaran, however, also pointed
   out that from the order of the District Magistrate and Collector
E dated 30th April, 2007, it would be more or less evident that
   the poultry sheds had been constructed before the proposed
   route alignment. From the order of the District Collector, Mr.
   Nedumaran also pointed out that while the appellant had no          •
  objection to the power transmission line being taken over its
  lands, the District Collector had taken into consideration the
F
  limited request made on behalf of the Appellant-Company that
  the route of the power line be diverted in the eastward direction
  within the limits of its lands instead of passing through the
  middle of the said lands which would cause extensive damage
  to its poultry farm. Mr. Nedumaran submitted that the Collector,
G
  by invoking his powers under Section 17(3) of the Indian
  Telegraph Act, 1885, directed the Appellant-Company to realign      .-
  the transmission lines in such a way that they did not pass
  directly above the poultry sheds of the Respondent No.1
  situated at S.F. Nos.242/2 and 249/3, Nanniyur Village, Karur
H Taluk.
           M.D., M/S. RAMAKRISHNA POULTRY P. LTD. v. R. 1067
             CHELLAPPAN & ORS. [ALTAMAS KABIR, J.]

                26. On consideration of the rival submissions made on            A
          lbehalf of the respective parties, it is obvious that a balance will
          have to be achieved between the appellant's grievance and
          both the technical as well as techno ecological feasibility of
          altering the route of the transmission lines in keeping with the
          directions given by the District Collector. The simplest and the       B
          most ideal solution would have been to alter the route of the
         transmission lines so that they did not directly pass over the
~   •     appellant's poultry sheds, particularly when the appellant is
         ready and willing to bear the expenses of such alteration.
         However, since, according to the Power Grid Corporation and             c
         its experts, that would entail a deviation over the lands of the
         Respondent No.1, R. Chellappan, the same gave rise to the
         objections raised by R. Chellappan. Keeping aside the technical
         aspect of the matter as to whether the order passed by the
         District Collector was one under Sections 16 or 17 of the Indian
    •                                                                            D
         Telegraph Act, 1885, in order to arrive at a practical solution
         to the problem, the Power Grid Corporation accepted the
         alternate suggestion made on behalf of the Appellant-Company
         and raised the height of the lowest point of sag of the
         transmission lines between the two towers on either side of the
         poultry sheds of the Appellant-company from 46.5 meters To              E
         52 meters, which in practical terms means a clearance of 30
    ,;
         ft. between the lowest point of the sag and the highest point of
         the poultry shed. Of course, it has been contended by Mr.
         Ganesh that according to the report of the expert, even if the
         height of the tower was raised to a 100 meters, the electro-            F
         magnetic field created by the transmission of high voltage
         electricity would still encompass the poultry sheds and
         adversely affect the reproductive system not only of the chickens
         but of all living things within that zone.
                                                                                 G
              27. However, what goes against the case of the Appellant-
         Company is the fact that the purchases of the land for starting
         the poultry business and the erection of the poultry sheds were
         effected at a point of time when the process of identifying the
         route of the transmission lines was already in progress and             H
    1068        SUPREME COURT REPORTS (2009] 8 S.C.R.


A suNey work was being undertaken. We find it difficult to accept
                                                                               1
  that the Appellant- company did not have knowledge of the
  ongoing project. which is for the benefit of a large number of
  people of the area as against the interest of a single individual.
  In view of the objections on behalf of the Power Grid
B Corporation that the deviation in the transmission lines, as
  suggested on behalf of the Appellant-company, could not be
  practically achieved, we are left with the next best solution, i.e ..
  to increase the clearance between the lowest point of the sag
  of the transmission cable and the top most portion of the
c appellant's poultry sheds. It should not also be forgotten that from
  the point of the sag on both sides the cable moves upwards
  and the clearance becomes even greater on both sides of the
  lowest spot. During the hearing we had asked Mr. Tripathi to
  confirm with the Engineers of the Power Grid Corporation to
  explore the possibility of raising the height of the towers even
0
  further to lessen the damage, if any, that may be caused to the
  egg laying capacity of the layers in the appellant's poultry farm.
       28. Although, the response appears to be equivocal, we
  set aside the order of the Division Bench of the Madras High
E Court impugned in this appeal and direct the Power Grid
  Corporation to increase the clearance indicated above from 52
  meters to 56 meters so that the clearance between the lowest
  point of the sag of the cable and the top most portion of the           >-
  poultry shed is not less than 40 ft.
F
       29. The Appellant-Company will be entitled to such
  compensation to which it may be entitled for use of its lands or
  the damage caused thereto on account of the erection of the
  tower/pylon for carrying the transmission lines over the
  appellant's plant, in accordance with the provisions of Section
G 10(d) of the Indian Telegraph Act, 1885.

        30. The appeal is accordingly allowed to the extent
   indicated hereinabove.

H R.P.                                              Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Telegraph Act"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.