M/S ABCI INFRASTRUCTURES PVT. LTD.versusUNION OF INDIA AND OTHERS
- Citation
- 2025 INSC 215
- Decided
- 13 February 2025
- Disposal
- Appeal(s) allowed
- Bench
- SANJIV KHANNA
Holding
The Court held that the mistake was a patent error not covered by Section 20, so BRO was justified in forfeiting the guarantee, but equity required the appellant to pay Rs 1 crore and the guarantee be returned.
Summary
M/s ABCI Infrastructures Pvt. Ltd. submitted a financial bid of Rs 1,569 crores for a tunnel project but due to a typographical error the bid appeared as Rs 1,569 only. The appellant discovered the mistake on 24‑08‑2023, promptly informed BRO and sought to withdraw or rectify the bid, but BRO demanded justification, declared the appellant a defaulter and ordered encashment of the Rs 15.04 crore bank guarantee. The High Court dismissed the appellant's writ petition and the matter reached the Supreme Court. The Court examined whether the mistake fell within Section 20 of the Contract Act, 1872 and whether equitable relief could be granted. It held that the error was a self‑evident patent mistake not covered by Section 20, and that BRO was justified in invoking the guarantee, but equity required the appellant to pay a nominal Rs 1 crore and the guarantee be returned. Consequently, the Supreme Court set aside the impugned judgment, directed the payment, and allowed the appeal.
Issues considered
- Whether BRO was justified in accepting the erroneous bid of Rs 1,569 and forfeiting the bank guarantee of Rs 15.04 crore.
- Whether the appellant is entitled to relief under Section 20 of the Contract Act, 1872 for a mistake of fact in the bid.
Legislation cited
- Contract Act, 1872s. 20
Subjects
Judgment
[2025] 3 S.C.R. 128 : 2025 INSC 215
M/s ABCI Infrastructures Pvt. Ltd.
v.
Union of India and Others
(Civil Appeal No. 2546 of 2025)
14 February 2025
[Sanjiv Khanna,* CJI, Sanjay Kumar and
K.V. Viswanathan, JJ.]
Issue for Consideration
Whether BRO-Border Road Organisation was justified in accepting
the bid of Rs.1,569/-, and on the failure of the appellant-L1 bidder
to execute the agreement asking for forfeiture vide encashment
of bank guarantee of Rs.15,04,64,000/-.
Headnotes†
Contract Act, 1872 – s.20 – Mistake of fact – Tender dispute –
Forfeiture of bank guarantee/bid security on default –
Respondent no.2- Border Road Organisation invited bids
for the construction of tunnels and appellant ranked as L-1
bidder – When financial bids opened, the appellants discovered
their mistake that instead of appellant’s bid price of Rs.1569
Crores, the quoted amount appeared to be just Rs.1569/- –
Next day, the appellant informed the authorities regarding
the mistake but respondent no.2 called upon the appellant
to justify the quoted amount of Rs.1569/- – Respondent no.2,
stating that the appellant had been declared a defaulter, and
their bid security was to be forfeited, asked the appellant’s
bank to encash the bank guarantee and remit Rs.15,04,64,000
to respondent no.2 – Writ petition by the appellant – Dismissed
by the High Court – Correctness:
Held: As per explanation to s.20, an erroneous opinion as to the
value of the thing which forms the subject matter of an agreement is
not deemed to be a mistake as a matter of fact – Instant case does
not fall under any exception to the general principle on a person
seeking relief in equity on account of mistake, for the error or mistake
in quoting a price of Rs.1,569/- is self-evident – Contract for an
* Author
[2025] 3 S.C.R. 129
M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others
estimated value of more than Rs.1,500 crores requiring construction
of roads and tunnels in a hilly terrain can never be executed for a
mere Rs.1,569/- – Appellant was at fault and had made the mistake,
of having failed to add the required zeros in the financial bid – Plea
of a system glitch cannot be accepted, as others had successfully
uploaded their bids without problem – Claim of BRO that delay was
entirely due to the appellant’s mistake is flawed, ignoring its own
lapses – Mistakes, including by authorities, to be resolved through
corrective steps – Practical approach could have avoided the delay,
which was caused by BRO’s refusal to acknowledge appellant’s
genuine error and unwarranted cancellation of the bid – Alleged
two-month delay by appellant is incorrect – Appellant promptly
acknowledged the mistake – Appellant directed to pay Rs.1 crore
to BRO, as a consequence of their error – Upon receiving this
payment, BRO to return the appellant’s original bank guarantee or
demand draft of Rs.15.04 crores – Impugned judgment set aside.
[Paras 5, 10, 13-17]
Case Law Cited
West Bengal State Electricity Board v. Patel Engineering Company
Limited and Others [2001] 1 SCR 352 : (2001) 2 SCC 451;
M/s Omsairam Steels & Alloys Pvt. Ltd. v. Director of Mines and
Geology, BBSR & Ors., 2024 INSC 520; Coimbatore District Central
Cooperative Bank v. Coimbatore District Central Cooperative Bank
Employees Association and Another [2007] 5 SCR 430 : (2007)
4 SCC 669 – referred to.
Moffett, H. and C. Co. v. Rochester, 178 U.S. 373 (1900); Hearne
v. New England Marine Ins. Co., 22 L. Ed. 395; Spina Asphalt
Paving Excavating Contractors, Inc. v. Borough of Fairview,
304 NJ Super 425 – referred to.
List of Acts
Contract Act, 1872.
List of Keywords
Tenders; Mistake of fact; Delay; Online technical and financial
bids; Bank guarantee; System error; Typographical mistake; Patent
error; Forfeiture of bid security; Bid specifications; Relief in equity;
Defaulter of bid; Cancellation of bid.
130 [2025] 3 S.C.R.
Digital Supreme Court Reports
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2546 of 2025
From the Judgment and Order dated 07.10.2023 of the High Court
of Himachal Pradesh at Shimla in CWP No. 6658 of 2023
Appearances for Parties
Mukul Rohatgi, Sr. Adv., Gaurav Khanna, Ms. Natasha Sahrawat,
Ms. Deepali Bhanot, Gautam Barnwal, Rudraksh Pandey,
Ms. Alisha Roy, Advs. for the Appellant.
Ms. Archana Pathak Dave, A.S.G., Dr. N. Visakamurthy, Yashraj
Singh Bundela, Raman Yadav, Hitarth Raja, Udit Dedhiya, Mukesh
Kumar Maroria, Sanjay Kapur, Surya Prakash, Arjun Bhatia, Ms.
Shubhra Kapur, Ms. Mahima Kapur, Advs. for the Respondents.
Judgment / Order of the Supreme Court
Judgment
Sanjiv Khanna, CJI
Leave granted.
2. This is an avoidable litigation. No doubt, there was a mistake on the
part of the Appellant – M/s ABCI Infrastructure Private Limited, albeit,
instead of taking a pragmatic approach, Respondent No. 2 - Border
Road Organisation1 under the Ministry of Defence, Union of India,
adopted an obdurate and overly legalistic stance, causing a delay
in the project’s execution.
3. We begin by briefly discussing the facts of the case:
• On 23.02.2023, BRO invited bids for the design and construction
of two-lane twin tunnels, approximately 4.1 kilometres long, at
Shinkun La Pass, including civil, electrical, and mechanical
work, with approaches connecting the Darcha-Padam Highway
to NHDL specifications in Himachal Pradesh and Ladakh.
The estimated cost of the project was Rs.15,04,64,00,000/-
1 Hereinafter, “BRO.”
[2025] 3 S.C.R. 131
M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others
(Rs. 1,504.64 crores). The project was to be completed within
48 months. The bid security amount was Rs.15,04,64,000/-
(Rs. 15.04 crores)
• Ten bidders, including the Appellant, had submitted their online
Technical and Financial Bids on 03.06.2023. The Appellant, like
others, had furnished a bank guarantee of Rs.15,04,64,000/-.
• On 05.06.2023, technical bids were opened and seven bidders,
including the Appellant, were declared technically qualified.
• On 24.08.2023, the financial bids of seven bidders, including
the Appellant, were opened and the results were declared.
• The Appellant was ranked as L-1 bidder, with the bid price of
Rs.1,569/- (Rupees One thousand five hundred and sixty-nine
only). According to the Appellant, they had quoted a bid price
of Rs.1,569 crores. However, due to what they claim was a
system error, the quoted amount appeared as just Rs.1,569.
• The Appellant claims that they discovered the mistake on
24.08.2023 when the financial bids were opened and announced,
and therefore, on the next day, 25.08.2023, they informed
the authorities that their actual bid was Rs.1,569 crores, not
Rs.1,569. They attributed the error to a typographical mistake
or a critical technical issue with the server. While we would not
accept the plea of system error, the figure quoted was clearly
unrealistic, a patent error and a mistake given the scale and
nature of the work tendered. Though the mistake was bald-
faced, what followed is incomprehensible, with BRO, insisting on
accepting the bid, in spite of letters from the Appellant wanting
to withdraw from the tender.
• BRO, guided by the Evaluation Committee, instead of accepting
the obvious, vide letter dated 26.08.2023, called upon the
Appellant to justify the quoted amount of Rs.1,569 by providing
a detailed price analysis, including the scope of work, completion
schedule, risk allocation, safety requirements, and proof of
capability to complete the project, by 31.08.2023.
• On 30.08.2023, the Appellant reiterated that their intended bid
was Rs.1,569 crores, not Rs.1,569, attributing the error to a
technical or typographical mistake.
132 [2025] 3 S.C.R.
Digital Supreme Court Reports
• On 07.09.2023, the Appellant sent another letter stating
they should not be considered the L1 bidder, and the bank
guarantee of Rs.15,04,64,000 may be returned to them without
encashment.
• On 12.09.2023, the Appellant again wrote emphasizing that the
bid was an error and that the bid security should not be forfeited.
• Vide letter 16.09.2023, BRO, unmoved, wrote to the Appellant’s
bank, the State Bank of India, stating that the Appellant had
been declared a defaulter, and their bid security was to be
forfeited. The bank was asked to encash the bank guarantee
and remit Rs.15,04,64,000 to BRO.
• The Appellant filed a writ petition before the High Court of
Himachal Pradesh at Shimla, which stands dismissed by the
impugned judgment dated 07.10.2023.
4. The short question before us is whether BRO was justified in accepting
the bid of Rs.1,569, and on the failure of the Appellant to execute the
agreement asking for forfeiture vide encashment of bank guarantee
of Rs.15,04,64,000.
5. A mistake may be unilateral or mutual, but it is always unintentional.
If it is intentional, it ceases to be a mistake. Mistakes or errors,
though avoidable, are committed inadvertently. They have varied
consequences in law. As per Section 20 of the Indian Contract Act,
18722 whereby both parties to an agreement are under a mistake as
to matter of fact essential to an agreement, the agreement is void.
The explanation to Section 20 says that an erroneous opinion as to
the value of the thing which forms the subject matter of an agreement
is not deemed to be a mistake as a matter of fact. This will not be
a case covered by Section 20 of the Contract Act. However, this is
not the first time that this question has arisen either before this Court
or Courts outside of India. In West Bengal State Electricity Board
v. Patel Engineering Company Limited and Others3, this Court
referred to paragraph 84 of American Jurisprudence (2nd Edition,
Volume 64 at page 944), which reads:
2 Hereinafter, “Contract Act.”
3 (2001) 2 SCC 451
[2025] 3 S.C.R. 133
M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others
“As a general rule, equitable relief will be granted to a
bidder for a public contract where he has made a material
mistake of fact in the bid which he submitted, and where,
upon the discovery of that mistake, he acts promptly in
informing the public authorities and requesting withdrawal
of his bid or opportunity to rectify his mistake particularly
when he does so before any formal contract is entered into.”
6. Thereafter, reference was made to two decisions of the Supreme
Court of the United States in Moffett, H. and C. Co. v. Rochester4
and Hearne v. New England Marine Ins. Co.5 wherein it is observed
that where the mistake is apparent and the party promptly informs
the other as soon as it is discovered but before entering into a
contract, equitable orders may be passed. However, the mistake
should be clear, explicit, and undisputed. Further, a mistake on one
side may be a ground for rescinding but not for reforming a contract
where the minds of the parties have not met, yet there is no contract
and hence none to be rectified. Relief may not be granted where
it is inequitable. While accepting this legal position, this Court in
West Bengal State Electricity Board (supra) has propounded the
following exceptions to the general principle on a person seeking
relief in equity on account of mistake:
“ 27. ……..
(1)Where the mistake might have been avoided by the
exercise of ordinary care and diligence on the part of the
bidder; but where the offeree of the bid has or is deemed
to have knowledge of the mistake, he cannot be permitted
to take advantage of such a mistake.
(2) Where the bidder on discovery of the mistake fails
to act promptly in informing to the authority concerned
and request for rectification, withdrawal or cancellation of
bid on the ground of clerical mistake is not made before
opening of all the bids.
(3) Where the bidder fails to follow the rules and regulations
set forth in the advertisement for bids as to the time when
4 178 U.S. 373 (1900)
5 22 L. Ed. 395
134 [2025] 3 S.C.R.
Digital Supreme Court Reports
bidders may withdraw their offer; however where the
mistake is discovered after opening of bids, the bidder
may be permitted to withdraw the bid.”
7. This judgment also refers to a decision of the Superior Court of
New Jersey in Spina Asphalt Paving Excavating Contractors,
Inc. v. Borough of Fairview.6 The said case is related to the
rectification of mistakes in the bid specifications. Relief granted in
the said case was upheld by the Superior Court with the caution
that generally an error in the statement of a price would not be
treated as immaterial and it is only when the case of error was
patent and the true intent of the bidder obvious that such an error
might be disregarded.
8. In West Bengal State Electricity Board (supra), the private party,
the bidder did not succeed for several reasons, including the factum
that the error was not obvious and self-evident. Further, the correction
of such mistakes after one and a half months after the opening of
the bids would have violated the express clauses relating to the
computation of the bid amount. Thus, waiver of the rule or conditions
in favour of the one bidder would have created unjustifiable doubts in
the minds of others impairing the rule of transparency and fairness
and providing room for manipulation for awarding contracts.
9. The decision in West Bengal State Electricity Board (supra) was
referred to and followed where a relief to the bidder was apparent
before this Court in M/s Omsairam Steels & Alloys Pvt. Ltd. v.
Director of Mines and Geology, BBSR & Ors.7 This decision
observes that while the Court must exercise a lot of restraint in
exercising the power of judicial review in contractual commercial
matters, the doctrine of proportionality nevertheless applies when
the error or mistake is writ large and equity merits the grant of
some relief. Reference was made to the decision in Coimbatore
District Central Cooperative Bank v. Coimbatore District Central
Cooperative Bank Employees Association and Another8 where
discussing the question of proportionality or punishment imposed
on the striking workmen it is observed:
6 304 NJ Super 425
7 2024 INSC 520
8 (2007) 4 SCC 669
[2025] 3 S.C.R. 135
M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others
“18. “Proportionality” is a principle where the court is
concerned with the process, method or manner in which
the decision-maker has ordered his priorities, reached
a conclusion or arrived at a decision. The very essence
of decision-making consists in the attribution of relative
importance to the factors and considerations in the case.
The doctrine of proportionality thus steps in focus true
nature of exercise—the elaboration of a rule of permissible
priorities.
19. de Smith states that “proportionality” involves
“balancing test” and “necessity test”. Whereas the former
(balancing test) permits scrutiny of excessive onerous
penalties or infringement of rights or interests and a
manifest imbalance of relevant considerations, the latter
(necessity test) requires infringement of human rights
to the least restrictive alternative. [Judicial Review of
Administrative Action (1995), pp. 601-05, para 13.085;
see also Wade & Forsyth: Administrative Law (2005),
p. 366.]
20. In Halsbury’s Laws of England (4th Edn.), Reissue,
Vol. 1(1), pp. 144-45, para 78, it is stated:
“The court will quash exercise of discretionary
powers in which there is no reasonable
relationship between the objective which is
sought to be achieved and the means used to
that end, or where punishments imposed by
administrative bodies or inferior courts are wholly
out of proportion to the relevant misconduct. The
principle of proportionality is well established in
European law, and will be applied by English
courts where European law is enforceable in the
domestic courts. The principle of proportionality
is still at a stage of development in English law;
lack of proportionality is not usually treated as
a separate ground for review in English law,
but is regarded as one indication of manifest
unreasonableness.”
136 [2025] 3 S.C.R.
Digital Supreme Court Reports
Accordingly, in the said case the Appellant was directed to make a
payment of Rs.3 crores within the stipulated period and on the said
payment the security deposit in the form of a bank guarantee of over
Rs.9 crores was directed to be refunded.
10. The present case does not fall under any exception, for the error
or mistake in quoting a price of Rs.1,569/-, does not require any
argument and cannot be debated as it is self-evident. A contract
of this nature for an estimated value of more than Rs.1,500 crores
spread over 48 months requiring construction of roads and tunnels
of the length of more than 4 kilometres in a hilly terrain can never
be executed for a mere Rs.1,569/-.
11. At the same time, we agree with BRO, that the Appellant was at
fault and had made the mistake, of having failed to add the required
zeros in the financial bid. The plea of a system glitch should not be
accepted, as others had successfully uploaded their bids without a
problem.
12. BRO justified encashing the bank guarantee by citing delays caused
by issuing a second notice inviting bids. This claim is baseless, as
BRO was aware of the Rs.1,569/- error. Instead of declaring the bid
non est due to the clear mistake, BRO asked the appellant to justify
the bid, cancelled the notice, declared the Appellant a defaulter,
invoked the bank guarantee, and issued a fresh notice inviting bids.
13. Thus, BRO’s claim that the delay was entirely due to the Appellant’s
mistake is flawed, ignoring BRO’s own lapses. Mistakes, including by
authorities, should be resolved through corrective steps. A practical
approach could have avoided the delay, which was caused by
BRO’s refusal to acknowledge the Appellant’s genuine error and the
unwarranted cancellation of the bid.
14. The alleged two-month delay by the Appellant is incorrect. The error,
submitted on 03.06.2023, became apparent only when financial bids
were opened on 24.08.2023. The Appellant promptly acknowledged
the mistake on 25.08.2023.
15. A fresh tender was issued, and financial bids opened on 09.01.2024
revealed the lowest bid of Rs.1,290 crores, lower than the earlier
Rs.1,351 crores. Thus, while delayed, the contract was awarded at
a lower cost.
[2025] 3 S.C.R. 137
M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others
16. In view of the aforesaid discussion, we direct the Appellant to pay
Rs.1 crore to BRO, as a consequence of their error. Upon receiving
this payment, BRO shall return the Appellant’s original bank guarantee
or demand draft of Rs.15.04 crores within one week.
17. The impugned judgment is set aside, and the appeal is allowed in
the aforesaid terms. There would be no order as to costs.
Result of the case: Appeal allowed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.