M/S C & C CONSTRUCTIONS LTD.versusIRCON INTERNATIONAL LTD.
- Citation
- 2025 INSC 138
- Decided
- 31 January 2025
- Disposal
- Dismissed
- Bench
- ABHAY S OKA
Holding
The appellant is estopped by its own undertaking and the contractually valid clause 49.5 bars any claim for damages, and the court's jurisdiction under Section 37 is limited to the grounds available under Section 34, so the appeal is dismissed.
Summary
The appellant, C & C Constructions Ltd., contracted with IRCON International Ltd. to construct five road over bridges, but delays attributable to the respondent led the appellant to seek extensions of time under clause 49 of the General Conditions of Contract (GCC). The appellant gave a solemn undertaking not to claim any amount beyond escalation, yet later invoked the arbitration clause to claim damages, which the arbitral tribunal rejected on the basis of clause 49.5 of the GCC. The appellant challenged the award under Section 34 and appealed the dismissal under Section 37, arguing that clause 49.5 was invalid or waived. The Supreme Court held that the appellant was estopped by its own undertakings and the contractually valid clause 49.5 barred the claim, and that the scope of interference under Section 37 is limited to the grounds of Section 34. Consequently, the Court dismissed the appeal, upholding the lower courts' decisions.
Issues considered
- The validity and enforceability of clause 49.5 of the General Conditions of Contract under the Arbitration and Conciliation Act, 1996.
- Whether the respondent waived clause 49.5 by its communications regarding extension of time and financial burden claims.
- Whether the appellant was estopped from challenging clause 49.5 after giving a solemn undertaking not to claim extra amounts.
- The scope of judicial interference in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 16, s. 34, s. 37
Headnote
Issue for Consideration Matter pertains to the order passed by the Division Bench of the High Court, dismissing an appeal u/s.37 of the Arbitration and Conciliation Act, 1996, holding that the requirement of clause 49.5 was never waived by the respondent, that clause 49.5 was a valid clause, Headnotes† Arbitration and Conciliation Act, 1996 – s.37 – Arbitration award – Scope of interference in an appeal u/s.37 – Dispute between the appellant and the respondent over construction of Road Over Bridges – Case of the appellant that delay in construction
Subjects
Judgment
[2025] 1 S.C.R. 1413 : 2025 INSC 138
M/s C & C Constructions Ltd.
v.
IRCON International Ltd.
(Civil Appeal No. 6657 of 2023)
31 January 2025
[Abhay S. Oka* and Ujjal Bhuyan, JJ.]
Issue for Consideration
Matter pertains to the order passed by the Division Bench of the
High Court, dismissing an appeal u/s.37 of the Arbitration and
Conciliation Act, 1996, holding that the requirement of clause 49.5
was never waived by the respondent, that clause 49.5 was a valid
clause, upheld the arbitral award.
Headnotes†
Arbitration and Conciliation Act, 1996 – s.37 – Arbitration
award – Scope of interference in an appeal u/s.37 – Dispute
between the appellant and the respondent over construction
of Road Over Bridges – Case of the appellant that delay
in construction work for the reasons attributable to the
respondent, resulted in additional financial burdens – Appellant
sought extension of time, and the same was extended by the
respondent – Appellant then sought damages on account
of delay on part of the respondent, however, the claims
rejected – Thereafter, undertakings by the appellant that it
would not claim anything extra other than escalation for
the work executed – Two years later, the appellant invoked
arbitration clause on basis of the claims raised – Arbitral
tribunal rejected the claims based on clause 49.5 of GCC
which disentitles the appellant from raising any claim for
damages or compensation for failure or delay caused by the
respondent in fulfilling its obligations under the contract –
Petition u/s.34 by the appellant – Dismissed by the Single
Judge of the High Court holding that the clause 49.5 would
bar the appellant’s claim – Appeal before the Division Bench
u/s.37 also dismissed – Correctness:
* Author
1414 [2025] 1 S.C.R.
Supreme Court Reports
Held: Scope of interference in an appeal u/s.37, in examining an
order, setting aside or refusing to set aside an award, is limited
and restricted – On facts, the appellant acted upon clause 49.5
and sought an extension of time on three occasions – Solemn
undertaking by the appellant not to make any claim other than
escalation in respect of delays in the completion of work, however,
claim made contrary to the undertakings – By the undertakings, the
appellant agreed not to make a claim contrary to what is provided
in clause 49.5, thus, by conduct, the appellant was estopped from
challenging the validity of clause 49.5 – Furthermore, Clause 49.4
would apply when the delay is not due to the respondent – In the said
matter, the delay was on the part of the respondent, hence, clause
49.5 would apply and not clause 49.4 – Also it cannot be inferred
that clause 49.5 was waived by the respondent – Respondent
stated that the claim for financial burden would have to be dealt with
together with the proposal for an extension of time, and the said
claim cannot be processed separately – Thus, on two occasions,
on specific requests made by the appellant under clause 49 of
the GCC, the extension of time was granted by the respondent –
Except sub-clause 5 of clause 49, no other sub-clause which
provides for grant of extension when the delay was attributable
to the respondent – Thus, the order passed by the Division
Bench upheld – General Conditions of Contract – Clause 49.5.
[Paras 19, 23, 26-29]
Case Law Cited
Larsen Air Conditioning and Refrigeration Company v. Union of
India and Ors. [2023] 11 SCR 86 : (2023) 15 SCC 472; Konkan
Railway Corporation Limited v. Chenab Bridge Project Undertaking
[2023] 11 SCR 215 : (2023) 9 SCC 85 – relied on.
Pam Developments Pvt. Ltd. v. State of West Bengal [2019] 9
SCR 252 : (2019) 8 SCC 112; ONGC v. Wig Brothers Builders
and Engineers Private Limited (2010) 13 SCC 377 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996.
List of Keywords
Arbitration award; Arbitral award; Arbitration clause; Scope of
interference in appeal u/s.37; Construction of Road Over Bridges;
Delay in construction work; Additional financial burdens; Extension
[2025] 1 S.C.R. 1415
M/s C & C Constructions Ltd. v. IRCON International Ltd.
of time; Damages; Escalation for the work executed; Claim for
damages or compensation; Solemn undertaking; Estopped from
challenging validity of clause 49.5; Delay; Financial burden; General
Conditions of Contract Clause 49.5.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6657 of 2023
From the Judgment and Order dated 01.03.2021 of the High Court
of Delhi at New Delhi in FAO (OS) (COMM) No. 36 of 2021
Appearances for Parties
Vikas Goel, Tarun Dua, Ritesh Sharma, Pragun Dua, Ms. Anisha
Dahiya, Deepal Hooda, Rahul Shyam Bhandari, Advs. for the
Appellant.
Gaurav Pachnanda, Sr. Adv., Sidhant Goel, Mohit Goel, Shubham S
Saxena, Karmanya D Sharma, Ms. Nikita Jaitly, Ms. Avni Sharma,
Sahil Tagotra, Advs. for the Respondent.
Judgment / Order of the Supreme Court
Judgment
Abhay S. Oka, J.
FACTUAL ASPECTS
1. This appeal arises out of the impugned judgment and order of the
Division Bench of the High Court of Delhi dated 1st March, 2021,
which is passed in an appeal under Section 37 of the Arbitration and
Conciliation Act, 1996 (for short, ‘the Arbitration Act’).
2. We refer to a few factual aspects of the case. An agreement dated
28th June, 2012 was entered into between the appellant and the
respondent for constructing five Road Over Bridges (for short, ‘ROBs’)
and their approaches at different locations in the State of Rajasthan.
The schedule of completion in respect of each ROB was different. The
locations where ROBs were to be constructed have been described
as LC-200, LC-89, LC-228, LC-233 and LC-108. According to the
appellant’s case, the work at the sites was delayed for the reasons
attributable to the respondent. According to the appellant’s case,
1416 [2025] 1 S.C.R.
Supreme Court Reports
the respondent withdrew the work relating to the construction of two
ROBs (LC-200 and LC-233) from the scope of work and certified
the completion of the remaining work. There is no dispute that we
are not concerned with LC-200 and LC-233 in this appeal. In the
case of LC-89 and LC-228, the scheduled completion date was 15th
September, 2013. For LC-108, it was 16th July, 2013. As per the
completion certificate dated 22nd March 2016, the work of LC-89
was completed on 8th October 2014, and the work of LC-228 was
completed on 21st March 2015. According to the appellant’s case,
work at LC-108 was completed on 31st March 2017.
3. On 19th June 2013, the appellant addressed a letter to the respondent’s
General Manager stating that the construction delay of ROBs at LC-
108 was due to various hindrances at the site. By the said letter,
the appellant requested the respondent to grant an extension of
264 days. The appellant contended that the delay in construction
work has resulted in an additional financial burden on account of the
establishment and overheads, etc., for a longer period than planned,
for which the appellant would be claiming separately. By the reply
dated 14th October 2013, the respondent informed the appellant that
the statement of the appellant that it would be claiming separately
for financial burden was not acceptable. The respondent stated
that the claim would have to be considered along with the prayer
for extension. Therefore, the respondent requested the appellant
to submit a detailed claim immediately so that the prayer for an
extension of time could be considered. Separate letters dated 30th
August, 2013 were addressed by the appellant to the respondent
regarding LC-89 and LC-228 for grant of extension by 430 and
437 days, respectively. By a letter dated 29th November, 2013, the
respondent granted an extension of time as follows:
LC No. Extension Upto Penalty
228 20th March, 2014 With Penalty
89 28th February, 2014 With Penalty
108 31st March, 2014 Without Penalty
4. On 28th February, 2014, 09th April, 2014 and 19th April, 2014, the
appellant again applied for a grant extension of time regarding LC
Nos. 89, 228 and 108, respectively. By a letter dated 24th May, 2014,
the respondent granted an extension of time as follows:
[2025] 1 S.C.R. 1417
M/s C & C Constructions Ltd. v. IRCON International Ltd.
LC No. Extension Upto Penalty
228 31st January, 2015 Without Penalty
89 30th November, 2014 Without Penalty
108 15th December, 2014 Without Penalty
5. By letters dated 03rd September, 2014, the appellant submitted
separate claims concerning the three ROBs for damages on account
of the delay on the part of the respondent. By letters dated 14th
October, 2014, the respondent rejected the claims. The appellant
applied for further extension of time by letters dated 08th January,
2015. In response, the respondent addressed a letter dated 09th
January, 2015 by which the appellant was called upon to give
undertakings to the effect that the appellant will not claim anything
extra other than escalation for the work executed. The appellant
submitted undertakings on 14th January, 2015 accordingly.
6. The appellant invoked the arbitration clause on 25th January 2017.
The appellant filed a statement making a claim for Rs. 44.11 crores
under 15 substantive heads besides the claim of interest and costs.
The respondent filed its statement of defence on 25th August, 2017.
7. The respondent filed an application under Section 16(2) of the
Arbitration Act. It was contended in the said application that clause
49.5 of the General Conditions of Contract (for short, ‘GCC’) disentitles
the appellant from raising any claim for damages or compensation for
failure or delay caused by the respondent in fulfilling its obligations
under the contract. The Arbitral Tribunal passed the order in the
respondent’s application under Section 16 of the Arbitration Act in
nature of an award dated 21st December, 2019 by which all claims
were rejected based on clause 49.5 of GCC.
8. Aggrieved by the impugned award dated 21st December 2019, the
appellant preferred a petition under Section 34 of the Arbitration
Act. The learned Single Judge of the High Court of Delhi dismissed
the petition, holding that a term like clause 49.5 of the GCC would
bar the appellant’s claim. Moreover, the appellant had accepted the
communication dated 14th October 2014, issued by the respondent
dismissing the claim. It was also held that clause 49.5 was valid
and, after the appellant accepted the same, it could not contend to
the contrary.
1418 [2025] 1 S.C.R.
Supreme Court Reports
9. Being aggrieved by the judgment of the learned Single Judge, the
appellant preferred an appeal before the Division Bench of the High
Court of Delhi by invoking Section 37 of the Arbitration Act. While
dismissing the appeal, the Division Bench held that the requirement
of clause 49.5 was never waived by the respondent. The Division
Bench held that clause 49.5 was a valid clause. After holding that
the powers of the Court while dealing with an appeal under Section
37 of the Arbitration Act are limited by Section 34, the Division Bench
dismissed the appeal.
SUBMISSIONS
10. The learned counsel appearing for the appellant has made detailed
submissions. His first submission is that the award of the Arbitral
Tribunal was contrary to public policy and suffered from patent
illegality. The learned counsel also pointed out that the main issue
was whether a clause prohibiting the payment of damages, like clause
49.5, could be enforced. He submitted that the Arbitral Tribunal and the
learned Single Judge failed to appreciate the crucial aspects striking
at the root of the award. The learned counsel pointed out various
decisions of the Delhi High Court and this Court. After relying upon
several decisions of this Court, he urged that the parties to the contract
cannot contract against the Indian Contract Act, 1872 (for short, ‘the
Contract Act’). He submitted that the finding recorded by the Arbitral
Tribunal that clause 49.5 aims to protect the interests of PSUs and
the Government is illegal. He relied upon the decision of this Court in
the case of Pam Developments Pvt. Ltd. v. State of West Bengal1.
The learned counsel submitted that the additional documents filed by
the appellant ought to be considered. Therefore, the learned counsel
appearing for the appellant submitted that the impugned judgments
deserve to be set aside.
11. Learned counsel for the respondent submitted that clause 49.5 of
GCC read with clause 12 of the Special Conditions of Contract (for
short ‘SCC’) are limitation of liability clauses. These clauses are
not in conflict with either Section 23 or Section 28 of the Contract
Act. He submitted that if clause 49.5 of GCC and clause 12 of SCC
are read together, it is apparent that in case of delay or fault on the
1 (2019) 8 SCC 112
[2025] 1 S.C.R. 1419
M/s C & C Constructions Ltd. v. IRCON International Ltd.
part of the employer (respondent), a reasonable extension of time
can be granted and payment of price variation as per the formula
agreed between the parties in the contract itself can be made.
Learned counsel submitted that this Court has consistently upheld
the enforceability of limitation of liability clauses. He relied upon what
is held in paragraph 10 of the decision of this Court in the case of
ONGC v. Wig Brothers Builders and Engineers Private Limited2.
He submitted that the appellant made an irreversible election to
accept the extension of time in terms of the agreed scheme of the
contract between the parties without payment of liquidated damages.
Therefore, the appellant is not entitled to make any additional claim
for compensation and/or damages beyond the stipulations in the
contract and contrary to the express prohibition in clause 49.5
of GCC. He pointed out the letters addressed by the respondent
by which initially liquidated damages/penalty were imposed on
the appellant for the delay. However, on the request made by the
appellant, the respondent granted an extension of time by waiving
liquidated damages. Therefore, the appellant made an irreversible
election to accept an extension of time under clause 49.5 of GCC.
He relied upon three letters addressed by the appellant in which the
appellant agreed not to make any claim other than escalation against
the respondent because of the delay on the part of the respondent
for which an extension of time has been sought. He pointed out
that the claim for damages was raised two years after the date of
the last extension. Learned counsel would, thus, submit that the
appellant has lost its right to challenge clause 49.5 and therefore,
no interference is called for with the impugned judgment.
OUR VIEW
12. We are concerned with three ROBs bearing numbers LC-89, LC-228
and LC-108. Clause 49.5 of GCC reads thus:
“49.5 Delays due to Employer/Engineer
In the event of any failure or delay by the Employer/
Engineer in fulfilling his obligations under the contract,
then such failure or delay, shall in no way affect or vitiate
the contract or alter the character thereof; or entitle
the Contractor to damages or compensation thereof
2 (2010) 13 SCC 377
1420 [2025] 1 S.C.R.
Supreme Court Reports
but in any such case, the Engineer shall grant such
extension or extensions of time to complete the work, as
in his opinion is/are reasonable.”
(emphasis added)
13. Initially, by a letter dated 11th February, 2013, the respondent had
imposed a penalty on the appellant for slippage of milestones and
non-deployment of engineers. On 19th June, 2013, a letter was
addressed by the appellant to the respondent in respect of LC-108
seeking an extension of time of 264 days as there were delays on the
part of the respondent. The said letter mentioned that as the delay
resulted in an additional financial burden on the appellant, they would
claim it separately. Similar separate letters in respect of LC-228 and
LC-89 were addressed by the appellant on 30th August, 2013. In the
said three letters, the appellant invoked clause 49 of GCC for grant
of extension of time. Sub-clause No.5 of clause 49 is the only sub-
clause in clause 49 which provides for extension of time on account
of delay due to the respondent. By a letter dated 29th November,
2013, the respondent communicated to the appellant the decision
regarding the grant of extension of time regarding LC-228, LC-89
and LC-108 till 09th April, 2014, 28th February, 2014 and 19th April,
2014 respectively. As stated in the letter, in the case of LC-89 and
LC-228, the extension was granted subject to penalty. In the case of
LC-89, the appellant addressed a letter dated 28th February, 2014 to
the respondent requesting that an extension of time be granted till
30th May, 2014, without penalty. Similar letters were addressed on
9th April, 2014 regarding LC-228 and on 19th April, 2014 regarding
LC-108, wherein a request was made to grant an extension of time
till 31st January, 2015 and 15th December, 2014 respectively, without
penalty. It is pertinent to note that in these letters, the appellant did
not state that it would be making any claim on account of the delay
on the part of the respondent. On 28th February, 2014, 9th April, 2014
and On 19th April, 2014, by separate letters, the appellant applied
for grant of extension of time for all three ROBs without penalty.
14. By letter dated 24th May, 2014, the respondent approved the extension
of time for LC-228, LC-89 and LC-108 up to 31st January, 2015, 30th
November, 2014 and 15th December, 2014 respectively. The extension
was granted without penalty. Thus, based on the requests made
by the appellant, while granting further extension, the respondent
waived the penalty.
[2025] 1 S.C.R. 1421
M/s C & C Constructions Ltd. v. IRCON International Ltd.
15. Thereafter, on 03rd September, 2014, the appellant addressed three
separate letters to the respondent raising monetary claims on account
of the delay on the part of the respondent. The respondent replied
on 14th October, 2014 by separate letters. The letters are identical.
For the sake of convenience, we are referring to the letter of the
respondent in respect of LC-108, which reads thus:
“The claim of Rs. 65696068/- is not at all admissible and
acceptable. The time extension which has been granted to
you without penalty is not at all basis of any claims as per
clause 49 of General Conditions of Contract. As per clause
No. 4.1 of Special Conditions of Contract your claims is not
tenable. The same was already discussed with you earlier
and in response to that you had removed your lines of
“It is also to mention here that delay in work is resulting
in additional financial burden on us on account of
establishment and over heads and cost overrun etc.,
for a lengthier period than planned, for which we will
be claiming separately” from your request letter for
extension of time. That time you were also agreed
with it and re submitted your request letter without
such lines.
Once again you are requested to complete the work
within the extended period and do not waste your time
as well as our time in writing such type of false claims.”
(emphasis added)
16. Thereafter, concerning the three LCs, separate letters were addressed
by the appellant on 8th January, 2015, requesting the respondent
to grant further extension. The respondent sent separate replies
to these three letters on 9th January, 2015. In the said letters, the
respondent informed the appellant as under:
“Vide above mentioned letters you have requested for
Extension of Time in respect of ROB in lieu of LC No. 89
(Dadi ka Phatak) up to 30.06.2015. In this connection
you are requested to kindly submit an undertaking that
you will not claim anything extra other than escalation
for work executed in the extended.”
(emphasis added)
1422 [2025] 1 S.C.R.
Supreme Court Reports
17. Pursuant to the said letters, by three separate letters dated 14th
January, 2015, in respect of the said three LCs, the appellant
submitted undertakings in the following terms:
“We, therefore, undertake that we will not make any claim
other than Escalation against the IRCON because of
the delay in completion of which extension of time
has been sought by us.”
(emphasis added)
18. After giving the said undertakings, two years thereafter, on 25th
January, 2017, the appellant made claims on account of delay on
the part of the respondent, for which an extension was granted. The
appellant invoked the arbitration clause on the basis of the said claims.
19. Considering the conduct of the appellant, the following conclusions
can be drawn:
a) The appellant acted upon clause 49.5 and sought an extension
of time on three occasions;
b) The claim in the letter dated 25th January, 2017 was made by
the appellant after giving solemn undertaking on 14th January,
2015 not to make any claim other than escalation in respect of
delays in the completion of work. The claim made was contrary
to the undertakings;
c) By the undertakings, the appellant agreed not to make a claim
contrary to what is provided in clause 49.5; and
d) Therefore, by conduct, the appellant was estopped from
challenging the validity of clause 49.5.
20. At this stage, we must refer to the decision of the learned Single
Judge in the petition under Section 34 filed by the appellant. The
contentions raised by the appellant have been reproduced by the
learned Single Judge of Delhi High Court in paragraphs 12 and 13
of the Judgment. Paragraphs 12 and 13 read thus:
“12. Mr. Naveen Kumar, learned counsel for the petitioner
has primarily submitted that the Tribunal has clearly erred in
accepting the application of the respondent under Section
16 of the Act of 1996. The Tribunal should have allowed
the petitioner to produce evidence that the delay in
[2025] 1 S.C.R. 1423
M/s C & C Constructions Ltd. v. IRCON International Ltd.
discharging the obligations under the contract was
clearly on the respondent and as such, the petitioner
was entitled to the claims, which were in the nature
of damages.
13. That apart, he has drawn my attention to various
documents to contend that the respondent had by its
own conduct, not adhered to Clause 49.5 of the GCC.
In support of his submission, he has drawn my attention
to page 670 of the documents, wherein the respondent
in its communication to the petitioner has stated for grant
of extension of time, the petitioner’s claims for additional
financial burden has to be dealt together. In other words, the
respondent has agreed with the claim of the petitioner for
additional financial burden. Mr. Kumar has relied upon the
judgment reported in MANU/SC/1620/2009, Asian Techs
Ltd. v. Union of India, in support of his submission that
de-hors a stipulation which bars a claim, still the Arbitrator
can consider the aspect of delay and award the claim, if
justified.”
(emphasis added)
21. No other submission made by the appellant has been noted in the
judgment. The learned Single Judge firstly held that on the plain
reading of clause 49.5 of the GCC, the claims made by the appellant
before the Arbitrator were barred. Learned Single Judge held that
having accepted the stipulation in clause 49.5, the appellant could
not have contended otherwise.
22. Now, we turn to the impugned judgment of the Division Bench. The
first contention raised by the appellant was that all 15 monetary
claims could not have been summarily rejected by the Arbitral
Tribunal exercising jurisdiction under Section 16 of the Arbitration Act,
without giving an opportunity to the appellant to lead evidence and
to prove that the claims were not barred by clause 49.5. Secondly,
the appellant sought to rely upon clause 49.4. Another contention
raised on behalf of the appellant was that clause 49.5 was waived
by the respondent.
23. As the claims were hit by Clause 49.5 on its plain reading, there was
no question of allowing the appellant to lead evidence. Clause 49.4
1424 [2025] 1 S.C.R.
Supreme Court Reports
will apply when the delay is not due to the respondent. Admittedly,
in this case, the delay was on the part of the respondent. Hence,
clause 49.5 will apply and not clause 49.4.
24. Now, in this appeal, a contention has been raised that the validity
of clause 49.5 ought to have been examined in the light of Sections
23 and 28 of the Contract Act, but the High Court has not examined
the said issue. Careful perusal of the judgment of the learned Single
Judge shows that the contention that the validity of clause 49.5 ought
to be decided in the light of Sections 23 and 28 of the Contract
Act was not raised before the learned Single Judge in a petition
under Section 34. The said contention was not raised even before
the Division Bench in appeal under Section 37. Therefore, it is not
open to the appellant to raise the said contention in this appeal for
the first time.
25. A contention was raised for the first time in appeal under Section 37
that clause 49.5 was waived by the respondent. Apart from the fact
that said contention could not have been raised for the first time in
appeal under Section 37 of the Arbitration Act, on the applications
made by the appellant specifically invoking clause 49, the respondent
granted an extension of time on more than one occasion. On this
behalf, much capital was sought to be made about what is stated
by the respondent in its letter dated 14th October, 2013. Though
the said contention could not have been raised in an appeal under
Section 37 still, we are examining the same. In the letter dated 14th
October, 2013, the respondent stated:
“Vide above mentioned letter, you have requested for
extension of time for a total of 264 days. However, in,
your letter you have mentioned as under:
“it is also mentioned here that delay in work in resulting
in additional financial burden on us on account of
establishment and over heads etc., for a longer period
than planned, for which we will be claiming separately”
For grant of extension of time, your claim for additional
financial burden has to be dealt together with the proposal
of extension of time. Hence, your statement that you will
be claiming separately for additional financial burden is
not acceptable.
[2025] 1 S.C.R. 1425
M/s C & C Constructions Ltd. v. IRCON International Ltd.
Hence, you are requested to submit your detailed
claim immediately so that your request for extension
of time can be processed early.”
26. By no stretch of imagination, after reading the said letter it can be
inferred that clause 49.5 was waived by the respondent. In fact, the
respondent stated that the claim for financial burden would have to
be dealt with together with the proposal for an extension of time, and
the said claim cannot be processed separately. Thereafter, on two
occasions, on specific requests made by the appellant under clause
49 of the GCC, the extension of time was granted by the respondent.
Except sub-clause 5 of clause 49, there is no other sub-clause which
provides for grant of extension when the delay was attributable to
the respondent. The extensions were granted at the instance of the
appellant by invoking clause 49. Hence, the argument of waiver of
Clause 49.5 by the respondent deserves to be rejected. Moreover,
detailed claim, as stated in the letter dated 14th October, 2013 was
not submitted by the appellant. Therefore, the Division Bench rightly
found no merit in the said contention.
27. As far as scope of interference in an appeal under Section 37 of
Arbitration Act is concerned, the law is well settled. In the case of
Larsen Air Conditioning and Refrigeration Company v. Union
of India and Ors.3 in paragraph 15, this court held thus:
“15. The limited and extremely circumscribed jurisdiction
of the court under Section 34 of the Act, permits the
court to interfere with an award, sans the grounds of
patent illegality i.e. that “illegality must go to the root of
the matter and cannot be of a trivial nature”; and that the
Tribunal “must decide in accordance with the terms of
the contract, but if an arbitrator construes a term of the
contract in a reasonable manner, it will not mean that the
award can be set aside on this ground” [ref : Associate
Builders [Associate Builders v. DDA, (2015) 3 SCC 49 :
(2015) 2 SCC (Civ) 204] , SCC p. 81, para 42]. The other
ground would be denial of natural justice. In appeal,
Section 37 of the Act grants narrower scope to the
3 (2023) 15 SCC 472
1426 [2025] 1 S.C.R.
Supreme Court Reports
appellate court to review the findings in an award,
if it has been upheld, or substantially upheld under
Section 34.”
(emphasis added)
28. In the case of Konkan Railway Corporation Limited v. Chenab
Bridge Project Undertaking4 in paragraph 18, this court held thus:
“18. At the outset, we may state that the jurisdiction of the
court under Section 37 of the Act, as clarified by this Court
in MMTC Ltd. v. Vedanta Ltd. [MMTC Ltd. v. Vedanta Ltd.,
(2019) 4 SCC 163 : (2019) 2 SCC (Civ) 293] , is akin to
the jurisdiction of the court under Section 34 of the Act.
[Id, SCC p. 167, para 14:“14. As far as interference with
an order made under Section 34, as per Section 37, is
concerned, it cannot be disputed that such interference
under Section 37 cannot travel beyond the restrictions laid
down under Section 34. In other words, the court cannot
undertake an independent assessment of the merits of the
award, and must only ascertain that the exercise of power
by the court under Section 34 has not exceeded the scope
of the provision.”] Scope of interference by a court in an
appeal under Section 37 of the Act, in examining an order,
setting aside or refusing to set aside an award, is restricted
and subject to the same grounds as the challenge under
Section 34 of the Act.”
29. Considering the limited scope of interference, as laid down by this
Court, we find absolutely no merit in the appeal and the same is
accordingly dismissed.
Result of the case: Appeal dismissed.
†
Headnotes prepared by: Nidhi Jain
4 (2023) 9 SCC 85
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.