Created byFuzzy Cloud

Supreme Court of India

M/S KARNATAKA EMTA COAL MINES LIMITED AND ANOTHERversusCENTRAL BUREAU OF INVESTIGATION

Citation
2024 INSC 623
Decided
23 August 2024
Disposal
Appeal(s) allowed

Holding

The Supreme Court held that the CBI’s prosecution was unsustainable because the CAG report cannot form the basis of criminal liability and the dispute was civil in nature, leading to the quashing of the charge and charge‑framing orders.

Summary

The appeals challenge the Special Judge’s order on charge (24‑12‑2021) and charge‑framing order (03‑03‑2022) against Karnataka Emta Coal Mines Ltd (KECML) and its former MD for alleged conspiracy to illegally sell coal washery rejects. The Court examined whether the CBI’s investigation was predicated solely on the 2013 CAG audit report, whether that report could create criminal liability, and the effect of earlier Karnataka High Court judgments that held the dispute to be civil. It held that the CAG report has only persuasive value, the High Court’s findings exonerated the appellants, and the CBI’s reliance on the audit report amounted to a fishing enquiry. Consequently, the prosecution was deemed unsustainable and the orders of charge and charge‑framing were set aside.

Issues considered

  • Did the CBI primarily rely on the CAG audit report or conduct an independent investigation?
  • Can the CAG audit report fasten liability on KECML under the Prevention of Corruption Act?
  • What is the import of the Karnataka High Court judgment dated 24‑03‑2016?
  • What is the sanctity of an audit report in law?
  • Was KECML required to account for coal rejects or dispose of them as per the mining plan?
  • Can KECML be blamed for not setting up a pit‑head coal washery?
  • Did the coal rejects have any useful calorific value making them saleable?
  • Does the Aryan Energy case have persuasive value in the present dispute?
  • Inherent jurisdiction of the High Court under Section 482 Cr.P.C.
  • Extraordinary powers of the Supreme Court under Article 136 of the Constitution
  • Application of mind at the stage of Section 227/277 Cr.P.C.

Legislation cited

Subjects

Joint Venture AgreementFuel Supply AgreementWashability ReportAudit ReportCoal RejectsCoal block allocationCalorific ValueAryan Energy CaseSection 482 of Code of Criminal Procedure, 1973Inherent Jurisdiction of the High CourtExtraordinary powers of the Supreme CourtSection 227 of Code of Criminal Procedure, 1973Application of mind u/s.227 of Cr.PC

Judgment

                 [2024] 8 S.C.R. 1146 : 2024 INSC 623

     M/s Karnataka Emta Coal Mines Limited and Another
                             v.
               Central Bureau of Investigation
                (Criminal Appeal Nos. 1659-1660 of 2024)
                                23 August 2024
           [Hima Kohli* and Ahsanuddin Amanullah, JJ.]

                           Issue for Consideration
       The present appeals challenge the Order on Charge dated
       24.12.2021 and Order framing Charges dated 03.03.2022 passed
       by the Special Judge (Prevention of Corruption Act) Central Bureau
       of Investigation registered u/s.120-B r/w. ss.409/420 of the IPC and
       ss.13(1)(d)/ 13(2) of the Prevention of Corruption Act, 1988. The
       appellants before this Court are M/s Karnataka Emta Coal Mines
       Limited (KECML) arrayed as accused No. 12 in the chargesheet
       and Chairman and Managing Director of Emta Coal Limited and
       former Managing Director of accused No. 12, arrayed as accused
       No. 6 in the chargesheet.
       The issues which arose for consideration are: Did CBI Primarily
       Rely on the Audit Report of the Comptroller and Auditor General
       (CAG) or independently investigated the matter; Could the Audit
       Report of the CAG fasten any liability on KECML; What is the
       import of the Judgment dated 24.03.2016 of the Karnataka High
       Court; What is the sanctity of an Audit Report in Law; What is the
       effect of the absence of any strategy in the Mining plan to dispose
       off the coal rejects; Was KECML required to account for the coal
       rejects; Can KECML be blamed for not setting up the coal washery
       at the pithead; Did the coal rejects have any useful calorific value
       making it a saleable commodity; Does the Aryan Energy case has
       a persuasive value; Inherent Jurisdiction of the High Court under
       Section 482, Cr.PC; Extraordinary powers of the Supreme Court
       under Article 136 of the Constitution of India; Application of mind
       at the stage of Section 277, Cr.PC.

                                  Headnotes†
       Prevention of Corruption Act, 1988 – ss.13(1)(d)/13(2) – Penal
       Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
       (Development & Regulation) Act, 1957 – Did CBI Primarily Rely
* Author
[2024] 8 S.C.R.                                                              1147

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

     on the Audit Report of the Comptroller and Auditor General
     (CAG) or independently investigated the matter:
     Held: The file produced by the respondent-CBI reveals that
     premised on the Source Information Report (SIR) submitted by an
     Inspector from the Department pertaining to some irregularities in
     the allocation of coal blocks under the Government Dispensation
     Category allegedly in connivance with public servants, the matter
     was taken up by CBI for verification – The notings in the file
     states that it was not possible to verify the allegations discretely –
     Therefore, the SIR was directed to be registered as a PE – These
     records falsifies the suggestion made by the respondent-CBI that
     there was a SIR that disclosed irregularities in the Joint Venture
     Agreement (JVA) executed between M/s. Karnataka Power
     Corporation Limited (KPCL) and KECML – The stand of the
     respondent-CBI that PE-5 was registered well before the Audit
     Report of the CAG and originated independently thereof, is also
     factually misleading because CBI’s own record shows that the
     scope of enquiry in respect of PE-5 registered on 28.09.2012,
     was entirely different and had no relationship with the JVA and
     other agreements executed by KPCL and KECML – Thus, the
     plea of the respondent-CBI that it conducted an investigation in
     the present case during the course of the inquiry in respect of
     PE-5 registered by it in the year 2012 is belied as the Source
     Information Report (SIR) was on a completely different aspect –
     CBI only got activated only on stumbling upon the Audit Report of
     the CAG submitted in 2013 – There is nothing brought on record
     to show to the contrary. [Paras 8.3, 21.2(a)]
     Prevention of Corruption Act, 1988 – ss.13(1)(d)/ 13(2) – Penal
     Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
     (Development & Regulation) Act, 1957 – Could the Audit Report
     of the CAG fasten any liability on KECML:
     Held: The Supreme Court having already dismissed the appeal
     filed by KPCL against the judgment of the Karnataka High Court,
     having held in clear terms that the CAG Report could not form the
     basis for launching proceedings against the appellants and further,
     having upheld the findings returned by the Karnataka High Court
     that the CAG Report appears to have been the starting point for
     the entire disputes between the parties who till then, were smoothly
     discharging their obligations under various agreements, there is
     no reason to take a different view only on the ground that the
1148                                                         [2024] 8 S.C.R.

                     Digital Supreme Court Reports


    respondent-CBI was not a party in the aforesaid proceedings –
    Further, the CAG Report had not attained finality inasmuch as its
    recommendations have not been tabled before the Parliament or
    accepted so far – The said report at best, has a persuasive value
    but no more. [Paras 9.5, 21.2(b)]
    Prevention of Corruption Act, 1988 – ss.13(1)(d)/13(2) – Penal
    Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
    (Development & Regulation) Act, 1957 – What is the import of
    the Judgment dated 24.03.2016 of the Karnataka High Court:
    Held: The decision dated 24.03.2016 of the Karnataka High
    Court in a writ petition filed by KECML against KPCL has been
    wrongly overlooked – The High Court had an occasion to
    scrutinize the very same agreements and the CAG report that
    formed the basis of the investigation conducted by the respondent-
    CBI to return positive findings in favour of the appellants –
    The view taken by the Karnataka High Court has been upheld by
    this Court in a judgment rendered on 20.05.2022 which was just
    a few days after Charges were framed by the Special Judge, CBI
    on 03.03.2022. [Para 21.2(f)]
    Mines and Minerals (Development & Regulation) Act, 1957 –
    What is the sanctity of an Audit Report in Law:
    Held: The CAG Report is subject to scrutiny by the Parliament
    and the Government can always offer its views on the said
    report – Merely because the CAG is an independent constitutional
    functionary does not mean that after receiving a report from it and
    on the PAC scrutinizing the same and submitting its report, the
    Parliament will automatically accept the said report – The Parliament
    may agree or disagree with the Report – It may accept it as it is
    or in part – In the instant case, it is not in dispute that the Audit
    Report of the CAG has not been tabled before the Parliament for
    soliciting any comments from the PAC or the respective Ministries –
    Therefore, the views taken by the CAG to the effect that tremendous
    loss had been caused to the public exchequer on account of
    the coal rejects being disposed of by the KPCL and KECML
    remains a view point but cannot be accepted as decisive – The
    respondent-CBI has largely relied on the findings and the
    conclusions drawn in the Audit Report of the CAG to launch the
    prosecution against the appellants on an assumption that the said
    Report has the seal of approval of the Parliament and has attained
    finality, which is not the case. [Para 11.5]
[2024] 8 S.C.R.                                                           1149

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

     Prevention of Corruption Act, 1988 – ss.13(1)(d)/13(2) – Penal
     Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
     (Development & Regulation) Act, 1957 – What is the effect of
     the absence of any strategy in the Mining plan to dispose off
     the coal rejects:
     Held: The explanation offered by the appellants that at that point
     in time, the Central Government had not come out with any
     specific plan to dispose off the coal rejects is validated by the
     reply furnished by the Minister of State, MoC, in the Lok Sabha
     in response to an unstarred question seeking an answer from the
     Government of India as to whether it had framed any National Policy
     for exploitation of the coal rejects – The reply given was that the
     Government had not framed any National Policy for exploitation
     of coal rejects and the same was still under consideration – That
     being the position, it was left to KPCL and KECML to devise a
     satisfactory and safe method to dispose off the coal rejects –
     This was done in terms of Article 5(2)(b) of the JVA that required
     KECML to dispose off the rejects in a manner that would ensure
     that there was no threat to the environment – This Court does
     not find any irregularity in the route adopted to dispose off the
     coal rejects. [Para 13.2]
     Prevention of Corruption Act, 1988 – ss.13(1)(d)/13(2) – Penal
     Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
     (Development & Regulation) Act, 1957 – Was KECML required
     to account for the coal rejects:
     Held: The clauses of the JVA and FSA clearly indicate that KECML
     was only obliged to provide a specified grade of washed coal
     (Grade – D) having a specific GCV in the range of 4200-4940
     Kcal/kg – When coal has been defined in the JVA and FSA as
     “washed coal with guaranteed value” and one that satisfied the
     parameters laid down in Annex-1 attached to the JVA and FSA
     and further, KECML was required to ensure that all “shales/stones”
     are removed from the coal before making the supply, there was
     no occasion for KECML to account for the rejects – All that KPCL
     was required to do was to buy from KECML, the washed coal
     with a particular guaranteed value and one that would satisfy
     the specified quality parameters, at a predetermined price – The
     agreement governing the parties required KECML to dispose off
     the rejects safely – KECML was not required to account for the
     coal rejects to KPCL. [Para 14.3]
1150                                                            [2024] 8 S.C.R.

                      Digital Supreme Court Reports


    Prevention of Corruption Act, 1988 – ss.13(1)(d)/13(2) – Penal
    Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
    (Development & Regulation) Act, 1957 – Can KECML be blamed
    for not setting up the coal washery at the pithead:
    Held: KECML could not be faulted for failing to set up the coal
    washery at the pithead, in terms of the JVA as that was for reasons
    beyond its control which included a prolonged litigation between
    the MoC and CIPCO in relation to the very same coal blocks
    allocated to KPCL which in turn delayed the project considerably –
    Production of coal could only commence in September, 2008 when
    the curtains were drawn on the aforesaid litigation – The Board
    of KPCL consciously acceded to the proposal made by KECML
    that a MoU be executed with GCWL for washing of mined coal
    at its washery – Pertinently, GCWL was not an unknown entity to
    KPCL as the latter had prior dealings with the said Company for
    washing of mined coal in another project – This decision taken
    by the parties in their commercial wisdom has been sought to be
    selectively tainted with criminal intention attributed to the appellants,
    without any basis. [Para 21.2 (k)]
    Prevention of Corruption Act, 1988 – ss.13(1)(d)/13(2) – Penal
    Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
    (Development & Regulation) Act, 1957 – Did the coal rejects
    have any useful calorific value making it a saleable commodity:
    Held: The Detailed Washability Report of the Government
    Laboratory namely, CIMFR, Nagpur – The said Report stated in
    so many words that the rejects did not contain any useful calorific
    value Reliance placed by the respondent-CBI on the revised Mining
    Plan submitted by the appellants to the MoC in 2010, that mentions
    a new technology for utilization of rejects for its carbon value,
    namely FBC is of no consequence as the said technology had
    not even been introduced when MoC approved the original Mining
    Plan, submitted by KECML in the year 2004 – Even otherwise, it
    is not in dispute that for applying the said technology, a plant was
    required to be established after obtaining necessary approvals
    from several agencies. [Para 16.1]
    Prevention of Corruption Act, 1988 – ss.13(1)(d)/13(2) – Penal
    Code, 1860 – s.120-B r/w. ss.409/420 – Mines and Minerals
    (Development & Regulation) Act, 1957 – Does the Aryan Energy
    case has a persuasive value:
[2024] 8 S.C.R.                                                              1151

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

     Held: An interpretation of the very same clauses in the agreement
     relating to the manner of disposal off the coal rejects came up for
     consideration before the Karnataka High Court in a writ petition filed
     by Aryan Energy against KPCL – Having scrutinized the clauses
     forming a part of the agreement executed between the parties
     vide judgment dated 22.07.2021, the Karnataka High Court clearly
     observed that KPCL did not have any claim over the coal rejects
     generated during washing of the coal – The submissions made
     by the respondent-CBI that the aforesaid judgment came much
     after institution of the chargesheet by the, respondent-CBI is of no
     consequence – Even if that was so, nothing prevented the Special
     Judge, CBI from taking into consideration the view expressed in the
     said judgement at the time of framing charges, particularly, when
     the clause relating to disposal of the coal rejects in an environment
     friendly manner incorporated in the agreement between KPCL and
     Aryan Energy was identical to the one contained in the agreement
     between KPCL and KECML. [Para 21.2(g)]
     Code of Criminal Procedure, 1973 – s.482 – Inherent Jurisdiction
     of the High Court:
     Held: Section 482 Cr.P.C recognizes the inherent powers of the
     High Court to quash initiation of prosecution against the accused
     to pass such orders as may be considered necessary to give effect
     to any order under the Cr.P.C or to prevent abuse of the process
     of any court or otherwise to secure the ends of justice – It is a
     statutory power vested in the High Court to quash such criminal
     proceedings that would dislodge the charges levelled against
     the accused and based on the material produced, lead to a firm
     opinion that the assertions contained in the charges levelled by the
     prosecution deserve to be overruled – While exercising the powers
     vested in the High Court under Section 482, Cr.P.C, whether at
     the stage of issuing process or at the stage of committal or even
     at the stage of framing of charges, which are all stages that are
     prior to commencement of the actual trial, the test to be applied
     is that the Court must be fully satisfied that the material produced
     by the accused would lead to a conclusion that their defence is
     based on sound, reasonable and indubitable facts – The material
     relied on by the accused should also be such that would persuade
     a reasonable person to dismiss the accusations levelled against
     them as false. [Paras 18.7, 18.8]
     Constitution of India – Art.136 – Extraordinary powers of the
     Supreme Court under Article 136:
1152                                                          [2024] 8 S.C.R.

                     Digital Supreme Court Reports


    Held: Article 136 can be invoked by a party in a petition for special
    leave to appeal from any judgement, decree, determination,
    sentence or order in any cause or matter passed or made by a
    Court or Tribunal within the territory of India – The reach of the
    extraordinary powers vested in this Court under Article 136 of the
    Constitution of India is boundless – Such unbridled powers have
    been vested in Court, not just to prevent the abuse of the process
    of any court or to secure the ends of justice as contemplated in
    Section 482, Cr.P.C, but to ensure dispensation of justice, correct
    errors of law, safeguard fundamental rights, exercise judicial review,
    resolve conflicting decisions, inject consistency in the legal system
    by settling precedents and for myriad other to undo injustice,
    wherever noticed and promote the cause of justice at every level –
    The fetters on this power are self imposed and carefully tampered
    with sound judicial discretion. [Para 19.6]
    Code of Criminal Procedure, 1973 – s.277 – Application of
    mind at the stage of s.227 of Cr.PC – discussed.
    Constitution of India – Art. 136 – Prevention of Corruption
    Act, 1988 – ss.13(1)(d)/13(2) – Penal Code, 1860 – s.120-B r/w.
    ss.409/420 – Mines and Minerals (Development & Regulation)
    Act, 1957 – The Special Judge, CBI passed an order on
    charge dated 24.12.2021 and the order framing charges dated
    03.03.2022 qua appellants – Sustainability:
    Held: This Court is of the opinion that the respondent-CBI embarked
    on a roving and fishing inquiry on the strength of the Audit Report
    of the CAG and then started working backwards to sniff out criminal
    intent against the appellants – The underpinnings of what was a
    civil dispute premised on a contract between the parties, breach
    whereof could at best lead to determination of the contract or even
    the underlying lease deed, has been painted with the brush of
    criminality without any justification – This criminal intent has been
    threaded into the dispute by the respondent-CBI by misinterpreting
    the clauses of the agreements governing the parties and by
    heavily banking on the observations made in the Audit Report
    of the CAG that has not attained finality till date – In view of the
    glaring infirmities, the impugned orders deserve interference in
    exercise of the powers vested in this court under Article 136 of the
    Constitution of India – The order on charge dated 24.12.2021 and
    the order framing charges dated 03.03.2022 passed by the Special
    Judge, CBI qua the appellants before this Court are unsustainable
    and accordingly quashed and set aside. [Paras 21.3, 21.4]
[2024] 8 S.C.R.                                                            1153

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                              Case Law Cited
     P.S.R. Sadhanantham v. Arunachalam [1980] 2 SCR 873 : (1980)
     3 SCC 141 – followed.
     Uttam Chand v. ITO (1982) 2 SCC 543; G.L. Didwania v. ITO
     (1995) Supp(2) 724; Arun Kumar Aggarwal v. Union of India [2013]
     3 SCR 508 : (2013) 7 SCC 1; Rajiv Thapar and Others v. Madan
     Lal Kapoor [2013] 3 SCR 52 : (2013) 3 SCC 330; State of Orissa
     v. Debendra Nath Padhi [2004] Supp. 6 SCR 460 : (2005) 1 SCC
     568; Anand Kumar Mohatta and Another v. State (NCT of Delhi),
     Department of Home and Another [2018] 13 SCR 1028 : (2019)
     11 SCC 706; State of Karnataka v. L. Munniswamy [1977] 3 SCR
     113 : (1977) 2 SCC 699; Arunachalam v. P.S.R. Sadhanantham
     and Another [1979] 3 SCR 482 : (1979) 2 SCC 297; Khoday
     Distilleries Limited and Others v. Mahadeshwara S.S.K. Limited
     [2019] 3 SCR 411 : (2012) 12 SCC 291; Mekala Sivaiah v. State
     of Andhra Pradesh [2022] 6 SCR 989 : (2022) 8 SCC 253; Union
     of India v. Prafulla Kumar Samal and Another [1979] 2 SCR 229 :
     (1979) 3 SCC 4; State of Tamil Nadu v. N. Suresh Rajan and Others
     [2014] 1 SCR 135 : (2014) 11 SCC 709 – relied on.
     CBI v. S.M. Jaamdar & Others; M.L. Sharma v. The Principal
     Secretary and Others [2014] 12 SCR 110 : (2014) 9 SCC 614;
     Girish Kumar Suneja v. CBI [2017] 9 SCR 544 : (2017) 14 SCC
     809; KPCL v. Aryan Energy Private Limited and Others, COMAP
     No. 12, 13, 14 and 15 and 2020 decided on 22nd July, 2021;
     Centre for Public Interest Litigation v. Union of India [2012] 3 SCR
     147 : (2012) 3 SCC 1; Pathan Mohammed Suleman Rehmatkhan
     v. State of Gujarat [2013] 12 SCR 446 : (2014) 4 SCC 156;
     Radheshyam Kejriwal v. State of West Bengal and Another [2011]
     4 SCR 889 : (2011) 3 SCC 581; Ashoo Surendranath Tewari v.
     Deputy Superintendent of Police, EOW, CBI and Another (2020) 9
     SCC 636; J Sekar alias Sekar Reddy v. Directorate of Enforcement
     [2022] 3 SCR 698 : (2022) 7 SCC 370; Prem Raj v. Poonamma
     Menon & Another [2024] 4 SCR 29 : (2024) SCC OnLine SC 483;
     B. Jayaraj v. State of Andhra Pradesh [2014] 4 SCR 554 : (2014)
     13 SCC 55; P. Satyanarayana Murthy v. District Inspector of Police,
     State of Andhra Pradesh and Another (2015) 10 SCC 152; State
     through Central Bureau of Investigation v. Dr Anup Kumar Srivastava
     [2017] 9 SCR 341 : (2017) 15 SCC 560; K. Shanthamma v. State
     of Telangana (2022) 4 SCC 574; Neeraj Dutta v. State (NCT of
     Delhi) [2023] 2 SCR 997 : (2023) 4 SCC 731; Soundarajan v. State
     Rep. by the Inspector of Police Vigilance Anticorruption Dindigul
1154                                                      [2024] 8 S.C.R.

                    Digital Supreme Court Reports


    [2023] 4 SCR 133 : (2023) SCC OnLine SC 424; M.S Associates
    and Others v. Union of India (2005) SCC Online Gau 308; (2005)
    275 ITR 502; The King Emperor v. Khawaja Nazir Ahmed, AIR
    (1945) PC 18; Niranjan Singh Karam Singh v. Jitendra Bhimraj
    Bijjaya And Others [1990] 3 SCR 633 : (1990) 4 SCC 76; State of
    Maharashtra v. Som Nath Thapa [1996] Supp. 1 SCR 189 : (1996)
    4 SCC 659; State of Bihar v. Ramesh Singh [1978] 1 SCR 257 :
    (1977) 4 SCC 39; K.G. Premshanker v. Inspector of Police and
    Another [2002] Supp. 2 SCR 350 : (2002) 8 SCC 87; Manohar
    Lal Sharma v. Principal Secretary and Another [2014] 8 SCR 446 :
    (2014) 9 SCC 516; Standard Chartered Bank(1) v. Directorate of
    Enforcement [2006] 2 SCR 709 : (2006) 4 SCC 278; Collector
    of Customs v. L.R. Melwani, AIR 1970 SC 962; K.C. Builders v.
    CIT [2004] 1 SCR 1134 : (2004) 2 SCC 731; Rukmini Narvekar
    v. Vijaya Satardekar and Others [2008] 14 SCR 271: (2008) 14
    SCC 1; State of Punjab and Others v. Rafiq Masih (White Washer)
    Others [2014] 13 SCR 1343 : AIR (2015) 1267 – referred to.

                              List of Acts
    Coal Mines (Nationalization) Act, 1973; Mines and Minerals
    (Development & Regulation) Act, 1957; Prevention of Corruption
    Act, 1988; (Duties, Powers and Conditions of Service) Act, 1971;
    Evidence Act, 1872; Comptroller and Auditor General (Duties,
    Powers and Conditions of Service) Act, 1971; Penal Code, 1860;
    Code of Criminal Procedure, 1973.

                           List of Keywords
    Joint Venture Agreement; Fuel Supply Agreement; Washability
    Report; Audit Report; Coal Rejects; Coal block allocation;
    Calorific Value; Aryan Energy Case; Section 482 of Code of
    Criminal Procedure, 1973; Inherent Jurisdiction of the High Court;
    Extraordinary powers of the Supreme Court; Section 227 of Code
    of Criminal Procedure, 1973; Application of mind u/s.227 of Cr.PC.

                          Case Arising From
    CRIMINAL APPELLATE JURISDICTION: Criminal Appeal Nos.
    1659-1660 of 2024
    From the Judgment and Order dated 24-12-2021 in CN No.
    CBI/317/2019 and Order dated 03-03-2022 in CN No. CBI/317/2019
    passed by the Special Judge (PC Act), CBI, Rouse Avenue District
    Court
[2024] 8 S.C.R.                                                                   1155

            M/s Karnataka Emta Coal Mines Limited and Another v.
                       Central Bureau of Investigation

                                   Appearances for Parties
       Ranjit Kumar, Sr. Adv., Abhimanyu Bhandari, Ms. Rooh-e-hina Dua,
       Ayush Aggarwal, Sangram S. Saron, Arav Pandit, Advs. for the
       Appellants.
       R.S. Cheema, Sr. Adv., Ms. Tarannum Cheema, Akshay Nagrajan,
       Akash Singh, Mukesh Kumar Maroria, Advs. for the Respondent.
                       Judgment / Order of the Supreme Court

                                             Judgment
       Hima Kohli, J.
                                               INDEX*

         S. Details                                            Paras No.     Page
         No.                                                                 No.
          1.     A.     PREFACE                                1-2           1
          2.     B.     FACTUAL BACKDROP                       3-3.10.5      2
          3.            3.1      Joint Venture Agreement       3.1.1-3.1.4   3-9
          4.            3.2      Correspondence                3.2.1-3.2.3   9-13
          5.            3.3      Fuel Supply Agreement         3.3.1-3.3.3   13-18
          6.            3.4      Memorandum of                 3.4.1-3.4.2   18-21
                                 Understanding
          7.            3.5      Washability Report of the     3.5.1         21-22
                                 Central Institute of Mining
                                 and Fuel Research,
                                 Nagpur
          8.            3.6      Revised Mining Plan           3.6.1-3.6.2   22-23
          9.            3.7      Information submitted         3.7.1-3.7.2   23-25
                                 by KECML to the Coal
                                 Controller
         10.            3.8      Audit Objection raised by     3.8.1-3.8.3   25-29
                                 the CAG
         11.            3.9      Preliminary Enquiry           3.9.1-3.9.2   29-31
                                 registered by
                                 respondent – CBI

* Ed. Note: Pagination as per the original Judgment.
1156                                                             [2024] 8 S.C.R.

                        Digital Supreme Court Reports



        12.        3.10 Litigation between KPCL         3.10.1-         31-33
                        and KECML                       3.10.6
        13.   C.   SUBMISSIONS
        14.        4.     Arguments by Counsel for      4.1-4.17        33-42
                          the Appellants
        15.        5.     Arguments by Counsel for      5.1-5.15        42-50
                          the respondent – CBI
        16.        6.     Rejoinder Arguments by        6.1-6.4         50-53
                          Counsel for the appellants
        17.   D.   DISCUSSION AND ANALYSIS              7.1-7.3         53-54
        18.        Did CBI Primarily Rely on the        8.1-8.3         55-57
                   Audity Repot of the CAG?
        19.        Could the Audit Report of the        9.1-9.5         57-60
                   CAG fasten any liability on
                   KECML?
        20.        Import of the Judgment               10.1-10.3       60-63
                   dated 24th March, 2016 of the
                   Karnataka High Court
        21.        Sanctity of an Audit Report in       11.1-11.5       63-66
                   Law
        22.        Denial of Sanctions by the           12.1-12.5       66-74
                   Sanctioning Authorities and the
                   effect on the Appellants
        23.        Effect of the absence of any         13.1-13.2       74-75
                   strategy in the Mining plan to
                   dispose off the coal rejects
        24.        Was KECML required to                14.1-14.3       75-77
                   account for the coal rejects?
        25.        Can KECML be blamed for not          15.1-15.4       77-79
                   setting up the coal washery at
                   the pithead?
        26.        Did the coal rejects have any        16.1            79-80
                   useful calorific value making it a
                   saleable commodity?
[2024] 8 S.C.R.                                                        1157

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation


       27.          Persuasive Value of the Aryan       17.1-17.2    80-82
                    Energy Case
       28.          Inherent Jurisdiction of the High   18.1-18.7    82-87
                    Court under Section 482, Cr.P.C
       29.          Extraordinary powers of the     19.1-19.9        88-93
                    Supreme Court under Article 136
                    of the Constitution of India
       30.          Application of mind at the stage    20.1-20.4    93-95
                    of Section 277, CrPC
       31.   E.     CONCLUSION                          21.1-21.4    95-102
                                  CITATIONS

      S. No. Title                                Citation
         1   ‘CBI vs. S.M. Jaamdar &
             Others’
         2   M.L. Sharma v. The Principal         (2014) 9 SCC 614
             Secretary and Others
         3   Girish Kumar Suneja v. CBI           (2017) 14 SCC 809
         4   KPCL v. Aryan Energy Private         COMAP No. 12, 13, 14
             Limited1 and Others                  and 15 and 2020 decided
                                                  on 22nd July, 2021
         5        Centre for Public Interest      (2012) 3 SCC 1
                  Litigation v. Union of India
         6        Arun Kumar Aggarwal v. Union (2013) 7 SCC 1
                  of India
         7        Pathan Mohammed Suleman      (2014) 4 SCC 156
                  Rehmat khan v. State of
                  Gujarat
         8        Radheshyam Kejriwal v. State (2011) 3 SCC 581
                  of West Bengal and Another
         9        Ashoo Surendranath Tewari    (2020) 9 SCC 636
                  v. Deputy Superintendent of
                  Police, EOW, CBI and Another
        10        J Sekar alias Sekar Reddy v.    (2022) 7 SCC 370
                  Directorate of Enforcement
        11        Prem Raj v. Poonamma            2024 SCC OnLine SC 483
                  Menon & Another
1158                                                         [2024] 8 S.C.R.

                         Digital Supreme Court Reports



          12       Neeraj Dutta v State (NCT of    (2023) 4 SCC 731
                   Delhi)
          13       B. Jayaraj v State of Andhra    (2014) 13 SCC 55
                   Pradesh
          14       P. Satyanarayana Murthy v       (2015) 10 SCC 152
                   District Inspector of Police,
                   State of Andhra Pradesh and
                   Another
          15       K. Shanthamma v State of        (2022) 4 SCC 574
                   Telangana
          16       State through Central Bureau    (2017) 15 SCC 560
                   of Investigation v Dr Anup
                   Kumar Srivastava
          17       Soundarajan v State Rep.        (2023) SCC OnLine SC
                   by the Inspector of Police      424
                   Vigilance Anticorruption
                   Dindigu
          18       M.S Associates and others v.    (2005) SCC Online Gau
                   Union of India                  308; (2005) 275 ITR 502
          19       The King Emperor v. Khawaja     AIR (1945) PC 18
                   Nazir Ahmand
          20       Manohar Lal Sharma vs.          (2014) 9 SCC 516
                   Principal Secretary and
                   Another
                                   GLOSSARY
    Abbreviations of Acts

        Act of 1973 Coal Mines (Nationalization) Act, 1973
        CAG Act         Comptroller and Auditor General (Duties, Powers and
                        Conditions of Service) Act, 1971
        Cr.P.C          Code Criminal Procedure, 1973
        CVC             Central Vigilance Commission
        IPC             Indian Penal Code
        MMDR Act, Mines and Minerals (Development & Regulation)
                  Act, 1957
        P.C. Act        Prevention of Corruption Act
[2024] 8 S.C.R.                                                    1159

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

     Abbreviations of Companies

      AEPL          M/s Aryan Energy Private Limited
      EMTA          M/s Eastern Mineral and Trading Agency
      GCWL          M/s Gupta Coalfields and Washeries Limited
      KECML         M/s Karnataka Emta Coal Mines Limited
      KPCL          M/s Karnataka Power Corporation Limited
      SAS           M/s. SAS India Private Limited
     Abbreviations of Government Organizations

      CAG           Comptroller and Auditor General
      CBI           Central Bureau of Investigation
      CIMFR         Central Institute of Mining and Fuel Research
      CIPCO         M/s. Central India Power Company
      DoPT          Department of Personnel and Training
      MoC           Ministry of Coal
      MoEF&CC Ministry of Environment, Forest and Climate Change
      MoPPP         Ministry of Personnel, Public Grievances and
                    Punishment
     Abbreviations of terms

      BTPS          Bellary Thermal Power Station
      CV            Calorific Value
      FBC           Fluidized Bed Combustion
      FSA           Fuel Supply Agreement
      GCV           Gross Calorific Value
      IBOCM         Integrated Baranj Open Cast Mines
      JVA           Joint Venture Agreement
      JVC           Joint Venture Company
      MoU           Memorandum of Understanding
      MT            Metric Tones
      PE            Preliminary Enquiry
      SIR           Source Information Report
1160                                                                       [2024] 8 S.C.R.

                              Digital Supreme Court Reports


       Hima Kohli, J.
       A.      PREFACE
1.     The present appeals challenge the Order on Charge dated
       24 th December, 2021 and Order framing Charges dated
       03rd March, 2022 passed by the learned Special Judge (Prevention
       of Corruption Act1) Central Bureau of Investigation,2 Coal Block Case
       No.-01, Rouse Avenue District Court, Delhi3 in a case4 registered
       under Section 120-B read with Sections 409/420 of the Indian Penal
       Code5 and Sections 13(1)(d)/ 13(2) of the P.C. Act, 1988 titled ‘CBI
       vs. S.M. Jaamdar & Others’. The appellants before this Court are
       M/s Karnataka Emta Coal Mines Limited6 arrayed as accused No. 12
       in the chargesheet and Shri Ujjal Kumar Upadhaya, Chairman and
       Managing Director of Emta Coal Limited and former Managing Director
       of accused No. 12, arrayed as accused No. 6 in the chargesheet.
2.     It may be noted at the outset that a challenge has been laid to the
       impugned orders passed by the learned Special Judge directly before
       this Court in the light of the directions issued in M.L. Sharma v. The
       Principal Secretary and Others7 vide order dated 25th July, 2014
       and upheld in Girish Kumar Suneja v. CBI 8 vide Judgement dated
       13th July, 2017 wherein directions have been issued that this Court
       alone shall have the jurisdiction to entertain cases relating to coal
       block allocation across the country, in particular, cases where the
       parties seek a stay of the investigation/trial in a matter relating to coal.
       B.      FACTUAL BACKDROP
3.     The contours of the case being intricately intertwined with several
       documents including Agreements, Memorandum of Understandings,9
       correspondence etc. referred to by both sides, the factual narrative


1    In short ‘P.C. Act’
2    In short CBI
3    Hereinafter referred to as ‘learned Special Judge, CBI’
4    Case No. CBI/317 /2019; CNR No. DLCT11-001312-2019 in RC No. 220-2015- E-0002; Branch: CBI/
     EOU-IV, EO-II/New Delhi
5    In short ‘IPC’
6    In short “KECML”
7    [2014] 12 SCR 110 : (2014) 9 SCC 614
8    [2017] 9 SCR 544 : (2017) 14 SCC 809
9    In short ‘MoU’
[2024] 8 S.C.R.                                                            1161

            M/s Karnataka Emta Coal Mines Limited and Another v.
                       Central Bureau of Investigation

       must be delineated chronologically at some length to appreciate the
       context of the case.
       3.1. JOINT VENTURE AGREEMENT
               3.1.1 A Joint Venture Agreement10 was executed between
                     Karnataka Power Corporation Limited11 and M/s Eastern
                     Mineral and Trading Agency12 for a period of 25 years for
                     the development of captive coal mines and supply of coal
                     to the Thermal Power Plant operated by KPCL namely,
                     Bellary Thermal Power Station13 with the tentative date of
                     commissioning scheduled in December, 2005. KPCL was
                     allocated three coal blocks by the Government of India
                     under the Western Coalfield Limited command area situated
                     in the State of Maharashtra for the development/operation
                     of coal mines dedicated to feeding BTPS.
               3.1.2 The JVA was executed between KPCL and EMTA on 13th
                     September, 2002 which gave birth to the Joint Venture
                     Company14 namely, M/s KECML. The shareholding of
                     EMTA in the JVC was to the extent of 76 per cent and
                     that of KPCL was 24 per cent. In the JVA, it was agreed
                     that there would be five directors from each of the two
                     companies and the nominee of KPCL would be the
                     Chairman of KECML who would have the right to cast
                     vote. The relevant clauses of the JVA referred to and
                     relied upon by the parties are extracted hereinbelow:
                         “AGREEMENT ON CAPTIVE COAL MINING
                          PROJECT THROUGH A JOINT VENTURE
                         xxxxx
                         “COAL” means washed coal with guaranteed
                         values as per article-6 clause 3 C and satisfies
                         quality parameter laid down in Annexure-1
                         attached to this agreement.
                         xxxxx


10   In short ‘JVA’
11   In short ‘KPCL’
12   In short ‘EMTA’
13   In short ‘BTPS’
14   In short ‘JVC’
1162                                          [2024] 8 S.C.R.

        Digital Supreme Court Reports


        “KPCL Coal Mines” means the coal mine(s)
        to be allotted to KPCL by Ministry of Coal,
        Government of India in which mining rights shall
        be given to the Company and which shall be
        developed/operated through the Company for
        captive use of KPCL.
        Xxxxx
        “GCV (ADB)” Gross Calorific value on ‘Air
        dried basis’ in kcal/kg determined through a
        Bomb Calorimeter as measured at BTPS as
        per IS 1350(part -I)
        xxxxx
        “D Grade Coal” means “Non-long flame coal”
        having Useful Heat Value(UHV) in the range of
        4200 to 4940 Kcal/Kg as per GOI notification.
        xxxxx
                           ARTICLE 2
             THE COMPANY AND ITS OBJECTIVES
        1.    The Parties of this agreement shall form and
              incorporate the Company as a Public Limited
              Company under the Companies Act, 1956
              having its registered office at Bangalore.
        2.    The Company shall be named KARNATAKA
              EMTA COAL MINES LIMITED; or in case
              such name is not available, any other
              name which may be mutually acceptable
              to the Parties.
        3.    The main object of the Company shall
              be to develop the captive coal mines
              of KPCL and produce coal from KPCL
              coal mines and to supply, transport and
              deliver such coal wholly and exclusively
              to KPCL.
        4.    For achieving the above main object, EMTA
              on behalf of the Company shall, inter-alia,
[2024] 8 S.C.R.                                                       1163

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                        take up the following activities with regard
                        to the KPCL Coal Mines:
                          (a)   survey and preparation of plans
                                for mining;
                          (b)   drilling and prospecting;
                          (c)   mining either in open cast process
                                or underground or both;
                          xxxxx
                          (e)   raising coal and stacking the same
                                on surface;
                          xxxxx
                        (g) Establishing coal washery of
                        adequate capacity at the pit head
                        and supply of coal of the required
                        specification to the power plant of KPCL
                        by Rail mode;
                        xxxxx
                        (m) preparation of plans, obtention of
                        approval of Site Clearance from Ministry
                        of Environment & Forest Govt. of India;
                        (n) preparation of Mining Plan and its
                        approval from Ministry of Coal, Govt. of
                        India;
                        xxxxx
                        (r) arrangement of approval for coal linkage
                        from KPCL Coal Mines to the power
                        stations of KPCL;
                        (s) arrangement of railway siding nearest
                        to the KPCL Coal Mines, and
                        xxxxx
                        (u) undertake all other allied jobs for coal
                        mining & washery operations.
1164                                         [2024] 8 S.C.R.

        Digital Supreme Court Reports


                         ARTICLE 5
               BUSINESS OF THE COMPANY
        To achieve the main objects of the Company as
        mentioned in clause 3 of Article 2, EMTA shall
        be responsible for development, operation of
        KPCL coal mines and delivery of coal to BTPS
        or any other thermal power station under KPCL,
        the terms and conditions of which shall be
        governed by an agreement to be executed by
        and between Company and EMTA.
        EMTA’s Scope of work shall comprise as follows:
        1.   Development and Operation of KPCL
             coal mines
        2.   Establishing coal washery at Pit head
        a)   EMTA shall ensure establishment of coal
             washery at the pit head so that the coal to
             be supplied by the company should meet
             the required specification of KPCL and
             KPCL is not liable to pay any additional
             charges towards washing of coal.
        b)   EMTA shall take all the clearances
             required for the setting up the coal
             washery from the concerned authorities
             and to properly dispose off the
             coal rejects to the satisfaction of
             environmental regulation.
        c)   EMTA shall keep liaison with the concerned
             railway authorities and organise railway
             siding at nearest distance from mines/
             washery area for movement of coal to
             BTPS by rail.
        3.   Arranging transportation of coal to
             BTPS
             xxxxx
[2024] 8 S.C.R.                                                        1165

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                    6.   Quantity
                         a.   The total quantity of coal required to
                              be supplied to BTPS is approximately
                              2 Million Tonnes (+)/(-) 10% per
                              annum.
                    7.   Quality
                         a)   The quality of coal shall be determined
                              by drawing coal samples from railway
                              wagons on receipt at KPCL power
                              plants before unloading.
                         b)   A third party agency shall be
                              appointed jointly by the parties of
                              the agreement for sampling and
                              analysis of coal received at BTPS
                              end. The third party agency shall
                              carry out the sampling and analysis
                              of coal in the presence of the
                              representative of the parties.…….
                         xxxxx
                         d)   An independent inspection agency
                              shall supervise and certify the quality
                              of coal received at BTPS and the
                              result of analysis certified by the
                              independent inspection agency as
                              per the procedure stated above shall
                              be binding to all concerned for all
                              commercial purposes.
                         xxxxx
                    9.   Delivery Period
                    a.   The delivery of coal to BTPS shall
                         commence one month prior to the
                         scheduled date of synchronisation of
                         first unit with coal at BTPS. The tentative
                         date of commissioning maybe taken as
                         Dec. 2005.
                         xxxxx
1166                                           [2024] 8 S.C.R.

        Digital Supreme Court Reports


        13. T h e c o m p a n y s h a l l p r o v i d e a n
            undertaking to the Ministry of Coal,
            Government of India that the coal
            produced from the KPCL Coal Mines
            shall be wholly and exclusively supplied,
            transported and delivered to KPCL.
                        ARTICLE – 6
                  COMMERCIAL TERMS
        Fuel supply agreement shall be executed
        between KPCL and Company to record the
        terms and conditions of coal supply from KPCL
        coal mines to KPCL which shall be governed
        by the following commercial terms :
        1.   Price
        a)   KPCL shall purchase the entire quantity of
             specified coal supplied to BTPS at a price
             of Rs. 1650.47 per tonne, the detailed
             break up of which is as per Annexure - II
             attached to this agreement
        xxxxx
        c)   The price shall be firm at the agreed
             price i.e. Rs.1650.47 per MT for a
             quantity of one million tonnes in the
             first year of BTPS - operation subject
             to price variation as per clause 3.D(b)-
             l(a) but limited to 50% increase in base
             price only. And 100% variation in statuary
             charges as per clause 3.D(a).
             xxxxx
        2.   Basis of payment and price adjustment
             KPCL shall pay the price of coal for the
             quantity and quality of coal on receipt at
             BTPS on rake to rake basis as detailed
             herein below:
[2024] 8 S.C.R.                                                     1167

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                        A)     QUANTITY …
                        B)     QUALITY …
                        C)     PRICE ADJUSTMENT
                        The size of coal, ash content, and GCV of
                        coal would be checked and compared with
                        the guaranteed values as indicated below:

                        (a)    GCV (ARB)    4500 in Kcal/KG
                        (b)    Permissible Max. 4500 Kcal/Kg &
                               variation   Min. 4000 Kcal/Kg.
                        (c)    Ash content 0 to 25 mm with
                               (ADB)       fines (upto-2 mm) not
                                           exceeding 20%
                        Suitable price adjustment would be carried
                        out be KPCL for variation in properties
                        compared to the guaranteed value as
                        indicated in the following paragraphs.
                        i)     ASH CONTENT(ADB)…
                        ii)    GCV (ARB)
                        a) No Pro rata price adjustment is allowed
                        for the GCV over and above 4500 Kcal/Kg.
                        b) In case the GCV is between 4200 to
                        4500 Kcal/Kg the price adjustment will be
                        on the Base Price on Pro rata basis.
                        c) In ease the GCV of the coal supplied
                        falls between 4000-4200 Kcal/Kg, the
                        price payable is restricted to 50% of the
                        Base Price.
                        d) In case the· GCV is below 4000 Kcal/
                        Kg KPCL shall not require to pay for
                        such supplies including freight and other
                        incidental charges.
                        xxxx
1168                                            [2024] 8 S.C.R.

        Digital Supreme Court Reports


             D)    Price Variation....
        4.   Penalty
        a)   The delivery period stipulated in Clause
             No 9 of Article 5 for the supply of coal shall
             be the essences of the contract. In the
             event of failure to commence the delivery
             of coal within the stipulated time specified
             in Clause 9 of Article 5 KPCL shall impose
             a penalty at a rate of l/2% of initial contract
             value of Rs.330.09 Crores i.e. Rs.l.65
             crores for every week’s delay subject to
             a maximum of 10% of the contract value
             of Rs.330.09 crores i.e. Rs.33.00 crores
        b)   In the event of delay in commencement
             of mining operation or washery or due
             to non-availability o(railway siding or for
             any other reason, Company shall arrange
             coal supply from any other source with the
             same specification as indicated under 3 c)
             of above….
        xxxxx
        5.   Fuel Supply Agreement shall be executed
             between KPCL and the company on
             the terms and conditions stipulated in
             the L.O.A. dated 8.7.2002 and relevant
             clauses as agreed upon between the
             parties under this agreement.
        xxxxx
                          ARTICLE 9
                OBLIGATIONS OF THE PARTIES
        The parties shall at their own cost and expense
        observe, undertake, comply with and perform
        in addition to and not in derogation of their
        obligations elsewhere set out in this Agreement,
        the following:
[2024] 8 S.C.R.                                                                 1169

            M/s Karnataka Emta Coal Mines Limited and Another v.
                       Central Bureau of Investigation

                         Obligation of KPCL
                         1.     It shall apply to the Central and the relevant
                                state governments for the allotment of the
                                KPCL coal mines.
                         2.     It shall purchase the Coal supplied to it as
                                per the terms agreed to in the Fuel Supply
                                Agreement.
                         Obligation of EMTA
                         1.     It shall arrange for the identification of
                                mining block(s) for present and future
                                requirement, the acquisition of private
                                land and allotment of vested lands by the
                                State Government required for mining
                                operation and KPCL will render assistance,
                                if required.
                         2.     It shall ensure supply of coal from KPCL
                                coal mines to KPCL power plants as per
                                the guaranteed values indicated in 3 c)
                                of Article 6 and specification stated in
                                Annexure - I attached to this agreement.
                         xxxx
                         6.     It shall establish Washery at the pit
                                head and get all clearances required for
                                setting up the washery to effect washing
                                of coal to meet the specification.”
                         xxxx
                                                        [emphasis added]
               3.1.3 Annexure–I appended to the aforesaid JVA specifies the
                     desired characteristics of the coal and contains a computed
                     statement relating to the expected coal quality with the
                     range for the maximum and minimum. The calorific value15




15   In short ‘C.V.’
1170                                                               [2024] 8 S.C.R.

                              Digital Supreme Court Reports


                         in Gross Calorific Value16 has been mentioned in the first
                         column under the head ‘Description’ and in the column of
                         “Expected Product Coal” that states as follows:
                         ‘DESIRED CHARACTERISTICS OF WCL COAL
                          EXPECTED COAL QUALITY WITH THE RANGE FOR MAXIMUM & MINIMUM
                          DESCRIPTION    UNITS      EXPECTED           RANGE
                                                 PRODUCT COAL
                                                                 MINUMUM MAXIMUM
                            Gross C.V. Kcal/K.gm       4995
                               xxxxxx
                           Size of Coal    mm                   0-25 mm (0-2 mm fines
                                                                not>20%

               3.1.4 Annexure–II that prescribes the price schedule for
                     mining, washing and delivery of washed coal to BTPS,
                     specifies amongst others, the total price of coal at the
                     pit head as follows:
                                        PRICE SCHEDULE
                                              FOR
                               MINING, WASHING AND DELIVERY OF
                                    WASHED COAL TO BTPS
                         Sl.     Particulars                         Price Per
                         No.                                         Metric tonne
                         1.      xxxxx
                                 f) Total price of coal at pit head 860.70
                                 (Railway Siding) (a+b+c+d-e)
                                 xxxx
                         7.      Railway Freight from captive mines 608.90
                                 to BTPS
                                 xxxx
                         9.      Landed cost per MT of washed       1650.47
                                 coal at BTPS including Sales Tax
       3.2. CORRESPONDENCE
               3.2.1 Vide letter dated 10th November, 2003, the Ministry of
                     Coal,17 Union of India allocated three coal blocks to



16   In short ‘G.C.V.’
17   In short ‘MoC’
[2024] 8 S.C.R.                                                              1171

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

                        KPCL for power generation for the proposed Thermal
                        Power Station at Bellary, Karnataka.18 As much emphasis
                        has been laid on the contents of the said letter by the
                        respondent-CBI, the same is reproduced hereinbelow
                        for ready reference :
                                      ‘No. 47011/1(1)/2002-CPAM/CA
                                          GOVERNMENT OF INDIA
                                              MINISTRY OF COAL
                                                       ….
                                   New Delhi, dated the 10th November, 2003
                        ‘To,
                        M/s. Karnataka Power Corporation Ltd.,
                        Shakti Bhavan No. 82,
                        Race Course Road,
                        Bangalore - 560 00l,
                        KARNATAKA.
                        ‘Subjet: Allocation of Kiloni, Manoradeep and
                        Baranj I-IV captive coal blocks for power
                        generation to M/s KPCL for their proposed 1000
                        MW(2x500 MW) TPS at Bellary, Karnataka.
                        ……….
                        The Screening Committee has agreed to identify
                        Baranj l-IV. Manoradeep and Kiloni under the
                        command area of WCL in the State of Maharashtra
                        to meet the requirement of coal for the exclusive
                        use in the proposed TPS at Bellary. Karnataka.
                        The allocation of these blocks are subject to the
                        following conditions :-
                         (i)    The coal mined from the blocks shall
                                exclusively be used by the company to
                                meet the requirement of coal in their
                                proposed TPS.


18   at Kiloni, Manoradeep and Beranj I to IV blocks
1172                                              [2024] 8 S.C.R.

               Digital Supreme Court Reports


        (ii)    Synchronization/commissioning of the end use
                plant should be December, 2006.
        (iii) The setting up of the proposed TPS should
              be completed by the Company before coal
              production starts from the captive mine.
              The bar chart for the coal production
              should be modified suitably.
        (iv) The coal mining will be done in accordance
             with the provisions of Mines & Minerals
             (Development & Regulation) Act, 1957 and
             Mineral Concession Rules, 1960 and subject
             to the provisions of other relevant statutes.
        (v)     Allocation of coal block may be cancelled
                in case of unsatisfactory progress of
                implementation of their proposed end use
                plant, development of captive coal mine or
                any of them.
        3. The allotment of the captive blocks will also be
        subject to the following conditions:
        (i)     The end use for which coal mined from
                the captive block should be utilized and
                all the conditions imposed by the Central
                Government mentioned in this letter conveying
                offer by the Screening Committee of captive
                block to M/s. Karnataka Power Corporation
                Ltd, may be clearly specified in the mining
                lease.
        (ii)    All the conditions imposed by the Central
                Government while conveying the previous
                approval to the State Government under
                Section 5(1) of the Mines and Minerals
                (Development & Regulation) Act, 1957 for
                grant of mining lease in favour of captive
                mining party should clearly form part of the
                lease deed to be executed between the
                concerned State Government and the party.
[2024] 8 S.C.R.                                                         1173

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                    (iii) In case the captive block has been offered
                          for washing-cum-end use, the deed must
                          clearly specify that the beneficiated coal
                          from the washery will exclusively be used
                          for the end use (power generation) as
                          approved by the Central Government and
                          not for commerce or otherwise. Tailings,
                          middlings or rejects, as the case may be,
                          shall be used for captive consumption
                          only by the applicant as approved by the
                          Central Government.
                    (iv) The allocattee would furnish to this
                         Ministry detailed plan for disposal of
                         unusable containing carbon materials
                         obtained during the process of mining or
                         any process thereafter including washing
                         etc. so as to avoid any need for disposal of
                         the same through sale etc. at a later stage,
                         within 30 days of receipt of this letter or
                         submission of mining plan whichever is
                         earlier.
                    (v) No coal shall be sold, delivered, transferred
                        or disposed of except for the stated captive
                        mining purpose (power generation) except
                        with the previous approval of the Central
                        Government in writing.
                    (vi) There should be complete synchronization
                         between the captive coal mining operations
                         and the development of end-use (power
                         generation) plant so that no situation arises
                         where the company is left with coal extracted
                         from the captive block when the end-use plant
                         is yet to be operational.
                    (vii) Approval of mining plan shall be considered
                          only after financial closure for the end use
                          project is achieved.
                    (viii) Existing coal linkage from CIL/SCCL, would
                           not be disturbed in any way with the coal
1174                                                                  [2024] 8 S.C.R.

                                Digital Supreme Court Reports


                                 mined from the allocated blocks. The coal
                                 linkage of 2.5 mtpa provided for the TPS
                                 from MCL shall continue.
                         (ix) Further, detailed exploration of the block, if
                              required, shall be carried out by CMPDIL or
                              under its direct supervision, on payment basis
                              by the applicant.
                         (x)     Violation of any of the conditions will render
                                 the allocation of the block/ grant of the lease
                                 as the case may be liable for cancellation.
                                 4. The progress in the end use project and the
                                 development of the allocated blocks should
                                 be reported to this Ministry every 3 months
                                 from date of issuance of this letter.
                                 5. The company may approach CIL for more
                                 detailed information, geological report etc.
                                 and contract the State Government authorities
                                 concerned for completing the necessary
                                 formalities for attaining mining lease rights and
                                 related matters. The company will be required
                                 to apply for mining lease within a period of
                                 six months. The arrangement of transport of
                                 coal, if any, etc. will have to be worked out by
                                 the company in consultation with the Ministry
                                 of Railways/Ministry of Surface Transport
                                 depending on the mode of transport.
                                                                 Yours faithfully,
                                                                      (S. Gulati)
                                                                        Director”
                                                            (emphasis added)
              3.2.2. On 16 April, 2004, the Ministry of Coal and Mines issued
                                  th

                     a Gazette Notification under Section 3(3)(a)(III)(4) of the
                     Coal Mines (Nationalization) Act, 197319 stating as below:


19   For short ‘1973 Coal Act
[2024] 8 S.C.R.                                                           1175

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

                              “MINISTRY OF COAL AND MINES
                                     (Department of Coal)
                                       NOTIFICATION
                                         New Delhi, the 16th July, 2004
                       S.O. 824(E) - In exercise of the powers conferred
                       by item(4) of subclause (Ill) of clause (a) of
                       Sub-section (3) of Section 3 of the Coal Mines
                       (Nationalisation) Act, 1973 (26 of 1973) the
                       Central Government hereby specifies as an end
                       use the supply of coal from the coal mines of
                       Kiloni, Manoradeep and Baranj I-IV blocks by the
                       Karnataka EMTA Coal Mines Limited on an exclusive
                       basis to the Karnataka Power Corporation Limited
                       for generation of thermal power in their proposed
                       1000 MW (2 x 500 MW) TPS at Ballary, Karnataka
                       subject to condition that the Karnataka Power
                       Corporation Limited holds at least 26 per cent of
                       voting equity share capital of the Karnataka EMTA
                       Coal Mines Limited at all times.
                                              [F.No. 13016/33/2003-CA]
                                                APVN Sarma, Jt. Secy.”
              3.2.3 On 08th December, 2004, the MoC, Government of India
                    issued a letter to KECML approving the Mining Plan
                    submitted by it for the Baranj Open Pit Project under
                    Section 5(2)(b) of the Mines and Mineral (Development &
                    Regulation) Act, 195720. The appellants herein have taken
                    a plea that the Mining Plan did not contain any provision
                    contrary to the JVA with respect to the rejects and what
                    KECML was required to do to dispose off the rejects,
                    was stipulated under Clause 5(2)(b) of the JVA which
                    required it to dispose off the rejects in an environment
                    friendly manner. It was submitted that there was no clause
                    in the Mining Plan that ran contrary to the JVA. The said
                    plea has however been disputed by the respondent-CBI.


20   For short ‘MMDR Act’
1176                                                            [2024] 8 S.C.R.

                            Digital Supreme Court Reports


      3.3 FUEL SUPPLY AGREEMENT
              3.3.1 Article 6 of the JVA stipulated execution of an Agreement
                    between KPCL and EMTA for supply of washed coal,
                    described as the ‘Fuel Supply Agreement21. The FSA
                    was executed on 09th May, 2007 and its relevant clauses
                    are as below:
                                 FUEL SUPPLY AGREEMENT
                       ‘THIS AGREEMENT made this ninth day of May two
                       thousand seven between KARNATAKA EMTA COAL
                       MINES LIMITED, …… called the “Supplier”…….of
                       the First Part and
                       KARNATAKA POWER CORPORATION LIMITED,
                       …. called the “Purchaser’….of the Second Part.
                                 WITNESSETH AS FOLLOWS
                       a)    WHEREAS Purchaser inter alia is engaged in
                             the business of generating power through its
                             various thermal, hydel, wind power stations
                             and is taking up a new thermal power plant
                             named as Bellary Thermal Power Station
                             (hereinafter referred to as BTPS), with an
                             initial capacity of 500 MW likely date of
                             commissioning is July, 2007.
                       b)    AND WHEREAS the annual requirement of
                             coal at BTPS will be approximately 2 million
                             tonnes.
                       c)    AND WHEREAS pursuant to the policy of
                             Govt. of India of leasing out coal mines to
                             power generating agencies for use as captive
                             coalmine(s) for their own consumption, the
                             Purchaser has been allocated mining block(s)
                             identified as Baranj I-IV, Manoradeep & Kiloni
                             vide allotment Letter No.47011/1(1)12002-
                             CPAM/CA dated 10.11.2003 . The Purchaser
                             has assigned and entrusted the responsibility


21   For short ‘FSA’
[2024] 8 S.C.R.                                                     1177

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                     to develop and operate the said coal mines to
                     the Supplier. For this purpose, the Purchaser
                     has entered into a Joint Venture Agreement
                     dated 13.9.2002 with, M/s. Eastern Minerals &
                     Trading Agency (in short EMTA hereinafter),
                     to form a joint venture company (hereinafter’
                     called the “Supplier”) for development and
                     operation of such coal) mines. The entire
                     amount of coal produced from such coal
                     mines shall be sold, transported and
                     delivered by the Supplier exclusively to the
                     Purchaser for use at BTPS in accordance
                     with the provisions of this Agreement.
                     xxxxx
                                   ARTICLE 1
                                 DEFINITIONS
                     xxxxx
                     “Coal” means washed coal with guaranteed
                     values as per Article-6 and satisfies quality
                     parameter laid down in Annexure -I attached
                     to this agreement.
                     xxxxx
                     “GCV (ADB)” means Gross Calorific value
                     on air dried basis in Kcal/Kg determined
                     through a Bomb Calorimeter as measured
                     at BTPS as per IS 1350 (Part- II).
                     xxxxx
                     “Joint Venture Agreement’’ means the
                     agreement dated 13.09.2002 entered into
                     between the Purchaser and M/s. Eastern
                     Minerals & Trading Agency to form a joint
                     venture company.
                     xxxxx
                     “Specified Coal” means washed coal as
                     defined in the Schedule of Specification
                     (Annexure I) of this Agreement.
                     xxxxx
1178                                               [2024] 8 S.C.R.

               Digital Supreme Court Reports


                             ARTICLE 4
                     CONDITIONS PRECEDENT
        4.1 The respective obligations of the Parties
            under this Agreement shall be subject to the
            satisfaction in full of each of the following
            conditions precedent prior to Commencement
            Date:
        i)      The Purchaser has assigned the mining rights
                in favour of the Supplier
        ii)     The Supplier has obtained all the necessary
                clearances and approvals required from the
                concerned authorities regarding operation of
                the Designated Coal Mines and submitted a
                copy of same to the Purchaser.
        iii)    The Supplier has registered this Agreement
                with the relevant authority at the time and
                in the manner stipulated in the Monopolies
                and Restrictive Trade Practices Act, 1969 as
                amended from time to time, to the extent the
                provisions are required to be registered.
                xxxxx
                             ARTICLE 5
                        QUANTITY AND QUALITY
        5.1 QUANTITY
        The Supplier shall supply and the Purchaser shall
        take coal in quantities of 2 Million Tonnes (+)/(-) 10%
        per annum. The quantity may increase depending
        on requirement of the Purchaser.……
        5.2 QUANTITY
        5.2.1 The Supplier shall ensure that it shall
        supply the Washed Coal with guaranteed
        value as per Article – 6 and satisfies quality
        parameter laid down in Annexure-I attached to
        this agreement to the Delivery Points without
        any interruption and shall maintain quality of
[2024] 8 S.C.R.                                                            1179

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                    supply as required. The following procedure is
                    indicated in respect of Joint Sampling.
                    a)   third party agency shall be appointed
                         jointly by the parties of the agreement for
                         sampling and analysis of coal received at
                         BTPS end….
                    b)   The third party agency shall be required to
                         undertake sampling and analysis of coal as
                         per the provision of ISI/ BIS or mutually agreed
                         procedure.
                    c)   The payment to the third party agency shall
                         be borne by the supplier.
                    d)   In the absence of certification by the
                         independent Inspection agency for any rake,
                         KPCL is not liable for payment for such rake.
                    5.2.2 The Supplier shall take all reasonable
                    steps to ensure that shalesIstones are removed
                    from the coal and no lumpy and/ or oversized
                    coal is supplied and the quality of coal shall
                    fall within the parameters indicated in the
                    Annexure - I. The methodology for verifying the
                    incidence of stonesIshales shall be mutually agreed
                    to between the Purchaser and the Supplier. The
                    size of coal shall be less than 25 mm (0-2 mm
                    fine not >20%).
                    xxxxx
                                       ARTICLE 6
                             CONTRACT PRICE OF COAL
                    6.1 The Purchaser shall purchase the entire quantity
                    of Specified Coal supplied to it at the commercial
                    terms and conditions stated herein below:
                    6.1.1 Price
                    a)   Purchaser shall purchase the entire quantity
                         of specified coal supplied to BTPS at a price
                         of Rs. l 650.47 per tonne, the detailed break
1180                                               [2024] 8 S.C.R.

              Digital Supreme Court Reports


               up of which is as per Annexure - II attached
               to this agreement.
        xxxxx
        6.1.3 Basis of payment and price adjustment
        xxxxx
        C) PRICE ADJUSTMENT
        The size of coal, ash content and GCV of coal would
        be checked and compared with the guaranteed
        values as indicated below:
        (a)     GCV (ARB)             4500 in Kcal/KG
        (b)     Permissible variation max. 4500 Kcal/Kg.&
        (c)     Ash content           32% maximum
        (d)     Size of coal          0 to 25 mm with fines
                                      (upto-2mm) not exceeding
                                      20%
        (e)     Total moisture       6% minimum; 15 maximum
        Suitable price adjustment would be carried out by
        Purchaser for variation in properties compared to
        the guaranteed value as indicated in the following
        paragraphs.
        xxxxx
        ii) GCV (ARB)
        a)     No Pro rata price adjustment is allowed for the
               OCV over and above 4500 Kcal/kg.
        b)     In case the GCV is between 4200 to 4500
               Kcal/Kg the price adjustment will be on the
               Base Price on Pro rata basis.
        c)     In case the GCV of the coal supplied falls
               between 4000-4200 Kcal/Kg, the price
               payable is restricted to 50% of the Base Price.
        d)     In case the GCV is below 4000 Kcal/Kg
               Purchaser shall not be required to pay for such
               supplies including freight and other incidental
               charges. The coal supplied having GCV of
               below 4000 Kcal/Kg will be consumed.
[2024] 8 S.C.R.                                                          1181

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                    Adjusted rate per Mt. is calculated as per formula
                    defined in Annexure-III
                    iii)    The size of coal shall not exceed 0 to 25mm
                            with fines (0-2 mm) not exceeding 20%.....
                    xxxxx
                                         ARTICLE 8
                           SAMPLING OF COAL AND ANALYSIS OF
                                       QUALITY
                    8.1 The quality of coal shall be determined by
                    drawing coal samples from railway wagons on
                    receipt at KPCL power plants before unloading.
                    8.2 A third party agency shall be appointed
                    jointly by the parties of the agreement for
                    sampling and analysis of coal received at BTPS
                    end. The third party agency shall carry out the
                    sampling and analysis of coal in the presence
                    of the representative of the parties.
                    8.3 The third party agency shall be required to
                    undertake sampling and analysis of coal as per the
                    provision of ISIIBIS or mutually agreed procedure.
                    8.4 The payment to the third party agency shall
                    be borne by the Supplier.
                    xxxxx
                                        ARTICLE 10
                                          PENALTY
                    10.1 The Supplier has agreed to commence
                    supply of coal to BTPS on commissioning which
                    has been rescheduled July 2007.
                    10.2 The delivery period stipulated in 10.1
                    above for the supply of coal as envisaged in
                    Article 5 shall be the essence of the contract.
                    In the event of failure to commence the delivery
                    of coal within the stipulated time specified above,
                    Purchaser shall impose a penalty at a rate of
1182                                                           [2024] 8 S.C.R.

                              Digital Supreme Court Reports


                        l/2% of initial contract value of Rs.330.09 crores
                        i.e. Rs 1.65 crores for every week’s delay subject
                        to a maximum of 10% of the contract value of
                        Rs.330.09 crores i.e. Rs.33.00 crores.
                                                       (emphasis added)
              3.3.2 In terms of Articles 2 and 5 of the FSA, a Tripartite
                    Agreement was executed between KECML, KPCL and
                    M/s SGS India Private Limited22 on 20th June, 2008.
                    M/s SGS was appointed as a third-party agency for
                    purposes of sampling and analysis of the coal to be
                    received at BTPS.
              3.3.3 For the sake of completion of narration, it may be
                    noted here that although the MoC had approved the
                    Mining Plan submitted by KECML on 08th December,
                    2004 and the FSA referred to above was executed on
                    09th May, 2007, the actual mining and coal production
                    could be commenced by KECML only in September,
                    2008 on account of the litigation initiated by M/s Central
                    India Power Company23 against the MoC in relation to
                    the coal block allocated to KPCL. In July, 2003 CIPCO
                    filed a writ petition24 before the Nagpur Bench of the
                    Bombay High Court seeking reallocation of coal blocks
                    allocated to KPCL. On 21st May, 2006, a status quo
                    order was passed by the High Court in the said petition
                    and KECML and KPCL were also made parties. The
                    said petition was finally dismissed by the High Court on
                    10th August, 2006 which dismissal order was upheld by
                    this Court on 05th January, 2007. Due to the status quo
                    order operating in all this duration, the coal production
                    could commence at site only in September, 2008 and
                    washed coal was supplied by KECML to the BTPS w.e.f.
                    December, 2008. Due to non-supply of washed coal by
                    KPCL as stipulated in Article 6(4) of the JVA and Article
                    10 of the FSA, KPCL imposed penalties on KECML for
                    the delay.


22   In short ‘SGS’
23   Hereinafter referred to as ‘CIPCO’
24   Writ Petition No. 2923 of 2003
[2024] 8 S.C.R.                                                            1183

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

      3.4 MEMORANDUM OF UNDERSTANDING
              3.4.1 Since Article 5(2) of the JVA required the appellants to
                    establish a coal washery at the pithead to supply coal of
                    the required specification for the consumption of BTPS
                    and there were several layers of clearances required from
                    the authorities to establish the washery at the pithead,
                    it is the stand of the appellants that KECML entered
                    into a Memorandum of Understanding25 with M/s Gupta
                    Coalfields and Washeries Limited26 for washing of the
                    mined coal, transportation of raw coal, transportation of
                    washed coal from the washery to Majri Railway siding of
                    KECML and loading into the railway wagons for onward
                    despatch to BTPS. For the said purpose, GCWL agreed
                    to dedicate its Majri washery to KECML. Following are
                    the relevant terms of the aforesaid MoU:
                              “MEMORANDUM OF UNDERSTANDING’
                        “This MEMORANDUM OF UNDERSTANDING
                        is made and executed on this 20 th May of
                        December, 2008
                        BETWEEN
                        KARNATKA EMTA COAL MNINES LIMITED,
                        ……. through its Director, Shri Bikash Mukherjee
                        herein after referred as ‘KECML’, …… assigns of
                        the FIRST PART.
                        AND
                        GUPTA COALFILEDS & WASHERIES LTD., ……
                        through its Managing Director, Shri Padmesh Gupta
                        ……. assigns of the SECOND PART
                        xxxxx
                        NOW BOTH THE PARTIES HAVE AGREED TO
                        SIGN AN MOU TO UNDERTAKE THE ABOVE
                        ACTIVITIES WITHNESSETH AS UNDER –


25   For short ‘MoU’
26   Hereinafter referred to as ‘GCWL’
1184                                             [2024] 8 S.C.R.

             Digital Supreme Court Reports


        1.    KECML has entered into a Coal Purchase
              Agreement with KPCL dated 9th May, 2007,
              whereby KECML shall require to supply
              coal from the above designated coal mines
              with the following parameters

                a)    GCV (ARB)       4500 Kcal/Kg
                b)    Permissible     Max 4500 Kcal/Kg
                      variation       & Min 4000 Kcal/Kg
                c)    Size            0-50 mm with fines
                                      (upto -2 mm) not
                                      exceeding 20%
                d)    Total moisture 6% minimum,
                                     15% maximum
             Suitable price adjustment (CIFD BTPS basis)
             would be earned out for variation in properties
             compared to the guaranteed values as follows
             xxxxx
             It has been agreed by the parties hereto that
             the above parameters shall be maintained by
             GCWL for onward supply of coal to BTPS of
             KPCL by KECML
        2.    KECML has agreed to provide minimum 2
              mtpa (Min 8000 tonnes on daily average basis)
              raw coal to Majri washery of GCWL from their
              Raw Coal Dump Yard. It shall be GCWL’s
              responsibility to arrange/transport Raw Coal
              from the mines to MAJRI washery process
              the coal to achieve agreed specifications of
              the washed coal, transportation of washed
              coal to Majri railway siding to load minimum
              two rakes daily, supervise the loading of
              washed coal, onward delivery at BTPS
              power plant and co-ordination.
              xxxxx
        4.    GCWL has agreed to deliver washed coal of
              following specifications –
[2024] 8 S.C.R.                                                          1185

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation


                         Ash (ABD)            Less than 32 %
                         GCV (ARB)            4500 Kcal/Kg
                         Size                 0-5 mm



                    5.   Yield Parameters GCWL shall ensure,
                         broadly, of 90% if the ash content of the
                         raw coal is 35% to 36% and in the event
                         ash content of the raw coal is found to be
                         40%, the yield shall be 80%. However, after
                         analysis of the full seam of coal available
                         from the mine the yield percentage will be
                         settled on suitable terms.
                         xxxxx
                    7.   KECML shall pay Rs. 90/- Per MT (excluding
                         all taxes as applicable) of raw coal towards
                         washing charges including charges for
                         loading washed coal to dumpers for
                         transportation to railway siding. All taxes
                         and duties are applicable shall be reimbursed
                         by KECML at actual. The above charges will
                         remain firm for 3 years ….
                    8.   It will be the responsibility of GCWL to
                         transport raw coal from mines to washery
                         and washed coal from washery to KECML
                         siding and supervise the loading onto
                         railway wagons. The transportation rates
                         shall be decided mutually by both the parties
                         which shall be reimbursed by KECML at actual
                         KECML shall place indents with railways and
                         make rail freight payments etc, as per RR on
                         actual
                         xxxxx
                    12. That the rejects shall be the joint property of
                        KECML and GCWL and it shall be disposed
1186                                                    [2024] 8 S.C.R.

                  Digital Supreme Court Reports


                    off/sold jointly at mutually agreed terms,
                    subject to compliance of rules/ regulations/
                    guidelines of Ministry of Coal, Government
                    of India, if applicable.
                    xxxxx”
        3.4.2 The appellants have stated that the draft MoU was sent
              to KPCL for its approval by Mr. Murlidhar Rao, the then
              Director (Technical) of KPCL and Director of KECML and
              after deliberations between 18th December, 2008 and
              12th January, 2009, the same was finally approved and
              ratified by the Board of KECML on 13th January, 2009. In
              the meeting of the Board of Directors of KECML held on
              13th January, 2009, those who had participated included
              Mr. S.M Jaamdar, the then Managing Director of KPCL
              and Chairman of KECML, Mr. R. Balasubramanian, the
              then Executive Director and Company Secretary of KPCL
              and Director of KECML, Mr. D.C. Sreedhar, the then
              Director (Finance) of KPCL and Director of KECML, Mr.
              U.K. Upadhyaya, Chairman and Managing Director of
              EMTA and former MD of KECML (appellant No. 2 in the
              appeals). In the Meeting held on 23rd February, 2010, the
              Board of Directors of KECML subsequently concluded
              that washing of raw coal was necessary since a specific
              grade of coal was required by the BTPS for generation
              of power and therefore, washed coal should continue
              to be supplied on the same basis. The appellants have
              also pointed out that GCWL was known to KPCL that
              had earlier entered into an agreement with GCWL along
              with two other washery operators for washing of coal
              mined by Western Coalfields Limited. However, the
              respondent-CBI has questioned the execution of the
              MoU between KECML and GCWL, in particular, Clause
              12 thereof.
    3.5 WASHABILITY REPORT OF THE CENTRAL INSTITUTE OF
        MINING AND FUEL RESEARCH, NAGPUR
        3.5.1 In the year 2009, to check the statistics of the coal mine,
              the appellants approached a Government Laboratory,
[2024] 8 S.C.R.                                                              1187

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

                        namely, Central Institute of Mining and Fuel Research27
                        for testing of the Integrated Baranj Open Cast Mines28.
                        The team of officers from CIMFR visited the site, collected
                        100 MT of coal for testing and furnished a Detailed
                        Washability Report. The report states that the rejects did
                        not contain any useful c.v. as the GCV of the rejects was
                        1094 Kcal/Kg and the useful heat value was negative.
      3.6 REVISED MINING PLAN
              3.6.1 After the mining continued for about two years in terms
                    of the original Mining Plan submitted in the year 2004,
                    KPCL decided to increase the capacity of BTPS from 2.5
                    Mty to 5 Mty. As a result, the appellants were required to
                    prepare a revised Mining Plan for supplying the increased
                    mining demands. On 20th December, 2010, the appellants
                    addressed a letter to the MoC for seeking approval of the
                    revised Mining Plan. At that stage, a new technology for
                    utilization of the rejects for its carbon value was introduced,
                    described as the Fluidised Bed Combustion29. The letter
                    issued by the appellants to the MoC mentioned that the
                    rejects generated could be gainfully utilized for its carbon
                    content by generating power through FBC/CFBC power
                    plants of appropriate capacity. It is not in dispute that
                    the new technology of FBC could have been put to use
                    only when a plant in respect of the same was set up for
                    which several approvals would be required from various
                    departments besides the process of acquiring land for
                    setting up the plant spreading over four to five years, as a
                    power plant could not be installed within the mining lease
                    area. The appellants have pleaded that KPCL could not
                    have started using the rejects immediately upon receiving
                    approval of the revised Mining Plan and that the rejects
                    having optimum useful heat value/GCV i.e. 2500 Kcal/
                    kg, could have been used only by applying the FBC
                    technology after such a facility was set up.



27   In short ‘CIMFR’
28   In short ‘IBOCM’
29   For short FBC.
1188                                                        [2024] 8 S.C.R.

                          Digital Supreme Court Reports


             3.6.2 Vide letter dated 24th August, 2011, the MoC approved
                   the revised Mining Plan submitted by KECML whereafter
                   the process of obtaining preliminary approvals including
                   environmental clearance from the Ministry of Environment,
                   Forest and Climate Change, Government of India30 for
                   the enhanced capacity of 5 MTPA coal from 2.5 MTPA
                   was initiated. While the Terms of Reference was granted
                   by the MoEF&CC, the mandatory public hearing required
                   to obtain environment clearance could not be conducted
                   since this Court passed an order in the year 2014
                   deallocating all captive coal blocks. Before that, due to
                   disputes that had arisen between KECML and GCWL,
                   washing of coal was stopped at the washery of GCWL
                   w.e.f. 22nd May, 2012.
      3.7 INFORMATION SUBMITTED BY KECML TO THE COAL
          CONTROLLER
             3.7.1 On 14th December, 2012, the Office of the Coal Controller
                   that falls under the MoC called upon the KECML to
                   furnish details in terms of the prescribed formats in
                   respect of the production, stock, despatch of coal to
                   the washery etc. Vide letter dated 16th January, 2013,
                   KECML furnished the detailed data as per the prescribed
                   format. The said letter stated that from December, 2008
                   to December, 2012, approximately 3,61,000 MT of rejects
                   was generated at the washery; that the ash content of
                   the raw coal varied from 35 per cent to 37 per cent and
                   the content of the washed coal varied from 32 per cent
                   to 34 per cent; that the yield of the washery was about
                   95 per cent to 96 per cent and the residual 4 per cent
                   of the raw coal were rejects whose ash content was
                   over 90 per cent and was therefore not marketable. It
                   was further stated that the quality of the rejects was
                   so poor that no records were maintained regarding its
                   utilization. However, the rejects were used to fill up low
                   land area of siding and road between coal blocks to the
                   washery and for pit dumping near the washery.


30   In short ‘MoEF&CC’
[2024] 8 S.C.R.                                                                                1189

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

             3.7.2 To substantiate the statement made that the yield of the
                   washery was 95 to 96 per cent, the appellants relied
                   on the Washability Report prepared by CIMFR, Nagpur
                   unit dated 01st August, 2009 which records that IBOCM
                   coal is amenable to wash with yield varying from 90 to
                   98 per cent at the desired ash level of 32 per cent. The
                   Report has recorded that the GCV of the mined coal fit
                   for transporting to BPTS is 4464 Kcal/kg and that of the
                   rejects is 1094 Kcal/kg. The data prepared in a format
                   and submitted in a tabulated format by KECML to the
                   Coal Controller for the period between the year 2008-09
                   and 2012-13 is extracted below:
               Sl.   Year    Production   QTY OF COAL   QTY OF COAL    WASHED     REJECTS    REJECTS
               No.                         DIRECTYLY    DESPATCHED      COAL     PRODUCED   CONSUMED
                                          DESPTACHED    TO WASHERY    PRODUCED              (APPROX.)
                                           TO SIDING
                1        2       3              4            5           6           7          8
                1    2008     990839          7744         90436       860367      40069      30000
                       09
                2    2009     2252358          0          2216334     21177107     98627      70000
                       10
                3    2010     2274995          0          2368455      2263059    105396      70000
                        11
                4    2011     2189869          0          2205395      2108000     97395      50000
                       12
                5    2012     1832770       1606343       225056       205200      19856      20000
                       13
                  Total       9539831       1614087       7915676      7554333    361343     240000

                      Ash % of Raw coal varies from 35% to 37%
                      Ash % of wash coal varies from 32% to 34%
                      % age of yield of washed coal varies from 95-96%
                      7915676 X (35+37)/2 = 7554333 X (32+34)/2 + 361343 X (A)
                      where A= Ash% of Rejects,
                      Hence A = (284964336 - 249292989)/ 361343 = 98.7%
                      The quality of rejects is as good as stone and not saleable
             Pertinently, the data regarding despatch of coal for washing has
             been furnished only upto May, 2012 since a dispute had arisen
             between KECML and GCWL thereafter. The second last column
             mentions the total rejects produced at IBOCM as 3,61,343 MT31
             and the rejects consumed as 2,40,000 MT.


31   Metric Tonnes
1190                                                           [2024] 8 S.C.R.

                           Digital Supreme Court Reports


      3.8 AUDIT OBJECTIONS RAISED BY THE COMPTROLLER AND
          AUDITOR GENERAL32
              3.8.1 On 31 st October, 2013, the Office of the Principal
                    Accountant General (E&RSA), Karnataka raised an
                    audit inquiry on KPCL on the subject of non-utilization
                    of the washery rejects and the resultant undue benefit
                    of ₹ 53.37 crores to a private company. The audit inquiry
                    noted that KECML had engaged a third party agency
                    namely, GCWL through a MoU for washing of coal and
                    Clause 12 of the MoU stipulated that rejects should be
                    the joint property of KECML and GCWL which ought
                    to be disposed of/sold jointly at mutually agreed terms
                    subject to compliance of the relevant rules, regulations/
                    guidelines issued by the MoC, if applicable. It was
                    stated that KECML had executed the MoU with GCWL
                    to dispose off the rejects without the concurrence of
                    KPCL and KPCL did not demand the washery rejects
                    from KECML either for its captive consumption or for
                    its disposal. Further, it was stated that no coal could
                    be sold/delivered/disposed of except for captive mining
                    purpose, i.e., power generation and with the previous
                    written approval of the Central Government.
              3.8.2 The observations made by the CAG in Audit Inquiry
                    No. 18 are extracted below:
                       “We observed that
                       ¾    Depending on the type of coal being washed
                            and the requirement of the captive user, the
                            rejects and middlings are generated from
                            washery. A study report indicates that washing
                            of D-grade coal generates rejects and middling
                            of F and G-grade, and such low quality coal
                            was also being used in power generation.
                       ¾    The purpose of allocation of coal blocks
                            for captive use under section 3(3) of the
                            Coal Mines (Nationalisation) Act, 1973 is
                            not to enable free trading of coal by private


32   For short “CAG”
[2024] 8 S.C.R.                                                                                 1191

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                           companies. The basic concept of captive
                           mining permitted under the aforesaid Act is that
                           the coal obtained from a captive block shall be
                           used entirely and exclusively for the specified
                           and approved end use by the allocatee
                           Company and, therefore, the production of
                           surplus coal should not result in any undue
                           advantage to the captive block allocatee as
                           the coal block is allotted to them for use in
                           their end-use plant only and any additional
                           production from the block should be made
                           available to the Government for utilization.
                    ¾      While allocating the coal block in November
                           2003, the Government directed the Company to
                           use the rejects for its own captive consumption.
                    ¾      In reply to the clarification sought (October
                           2003) by the Ministry of Coal regarding detailed
                           plan about the use of middling, tailings and
                           rejects etc, the Company informed (October
                           2003) that the same was proposed to be used
                           for power generation with fluidized-bed boilers.
                    Thus, the inaction on the part of the Company
                    resulted in the KECML/EMTA disposing the coal
                    rejects without transferring the revenue to KPCL.
                    Considering the coal rejects as G-grade based on
                    GCV undue benefit afforded to the KECML/EMTA
                    worked out to Rs. 52.37 crore, as detailed below:
                        Year          Coal         Minimum       Average CIL      Loss (₹)
                                  produced at     quantity of      rate of G
                                  Baranj OCP    rejects as per    grade coal
                                  (in Tonnes)    MOU (10%)           (Rs.)
                      2008-09     990839.026      99083.903           590       58459502.53
                      2009-10     2252358.28      225235.83           620      139646213.05
                      2010-11     2274994.46      227499.45           650      147874639.58
                      2011-12       2188869        218886.9           650      142276485.00
                      2012-13       570869.3       57086.93           620       35393896.60
                    (up to June
                       2012)
                                                                               52,36,50,736.76

                    Facts and Figures may be confirmed”
1192                                                                                            [2024] 8 S.C.R.

                               Digital Supreme Court Reports


               3.8.3 Vide letter dated 17th December, 2013, KPCL submitted
                     the following reply to Audit Inquiry No. 18:
        “Sl.   Question                                            KPCL Reply
        No.
        1.     Audit Inquiry No. 18                              The Audit objection is raised as if the
               Sub: Non-utilisation of washery rejects by entire rejects have been appropriated
               the company and resultant undue benefit of by KECML and that the rejects have a
               Rs 52.37crores to private company.                market value of Rs. 52.37 crores. These
                                                                 are factually incorrect in view of the
               In November 2003, Government of India following : -
               allocated captive coal blocks in Wardha
               Valley region to the Company to develop it as a) The assessment of washery rejects
               source of supply to its thermal power plant al does not have any direct co-relation with
               Bellary. In accordance with the requirement the quantity of coal produced at Integrated
               of the Company, the JV Company (KECML) Baranj OCP, rather, the quantity sent
               engaged (December 2008) a third party agency, to washery and the quantity actually
               M/s Gupta Coalfields and Washeries Limited dispatched to the thermal power stations of
               (GCWL), Nagpur through a Memorandum of KPCL after the processing in the washery
               Understanding for washing of coal. Clause 12 are the two important quantities giving idea
               of the MOU stipulated that the rejects should of reject generation at the washery. We are
               be the joint property of KECML and GCWL furnishing below the year-wise quantity of
               and it should be disposed off/ sold jointly at coal sent to washery from Integrated Baranj
               mutually agreed terms, subject to compliance of OCP, the quantity of rejects generation
               rules/regulations/guidelines of Ministry of Coal, and the quantity of coal finally dispatched
               Government of India, if applicable.               to KPCL.
               The washing of coal was carried out till the end
               of June 2012 before it was discontinued due to
               dispute between the parties to the MOU.
               KECML entered into MOU with GCWL to
               dispose of the rejects without the concurrence
               of the Company. Despite the fact that the
               Company holds the right on the captive
               coal blocks, no provision was made in the
               FSA made by the Company with KECML for
               supply of rejects/middling. It did not demand
               the washery rejects from KECML either for
               its captive consumption or for its disposal by      Year      Coal     Minimum         Average Loss (Rs.)
               its own means with the approval of Central                    produced quantity        CIL rate
               Government.                                                   at Baranjof rejects      of G
                                                                             OCP (in  as per          grade
               The conditions of allocation inter-alia included              Tonnes)  MOU             coal
               that if the coal was being washed, tailings,                           (10%)           (Rs.)
               middling or rejects, as the case may be,            2008-09 990839.026 99083.903       590      58459502.53
               from washery should be used for captive             2009-10   2252358.28   225235.83   620      139646213.05
               consumption only by the Company as approved         2010-11   2274994.46   227499.45   650      147874639.58
               by the Central Government. Further, no coal         2011-12   2188869      218886.9    650      142276485.00
               shall be sold, delivered, transferred or disposed   2012-13   570869.3     57086.93    620      35393896.60
               of except for the stated captive mining purpose     (up to
               (power generation) and with the previous            May
               approval of the Central Government in writing.      2012)
                                                                                                               52,36,50,736.76
               We observed that:
               > Depending on the type of coal being               b) It may be noted that the said rejects
               washed and the requirement of the captive           are only Stones / Boulders not consistent
               user, the rejects and middling are generated        with the size of coal : ( - 25 mm) for which
               from washery. A study report indicates that         the boiler is designed, hardly have
[2024] 8 S.C.R.                                                                                            1193

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

          washing of D-grade coal generates rejects                    any calorific value. Therefore the said
          and middling of F and G-grade, and such                      rejects have been used for leveling,
          low quality coal was also being used in                      piling etc. towards facilitating Integrated
          power generation.                                            Baranj OCP.
          > The purpose of allocation of coal blocks for               c) The Audit comment is a generalized
          captive use under section 3(3) of the Coal Mines’            observation without any factual support
          (Nationalization) Act, 1973 is not to enable free            and as such cannot be concluded that
          trading of coal by private companies. The basic              the washery rejects irrespective of the
          concept of captive mining permitted under the                geological location of the source of coal
          aforesaid Act is that the coal obtained from                 would have Useful Heat Value (UHV) to
          a captive block shall be used entirely and                   cater to the generation requirement. In
          exclusively for the specified and approved end               fact, the rejects generated in the present
          use by the allocatee Company and, therefore,                 case are only shale and non- coal matter.
          the production, of surplus coal should not result            Hence the conclusion drawn by Audit
          in any undue advantage to the captive block                  that the rejects are G- grade is not only
          allocatee as the coal block is allotted to them              arbitrary but also not based on the ground
          for use in their end-use plant only and any                  geological realties.
          additional production from the block should be
                                                           Thus, the abandonment of rejects at
          made available to the Government for utilization.
                                                           the collieries end has been resorted
          While allocating the coal block in November to based on its utility, as otherwise its
          2003, the Government directed the Company to transportation would have imposed
          use the rejects for its own captive consumption. additional burden on the Company.
          > In reply to the clarification sought (October The abandonment of rejects is, therefore,
          2003) by the Ministry of Coal regarding detailed in order.
          plan about the use of middling, tailings and
          rejects, etc, the Company informed (October
          2003) that the same was proposed to be used
          for power generation with fluidized-bed boilers.
          Thus, the inaction on the part of the Company
          resulted in the KECML / EMTA disposing the
          coal rejects without transferring the revenue
          to KPCL Considering the coal rejects as
          G-grade base on GCV undue benefit afforded
          to the KECML / EMTA worked out to Rs.52.37
          crore, as detailed below.
           Year         Quantity        Quantity       Quantity of
                        sent to         of rejects     coal finally
                        Washery from    generation     dispatched to
                        integrated                     KPCL
                        Baranj OCP
           2008-09      9,31,195.026    98,940.003     8,08,871.000
           2009-10      22,16,334.815   71,891.838     21,68,827.000
           2010-11      23,68,121.815   1,24,137.309   22,12,460.790
           2011-12      23,68,121.995   33,081.099     21,63,569.650
           2012-13      2,25,035.600    34,978.967     2,11,206.350
           (up to
           June 2012)
                        79,46,082.736   3,63,023.216 75,63,934.800

     Though KPCL requested the CAG to drop the audit objection in
     view of its clarification, it is a matter of record that the CAG did not
     accept the explanation offered by KPCL. Instead, CAG observed in
     its Audit Report for the year ending March, 2013 that coal rejects
1194                                                          [2024] 8 S.C.R.

                           Digital Supreme Court Reports


      worth ₹52.37 crore had been misappropriated by KECML and GCWL
      on account of the inaction on the part of the KPCL.
      3.9 PRELIMINARY INQUIRY REGISTRED BY RESPONDENT-CBI
              3.9.1 On receiving the Report from the Office of the CAG,
                    KPCL dashed off a letter dated 31 st July, 2014 to
                    KECML seeking an account of the rejects generated
                    by washing of coal and demanded reimbursement of
                    the cost of the rejects. KECML responded vide letter
                    dated 14th August, 2014 reiterating therein that the
                    percentage of rejects generated at the washery were
                    only 4.39 per cent of the total coal produced at the
                    IBOCM and the said rejects did not possess any c.v.
                    having no carbon and only being stones/boulders.
                    Therefore, the same had been used at the site for
                    levelling, piling etc. for facilitation of smooth mining
                    operations at the IBOCM.
              3.9.2 In the meantime, based on a Source Information
                    Report33 pertaining to some irregularities committed in
                    the allocation of coal blocks under the ‘Government
                    Dispensation’ category, failure to follow the due procedure
                    resulting in large private companies having connived with
                    public servants and gaining undue benefit a Preliminary
                    Inquiry34 was registered by the Superintendent of Police,
                    CBI on 28th September, 2012. In all, three Preliminary
                    Inquiries were registered namely, PE 2, PE 4 and
                    PE 5. The FIR35 subject matter of the present appeal
                    was registered by the respondent-CBI on 13th March,
                    201336 under Section 120-B read with Sections 409 and
                    420, IPC and under Section 13(2) read with 13(1)(d)
                    of the PC Act alleging substantive offences against the
                    appellants and other co-accused. Following are the fourteen
                    persons/entities who have been arrayed as accused by
                    the respondent-CBI:



33   ‘SIR-03/12
34   PE 5/2012-BS&FC, Delhi Coal Block Cases
35   FIR No. RC: 220 2015 E 0002
[2024] 8 S.C.R.                                                                               1195

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation


                                               FUNCTIONARIES OF KPCL
                         A-1    SM Jaamdar, (Rtd IAS and the then Managing Director Karnataka
                                Power Corporation Limited “(KPCL”) and Chairman of Karnataka
                                EMTA Coal Mines Ltd (“KECML”)
                         A-2    Balasubramanium, then Executive Director and Company
                                Secretary, KPCL and Director KECML
                         A-3    Muralidhar Rao, Director (Technical) KPCL, Director – KECML
                         A-4    DC Sreedharan, Director (Technical) KPCL and Director KECML
                         A-5    H.N. Narayana Prasad, the then Director (Technical) KPCL, and
                                Former Director KECML
                                             FUNCTIONIARIES OF KECML
                         A-6    Ujjal Kumar Upadhyay, Chairman and MD EMTA Coal Ltd and
                                Managing Director of KECML
                         A-7    Bikash Mukherjee, Director EMTA and Former Director of KECML
                         A-8    Bishwanath Dutta, Director EMTA and Director KECML
                         A-9    Purajit Roy, Executive Director and CFO M/s EMTA Coal Ltd
                         A-10   Ashok Tooley, Director KECML
                                              FUNCTIONARIES OF GCWL
                         A-11   Padmesh Gupta, CMD Gupta Coal Washeries Limited
                                     CORPORATE ENTITIES & FUNCTIONARIES
                         A-12   Karnataka EMTA Coal Mines Ltd. (KECML)
                         A-13   M/s Eastern Minerals and Trading Agency (EMTA)
                         A-14   Gupta Coal Washeries Limited

              Though the appellants have asserted that the respondent-CBI
              has registered the complaint on coming across the Report of the
              CAG, the said submission has been refuted by the respondent-
              CBI who has pleaded that it had conducted an independent
              investigation after registering the PE which was followed by
              registering of the FIR.
      3.10 LITIGATION BETWEEN KPCL AND KECML
              3.10.1 Aggrieved by the letter dated 31st July, 2014 addressed
                     by KPCL to KECML, KECML filed two writ petitions37
                     before the High Court of Karnataka praying inter alia
                     for quashing of the letters dated 31st July, 2014 and
                     24 th December, 2014 issued by KPCL. In the writ



37   Writ Petition 2995 to 2996 of 2016 (GM-MMS) c/w Writ Petition Nos. 2997 to 2998 of 2016 (GM-MMS)
1196                                                                [2024] 8 S.C.R.

                             Digital Supreme Court Reports


                          petitions38 EMTA and KECML assailed a demand of
                          ₹ 52,37,00,000/- (Rupees Fifty two crore thirty seven lakh
                          only) raised by KPCL towards the value of the coal rejects,
                          as arbitrary. Challenge was also laid to the decision taken
                          by KPCL to deduct ₹ 90 (Rupees Ninety) per MT towards
                          non-washing of coal, in terms of its communications
                          dated 23rd November, 2013 and 29th January, 2014. Vide
                          Judgment dated 24th March, 2016 the Division Bench
                          of the High Court allowed both the writ petitions39 and
                          quashed the communications issued by KPCL to KECML.
                          Further, KPCL was restrained from initiating any demand
                          against KECML on the basis of the report of the CAG and
                          called upon to reimburse the amounts already deducted
                          by KPCL towards non-washing of coal.
              3.10.2 For the sake of completion of the narrative pertaining to the
                     aforesaid litigation, it is pertinent to note that the aforesaid
                     judgement dated 24th March, 2016, was challenged by
                     KPCL before this Court by preferring Petitions for Special
                     Leave to Appeal.40 Vide Judgment dated 20th May, 2022,
                     both the Civil Appeals41 were dismissed.
              3.10.3 On 31st July 2017, the respondent-CBI submitted a
                     request to the Ministry of Personnel Public Grievances
                     and Pension,42 Government of India for grant of sanction
                     to prosecute Mr. Yogendra Tripathi (IAS), Managing
                     Director, KPCL and Mr. R. Nagaraja, Director (Finance)
                     of KPCL and nominee Director on the Board of KECML
                     under Section 19 of the PC Act. However, the Board
                     of KPCL, which was the Sanctioning Authority, refused
                     sanction for prosecution of Mr. R. Nagaraja by passing
                     a detailed order.
              3.10.4 After examining the order passed by the Board of KPCL
                     refusing to grant sanction to prosecute Mr. R. Nagaraja,


38   Ibid
39   ibid
40   Petition for Special Leave to Appeal (C) No. 26367-26370/2016
41   Civil Appeal Nos. 5401-5404/2017
42   For short ‘MoPP&P’
[2024] 8 S.C.R.                                                              1197

            M/s Karnataka Emta Coal Mines Limited and Another v.
                       Central Bureau of Investigation

                         the Department of Personnel & Training,43 Government of
                         India addressed a letter dated 16th September, 2018 to the
                         respondent–CBI stating that the Competent Authority i.e.,
                         the Central Government had denied sanction for prosecution
                         of Mr. Yogendra Tripathi, the then Managing Director of
                         KPCL. It is a matter of record that the respondent–CBI
                         did not take any steps to challenge the decision taken by
                         the Sanctioning Authority and the Competent Authority
                         refusing permission to grant sanction for the prosecution
                         of Mr. R. Nagaraja and Mr. Yogendra Tripathi.
               3.10.5 The Charge-sheet was finally filed by the respondent–CBI
                      against 14 persons/entities alleging that they had illegally
                      disposed of the coal rejects in IBOCM. A Supplementary
                      Chargesheet was filed on 4th November, 2019. Out of
                      the two charges, one charge relating to allegations of
                      recovery of payment for washing charges was dropped
                      by the respondent-CBI.
               3.10.6 On 1st September, 2021, the appellants filed an application
                      before the learned Single Judge under Section 227 read
                      with Section 239 of the Criminal Procedure Code44 for
                      discharging them in the case. By the common impugned
                      order dated 24th December, 2021, the said application
                      was dismissed and charges were framed against them
                      on 3rd March, 2022, under Section 409 IPC and 120 (B)
                      r/w Section 13(1)(c), 13(1)(d) r/w Section 13(2) PC Act
                      i.e. resulting in filing of the present appeals.
       C.      SUBMISSIONS
4.     ARGUMENTS BY COUNSEL FOR THE APPELLANTS
       Following are the arguments advanced by Mr. Ranjit Kumar, learned
       Senior Advocate appearing for the appellant No.1 and Mr. Abhimanyu
       Bhandari, learned counsel appearing for the appellant No.2 :-
       4.1 That KPCL did not have any right over the rejects produced
           from the mine and therefore, cannot claim any entitlement



43   For short ‘DoPT’
44   In short ‘Cr.P.C’
1198                                                                  [2024] 8 S.C.R.

                            Digital Supreme Court Reports


              thereto. The terms and conditions stipulated in the JVA dated
              13th September, 2002, in particular Articles 5(1)(b), 5(2)(b),
              5(13) and 6(3)(c) and Annexure I, when read together, would
              demonstrate that the obligation cast on the KECML was limited
              to providing KPCL specified quality of “washing coal” containing
              a guaranteed value and having a specified heat value and
              KECML was only required to dispose off the rejects to avoid
              any environmental hazards.
      4.2 That the original Mining Plan which was submitted by KECML
          and was approved by the MoC in the year 2004, did not contain
          any specific provision relating to how the rejects were to be
          disposed off and nor did the allocation letter issued by the MoC
          to KPCL state anything in this regard. For this, reliance has been
          placed on the reply furnished by the Minister of State, MoC, in
          the Lok Sabha in response to an unstarred question seeking
          an answer from the Government of India as to whether it had
          framed any National Policy for exploitation of coal rejects. The
          reply furnished by the Minister was in the negative along with
          a clarification given that formulation of a policy of disposal of
          surplus coal, by-products and middling stock rejects from coal
          blocks was under the consideration of the Government.
      4.3 Citing Clauses 5.2 and 5.2.2 of the FSA dated 09th May,
          2007 and the definition clauses in respect of the expressions,
          “Purchaser” and “specified coal”, it has been urged that none of
          the clauses in the FSA have stated that KPCL would purchase
          or claim rights over the rejects and that KECML was to ensure
          that “shales/stones” are removed from the coal and the quality
          of coal meets the parameters indicated in Annexure I.
      4.4. To fortify the submission that KECML was only required to
           dispose off the coal rejects in an environment friendly manner
           and that KPCL would have no right over the rejects or claim
           any entitlement over them, reference has been made to the
           decision of the Division Bench of the Karnataka High Court
           in the case of KPCL v. Aryan Energy Private Limited45 and
           Others46 and the clause in the Agreement governing KPCL


45   In short ‘AEPL’
46   COMAP No. 12, 13, 14 and 15 and 2020 decided on 22nd July, 2021
[2024] 8 S.C.R.                                                         1199

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

              and AEPL to contend that it was similar to the present case
              inasmuch as like KECML, AEPL was also required to dispose
              off the rejects in a manner that would satisfy environmental
              regulations. In the above case the Karnataka High Court has
              held that the clauses of the Agreement between the parties
              appearing before it showed that coal rejects were the property
              of AEPL and KPCL had no claim over it and that the term
              regarding disposal of coal rejects was imposed by KPCL only
              to ensure compliance of the environmental regulations.
              4.4.1 Notably, the aforesaid judgement of the High Court
                    was challenged by KPCL before this Court by way of
                    petition for special leave to appeal47. The said petition
                    was disposed of by this Court on 26th April, 2024, noting
                    that during the pendency of the petitions, the parties had
                    settled their disputes amongst themselves and part of
                    the decretal amount deposited by KPCL to discharge its
                    liability towards supply of washed coal by AEPL along
                    with interest etc. was directed to be released in favour
                    of AEPL in terms of the Compromise Deed.
      4.5. That the Washability Report of CIMFR, Nagpur for the year 2009
           had stated that the rejects had a GCV of 1094 Kcal/kg and
           less and therefore, the same could not have been utilized in
           the BTPS. For the said reason, KECML had used the rejects
           for captive consumption of the mine i.e. for levelling, piling etc.
           The very same Report was also referred to by KPCL in its reply
           to the audit objections raised by CAG to state that no loss has
           been caused to KPCL since the rejects were in the nature of
           stones and boulders and did not have useful heat value.
      4.6. To substantiate their submission that the rejects did not have
           the requisite GCV for being utilized in the BTPS, learned
           counsel have quoted a Circular issued by the NITI Aayog in the
           year 2020 which states that coal rejects having GCV of 1500
           Kcal/kg are to be used in back filling of mines and can be used
           in construction of highways, roads etc. whereas rejects having
           GCV in the range of 1500 Kcal/kg to 2200 Kcal/Kg, can be
           used in FPC Boilers.


47   Petition for Special Leave to Appeal (Civil) No. 395-398 of 2022
1200                                                       [2024] 8 S.C.R.

                          Digital Supreme Court Reports


      4.7. That at the time of filing the chargesheet on 04th January, 2018,
           the respondent-CBI completely ignored the judgement dated
           24th March, 2016 passed by the Karnataka High Court in the
           writ petition filed by the appellants against KPCL wherein it has
           been clearly held that KPCL does not have any right over the
           rejects generated during the process of mining and resultantly,
           the demand letter dated 31th July, 2014, issued by KPCL was
           set aside. The said judgement has also been upheld by this
           Court vide judgement dated 20th May, 2022.
      4.8. That KPCL has been blowing hot and cold. First, it had filed
           objections to the quantification of coal rejects as recorded by
           the CAG in its Report but when its objections were rejected by
           the CAG, it changed its stand and proceeded to raise an illegal
           demand on the appellants on the basis of the very same CAG
           Report, which has been quashed by the High Court.
      4.9. That both, the Karnataka High Court and this Court having
           quashed the demands made by KPCL in respect of the value
           of rejects to the tune of ₹ 52 Crore, no case has been made out
           by the respondent-CBI to prosecute the appellants particularly
           when on the advice of the Central Vigilance Commission,48 the
           Central Government refused to grant sanction for the prosecution
           of Mr. Yogendra Tripathi (IAS), Managing Director, KPCL and
           Mr. R. Nagaraja, Director (Finance) of KPCL and nominee
           Director on the Board of KECML. A different treatment cannot
           be meted out to the appellants.
      4.10. That the respondent-CBI has solely relied on the Report of
            the CAG of 2013 to launch its prosecution in the year 2015.
            However, the Report of the CAG has not been approved by
            the Parliament in accordance with the procedure prescribed
            under Section 19(A) and other provisions of the Comptroller and
            Auditor General’s (Duties, Powers and Conditions of Service)
            Act, 197149 read with Articles 148 to 151 of the Constitution
            of India.



48   In short ‘CVC’
49   In short ‘CAG Act’
[2024] 8 S.C.R.                                                        1201

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

      4.11. That the analysis of the rejects and the manner in which loss
            was allegedly caused to KPCL, has primarily been arrived at by
            the respondent – CBI from the Report of the CAG and once this
            Court has held that the Report of CAG cannot be the basis for
            launching prosecution against the appellants, the entire basis
            of launching the prosecution is eroded.
      4.12. Stating that contrary to the prescribed procedure that
            contemplates that the Report of the CAG in relation to the
            accounts of a Government Company shall be submitted to the
            Government and the Central Government/State Government, as
            the case may be, shall place the said Report before each House
            of the Parliament/State Legislature and the Public Accounts
            Committee/the Joint Parliamentary Committee is required to
            scrutinize the said Report. In the instant case, the Report of
            the CAG has not been accepted either by the Public Accounts
            Committee or by the Committee of Public Undertakings or
            by the Joint Parliamentary Committee nor has it been tabled
            before each House of the Parliament. It is only when the
            Report is tabled in the Parliament and duly scrutinized and the
            Government offers its view on the Report, can it form the basis
            for initiating any action. Decisions in Centre for Public Interest
            Litigation v. Union of India,50 Arun Kumar Aggarwal v. Union
            of India51 and Pathan Mohammed Suleman Rehmatkhan v.
            State of Gujarat52 have been cited to bring home the argument
            that when the Report of the CAG is subject to scrutiny by the
            Public Accounts Committee/Joint Parliamentary Committee, it
            would not be proper to refer to its findings or the conclusions
            drawn therein.
      4.13. That the learned Special Judge, CBI has blindly accepted the
            charge levelled by the respondent-CBI quantifying the loss
            purportedly caused to KPCL on account of illegal sale of rejects
            at ₹49,03,54,159/- (Rupees Forty nine crore three lakh fifty four
            thousand one hundred and fifty nine only). The observations
            made in para 104 of the impugned judgement to the effect that


50   [2012] 3 SCR 147 : (2012) 3 SCC 1
51   [2013] 3 SCR 508 : (2013) 7 SCC 1
52   [2013] 12 SCR 446 : (2014) 4 SCC 156
1202                                                          [2024] 8 S.C.R.

                            Digital Supreme Court Reports


             the respondent-CBI has quantified the rejects on the basis of
             the documents of KECML and has calculated the loss on the
             basis of the rate of the lowest grade of coal prevailing at the
             relevant point of time is therefore, devoid of merits. Reliance
             has been placed on the information in the Coal Directory of
             India published by the MoC for the year 2010-2011 that has
             categorized coal and coke and clarified that w.e.f. January, 2011,
             by virtue of a notification issued by the MoC, there has been a
             switchover from the existing Useful Heat Value53 based system
             of grading and pricing of non-coking coal produced in India to
             fully variable GCV system.
             4.13.1. Under the JVA/FSA, KECML was required to supply
                     Grade ‘D’ coal to KPCL. As per the Coal Directory of
                     India, 2010-2011, Grade ‘D’ coal in terms of the old
                     grades of non-coking coal would be equivalent to Grade
                     ‘G-7’ and ‘G-8’ under the new grades of non-coking
                     coal. The GCV range in respect of Grade ‘G-7’ coal
                     has been fixed between 5201 Kcal/kg and 5500 Kcal/
                     kg and in respect of Grade ‘G-8’ coal, between 4901
                     Kcal/kg and 5200 Kcal/kg. In the instant case, even as
                     per the Report of the CIFMR, Nagpur, the coal rejects
                     were found to be below either of the aforesaid grades of
                     non-coking coal, having been pegged at a GCV of 1094
                     Kcal/kg. Therefore, it is contended that the chargesheet
                     filed by the respondent-CBI quantifying the loss suffered
                     by KPCL at ₹49,03,54,159/- (Rupees Forty nine crore
                     three lakh fifty four thousand one hundred and fifty nine
                     only), is without any basis and contrary to the records.
      4.14. That the Coal Controller did not raise any issue with regard to the
            disposal of the rejects and the respondent-CBI has neither made
            the Coal Controller a witness or an accused in the present case.
      4.15. The judgements in Radheshyam Kejriwal v. State of West
            Bengal and Another; 54 Ashoo Surendranath Tewari v.




53   In short UHV
54   [2011] 4 SCR 889 : (2011) 3 SCC 581
[2024] 8 S.C.R.                                                                 1203

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

              Deputy Superintendent of Police, EOW, CBI and Another;55
              J Sekar alias Sekar Reddy v. Directorate of Enforcement;56
              and Prem Raj v. Poonamma Menon & Another 57 have been
              cited to argue that it is settled law that where a party has been
              exonerated on merits in civil adjudication, criminal prosecution
              cannot be permitted to continue on the same set of facts and
              circumstances.
      4.16. That the respondent – CBI has failed to produce any document
            to demonstrate that the accused Nos.1 to 5 had made any
            demand for illegal gratification or there was acceptance of
            any such demand made. In the absence of proof of demand
            and acceptance of illegal gratification by the public servant, no
            offence is made out under Section 13(1)(d) of the PC Act. For
            this proposition, reliance has been placed on B. Jayaraj v State
            of Andhra Pradesh;58 P. Satyanarayana Murthy v District
            Inspector of Police, State of Andhra Pradesh and Another;59
            State through Central Bureau of Investigation v Dr Anup
            Kumar Srivastava;60 K. Shanthamma v State of Telangana;61
            Neeraj Dutta v State (NCT of Delhi);62 Soundarajan v State
            Rep. by the Inspector of Police Vigilance Anticorruption
            Dindigul.63
      4.17. Lastly, it has been strenuously argued that sanction to prosecute
            Mr. Yogendra Tripathi and Mr. R. Nagaraja64 having been denied
            by the Sanctioning Authority i.e. the Board of Directors of KPCL
            and the CVC and the said orders having been upheld by the
            DoPT and no steps having been taken by the respondent – CBI
            to challenge the said decision, a different yardstick cannot be
            adopted in respect of the appellants. The matter having attained
            finality, the appellants deserve to be discharged.


55   (2020) 9 SCC 636
56   [2022] 3 SCR 698 : (2022) 7 SCC 370
57   [2024] 4 SCR 29 : 2024 SCC OnLine SC 483
58   [2014] 4 SCR 554 : (2014) 13 SCC 55
59   (2015) 10 SCC 152
60   [2017] 9 SCR 341 : (2017) 15 SCC 560
61   (2022) 4 SCC 574
62   [2023] 2 SCR 997: (2023) 4 SCC 731
63   [2023] 4 SCR 133 : (2023) SCC OnLine SC 424
64   (both of who were serving officers in KPCL at the relevant point of time)
1204                                                       [2024] 8 S.C.R.

                     Digital Supreme Court Reports


5.   ARGUMENTS BY COUNSEL FOR THE RESPONDENT-CBI
     5.1 Mr. Cheema, learned Senior Advocate appearing for the
         respondent – CBI has refuted each and every argument
         advanced by learned counsel for the appellants. He submitted
         that the appellants have unduly placed heavy reliance on the
         fact that the original Mining Plan was approved by the MoC on
         08th December, 2004 and the said Mining Plan did not contain
         any specific clause for disposal of rejects. Similarly, unnecessary
         reference has been made by the appellants to Rule 22(5) of
         the Mineral Concession Rules, 1960 to demonstrate what
         information is required to be disclosed in a Mining Plan. It is
         submitted that the argument advanced by the appellants that
         in the absence of any stipulation in the Mining Plan regarding
         disposal of the rejects, there could be no inference of commission
         of any offence or a shadow cast on the conduct of the appellants,
         is flawed.
     5.2 Learned counsel for the respondent-CBI has canvassed that
         there was a latent error in the assumption of the appellants that
         it was for the MoC to incorporate a clause regarding disposal of
         the rejects in the Mining Plan and in the absence of any such
         clause, KPCL or KECML could not be held responsible for the
         disposal of the rejects, which was done in an illegal manner or
         that when the Mining Plan was silent regarding the manner in
         which the rejects were to be disposed of, it was for KPCL and
         KECML to deal with the rejects in an appropriate manner. The
         aforesaid presumptions are stated to be without any basis and
         opposed to the letter dated 10th November, 2003, addressed
         by the MoC to KPCL that lays down the conditions of allotment
         of the captive coal blocks in para 3 that specifically states in
         sub-para (iv) as follows:
          “3 The allotment of the captive blocks will also be subject
          to the following conditions:·
          xxxxx
          (iv) The allocattee would furnish to this Ministry detailed
          plan for disposal of unusable containing carbon material
          obtained during the process of a mining or any process
          thereafter including washing etc. so as to avoid any need
[2024] 8 S.C.R.                                                          1205

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           for disposal of the same through sale etc. at a later stage,
           within 30 days of receipt of this letter or submission of
           mining plan whichever is earlier.”
     5.3 As per the respondent-CBI, it was the duty of KPCL to furnish the
         detailed plan for the disposal of the rejects to the Ministry within
         30 days of the receipt of the letter dated 10th November, 2003
         or submission of the Mining Plan, whichever is earlier and this
         requirement was independent of the Mining Plan. Therefore,
         absence of any plans mentioned in the Mining Plan to deal
         with the rejects would not exonerate the appellants who
         remained under an obligation to furnish a detailed plan for the
         disposal of the rejects in terms of the Allocation letter dated
         10th November, 2003 issued by the MoC.
     5.4 Referring to the letter dated 31st January, 2006 addressed
         by the MoC to the Secretary, Industries, Energy and Labour
         Department, State of Maharashtra, learned counsel for the
         respondent-CBI submitted that the appellants were aware of
         the fact that the rejects could not have been disposed of by
         KECML since the said letter had conveyed the approval of the
         Central Government to grant mining lease for coal in three
         coal blocks in favour of KECML with certain stipulations, one
         of which was as follows:
           “ii) No coal mined from the allocated blocs shall be
           sold, delivered, transferred of disposed of except for
           the aforestated captive mining purposes except with the
           previous approval of the Central Government”
     5.5 To reinforce the above plea, reliance has also been placed on
         the statement of Dr. Manmohan Seam, cited as witness No. 12
         who had prepared the Mining Plan in question and stated that
         in case of washing of coal the allocatees are required to obtain
         an approval from the MoC in terms of the letter of allotment and
         since the MoC has not allocated any coal block for washing
         of coal alone, the expression used in para 3 (iii) of the letter
         dated 10th November, 2003 written by the MoC has to be read
         and understood to mean ‘washing-cum-end use’. Therefore,
         emphasis on non-incorporation of a detailed plan for the disposal
         of the rejects in the original Mining Plan has no relevance and
         cannot offer any defence to the appellants.
1206                                                                   [2024] 8 S.C.R.

                            Digital Supreme Court Reports


      5.6 It has next been submitted that the order refusing grant of
          sanction to prosecute Mr. Yogendra Tripathi (IAS), Managing
          Director, KPCL and Mr. R. Nagaraja, Director (Finance) of
          KPCL and nominee Director on the Board of KECML by the
          Sanctioning Authority and the Competent Authority is not a
          relevant circumstance at the stage of consideration and framing
          of charge and no benefit can be given to the appellants on
          that basis. The orders passed by the Competent Authority
          refusing to grant sanction are sought to be described as mere
          administrative orders. Learned counsel argued that in any
          event, the two officers mentioned above were public servants
          and the factum of the Competent Authority having refused to
          grant sanction to prosecute them cannot enure to the benefit of
          the appellants herein who are not public servants and cannot
          seek any parity with public servants.
      5.7 Learned counsel for the respondent-CBI points out that the
          Order on Charge impugned by the appellants herein was also
          challenged by the accused No. 1 to 5 (functionaries of KPCL
          who had since retired), by filing a Petition for Special Leave to
          Appeal65 in this Court which was dismissed as withdrawn vide
          order dated 09th February, 2024.
      5.8 It is submitted that at the stage of framing of charges, the trial
          Court must confine itself to the material brought on record by way
          of the chargesheet filed under Section 173 Cr.P.C and merely
          because some other Authority has taken a different view with
          regard to the complicity of some co-accused who are public
          servants and denied the request made by the respondent-CBI
          for sanctioning their prosecution, is irrelevant.
      5.9 As for case law cited by learned counsel for the appellants to
          substantiate their submission that sanction under Section 197
          Cr.P.C is mandatory for prosecuting public servants (A-1 to
          A-5 in the instant case), the submission made is that for the
          said purpose, facts and circumstances of each case have to
          be examined and there cannot be any universal findings in
          this regard.



65   SLP (Crl.) Dy No. 20094/2023 titled S.M. Jaamdar & Others v. CBI
[2024] 8 S.C.R.                                                        1207

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

      5.10 Learned counsel for the respondent – CBI has strenuously
           disputed as incorrect, the argument advanced on behalf of the
           appellants that the respondent – CBI has filed the Chargesheet
           solely on the basis of the CAG Report and submitted that a
           reading of the FIR dated 31st March, 2015 would demonstrate
           that this case was not triggered by the Report of the CAG. In
           fact, PE 5/2012 was registered on 28th September, 2012 in
           connection with the irregularities noticed in the allocation of
           coal blocks under the Government Dispensation route for the
           period between 1993 and 2006. Asserting that PE 5 did not
           emanate from the CAG Report and originated independently
           thereof, learned counsel submitted that during the course of
           the preliminary enquiry, several documents including the CAG
           Report were examined by the respondent – CBI. In fact, the
           respondent – CBI had conducted its own independent enquiry
           into the allegations for arriving at a conclusion relating to the
           commission of the offence or quantification of the extent of
           misappropriation. In view of the aforesaid submission, the
           contentions of the appellants based on a reading of the provisions
           of the CAG Act and the Constitution of India are stated to be
           extraneous to the controversy raised before this Court just as
           the case law cited by them regarding the nature of the CAG
           Report. Learned counsel has cited the judgment of the Gauhati
           High Court in M.S Associates and others v. Union of India66
           to urge that even if the CAG Report has not been placed before
           the Parliament/State Legislature, contents thereof can serve as
           information for starting an investigation into a criminal offence.
      5.11 Coming next to the judgement passed by the Karnataka High
           Court in the case of Aryan Energy (supra) and cited by the other
           side, it is submitted on behalf of the respondent-CBI that the said
           judgment was passed on 22nd July, 2021, much after institution
           of the chargesheet by the respondent–CBI in the present case.
           Learned counsel submits that the said judgement addresses a
           situation where no criminal case has been registered against
           any of the parties appearing before the High Court. The main
           dispute in that matter was relating to the entitlement of KPCL
           to the value of the coal rejects. The Commercial Court had


66   (2005) SCC Online Gau 308; (2005) 275 ITR 502
1208                                                       [2024] 8 S.C.R.

                    Digital Supreme Court Reports


         decreed the suits in favour of AEPL by holding that as per the
         contractual stipulations between the parties, AEPL was only
         required to dispose off the coal rejects in a manner that would
         satisfy environmental regulations and KPCL was not entitled
         to the value of the coal rejects. Learned counsel submits that
         the terminology used in the contract governing the parties was
         different and therefore the said judgement does not have any
         relevance to the facts of the instant case.
    5.12 Learned counsel for the respondent-CBI goes on to argue that
         even the judgement dated 24th March, 2016, passed by the
         Karnataka High Court in a writ petition filed by KECML against
         KPCL cannot be of any assistance to the appellants for the
         reason that the respondent – CBI had not been impleaded as
         a party in the said proceedings and the said judgement has
         confined itself to the demands made by KPCL for recovery of
         amounts from KECML towards the value of the coal rejects.
         Further, the FIR in the present case was registered on
         13th March, 2015 whereas the judgement was delivered by the
         Karnataka High Court one year later, on 24th March, 2016. By
         the time the appeal preferred by KPCL against the judgment of
         the High Court was dismissed by this Court on 20th May, 2022,
         Charges had already been framed by the learned Special Judge,
         CBI against the appellants on 24th December, 2021.
    5.13 Learned counsel for the respondent–CBI has emphatically
         argued that Clause 12 of the MoU dated 20th December, 2008
         executed between KECML and GCWL states that the rejects
         shall be the joint property of KECML and GCWL and it shall be
         disposed of/sold jointly at mutually agreed terms. It is contended
         that the above clause clearly demonstrates the underlying intent
         of the appellants to conspire with GCWL to sell the rejects in
         the market and cause monetary loss to KPCL by depriving it
         of the value of the rejects.
    5.14 The attention of this Court has also been drawn to the letter dated
         10th September, 2009, issued by KECML to GCWL enclosing
         therewith a Debit Note of even date for a sum of ₹ 4,30,38,500/-
         (Rupees Four crore thirty lakh thirty eight thousand five hundred
         only) towards “disposal of foreign material during washing” and
         it has been argued that the said Debit Note was raised on the
[2024] 8 S.C.R.                                                       1209

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

             instructions of Mr. Purujit Roy (accused No. 9), as stated by
             Mr. N.K. Ganorkar (PW 26) who was one of the two signatories
             of the said Debit Note and Mr. S.K. Gupta, an employee of
             GCWL (PW 16).
      5.15 Learned counsel for the respondent–CBI also referred to a
           Certificate dated 12th July, 2010 issued by Mr. Avijit Sarkar
           who was working in the Finance and Accounts Department
           of KECML. The said Certificate refers to the MoU dated
           20th December, 2008 and states that the rejects generated in
           the process of washing of coal undertaken by GCWL at their
           washery at Majiri during 2009-10, is owned by GCWL.
      5.16 Lastly, learned counsel for the respondent-CBI has canvassed
           that the findings returned in a civil proceeding are not binding
           in a prosecution founded on similar allegations and it is for the
           criminal Court to arrive at any decision on its own and not to
           reach any conclusion by reference to any previous decisions
           relating to the parties which cannot be treated as binding upon
           it. In support of the said submission, he has cited The King
           Emperor v. Khawaja Nazir Ahmed.67 It has thus been argued
           by the respondent-CBI that the present appeals are devoid of
           merits and deserve to be dismissed.
      5.17 On the scope of Section 227, Cr.P.C. and the power of the
           Special Judge to pass an order of discharge, learned counsel
           for the respondent-CBI has cited the decisions in Union of
           India v. Prafulla Kumar Samal and Another 68 and Niranjan
           Singh Karam Singh v. Jitendra Bhimraj Bijjaya And Others.69
           The decisions in State of Maharashtra v. Som Nath Thapa,70
           State of Tamil Nadu v. N. Suresh Rajan and Others71 have
           been relied on to make a point that at the stage of framing of
           charges, the Court cannot appraise the evidence as is done at
           the time of trial and the Court must proceed on an assumption
           that the materials brought on record by the prosecution are


67   AIR (1945) PC 18
68   [1979] 2 SCR 229 : (1979) 3 SCC 4
69   [1990] 3 SCR 633 : (1990) 4 SCC 76
70   [1996] Supp. 1 SCR 189 : (1996) 4 SCC 659
71   [2014] 1 SCR 135 : (2014) 11 SCC 709
1210                                                          [2024] 8 S.C.R.

                            Digital Supreme Court Reports


             true. Alluding to the judgment in State of Bihar v. Ramesh
             Singh,72 learned counsel submitted that at the initial stage of
             the trial, if there is a strong suspicion that gives an impression
             to the Court for drawing a presumption that the accused has
             committed an offence, it is not open for the Court to state that
             there is insufficient ground for proceeding against the accused.
      5.18 Both sides have also relied on K.G. Premshanker v. Inspector
           of Police and Another 73 which discusses the effect of a decision
           of a civil Court on criminal proceedings against the same person
           pertaining to the same cause in the context of Sections 40 to
           43 of the Indian Evidence Act, 1872 as to which judgments of
           the courts are relevant and the extent of the relevance.
6.    REJOINDER ARGUMENTS BY COUNSEL FOR THE APPELLANTS
      In their rejoinder arguments, learned counsel for the appellants have
      disputed the submissions made on behalf of the respondent-CBI and
      reiterated the pleas taken by them. We do not propose to repeat
      the said submissions except for touching on the aspects which were
      not addressed earlier.
      6.1 It has been stated that the MoU dated 20th December, 2008
          was executed to meet the urgent requirement of coal for BTPS.
          The purpose of incorporating Clause 12 was to keep a check
          on the rejects generated by GCWL during the washing of coal.
          The said clause specifically mentions that any disposal/sale
          of the rejects would be subject to compliances of the relevant
          rules and regulations. Learned counsel submitted that it is the
          case of the respondent-CBI itself that GCWL sold the rejects by
          mixing it with good coal at their washery. There is no document
          produced by the respondent-CBI to connect the rejects sold
          by GCWL to the appellants. The appellants cannot be roped
          in on the bald statements made by the functionaries of GCWL
          connecting them with the coal purchased in e-auction from
          WCL and sold off.
      6.2 As for the Debit Note dated 21st March, 2009, it is submitted
          that the same was recovered from GCWL and not KECML.


72   [1978] 1 SCR 257 : (1977) 4 SCC 39
73   [2002] Supp. 2 SCR 350 : (2002) 8 SCC 87
[2024] 8 S.C.R.                                                       1211

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           The said Debit Note was neither acted upon nor approved by
           the Board of Directors of KECML and there is no supporting
           correspondence relating to the Debit Note to demonstrate any
           complicity on the part of the appellants.
     6.3 The appellants have disputed the Certificate dated 12th July, 2010,
         purportedly issued by Mr. Avijit Sarkar to GCWL stating that the
         email was despatched by the said employee from his personal
         email id and not from the official email id of KECML and he was
         not authorized by the Board of Directors of KECML to issue
         any such email. Even otherwise, the Certificate runs contrary to
         Clause 12 of the MoU, as it purports to give 100% entitlement
         of the rejects to GCWL.
     6.4 During the course of rejoining, arguments have also been
         advanced on the quantum of the rejects which as per the
         appellants, has been wrongly quantified by the respondent–CBI
         at 8,03,859.277 MT. Learned counsel contended that the said
         figure has been pulled out by the respondent-CBI from the CAG
         Report though it claims it has not relied on it to register the PE,
         followed by registration of the FIR. The attention of this Court
         has been drawn to the mismatch between the quantity of rejects
         for a period of two months (April and May of the year, 2012-13)
         claimed to be 207,837.117 MT by referring to a Certificate dated
         07th June, 2016 issued by Mr. S.N. Roy, Statutory Auditor of
         KECML vis-à-vis the quantity of rejects generated for a period
         of twelve months for the previous year (2011-2012) that came
         to only 74,511.709 MT. Learned counsel submitted that in reply
         to the Audit query raised by the CAG, KECML had specifically
         stated that the total production of coal upto May, 2012 was
         79,46,082.736 MT which included coal and rejects. This figure
         has not been disputed by the respondent – CBI. The quantity
         of the rejects upto May, 2012 was 75,63,934.800 MT of the
         washed coal which figure has also not been disputed by the
         respondent-CBI. An inference would therefore have to be drawn
         that, at best, the difference between both the aforesaid figures
         would be the extent of the rejects of coal. It has been urged that
         once the extent of production and the quantum of coal sent to
         KPCL has not been disputed, there is no question of inflating
         the quantum of rejects, as alleged. The respondent–CBI has
         therefore blindly accepted the version put forth by GCWL that it
1212                                                        [2024] 8 S.C.R.

                            Digital Supreme Court Reports


             had supplied good coal to KPCL from its own pocket, which suits
             its purpose because when the washing activity was stopped at
             Majri on 22nd May, 2012, disputes had arisen between KECML
             and GCWL, that are pending adjudication before the Arbitration
             Tribunal and GCWL has inflated its claims to raise exorbitant
             demands on KECML.
      D.     DISCUSSION AND ANALYSIS
      7.1 We have given our anxious consideration to the arguments
          advanced by learned counsel for the parties, gone through the
          records and perused the impugned orders. The grievance of the
          appellants arises from the decision taken by the learned Special
          Judge, CBI to reject the application moved by them for seeking
          discharge in the matter and proceeding to frame charges against
          them alongwith the other co-accused for having entered into
          a criminal conspiracy with an object to facilitate illegal sale of
          coal rejects by GCWL that were generated during washing of
          coal and to have gained undue pecuniary advantage therefrom.
      7.2 The genesis of the investigation conducted by the respondent–
          CBI in respect of the coal block allocation lies in the judgement
          of this Court dated 25th August 2014 rendered in Manohar Lal
          Sharma vs. Principal Secretary and Another.74 The petitioner
          therein filed a petition under Article 32 of the Constitution of
          India and challenged the allocation of coal blocks to Private
          Companies for the period between 1993 and 2011 on the
          ground that they violated the principles of trusteeship of natural
          resources by giving away precious resources as largesse without
          complying with the mandatory provisions of the MMDR Act and
          1973 Coal Act. After a detailed scrutiny, this Court declared that
          the entire allocation of coal blocks as per the recommendations
          made by the Screening Committee from the year 1993 onwards
          through the Government dispensation route suffered from
          arbitrariness, and that no fair and transparent procedure had
          been adopted.
      7.3 In the course of the proceedings in the aforesaid matter, the
          respondent–CBI registered a Preliminary inquiry to investigate


74   [2014] 8 SCR 446 : (2014) 9 SCC 516
[2024] 8 S.C.R.                                                         1213

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

              the irregularities in allocation of coal blocks under the
              Government Dispensation Route and to State PSUs, who were
              allowed to form JVA by joining hands with Private Companies
              for purposes of development and operation of coal mines. PE 5
              was registered on 28th September, 2012. It related to all the
              coal block allocations made during the year 1993 to 2006. It
              is not in dispute that the coal allocation in favour of KPCL was
              also a subject matter of investigation, but nothing untoward
              was noticed in that. The JVA between KPCL and KECML also
              withstood the test of scrutiny. As a result, allocation of coal
              blocks made in favour of KPCL were not interfered with.
8.    DID CBI PRIMARILY RELY ON THE AUDIT REPORT OF THE CAG?
      8.1 We shall first examine the submission made by the appellants
          that the respondent–CBI solely relied on the Audit report of the
          CAG of 2013 to launch its prosecution in the year 2015. This
          contention has been strongly refuted by the respondent–CBI
          that has asserted that the Department had on its own initiative,
          come across several documents including the CAG Report
          which exposed commission of the offence and the extent of
          misappropriation of money by the appellants and the other
          co-accused and it had not solely relied on the CAG Report to
          commence the investigation.
      8.2 In the course of hearing, this Court had directed learned counsel
          for the respondent–CBI to produce the files of the Department on
          the basis whereof, three Preliminary Inquiries were registered –
          PE-2/2012/EO-I,75 PE-4/2012/EO-I76 and PE-5/2012/EO-I.77 It
          transpires from the said records that PE-2 was registered on
          02nd June, 2012 on the directions issued by the CVC that had
          forwarded a complaint received by it alleging irregularities in the
          allotment of coal blocks to Private Companies during the period
          2006 to 2009 and in awarding a contract by State owned PSUs
          for the development of coal blocks allocated to them under the
          Government dispensation. Subsequently, two more references
          were received by the respondent–CBI from the CVC and vide OM


75   In short PE-2
76   In short PE-3
77   In short PE-4
1214                                                          [2024] 8 S.C.R.

                         Digital Supreme Court Reports


               dated 19th September, 2012, the CVC forwarded a third complaint
               received from seven Members of Parliament (Lok Sabha) and
               directed the respondent – CBI to conduct a preliminary inquiry.
       8.3 The file produced by the respondent–CBI reveals that premised
           on the Source Information Report78 submitted by an Inspector
           from the Department pertaining to some irregularities in the
           allocation of coal blocks under the Government Dispensation
           Category allegedly in connivance with public servants, the matter
           was taken up by CBI for verification. The notings in the file
           states that it was not possible to verify the allegations discretely.
           Therefore, the SIR was directed to be registered as a PE. These
           records falsifies the suggestion made by the respondent–CBI that
           there was a SIR that disclosed irregularities in the JVA executed
           between KPCL and KECML. The stand of the respondent – CBI
           that PE-5 was registered well before the Audit Report of the
           CAG and originated independently thereof, is also factually
           misleading because CBI’s own record shows that the scope of
           enquiry in respect of PE-5 registered on 28th September, 2012,
           was entirely different and had no relationship with the JVA
           and other agreements executed by KPCL and KECML. No
           other documents have been filed by the respondent – CBI to
           demonstrate that it had initiated an independent inquiry into
           the mining operations of KPCL or that it was during the course
           of its inquiry into the affairs of KPCL and KECML that it had
           stumbled upon some irregularities in the MoU executed between
           KECML with GCWL. Quite clearly, the respondent–CBI made
           the Audit Report of the CAG submitted in 2013, a launching pad
           for initiating the prosecution of the appellants in respect of the
           allegations levelled in the present case and subsequently sought
           to substantiate them by delving into the records maintained by
           KPCL, KECML and GCWL. In other words, there was no move
           within the Department to investigate KPCL or KECML before
           2015. The PE’s registered in the year 2012 did not inculpate
           the appellants in any manner. The entire focus of the said
           PE’s was on the larger issue of irregularities in the allocation
           of coal blocks through the Government dispensation route. In
           this background, the respondent–CBI cannot be heard to state


78   For short ‘SIR’
[2024] 8 S.C.R.                                                    1215

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           that CBI was independently investigating the matter at hand
           well before 2015 or the Audit Report of the CAG of 2013 was
           not the trigger point for commencing the investigation.
9.   COULD THE AUDIT REPORT OF THE CAG FASTEN ANY LIABILITY
     ON KECML?
     9.1 Coming next to the CAG Report, as much hinges on the said
         Report, we may note that the same was considered by the
         Division Bench of the High Court of Karnataka in its judgement
         dated 24th March, 2016, wherein, it was noticed that there was
         no dispute between KPCL and KECML regarding the obligations
         cast on them under the contracts for the development of
         captive coal blocks and for supply of coal for consumption
         at the Thermal Power Station (BPCL) located in the State of
         Karnataka until the CAG submitted an Audit Report for the year
         ending March, 2013. The High Court took note of the Report
         of the CAG which stated that the total production of coal from
         one of the open cast mines between 2008-09 and June 2012
         was 80.78 lacs MT and a minimum quantity of coal rejects
         ought to be 10% of the total production which would come to
         8.28 lacs MT which financially translated into ₹52,37,00,000/-
         (Rupees Fifty Two Crores Thirty Seven Lacs only). Based
         on the above analysis, the CAG raised an audit objection
         and called upon KPCL to explain the loss of ₹52,37,00,000/-
         (Rupees Fifty Two Crores Thirty Seven Lacs only) allegedly
         caused to the public exchequer, on account of the rejects being
         disposed of in terms of a MoU executed between KECML and
         GCWL. The stand taken by KPCL was also noted by the court.
         KPCL submitted its Audit Objections to the said Report stating
         inter alia that the valuation of the rejects was erroneous; that
         assessment of washery rejects did not have any co-relation
         with the quantity of coal produced at the open coal mines;
         that the rejects generated in the mining operation were only
         stones and boulders and could not be used for generation of
         electricity at BPCL and lastly, that all the rejects were used
         for levelling and piling work within the mines for better mining
         operations. However, all the said objections were rejected by
         the CAG that maintained its stand in the final Report.
     9.2 The High Court observed that at that stage, KPCL did a
         sudden summersault. Faced with the Audit Report of the CAG,
1216                                                       [2024] 8 S.C.R.

                    Digital Supreme Court Reports


         KPCL proceeded to raise a demand on the appellants seeking
         reimbursement to the tune of ₹52,37,00,000/- (Rupees Fifty
         two crores thirty seven lacs only) as cost of the rejects and
         threatened KECML that in case of default of payment, recovery
         would commence from their running bills. This made KECML
         file two writ petitions, which were allowed by the High Court
         with the following observations:
         xxxxxxx
         “36. We find that the report of CAG cannot be the sole basis
         for any liability being caused or for that matter the sole
         basis for the prosecution to be launched. However, mere
         drawing up of FIR by the CBI against unknown officials
         of KPCL, EMTA and KEMTA cannot provide legal basis
         or impetus for unilateral demand by KPCL for recovery of
         ₹52,37,00,000/- (Rupees Fifty Two Crores Thirty Seven
         Lakh) only. We hold that such action is arbitrary and
         unsustainable in law.”
    9.3. The aforesaid judgement was assailed by KPCL by approaching
         this Court. The said appeals were dismissed by a three Judges
         Bench of this Court of which one of us (Hon’ble Ms. Hima Kohli, J)
         was a member with the observations that the Audit Report
         of the CAG appeared to have been the starting point for the
         entire dispute between the parties. When the CAG Report
         was first submitted, KPCL had itself raised objections to the
         quantification of the coal rejects by the CAG but on its objections
         being turned down, KPCL raised a demand on KECML seeking
         reimbursement on the basis of very same CAG Report to which
         it had not so long ago, filed objections.
    9.4. The observations made by this Court in the captioned decision
         are germane and are extracted below:
            “13. The present matter pertains to a tender that was
            awarded by the appellant to EMTA nearly twenty years
            ago, in the year 2002. The CAG report that appears
            to have been the starting point for the entire dispute
            between the parties is dated March, 2013, close to a
            decade back. In such circumstances, to even advert to
            arguments on the maintainability of the writ petitions
            would be unjust to the parties involved.
[2024] 8 S.C.R.                                                           1217

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

             14. Coming to the merits of the appeal, from the facts,
             it appears that in the first instance, when the CAG
             report was first submitted, the appellant itself had raised
             objections to the quantification of coal rejects arrived at
             by the CAG. However, when the audit objections were
             rejected by the CAG, and the final report was made
             available, the appellant demanded reimbursement from
             KEMTA based on the same CAG report to which it had
             filed objections. Such a change of stand by the appellant
             has not been sufficiently explained.
             15. Additionally, a bare perusal of the clauses contained
             in the various agreements entered into between the
             parties does not indicate that such deductions could
             be made for the purposes of washing charges. There
             does not appear to be any specification laid down as to
             the method required to be adopted for washing of coal.
             16. No material has been placed on record by the
             appellant to suggest that there was ever any problem
             with respect to the quality of coal being supplied by
             KEMTA to the appellant. Rather, the impugned order
             suggests that coal supplied by KEMTA was utilized by
             the appellant in its thermal power plants in order to
             generate electricity.
             17. Taking into consideration the above facts and
             circumstances, we are of the opinion that no material
             has been brought to the notice of this Court that would
             compel us to interfere with the impugned common
             judgment passed by the High Court in exercise of our
             jurisdiction under Article 136 of the Constitution.
             18. Accordingly, the Civil Appeals filed by the appellant
             are dismissed.”
     9.5. We are therefore of the opinion that this Court having already
          dismissed the appeal filed by KPCL against the judgment of
          the Karnataka High Court, having held in clear terms that the
          CAG Report could not form the basis for launching proceedings
          against the appellants and further, having upheld the findings
          returned by the Karnataka High Court that the CAG Report
1218                                                          [2024] 8 S.C.R.

                            Digital Supreme Court Reports


             appears to have been the starting point for the entire disputes
             between the parties who till then, were smoothly discharging
             their obligations under various agreements, there is no
             reason to take a different view only on the ground that the
             respondent–CBI was not a party in the aforesaid proceedings.
             The chronology of the events speak for themselves and need
             no further elaboration.
10. IMPORT OF THE JUDGMENT DATED 24TH MARCH, 2016 OF THE
    KARNATAKA HIGH COURT
      10.1. Coming next to the submission made by learned counsel for
            the respondent that the judgement dated 24th March, 2016
            passed by the Karnataka High Court in a writ petition filed
            by KECML against KPCL is of no consequence, as the said
            judgment was confined to examining the demands made by
            KPCL on KECML for reimbursement towards the value of the
            coal rejects, the same is found to be erroneous. It is well-settled
            that in a case of exoneration on merits in relation to adjudication
            proceedings in a civil matter where the allegations are found
            to be unsustainable and the party is held as innocent, criminal
            prosecution on the same set of facts and circumstances cannot
            be permitted to continue. In Radheshyam Kejriwal (supra),
            a three judges Bench of this Court reconciled the conflict
            between the view taken in Standard Chartered Bank(1) v.
            Directorate of Enforcement79 and Collector of Customs
            v. L.R. Melwani 80 on the one hand where it was held that
            adjudication proceedings and criminal proceedings are two
            independent proceedings and both can go on simultaneously
            and findings in the adjudication proceedings is not binding on
            the criminal proceedings and the judgments in Uttam Chand
            v. ITO,81 G.L. Didwania v. ITO,82 K.C. Builders v. CIT 83 where
            the view taken was that when there is a categorical finding in
            the adjudication proceedings exonerating a person which is
            binding and conclusive, the prosecution cannot be allowed to


79   [2006] 2 SCR 709 : (2006) 4 SCC 278
80   AIR 1970 SC 962
81   (1982) 2 SCC 543
82   (1995) Supp(2) 724
83   [2004] 1 SCR 1134 : (2004) 2 SCC 731
[2024] 8 S.C.R.                                                          1219

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           stand, this Court summarized the ratio of the decisions in the
           following words:
             “38. The ratio which can be culled out from these
             decisions can broadly be stated as follows:
             (i) Adjudication proceedings and criminal prosecution
             can be launched simultaneously;
             (ii) Decision in adjudication proceedings is not necessary
             before initiating criminal prosecution;
             (iii) Adjudication proceedings and criminal proceedings
             are independent in nature to each other;
             (iv) The finding against the person facing prosecution
             in the adjudication proceedings is not binding on the
             proceeding for criminal prosecution;
             (v) Adjudication proceedings by the Enforcement
             Directorate is not prosecution by a competent court
             of law to attract the provisions of Article 20(2) of the
             Constitution or Section 300 of the Code of Criminal
             Procedure;
             (vi) The finding in the adjudication proceedings in favour
             of the person facing trial for identical violation will
             depend upon the nature of finding. If the exoneration
             in adjudication proceedings is on technical ground and
             not on merit, prosecution may continue; and
             (vii) In case of exoneration, however, on merits where
             the allegation is found to be not sustainable at all and
             the person held innocent, criminal prosecution on the
             same set of facts and circumstances cannot be allowed
             to continue, the underlying principle being the higher
             standard of proof in criminal cases.
             39. In our opinion, therefore, the yardstick would
             be to judge as to whether the allegation in the
             adjudication proceedings as well as the proceeding
             for prosecution is identical and the exoneration
             of the person concerned in the adjudication
             proceedings is on merits. In case it is found on merit
1220                                                           [2024] 8 S.C.R.

                               Digital Supreme Court Reports


                  that there is no contravention of the provisions of
                  the Act in the adjudication proceedings, the trial
                  of the person concerned shall be an abuse of the
                  process of the court.”
                                                         [emphasis added]
              The aforesaid view also finds resonance in Ashoo Surendranath
              Tewari (supra) and J Sekar alias Sekar Reddy(supra).
      10.2. We are of the view that if there was any breach of contract or
            default on the part of KECML, KPCL was well empowered to
            determine the lease. However, KPCL did not do so. Instead,
            on being confronted with the Audit Objections taken by CAG,
            it raised a demand on KECML for the value of the coal rejects.
            This demand was quashed and set aside by the Karnataka
            High Court and this Court.
      10.3. On applying the decisions cited above to the facts of the instant
            case, this Court cannot turn a blind eye to the view taken in
            the judgement dated 24th March, 2016 passed by the Division
            Bench of the High Court of Karnataka in a dispute directly arising
            between KPCL and KECML pertaining to the very same cause
            of action based on the obligations cast on both the parties under
            various agreements executed for the development of captive
            coal blocks and for supply of coal, which was finally upheld
            by this Court vide judgement dated 20th May, 2022. The said
            judgments have cleared KECML of any blame. On the same
            set of facts and logic, we are of the opinion that no criminality
            can be attributed to the appellants.
11. SANCTITY OF AN AUDIT REPORT IN LAW
      11.1. As the sanctity of the Audit Report of the CAG of 2013 has
            been questioned by the appellants, we propose to examine
            this aspect. Before the year 1971, the CAG used to function
            under the Government of India (Audit and Accounts Order),
            1936 as adopted by the Government of India (Provisional
            Constitution) Order, 1947. This was followed by the promulgation
            of the Comptroller and Auditor General’s (Duties, Powers and
            Conditions of Service) Act, 197184. By virtue of Section 26 of the


84   For short ‘the CAG Act’
[2024] 8 S.C.R.                                                        1221

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           CAG Act, the earlier Order of 1936 was repealed. Section 10 of
           the CAG Act requires the CAG to compile the accounts of the
           Union and the States and on the basis of the said accounts, to
           prepare an annual account for being submitted to the President
           of India or the Governor of the State/Administrator of the Union
           Territory, as the case may be. The scope of the audit of the
           Union and the States has been stated in Section 13 of the
           CAG Act.
     11.2. Article 149 of the Constitution of India defines the duties and
           powers of the CAG and provides thus:
             “149. Duties and powers of the Comptroller and
             Auditor-General
             The Comptroller and Auditor-General shall perform
             such duties and exercise such powers in relation to
             the “accounts of the Union and of the States and of
             any other authority or body as may be prescribed by or
             under any law made by Parliament and, until provision
             in that behalf is so made, shall perform such duties
             and exercise such powers in relation to the accounts
             of the Union and of the States as were conferred on or
             exercisable by the Auditor-General of India immediately
             before the commencement of this Constitution in relation
             to the accounts of the Dominion of India and of the
             Provinces respectively.”
     11.3 The duties of the CAG have been described and discussed
          at some length in the Arun Kumar Aggarwal (supra) in the
          following words:
             “60. The audit of the Union and the States is under
             Section 13 of the Act. The scope of the audit extends to
             the audit of all expenditure so as to ascertain whether
             the monies shown in the accounts as having been
             disbursed were legally available for such disbursement
             and whether the expenditure conforms to the authority
             which governs it. The CAG has to satisfy himself
             that the rules and procedures designed to secure an
             effective check on the assessment, collection and proper
             allocation of revenue are being duly observed under
1222                                                  [2024] 8 S.C.R.

                Digital Supreme Court Reports


        Section 16. The CAG also has to examine decisions
        which have financial implications including the propriety
        of the decision making.
        61. The reports of the CAG are required to be submitted
        to the President, who shall cause them to be laid
        before each House of Parliament, as provided under
        Article 151(1). In relation to the States, reports are
        submitted to the Governor, who shall cause them to be
        laid before the legislature of the State, as per Article
        151(2) of the Constitution. When reports are received in
        Parliament, they are scrutinised by the Public Accounts
        Committee (PAC).
        62. The PAC is established in accordance with Rule 308
        of the Rules of Procedure and Conduct of Business in
        Lok Sabha. The function of the PAC is to examine the
        accounts of the Union and the report of the CAG. The
        PAC shall be principally concerned whether the policy
        is carried out efficiently, effectively and economically,
        rather than with the merits of government policy. Its
        main functions are to see that public monies are
        applied for the purposes prescribed by Parliament, that
        extravagance and waste are minimised and that sound
        financial practices are encouraged in estimating and
        contracting, and in administration generally. The PAC
        also has the power to receive evidence, the power to
        send for persons, papers and record and can receive
        oral evidence on solemn affirmation. Once the report
        is prepared, the report of the PAC is presented to the
        House.
        xxxxx
        68. We may, however, point out that since the report
        is from a constitutional functionary, it commands
        respect and cannot be brushed aside as such, but
        it is equally important to examine the comments
        what respective Ministries have to offer on the
        CAG’s Report. The Ministry can always point out,
        if there is any mistake in the CAG’s report or the
        CAG has inappropriately appreciated the various
[2024] 8 S.C.R.                                                        1223

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

             issues. For instance, we cannot as such accept
             the CAG report in the instant case.”
                                                    [emphasis added]
           A similar view has been expressed in Pathan Mohammed
           Suleman Rehmatkhan (supra) and Centre for Public Interest
           Litigation (supra).
     11.4. It is, therefore, evident that the recommendations of the PAC are
           premised on the response that is received from the concerned
           Ministries and the Action Taken Reports which includes the
           replies furnished by the Government and the comments of
           the PAC to the said replies. Finally, it is for the Parliament to
           comment on the CAG’s Report after it receives the report of
           the PAC.
     11.5. In the instant case, admittedly the aforesaid procedure has not
           been followed. As noticed above, the CAG Report is subject
           to scrutiny by the Parliament and the Government can always
           offer its views on the said report. Merely because the CAG is
           an independent constitutional functionary does not mean that
           after receiving a report from it and on the PAC scrutinizing the
           same and submitting its report, the Parliament will automatically
           accept the said report. The Parliament may agree or disagree
           with the Report. It may accept it as it is or in part. It is not in
           dispute that the Audit Report of the CAG has not been tabled
           before the Parliament for soliciting any comments from the PAC
           or the respective Ministries. Therefore, the views taken by the
           CAG to the effect that tremendous loss had been caused to the
           public exchequer on account of the coal rejects being disposed
           of by the KPCL and KECML remains a view point but cannot be
           accepted as decisive. The respondent–CBI has largely relied
           on the findings and the conclusions drawn in the Audit Report
           of the CAG to launch the prosecution against the appellants on
           an assumption that the said Report has the seal of approval of
           the Parliament and has attained finality, which is not the case.
12. DENIAL OF SANCTIONS BY THE SANCTIONING AUTHORITIES
    AND THE EFFECT ON THE APPELLANTS
     12.1.It is relevant to note that the very same Audit objections taken
          by the CAG and relied upon by the respondent–CBI to allege
1224                                                     [2024] 8 S.C.R.

                  Digital Supreme Court Reports


        conspiracy and loss to the public exchequer were thoroughly
        examined and found to be meritless by two separate set of
        Sanctioning Authorities. When it came to Mr. R. Nagaraja, the
        then Director (Finance) of KPCL and the nominee Director
        on the Board of KECML, the Sanctioning Authority, i.e., the
        Board of KPCL went through several documents during its
        deliberations including the MoU between the KECML and
        GCWL forwarded by the respondent–CBI for seeking sanction
        to prosecute him. The reasons for holding that the CAG Report
        was without any factual basis, were elaborately dealt with as
        below:
          “DETAILED REPORT OF THE BOARD OF KPCL IN
          RELATION TO THE CBI REPORT DATED 28.07.2017
          AS REGARDS SHRI R. NAGARAJA
          xxxxx
          1.8 There is an Memorandum of Understanding dated
          20.12.2008 between Gupta Coal Fields and Washeries
          Ltd (‘GCWL’) and KECML under which GCWL was
          required to wash and supply the coal of required
          specification to the Power Plant of KPCL in respect
          of coal mined by KECML. Clause 12 of the said MoU
          stipulates that “the rejects generated shall be the joint
          property of KECML and GCWL and can be disposed off
          / sold at mutually agreed terms subject to compliance
          of rules / regulations / guidelines of Ministry of Coal,
          Government of India, if applicable”. KPCL allowed
          KECML to sign an MoU with Gupta under which rejects
          belonging to KPCL was put under the joint ownership of
          Gupta and KECML by virtue of Clause 12. Gupta has
          sold those rejects resulting in an illegal gain of Rs.52.37
          crores to Gupta (as per CAG) and loss to KPCL. The
          Board of KECML which conspired to insert Clause 12
          of the MoU did not take any protective / mitigative
          measures to prevent the loss despite it being raised at
          a lower level. The facts in relation to the above offence
          are elaborated in detail herein below.
          xxxxx
[2024] 8 S.C.R.                                                           1225

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

             B.     Consideration of the report of CBI dated
                    27.07.2017 (along with annexures) by the Board
                    of KPCL and their Report thereon
             2.     The entire matter including the 344 documents
                    produced along with the Report and the witness
                    statements of 67 witnesses have been perused by
                    the members of the Board. The Board has also
                    considered the applicable law on the point.
             3.     The offence is complained of by Shri R. Nagaraja
                    in his capacity as a nominee of KPCL in the Board
                    of KECML. It is the matter of fact that the nominees
                    of KPCL who have been appointed to the Board
                    of KECML are not persons well versed in mining
                    matters. As KPCL was not capable of handling
                    mining operations, a joint Venture Company was
                    formed. The Board of KECML and the nominees
                    of KPCL on the Board entirely depended on
                    the inputs provided by the Managing Director,
                    Statutory Auditor and other personnel for making
                    their decisions.
             4.     The Mining Plan for the operationalization of
                    the mine was prepared by Dr. Seam who was
                    a Ministry of Coal official and not an employee
                    of KECML or KPCL. The Mining Plan was
                    approved by the Ministry of Coal when it did
                    not contain any provisions for disposal of
                    the rejects. In such a situation, the Board of
                    Directors of KECML and especially the KPCL
                    nominees (A-1 to A-7) could not be blamed for
                    the non-compliance of the Allotment Letter and
                    there is no act of omission or commission on
                    the part of KPCL’s employees including Shri
                    R. Nagaraja.
             5.     A perusal of the KPCL Office Notes (Document
                    No.199 to 202) for the period indicates that by way
                    of letter dated 12.01.2009, the Managing Director of
                    KPCL had specifically raised the issue of whether
                    washing of coal is required or not. If washing was
1226                                                 [2024] 8 S.C.R.

               Digital Supreme Court Reports


             not necessary, then the question of generation
             of rejects would not arise at all. Therefore, after
             taking into account the office note generated by
             Shri Purushottam, Shri R. Nagaraja had sought to
             examine whether washing is required at all. Hence,
             Shri R. Nagaraja has acted with great prudence
             to ensure that no loss is caused to KPCL under
             the directions of Dr. S.M. Jaamdar, MD, KPCL.
        6.   If washing of coal was not required, then the
             MoU with Gupta was not required to be approved
             inasmuch as the main purpose of the agreement
             was to start the washing process. Although the
             MoU was ratified, it could not be operationalized
             specifically Clause 12 of the MoU was not ratified
             by the Board of KECML. Conditional ratification of
             MoU does not mean that the Board has dishonestly
             refrained from protecting the interest of KPCL.
             (See Board minutes of KECML at Document
             No.232)
        7.   From the reading of the Clause 12, it appears
             that the fact that there was no concluded
             contract vis-à-vis of rejects inasmuch it was
             understood that it was to be sold on ‘mutually
             agreed terms’ and ‘subject to legal clearances’.
             This implies that GCWL and KECML had to
             mutually agree for the terms of the sale and
             same had to be approved by Ministry of Coal.
             Given the fact that the MoU was only conditionally
             ratified, it was incumbent upon the officials of
             KECML that before they agree to any terms for
             the sale of the rejects that they had to bring the
             matter up to the Board of KECML. The subsequent
             events indicate that even the officials of KECML
             were of the same understanding.
        8.   Even assuming that the Clause 12 of the MoU
             was approved, another aspect of the matter
             which has to be noted is that Clause 12 of
             the MoU does not violate the terms of the
[2024] 8 S.C.R.                                                       1227

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                    Allotment Letter inasmuch as it specifically
                    required that the approval of the Ministry of
                    Coal be obtained before such a disposal. A
                    bare reading of the Clause 12 does not indicate
                    any illegality a sought to be alleged by the
                    CBI. Therefore, the approval of the MoU in the
                    Board Meeting on 13.01.2009 cannot be said to
                    be an act of negligence or error in judgment and
                    no imputation of any wrongdoing can be imposed
                    any KPCL nominee present in the Board Meeting
                    on 13.01.2009.
             xxxxx
             10. Additionally, KECML wrote a letter wherein
                 it sought for a waiver from meeting the
                 specification if raw coal was supplied. The
                 difficulty for the Management of KPCL was that
                 if the raw coal did not match the specification,
                 it would not be utilization for the generation
                 of power. This would result in stoppage of
                 generation resulting in power crisis in the
                 State of Karnataka. The better alternative would
                 have been to wait for the certificate of the Coal
                 Controller regarding whether the raw coal met
                 the requirements of KPCL of not. Hence, no
                 confirmation was given. This was a managerial
                 decision taken in the best interest of the State of
                 Karnataka as the power generation could not be
                 compromised to save washing cost. The cost of
                 procurement of power would be tremendous
                 and outweighed any temporary disadvantage
                 caused by not abiding by the Board Minutes
                 of 13.06.2009. This decision was vindicated
                 by the letter issued by the Coal Controller’s
                 Office on 09.12.2009 wherein it concluded that
                 to obtain the agreed parameter of coal quality,
                 washing would be required. Therefore, it cannot
                 be said that there was an act of omission or
                 negligence or error in judgment on part of the
                 KPCL nominees on the Board of KECML. The
1228                                               [2024] 8 S.C.R.

                Digital Supreme Court Reports


              decision was taken keeping the best interests
              of KPCL in mind and cannot be faulted.
        xxxxx
        16. The contention of CBI that there is a violation of
            the allotment order that tailings and rejects are
            the property of KPCL and should be utilized only
            for its end use of power generation appears to be
            based on a strict interpretation of the allotment
            conditions. Technically, Bellary Thermal Plant of
            500 MW capacity is designed to use pulverized
            coal for firing and coal of reasonable quality. As
            such the condition that middlings, tailings &
            rejects should be used for power generation
            by KPCL is neither feasible nor appropriate. On
            the other hand, since disposal of rejects is an
            environmental issue, KPCL has insisted that
            the same should be subject to compliance of
            environmental norms. When KPCL was not in a
            position to use the reject for power generation,
            the onus is on the mining operator to dispose
            of the same as permitted under law. Given the
            facts as stated above, there cannot be any act of
            negligence on part of the nominees of KPCL in
            this regard as well.
        17. The CAG report is without factual basis for the
            following reasons:
        i)    The quantum of rejects is assumed as 10% of
              the coal based on MoU whereas as per actuals it
              was 4.39% as evident from the Coal Controller’s
              certificate, Statements of inward and outward
              movements of Coal as submitted by GCWL.
        ii)   Without even knowing the calorific value of the
              rejects, it has been assumed to be G Grade
              coal. Even going by the statement of Shri
              Padmesh Gupta of GCWL, the rejects were
              of such a low calorific value that it could not
              be sold without blending. Hence, it could not
[2024] 8 S.C.R.                                                           1229

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                    have been of G grade. Hence, the basis of the
                    calculation is wrong.
             xxxxx
             20. The assumption of the CBI that the exact
                 quantity of rejects that have been sold off
                 cannot be ascertained is a self-serving
                 statement inasmuch as for the purpose of
                 blending of coal, Gupta has to purchase the
                 raw coal / washed coal and pay royalty / sales
                 tax on the same whereas there is no sales tax
                 / royalty paid on the rejects. With this number,
                 it is easily possible to arrive at the exact quantity
                 of reject coal. As the quantity of reject coal
                 generated / available at Majri Washery as per
                 the Stock statement far exceeds the reject
                 coal quantity claimed to be generated by the
                 washing of KECML’s coal, in order to divert
                 other rejects as KECML’s rejects, the absurdly
                 high amount has been claimed. Hence, there is
                 absolutely no evidence to show that any reject has
                 been sold and if so, what is the quantity of rejects
                 sold. In such a situation, there is no basis for
                 assuming that KPCL has suffered any unlawful
                 loss or that GCWL has gained unlawfully during
                 this process.
             21. CBI has produced a Debit Note No.KECML/DN/08-
                 09/09 dated 31.03.2009 for Rs.4,30,38,500/- which
                 was recovered at GCWL (and not at KECML) and
                 there is a statement from GCWL that this Debit Note
                 was not honoured. An examination of the Debit
                 Note, Annual Accounts of KECML for 2008-09
                 and other documents produced along with the
                 Report would indicate that this Debit Note is a
                 fabricated document for the following reasons:
             a.     The Note is generated as on the last date of the
                    financial year 2008-2009 but is forwarded only in
                    the next financial year in September 2009 indicating
                    that it is an afterthought.
1230                                                [2024] 8 S.C.R.

                 Digital Supreme Court Reports


        b.   This Debit Note does not find a mention in the
             Annual Accounts of 2008-2009 i.e. it should have
             created an income stream for KECML.
        c.   If the Debit Note was a genuine document, then
             KECML had to classify the sales of washer rejects
             of 86,077 MT as “other income” in the Annual
             Accounts. However, it is shown as washing loss.
        d.   There are no corresponding Debit Notes of this
             nature (viz. For foreign material) amongst the
             several admitted Debit Notes and no mention
             of this Debit Note or such an arrangement for
             subsequent years.
        e.   KECML officials have written emails asking for
             accounts of the stock and Gupta has stated that
             the rejects are still lying with them.
        22. There are two types of rejects as reflected in the
            Annual accounts. One is the rejects lost due to
            stones, boulders etc. for which no royalty was
            paid. These rejects were not even transported
            to Gupta and are not classified as ‘washery
            loss’. The washery loss is evident from the
            Coal Controller’s certificates.
        xxxxx
        38. To say the least, there is no evidence whatsoever
            that is collected by the investigator that would
            indicate that there was either any request or a
            demand by the public servant concerned for a
            valuable thing or a pecuniary advantage at any
            point of time upon the beneficiary for any reason
            whatsoever. A mere omission on the part of the
            public servant or a negligent act on his part which
            has enured to the beneficiary cannot be said to act
            of misconduct on the part of the public servant to
            bring him within the ambit of Section 13(1) (d) of
            the Prevention of Corruption Act, 1988.
        xxxxxx
[2024] 8 S.C.R.                                                      1231

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

             48. Shri R. Nagaraja has an impeccable and
                 unblemished service record in his 27 years
                 of service as an officer and he has held many
                 important and sensitive posts during his
                 service span in KPCL. Any action against him
                 on the basis of a charge devoid of any merit and
                 substance would not only tarnish his otherwise
                 impeccable reputation but will also have a
                 bearing on the morale of the public services.
             49. For the reasons enumerated in para 3 to
                 48 above, we, the Board of KPCL, hereby
                 exercising our powers under Section 19 of the
                 Prevention of Corruption Act, 1988 refuse to
                 grant sanction to prosecute Shri R. Nagaraja for
                 the offences alleged to have been committed
                 under Sections 120B r/w 409 and 420 of the
                 Indian Penal Code, 1860 and Sections 13(2) read
                 with 13(1)(d) of the Prevention of Corruption
                 Act, 1988.”
     12.2. It is apparent from the above that after Sanctioning Authority
           had scrutinized all the relevant documents and the depositions
           as many as of 67 witnesses submitted by the respondent-CBI,
           it observed that there was no evidence to show that any rejects
           generated by washing of coal had been sold or that KPCL had
           suffered an unlawful loss during the process. As a result, the
           Board of KPCL refused to grant sanction to the respondent-
           CBI to prosecute Mr. R. Nagaraja for offences alleged to have
           been committed by him. It is noteworthy that no appeal has
           been filed by the respondent – CBI against denial of sanction.
     12.3. Similarly, the request made by the respondent-CBI for seeking
           sanction to prosecute Mr. Yogendra Tripathi, the then Managing
           Director, KPCL was denied by the Competent Authority in the
           Central Government in terms of the letter dated 16th April, 2018,
           issued by the DoPT. The order passed by the DoPT shows that
           it took note of the Report of the respondent-CBI, the records
           submitted by it along with the Report, the advice received from
           the CVC and then summarized the allegations levelled by the
           respondent-CBI that formed the basis of its proposal to seek
1232                                                      [2024] 8 S.C.R.

                   Digital Supreme Court Reports


        sanction for prosecution of the aforesaid officer. The said request
        was finally rejected by the Competent Authority in the Central
        Government with the following observations:
          “xxxxx
          12. AND WHEREAS the debit note recovered at GCWL
              and the certificate are contradictory to each other in
              as much as debit note imposes a realizable value
              on the rejects and the certificate claims that it has
              been written off. Neither document is supported by
              the annual accounts. Hence, they are extraneous
              and fabricated as an afterthought.
          13. AND WHEREAS washery loss and loss due to
              stone bounders etc. are different. The certificate
              combines the two losses and claims them as
              washing loss. The rejects quantified as 8.03. MT
              only reproduces what is disclosed in the accounts
              as processed wastage.
          14. AND WHEREAS on examination of records,
              statement of witnesses etc, it was seen that there is
              no evidence of any purported conspiracy between
              the accused officer and GCWL or any quid pro
              quo in this regard. The reason for deferring the
              agenda in 41st Board Meeting have been explained
              in the detailed note of M/s KPCL and appear to
              be reasonable. It has been mentioned that the
              revised mining plan was approved in the Board
              Meeting of the Joint Venture KECML by which
              a new technology was to be implemented which
              could have been issued of rejection irrelevant.
          15. AND WHEREAS the comments of the Govt.
              of Karnataka have been obtained. They have
              stated that there is no material to support
              the allegation that he conspired to illegally
              dispose off the rejects and therefore deferred
              the agenda. Hence, no criminal intent can
              be attributed to Shri Yogendra Tripathi and
              have recommended declining of sanction for
[2024] 8 S.C.R.                                                         1233

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                    prosecution U/s 120B r/w 409 and 420 of IPC
                    and Section 13 of the Prevention of Corruption
                    Act, 1988.
             16. AND WHEREAS the proposal was sent to
                 the CVC for their advice. The CVC advised
                 declining of sanction for prosecution against
                 Shri Yogendra Tripathi, IAS(KN:1985), the then
                 Managing Director Karnataka Power Corporation
                 Ltd. (KPCL), Bangalore, in case RC:2202015
                 E0002 dated 13.03.2015.
             17. AND WHEREAS all case records sent by the
                 investigating agency were sent to the Hon’ble
                 Prime Minister, who is the Competent Authority
                 in the Central Government, to decide sanction
                 for prosecution in respect of the IAS officers.
             18. AND THEREFORE The Competent Authority, in
                 view of the above position and after carefully
                 considering the facts and circumstances of the
                 case and considering all other relevant material/
                 documents, including evidence submitted by
                 the Investigating Agency with the proposal,
                 has approved the proposal to decline sanction
                 for prosecution against Shri Yogendra Tripathi,
                 IAS (KN:85) in the instant case, under Section
                 19 of the Prevention of Corruption Act, 1988.”
     12.4. The aforesaid order reveals that before applying its mind, the
           Competent Authority in the Central Government had sought
           comments from the Government of Karnataka who had stated
           that there was no material produced by the respondent-CBI in
           support of the allegation that Mr. Yogendra Tripathi had conspired
           to illegally dispose off the coal rejects or with malafide intention
           deferred the agenda in the 41st Board Meeting of the KPCL.
           The Competent Authority separately sent the said proposal
           submitted by the respondent-CBI to the CVC for seeking
           advice. After examining all the records sent by the investigation
           agency including the evidence submitted by it, the Office of the
           Prime Minister who is the Competent Authority in the Central
           Government, approved the proposal to decline the sanction for
1234                                                     [2024] 8 S.C.R.

                   Digital Supreme Court Reports


         prosecuting Mr. Yogendra Tripathi. Yet again, no appeal has
         been filed by the respondent – CBI before the court questioning
         the said decision.
    12.5. The respondent-CBI having accepted the decision taken
          by the Sanctioning Authority in respect of Mr. R. Nagaraja
          and the decision of the Competent Authority in the Central
          Government in respect of Mr. Yogendra Tripathi, both senior
          most serving officers of KPCL and were also on the Board of
          KECML, cannot be permitted to argue that these were merely
          administrative decisions and even if permission to prosecute
          the aforesaid officers has been denied, the Department can
          still proceed against the appellants based on the very same set
          of material/documents/evidence etc. that have been minutely
          scrutinized by different authorities at the highest level and
          they have independently arrived at an identical conclusion of
          refusing to grant sanction to prosecute senior functionaries of
          KPCL. Simply because the said senior functionaries of KPCL
          were public servants, does not detract from the fact that
          the respondent-CBI has described them as co-accused in a
          criminal conspiracy and attributed similar motives to them as
          the appellants herein. If they have been let off the hook and
          the respondent-CBI has not challenged the said decisions,
          there is no reason to proceed against the appellants herein on
          the basis of the very same set of facts and material gathered
          during the course of investigation.
13. EFFECT OF THE ABSENCE OF ANY STRATEGY IN THE MINING
    PLAN TO DISPOSE OFF THE COAL REJECTS
    13.1. Coming next to the stand taken by the respondent-CBI that
          absence of any plan mentioned in the Mining Plan to deal with
          the rejects could not exonerate the appellants who werebound by
          the terms and conditions of the letter dated 10th November, 2003
          issued by the MoC, we may note the assertion of the respondent-
          CBI that the Mining Plan of the coal blocks in question did
          not contain any plan for disposal of rejects, usable, tailings,
          middlings, etc., that would be generated on account of mining/
          washing of coal, is contrary to the records. Article 5(2)(b) of
          the JVA required EMTA to take all clearances for setting up
          the coal washery from the concerned authorities and properly
[2024] 8 S.C.R.                                                           1235

         M/s Karnataka Emta Coal Mines Limited and Another v.
                    Central Bureau of Investigation

           dispose off the coal rejects to the satisfaction of environmental
           regulations.
      13.2. The explanation offered by the appellants that at that point in time,
            the Central Government had not come out with any specific plan
            to dispose off the coal rejects is validated by the reply furnished
            by the Minister of State, MoC, in the Lok Sabha in response to
            an unstarred question seeking an answer from the Government
            of India as to whether it had framed any National Policy for
            exploitation of the coal rejects. The reply given was that the
            Government had not framed any National Policy for exploitation
            of coal rejects and the same was still under consideration. That
            being the position, it was left to KPCL and KECML to devise
            a satisfactory and safe method to dispose off the coal rejects.
            This was done in terms of Article 5(2)(b) of the JVA that required
            KECML to dispose off the rejects in a manner that would ensure
            that there was no threat to the environment. We do not find any
            irregularity in the route adopted to dispose off the coal rejects.
14.   WAS KECML REQUIRED TO ACCOUNT FOR THE COAL REJECTS?
      14.1. Much emphasis has been laid by the respondent-CBI on the
            contents of the allocation letter dated 10th November, 2003 issued
            by the MoC, Government of India to KPCL to canvass that the
            coal mined from the allocated blocks was to be exclusively
            used to meet the requirements of coal in the proposed thermal
            power station namely, BTPS and on the condition that no coal
            was to be sold /delivered/transferred/disposed of except for the
            purpose of power generation and with the previous approval of
            the Central Government. We are afraid, the said letter cannot be
            read in isolation and out of context for the very same reasons
            as have been noted above.
      14.2.When the Central Government did not formulate any National
           Policy for exploitation of coal rejects, it is fallacious on the part
           of the respondent-CBI to argue that the conditions imposed
           by the Central Government while conveying its approval to
           the State Government for grant of mining lease in favour of
           KPCL ought to have formed a part of the lease deed to be
           executed. Fact of the matter is that there was no such condition
           imposed in the Notification dated 16th July, 2004, issued by
           the MoC. The said notification simply specified the end use of
1236                                                                                   [2024] 8 S.C.R.

                                Digital Supreme Court Reports


               the coal from the allocated coal blocks for supply to KPCL to
               generate thermal power in the proposed BPCL. The original
               Mining Plan of September, 2004 submitted by KECML to the
               MoC for its approval also did not elucidate the manner in which
               the coal rejects were to be disposed of. The said Mining Plan
               had the approval of the MoC which did not raise any objection
               relating to the absence of any condition for dealing with the
               coal rejects. The inevitable conclusion is that disposal of the
               coal rejects was to be undertaken by KECML strictly in terms
               of Article 5(2)(b) of the JVA and no more.
       14.3. Moreover, a closer look at the clauses of the JVA and FSA
             clearly indicate that KECML was only obliged to provide a
             specified grade of washed coal (Grade – D) having a specific
             GCV in the range of 4200-4940 Kcal/kg.85 When coal has been
             defined in the JVA and FSA as “washed coal with guaranteed
             value” and one that satisfied the parameters laid down in
             Annex-1 attached to the JVA and FSA86 and further, KECML
             was required to ensure that all “shales/stones” are removed
             from the coal before making the supply,87 there was no occasion
             for KECML to account for the rejects. All that KPCL was
             required to do was to buy from KECML, the washed coal with
             a particular guaranteed value and one that would satisfy the
             specified quality parameters, at a predetermined price.88 The
             agreement governing the parties required KECML to dispose
             off the rejects safely. KECML was not required to account for
             the coal rejects to KPCL. KPCL itself understood the clauses
             in the JVA and the FSA to mean the same and it was satisfied
             with the manner in which KECML was discharging its obligations
             under the agreements till Audit Objections were raised by the
             CAG in October, 2013. That’s when KPCL did a complete flip
             flop and for the first time, raised a demand on KECML seeking
             reimbursement towards the value of the coal rejects, a decision
             that was successfully assailed by the appellants in the High



85   ‘Grade D Coal’ as defined under ‘Definition and Interpretation’ clause of the JVA dt 13th September, 2002.
86   ‘Coal’ as defined under ‘Definition and Interpretation’ clause of the JVA dt. 13th September, 2002 and
     Article 1 of FSA dt. 09th May, 2007
87   Article 5.2.2 of the FSA
88   Annexure-II of the JVA and Article 6.1.1 of the FSA
[2024] 8 S.C.R.                                                          1237

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           Court and the challenge laid by KPCL to the said judgement
           was repelled by this Court.
15. CAN KECML BE BLAMED FOR NOT SETTING UP THE COAL
    WASHERY AT THE PITHEAD?
     15.1. As for the allegation levelled by the respondent–CBI that
           KECML violated the terms of Articles 2(4)(g) and 5(2)(b) of the
           JVA having failed to setup the coal washery at the pithead, the
           sequence of events narrated above, shows that the fault does
           not lie at the door of the appellants. It was on account of some
           litigation between CIPCO and MoC in relation to the coal blocks
           allocated to KPCL wherein interim orders were granted by the
           High Court in favour of CIPCO, that the project got delayed.
           Production of coal could commence only in September, 2008
           after the aforesaid litigation came to an end. By then, much time
           was lost. The conditions stipulated in the agreements governing
           KPCL and KECML placed an obligation on KECML to supply
           washed coal with a definite GCV and specified parameters
           for the consumption of the Thermal Power Station at Bellary
           and failure to deliver coal within the stipulated time, attracted
           penalties.
     15.2. It was in this background that KECML executed the MoU with
           GCWL for washing of the mined coal at its washery at Majri,
           transportation of the raw coal from the mines and washed
           coal to the Railway Siding for delivery to BTPS. Records
           reveal that the draft of MoU was duly deliberated upon by the
           Board of Directors of KECML and finally approved and ratified
           on 13th January, 2009. Subsequently, in the meeting held on
           23rd February, 2010, the Board of Directors of KECML concluded
           that washing of raw coal was a prerequisite to meet the specified
           grade of coal with a defined GCV for generation of power at
           BTPS. The necessity of supplying washed coal to obtain the
           agreed parameter of coal quality was also recognized by the
           office of the Coal Controller in its letter dated 9th December, 2009.
           This fact finds mention in the detailed Report of the Board
           of KPCL that refused permission to the respondent-CBI to
           prosecute Mr. R. Nagaraja.
     15.3. It is clear from the above that the decision of KECML to enter
           into a MoU with GCWL for washing of coal was actuated by
1238                                                        [2024] 8 S.C.R.

                    Digital Supreme Court Reports


         compelling circumstance faced by it and KPCL had taken a
         calibrated decision in its commercial wisdom to duly concur
         with the said decision knowing very well that non-supply of a
         specified grade of washed coal by KECML would have serious
         consequences of stoppage of generation of power at BTPS and
         a cascading effect of resulting in a power crisis in the State of
         Karnataka.
    15.4. We do not propose to Labour much on the contention of the
          respondent-CBI that allocation of the coal block was in favour
          of KPCL and not in favour of KECML as stands adequately
          explained on a perusal of the Notification dated 16th July, 2024
          which shows that the Central Government did recognize the
          fact that it was KECML who was required to supply coal from
          the coal mines allocated to KPCL and end use of the said
          coal was specified for generation of Thermal Power Station at
          Bellary, Karnataka. In our view, having regard to the aforesaid
          notification, nothing much turns on the submission made by
          the respondent-CBI that the coal block allocation was only in
          favour of KPCL and it ought to have a right over the rejects to
          the exclusion of KECML and others.
16. DID THE COAL REJECTS HAVE ANY USEFLUL CALORIFIC
    VALUE MAKING IT A SALEABLE COMMODITY?
    16.1. We find that the Detailed Washability Report of the Government
          Laboratory namely, CIMFR, Nagpur has been ignored by the
          respondent-CBI. It was the said Report that formed the basis of
          the information furnished by KECML with respect to production,
          stock, despatch of coal to the washery etc., as was demanded
          by the office of the Coal Controller, a department that falls under
          the MoC. The said Report stated in so many words that the
          rejects did not contain any useful c.v. Reliance placed by the
          respondent-CBI on the revised Mining Plan submitted by the
          appellants to the MoC in 2010, that mentions a new technology
          for utilization of rejects for its carbon value, namely FBC is of
          no consequence as the said technology had not even been
          introduced when MoC approved the original Mining Plan,
          submitted by KECML in the year 2004. Even otherwise, it is
          not in dispute that for applying the said technology, a plant was
          required to be established after obtaining necessary approvals
          from several agencies. The plant could not be established by
[2024] 8 S.C.R.                                                         1239

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           KECML for the reason that the revised Mining Plan submitted
           by it was approved by the MoC only on 24th August, 2011.
           Consequent steps that were required to be taken by KECML
           for obtaining necessary approvals from the MoEF&CC and
           other govt. agencies came to a grinding halt when an order was
           passed by this Court in the year 2014, deallocating all captive
           coal blocks, including those allocated to KPCL. Therefore, any
           reference by the respondent-CBI to the revised Mining Plan is
           of no consequence.
17. PERSUASIVE VALUE OF THE ARYAN ENERGY CASE
     17.1 KPCL’s entitlement over the coal rejects has been separately
          tested by the High Court of Karnataka in the case of Aryan
          Energy (supra). Pertinently, in that case the clauses forming
          a part of the Agreement between KPCL and Aryan Energy
          particularly with respect to the disposal of the coal rejects is the
          same as in the instant case. Aryan Energy was also required
          to dispose off the coal rejects by making compliance of the
          environmental regulations. In the said case, the High Court of
          Karnataka returned a finding that KPCL did not have any claim
          over the coal rejects generated during washing of coal. The view
          taken was that as long as disposal of the coal rejects was in
          line with the environmental regulations, KPCL did not have any
          role to play in the disposal of the coal rejects. It was specifically
          observed by the High Court that the agreement between KPCL
          and Aryan Energy included a condition that KPCL would only
          buy washed coal at a predetermined price and that it was not
          entitled to lay a claim on the coal rejects generated during the
          processing of raw coal. In view of the terms and conditions of
          the agreement between the parties, the High Court concluded
          that KPCL could not have raised any demand on Aryan Energy
          claiming reimbursement for the value of the coal rejects. It is
          a matter of record that although KPCL had challenged the
          judgement and order dated 22nd July, 2021 passed by the
          High Court of Karnataka44 before this court, the said petitions
          were disposed of on 26th April, 2014 noting that the parties had
          settled their inter se disputes amongst themselves in terms of a
          Compromise Deed and as a result, part of the decretal amount
          deposited by KPCL before the Commercial Court was agreed
          to be released in favour of Aryan Energy.
1240                                                           [2024] 8 S.C.R.

                            Digital Supreme Court Reports


      17.2 We do not see why the aforesaid decision would not have any
           persuasive value when the clauses in the agreement between
           KPCL and KECML for disposing off the coal rejects are identical.
           On going through the agreements executed between KPCL and
           Aryan Energy, the High Court had shot down the plea of KPCL
           that it was entitled to the coal rejects. Though KPCL assailed
           the said decision before this Court, it settled its dispute with
           Aryan Energy and the appeals preferred by it were disposed
           of as compromised. The contention of the respondent-CBI that
           the order of the High Court of Karnataka is not relevant for
           the present case since there was no criminal case registered
           therein, cannot be a distinguishing feature when the terms and
           conditions of the contract between KPCL and Aryan Energy on
           the aspect of disposal of the coal rejects is pari materia. We are
           of the opinion that the judgment in the case of Aryan Energy
           does have persuasive value.
18. INHERENT JURISDICTION OF THE HIGH COURT UNDER
    SECTION 482, Cr.P.C
      18.1. For seeking quashing of the chargesheet and the order framing
            charges, learned counsel for the appellants has cited decisions
            of this court that lay down the proposition of law relating
            to quashing of criminal proceedings by a High Court under
            Section 482, Cr.P.C. In Rajiv Thapar and Others v. Madan
            Lal Kapoor,89 this court held as under:
                 “29. The issue being examined in the instant case is the
                 jurisdiction of the High Court under Section 482 CrPC,
                 if it chooses to quash the initiation of the prosecution
                 against an accused at the stage of issuing process,
                 or at the stage of committal, or even at the stage of
                 framing of charges. These are all stages before the
                 commencement of the actual trial. The same parameters
                 would naturally be available for later stages as well. The
                 power vested in the High Court under Section 482 CrPC,
                 at the stages referred to hereinabove, would have far-
                 reaching consequences inasmuch as it would negate
                 the prosecution’s/complainant’s case without allowing


89   [2013] 3 SCR 52 : (2013) 3 SCC 330
[2024] 8 S.C.R.                                                           1241

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

             the prosecution/complainant to lead evidence. Such a
             determination must always be rendered with caution,
             care and circumspection. To invoke its inherent
             jurisdiction under Section 482 CrPC the High Court
             has to be fully satisfied that the material produced
             by the accused is such that would lead to the
             conclusion that his/their defence is based on sound,
             reasonable, and indubitable facts; the material
             produced is such as would rule out and displace the
             assertions contained in the charges levelled against
             the accused; and the material produced is such as
             would clearly reject and overrule the veracity of the
             allegations contained in the accusations levelled by
             the prosecution/complainant. It should be sufficient
             to rule out, reject and discard the accusations
             levelled by the prosecution/complainant, without
             the necessity of recording any evidence. For this
             the material relied upon by the defence should not
             have been refuted, or alternatively, cannot be justifiably
             refuted, being material of sterling and impeccable quality.
             The material relied upon by the accused should
             be such as would persuade a reasonable person
             to dismiss and condemn the actual basis of the
             accusations as false. In such a situation, the judicial
             conscience of the High Court would persuade it
             to exercise its power under Section 482 CrPC to
             quash such criminal proceedings, for that would
             prevent abuse of process of the court, and secure
             the ends of justice.”
                                                    [emphasis added]
     18.2 In the captioned case, this court had further observed that the
          discretion vested in the High Court under Section 482 Cr.P.C
          can be exercised suo moto to prevent abuse of the process of
          a Court, and/or to secure the ends of justice. After listing the
          factors that ought to weigh with the High Court to make a just
          and rightful choice, it was observed thus:
             “30. Based on the factors canvassed in the foregoing
             paragraphs, we would delineate the following steps to
1242                                                            [2024] 8 S.C.R.

                            Digital Supreme Court Reports


                 determine the veracity of a prayer for quashment raised
                 by an accused by invoking the power vested in the High
                 Court under Section 482 CrPC:
                 30.1. Step one: whether the material relied upon by the
                 accused is sound, reasonable, and indubitable i.e. the
                 material is of sterling and impeccable quality?
                 30.2. Step two: whether the material relied upon by the
                 accused would rule out the assertions contained in the
                 charges levelled against the accused i.e. the material
                 is sufficient to reject and overrule the factual assertions
                 contained in the complaint i.e. the material is such as
                 would persuade a reasonable person to dismiss and
                 condemn the factual basis of the accusations as false?
                 30.3. Step three: whether the material relied upon by
                 the accused has not been refuted by the prosecution/
                 complainant; and/or the material is such that it cannot
                 be justifiably refuted by the prosecution/complainant?
                 30.4. Step four: whether proceeding with the trial would
                 result in an abuse of process of the court, and would
                 not serve the ends of justice?
                 30.5. If the answer to all the steps is in the affirmative,
                 the judicial conscience of the High Court should
                 persuade it to quash such criminal proceedings in
                 exercise of power vested in it under Section 482
                 CrPC. Such exercise of power, besides doing justice
                 to the accused, would save precious court time,
                 which would otherwise be wasted in holding such
                 a trial (as well as proceedings arising therefrom)
                 specially when it is clear that the same would not
                 conclude in the conviction of the accused.”
                                                        [emphasis added]
      18.3 In State of Orissa v. Debendra Nath Padhi,90 the powers of
           the High Court under Section 482, Cr.P.C and Article 226 of the
           Constitution of India were highlighted and the court observed that:


90   [2004] Supp. 6 SCR 460 : (2005) 1 SCC 568
[2024] 8 S.C.R.                                                               1243

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

                 “29. Regarding the argument of the accused having
                 to face the trial despite being in a position to produce
                 material of unimpeachable character of sterling quality,
                 the width of the powers of the High Court under
                 Section 482 of the Code and Article 226 of the
                 Constitution is unlimited whereunder in the interests
                 of justice the High Court can make such orders as
                 may be necessary to prevent abuse of the process
                 of any court or otherwise to secure the ends of
                 justice within the parameters laid down in Bhajan
                 Lal case91 [1992 Supp (1) SCC 335 : 1992 SCC (Cri)
                 426].”
                                                        [emphasis added]
      18.4 In Rukmini Narvekar v. Vijaya Satardekar and Others,92 this
           Court has observed that the width of the powers of the High
           Court under Section 482, Cr.P.C and under Article 226 of the
           Constitution of India are unlimited, that the High Court could
           make such orders as may be necessary to prevent abuse of
           the process of any Court or otherwise to secure the ends of
           justice. In a concurring order passed in the very same case, it
           was observed in addition that in exercising jurisdiction under
           Section 482, Cr.P.C, the High Court is free to consider even
           material that may be produced on behalf of the accused to arrive
           at a decision whether charge as framed could be maintained.
      18.5 In Anand Kumar Mohatta and Another v. State (NCT of
           Delhi), Department of Home and Another,93 referring to the
           provisions of Section 482, Cr.P.C, this Court held as follows:
                 16. There is nothing in the words of this section which
                 restricts the exercise of the power of the Court to prevent
                 the abuse of process of court or miscarriage of justice
                 only to the stage of the FIR. It is settled principle of
                 law that the High Court can exercise jurisdiction under
                 Section 482 CrPC even when the discharge application



91   (1992) Supp (1) SCC 335
92   [2008] 14 SCR 271 : (2008) 14 SCC 1
93   [2018] 13 SCR 1028 : (2019) 11 SCC 706
1244                                                   [2024] 8 S.C.R.

                Digital Supreme Court Reports


        is pending with the trial court [G. Sagar Suri v. State
        of U.P., (2000) 2 SCC 636, para 7 : 2000 SCC (Cri)
        513. Umesh Kumar v. State of A.P., (2013) 10 SCC
        591, para 20 : (2014) 1 SCC (Cri) 338 : (2014) 2 SCC
        (L&S) 237] . Indeed, it would be a travesty to hold
        that proceedings initiated against a person can be
        interfered with at the stage of FIR but not if it has
        advanced and the allegations have materialised into
        a charge-sheet. On the contrary it could be said
        that the abuse of process caused by FIR stands
        aggravated if the FIR has taken the form of a charge-
        sheet after investigation. The power is undoubtedly
        conferred to prevent abuse of process of power of
        any court.
        xxxxx
        28. In State of Haryana v. Bhajan Lal [State of Haryana
        v. Bhajan Lal, 1992 Supp (1) SCC 335 : 1992 SCC (Cri)
        426], this Court has set out the categories of cases
        in which the inherent power under Section 482 CrPC
        can be exercised. Para 102 of the judgment reads as
        follows : (SCC pp. 378-79)
          “102. In the backdrop of the interpretation of the
          various relevant provisions of the Code under
          Chapter XIV and of the principles of law enunciated
          by this Court in a series of decisions relating to the
          exercise of the extraordinary power under Article
          226 or the inherent powers under Section 482 of
          the Code which we have extracted and reproduced
          above, we give the following categories of cases
          by way of illustration wherein such power could
          be exercised either to prevent abuse of the
          process of any court or otherwise to secure the
          ends of justice, though it may not be possible
          to lay down any precise, clearly defined and
          sufficiently channelised and inflexible guidelines
          or rigid formulae and to give an exhaustive list of
          myriad kinds of cases wherein such power should
          be exercised.
[2024] 8 S.C.R.                                                        1245

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                (1) Where the allegations made in the first
                information report or the complaint, even if they
                are taken at their face value and accepted in their
                entirety do not prima facie constitute any offence
                or make out a case against the accused.
                (2) Where the allegations in the first information
                report and other materials, if any, accompanying
                the FIR do not disclose a cognizable offence,
                justifying an investigation by police officers under
                Section 156(1) of the Code except under an order
                of a Magistrate within the purview of Section 155(2)
                of the Code.
                (3) Where the uncontroverted allegations made in
                the FIR or complaint and the evidence collected in
                support of the same do not disclose the commission
                of any offence and make out a case against the
                accused.
                (4) Where, the allegations in the FIR do not
                constitute a cognizable offence but constitute only a
                non-cognizable offence, no investigation is permitted
                by a police officer without an order of a Magistrate
                as contemplated under Section 155(2) of the Code.
                (5) Where the allegations made in the FIR or
                complaint are so absurd and inherently improbable
                on the basis of which no prudent person can ever
                reach a just conclusion that there is sufficient
                ground for proceeding against the accused.
                (6) Where there is an express legal bar engrafted
                in any of the provisions of the Code or the Act
                concerned (under which a criminal proceeding
                is instituted) to the institution and continuance of
                the proceedings and/or where there is a specific
                provision in the Code or the Act concerned,
                providing efficacious redress for the grievance of
                the aggrieved party.
                (7) Where a criminal proceeding is manifestly
                attended with mala fide and/or where the proceeding
1246                                                             [2024] 8 S.C.R.

                            Digital Supreme Court Reports


                     is maliciously instituted with an ulterior motive for
                     wreaking vengeance on the accused and with
                     a view to spite him due to private and personal
                     grudge.”
      18.6. In State of Karnataka vs. L. Munniswamy,94 Y.V. Chandrachud, J.
            as he then was (speaking for a three Judge Bench) observed
            thus:
                 “7. … In the exercise of this wholesome power, the High
                 Court is entitled to quash a proceeding if it comes to
                 the conclusion that allowing the proceeding to continue
                 would be an abuse of the process of the Court or
                 that the ends of justice require that the proceeding
                 ought to be quashed. The saving of the High
                 Court’s inherent powers, both in civil and criminal
                 matters, is designed to achieve a salutary public
                 purpose which is that a court proceeding ought
                 not to be permitted to degenerate into a weapon
                 of harassment or persecution. In a criminal case,
                 the veiled object behind a lame prosecution, the
                 very nature of the material on which the structure
                 of the prosecution rests and the like would justify
                 the High Court in quashing the proceeding in the
                 interest of justice.”
                                                        [ emphasis added]
      18.7 As can be gathered from the above, Section 482 Cr.P.C
           recognizes the inherent powers of the High Court to quash
           initiation of prosecution against the accused to pass such
           orders as may be considered necessary to give effect to any
           order under the Cr.P.C or to prevent abuse of the process of
           any court or otherwise to secure the ends of justice. It is a
           statutory power vested in the High Court to quash such criminal
           proceedings that would dislodge the charges levelled against
           the accused and based on the material produced, lead to a firm
           opinion that the assertions contained in the charges levelled
           by the prosecution deserve to be overruled.


94   [1977] 3 SCR 113 : (1977) 2 SCC 699
[2024] 8 S.C.R.                                                            1247

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

      18.8 While exercising the powers vested in the High Court under
           Section 482, Cr.P.C, whether at the stage of issuing process
           or at the stage of committal or even at the stage of framing of
           charges, which are all stages that are prior to commencement
           of the actual trial, the test to be applied is that the Court must
           be fully satisfied that the material produced by the accused
           would lead to a conclusion that their defence is based on sound,
           reasonable and indubitable facts. The material relied on by the
           accused should also be such that would persuade a reasonable
           person to dismiss the accusations levelled against them as false.
19. EXTRAORDINARY POWERS OF THIS COURT UNDER ARTICLE
    13 OF THE CONSTITUTION OF INDIA
      19.1. When it comes to invocation of the powers vested in this Court
            under Article 136 of the Constitution of India, unlike Section 482
            Cr.P.C that has a statutory flavour, Article 136 confers
            plenary powers on this Court to interfere in suitable cases. In
            Arunachalam v. P.S.R. Sadhanantham and Another,95 this
            court has expounded on the amplitude of its powers under
            Article 136 in the following words:
                 “4. ……Article 136 of the Constitution of India invests
                 the Supreme Court with a plentitude of plenary,
                 appellate power over all Courts and Tribunals in
                 India. The power is plenary in the sense that there
                 are no words in Article 136 itself qualifying that
                 power. But, the very nature of the power has led the
                 Court to set limits to itself within which to exercise
                 such power. It is now the well established practice of
                 this Court to permit the invocation of the power under
                 Article 136 only in very exceptional circumstances, as
                 when a question of law of general public importance
                 arises or a decision shocks the conscience of the Court.
                 But, within the restrictions imposed by itself, this
                 Court has the undoubted power to interfere even
                 with findings of fact, making no distinction between
                 judgments of acquittal and conviction, if the High
                 Court, in arriving at those findings, has acted


95   [1979] 3 SCR 482 : (1979) 2 SCC 297
1248                                                           [2024] 8 S.C.R.

                            Digital Supreme Court Reports


                 “perversely or otherwise improperly”. (See State of
                 Madras v. A. Vaidyanatha Iyer [AIR 1958 SC 61 : [1958]
                 SCR 580 : 1958 Cri LJ 232] and Himachal Pradesh
                 Administration v. Om Prakash [(1972) 1 SCC 249 :
                 [1972] 2 SCR 765])…….”
                 5. A doubt has been raised about the competence
                 of a private party, as distinguished from the State, to
                 invoke the jurisdiction of this Court under Article 136
                 of the Constitution against a judgment of acquittal by
                 the High Court. We do not see any substance in the
                 doubt. Appellate power vested in the Supreme Court
                 under Article 136 of the Constitution is not to be
                 confused with ordinary appellate power exercised
                 by appellate courts and Appellate Tribunals under
                 specific statutes.As we said earlier, it is a plenary
                 power, ‘exercisable outside the purview of ordinary
                 law’ to meet the pressing demands of justice (vide
                 Durga Shankar Mehta v. Thakur Raghuraj Singh [AIR
                 1954 SC 520 : [1955] 1 SCR 267 : 1954 SCJ 723]).
                 Article 136 of the Constitution neither confers on
                 anyone the right to invoke the jurisdiction of the
                 Supreme Court nor inhibits anyone from invoking
                 the Court’s jurisdiction. The power is vested in the
                 Supreme Court but the right to invoke the Court’s
                 jurisdiction is vested in no one. The exercise of the
                 power of the Supreme Court is not circumscribed by
                 any limitation as to who may invoke it. …….. Appeals
                 under Article 136 of the Constitution are entertained by
                 special leave granted by this Court, whether it is the
                 State or a private party that invokes the jurisdiction of
                 this Court, special leave is not granted as a matter of
                 course but only for good and sufficient reasons, as well
                 established by the practice of this Court.”
                                                       [emphasis added]
      19.2. In P.S.R. Sadhanantham v. Arunachalam,96 a Constitution
            Bench of five judges elaborated the content and character


96   [1980] 2 SCR 873 : (1980) 3 SCC 141
[2024] 8 S.C.R.                                                            1249

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           of Article 136 vis-à-vis Article 21 and made the following
           observations:
             “7. Specificity being essential to legality, let us see if
             the broad spectrum spread out of Article 136 fills the
             bill from the point of view of “procedure established by
             law”. In express terms, Article 136 does not confer
             a right of appeal on a party as such but it confers
             a wide discretionary power on the Supreme Court
             to interfere in suitable cases. The discretionary
             dimension is considerable but that relates to the power of
             the court. The question is whether it spells by implication,
             fair a procedure as contemplated by Article 21. In our
             view, it does. Article 136 is a special jurisdiction. It is
             residuary power; it is extraordinary in its amplitude,
             its limit, when it chases injustice, is the sky itself.
             This Court functionally fulfils itself by reaching out
             to injustice wherever it is and this power is largely
             derived in the common run of cases from Article
             136. Is if merely a power in the court to be exercised
             in any manner it fancies? Is there no procedural
             limitation in the manner of exercise and the occasion
             for exercise? Is there no duty to act fairly while hearing
             a case under Article 136, either in the matter of grant
             of leave or, after such grant, in the final disposal of the
             appeal? We have hardly any doubt that here is a
             procedure necessarily implicit in the power vested
             in the summit court. It must be remembered that
             Article 136 confers jurisdiction on the highest court.
             The founding fathers unarguably intended in the
             very terms of Article 136 that it shall be exercised
             by the highest judges of the land with scrupulous
             adherence to judicial principles well established by
             precedents in our jurisprudence. Judicial discretion
             is canalised authority, not arbitrary eccentricity….
             xxxxx
             10. Once we hold that Article 136 is a composite
             provision which vests a wide jurisdiction and, by the
             very fact of entrusting this unique jurisdiction in the
1250                                                      [2024] 8 S.C.R.

                   Digital Supreme Court Reports


           Supreme Court, postulates, inarticulately though, the
           methodology of exercising that power, nothing more
           remains in the objection of the petitioner. It is open
           to the court to grant special leave and the subsequent
           process of hearing are (sic is) well-established. Thus,
           there is an integral provision of power-cum-procedure
           which answers with the desideratum of Article 21
           justifying deprivation of life and liberty.
                                                  [emphasis added]
    In a concurring judgement in the captioned case, it was further
    observed that:
           21. Plainly, the jurisdiction conferred by Article 136
           seeks to confer on this Court the widest conceivable
           range of judicial power, making it perhaps among
           the most powerful courts in the world. The judicial
           power reaches out to every judgment, decree,
           determination, sentence or order affecting the rights
           and obligations of persons in civil matters, of life
           and liberty in criminal matters as well as matters
           touching the Revenues of the State. It is an attempt
           to ensure that the foundations of the Indian Republic,
           which have been laid on the bedrock of justice, are not
           undermined by injustice anywhere in the land, Bharat
           Bank Ltd. v. Employees of these Bharat Bank Ltd
           [1950 SCC 470 : AIR 1950 SC 188 : [1950] SCR 459,
           474 : 1950 LLJ 21 : (1950-51) 2 FJR 1] . As the court
           observed in Durga Shankar Mehta v. Thakur Raghuraj
           Singh [AIR 1954 SC 520 : [1955] 1 SCR 267, 272 :
           9 ELR 494] Article 136 “vests in the Supreme Court
           a plenary jurisdiction in the matter of entertaining and
           hearing appeals by grant of special leave”.
           22. Nonetheless, there is a limitation which, in our
           opinion, is of immediate relevance. It is a limitation
           in-built in to the jurisdiction of the court and flows from
           the nature and character of the case intended to be
           brought before the court. It is a limitation which requires
           compliance despite the apparent plenitude of power
           vested in the court. When a petition is presented to the
[2024] 8 S.C.R.                                                                1251

           M/s Karnataka Emta Coal Mines Limited and Another v.
                      Central Bureau of Investigation

                 court under Article 136, the court will have due regard
                 to the nature and character of the case sought to be
                 brought before it when entertaining and disposing of
                 the petition.
                                                        [ emphasis added]
      19.3 In Khoday Distilleries Limited and Others v. Mahadeshwara
           S.S.K. Limited,97 this Court observed that Article 136 commences
           with a non-obstante clause, the words are of overriding effect and
           clearly indicate the intention of the framers of the Constitution
           that it is a special jurisdiction and a repository of residuary
           powers unfettered by any Statute or any provisions of Chapter
           IV of Part V of the Constitution of India. It was also observed
           that the jurisdiction under Article 136 of the Constitution cannot
           be barred by the Statute since it is an extraordinary power.
      19.4 In State of Punjab and others v. Rafiq Masih (White Washer)
           others,98 in the same strain, this Court has held that Article 136
           is a special jurisdiction and can be described as a ‘residuary
           power, extraordinary in its amplitude, its limits when it chases
           injustice, is the sky itself’. It is a corrective jurisdiction that vests
           a discretion in this Court to settle the law clearly and makes
           the law operational thereby making it a binding precedent for
           the future instead of keeping it vague.
      19.5 In Mekala Sivaiah v. State of Andhra Pradesh,99 this Court
           commented on the circumstances in which the power under
           Article 136 is exercised and held thus:
                 “14. Before adverting to the merits of the contention
                 raised, it is important to reiterate that Article 136 of the
                 Constitution of India is an extraordinary jurisdiction
                 which this Court exercises when it entertains an
                 appeal by special leave and this jurisdiction, by its
                 very nature, is exercisable only when this Court is
                 satisfied that it is necessary to interfere in order
                 to prevent grave or serious miscarriage of justice.


97   [2019] 3 SCR 411 : (2012) 12 SCC 291
98   [2014] 13 SCR 1343 : AIR (2015) 1267
99   [2022] 6 SCR 989 : (2022) 8 SCC 253
1252                                                     [2024] 8 S.C.R.

                   Digital Supreme Court Reports


            15. It is well settled by judicial pronouncement that
            Article 136 is worded in wide terms and powers
            conferred under the said Article are not hedged by
            any technical hurdles. This overriding and exceptional
            power is, however, to be exercised sparingly and
            only in furtherance of cause of justice. Thus, when
            the judgment under appeal has resulted in grave
            miscarriage of justice by some misapprehension
            or misreading of evidence or by ignoring material
            evidence then this Court is not only empowered but
            is well expected to interfere to promote the cause
            of justice.”
                                                 [emphasis added]
    19.6 From the aforesaid discussion, it is apparent that Article 136
         can be invoked by a party in a petition for special leave to
         appeal from any judgement, decree, determination, sentence
         or order in any cause or matter passed or made by a Court
         or Tribunal within the territory of India. The reach of the
         extraordinary powers vested in this Court under Article 136 of
         the Constitution of India is boundless. Such unbridled powers
         have been vested in Court, not just to prevent the abuse of
         the process of any court or to secure the ends of justice as
         contemplated in Section 482, Cr.P.C, but to ensure dispensation
         of justice, correct errors of law, safeguard fundamental rights,
         exercise judicial review, resolve conflicting decisions, inject
         consistency in the legal system by settling precedents and for
         myriad other to undo injustice, wherever noticed and promote
         the cause of justice at every level. The fetters on this power
         are self imposed and carefully tampered with sound judicial
         discretion.
    19.7 Coming back to the case in hand, ordinarily, a party aggrieved
         by the filing of a chargesheet or framing of charges ought to
         first approach the High Court in a petition under Section 482,
         Cr.P.C. Though such a route would have been available to
         the appellants herein as well, but in view of the categorical
         directions issued by this court in M.L. Sharma (supra) that
         this Court alone shall have the jurisdiction to entertain cases
         relating to allocation of coal blocks including cases for staying
[2024] 8 S.C.R.                                                         1253

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           the investigation or trial in a matter relating to coal, one rung of
           an appeal before the High Court for quashing the chargesheet
           or interfering in the order on charge by invoking the inherent
           jurisdiction under Section 482 Cr.P.C. stands fore closed. The
           appellants were left with only one chance of directly invoking
           Article 136 of the Constitution of India and filing a petition
           for special leave before this court to challenge the impugned
           orders passed by the learned Special Judge, CBI framing
           charges against them and dismissing their application for
           seeking discharge.
     19.9 Given the broad amplitude of the extraordinary powers of
          this Court under Article 136 of the Constitution of India,
          the respondent-CBI cannot be heard to urge that since a
          Chargesheet has already been filed against the appellants
          and charges framed, the appellants should be left to take all
          the pleas available to them before the learned Special Judge,
          CBI during the course of the trial and that no interference is
          called for by this Court at this stage. Such an approach does
          not commend itself to this Court in the facts and circumstances
          of this case.
20. APPLICATION OF MIND AT THE STAGE OF SECTION 227, Cr.P.C
     20.1 We may note that there is no quarrel with the broad proposition
          canvassed by learned counsel for the respondent- CBI that at
          the stage of Section 227, Cr.P.C., the Special Judge, CBI had
          to sift the evidence to find out whether there was sufficient
          ground for proceedings against the appellants. That exercise
          would include taking a prima facie view on the nature of the
          evidence recorded by the CBI and the documents placed before
          the court so as to frame any charge. At the same time, one
          must be mindful of the language used in Section 227 of the
          Cr.P.C, which is extracted below:
             “227. Discharge.—If, upon consideration of the record
             of the case and the documents submitted therewith,
             and after hearing the submissions of the accused and
             the prosecution in this behalf, the Judge considers that
             there is not sufficient ground for proceeding against the
             accused, he shall discharge the accused and record his
             reasons for so doing.”
1254                                                     [2024] 8 S.C.R.

                   Digital Supreme Court Reports


    20.2. As observed in Prafulla Kumar Samal (supra) the expression
          “not sufficient ground for proceeding against the accused”
          clearly shows that the Judge is not a mere post office to frame
          the charge at the behest of the prosecution. The Judge must
          exercise the judicial mind to the facts of the case in order to
          determine whether a case for trial has been made out by the
          prosecution. The principles governing the scope of Section 227,
          Cr.P.C. have been succinctly summarized in the caption case
          as below:
           “10. Thus, on a consideration of the authorities
           mentioned above, the following principles emerge:
           (1) That the Judge while considering the question of
           framing the charges under Section 227 of the Code has
           the undoubted power to sift and weigh the evidence for
           the limited purpose of finding out whether or not a prima
           facie case against the accused has been made out.
           (2) Where the materials placed before the Court disclose
           grave suspicion against the accused which has not
           been properly explained the Court will be fully justified
           in framing a charge and proceeding with the trial.
           (3) The test to determine a prima facie case would
           naturally depend upon the facts of each case and it is
           difficult to lay down a rule of universal application. By
           and large however if two views are equally possible
           and the Judge is satisfied that the evidence produced
           before him while giving rise to some suspicion but not
           grave suspicion against the accused, he will be fully
           within his right to discharge the accused.
           (4 ) That in exercising his jurisdiction under Section
           227 of the Code the Judge which under the present
           Code is a senior and experienced court cannot
           act merely as a Post Office or a mouthpiece of
           the prosecution, but has to consider the broad
           probabilities of the case, the total effect of the
           evidence and the documents produced before the
           Court, any basic infirmities appearing in the case
           and so on. This however does not mean that the
           Judge should make a roving enquiry into the pros
[2024] 8 S.C.R.                                                           1255

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

             and cons of the matter and weigh the evidence as
             if he was conducting a trial.”
                                                    [emphasis added]
     20.3. To the same effect is the view expressed in Niranjan Singh
           KS Punjabi (supra) where this court has observed as follows:
             “5. Section 227, introduced for the first time in the new
             Code, confers a special power on the Judge to discharge
             an accused at the threshold if ‘upon consideration’ of the
             record and documents he considers ‘that there is not
             sufficient ground’ for proceeding against the accused.
             In other words his consideration of the record and
             document at that stage is for the limited purpose of
             ascertaining whether or not there exists sufficient grounds
             for proceeding with the trial against the accused. If he
             comes to the conclusion that there is sufficient ground to
             proceed, he will frame a charge under Section 228, if not
             he will discharge the accused. It must be remembered
             that this section was introduced in the Code to
             avoid waste of public time over cases which did not
             disclose a prima facie case and to save the accused
             from avoidable harassment and expenditure.
             6. The next question is what is the scope and
             ambit of the ‘consideration’ by the trial court at
             that stage.………..It is obvious that since he is at
             the stage of deciding whether or not there exists
             sufficient grounds for framing the charge, his
             enquiry must necessarily be limited to deciding if
             the facts emerging from the record and documents
             constitute the offence with which the accused is
             charged. At that stage he may sift the evidence
             for that limited purpose but he is not required to
             marshal the evidence with a view to separating the
             grain from the chaff. All that he is called upon to
             consider is whether there is sufficient ground to
             frame the charge and for this limited purpose he
             must weigh the material on record as well as the
             documents relied on by the prosecution.”
                                                    [emphasis Added]
1256                                                    [2024] 8 S.C.R.

                   Digital Supreme Court Reports


    20.4. In N. Suresh Rajan (supra), the following view was expressed
          as to the role of the trial Court at the time of considering an
          application for discharge.
           “29. We have bestowed our consideration to the rival
           submissions and the submissions made by Mr Ranjit
           Kumar commend us. True it is that at the time of
           consideration of the applications for discharge,
           the court cannot act as a mouthpiece of the
           prosecution or act as a post office and may sift
           evidence in order to find out whether or not the
           allegations made are groundless so as to pass
           an order of discharge. It is trite that at the stage of
           consideration of an application for discharge, the court
           has to proceed with an assumption that the materials
           brought on record by the prosecution are true and
           evaluate the said materials and documents with a
           view to find out whether the facts emerging therefrom
           taken at their face value disclose the existence of all
           the ingredients constituting the alleged offence. At this
           stage, probative value of the materials has not to be
           gone into and the court is not expected to go deep
           into the matter and hold that the materials would not
           warrant a conviction. In our opinion, what needs
           to be considered is whether there is a ground for
           presuming that the offence has been committed
           and not whether a ground for convicting the
           accused has been made out.To put it differently,
           if the court thinks that the accused might have
           committed the offence on the basis of the materials
           on record on its probative value, it can frame
           the charge; though for conviction, the court has
           to come to the conclusion that the accused has
           committed the offence. The law does not permit
           a mini trial at this stage.”
                                                 [emphasis added]
    20.5 The aforesaid parameters had to be kept in mind by the learned
         Special Judge, CBI at the time of considering the records/
         documents submitted by the respondent-CBI and the material
[2024] 8 S.C.R.                                                          1257

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           produced by the appellants. In our view, the said consideration
           is lacking in the impugned orders for the reasons noticed above.
21. CONCLUSION
     21.1 Though multiple arguments have been advanced by learned
          counsel for the appellants to assail the impugned orders
          passed by the learned Special Judge, CBI, including a plea
          that no offence is made out under Section 13(1)(d) of the P.C.
          Act for various reasons, this Court has consciously elected to
          confine itself only to those aspects that in our opinion, would
          be sufficient to arrive at a prima facie view that the allegations
          levelled against the appellants have pre-dominant contours
          of a dispute of a civil nature, does not have the makings of a
          criminal offence and on an overall conspectus of the case, would
          persuade any reasonable person to dismiss the accusations
          levelled. Therefore, this court declines to go into the nitty gritties
          of the documents/evidence, or the contrasting data produced
          by the parties to test their probative value.
     21.2 The prima facie findings of this Court, based on the documents
          and material placed before us are as follows:
           (a)   The plea of the respondent-CBI that it conducted an
                 investigation in the present case during the course of the
                 inquiry in respect of PE-5 registered by it in the year 2012
                 is belied as the SIR was on a completely different aspect.
                 CBI only got activated only on stumbling upon the Audit
                 Report of the CAG submitted in 2013. There is nothing
                 brought on record to show to the contrary.
           (b)   The CAG Report had not attained finality inasmuch as
                 its recommendations have not been tabled before the
                 Parliament or accepted so far. The said report at best,
                 has a persuasive value but no more.
           (c)   The Sanctioning Authority namely, the Board of Directors
                 of KPCL in respect of Mr. R Nagarajan, the then Finance
                 Director of KPCL and nominee Director of the Board of
                 KECML had the occasion to thoroughly scrutinize all
                 the relevant documents including the MoU dated 20th
                 December, 2008 executed between KECML and GCWL
                 as also the depositions of 67 witnesses submitted by
1258                                                    [2024] 8 S.C.R.

                   Digital Supreme Court Reports


              the respondent-CBI. Only thereafter, did it arrive at a
              conclusion that there was nothing to demonstrate that any
              rejects generated by washing of the coal had been sold
              by the appellants or that KPCL had suffered an unlawful
              loss due to the same.
        (d)   The Competent Authority in the Central Government who
              was approached by the respondent-CBI for sanction to
              prosecute Mr. Yogendra Tripathi, the then Managing
              Director of KPCL sought comments from two separate
              sources. The Government of Karnataka opined that no
              criminal intent could be attributed to the said officer. A
              proposal was also sent to the CVC for their advice. The
              CVC too recommended that the sanction for prosecuting
              the officer ought to be declined. The Competent Authority
              in the Central Government after going through the
              entire documents and material including the evidence
              submitted by the respondent-CBI and the opinions
              solicited, declined sanction for the prosecution of the
              aforesaid officer.
        (e)   The respondent-CBI did not approach the Court to
              challenge the aforesaid decisions. Having accepted the
              decision taken by the Sanctioning Authority/Competent
              Authority in the Central Government and dropping the
              charges against the seniormost functionaries in KPCL, who
              were also holding positions in the Board of KECML, there
              is no justification to press charges against the appellants
              herein whose role is similar to them.
        (f)   The decision dated 24th March, 2016 of the Karnataka High
              Court in a writ petition filed by KECML against KPCL has
              been wrongly overlooked. The High Court had an occasion
              to scrutinize the very same agreements and the CAG report
              that formed the basis of the investigation conducted by the
              respondent–CBI to return positive findings in favour of the
              appellants. The view taken by the Karnataka High Court
              has been upheld by this Court in a judgment rendered on
              20th May, 2022 which was just a few days after Charges
              were framed by the learned Special Judge, CBI on 3rd
              March, 2022.
[2024] 8 S.C.R.                                                      1259

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

           (g)   Yet again, an interpretation of the very same clauses
                 in the agreement relating to the manner of disposal off
                 the coal rejects came up for consideration before the
                 Karnataka High Court in a writ petition filed by Aryan
                 Energy against KPCL. Having scrutinized the clauses
                 forming a part of the agreement executed between the
                 parties vide judgment dated 22nd July, 2021, the Karnataka
                 High Court clearly observed that KPCL did not have any
                 claim over the coal rejects generated during washing of
                 the coal. The submissions made by the respondent – CBI
                 that the aforesaid judgment came much after institution
                 of the chargesheet by the, respondent-CBI is of no
                 consequence. Even if that was so, nothing prevented the
                 learned Special Judge, CBI from taking into consideration
                 the view expressed in the said judgement at the time of
                 framing charges, particularly, when the clause relating
                 to disposal of the coal rejects in an environment friendly
                 manner incorporated in the agreement between KPCL
                 and Aryan Energy was identical to the one contained in
                 the agreement between KPCL and KECML.
           (h)   Perusal of the relevant clauses of the JVA read in
                 conjunction with the terms and conditions stipulated in
                 the FSA leave no manner of doubt that all that KPCL
                 required KECML to do was to provide it a specified grade
                 of washed coal having a specific GCV to be purchased
                 at a predetermined price for being supplied to BPCL for
                 generation of power. The agreement between the parties
                 did not contemplate that KPCL would be entitled to claim
                 the ‘shales/stones’ that were required to be removed
                 from the coal before supplies were made by KECML.
                 Under the agreements governing the parties KECML was
                 required to dispose off the coal rejects properly, to the
                 satisfaction of environmental regulation, as prescribed
                 in Article 5(2)(b) of the JVA.
           (i)   The MoC did not impose any condition in the Notification
                 dated 16th July, 2004 which required KECML to hand
                 over the coal rejects to KPCL; nor did the MoC issue
                 any Guidelines as to the manner in which the coal
                 rejects were to be disposed of. Once the Mining Plan of
1260                                                      [2024] 8 S.C.R.

                   Digital Supreme Court Reports


              September, 2004 submitted by KECML was approved
              by the MoC, nothing further was required to be done by
              KECML except for following the conditions imposed on it.
        (j)   The Central Government had not come up with any specific
              plan to dispose off the coal rejects, as is apparent from
              a perusal of the reply submitted by the Minister of State,
              MoC in the Lok Sabha, stating that the Government had
              not framed any National Policy for exploitation of coal
              rejects and the same was still under consideration. In
              the absence of a policy to dispose off the coal rejects,
              the appellants cannot be blamed for complying with the
              terms and conditions stipulated in the JVA.
        (k)   KECML could not be faulted for failing to set up the coal
              washery at the pithead, in terms of the JVA as that was
              for reasons beyond its control which included a prolonged
              litigation between the MoC and CIPCO in relation to the
              very same coal blocks allocated to KPCL which in turn
              delayed the project considerably. Production of coal could
              only commence in September, 2008 when the curtains
              were drawn on the aforesaid litigation. The Board of KPCL
              consciously acceded to the proposal made by KECML that
              a MoU be executed with GCWL for washing of mined coal
              at its washery. Pertinently, GCWL was not an unknown
              entity to KPCL as the latter had prior dealings with the said
              Company for washing of mined coal in another project. This
              decision taken by the parties in their commercial wisdom
              has been sought to be selectively tainted with criminal
              intention attributed to the appellants, without any basis.
        (l)   There was no getting around the process of washing
              of raw coal which was the predominant prerequisite to
              meet the specified grade of coal with the defined GCV for
              generation of power at BTPS. Failure to supply washed
              coal to KPCL not only invited heavy penalties on KECML in
              terms of the JVA, it would have had serious consequences
              of stoppage of generation of power at BTPS, resulting in
              power outages in the State of Karnataka.
        (m) The Washability Report submitted by CIMFR, Nagpur,
            a Government Laboratory stated in so many words that
[2024] 8 S.C.R.                                                        1261

        M/s Karnataka Emta Coal Mines Limited and Another v.
                   Central Bureau of Investigation

                 the coal rejects did not contain any useful c.v. Therefore,
                 the entire edifice of criminality and conspiracy built by the
                 respondent-CBI on the premise that the coal rejects had
                 a commercial c.v. with an assertion that the appellants
                 had profited from the sale thereof in the open market
                 and pocketed the sale proceeds, flies in the face of the
                 Washability Report.
           (n)   The Revised Mining Plan submitted by the appellants to
                 the MoC in the year 2010 and approved in 2011, could not
                 have been relied on by the respondent-CBI for pressing
                 charges against the appellants on a plea that had the new
                 technology for utilizing the coal rejects been put to use,
                 the losses could have been mitigated. It is not in dispute
                 that the new technology namely, FBC was not even in
                 vogue when the MoC had approved the original Mining
                 Plan submitted by KECML in the year 2004. Besides that,
                 before putting the new technology to use, there were
                 several steps required to be undertaken, which included
                 obtaining approvals from different government agencies
                 and establishment of a plant. None of that could take place
                 as an order was passed by this court in the year 2014,
                 deallocating all captive coal mines.
     21.3 In the light of the aforesaid discussion, we are of the opinion
          that the respondent–CBI embarked on a roving and fishing
          inquiry on the strength of the Audit Report of the CAG and
          then started working backwards to sniff out criminal intent
          against the appellants. The underpinnings of what was a civil
          dispute premised on a contract between the parties, breach
          whereof could at best lead to determination of the contract or
          even the underlying lease deed, has been painted with the
          brush of criminality without any justification. This criminal intent
          has been threaded into the dispute by the respondent-CBI by
          misinterpreting the clauses of the agreements governing the
          parties and by heavily banking on the observations made in
          the Audit Report of the CAG that has not attained finality till
          date. In view of the glaring infirmities mentioned hereinabove,
          the impugned orders deserve interference in exercise of the
          powers vested in this court under Article 136 of the Constitution
          of India.
1262                                                   [2024] 8 S.C.R.

                       Digital Supreme Court Reports


    21.4 For all the reasons enumerated above, the present appeals
         succeed. The order on charge dated 24th December, 2021 and
         the order framing charges dated 3rd March, 2022 passed by
         the learned Special Judge, CBI qua the appellants before this
         Court are unsustainable and accordingly quashed and set aside.

    Result of the case: Appeals allowed.



    †
        Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Joint Venture Agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.