M/S KULJA INDUSTRIES LIMITEDversusCHIEF GEN. MANAGER W.T. PROJ. BSNL AND ORS.
- Citation
- 2013 INSC 673
- Decided
- 4 October 2013
- Disposal
- Appeal(s) allowed
- Bench
- T S THAKUR
Holding
A State‑owned entity may blacklist a contractor only if the decision complies with natural justice, fairness and proportionality; permanent debarment is excessive and the period must be fixed by the competent authority.
Summary
The appellant, Kulja Industries Ltd., supplied telecom equipment to BSNL under two tenders. BSNL later alleged that the appellant, in collusion with BSNL officials, received excess payments of Rs 7.98 crore through duplicate bills and blacklisted the appellant permanently. The appellant challenged the blacklisting, arguing that the tender documents allowed only a "suitable period" of debarment, that the decision lacked a fair hearing, and that permanent debarment was disproportionate. The Supreme Court held that the power to blacklist is inherent in the party awarding the contract, but when exercised by a State instrumentality it must satisfy natural justice, fairness, proportionality and non‑discrimination. Permanent debarment was deemed too harsh; the period of debarment should be fixed by the competent authority based on guidelines. The Court allowed the appeal, set aside the High Court order, affirmed the blacklisting but remanded the matter to determine the appropriate debarment period.
Issues considered
- The legality of BSNL's permanent blacklisting of the supplier under the tender provisions
- Whether the power to blacklist is limited to the specific clauses of the tender document
- Whether a decision to blacklist by a State instrumentality is subject to judicial review under Articles 226 and 32
- The requirement of natural justice, fairness, proportionality and non‑discrimination in debarment orders
- The appropriate period of debarment and whether permanent debarment is permissible
Legislation cited
- Constitution of Indias. Article 14, s. Article 226, s. Article 32
- Indian Penal Code, 1860s. Section 120B, s. Section 420
- Prevention of Corruption Act, 1988s. Section 13(1)(d), s. Section 13(2)
Subjects
Judgment
[2013) 14 S.C.R. 430
A M/S KULJA INDUSTRIES LIMITED
v.
CHIEF GEN. MANAGER W.T. PROJ. BSNL AND ORS.
(Civil Appeal No. 8944 of 2013)
OCTOBER 4, 2013
B
[T.S. THAKUR AND VIKRAMAJIT SEN, JJ.]
Contract - Contract with Government Company - For
supply of goods - Purchaser black-listed the supplier
C permanently on the ground that it committed gross misconduct
and irregularities by receiving excessive payments from the
purchaser - Held: Power to black-list a contractor is inherent
in the party allotting the contract - But if such decision is
taken by State or its instrumentalities, it is subject to judicial
D review and open to scrutiny on the touchstone of fairness,
relevance, natural justice, non-discrimination, equality and
proportionality - 'Debarment' though recognised as an
effective method for disciplining deviant suppliers, it is never
permanent - Period of debarment would invariably depend
E upon the nature of the offence committed by the erring
contractor - In the facts of present case, permanent
debarment is too harsh - Matter remanded back to competent
authority to determine the period of debarment - Constitution
of India, 1950 - Arts.226 and 32 - Judicial Review.
F Respondent-company (BSNL) entered into contract
with the appellant-Company. BSNL black-listed the
appellant permanently on the ground that the appellant
had committed gross misconduct and irregularities by
receiving excessive payments from BSNL and thereby
G wrongfully causing loss to the said company. The
appellant denied these allegations contending that BSNL
Policy/Manual did not provide for punitive action in the
nature of blacklisting and that excess payment at best
H 430
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 431
MANAGER W.T. PROJ. BSNL
could be said to be irregularity which had been cured by A
refund of the amount. The question for consideration in
the present appeal is whether BSNL could have
blacklisted the appellant for allotment of future contracts
for all times to come.
B
Allowing the appeal, the Court
HELD: 1. A literal construction of the provisions of
paras 31 and 32 of the bid document would mean that the
power to disqualify or blacklist a supplier is available to
the purchaser only in the three situations enumerated in C
paras 31 and 32 and no other. Any such interpretation
would, however, give rise to anomalous results. It is
because, in cases where a supplier is found guilty of
much graver offences, failures or violations, resulting in
much heavier losses and greater detriment to the D
purchasers in terms of money, reputation or prejudice to
public interest may go unpunished simply because all
such acts of fraud, misrepresentation or the like have not
been specifically enumerated as grounds for blacklisting
of the supplier in paras 31 and 32 of the tender document. E
That could never be the true intention of the purchaser
wh~n it stipulated paras 31 and 32 as conditions of the
tender document by which the purchaser has reserved
to itself the right to disqualify or blacklist bidders for
breach or violation committed by them. If bidders who F
commit a breach of a lesser degree could be punished
by an order of blacklisting there is no reason why a
breach of a more serious nature should go unpunished,
be ignored or rendered inconsequential by reason only
of an omission of such breach or violation in the text of G
paras 31 and 32 of the tender document. Paras 31 and
32 cannot, in that view, be said to be exhaustive; nor is
the power to blacklist limited to situations mentioned
therein. [Para 16) [442-H; 443-A-D)
2. The power to blacklist a contractor whether the H
432 SUPREME COURT REPORTS [2013] 14 S.C.R.
A contract be for supply of material or equipment or for the
execution of any other work whatsoever is inherent in the
party allotting the contract. There is no need for any such
power being specifically conferred by statute or reserved
by contractor. That is because 'blacklisting' simply
s signifies a business decision by which the party affected
by the breach decides not to enter into any contractual
relationship with the party committing the breach.
Between two private parties the right to take any such
decision is absolute and untrammelled by any
c constraints whatsoever. The freedom to contract or not
to contract is unqualified in the case of private parties.
But any such decision is subject to judicial review when
the same is taken by the State or any of Its
instrumentalities. This implies that any such decision will
be open to scrutiny not only on the touchstone of the
0
principles of natural justice but also on the doctrine of
proportionality. A fair hearing to the party being
blacklisted thus becomes an essential pre-condition for
a proper exercise of the power and a valid order of
blacklisting made pursuant thereto. The order itself being
E reasonable, fair and proportionate to the gl'avity of the
offence is similarly examinable by a writ Court. [Para 17]
[443-E-H; 444-A]
Erusian Equipment and Chemicals Ltd. vs. State of West
F Bengal and Anr. (1975) 1 SCC 70: 1975 (2) SCR 674; Mis
Southern Painters vs. fertilizers and Chemicals Travancore
Ltd. and Anr. AIR 1994 SC 1277; Patel Engineering Ltd.
Union of India (2012) 11 SCC 257; B.S.N. Joshi and Sons
Ltd. vs. Nair Coal Services Ltd. and Ors. (2006) 11 SCC 548:
G 2006 (8) Suppl. SCR 11; Joseph Vilangandan vs. The
Executive Engineer, (PWD) Emakulam and Ors. (1978) 3
sec 36: 1978 (3) SCR 514 - relied on.
3. Every matter that is subject to judicial review before
a Writ Court exercising powers under Article 226 or Article
H
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 433
MANAGER W.T. PROJ. BSNL
32 of the Constitution cannot be arbitrary or A
discriminatory. Even though the right of the writ
petitioner is in the nature of a contractual right, the
manner, the method and the motive behind the decision
of the authority whether or not to enter into a contract is
subject to judicial review on the touchstone of fairness, B
relevance, natural justice, non-discrimination, equality
and proportionality. All these considerations that go to
determine whether the action is sustainable in law have
been sanctified by judicial pronouncements of this Court
and are of seminal importance in a system that is c
committed to the rule of law. [Para 19) [445-C-D]
Radha krishna Agarwal and Ors. vs. State of Bihar and
Ors. (1977) 3 SCC 457: 1977 (3) SCR 249; E.P. Royappa
vs. State of Tamil Nadu and Anr. (1974) 4 sec 3: 1974 (2)
SCR 348; Maneka Gandhi vs. Union of India and Anr. (1978) D
1 SCC 248: 1978 (2) SCR 621; Ajay Hasia and Ors. vs.
Khalid Mujib Sehravardi and Ors. (1981) 1 SCC 722: 1981
(2) SCR 79; R.D. Shetty vs. International Airport Authority of
India and Ors., (1979) 3 SCC 489: 1979 (3) SCR 1014;
Dwarkadas Marfatia and sons vs. Board of Trustees of the E
Port of Bombay (1989) 3 SCC 751; Mis Mahabir Auto Stores
and Ors. vs. Indian Oil Corporation Ltd. (1990) 3 SCC 752:
1990 (1) SCR 818 - relied on.
4. 'Debarment' is recognised and often used as an F
effective method for disciplining deviant suppliers/
contractors who may have committed acts of omission
and commission or frauds including misrepresentations,
falsification of records and other breaches of the
regulations under which such contracts were allotted. G
What is notable is that the 'debarment' is never
permanent and the period of debarment would invariably
depend upon the nature of the offence committed by the
erring contractor. [Para 24) [449-G; 450-A]
5. In the present case according to the respondent- H
434 SUPREME COURT REPORTS [2013] 14 S.C.R.
A BSNL, the appellant had fraudulently withdrawn a huge
amount of money which was not due to it,· in collusion
and conspiracy with the officials of the respondent-
corporation. Even so permanent debarment from future
contracts for all times to come may sound too harsh and
B heavy a punishment to be considered reasonable
especially when (a) the appellant is supplying bulk of its
manufactured products to the respondent-BSNL and (b)
The excess amount received by it has already been paid
back. [Para 25) [450-B-C]
c 6. A remand back to the competent authority would
be a more appropriate option to determine the period for
which the appellant would remain blacklisted. This is,
firstly because blacklisting is in the nature of penalty the
quantum whereof is a matter that rests primarily with the
D authority competent to impose the same. Secondly,
because while determining the period for which the
blacklisting should be effective, the respondent-
Corporation may for the sake of objectivity and
transparency formulate broad guidelines to be followed
E in such cases. Different periods Qf debarment depending
upon the gravity of the offences, violations and breaches
may be prescribed by such guidelines. While, it may not
be possible to exhaustively enumerate all types of
offences and acts of misdemeanour, or violations of
F contractual obligations by a contractor, the respondent-
Corporati~n may do so as far as possible to reduce if not
totally eliminate arbitrariness in the exercise of the power
vested in it and inspire confidence in the fairness of the
order which the competent authority may pass against a
G defaulting contractor. [Para 26) [450-E-H; 451-A-BJ
Case Law Reference:
1975 (2) SCR 67 4 relied on Para 17
AIR 1994 SC 1277 relied on Para 18
H
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 435
MANAGER W.T. PROJ. BSNL
(2012) 11 sec 251 relied on Para 18 A
2006 (8) Suppl. SCR 11 relied on Para 18
1978 (3) SCR 514 relied on Para 18
1977 (3) SCR 249 relied on Para 19 B
1974 (2) SCR 348 relied on Para 19
1978 (2) SCR 621 relied on Para 19
1981 (2) SCR 79 relied on Para 19
c
1979 (3) SCR 1014 relied on Para 19
(1989) 3 sec 151 relied on Para 19
1990 (1) SCR 818 relied on Para 19
CIVIL APPELLATE JURISDICTION : Civil Appeal No. D
8944 of 2013.
From the Judgment & Order dated 06.04.2011 of the High
Court of Judicature at Bombay in Writ Petition No. 2289 of
2011. E
Mukul Rohatgi, Pravin H. Parekh, Sumit Goel, Ritika Sethi,
Abhishek Vinod Deshmukh (for Parekh & Co.) for the Appellant.
Vikas Bansal, Madhurima Mridual, D.S. Mahra, Gaurav
Agrawal, Arvind Kumar Sharma for the Respondents. F
The Judgment of the Court was delivered by
T.S. THAKUR, J. 1. Leave granted.
2. The short question that falls for determination in this G
appeal is whether the respondent-Bharat Sanchar Nigam
Limited (for short 'BSNL') could have blacklisted the appellant
for allotment of future contracts for all times to come. High Court
of Judicature at Bombay before whom the blacklisting order
was assailed by the appeliant has answered that question in H
436 SUPREME COURT REPORTS [2013] 14 S.C.R.
A the affirmative and dismissed Writ Petition No.2289 of 2011
filed by the appellant giving rise to the present appeal.
3. Two tender notices for supply of Permanent Lubricated
HOPE Pipe (Telecom Ducts) and Installation of O.F. Cable
through Blowing Technique were issued by BSNL in the year
8
2004 and 2005. It is common ground that the appellant-
company emerged successful in regard to both the tender
notices. It is also not in dispute that several orders for supply
of the material were placed with the appellant-company during
the years 2004-2006 and that goods were supplied to various
C consignee units of BSNL pursuant to the same. The appellant's
case is that a "receipt certificate" was issued in its favour after
delivery of the goods and that bills for payment of the price of
the goods were raised in triplicate to the Chief Controller of
Accounts, WTP BSNL, Mumbai from time to time. The
D appellant's further case is that a single account to receive 95%
of the payment due from BSNL was maintained by it and since
the amounts received from the respondent-BSNL by cheques
did not carry any particulars of the consignment for which such
payment was being made it could, in no way, discover excess
E payment, if any, releasep by BSNL against the bills sent by the
appellant.
4. The appellant's further case is that on gaining
knowledge about the excess payments received by it, an offer
F for reconciliation of the accounts was made to the BSNL and
since any such reconciliation was likely to take 30 to 45 days,
the appellant offered to adjust the excess amount credited to
its account towards the outstanding bills on an ad hoc basis.
A letter dated 10th May, 2006 was, according to the appellant,
G addressed to the respondent-BSNL in that regard.
5. The respondent-BSNL on the other hand has a different
story to tell. According to it four of its officers had abused their
official position and fraudulently generated 'voucher numbers'
on the dupiicate and triplicate copies of the bills submitted by
H the appellant to facilitate payments as if the said bills were
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 437
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
genuine thereby causing wrongful loss to the respondent-BSNL A
and a corresponding gain to the appellant. There was in this
process an excess payment of Rs.7.98 crores made and
credited to the account of the appellant by the accounts officer
of respondent-BSNL.
B
6. Taking note of the fraudulent payments made to the
appellant, the BSNL lodged an FIR with CBI ACB Mumbai
against one of its Senior Accounts Officers and a Director of
the appellant-company alleging commission of offences
punishable under Section 120B read with Section 420 Indian C
Penal Code and Section 13(2) read with Section 13(1)(d) of
Prevention of Corruption Act, 1988. Investigation that followed
has culminated in a charge-sheet filed before the Special
Judge for CBI cases, Bombay in which four officials of the
BSNL including D. Tripathi-Senior Accounts Officer, Laxman
Dixit-Assistant Accounts Officer, Krishnakumari Patnaik-Junior D
Accounts Officer, Poolchand Yadav-Cashier and Lalit Gupta-
Director and Bhavani Sharma-Consultant of the appellant-
company have been arraigned as accused persons.
7. What is important for the present is that by a letter dated E
21st April, 2010, BSNL blacklisted the appellant permanently
on the ground that the appellant had committed gross
misconduct and irregularities by receiving excessive payments
amounting to Rs. 7,98,55,508/- from BSNL thereby wrongfully
causing loss to the said company. The appellant denied these F
allegations, inter alia, contending that BSNL Policy/Manual did
not provide for punitive action In the nature of blacklisting and
that excess payment at best was an irregularity which had been
cured by refund of the amount in question. The appellant also
alleged that reconciliation of accounts revealed that the G
appellant was entitled to an amount, far in excess of the
payments received by it. That assertion was repeated in a legal
notice sent by the appellant-company but since BSNL took no
corrective action in terms of the reconciliation, W.P. No.4536
of 2010 was filed before the High Court of Judicature at H
438 SUPREME COURT REPORTS [2013) 14 S.C.R.
A Bombay in which it assailed the blacklisting order. The High
Court allowed the petition on the short ground that the appellant
had not been afforded any opportunity of being heard before
the blacklisting order was issued by the respondent. The High
Court did not go into the merits of the dispute but reserved
B liberty to the appellant to raise all such contentions as were
open to it if and when BSNL issued a show cause notice for
blacklisting it again. The BSNL was left free to pass a fresh
order and take a final decision in the matter within six weeks
from the date of the issue of the show cause notice.
c 8. A show cause notice was accordingly issued by BSNL
on 4th November, 2010 to which the appellant filed a reply. The
appellant was also called for a personal hearing in support of
its reply to the show cause notice as directed by the High Court.
By an order dated 15th January, 2011 BSNL once again
D directed the blacklisting of the appellant, inter alia, holding that
the appellant had defrauded BSNL by using duplicate and
triplicate copies of the bills that stood already cleared for
payment. These bogus and fraudulent claims made under
bogus and fabricated bills were then processed by some of the
E officers of the BSNL for payment resulting in doubl~ and at
times triple payment in favour of the appellant. The relevant
portion of the blacklisting order is to the following effect:
"Hence, the supplier with a clear intention to
F defraud BSNL, WTP, Mumbai, have prepared duplicate
and triplicate copies of bills already processed for
payment and have again put up the same for payment
with BSNL. Thus, in short tl1ese were bogus and/or
fraudulent claims made on the basis of forged and/or
fabricated bills/documents. Thereafter, by joining hands
G
with some of the erring officers of BSNL, the supplier has
got the afore mentioned duplicate and triplicate copies
of bills processed for payment and have fraudulently
received double/triple payment(s) for supplying material
only once.
H
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 439
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
Therefore, by not only claiming but also receiving A
double and/or triple payment on the basis of forged!
fabricated/duplicate and triplicate copies of same bills,
the supplier has committed gross fraud on the public
exchequer. The fraudulent act on the part of supplier got
completed by not only claiming such bogus payments B
but also by receiving the same from BSNL. Moreover, by
letter dated 10th May, 2006, the supplier has not only
acknowledged but have also accepted the fact of
claiming as also accepting aforesaid bogus payments
and hence the supplier had agreed for reconciliation of c
same after deducting such bogus payments. If the
accounts would not have reconciled, the supplier would
have caused huge losses to the public exchequer.
Hence, there is every apprehension that if the
supplier is allowed to deal in any manner with the BSNL D
in future, the supplier will venture into committing same
and/or similar fraud (s) on the public exchequer and
therefore, it is not at all in the interest of public exchequer
that the supplier continues to be authorised supplier of
BSNL. E
Hence, in view of the all the above facts and
circumstances and the entire record and proceedings of
this case, it is possible for this organisation to take a view
to permanent banning and impose penalty upon the F
supplier so as to prevent the supplier from dealing with
entire BSNL,' throughout the country in any manne'r,
consequently stopping all the future business
transactions of entire BSNL with the supplier.
Hereby Mis. Kulja Industries Ltd., Solan (Himachal G
Pradesh) is permanently banned and is consequently
prevented from having any business dealing with entire
BSNL through the country.
This is issued with the approval of the competent H
440 SUPREME COURT REPORTS [2013] 14 S.C.R.
A authority.
Sdl-
AGM (MM) 15.1.2011
B O!o CGM, WTP, Mumbai-54n
9. Aggrieved by the above order the appellant once again
approached the High Court in W.P. No. 2289 of 2011 which
was heard and dismissed by a Division Bench of the High Court
C in terms of the order impugned in this appeal. The High Court
was of the opinion that reconciliation of the account had proved
that the appellant had received payment twice over for the
supplies made by it and that merely because the excess
payment received had been subsequently refunded by the
appellant did not obliterate the act of misconduct and fraud. The
D High Court observed:
"In the order impugned, the Authority has stated that
on the reconciliation of the account, it was found as a fact
that the Petitioner has received payment twice for the
E supply of the same material, because the supply was
ongoing and the amount was found to be payable to the
Petitioner, that was paid to him. Mere payment of the
amount does not wipe out the fact that the Petitioner had
submitted the Bills claiming double payment. In our
F opinion, in view of this finding, no interference is called
for in the order impugned. The Petition is rejected. No
costs." ·
10. The present appl;!al calls in question the correctness
of the above order of the High Court as noticed earlier.
G
11. Appearing for the appellant-company, Mr. Mukul
Rohatgi, strenuously argued that debarring the appellant
permanently and for all times to come was wholly arbitrary and
unjustified. It was contended that the blacklisting order had
H
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 441
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
serious civil consequences for the person blacklisted making A
it obligatory for the Authority passing the order to act fairly and
reasonably. Inasmuch as respondent-BSNL had blacklisted the
appellant permanently, the decision was neither'fair nor
reasonable. Paras 31 and 32 of the bid document also,
according to the learned counsel, provides for blacklisting only B
for a "suitable period". This implies that blacklisting had to be
for a definite period and not for all times to come. Since the
products manufactured by the appellant were mostly, if not
entirely, supplied for consumption to the respondent-BSNL, any
order permanently blacklisting the appellant from entering into c
contracts making supplies was tantamount to rendering the
appellant jobless and economically defunct. No such order of
blacklisting could, therefore, be sustained as the punishment
implicit in such an order was totally disproportionate to the
gravity of the offence allegedly committed by the appellant. D
12. On behalf of the respondent-BSNL, it was argued by
Mr. Bansal that the blacklisting order under challenge was not
relatable to paras 31 and 32 of the bid document. The order
simply declared the petitioner-company ineligible for allotment
of any contract in future in terms of para 2.3 of the tender E
document, the relevant portion wherefore reads as under:
"2.3 Disqualification Clause: The supplier/ Manufacturers
in the following category are not eligible to bid in the said
tender. F
i.
ii. Firms against whom investigation cases are registered
with the CBI or other statutory investigations agencies of
State/Central Govt. G
iii "
13. It was further contended by the learned counsel that
even if the order was held to be referable to paras 31 and 32
H
442 SUPREME COURT REPORTS [2013] 14 S.C.R.
A of the bid document, an order permanently blacklisting the
appellant was also justified having regard to the nature of the
fraud committed by it in collusion with the officers of the
respondent-corporation and involving a huge amount of nearly
eight crores.
B
14. We may at the outset deal with the contention whether
paras 31 and 32 of the, bid document to which Mr. Rohtagi has
made reference is the· only source of the power to blacklist a
defaulting contractor. These paras are as under:
c "31. Purchaser reserves the right to disqualify the supplier
for a suitable period who habitually failed to supply the
equipment in time. Further, the suppliers whose
equipment do not perform satisfactory in the field in
accordance with the specifications may also be
D disqualified for a suitable period as decided by the
purchaser.
32. Purchaser reserves the right to blacklist a bidder for
a suitable period in case he fails to honour his bid without
sufficient grounds."
E
15. A plain reading of the above would show that BSNL,
the purchaser has reserved the right to disqualify any supplier
who
F (a) habitually fails to supply the equipment in time or (b)
the equipment supplied by the supplier does not perform
· satisfactory in the field in accordance with the
specifications or
(c) fails to honour his bid without sufficient grounds.
G
16. A literal construction of the provisions of paras 31 and
32 extracted above would mean that the power to disqualify or
blacklist a supplier is available to the purchaser only in the three
situations enumerated in paras 31 and 32 and no other. Any
H such interpretation would, however, give rise to anomalous
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 443
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
results. We say so because in cases where a supplier is found A
guilty of much graver offences, failures or violations, resulting
in much heavier losses and greater detriment to the purchasers
in terms of money, reputation cir prejudice to public interest may
go unpunished simply because all such acts of fraud,
misrepresentation or the like have not been specifically B
enumerated as grounds for blacklisting of the supplier in paras
31 and 32 of the tender document. That could in our opinion
never be the true intention of the purchaser when it stipulated
paras 31 and 32 as conditions of the tender document by which
the purchaser has reserved to itself the right to disqualify or c
blacklist bidders for breach or violation committed by them. If
bidders who commit a breach of a lesser degree could be
punished by an order of blacklisting there is no reason why a
breach of a more serious nature should go unpunished, be
ignored or rendered inconsequentis:il by reason only of an
D
omission of such breach or violation in the text of paras 31 and
32 of the tender document. Paras 31 and 32 cannot, in that
view, be said to be exhaustive; nor is the power to blacklist
limited to situations mentioned therein.
17. That apart the power to blacklist a contractor wheth~ir E
the contract be for supply of material or equipment or for the
execution of any other work whatsoever is in our opinion
inherent in the party allotting the contract. There is no need for
any such power being specifically conferred by statute or
reserved by contractor. That is because 'blacklisting' simply F
signifies a business decision by wh,ich tile party affected by the
breach decides not to enter into any contractual relationship
with the party committing the breach. Between two private
parties the right to take any such decision is absolute and
untrammelled by any constraints whatsoever. The freedom to G
contract or not to contract is unqualified in the case of private
parties. But any such decision is subject to judicial review when
the same is taken by the State or any of its instrumentalities.
This implies that any such decision will be open to scr:.itiny not
only on the touchstone of the principles of natural justice but also H
444 SUPREME COURT REPORTS [2013) 14 S.C.R.
A on the doctrine of proportionality. A fair hearing to the party
being blacklisted thus becomes an essential pre-condition for
a proper exercise of the power and a valid order of blacklisting
made pursuant thereto. The order itself being reasonable, fair
and proportionate to the gravity of the offence is similarly
B examinable by a writ Court. The legal position on the subject
is settled by a long line of decisions rendered by this Court
starting with Erusian Equipment & Chemicals Ltd. v. State of
West Bengal and Anr. (1975) 1 SCC 70 where this Court
declared that blacklisting has the effect of preventing a person
c from entering into lawful relationship with the Government for
purposes of gains and that the Authority passing any such order
was required to give a fair hearing before passing an order
blacklisting a certain entity. This Court observed:
"20. Blacklisting has the effect of preventing a person
D from the privilege and advantage of entering into lawful
relationship with the Government for purposes of gains.
The fact that a disability is created by the order of
blacklisting indicates that the relevant authority is to have
an objective satisfaction. Fundamentals of fair play
E require tha,t the person concerned should be given an
opportunity to represent his case before he is put on the
blacklist. "
18. Subsequent decisions of this Court in M/s Southern
F Painters v. Fertilizers & Chemicals Travancore Ltd. and Anr.
AIR 1994 SC 1277; Patel Engineering Ltd. Union of India
(2012) 11 SCC 257; B.S.N. Joshi & Sons Ltd. v. Nair Coal
Services Ltd. & Ors. (2006) 11 SCC 548; Joseph Vilangandan
v. The Executive Engineer, (PWD) Ernakulam & Ors. (1978)
G 3 SCC 36 among others have followed the ratio of that decision
and applied the principle of audi alteram partem to the process
that may eventually culminate in the blacklisting of a contractor.
19. Even the second facet of the scrutiny which the
blacklisting order must suffer is no longer res integra. The
H decisions of this Court in Radha krishna Agarwal and Ors. v.
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 445
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
State of Bihar & Ors. (1977) 3 SCC 457; E.P. Royappa v. A
State of Tamil Nadu and Anr. (1974) 4 SCC 3; Maneka
Gandhi v. Union of India and Anr. (1978) 1 SCC 248; Ajay
Hasia and Ors. v. Khalid Mujib Sehravardi and Ors., (1981)
1 SCC 722; R. D. Sheffy v. International Airport Authority of
India and Ors., (1979) 3 SCC 489 and Dwarkadas Marfatia B.
and sons v. Board of Trustees of the Port ofBombay (1989)
3 sec 751 have ruled against arbitrariness and discrimination
in every matter that is subject to judicial review before a Writ
Court exercising powers under Article 226 or Article 32 of the
Constitution. It is also well settled that even though the right of c
the writ petitioner is in the nature of a contractual right, the
manner, the method and the motive behind the decision of the
authority whether or not to enter into a contract is subject to
judicial review on the touchstone of fairness, relevance, natural
justice, non-discrimination, equality and proportionality. All these
0
considerations that go to determine whether the action is
sustainable in law have been sanctified by judicial
pronouncements of this Court and are of seminal importance
in a system that is committed to the rule of law. We do not
consider it necessary to burden this judgment by a copious
E
reference to the decisions on the subject. A reference to the
following passage from the decision of this Court in Mis
Mahabir Auto Stores & Ors. v. Indian Oil Corporation Ltd.,
(1990) 3 sec 752 should, in our view, suffice:
"11. It is well settled that every action of the State or an F
instrumentality o( the State in exercise of its executive
power, must be informed by reason. Jn appropriate cases,
actions uninformed by reason may be questioned as
arbitrary in proceedings under Article 226 or Article 32
of the Constitution. Reliance in this connection may be G
placed on the obseNations of this Court in Miss Radha
Krishna Agarwal and Ors. v. State of Bihar and Ors.,
[1977] 3 SCR 249 ...... In case any right conferred on the
citizens which is sought to be interfered, such action is
subject to Article 14 of the Constitution, and must be H
446 SUPREME COURT REPORTS [2013] 14 S.C.R.
A reasonable and can be taken only upon lawful and
relevant grounds of public interest. Where there is
arbitrariness in State action of this type of entering or not
entering into contracts, Article 14 springs up and judicial
review strikes such an action down. Every action of the
B State executive authority must be subject to rule of Jaw
and must be informed by reason. So, whatever be the
activity of the public authority, in such monopoly or semi-
monopoly dealings, it should meet the test of Article 14
of the Constitution. If a Governmental action even in the
c matters of entering or not entering into contracts, fails to
satisfy the test of reasonableness, the same would be
unreasonable....... It appears to us that rule of reason
and rule against arbitrariness and discrimination, rules
of fair play and natural justice are part of the rule of law
applicable in situation or action by State instrumentality
D
in dealing with citizens in a situation like the present one.
Even though the rights of the citizens are in the nature
of contractual rights, the manner, the method and motive
of a decision of entering or not entering into a contract,
are subject to judicial review on the touchstone of
E relevance and reasonableness, fair play, natural justice,
equality and non-discrimination in the type of the
transactions and nature of the dealing as in the present
case."
F 20. The legal position governing blacklisting of suppliers
in USA and UK.is ro different. In USA instead of using the,
expression 'Blacklisting' the term "debarring" is used by the
Statutes and the Courts. The Federal Government considers
'suspension and debarment' as a powerful tool for protecting
G taxpayer resources and maintaining integrity of the processes
for federal acquisitions. Comprehensive guidelines are,
therefore, issued by the government for protecting public
interest from those contractors and recipients who are non-
responsible, lack business integrity or engage in dishonest or
H illegal conduct or are otherwise unable to perform satisfactorily.
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 447
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
These guidelines prescribe the following among other grounds A
for debarment:
(a) Conviction of or civil judgment for -
(1) Commission of fraud or a criminal offense in
connection with obtaining, attempting to obtain, or B
performing a public or private agreement or
transaction;
(2) Violation of Federal or State antitrust statutes,
including those proscribing price fixing between c
competitors, allocation of customers between
competitors, and bid rigging;
(3) Commission of embezzlement, theft, forgery,
bribery, falsification or destruction of records,
making false statements, tax evasion, receiving D
stolen property, making false claims, or
obstruction of justice; or
(4) Commission of any other offense indicating a lack
of business integrity or business honesty that E
seriously and directly affects your present
responsibility;
(b) iolation of the terms of a public agreement or
transaction so serious as to affect the integrity F
of an agency program, such as-
(1) A willful failure to perform in accordance with the
terms of one or more public agreements or
transactions;
G
(2) A history of failure to perform or o( unsatisfactory
performance of one or more public agreements or
transactions; or
(3) A willful violation of a statutory or regulatory
H
448 SUPREME COURT REPORTS [2013] 14 S.C.R.
A provision or requirement applicable to a public
agreement or transaction;
(c) xxxx
(d) Any other cause of so serious or compelling a
B nature that it affects your present
responsibility.
21. The guidelines also stipulate the factors that may
influence the debarring official's decision which include the
C following:
(a) The actual or potential harm or impact that results
or may result from the wrongdoing.
(b) The frequency of incidents and/or duration of the
D wrongdoing.
(c) Whether there is a pattern or prior history of
wrongdoing.
(d) Whether contractor has been excluded or
E disqualified by an, agency of the Federal
Government or have not been allowed to
participate in State or local contracts or assistance
agreements on a basis of conduct similar to one
or more of the causes for debarment specified in
F this part.
(e) Whether and to what extent did the contractor plan,
initiate or carry out the wrongdoing.
(f) Whether the . contractor has accepted
G responsibility for the wrongdoing and recognized
the seriousness of the misconduct.
(g) Whether the contractor has paid or agreed to pay
all criminal, civil and administrative liabilities for
H the improper activity, including any investigative
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 449
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
or administrative costs incurred by the A
government, and have made or agreed to make
full restitution.
((h) Whether contractor has cooperated fully with the
government agencies during the investigation and 8
any court or administrative action.
(i) Whether the wrongdoing was peNasive within the
contractor's organization.
(j) The kind of positions held by the individuals C
involved in the wrongdoing.
(k) Whether the contractor has taken appropriate
corrective action or remedial measures, such as
establishing ethics training and implementing D
programs to prevent recurrence.
(/) Whether the contractor fully investigated the
circumstances surrounding the cause for
debarment and, if so, made the result of the
investigation. available to the debarring official." E
22. As regards the period for which the order of debarment
will remain effective, the guidelines state that the same would
depend upon the seriousness of the case leading to such
debarment.
F
23. Similarly in England, Wales and Northern Ireland, there
are statutory provisions that make operators ineligible on
several grounds including fraud, fraudulent trading or conspiracy
to defraud, bribery etc.
G
24. Suffice it to say that 'debarment' is recognised and
often used as an effective method for disciplining deviant
suppliers/contractors who may have committed acts of
omission and commission or frauds including
misrepresentations, falsification of records and other breaches H
450 SUPREME COURT REPORTS [2013] 14 S.C.R.
A of the regulations under which such contracts were allotted.
What is notable is that the 'debarment' is never permanent and
the period of debarment would invariably depend upon the
nature of the offence committed by the erring contractor.
• :25. In the case at hand according to the respondent-BSNL,
8
the aippellant had fraudulently withdrawn a huge amount of
money which was not due to it in collusion and conspiracy with
the officials of the respondent-corporation. Even so permanent
debarment from future contracts for all times to come may
sound too harsh and heavy a punishment to be considered
C reasonable especially when (a) the appellant is supplying bulk
of its manufactured products to the respondent-BSNL and (b}
The excess amount received by it has already been paid back.
~~6. The next question then is whether this Court ought to
D itself determine the time period for which the appellant should
be blacklisted or remit the matter back to the authority to do
so having regard to the attendant facts and circumstances. A
remand back to the competent authority has appealed to us to
be a more appropriate option than an order by which we may
E ourselves determine the period for which the appellant would
remain blacklisted. We say so for two precise reasons. Firstly,
because blacklisting is in the nature of penalty the quantum
whemof is a matter that rests primarily with the authority
competent to impose the same. In the realm of service
F jurisprudence this Court has no doubt cut short the agony of a
delinquent employee in exceptional circumstances to prevent
delay and further litigation by modifying the quantum of
punishment but such considerations do not apply to a company
engaged in a lucrative business like supply of optical fibre/
G HOPE pipes to BSNL. Secondly, because while determining
the pmiod for which the blacklisting should be effective the
respondent-Corporation may for the sake of objectivity and
transparency formulate broad guidelines to be followed in such
cases. Different periods of debarment depending upon the
H gravity of the offences, violations and breaches may be
KULJA INDUSTRIES LIMITED v. CHIEF GEN. 451
MANAGER W.T. PROJ. BSNL [T.S. THAKUR, J.]
prescribed by such guidelines. While, it may not be possible A
to exhaustively enumerate all types of offences and acts of
misdemeanour, or violations of contractual obligations by a
· contractor, the respondent-Corporation may do so as far as
possible to reduce if not totally eliminate arbitrariness in the
exercise of the power vested in it and inspire confidence in the 8
fairness of the order which the competent authority may pass
against a defaulting contractor.
27. In the result, we allow this appeal, set aside the order
passed by the High Court and allow writ petition No.2289 of
2011 filed by the appellant but only to the extent that while the C
order blacklisting the appellant shall stand affirmed, the period
for which such order remains operative shall be determined
afresh by the competent authority on the basis of guidelines
which the Corporation may formulate for that purpose. The
needful shall be done by the Corporation and/or the competent D
authority expeditiously but not later than six months from today.
The parties are left to bear their own costs.
Kalpana K. Tripathy Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.