M/S PREM COTTEXversusUTTAR HARYANA BIJLI VITRAN NIGAM LTD. & ORS.
- Citation
- 2021 INSC 617
- Decided
- 5 October 2021
- Disposal
- Dismissed
- Bench
- HEMANT GUPTA
Holding
The raising of an additional demand for short billing does not amount to a deficiency in service, and Section 56(2) does not bar recovery in the present facts, leading to dismissal of the appeal.
Summary
M/S Prem Cottex, a cotton yarn manufacturer, was issued a short assessment notice by Uttarakhand Bijli Vitran Nigam Ltd. alleging that the multiply factor (MF) used in its electricity bills was incorrectly applied, resulting in short billing of about Rs.1.35 crore. The appellant filed a consumer complaint under the Consumer Protection Act, 1986, claiming a deficiency in service and invoking the two‑year bar on recovery under Section 56(2) of the Electricity Act, 2003. The National Consumer Dispute Redressal Commission dismissed the complaint, holding that the issue was an "escaped assessment" rather than a deficiency in service. On appeal, the Supreme Court held that raising an additional demand for short billing does not constitute a deficiency in service and that the respondents were not liable under the CPA. The Court further clarified that Section 56(2) bars both recovery and disconnection, but the bar does not apply where the demand is raised after the mistake is discovered and the limitation period has not commenced. Consequently, the appeal was dismissed and the appellant was directed to pay the remaining amount of the demand.
Issues considered
- Whether the issuance of a short assessment notice for short billing amounts to a deficiency in service under the Consumer Protection Act, 1986.
- Interpretation of Section 56(2) of the Electricity Act, 2003 – does it bar both recovery of dues and disconnection of supply, and how does the limitation period apply.
Legislation cited
- Consumer Protection Act, 1986s. 2(1)(g)
- Electricity Act, 2003s. 56(1), s. 56(2)
- Limitation Act, 1963s. 17(1)(c)
Subjects
Judgment
[2021] 8 S.C.R. 645 645
M/S PREM COTTEX A
v.
UTTAR HARYANA BIJLI VITRAN NIGAM LTD. & ORS.
(Civil Appeal No. 7235 of 2009)
OCTOBER 05, 2021 B
[HEMANT GUPTA AND V. RAMASUBRAMANIAN, JJ.]
Consumer Protection Act, 1986 – 2(1)(g) – Deficiency in
service – When not – Additional demand raised by respondent no.3
alleging short billing in view of wrong multiply factor (MF) applied C
in the bills raised for particular period – Challenged by appellant
inter alia pleading bar u/s.56, 2003 Act – Complaint dismissed by
National Consumer Dispute Redressal Commission – On appeal,
held: Before going into the question of bar u/s.56(2), the consumer
forum is obliged to find out at the threshold whether there was any
deficiency in service – Raising of an additional demand in the form D
of short assessment notice, on the ground that the multiply factor
was wrongly mentioned in the bills raised during particular period,
does not tantamount to deficiency in service – If a licensee discovers
in the course of audit or otherwise that a consumer has been short
billed, it is entitled to raise a demand – So long as the consumer E
does not dispute the correctness of the claim made by the licensee
that there was short assessment, it is not open to the consumer to
claim that there was any deficiency – Appellant never disputed the
correctness of the respondents’ claim that the MF to be applied was
10, but it was wrongly applied as 5 – National Commission correctly
pointed out that it is a case of “escaped assessment” and not F
“deficiency in service” – Respondents not guilty of any deficiency
in service – Complaint rightly dismissed – Electricity Act, 2003 –
s.56(2).
Electricity Act, 2003 – s.56(2) – Bar under – Held: Bar u/
s.56(2) operates on two distinct rights of the licensee, (i) the right G
to recover (ii) the right to disconnect – Bar with reference to the
enforcement of the right to disconnect, is an exception to the law of
limitation – Limitation Act, 1963.
Electricity Act, 2003 – s.56(1) – Impact of, on s.56(2) –
Discussed. H
645
646 SUPREME COURT REPORTS [2021] 8 S.C.R.
A Dismissing the appeal, the Court
HELD: 1.1 The appellant never disputed the correctness
of the claim of the respondents that the multiply factor (MF) to
be applied was 10, but it was wrongly applied as 5. A careful
reading of Section 56(2), Electricity Act, 2003 would show that
B the bar contained therein is not merely w ith respect to
disconnection of supply but also with respect to recovery. If Sub-
section (2) of Section 56 is dissected into two parts it will read as
follows :-(i) No sum due from any consumer under this Section
shall be recoverable after the period of two years from the date
when such sum became first due; and (ii) the licensee shall not
C cut off the supply of electricity. Therefore, the bar actually operates
on two distinct rights of the licensee, namely, (i) the right to
recover; and (ii) the right to disconnect. The bar with reference
to the enforcement of the right to disconnect, is actually an
exception to the law of limitation. Under the law of limitation,
D what is extinguished is the remedy and not the right. What is
extinguished by the law of limitation, is the remedy through a
court of law and not a remedy available, if any, de hors through a
court of law. However, section 56(2) bars not merely the normal
remedy of recovery but also bars the remedy of disconnection.
The second part of Section 56(2) is an exception to the law of
E limitation. Once it is held that the term “first due” would mean
the date on which a bill is issued, (as held in para 6.9 of
Rahamatullah Khan) and once it is held that the period of
limitation would commence from the date of discovery of the
mistake (as held in paragraphs 9.1 to 9.3 of Rahamatullah Khan),
F then the question of allowing licensee to recover the amount by
any other mode but not take recourse to disconnection of supply
would not arise. But Rahamatullah Khan says in the penultimate
paragraph that “the licensee may take recourse to any remedy
available in law for recovery of the additional demand, but barred
from taking recourse to disconnection of supply under sub-section
G (2) of section 56 of the Act”.The decision in Rahamatullah Khan
is distinguishable on facts. [Paras 9, 14-16 and 18][652-G-H;
653-A-F; 654-B]
Assistant Engineer (D1), Ajmer Vidyut Vitran Nigam
limited and Anr. vs. Rahamatullah Khan alias
H
M/S PREM COTTEX v. UTTAR HARYANA BIJLI VITRAN NIGAM 647
LTD
Rahamjulla (2020) 4 SCC 650:[2020] 2 SCR 929 – A
distinguished.
1.2 Even otherwise there are two things in this case, which
cannot be overlooked. The first is that the question whether the
raising of an additional demand, by itself would tantamount to any
deficiency in service, clothing the consumer fora with a power to B
deal with the dispute, was not raised or considered in
Rahamatullah Khan. The second is the impact of Sub-section (1)
of Section 56 on Sub-section (2) thereto. The fora constituted
under the Consumer Protection Act, 1986 is entitled to deal with
the complaint of a consumer, either in relation to defective goods
or in relation to deficiency in services. The word “deficiency” is C
defined in Section 2(1)(g) of the Consumer Protection Act, 1986.
The raising of an additional demand in the form of “short
assessment notice”, on the ground that in the bills raised during
a particular period of time, the multiply factor was wrongly
mentioned, cannot tantamount to deficiency in service. If a D
licensee discovers in the course of audit or otherwise that a
consumer has been short billed, the licensee is certainly entitled
to raise a demand. So long as the consumer does not dispute the
correctness of the claim made by the licensee that there was
short assessment, it is not open to the consumer to claim that
there was any deficiency. This is why, the National Commission, E
in the impugned order correctly pointed out that it is a case of
“escaped assessment” and not “deficiency in service”. [Paras
19-21][654-C-H]
1.3 In fact, even before going into the question of Section
56(2), the consumer forum is obliged to find out at the threshold F
whether there was any deficiency in service. It is only then that
the recourse taken by the licensee for recovery of the amount,
can be put to test in terms of Section 56. The respondents cannot
be held guilty of any deficiency in service and hence dismissal of
the complaint by the National Commission is perfectly in order.
G
With respect to the second aspect, namely, the impact of Sub-
section (1) on Sub-section (2) of Section 56, it is seen that the
bottom line of Sub-section (1) is the negligence of any person to
pay any charge for electricity. Sub-section (1) starts with the words
H
648 SUPREME COURT REPORTS [2021] 8 S.C.R.
A “where any person neglects to pay any charge for electricity or any
some other than a charge for electricity due from him”. Sub-section
(2) uses the words “no sum due from any consumer under this
Section”.Therefore, the bar under Sub-section (2) is relatable to
the sum due under Section 56. Sub-section (1) deals specifically
with the negligence on the part of a person to pay any charge for
B
electricity or any sum other than a charge for electricity. What is
covered by section 56, under sub-section (1), is the negligence on
the part of a person to pay for electricity and not anything else nor
any negligence on the part of the licensee. [Paras 22-24][655-A-E]
1.4 In other words, the negligence on the part of the
C licensee which led to short billing in the first instance and the
rectification of the same after the mistake is detected, is not
covered by Sub-section (1) of Section 56. Consequently, any claim
so made by a licensee after the detection of their mistake, may
not fall within the mischief, namely, “no sum due from any
D consumer under this Section”, appearing in Sub-section (2). Sub-
section (1) of Section 56 deals with the disconnection of electric
supply if any person “neglects to pay any charge for electricity”.
The question of neglect to pay would arise only after a demand is
raised by the licensee. If the demand is not raised, there is no
occasion for a consumer to neglect to pay any charge for
E electricity. Sub-section (2) of Section 56 has a non-obstante clause
with respect to what is contained in any other law, regarding the
right to recover including the right to disconnect. Therefore, if
the licensee has not raised any bill, there can be no negligence
on the part of the consumer to pay the bill and consequently the
F period of limitation prescribed under Sub-section (2) will not start
running. So long as limitation has not started running, the bar for
recovery and disconnection will not come into effect. Hence the
decision in Rahamatullah Khan and Section 56(2) will not go to
the rescue of the appellant. The National Commission was justified
in rejecting the complaint and there is no reason to interfere
G with the said Order. However, since the appellant has already
paid 50% of the demand amount pursuant to an interim order
passed by this Court on 19.08.2014, eight weeks time given to
the appellant to make payment of the balance amount. [Paras 22-
27][655-E-H; 656-A-C]
H
M/S PREM COTTEX v. UTTAR HARYANA BIJLI VITRAN NIGAM 649
LTD
Mahabir Kishore & Ors. vs. State of Madhya Pradesh A
(1989) 4 SCC 1 : [1989] 3 SCR 596 – referred to.
Case Law Reference
[2020] 2 SCR 929 distinguished Para 8
[1989] 3 SCR 596 referred to Para 12 B
CIVIL APPELLATE JURISDICTION: Civil Appeal No.7235 of
2009
From the Judgment and Order dated 01.10.2009 of National
Consumer Disputes Redressal Commission, New Delhi in Consumer
Complaint No.156 of 2009. C
K. C. Mittal, Arvind Jain, Harish Pandey, Amresh Anand, Advs.
for the Appellant.
Arun Bhardwaj, Addl. AG, Rahul Kumar Sharma, Ms. Gauraan
Bhardwaj, Abhishek Sharma, Vishwa Pal Singh, Brijender Singh Dhull,
D
Ashish Pandey, Advs. for the Respondents.
The Judgment of the Court was delivered by
V. RAMASUBRAMANIAN, J.
1. Challenging an Order of the National Consumer Disputes
Redressal Commission (for short “National Commission”), dismissing E
their consumer complaint on the ground that there was no deficiency in
service on the part of the licensee (electricity distribution company), the
consumer of electricity has come up with the above statutory appeal.
2. We have heard Sh. K.C. Mittal, learned counsel for the appellant
and Mr. Arun Bhardwaj, learned Additional Advocate General for the F
State of Haryana, appearing for the respondents.
3. The appellant is carrying on the business of manufacturing cotton
yarn in Panipat, Haryana. The appellant is having a L.S. connection,
which got extended from 404.517 KW to 765 KW with C.D 449 KVA
to 850 KVA, on 3.08.2006. G
4. After 3 years of the grant of extension, the appellant was served
with a memo dated 11.09.2009 by the third respondent herein, under the
caption “short assessment notice”, claiming that though the multiply
factor (MF) is 10, it was wrongly recorded in the bills for the period
H
650 SUPREME COURT REPORTS [2021] 8 S.C.R.
A from 3.08.2006 to 8/09 as 5 and that as a consequence there was short
billing to the tune of Rs.1,35,06,585/-. The notice called upon the appellant
to pay the amount as demanded, failing which certain consequences
would follow.
5. Aggrieved by the said notice, the appellant gave a representation
B on 22.09.2009 and then filed a consumer complaint before the National
Commission, contending inter alia that the demand made by the
respondents is the outcome of a glaring mistake and gross negligence on
their part and that under Section 56 of the Electricity Act, 2003 (for
short “the Act”), no amount due from a customer is recoverable after a
period of two years from the date on which it became first due.
C
6. By an Order dated 1.10.2009, the National Commission
dismissed the complaint on the ground that it is a case of “escaped
assessment” and not a case of “deficiency in service”. Aggrieved by
the said Order, the appellant is before us.
7. While ordering notice in the above appeal on 13.11.2009, this
D Court granted interim stay of the impugned order. However, on an
application filed on behalf of the respondents for vacating the interim
order, this Court modified the stay Order on 19.08.2014 directing the
appellant to pay to the first respondent herein, 50% of the demand amount
within six weeks with a condition that in case the appellant succeeded,
E the said amount shall be refunded with interest @ 9% p.a. Accordingly,
the appellant has paid a sum of Rs.54,03,293/-, on 24.09.2014. The
appellant claims to have already paid a sum of Rs.13,50,000/- on 9.10.2009
itself and this amount, together with the amount deposited on 24.09.2014
pursuant to the interim order of this Court, constituted 50% of the amount
as demanded in short assessment notice dated 11.09.2009.
F 8. The sheet anchor of the case of the appellant is Section 56(2)
of the Act and the exposition of law made by this Court in the decision in
Assistant Engineer (D1), Ajmer Vidyut Vitran Nigam limited and
Anr. vs. Rahamatullah Khan alias Rahamjulla1.
9. Before we proceed to consider the statutory provision and the
G decision of this Court relied upon by the appellant, it is relevant to take
note of the fact that the appellant never disputed the correctness of the
claim of the respondents that the multiply factor (MF) to be applied was
10, but it was wrongly applied as 5. The only grievance raised by the
appellant both in their representation and in their consumer complaint
H 1
(2020) 4 SCC 650
M/S PREM COTTEX v. UTTAR HARYANA BIJLI VITRAN NIGAM 651
LTD [V. RAMASUBRAMANIAN, J.]
was that they cannot be made to suffer on account of the negligence on A
the part of the respondents and that on the basis of the bill already raised,
they have charged their customers and that it may not be possible for
them to go back to their customers with an additional demand now. In
addition, the bar under Section 56 was also pleaded.
10. Section 56 of the Electricity Act, 2003 reads as under:- B
“56. Disconnection of supply in default of payment. - (1)
Where any person neglects to pay any charge for electricity
or any sum other than a charge for electricity due from him to
a licensee or the generating company in respect of supply,
transmission or distribution or wheeling of electricity to him,
C
the licensee or the generating company may, after giving not
less than fifteen clear days’ notice in writing, to such person
and without prejudice to his rights to recover such charge or
other sum by suit, cut off the supply of electricity and for that
purpose cut or disconnect any electric supply line or other
works being the property of such licensee or the generating D
company through which electricity may have been supplied,
transmitted, distributed or wheeled and may discontinue the
supply until such charge or other sum, together with any
expenses incurred by him in cutting off and reconnecting the
supply, are paid, but no longer:
E
Provided that the supply of electricity shall not be cut
off if such person deposits, under protest, -
(a) an amount equal to the sum claimed from him, or
(b) the electricity charges due from him for each month
calculated on the basis of average charge for electricity F
paid by him during the preceding six months,
whichever is less, pending disposal of any dispute
between him and the licensee.
(2) Notwithstanding anything contained in any other
law for the time being in force, no sum due from any consumer, G
under this section shall be recoverable after the period of
two years from the date when such sum became first due unless
such sum has been shown continuously as recoverable as
arrear of charges for electricity supplied and the licensee
shall not cut off the supply of the electricity.”
H
652 SUPREME COURT REPORTS [2021] 8 S.C.R.
A 11. In Rahamatullah Khan (supra), three issues arose for the
consideration of this Court. They were (i) what is the meaning to be
ascribed to the term “first due” in Section 56(2) of the Act; (ii) in the
case of a wrong billing tariff having been applied on account of a mistake,
when would the amount become first due; and (iii) whether recourse to
disconnection may be taken by the licensee after the lapse of two years
B
in the case of a mistake.
12. On the first two issues, this Court held that though the liability
to pay arises on the consumption of electricity, the obligation to pay
would arise only when the bill is raised by the licensee and that,
therefore, electricity charges would become “first due” only after
C the bill is issued, even though the liability would have arisen on
consumption. On the third issue, this Court held in Rahamatullah Khan
(supra), that “the period of limitation of two years would commence
from the date on which the electricity charges became first due under
Section 56(2)”. This Court also held that Section 56(2) does not preclude
D the licensee from raising an additional or supplementary demand after
the expiry of the period of limitation in the case of a mistake or bonafide
error. To come to such a conclusion, this Court also referred to Section
17(1)(c) of the Limitation Act, 1963 and the decision of this Court in
Mahabir Kishore & Ors. vs. State of Madhya Pradesh 2.
E 13. Despite holding that electricity charges would become first
due only after the bill is issued to the consumer (para 6.9 of the SCC
Report) and despite holding that Section 56(2) does not preclude the
licensee from raising an additional or supplementary demand after the
expiry of the period of limitation prescribed therein in the case of a
mistake or bonafide error (Para 9.1 of the SCC Report), this Court
F came to the conclusion that what is barred under Section 56(2) is only
the disconnection of supply of electricity. In other words, it was held by
this Court in the penultimate paragraph that the licensee may take
recourse to any remedy available in law for the recovery of the additional
demand, but is barred from taking recourse to disconnection of supply
G under Section 56(2).
14. But a careful reading of Section 56(2) would show that the
bar contained therein is not merely with respect to disconnection of
supply but also with respect to recovery. If Sub-section (2) of Section 56
is dissected into two parts it will read as follows:-
H 2
(1989) 4 SCC 1
M/S PREM COTTEX v. UTTAR HARYANA BIJLI VITRAN NIGAM 653
LTD [V. RAMASUBRAMANIAN, J.]
(i) No sum due from any consumer under this Section shall be A
recoverable after the period of two years from the date
when such sum became first due; and
(ii) the licensee shall not cut off the supply of electricity.
15. Therefore, the bar actually operates on two distinct rights of
the licensee, namely, (i) the right to recover; and (ii) the right to B
disconnect. The bar with reference to the enforcement of the right to
disconnect, is actually an exception to the law of limitation. Under the
law of limitation, what is extinguished is the remedy and not the right. To
be precise, what is extinguished by the law of limitation, is the remedy
through a court of law and not a remedy available, if any, de hors through C
a court of law. However, section 56(2) bars not merely the normal remedy
of recovery but also bars the remedy of disconnection. This is why we
think that the second part of Section 56(2) is an exception to the law of
limitation.
16. Be that as it may, once it is held that the term “first due” D
would mean the date on which a bill is issued, (as held in para 6.9 of
Rahamatullah Khan) and once it is held that the period of limitation
would commence from the date of discovery of the mistake (as held in
paragraphs 9.1 to 9.3 of Rahamatullah Khan), then the question of
allowing licensee to recover the amount by any other mode but not take
recourse to disconnection of supply would not arise. But Rahamatullah E
Khan says in the penultimate paragraph that “the licensee may take
recourse to any remedy available in law for recovery of the
additional demand, but barred from taking recourse to disconnection
of supply under sub-section (2) of section 56 of the Act”.
17. It appears from the narration of facts in paragraph 2 of F
Rahamatullah Khan (supra) that this Court was persuaded to take the
view that it did, on account of certain peculiar facts. The consumer in
that case was billed under a particular tariff code for the period from
July-2009 to September-2011. But after audit, it was discovered that a
different tariff code should have been applied. Therefore, a show cause G
notice was issued on 18.03.2014 raising an additional demand for the
period from July-2009 to September-2011. Then a bill was raised on
25.05.2015 for the aforesaid period. Therefore, the consumer successfully
challenged the demand before the District Consumer Forum, but the
Order of the District Forum was reversed by the State Commission on
an appeal by the licensee. The National Commission on a revision filed H
654 SUPREME COURT REPORTS [2021] 8 S.C.R.
A by the consumer, set aside the order of the State Commission and restored
the order of the District Forum. It was this Order of the National
Commission that was under challenge before this Court in Rahamatullah
Khan (supra).
18. Eventually, this Court disposed of the appeals, preventing the
B licensee from taking recourse to disconnection of supply, but giving them
liberty to take recourse to any remedy available in law for recovery of
the additional demand. Therefore, the decision in Rahamatullah Khan
(supra) is distinguishable on facts.
19. Even otherwise there are two things in this case, which we
C cannot overlook. The first is that the question whether the raising of an
additional demand, by itself would tantamount to any deficiency in service,
clothing the consumer fora with a power to deal with the dispute, was
not raised or considered in Rahamatullah Khan (supra). The second is
the impact of Sub-section (1) of Section 56 on Sub-section (2) thereto.
D 20. The fora constituted under the Consumer Protection Act, 1986
is entitled to deal with the complaint of a consumer, either in relation to
defective goods or in relation to deficiency in services. The word
“deficiency” is defined in Section 2(1)(g) of the Consumer Protection
Act, 1986 as follows:-
E “2(1)(g) “deficiency” means any fault, imperfection,
shortcoming or inadequacy in the quality, nature and manner
of performance which is required to be maintained by or under
any law for the time being in force or has been undertaken to
be performed by a person in pursuance of a contract or
otherwise in relation to any service;
F
21. The raising of an additional demand in the form of “short
assessment notice”, on the ground that in the bills raised during a
particular period of time, the multiply factor was wrongly mentioned,
cannot tantamount to deficiency in service. If a licensee discovers in the
course of audit or otherwise that a consumer has been short billed, the
G
licensee is certainly entitled to raise a demand. So long as the consumer
does not dispute the correctness of the claim made by the licensee that
there was short assessment, it is not open to the consumer to claim that
there was any deficiency. This is why, the National Commission, in the
impugned order correctly points out that it is a case of “escaped
H assessment” and not “deficiency in service”.
M/S PREM COTTEX v. UTTAR HARYANA BIJLI VITRAN NIGAM 655
LTD [V. RAMASUBRAMANIAN, J.]
22. In fact, even before going into the question of Section 56(2), A
the consumer forum is obliged to find out at the threshold whether there
was any deficiency in service. It is only then that the recourse taken by
the licensee for recovery of the amount, can be put to test in terms of
Section 56. If the case on hand is tested on this parameter, it will be
clear that the respondents cannot be held guilty of any deficiency in
B
service and hence dismissal of the complaint by the National Commission
is perfectly in order.
23. Coming to the second aspect, namely, the impact of Sub-
section (1) on Sub-section (2) of Section 56, it is seen that the bottom
line of Sub-section (1) is the negligence of any person to pay any charge
for electricity. Sub-section (1) starts with the words “where any person C
neglects to pay any charge for electricity or any some other than a
charge for electricity due from him”.
24. Sub-section (2) uses the words “no sum due from any
consumer under this Section”. Therefore, the bar under Sub-section
(2) is relatable to the sum due under Section 56. This naturally takes us D
to Sub-section (1) which deals specifically with the negligence on the
part of a person to pay any charge for electricity or any sum other
than a charge for electricity. What is covered by section 56, under
sub-section (1), is the negligence on the part of a person to pay for
electricity and not anything else nor any negligence on the part of E
the licensee.
25. In other words, the negligence on the part of the licensee
which led to short billing in the first instance and the rectification of the
same after the mistake is detected, is not covered by Sub-section (1) of
Section 56. Consequently, any claim so made by a licensee after the F
detection of their mistake, may not fall within the mischief, namely,”no
sum due from any consumer under this Section”, appearing in Sub-
section (2).
26. The matter can be examined from another angle as well. Sub-
section (1) of Section 56 as discussed above, deals with the disconnection G
of electric supply if any person “neglects to pay any charge for
electricity”. The question of neglect to pay would arise only after a
demand is raised by the licensee. If the demand is not raised, there is no
occasion for a consumer to neglect to pay any charge for electricity.
Sub-section (2) of Section 56 has a non-obstante clause with respect to
what is contained in any other law, regarding the right to recover including H
656 SUPREME COURT REPORTS [2021] 8 S.C.R.
A the right to disconnect. Therefore, if the licensee has not raised any bill,
there can be no negligence on the part of the consumer to pay the bill
and consequently the period of limitation prescribed under Sub-section
(2) will not start running. So long as limitation has not started running,
the bar for recovery and disconnection will not come into effect. Hence
the decision in Rahamatullah Khan and Section 56(2) will not go to the
B
rescue of the appellant.
27. Therefore, we are of the view that the National Commission
was justified in rejecting the complaint and we find no reason to interfere
with the Order of the National Commission. Accordingly, the appeal is
dismissed. However, since the appellant has already paid 50% of the
C demand amount pursuant to an interim order passed by this Court on
19.08.2014, we give eight weeks time to the appellant to make payment
of the balance amount. There shall be no order as to costs.
Divya Pandey Appeal dismissed.
D
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.