Created byFuzzy Cloud

Supreme Court of India

NABHA POWER LIMITEDversusPUNJAB STATE POWER CORPORATION LIMITED AND OTHERS

Citation
2025 INSC 1002
Decided
19 August 2025
Disposal
Dismissed

Holding

The Court held that the appellants were not entitled to the deemed export benefits under Para 8.3 of the FTP and that the DGFT notifications and the press release did not constitute a “Change in Law”, therefore no compensation is payable.

Summary

Nabha Power Ltd (NPL) and Talwandi Sabo Power Ltd (TSPL) entered into Power Purchase Agreements (PPA) with Punjab State Power Corporation Ltd (PSPCL) for a 700 MW coal‑fired project. They claimed that deemed export benefits under Paragraph 8.3 of the Foreign Trade Policy (FTP) 2009‑2014 were available at the bid cut‑off date and that subsequent DGFT notifications and a Cabinet press release withdrawing those benefits constituted a “Change in Law” under Article 13 of the PPA, entitling them to compensation. The State Commission and the Appellate Tribunal for Electricity held that the benefits were not available and that the notifications were merely clarificatory, not a change in law. On appeal, the Supreme Court examined the statutory definitions of “goods”, “manufacture”, and the procedural prerequisites for FTP benefits, concluding that a power plant is an immovable asset and does not satisfy the FTP’s requirement of supply of movable “goods”. Consequently, the Court held that the appellants were ineligible for the deemed export benefits and that no “Change in Law” occurred, so no restitutionary relief could be awarded. The appeals were dismissed.

Issues considered

  • Whether deemed export benefits under Para 8.3 of the Foreign Trade Policy 2009‑2014 were legitimately available to the appellants as of the bid cut‑off date and whether DGFT notifications amount to a “Change in Law” under the PPA.
  • Whether the Press Release of Cabinet Decision changing the threshold for deemed export benefits constitutes a “Change in Law” within the meaning of Article 13 of the PPA.
  • Whether the appellants are entitled to restitutionary compensation under Article 13.1.1(ii) of the PPA.

Legislation cited

Headnote

1308 : 2025 INSC 1002 Nabha Power Limited v. Punjab State Power Corporation Limited and Others (Civil Appeal No. 8694 of 2017) 19 August 2025 [B.R. Gavai, CJI and Augustine George Masih,* J.] Issue for Consideration Issue arose whether deemed export benefits under Para 8.3 of Foreign Trade under the Power Purchase Agreement dated 18.01.2010; whether the Press Release of Cabinet Decision pertaining to change of threshold of so-deemed export benefits would constitute a “Change in Law” under the PPA; and if so, whether the appellants entitled to restitutionary relief in

Subjects

Deemed export benefitsForeign Trade PolicyBid cut‑off dateDGFT notificationsChange in LawPower Purchase AgreementPress Release Cabinet DecisionRestitutionary reliefCompensationSpecial Purpose VehiclesMega Watt coal‑fired power projectTariff‑Based Competitive BiddingCustoms duty exemptionTerminal Excise DutyDrawback

Judgment

                 [2025] 8 S.C.R. 1308 : 2025 INSC 1002

                    Nabha Power Limited
                             v.
      Punjab State Power Corporation Limited and Others
                       (Civil Appeal No. 8694 of 2017)
                                19 August 2025
           [B.R. Gavai, CJI and Augustine George Masih,* J.]


                           Issue for Consideration
       Issue arose whether deemed export benefits under Para 8.3 of
       Foreign Trade Policy 2009-2014-FTP were legitimately available to
       the appellants as of the bid cut-off date and would notifications by
       Directorate General of Foreign Trade amount to “Change in Law”
       under the Power Purchase Agreement dated 18.01.2010; whether
       the Press Release of Cabinet Decision pertaining to change of
       threshold of so-deemed export benefits would constitute a “Change
       in Law” under the PPA; and if so, whether the appellants entitled
       to restitutionary relief in the form of compensation.

                                  Headnotes†
       Electricity Act, 2003 – ss. 63, 125 – Foreign Trade (Development
       & Regulation) Act, 1992 – s.5 read with Paragraph 1.2 of the
       FTP – Customs Act, 1962 – Availability of benefits under the
       Foreign Trade Policy to power plant as of the cut-off date –
       Claim for Deemed Export Benefits, eligibility – Withdrawal
       of Foreign Trade Policy Para 8.3 benefits, if constitutes
       change in law – Appellants-NPL and TSPL, Special Purpose
       Vehicles formulated to develop Mega Watt coal-fired power
       project at Rajpura, Punjab, through Tariff-Based Competitive
       Bidding, entered into a Power Purchase Agreement with
       Punjab State Power Corporation Limited-PSPCL – NPL
       sought concessions or exemption from payment of customs
       duty while importing capital goods – FTP amended that
       Terminal Excise Duty exemptions under the FTP would not
       be available for the supplies made to a non-MPP (with cut-off
       date being 01.10.2009) – Petition by NPL that the Mega Power
       benefits were factored into the bid and hence did not warrant
       pass-through to PSPCL, and compensation under Art. 13.1.1(ii)


* Author
[2025] 8 S.C.R.                                                            1309

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     of the PPA for the withdrawal of FTP benefits post the cut off
     date of 02.10.2009, alternatively – State Commission dismissed
     the Petition holding that since the NPL had elected to avail
     benefits under the MPP 2009, it was precluded from claiming
     concurrent benefits under the FTP and withdrawal of benefits
     by DGFT did not constitute as a “Change in Law” within the
     meaning of Art. 13 of the PPA – Appellate tribunal also rejected
     the claims by the NPL and primarily the challenge to the
     post-bid withdrawal of fiscal incentives which were allegedly
     available earlier under the FTP and their classification as a
     “Change in Law” event under the PPA – Interference with:
     Held: Not called for – Press Release dated 01.10.2009 would
     neither amount to “law” within the meaning conceptualized in
     the PPA, as it would only be the Notifications dated 11.12.2009
     and 14.12.2009 that would have amounted to “law”, nor it would
     thereby amount to “Change in Law” – Essential prerequisites
     that ought to be satisfied by the appellants in order to be eligible
     for the deemed export benefits are the claim for Deemed Export
     Benefits relates exclusively to “goods” and is inapplicable to any
     other thing which is not “goods”, such goods, though supplied,
     do not physically exit the territorial boundaries of the country;
     that the goods to be supplied must be “manufactured in India”;
     that there must be an act constituting “supply of goods” to the
     power projects for the project to claim Deemed Export Benefits;
     that the act of “supply of goods” is either by the main contractor
     and/or the sub-contractor to the concerned power project; and the
     supply is undertaken strictly in accordance with the procedural
     framework prescribed under ICB – Embedded power plant of
     hundreds of Mega Watts would not be able to qualify as “capital
     goods” for entitlement of the appellants under the FTP for the
     deemed export benefits – Para 9.36 of the FTP requires that the
     manufactured good should have been brought into existence with
     a distinctive name, character, or use, such a feasibility impossible
     when it comes to the concerned power plants – Supply of goods”
     to a power plant, as is contemplated u/Para 8.2(g) of the FTP
     remains unfulfilled – Even at the time of bidding, the to-be then
     constructed Power Plant itself was deemed as the concerned
     capital goods for the deemed export benefits, implying that there
     was no distinct supply of goods by either a main contractor or a
     sub-contractor thereof – Such a situation of suo moto acclaimed
     manufacturing in the Project’s own right shall not stand the instant
1310                                                          [2025] 8 S.C.R.

                         Supreme Court Reports


    test – Appellants, failed to establish the procurement of “supply of
    goods” as per the mandate of ICB either at the stage of Independent
    Power Producer or Engineering Procurement Contract, owing
    to the fact that such procurement of the components was done
    through directly entering into contract with their subsidiaries or
    joint venture or related companies – Thus, the appellants not
    entitled to the deemed export benefits under Para 8.3 of the FTP
    for their inability to fulfil the essentail prerequisites – Plea as to
    the alleged withdrawal of the said benefits through notifications of
    DGFT dated 28.12.2011 and 21.03.2012 collectively and whether
    that would amount to a “Change in Law” as per Art. 13 of the PPA
    not delved into – Said notifications issued through DGFT mere
    clarificatory in nature – No interpretation of law was undertaken
    prior to the cut-off date to the effect that a developer shall be
    able to import goods to be assembled into a power plant and also
    claim the deemed export benefits on those, thus, tribunal correctly
    concluded the said circulars to be merely clarificatory and not as
    something which has either changed or introduced something
    new, being allegedly oppressive towards the appellants – In view
    thereof, appellants not entitled to restitutionary relief in the form
    of compensation. [Paras 44, 57-62, 67-80]

                             Case Law Cited
    Nabha Power Limited and Another v. Punjab State Power
    Corporation Limited and Another [2024] 11 SCR 445 : (2025) 5
    SCC 353 – relied on.
    Shivshankara and Another v. H.P. Vedavyasa Char [2023] 6 SCR
    359 : (2023) 13 SCC 1; Haryana Power Purchase Centre v. Sasan
    Power Limited and Others [2023] 8 SCR 1 : (2024) 1 SCC 247;
    GMR Warora Energy Limited v. Central Electricity Regulatory
    Commission (CERC) and Others [2023] 8 SCR 183 : (2023) 10
    SCC 401; Nabha Power Limited (NPL) v. Punjab State Power
    Corporation Limited (PSPCL) and Another [2017] 14 SCR 301 :
    (2018) 11 SCC 508; Babu Verghese and Others v. Bar Council
    of Kerala and Others [1999] 1 SCR 1121 : (1999) 3 SCC 422;
    Vadilal Chemicals Ltd. v. State of A.P. and Others [2005] Supp. 2
    SCR 1 : (2005) 6 SCC 292; MSCO. Pvt. Ltd. v. Union of India and
    Others [1985] 1 SCR 1146 : (1985) 1 SCC 51; Trutuf Safety Glass
    Industries v. Commissioner of Sales Tax, U.P. [2007] 8 SCR 860 :
    (2007) 7 SCC 242; P.C. Cheriyan v. Mst. Barfi Devi [1980] 1 SCR
    961 : (1980) 2 SCC 461; Quality Steel Tubes (P) Ltd v. Collector of
[2025] 8 S.C.R.                                                            1311

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     Central Excise, U.P. [1994] Supp. 6 SCR 439 : (1995) 2 SCC 372;
     Union of India and Another v. Delhi Cloth and General Mills Co. Ltd.
     [1963] Supp. 1 SCR 586 : 1962 SCC OnLine SC 148; Collector
     of Central Excise, Baroda v. Ambalal Sarabhai Enterprises (P)
     Ltd. [1989] 3 SCR 784 : (1989) 4 SCC 112; Union Carbide India
     Limited v. Union of India and Others [1986] 2 SCR 162 : (1986)
     2 SCC 547; India Cine Agencies v. Commissioner of Income Tax,
     Madras [2008] 15 SCR 1122 : (2008) 17 SCC 385; Commissioner
     of Income Tax, Orissa and Others v. M/s N.C. Budharaja and
     Company and Others [1993] Supp. 2 SCR 185 : (1994) Supp.
     1 SCC 280; Moti Laminates Pvt. Ltd. and Others v. Collector of
     Central Excise, Ahmedabad [1995] 2 SCR 81 : (1995) 3 SCC 23;
     Union Carbide India (supra), Bhor Industries Limited, Bombay v.
     Collector of Central Excise, Bombay [1989] 1 SCR 382 : (1989)
     1 SCC 602; Hindustan Polymers v. Collector of Central Excise
     [1989] 3 SCR 974 : (1989) 4 SCC 323 – referred to.
     Commissioner of Income-Tax v. Geo Tech Foundation &
     Constructions (2000) 241 ITR 90 : 1999 SCC OnLine Ker 341 –
     referred to.

                      Books and Periodicals Cited
     P. Ramanatha Aiyar’s Advanced Law Lexicon Fifth Edition; Supreme
     Court Words and Phrases by Surendra Malik and Sumit Malik
     Third Edition – referred to.

                                List of Acts
     Electricity Act, 2003; Foreign Trade (Development & Regulation)
     Act, 1992; Customs Act, 1962; Central Excise Act, 1944.

                             List of Keywords
     Deemed export benefits; Foreign Trade Policy; Bid; Cut-off date;
     Notifications by Directorate General of Foreign Trade; Change
     in Law; Power Purchase Agreement; Press Release of Cabinet
     Decision; Restitutionary relief; Compensation; Special Purpose
     Vehicles; Mega Watt coal-fired power project; Tariff-Based
     Competitive Bidding; Punjab State Power Corporation Limited-
     PSPCL; Exemption from payment of customs duty; Importing
     capital goods; Terminal Excise Duty exemptions; Drawback; Mega
     Power benefits; Post-bid withdrawal; Fiscal incentives; Supply of
     goods; “Capital goods”.
1312                                                          [2025] 8 S.C.R.

                          Supreme Court Reports


                             Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 8694 of 2017
     From the Judgment and Order dated 04.07.2017 of the Appellate
     Tribunal for Electricity at New Delhi in AN No. 47 of 2015
     With
     Civil Appeal No. 8739 of 2017

                          Appearances for Parties
     Advs. for the Appellant:
     C.S. Vaidyanathan, A.N.S. Nadkarni, Arvind Datar, Sr. Advs.,
     Mahesh Agarwal, Shri Venkatesh, Rohan Talwar, Shashwat Singh,
     Ms. Priya Dhankar, Naman Agarwal, E. C. Agrawala, Vishrov
     Mukerjee, Pratyush Singh, Raghav Malhotra, Ms. Juhisenguttuvan,
     Pranav Bansal, Rahul Khurana, Kumar Visalaksh, M/s. Trilegal.
     Advs. for the Respondents:
     M G Ramachandran, Balbir Singh, Sr. Advs., Mrs. Poorva Saigal,
     K.V. Mohan, Mrs. Pallavi Saigal, Ms. Shirin Gupta, Rishabh Saxena,
     Subhan Arya, Aneesh Bajaj, Ms. Srishti Khandaria, Ms. Sunieta
     Ojha, Ms. Gargi Kumar.

                 Judgment / Order of the Supreme Court

                                  Judgment

     Augustine George Masih, J.

1.   These two appeals pertain to the following common questions of law:
     (i)    Whether deemed export benefits under Para 8.3 of Foreign
            Trade Policy 2009-2014 (hereinafter “FTP”) were legitimately
            available to the Appellants as of the bid cut-off date and would
            notifications by Directorate General of Foreign Trade (hereinafter,
            “DGFT”) amount to “Change in Law” under the Power Purchase
            Agreement dated 18.01.2010 (hereinafter, “PPA”);
     (ii)   Whether the Press Release of Cabinet Decision pertaining
            to change of threshold of so-deemed export benefits would
            constitute a “Change in Law” under the PPA; and
     (iii) If so, whether Appellants are entitled to restitutionary relief in
           the form of compensation.
[2025] 8 S.C.R.                                                     1313

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

2.   The Civil Appeal No. 8694 of 2017 as filed by the Nabha Power
     Limited (hereinafter, “NPL”) under Section 125 of the Electricity Act,
     2003 (hereinafter, “EA 2003”), arises from the Common Judgment
     dated 04.07.2017 (hereinafter, “Impugned Judgment”) in Appeal
     No. 47 of 2015 passed by the Appellate Tribunal for Electricity,
     New Delhi (hereinafter, “APTEL”) owing to rejection of the claim(s)
     moved by the NPL for relief under Article 13 of the PPA executed
     by it with the Punjab State Power Corporation Limited (hereinafter
     “PSPCL”), and primarily the challenge to the post-bid withdrawal of
     fiscal incentives which were allegedly available earlier under the FTP
     and their classification as a “Change in Law” event under the PPA.
3.   Similarly, Civil Appeal No. 8739 of 2017, filed by the Talwandi Sabo
     Power Limited (hereinafter, “TSPL”) also arises from the same
     Impugned Judgment in Appeal No. 32 of 2015 by APTEL. Since
     both of the aforesaid appeals before the APTEL involved common
     issues, they were heard together. The prime grievance for both the
     Appellants therein was that the Punjab State Electricity Regulatory
     Commission at Chandigarh (hereinafter, “State Commission”) had,
     although vide separate orders, held them to be not eligible for the
     aforementioned benefits and liable to pass on the same to PSPCL,
     Respondent No. 01 herein.
4.   Both, NPL and TSPL, are Special Purpose Vehicles (hereinafter,
     “SPVs”) which were formulated to develop the concerned power
     projects. This was done under Section 63 of the EA 2003 through
     Tariff-Based Competitive Bidding. PSPCL is one of the successors
     of the Punjab State Electricity Board (hereinafter, “PSEB”) and is a
     state-owned generating and distributing company in Punjab.
5.   Since both these appeals arise out of the same Impugned Judgment
     with issues being common, the same are being dealt with together.
     We shall refer and adopt facts from the Civil Appeal No. 8694 of
     2017 as preferred by NPL, treating it to be the main appeal.
6.   The NPL was incorporated on 25.09.2007 by PSEB to develop
     a dual 700 Mega Watt coal thermal power project at Rajpura in
     Punjab (hereinafter, “Project”). While the PSEB was unbundled, 100
     percent of the shares of the NPL were acquired by the Respondent
     No. 03, being L&T Power Development Limited (hereinafter, “L&T”)
     through the bidding process initiated on 10.06.2009, with final date
     of bid submission being 09.10.2009, and after an evaluation of the
1314                                                        [2025] 8 S.C.R.

                          Supreme Court Reports


     technical and financial bids by a committee chaired by the Principal
     Secretary, Department of Power, Government of Punjab. Thereby,
     NPL became a wholly owned subsidiary of L&T. Consequently, the
     PPA was executed between NPL and PSPCL.
7.   In the interregnum, the Government of India, exercising its powers
     under Section 5 of the Foreign Trade (Development & Regulation)
     Act, 1992 (hereinafter “FTP Act 1992”) read with Paragraph 1.2 of
     the FTP, notified the Foreign Trade Policy, 2009-2014 (hereinafter,
     “FTP”), on 27.08.2009. Moreover, the Union Cabinet vide its Decision
     dated 01.10.2009 reduced the threshold qualification as a Mega
     Power Project to 500 Mega Watt from 1,000 Mega Watt for single
     location projects under the Mega Power Policy, 2006 (hereinafter,
     “MPP 2006”). On the same date, there was a press release by
     the Press Information Bureau that the Union Cabinet has taken a
     decision that it is not mandatory for an inter-state sale of power from
     a project to be eligible under the MPP 2006 (hereinafter, “Press
     Release dated 01.10.2009”).
8.   This Decision dated 01.10.2009 led to two changes:
     (i)    Amendment of the existing eligibility criteria of being a MPP as
            set out under Entry 400 of the Principal Customs Notification No.
            21 of 2002 dated 01.03.2002 by the Department of Revenue,
            Ministry of Finance, Government of India through its powers
            under Section 25 of the Customs Act, 1962 (hereinafter, “CA
            1962”);
     (ii)   Issuance of Memorandum No. A-118/2003-IPC modifying the
            MPP (hereinafter, “MPP 2009”).
9.   It is pertinent to note that it was only through Notifications Nos.
     91/2009-Cus dated 11.12.2009 and 92/2009-Cus dated 14.12.2009
     that the aforesaid benefits were brought into effect.
10. In pursuance of the same, NPL sought grant of status as a Mega
    Power Project from Ministry of Power, Government of India, which
    was granted to it on 30.07.2010.
11. For its application to obtain an Essentiality Certificate from the
    Department of Energy, Government of Punjab, NPL sought a
    recommendation from PSPCL to the effect that Essentiality Certificate
    be issued to NPL for seeking concessions or exemption from payment
    of customs duty while importing capital goods. Against this, NPL
[2025] 8 S.C.R.                                                          1315

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     gave an undertaking vide Affidavit dated 23.05.2011 that any benefits
     which shall accrue on NPL for its change of status to a Mega Power
     Project, shall be passed on to PSPCL. The Essentiality Certificate
     was thereafter issued on 13.06.2011.
12. Another agony came for the Appellant when the Directorate General of
    Foreign Trade (hereinafter, “DGFT”) convened a Policy Interpretation
    Committee (hereinafter, “PIC”) on 15.03.2011, which opined that
    Terminal Excise Duty exemptions under the FTP would not be
    available for the supplies made to a non-MPP (with cut-off date being
    01.10.2009) and any such duty shall not be refunded in any manner
    including as a drawback under Paragraph 8.3(b) of the FTP. It further
    clarified that if a Bill of Entry is in the name of a project authority, the
    deemed export benefits would not be made available. To effectuate
    the same, Public Notices dated 27.04.2011 and 28.04.2011 were
    issued under the FTP Act 1992, amending the FTP.
13. Since the legalities had made NPL ineligible for the assumed
    benefits on their end, it moved Petition No. 30 of 2012 before the
    State Commission seeking (a) a declaration that the Mega Power
    benefits were factored into the bid and hence did not warrant pass-
    through to PSPCL, and (b) compensation under Article 13.1.1(ii) of
    the PPA for the withdrawal of FTP benefits post the cut-off date of
    02.10.2009, alternatively.
14. The State Commission, while dismissing the Petition vide Order
    dated 12.11.2012 (hereinafter, “First Order of Commission”), held
    that since the NPL had elected to avail benefits under the MPP
    2009, it was precluded from claiming concurrent benefits under the
    FTP. Moreover, withdrawal of benefits by DGFT did not constitute
    as a “Change in Law” within the meaning of Article 13 of the PPA.
15. Assailing the findings of the State Commission, NPL moved Appeal
    No. 29 of 2013 before APTEL, which, in its Order dated 30.06.2014
    (hereinafter, “First Order of APTEL”), remanded the matter to the
    State Commission for reconsideration of the issue on the FTP. It
    directed the State Commission to also ascertain and opine as to
    whether the benefits under the FTP were available to the NPL as
    on the cut-off date.
16. On remand, the State Commission vide its majority opinion
    culminating in its Order dated 16.12.2014 (hereinafter, “Second
    Order of Commission”) in Petition No. 30 of 2012 reiterated its earlier
1316                                                       [2025] 8 S.C.R.

                         Supreme Court Reports


     conclusions, observing that the benefits of the FTP were neither
     available to NPL as on the cut-off date nor their withdrawal attract
     the consequences of “Change in Law”. It further went on to observe
     that NPL had not produced contemporaneous DGFT endorsements
     to substantiate its eligibility to claim FTP benefits under Para 8.3.
     Not only that, but as per their own Affidavit dated 23.05.2011, NPL
     was to mandatorily pass on the benefits accrued under the MPP
     2009 to the PSPCL.
17. Aggrieved from the reaffirmation of the findings by the State
    Commission in Second Order of Commission, the NPL again moved
    APTEL in Appeal No. 47 of 2015. It asserted that at the time of
    bidding, deemed export benefits were not only in force but also
    factored into the financial modelling and tariff computation. Also,
    that the said benefits were not withdrawn until the Public Notices of
    April 2011 on behalf of DGFT, which postdated the bid submission
    and execution of the PPA. Furthermore, relying on the DGFT’s
    Policy Circular No. 39 of 2000 and the minutes of the PIC meeting
    dated 15.03.2011, it asserted that it had a legitimate expectation
    that deemed export benefits under Para 8.3 of the FTP would be
    available. Accordingly, NPL contended that the sudden withdrawal of
    the said benefits arguably resulted in material escalation of project
    costs and thereby fell within the “Change of Law” clause of the PPA.
18. On the other hand, PSPCL, challenging the above contentions of
    the NPL, submitted that the benefits under FTP Para 8.3 were never
    intended for immovable infrastructure like thermal power plants and
    that the FTP, by its very nature, was framed to promote exports of
    manufactured goods and, accordingly, extended benefits to goods that
    were exported or supplied against foreign exchange earnings or to
    specified projects under International Competitive Bidding (hereinafter,
    “ICB”). Since a thermal power plant constructed in-situ did not meet
    the definitional threshold of “goods” or “manufacture” under the FTP
    or law(s) on central excise, therefore, NPL’s reliance on deemed
    export provisions was misplaced. PSPCL further contended that the
    DGFT circulars did not carry the force of law and any withdrawal of
    benefits thereunder did not amount to legislative change warranting
    relief under Article 13 of the PPA.
19. The APTEL referred to the definitions of the terms “manufacture,”
    “manufactured goods” and “deemed exports” under the FTP as
    well as the Central Excise Act, 1944 (hereinafter, “CEA 1944”) and
[2025] 8 S.C.R.                                                       1317

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     observed that the FTP was expressly designed to incentivize domestic
     production of movable goods for export or deemed export and the
     concept of “goods” under the statute denoted a tangible and movable
     property, subject to classification under the Customs Tariff. Therefore,
     a generating station, as in the instant case, comprising of turbines,
     boilers, auxiliaries and associated civil works, was nevertheless an
     integrated, immovable asset assembled on‑site and did not, as a
     whole, constitute a manufactured good capable of being exported
     under the FTP. An attempt to sever individual components to obtain
     the relief of deemed export is inconsistent with the scheme of the
     statute, requiring the final product shipped or deemed to be shipped
     to a buyer outside the jurisdiction of India. Observing that the NPL’s
     reliance on Para 8.3 was based on misconstrued interpretation of
     the letter as well as the spirit of the regime, it held that said fiscal
     incentives were inherently inapplicable to an in‑situ coal‑based
     thermal power plant.
20. To examine whether the Public Notices dated 27.04.2011 and
    28.04.2011 constituted a “Change in Law” under Article 13 of the
    PPA, APTEL while perusing the language of Article 13 clarified that
    Article 13.1.1(ii) extended to “any change in law” affecting “taxes,
    duties, cesses, levies, fees and charges” which altered the cost to
    the seller of performing its obligations. The NPL had contended that
    withdrawal of deemed export benefits, though effected by said Public
    Notices rather than a parliamentary enactment, was indisputably
    a change in the law or law‑making process, and that the resulting
    increase in capital cost which engaged the “Change in Law” provision
    was rejected by APTEL observing that the said clause had only
    envisioned a legislation and/or a statutory enactment in form of
    a regulation by a competent authority. Therefore, the said Public
    Notices were merely administrative policy instruments, not meeting
    the threshold of “Change in Law”. It further opined that while the said
    Notices might have affected the cost of NPL, the remedy doesn’t lie
    as a contractual relief under the PPA, but judicial review of the said
    administrative action.
21. Reviewing the satisfaction of the procedural thresholds by NPL under
    Article 13 of the PPA, namely, timely notice for the alleged “Change
    in Law” event, and quantification of the impact on tariff owing to the
    said event, APTEL observed that while NPL reserved its right vide
    the Affidavit dated 23.05.2011, it never pursued any reference to
1318                                                        [2025] 8 S.C.R.

                         Supreme Court Reports


     confirmation of the eligibility of said benefits under the FTP, either by
     the Central Government or by DGFT. Such a belated invocation of
     Article 13 of the PPA, without a binding interpretation, would ascertain
     that NPL failed to discharge the onus to demonstrate that a “Change
     in Law” event had occurred. Furthermore, it is to be considered
     that neither the claim for additional cost was substantiated nor PPA
     envisaged restoration of benefits.
22. Apparently being disconsolate from the concurrent findings against
    them, NPL moved the Civil Appeal No. 8694 of 2017 before this
    Court. NPL has reiterated its grievances.
23. Primarily, NPL has asserted that APTEL erred in holding that the
    deemed export benefits under Para 8.3 of the FTP were never
    available to a coal‑based thermal power plant assembled in‑situ.
    The grounds, as raised in the instant Civil Appeal plead that both
    the statutory text and DGFT circulars envisaged relief on individual
    capital‑goods components, which collectively form the “goods”
    supplied to the project under ICB. It further submits that the APTEL’s
    narrow reading of “manufactured goods” contravenes the plain
    language of the FTP and the FTP Act 1992, which defines “deemed
    exports” by reference to supply to specified end‑users rather than
    physical shipment of entire power stations abroad.
24. It went on to further contend that APTEL misconstrued the “Change
    in Law” clause by restricting its scope to parliamentary enactments
    and delegated legislation. The grounds elaborate that Article 13.1.1(ii)
    expressly extends to “any change in any law,” a phrase wide enough
    to include executive notifications issued under statutory authority,
    which alter duties, levies or benefits. Moreover, the Public Notice
    dated 27.04.2011 and 28.04.2011, issued pursuant to powers under
    the FTP Act 1992, are thus argued to be legislative in character and
    binding, triggering contractual relief.
25. Additionally, NPL avers that Impugned Judgment overlooked its
    legitimate expectation, cultivated by DGFT practice and minutes
    of the PIC Meeting dated 15.03.2011, that deemed export benefits
    under Para 8.3 of the FTP would subsist until formally rescinded. By
    refusing to quantify loss on the basis of contemporaneous tariff models
    and the record of actual procurement, the State Commission is also
    said to have abdicated its duty to enforce the economic equilibrium
    principle fundamental to Article 13. It also faults the APTEL’s finding
[2025] 8 S.C.R.                                                       1319

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     on procedural non‑compliance, pointing out that timely notice was
     given and that the quantification of incremental costs, derived from
     pre‑bid financial schedules, was neither speculative nor premature.
26. Also, adopting their contentions before the State Commission and
    APTEL, NPL has put forth that while formulating its bid, it had factored
    in two critical streams of fiscal incentives available under distinct
    schemes: (i) the Mega Power Policy, which promised concessional
    customs duty and full exemption from excise duties for thermal power
    projects exceeding 1,000 Mega Watt; and (ii) the benefits under Para
    8.3 of the FTP were applicable to deemed exports, including Advance
    Authorization, Deemed Export Drawback, and exemption from
    Terminal Excise Duty on procurement of domestically manufactured
    capital goods. While the former pertained specifically to recognized
    MPPs, the latter applied to non-Mega Projects executing contracts
    under ICB. As on the bid date, the Project did not have formal
    MPP status, and hence, the bid was premised on the availability
    of benefits under the FTP. Concluding, NPL, relying on the maxim
    contemporanea expositio, referred to the benefits granted to others,
    allegedly similarly placed Projects and contended that contemporary
    interpretation should be adopted.
27. In its Counter Affidavit dated 12.09.2017, PSPCL comprehensively
    refutes NPL’s claim that the withdrawal of FTP Para 8.3 benefits
    constitutes a “Change in Law” event warranting contractual
    compensation. PSPCL first underscores that the FTP incentive
    scheme was designed exclusively for “goods”, being tangible,
    movable items, as classifiable under the Customs Tariff Schedule,
    and not for immovable assets such as power plants. Referring to the
    legislative history of the FTP and definitions under the CEA 1944,
    which repeatedly distinguish between supply of goods for export and
    installation of infrastructure projects on-site, it sought to demonstrate
    that policy makers never contemplated deemed export benefits for
    entire power stations. It further emphasized that any interpretation
    extending relief to generating assets would render incoherent the
    statutory regime of export‑linked incentives.
28. Supplementing the aforesaid contentions, PSPCL asserts that
    NPL’s invocation of Article 13 is both contractually and procedurally
    flawed, stressing that the PPA draws a clear line between benefits
    under the MPP and those under the FTP, and that NPL’s election
1320                                                       [2025] 8 S.C.R.

                         Supreme Court Reports


     to opt for concessions under the MPP 2009, confirmed by its own
     Affidavit dated 23.05.2011, precludes a second bite at the cherry. The
     Counter Affidavit additionally characterizes NPL’s protest reservation
     as mere lip service, asserting that no synchronous decision or order
     by the DGFT had ever recognized NPL’s eligibility to benefits under
     Para 8.3 of the FTP.
29. On the “Change in Law” issue, PSPCL argues that only statutory
    enactments or delegated legislation under the FTP Act 1992 qualify,
    and that administrative notices, lacking the force of regulation,
    cannot be contractual triggers. Finally, PSPCL submits that NPL’s
    cost‑impact calculations are hypothetical, relying on benefit rates
    that were never certified by DGFT, and that benefits, if any, must
    be sought through statutory appeals rather than by recourse to the
    PPA’s “Change in Law” clause.
30. In its Rejoinder dated 15.11.2017, NPL insists that the Counter
    Affidavit dated 12.09.2017 misconceives both the factual matrix and
    the legal contours of the “Change in Law” provision. It reiterates that
    the statutory framework of the FTP contemplates deemed export
    treatment for capital goods supplied under ICB, irrespective of physical
    export, and that numerous circulars by DGFT and meetings of PIC
    had long signalled such availability. The Rejoinder emphasizes that
    the PIC meeting dated 15.03.2011 and the Public Notices dated
    27.04.2011 and 28.04.2011 are legislative in character, having been
    issued under rule‑making powers conferred by the Parliament, and
    thus squarely fall within the ambit of Article 13.
31. Addressing PSPCL’s argument on estoppel, it asserts that its Affidavit
    dated 23.05.2011 was executed under protest and duress, simply to
    obtain MPP status, and cannot be construed as a waiver of separate
    FTP entitlements, further contending that it had repeatedly sought
    clarification from DGFT, within the period between bid submission
    and execution of the PPA, but was left in regulatory limbo until April
    2011. Regarding quantification, NPL has provided detailed schedules
    showing incremental capital cost computed at the exact FTP rates
    in force on the cut‑off date, thereby demonstrating a concrete,
    non‑speculative loss.
32. The Rejoinder dated 15.11.2017 also challenges PSPCL’s attempt
    to assert a narrow interpretation of “law”, arguing that executive
    notifications issued under statutory authority are binding legal
[2025] 8 S.C.R.                                                              1321

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     instruments and that contractual remedies for their withdrawal are
     expressly provided in Article 13. Concluding, it also urged that
     the sanctity of competitive bidding and the doctrine of equitable
     adjustment demand that PSPCL bear the financial burden of a post‑bid
     policy reversal for which NPL could not have planned.
33. Through detailed references, as raised by all the Senior Advocates
    before us, we have been able to peruse all the submissions at
    length, including all the material on record through their assistance,
    inclusive of the Impugned Judgment.
34. We shall first deal with the issue as to whether the notifications by
    Directorate General of Foreign Trade and Press Release of a Cabinet
    Decision pertaining to change of threshold so-deemed export benefits
    would constitute a “Change in Law” under the PPA.
35. Before we delve into the submission by the parties to this effect and
    the analysis thereof, it is critical to refer the PPA as executed by
    the parties, especially Article 13 of the PPA, which reads as follows:

           “ARTICLE 13: CHANGE IN LAW
           13.1. Definitions
           In this Article 13, the following terms shall have the following
           meanings:
                13.1.1 “Change in Law” means the occurrence of
                any of the following events after the date, which is
                seven (7) days prior to the Bid Deadline:
                      (i) the enactment, bringing into effect, adoption,
                      promulgation, amendment, modification or
                      repeal, of any Law or (ii) a change in interpretation
                      of any Law by a Competent Court of law,
                      tribunal or Indian Governmental Instrumentality
                      provided such Court of law, tribunal or Indian
                      Governmental Instrumentality is final authority
                      under law for such interpretation or (iii) change
                      in any consents, approvals or licenses available
                      or obtained for the Project, otherwise than for
                      default of the Seller, which results in any change
                      in any cost of or revenue from the business of
                      selling electricity by the Seller to the Procurer
1322                                                    [2025] 8 S.C.R.

                      Supreme Court Reports


                  under the terms of this Agreement or (iv) any
                  change in the (a) Declared Price of Land for
                  the Project or (b) the cost of implementation of
                  the resettlement and rehabilitation package of
                  the land for the Project mentioned in the RfP
                  or (c) the cost of implementing Environmental
                  Management Plan for the Power Station (d)
                  Deleted
                  but shall not include (i) any change in any
                  withholding tax on income or dividends
                  distributed to the shareholders of the Seller, or
                  (ii) change in respect of UI Charges or frequency
                  intervals by an Appropriate Commission.

             13.1.2 ‘Competent Court’ means:
                  The Supreme Court or any High Court or any
                  tribunal or any similar judicial or quasi-judicial
                  body in India that has jurisdiction to adjudicate
                  upon issues relating to the Project.
        13.2. Application and Principals for computing impact
              of Change in Law
        While determining the consequence of Change in Law
        under this Article 13, the Parties shall have due regard to
        the principle that the purpose of compensating the Party
        affected by such Change in Law, is to restore through
        Monthly Tariff payments, to the extent contemplated in
        this Article 13, the affected Party to the same economic
        position as if such Change in Law has not occurred.
             a) Construction Period
             As a result of any Change in Law, the impact of
             increase/decrease of Capital Cost of the Project in the
             Tariff shall be governed by the formula given below:
                  For every cumulative increase/ decrease of
                  each Rupees 16,50,00,000/- (Rupees Sixteen
                  crore fifty lakhs) in the Capital Cost over the
                  term of this Agreement, the increase/decrease
[2025] 8 S.C.R.                                                           1323

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

                       in Non Escalable Capacity Charges shall be
                       an amount equal to 0.267% (percentage zero
                       point two six seven) of the Non Escalable
                       Capacity Charges. Provided that the Seller
                       provides to the Procurer documentary proof
                       of such increase/ decrease in Capital Cost for
                       establishing the impact of such Change in Law.
                       Jn case of Dispute, Article 17 shall apply.
                       It is clarified that the above mentioned
                       compensation shall be payable to either Party,
                       only with effect from the date on which the total
                       increase/decrease exceeds amount of Rupees
                       16,50,00,000/- (Rupees Sixteen crore fifty
                       lakhs).
                    b) Operation Period
                    As a result of Change in Law, the compensation for
                    any increase/decrease in revenues or cost to the
                    Seller shall be determined and effective from such
                    date, as decided by the Appropriate Commission
                    whose decision shall be final and binding on both
                    the Parties, subject to rights of appeal provided
                    under applicable Law.
                    Provided that the above mentioned compensation
                    shall be payable only if and for increase/ decrease
                    in revenues or cost to the Seller is in excess of an
                    amount equivalent to 1% of the Letter of Credit in
                    aggregate for a Contract Year.
           13.3. Notification of Change in Law
                    13.3.1. If the Seller is affected by a Change in Law
                            in accordance with Article 13.2 and wishes
                            to claim a Change in Law under this Article,
                            it shall give notice to the Procurer of such
                            Change in Law as soon as reasonably
                            practicable after becoming aware of the
                            same or should reasonably have known
                            of the Change in Law.
1324                                                     [2025] 8 S.C.R.

                       Supreme Court Reports


             13.3.2.    Notwithstanding Article 13.3.1, the Seller
                        shall be obliged to serve a notice to the
                        Procurer under this Article 13.3.2 if it
                        is beneficially affected by a Change in
                        Law. Without prejudice to the factor of
                        materiality or other provisions contained in
                        this Agreement, the obligation to inform the
                        Procurer contained herein shall be material.
                        Provided that in case the Seller has not
                        provided such notice, the Procurer shall have
                        the right to issue such notice to the Seller.
             13.3.3. Any notice served pursuant to this Article
                     13.3.2 shall provide, amongst other things,
                     precise details of:
                       (a) the Change in Law; and
                       (b) the effects on the Seller of the matters
                       referred to in Article 13.2.
        13.4. Tariff Adjustment Payment on account of Change
              in Law
             13.4.1. Subject to Article 13.2, the adjustment in
                     Monthly Tariff Payment shall be effective
                     from:
                        (i) the date of adoption, promulgation,
                        amendment re-enactment or repeal of the
                        Law or Change in Law; or
                        (ii) the date of order/judgment of the
                        Competent Court or tribunal or Indian
                        Governmental Instrumentality, if the
                        Change in Law is on account of a change
                        in interpretation of Law.
             13.4.2. The payment for Changes in Law shall be
                     through Supplementary Bill as mentioned
                     in Article 11.8. However, in case of any
                     change in Tariff by reason of Change in
                     Law, as determined in accordance with this
[2025] 8 S.C.R.                                                              1325

                         Nabha Power Limited v.
           Punjab State Power Corporation Limited and Others

                            Agreement, the Monthly Invoice to be raised
                            by the Seller after such change in Tariff shall
                            appropriately reflect the changed Tariff.”
36. A contention is raised on behalf of the learned Senior Advocates
    for the Appellants that the Request for Proposal and the contractual
    framework between the parties as a whole clearly set a cut-off date for
    “Change in Law” under the Article 13 of the PPA and required them
    to deem all the prevailing laws, regulations, and their interpretations
    thereof to have been factored in the bidding process and the price
    thereof. It is accordingly contended that “law” included not only the
    statutory texts from the wisdom of the legislature but also any such
    authoritative interpretations of the law by an “Indian Government
    Instrumentality”, which they press DGFT to be one.
37. Moreover, arguing that similar benefits were given under FTP to MPP
    and non-MPP projects and to substantiate, reliance was placed on
    equivalent benefits being given to 144 other projects, implying settled
    nature of law. Alternatively, it is also argued that this interpretation
    was altered through the PIC dated 15.03.2011, and subsequently,
    led to withdrawing the benefits under Para 8.3(a) and (b) of the
    FTP for non-MPP altogether. Such an act would, the Appellants
    contend, constitute “Change in Law”, owing to the modifications to
    the existing entitlements.
38. Assailing the orders of the State Commission as well as the APTEL, it
    is also pressed that those forums erroneously only dealt with whether
    the Appellants satisfied the conditions under the FTP as opposed to
    the legality as to whether the said benefits were available as on the
    cut-off date, thereby committing of a jurisdictional error on their part by
    expanding the scope of the remand, being in contradiction to the law
    laid down in Shivshankara and Another v. H.P. Vedavyasa Char1.
    Relying on the decision of this Court in Haryana Power Purchase
    Centre v. Sasan Power Limited and Others2, it is further argued that
    the best material to establish that whether a project was exempted
    from the concerned duties as on the cut-off would be instances of
    other similarly placed project where goods were also treated to be
    exempt under the instant FTP.


1   (2023) 13 SCC 1
2   (2024) 1 SCC 247
1326                                                     [2025] 8 S.C.R.

                        Supreme Court Reports


39. On the other hand, the Respondents had relied on decision of
    this Court in GMR Warora Energy Limited v. Central Electricity
    Regulatory Commission (CERC) and Others3 to substantiate their
    claim for “Change in Law” through withdrawal of deemed export
    benefits through circulars of Ministry of Commerce and Industry as
    well as the Notification dated 28.12.2011. This contention is also
    rebutted by the Appellants claiming that the same is not applicable
    in the present case for having a varied factual matrix.
40. Whether the Press Release of Cabinet Decision pertaining to change
    of threshold of so-deemed export benefits constitutes a “Change
    in Law” under the PPA, an issue-at-hand, has been substantively
    dealt as part of decision of this Court in Nabha Power Limited
    and Another v. Punjab State Power Corporation Limited and
    Another4 wherein the question before this Court, arising from the
    same PPA and an equivalent dispute, was the juxtaposition of the
    MPP and the Press Release dated 01.10.2009. Therein, the 3-Judge
    Bench of this Court went on to observe that the fulcrum of the claim
    of the Appellant therein is anchored in the assertion that the Press
    Release dated 01.10.2009 was not merely a policy statement but a
    clear indication of an imminent shift in the regime of law governing
    the field. Appellant therein also claimed the said Press Release
    swayed its bid dated 09.10.2009 in terms of the incorporation of
    the deemed benefits and thereby created a legitimate expectation
    that the proposed exemptions would come into force, forming a vital
    part of the risk calculus vis-à-vis structuring of its bid amount. The
    Respondent therein went on to contend that no “Change in Law”
    occurred until the publication of Notification Nos. 91/2009-Cus and
    92/2009-Cus dated 11.12.2009 and 14.12.2009 respectively, implying
    that no expectation raised by the Appellant therein could be said to
    have been crystallised.
41. Answering the query, the Bench while placing reliance on earlier
    decisions of this Court, observed that the golden rule, as applicable
    on contractual interpretation, mandates that the words should be
    given their ordinary and grammatical meaning and should not depart
    from the mandate to avoid either absurdity or repugnancy, even the


3   (2023) 10 SCC 401
4   (2025) 5 SCC 353
[2025] 8 S.C.R.                                                      1327

                         Nabha Power Limited v.
           Punjab State Power Corporation Limited and Others

     business efficacy test, for which the jurisprudence was reiterated and
     outlined in Nabha Power Limited (NPL) v. Punjab State Power
     Corporation Limited (PSPCL) and Another5, cannot override an
     express term. While analysing the PPA, this Court elaborated that
     while Article 1.1 of the PPA elaborated “law” to include statutes,
     regulations, notifications, orders, and interpretations, the Article
     13.1.1. defined “Change in Law” as an enactment, amendment or
     repeal after 02.10.2009. Therefore, contention of the Appellant therein
     that the Press Release dated 01.10.2009 amounts to an “order” was
     held to have failed, while also referring its meaning in the Black’s
     Law Dictionary, which required a binding command. However, such
     notifications only emerged on 11.12.2009 and 14.12.2009.
42. Dealing with the subsequent questions of law, it also clarified that
    the contention of Appellant therein on failure of the Respondent to
    issue a notice as per the provisions of Article 13.3.1 and 13.3.2
    would vitiate the provisions is misplaced owing to the fact that the
    PPA only obligates a seller, and not a buyer as was PSPCL in the
    said case, to have notified in case the “Change in Law” when it is
    beneficial to it. The Bench also rejected the claims of the Appellant
    therein that the sub-clauses pertaining to changes in interpretation,
    licenses, land prices or rehabilitation costs are not applicable in the
    present case. Furthermore, placing reliance on Babu Verghese and
    Others v. Bar Council of Kerala and Others6 as well as Section
    21 of the General Clauses Act, 1897, it held that CA 1962 required
    the concerned notification to have been issued in a certain manner
    and be duly published in the official gazette, and reiterated that law,
    whether parliamentary or subordinate, must be published to enable
    them to take effect.
43. The Bench additionally clarified that the claim for legitimate
    expectation or promissory estoppel arising from the Press Release
    dated 01.10.2009 would not survive as the Central Government
    was neither a party to the PPA nor was the same subject to any
    judicially enforceable promise and no order of any court gave the
    said Press Release a legal force. Concluding, the 3-Judge Bench,
    relying on numerous precedents, confirmed that only duly promulgated


5   (2018) 11 SCC 508
6   (1999) 3 SCC 422
1328                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


     notifications, and not Press Releases or Communications, would
     constitute as “Change in Law”. Accordingly, no “Change in Law” had
     occurred until the Notifications dated 11.12.2009 and 14.12.2009,
     thereby implying that the benefits would have been deemed to be
     accrued only from the said dates.
44. Therefore, the aforesaid decision of 3-Judge Bench in Nabha
    Power Limited (supra) squarely covers the field of law in relation
    to the issue of determination of “Change in Law” in the instant case
    and same is answered accordingly, holding that the Press Release
    dated 01.10.2009 would neither amount to “law” within the meaning
    conceptualized in the PPA, as it would only be the Notifications dated
    11.12.2009 and 14.12.2009 that would have amounted to “law”, nor
    it would thereby amount to “Change in Law” as argued by Appellants
    in the instant Civil Appeals.
45. Having answered the issue pertaining to “Change in Law” we shall
    now deal with the issue as to whether deemed export benefits under
    Para 8.3 of the FTP were legitimately available to the Appellants
    as on the bid cut-off date. It is pertinent to also acknowledge that
    this issue shall also determine the contention of Appellants that
    withdrawal of deemed export benefits by notifications of DGFT dated
    28.12.2011 and 21.03.2012 collectively constitutes “Change in Law”
    as per the PPA.
46. It appears that the learned Senior Advocates appearing for NPL before
    the APTEL and the learned counsel appearing for TSPL therein had
    argued to the effect that the conditions prescribed under the FTP
    have been unambiguously satisfied. On the legal aspect, it was
    submitted that the scheme of FTP clearly pertains to “goods” and
    not to any “services”. Accordingly, contending that the whole power
    plant falls within the definition of “capital goods”, thereby eligible for
    the deemed export benefits.
47. To substantiate the said claim, the counsels elaborated that as Para
    9.12 of the FTP, “capital goods” encompasses any plant, machinery,
    equipment or accessories required, either directly or indirectly, for
    the production or rendering of services, including those necessary
    for replacement, modernisation, technological upgradation, and
    expansion, and also extends to machinery for packaging, power
    generating sets, instrumentations, and equipment(s) for various
    specialized functions. Placing reliance on the Minutes No. 01180
[2025] 8 S.C.R.                                                      1329

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     dated 15.04.2008 of the Norms Committee, it was contended that
     a power project was indeed recognised to fall within the ambit of
     “capital goods”, reiterating that key components such as turbines
     and generators used within a plant are an integral input, enabling
     the project to be entitled to advanced authorization benefits, which,
     as further contented, are akin to the duty drawback contemplated
     under Para 8.3(c) of the FTP.
48. It was further argued that the whole process of developing a power
    plant constitute as “manufacture” when placed in juxtaposition to
    the definition so provided under Para 9.36 of the FTP as it adopts
    a broader definition, including making, assembling, fabricating,
    processing, and bringing new product into existence. Such
    comprehensive scope, as contended, would also cover activities
    of construction where the imported and indigenous materials, such
    as the boilers, turbines, and generators are assembled on-site,
    resulting in a new, and functional power plant. This was further
    contented to be in line with the clarification issued by the DGFT on
    05.12.2000, apparently stating that assembly and commissioning at
    site to constitute “manufactured in India” for the purpose of availing
    deemed export benefits under the FTP. As the said clarification
    was in force as on the bid date, the Appellants met the criterion for
    “manufactured in India”, thereby fulfilling both the critical conditions
    for availing the aforesaid benefits.
49. Having failed on the said contentions before the APTEL, it appears
    that the Appellants have moulded the contentions before this Court to
    imply that the aforesaid were not the asserted case before the APTEL
    and instead the APTEL had erred in determining the entitlement of
    deemed export benefits under the FTP based on the imports made
    after the grant of MPP status and alleged policy changes as opposed
    to assessing the position of the Appellants as it stood on the cut-off
    date vis-à-vis the FTP.
50. It is now further argued that APTEL had erred in concluding that
    the Appellants claimed entire plant as “capital goods”, which is
    manifestly perverse and the contention was confined to the discrete
    components as supplied by both, the main contractor(s) and the
    sub-contractor(s). It is contended that numerous components were
    imported for the boiler, turbine, and generators which were then
    claimed to be assembled on-site into new products with distinct
1330                                                          [2025] 8 S.C.R.

                          Supreme Court Reports


      names, characteristics, and functions, meeting the stipulations under
      the FTP as these indigenous components, which were procured for
      the power plant would qualify as “goods” under the FTP as their
      importation was directly linked to the MPP.
51. Moreover, the APTEL ought not to have invoked the definition of
    “manufacture” under the CEA 1944, and such a disregard of the
    broader ambit of definition under Para 9.36 of the FTP, and the
    DGFT Circulars dated 05.12.2000 and 15.04.2008 recognising on-
    site assembly, erection, and testing thereof as “manufacture”. To
    support this, reliance is placed on decisions of this Court in Vadilal
    Chemicals Ltd. v. State of A.P. and Others7, MSCO. Pvt. Ltd. v.
    Union of India and Others8, Trutuf Safety Glass Industries v.
    Commissioner of Sales Tax, U.P.9 and P.C. Cheriyan v. Mst. Barfi
    Devi10. APTEL could not have also observed the clarifications issued
    by the DGFT to be an incorrect interpretation of the FTP.
52. It is subsequently raised that all the goods were supplied by contractors
    is also acknowledged by the APTEL vide Impugned Judgment in Para
    76(d). For this, it is contended that such importation would imply to
    squarely fall within the definition of “eligible supplier” under Para 8.2(f)
    of the FTP for the said goods are said to be procured from domestic
    manufacturers supplying against an process of ICB. It is pressed
    into service on part of the Appellants that on the mandate of ICB
    as per Para 8.4.4(iv) of the FTP, APTEL further erred in adopting a
    restrictive interpretation and the mandate was complied with at the
    stage of Independent Power Producer stage in light of the DGFT
    Clarification dated 14.08.2008. Subsequent arrangements made for
    stage of Engineering and Procurement, and construction through
    sub-contracts does not dilute the aforesaid compliance.
53. Concluding, it is contended that the projects were duly certified as
    MPP and a subsequent refusal to extend such deemed export benefits
    would be in derogation of the mandate of the FTP.
54. Alternatively, the Appellants have also argued that as per a collective
    reference to the FTP and the MPP, if it is to be held that they were


7    (2005) 6 SCC 292
8    (1985) 1 SCC 51
9    (2007) 7 SCC 242
10   (1980) 2 SCC 461
[2025] 8 S.C.R.                                                           1331

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     not entitled to the deemed export benefits under the FTP as MPP,
     owing to the same eligibility conditions for a non-MPP under the
     FTP, as on the cut-off date, they were equally entitled as a non-MPP.
55. Countering the aforesaid contentions raised on behalf of the
    Appellants, learned Senior Advocate on behalf of the opposing
    Respondent(s), while vehemently contesting the claims of the
    Appellants have reiterated their successful claims before the APTEL.
56. Before we delve into the submissions moved by the Appellants, it is
    pertinent to refer to Chapter 8 of the FTP, which reads as follows:

           “8.1 Deemed Exports
           ‘Deemed Exports’ refer to those transactions in which
           goods supplied do not leave country, and payment for
           such supplies is received either in Indian rupees or in free
           foreign exchange.

           8.2 Categories of Supply
           Following categories of supply of goods by main / sub-
           contractors shall be regarded as ‘Deemed Exports’ under
           FTP, provided goods are manufactured in India:
                (a) Supply of goods against Advance Authorisation /
                Advance Authorisation for annual requirement / DFIA;
                (b) Supply of goods to EOUs / STPs / EHTP / BTP;
                (c) Supply of capital goods to EPCG Authorisation
                holders;
                (d) Supply of goods to projects financed by multilateral
                or bilateral Agencies / Funds as notified by Department
                of Economic Affairs (DEA), MoF under International
                Competitive Bidding (ICB) in accordance with
                procedures of those Agencies / Funds, where legal
                agreements provide for tender evaluation without
                including customs duty;
                Supply and installation of goods and equipment
                (single responsibility of turnkey contracts) to projects
                financed by multilateral or bilateral Agencies / Funds
                as notified by DEA, MoF under ICB in accordance
1332                                                    [2025] 8 S.C.R.

                      Supreme Court Reports


             with procedures of those Agencies / Funds, which
             bids may have been invited and evaluated on the
             basis of Delivered Duty Paid (DDP) prices for goods
             manufactured abroad;
             (e) Supply of capital goods, including in unassembled /
             disassembled condition as well as plants, machinery,
             accessories, tools, dies and such goods which are
             used for installation purposes till stage of commercial
             production, and spares to extent of 10% of FOR value
             to fertilizer plants;
             (f) Supply of goods to any project or purpose in
             respect of which the MoF, by a notification, permits
             import of such goods at zero customs duty;
             (g) Supply of goods to power projects and refineries
             not covered in (f) above;
             (h) Supply of marine freight containers by 100% EOU
             (Domestic freight containers-manufacturers) provided
             said containers are exported out of India within 6
             months or such further period as permitted by customs;
             (i) Supply to projects funded by UN Agencies; and
             (j) Supply of goods to nuclear power projects through
             competitive bidding as opposed to ICB.
             Benefits of deemed exports shall be available under
             paragraphs (d), (e), (f) and (g) only if the supply is
             made under procedure of ICB.

        8.3 Benefits for Deemed Exports
        Deemed exports shall be eligible for any / all of following
        benefits in respect of manufacture and supply of goods
        qualifying as deemed exports subject to terms and
        conditions as in HBP v1:-
             (a) Advance Authorisation / Advance Authorisation
             for annual requirement / DFIA.
             (b) Deemed Export Drawback.
[2025] 8 S.C.R.                                                           1333

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

                (c) Exemption from terminal excise duty where
                supplies are made against ICB. In other cases, refund
                of terminal excise duty will be given. Exemption from
                TED shall also be available for supplies made by
                an Advance Authorisation holder to a manufacturer
                holding another Advance Authorization if such
                manufacturer, in turn, supplies the product(s) to an
                ultimate exporter.

           Benefits to the Supplier
             8.4.1. (i) In respect of supplies made against Advance
                    Authorisation / DFIA in terms of paragraph 8.2(a)
                    of FTP, supplier shall be entitled to Advance
                    Authorisation / DFIA for intermediate supplies.
                     (ii) If supplies are made against Advance
                     Release Order (ARO) or Back to Back Letter of
                     Credit issued against Advance Authorisation /
                     DFIA in terms of paragraphs 4.1.11 and 4.1.12 of
                     FTP, suppliers shall be entitled to benefits listed
                     in paragraphs 8.3(b) and (c) of FTP, wherever
                     is applicable.
             8.4.2. In respect of supply of goods to EOU / EHTP /
                    STP / BTP in terms of paragraph 8.2(b) of FTP,
                    supplier shall be entitled to benefits listed in
                    paragraphs 8.3(a), (b) and (c) of FTP, whichever
                    is applicable.
             8.4.3. In respect of supplies made under paragraph
                    8.2(c) of FTP, supplier shall be entitled to the
                    benefits listed in paragraphs 8.3(a), (b) and (c)
                    of the Policy, whichever is applicable.
             8.4.4. (i) In respect of supplies made under paragraphs
                    8.2(d), (f) and (g) of FTP, supplier shall be
                    entitled to benefits listed in paragraphs 8.3(a),
                    (b) and (c), whichever is applicable.
                     (ii) In respect of supplies mentioned in paragraph
                     8.2(d), supplies to projects funded by such
                     Agencies alone, as may be notified by DEA, MoF,
1334                                            [2025] 8 S.C.R.

           Supreme Court Reports


        shall be eligible for deemed export benefits. A list
        of such Agencies / Funds is given in Appendix
        13 of HBP v1.
        (iii) Benefits of deemed exports under para
        8.2(f) of FTP shall be applicable in respect
        of items, import of which is allowed by DoR
        at zero customs duty, subject to fulfillment of
        conditions specified under Notification No.
        21/2002-Customs dated 1.3.2002, as amended
        from time to time.
        (iv) Supply of Capital goods and spares upto
        10% of FOR value of capital goods to power
        projects in terms of paragraph 8.2(g), shall be
        entitled for deemed export benefits provided
        the ICB procedures have been followed at
        Independent Power Producer (IPP) / Engineering
        and Procurement Contract (EPC) stage. Benefit
        of deemed exports shall also be available for
        renovation / modernization of power plants.
        Supplier shall be eligible for benefits listed in
        paragraph 8.3(a) and (b) of FTP, whichever is
        applicable. However, supply of goods required
        for setting up of any mega power projects as
        specified in S.No. 400 of DoR Notification
        No. 21/2002-Customs dated 1.3.2002, as
        amended, shall be eligible for deemed export
        benefits as mentioned in paragraph 8.3(a),
        (b) and (c) of FTP, whichever is applicable, if
        such mega power project complies with the
        threshold generation capacity specified therein,
        in Customs Notification.
        (v) Supplies under paragraph 8.2(g) of FTP to
        new refineries being set up during Ninth Plan
        period and spilled over to Tenth Plan period,
        shall be entitled for deemed export benefits in
        respect of goods mentioned in list 17 specified in
        S.No. 228 of Notification No. 21/2002-Customs
        dated 1.3.2002, as amended from time to time.
[2025] 8 S.C.R.                                                            1335

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

                      Supplier shall be eligible for benefits listed in
                      paragraphs 8.3(a) and (b) of FTP, whichever
                      is applicable.
             8.4.5. In respect of supplies made under paragraph
                    8.2(e) of FTP, supplier shall be eligible for
                    benefits listed in paragraph 8.3(a) and (b) of
                    FTP, whichever is applicable. Benefit of deemed
                    exports shall be available in respect of supplies
                    of capital goods and spares to Fertilizer Plants
                    which are set up or expanded / revamped /
                    retrofitted / modernized during Ninth Plan period.
                    Benefit of deemed exports shall also be available
                    on supplies made to Fertilizers Plants, which
                    have started in the 8th / 9th Plan periods and
                    spilled over to 10th Plan period.
             8.4.6. Supplies of goods to projects funded by UN
                    Agencies covered under para 8.2(i) of FTP are
                    eligible for benefits listed in paragraph 8.3(a)
                    and (b) of FTP, whichever is applicable.
             8.4.7. In respect of supplies made to Nuclear Power
                    Projects under para 8.2(j) of FTP, the supplier
                    would be eligible for benefits given in para 8.3(a),
                    (b) and (c) of FTP, whichever is applicable.
                    Supply of only those goods required for setting
                    up any Nuclear Power Poject specified in list 43
                    at S.No. 401 of Notification No. 21/2002-Customs
                    dated 1.3.2002, as amended from time to time,
                    having a capacity of 440MW or more as certified
                    by an officer not below rank of Joint Secretary
                    to Government of India in Department of Atomic
                    Energy, shall be entitled for deemed exports
                    benefits in cases where procedure of competitive
                    bidding (and not ICB ) has been followed.

           8.5 Eligibility for refund of terminal excise duty /
           drawback
           Supply of goods will be eligible for refund of terminal excise
           duty in terms of para 8.3(c) of FTP, provided recipient of
1336                                                    [2025] 8 S.C.R.

                      Supreme Court Reports


        goods does not avail CENVAT credit / rebate on such
        goods. Similarly, supplies will be eligible for deemed
        export drawback in terms of para 8.3(b) of FTP on Central
        Excise paid on inputs / components, provided CENVAT
        credit facility / rebate has not been availed by applicant.
        Such supplies will however be eligible for deemed export
        drawback on customs duty paid on inputs / components.
          8.5.1. Simple interest @ 6% per annum will be payable
                 on delay in refund of drawback and terminal
                 excise duty under deemed export scheme, if
                 the case is not settled within 30 days of receipt
                 of complete application (as in paragraph 9.10.1
                 of HBP v1).

          8.6.1. Supplies to be made by the main / sub-
                 contractor
                  In all cases of deemed exports, supplies shall
                  be made directly to designated Projects /
                  Agencies / Units / Advance Authorisation /
                  EPCG Authorisation holders. Sub-contractor
                  may, however, make supplies to main contractor
                  instead of supplying directly to designated
                  projects / Agencies. Such supplies shall be
                  eligible for deemed export benefits as per
                  procedure laid down in paragraph 8.4 of HBP v1.
          8.6.2. Supplies made by an Indian sub-contractor of
                 an Indian or foreign main contractor directly to
                 the designated projects / Agencies, shall also
                 be eligible for deemed export benefits provided
                 sub-contractor is indicated either originally or
                 subsequently in the contract, and payment
                 certificate is issued by project authority in the
                 name of sub-contractor as in Appendix 22C of
                 HBP v1.”
        The following definitions within FTP also ought to be
        referred:
        “9.12 ‘Capital Goods’ means any plant, machinery,
              equipment or accessories required for manufacture
[2025] 8 S.C.R.                                                             1337

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

                    or production, either directly or indirectly, of goods
                    or for rendering services, including those required
                    for replacement, modernisation, technological
                    upgradation or expansion. It also includes packaging
                    machinery and equipment, refractories for initial
                    lining, refrigeration equipment, power generating
                    sets, machine tools, catalysts for initial charge,
                    equipment and instruments for testing, research
                    and development, quality and pollution control.
                    Capital goods may be for use in manufacturing,
                    mining, agriculture, aquaculture, animal husbandry,
                    floriculture, horticulture, pisciculture, poultry,
                    sericulture and viticulture as well as for use in
                    services sector.

                           xxx              xxx               xxx
           9.14 ‘Component’ means one of the parts of a sub-
                assembly or assembly of which a manufactured
                product is made up and into which it may be
                resolved. A component includes an accessory or
                attachment to another component.

                           xxx              xxx               xxx
           9.36 ‘Manufacture’ means to make, produce, fabricate,
                assemble, process or bring into existence, by
                hand or by machine, a new product having
                a distinctive name, character or use and
                shall include processes such as refrigeration,
                re-packing, polishing, labelling, Re-conditioning
                repair, remaking, refurbishing, testing, calibration,
                re-engineering. Manufacture, for the purpose of FTP,
                shall also include agriculture, aquaculture, animal
                husbandry, floriculture, horticulture, pisciculture,
                poultry, sericulture, viticulture and mining.”
57. From a perusal of the FTP, pleadings as well as submissions of
    the parties, as aforesaid, there are five essential prerequisites that
    ought to be satisfied by the Appellants in order to be eligible for the
    deemed export benefit(s). The said pre-conditions can be enumerated
    in the following manner:
1338                                                         [2025] 8 S.C.R.

                          Supreme Court Reports


     (i)    The claim for Deemed Export Benefits relates exclusively to
            “goods” and is inapplicable to any other thing which is not
            “goods”. Such goods, though supplied, do not physically exit
            the territorial boundaries of the country.
     (ii)   The goods to be supplied must be “manufactured in India”.
     (iii) There must be an act constituting “supply of goods” to the
           power projects for the project to claim Deemed Export Benefits.
     (iv) The act of “supply of goods” is either by the main contractor
          and/or the sub-contractor to the concerned power project.
     (v)    The supply is undertaken strictly in accordance with the
            procedural framework prescribed under ICB.
58. Now we would proceed to consider and deal with the above culled
    out essential ingredients for being eligible for claim of Deemed
    Export Benefits.
59. From the FTP, it is apparent that the foremost prerequisite to avail
    the deemed export benefits is limited to “goods”, the definition for
    which is absent therein, despite there being an explicit reference to
    “capital goods” and “consumer goods”. Accordingly, we may refer to
    the following references to define “goods”. Firstly, in Fifth edition of
    P. Ramanatha Aiyar’s Advanced Law Lexicon, wherein, goods has
    been defined as:
            “‘GOODS’ means every kind of movable property other
            than actionable claims and money; and includes stocks
            and shares, growing crops, grass and things attached, to
            or forming part of the land which are agreed to be severed
            before sale or under the contract of sale. [Sale of Goods
            Act (3 of 1930), S. 2(7)]
            For the purposes of this clause, “goods” includes any article
            material or substance which is capable of being bought and
            sold for a consideration and such goods shall be deemed
            to be marketable. [Central Excise Act (1 of 1944), S. 2,
            Expln. as inserted by Finance Act (18 of 2008), S. 78]

                    xxx                 xxx                  xxx
            ‘Goods’ means all kinds of movable property other than
            actionable claims, stocks, shares and securities, and
[2025] 8 S.C.R.                                                           1339

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

           includes all materials, articles and commodities including
           the goods (as goods or in some other form), involved in
           the execution of a works contract or those goods used or
           to be used in the construction, fitting out, improvement or
           repair of movable or immovable property and also includes
           all growing crops, grass and things attached to or forming
           part of the land which are agreed to be severed before
           sale or under the contract of sale and also includes motor
           spirit.”[A.P. General Sales Tax Act (6 of 1957), S. 2(1)(h)
           as cited in Tata Consultancy Services v. State of A.P.,
           (2005) 1 SCC 308, 316, para 7])

                    xxx                xxx                  xxx
           ‘GOODS’ means all kinds of movable property (other
           than newspaper, actionable claims, stocks and shares
           and securities), and includes, all materials, commodities,
           and articles including the goods, as goods or in some
           other form) involved in the execution of a work-contract
           or, those goods to be used in the fitting out improvement
           or repair of moveable property and all growing crops,
           grass or things, attached to, or forming part of, the lands
           which are agreed to be severed before sale or under the
           contract of sale. [Karnataka Sales Tax Act (25 of 1957), S.
           2(m) and T.N. General Sales Tax Act (1 of 1959), S. 2(j)
           as cited in Vikas Sales Corpn v. Commr. of Commercial
           Taxes, (1996) 4 SCC 433, 441-42, pp. 15, 16: AIR 1996
           SC 2082]
           ‘GOODS’ means machinery, motor vehicles, equipment,
           furniture, articles of stationary, textiles raw materials,
           drugs, scientific instruments, chemical, food grains, oil and
           oil seeds or other commodity required for consumption,
           use or distribution by a procurement entity in discharge
           of its public duties’. [Karnataka Transparency in Public
           Procurement Act (29 of 2000), S. 2(b) as cited in State of
           Karnataka v. Fisheries Welfare Co-operative Society Ltd.,
           AIR 2012 Kar 132, para 2].”
     Secondly, in Third Edition of Supreme Court Words and Phrases
     by Surendra Malik and Sumit Malik, “goods” are defined to be as:
1340                                                          [2025] 8 S.C.R.

                              Supreme Court Reports


             “‘Goods’- Constitution of India - Sch. VII List II Entries 53
             & 54 and Arts. 366(12) & (29-A)
             ‘Goods’ may be tangible or intangible prop- erty. It would
             become goods provided it has the attributes thereof having
             regard to (a) its utility; (b) capable of being bought and
             sold; and (c) capable of being transmitted, transferred,
             delivered, stored and possessed. (Para 151)”
60. It is apparent from the aforesaid that in the common parlance, the
    term “goods” denotes movable items and shall exclude immovable
    items. To further elaborate, this Court in Quality Steel Tubes (P)
    Ltd v. Collector of Central Excise, U.P.11 went on to observe that for
    a good to qualify as “excisable”, it must qualify as “goods” and should
    also be able to satisfy the “marketability test” which was established
    in Union of India and Another v. Delhi Cloth and General Mills
    Co. Ltd.12 and was reiterated in the subsequent decisions of this
    Court in Collector of Central Excise, Baroda v. Ambalal Sarabhai
    Enterprises (P) Ltd.13 and Union Carbide India Limited v. Union
    of India and Others14. Therefore, it stands settled that an immovable
    property, especially a machinery embedded to earth, as in the instant
    case, would fail the aforesaid test.
61. It is also true that Captive Power Plants have been recognized
    as “capital goods” within the scope of subsequent FTP, but those
    importable products are movable and cannot be equated to the
    Project Plant in the instant case. The correct means to analyse
    and determine expression “capital goods” would be subject to the
    definition of the term “goods” especially when Para 9.12 of the FTP
    only encompasses movable items. It would not be possible within the
    given canvas to hold that an embedded power plant of hundreds of
    Mega Watts would be able to qualify as “capital goods” for entitlement
    of the Appellants under the FTP for the deemed export benefits.
62. The second prerequisite is derived from the opening paragraph of
    Para 8.2 of the FTP makes it obligatory that concerned goods as
    required to be supplied must be manufactured in India. Para 9.36


11   (1995) 2 SCC 372
12   1962 SCC OnLine SC 148
13   (1989) 4 SCC 112
14   (1986) 2 SCC 547
[2025] 8 S.C.R.                                                          1341

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     of the FTP goes on to define “manufacture” as making, producing,
     fabricating, assembling, processing, or otherwise bringing into
     existence, by hand or machine, a new product with a distinctive
     name, character, or use, and goes on to include processes like
     refrigeration, repacking, polishing, labelling, reconditioning, repairing,
     remaking, refurbishing, testing, calibration, and re-engineering, as
     well as activities like agriculture, horticulture, floriculture, animal
     husbandry, pisciculture, poultry, sericulture, viticulture, and mining.
     Dealing further with “manufacture”, we may refer to the Fifth edition
     of P. Ramanatha Aiyar’s Advanced Law Lexicon wherein, the varied
     and relevant connotations of the word have been elaborated as:
           “‘MANUFACTURE’ implies a change, but every change is
           not manufacture and yet every change of an article is the
           result of treatment labour and manipulation. But something
           more is necessary and there must be transformation; a
           new and different article must emerge having a distinctive
           name, character or use. [Words and Phrases, Permanent
           Edition, Vol XXVI, as cited in Union of India v. Ahmedabad
           Electricity Co. Ltd., AIR 2004 SC 11, 16, para 19]
           Conversion of raw materials into a finished product, e.g.
           converting iron ore into steel plate.
           Manufacture is: (1) The application, to material, of labour
           or skill, whereby the original article is changed to a new,
           different, and useful article, provided the process is of a
           kind popularly regarded as manufacture, or (2) the product
           of such process.
           ‘Whatever is made by human labour, either directly or
           through the instrumentality of machinery.’ (Abbott L. Dict.)
           To constitute a manufacture, within the customs duty acts,
           there must be a transformation. Mere labour bestowed on
           an article, even if the labour is applied through machinery,
           will not make it a manufacture, unless it has progressed so
           far that a transformation ensues, and the article becomes
           commercially known as another and different article from
           that as which it began its existence.
           Every alteration in an article does not confer on it a new
           character as a manufacture. To constitute a new and
1342                                                       [2025] 8 S.C.R.

                      Supreme Court Reports


        different article and a manufactured article, it must be
        so changed as to have a positive and specific use in its
        new state.
        ‘The process of making a thing by art.’ (Burrill)
        The word ‘manufacture’ is a compound word of Latin origin
        derived from the words “manu,” by hand and “facere,” to
        do, to make, to form; but the meaning is not confined to
        that which is done by hand alone, but by machinery as
        well. (In re Tecopa Min, etc., Co., 110 Fed 120, 121. See
        also 110 IC 788: 29 Cr LJ 756: 1928 Pat 506)

                xxx                xxx                 xxx
        Etymologically, ‘manufacture’ is a compound word from
        Latin “manu” meaning “hand” and “facere” which means
        “made”. Thus, in its primary sense, ‘manufacturing’ is
        fashioning of a raw or wrought material by manual or
        mechanical manipulation, resulting in its transformation; a
        new and different article must emerge having a distinctive
        name, character or use. Raghbir Chand Som Chand v.
        Excise & Taxn. Officer, (1960) 11 STC 149, 164-5 (Punj).
        Also see North Bengal Stores Ltd. v. Board of Revenue,
        (1938-50) 1 STC 157, 163-4 (Cal); State of Bihar v.
        Chrestien Mica Industries Ltd., (1956) 7 STC 626, 631
        (Pat), affirmed (1961) 12 STC 150 (SC); G.R. Kulkarni v.
        The State, (1957) 8 STC 294 (MP); CIT v. Casino (Pvt.)
        Ltd., (1973) 91 ITR 289 (Ker)

                xxx                xxx                 xxx
        ‘The word ‘Manufacture’,’ said ABBOTT, C.J., in R. v.
        Wheeler, 2 B. & Ald. 349, has been generally understood
        to denote, either a thing made which is useful for its own
        sake and vendible as such, as a medicine, a stove, a
        telescope, and many others; or to mean an engine or
        instrument, or some part of an engine or instrument, to be
        employed either in the making of some previously known
        article, or in some other useful purpose, as a stocking
        frame, or a steam engine for raising water from mines;
        or, it may, perhaps, extend also to a new process to be
        carried on by known implements or elements acting upon
[2025] 8 S.C.R.                                                             1343

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

           known substances, and ultimately producing some other
           known substance but producing it in a cheaper or more
           expeditious manner, or of a better or more useful kind.
           No mere philosophical or abstract principle can answer
           to the word ‘Manufactures.’ Something of a corporeal and
           substantial nature,— something that can be made by man
           from the matters subjected to his art and skill, or at the
           least some new mode of employing practically his art and
           skill, is required to satisfy the word.” (See also Gibson v.
           Brand, 4 M. & G. 199)

                    xxx                 xxx                  xxx
           The expression ‘manufacture’ is normally related to
           movable articles and goods. It cannot be employed to
           denote construction of a building or a dam or a bridge.
           [CIT v. Ceo Tech Foundation and Construction, (2000)
           241 ITR 90 (Ker)]”
63. Even a 5-Judge Bench of this Court, in Delhi Cloth and General
    Mills (supra), while dealing with determination of excise duty on the
    Respondents therein under the Central Excise and Salt Act, 1944
    observed that:
           "16. This consideration of the meaning of the word
                ‘goods’ provides strong support for the view that
                “manufacture” which is liable to excise duty under
                the Central Excise and Salt Act, 1944 must be the
                ‘bringing into existence of a new substance known to
                the market’. ‘But,’ says the learned counsel, “look at
                the definition of ‘manufacture’ in the definition clause
                of the Act and you will find that ‘manufacture’ is defined
                thus: ‘Manufacture includes any process incidental
                or ancillary to the completion of a manufactured
                product.’ [Section 2(f)]. We are unable to agree with
                the learned counsel that by inserting this definition of
                the word ‘manufacture’ in Section 2(f) the legislature
                intended to equate ‘processing’ to ‘manufacture’ and
                intended to make more ‘processing’ as distinct from
                ‘manufacture’ in the sense of bringing into existence
                of a new substance known to the market, liable to
                duty. The sole purpose of inserting this definition
1344                                                               [2025] 8 S.C.R.

                             Supreme Court Reports


                    is to make it clear that at certain places in the Act
                    the word ‘manufacture’ has been used to mean a
                    process incidental to the manufacture of the article.
                    Thus in the very item under which the excise duty
                    is claimed in these cases, we find the words; ‘in or
                    in relation to the manufacture of which any process
                    is ordinarily carried on with the aid of power’. The
                    definition of ‘manufacture’ as in Section 2(f) puts it
                    beyond any possibility of controversy that if power
                    is used for any of the numerous processes that are
                    required to turn the raw material into a finished article
                    known to the market the clause will be applicable;
                    and an argument that power is not used in the
                    whole process of manufacture using the word in its
                    ordinary sense, will not be available. It is only with
                    this limited purpose that the legislature, in our opinion,
                    inserted this definition of the word ‘manufacture’ in
                    the definition section and not with a view to make the
                    mere ‘processing’ of goods as liable to excise duty.”
64. While discussing the meaning of the word “production”, a reference
    was made by this Court to the elaboration of “manufacture” as well
    in India Cine Agencies v. Commissioner of Income Tax, Madras15
    in a dispute involving entitlement of benefits under Sections 32-AB,
    80-HH, 80-I of Income Tax Act, 1961 as:
             "5.    In Words and Phrases, 2nd Edn. by Justice R.P.
                    Sethi the expressions ‘produce’ and ‘production’ are
                    described as under:
                    ‘In Webster’s New International Dictionary, the word
                    ‘produce’ means something that is brought forth either
                    naturally or as a result of effort and work; a result
                    produced. In Black’s Law Dictionary, the meaning of
                    the word ‘produce’ is to ‘bring into view or notice; to
                    bring to surface’. A reading of the aforesaid dictionary
                    meanings of the word ‘produce’ does indicate that if a
                    living creature is brought forth, it can be said that it is
                    produced. [See CIT v. Venkateswara Hatcheries (P)


15   (2008) 17 SCC 385
[2025] 8 S.C.R.                                                            1345

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

                Ltd. [(1999) 3 SCC 632] , CIT v. N.C. Budharaja and
                Co. [1994 Supp (1) SCC 280 : (1993) 204 ITR 412] ]
                Production or produce.—The word ‘production’ or
                ‘produce’ when used in juxtaposition with the word
                ‘manufacture’ takes in bringing into existence new
                goods by a process, which may or may not amount
                to manufacture. It also takes in all the by-products,
                intermediate products and residual products, which
                emerge in the course of manufacture of goods. The
                expressions ‘manufacture’ and ‘produce’ are normally
                associated with movable articles and goods, big and
                small but they are never employed to denote the
                construction activity of the nature involved in the
                construction of a dam or for that matter a bridge, a
                road and a building. [See Moti Laminates (P) Ltd. v.
                CCE [(1995) 3 SCC 23] .]’
           6.   In Advanced Law Lexicon, 3rd Edn. by P. Ramanatha
                Aiyar, the expressions ‘production’ and ‘manufacture’
                are described as under:
                ‘ ‘Production’ with its grammatical variations and
                cognate expressions; includes—
                     (i) packing; labelling, re-labelling, of containers,
                     (ii) re-packing from bulk packages to retail
                     packages, and
                     (iii) the adoption of any other method to render
                     the product marketable.
                ‘Production’ in relation to a feature film, includes any
                of the activities in respect of the making thereof. [Cine
                Workers and Cinema Theatre Workers (Regulations
                of Employment) Act (50 of 1981), Section 2(i).]
                                           ***
                The word ‘production’ may designate as well a thing
                produced as the operation of producing; (as) production
                of commodities or the production of a witness.
                                           ***
1346                                                                [2025] 8 S.C.R.

                                 Supreme Court Reports


                       ‘Manufacture’ includes any art, process or manner of
                       producing, preparing or making an article, and also
                       any article prepared or produced by manufacture.
                       [Patents and Designs Act (2 of 1911), Section 2(10).]
                                                   ***
                       ‘Manufacture’ includes any process—
                              (i) incidental or ancillary to the completion of a
                              manufactured product; and
                              (ii) which is specified in relation to any goods
                              in the section or Chapter Notes of the First
                              Schedule to the Central Excise Tariff Act, 1985
                              (5 of 1986) as amounting to manufacture, or,
                              and the word ‘manufacturer’ shall be construed
                              accordingly and shall include not only a person
                              who employs hired labour in the production or
                              manufacture of excisable goods, but also any
                              person who engages in their production or
                              manufacture on his own account;
                              (iii) which is specified in relation to any goods
                              by the Central Government, by notification in the
                              Official Gazette, as amounting to manufacture.
                              [Central Excise Act (1 of 1944), Section 2(f)]’ ”
65. Placing reliance on this Court’s decision in Commissioner of Income
    Tax, Orissa and Others v. M/s N.C. Budharaja and Company and
    Others16, High Courts, such as that of Kerala, in Commissioner
    of Income-Tax v. Geo Tech Foundation & Constructions17 have
    also proceeded to hold that while “manufacture” and “produce” are,
    in the usual understanding, associated with movable articles and
    goods, the same can never be deemed to also include or to denote
    an activity amounting to construction.
66. Similarly, in Moti Laminates Pvt. Ltd. and Others v. Collector
    of Central Excise, Ahmedabad18, this Court observed that excise


16   (1994) Supp. 1 SCC 280
17   (2000) 241 ITR 90 : 1999 SCC OnLine Ker 341
18   (1995) 3 SCC 23
[2025] 8 S.C.R.                                                     1347

                          Nabha Power Limited v.
            Punjab State Power Corporation Limited and Others

      duty can only be applied to the produced goods which are usable,
      movable, saleable, and marketable. Also from the aforementioned
      decisions like the Union Carbide India (supra), Bhor Industries
      Limited, Bombay v. Collector of Central Excise, Bombay19, and
      Hindustan Polymers v. Collector of Central Excise20, it was
      reiterated that goods ought to be known in the market and should
      be capable of being sold.
67. Therefore, in the light of the above, the instant case, as projected
    and pressed before us by the Appellants, would fall foul of
    the essentiality when Para 9.36 of the FTP requires that the
    manufactured good should have been brought into existence with
    a distinctive name, character, or use. Such a feasibility would be
    impossible when it comes to the concerned power plants in the
    instant set of Appeals.
68. The third essential criterion for availing the said deemed export
    benefits is “supply of goods” to a power plant, as is contemplated
    under Para 8.2(g) of the FTP. However, from the original pleadings
    of the Appellants before the APTEL, it is established that they had
    made an unsuccessful attempt to argue that the whole power plant
    under their concerned Project fell within the ambit of definition of
    supply of “goods”. Contemplating their contention on the basis
    that the power plant falls within “capital goods”, it would neither be
    permissible nor viable to supply a power plant to itself as per the
    mandate of the FTP and especially, in the light of Para 8.2(g) of
    the FTP contemplating categorization of “supply of goods” to power
    projects and refineries not covered in Para 8.2(f) which, in turn,
    deals with supply of goods to any project or purpose in respect
    of which the Ministry of Finance, by a notification, permits import
    of such goods at zero customs duty. Therefore, we are inclined to
    accept the contentions raised on behalf of PSPCL and observe this
    condition to remain unfulfilled.
69. The fourth foundational prerequisite to avail the deemed export
    benefits, as stipulated through Para 8.2, read with Para 8.6 of the
    FTP mandates that the supply of goods must be effected either by
    the main contractor or the sub-contractor to the concerned project.


19   (1989) 1 SCC 602
20   (1989) 4 SCC 323
1348                                                      [2025] 8 S.C.R.

                        Supreme Court Reports


     In the present factual matrix an entitlement to the deemed export
     benefits only accrue when the goods, as manufactured by the main
     contractor, are supplied to the Project, herein being either the NPL
     or TSPL, or in the alternative, the goods are manufactured by the
     sub-contractor and supplied directly to the project or through the
     main contractor. However, it appears that before the forums of law
     below, and even at the time of bidding, the to-be then constructed
     Power Plant itself was deemed as the concerned capital goods for the
     deemed export benefits, implying that there was no distinct supply of
     goods by either a main contractor or a sub-contractor thereof. Rather,
     a claim to seek the benefits in respect of the entire power plant was
     made. Such a situation of suo moto acclaimed manufacturing in the
     Project’s own right shall not stand the instant test.
70. The fifth prerequisite for availing the aforementioned benefits under
    the FTP is a strict adherence to the necessity of procurement of
    goods through ICB, as stipulated in the latter part of the Para 8.2
    and Para 8.4.4(iv) of the FTP. Herein, it is categorically made
    mandatory that the supplies as contemplated under clauses (d),
    (e), (f), and (g) of the Para 8.2 would qualify for the deemed export
    benefits only if the same is so effected through the mandate of
    ICB. Moreover, Para 8.4.4(iv) provides that the supply of capital
    goods and permissible spare up to 10% of the Free on Rail value
    to the concerned power projects under Para 8.2(g), subject to
    the condition that ICB has been adopted either at the stage of
    Independent Power Producer or Engineering Procurement Contract.
    The said benefit originally also extended to the MPPs, subject to the
    capacity thresholds as prescribed under Department of Revenue’s
    Notification No. 21/2002-Customs. Therefore, it is an incorrect and
    misplaced contention subsequently raised by the Appellants before
    this Court that the proviso to Para 8.2 is applicable to all kinds of
    projects therein and that Para 8.4.4(iv) is a special provision and
    deals specifically with Para 8.2(g).
71. Moreover, by virtue of amendments dated 14.01.2010 and 08.02.2010
    to the FTP, a limited relaxation was carved out exclusively for the
    MPPs wherein the mandate of ICB had been exempted if the required
    quantum of power had been tied up through adopting of Tariff-Based
    Competitive Bidding, or the project was awarded in the said manner.
    Clearly, as on the concerned cut-off date, neither of the Appellants
    would have been able to plead that Tariff-Based Competitive
[2025] 8 S.C.R.                                                      1349

                        Nabha Power Limited v.
          Punjab State Power Corporation Limited and Others

     Bidding was a permissible alternative under the FTP for either of
     the aforesaid stages. It is submitted on behalf of the Appellants that
     ICB was conducted at the Independent Power Producer stage, in
     tune with the mandate of Section 63 of the EA 2003 for selection of
     the power developer, therefore, having sufficed the condition under
     Para 8.4.4(iv) it was not required to conduct ICB at the Engineering
     Procurement Contract stage.
72. A perusal thereof, clarifies that the essence of deemed export
    benefits lay in the supply of goods to power projects, not in power
    procurement arrangements. A collective and comprehensive reading
    of Para 8.2, Para 8.4.4(iv) and Para 8.6 of the FTP establishes that
    the Independent Power Producer stage is in reference to the main
    contractor vis-à-vis supply of goods to the concerned project, while
    the Engineering Procurement Contract stage concerns the supply by
    a sub-contractor to the Engineering Procurement Contract contractor.
    Undoubtedly, and admittedly, mandate of ICB may be claimed, on
    behalf of the Appellants, to have been followed during their bidding
    process leading to the PPAs, but no evidence has been produced
    on record by the Appellants to determine whether such a mandate
    i.e. ICB process was adopted by them for procurement of goods
    concerned and/or to be supplied as per Para 8.4.4(iv) of the FTP,
    which mandates ICB either at the stage of Independent Power
    Producer or Engineering Procurement Contract when in relation
    to a “supply of goods” as per Para 8.2(g) of the FTP. Reliance on
    Tariff-Based Competitive Bidding by the Appellants for selection of
    the power project developer cannot be equated with the mandate
    of the ICB for supply of goods and is, therefore, a misnomer and a
    misplaced plea raised on their part.
73. Considering the above contentions as raised before us albeit for
    the first time, the Appellants, have clearly failed to establish the
    procurement of “supply of goods” as per the mandate of ICB
    either at the stage of Independent Power Producer or Engineering
    Procurement Contract, owing to the fact that such procurement of
    the components was done through directly entering into contract(s)
    with their subsidiaries or joint venture or related companies, we
    do not find any reason to further deal with the contentions raised
    by the Appellants vis-à-vis other prerequisites as all the essential
    pre-conditions unless ticked would not render them eligible for the
    benefit claimed.
1350                                                     [2025] 8 S.C.R.

                        Supreme Court Reports


74. The instant issue is answered against the Appellants to the effect
    that they were not entitled to the deemed export benefits under
    Para 8.3 of the FTP.
75. Having answered in the negative as aforesaid with regard to the
    entitlement of the Appellants for the deemed export benefits under the
    FTP, we ought not delve into the plea as to the alleged withdrawal of
    the said benefits through notifications of the DGFT dated 28.12.2011
    and 21.03.2012 collectively and whether that would amount to a
    “Change in Law” as per Article 13 of the PPA.
76. However, while placing reliance on our discussion above of the
    issue(s), the aforesaid notifications issued through DGFT were
    mere clarificatory in nature. As a matter of fact, no interpretation
    of law was undertaken prior to the cut-off date to the effect that a
    developer shall be able to import goods to be assembled into a
    power plant and also claim the deemed export benefits on those.
    Therefore, APTEL, while dealing with the said issue in detail, and
    correctly so, concluded that the aforesaid contended circulars to be
    merely clarificatory and not as something which has either changed
    or introduced something new, being allegedly oppressive towards
    the Appellants.
77. Hypothetically, even assuming the case of the Appellants to the said
    effect to be good in law and that notification(s) would indeed amount
    to a “Change in Law”, it is merely an academic exercise without any
    impact on the legal position of the Appellants. They were, and still
    are not, entitled to any deemed export benefits under the FTP for
    their inability to fulfil the concerned prerequisites as discussed by
    us above.
78. Now, we shall proceed to consider the third issue in the instant Civil
    Appeals, which is subject to positive contemplation of the earlier
    issues as dealt by us and if so, whether Appellants are entitled to
    restitutionary relief in the form of compensation.
79. It is clear from the detailed analysis of the first and second issues
    raised in the instant Civil Appeals that the Appellants have not been
    able to establish those in their favour and accordingly, there cannot
    arise any question for compensation to the Appellants by the PSPCL
    as a means of restitutionary relief.
[2025] 8 S.C.R.                                                      1351

                           Nabha Power Limited v.
             Punjab State Power Corporation Limited and Others

80. The Appellants have failed to impress this Court with their submissions
    in these Civil Appeals and we find no ground to interfere with the
    Impugned Judgment and order dated 04.07.2017 passed by the
    Appellate Tribunal for Electricity, New Delhi.
81. These Appeals are dismissed being devoid of merit.
82. There shall be no order as to costs.
83. Pending application(s), if any, also stand disposed of.

     Result of the case: Appeals dismissed.




     †
         Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Deemed export benefits"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

NABHA POWER LIMITED versus PUNJAB STATE POWER CORPORATION LIMITED AND OTHERS — 2025 INSC 1002 - Legal Desk AI