Created byFuzzy Cloud

Supreme Court of India

OPG POWER GENERATION PRIVATE LIMITEDversusENEXIO POWER COOLING SOLUTIONS INDIA PRIVATE LIMITED & ANR.

Citation
2024 INSC 711
Decided
20 September 2024
Disposal
Dismissed

Holding

The arbitral award is not in conflict with public policy nor vitiated by patent illegality; the holding company is bound, the claim is within limitation under Article 55, the specific counter‑claims are time‑barred, and the award is not perverse.

Summary

OPG Power Generation (the appellant) and its holding company Gita Power were sued by Enexio Power Cooling Solutions for unpaid amounts under supply and erection orders for an air‑cooled condenser unit. The arbitral tribunal held that Gita Power, as the holding company, was bound by the arbitration agreement and jointly and severally liable with OPG, and that Enexio's claim for the outstanding principal amount was within the limitation period under Article 55 of the Limitation Act, 1963, while the counter‑claims for repair/replacement of gear boxes and fan modules were time‑barred. The tribunal’s reasoning was found to be intelligible and not perverse, and the award was not in conflict with the public policy of India nor vitiated by patent illegality. Accordingly, the Supreme Court dismissed the appeals and restored the arbitral award.

Issues considered

  • Whether the holding company Gita Power can be subjected to arbitration and be held jointly and severally liable with OPG.
  • Whether Enexio's claim for the outstanding principal amount is barred by limitation.
  • Whether the counter‑claim for cost of repair/replacement of gear boxes and fan modules is barred by limitation despite the main claim being within limitation.
  • Whether the award for payment of the outstanding principal amount with interest is perverse for not adjusting debit notes.
  • Whether the arbitral tribunal adopted a different yardstick for the claim and the counter‑claim, rendering the award flawed.
  • Whether the award is in conflict with the public policy of India or vitiated by patent illegality.

Legislation cited

Subjects

Arbitral awardPublic policy of IndiaPatent illegalityHolding companyJointly and severally liableLimitationCounter claimContractual relationshipOutstanding principal amount with interestPerverse awardDifferent yardstickComposite tenderDeclaratory reliefLiquidated damagesCustoms dutyLimitation Act, 1963AcknowledgementGroup of companies doctrinePerformance guarantee testBreach of contractExtension of limitation

Judgment

                  [2024] 9 S.C.R. 490 : 2024 INSC 711

             OPG Power Generation Private Limited
                               v.
           Enexio Power Cooling Solutions India Private
                         Limited & Anr.
                    (Civil Appeal Nos. 3981-3982 of 2024)
                               20 September 2024
                [Dr. Dhananjaya Y. Chandrachud, CJI,
                J.B. Pardiwala and Manoj Misra,* JJ.]

                             Issue for Consideration
       Issue arose as to whether the arbitral award is in conflict with the
       public policy of India, or/and is vitiated by patent illegality appearing
       on the face of the award; whether the holding company could
       have been subjected to arbitration and made jointly and severally
       liable along with the project beneficiary-appellant for the award;
       whether respondent’s claim for the outstanding principal amount
       barred by limitation; whether the counter claim, in respect of cost
       of repair/replacement of gear boxes and fan modules, could be
       treated as barred by time when the other side’s claim, arising out of
       same contractual relationship, was found within limitation; whether
       arbitral award for payment of the outstanding principal amount with
       interest is perverse; whether the reasoning of the arbitral tribunal
       is flawed and vitiated by adopting different yardstick for adjudging
       the counterclaim than what was adopted for adjudging the claim;
       if so, whether it vitiated the award and rendered it vulnerable to
       a challenge u/s. 34 of the Arbitration and Conciliation Act, 1996.

                                    Headnotes†
       Arbitration and Conciliation Act, 1996 – s. 34(2)(b)(ii) – Arbitral
       Award – Challenge to – Arbitral award, if in conflict with
       the public policy of India, or/and vitiated by patent illegality
       appearing on the face of the award – Appellant company floated
       composite tender for design, manufacture and commissioning
       of an air-cooled condenser unit, however, supply and
       erection orders issued by its holding company – Appellant
       later confirmed those orders – Respondent had bid for the
       project – Dispute between parties as regards declaration qua
       invalidity of debit notes, outstanding principal amount and
* Author
[2024] 9 S.C.R.                                                               491

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     interest – Respondent invoked arbitration – Arbitral award
     passed an award in favour of the respondent, holding that
     the holding company and appellant jointly and severally
     liable; that declaratory relief sought by respondent qua debit
     notes-towards liquidated damages and customs duty beyond
     the period of limitation, however, claim for unpaid dues payable
     under the contract within the period of limitation – Single
     Judge of the High Court set aside the award, however the
     Division Bench restored the same – Justification:
     Held: Division Bench of the High Court justified in setting aside
     the judgment and order of the Single Judge and restoring the
     arbitral award – No palpable error in the arbitral award as to be
     termed ‘patently illegal’/‘perverse’, or in conflict with public policy
     of India – Though the ACC Unit /project was of the appellant,
     the holding company of the appellant actively participated in the
     formation of the contract for the project – They not only acted as
     a single economic entity but as agents of each other – Hence,
     the arbitral tribunal justified in holding that holding company was
     bound by the arbitration agreement and jointly and severally liable
     along with appellant to pay the awarded amount – Claim of the
     respondent was an indivisible claim for compensation in lieu of
     goods supplied, and work done, based on breach of the contract,
     thus limitation for the claim governed by Art. 55, and not by Arts.
     14, 18 and 113, of the Schedule to the 1963 Act – Claimant’s claim
     for the outstanding principal amount matured on 19 March 2016,
     thus, limitation started to run from that date – However, even if
     limitation is counted from 21 September 2015, deemed date of
     completion of the supply/work (as found by the tribunal) it would
     have no material bearing on the award – Limitation for the claim
     as well as counterclaim, other than those relating to cost of repair/
     replacement of gear boxes and fan modules, stood extended,
     u/s. 18 of the 1963 Act, on the basis of acknowledgement made
     in the minutes of meeting, and, thus, those were within limitation
     and rightly considered on merit – Counterclaims qua cost of
     repair /replacement of gear boxes and fan modules rightly held
     barred by time as in respect thereof there was no recital in the
     minutes of meeting – Rejection of prayer to declare debit notes
     invalid, on ground of limitation, had no adverse impact on the
     claimant’s claim for compensation, which was well within the
     extended period of limitation – Also, the arbitral tribunal did not
492                                                                [2024] 9 S.C.R.

                         Digital Supreme Court Reports


       adopt different yardstick, the reasoning of the arbitral tribunal not
       flawed or perverse – Limitation Act, 1963 – Arts. 14, 18 and 55
       of the Schedule. [Paras 150, 151]
       Arbitration and Conciliation Act, 1996 – Holding company of
       appellant, if could be subjected to arbitral proceedings and
       made jointly and severally liable along with appellant for the
       dues of claimant:
       Held: Holding company bound by the arbitration agreement and
       thus, jointly and severally liable along with the appellant for the
       dues payable to the claimant – Arbitral tribunal found that the
       holding company of the appellant had issued the Purchase Orders
       and had actively participated in the formation of the contract
       even though the ACC unit was of the appellant; initial 10% of the
       purchase price was provided by the holding company; subsequent
       Purchase Orders issued by the appellant were on similar terms
       and were issued by way of affirmation to obviate technical |
       issues – Said circumstances had a material bearing for invocation
       of Group of Companies doctrine to bind holding company with the
       arbitration agreement and fasten it with liability, jointly and severally
       with the appellant, in respect of the Purchase Orders relating to
       ACC Unit – Thus, no reason to interfere with the findings of the
       arbitral tribunal more so when it is based on a possible view of
       the matter. [Para 81]
       Limitation Act, 1963 – Art. 14, 18, 55 of the Schedule – Claim in
       respect of declaration qua invalidity of debit notes; outstanding
       principal amount; and interest – Applicability of Art. 14, 18,
       55 to the claim – Limitation for the claim:
       Held: On facts, there is an indivisible claim in respect of the
       outstanding principal amount for the goods supplied and the work
       done – Moreover, the payments under the supply purchase order
       were to be on pro rata basis, and full payment for the supplies
       was dependent on supporting documents, including certificates,
       to be provided by the purchaser, which were not provided – Thus,
       when full payments under the supply/erection purchase orders were
       dependent on certificates relating to completion/commissioning/
       guaranteed performance etc., the claimant waited till successful
       completion/commissioning/guaranteed performance of the project
       to file a composite claim for the balance amount payable under
       both the purchase orders – Thus, Art. 14 not applicable to the
[2024] 9 S.C.R.                                                              493

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     claim as framed – As regards applicability of Art. 18, since the
     payments under the contract were to be made on pro rata basis,
     dependent on work done and certificates issued, which were not
     issued, hence, the claimant was entitled to make a composite
     claim for the goods supplied and the work done after the project
     was successfully complete-when the Unit was commissioned
     followed by guaranteed performance because it is only then, when
     the outstanding amount, as per the Bills/Invoices raised, became
     due and payable to the claimant in terms of the contract, thus,
     Art. 18 would also not apply – Art. 55 was applicable since the
     claim was for compensation which includes a specified amount
     payable under a contract, in respect of the goods supplied and
     the work done under a contract – Claim was based on a breach
     of the contractual obligation as, according to the findings returned
     by the tribunal, the appellants failed to fulfil their obligations of
     making payment of the outstanding principal amount payable
     under the contract despite raising of bills/invoices by the claimant –
     Thus, the claim for the outstanding principal amount not barred
     by limitation. [Paras 105-107]
     Limitation Act, 1963 – Starting point of limitation for the claim –
     Date from which the limitation period is to be counted:
     Held: Under Art. 55, the limitation period begins to run when the
     contract is broken or where there are successive breaches, when
     the breach in respect of which the suit is instituted occurs, or
     where the breach is continuing, when it ceases – Claim is for the
     outstanding principal amount due to the claimant on discharge of
     his obligations under the contract – Thus, the cause of action for
     the claim is appellants’ failure to make payment of the outstanding
     principal amount to the claimant despite discharge of contractual
     obligations by it – Nothing brought to the notice that there was
     any fixed date, or period of credit, for payment of the balance
     amount – Starting point of limitation should be the date when the
     claimant had fulfilled all its obligations under the contract and
     was entitled for release of the outstanding amount payable under
     the contract – Tribunal concluded that commissioning took place
     in the month of May 2015; technical issues were resolved by 21
     September 2015; and performance guarantee period expired
     on 19 March 2016 – Final payment of the principal outstanding
     amount was dependent on meeting the requirement of performance
     guarantee, the cause of action for the claim, as made, matured on
494                                                             [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       expiry of that stipulated period of 180 days within which, despite
       request, the appellants failed to undertake the performance
       guarantee test – Thus, even though there might be several bills/
       invoices raised/issued by the claimant during execution of the
       contract, the claim of the claimant for the outstanding principal
       amount matured on expiry of 180 days from the date of the notice
       given by the claimant to the appellants to undertake the performance
       guarantee test – Thus, limitation for the claim started to run from
       19 March 2016. [Paras 109-113]
       Limitation Act, 1963 – s. 18 – Limitation extended by
       acknowledgement – By virtue of acknowledgment, if any, the
       claimant, if entitled to extension of the period of limitation:
       Held: s. 18 deals with the effect of acknowledgement in writing –
       Sub-section (1) thereof provides that where, before the expiration
       of the prescribed period for a suit or application in respect of any
       right, an acknowledgement of liability in respect of such right has
       been made in writing signed by the party against whom such right
       is claimed, a fresh period of limitation to be computed from the
       time when the acknowledgment was so signed – Explanation to
       s. 18 provides that an acknowledgment may be sufficient though
       it omits to specify the exact nature of the right or avers that the
       time for payment has not yet come or is accompanied by a refusal
       to pay, or is coupled with a claim to set off, or is addressed to a
       person other than a person entitled to the right – On facts, the
       limitation period started to run from 19 March 2016 – Within three
       years therefrom, in the minutes of meeting dated 19 April 2018
       there was a clear acknowledgement that the amount claimed by the
       claimant is the balance amount payable, though subject to debit,
       by way of set off, against various claims made by the appellant
       upon the claimant – Such an acknowledgment was sufficient to
       extend the limitation period as it admitted the existing liability of
       the appellants qua the balance amount payable to the claimant
       under the contract – Benefit of such an acknowledgement would
       not be lost merely because a set off is claimed – Thus, minutes
       of meeting dated 19 April 2018, though claims a set off, is a valid
       acknowledgement of the existing liability within the ambit of s. 18
       and it extends the period of limitation for a period of 3 years from
       the date it was made – Thus, the claim made on 2 May 2019,
       within the period of limitation. [Paras 116, 119]
[2024] 9 S.C.R.                                                               495

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     Arbitration and Conciliation Act, 1996 – s. 23 (2A) – Counter
     claim – Nature of – Counterclaim in respect of cost of repair/
     replacement of gear box and fan modules, if barred by time:
     Held: Counterclaim is a claim made by a defendant in a suit
     against the plaintiff – It is a claim, independent of and separable
     from the plaintiff’s claim, which can be enforced by a cross
     action – Counterclaim preferred by the defendant in a suit is a
     cross suit and even if the suit is dismissed, counterclaim shall
     remain alive for adjudication – Purpose of the scheme relating to
     counterclaim is to avoid multiplicity of proceedings – s. 23 (2A) gives
     respondent to a claim a right to submit a counterclaim or plead a
     set off, which shall be adjudicated upon by the arbitral tribunal, if
     such counterclaim or set off falls within the scope of the arbitration
     agreement – Counterclaim is like a cross suit, or a separate suit,
     and the limitation of a counterclaim is to be counted from the date
     of accrual of the cause of action which it seeks to espouse – As a
     logical corollary thereof, it is quite possible that even though a suit
     or a claim is within the period of limitation, the counterclaim may
     well be barred by limitation, if the cause of action espoused therein
     accrued beyond the prescribed period of limitation – On facts, the
     counterclaim in respect of cost of repair/replacement of gear box
     and fan modules, barred by time – Tribunal took 21 September 2015
     as the start point of limitation for the counterclaim on the premise
     that it would be the date when the Takeover Certificate is deemed
     to have been issued, the supplier had fulfilled its obligations – On
     basis thereof, the tribunal found counterclaims as regards cost of
     repair/replacement of gear boxes and of fan modules barred by
     time as the counterclaim was filed on 15 July 2019 i.e., more than
     three years later, and there existed no acknowledgement in respect
     thereof – However, for other issue, 19 March 2016 is found as the
     start point of limitation for the claim because that is the date when
     180 days period of guaranteed performance, part of supplier’s
     liability, expired – Whether the limitation period is counted from
     21 September 2015 or 19 March 2016, the counterclaim filed on
     15 July 2019 was beyond the prescribed period of three years
     inasmuch as its cause of action could not have arisen after 19
     March 2016. [Paras 120, 122, 124, 125, 128, 129]
     Limitation Act, 1963 – s. 18 – Effect of acknowledgment in
     writing – Extension of the period of limitation – Minutes of
     meeting, if extended the limitation of counterclaims:
496                                                               [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       Held: To extend the period of limitation with the aid of s. 18, the
       acknowledgment must involve an admission of a subsisting jural
       relationship between the parties and a conscious affirmation of
       an intention of continuing such relationship regarding an existing
       liability – Such intention can be gathered from the nature of the
       admission – Admission need not be express, or regarding a precise
       amount, but must be made in circumstances and in words from
       which the court can reasonably infer that the person making the
       admission intended to refer to a subsisting liability as on the date of
       the statement – However, where an acknowledgement is in respect
       of a specified sum of money or a specific right only, and not in
       general terms, it would extend the period of limitation only in respect
       thereof, and not of other claims which, though may have arisen
       out of same jural relationship, are not specified therein – On facts,
       minutes of meeting did not extend the limitation of counterclaims –
       Minutes of meeting made no reference to the items referable to
       counterclaims-cost of repair/replacement of Gear Box and Fan
       Modules – Also no acknowledgment in general terms in regard
       to liabilities subsisting under the contract – Said minutes could
       not be treated as acknowledgment for the purpose of extending
       limitation of the counterclaims not specified therein – Thus, when
       the counterclaims were otherwise barred by limitation on the date
       of filing of counterclaim, the tribunal justified in rejecting them as
       barred by limitation. [Paras 137, 138]
       Limitation Act, 1963 – Rejection of claimant’s prayer to declare
       debit notes invalid, if had adversely affected the claim for the
       outstanding principal amount in respect of the goods supplied/
       work done under the contract :
       Held: Rejection of prayer to declare debit notes invalid did not
       affect respondent’s claim for the outstanding principal amount –
       Relief for declaratory relief was rightly held barred by limitation
       by the tribunal – Rejection of declaratory relief did not impact
       relief for compensation, since relief for compensation was not a
       consequential relief, dependent on debit notes being declared
       invalid because issuance of debit notes was a unilateral act of
       the employer which on its own did not extinguish the right of the
       contractor – No doubt, where the relief sought is consequential to
       the declaration, and declaratory relief is found barred by time, the
       prayer for consequential relief will also fail – But where declaration
       is just an optional relief-on which the main relief is not dependent,
[2024] 9 S.C.R.                                                                 497

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     rejection of it as barred by limitation would not extinguish the
     claim in respect of which substantive relief is sought – In such
     circumstances, it was open for the contractor to sue for its dues
     without seeking a declaration qua the debit notes – Thus, rejection
     of the declaratory relief as barred by limitation, did not have a
     material bearing on respondent’s claim against the appellants’ for the
     outstanding principal amount payable under the contract – Amount,
     as shown debited in the debit notes, was not to be automatically
     adjusted against the principal outstanding amount payable to
     respondent – While deciding the claim of respondent, the tribunal
     was well within its remit to adjudicate upon the issue whether such
     amount should be adjusted or not against the outstanding principal
     amount payable to respondent – No perversity in the award on
     this count. [Paras 139, 141]
     Arbitration and Conciliation Act, 1996 – ss. 34, 37 – Arbitral
     award – Setting aside of – Plea that the arbitral tribunal adopted
     different yardstick for adjudicating the claim than what was
     adopted for the counterclaim; and the reasoning is completely
     flawed and perverse :
     Held: Distinction would have to be drawn between an arbitral award
     where reasons are either lacking/unintelligible or perverse and an
     arbitral award where reasons are there but appear inadequate
     or insufficient – In a case where reasons appear insufficient or
     inadequate, if, on a careful reading of the entire award, coupled
     with documents recited/relied therein, the underlying reason, factual
     or legal, that forms the basis of the award, is discernible/intelligible,
     and the same exhibits no perversity, the court need not set aside
     the award while exercising powers u/s. 34 or s. 37, rather it may
     explain the existence of that underlying reason while dealing with
     a challenge laid to the award – In doing so, the court does not
     supplant the reasons of the arbitral tribunal but only explains it for
     a better and clearer understanding of the award – On facts, the
     arbitral tribunal did not adopt different yardstick for adjudicating
     the claim than what was adopted for the counterclaim and the
     reasoning of the arbitral tribunal is not flawed or perverse – Though
     reasons recorded in the award at first blush appear insufficient,
     or a bit confusing, but, when those reasons are examined in the
     context of the documents placed and the arguments advanced,
     the underlying reasons, which form basis of the conclusion, are
     not only intelligible but sound – Mistake, if any, committed by
498                                                               [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       the arbitral tribunal in using the words ‘ongoing negotiations’ in
       place of acknowledgement is trivial does not go to the root of the
       matter as to have a material bearing on the conclusion – Thus,
       for this mistake alone, the award is not liable to be set aside –
       Furthermore, it cannot be said that the arbitral tribunal was obliged
       to accept the admission contained in the minutes of meeting qua
       liquidated damages and customs duties, because it relied on it for
       extending the limitation – Tribunal was well within its jurisdiction
       in drawing a conclusion that the claimant was not liable in respect
       of those items which formed part of the counterclaim, based on
       consideration of the entire evidence, at variance with the recitals
       in the acknowledgement – Such conclusion is a plausible view
       and cannot be termed perverse – Single Judge of the High Court
       erred in law while interfering with the arbitral award – Furthermore,
       as regards the plea that the appellate court-Division Bench of the
       High Court exceeded its jurisdiction while providing its own reasons
       to support the conclusion in the award, the appellate court took
       pains, and rightly so, to understand and explain the underlying
       reason on which the claim of the respondent was found within
       limitation – Appellate court was well within its jurisdiction to explain
       the underlying legal principle which the arbitral tribunal had applied;
       and in doing so, it did not supplant the reasons provided in the
       award – Impugned order of the Division Bench does not suffer
       from any legal infirmity. [Paras 144-149]
       Arbitration and Conciliation Act, 1996 – s. 34(2)(b)(ii) – Arbitral
       Award – Challenge to – Award may be set aside when in conflict
       with the public policy of India – Scope of public policy:
       Held: For an award to be against public policy of India a mere
       infraction of the municipal laws of India not enough – There must
       be, inter alia, infraction of fundamental policy of Indian law including
       a law meant to serve public interest or public good. [Para 36]
       Arbitration and Conciliation Act, 1996 – ss. 34 and 48 (as
       amended by the Amendment, 2015) – Amendment, 2015
       adding Explanations to s. 34(2)(b)(ii) and s. 48(2)(b), in place
       of the earlier Explanation, wherein Explanation 1 clause (ii) to
       s. 34(2)(b)(ii) and s. 48(2)(b), specifies that an arbitral award
       is in conflict with the public policy of India, only if, it is in
       contravention with the fundamental policy of Indian law –
       Expression “in contravention with the fundamental policy of
       Indian law” – Meaning of:
[2024] 9 S.C.R.                                                              499

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     Held: After the ‘2015 amendments’ in s. 34 (2)(b)(ii) and s. 48(2)
     (b), the phrase “in conflict with the public policy of India” must
     be accorded a restricted meaning in terms of Explanation –
     Expression “in contravention with the fundamental policy of Indian
     law” by use of the word ‘fundamental’ before the phrase ‘policy
     of Indian law’ makes the expression narrower in its application
     than the phrase “in contravention with the policy of Indian law”,
     which means mere contravention of law is not enough to make
     an award vulnerable – To bring the contravention within the fold
     of fundamental policy of Indian law, the award must contravene
     all or any of such fundamental principles that provide a basis for
     administration of justice and enforcement of law in this country –
     Violation of the principles of natural justice; disregarding orders of
     superior courts in India or the binding effect of the judgment of a
     superior court; and violating law of India linked to public good or
     public interest, are considered contravention of the fundamental
     policy of Indian law – However, while assessing whether there has
     been a contravention of the fundamental policy of Indian law, the
     extent of judicial scrutiny must not exceed the limit as set out in
     Explanation 2 to s. 34(2)(b)(ii). [Para 52]
     Arbitration and Conciliation Act, 1996 – ss. 34 and 48 (as
     amended by the Amendment, 2015) – Explanation 1 clause (iii)
     to s. 34(2)(b)(ii) and s. 48(2)(b) inserted by 2015 Amendment,
     that an award is in conflict with the public policy of India, inter
     alia, if it conflicts with the ‘most basic notions of morality or
     justice’ – Most basic notions of ‘morality’ – Explanation:
     Held: It would cover such agreements as are not illegal but would
     not be enforced given the prevailing mores of the day – Interference
     on this ground would be only if something shocks the court’s
     conscience. [Para 59]
     Arbitration and Conciliation Act, 1996 – ss. 34 and 48 (as
     amended by the Amendment, 2015) – Explanation 1 clause (iii)
     to s. 34(2)(b)(ii) and s. 48(2)(b) inserted by 2015 Amendment,
     that an award is in conflict with the public policy of India, inter
     alia, if it conflicts with the ‘most basic notions of morality or
     justice’ – Most basic notions of ‘justice’ – Explanation:
     Held: Term ‘legal justice’ is not used in Explanation 1, thus, simple
     conformity or non-conformity with the law is not the test to determine
     whether an award is in conflict with the public policy of India in
     terms of Explanation 1 – Test is that it must conflict with the most
500                                                               [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       basic notions of justice – For lack of any objective criteria, it is
       difficult to enumerate the ‘most basic notions of justice’ – More
       so, justice to one may be injustice to another – As regards justice
       being done, it is about rendering, in accord with law, what is right
       and equitable to one who has suffered a wrong – Dispensation of
       justice in its quality may vary, dependent on person who dispenses
       it – Thus, the placement of words “most basic notions” before “of
       justice” in Explanation 1 has its significance – Object of inserting
       Explanations 1 and 2 in place of earlier explanation to s. 34(2)(b)(ii)
       was to limit the scope of interference with an arbitral award, thus
       the amendment consciously qualified the term ‘justice’ with ‘most
       basic notions’ of it – Giving a broad dimension to this category
       would be deviating from the legislative intent – Thus, considering
       that the concept of justice is open-textured, and notions of justice
       could evolve with changing needs of the society, it would not be
       prudent to cull out “the most basic notions of justice” – They ought
       to be such elementary principles of justice that their violation could
       be figured out by a prudent member of the public who may, or may
       not, be judicially trained, which means, that their violation would
       shock the conscience of a legally trained mind – This ground would
       be available to set aside an award, if the award conflicts with such
       elementary/fundamental principles of justice that it shocks the
       conscience of the Court. [Paras 55, 58]
       Arbitration and Conciliation Act, 1996 – s. 34 (2-A) (as inserted
       by the Amendment, 2015) –Sub-section (2-A) of s. 34 providing
       that the Court may also set aside an arbitral award if it is vitiated
       by patent illegality appearing on the face of the award – Patent
       illegality appearing on the face of the award – Meaning of:
       Held: Proviso to sub-section (2-A) states that an award shall not
       be set aside merely on the ground of an erroneous application of
       the law or by reappreciation of evidence – Thus, an award could
       be set aside if it is patently illegal – However, illegality must go
       to the root of the matter and if the illegality is of trivial nature, it
       cannot be held that award is against public policy. [Para 60]
       Arbitration and Conciliation Act, 1996 – s. 34 –Arbitral Award –
       Scope of interference – Perversity as a ground for setting
       aside an arbitral award:
       Held: Interference with an arbitral award is only on limited grounds
       as set out in s. 34 – Possible view by the arbitrator on facts is to
       be respected as the arbitrator is the ultimate master of the quantity
[2024] 9 S.C.R.                                                              501

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     and quality of evidence to be relied upon – Arbitral decision must
     not be perverse or so irrational that no reasonable person would
     have arrived at the same – If an award is perverse, it would be
     against the public policy of India – It is only when an arbitral award
     could be categorized as perverse, that on an error of fact an arbitral
     award may be set aside – Mere erroneous application of the law
     or wrong appreciation of evidence by itself is not a ground to set
     aside an award as is clear from the provisions of sub-section (2-A)
     of s. 34. [Paras 63, 68]
     Arbitration and Conciliation Act, 1996 – s. 31 – Forms and
     contents of arbitral award – Scope of interference – Ground
     of insufficient, or improper/erroneous or lack of reasons:
     Held: Arbitral award on the ground of improper or inadequate
     reasons, or lack of reasons, can be placed in three categories,
     (1) where no reasons are recorded, or the reasons recorded are
     unintelligible; (2) where reasons are improper, that is, they reveal
     a flaw in the decision-making process; and (3) where reasons
     appear inadequate – Awards falling in category (1) are vulnerable
     as they would be in conflict with the provisions of s. 31(3), thus,
     liable to be set aside u/s. 34, unless the parties have agreed that
     no reasons are to be given, or the award is an arbitral award on
     agreed terms u/s. 30 – Awards falling in category (2) are amenable
     to a challenge on ground of impropriety or perversity, strictly in
     accordance with the grounds set out in s. 34 – In a challenge to
     award falling in category (3), before taking a decision the Court
     must take into consideration the nature of the issues arising
     between the parties in the arbitral proceedings and the degree of
     reasoning required to address them – If reasons are intelligible
     and adequate on a fair-reading of the award and, in appropriate
     cases, implicit in the documents referred to therein, the award is
     not to be set aside for inadequacy of reasons – However, if gaps
     are such that they render the reasoning in support of the award
     unintelligible, or lacking, the Court exercising power u/s. 34 may
     set aside the award. [Paras 71.3, 71.6]
     Arbitration and Conciliation Act, 1996 – Arbitral award –
     Scope of interference with the interpretation/construction of
     a contract accorded in the award :
     Held: Arbitral tribunal must decide in accordance with the terms of
     the contract – In a case where an arbitral tribunal passes an award
     against the terms of the contract, the award would be patently
502                                                               [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       illegal – However, an arbitral tribunal has jurisdiction to interpret
       a contract having regard to terms and conditions of the contract,
       conduct of the parties including correspondences exchanged,
       circumstances of the case and pleadings of the parties – If the
       conclusion of the arbitrator is based on a possible view of the
       matter, the Court should not interfere – But where, on a full reading
       of the contract, the view of the arbitral tribunal on the terms of a
       contract is not a possible view, the award would be considered
       perverse and as such amenable to interference. [Para 72]
       Arbitration – Arbitration agreement/contract – Unexpressed
       term, if can be read into a contract as an implied condition:
       Held : Ordinarily, terms of the contract are to be understood in the
       way the parties wanted and intended them to be – In agreements
       of arbitration, where party autonomy is the grund norm, how the
       parties worked out the agreement, is one of the indicators to
       decipher the intention, apart from the plain or grammatical meaning
       of the expressions used – However, reading an unexpressed
       term in an agreement would be justified on the basis that such a
       term was always and obviously intended by the parties thereto –
       Unexpressed term can be implied if, and only if, the court finds
       that the parties must have intended that term to form part of their
       contract – It is not enough for the court to find that such a term
       would have been adopted by the parties as reasonable men if
       it had been suggested to them – Rather, it must have been a
       term that went without saying, a term necessary to give business
       efficacy to the contract, a term which, although tacit, forms part of
       the contract – But before an implied condition, not expressly found
       in the contract, is read into a contract, by invoking the business
       efficacy doctrine, it must be reasonable and equitable; it must be
       necessary to give business efficacy to the contract, that is, a term
       will not be implied if the contract is effective without it; it must be
       obvious, it must be capable of clear expression; and it must not
       contradict any terms of the contract. [Paras 73, 75]
       Limitation Act, 1963 – Arts. 14, 18 and 55 of the Schedule –
       Applicability to the claim, when:
       Held: Art. 14 applies where the suit/ claim is for the price of goods
       sold and delivered; and no fixed period of credit is agreed upon
       whereas Art.18 applies where the suit/claim is for the price of work
       done by the plaintiff/claimant for the defendant at his request; and
       no time has been fixed for payment – Thus, where a suit is for
[2024] 9 S.C.R.                                                               503

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     goods supplied and work done by the plaintiff (a contractor) and the
     price of materials and the price of work is separately mentioned,
     and the time for payment is not fixed by the contract, Art. 14 will
     apply to the former claim, and Art. 18 to the latter – But where a
     claim is made for a specific sum of money as one indivisible claim
     on the contract, without mentioning any specific sum as being the
     price of goods or price of the work done, neither Art. 14 nor Art. 18
     would apply, but only Art. 55, which provides for all actions based
     on a contract, not otherwise provided for, would apply – Art. 55
     is a residuary Article in respect of all actions based on a contract
     not otherwise specially provided for – For the applicability of Art.
     55, the suit should be based on a contract, there must be breach
     of the contract, the suit should be for compensation and the suit
     should not be covered by any other Article specially providing for
     it – Phrase ‘compensation for breach of contract’, as occurring in
     Art. 55 would comprehend also a claim for money due under a
     contract – Thus, even a suit for recovery of a specified amount,
     based on a contract, is a suit for compensation, and if the suit is
     a consequence of defendant breaching the contract or not fulfilling
     its obligation(s) thereunder, the limitation for institution of such a
     suit would be covered by Art. 55, provided the suit is not covered
     by any other Art. specially providing for it. [Paras 91, 92, 95, 98]
     Words and phrases – Expression ‘public policy’ – Meaning
     and scope of. [Paras 30-40]
     Words and phrases – Term ‘justice’ – Meaning of:
     Held: Justice is the virtue by which the society/court/tribunal gives
     a man his due, opposed to injury or wrong – Justice is an act of
     rendering what is right and equitable towards one who has suffered
     a wrong – Thus, while tempering justice with mercy, the court must
     be very conscious, that it has to do justice in exact conformity
     with some obligatory law, for the reason that human actions are
     found to be just or unjust on the basis of whether the same are
     in conformity with, or in opposition to, the law – Thus, in ‘judicial
     sense’, justice is nothing more nor less than exact conformity to
     some obligatory law; and all human actions are either just or unjust
     as they are in conformity with, or in opposition to, the law. [Para 54]

                               Case Law Cited
     Dyna Technologies Pvt. Ltd. v. Crompton Greaves Lt. [2019] 15
     SCR 295 : (2019) 20 SCC 1 – relied on.
504                                                          [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       Bharat Sanchar Nigam Limited v. Nortel Networks Pvt. Ltd. [2021]
       2 SCR 644 : (2021) 5 SCC 738; B & T AG v. Ministry of Defence
       [2023] 7 SCR 599 : (2024) 5 SCC 358; Ssangyong Engg. &
       Construction Co. Ltd. v. NHAI [2019] 7 SCR 522 : (2019) 15 SCC
       131; Associate Builders v. Delhi Development Authority [2014]
       13 SCR 895 : (2015) 3 SCC 49; UHL Power Company limited
       v. State of Himachal Pradesh [2022] 1 SCR 1 : (2022) 4 SCC
       116; Heidelbergh Cement India Ltd. v. The Indure Pvt. Ltd. 2022/
       DHC/003952; MMTC Ltd. v. Vedanta Ltd. [2019] 3 SCR 1023 :
       (2019) 4 SCC 163; Haryana Tourism Ltd. v. Kandhari Beverages
       Ltd. [2022] 2 SCR 316 : (2022) 3 SCC 237; Geo Miller & Co. (P)
       Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd [2019] 11 SCR 1108 :
       (2020) 14 SCC 643; Steel Authority of India Ltd. v. Gupta Brothers
       Steel Tubes Ltd. [2009] 14 SCR 253 : (2009) 10 SCC 63; Delhi
       Airport Metro Express Pvt. Ltd. v. DMRC Ltd. [2022] 3 SCR 716 :
       (2022) 1 SCC 131; Oil and Natural Gas Corporation Ltd. v. Afcons
       Gunanusa JV [2022] 10 SCR 660 : (2024) 4 SCC 481; Gherulal
       Parakh v. Mahadeodas Maiya and others [1959] Supp. 2 SCR 406:
       AIR (1959) SC 781; Central Inland Water Transport Corporation
       v. Brojo Nath Ganguly [1986] 2 SCR 278 : (1986) 3 SCC 156;
       Renusagar Power Co. Ltd. v. General Electric Co. [1993] Supp. 3
       SCR 22 : (1994) Supp (1) SCC 644; Oil and Natural Gas Corporation
       (ONGC) v. Saw Pipes Ltd. [2003] 3 SCR 691 : (2003) 5 SCC 705;
       D.D.A v. M/s. R.S. Sharma & Co. [2008] 12 SCR 785 : (2008) 13
       SCC 80; Oil and Natural Gas Corporation Limited v. Western Geco
       International Limited [2014] 12 SCR 1 : (2014) 9 SCC 263; Delhi
       Administration v. Gurdip Singh Uban [1999] Supp. 1 SCR 650 :
       (2000) 7 SCC 296; Patel Engineering Limited v. North Eastern
       Electric Power Corporation Limited [2020] 4 SCR 156 : (2020) 7
       SCC 167; Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro
       Express Pvt. Ltd. [2024] 4 SCR 473 : 2024 INSC 292; Pure Helium
       India (P) Ltd v. ONGC [2003] Supp. 4 SCR 561 : (2003) 8 SCC
       593; McDermott International Inc. v. Burn Standard Co. Ltd. [2006]
       Supp. 2 SCR 409 : (2006) 11 SCC 181; South East Asia Marine
       Engg. & Construction Ltd. (SEAMEC Ltd.) v. Oil India Ltd. [2020]
       4 SCR 254 : (2020) 5 SCC 164; Bharat Aluminium Co. V. Kaiser
       Aluminium Technical Services Inc. [2016] 1 SCR 364 : (2016) 4
       SCC 126; Adani Power (Mundra) Ltd. v. Gujarat ERC [2019] 8 SCR
       1017 : (2019) 19 SCC 9; Nabha Power Limited (NPL) v. Punjab
       State Power Corporation Limited (PSPCL) and Another [2017] 14
       SCR 301 : (2018) 11 SCC 508; Cox & Kings Ltd. v. SAP India (P)
[2024] 9 S.C.R.                                                             505

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     Ltd. [2023] 15 SCR 621 : (2024) 4 SCC 1; State of Goa v. Praveen
     Enterprises [2011] 10 SCR 1026 : (2012) 12 SCC 581; Mahomed
     Ghasita v. Siraj-ud-Din and others AIR (1922) Lah 198 (FB) : ILR
     (1921) 2 Lah 376 (FB) : (1921) SCC OnLine Lah 303; Dhapia v.
     Dalla (1969) All LJ 718 : AIR (1970) All 206 : (1969) SCC OnLine All
     79; Major (Retd.) Inder Singh Rekhi v. Delhi Development Authority
     [1988] 3 SCR 351 : (1988) 2 SCC 338; Khan Bahadur Shapoor
     Fredom Mazda v. Durga Prasad Chamaria and others [1962] 1
     SCR 140 : AIR (1961) SC 1236; J.C. Budhraja v. Chairman Orissa
     Mining Corporation Ltd. and Others [2008] 1 SCR 821 : (2008) 2
     SCC 444; Rajni Rani v. Khairati Lal [2014] 10 SCR 971 : (2015) 2
     SCC 682; Thomas Mathew v. KLDC Ltd. (2018) 12 SCC 560; Bans
     Gopal v. Mewa Ram AIR (1930) All 461 : (1929) SCC OnLine All
     152; Kali Das Chaudhuri v. Drapaudi Sundari Dassi AIR (1918) Cal
     294: (1917) SCC OnLIne Cal 23; Prem Singh & Ors v. Birbal & Ors.
     [2006] Supp. 1 SCR 692 : (2006) 5 SCC 353; Padhiyar Prahladji
     Chenaji v. Maniben Jagmalbhai & Ors. [2022] 2 SCR 455 : (2022)
     12 SCC 128 – referred to.

                       Books and Periodicals Cited
     Chitty on Contracts Volume 1, 35th Edition, paragraph 19-112;
     P. Ramanatha Aiyar’s Advanced Law Lexicon, 6th Edition,
     Volume III, page 2621; U.N. Mitra’s Law of Limitation and
     Prescription, Sixteenth Edition, Volume 1, at page 1063, published
     by LexisNexis; P. Ramanatha Aiyar’s Advanced Law Lexicon, 4th
     Edition at page 596; Russell on Arbitration (24th Edition, page 304);
     Anson’s Law of Contract (29th Oxford Edition) – referred to.

                                List of Acts
     Arbitration and Conciliation Act, 1996; Commercial Courts Act, 2015;
     Amended Letters Patent, 1865; Limitation Act, 1963; Contract Act,
     1872; Foreign Awards (Recognition and Enforcement) Act, 1961.

                             List of Keywords
     Arbitral award; Conflict with the public policy of India; Patent
     illegality; Holding company; Jointly and severally liable; Barred
     by limitation; Counter claim; Contractual relationship; Limitation;
     Outstanding principal amount with interest; Perverse; Adopting
     different yardstick for adjudging counterclaim; Composite tender;
     Declaration qua invalidity of debit notes; Liquidated damages;
     Customs duty; Arts. 14, 18 and 113, of the Schedule to Limitation
506                                                               [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       Act, 1963; Acknowledgement; Claim for compensation; Purchase
       orders; Group of companies doctrine; Starting point of limitation;
       Date from which the limitation period to be counted; Cause of action;
       Discharge of contractual obligations; Performance guarantee test;
       Breach of the contract; Limitation extended by acknowledgement;
       Extension of the period of limitation; Acknowledgement in writing;
       Claim to set off; Valid acknowledgement; Minutes of meeting;
       Avoid multiplicity of proceedings; Takeover certificate; Subsisting
       jural relationship; Declaratory relief; Mistake; Ongoing negotiations;
       Scope of public policy; Infraction of municipal laws of India;
       Infraction of fundamental policy of Indian law; Public interest or
       public good; In contravention with fundamental policy of Indian law;
       Administration of justice; Enforcement of law; Principles of natural
       justice; Disregarding orders of superior courts; Judicial scrutiny;
       Most basic notions of morality or justice; Legal justice; Dispensation
       of justice; Judicial mind; Patent illegality appearing on face of award;
       International commercial arbitrations; Erroneous application of law;
       Re-appreciation of evidence; Improper or inadequate reasons;
       Lack of reasons; Reasons recorded unintelligible; Impropriety or
       perversity; Degree of reasoning; Fair-reading of award; Inadequacy
       of reasons; Interpretation/construction of contract accorded in
       award; Unexpressed term; Party autonomy; Grund norm; Implied
       condition; Business efficacy doctrine.

                               Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 3981-3982
       of 2024
       From the Judgment and Order dated 01.09.2021 of the High Court
       of Judicature at Madras in OSA (CAD) Nos. 174 and 175 of 2021
       With
       Civil Appeal Nos. 3983-3984 of 2024
                            Appearances for Parties

       Abhimanyu Bhandari, Aman Gupta, Arjun Sayal, Shreyan Das, Advs.
       for the Appellant.
       Gaurab Banerjee, Sr. Adv., Mayank Mishra, Sarvesh Singh Baghel,
       Ms. Ayshwarya Chandra, Ms. Anukriti Kudesia, Arun Pratap Singh
       Rajawat, Advs. for the Respondents.
[2024] 9 S.C.R.                                                        507

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

                      Judgment / Order of the Supreme Court

                                          Judgment
      Manoj Misra, J.
1.    These two appeals are directed against a common judgment and
      order of the High Court1 dated 1 September 2021 passed in OSA
      (CAD) Nos. 174-175 of 2021, whereby, exercising powers under
      Section 37 of the Arbitration and Conciliation Act, 19962 read with
      Section 13(1) of the Commercial Courts Act, 20153 and Clause 15
      of Amended Letters Patent, 1865 read with Order XXXVI Rule 9
      of O.S. Rules, the Division Bench of the High Court allowed the
      appeals, set aside the judgment and order of the Single Judge
      dated 23 December 2020 and restored the arbitral award dated
      13 July 2020.
      THE CONTRACT
2.    OPG Power Generation Private Ltd (in short OPG -the appellant in the
      leading appeal), a subsidiary of Gita Power and Infrastructure Private
      Limited (in short Gita Power – Respondent No.2 (R-2) in the leading
      appeal, and appellant in the connected appeal), floated a composite
      tender for design, manufacture, supply, erection and commissioning
      of air-cooled condenser unit (ACC Unit) with auxiliaries for 160 MW
      Coal Based Thermal Power Plant (Project) at Gummidipoondi in
      the State of Tamil Nadu. Enexio Power Cooling Solutions (in short
      Enexio - Respondent No.1 (R-1) in the leading appeal) bid for the
      project. After a series of correspondences /negotiations, on 4 March
      2013, R-2 issued two separate orders: (i) for design, engineering
      and supply of one ACC Unit with auxiliaries for 160 MW Coal Based
      Power Project at Gummidipoondi (in short, Supply Purchase Order);
      and (ii) for erection and commissioning of one unit of ACC with
      auxiliaries for 160 MW Coal Based Power Project at Gummidipoondi
      (in short, Erection Purchase Order). Interestingly, the tender was
      floated by OPG but the supply and erection orders were issued by
      its holding company (Gita Power - R-2) on 4 March 2013. However,


1    High Court of Judicature at Madras
2    1996 Act
3    2015 Act
508                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       later, in the month of July 2013, OPG confirmed those orders by
       issuing two separate orders with same terms and bearing the same
       date i.e. 4 March 2013.
3.     The supply / erection purchase orders with its enclosures contained
       an arbitration clause in the following terms:
            “Clause 21. ARBITRATION
            21.1. In the event of any dispute or difference arising
            under the Order or in connection therewith including any
            question relating to existence, meaning and interpretation
            of the Order or any alleged breach thereof that cannot be
            amicably settled between the Parties, the same shall be
            referred to the arbitration.
            21.2. Arbitration shall be conducted under the Rules of
            Conciliation and Arbitration of the International Chamber
            of Commerce by three arbitrators appointed in accordance
            with said rules. The place of arbitration will be at Chennai.
            The arbitration proceedings shall be conducted in the
            English language.
            21.3. The arbitrators shall take into consideration the will
            of the Parties as expressed in the Order, the evidence
            presented, the principles of equity and good faith. The
            decision(s) of the arbitrators shall be final and both Parties
            undertake to fulfil and execute the said decision(s).
            21.4. Notwithstanding any dispute between the parties,
            Parties shall not be entitled to withhold/ delay/defer their
            obligations under the Order and same shall be carried out
            strictly in accordance with the terms and conditions of the
            Order.”
4.     Clause 6 of the supply purchase order provided:
            “6-Tax and duties:
            6.1. Taxes, duties and levies payable and charged by the
            competent authority such as Excise Duty, Sales Tax, Cess
            will be borne and paid by the Purchaser.
            6.2. The Purchaser shall issue Central Sales Tax Form C
            or any other Form as applicable for interstate sale.”
[2024] 9 S.C.R.                                                          509

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

5.   Likewise, clause 6 of the erection purchase order provided:
           “6-Tax and duties:
           6.1. All taxes duties and local levies payable and charged
           by the Competent Authority for the Services, such as
           Service Tax, cess, work order tax and other charges which
           could be levied in connection with and during the Order,
           whether deducted at source or not, will be borne and paid
           by the Purchaser.
           6.2. Any statutory variation due to implication of new taxes
           and duties shall be paid by Purchaser.”
     THE DISPUTE BETWEEN PARTIES
6.   The intended completion/ commissioning date, as originally
     contemplated, was 31 March 2014. However, commissioning took
     place in May 2015. The total amount billed by Enexio (R-1) for the
     aforesaid two orders was Rs. 46,71,04,493 but the amount paid to
     it was Rs. 39,59,19,629 only. This gave rise to a dispute. According
     to Enexio (R-1), Rs.6,75,15,631 remained payable to it. Whereas,
     according to the appellant, nothing was due as from the remaining
     amount, following sums were deductible:
           “(i) Rs.3,30,00,000, vide debit note dated 24.08.2015,
           towards liquidated damages for delay in supply and
           erection.
           (ii) Rs.5,94,06,693, vide debit note dated 16.01.2016,
           towards customs duty.
           (iii) Rs. 1,72,854 towards dismantling modification - TG
           building.
           (iv) Rs. 27,40,161 towards ACC duct fabrication. Totaling
           Rs. 9,53,19,708.”
7.   On 19 April 2018 a meeting took place between the representatives
     of the parties. Minutes of that meeting were drawn in the following
     terms:
           “Minutes of meeting with M/s. OPG Power Generation Pvt.
           Ltd. and M/s. ENEXIO Power Cooling Solutions (I) Pvt.
           Ltd. dated 19.04.2018.
510                                                   [2024] 9 S.C.R.

                 Digital Supreme Court Reports


       Members Present:

                 OPGS                        ENEXIO
       1.   Mr. S. Swaminathan       1. Mr. Parasuram
       2.   Mrs. C. Kiruthiga        2. Mr. Ravi Rengasamy
       Sub.: Supply of Air-cooled condenser with auxiliaries
       for 160 MW Coal based Power Project of OPG Power
       Generation Pvt. Ltd. (OPGPG) – Debit Notes.
       Ref.: 1. Order No. OPGPG/ED/P-III/SUPPLY/008, dated
                 04.03.2013.
            2. O
                rder No. OPGPG/ED/P-III/ ERECTION /009,
               dated 04.03.2013

       Description                                Amount in Rs.
       Total Billed Amount                          467,104,493
       Amount Paid                                  395,919,629
       Balance Payable incl Retention                67,515,618
       OPGPG Debit
       LD- Delay in Supply                           30,900,000
       LD- Delay in Erection                          2,100,000
       Customs Duty                                  59,406,693
       Dismantling Modification – TG Building           172,854
       ACC duct Fabrication (Debit raised
       for Rs.63,40,161/- against which GEA
       have accepted for Rs.36,00,000/- that is
       reduced from payable)                          2,740,161
       Total OPGPS Debit                             95,319,708


       Final Payable by Enexio                       27,804,090
       The above figures are validated by respective Projects
       and Finance departments.
       However, we request that the CD, CVD and LD’s be looked
       at leniently and mutually settled. The Contract calls for
       all taxes such as ED, ST to be reimbursed and CVD is
       equivalent to Excise duty.
[2024] 9 S.C.R.                                                         511

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           LD is not only due to our ENEXIO’s fault. In any case, this
           did not cause for any delay in Plant commissioning. We
           have had huge losses due to US dollar increase during
           Project stage to the tune of Rs.1.82 crores.
           ENEXIO requested that the above amount of Rs.2,78,04,090/-
           payable by them to M/s. OPG Power Generation Pvt. Ltd.
           be adjusted against the amount to be received by M/s.
           ENEXIO Power Cooling Solutions (I) Pvt. Ltd. from M/s.
           OPGS Power Gujarat Pvt. Ltd.”
8.   According to Enexio (R-1), in that meeting, the parties were ad idem
     regarding the outstanding principal amount payable to Enexio (R-1)
     and there was no consensus on any other item mentioned in the
     minutes of the meeting.
9.   On 26 May 2018 OPG extended an offer of Rs. 300 lacs to Enexio
     (R-1) as full and final settlement of the account. This was not accepted
     by Enexio. Hence, the claim.
     ENEXIO’S (R-1’s) CLAIM
10. On 2 May 2019 Enexio (R-1) invoked the arbitration clause, under
    the extant ICC Rules, raising the following claims:

      S.No. Claim                                        Amount (in INR)
      A       Outstanding principal amount as due          6,75,15,631
              under the Purchase Orders
      B       Declaration that the Debit Note Nos.
              076/2015-16 and 077/2015-16, both dated
                                                           -
              24.08.2015, issued by the Employer,
              claiming deduction of aggregate amount
              of INR 3,30,00,000/- towards Liquidated
              Damages for the delay, are unlawful and
              unsustainable.
      C       Declaration that the Debit Note
              No.032/2015-16 dated 12.01.2016, issued
                                                           -
              by the Employer, claiming deduction of
              Rs.5,94,06,693/- towards Customs Duty,
              including CVD and SAD, is unlawful and
              unsustainable.
512                                                              [2024] 9 S.C.R.

                         Digital Supreme Court Reports



       D          Interest on outstanding principal amount    3,51,43,446
                  calculated @ 18% p.a. from respective
                  due date(s) of payments till 31.03.2019.
       E          Interest on outstanding principal amount
                  calculated @ 18% p.a. for further period
                                                              -
                  starting from 01.04.2019 till the date of
                  payment.
       F          Damages under the Purchase Orders           8,00,00,000
       G          Costs of arbitration
       THE COUNTERCLAIM
11. On 15 July 2019 OPG submitted its defense, and raised counterclaims
    in respect of: (a) liquidated damages for delay; (b) customs duties;
    (c) cost of erection of horizontal and vertical exhaust through external
    agency; (d) cost of repair/ replacement of gear boxes; and (e) cost
    of repair/ replacement of fan modules.
       The Award
12. On 13 July 2020 ICC Arbitral Tribunal, comprising of three members,
    delivered a unanimous award, whereunder OPG and Gita Power,
    who have separately filed these two appeals, were required to pay,
    jointly and severally, to the claimant (R-1 - Enexio):
           (i)      Rs. 6,11,75,470/- towards outstanding principal
                    amount due under the purchase orders;
           (ii)     Rs. 95,27,533/- towards ICC Administrative Costs
                    and the Tribunal fees and expenses incurred in the
                    arbitration; and
           (iii) Rs. 40,65,515/- towards claimant’s legal fees and
                 expenses.
                    In addition to the above, OPG and Gita Power were
                    directed to pay simple interest at a rate of 10% per
                    annum on: (a) Rs. 6,11,75,470/- from 30 October
                    2015 until the date of payment; (b) Rs.95,27,533/-
                    from the date of the award till the date of payment;
                    and (c) Rs. 40,65,515/- from the date of the award
                    till the date of payment.
[2024] 9 S.C.R.                                                              513

               OPG Power Generation Private Limited v.
      Enexio Power Cooling Solutions India Private Limited & Anr.

                     However, all other claims including counterclaims
                     were rejected.
     KEY FINDINGS IN THE AWARD
13. The key findings of the Arbitral Tribunal were:
     (a)       Gita Power and OPG are jointly and severally liable –
               Gita Power, being the holding company of OPG, had actively
               participated in the negotiations and had placed the purchase
               orders, which were later confirmed by OPG. In fact, they both
               acted as a single economic enterprise. Therefore, mere issuance
               of another set of purchase orders by OPG with same terms
               and conditions would not relieve Gita Power of its obligations,
               rather both would be jointly and severally liable to the claimant
               (Enexio).
     (b)       Claimant is entitled to the unpaid principal amount with
               interest – Principal amount of Rs. 6,75,15,631/- is due and
               payable to the claimant (Enexio) under the terms of the purchase
               orders, subject to reconciliation of Rs.63,40,161 spent on vertical
               duct erection. Thus, net amount payable to the claimant is Rs.
               6,11,75,470 plus interest.
     (c)       No Damages are payable by Enexio to OPG/ Gita Power for
               the delay – The claimant was entitled to extension up to the date
               of completion i.e., 21 September 2015. Therefore, Enexio has
               no liability towards liquidated damages for the delay. Moreover,
               all the completion requirements were achieved by that date.
     (d)       No liability of Enexio to pay customs duty – Clause 6 of
               the Supply / Erection Purchase orders stipulated that all taxes,
               duties and local levies payable would be borne and paid by
               the purchaser. Therefore, liability to pay customs duty would
               fall upon the purchaser/ employer.
     (e)       Limitation -
               (i)   Declaratory relief sought by Enexio qua the debit notes
                     (i.e., towards liquidated damages and customs duty) is
                     beyond the period of limitation prescribed by Article 58 of
                     the Limitation Act, 1963;4


4   1963 Act
514                                                           [2024] 9 S.C.R.

                      Digital Supreme Court Reports


           (ii)   However, Enexio’s claim for unpaid dues payable under
                  the contract is within the period of limitation; and
           (iii) OPG’s counterclaim for cost of repair/replacement of
                 gearboxes and fan modules is barred by limitation.
       Reasoning of the Arbitral Tribunal on limitation:
14. Regarding the finding on limitation, the Arbitral Tribunal (in short the
    “Tribunal”) observed that the declaratory relief qua the debit notes
    (i.e., towards: (a) Liquidated damages for the delay; and (b) Customs
    duty) was sought beyond three years from the date when the right
    to sue first accrued, therefore it was beyond the limitation period
    prescribed by Article 58 of the Schedule to the 1963 Act. The Tribunal
    noticed that the debit note for liquidated damages was issued on 24
    August 2015; the claimant acknowledged its receipt vide letter dated
    28 August 2015; whereas the request for arbitration was received by
    ICC Secretariat on 2 May 2019. Likewise, the debit note for customs
    duty was issued on 12 January 2016 that is, beyond three years
    from the date of request for arbitration.
15. Insofar as the relief for recovery of the unpaid amount under the
    purchase orders was concerned, the Tribunal opined that it was not
    barred by limitation because meaningful negotiations were ongoing
    between the parties as evidenced by the minutes of meeting dated
    19 April 2018, which was followed by a written offer of the purchaser/
    employer, dated 26 May 2018, to pay Rupees three crores to the
    claimant as full and final settlement of the account. The relevant
    observations in that regard are found in paragraph 16.03 (d) of the
    award, which is extracted below:
           “16.03 (d) Based on the arguments of the Parties’
           respective Counsel and with reference to the case law and
           statutes cited during the oral hearing in this arbitration, the
           Tribunal finds that as long as meaningful negotiations were
           ongoing between the parties the period of limitation of three
           years had not begun to run. Following the meeting held
           between the parties on 19th April 2018 the respondents
           made a written offer to settle the matter on 26th May 2018.
           Thus, the Tribunal finds that the period of limitation had
           not commenced until 26th May 2018 and consequently had
           not expired when the Request for Arbitration was received
[2024] 9 S.C.R.                                                         515

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           by the ICC Secretariat on 2nd May 2019. Accordingly, the
           Tribunal finds that items A, D, E and F claiming payment
           of money are not time barred.”
16. Regarding the counterclaim for cost of repair/ replacement of
    gearboxes and fan modules as barred by limitation, the Tribunal
    reasoned thus:
           “16.04 Time Bar in relation to the Respondents’
           counterclaims for the cost of repair/replacement of
           gearboxes and fan modules.
           There is no evidence that these counterclaims were
           included in the ongoing negotiations. The Tribunal has
           found that the Taking Over Certificate is deemed to
           have been issued on 21st September 2015. (See Section
           13.13 above). On that date the Claimant is deemed to
           have completed its obligations and thus, that is the latest
           date from which the limitation period of three years must
           run. The Claimant’s liabilities are barred by limitation on
           or earlier than 21st September 2018. The Counterclaim
           was delivered on 15th July 2019 and is, thus, barred by
           limitation……….”
     CHALLENGE TO THE AWARD U/S 34 OF THE 1996 ACT
17. Two applications, namely, O.P. Nos. 533 and 562 of 2020, were filed
    by OPG (the appellant in the leading Civil Appeal) and Gita Power
    (appellant in the connected appeal and R-2 in the leading appeal)
    respectively, under Section 34 of the 1996 Act, for setting aside the
    award dated 13 July 2020.
     Grounds of Challenge
18. OPG and Gita Power laid challenge to the arbitral award, inter alia,
    on the following grounds:
     (i)   Enexio’s (R-1’s) claim was made beyond the period of limitation
           prescribed by Articles 14 and 18 of the Schedule to the 1963
           Act. The arbitration clause was invoked on 2 May 2019, well
           beyond three years from the date (i.e., 31 March 2014) when the
           work ought to have been completed as per the contract. It was
           also beyond three years from the deemed date of completion
           (i.e., 21 September 2015).
516                                                             [2024] 9 S.C.R.

                        Digital Supreme Court Reports


       (ii)   Different yardstick was adopted in computing the limitation period
              of the claim than what was adopted for the counterclaim, which
              was not at all justified as both arose out of same contractual
              relationship.
       (iii) One part of the minutes of meeting dated 19 April 2018 that
             supported the counterclaim was discarded, while the other part,
             which favored the claimant, was accepted. This is nothing but
             perverse.
       (iv) The time for completion of the work under the contract was
            extended without any basis.
       (v)    Findings in the award are self-contradictory in as much as, if
              challenge to the debit note for damages on account of the delay
              was beyond limitation, there was no logic in denying adjustment
              of those damages against the unpaid dues payable to Enexio
              under the purchase orders.
       (vi) Material evidence qua liability for customs duty was ignored.
       SINGLE JUDGE’S ORDER U/S 34 OF THE 1996 ACT
19. The learned Single Judge in its judgment and order on the application,
    under Section 34 of the 1996 Act, charted the undisputed dates as
    follows:

              Date                              Events
        31.03.2014      Said work ought to have been completed by Enexio.
        24.08.2015      Debit note pertaining to liquidated damages was raised
                        by Gita and OPG
        21.09.2015      Deemed date of completion of said work
        12.01.2016      Debit note regarding customs duty was raised by Gita
                        and OPG
        19.04.2018      Talks between adversaries namely Enexio on one side
                        and Gita/OPG on the other side culminated in minutes
                        of meeting (Ex.C.78)
        26.05.2018      Gita/OPG offered to settle at Rs. 300 lacs as full and
                        final settlement (Ex. C. 79)
        22.08.2018      Gita/OPG sent communication enclosing cheque for Rs.
                        25 lakhs as part of Rs. 3 Crores in full quit (Ex. C. 80)
        29.10.2018      Enexio returned Rs. 25 lakhs cheque (Ex. C. 82)
[2024] 9 S.C.R.                                                           517

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.


      02.05.2019     Arbitral institution, namely, ICC request for arbitration
                     (to be noted, both parties agreed that this is the date
                     of commencement of arbitration within the meaning of
                     section 21 of A and C Act)
      15.07.2019     Gita/OPG made counter claim vide its pleadings before
                     AT
20. After charting the relevant dates, and perusing the arbitral award, in
    paragraph 25 of the judgment, the learned Single Judge observed:
           “25. There is a clear dichotomy in impugned award
           regarding the legal drill of testing limitation. AT has taken
           26.05.2018 as the reckoning date, that being the date on
           which written offer to settle the matter was made by Gita/
           OPG vide Ex. C. 79, but for testing the counter claim of
           Gita/OPG, AT has taken 21.09.2015 as the reckoning
           date or starting point of limitation, that being the date of
           deemed completion of said work. This Court is constrained
           to observe that this dichotomy is akin to classical division
           between science and mysticism. Therefore, this Court
           unhesitatingly holds that this is patently illegal and an
           implausible view. To be noted, this dichotomy is not a mere
           erroneous application of law, and it needs no reappreciation
           of evidence. It is also an infract of section 18 of A and C
           Act which provides for equal treatment of parties. More
           importantly, the law of limitation being based on public
           policy, as already delineated supra, infract of the same
           would clearly vitiate the impugned award as one being in
           conflict with public policy of India.”
21. The learned Single Judge thereafter proceeded to observe that the
    counterclaim and heads of claim were so intertwined with each other
    that a decision on one, with no decision on the other, would vitiate
    the entire award. Further, it was observed, if the arbitral tribunal had
    taken the date of joint meeting (i.e., 19 April 2018), and the follow
    up offer dated 26 May 2018, as the starting point of limitation for
    the claim, the same would be the starting point of limitation for the
    counterclaim as well. And if the starting point of limitation is taken
    as 21 September 2015 (i.e., the date of completion of the work), the
    claim, which was filed on 2 May 2019, was well beyond three years
    and as such barred by limitation. Thus, according to the learned Single
518                                                          [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       Judge there was inherent contradiction in the arbitral award which
       made it vulnerable to a challenge under Section 34 of the 1996 Act.
       Consequently, the learned Single Judge set aside the arbitral award.
22. Aggrieved by the judgment and order of the learned Single Judge,
    dated 23 December 2020, Enexio (R-1 herein) filed two appeals,
    namely, O.S.A. (CAD) Nos. 174 and 175 of 2021, before the Division
    Bench of the High Court, which came to be allowed by the impugned
    judgment.
       IMPUGNED JUDGMENT
23. The Division Bench of the High Court, inter alia, took the view that
    the minutes of meeting dated 19 April 2018, read with e-mail dated
    26 May 2018, amounted to an acknowledgment of the dues payable
    to Enexio, thereby satisfying the ingredients of Section 18 of the 1963
    Act for a fresh period of limitation to run from that date. It observed
    that when the last part of the minutes’ dated 19 April 2018 is read
    with subsequent communication dated 26 May 2018, it belies the
    stand of the counterclaimant that the counterclaims were admitted to
    the claimant. Thus, the Division Bench, inter alia, held that the view
    taken by the arbitral tribunal was a possible view and there was no
    patent illegality in the award meriting interference under Section 34
    of the 1996 Act. Consequently, the order of the learned Single Judge
    was set aside, and the arbitral award was restored.
24. We have heard Mr. Abhimanyu Bhandari for the appellants; Mr. Gaurab
    Banerjee for the claimant-respondent and have perused the record.
       SUBMISSIONS ON BEHALF OF APPELLANT(S)
25. The learned counsel for the appellants, inter alia, submitted:
       (i)   The Arbitral Tribunal, in paragraph 16.03(d) of the award qua
             claims (i), (iv), (v) and (vi) (corresponding claim numbers A, D,
             E and F) of the claimant-respondent, observed:
                  “As long as meaningful negotiations were ongoing
                  between the parties, the period of limitation of three
                  years had not begun to run. Following the meeting
                  held between the parties on 19th April, 2018 the
                  respondents made a written offer to settle the matter
                  on 26 May 2018. Thus, the Tribunal finds that the
                  period of limitation had not commenced until 26
[2024] 9 S.C.R.                                                          519

               OPG Power Generation Private Limited v.
      Enexio Power Cooling Solutions India Private Limited & Anr.

                    May 2018 and consequently had not expired when
                    the request for arbitration was received by the ICC
                    Secretariat on 2 May 2019.”
            The afore-quoted observations are in teeth of decisions of this
            Court in (i) Bharat Sanchar Nigam Limited v. Nortel Networks
            Pvt. Ltd.5 and (ii) B & T AG v. Ministry of Defence6 where
            it has been held that mere negotiations will not postpone the
            cause of action for the purpose of limitation.
     (ii)   The period of limitation for the claim would have to be counted
            as three years from the date of completion i.e., 21 September
            2015, which got over before 2 May 2019 i.e., the date when
            request was received for arbitration. Once the claim is barred
            by limitation, the award allowing the claim would be deemed to
            be violative of fundamental policy of Indian law and, therefore,
            vulnerable in the light of the law declared in (i) Ssangyong
            Engg. & Construction Co. Ltd. v. NHAI7 and (ii) Associate
            Builders v. Delhi Development Authority.8
     (iii) The Arbitral Tribunal applied different yardstick for computing
           limitation of the claim than what was adopted for the counterclaim.
           For example, the start point of limitation for the claim was taken
           as 26 May 2018 whereas for the counterclaim it was taken as
           21 September 2015. This amounted to unequal treatment of
           the parties more so when claim as well as counterclaim arose
           from the same contractual relationship.
     (iv) Once the declaratory relief qua Debit Notes dated 24 August
          2015 (i.e. in respect of Rs. 3,30,00,000 towards liquidated
          damages for the delay in supply and erection under the purchase
          orders) and 12 January 2016 (i.e. in respect of Rs. 5,94,06,693/-
          towards Customs Duties) was held barred by limitation, the
          amount reflected in the Debit Notes ought to have been deemed
          payable by the claimant and that amount ought to have been
          adjusted against any amount payable to the claimant.



5   [2021] 2 SCR 644 : (2021) 5 SCC 738, paragraphs 20 and 21
6   [2023] 7 SCR 599 : (2024) 5 SCC 358, paragraph 73
7   [2019] 7 SCR 522 : (2019) 15 SCC 131
8   [2014] 13 SCR 895 : (2015) 3 SCC 49
520                                                             [2024] 9 S.C.R.

                            Digital Supreme Court Reports


       (v)    The Division Bench erroneously relied on the minutes dated
              19 April 2018 to apply Section 18 of the 1963 Act for extending
              the period of limitation of the claim when it was nobody’s case
              that limitation stood extended thereby. Further, if the minutes
              dated 19 April 2018 were to be relied, it ought to have been
              relied in toto and not in part. That is, it should have been taken
              as an admission of liability of the claimant towards liquidated
              damages for the delay as well as customs duty.
       (vi) In paragraph 13 of the impugned judgment, the Division
            Bench sought to appreciate the evidence i.e. the minutes of
            meeting dated 19 April 2018, which was beyond the scope of
            powers exercisable under Section 37 read with Section 34 of
            the 1996 Act. In this regard, reliance was placed on: (i) UHL
            Power Company limited v. State of Himachal Pradesh;9 (ii)
            Dyna Technologies Pvt. Ltd. v. Crompton Greaves Lt.;10 (iii)
            Heidelbergh Cement India Ltd. v. The Indure Pvt. Ltd.;11 (iv)
            MMTC Ltd. v. Vedanta Ltd.;12 (v) Ssangyong Engg (supra);
            and (vi) Haryana Tourism Ltd. v. Kandhari Beverages Ltd.13
       (vii) The learned Single Judge justifiably set aside the award that
             was self-contradictory and perverse.
       (viii) Counterclaims for cost of repair/ replacement of gear boxes,
              which were defective, ought to have been adjudicated. In
              absence thereof, the arbitral award is rendered bad in law.
       (ix) The Division Bench of the High Court misconstrued the ratio
            of the decision of this Court in Geo Miller & Co. (P) Ltd. v.
            Rajasthan Vidyut Utpadan Nigam Ltd14 for treating the claim
            within, and the counterclaim beyond, the period of limitation.
       (x)    The subsequent purchase orders issued by OPG replaced the
              earlier purchase orders issued by Gita Power, and the supply/



9    [2022] 1 SCR 1 : (2022) 4 SCC 116, paragraphs 16 to 21
10   [2019] 15 SCR 295 : (2019) 20 SCC 1, paragraphs 27-43
11   2022/DHC/003952
12   [2019] 3 SCR 1023 : (2019) 4 SCC 163, paragraphs 11 to 13
13   [2022] 2 SCR 316 : (2022) 3 SCC 237, paragraphs 7 & 8
14   [2019] 11 SCR 1108 : (2020) 14 SCC 643 (para 28)
[2024] 9 S.C.R.                                                           521

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

            work was in respect of an OPG project, therefore Gita Power
            could not have been dragged into arbitration and made jointly
            and severally liable with OPG.
     SUBMISSIONS ON BEHALF OF FIRST RESPONDENT/ENEXIO
26. The learned counsel for the first respondent, inter alia, submitted:
     (i)    The findings in the award are factually correct. There is no
            patent illegality, as alleged, or otherwise, which may warrant
            interference under Section 34 of the 1996 Act. Therefore, the
            Division Bench of the High Court was justified in setting aside
            the order of the Single Judge and restoring the award.
     (ii)   The appellant’s case that all counterclaims were treated as
            barred by limitation and, therefore, not considered on merits,
            is factually incorrect. In all five counterclaims were there. Out
            of those five, counterclaims towards: (i) liquidated damages for
            the delay in supply and erection; (ii) customs duty; and (iii) cost
            of erection of horizontal and vertical exhaust duct through an
            external agency, were considered and decided on merits. The
            counterclaims for liquidated damages and customs duty were
            rejected whereas counterclaim for cost of erection of vertical duct
            was allowed. Only two counterclaims towards (i) cost of repair/
            replacement of Gear Boxes, due to alleged defective supply,
            amounting to Rs.9,76,000, and (ii) cost of repair/ replacement
            of Fan Modules, due to alleged defective supply, amounting
            to Rs.14,80,802, were dismissed as barred by limitation. The
            finding that these two counterclaims were barred by limitation
            is premised on there being no material to indicate that they
            were included in the ongoing negotiation.
     (iii) The arbitral tribunal considered the three counterclaims on
           merit by adopting the same yardstick qua limitation as applied
           to the claims. These three counterclaims were not treated as
           barred by limitation as they were cited in the minutes of the
           meeting dated 19 April 2018 wherein the principal amount due
           to OPG was also acknowledged. It is thus incorrect to state that
           the arbitral tribunal adopted different yardstick on the point of
           limitation while deciding counterclaims than what was adopted
           to decide the claims.
522                                                            [2024] 9 S.C.R.

                            Digital Supreme Court Reports


       (iv) Enexio’s claim of the balance amount was not barred by
            limitation even if the limitation period is counted from the date
            of completion of the project i.e., 21 September 2015, because
            before expiry of the period of limitation of three years, that is
            before 20 September 2018, vide minutes of the meeting dated 19
            April 2018, OPG had acknowledged in writing its liability towards
            the balance of the principal amount (i.e., Rs. 6,75,15,631)
            albeit subject to deductions. Thus, by virtue of Section 18 of
            the 1963 Act, from the date of written acknowledgment, which
            was followed by written communication dated 26 May 2018,
            fresh period of limitation of three years began to run.
       (v)   Inference drawn from the minutes of the meeting as well as
             subsequent conduct of the parties to conclude lack of consent
             on Enexio’s part for deductions in the outstanding amount, is a
             decision within the remit of the arbitral tribunal. Therefore, any
             error, if at all, would be an error within its jurisdiction, which
             is not amenable to interference under Section 34 of the 1996
             Act. Because, while examining the validity of an award under
             Section 34, the Court exercises supervisory and not appellate
             jurisdiction (vide: (i) Steel Authority of India Ltd. versus
             Gupta Brothers Steel Tubes Ltd.;15 (ii) Associated Builders
             (supra); (iii) Ssangyong Engg (supra); and (iv) Delhi Airport
             Metro Express Pvt. Ltd. v. DMRC Ltd.16).
       (vi) The learned Single Judge had erred in observing:
             (a)     That any infract qua limitation would violate public policy
                     and attract Section 34 (2) (b) (ii) read with Explanation 1
                     of the 1996 Act.’ Because limitation is a mixed question
                     of fact and law and if its determination depends on
                     interpretation / appreciation of evidence / materials on
                     record, any error, ipso facto, would not render the award
                     amenable to interference as is clear from the Proviso to
                     sub-section (2-A) of Section 34 of the 1996 Act.
             (b)     ‘That different dates could not have been taken for
                     determining limitation of the claim and the counterclaim,



15   [2009] 14 SCR 253 : (2009) 10 SCC 63
16   [2022] 3 SCR 716 : (2022) 1 SCC 131
[2024] 9 S.C.R.                                                           523

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

                   when both were intertwined and had arisen from a
                   common supply/works contract.’ Because three out of
                   five counterclaims were decided on merits and not on
                   limitation. The remaining two were rejected on limitation
                   as they were not reflected in the minutes of meeting dated
                   19 April 2018. Therefore, benefit of Section 18 of the 1963
                   Act was not available qua those counterclaims. Moreover,
                   there cannot be a general rule that limitation for claims
                   and counterclaims must have a common run because
                   counterclaim is a separate action which must stand on
                   its own legs, as has been held by this Court in Oil and
                   Natural Gas Corporation Ltd. v. Afcons Gunanusa JV.17
      (vii) The counterclaim for the cost of repair/ replacement of gearboxes
            and fan modules was rightly rejected by the arbitral tribunal as
            barred by limitation as regarding it there was no recital in the
            minutes of meeting dated 19 April 2018. Moreover, it was not
            intertwined with the claim for the balance amount as the cause
            of action for the two were different. One arose from supply and
            erection, and the other arose subsequently, post commissioning/
            completion of the project, on account of alleged defect in the
            material supplied.
      (viii) Gita Power being the holding company of OPG and having
             actively participated in the formation of the contract as also in
             issuance of purchase orders for the supply/ works, which carried
             the arbitration clause, was bound by the arbitration agreement
             and also liable jointly and severally along with OPG for the dues.
      ISSUES
27. Upon consideration of the rival submissions, the core issue which
    falls for our determination is:
             “Whether the arbitral award is in conflict with the public
             policy of India, or/ and is vitiated by patent illegality
             appearing on the face of the award?”
28. The answer to the above issue would depend, inter alia, on our
    determination of the following sub-issues:


17   [2022] 10 SCR 660 : (2024) 4 SCC 481
524                                                                                     [2024] 9 S.C.R.

                              Digital Supreme Court Reports


       (a)     Whether Gita Power (R-2) could have been subjected to
               arbitration and made jointly and severally liable along with OPG
               for the award, when the project beneficiary was OPG?
       (b)     Whether Enexio’s claim for the outstanding principal amount
               barred by limitation?
       (c)     Whether the counter claim, in respect of cost of repair /
               replacement of gear boxes and fan modules, could be treated
               as barred by time when the other side’s claim, arising out of
               same contractual relationship, was found within limitation?
       (d)     Whether arbitral award for payment of the outstanding principal
               amount with interest is perverse because it makes no adjustment
               for debit note(s) entries even though the prayer to declare them
               as invalid was rejected as barred by time?
       (e)     Whether the reasoning of the arbitral tribunal is flawed and
               vitiated by adopting different yardstick for adjudging the
               counterclaim than what was adopted for adjudging the claim?
               If so, whether it vitiated the award and rendered it vulnerable
               to a challenge under Section 34 of the 1996 Act?
       RELEVANT LEGAL PRINCIPLES GOVERNING A CHALLENGE
       TO AN ARBITRAL AWARD
29. Before we delve into the issue/ sub-issues culled out above, it would
    be useful to have a look at the relevant legal principles governing
    a challenge to an arbitral award. Recourse to a Court against an
    arbitral award may be made through an application for setting aside
    such award in accordance with sub-sections (2), (2-A) and (3) of
    Section 34 of the 1996 Act.18 Sub-section (2) of Section 34 has


18   Section 34. Application for setting aside arbitral award. --- (1) ………..
        (2) An arbitral award may be set aside by the Court only if---
                  (a) the party making the application establishes on the basis of the record of the arbitral
                       tribunal that---
                 (i) a party was under some incapacity; or
                 (ii) the arbitration agreement is not valid under the law to which the parties have subjected
                       it or, failing any indication thereon, under the law for the time being in force; or
                 (iii) the party making the application was not given proper notice of the appointment of an
                       arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
                 (iv) the arbitral award deals with the dispute not contemplated by or not falling within the
                       terms of the submission to arbitration, or it contains decisions on matters beyond the
                       scope of the submission to arbitration:
                 Provided that, if the decisions on matters submitted to arbitration can be separated from
                 those not so submitted, only that part of the arbitral award which contains decisions on
[2024] 9 S.C.R.                                                                                               525

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

      two clauses, (a) and (b). Clause (a) has five sub-clauses which
      are not relevant to the issues raised before us. Insofar as clause
      (b) is concerned, it has two sub-clauses, namely, (i) and (ii). Sub-
      clause (i) of clause (b) is not relevant to the controversy in hand.
      Sub-clause (ii) of clause (b) provides that if the Court finds that the
      arbitral award is in conflict with the public policy of India, it may set
      aside the award.
      Public Policy
30. “Public policy” is a concept not statutorily defined, though it has
    been used in statutes, rules, notification etc. since long, and is also
    a part of common law. Section 2319 of the Contract Act, 1872 uses
    the expression by stating that the consideration or object of an


                  matters not submitted to arbitration may be set aside; or
                  (v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance
                         with the agreement of the parties, unless such agreement was in conflict with the
                         provision of this Part from which the parties cannot derogate, or, failing such agreement,
                         was not in accordance with this Part; or
                   (b) the Court finds that –
                              (i) the subject matter of the dispute is not capable of settlement by arbitration under
                                   the law for the time being in force, or
                              (ii) the arbitral award is in conflict with the public policy of India.
                   Explanation 1. — For the avoidance of any doubt, it is clarified that an award is in conflict
                   with the public policy of India, only if, –
                   (i) the making of the award was induced or affected by fraud or corruption or was in
                         violation of section 75 or section 81; or
                   (ii) it is in contravention with the fundamental policy of Indian law; or
                   (iii) it is in conflict with the most basic notions of morality or justice.
                   Explanation 2--- For the avoidance of doubt, the test as to whether there is a contravention
                   with the fundamental policy of Indian law, shall not entail a review on the merits of the
                   dispute.
         (2A) An arbitral award arising out of arbitrations other than international commercial arbitrations,
              may also be set aside by the Court, if the Court finds that the award is vitiated by patent
              illegality appearing on the face of the award:
              Provided that an award shall not be set aside, merely on the ground of an erroneous application
              of the law or by reappreciation of evidence.
         (3) An application for setting aside may not be made after three months have elapsed from the
              date on which the party making that application had received the arbitral award or, if a request
              had been made under section 33, from the date on which that request had been disposed of
              by the arbitral tribunal:
              Provided that if the court is satisfied that the applicant was prevented by sufficient cause from
              making the application within the set period of three months it may entertain the application
              within a period of 30 days, but not thereafter.
19   Section 23.-- What consideration and objects are lawful, and what not. -- The consideration or
     object of an agreement is lawful, unless –
     it is forbidden by law; or
     is of such a nature that, if permitted, it would defeat the provisions of any law; or is fraudulent; or
     involves or implies, injury to the person or property of another; or
     the court regards it as immoral, or opposed to public policy.
     In each of these cases, the consideration or object of an agreement is said to be unlawful. Every
     agreement of which the object or consideration is unlawful is wide.
526                                                              [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       agreement is lawful, unless, inter alia, opposed to public policy. That
       is, a contract which is opposed to public policy is void.
31. In Chitty on Contracts,20 scope of public policy, largely accepted
    across jurisdictions for invalidation of contracts, has been summarized
    in the following terms:
              “Objects which on grounds of public policy invalidate
              contracts may, for convenience, be generally classified
              into five groups: first, objects which are illegal by common
              law or by legislation; secondly, objects injurious to good
              government either in the field of domestic or foreign affairs;
              thirdly, objects which interfere with the proper working of the
              machinery of justice; fourthly, objects injurious to marriage
              and morality; and, fifthly, objects economically against the
              public interest, viz contracts in restraint of trade…..”
32. In Gherulal Parakh v. Mahadeodas Maiya and others,21 a three-
    Judge Bench of this Court, in the context of Section 23 of the Contract
    Act, summarized the doctrine of public policy as follows:
              “Public policy or the policy of the law is an elusive concept;
              it has been described as untrustworthy guide, variable
              quality, uncertain one, unruly horse, etc; the primary duty
              of a court of law is to enforce a promise which the parties
              have made and to uphold the sanctity of contracts which
              formed the basis of society, but in certain cases, the court
              may relieve them of their duty on a rule founded on what is
              called the public policy; for want of better words Lord Atkin
              describes that something done contrary to public policy is
              a harmful thing, but the doctrine is extended not only to
              harmful cases but also to harmful tendencies; this doctrine
              of public policy is only a branch of common law, and, just
              like any other branch of common law, it is governed by
              precedents; the principles have been crystallized under
              different heads and though it is permissible for courts to
              expound and apply them to different situations, it should
              only be invoked in clear and incontestable cases of harm



20   Volume 1, 35th Edition, paragraph 19-112
21   [1959] Supp. 2 SCR 406 : AIR 1959 SC 781
[2024] 9 S.C.R.                                                               527

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

             to the public; Though the heads are not closed and though
             theoretically it may be permissible to evolve a new head
             under exceptional circumstances of a changing world, it
             is advisable in the interest of stability of society not to
             make any attempt to discover new heads in these days.
                                                         (Emphasis supplied)
33. In Central Inland Water Transport Corporation v. Brojo Nath
    Ganguly,22 this Court observed that the expressions ‘public policy’,
    ‘opposed to public policy’, or ‘contrary to public policy’ are incapable
    of precise definition. It was observed that public policy is not the policy
    of a particular government. Rather it connotes some matter which
    concerns the public good and the public interest. It was observed:
             “92.……what is for the public good or in the public interest
             or what would be injurious or harmful to the public good
             or the public interest has varied from time to time. As
             new concepts take the place of old, transactions which
             were once considered against public policy are now being
             upheld by the courts and, similarly, where there has been a
             well- recognized head of public policy, the courts have not
             shirked from extending it to new transactions and changed
             circumstances and have at times not even flinched from
             inventing a new head of public policy.”
                                                         (Emphasis supplied)
34. In Renusagar Power Co. Ltd. v. General Electric Co.,23 a three-
    Judge Bench of this Court observed that the doctrine of public policy
    is somewhat open- textured and flexible. By citing earlier decisions,
    it was observed that there are two conflicting positions which are
    referred to as the “narrow view” and the “broad view”. According to
    the narrow view, courts cannot create new heads of public policy
    whereas the broad view countenances judicial law making in these
    areas. In the field of private international law, it was pointed out, courts
    refuse to apply a rule of foreign law or recognize a foreign judgment
    or a foreign arbitral award if it is found that the same is contrary to
    the public policy of the country in which it is sought to be invoked


22   [1986] 2 SCR 278 : (1986) 3 SCC 156, paragraph 92
23   [1993] Supp. 3 SCR 22 : 1994 Supp (1) SCC 644
528                                                                                 [2024] 9 S.C.R.

                                 Digital Supreme Court Reports


       or enforced. However, it was clarified, a distinction is to be drawn
       while applying the rule of public policy between a matter governed by
       domestic law and a matter involving conflict of laws. It was observed
       that the application of the doctrine of public policy in the field of
       conflict of laws is more limited than that in the domestic law and the
       courts are slower to invoke public policy in cases involving a foreign
       element than when a purely municipal legal issue is involved. It was
       held that contravention of law alone will not attract the bar of public
       policy, and something more than contravention of law is required.
35. In fact, in Renusagar (supra), this Court was dealing with the
    enforceability of a foreign award. For that end, it had to interpret
    the expression “contrary to public policy” in the context of Section
    7(1)(b)(ii) of Foreign Awards (Recognition and Enforcement) Act,
    1961.24 While doing so, this Court held that -- (a) contravention of
    law alone will not attract the bar of public policy, and something
    more than contravention of law is required;25and (b) the expression
    ‘public policy’ must be construed in the sense the doctrine of public
    policy is applied in the field of private international law. Applying the
    said criteria, it was held that enforcement of a foreign award could
    be refused on the ground of being contrary to public policy if such
    enforcement would be contrary to (a) fundamental policy of Indian
    law or (b) the interests of India or (c) justice or morality.26 The Court
    thereafter proceeded to hold that a contravention of the provisions of
    the Foreign Exchange Regulation Act would be contrary to the public
    policy of India as that statute is enacted for the national economic
    interest to ensure that the nation does not lose foreign exchange
    which is essential for the economic survival of the nation.27
36. What is clear from above is that for an award to be against public
    policy of India a mere infraction of the municipal laws of India is not
    enough. There must be, inter alia, infraction of fundamental policy of
    Indian law including a law meant to serve public interest or public good.


24   Section 7. Conditions for enforcement of foreign awards. – (1) A foreign award may be enforced
     under this Act—
               *******
        (b)    if the court dealing with the case is satisfied that –
               *******
        (ii)   the enforcement of the award will be contrary to the public policy.
25   paragraph 65 of Renusagar (supra)
26   paragraph 66 of Renusagar (supra)
27   paragraph 75 of Renusagar (supra)
[2024] 9 S.C.R.                                                                  529

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

37. In Oil and Natural Gas Corporation (ONGC) v. Saw Pipes Ltd.28
    a two-Judge Bench of this Court, in the context of a challenge to a
    domestic arbitral award under Section 34(2)(b)(ii) of the 1996 Act
    as it stood prior to 2015 amendment, ascribed wider meaning to the
    expression ‘public policy of India’ in the following terms:
             “31. ……. the phrase public policy of India used in section
             34 in context is required to be given a wider meaning. It
             can be stated that the concept of public policy connotes
             some matter which concerns public good and the public
             interest. What is for public good or in public interest or what
             would be injurious or harmful to the public good or public
             interest has varied from time to time. However, the award
             which is, on the face of it, patently in violation of statutory
             provisions cannot be said to be in public interest. Such
             award/ judgment/ decision is likely to adversely affect the
             administration of justice. Hence, in our view, in addition
             to narrower meaning given to the term “public policy” in
             Renusagar case, it is required to be held that the award
             could be set aside if it is patently illegal. The result would
             be – award could be set aside if it is contrary to:
             (a)     fundamental policy of Indian law; or
             (b)     the interest of India; or
             (c)     justice or morality, or
             (d)     in addition, if it is patently illegal.
             Illegality must go to the root of the matter and if the illegality
             is of trivial nature, it cannot be held that award is against
             the public policy. Award could also be set aside if it is so
             unfair and unreasonable that it shocks the conscience of
             the court. Such award is opposed to public policy and is
             required to be adjudged void.
                                                         (Emphasis supplied)
38. Following the expansive view of the concept “contrary to public
    policy”, in D.D.A v. M/s. R.S. Sharma & Co.,29 which related to a


28   [2003] 3 SCR 691 : (2003) 5 SCC 705
29   [2008] 12 SCR 785 : (2008) 13 SCC 80
530                                                                   [2024] 9 S.C.R.

                              Digital Supreme Court Reports


       matter arising from a proceeding under Section 34, as it stood prior
       to 2015 amendment, a two-Judge Bench of this Court, on the scope
       of the power to set aside an arbitral award, summarized the general
       principles as follows:
              “21. …
              (a)      An award, which is
                       (i)    contrary to substantive provisions of law; or
                       (ii)   the provisions of the arbitration and Conciliation
                              Act, 1996; or
                       (iii) against the terms of the respective contract; or
                       (iv) patently illegal; or
                       (v)    prejudicial to the rights of the parties;
              Is open to interference by the court under Section 34(2)
              of the Act.
              (b)      The award could be set aside if it is contrary to:
                       (a)    fundamental policy of Indian law; or
                       (b)    the interest of India; or
                       (c)    justice or morality.
              (c)      The award could also be set aside if it is so unfair
                       and unreasonable that it shocks the conscience of
                       the court.
              (d)      It is open to the court to consider whether the award
                       is against the specific terms of contract and if so,
                       interfere with it on the ground that it is patently illegal
                       and opposed to public policy of India.”
39. In Oil and Natural Gas Corporation Limited v. Western Geco
    International Limited,30 which also related to the period prior to
    2015 amendment of Section 34 (2)(b)(ii),31 a three-Judge Bench
    of this Court, after considering the decision in Saw Pipes (supra),



30   [2014] 12 SCR 1 : (2014) 9 SCC 263 paragraphs 35, 38 and 39
31   See Footnote 18
[2024] 9 S.C.R.                                                                                         531

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

      without exhaustively enumerating the purport of the expression
      ‘fundamental policy of Indian law’, observed that it would include all
      such fundamental principles as providing a basis for administration of
      justice and enforcement of law in this country. The Court thereafter
      illustratively referred to three fundamental juristic principles, namely,
      (a) that in every determination that affects the rights of a citizen or
      leads to any civil consequences, the court or authority or quasi-
      judicial body must adopt a judicial approach, that is, it must act bona
      fide and deal with the subject in a fair, reasonable and objective
      manner and not actuated by any extraneous consideration; (b) that
      while determining the rights and obligations of parties the court or
      tribunal or authority must act in accordance with the principles of
      natural justice and must apply its mind to the attendant facts and
      circumstances while taking a view one way or the other; and (c) that
      its decision must not be perverse or so irrational that no reasonable
      person would have arrived at the same.
40. In Associate Builders (supra), a two-Judge Bench of this Court,
    held32 that audi alteram partem principle is undoubtedly a fundamental
    juristic principle in Indian law and is enshrined in Sections 1833 nand
    34 (2)(a)(iii)34 of the 1996 Act. In addition to the earlier recognized
    principles forming fundamental policy of Indian law, it was held
    that disregarding: (a) orders of superior courts in India; and (b)
    the binding effect of the judgment of a superior court would also
    be regarded as being contrary to the fundamental policy of Indian
    law.35 Further, elaborating upon the third juristic principle (i.e., qua
    perversity), as laid down in Western Geco (supra), it was observed
    that where: (i) a finding is based on no evidence; or (ii) an arbitral
    tribunal takes into account something irrelevant to the decision which
    it arrives at; or (iii) ignores vital evidence in arriving at its decision,
    such decision would necessarily be perverse.36 To this a caveat was
    added by observing that when a court applies the ‘public policy test’
    to an arbitration award, it does not act as a court of appeal and,



32   See paragraph 30 of the judgment in Associate Builders (supra)
33   Section 18. Equal treatment of parties. -- The parties shall be treated with equality and each party shall
     be given a full opportunity to present his case.
34   See Footnote 18
35   See paragraph 27 of the judgment in Associate Builders (supra)
36   Paragraph 31 of the judgment in Associate Builders (supra)
532                                                              [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       consequently, errors of fact cannot be corrected; and a possible
       view by the arbitrator on facts has necessarily to pass muster as
       the arbitrator is the ultimate master of the quantity and quality of
       evidence to be relied upon when he delivers his arbitral award. It
       was also observed that an award based on little evidence or on
       evidence which does not measure up in quality to a trained legal
       mind would not be held to be invalid on that score. Thus, once it is
       found that the arbitrator’s approach is not arbitrary or capricious, it
       is to be taken as the last word on facts.37
       2015 Amendment in Sections 34 and 48
41. The afore-mentioned judicial pronouncements were all prior to 2015
    Amendment. Notably, prior to the Amendment, 2015 the expression
    “in contravention with the fundamental policy of Indian law” was not
    used by the legislature in either Section 34(2)(b)(ii) or Section 48(2)
    (b). The pre-amended Section 34(2)(b)(ii) and its Explanation read:
              “S.34. Application for setting aside arbitral award—
              (1) *******
              (2) An arbitral award may be set aside by the court only if—
              ******
              (b) the court finds that –
              ******
              (ii) the arbitral award is in conflict with the public policy
              of India.
              Explanation.-- Without prejudice to the generality of sub-
              clause (ii) it is hereby declared, for the avoidance of any
              doubt, that an award is in conflict with the public policy of
              India if the making of the award was induced or affected
              by fraud or corruption or was in violation of section 75 or
              section 81.
              Whereas pre-amended Section 48(2)(b) and its Explanation
              read:



37   Paragraph 33 of the judgment in Associate Builders (supra)
[2024] 9 S.C.R.                                                                                            533

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

               S. 48. Conditions for enforcement of foreign awards. –
               (1) ********
               (2) Enforcement of an arbitral award may also be refused
               if the court finds that—
               (a). ******
               (b) the enforcement of the award would be contrary to the
               public policy of India.
               Explanation. – Without prejudice to the generality of sub-
               clause (b) of this section, it is hereby declared, for the
               avoidance of any doubt, that an award is in conflict with
               the public policy of India if the making of the award was
               induced or affected by fraud or corruption.
42. By the Amendment, 2015, in place of the old Explanation to Section
    34(2)(b)(ii), Explanations 1 and 2 were added to remove any doubt as
    to when an arbitral award is in conflict with the public policy of India.
43. At this stage, it would be pertinent to note that we are dealing with
    a case where the application under Section 34 of the 1996 Act was
    filed after the Amendment, 2015, therefore the newly substituted/
    added Explanations would apply.38
44. The Amendment, 2015 adds two explanations to each of the two
    sections, namely, Section 34(2)(b)(ii)39 and Section 48(2)(b),40 in place
    of the earlier Explanation. The significance of the newly inserted
    Explanation 1 in both the sections is two-fold. First, it does away with
    the use of words: (a) “without prejudice to the generality of sub-clause
    (ii)” in the opening part of the pre-amended Explanation to Section
    34(2)(b)(ii); and (b) “without prejudice to the generality of clause (b)
    of this section” in the opening part of the pre-amended Explanation


38   Ssangyong Engineering & Construction Co. Ltd (supra)
39   See footnote 18
40   Section 48(2)(b).--
     Explanation 1. — For the avoidance of any doubt, it is clarified that an award is in conflict with the public
     policy of India, only if ,--
     the making of the award was induced or affected by fraud or corruption or was in violation of section 75
     or section 81; or
     it is in contravention with the fundamental policy of Indian law; or
     it is in conflict with the most basic notions of morality or justice.
     Explanation 2.-- For the avoidance of doubt, the test as to whether there is a contravention with the
     fundamental policy of Indian law shall not entail a review on the merits of the dispute.
534                                                          [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       to Section 48(2)(b); secondly, it limits the expanse of public policy
       of India to the three specified categories by using the words “only
       if”. Whereas, Explanation 2 lays down the standard for adjudging
       whether there is a contravention with the fundamental policy of
       Indian law by providing that a review on merits of the dispute shall
       not be done. This limits the scope of the enquiry on an application
       under either Section 34(2)(b)(ii) or Section 48(2)(b) of the 1996 Act.
45. The Amendment, 2015 by inserting sub-section (2-A)41 in Section
    34, carves out an additional ground for annulment of an arbitral
    award arising out of arbitrations other than international commercial
    arbitrations. Sub-section (2-A) provides that the Court may also set
    aside an award if that is vitiated by patent illegality appearing on the
    face of the award. This power of the Court is, however, circumscribed
    by the Proviso, which states that an award shall not be set aside
    merely on the ground of an erroneous application of the law or by
    re-appreciation of evidence.
46. Explanation 1 to Section 34(2)(b)(ii), specifies that an arbitral award
    is in conflict with the public policy of India, only if,- (i) the making
    of the award was induced or affected by fraud or corruption or was
    in violation of Section 75 or Section 81; or (ii) it is in contravention
    with the fundamental policy of Indian law; or (iii) it is in conflict with
    the most basic notions of morality or justice.
47. In the instant case, there is no allegation that the making of the award
    was induced or affected by fraud or corruption, or was in violation of
    Section 75 or Section 81. Therefore, we shall confine our exercise in
    assessing as to whether the arbitral award is in contravention with
    the fundamental policy of Indian law, and/ or whether it conflicts with
    the most basic notions of morality or justice. Additionally, in the light
    of the provisions of sub-section (2-A) of Section 34, we shall examine
    whether there is any patent illegality on the face of the award.
48. Before undertaking the aforesaid exercise, it would be apposite to
    consider as to how the expressions (a) “in contravention with the
    fundamental policy of Indian law”; (b) “in conflict with the most basic
    notions of morality or justice”; and (c) “patent illegality” have been
    construed.



41   See Footnote 18
[2024] 9 S.C.R.                                                         535

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     In contravention with the fundamental policy of Indian law
49. As discussed above, till the Amendment, 2015 the expression “in
    contravention with the fundamental policy of Indian law” was not
    found in the 1996 Act. Yet, in Renusagar (supra), in the context of
    enforcement of a foreign award, while construing the phrase “contrary
    to the public policy”, this Court held that for a foreign award to be
    contrary to public policy mere contravention of law would not be
    enough rather it should be contrary to: (a) the fundamental policy
    of Indian law; and /or (b) the interest of India; and/ or (c) justice or
    morality.
50. In the judicial pronouncements that followed Renusagar (supra),
    already discussed above, the domain of what could be considered
    contrary to the ‘public policy of India’/ ‘fundamental policy of Indian
    law’ expanded, resulting in much greater interference with arbitral
    awards than what the lawmakers intended. This led to the Amendment,
    2015 in the 1996 Act.
51. In Ssangyong Engineering (supra), this Court dealt with the
    effect of the Amendment, 2015. While doing so, it took note of a
    supplementary report of February 2015 of the Law Commission of
    India made in the context of the proposed 2015 amendments. The
    said supplementary report has been extracted in paragraph 30 of
    that judgment. The key features of it are summarized below:
     (a)   Mere violation of law of India would not be a violation of public
           policy in cases of international commercial arbitrations held in
           India.
     (b)   The proposed 2015 amendments in 1996 Act (i.e., in Sections
           34(2)(b)(ii) and 48(2)(b) including insertion of sub-section (2-A)
           in Section 34) were on the assumption that the terms, such as,
           “fundamental policy of Indian law” or conflict with “most basic
           notions of morality or justice” would not be widely construed.
     (c)   The power to review an award on merits is contrary to the
           object of the Act and international practice.
     (d)   The judgment in Western Geco (supra) would expand the
           court’s power, contrary to international practice. Hence, a
           clarification needs to be incorporated to ensure that the term
           ‘fundamental policy of Indian law’ is narrowly construed. The
536                                                          [2024] 9 S.C.R.

                      Digital Supreme Court Reports


           applicability of Wednesbury principles to public policy will open
           the floodgates. Hence, Explanation 2 to Section 34(2)(b)(ii) has
           been proposed.
       After taking note of the supplementary report, the statement of
       objects and reasons of the Amendment Act, 2015, and the amended
       provisions of Sections 28, 34 and 48, this Court held:
           “34. What is clear, therefore, is that the expression public
           policy of India, whether contained in section 34 or in section
           48, would now mean the fundamental policy of Indian law
           as explained in paras 18 and 27 of Associate Builders i.e.
           the fundamental policy of Indian law would be relegated
           to Renusagar’s understanding of this expression. This
           would necessarily mean that Western Geco expansion
           has been done away with. In short, Western Geco, as
           explained in Paras 28 and 29 of Associate Builders, would
           no longer obtain, as under the guise of interfering with an
           award on the ground that the arbitrator has not adopted
           a judicial approach the court’s intervention would be on
           the merits of the award, which cannot be permitted post
           amendment. However, in so far as principles of natural
           justice are concerned, as contained in sections 18 and
           34(2)(a) (iii) of the 1996 Act, these continue to be the
           grounds of challenge of an award, as is contained in para
           30 of Associate Builders.
           35.*****
           36******
           37. In so far as domestic awards made in India are
           concerned, an additional ground is now available under
           sub-section (2-A), added by the Amendment Act, 2015 to
           section 34. Here, there must be patent illegality appearing
           on the face of the award, which refers to such illegality as
           goes to the root of the matter, but which does not amount
           to mere erroneous application of the law. In short, what
           is not subsumed within the fundamental policy of Indian
           law, namely, the contravention of a statute not linked to
           public policy or public interest, cannot be brought in by
           the back door when it comes to setting aside an award
           on the ground of patent illegality.
[2024] 9 S.C.R.                                                           537

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           38. Secondly, it is also made clear that reappreciation of
           evidence, which is what an appellate court is permitted
           to do, cannot be permitted under the ground of patent
           illegality appearing on the face of the award.
           39. To elucidate, para 42.1 of Associate Builders, namely,
           a mere contravention of the substantive law of India, by
           itself, is no longer a ground available to set aside an
           arbitral award. Para 42.2 of Associate Builders, however,
           would remain, for if an arbitrator gives no reasons for an
           award and contravenes section 31(3) of the 1996 Act,
           that would certainly amount to a patent illegality on the
           face of the award.
           40. The change made in Section 28(3) by the Amendment
           Act really follows what is stated in paras 42.3 to 45 in
           Associate Builders, namely, that the construction of the
           terms of a contract is primarily for an arbitrator to decide,
           unless the arbitrator construes the contract in a manner
           that no fair minded or reasonable person would; in short,
           that the arbitrator’s view is not even a possible view to
           take. Also, if the arbitrator wanders outside the contract
           and deals with the matters not allotted to him, he commits
           an error of jurisdiction. This ground of challenge will now
           fall within the new ground added under Section 34 (2-A).
           41. What is important to note is that a decision which is
           perverse, as understood in paras 31 and 32 of Associate
           Builders, while no longer being a ground for challenge
           under “public policy of India”, would certainly amount to a
           patent illegality appearing on the face of the award. Thus,
           a finding based on no evidence at all or an award which
           ignores vital evidence in arriving at its decision would be
           perverse and liable to be set aside on the ground of patent
           illegality. Additionally, a finding based on documents taken
           behind the back of the parties by the arbitrator would also
           qualify as a decision based on no evidence inasmuch as
           such decision is not based on evidence led by the parties,
           and therefore, would also have to be characterized as
           perverse.
           ********* ******* *******
538                                                       [2024] 9 S.C.R.

                    Digital Supreme Court Reports


          69. We therefore hold, following the aforesaid authorities,
          that in the guise of misinterpretation of the contract, and
          consequent errors of jurisdiction, it is not possible to
          state that the arbitral award would be beyond the scope
          of submission to arbitration if otherwise the aforesaid
          misinterpretation [which would include going beyond
          the terms of the contract], could be said to have been
          fairly comprehended as disputes within the arbitration
          agreement or which were referred to the decision of the
          arbitrators as understood by the authorities above. If an
          arbitrator is alleged to have wandered outside the contract
          and dealt with matters not allotted to him, this would be
          a jurisdictional error which could be corrected on the
          ground of patent illegality, which, as we have seen, would
          not apply to international commercial arbitrations that
          are decided under Part II of the 1996 Act. To bring in by
          the back door grounds relatable to Section 28 (3) of the
          1996 Act to be matters beyond the scope of submission
          to arbitration under section 34(2)(a)(iv) would not be
          permissible as this ground must be construed narrowly
          and so construed, must refer only to matters which are
          beyond the arbitration agreement or beyond the reference
          to the arbitral tribunal.”
52. The legal position which emerges from the aforesaid discussion
    is that after the ‘2015 amendments’ in Section 34 (2)(b)(ii) and
    Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the
    public policy of India” must be accorded a restricted meaning in
    terms of Explanation 1. The expression “in contravention with the
    fundamental policy of Indian law” by use of the word ‘fundamental’
    before the phrase ‘policy of Indian law’ makes the expression
    narrower in its application than the phrase “in contravention with the
    policy of Indian law”, which means mere contravention of law is not
    enough to make an award vulnerable. To bring the contravention
    within the fold of fundamental policy of Indian law, the award must
    contravene all or any of such fundamental principles that provide
    a basis for administration of justice and enforcement of law in this
    country. Without intending to exhaustively enumerate instances of
    such contravention, by way of illustration, it could be said that (a)
[2024] 9 S.C.R.                                                                       539

                 OPG Power Generation Private Limited v.
        Enexio Power Cooling Solutions India Private Limited & Anr.

       violation of the principles of natural justice; (b) disregarding orders
       of superior courts in India or the binding effect of the judgment of
       a superior court; and (c) violating law of India linked to public good
       or public interest, are considered contravention of the fundamental
       policy of Indian law. However, while assessing whether there has
       been a contravention of the fundamental policy of Indian law, the
       extent of judicial scrutiny must not exceed the limit as set out in
       Explanation 2 to Section 34(2)(b)(ii).
       Most basic notions of morality and justice
53. In Renusagar (supra) this Court held that an arbitral award is in
    conflict with the public policy of India if it is, inter alia, contrary to
    “justice and morality”. Explanation 1, inserted by 2015 Amendment,
    makes it clear that an award is in conflict with the public policy of
    India, inter alia, if it conflicts with the ‘most basic notions of morality
    or justice’.
       Justice
54. Justice is the virtue by which the society/ court / tribunal gives a man
    his due, opposed to injury or wrong. Justice is an act of rendering
    what is right and equitable towards one who has suffered a wrong.
    Therefore, while tempering justice with mercy, the court must be very
    conscious, that it has to do justice in exact conformity with some
    obligatory law, for the reason that human actions are found to be just
    or unjust on the basis of whether the same are in conformity with,
    or in opposition to, the law.42 Therefore, in ‘judicial sense’, justice
    is nothing more nor less than exact conformity to some obligatory
    law; and all human actions are either just or unjust as they are in
    conformity with, or in opposition to, the law.43
55.     But, importantly, the term ‘legal justice’ is not used in Explanation
       1, therefore simple conformity or non-conformity with the law is
       not the test to determine whether an award is in conflict with the
       public policy of India in terms of Explanation 1. The test is that it
       must conflict with the most basic notions of justice. For lack of any
       objective criteria, it is difficult to enumerate the ‘most basic notions


42    Union of India v. Ajeet Singh, (2013) 4 SCC 186, paragraph 26.
43    P. Ramanatha Aiyar’s Advanced Law Lexicon, 6th Edition, Volume III, page 2621.
540                                                                  [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       of justice’. More so, justice to one may be injustice to another. This
       difficulty has been acknowledged by many renowned jurists, as is
       reflected in the observations of this Court in Delhi Administration
       v. Gurdip Singh Uban,44 extracted below:
              “23. The words ‘justice’ and ‘injustice’, in our view, are
              sometimes loosely used and have different meanings to
              different persons particularly to those arrayed on opposite
              sides. One man’s justice is another’s injustice [Raplph
              Waldo Emerson: Essays (1803-82), First Series, 1841,
              “Circles]. Justice Cardozo said: “The web is entangled and
              obscure, shot through with a multitude of shades and colors,
              the skeins irregular and broken. Many hues that seem to
              be simple, are found, when analyzed, to be a complex and
              uncertain blend. Justice itself, which we are wont to appeal
              to what as a test as well as an ideal, may mean different
              things to different minds and at different times. Attempts
              to objectify its standards or even to describe them have
              never wholly succeeded (Selected Writings of Cardozo,
              pp 223-224, Falcon Publications, 1947).”
56. In Associate Builders (supra), while this Court was dealing with
    the concept “public policy of India”, in the context of a Section 34
    challenge prior to 2015 amendment, it was held that an award can be
    said to be against justice only when it shocks the conscience of the
    court.45 The Court illustrated by stating that where an arbitral award,
    without recording reasons, awards an amount much more than what
    the claim is restricted to, it would certainly shock the conscience of
    the court and render the award vulnerable and liable to be set aside
    on the ground that it is contrary to justice.
57. In Ssyangyong (supra), which dealt with post 2015 amendment
    scenario, it was observed that an argument to set aside an award on
    the ground of being in conflict with ‘most basic notions of justice’, can
    be raised only in very exceptional circumstances, that is, when the
    conscience of the court is shocked by infraction of some fundamental
    principle of justice. Notably, in that case the majority award created
    a new contract for the parties by applying a unilateral circular, and


44   [1999] Supp. 1 SCR 650 : (2000) 7 SCC 296
45   See paragraph 36 of the judgment in Associate Builders (supra)
[2024] 9 S.C.R.                                                            541

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

       by substituting a workable formula under the agreement by another,
       dehors the agreement. This, in the view of the Court, breached the
       fundamental principles of justice, namely, that a unilateral addition
       or alteration of a contract can never be foisted upon an unwilling
       party, nor can a party to the agreement be liable to perform a bargain
       not entered with the other party.46 However, a note of caution was
       expressed in the judgment by observing that this ground is available
       only in very exceptional circumstances and under no circumstance
       can any court interfere with an arbitral award on the ground that
       justice has not been done in the opinion of the court because that
       would be an entry into the merits of the dispute.
58. In the light of the discussion above, in our view, when we talk about
    justice being done, it is about rendering, in accord with law, what
    is right and equitable to one who has suffered a wrong. Justice is
    the virtue by which the society/ court / tribunal gives a man his due,
    opposed to injury or wrong. Dispensation of justice in its quality may
    vary, dependent on person who dispenses it. A trained judicial mind
    may dispense justice in a manner different from what a person of
    ordinary prudence would do. This is so, because a trained judicial mind
    is likely to figure out even minor infractions of law/ norms which may
    escape the attention of a person with ordinary prudence. Therefore,
    the placement of words “most basic notions” before “of justice” in
    Explanation 1 has its significance. Notably, at the time when the 2015
    Amendment was brought, the existing law with regard to grounds for
    setting aside an arbitral award, as interpreted by this Court, was that
    an arbitral award would be in conflict with public policy of India, if it is
    contrary to: (a) the fundamental policy of Indian law; (b) the interest
    of India; (c) justice or morality; and /or is (d) patently illegal. As we
    have already noticed, the object of inserting Explanations 1 and 2
    in place of earlier explanation to Section 34(2)(b)(ii) was to limit the
    scope of interference with an arbitral award, therefore the amendment
    consciously qualified the term ‘justice’ with ‘most basic notions’ of it.
    In such circumstances, giving a broad dimension to this category47
    would be deviating from the legislative intent. In our view, therefore,
    considering that the concept of justice is open- textured, and notions
    of justice could evolve with changing needs of the society, it would


46   See paragraph 76 of the judgment in Ssyanyong (supra)
47   in conflict with most basic notions of morality or justice
542                                                          [2024] 9 S.C.R.

                              Digital Supreme Court Reports


       not be prudent to cull out “the most basic notions of justice”. Suffice
       it to observe, they48 ought to be such elementary principles of justice
       that their violation could be figured out by a prudent member of the
       public who may, or may not, be judicially trained, which means, that
       their violation would shock the conscience of a legally trained mind.
       In other words, this ground would be available to set aside an arbitral
       award, if the award conflicts with such elementary/ fundamental
       principles of justice that it shocks the conscience of the Court.
       Morality
59. The other ground is of morality. On the question of morality, in
    Associate Builders (supra), this Court, after referring to the
    provisions of Section 23 of the Contract Act, 1872; earlier decision
    of this Court in Gherulal (supra); and Indian Contract Act by Pollock
    and Mulla, held that judicial precedents have confined morality to
    sexual morality. And if ‘morality’ were to go beyond sexual morality,
    it would cover such agreements as are not illegal but would not
    be enforced given the prevailing mores of the day. The court also
    clarified that interference on this ground would be only if something
    shocks the court’s conscience.49
       Patent Illegality
60. Sub-section (2-A) of Section 34 of the 1996 Act, which was inserted
    by 2015 Amendment, provides that an arbitral award not arising out
    of international commercial arbitrations, may also be set aside by the
    Court, if the Court finds that the award is visited by patent illegality
    appearing on the face of the award. The proviso to sub-section
    (2-A) states that an award shall not be set aside merely on the
    ground of an erroneous application of the law or by reappreciation
    of evidence. In Saw Pipes (supra), while dealing with the phrase
    ‘public policy of India’ as used in Section 34, this court took the
    view that the concept of public policy connotes some matter which
    concerns public good and public interest. If the award, on the face
    of it, patently violates statutory provisions, it cannot be said to be in
    public interest. Thus, an award could also be set aside if it is patently
    illegal. It was, however, clarified that illegality must go to the root of



48   most basic notions of justice
49   See paragraph 39 of Associate Builders (supra)
[2024] 9 S.C.R.                                                                                              543

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

       the matter and if the illegality is of trivial nature, it cannot be held
       that award is against public policy.
61. In Associate Builders (supra), this Court held that an award would
    be patently illegal, if it is contrary to:
       (a)     substantive provisions of law of India;
       (b)     provisions of the 1996 Act; and
       (c)     terms of the contract.50
       The Court clarified that if an award is contrary to the substantive
       provisions of law of India, in effect, it is in contravention of Section
       28(1)(a)51 of the 1996 Act. Similarly, violating terms of the contract,
       in effect, is in contravention of Section 28(3) of the 1996 Act.
62. In Ssangyong (supra) this Court specifically dealt with the 2015
    Amendment which inserted sub-section (2-A) in Section 34 of the
    1996 Act. It was held that “patent illegality appearing on the face
    of the award” refers to such illegality as goes to the root of matter,
    but which does not amount to mere erroneous application of law. It
    was also clarified that what is not subsumed within “the fundamental
    policy of Indian law”, namely, the contravention of a statute not
    linked to ‘public policy’ or ‘public interest’, cannot be brought in
    by the backdoor when it comes to setting aside an award on the
    ground of patent illegality.52 Further, it was observed, reappreciation
    of evidence is not permissible under this category of challenge to
    an arbitral award.53



50   See also three-Judge Bench decision of this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd. (2022)
     2 SCC 275
51   Section 28. -- Rules applicable to substance of dispute. — (1) Where the place of arbitration is
     situated in India,--
               (a) In an arbitration other than an international commercial arbitration, the arbitral tribunal shall
                    decide the dispute submitted to arbitration in accordance with the substantive law for the
                    time being in force in India
                    *******
               (2) *****
               (3) while deciding and making an award, the arbitral tribunal shall, in all cases, take into
                    account the terms of the contract and trade usages applicable to the transaction. (As
                    substituted by Act 3 of 2016 w.e.f 23.10.2015)
               Prior to substitution by Act 3 of 2016, sub-section (3) of Section 28 read as under:
               “(3) In all cases, the arbitral tribunal shall decide in accordance with the terms of the contract
               and shall take into account the usages of the trade applicable to the transaction.
52   See paragraph 37 of Ssyangyong (supra)
53   See paragraph 38 of Ssyangyong (supra)
544                                                          [2024] 9 S.C.R.

                            Digital Supreme Court Reports


       Perversity as a ground of challenge
63. Perversity as a ground for setting aside an arbitral award was
    recognized in Western Geco (supra). Therein it was observed that
    an arbitral decision must not be perverse or so irrational that no
    reasonable person would have arrived at the same. It was observed
    that if an award is perverse, it would be against the public policy
    of India.
64. In Associate Builders (supra) certain tests were laid down to
    determine whether a decision of an arbitral tribunal could be
    considered perverse. In this context, it was observed that where: (i)
    a finding is based on no evidence; or (ii) an arbitral tribunal takes
    into account something irrelevant to the decision which it arrives at;
    or (iii) ignores vital evidence in arriving at its decision, such decision
    would necessarily be perverse. However, by way of a note of caution,
    it was observed that when a court applies these tests it does not
    act as a court of appeal and, consequently, errors of fact cannot be
    corrected. Though, a possible view by the arbitrator on facts has
    necessarily to pass muster as the arbitrator is the ultimate master
    of the quantity and quality of evidence to be relied upon. It was also
    observed that an award based on little evidence or on evidence
    which does not measure up in quality to a trained legal mind would
    not be held to be invalid on that score.
65. In Ssangyong (supra), which dealt with the legal position post
    2015 amendment in Section 34 of the 1996 Act, it was observed
    that a decision which is perverse, while no longer being a ground
    for challenge under “public policy of India”, would certainly amount
    to a patent illegality appearing on the face of the award. It was
    pointed out that an award based on no evidence, or which ignores
    vital evidence, would be perverse and thus patently illegal. It was
    also observed that a finding based on documents taken behind the
    back of the parties by the arbitrator would also qualify as a decision
    based on no evidence in as much as such decision is not based on
    evidence led by the parties, and therefore, would also have to be
    characterized as perverse.54



54   See Paragraph 41 of Ssyangyong (supra).
[2024] 9 S.C.R.                                                                545

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

66. The tests laid down in Associate Builders (supra) to determine
    perversity were followed in Ssyanyong (supra) and later approved
    by a three-Judge Bench of this Court in Patel Engineering Limited
    v. North Eastern Electric Power Corporation Limited.55
67. In a recent three-Judge Bench decision of this Court in Delhi Metro
    Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd.,56
    the ground of patent illegality /perversity was delineated in the
    following terms:
             “40. In essence, the ground of patent illegality is available
             for setting aside a domestic award, if the decision of
             the arbitrator is found to be perverse, or so irrational
             that no reasonable person would have arrived at it; or
             the construction of the contract is such that no fair or
             reasonable person would take; Or, that the view of the
             arbitrator is not even a possible view. A finding based on
             no evidence at all or an award which ignores vital evidence
             in arriving at its decision would be perverse and liable to
             be set aside under the head of patent illegality. An award
             without reasons would suffer from patent illegality. The
             arbitrator commits a patent illegality by deciding a matter
             not within its jurisdiction or violating a fundamental principle
             of natural justice.”
      Scope of interference with an arbitral award
68. The aforesaid judicial precedents make it clear that while exercising
    power under Section 34 of the 1996 Act the Court does not sit in
    appeal over the arbitral award. Interference with an arbitral award
    is only on limited grounds as set out in Section 34 of the 1996 Act.
    A possible view by the arbitrator on facts is to be respected as
    the arbitrator is the ultimate master of the quantity and quality of
    evidence to be relied upon. It is only when an arbitral award could
    be categorized as perverse, that on an error of fact an arbitral award
    may be set aside. Further, a mere erroneous application of the law
    or wrong appreciation of evidence by itself is not a ground to set
    aside an award as is clear from the provisions of sub-section (2-A)
    of Section 34 of the 1996 Act.


55   [2020] 4 SCR 156 : (2020) 7 SCC 167
56   [2024] 4 SCR 473 : 2024 INSC 292
546                                                                                   [2024] 9 S.C.R.

                              Digital Supreme Court Reports


69. In Dyna Technologies (supra), a three-Judge Bench of this Court
    held that Courts need to be cognizant of the fact that arbitral awards
    are not to be interfered with in a casual and cavalier manner, unless
    the court concludes that the perversity of the award goes to the root
    of the matter and there is no possibility of an alternative interpretation
    that may sustain the arbitral award. It was observed that jurisdiction
    under Section 34 cannot be equated with the normal appellate
    jurisdiction. Rather, the approach ought to be to respect the finality
    of the arbitral award as well as party’s autonomy to get their dispute
    adjudicated by an alternative forum as provided under the law.
70. Now, we shall examine the scope of interference with an arbitral award
    on ground of insufficient, or improper/erroneous, or lack of, reasons.
       Reasons for the Award – When reasons, or lack of it, could
       vitiate an arbitral award.
71. Section 31 (3)57 of the 1996 Act provides that an arbitral award shall
    state reasons upon which it is based, unless (a) the parties have
    agreed that no reasons are to be given, or (b) the award is an arbitral
    award on agreed terms under Section 30.
       71.1 As to the form of a reasoned award, in Russell on Arbitration
            (24th Edition, page 304) it is stated thus:
                      “6.032. No particular form is required for a reasoned
                      award although ‘the giving of clearly expressed
                      reasons responsive to the issues as they were
                      debated before the arbitrators reduces the scope
                      for the making of unmeritorious challenges’. When
                      giving a reasoned award the tribunal need only set
                      out what, on its view of the evidence, did or did not
                      happen and explain succinctly why, in the light of what
                      happened, the tribunal has reached its decision, and
                      state what that decision is. In order to avoid being
                      vulnerable to challenge, the tribunal’s reasons must
                      deal with all the issues that were put to it. It should
                      set out its findings of fact and its reasoning so as to


57   Section 31. Form and contents of arbitral award. – (1) ….. (2)….
     (3) The arbitral award shall state the reasons upon which it is based, unless –
     (a) the parties have agreed that no reasons are to be given, or
     (b) the award is an arbitral award on agreed terms under section 30.
[2024] 9 S.C.R.                                                             547

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

                enable the parties to understand them and state why
                particular points were decisive. It should also indicate
                the tribunal’s findings and reasoning on issues argued
                before it but not considered decisive, so as to enable
                the parties and the court to consider the position
                with respect to appeal on all the issues before the
                tribunal. When dealing with controversial matters, it
                is helpful for the tribunal to set out not only its view
                of what occurred, but also to make it clear that it has
                considered any alternative version and has rejected
                it. Even if several reasons lead to the same result,
                the tribunal should still set them out. That said, so
                long as the relevant issues are addressed there is
                no need to deal with every possible argument or to
                explain why the tribunal attached more weight to some
                evidence than to other evidence. The tribunal is not
                expected to recite at great length communications
                exchanged or submissions made by the parties. Nor
                is it required to set out each step by which it reached
                its conclusion or to deal with each and every point
                made by the parties. It is sufficient that the tribunal
                should explain what its findings are and the evidential
                route by which it reached its conclusions.
     71.2 On the requirement of recording reasons in an arbitral award
          and consequences of lack of, or inadequate, reasons in an
          arbitral award, this Court in Dyna Technologies (supra) held:
                “34. The mandate under section 31 (3) of the
                Arbitration Act is to have reasoning which is intelligible
                and adequate and, which can in appropriate cases
                be even implied by the courts from a fair reading of
                the award and documents referred to thereunder, if
                need be. The aforesaid provision does not require an
                elaborate judgment to be passed by the arbitrators
                having regard to the speedy resolution of dispute.
                35. When we consider the requirement of a reasoned
                order, three characteristics of a reasoned order
                can be fathomed. They are: proper, intelligible and
                adequate. If the reasonings in the order are improper,
548                                                           [2024] 9 S.C.R.

                       Digital Supreme Court Reports


                  they reveal a flaw in the decision-making process. If
                  the challenge to an award is based on impropriety or
                  perversity in the reasoning, then it can be challenged
                  strictly on the grounds provided in section 34 of the
                  Arbitration Act. If the challenge to an award is based
                  on the ground that the same is unintelligible, the same
                  would be equivalent of providing no reasons at all.
                  Coming to the last aspect concerning the challenge
                  on adequacy of reasons, the court while exercising
                  jurisdiction under section 34 has to adjudicate the
                  validity of such an award based on the degree of
                  particularity of reasoning required having regard to the
                  nature of issues falling for consideration. The degree
                  of particularity cannot be stated in a precise manner
                  as the same would depend on the complexity of the
                  issue even if the court comes to a conclusion that
                  there were gaps in the reasoning for the conclusions
                  reached by the tribunal, the court needs to have
                  regard to the document submitted by the parties
                  and the contentions raised before the tribunal so
                  that awards with inadequate reasons are not set
                  aside in casual and cavalier manner. On the other
                  hand, ordinarily unintelligible awards are to be set
                  aside, subject to party autonomy to do away with the
                  reasoned award. Therefore, the courts are required to
                  be careful while distinguishing between inadequacy
                  of reasons in an award and unintelligible awards.”
       71.3 We find ourselves in agreement with the view taken in Dyna
            Technologies (supra), as extracted above. Therefore, in our
            view, for the purposes of addressing an application to set aside
            an arbitral award on the ground of improper or inadequate
            reasons, or lack of reasons, awards can broadly be placed in
            three categories:
            (1)   where no reasons are recorded, or the reasons recorded
                  are unintelligible;
            (2)   where reasons are improper, that is, they reveal a flaw in
                  the decision- making process; and
            (3)   where reasons appear inadequate.
[2024] 9 S.C.R.                                                                                      549

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

      71.4 Awards falling in category (1) are vulnerable as they would be
           in conflict with the provisions of Section 31(3) of the 1996 Act.
           Therefore, such awards are liable to be set aside under Section
           34, unless (a) the parties have agreed that no reasons are to
           be given, or (b) the award is an arbitral award on agreed terms
           under Section 30.
      71.5 Awards falling in category (2) are amenable to a challenge on
           ground of impropriety or perversity, strictly in accordance with
           the grounds set out in Section 34 of the 1996 Act.
      71.6 Awards falling in category (3) require to be dealt with care.
           In a challenge to such award, before taking a decision the
           Court must take into consideration the nature of the issues
           arising between the parties in the arbitral proceedings and
           the degree of reasoning required to address them. The Court
           must thereafter carefully peruse the award, and the documents
           referred to therein. If reasons are intelligible and adequate on
           a fair-reading of the award and, in appropriate cases, implicit
           in the documents referred to therein, the award is not to be set
           aside for inadequacy of reasons. However, if gaps are such that
           they render the reasoning in support of the award unintelligible,
           or lacking, the Court exercising power under Section 34 may
           set aside the award.
      Scope of interference with the interpretation / construction of
      a contract accorded in an arbitral award.
72. An arbitral tribunal must decide in accordance with the terms of
    the contract. In a case where an arbitral tribunal passes an award
    against the terms of the contract, the award would be patently illegal.
    However, an arbitral tribunal has jurisdiction to interpret a contract
    having regard to terms and conditions of the contract, conduct of the
    parties including correspondences exchanged, circumstances of the
    case and pleadings of the parties. If the conclusion of the arbitrator
    is based on a possible view of the matter, the Court should not
    intefere.58 But where, on a full reading of the contract, the view of


58   See: Steel Authority of India Ltd. v. Gupta Brother Steel Tubes Limited, (2009) 10 SCC 63; Pure Helium
     India (P) Ltd v. ONGC, (2003) 8 SCC 593; McDermott International Inc. v. Burn Standard Co. Ltd., (2006)
     11 SCC 181; MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163
550                                                                               [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       the arbitral tribunal on the terms of a contract is not a possible view,
       the award would be considered perverse and as such amenable to
       interference.59
       Whether unexpressed term can be read into a contract as an
       implied condition.
73. Ordinarily, terms of the contract are to be understood in the way the
    parties wanted and intended them to be. In agreements of arbitration,
    where party autonomy is the grund norm, how the parties worked out
    the agreement, is one of the indicators to decipher the intention, apart
    from the plain or grammatical meaning of the expressions used.60
74. However, reading an unexpressed term in an agreement would be
    justified on the basis that such a term was always and obviously
    intended by the parties thereto. An unexpressed term can be implied
    if, and only if, the court finds that the parties must have intended
    that term to form part of their contract. It is not enough for the court
    to find that such a term would have been adopted by the parties as
    reasonable men if it had been suggested to them. Rather, it must
    have been a term that went without saying, a term necessary to
    give business efficacy to the contract, a term which, although tacit,
    forms part of the contract.61
75. But before an implied condition, not expressly found in the contract,
    is read into a contract, by invoking the business efficacy doctrine, it
    must satisfy following five conditions:
       a.     it must be reasonable and equitable;
       b.     it must be necessary to give business efficacy to the contract,
              that is, a term will not be implied if the contract is effective
              without it;
       c.     it must be obvious that “it goes without saying”;
       d.     it must be capable of clear expression;
       e.     it must not contradict any terms of the contract.62


59   South East Asia Marine Engg. & Construction Ltd. (SEAMEC Ltd.) v. Oil India Ltd., (2020) 5 SCC 164
60   Bharat Aluminium Co. V. Kaiser Aluminium Technical Services Inc., (2016) 4 SCC 126.
61   Adani Power (Mundra) Ltd. v. Gujarat ERC, (2019) 19 SCC 9
62   Nabha Power Limited (NPL) v. Punjab State Power Corporation Limited (PSPCL) and Another, (2018) 11
     SCC 508, followed in Adani Power (supra)
[2024] 9 S.C.R.                                                           551

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     ANALYSIS/ DISCUSSION
76. Having noticed the legal principles governing a challenge to an
    arbitral award, we shall now proceed to address the issues culled
    out above, which arise for our consideration in these appeals.
     GITA POWER (R-2) BOUND BY THE ARBITRATION AGREEMENT
     AND THEREFORE JOINTLY AND SEVERALLY LIABLE
77. To have a clear understanding of the issue as to whether Gita Power
    (R-2), the appellant in the connected appeal, could be subjected to
    arbitral proceedings and made jointly and severally liable along with
    OPG for the dues of Enexio, a look at the facts relating to formation
    of the contract including the conduct of the parties would be apposite.
78. The relevant facts in this regard, which find mention in the award,
    are as follows:
     (a)   There were two companies, namely, Gita Power (R-2) and
           OPG (appellant). Gita Power is the holding company of OPG.
           Two Tenders were floated. One by a Gujarat Company in the
           same group, which related to design, manufacture, delivery
           to site, erection testing and commissioning of two ACC units
           with auxiliaries for a thermal power plant in Gujarat (for short
           Gujarat Unit). The other was issued by OPG in respect of design,
           manufacture, delivery to site, erection testing and commissioning
           of an ACC unit with auxiliaries for a thermal power plant at
           Gummidipoondi in Tamil Nadu (for short T.N. Unit).
     (b)   Enexio (R-1 – the claimant) submitted a single unpriced techno-
           commercial offer covering both projects. Following negotiations,
           a revised techno commercial offer covering both projects
           was submitted in August 2012. Thereafter, following further
           negotiations, another technical offer covering both projects was
           submitted by Enexio on 6 October 2012.
     (c)   On 5 November 2012, with reference to the techno offers, OPG
           addressed a letter to Enexio, in respect of T.N. Unit, stating thus:
                “Design, Engineering, Supply, Installation, Testing
                and Commissioning of Air Cooled Condenser with
                auxiliaries for 1 X 160 MW (Phase III) Coal Based
                Power Project at Gummudipoondi.
552                                                               [2024] 9 S.C.R.

                         Digital Supreme Court Reports


                    We refer to your offer GCTQD/ OPG - Gujarat –
                    Gummidipoondi /4239/12 / Rev 2 dated October 6,
                    2012 and technical and commercial discussions we
                    had with you of date. We have pleasure in informing
                    you of our intent to award a contract for Air Cooled
                    Condenser with auxiliaries in conformance to the
                    discussions you had with us.
                    Price: The price for the total scope is Rs. 44,00,00,000/-
                    (Forty four crores only).
                    Price basis: F.O.R. destination (Power Project site
                    at Gummidipoondi)
                    Taxes and Duties: Extra at actuals, but inclusive of
                    port handling charges.
                    Delivery schedule: The overall agreed time for
                    takeover of equipment will be March 2014.”
       (d)   On 4 March 2013, Gita Power (R-2), holding company of OPG,
             issued two separate Purchase Orders for:
             (i)    Design, Engineering and Supply of 1 Unit of ACC
                    with Auxiliaries for 160 MW Coal Based project at
                    Gummidipoondi (Supply Purchase Order); and
             (ii)   Erection and Commissioning of 1 Unit of ACC with
                    Auxiliaries for 160 MW Coal Based Power project at
                    Gummidipoondi (Erection Purchase Order).
       (e)   Pursuant to these purchase orders, on 1 April 2013 Enexio (R-
             1) submitted a Work Schedule. As per which, commissioning
             of the ACC Unit was planned on 31 March 2014.
       (f)   On 13 June 2013, the foundations for the ACC Unit were handed
             over to Enexio (R-1) by OPG.
       (g)   On 4 July 2013 Enexio received 10% of the Order price and
             on 23 July 2013 second payment of 10% of the Order price
             was received by Enexio. Both payments were made by Gita
             Power (R-2).
[2024] 9 S.C.R.                                                          553

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

      (h)    While the work was in progress, OPG issued two separate
             Purchase Orders, namely, supply purchase order and erection
             purchase order, on similar terms and with similar references as
             were there in the Purchase Orders issued by R-2 (Gita Power).
      (i)    In the statement of defense, it was stated that when the purchase
             orders were ready for issue, since Gita Power (R-2) was the
             holding company of OPG, it was felt that in the commercial
             interest of the project, the order for supply and erection of ACC
             Unit should be placed on the claimant by R-2. The statement of
             defense further states that soon after issuance of the purchase
             orders in the beginning of April 2013, OPG and R-2 were
             advised that as the project was being set up by OPG, and it
             had all the required registrations, etc. it would be advisable
             that the Purchase Orders placed on the claimant by R-2 for
             supply and erection of ACC Unit be substituted/ replaced by
             Purchase Orders in the name of OPG. In addition to above,
             OPG pleaded that the substitution/ replacement of purchase
             orders maintained the continuity of the rights and obligations
             undertaken from 4 March 2013.
79. Based on the above-noted facts, and the evidence brought on record
    during the arbitral proceedings, the Tribunal concluded that the
    ‘Group of Companies’ doctrine is applicable, as OPG and R-2 have
    represented themselves as a single economic entity which could
    switch duties and obligations from one to the other. The Tribunal
    held that – (a) R-2 is a proper party; (b) both OPG and R-2 were
    bound by the arbitration agreements, which gave rise to the arbitral
    proceedings; and (c) OPG and R-2 were jointly and severally liable
    to the claimant for complying with the award.
80. In Cox & Kings Ltd. v. SAP India (P) Ltd.,63 a Constitution Bench of
    this Court held that by interpreting the express language employed
    by the parties in the record of agreement, coupled with surrounding
    circumstances of its formation, performance, and discharge of the
    contract, a Court or Arbitral Tribunal is empowered to determine
    whether a non-signatory is a party to an arbitration agreement. It was
    held that ‘Group of Companies’ doctrine is premised on ascertaining


63   [2023] 15 SCR 621 : (2024) 4 SCC 1
554                                                            [2024] 9 S.C.R.

                       Digital Supreme Court Reports


       the intention of the non- signatory to be party to an arbitration
       agreement. The doctrine requires the intention to be gathered from
       additional factors such as direct relationship with the signatory parties,
       commonality of subject matter, composite nature of the transaction,
       and performance of the contract.
81. In the instant case, the Arbitral Tribunal has found that: (a) Gita
    Power is the holding company of OPG; (b) Gita Power had issued
    the Purchase Orders and had actively participated in the formation
    of the contract even though the ACC unit of Gummudipoondi was
    of OPG; (c) initial 10% of the purchase price was provided by Gita
    Power (R-2); (d) the subsequent Purchase Orders issued by OPG
    were on similar terms and were issued by way of affirmation to obviate
    technical issues. In our view, the above circumstances had a material
    bearing for invocation of “Group of Companies doctrine” to bind Gita
    Power (R-2) with the arbitration agreement and fasten it with liability,
    jointly and severally with OPG, in respect of the Purchase Orders
    relating to ACC Unit of Gummudipoondi project. Thus, bearing in mind
    that an arbitral tribunal has jurisdiction to interpret a contract having
    regard to the terms and conditions of the contract and conduct of the
    parties including correspondences exchanged, and, further, taking
    into account the provisions of sub-section (2-A) of Section 34 of the
    1996 Act limiting the scope of interference with a finding returned
    in an arbitral award, we do not find a good reason to interfere with
    the above findings of the Arbitral Tribunal more so when it is based
    on a possible view of the matter. We, therefore, reject the argument
    on behalf of R-2 that it was not bound by the arbitration agreement
    and that it ought not to have been made jointly and severally liable
    along with OPG for the dues payable to Enexio. Sub-issue (a) is
    decided in the aforesaid terms.
       ENEXIO’S CLAIM NOT BARRED BY LIMITATION.
82. On the issue as to whether Enexio’s claim was barred by time, the
    submissions of the appellants, inter alia, are:
       (a)   The date fixed by the contract for completion of the obligations
             of supply of goods and erection of ACC unit is 31 March 2014.
             Hence, the date of reckoning for the purposes of limitation ought
             to be 31 March 2014.
[2024] 9 S.C.R.                                                                                         555

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

      (b)     The contract was a mixture of supply of goods and services
              (i.e., works). Therefore, Article 14 of the Schedule to the
              1963 Act applied for the price of goods supplied, and Article
              18 applied for the price of works provided, for computing the
              limitation period of the claim. In either case, the limitation
              period of three years would commence to run, not later than,
              from 31 March 2014.
      (c)     Even if it is assumed that the deemed date of completion was
              21 September 2015 (as held by the arbitral tribunal), the claim
              being filed on 2 May 2019, was well beyond 3 years from that
              date.
      (d)     Once the period of limitation started to run, in terms of Articles
              14 and 18, mere negotiations could not have extended the
              period of limitation. Therefore, the award, which takes a contrary
              view, is patently illegal.
83. Before proceeding further, we must remind ourselves that sub-section
    (1) of Section 4364 of the 1996 Act makes the Limitation Act, 1963 (in
    short, 1963 Act) applicable to arbitrations as it applies to proceedings
    in Court. Sub-section (2) of Section 43 provides that unless otherwise
    agreed by the parties, an arbitral proceeding shall be deemed to
    have commenced on the date specified in Section 21.65 On a conjoint
    reading of sub-sections (1) and (2) of Section 43 of the 1996 Act




64   Section 43. Limitations. – (1) The Limitation Act, 1963 (36 of 1963) shall apply to arbitrations as it
     applies to proceedings in Court.
           (2) For the purposes of this section and the Limitation Act, 1963 (36 of 1963), an arbitration shall
     be deemed to have commenced on the date referred in section 21.
           (3) Where an arbitration agreement to submit future disputes to arbitration provides that any claim
     to which the agreement applies shall be barred unless some step to commence arbitral proceedings is
     taken within the time specified by the agreement, and a dispute arises to which the agreement applies,
     the court, if it is of opinion that in the circumstances of the case undue hardship would otherwise be
     caused, and notwithstanding that the time so fixed has expired, may on such terms, if any, as the justice
     of the case may require, extend the time for such period as it thinks proper.
           (4) Where the Court orders that an arbitral award be set aside, the period between the
     commencement of the declaration and the date of the order of the court shall be excluded in computing
     the time prescribed by the Limitation Act, 1963 (36 of 1963), for the commencement of the proceedings
     (including arbitration) with respect to the dispute so submitted.
65   Section 21. Commencement of arbitral proceedings. -- Unless otherwise agreed by the parties, the
     arbitral proceedings in respect of a particular dispute commence on the date on which a request for that
     dispute to be referred to arbitration is received by the respondent.
556                                                                                   [2024] 9 S.C.R.

                              Digital Supreme Court Reports


       along with Sections 366 and 2 (j)67 of the 1963 Act it is clear that if on
       the date of commencement of the arbitral proceeding, as referred to
       in Section 21 of the 1996 Act, the claim(s) is/are barred by limitation,
       as per the provisions of the 1963 Act, the Arbitral Tribunal will have
       to reject such claim(s) as barred by limitation.68
84. In the case in hand there is no dispute between the parties that
    the arbitral proceedings, in terms of Section 21 of the 1996 Act,
    commenced on 2 May 2019. Therefore, our exercise would be to
    determine whether the period of limitation got over prior to that date
    or not. For that purpose, it would be necessary to ascertain as to
    which Article of the Schedule was applicable to the claim. And if
    more than one applied, which one applied to which part of the claim.
85. According to the appellant(s) (i.e., OPG and Gita Power – appellant
    in the connected appeal), Articles 14 and 18 of the Schedule to
    the 1963 Act applied to the claim. Importantly, the award does not
    specify the Article(s) which were applied except Article 58 which
    was applied to the declaratory relief sought in the claim and which
    was found barred by time. However, as the claim is based on a
    contract, we will also consider the applicability of Article 55 and the
    residuary Article 113 of the Schedule,69 if none other Article(s) were
    applicable to the claim.


66   Section 3. — Bar of limitation. – (1) Subject to the provisions contained in sections 4 to 24 inclusive,
     every suit instituted, appeal preferred, and application made after the prescribed period shall be
     dismissed, although limitation has not been set up as a defense.
          (2) For the purposes of this Act –
                (a) a suit is instituted –
                       (i)   in an ordinary case, when the plaint is presented to the proper officer;
                       (ii) in the case of a pauper, when his application for leave to sue as a pauper is
                             made; and
                       (iii) in the case of a claim against the company which is being wound up by the court,
                             when the claimant first sends in his claim to the official liquidator;
                (b) any claim by way of a set-off or a counter claim, shall be treated as a separate suit and
                       shall be deemed to have been instituted –
                       (i)   in the case of a set off, on the same date as the suit in which the set off is
                             pleaded;
                       (ii) in the case of a counter claim, on the date on which the counter claim is made
                             in court;
                (c) an application by notice of motion in a High Court is made when the application is
                       presented to the proper officer of that court.
67   Section 2. Definitions. – In this Act, unless the context otherwise requires, --
                (j)   ‘period of limitation’ means the period of limitation prescribed for any suit, appeal or
                      application by the Schedule, and ‘prescribed period’ means the period of limitation
                      computed in accordance with the provisions of this Act.
68   State of Goa v. Praveen Enterprises, (2012) 12 SCC 581, paragraph 16.
69   The Schedule (PERIODS OF LIMITATION) See sections 2(j) and 3:
     PART II - SUITS RELATING TO CONTRACTS
[2024] 9 S.C.R.                                                                                            557

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

      Facts having material bearing on limitation
86. For a proper determination of the aforesaid issue, we need to have
    a close look at the material facts relevant to the issue of limitation.
    In our view, the material facts,70 inter alia, are:
      (a)     There was a composite Tender inviting offer for design,
              manufacture, delivery to site, erection, testing and commissioning
              of an ACC unit with auxiliaries for a thermal power plant.
      (b)     Enexio submitted a composite unpriced techno-commercial
              offer for the project.
      (c)     On 5 November 2012, with reference to the techno offer, OPG
              addressed a letter71 expressing intent to award contract for the
              project at a composite cost of 44 crores. This letter also sets
              out a tentative date for completion / takeover of the project
              i.e., March 2014.




      Article No.   Description of Suit                Period of Limitation   Time from which period begins
                                                                              to run
      14.           For the price of goods sold        Three years            The date of the delivery of the
                    and delivered where no fixed                              goods
                    period is agreed upon
      18.           For the price of work done by      Three years            When the work is done.
                    the plaintiff for the defendant
                    at his request, where no time
                    has been fixed for payment.
      55.           For compensation for the           Three years            When the contract is broken or
                    breach of any contract,                                   (where there are successive
                    express or implied not herein                             breaches) when the breach
                    specially provided for.                                   in respect of which the suit is
                                                                              instituted occurs or (where the
                                                                              breach is continuing) when it
                                                                              ceases.

     PART III – SUITS RELATING TO DECLARATIONS
      58.           To obtain any other                 Three years           When the right to sue first
                    Declaration                                               accrues.

     PART X – SUITS FOR WHICH THERE IS NO PRESCRIBED PERIOD
      113.          Any suit for which no period of     Three years            When the right to sue
                    limitation is provided elsewhere                           accrues.
                    in this Schedule

70   As gathered from paragraph 7 (including sub paragraphs 7.01 to 7.76) of the Arbitral Award under the
     title ‘Background to the Dispute’
71   Quoted in paragraph 79 (c) above
558                                                             [2024] 9 S.C.R.

                         Digital Supreme Court Reports


       (d)   In that backdrop, on 4 March 2013, Gita Power (R-2) issued
             two separate orders, one, for Design, Engineering and Supply
             of 1 Unit of ACC with Auxiliaries (Supply Purchase Order)
             and, second, for Erection and Commissioning of it (Erection
             Purchase Order).
       (e)   Pursuant to these purchase orders, on 1 April 2013, Enexio (R-
             1) submitted a Work Schedule. As per which, commissioning of
             the ACC Unit was planned on 31 March 2014. In furtherance
             thereof, Enexio received 10% of the order price in advance
             on 4 July 2013, and another 10% on 23 July 2013. Both the
             advance payments were received from Gita Power (R-2).
       (f)   While the work was in progress, in July 2013 OPG issued two
             orders replicating those that were issued by Gita Power (R-2)
             with insignificant variation.
       (g)   As per the Supply Purchase Order, payments were to be made
             in the following order:
             Payments:
             (i)    10% of Order Price as advance money on submission of
                    request for advance and advance payment bank guarantee
                    for 10% of the Order Price, valid until completion of supply;
             (ii)   10% against approval of Engineering Documentation;
             (iii) 65% of the Order Price on Pro Rata basis along with 100%
                   taxes after receipt of material at site;
             (iv) 5% of the Order Price upon submission of (a) invoice, and
                  (b) certificate on completion of punch points duly signed
                  by Parties;
             (v)    5% of the Contract Price upon submission of (a) invoice,
                    (b) take over certificate of Equipment issued by Purchaser;
                    and (iii) warranty bond for 10% of the contract valid up to
                    the end of warranty period;
             (vi) 5% of the Contract Price upon submission of (a) invoice, (b)
                  certificate of completion of performance test of equipment
                  by purchaser;
[2024] 9 S.C.R.                                                         559

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           (vii) Payments to be made within 25 days of submission of
                 invoice/ request for payment and other documents
     (h)   Annexure A of the Supply Purchase Order carried commercial
           conditions, inter alia, providing for Performance Guarantee Test
           in the following terms:
           (1)   The Performance Guarantee Test of the equipment shall be
                 carried out immediately after takeover of the equipment but
                 in no case later than two months from the date of takeover.
           (2)   Performance guarantee test will be carried out by the
                 representatives and manpower of the purchaser under
                 the supervision of the supplier’s engineer.
           (3)   In case the performance guarantee test is not carried out
                 due to reasons outside supplier’s control within 180 days
                 from the date of takeover, the guaranteed performance
                 shall be deemed to have been achieved and all liabilities
                 of supplier with respect to the performance guarantee test
                 shall be over. Within these said 180 days, the supplier
                 remains liable for the guaranteed performance of the
                 equipment.
           (4)   The Erection Purchase Order repeated most of the clauses
                 of the supply purchase order and provided for payment in
                 the following manner:
                 Payment
                 (i)    80% against progress of work on pro rata basis and
                        against certification by site officials.
                 (ii)   10% after mechanical completion / Punch list.
                 (iii) 10% of the contract price after Commissioning against
                       bank guarantee in favor of the owner for equivalent
                       value and valid for the entire warranty period.
     (j)   Enexio (R-1) asserted that it finished its work under the contract
           on or about February 2015. However, on 12 March 2015, OPG
           complained to Enexio in writing that certain work remained
           and, therefore, Enexio must instruct its team to complete the
           pending work.
560                                                             [2024] 9 S.C.R.

                          Digital Supreme Court Reports


       (k)   Enexio claimed that successful operation of the vacuum pump
             was carried out on 21 May 2015, which implies commissioning of
             the ACC unit. In response OPG asserted that three components
             of the ACC unit were defective.
       (l)   On 2 July 2015, OPG issued a debit note towards modifications
             to the turbine generator building. Thereafter, on 24 August
             2015, OPG issued two debit notes: (i) towards work related to
             lifting of the vertical duct; and (ii) towards liquidated damages
             permissible under the Supply Purchase Order and Erection
             Purchase Order for the delay in execution.
       (m) On 28 August 2015 Enexio wrote to OPG questioning the debit
           notes.
       (n)   On 21 September 2015 Enexio informed OPG that the turbine
             generator was running at full load and, thereby, requested OPG
             to arrange for Performance Guarantee Test (PG Test). This
             request was repeated by e-mails dated 3 October 2015 and 8
             October 2015. Later, on 9 October 2015, Enexio sent a letter
             to OPG attaching six protocols confirming commissioning of all
             relevant segments of the project. Not only that, on 20 October
             2015, Enexio sent a procedure for the PG Test. But the PG
             Test was not undertaken.
       (o)   On 12 January 2016, OPG issued debit note against OPG’s
             account for customs duty.
       (p)   On 22 August 2016 OPG informed Enexio that fan assembly
             had detached. On 20 January 2017 Enexio sent an e-mail to
             OPG, saying:
             “Sir,
             This is further to our visit to your site on 7/1/2016.
             Considering the time availability and on the interest
             of closing the issue, we suggest the following:
             1.      Using in-situ machining agency, the shaft dia
                     variation can be machined out after dismantling
                     the hub and blade assembly alone. Gearbox
                     will not be disturbed at all. We already obtained
                     offer for this.
[2024] 9 S.C.R.                                                          561

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

              2.     To match the machined out shaft dia and key
                     way, existing fan hub bore and key way can
                     be rebuild and machined after machining out
                     existing bore by 5mm.
              3.     To start the work, the spare gearbox supplied
                     by us at free of cost can be used and remaining
                     seven gear boxes can be attended one or two
                     at a time.
              4.     You being a valuable customer to us, we wish
                     to execute the correction work even though
                     this failure happened after our guarantee. We
                     will depute our engineer to site for entire work.
              5.     But we could not bear the commercial implications
                     since we already suffered loss and our money
                     is also locked up in this project due to various
                     reasons cited in our various earlier letters.
              6.     Hence, we request you to pay the correction
                     cost and not to deduct the same from us.
              We request you for above proposal.”
      (q)     On 2 March 2017 Enexio requested OPG to provide certificates
              for completion of Gummudipoondi as well as Gujarat project.
              The format of the desired certificate was sent by Enexio to OPG.
              Therein it was mentioned that ACC Unit was commissioned
              during May 2015 and was performing satisfactorily since then.
      (r)     On 6 March 2017 OPG confirmed that it would issue the
              required certificate for marketing purpose and that certificate
              would not absolve the claimant from its contractual obligations
              under the purchase orders which, according to OPG, were yet
              to be fulfilled.
      (s)     Following further exchanges between the parties, a meeting
              was held on 19 April 2018. The minutes72 of that meeting, inter
              alia, reflected that the principal amount outstanding towards
              Enexio under the contract was the one that was claimed by



72   See Paragraph 7 of this judgment.
562                                                          [2024] 9 S.C.R.

                       Digital Supreme Court Reports


             Enexio in the claim. However, the minutes indicated that it was
             not payable because of certain deductions claimed by OPG.
             According to Enexio, those deductions (i.e. towards customs
             duty and liquidated damages) were incorrectly recorded in
             the minutes even though there was no agreement in respect
             thereof.
       (t)   On 26 May 2018, on reiteration of demand by Enexio, OPG
             responded, vide communication dated 26 May 2018, and
             offered Rs.3 crores to Enexio as full and final settlement of
             the account. This offer was rejected by Enexio. Whereafter,
             arbitration proceeding commenced.
       Material Observations in the Award.
87. We shall now extract few observations/ findings in the award which,
    in our view, would be useful in determining the limitation issue. These
    observations/ findings, with their corresponding paragraph number
    in the award, are extracted below:
             “1). On 1st April 2013 the Claimant prepared its L1 Network
             Schedule which indicated the final activities leading to
             commissioning ..:
             Hook up with TG: 8-Mar-14 to 14-Mar-14
             Commissioning 22-Mar-14 to 31-Mar-14.
                                        ……(para 13.02 of the award)
             2). The Purchase Orders are silent on the mode of
             payment of the Claimant’s invoices except to note that:
             7.3. 65% of the Order Price shall be paid on Pro rata
             basis along with 100% Taxes and Duties after receipt of
             material at site.
             7.7 Payments will be made within twenty-five days of
             submission of Invoice/ request for payment and other
             documents.
                                     ….. (para 13.08 (b) of the award)
             3). No indication is given in the Purchase Orders as to
             what ‘other documents are required.
                                      …..(para 13.08 (c) of the award)
[2024] 9 S.C.R.                                                           563

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           4). The claimant asserts that until November 2013 payments
           were made to the claimant initially by Respondent no.2 and
           subsequently by Respondent no.1 by cheque/ RTGS but
           from 12th November 2013 all subsequent payments were
           made by letter of credit. In order to receive payment by this
           method the claimant asserts that additional documentation
           was required which created delays in payment.
                                    ……(para 13.08 (d) of the award)
           5). Respondent no.1 denies that there was delay in clearing
           payments to the claimant and asserts that all payments
           validly due to the claimant were made in time. Respondent
           no.1 asserts that:
           (i)    Invoices were submitted by the claimant later than
                  the date on the face of the invoice;
           (ii)   To compute the period in which payment of an invoice
                  is to be made the start date is the date on which the
                  invoice, complete with all supporting documents, is
                  received by Respondent no.1 which must be after
                  receipt of the relevant material at site; and
           (iii) In many cases, invoices were not accompanied by
                 the required backup documents and the payment of
                 the invoice could not be released until these backup
                 documents were submitted by the claimant.
                                    ……(para 13.08 (e) of the award)
           6). The tribunal accepts that delays by the Claimant in
           submitting its invoices, in providing the backup materials
           and in crediting payment to its account would be included
           in the times computed by the claimant between the date
           of the invoice and the date of payment as included in its
           tabulation of its invoices. However, examination of Exhibit
           C-21 indicates that for invoices paid before 12 November
           2013, over 90%, were paid in less than 50 days from the
           invoice date. Whereas, for invoices paid after 12 November
           only about 30% were paid within 50 days. Indeed, about
           25% of the invoices dated after 12 November 2013 were
           not paid for 100 days or longer. These percentages satisfy
564                                                      [2024] 9 S.C.R.

                  Digital Supreme Court Reports


       the tribunal that the introduction of payment by letter of
       credit, as it was arranged by Respondent no.1, was more
       onerous than could reasonably have been anticipated by
       the claimant when it entered into the contracts.
                                 …..(para 13.08 (g) of the award)
       7). Respondent no.1 decided that the original design of the
       Hot well drain pump was unnecessarily large and changed
       the specified pump to a smaller pump on 21st November
       2013. As a result, both the pump and the electric motor,
       which was required to drive the pump, had to be re-
       ordered. The claimant asserts, and respondent no.1 does
       not deny, that the original pump and motor would have
       been delivered to site on or about 17th February 2014.
                              ……..(para 13.10 (a) of the award)
       8). It was agreed at the hearing in this arbitration that the
       actual delivery date of the motors (which arrived a few
       days after the pump) could be taken as on or about 7th
       May 2014. Thus, there was a delay of approximately 79
       days in delivery.
                               ……(para 13.10 (b) of the award).
       9). On balance, the Tribunal is satisfied that the drain pump
       together with its motor, although a low value component,
       was a necessary part of the ACC unit and the decision
       by Respondent no. 1 to replace it at a late stage risked
       delaying the project. The time elapsed between the original
       estimated delivery date, and the assumed actual delivery
       date was 79 days.
                               …….(para 13.10 (e) of the award)
       10). The tribunal finds the following facts to be significant:
       (i)   The ACC unit could not be connected to the turbine
             generator flange until the turbine generator was in
             place to have the connection made. Thus, welding of
             the ACC unit to the turbine flange was dependent on
             both completion of the horizontal duct and pressure
             balancing bellows by the claimant and the installation
             of the turbine on behalf of Respondent no.1.
[2024] 9 S.C.R.                                                           565

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           (ii)   The ACC unit could not be commissioned, nor could
                  the PG test be conducted without a flow of turbine
                  exhaust steam. The turbine must be operational
                  to provide the necessary flow of exhaust steam.
                  Thus, both commissioning and the PG test were
                  dependent on both the ACC unit and the turbine
                  being operational.
           (iii) Up until the claimant was ready to erect the first
                 part of the horizontal duct there is no evidence that
                 the claimant was delayed by any other construction
                 activity on site. The claimant states that the vertical
                 duct erection was completed on 15th July 2014.
                 The vertical duct should have been completed on
                 7th February 2014. Thus, the tribunal finds that at
                 15th July 2014 the claimant was 158 days behind its
                 program which is not attributable to non-readiness
                 of Respondent no.1.
           (iv) The tribunal is satisfied that steam flowing (steam
                blowing) was being conducted by the turbine
                generator contractor in early February 2015 which
                would have been likely to have prevented the welding
                of the duct to the turbine flange. This process also
                indicates that the turbine was not operational.
           (v)    On the basis of Mr. Parasuram’s evidence, the
                  tribunal finds that the claimant had completed the
                  connection between the horizontal duct and the
                  turbine generator flange around February 2015 but
                  that commissioning of the ACC unit did not start
                  until April 2015. Mr. Parasuram attributes the delay
                  between February and April 2015 to Respondent
                  no.1’s other contractors having outstanding work.
                  Thus, completion of the Hook-up as described in
                  the L1 network Schedule which should have taken
                  place on 14th March 2014 did not take place until
                  mid- February 2015 by which time the ACC unit
                  construction was about 343 days behind schedule.
                  On the evidence presented to the tribunal it is not
                  possible to apportion the further delay of about 158
566                                                       [2024] 9 S.C.R.

                 Digital Supreme Court Reports


            days which occurred between 15th July 2014 and
            mid- February 2015 between slow progress by the
            claimant and hindrance to the claimant’s work by the
            ongoing turbine generator installation. However, the
            tribunal is satisfied that at least part of this delay was
            not attributable to the claimant.
                              ……..(para 13.13 (c) of the award)
       11). The tribunal now considers when, if at all, the ACC
       system was completed. There are three certificates which
       are referred to in the erection purchase order. These are:
       A certificate on competition of punch points;
       A Take Over Certificate of Equipment; and
       A certificate of competition of performance test.
       None of these certificates have been issued.
                             ………(para 13.13 (d) of the award)
       12). The only certificate issued by the respondents was
       dated 2 nd March 2017. In separate correspondence,
       Respondent no.1 stated that this certificate was issued
       for marketing purposes and did not absolve the claimant
       from its contractual obligation under the Purchase Orders.
                              ……..(para 13.13 (e) of the award)
       13). Notwithstanding the respondents’ caveat, the issuance
       by the respondents of the 2nd March 2017 certificate is
       considered significant by the tribunal. The respondents
       knew the purpose for which the certificate was required
       by the claimant and, if it did not believe in the veracity
       of what it was certifying, even for marketing purposes,
       then it behaved dishonestly. The tribunal has no basis
       for assuming that the respondents would have acted in
       such a dishonest manner and thus, concludes that the
       respondents must have believed that the ACC unit was
       operating satisfactorily when it issued that certificate.
       The certificate states that the ACC unit was operating
       satisfactorily from May 2015. However, the tribunal does
[2024] 9 S.C.R.                                                            567

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           not rely on this date as it was not material to the purpose
           for which the certificate was required and was the date
           included in the draft certificate provided by the claimant.
                                 ……….(para 13.13 (f) of the award)
           14). The tribunal concludes that all the criteria for issuing
           all three of the certificates listed above would have to
           be met before the ACC unit could be certified to be
           operating satisfactorily. The last alleged defects notified
           by Respondent no.1 in 2015, which has been exhibited,
           is dated 4th July 2015. (The fan assembly detached
           more than a year later, and that event could not have
           been the basis for withholding the relevant certificates
           through 2015). In its e-mail of 4th July 2015, Respondent
           no.1 notes gearbox defects but gave no details nor is the
           tribunal provided with any information about what action,
           if any, was taken in relation to the alleged gearbox defect.
           However, the tribunal is satisfied that on 4th July 2015 the
           ACC units were not yet in fit condition to merit the issue
           of the three relevant certificates.
                                 ……….(para 13.13 (g) of the award)
           15). The first indication that the claimant thought it was
           ready for a performance guarantee test was in its e-mail
           dated 21st September 2015. There is no evidence to
           suggest that both the certificate on completion of punch
           points and takeover certificate of equipment should not
           have been issued on or before 21st September 2015. In
           the absence of any evidence from Respondent no.1 that
           there were any remaining punch points or that the ACC
           system was not capable of being taken over, the tribunal
           finds that these certificates are deemed to have been
           issued on 21st September 2015 a delay from the planned
           date of 539 days.
                                    ……(para 13.13 (h) of the award)
           16). Equally, there is no further indication that the ACC unit
           was not capable of passing the PG test on 21st September
           2015. However, a PG test can only be deemed satisfactory
568                                                      [2024] 9 S.C.R.

                  Digital Supreme Court Reports


       if it is not carried out within 180 days of the issue of the
       taking over certificate. Accordingly, the PG test would
       be deemed to have been carried out satisfactorily only
       after a further 180 days had elapsed. Thus, the tribunal
       finds that the deemed achievement of Supplier’s liability
       in respect to Performance Guarantee Test pursuant to
       Clause 10.5 of Annexure A of the Erection Purchase
       Order only became effective on 19th March 2016. As
       the claimant was still requesting a PG test as late as
       20th May 2016 the tribunal is satisfied that the deeming
       provisions apply and the ACC unit is deemed to have
       passed the PG test. The Erection Purchase Order states
       that, where the PG test is deemed to have been carried
       out, the respondents remained liable for the guaranteed
       performance during the 180 days. However, it is silent on
       whether the deemed achievement of supplier’s liability in
       respect to Performance Guarantee test is retrospective
       to the date when the performance can be said to have
       been achieved. The tribunal finds that for the purposes
       of determining the delay caused by the failure to arrange
       a PG test it would be just to consider that the required
       performance was achieved on 21st September 2015 - the
       date on which the tribunal has found that the ACC unit
       was deemed to have been taken over.
                              ………(para 13.13 (i) of the award)
       17). Respondent no.1 did not issue the takeover certificate of
       equipment or a certificate of completion nor did it arrange a
       PG test. However, it has offered no evidence of any defects
       in the ACC unit that it has shown existed on 21st September
       2015. Accordingly, the tribunal is satisfied, on the balance
       of probabilities, that respondent no.1 delayed issuing the
       said certificates and the PG test because it was not in a
       position, due to other factors beyond the Claimant’s control,
       to properly commission the ACC unit. Therefore, the tribunal
       is satisfied that at 21st September 2015, Respondent no.1
       had delayed completion by 539 days and the claimant is
       entitled to 539 days’ extension of time.
                            …………(para 13.13 (j) of the award)
[2024] 9 S.C.R.                                                         569

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           18). Summary of Delays

           Delay in payment                            Nil
           Delay in handing over site                  Nil
           Due to change of specification
           of the Drain Pump                           79 days
           Delay in BBU approval                       Nil
           Staircase and pipe rack
           Hindrance                                   Nil
           Non-readiness of
           Respondent no.1                             539 days
           The tribunal finds that these delays are not cumulative but
           parallel. The effect of the drain pump being changed would
           have occurred before mid-February 2014 when the tribunal
           found that the project was delayed by 158 days. Thus, the
           delay at that point for which the claimant was responsible
           was 158 days less 79 days allowed for the change of drain
           pump. Thus, the claimant was in culpable delay of 79 days
           in mid-February. The delay in commissioning occurred
           after mid-February 2014. Thus, the total extension of time
           granted by the tribunal is 539 days.
                                      …….(para 13.14 of the award)
           19). Liquidated Damages
           As the tribunal has granted an extension of time for
           completion of the ACC unit to 21st September 2015 and
           has also found that the requirements for completion of the
           ACC units were achieved on that date, the tribunal finds
           that the claimant has no liability for liquidated damages….
                                     ……(para 13.15 of the award)”
     Relevant Article(s) of the Schedule to the Limitation Act, 1963
     applicable to the claim
88. Having taken note of the relevant facts as well as material observations
    in the arbitral award, we shall now consider as to which Article, or
    Articles(s), if more than one is applicable, of the Schedule to the
    1963 Act would apply to the claim(s) of Enexio. Notably, the claim
570                                                                                      [2024] 9 S.C.R.

                               Digital Supreme Court Reports


       was in respect of: (a) declaration qua invalidity of Debit note(s); (b)
       outstanding principal amount; and (c) interest. Insofar as relief qua
       declaration was concerned, it was found barred by time prescribed
       by Article 58, and there is no serious challenge to that finding. As
       regards claim for the outstanding principal amount, it was a composite
       claim for the balance amount payable for supplies made and work
       done under the Supply Purchase Order and the Erection Purchase
       Order respectively, which was found within limitation.
89. According to the appellant(s), Article 14 is applicable to the claim
    in respect of balance amount for the price of the goods supplied
    under the Supply Purchase Order; and Article 18 would apply to
    the claim for the work done under the Erection Purchase Order. It is
    their case that if the project was to be completed by 31 March 2014,
    three years period should be counted from that date and, therefore,
    claim would be barred by limitation as on 2 May 2019 i.e., the date
    of commencement of the arbitral proceeding.
90. Per contra, Enexio’s case is that it is a composite contract for design,
    manufacture, supply, erection and commissioning of air-cooled
    condenser unit (ACC Unit) with auxiliaries for 160 MW Coal Based
    Thermal Power Plant (Project) at Gummidipoondi in the State of
    Tamil Nadu whereunder payments were to be made on pro rata
    basis, and final payment was to be made only on completion of the
    work, subject to issuance of relevant certificates. The completion
    of work got delayed due to reasons beyond the control of Enexio,
    as held by the Tribunal, therefore, 539 days of extension, up to the
    deemed date of completion of the project i.e., 21 September 2015,
    was granted. In between, the contract was not repudiated by either
    party. Hence, the limitation period of three years would have to
    be counted from the date of completion of the work, that is, from
    21 September 2015. It is also their case that before expiry of the
    prescribed period of three years, a written acknowledgment of the
    outstanding amount was made vide minutes of the meeting dated 19
    April 2018. Therefore, by virtue of Section 1873 of the 1963 Act, a fresh


73   Section 18. Effect of acknowledgment in writing.— (1) Where, before the expiration of the prescribed
     period for a suit or application in respect of any property or right, an acknowledgement of liability in
     respect of such property or right has been made in writing signed by the party against whom such
     property or right is claimed, or by any person through whom he derives his title or liability, a fresh period
     of limitation shall be computed from the time when the acknowledgment was so signed.
     (2) Where the writing containing the acknowledgement is undated, oral evidence may be given of the
[2024] 9 S.C.R.                                                                                          571

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

       period of three years would start from the date of acknowledgement,
       which got further extended, by virtue of the provisions of Section
       1974 of the 1963 Act, on account of the offer made on 26 May 2018
       to pay Rs. 3 crores as full and final settlement of all dues. Hence,
       as on 2 May 2019, the claim was not barred by limitation.
91. A plain reading of Article 14 of the Schedule to the 1963 Act, which
    is pari materia Article 5275 of the First Schedule to the Limitation
    Act, 1908 (in short 1908 Act), would indicate that it applies where:
    (a) the suit/ claim is for the price of goods sold and delivered;
    and (b) no fixed period of credit is agreed upon. Whereas Article
    18 of the Schedule, which is pari materia Article 5676 of the First
    Schedule of the 1908 Act, applies where: (a) the suit/claim is for
    the price of work done by the plaintiff/ claimant for the defendant
    at his request; and (b) no time has been fixed for payment. Thus,
    where a suit is for goods supplied and work done by the plaintiff
    (a contractor) and the price of materials and the price of work is
    separately mentioned, and the time for payment is not fixed by the
    contract, Article 14 will apply to the former claim, and Article 18 to
    the latter. But where a claim is made for a specific sum of money
    as one indivisible claim on the contract, without mentioning any


     time when it was signed; but subject to the provisions of the Indian Evidence Act, 1872 (1 of 1872), oral
     evidence of its content shall not be received.
           Explanation.-- for the purposes of this section, --
                (a) an acknowledgement may be sufficient though it omits to specify the exact nature
                       of the property or right, or avers that the time for payment, delivery, performance or
                       enjoyment has not yet come or is accompanied by a refusal to pay, deliver, perform or
                       permit to enjoy, or is coupled with a claim to set off, or is addressed to a person other
                       than a person entitled to the property or right;
                (b) the word ‘signed’ means signed either personally or by an agent duly authorized in
                       this behalf; and
                (c) an application for the execution of a decree or order shall not be deemed to be an
                       application in respect of any property or right.
74   Section 19. Effect of payment on account of debt or of interest on legacy.--- Where payment on
     account of a debt or of interest on a legacy is made before the expiration of the prescribed period by the
     person liable to pay the debt or legacy or by his agent duly authorized in this behalf, a fresh period of
     limitation shall be computed from the time when the payment was made:
            Provided that, save in the case of payment of interest made before the 1st day of January, 1928, an
            acknowledgement of the payment appears in the handwriting of, or in writing signed by, the person
            making the payment.
            Explanation. — For the purposes of this section, --
                  (a) where mortgage land is in the possession of the mortgagee, the receipt of the rent or
                        produce of such land shall be deemed to be a payment;
                  (b) ‘debt’ does not include money payable under a decree or order of a court.
75   See Footnote 83
76   See Footnote 84
572                                                                            [2024] 9 S.C.R.

                            Digital Supreme Court Reports


       specific sum as being the price of goods or price of the work done,
       neither Article 14 nor Article 18 will apply, but only Article 55, which
       provides for all actions ex contractu (i.e., based on a contract) not
       otherwise provided for, would apply.77
92. Article 55, which is a combination of erstwhile Articles 11578 and 11679
    of the First Schedule to the 1908 Act, is a residuary Article in respect
    of all actions based on a contract not otherwise specially provided
    for. For the applicability of Article 55, four requirements should be
    satisfied, namely, (1) the suit should be based on a contract; (2)
    there must be breach of the contract; (3) the suit should be for
    compensation; and (4) the suit should not be covered by any other
    Article specially providing for it.
93. A breach of a contract may be by non-performance, or by repudiation
    or by both.80 In Anson’s Law of Contract (29th Oxford Edition), under the
    heading ‘Forms of Breach Which Justify Discharge’, it is stated thus:
              “The right of a party to be treated as discharged from further
              performance may arise in any one of three ways: the other
              party to the contract (a) may renounce its liabilities under
              it; (b) may by its own act make it impossible to fulfil them,
              (c) may fail to perform what it has promised. Of these
              forms of breach, the first two may take place not only in
              the course of performance but also while the contract is
              still wholly executory i.e., before either party is entitled to
              demand a performance by the other of the other’s promise.
              In such a case the breach is usually termed an anticipatory
              breach. The last can only take place at or during the time
              for performance of the contract.”
94. Thus, failure of a party to a contract in performing its obligation(s)
    thereunder could be considered a breach of contract for the purpose
    of bringing an action against it by the other party. In such an event,
    the other party can claim compensation or damages, or/ and, in
    certain cases, obtain specific performance.


77   See U. N. Mitra’s Law of Limitation and Prescription, Sixteenth Edition, Volume 1, at page 1063,
     published by LexisNexis.
78   See Footnote 86
79   See Footnote 87
80   P. Ramanatha Aiyar’s Advanced Law Lexicon, 4th Edition at page 596
[2024] 9 S.C.R.                                                                                       573

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

95. The phrase ‘compensation for breach of contract’, as occurring in
    Article 55 of the Schedule to the 1963 Act, would comprehend also
    a claim for money due under a contract. ‘Compensation’ is a general
    term comprising any payment which a party would be entitled to
    claim on account of any loss or damage arising from a breach of a
    contract, and the expression has not been limited only to a claim for
    unliquidated damages. The expression is wide enough to include a
    claim for payment of a certain sum.81
96. In Mahomed Ghasita v. Siraj-ud-Din and others,82 the plaintiff
    was to supply Italian marble and other stone required for flooring
    and was also to do all the work necessary for constructing the floor.
    The plaintiff sued for the balance of the money due to him based
    on this contract and the plaint made no mention of the price of the
    materials as distinct from the price of the work. The matter came
    before a Full Bench of the then Lahore High Court. Before the Full
    Bench the question was, what Article of the Limitation Act, 1908 is
    applicable to the suit. Sir Shadi Lal C.J., as His Lordship then was,
    speaking for the Bench held:
                “The action brought by the plaintiff was for the recovery
                of the balance of the money due to him on the strength
                of the contract described above; and the question for
                consideration is what article of the Limitation Act governs
                the claim. Our attention has been invited, in the first
                instance, to article 52,83 which prescribes a period of
                three years (enlarged to six years by the Punjab Loans
                Limitation Act of 1904) for the recovery of the price of
                goods sold and delivered to the defendant; and also to
                article 56,84 which lays down a period of three years for a
                suit to recover the price of work done by the plaintiff for


81   See U. N. Mitra’s Law of Limitation and Prescription, Sixteenth Edition, Volume 2, at pages 1342 & 1343,
     published by LexisNexis.
82   AIR 1922 Lah 198 (FB) : ILR (1921) 2 Lah 376 (FB) : 1921 SCC OnLine Lah 303
83   First Schedule of Limitation Act, 1908
      Article     Description of Suit                     Period of Limitation      Time from which
                                                                                    Period begins to run
      52          For the price of goods sold and         Three years               The date of the
                  delivered, where no fixed period of                               delivery of the goods.
                  credit is agreed upon.

84   First Schedule of Limitation Act, 1908
574                                                                             [2024] 9 S.C.R.

                               Digital Supreme Court Reports


                 the defendant. Now, as stated above, the plaintiff supplied
                 not only the materials, but also the labour, and it is clear
                 that neither of the aforesaid articles governs the suit in
                 its entirety. It is, however, urged that the action comprises
                 two claims, one for the price of the material supplied by
                 the plaintiff, and the other relating to the price of the work
                 done by him, and that these two claims should be dealt
                 with separately, and that they are governed by article 52
                 and article 56, respectively. The rule of law is no doubt
                 firmly established that a combination of several claims
                 in one action does not deprive each claim of its specific
                 character and description. The Code of Civil Procedure
                 allows a plaintiff, in certain circumstances, to combine in
                 one action two or more distinct and independent claims,
                 and it is quite possible that one of the claims may be
                 barred by limitation, and the other may be within time;
                 though both of them arise out of one and the same cause
                 of action. In a case of that description there is no reason
                 why the court should not apply to each claim the rule of
                 limitation specially applicable thereto. It is nowhere laid
                 down that only one article should govern the whole of the
                 suit, though it may consist of several independent claims,
                 and that the suit should not be split up into its component
                 parts for the purpose of the law of limitation.
                 The question, however, is whether the action as brought by
                 the plaintiff can be treated as a combination of two distinct
                 claims. Now, the plaint makes no mention of the price of
                 the materials as distinct from the price of the work and
                 contains no reference whatsoever to two claims. There is
                 only one indivisible claim, and that is for the balance of
                 the money due to the plaintiff on the basis of a contract,
                 by which he was to be paid for everything supplied and



       Article     Description of Suit                  Period of Limitation   Time from which
                                                                               Period begins to run
       56          For the price of work done by the    Three years            When the work is
                   plaintiff for the defendant at his                          done.
                   request where no time has been
                   fixed for payment.
[2024] 9 S.C.R.                                                                                   575

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

                done by him in connection with the flooring of the building
                at a comprehensive rate. The claim, as laid in the plaint is
                an indivisible one; it cannot be split up into two portions.
                We must, therefore, hold that it falls neither under article
                52, nor under article 56.
                The learned advocate for the plaintiff contends that as
                neither of the above articles governs the claim, it should
                come within article 120.85 The judgment in Radha Kishen
                v. Basant Lal, which is relied upon in support of this
                contention, no doubt, related to a suit for the recovery of
                a sum of money alleged to be due for the work performed
                and material supplied by the plaintiff to the defendant under
                a contract, and the learned judges held that neither article
                52 nor article 56 was applicable to the entire claim. They
                then made the following observation –
                      “There is no other articles specially applicable,
                      and hence the only article which can be applied
                      is article 120.”
                Now with all deference to the learned judges we are
                unable to hold that there is no other article governing
                a claim of that character. It seems that their attention
                was not drawn to article 115,86 which governs every


85   First Schedule of Limitation Act, 1908
      Article      Description of Suit                   Period of Limitation   Time from which
                                                                                Period begins to run
      120          Suit for which no period of           Six years              When the right to sue
                   limitation is provided elsewhere in                          accrues.
                   this Schedule.

86   First Schedule of Limitation Act, 1908
      Article      Description of Suit                   Period of Limitation   Time from which
                                                                                Period begins to run
      115          For compensation for the breach       Three years            When the contract
                   of any contract, express or                                  is broken, or (where
                   implied, not in writing registered                           there are successive
                   and not herein specially provided                            breaches) when the
                   for.                                                         breach in in respect
                                                                                of which the suit is
                                                                                Instituted occurs, or
                                                                                (where the breach is
                                                                                continuing) when it
                                                                                ceases.
576                                                                                 [2024] 9 S.C.R.

                                 Digital Supreme Court Reports


                 suit for compensation for the breach of a contract not in
                 writing registered and not specially provided for in the
                 Limitation Act. It is beyond doubt that this article is a
                 general provision applying to all actions ex contractu not
                 specially provided for otherwise; and the present claim
                 certainly arises out of a contract entered into between
                 the parties. The word ‘compensation’ in article 115 as
                 well as in article 11687 has the same meaning as it has
                 in section 7388 of the Indian Contract Act and denotes
                 a sum of money payable to a person on account of
                 the loss or damage caused to him by the breach of a
                 contract. It has been held, and we consider rightly, that
                 a suit to recover a specified sum of money on a contract
                 is a suit for compensation within articles 115 and 116
                 --- vide Nobocoomar Mookhopadhaya v. Siru Mullick89
                 and Husain Ali Khan v. Hajiz Ali Khan.90
                 We are accordingly of opinion that the present claim must
                 be regarded as one for compensation for the breach of
                 a contract, and that there is no special provision in the


87   First Schedule of Limitation Act, 1908
       Article      Description of Suit               Period of Limitation   Time from which        Period
                                                                             begins to run
       116          For compensation for the          Six years              When the period of limitation
                    breach of a contract in writing                          would begin to run against
                    registered.                                              a suit brought on a similar
                                                                             contract not registered.

88   The Indian Contract Act, 1872.
          Section 73. Compensation for loss or damage caused by breach of contract.-- When a
          contract has been broken, the party who suffers by such breach is entitled to receive, from the
          party who has broken the contract, compensation for any loss or damage caused to him thereby,
          which naturally arose in the usual course of things from such breach, or which the parties knew,
          when they made the contract, would be likely to result from the breach of it.
          Such compensation is not to be given for any remote and indirect loss or damage sustained by
          reason of the breach.
          Compensation for failure to discharge obligation resembling those created by contract.---
          When an obligation resembling those created by contract has been incurred and has not been
          discharged, any person injured by the failure to discharge it is entitled to receive the same
          compensation from the party in default, as if such person had contracted to discharge it and had
          broken his contract.
          Explanation.-- In estimating the loss or damage arising from a breach of contract, the means which
          existed of remedying the inconvenience caused by the non-performance of the contract must be
          taken into account
89   (1890) ILR 6 Cal 94
90   (1881) ILR 3 All 600 (FB)
[2024] 9 S.C.R.                                                                                    577

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

                Act which governs the claim. It must, therefore, come
                under the general provision contained in article 115, which
                governs every action arising out of contract, not otherwise
                specially provided for.”
                                                                   (Emphasis supplied)
97. In Dhapia v. Dalla91 before a Full Bench of the Allahabad High Court
    the question was, what Article of the First Schedule to the 1908
    Act would apply to a suit for recovery of a specified sum under a
    contract. In that suit, the plaintiff had made defendant(s) partner to
    one half of the fishery rights in the tank arising from a Theka, on
    the condition that they would pay him half the Theka money. The
    allegations made in the plaint showed that the defendant(s) had
    already worked out the Theka in respect of their share in it. As that
    suit was not filed within three years from the date of breach, it was
    dismissed by the trial court as barred by limitation by applying Article
    11592 of the First Schedule to the 1908 Act. The plaintiff preferred
    appeal, which was allowed on the finding that Article 12093 of the
    First Schedule to the 1908 Act applied, whereunder the limitation
    was six years. When the matter travelled to the High Court, an
    argument was raised that neither Article 115 nor Article 120 could
    apply, rather Article 11394 would apply. It was contended before the
    High Court that Article 113 should apply as the claim is nothing but
    for specific performance. Rejecting this submission and holding
    that Article 115 of the First Schedule to 1908 Act would apply, the
    Full Bench held:
                “8. In our opinion there is no force in this argument. It is true
                that there was a contract between the parties inasmuch as
                the plaintiff gave to the defendants one half of the fishery


91   1969 All LJ 718 : AIR 1970 All 206 : 1969 SCC OnLine All 79
92   See Footnote 86
93   See Footnote 85
94   First Schedule of Limitation Act, 1908
      Article     Description of Suit      Period of Limitation     Time from which Period begins
                                                                    to run
      113         For specific             Three years              The date fixed for the performance,
                  performance of                                    or, if no such date is fixed, when
                  contract                                          the plaintiff has notice that
                                                                    performance is refused.
578                                                      [2024] 9 S.C.R.

                  Digital Supreme Court Reports


       rights in the tank, on the condition that they would pay
       him half the theka money. The allegations made in the
       plaint show that the defendants had already worked out
       the theka in respect of their share in it. All that remained
       to be done was to pay the proportionate theka money
       to the plaintiff. In such circumstances no suit for specific
       performance of contract could be filed: only a suit to enforce
       the agreement so far as it related to the payment of the
       proportionate theka money could be, and has been filed.
       9. The relevant portion of section 12 of the Specific Relief
       Act (Act 1 of 1877) reads as follows:
            “… The specific performance of any contract
            may in the discretion of the court be enforced—
            (a)   When the act agreed to be done is in the
                  performance, wholly or partly, of a trust;
            (b)   When there exists no standard for
                  ascertaining the actual damages caused
                  by the non-performance of the act agreed
                  to be done;
            (c)   When the act agreed to be done is such
                  that pecuniary compensation for its non-
                  performance would not afford adequate
                  relief, or
            (d)   When it is probable that pecuniary
                  compensation cannot be got for the
                  non- performance of the act agreed to be
                  done……”
       10. A suit for the recovery of a specified sum under a
       contract cannot be said to be a suit of the nature where
       pecuniary compensation would not afford adequate relief.
       We are, therefore, of the opinion that the suit out of which
       this civil revision arises cannot be said to be a suit for
       the specific performance of a contract and will not be
       governed by Article 113 of the First Schedule to the Indian
       Limitation Act, 1908
                            xxxxx        xxxxx
[2024] 9 S.C.R.                                                              579

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

               13. We now proceed to consider why Article 115 of the
               First Schedule to the Limitation Act should apply to the
               facts of the present case. Article 115 applies when there is
               a breach of contract, and suit is for compensation for the
               loss suffered by the innocent party. A breach of contract
               ‘occurs where a party repudiates or fails to perform one or
               more of the obligations imposed upon him by the contract’:
               (vide Cheshire and Fifoot, p 484). ‘If one of two parties
               to a contract breaks the obligation which the contract
               imposes, a new obligation will in every case arise – a
               right of action conferred upon the party injured by the
               breach’ (vide Anson’s Law of Contract, p 412). Admittedly,
               in the present case, there was a contract and according
               to the plaintiff and the findings of the court a breach of
               contract had occurred inasmuch as the defendants failed
               to pay the stipulated amount upon the date fixed under
               the contract.
               14. Difficulty can, however, be caused by the word
               ‘compensation’ used in Article 115. It can be argued that
               the words compensation for breach of contract point
               rather to a claim for unliquidated damages than to the
               payment of a certain sum, and, therefore, where the suit
               is for the recovery of a specified sum, and not for the
               determination of unliquidated damages, this article should
               not apply. In our opinion this contention would be wholly
               untenable because it was not accepted by this court in
               the Full Bench case of Hussain Ali Khan versus Hafiz Ali
               Khan95 and by the Privy Council in the case of Tricomdas
               Coovarji Bhoja versus Sri Gopinath Jiu Thakur.96 In the
               case of Husain Ali Khan Article 116 of Schedule II of
               the Limitation Act (Act XV of 1877) was the subject of
               interpretation. Articles 115 and 116 of Schedule II of Act
               XV of 1877 have been reproduced verbatim in the Indian
               Limitation Act, 1908. Article 115 deals with the breach of
               contracts not in writing and registered while Article 116
               provided for breach of contracts in writing and registered.


95   I.L.R. 3 All 600
96   AIR 1916 PC 182
580                                                     [2024] 9 S.C.R.

                 Digital Supreme Court Reports


       It is, therefore, obvious, that the meaning which has to be
       given to the words ‘compensation for breach of contract’
       occurring in both the Articles will have to be the same.
                      xxx          xxx          xxx
       16. In the case of Tricomdas Cooverji Bhoja the argument
       that the words ‘compensation for breach of a contract’
       point rather to a claim of unliquidated damages than to
       the claim of payment of certain sum was not accepted
       because the word compensation has been used in the
       Indian Contract Act in a very wide sense.
       17. The relevant portion of section 73 of the Indian
       Contract Act reads as follows:
            ‘73. When a contract has been broken, the party
            who suffers by such breach is entitled to receive,
            from the party who has broken the contract,
            compensation for any loss or damage caused to
            him thereby, which naturally arose in the usual
            course of things from such breach, or which the
            parties knew, when they made the contract, to
            be likely to result from the breach of it.
            Such compensation is not to be given for any
            remote and indirect loss or damage sustained
            by reason of the breach……
            Illustrations
            ………………..
            (n) A contracts to pay a sum of money to B on
            a day specified. A does not pay the money on
            that day; B, in consequence of not receiving the
            money on that day is unable to pay his debts,
            and is totally ruined. A is not liable to make
            good to B anything except the principal sum
            he contracted to pay, together with interest up
            to the day of payment.’
       18. It is, therefore, clear that the word compensation has
       been used, in section 73 of the Indian Contract Act in a very
       wide sense and the present case would be covered by it.
[2024] 9 S.C.R.                                                              581

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

              19. We see no reason why the words ‘compensation for
              breach of contract’ as used in Article 115 should be given
              a meaning different from the same words as used in Article
              116. Article 115 being a residuary Article for suits based
              on breach of contract, it is obvious that the suit out of
              which this revision arises would be governed by the said
              Article.”
                                                        (Emphasis supplied)
98. On a consideration of the aforesaid decisions as well as the provisions
    of Section 73 of the Contract Act and Article 55 of the Schedule to
    the 1963 Act, we are of the view that even a suit for recovery of a
    specified amount, based on a contract, is a suit for compensation,
    and if the suit is a consequence of defendant breaching the contract
    or not fulfilling its obligation(s) thereunder, the limitation for institution
    of such a suit would be covered by Article 55 of the Schedule to
    the 1963 Act, provided the suit is not covered by any other Article
    specially providing for it.
99. In the instant case, there is no dispute that the claim is based on a
    contract. The finding of the Arbitral Tribunal in paragraph 13.13 (i)97
    of the award is that the appellant(s) herein had failed to undertake
    the performance guarantee test, despite request of the claimant,
    within the period specified therefor. The final payment of the bill(s)
    / invoice(s) was dependent on issuance of certificate(s) including
    one relating to successful completion of the performance guarantee
    test (PG Test). Further, the contract provided that if the performance
    guarantee is not undertaken by the purchaser (appellant(s) herein),
    it could be deemed that the supplier (claimant -R-1) had fulfilled
    its obligation of providing a guaranteed performance of the project
    under the contract. In these circumstances, when, despite request of
    the contractor /supplier, the employer/ purchaser failed to undertake
    the PG Test, the Arbitral Tribunal justifiably concluded that even
    though the supplier (claimant) had fulfilled its obligations under the
    contract, the purchaser (appellant(s) herein) had failed in fulfilling its
    obligation of making payment of the outstanding principal amount to
    the claimant, which had become due and payable under the contract.
    In our view, therefore, the claim being one for ‘compensation’ (which


97   Extracted in paragraph 88 (16) of this judgment.
582                                                           [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       term includes a specified outstanding amount), based on breach of
       a contract, the limitation for the claim would fall within the ambit of
       Article 55 of the Schedule to the 1963 Act unless demonstrated that
       the claim is specially covered by any other Article of the Schedule.
100. In Geo Miller (supra)98 a three-Judge Bench of this Court held that
     in a commercial dispute, though mere failure to pay may not give
     rise to a cause of action, once the applicant has asserted their claim
     and the respondent fails to respond to such claim, such failure will
     be treated as a denial of the applicant’s claim giving rise to a dispute
     and, therefore, a cause of action for reference to arbitration would
     come into existence. It was also observed that it would not lie in
     the mouth of the claimant to plead that it waited to refer the dispute
     to arbitration because it was making representations and sending
     reminders to the respondent to settle the matter.
101. In Major (Retd.) Inder Singh Rekhi v. Delhi Development
     Authority,99 in the context of commencement of the period of
     limitation for making a reference application under Section 20 of
     the erstwhile Arbitration Act, 1940, it was held by this Court that
     to be entitled to have an order of reference under Section 20, it
     is necessary that there should be an arbitration agreement and
     secondly, differences must arise to which the agreement applied.
     Once there is an assertion of claim by the appellant and silence as
     well as refusal in respect of the same by the respondent, a dispute
     would arise regarding non-payment of the alleged dues. The Court
     thereafter went on to observe:
              “4. ……. The High Court proceeded on the basis that the
              work was completed in 1980 and therefore, the appellant
              became entitled to the payment from that date, and the
              cause of action under article 137 arose from that date.
              But in order to be entitled to ask for the reference under
              section 20 of the Act there must not only be an entitlement
              to money but there must be a difference, or dispute must
              arise. It is true that on completion of the work a right to
              get payment would normally arise but where the final bills
              as in this case have not been prepared as appears from


98   See paragraph 29 of the judgment in Geo Miller (supra)
99   (1988) 2 SCC 338
[2024] 9 S.C.R.                                                            583

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

              the record and when the assertion of the claim was made
              on 28.2.1983 and there was non- payment, the cause of
              action arose from that date, that is to say, 28.2.1983. It
              is also true that a party cannot postpone the approval of
              cause of action by writing reminders or sending reminders
              but where the bill had not been finally prepared, the claim
              made by a claimant is the accrual of the cause of action.
              A dispute arises where there is a claim and a denial
              and repudiation of the claim. The existence of dispute is
              essential for appointment of an arbitrator under Section 8
              or reference under section 20 of the Act. There should be
              dispute and there can only be a dispute when a claim is
              asserted by one party and denied by the other on whatever
              grounds. Mere failure or inaction to pay does not lead to
              the inference of the existence of dispute. Dispute entails
              a positive element and assertion of denying, not merely
              inaction to accede to a claim or a request. Whether in
              a particular case a dispute has arisen or not has to be
              found out from the facts and circumstances of the case.”
102. Interpreting the decision of this Court in Inder Singh Rekhi (supra),
     in B & TG AG (supra) it was, inter alia, held that three principles of
     law are discernible from the aforesaid decision: (1) ordinarily, on the
     completion of the work, the right to receive the payment begins; (2)
     a dispute arises when there is a claim on one side and its denial/
     repudiation by the other; and (3) a person cannot postpone the accrual
     of cause of action by repeatedly writing letters, or sending reminders.
     In other words, bilateral discussions for an indefinite period would
     not save the situation so far as the accrual of cause of action and
     the right to apply for appointment of arbitrator is concerned.
103. In the case in hand, the award reveals that in respect of payment of
     Claimant’s invoices, the Purchase Orders provided that 65% of the
     Order Price was to be paid on pro rata basis along with 100% taxes
     and duties after receipt of material at site, within 25 days of submission
     of Invoice/ request for payment, and other documents.100 The award
     recites that there is no indication in the Purchase Orders as to what



100 Paragraph 13.08 (b) of the Award
584                                                                          [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       ‘other documents’ were required.101 Not only that, payment, including
       balance payment, was dependent on issuance of: (i) certificate on
       completion of punch points signed by parties; (ii) take over certificate
       of equipment (to be issued by the Purchaser); and (iii) certificate of
       completion of performance test of equipment (to be issued by the
       Purchaser).102 But none of these certificates was issued.103 In these
       circumstances, the Arbitral Tribunal had to consider various facts and
       circumstances to come to a definite conclusion that the work was
       completed on 21 September 2015. In holding so, Tribunal relied on:
       (a) an e-mail sent by the claimant on 21 September 2015 showing
       its readiness to a performance guarantee test; and (b) the fact that
       there was no evidence to suggest that the certificates on completion,
       as ought to have been issued, should not have been issued on or
       before 21 September 2015.104 The Tribunal also took note of the
       terms and conditions of the contract which were to the effect that the
       performance guarantee test can be deemed satisfactory if, despite
       request, it is not carried out within 180 days of the issue of the taking
       over certificate. The Tribunal noticed that vide certificate dated 2 March
       2017 the appellant(s) admitted that unit was commissioned in May
       2015 and there was a request of the claimant dated 21 September
       2015 to undertake performance guarantee test.105 Taking all of this
       into account, the Tribunal held that the “deemed achievement of
       supplier’s liability in respect to performance guarantee”, pursuant to
       clause 10.5 of Annexure A of the Erection Purchase Order, became
       effective on 19 March 2016.106
104. From the discussion thus far, following dates emerge which, in our
     view, would be relevant for determining the start point of limitation
     for the claim:
       (a)    21 September 2015 i.e., the deemed date of completion of the
              supply/ work undertaken by the claimant under the Purchase
              Orders/ contract; and


101 Paragraph 13.08 (c) of the Award
102 Paragraph 7.32 of the Award
103 Paragraph 13.13 (d) of the Award
104 Paragraph 13.13 (h) of the Award.
105 See Paragraph 88 (16) above including paragraph 13.13 (f) of the Award.
106 Paragraph 13.13 (i) of the Award.
[2024] 9 S.C.R.                                                           585

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     (b)   19 March 2016 i.e., the deemed date by which the supplier
           (Claimant) had fulfilled its liability under the contract relating to
           guaranteed performance of the Unit concerned.
105. Now, we shall consider whether Articles 14 and 18 of the Schedule
     to the 1963 Act were applicable or not. Article 14 applies where
     the suit is for the price of the goods sold and delivered, and
     there is no fixed period of credit agreed upon. Here, there is an
     indivisible claim in respect of the outstanding principal amount for
     the goods supplied and the work done. Moreover, the payment(s)
     under the supply purchase order were to be on pro rata basis,
     and full payment for the supplies was dependent on supporting
     documents, including certificates, to be provided by the purchaser,
     which were not provided. Thus, when full payment(s) under the
     supply/erection purchase order(s) were dependent on certificates
     relating to completion/ commissioning /guaranteed performance
     etc., the claimant waited till successful completion / commissioning /
     guaranteed performance of the project to file a composite claim for
     the balance amount payable under both the purchase orders. In our
     view, therefore, Article 14 is not applicable to the claim as framed.
106. Insofar as Article 18 is concerned, it is to apply where the suit is
     for the price of the work done by the plaintiff for the defendant at
     his request, and where no time has been fixed for payment. In the
     instant case, there is an indivisible claim for the outstanding amount
     in respect of goods supplied and the work done. As already noticed
     above, the payment(s) under the contract were to be made on pro
     rata basis, dependent on work done and certificates issued, which,
     as per the finding in the award, were not issued. Hence, the claimant
     was entitled to make a composite claim for the goods supplied and
     the work done after the project was successfully complete i.e., when
     the Unit was commissioned followed by guaranteed performance.
     Because it is only then, when the outstanding amount, as per the
     Bills / Invoices raised, became due and payable to the claimant
     in terms of the contract. Thus, in our view, Article 18 would also
     not apply.
107. As it is not demonstrated that any other Article of the Schedule
     specially providing for the claim, as was made by R-1, was applicable,
     in our view, Article 55 of the Schedule was applicable to the claim,
     inter alia, for the following reasons:
586                                                             [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       (a)    The claim was for compensation (in as much as the term
              ‘compensation’ includes a specified amount payable under a
              contract107) in respect of the goods supplied and the work done
              under a contract; and
       (b)    The claim was based on a breach of the contractual obligation
              as, according to the findings returned by the Arbitral Tribunal,
              the respondents to the claim (appellant(s) herein) had failed to
              fulfil their obligation(s) of making payment of the outstanding
              principal amount payable under the contract despite raising of
              bills / invoices by the claimant.
       Starting Point of Limitation for the Claim
108. Having determined that limitation for the claim would be governed by
     Article 55 of the Schedule to the 1963 Act, we shall now ascertain
     the date from which the limitation period is to be counted.
109. Under Article 55, the limitation period begins to run when the contract
     is broken or where there are successive breaches, when the breach
     in respect of which the suit is instituted occurs, or where the breach
     is continuing, when it ceases.
110. In the case in hand, it is nobody’s case that either party repudiated
     the contract. Further, the claim is not in respect of non-payment of
     any specific bill or invoice during execution of the contract. Rather,
     it is for the outstanding principal amount due to the claimant on
     discharge of his obligations under the contract. No doubt, list of
     unpaid bills / invoices was placed on record of the arbitral proceedings
     to demonstrate that bills / invoices were raised / issued, but the
     same was by way of evidence to support the claim, which was for
     the entire outstanding principal amount payable to the claimant on
     discharge of its obligations under the contract. Thus, simply put, the
     cause of action for the claim in question is appellant(s)’ failure to
     make payment of the outstanding principal amount to the claimant
     despite discharge of contractual obligations by it.
111. At this stage, we would like to put on record that nothing was brought
     to our notice that there was any fixed date, or period of credit, for
     payment of the balance amount. In the above circumstances, in
     our view, the starting point of limitation should be the date when


107 See our discussion in paragraphs 96 to 98 of this judgment
[2024] 9 S.C.R.                                                            587

               OPG Power Generation Private Limited v.
      Enexio Power Cooling Solutions India Private Limited & Anr.

     the claimant had fulfilled all its obligations under the contract and
     was entitled for release of the outstanding amount payable under
     the contract.
112. As per the contract, if, after takeover, the purchaser (appellant(s)
     herein) fails to undertake the performance guarantee test, within 180
     days from the date of request for it by the supplier (i.e., claimant), it
     is to be deemed that the supplier has fulfilled its liability in respect of
     the guaranteed performance. Apparently, passing the performance
     guarantee test was last of the supplier’s (claimant’s) obligations,
     whereafter the supplier was entitled for release of the balance amount.
     The Tribunal has found: (a) that as per certificate dated 2 March
     2017, the commissioning took place in May 2015; (b) at that time
     there were certain technical issues, which were resolved later; (c)
     on 21 September 2015, claimant sent request to the appellant(s) to
     undertake performance guarantee test, but there was no response
     to the request; and (d) the period of 180 days, counted from 21
     September 2015, expired on 19 March 2016. In the light of the above
     findings, the Tribunal concluded that commissioning took place in the
     month of May 2015; technical issues were resolved by 21 September
     2015; and performance guarantee period expired on 19 March 2016.
113. Based on the above, while bearing in mind that final payment of
     the principal outstanding amount was dependent on meeting the
     requirement of performance guarantee, in our view, the cause of
     action for the claim, as made, matured on expiry of that stipulated
     period of 180 days within which, despite request, the appellant(s)
     (i.e., purchaser) failed to undertake the performance guarantee test.
     Thus, even though there might be several bills/ invoices raised/
     issued by the claimant during execution of the contract, the claim
     of the claimant for the outstanding principal amount matured on
     expiry of 180 days from the date of the notice given by the claimant
     to the appellant(s) (i.e., respondents to the claim) to undertake the
     performance guarantee test. We, therefore, conclude that limitation
     for the claim started to run from 19 March 2016.
114. At this stage, we may notice, only to reject, an alternative submission
     made on behalf of the appellant, which is, that if Article 55 was
     applicable, the breach of the contract occurred when the claimant
     failed to complete the project by 31 March 2014, as promised,
     therefore, the period of limitation should be counted from that date.
588                                                          [2024] 9 S.C.R.

                           Digital Supreme Court Reports


       This argument, in our view, is not sustainable, because time was
       not the essence of the contract in as much as there was a clause
       for liquidated damages for delay in completion (See Clause 13 of
       Annexure A of the Supply Purchase Order as extracted in paragraph
       7.32 of the award). Moreover, there is no material on record to
       indicate that the contract was repudiated by the appellant on any
       date for non-completion of the project by the date stipulated. Rather,
       the materials on record, as recited in the award, indicate that parties
       continued to engage with each other and accepted performance of
       contractual obligations even beyond the stipulated date. Further,
       there is a clear finding in the award that the claimant was entitled
       to extension of 539 days. For the above reasons, we reject the
       alternative submission made on behalf of the appellant(s).
       Limitation Extended by Acknowledgement dated 19.04.2018
       under Section 18 of the 1963 Act
115. As the limitation period of three years prescribed by Article
     55, if counted from 19 March 2016, expired before the date of
     commencement of the arbitral proceeding (i.e., 2 May 2019), we will
     have to consider whether, by virtue of acknowledgment, if any, the
     claimant was entitled to extension of the period of limitation.
116. Section 18108 of the 1963 Act deals with the effect of acknowledgement
     in writing. Sub-section (1) thereof provides that where, before the
     expiration of the prescribed period for a suit or application in respect
     of any right, an acknowledgement of liability in respect of such right
     has been made in writing signed by the party against whom such
     right is claimed, a fresh period of limitation shall be computed from
     the time when the acknowledgment was so signed. The Explanation
     to this section provides that an acknowledgment may be sufficient
     though it omits to specify the exact nature of the right or avers that
     the time for payment has not yet come or is accompanied by a
     refusal to pay, or is coupled with a claim to set off, or is addressed
     to a person other than a person entitled to the right.
117. In Khan Bahadur Shapoor Fredom Mazda v. Durga Prasad
     Chamaria and others109 while dealing with Section 19 of the 1908
     Act, which is pari materia Section 18 of the 1963 Act, this Court held


108 See Footnote 73
109 [1962] 1 SCR 140 : AIR 1961 SC 1236
[2024] 9 S.C.R.                                                            589

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     that for a valid acknowledgement, under the provision, the essential
     requirements are: (a) it must be made before the relevant period
     of limitation has expired; (b) it must be in regard to the liability in
     respect of the right in question; and (c) it must be made in writing
     and must be signed by the party against whom such right is claimed.
     In paragraph 6 of the judgment, it was observed:
           “6. ….. The statement on which a plea of acknowledgement
           is based must relate to a present subsisting liability though
           the exact nature or the specific character of the said
           liability may not be indicated in words. Words used in the
           acknowledgment must, however, indicate the existence
           of jural relationship between the parties such as that of
           debtor and creditor, and it must appear that the statement
           is made with the intention to admit such jural relationship.
           Such intention can be inferred by implication from the
           nature of the admission, and need not be expressed in
           words. If the statement is fairly clear then the intention
           to admit jural relationship may be implied from it. The
           admission in question need not be express but must
           be made in circumstances and in words from which the
           court can reasonably infer that the person making the
           admission intended to refer to a subsisting liability as
           at the date of the statement. In construing words used
           in the statements made in writing on which a plea of
           acknowledgment rests oral evidence has been expressly
           excluded but surrounding circumstances can always be
           considered. Stated generally courts lean in favor of a liberal
           construction of such statements though it does not mean
           that where no admission is made one should be inferred,
           or where a statement was made clearly without intending
           to admit the existence of jural relationship such intention
           could be fastened on the maker of the statement by an
           involved or far-fetched process of reasoning……
           7. …… The effect of the words used in a particular
           document must inevitably depend upon the context in which
           the words are used and would always be conditioned by
           the tenor of the said document…….”
                                                  (Emphasis supplied)
590                                                           [2024] 9 S.C.R.

                           Digital Supreme Court Reports


118. In J.C. Budhraja v. Chairman Orissa Mining Corporation Ltd.
     and Others,110 following the decision in Khan Bahadur Shapoor
     (supra), a three-Judge Bench of this Court held:
             “21. It is now well settled that a writing to be an
             acknowledgement of liability must involve an admission
             of a subsisting jural relationship between the parties
             and a conscious affirmation of an intention of continuing
             such relationship in regard to an existing liability. The
             admission need not be in regard to any precise amount
             nor by expressed words. If a defendant writes to the
             plaintiff requesting him to send his claim for verification
             and payment, it amounts to an acknowledgment. But if
             the defendant merely says, without admitting liability, it
             would like to examine the claim or the accounts, it may
             not amount to acknowledgment. In other words, a writing,
             to be treated as an acknowledgement of liability should
             consciously admit his liability to pay or admit his intention
             to pay the debt. Let us illustrate. If a creditor sends a
             demand notice demanding payment of Rs.1,00,000 due
             under a promissory note executed by the debtor and
             the debtor sends a reply stating that he would pay the
             amount due, without mentioning the amount, it will still be
             an acknowledgment of liability. If a writing is relied on as
             an acknowledgement for extending the period of limitation
             in respect of the amount or right claimed in the suit, the
             acknowledgement should necessarily be in respect of the
             subject matter of the suit. If a person executes a work and
             issues a demand letter making a claim for the amount due
             as per the final bill and the defendant agrees to verify the
             bill and pay the amount, the acknowledgement will save
             limitation for a suit for recovery of only such bill amount,
             but will not extend the limitation in regard to any fresh or
             additional claim for damages made in the suit, which was
             not a part of the bill or the demand letter. ……….. What
             can be acknowledged is a present subsisting liability. An



110 [2008] 1 SCR 821 : (2008) 2 SCC 444
[2024] 9 S.C.R.                                                                 591

                 OPG Power Generation Private Limited v.
        Enexio Power Cooling Solutions India Private Limited & Anr.

               acknowledgement made with reference to a liability, cannot
               extend limitation for a time-barred liability or a claim that
               was not made at the time of acknowledgement or some
               other liability relating to other transactions. Any admission
               of jural relationship in regard to the ascertained sum due
               or a pending claim, cannot be an acknowledgment for a
               new additional claim for damages.
                                                           (Emphasis supplied)
119. In the instant case, as found above, the limitation period started
     to run from 19 March 2016. Within three years therefrom, in
     the minutes of meeting dated 19 April 2018111 there was a clear
     acknowledgement that the amount claimed by Enexio (as is there in
     the claim) is the balance amount payable, though subject to debit,
     by way of set off, against various claims made by the appellant(s)
     herein upon the claimant. In our view, such an acknowledgment
     is sufficient to extend the limitation period as it admits the existing
     liability of the appellant(s) qua the balance amount payable to the
     claimant under the contract. Benefit of such an acknowledgement
     would not be lost merely because a set off is claimed, inasmuch
     as clause (a) of the Explanation to Section 18, inter alia, provides
     that an acknowledgement for the purposes of this Section may be
     sufficient though it is accompanied by a refusal to pay, or is coupled
     with a claim to set off. This would imply that, subject to fulfilment of
     other conditions of Section 18, once the defendant acknowledges
     that he owes a certain sum to the plaintiff there would be sufficient
     acknowledgment within the meaning of Section 18, even though he
     states that he is entitled to set off against this sum another sum which
     the plaintiff owes him. Thus, in our view, the minutes of meeting dated
     19 April 2018, though claims a set off, is a valid acknowledgement
     of the existing liability within the ambit of Section 18 of the 1963 Act
     and it extends the period of limitation for a period of 3 years from
     the date it was made. In consequence, the claim of Enexio, made
     on 2 May 2019, was well within the period of limitation. Sub-issue
     (b) is decided in the aforesaid terms.



111   Minutes are quoted in paragraph 7 of this judgment
592                                                               [2024] 9 S.C.R.

                              Digital Supreme Court Reports


       APPELLANT(S) COUNTERCLAIM IN RESPECT OF COST OF
       REPAIR/ REPLACEMENT OF GEAR BOX AND FAN MODULES
       BARRED BY TIME
120. Now, we shall consider whether the counterclaim was barred by
     limitation. Before that, we must understand the true nature of a
     counterclaim. A counterclaim is a claim made by a defendant in a
     suit against the plaintiff. It is a claim, independent of and separable
     from the plaintiff’s claim, which can be enforced by a cross action.
     Counterclaim preferred by the defendant in a suit is a cross suit
     and even if the suit is dismissed, counterclaim shall remain alive for
     adjudication. The purpose of the scheme relating to counterclaim is
     to avoid multiplicity of proceedings.112
121. In Afcons Gunanusa JV (supra), after considering a plethora
     of precedents and authoritative texts, this Court summarized the
     legal principles relating to counterclaims, in the context of arbitral
     proceedings, as under:
               “168. On our analysis of the statutory framework of the
               Arbitration Act and the CPC, related academic discourse
               and judicial pronouncements, the following conclusions
               emerge:
               (i)    Claims and counter-claims are independent and
                      distinct proceedings;
               (ii)   A counter-claim is not a defense to a claim and its
                      outcome is not contingent on the outcome of the
                      claim;
               (iii) Counter-claims are independent claims which could
                     have been raised in separate proceedings but are
                     permitted to be raised in the same proceeding as a
                     claim to avoid a multiplicity of proceedings; and
               (iv) the dismissal of proceedings in relation to the original
                    claim does not affect the proceedings in relation to
                    the counter-claim.”




112 Rajni Rani v. Khairati Lal, (2015) 2 SCC 682, paragraph 9.6.
[2024] 9 S.C.R.                                                                                           593

                 OPG Power Generation Private Limited v.
        Enexio Power Cooling Solutions India Private Limited & Anr.

122. Section 23 (2A)113 of the 1996 Act gives respondent to a claim a right
     to submit a counterclaim or plead a set off, which shall be adjudicated
     upon by the arbitral tribunal, if such counterclaim or set off falls within
     the scope of the arbitration agreement. Section 43 (1)114of the 1996
     Act provides that the 1963 Act shall apply to arbitrations as it applies
     to proceedings in court. Section 3(2)(b)115 of the 1963 Act provides
     that any claim by way of set off or a counterclaim, shall be treated
     as a separate suit and shall be deemed to have been instituted –
     (i) in the case of a set off, on the same date as the suit in which
     the set off is pleaded; (ii) in the case of a counterclaim, on the date
     on which the counterclaim is made in court. It is thus clear that a
     counterclaim is to be treated as a separate suit for the purposes of
     limitation and, to ascertain whether it is within limitation, the date of
     reckoning is the date when the counterclaim is filed and not when
     the claim/ suit is filed. At this stage, it be noted that Section 21 of
     the 1996 Act is not relevant for determining the date of institution of
     a counterclaim as it is for a claim. There is however one exception.
     Where the respondent against whom a claim is made, had also
     made a claim against the claimant and sought arbitration by serving
     a notice to the claimant but subsequently raises that claim as a
     counterclaim in the arbitration proceedings initiated by the claimant,
     instead of filing a separate application under Section 11 of the 1996
     Act, the limitation for such counterclaim should be computed, as on
     the date of service of notice of such claim on the claimant and not
     on the date of filing of the counterclaim.116
123. In Thomas Mathew v. KLDC Ltd.117 this Court, in the context
     of a claim referable to Article 55 of the Schedule to the 1963
     Act, by relying on Section 3 (2)(b) of the 1963 Act, held that a


113 Section 23. Statement of claim and defence.—
    (1) …..
    (2) …..
    (2-A) The respondent, in support of his case, may also submit a counter-claim or plead set-off, which
    shall be adjudicated by the arbitral tribunal, if such counter-claim or set-off falls within the scope of the
    arbitration agreement.
114 See Footnote 64
115 See Footnote 66
116 See State of Goa v. Praveen Enterprises, (2012) 12 SCC 581, paragraph 20; and Voltas Ltd. v. Rolta
    India Ltd., (2014) 4 SCC 516.
117 (2018) 12 SCC 560, paragraph 9
594                                                                               [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       counterclaim is required to be treated as a separate suit and the
       period of limitation would be three years from the date of accrual
       of the cause of action.
124. It is therefore well settled that a counterclaim is like a cross suit, or a
     separate suit, and the limitation of a counterclaim is to be counted from
     the date of accrual of the cause of action which it seeks to espouse.
     As a logical corollary thereof, it is quite possible that even though a
     suit or a claim is within the period of limitation, the counterclaim may
     well be barred by limitation, if the cause of action espoused therein
     accrued beyond the prescribed period of limitation.
125. In the instant case, the counterclaims were for: (a) liquidated
     damages for the delay in supply and erection; (b) reimbursement of
     customs duties; (c) cost of erection of horizontal and vertical exhaust
     duct through an external agency; (d) cost of repair/ replacement of
     Gear Box, due to alleged defective supply; and (e) cost of repair/
     replacement of Fan Modules, due to alleged defective supply. Out of
     the above five counterclaims, three counterclaims, namely, (a), (b)
     and (c), were dealt by the Arbitral Tribunal on merits, as they stood
     recited in the minutes of meeting dated 19 April 2018. Whereas
     the remaining two, namely, (d) and (e), were treated as barred by
     limitation because in respect thereof there was no recital / material
     to show that they were subject matter of negotiation between the
     parties. The counterclaim (a) (i.e., relating to liquidated damages
     for the delay) was rejected because the Tribunal found the claimant
     entitled to extension of time as the ACC Unit project envisaged
     Hook-up / connection to the turbine generator flange which could
     took place only in February 2015 as turbine generator installation,
     which was being done by another contractor employed by OPG, got
     delayed.118 The counterclaim (b) (i.e., reimbursement of customs
     duties) was rejected because, according to the Tribunal, as per the
     Supply Purchase Order, all Taxes, duties and levies were to be borne
     by the purchaser (appellant(s) herein).119 Insofar as counterclaim
     (c) was concerned, it was allowed and the counterclaimant was
     allowed set off in respect thereof. The summary of how each of the
     counterclaims were dealt with, is found in paragraph 17 of the Award.


118 See paragraphs 13.13 (c) and 13.15 of the Award, extracted in 88 (10) and 88 (19) above.
119 Paragraph 14 of the Award.
[2024] 9 S.C.R.                                                         595

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

126. We have, therefore, to consider whether the two counterclaims (d)
     and (e) were justifiably held time-barred or not. More particularly,
     because claimant’s claim which arose out of same contract was
     found within limitation.
127. Since counterclaim is to be treated as a separate suit or a cross-suit,
     its limitation would have to be determined independent of the claim,
     based on the cause of action espoused therein. Therefore, we would
     have to determine as to when the right to seek for the counterclaims
     (d) and (e) accrued. In this context, while dealing with the previous
     issue i.e., regarding the claim being within limitation, we noticed a
     few dates which, in our view, would be helpful in determining the
     present issue. These dates are:
     (a)   May 2015 - when ACC Unit got commissioned and was operating
           satisfactorily, as per certificate dated 2 March 2017 issued by
           OPG.
     (b)   21 September 2015 – deemed date of takeover of the project
           i.e., when all alleged defects were removed by the claimant,
           and a request was made by the claimant to the purchaser
           (appellant(s) herein) to undertake performance guarantee test.
     (c)   19 March 2016 – when the period of 180 days of guaranteed
           performance expired. This date is important because, as per
           the contract, if, within the aforesaid period, the performance
           guarantee test is not undertaken, despite request of the supplier,
           it is to be deemed that the supplier has discharged its liability
           of a guaranteed performance of 180 days.
128. The Tribunal takes 21 September 2015 as the start point of limitation
     for the counterclaim on the premise that it would be the date when
     the Takeover Certificate is deemed to have been issued. That is, the
     supplier had fulfilled its obligations. On basis thereof, the Tribunal
     found counterclaims (d) and (e) barred by time as the counterclaim
     was filed on 15 July 2019 i.e., more than three years later, and there
     existed no acknowledgement in respect thereof.
129. However, while dealing with the previous issue, we found 19 March
     2016 as the start point of limitation for the claim because that is the
     date when 180 days period of guaranteed performance, which was
     part of supplier’s liability, expired. Be that as it may, whether we
     count the limitation period from 21 September 2015 or 19 March
596                                                                                   [2024] 9 S.C.R.

                              Digital Supreme Court Reports


       2016, the counterclaim which was filed on 15 July 2019 was beyond
       the prescribed period of three years inasmuch as its cause of action
       could not have arisen after 19 March 2016 because by 19 March
       2016, the supplier / contractor had fulfilled its obligation of guaranteed
       performance for 180 days.
       Minutes of meeting dated 19 April 2018 did not extend limitation
       of counterclaims (d) and (e)
130. In these circumstances, the question that falls for our consideration
     is whether the minutes of meeting dated 19 April 2018 extended the
     period of limitation for counterclaim(s)120 (d) and (e) as it did for the
     claim as well as counterclaims (a) (b) and (c). The contention on behalf
     of the appellant(s) is that the claim and the counterclaim arose out of
     same contractual relationship, therefore, if the acknowledgment dated
     19 April 2018 extends limitation of one part of the claim/ counterclaim,
     it would automatically extend limitation of the remaining part of the
     claim / counterclaim. Per contra, learned counsel for Enexio (R-1)
     contended that there could be multiple claims arising out of the same
     contract, if the acknowledgment extending limitation under Section
     18 of 1963 Act relates to only few, limitation for the rest would not
     get extended. Thus, the Tribunal committed no such error which may
     warrant interference under Section 34 of the 1996 Act.
131. We have given our thoughtful consideration to the rival submissions.
     The minutes of meeting dated 19 April 2018 was drawn within three
     years of accrual of the cause of action for the claim, whether we
     count limitation from 19 March 2016 (as determined by us) or 21
     September 2015 (as determined by the Tribunal). Therefore, the
     crucial question, which we must consider and decide, is whether those
     minutes could be considered as an acknowledgment of subsisting
     liability qua counterclaims (d) and (e).
132. The minutes121 of meeting dated 19 April 2018 incorporates a table
     giving specific description of the items and their corresponding value
     on which parties, purportedly, admitted their respective liabilities.
     Interestingly, the balance amount payable to the contractor (Enexio -
     R-1) finds mention there and so does contractor’s liability towards



120 For description of counterclaims (a) to (e), see paragraph 126 of this judgment.
121 Extracted in paragraph 7 of this judgment
[2024] 9 S.C.R.                                                                             597

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

       liquidated damages, customs duty, dismantling – TG Building and
       ACC Duct fabrication, which have all been addressed on merits in the
       Award. But, there is no mention of items referable to counterclaims
       (d) and (e), which have been held time barred. Further, the minutes
       do not state that parties acknowledge, or are willing to settle, any
       other, or all their rights/ obligations, arising from, or under, the
       contract. Thus, the acknowledgment is specific and in respect of
       certain items only.
133. In J.C. Budhraja (supra) this Court held that a writing to be an
     acknowledgement of liability must involve an admission of a subsisting
     jural relationship between the parties and conscious affirmation of an
     intention of continuing such relationship regarding existing liability.
     The Court added that the admission need not be in respect of any
     precise amount nor by expressed words. However, it was clarified
     that any admission of jural relationship in regard to a certain sum
     due, or a pending claim, cannot be an acknowledgement for a new
     additional claim for damages.122 That apart, in J.C. Budhraja (supra),
     this Court rejected an argument that if there was acknowledgment of
     any liability in regard to a contract, then one was at liberty to make
     any claim in regard to the contract. Relevant portion of the judgment
     is extracted below:
              “27. The appellant next contended, relying on Section 18 of
              the Limitation Act, that as there was acknowledgement of
              liability in regard to Contract no. 30/F-2 in the letter dated
              28-10-1978, and the notice invoking arbitration was issued
              on 4-6-1980 within three years from 28-10-1978, he was at
              liberty to make any claim in regard to the contract before
              the arbitrator even though such claims had not been made
              earlier and all such claims have to be treated as being
              within the period of limitation. Such a contention cannot
              be countenanced. As noticed above, the cause of action
              arose on 14-4-1977. But for the acknowledgement on 28-
              10-1978, on the date of invoking arbitration 4-6-1980, the
              claims could have been barred by time as being beyond
              the period of limitation. The limitation is extended only in
              regard to the liability which was acknowledged in the letter


122 See paragraph 21 of J.C. Budhraja (supra) extracted in paragraph 119 of this judgment.
598                                                            [2024] 9 S.C.R.

                            Digital Supreme Court Reports


              dated 28-10-1978. It is not in dispute that either on 28-10-
              1978 or on 4-3-1980, the contractor had not made the fresh
              claims aggregating to Rs.67,64,488 and the question of
              such claims made in future for the first time on 27-6-1986,
              being acknowledged by OMC on 28-10-1998 did not arise.”
                                                    (Emphasis supplied)
134. On the question of extension of limitation, where only a part of the
     liability, or a specific amount, is acknowledged during the period of
     limitation, there are long-standing decisions of various High Courts
     upholding the same principle as is discernible from the decision in
     J.C. Budhraja (supra). Some of these decisions are being noticed
     below.
135. In Bans Gopal v. Mewa Ram123 in the context of applicability of
     Section 19 of the 1908 Act, which is pari materia Section 18 of the
     1963 Act, the question before the Allahabad High Court was, whether
     a creditor could recover Rs.585 when acknowledgment was in respect
     of Rs.200 only. One of the arguments was that acknowledgment of
     a sum of Rs.200 cannot be taken as an acknowledgment of a sum
     of Rs.585. Accepting the argument, the Court held:
              “4. ….. It is true that if no definite sum had been mentioned
              and there had been an acknowledgement in general terms
              the amount of the debt would have been discovered from
              the evidence as mentioned in Explanation 1, Section 19
              of the Limitation Act. In the present case, however, there
              is a definite acknowledgement of Rs.200 and if this is
              to be used to save limitation, it could be done only with
              respect to the sum acknowledged, and not with respect
              to any sum that may be proved to be due on that date.”
                                                    (Emphasis supplied)
136. In Kali Das Chaudhuri v. Drapaudi Sundari Dassi124 for the purpose
     of seeking the benefit of extension of limitation, the letter sought to
     be relied by the plaintiff as an acknowledgement made by solicitor
     of the defendant stated thus:



123 AIR 1930 All 461 : 1929 SCC OnLine All 152
124 AIR 1918 Cal 294: 1917 SCC OnLIne Cal 23
[2024] 9 S.C.R.                                                          599

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

           “Your client Babu Hari Prasad Saha was the gomoshta
           at Calcutta in the employ of the firm of Dwarka Nath
           Makhan Lal Saha, remunerated by a share of the profits,
           and being liable for a proportionate share of the losses.
           He was struck by paralysis in the Bengali year 1307, from
           which time he could not do active work. He, however,
           continued to be in Calcutta till 1311 when he left Calcutta
           and went away to his home at Urapara. Our clients have
           all along been ready and willing to have the accounts
           duly taken up to this time that your client retired from
           Calcutta. Your client as the managing gomostha has
           to make up and explain the accounts up to that time.
           Our clients will offer every facility in the matter of the
           adjustment of accounts. …… It is not the fact that your
           client retired on 27th June 1910. He ceased to do active
           work in 1307 and retired in 1311. Our clients have no
           recollection of any notice from Messrs Dutta and Guha.
           Our clients are ready to pay to your client whatever may
           be found due on an adjustment of the accounts up to
           1311.”
     Interpreting the aforesaid letter, in the context of plaintiff’s argument
     that it be treated as an acknowledgment of subsistence of relationship
     up to 27 June 1910, the Calcutta High Court held:
           “Now, as I read that letter, that contains three material
           statements: it contains a statement that plaintiff was
           gomostha of the defendants; the second statement is
           that he was employed up to 1311 (BS) (corresponding
           with 1904 - 1905], and no longer; and the third statement
           is that the defendants were willing and ready to pay to
           the plaintiff whatever might be found due to him on an
           adjustment of the accounts up to 1311. Now, what is the
           claim of the plaintiff in this case? He brought his suit in
           order to establish his right to have the accounts taken
           upon the basis that he was a partner, and that he was
           entitled to have the accounts taken down to June 1910.
           The defendants’ solicitors wrote that he was not a partner
           and that he was not entitled to have the accounts taken
           up to 1910, but that he was only entitled to have the
           accounts up to 1311 (BS) (corresponding with 1904 –
600                                                          [2024] 9 S.C.R.

                      Digital Supreme Court Reports


           1905). I cannot understand how that can be taken to be
           an acknowledgement of the right which the plaintiff was
           endeavoring to substantiate in his plaint. I can understand
           it being said and argued with considerable force that it
           was an acknowledgement of some part of the plaintiffs
           claim, inasmuch as his claim was to have the accounts
           taken up to June 1910, and inasmuch as the defendants
           admitted that he was entitled to have the accounts taken
           up to 1904 - 1905: to that extent it is an acknowledgment,
           but in my judgment it is not an acknowledgement of the
           right alleged by the plaintiff, namely, that he was entitled
           to have the accounts taking up to June 1910.”
                                                  (Emphasis supplied)
137. Having considered the judicial precedents on the subject, in our
     view, to extend the period of limitation with the aid of Section 18,
     the acknowledgment must involve an admission of a subsisting jural
     relationship between the parties and a conscious affirmation of an
     intention of continuing such relationship regarding an existing liability.
     Such intention can be gathered from the nature of the admission.
     In other words, the admission in question need not be express, or
     regarding a precise amount, but must be made in circumstances and
     in words from which the court can reasonably infer that the person
     making the admission intended to refer to a subsisting liability as on
     the date of the statement. However, where an acknowledgement is
     in respect of a specified sum of money or a specific right only, and
     not in general terms, it would extend the period of limitation only in
     respect thereof, and not of other claims which, though may have
     arisen out of same jural relationship, are not specified therein. In
     other words, where an acknowledgement of liability is made only
     with reference to a portion of the claim put forward by the plaintiff/
     claimant, it would extend limitation only in respect of such portion,
     and not of the entire claim of the plaintiff.
138. Reverting to the case in hand, the minutes of meeting dated 19 April
     2018 made no reference to the items referable to counterclaims
     (d) and (e). There is also no acknowledgment in general terms in
     regard to liabilities subsisting under the contract. Therefore, in our
     view, the said minutes could not be treated as an acknowledgment
     for the purpose of extending limitation of counterclaims (d) and
[2024] 9 S.C.R.                                                                                          601

                 OPG Power Generation Private Limited v.
        Enexio Power Cooling Solutions India Private Limited & Anr.

       (e), which were not specified therein. In consequence, when
       counterclaims (d) and (e) were otherwise barred by limitation on
       the date of filing of counterclaim, the Tribunal was legally justified
       in rejecting them as barred by limitation. Sub-issue (c) is decided
       in the aforesaid terms.
       REJECTION OF PRAYER TO DECLARE DEBIT NOTES INVALID
       DID NOT AFFECT ENEXIO’S CLAIM FOR THE OUTSTANDING
       PRINCIPAL AMOUNT.
139. We shall now consider whether rejection of Enexio’s prayer to
     declare debit notes invalid, had adversely affected the claim for the
     outstanding principal amount in respect of the goods supplied/ work
     done under the contract. In this regard, at the outset, we must bear
     in mind that it is trite that limitation bars the remedy but does not
     extinguish the right, save in a case which is covered by Section 27 of
     the 1963 Act.125 It is equally settled that in a suit or a claim, multiple
     reliefs may be claimed by virtue of Order II Rule 3 of the Code of
     Civil Procedure, 1908,126 that is, the plaintiff may unite in the same
     suit several causes of action against the same defendant(s). The
     period of limitation is prescribed by the Schedule to the 1963 Act.127
     The Schedule to the 1963 Act is divided into three Divisions. The
     First Division, which deals with suits, is relevant for the purposes of
     this case inasmuch as by virtue of Section 43 (1) of the 1996 Act
     the provisions of the 1963 Act apply to arbitrations as they apply to
     proceedings in Court. The First Division of the Schedule comprises
     of ten (X) Parts. Each Part deals with suit(s) of a different nature.
     The period of limitation, including its start point, is dependent on its
     nature as well as event, if any, as specified in the Article(s) of the
     Schedule. Therefore, when CPC, in certain circumstances, permits
     combining in one action two or more distinct and independent claims,
     it is quite possible that one of the claims may be barred by limitation
     and the other may be within time.128


125 Prem Singh & Ors v. Birbal & Ors., (2006) 5 SCC 353, paragraphs 11 and 12.
126 Order II Rule 3, CPC.— Joinder of causes of action.— (1) Save as otherwise provided, a plaintiff may
    unite in the same suit several causes of action against the same defendant, or the same defendants
    jointly; and any plaintiffs having causes of action in which they are jointly interested against the same
    defendant or the same defendants jointly may unite such causes of action in the same suit.
           (2) Where causes of action are united, the jurisdiction of the Court as regards the suit shall depend
           on the amount or value of the aggregate subject-matter at the date of instituting the suit.
127 See Section 2(j) of the Limitation Act, 1963.
128 See Mohamed Ghasita v. Siraj-ud-Din and Ors. (supra), extracted in paragraph 97 of this judgment.
602                                                                            [2024] 9 S.C.R.

                            Digital Supreme Court Reports


140. In the instant case, as already held, the claim for compensation i.e.,
     recovery of outstanding principal amount was covered by Article
     55 of the Schedule and the start point of limitation was 19 March
     2016; whereas for the relief of declaration, Article 58 was applicable.
     For which, the start point of limitation was the date when the debit
     note was communicated to Enexio i.e., the claimant. According to
     the arbitral tribunal, one debit note was issued on 24 August 2015,
     which was acknowledged by the claimant vide letter dated 28 August
     2015, and the other was issued on 12 January 2016. Therefore, the
     period of limitation i.e., three years expired before 2 May 2019, that
     is, when request for arbitration was received by ICC Secretariat. In
     these circumstances, the relief for declaratory relief was held barred
     by limitation, and rightly so, by the arbitral tribunal.
141. Now, the question is whether rejection of declaratory relief impacted
     the relief for compensation. Answer to it, in our view, is obviously no.
     The reason is that the relief for compensation was not a consequential
     relief i.e., dependent on debit note(s) being declared invalid because
     issuance of debit note(s) was a unilateral act of the employer which
     on its own did not extinguish the right of the contractor. No doubt,
     where the relief sought is consequential to the declaration, and
     declaratory relief is found barred by time, the prayer for consequential
     relief will also fail.129 But where declaration is just an optional relief
     i.e., on which the main relief is not dependent, rejection of it as
     barred by limitation would not extinguish the claim in respect of
     which substantive relief is sought. In the instant case, debit note was
     unilaterally issued by the employer of the contractor. It, therefore,
     did not bind the contractor. In such circumstances, it was open for
     the contractor to sue for its dues without seeking a declaration qua
     the debit notes. Consequently, rejection of the declaratory relief as
     barred by limitation, in our considered view, did not have a material
     bearing on Enexio’s claim against the appellant(s) herein for the
     outstanding principal amount payable under the contract. And, further,
     that amount, as shown debited in the debit note(s), was not to be
     automatically adjusted against the principal outstanding amount
     payable to Enexio. In our view, while deciding the claim of Enexio,
     the arbitral tribunal was well within its remit to adjudicate upon the



129 See Padhiyar Prahladji Chenaji v. Maniben Jagmalbhai & Ors., (2022) 12 SCC 128, paragraph 17
[2024] 9 S.C.R.                                                                                    603

                OPG Power Generation Private Limited v.
       Enexio Power Cooling Solutions India Private Limited & Anr.

       issue whether such amount should be adjusted or not against the
       outstanding principal amount payable to Enexio. For the reasons
       aforesaid, there is no perversity in the award on this count. Sub-
       issue (d) is decided accordingly.
       THE ARBITRAL TRIBUNAL DID NOT ADOPT DIFFERENT
       YARDSTICK / REASONING OF THE ARBITRAL TRIBUNAL IS
       NOT FLAWED OR PERVERSE
142. The next argument on behalf of the appellant(s) is that the arbitral
     tribunal adopted different yardstick for adjudicating the claim than what
     was adopted for the counterclaim; and the reasoning is completely
     flawed and perverse. By referring to paragraphs 16.03 (d)130 and
     16.04131 of the award it was submitted:
       (a)    If negotiations could extend limitation for the claim, it would
              extend limitation for the counterclaim as well, because both
              arise from same contractual relationship. Moreover, it is well
              settled that negotiations by themselves do not extend limitation
              as held by this Court in Geo Miller (supra) and B & T AG
              (supra).
       (b)    If the minutes of meeting dated 19 April 2018 could be relied
              on to hold that appellant(s) had admitted their liability qua the
              claim for the outstanding principal amount, it ought to have
              been relied also for upholding Enexio’s liability qua liquidated
              damages for delay and customs duty.
143. At first blush, the above arguments appear attractive, but, when
     we test them by reading the award in its entirety, we find that the
     tribunal did not reject the counterclaims qua liquidated damages
     and custom duties as barred by limitation. Rather, rejected them
     on merit. Liquidated damages were denied because Enexio was
     entitled to 539 days extension for completion; and customs duties
     were found payable by the purchaser. The findings thereon are
     based on construction of the terms of the contract with reference to
     the conduct of the parties, therefore, it does not call for interference
     under Section 34 of the 1996 Act.



130 See paragraph 15 of this judgment wherein paragraph 16.03(d) of the award has been extracted.
131 See paragraph 16 of this judgment wherein paragraph 16.04 of the award has been extracted.
604                                                          [2024] 9 S.C.R.

                      Digital Supreme Court Reports


144. As far as extension of limitation by negotiation is concerned, a careful
     look at paragraph 16.03(d) of the arbitral award would indicate that
     there is a reference to two more aspects, ‘apart from meaningful
     negotiations’, to conclude that limitation for the claim was saved.
     These are: (a) the minutes of meeting dated 19 April 2018; and (b)
     the written offer of OPG (respondent(s) to the claim) dated 26 May
     2018 to settle the matter. We have already found, while deciding sub-
     issues (b) and (c), that the minutes of meeting dated 19 April 2018
     tantamounted to an acknowledgment under Section 18 of the 1963
     Act qua the items mentioned therein. We also noticed that it carried
     no mention regarding those items on which counterclaims were based,
     and therefore, they were rejected as barred by limitation. In these
     circumstances, though paragraph 16.03(d) of the award gives the
     impression that limitation was extended because negotiations were
     ongoing in respect of items related to the claim, the limitation was
     extended by applying the principle of acknowledgment as enshrined
     in Section 18 of the 1963 Act on basis of two documents i.e., the
     minutes of meeting dated 19 April 2018; and the offer letter dated
     26 May 2018. Importantly, the principle of extension of limitation
     by acknowledgement was applied in respect of only those claims
     regarding which a mention was there in the minutes of meeting
     dated 19 April 2018. In respect of claims regarding which there was
     no recital in the minutes, the tribunal observed that they were not
     part of the negotiations. Thus, though the term used in paragraph
     16.03(d) of the award is ‘negotiation(s)’, the tribunal, by referring
     to minutes dated 19 April 2018 and settlement offer dated 26 May
     2018, indicated the underlying legal principle / rationale behind its
     conclusion. We, therefore, conclude that though reasons recorded
     in the award at first blush appear insufficient, or a bit confusing, but,
     when those reasons are examined in the context of the documents
     placed and the arguments advanced, the underlying reasons, which
     form basis of the conclusion, are not only intelligible but sound. For the
     aforesaid reasons and in the light of the law expounded in paragraph
     71.6 above, we reject the submission of the appellant(s)’ counsel
     that the reasoning of the arbitral tribunal is flawed/perverse or that
     the award is vitiated by adopting different yardstick for adjudging the
     claim than what was adopted for the counterclaim. Even otherwise,
     the mistake, if any, committed by the arbitral tribunal in using the
     words ‘ongoing negotiations’ in place of acknowledgement is trivial
     does not go to the root of the matter as to have a material bearing
[2024] 9 S.C.R.                                                          605

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     on the conclusion. Therefore, for this mistake alone, the award is
     not liable to be set aside.
145. The other submission on behalf of the appellant that the arbitral
     tribunal was obliged to accept the admission contained in the minutes
     of meeting dated 19 April 2018 qua liquidated damages and customs
     duties, because it relied on it for extending the limitation, is equally
     unacceptable. Reason being that acknowledgment is just a piece of
     evidence, like an admission. An admission can always be explained.
     Therefore, even if it is used for extending the limitation, it cannot be
     regarded as conclusive proof of either the claim or the counterclaim
     regarding which there is an acknowledgement. Because the Court
     or the Tribunal would have to decide the claim or the counterclaim,
     if within limitation, upon consideration of the entire evidence led
     before it. No doubt, in that process, the acknowledgement would also
     have to be considered as a piece of evidence. Thus, in our view,
     the tribunal was well within its jurisdiction in drawing a conclusion,
     based on consideration of the entire evidence, at variance with the
     recitals in the acknowledgement.
146. Otherwise also, as is clear from the award, the claimant had
     challenged the recital in the minutes i.e., regarding its liability for
     liquidated damages and customs duties, by claiming that it was
     economically coerced into making such admission. Circumstances,
     proven on record, indicated that (a) soon after the meeting dated
     19 April 2018, the claimant had sent a denial of its liability; and (b)
     later, on 26 May 2018, the appellant(s) herein had made an offer
     of Rs.3 crores to Enexio towards full and final settlement of all its
     claim. In these circumstances, based on the evidence led by the
     parties, the tribunal was well within its remit to conclude that the
     claimant was not liable in respect of those items which formed part
     of the counterclaim. Such conclusion, which is based on proven
     circumstances, is a plausible view and cannot be termed perverse.
     Hence, it is not amenable to interference in a challenge under Section
     34 of the 1996 Act. In our view, therefore, the learned Single Judge
     of the High Court erred in law while interfering with the arbitral award.
147. Before closing discussion on the issue, it would be necessary to
     address an alternative submission raised on behalf of the appellants.
     It was argued that the learned Single Judge and the Division Bench
     of the High Court, admittedly, were exercising jurisdiction under
606                                                          [2024] 9 S.C.R.

                             Digital Supreme Court Reports


       Sections 34 and 37, respectively, of the 1996 Act. As, while exercising
       jurisdiction under Section 34, the Court does not sit in appeal over
       the award, it cannot substitute the reasoning in the award with its
       own. Likewise, the appellate court exercising power under Section
       37 cannot have greater power than what a Court possesses under
       Section 34. Consequently, it was argued, the appellate court (i.e.,
       the Division Bench of the High Court) exceeded its jurisdiction while
       providing its own reasons to support the conclusion in the award. It
       was also urged that in absence of proper reasons in the award, the
       only course available was to set aside the award with liberty to the
       parties to undertake fresh arbitration.
148. We have given due consideration to the above submission. In our
     view, a distinction would have to be drawn between an arbitral award
     where reasons are either lacking/unintelligible or perverse and an
     arbitral award where reasons are there but appear inadequate
     or insufficient.132 In a case where reasons appear insufficient or
     inadequate, if, on a careful reading of the entire award, coupled
     with documents recited/ relied therein, the underlying reason,
     factual or legal, that forms the basis of the award, is discernible/
     intelligible, and the same exhibits no perversity, the Court need
     not set aside the award while exercising powers under Section 34
     or Section 37 of the 1996 Act, rather it may explain the existence
     of that underlying reason while dealing with a challenge laid to
     the award. In doing so, the Court does not supplant the reasons
     of the arbitral tribunal but only explains it for a better and clearer
     understanding of the award.
149. In the instant case, the appellate court took pains, and rightly so, to
     understand and explain the underlying reason on which the claim
     of Enexio was found within limitation. As noticed above, paragraph
     16.03 (d) of the award contains the reason based on which the
     arbitral tribunal concluded that Enexio’s claim was within limitation.
     However, in paragraph 16.03 (d), the arbitral tribunal failed to state,
     in so many words, that it was treating the minutes of meeting dated
     19 April 2018 as an acknowledgment within the meaning of Section
     18 of the 1963 Act. This omission on the part of the arbitral tribunal
     was trivial and did not travel to the root of the award, therefore, in our


132 See paragraphs 71.2 to 71.6 of this judgment.
[2024] 9 S.C.R.                                                          607

              OPG Power Generation Private Limited v.
     Enexio Power Cooling Solutions India Private Limited & Anr.

     view, the appellate court was well within its jurisdiction to explain the
     underlying legal principle which the arbitral tribunal had applied; and
     in doing so, it did not supplant the reasons provided in the award.
     In this view of the matter, the impugned order of the Division Bench
     does not suffer from any legal infirmity. Sub-issue (e) is decided in
     the aforesaid terms.
     SUMMARY OF OUR CONCLUSIONS
150. In the light of the analysis above, we summarize our conclusions
     as follows:
     (i)    Though the ACC Unit /project was of OPG, Gita Power, as
            the holding company of OPG, had actively participated in the
            formation of the contract for the project. Not only did it place
            purchase order(s) on Enexio but made advance payment(s)
            thereunder to Enexio, which were subsequently affirmed by
            OPG. The two, therefore, not only acted as a single economic
            entity but as agents of each other. Hence, the arbitral tribunal
            was justified in holding that Gita Power was bound by the
            arbitration agreement and jointly and severally liable along with
            OPG to pay the awarded amount.
     (ii)   The claim of Enexio was an indivisible claim for compensation
            in lieu of goods supplied, and work done, based on breach of
            the contract, therefore limitation for the claim was governed by
            Article 55, and not by Articles 14, 18 and 113, of the Schedule
            to the 1963 Act.
     (iii) The claimant’s claim for the outstanding principal amount
           matured on 19 March 2016. Therefore, limitation started to
           run from that date. However, even if we count limitation from
           21 September 2015 (as found by the Tribunal) it will have no
           material bearing on the award for the reason indicated below.
     (iv) The limitation for the claim as well as counterclaim(s), other
          than those relating to cost of repair/replacement of gear boxes
          and fan modules, stood extended, under Section 18 of the 1963
          Act, on the basis of acknowledgement made in the minutes of
          meeting dated 19 April 2018, and, therefore, those were within
          limitation as on the date of : (a) commencement of arbitration
          (i.e. 2 May 2019); and (b) the date of filing counterclaim (i.e.
          15 July 2019) and were rightly considered on merit.
608                                                          [2024] 9 S.C.R.

                           Digital Supreme Court Reports


       (v)     The counterclaims qua cost of repair /replacement of gear
               boxes and fan modules were rightly held barred by time as in
               respect thereof there was no recital in the minutes of meeting
               dated 19 April 2018.
       (vi) Rejection of prayer to declare debit notes invalid, on ground
            of limitation, had no adverse impact on the claimant’s claim
            for compensation, which was well within the extended period
            of limitation.
151. Based on our conclusions above, we are of the view that there is no
     palpable error in the arbitral award as to be termed ‘patently illegal’ /
     ‘perverse’, or in conflict with public policy of India. Therefore, the
     Division Bench of the High Court was justified in setting aside the
     judgment and order of the Single Judge and restoring the arbitral
     award. Accordingly, the appeal(s) fail and are hereby dismissed.
     Parties to bear their own costs.
152. Pending application(s), if any, stand disposed of.

       Result of the Case: Appeal dismissed.



       †
           Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitral award"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

OPG POWER GENERATION PRIVATE LIMITED versus ENEXIO POWER COOLING SOLUTIONS INDIA PRIVATE LIMITED & ANR. — 2024 INSC 711 - Legal Desk AI