SOMDATT BUILDERS-NCC-NEC(JV)versusNATIONAL HIGHWAYS AUTHORITY OF INDIA & ORS.
- Citation
- 2025 INSC 113
- Decided
- 26 January 2025
- Disposal
- Appeal(s) allowed
- Bench
- ABHAY S OKA
Holding
The arbitral award was valid, the excess geogrid quantity did not constitute a variation requiring rate revision, and the Division Bench exceeded its limited jurisdiction under Section 37, so the award is restored.
Summary
The Supreme Court heard an appeal by Somdatt Builders‑NCC‑NEC (JV) against a Delhi High Court Division Bench order that set aside an arbitral award under Section 37 of the Arbitration and Conciliation Act, 1996. The dispute concerned whether the excess quantity of geogrid required for a reinforced earth wall, beyond the Bill of Quantities, amounted to a "variation" under Clauses 51 and 52 of the contract, thereby giving the Engineer power to revise rates. The Dispute Review Board and the arbitral tribunal, both comprising technical experts, held that there was no variation and that payment should be made at the BOQ rate. The High Court Single Judge upheld this award under Section 34, but the Division Bench overturned it, invoking public policy and patent illegality. The Supreme Court held that courts must exercise great restraint, cannot re‑appraise the merits of an award upheld under Section 34, and that the Division Bench exceeded its limited jurisdiction under Section 37; consequently the arbitral award was restored.
Issues considered
- The increase in quantity of geogrid beyond the BOQ constitutes a variation under Clause 51/52 requiring rate renegotiation by the Engineer.
- Whether the arbitral award can be set aside under Section 37 on grounds of public policy, patent illegality, or shocking the conscience of the court.
- The scope of judicial interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 34, s. 34(2)(b)(ii), s. 37, s. 51, s. 52, s. 52.1, s. 52.2, s. 52.3
Subjects
Judgment
[2025] 2 S.C.R. 203 : 2025 INSC 113
Somdatt Builders-NCC-NEC(JV)
v.
National Highways Authority of India & Ors.
(Civil Appeal No. 2058 of 2012)
27 January 2025
[Abhay S. Oka and Ujjal Bhuyan,* JJ.]
Issue for Consideration
Issue arose as regards correctness of the judgment of the Division
Bench setting aside the arbitral award u/s.37 of the Arbitration and
Conciliation Act.
Headnotes†
Arbitration and Conciliation Act, 1996 – s.34 and 37 –
Jurisdiction under – Exercise of – Interference with the
decision of the arbitrator – Execution of contract awarded by
National Highways Authority of India-NHAI to the appellant
regarding construction of lanes on National Highway – Dispute
as regards geogrid/geotextile material exceeded the Bill of
Quantities-BOQ quantities in the contract, and the power
of the Engineer to revise the rates given in the BOQ in the
event of increase in actual quantities – Appellant’s case that
the Engineer/Employer intending wrongful application of the
Conditions of Particular Application for downward revision of
rates for BOQ item of geogrid for quantity in excess of BOQ
quantity – Recommendation by Dispute Review Board-DRB that
quantities of geogrid required limited to facia area provided
in the BOQ to be paid as per the BOQ rates – Invocation of
arbitration clause by NHAI – Arbitral tribunal holding that the
quantity of geogrid given at the tender stage by NHAI was
wrong, there was no change in the design but mere increase
in the quantity beyond the BOQ quantity, directed NHAI to pay
the appellant for the actual quantity of geogrid required to be
executed to complete the work as per the approved design
at the BOQ rate – Application by NHAI u/s.34 – Single Judge
of the High Court upheld the arbitral award – However, the
Division Bench set aside the same – Sustainability:
* Author
204 [2025] 2 S.C.R.
Digital Supreme Court Reports
Held: Not sustainable – Great deal of restraint is required to
be shown by the Courts while examining the validity of an
arbitral award when such an award has been upheld, wholly or
substantially, u/s.34 – Court cannot undertake an independent
assessment of the merits of the award and must only ascertain that
the exercise of power by the court u/s. 34 has not exceeded the
scope of the provision – View taken by DRB and arbitral tribunal,
both comprising of technical experts, that there is no variation
either in the form or quality or quantity of the works is the correct
one which was acknowledged by the Single Judge – At the time
of execution of the contract, the geogrid required turned out to
be much more than the estimated figure given in the contract –
As such both the fact finding authorities held that there was no
variation in terms of Clause 51.1 and the Engineer did not have
the competence to renegotiate the price or rate of the geogrid
for the excess quantity of geogrid required – This is clearly a
plausible view – It is the correct interpretation of Clause 51 made
by the DRB and the arbitral tribunal, in a reasonable manner
based on the evidence on record – As such, the Single Judge
rightly declined to interfere with the award of the arbitral tribunal
u/s.34, affirming the decision of the DRB – Division Bench of the
High Court not at all justified in setting aside the arbitral award
exercising extremely limited jurisdiction u/s.37 by merely using
expressions like ‘opposed to the public policy of India’, ‘patent
illegality’ and ‘shocking the conscience of the court’ – Thus, the
judgment and order passed by the Division Bench of the High
Court is set aside and the arbitral award is restored. [Paras 27.3,
28, 33, 34, 36, 42, 43]
Arbitration and Conciliation Act, 1996 – Arbitral award – Public
policy in India – Explanation:
Held: Public policy in India means the fundamental policy of Indian
law – Violation of Indian statutes linked to public policy or public
interest and disregarding orders of superior courts in India would
be regarded as being contrary to the fundamental policy of Indian
law – It would also mean that the arbitral award is against basic
notions of justice or morality – Arbitral award can be set aside on
the ground of patent illegality, where the illegality goes to the root
of the matter but reappreciation of evidence cannot be permitted
under the ground of patent illegality. [Para 37]
[2025] 2 S.C.R. 205
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
Case Law Cited
Ssangyong Engineer and Construction Company Ltd. v. NHAI
[2019] 7 SCR 522 : (2019) 15 SCC 131; Reliance Infrastructure
Ltd. v. State of Goa [2023] 8 SCR 379 : (2024) 1 SCC 479 –
relied on.
S.V. Samudram v. State of Karnataka [2024] 1 SCR 281 :
(2024) 3 SCC 623; M/s. Hindustan Construction Company Ltd. v.
M/s NHAI [2023] 11 SCR 623 : (2024) 2 SCC 613; Konkan Railway
Corporation Limited v. Chenab Bridge Project Undertaking [2023]
11 SCR 215 : (2023) 9 SCC 85; M/s. Larsen Air Conditioning
and Refrigeration Company v. Union of India 2023 INSC 708 :
[2023] 11 SCR 86; MMTC Ltd. v. Vedanta Limited [2019] 3 SCR
1023 : (2019) 4 SCC 163; MP Power Generation Company Ltd. v.
Ansaldo Energia SPA (2018) 16 SCC 661; Associate Builders v.
DDA [2014] 13 SCR 895 : (2015) 3 SCC 49; PSA Sical Terminals
Private Ltd. v. Board of Trustees of V.O. Chidambranar Port Trust
Tuticorin [2021] 5 SCR 408 : (2023) 15 SCC 781– referred to.
Grinaker Construction (TVL) Ltd Vs. Transvaal Provincial
Administration, 1982 (1) AD 78 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996.
List of Keywords
Dispute Review Board; Arbitral award; Interference with arbitral
award; Public policy; Public policy in India; Patent illegality; Bill of
quantities; Geogrid; Geotextile; General Conditions of Contract;
National Highway; Variation in quantity; Variation in design;
Technical experts; Interference with the decision of arbitrator;
Execution of contract awarded by National Highways Authority of
India; Construction of lanes on National Highway; Arbitration clause;
Court of appeal; Interpretation of contractual terms; Opposed to
the public policy of India; Patent illegality; Shocking the conscience
of the court; Basic notions of justice or morality.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2058 of 2012
From the Judgment and Order dated 17.11.2009 of the High Court
of Delhi at New Delhi in FAO No. 427 of 2007
206 [2025] 2 S.C.R.
Digital Supreme Court Reports
Appearances for Parties
Arvind Minocha, Sr. Adv., Rakesh Kharab, Mayank Kshirsagar,
Ms. Dhanlaxmi Iyer, Advs. for the Appellant.
Krishnan Venungopal, Sr. Adv., Vikas Goel, Abhishek Kumar,
Avinash Mathews, Ms. Garima Kaul, Santosh Kumar - I,
Advs. for the Respondents.
Judgment / Order of the Supreme Court
Judgment
Ujjal Bhuyan, J.
Heard learned counsel for the parties.
2. This civil appeal by special leave is directed against the judgment
and order dated 17.11.2009 passed by the High Court of Delhi at
New Delhi (‘High Court’) in FAO(OS) No. 427 of 2007 [National
Highways Authority of India Vs. Som Datt Builders-NCC-NEC(JV)].
2.1. By the aforesaid judgment, the High Court allowed the
appeal of the respondent-National Highways Authority of
India (‘respondent’ or ‘NHAI’ hereinafter) under Section 37 of
the Arbitration and Conciliation Act, 1996 (briefly ‘the 1996
Act’ hereinafter). It may be mentioned that respondent had
challenged, by way of the aforesaid appeal, the judgment and
order of the learned Single Judge in OMP No. 316/2005 dated
29.08.2007 whereby the learned Single Judge dismissed the
application filed by NHAI under Section 34 of the 1996 Act
for setting aside the award dated 03.06.2005 passed by the
Arbitral Tribunal.
3. The matter relates to execution of a contract awarded by NHAI to the
appellant regarding the work of four laning and strengthening of the
existing two lane section between Km. 470.000 and Km. 38.000 on
NH-2 (construction package II-B) near Kanpur in the State of Uttar
Pradesh under World Bank Loan Assistance.
4. At the outset, it would be apposite to advert to the relevant facts.
5. Following a process of open bid tender, the related contract was
allotted by NHAI to the appellant vide the contract agreement dated
[2025] 2 S.C.R. 207
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
27.03.2002 who undertook to execute the work at the contract price
of Rs. 4,961,183,599.00. Appellant is a joint venture of Somdatt
Builders Pvt. Ltd., Nagarjuna Construction Company and Navayug
Engineering Company Limited having its principal place of business
at East of Kailash, New Delhi.
6. A joint venture between Consulting Engineering Services (I) Ltd.
and BECA International Consultants Ltd. was appointed by NHAI
as the Engineer of the project in terms of the contract agreement
to supervise the construction work.
7. It was a unit rate contract comprising of a detailed Bill of Quantities
(BOQ). The BOQ contained description of the items of the work to be
executed by the appellant as contractor and the estimated quantity
of each item. The rates of each BOQ item were to be filled in by
the contractor (appellant).
8. The contract agreement provided for a mechanism of dispute
resolution at the first instance through a Dispute Review Board (‘DRB’)
prior to the parties availing of their remedy by way of arbitration.
A three-member panel of DRB was constituted comprising of one
member appointed by each of the two parties and the third member
appointed by the aforesaid two members.
9. While executing the contract, a dispute arose between the parties in
respect of item No. 7.07 of the BOQ which provided for reinforced
earth structure including soil reinforcing geogrid with all fixtures
and accessories complete as per approved design and drawing of
specialised firm and matters connected therewith. The dispute was
not really in respect of the nature of the work to be performed but
was the consequence of the geogrid/geotextile material exceeding
the BOQ quantities in the contract. In essence, the dispute relates
to power of the Engineer to revise the rates given in the BOQ in
the event of increase in actual quantities. This was contested by
the appellant.
10. Appellant raised the aforesaid dispute before the DRB contending
that the Engineer/Employer was intending wrongful application of
Clause 52.2 of the Conditions of Particular Application (COPA) for
downward revision of rates for BOQ item No. 7.07 (ii) of geogrid for
quantity in excess of BOQ quantity. DRB heard both the sides and
deliberated upon the issue in detail. DRB vide its decision dated
208 [2025] 2 S.C.R.
Digital Supreme Court Reports
15.03.2004 recommended that quantities of geogrid required limited
to the facia area provided in the BOQ have to be paid as per the
BOQ rates.
11. Respondent NHAI was not satisfied with the aforesaid decision of
DRB and invoked the arbitration clause in the contract agreement
whereafter the dispute was referred to arbitration before an Arbitral
Tribunal comprising of three arbitrators: one arbitrator appointed by
each of the two parties and the third arbitrator appointed by the two
arbitrators so appointed. It is on record that each of the arbitrators
were technical experts conversant with the nature of the contract.
Arbitral Tribunal, by a majority of 2:1, passed the award dated
03.06.2005. Arbitral Tribunal held that the quantity of geogrid given
at the tender stage by NHAI was wrong. Therefore, the increase in
quantity was a mere increase to meet the requirement for completion
of the RE wall work which was indicated by the RCC facia quantity
at the tender stage. There was no change in the design but mere
increase in the quantity beyond the BOQ quantity which did not attract
Clause 52.2. In this context, Arbitral Tribunal held that the Engineer
does not possess the power to revise the rates for additional quantity
of geogrid required for actual execution of work as per the approved
design. Upholding the recommendations of DRB, Arbitral Tribunal
held that variation in terms of Clause 51.1 was not established and
directed NHAI to pay the appellant for the actual quantity of geogrid
required to be executed to complete the work of RE wall as per the
approved design at the BOQ rate.
12. The aforesaid award dated 03.06.2005 was challenged by the
respondent-NHAI under Section 34 of the 1996 Act which was heard
and decided by a learned Single Judge of the High Court. Learned
Single Judge examined the contours of Clauses 51.1, 51.2, 52.1,
52.2, 52.3 and 55.1 and came to the definite conclusion that there
was no change in the design. The BOQ rate would apply since the
matter was one of mere change in quantity. By the judgment and
order dated 29.08.2007, learned Single Judge of the High Court
found no merit in the application filed by NHAI under Section 34 of
the 1996 Act and dismissed the same.
13. It was thereafter that NHAI as the appellant preferred the appeal
before a Division Bench of the High Court under Section 37 of the
1996 Act. The Division Bench examined the primary contention
[2025] 2 S.C.R. 209
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
of NHAI that under the contractual terms, all variations in quantity
beyond the tolerance limits set out in the contract, whether arising as
a result of issuance of instructions by the Engineer or arising even
without the issuance of instructions, were open to renegotiation of the
rates by the Engineer. By the judgment and order dated 17.11.2009
(‘impugned judgment’), Division Bench agreed with the contention
of NHAI and set aside the award of the Arbitral Tribunal as well as
the order of the learned Single Judge.
14. Being aggrieved, the contractor (appellant) preferred the related
special leave petition. On 14.12.2009, this Court had issued notice
and passed an interim order staying encashment of the bank
guarantee subject to the appellant renewing it for a period of one
year. Vide order dated 10.02.2012, this Court granted leave and
directed continuance of the interim order. Hence the civil appeal.
15. Contention of the appellant is that it is NHAI who had provided the
wrong quantity in respect of item No. 7.07 of the BOQ on the basis
of which appellant had tendered. Upon approval of the design by
the Engineer when the increased quantity became known in April,
2003, the Engineer held that BOQ rate would be payable for the
entire quantity which was not acceptable to NHAI. The increase in
quantity was not as a result of any change in the design or as a
result of any instructions given by the Engineer. The enhancement
in the quantity was necessitated because wrong information was
furnished by the respondent at the stage of tender itself. On dispute
being raised, this position was accepted by the DRB and thereafter
by the Arbitral Tribunal. Application filed by the respondent under
Section 34 of the 1996 Act for setting aside of the arbitral award
was rightly rejected by the learned Single Judge of the High Court.
Division Bench of the High Court fell in error and committed a
manifest mistake in overturning the technical findings of the three
authorities below while exercising limited jurisdiction under Section 37
of the 1996 Act.
16. Counter affidavit has been filed by respondent NHAI. Reliance has
been placed on Clauses 51 and 52 of COPA. Clause 51 of COPA
has two parts: 51.1 and 51.2. Clause 51.1 covers instructed variations
which includes any increase or decrease in the quantity of work. As
per Clause 51.2, for increase or decrease in quantity of any material,
instructions of the Engineer are not required. A combined reading
210 [2025] 2 S.C.R.
Digital Supreme Court Reports
of Clauses 51.1 and 51.2 would indicate that though increase or
decrease in the quantity of any work may be without instructions but
it nonetheless remains a variation. Once it is a variation, Engineer
has got the power to fix a new rate. This power is traceable to
Clause 52.1, which does not make any distinction between instructed
variation or uninstructed variation; on the other hand, it provides
that all variations referred to in Clause 51 are to be valued by the
Engineer. In case of instructed variation only, notice is required to
be given in terms of the second proviso to Clause 52.2. If this be
the position, view taken by the Division Bench of the High Court is
the correct one and calls for no interference.
17. Mr. Arvind Minocha, learned senior counsel for the appellant, at
the outset submits that the core issue involved in this appeal is
the justification or otherwise of the decision of the Division Bench
of the High Court upsetting concurrent findings of three authorities
while exercising jurisdiction under Section 37 of the 1996 Act. He
submits that the dispute raised by the appellant was decided in its
favour by the DRB comprising wholly of technical experts. Arbitral
Tribunal again comprising of technical persons passed the award
in favour of the appellant by confirming the decision of the DRB.
When the respondent filed application under Section 34 of the 1996
Act for setting aside of the award, learned Single Judge of the High
Court dismissed the same and affirmed the award passed by the
Arbitral Tribunal.
17.1. Learned senior counsel submits that scope of interference
by the appellate court under Section 37 of the 1996 Act
is extremely limited. None of the grounds for invocation of
jurisdiction under Section 37 of the 1996 Act were satisfied.
Learned Single Judge while exercising jurisdiction under
Section 34 of the 1996 Act had repelled the challenge of the
respondent to the arbitral award. View taken by the learned
Single Judge is a plausible view, if not the only possible view.
Therefore, Division Bench committed a manifest error in setting
aside the arbitral award as well as the order passed by the
learned Single Judge affirming the same.
17.2. Adverting to the facts of the case, learned senior counsel
submits that the scope of the contract involved construction
of 50 Kms. of road, service roads on both sides, drains,
[2025] 2 S.C.R. 211
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
17 main bridges, 65 culverts and 20 under-passes. The 51
Kms. stretch of road included raised carriageway of about 22
Kms. having Reinforced Concrete wall (RCC wall) on both
sides for 9.5 Kms. and Reinforced Earth wall (RE wall) for
about 12 Kms. with concrete facia panels. After the award of
work, the design of the wall was to be done by the appellant
based on the design criteria given in the contract with the
approval of the Engineer appointed by the respondent. The
item RE wall is mentioned at item No. 7.07 in the BOQ having
three sub-items:
(i) RCC facia wall on both sides,
(ii) filter media,
(iii) geogrid.
17.3. He submits that dispute in the present matter relates to the sub-
item geogrid as the respondent had given a wrong estimate of
the quantity in respect of geogrid while correct quantities were
given for the other two sub-items. This mistake was detected
when the design was prepared by the appellant and approved
by the Engineer. When the quantity of material in respect of
geogrid increased, the Engineer decided that the BOQ rate
would be applicable for the increased quantity of geogrid.
17.4. After the appellant commenced the work, the respondent was
making the monthly payment for the said item as per the BOQ
rate. After a new Engineer was appointed by the respondent, it
was decided that the rate for the increased quantity of geogrid
should be renegotiated.
17.5. Thereafter, the matter was referred by the appellant to the
DRB which decided in favour of the appellant. DRB held that
variation in terms of Clause 51.1 was not established and
recommended payment of geogrid at the BOQ rate for the
entire quantity.
17.6. Respondent did not accept the above recommendations of
the DRB and invoked the arbitration clause in the contract.
Arbitral Tribunal, comprised wholly of technical persons, by
a majority of 2:1 held that increase in the quantity of geogrid
for erection of the RE wall as per the approved design could
212 [2025] 2 S.C.R.
Digital Supreme Court Reports
not be termed as a variation in terms of Clause 51.1. Further
holding that the Engineer did not have the power to revise the
rate qua the BOQ rate for the additional quantity of geogrid
required for execution of the work as per the approved design,
Arbitral Tribunal directed payment as per the BOQ rate for
the additional quantity.
17.7. In the application filed by the respondent under section 34
of the 1996 Act for setting aside of the arbitral award, the
challenge centred around Clauses 51 and 52 only. Learned
Single Judge rejected the challenge of the respondent and
upheld the arbitral award. After the award was confirmed
by the learned Single Judge under Section 34 of the 1996
Act, the Division Bench acting as the appellate court was
not at all justified to overturn the concurrent findings of three
adjudicating fora while exercising extremely limited jurisdiction
under Section 37 of the 1996 Act.
17.8. He further submits that the interpretation given by the Division
Bench is not only contrary to Clause 51.1 and the proviso to
Clause 52.2 but renders those provisions completely otiose.
Division Bench misdirected itself by stretching the meaning of
the word variation by referring to dictionary meanings whereas
the said expression has to be understood in the context of
the relevant clauses of the contract. Division Bench failed to
appreciate that in so far automatic increase in the quantity is
concerned, the rate which is payable is the one as agreed
in the BOQ. If any other rate is to be fixed, the same can be
considered only in case of instructed variation provided 14
days prior notice before commencement of the work is given
which was admittedly not done in the present case. In this
connection he places reliance on a Delhi High Court judgment
in the case of NHAI vs. M/s ITD Cementation India Limited.1
17.9. On the limited scope of interference under Section 37 of the
1996 Act, learned senior counsel for the appellant has placed
reliance on the following decisions:
1 (2009) 113 DRJ 176
[2025] 2 S.C.R. 213
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
(i) S.V. Samudram Vs. State of Karnataka,2
(ii) M/s. Hindustan Construction Company Ltd. Vs. M/s NHAI 3
(iii) Reliance Infrastructure Ltd. Vs. State of Goa 4
(iv) Konkan Railway Corporation Limited Vs. Chenab Bridge
Project Undertaking 5
(v) M/s Larsen Air Conditioning and Refrigeration Company
Vs Union of India 6
(vi) MMTC Ltd. Vs. Vedanta Limited 7
(vii) MP Power Generation Company Ltd. Vs. Ansaldo Energia
SPA8
18. Per contra, Mr. Krishnan Venugopal, learned senior counsel appearing
for NHAI submits that Division Bench of the High Court has rightly
set aside the arbitral award finding the same to be perverse.
18.1. He submits that the core issue involved in the present appeal
is whether the arbitral award dated 03.06.2005 goes contrary
to the only interpretation of Clauses 51 and 52 of the General
Conditions of Contract (GCC) read with COPA as contained in
the contract dated 27.03.2002 executed between the parties.
18.2. Learned senior counsel submits that subject matter of the
dispute relates to BOQ item No. 7.07 (II) i.e. geogrid. Due
to change in design of the RE wall, quantity of geogrid
increased almost by 300 percent during execution. Since the
twin conditions contemplated under Clause 52.2 were being
fulfilled i.e. overall quantity of geogrid executed by more
than 25 percent from the estimated quantity and the cost of
geogrid being more than 2 percent of the contract value, the
rate for the additional quantity of geogrid was required to be
reworked. Therefore, the present case is that of instructed
2 [2024] 1 SCR 281 : (2024) 3 SCC 623
3 [2023] 11 SCR 623 : (2024) 2 SCC 613
4 [2023] 8 SCR 379 : (2024) 1 SCC 479
5 [2023] 11 SCR 215 : (2023) 9 SCC 85
6 [2023] 11 SCR 86 : 2023 INSC 708
7 [2019] 3 SCR 1023 : (2019) 4 SCC 163
8 (2018) 16 SCC 661
214 [2025] 2 S.C.R.
Digital Supreme Court Reports
variation under Clause 51.1(a) for which the appellant was also
notified on 28.10.2003 fulfilling the requirement of 14 days’
notice contained in Clause 52.2.
18.3. Referring to the arbitral award, Mr. Venugopal submits that
contrary to the evidence on record and contrary to the relevant
clauses of the contract, Arbitral Tribunal held that it was not
a case of instructions issued by the Engineer but a case of
automatic increase of quantity. Referring to Clause 51.1(a),
he submits that increase or decrease in quantity is also a
variation and as per Clause 51.2, no instructions are required
for such increase or decrease of quantity though the same
continues to be a variation.
18.4. Even assuming but not admitting that the Engineer did not
issue any notice to the appellant then also, according to Mr.
Venugopal, a bare reading of Clause 52.2 would make it
apparent that for a non-instructed variation, the condition of
giving 14 days’ notice would not apply.
18.5. Learned senior counsel also submits that the contention
of the appellant that the quantity of geogrid had increased
due to negligence and wrong mentioning of figures by the
respondent is totally fallacious in as much as Clause 55.1 of
the contract clarifies that the quantity set out in the contract
are the estimated quantities only.
18.6. He would therefore contend that this is not a case of plausible
interpretation but a case of adopting an interpretation which is
contrary to the only possible interpretation of the contractual
clauses. Arbitral Tribunal has rewritten the contract by
ignoring the plain and simple language of the relevant
clauses and the parties’ intentions besides overlooking the
evidence on record which is legally impermissible. All these
aspects were raised by the respondent in its application
under Section 34 of the 1996 Act but the learned Single
Judge failed to consider the same by placing reliance on a
South African judgment which is clearly distinguishable in
the facts of the present case. Therefore, Division Bench of
the High Court acting as the appellate court under Section
37 of the 1996 Act rightly interfered in the matter by setting
aside the arbitral award.
[2025] 2 S.C.R. 215
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
18.7. Learned senior counsel has placed reliance on the following
decisions to buttress his submissions:
(i) Associate Builders Vs. DDA9
(ii) Ssangyong Engineer and Construction Company Ltd.
Vs. NHAI 10
(iii) PSA Sical Terminals Private Ltd. Vs. Board of Trustees
of V.O. Chidambranar Port Trust Tuticorin11
18.8. Learned senior counsel further submits that the judgment in
the case of NHAI Vs. M/s ITD Cementation India Limited, cited
and relied upon by the appellant, is not applicable to the facts
of the present case. Firstly, the judgment is by a Single Bench
whereas the impugned order has been passed by a Division
Bench which is also later in point of time. Secondly, the said
judgment does not deal with the power of the Engineer to fix
a new rate in terms of Clause 52.
18.9. He finally submits that the present appeal is devoid of any merit
and the same is therefore liable to be dismissed by this Court.
19. Submissions made by learned counsel for the parties have received
the due consideration of the court.
20. At the outset, it would be relevant to advert to Clauses 51 and 52 of
the GCC read with COPA. Clauses 51 and 52 are as under:
Alteration, Additions and Omissions
51.1 Variations (GCC)
The Engineer shall make any variation of the form, quality
or quantity of works or any part thereof that may, in his
opinion, be necessary and for the purpose, or if for any
other reason it shall, in his opinion, be appropriate, he
shall have the authority to instruct the Contractor to do
and the Contractor shall do any of the following:-
(a) increase or decrease the quantity of any work included
in the Contract.
9 [2014] 13 SCR 895 : (2015) 3 SCC 49
10 [2019] 7 SCR 522 : (2019) 15 SCC 131
11 [2021] 5 SCR 408 : (2023) 15 SCC 781
216 [2025] 2 S.C.R.
Digital Supreme Court Reports
(b) omit any such work (but not if the omitted work is to be
carried out by the Employer or by another contractor),
(c) change the character or quality or kind of any such
work,
(d) change the levels, lines, position and dimensions of
any part of the works,
(e) execute additional work of any kind necessary for
the completion of the works, or
(f) change any specified sequence or timing of
construction of any part of the works.
No such variation shall in any way vitiate or invalidate the
Contract, but the effect, if any, of all such variations shall
be valued in accordance with Clause 52.
Provided that where the issue of an instruction to vary
the works is necessitated by some default of or breach of
contract by the Contractor or for which he is responsible,
any additional cost attributable to such default shall be
borne by the Contractor.
51.2 Instructions for Variations (GCC)
The Contractor shall not make any such variation without
an instruction of the Engineer.
Provided that no instruction shall be required for increase or
decrease in the quantity of any work where such increase
or decrease is not the result of an instruction given under
this Clause, but is the result of the quantities exceeding
or being less than those stated in the Bill of Quantities.
52.1 Valuation of Variations (GCC)
All variations referred to in Clause 51 and any additions to
be Contract Price which are required to be determined in
accordance with Clause 52 (for the purposes of this Clause
referred to as “varied work”), shall be valued at the rates
and prices set out in the Contract if, in the opinion of the
Engineer, the same shall be applicable. If the contract does
not contain any rates or prices applicable to the varied
work, the rates and prices in the Contract shall be used
[2025] 2 S.C.R. 217
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
as the basis for valuation so far as may be reasonable,
failing which, after due consultation by the Engineer with the
Employer and the Contractor, suitable rates or prices shall
be agreed upon between the Engineer and the Contractor.
In the event of disagreement, the Engineer shall fix such
rates or prices as are, in his opinion, appropriate and
shall notify the Contractor accordingly, with a copy to the
Employer. Until such time as rates or prices are agreed
or fixed, the Engineer shall determine provisional rates or
prices to enable on-account payments to be included in
certificates issued in accordance with Clause 60.
(COPA)
Where the Contract provides for the payment of the Contract
Price in more than one currency, and varied work is valued
at, or on the basis of, the rates and prices set out in the
Contract, payment for such varied work shall be made
in the proportions of various currencies specified in the
Appendix to Bid for payment of the Contract Price. Where
the Contract provides for payment of the Contract Price
in more than one currency, and new rates or prices are
agreed, fixed, or determined as stated above, the amount
or proportion payable in each of the applicable currencies
shall be specified when the rates or prices are agreed, fixed,
or determined, it being understood that in specifying these
amounts or proportions the Contractor and the Engineer (or,
failing agreement, the Engineer) shall take into account the
actual or expected currencies of cost (and the proportions
thereof) of the inputs of the varied work without regard to the
proportions of various currencies specified in the Appendix
to Bid for payment of the Contract Price.
52.2 Power of Engineer to fix Rates (GCC)
Provided that if the nature or amount of any varied work
relative to the nature or amount of the whole of the works
or to any part thereof, is such that, in the opinion of the
Engineer, the rate or price contained in the Contract for
any item of the works is, by reason of such varied work,
rendered inappropriate or inapplicable, then, after due
consultation by the Engineer with the Employer and the
218 [2025] 2 S.C.R.
Digital Supreme Court Reports
Contractor, a suitable rate or price shall be agreed upon
between the Engineer and the Contractor. In the event
of disagreement the Engineer shall fix such other rate
or price as is, in his opinion, appropriate and shall notify
the Contractor accordingly, with a copy to the Employer.
Until such time as rates or prices are agreed or fixed, the
Engineer shall determine provisional rates or prices to
enable on-account payments to be included in certificates
issued in accordance with Clause 60.
(COPA)
Where the Contract provides for the payment of the
Contract Price in more than one currency, the amount or
proportion payable in each of the applicable currencies
shall be specified when the rates or prices are agreed, fixed
or determined as stated above, it being understood that
in specifying these amounts or proportions the Contractor
and the Engineer (or, failing agreement, the Engineer)
shall take into account the actual or expected currencies
of cost (and the proportions thereof) of the inputs of the
varied work without regard to the proportions of various
currencies specified in the Appendix to Bid for payment
of the Contract Price.
(GCC)
Provided also that no varied work instructed to be done by
the Engineer pursuant to Clause 51 shall be valued under
Sub-Clause 52.1 or under this Sub-Clause unless, within
14 days of the date of such instruction and, other than
in the case of omitted work, before the commencement
of the varied work, notice shall have been given either:
(a) by the Contractor to the Engineer of his intention
to claim extra payment or a varied rate or price, or
(b) by the Engineer to the Contractor of his intention to
vary a rate or price. (GCC)
(COPA)
Provided further that no change in the rate or price for
any item contained in the Contract shall be considered
[2025] 2 S.C.R. 219
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
unless such item accounts for an amount more than 2
percent of the Contract Price, and the actual quantity of
work executed under the item exceeds or falls short of
the quantity set out in the Bill of Quantities by more than
25 percent.
52.3 Variations Exceeding 15 per cent (GCC)
If, on the issue of the Taking-Over Certificate for the whole
of the works, it is found that as result of :
(a) all varied work valued under Sub-Clauses 52.1 and
52.2 and
(b) all adjustments upon measurement of the estimated
quantities set out in Bill of Quantities, excluding
provisional sums, dayworks and adjustments of price
made under Clause 70.
But not from any other cause, there have been additions to
or deductions from Contract Price which taken together are
in excess of 15 per cent of the “Effective Contract Price”
(which for the purposes of this Sub-Clause shall mean
Contract Price, excluding provisional sums and allowance
for dayworks, if any) then and in such event (subject to
any action already taken under any of Sub-Clauses of this
Clause), after due consultation by the Engineer with the
Employer and the Contractor, there shall be added to or
deducted from Contract Price, such further sum as may
be agreed between the Contractor and Engineer or, failing
agreement, determined by the Engineer having regard to
the Contractor’s site and general overhead costs of the
Contract. The Engineer shall notify the Contractor of any
determination made under this Sub-Clause, with copy
to the Employer. Such sum shall be based only on the
amount by which such additions or deductions shall be
in excess of 15 per cent of the Effective Contract Price.
(COPA)
Where the Contract provides for the payment of the
Contract Price in more than one currency, the amount or
proportion payable in each of the applicable currencies
shall be specified when such further sum is agreed or
220 [2025] 2 S.C.R.
Digital Supreme Court Reports
determined, it being understood that in specifying these
amounts or proportions the Contractor and the Engineer
(or, failing agreement, the Engineer) shall take into account
the currencies (and the proportions thereof) in which the
Contractor’s site and general overhead cost of the Contract
were incurred without being bound by the proportions of
various currencies specified in the Appendix to Bid payment
of the Contract Price.
21. DRB while rejecting the contention of NHAI was of the view that the
design of geogrid is contingent to the height and area of facia panel
within the prescribed length mentioned in the BOQ and based on the
parameters/specifications as prescribed in the agreement, there was
no change in the concept or design. Basically, the design submitted
by the appellant was approved and accepted by the Engineer. Since
the work was done as per the valid approved design, plea taken by
NHAI that there was a change of form in terms of the wall heights and
length of RE wall could not be evidenced by NHAI. After an in-depth
analysis, DRB concluded that there was no change of form but only
a working arrangement. The design having been approved after the
full knowledge of the Engineer that enhancement in quantity to a large
extent was involved and accordingly, the matter was referred by the
Engineer for allocation of funds. Therefore, there was no variation
as per Clause 51.1 or Clause 51.2 and hence payment as per the
BOQ rate should be made for the entire quantity. Though NHAI
had contended that appellant had changed the form and varied the
design, this could not be proved in any way. Therefore, DRB held
that variation in terms of Clause 51.1 could not be established. As
such, DRB recommended that quantities of geogrid required, limited
to the facia area, should be paid as per the BOQ rates.
22. As already noticed, the DRB recommendations were not acceptable
to NHAI which thereafter invoked the arbitration clause. Arbitral
Tribunal comprised of three arbitrators; one each appointed by the
two parties who thereafter appointed the third arbitrator. All the
three arbitrators were technical experts. Arbitral Tribunal referred
to Clause 67.1 of the GCC which says that recommendations of
the DRB shall be binding on both parties giving prompt effect to it
until and unless the same is revised by the Arbitral Tribunal. Arbitral
Tribunal, therefore, was of the view that NHAI should have complied
with the DRB recommendations which was subject to outcome of the
[2025] 2 S.C.R. 221
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
arbitral award. However, NHAI failed to do so. Thereafter, Arbitral
Tribunal framed the core issue to be considered viz. whether as per
the contract, Engineer has the right to revise the rate for additional
quantities of geogrid in excess of the BOQ quantities which are
required for actual execution of the RE wall as per approved design.
After thorough examination of the rival claims, Arbitral Tribunal
recorded the finding that the quantity of geogrid given at the tender
stage which was part of the responsibility of NHAI was found to be
erroneous. Therefore, the increase in quantity was merely to meet
the requirement for completion of the RE wall which was indicated
by the RCC facia quantity at the tender stage. NHAI had admitted
the fact that the design evolved by the appellant’s consultant met
the specified criteria. In other words, there was no change in the
design and NHAI could not establish the same before the Arbitral
Tribunal which held as follows:
8.3 In a contract of the type in question which is an item
rate contract based on the price schedule of provisional
quantities the ultimate contract amount can be ascertained
when all the work done in terms of the contract is finally
measured and the contract amount computation done
on the. basis of the prices and rates set out in the Bill of
Quantities. The contract between the parties, therefore,
is a frame work which determines the parties rights and
obligations. The scope of work in this case was indicated
by RCC facia quantity as mentioned hereinbefore which
determines the length of the RE Wall to be constructed
for raised carriage way and the quantity of other sub-item
i.e. the geogrid quantity to be used is contingent to the
facia quantity. Both the parties knew about the scope of
work of RE Wall in this manner and both knew that it was
impossible to determine the ultimate contract amount before
the completion of RE Wall work and if ultimate quantity
exceeds the BOQ quantity, it will be an automatic change
and shall be paid at BOQ rate in such type of measurement
contracts where the quantities are provisional and ultimate
quantities required for completion of the work are to be
executed and paid as per the quoted rate.
8.4 The fact that ultimate measured amount of work
performed is different from estimated quantity is irrelevant
222 [2025] 2 S.C.R.
Digital Supreme Court Reports
because both the parties contracted on the basis that the
ultimate quantity may increase or decrease.
22.1. On the above basis, Arbitral Tribunal concluded that the
change in quantity did not constitute a variation so as to attract
the provisions of Clause 52.2, further noting that this clause
clearly provides that it would be applicable only in respect
of varied work instructed to be done by the Engineer as per
Clause 51 and that the present was not a case where such
instructions were required. While upholding the interpretation
of the appellant of Clauses 51 and 52, Arbitral Tribunal held
that the Engineer does not possess the power to revise the
rates for additional quantity of geogrid required for actual
execution of the work as per the approved design. Arbitral
Tribunal upheld the recommendations of DRB and passed
the following award:
(i) The variation in terms of Clause 51.1 is not established.
(ii) Claimant (NHAI) was directed to pay the Respondent
(Som Datt Builders - NCC-NEC- JV) the actual quantity
of geogrid required to be executed to complete the work
of RE wall as per the approved design at the BOQ rate.
23. DRB had recorded a finding of fact that there was no change in
the concept or design. As a matter of fact, the design prepared and
submitted by the appellant was approved by the Engineer whereafter
the related work was executed as per the approved design. On the
basis of such finding of fact, DRB interpreted Clauses 51 and 52 to
hold that there was no instructed variation and, therefore, the excess
quantity of geogrid required while executing the work, limited to the
facia area, should be paid as per the BOQ rates. Arbitral Tribunal
reiterated the aforesaid finding of fact and affirmed the interpretation
given by the DRB. On that basis, Arbitral Tribunal concluded that
the change in quantity did not constitute a variation so as to attract
the provisions of Clause 52.2. Arbitral Tribunal concurred with the
DRB that the Engineer did not have the competence to revise the
rates for the additional quantity of geogrid required for execution of
the work as per the approved design.
24. In the proceedings under Section 34 of the 1996 Act, learned Single
Judge examined Clauses 51 and 52 in detail and thereafter opined
that the decision of the Arbitral Tribunal could not be faulted. Analysis
[2025] 2 S.C.R. 223
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
of Clause 51.1 read with the other clauses would indicate that the
variations referred therein are instructed variations. In the present
case, Clause 52 would not come into play since the same arises
only in the case of instructed variations. Learned Single Judge noted
with approval the finding of the Arbitral Tribunal that the ultimate
measured work performed was different from the estimated quantity
but the parties had contracted on the basis that such quantity may
increase or decrease. There was no change in the design in view
of the clear admission of NHAI before the DRB that the design was
reviewed and found according to the specified criteria and that NHAI
was unable to establish any change in the design. Learned Single
Judge while exercising jurisdiction under Section 34 of the 1996 Act
after analysing Clauses 51 and 52 held that the Arbitral Tribunal
had reached the conclusion that the second para of Clause 52.2,
which mandates that the said provision would be applicable only for
varied work instructed to be done by the Engineer as per Clause 51,
was not attracted to the facts of the present case, and therefore,
the Engineer did not give any notice of 14 days of his intention to
vary the rate. Since the matter fell within the domain of uninstructed
variations, there was no need to give 14 days’ notice which is the
requirement in the case of instructed variation.
24.1. Learned Single Judge also referred to a decision of the Appellate
Division of the South African Court in Grinaker Construction
(TVL) Ltd Vs. Transvaal Provincial Administration12, where
similar contractual clauses came up for interpretation. Learned
Single Judge agreed with the interpretation given by the
South African Court that automatic increase or decrease in
the quantity did not form part of the variation.
24.2. Learned Single Judge highlighted the aspect that the
interpretation given to the aforesaid clauses was also the
interpretation arrived at by the DRB as also by the Arbitral
Tribunal. The contractual clauses have been interpreted by
technical people who were well conversant with the nature of
the dispute and for this reason also greater weight has to be
given to such a view. Learned Single Judge held that once
a contracted price is provided and the quantities are held
12 1982 (1) AD 78
224 [2025] 2 S.C.R.
Digital Supreme Court Reports
to be tentative, any increase or decrease in quantity must
be governed by the same price. It is only in respect of any
instructed variation arising from the instruction of the Engineer
on account of any additional work or less work that there can
be some element of renegotiation and determination in terms
of Clauses 51 and 52 of the GCC. Therefore, learned Single
Judge concurred with the view taken by the Arbitral Tribunal
which had affirmed the view of the DRB.
25. Learned Single Judge also reiterated the well-recognised principle in
arbitration that the court exercising jurisdiction under Section 34 of
the 1996 Act does not sit as a court of appeal over the decision of
an arbitral tribunal, further reiterating the proposition that a contract
has to be interpreted by the arbitrator who is the chosen judge of
the parties. So long as the view of the arbitrator is a plausible one
though it may not be the only possible view, there should be no
interference by the court under Section 34 of the 1996 Act.
26. According to us, learned Single Judge had adopted the correct
approach and had rightly declined to interfere with the award of the
Arbitral Tribunal affirming the decision of the DRB.
27. Let us now deal with the impugned order. Division Bench of the
High Court exercising jurisdiction under Section 37 of the 1996
Act acknowledged that primarily it was for the Arbitral Tribunal to
interpret the contractual terms and if the interpretation given by
the Arbitral Tribunal is a plausible one, then the court would not
interfere with the award merely because according to the court,
another interpretation is preferable. Having said that, Division Bench
examined Clauses 51 and 52 of the contract. Instead of interpreting
the aforesaid clauses in the contractual context, Division Bench
went into the dictionary meaning of the expression ‘variation’ and
opined that variation would mean the difference between what
is provided for or contemplated in relation to the work under the
contract and what is the final effect or outcome. Such variation or
outcome may be or may not be the result of an instruction given
by the Engineer. It has further been observed that the instruction
issued by the Engineer to the contractor does not necessarily mean
that the contractor should carry out a ‘variation’. It may relate to
performance of one or more of the specific acts enumerated in
Clause 51.1. According to the Division Bench, variation in quantity,
even when it is not a result of an instruction given under Clause
[2025] 2 S.C.R. 225
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
51.1 by the Engineer to the contractor does not cease to be a
variation within the meaning of that expression used in Clause 51.1.
Division Bench, therefore, opined that there is no basis or underlying
principle stated either by the Arbitral Tribunal or by the learned
Single Judge that only if the variation is the result of instruction
given by the Engineer under Clause 51.1, rates and prices of the
BOQ items in question would be open to renegotiation and not
otherwise; variation in quantity, even when it is not a result of an
instruction given by the Engineer to the contractor under Clause
51.1, does not cease to be a ‘variation’ within the meaning of the
expression used in Clause 51.1.
27.1. Division Bench disagreed with the observations of the
Arbitral Tribunal as upheld by the learned Single Judge that
even if there was error in estimating the quantity of geogrid
while preparing the BOQ, that by itself would not lead to the
conclusion that NHAI cannot seek renegotiation of the rates
even if the actual quantity exceeds by over 300 percent. The
contract does not provide that NHAI should suffer on account
of the estimated quantities mentioned in the BOQ turning out
to be way off the mark when the contract is executed.
27.2. It was on the above basis, Division Bench held that there is
no reason as to why variation in quantity beyond the limits
set out in the contract, whether instructed or not instructed,
should not lead to renegotiation of the rates at the instance
of either party. That would be the only fair, reasonable and
equitable way to work the contract.
27.3. Division Bench, therefore, held that interpretation of the
contractual terms given by the Arbitral Tribunal and accepted
by the learned Single Judge cannot be accepted as a plausible
interpretation. Division Bench observed that such interpretation
is unreasonable and wholly implausible and that the arbitral
award is opposed to the public policy of India, shocking the
conscience of the court. Therefore, the order of the learned
Single Judge as well as the arbitral award were set aside.
28. We are afraid we cannot accept such sweeping conclusions reached
by the Division Bench. Interpretation given by the Division Bench
to the plain language of Clauses 51 and 52 is not at all a plausible
one, not to speak of being the only possible interpretation and,
226 [2025] 2 S.C.R.
Digital Supreme Court Reports
therefore, committed a manifest error in interfering with an arbitral
award in a proceeding under Section 37 of the 1996 Act when the
learned Single Judge did not find any justification at all to interfere
with the arbitral award within the limited scope under Section 34 of
the 1996 Act. A closer look at Clauses 51 and 52 would clearly show
that the view taken by DRB and Arbitral Tribunal, both comprised
of technical experts, is the correct one which was acknowledged by
the learned Single Judge.
29. As per Clause 51.1, Engineer has the competence to make any
variation of the form, quality or quantity of works, either wholly
or any part thereof, if in his opinion, it is necessary to do so. In
that event, Engineer has the authority to instruct the contractor to
carry out the same and the contractor shall in such event would be
under an obligation to do what is contemplated in sub-clauses (a)
to (f) thereunder, such as, increase or decrease in the quantity of
any work included in the contract, etc.. Clause 51.1 clarifies that
such instructed variation shall not vitiate or invalidate the contract,
but such variation shall be valued in accordance with Clause 52.
What Clause 51.2 indicates is that it is not open to the contractor
to make such variation without any instruction from the Engineer.
Proviso to Clause 51.2 is relevant. It says that no instruction from
the Engineer would be required for the increase or decrease in
the quantity of any work where such increase or decrease is not
the result of any instruction given under Clause 51.1 but is the
result of the quantities exceeding or being less than those stated
in the BOQ.
30. Clause 52.2, on the other hand, mentions that all variations referred
to in Clause 51 (which means instructed variations) shall be valued at
the rates and prices in the contract, if in the opinion of the Engineer,
the same is applicable. If the contract does not contain any rates
or prices applicable to the varied works, the rates and prices in
the contract shall be used as the basis for valuation so far it may
be reasonable. If this is not possible, then the Engineer shall carry
out the valuation after due consultation with the Employer and the
contractor. The GCC proviso to Clause 52.2 says that no varied
work instructed to be done by the Engineer shall be valued under
Clause 52.1 or under Clause 52.2 unless 14 days’ notice is given
by either of the parties.
[2025] 2 S.C.R. 227
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
31. The further proviso under COPA to Clause 52.2 says that no change
in the rate or price for any item contained in the contract shall be
considered unless such item accounts for more than 2 percent of
the contract price and the actual quantity of the work executed under
the item exceeds or falls short of the quantity set out in the BOQ by
more than 25 percent.
32. The aforesaid provision is not a mandate for change in the rate or
price for any item contained in the contract, if such item accounts for
an amount which is more than 2 percent of the contract price and
the actual quantity of work executed under the item exceeds or falls
short of the quantity set out in the BOQ by more than 25 percent.
Rather, it is an enabling provision which enables either of the parties
to consider change in the rate or price of any item mentioned in the
contract, in the event, the above two conditions are fulfilled.
33. In so far Clause 51.1 is concerned, the variation contemplated
thereunder relates to the form, quality or quantity of the works which
in the opinion of the Engineer is necessary. In the present case,
there is a clear finding of fact by two authorities i.e. DRB and the
Arbitral Tribunal, both comprised of technical experts, that there is no
variation either in the form or quality or quantity of the works. What
actually happened is that at the time of execution of the contract
pertaining to the RE wall, the geogrid required turned out to be much
more than the estimated figure given in item No. 7.7 of the contract.
It is in this backdrop that both the fact finding authorities held that
there was no variation in terms of Clause 51.1 and that the Engineer
did not have the competence to renegotiate the price or rate of the
geogrid for the excess quantity of geogrid required.
34. As already discussed above, this is clearly a plausible view. In fact,
according to us, it is the correct interpretation of Clause 51 made by
the DRB and the Arbitral Tribunal. As such, learned Single Judge
rightly declined to interfere with the award under Section 34 of the
1996 Act. If that be the position, there was no justification at all for
the Division Bench of the High Court to set aside the award under
Section 37 of the 1996 Act.
35. Though learned counsel for the parties had cited a number of decisions
at the time of hearing, it is not necessary to refer to and discuss
each one of them. However, reference to a few of the judgments
would suffice.
228 [2025] 2 S.C.R.
Digital Supreme Court Reports
36. In MMTC Ltd. Vs. Vedanta Ltd.,13 this Court held that as far as
Section 34 is concerned, the position is well settled that the court
does not sit in appeal over an arbitral award and may interfere on
merits only on the limited ground provided under Section 34(2)(b)(ii)
i.e. if the award is against the public policy of India. Even then, the
interference would not entail a review on the merits of the dispute
but would be limited to situations where the findings of the arbitrator
are arbitrary, capricious or perverse or when the conscience of the
court is shocked or when the illegality is not trivial but goes to the
root of the matter. An arbitral award may not be interfered with if the
view taken by the arbitrator is a possible view based on facts. As far
as interference with an order made under Section 34 by the court
under Section 37 is concerned, it has been held that such interference
under Section 37 cannot travel beyond the restrictions laid down
under Section 34. In other words, the court cannot undertake an
independent assessment of the merits of the award and must only
ascertain that the exercise of power by the court under Section 34
has not exceeded the scope of the provision.
37. What is public policy of India has been explained in Ssangyong
Engineer and Construction Company Ltd. (supra). It means the
fundamental policy of Indian law. Violation of Indian statutes linked
to public policy or public interest and disregarding orders of superior
courts in India would be regarded as being contrary to the fundamental
policy of Indian law. It would also mean that the arbitral award is
against basic notions of justice or morality. An arbitral award can be
set aside on the ground of patent illegality i.e. where the illegality
goes to the root of the matter but re-appreciation of evidence cannot
be permitted under the ground of patent illegality.
38. In PSA Sical Terminals Private Ltd. (supra), this Court reiterating
the well settled principles held as under:
40. It will thus appear to be a more than settled legal
position, that in an application under Section 34, the court is
not expected to act as an appellate court and reappreciate
the evidence. The scope of interference would be limited
to grounds provided under Section 34 of the Arbitration
Act. The interference would be so warranted when the
13 [2019] 3 SCR 1023 : (2019) 4 SCC 163
[2025] 2 S.C.R. 229
Somdatt Builders-NCC-NEC(JV) v.
National Highways Authority of India & Ors.
award is in violation of “public policy of India”, which has
been held to mean “the fundamental policy of Indian law”.
A judicial intervention on account of interfering on the
merits of the award would not be permissible. However,
the principles of natural justice as contained in Sections
18 and 34(2)(a)(iii) of the Arbitration Act would continue to
be the grounds of challenge of an award. The ground for
interference on the basis that the award is in conflict with
justice or morality is now to be understood as a conflict
with the “most basic notions of morality or justice”. It is
only such arbitral awards that shock the conscience of
the court, that can be set aside on the said ground. An
award would be set aside on the ground of patent illegality
appearing on the face of the award and as such, which
goes to the roots of the matter. However, an illegality with
regard to a mere erroneous application of law would not
be a ground for interference. Equally, reappreciation of
evidence would not be permissible on the ground of patent
illegality appearing on the face of the award.
41. A decision which is perverse, though would not be a
ground for challenge under “public policy of India”, would
certainly amount to a patent illegality appearing on the face
of the award. However, a finding based on no evidence at
all or an award which ignores vital evidence in arriving at
its decision would be perverse and liable to be set aside
on the ground of patent illegality.
39. In Reliance Infrastructure Ltd. (supra), this Court referring to one
of its earlier decisions in UHL Power Company Ltd. Vs. State of
Himachal Pradesh,14 held that scope of interference under Section 37
is all the more circumscribed keeping in view the limited scope of
interference with an arbitral award under Section 34 of the 1996
Act. As it is, the jurisdiction conferred on courts under Section 34
of the 1996 Act is fairly narrow. Therefore, when it comes to scope
of an appeal under Section 37 of the 1996 Act, jurisdiction of the
appellate court in examining an order passed under Section 34,
either setting aside or refusing to set aside an arbitral award, is all
the more circumscribed.
14 (2022) 4 SCC 116
230 [2025] 2 S.C.R.
Digital Supreme Court Reports
40. Again in M/s Larsen Air Conditioning and Refrigeration Company
(supra), this Court reiterated the position that Section 37 of the
1996 Act grants narrower scope to the appellate court to review the
findings in an arbitral award if it has been upheld or substantially
upheld under Section 34.
41. This Court in M/s. Hindustan Construction Company Ltd. (supra)
declared that it is the settled jurisprudence of the courts in the country
that arbitral awards which contain reasons especially when they
interpret contractual terms ought not to be interfered with lightly. An
error in the interpretation of contractual terms by an arbitrator is an
error within his jurisdiction and would, therefore, not be a ground to
interfere with an arbitral award.
42. As already discussed above, the Arbitral Tribunal had interpreted
Clause 51 in a reasonable manner based on the evidence on record.
This interpretation was affirmed by the learned Single Judge exercising
jurisdiction under Section 34 of the 1996 Act. Therefore, Division Bench
of the High Court was not at all justified in setting aside the arbitral
award exercising extremely limited jurisdiction under Section 37 of
the 1996 Act by merely using expressions like ‘opposed to the public
policy of India’, ‘patent illegality’ and ‘shocking the conscience of the
court’. As reiterated by this Court in Reliance Infrastructure Ltd. (supra),
it is necessary to remind the courts that a great deal of restraint is
required to be shown while examining the validity of an arbitral award
when such an award has been upheld, wholly or substantially, under
Section 34 of the 1996 Act. Frequent interference with arbitral awards
would defeat the very purpose of the 1996 Act.
43. For all the aforesaid reasons, we are of the unhesitant view that the
impugned order cannot be sustained. Accordingly, judgment and
order dated 17.11.2009 passed by the Division Bench of the High
Court is hereby set aside and the arbitral award dated 03.06.2005 is
restored. Consequently the appeal is allowed. However, there shall
be no order as to cost.
Result of the case: Appeal allowed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.