Created byFuzzy Cloud

Supreme Court of India

SUBODH KUMAR SINGH RATHOURversusTHE CHIEF EXECUTIVE OFFICER & ORS.

Citation
2024 INSC 486
Decided
9 July 2024
Disposal
Case Allowed

Holding

The cancellation of the tender was arbitrary, capricious and violative of Article 14, making the writ petition maintainable and the notice of cancellation quashed.

Summary

The appellant was awarded a PPP tender by the Kolkata Metropolitan Development Authority (KMDA) to maintain two underpasses, but KMDA later cancelled the tender citing alleged technical faults and a policy change. The appellant challenged the cancellation via a writ petition, which the High Court upheld, holding the cancellation was within administrative discretion. On appeal, the Supreme Court examined the scope of judicial review of State actions in contractual matters, emphasizing the public law element and the requirement of fairness under Article 14. It scrutinised internal file‑notings, which revealed that the cancellation was prompted by a minister’s instruction, not by any technical defect or genuine policy need, and was therefore arbitrary, capricious and violative of Article 14. The Court quashed the notice of cancellation, set aside the High Court’s order, and restored the appellant’s vested rights.

Issues considered

  • The scope of judicial review of State actions in contract/tender disputes under writ jurisdiction.
  • Whether the cancellation of the tender by KMDA is amenable to writ jurisdiction.
  • Whether the cancellation was arbitrary or unfair, thereby violating Article 14 of the Constitution.

Legislation cited

Subjects

contract/tender disputesjudicial reviewwrit jurisdictionArticle 14arbitrarinesspublic‑private partnershippublic law elementadministrative discretioninternal file notingsministerial directioncancellation of tenderpublic interestfairnessreasonableness

Judgment

                 [2024] 7 S.C.R. 532 : 2024 INSC 486

                    Subodh Kumar Singh Rathour
                                 v.
                  The Chief Executive Officer & Ors.
                       (Civil Appeal No. 6741 of 2024)
                                  09 July 2024
                [Dr. Dhananjaya Y. Chandrachud, CJI,
                J.B. Pardiwala* and Manoj Misra, JJ.]

                            Issue for Consideration
       Scope of judicial review of the actions of the State in the matters
       relating to contract/tender disputes under writ jurisdiction; whether
       the action on the part of the respondent in cancelling the tender
       was amenable to the writ jurisdiction of the High Court; if so,
       whether the said action could be termed as arbitrary or unfair
       and in consequence of violation of Article 14 of the Constitution
       of India.

                                  Headnotes†
       Contract/tender disputes – Judicial review – Scope – Tender
       awarded to the appellant on Public-Private Partnership basis
       for maintenance of two underpasses was cancelled by the
       respondent-Kolkata Metropolitan Development Authority
       stating that there was a technical fault therein and also on
       account of a change in policy whereby, the operation &
       maintenance of the concerned underpasses was handed over
       to another authority – Action to cancel the tender, if amenable
       to writ jurisdiction and whether was arbitrary and influenced
       by extraneous considerations:
       Held: The tender was not terminated pursuant to any terms of the
       contract subsisting between the parties – Respondent cancelled
       the tender saying that there was technical fault in the tender
       that was floated – Thus, the respondent exercised powers in its
       executive capacity as the action to cancel the tender fell outside
       the purview of the terms of the contract – Hence, the present
       matter is not purely a contractual dispute even if related to a
       tender, as the dispute involves a public law element – Although
       there is no discharge of a public function by the respondent


* Author
[2024] 7 S.C.R.                                                              533

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     towards the appellant yet there is a right to public law action
     vested in him against the respondent in terms of Article 14 – Thus,
     writ petition filed by the respondent was maintainable and the
     relief prayed for could have been considered by the High Court
     in exercise of its writ jurisdiction – On facts, just a month prior to
     cancelling the tender, the respondent issued work stop notice to
     the appellant, asking to stop all work in respect of the tender in
     view of the handing over of the operation & maintenance of the
     concerned underpasses by the respondent to another authority,
     Kolkata Municipal Corporation – Appellant pointed out that the
     work stop orders were misconceived as the respondent continued
     to retain the custody as well as the advertisement rights of the
     concerned underpasses – As such the respondent even after
     the change in policy, remained well within its rights to continue
     charging license fee in lieu of the advertisement rights by way
     of the tender issued to the appellant – Change in policy had no
     bearing on the cancellation of the tender – It was only after the
     appellant highlighted why the work stop orders were misconceived
     and uncalled for, that the respondent immediately flipped its stance
     and in its notice of cancellation that was issued just 1-month
     later, it attributed ‘technical faults’ in the tender – Furthermore,
     although the internal-file notings mention about the policy change
     in the operation and maintenance of the concerned underpasses,
     however, the cancellation of the tender for work was neither due
     to any technical fault nor due to the policy change but it was at
     the behest of the concerned minister who suggested to cancel the
     tender – The concerned minister’s decision to cancel the tender on
     account of purported ‘change in policy’ was without any application
     of mind, capricious and influenced by malice – Cancellation of the
     tender was not in public interest – Present lis is a classic case of
     an arbitrary and capricious exercise of powers by the respondent
     to cancel the tender on the basis of extraneous considerations
     and at the behest of the concerned Minister-In-Charge – Notice
     of cancellation was non-est, quashed – Impugned judgment of
     the High Court upholding the decision of the respondent to cancel
     the tender, set aside. [Paras 60-62, 103-105, 107, 122]
     Contract/tender disputes – Involving State or its
     instrumentalities – Administrative actions of the State –
     Judicial Review – Shift in the scope of – Earlier position of
     law; misconception of the State as a Largesse – Concept of
     ‘Public Law’ Element in contractual matters – Development
534                                                            [2024] 7 S.C.R.

                       Digital Supreme Court Reports


       of principles of natural justice, reasonableness and
       proportionality – Judicial review and administrative discretion
       – Interplay between – Discussed.
       Administrative Law – Internal-file notings – Judicial review –
       Constitution of India – Article 14 – Tender awarded to the
       appellant was cancelled by the respondent-Authority on the
       ground that there was a technical fault therein – Challenge
       to – Appellant relied on various notings made in the internal
       file of the respondent in respect of the tender to contend
       that the cancellation thereof was arbitrary and influenced by
       extraneous considerations:
       Held: Once a decision has been officially made through proper
       means and channel, any internal deliberations or file notings
       that formed a part of that decision-making process can certainly
       be looked into by the Court for the purposes of judicial review
       in order to satisfy itself of the impeccability of the said decision
       and whether it conforms to the principles enshrined in Article
       14 of the Constitution – In the present case, if the purported
       action of cancelling the tender was claimed to have been taken
       in view of certain technical faults in the same or even a change
       in policy, the same ought to be clearly reflected from its internal
       file notings as-well, pursuant to which the purported decision
       was taken – However, in the entire records, there is no whisper
       of any particular clauses of the tender that was floated nor of
       any conflict or technical fault in the same, as claimed by the
       respondent – From the internal-file notings it is evident that the
       notice of cancellation issued to the appellant was at the behest
       of the concerned minister – Respondent recorded that, because
       instructions for cancellation were received from the higher-ups,
       there was no option but to proceed with the cancellation – Even
       before the respondent could properly and thoroughly explore the
       possibility of acceding to such request by consulting its legal
       cell, the tender was cancelled only at the instance and specific
       instructions of the concerned minister. [Paras 85, 90]
       Contract/tender disputes – Administrative Decisions – Public
       Interest – Potential financial losses – Possibility of fetching
       higher license fees if can be a ground to cancel the tender:
       Held: No – Any decision to terminate a contract must be grounded
       in a real and palpable public interest, duly supported by cogent
[2024] 7 S.C.R.                                                             535

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     materials and circumstances in order to ensure that State actions
     are fair, transparent, and accountable – Public interest cannot
     be used as a pretext to arbitrarily terminate contracts and there
     must be a clear and demonstrable ramification or detriment on
     the public interest to justify any such action – Considerations
     of public interest should not be narrowly confined to financial
     aspects – Courts must have a more holistic understanding of
     public interest wherever the fairness of public authorities is in
     question, giving due regard to the broader implications of such
     action on the stability of contractual obligations – Merely because
     the financial terms of a contract are less favourable over a period
     of time does not justify its termination – Respondent’s stance of a
     mere possibility of fetching higher license fees was no ground to
     cancel the tender for the purposes of rectifying it, especially when
     it failed to demonstrate as to how there was a technical fault in
     the tender or how potential interested bidders did not participate
     due to it or how fetching higher license fees was more than a
     mere possibility. [Paras 115, 116, 118]
     Tenders – Sanctity of Public-Private Partnership Tenders –
     Termination of tenders – Public authorities cautioned – Duty
     of Courts:
     Held: Public tenders are a cornerstone of governmental
     procurement processes, ensuring transparency, competition, and
     fairness in the allocation of public resources – It emanates from the
     Doctrine of Public Trust which lays down that all natural resources
     and public use amenities & structures are intended for the benefit
     and enjoyment of the public – Public tenders are designed to
     provide level playing field for all potential bidders – Its sanctity
     lies in their role in upholding the principles of equal opportunity
     and fairness – Once a contract has come into existence through a
     valid tendering process, its termination must adhere strictly to the
     terms of the contract, with the executive powers to be exercised
     only in exceptional cases by the public authorities and that too in
     loathe – Arbitrary terminations of contract create uncertainty and
     unpredictability, thereby discouraging public participation in the
     tendering process – Courts are duty bound to zealously protect the
     sanctity of any tender duly conducted and concluded by ensuring
     that the larger public interest of upholding bindingness of contracts
     are not sidelined by a capricious or arbitrary exercise of power by
     the State – Failure on the part of the courts to zealously protect
536                                                              [2024] 7 S.C.R.

                        Digital Supreme Court Reports


       the binding nature of a lawful and valid tender, would erode
       public faith in contracts and tenders – Public authorities also to
       be circumspect in disturbing or wriggling out of its contractual
       obligations through means beyond the terms of the contract in
       exercise of their executive powers. [Paras 124-126]
       Contractual disputes – Judicial review – Amenability to
       writ jurisdiction – Private law element vis-à-vis public law
       element – Demarcation – Assessment:
       Held: Demarcation between a private law element and public law
       element in the context of contractual disputes, may be assessed
       by ascertaining whether the dispute or the controversy pertains
       to the consensual aspect of the contract or tender in question or
       not – Judicial review does not extend to fixing contract stipulations
       but ensures that the public authorities act within their authority to
       prevent arbitrariness – Judicial review is permissible to prevent
       arbitrariness of public authorities and to ensure that they do not
       exceed or abuse their powers in contractual transactions and
       requires overseeing the administrative power of public authorities
       to award or cancel contracts or any of its stipulations – Although
       disputes arising purely out of contracts are not amenable to writ
       jurisdiction yet keeping in mind the obligation of the State to act
       fairly and not arbitrarily or capriciously, when contractual power is
       being used for public purpose, it is certainly amenable to judicial
       review. [Paras 57-59]
       Contract/tender disputes – Contractual disputes concerning
       public authorities – Arbitrary exercise of powers by public
       functionaries – Challenge to – Constitution of India – Article
       14 – Duty of Courts:
       Held: Where State action is challenged on the ground of being
       arbitrary, unfair or unreasonable, the State would be under an
       obligation to comply with the basic requirements of Article 14
       and not act in an arbitrary, unfair and unreasonable manner –
       This is the constitutional limit of their authority – There is a jural
       postulate of good faith in business relations and undertakings
       which is given effect to by preventing arbitrary exercise of powers
       by the public functionaries in contractual matters with private
       individuals – With the rise of the Social Service State more and
       more public-private-partnerships continue to emerge, which makes
       it all the more imperative for the courts to protect the sanctity of
       such relation. [Para 56]
[2024] 7 S.C.R.                                                             537

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     Contract – Contractual disputes – Arbitrariness of State
     actions – Meaning and Import of – Test of reasonableness –
     Vice of arbitrariness – When attracted:
     Held: The question, whether an impugned action is arbitrary or
     not, is to be answered on the facts and in the circumstances of a
     given case – An obvious test to apply is to see whether there is
     any discernible principle emerging from the impugned act and if
     so, does it satisfy the test of reasonableness – Where a mode is
     prescribed for doing an act and there is no impediment in following
     that procedure, the performance of the act otherwise and in a
     manner which does not disclose any discernible principle which
     is reasonable, may itself attract the vice of arbitrariness – Every
     State action must be informed by reason and an act uninformed
     by reason, is arbitrary – To enthuse efficiency in administration,
     a balance between accountability and autonomy of action should
     be carefully maintained – Whether the public authority acted bona
     fide would be gauged from the impugned action and attending
     circumstances – The authority should justify the action assailed
     on the touchstone of justness, fairness and reasonableness –
     Test of reasonableness is more strict – Supporting an order with
     a rationale which in the circumstances is found to be reasonable
     will go a long way to repel a challenge to State action – The
     reasons need not in every case be part of the order as such – If
     there is absence of good faith and the action is actuated with an
     oblique motive, it could be characterised as being arbitrary – A
     total non-application of mind without due regard to the rights of
     the parties and public interest may be a clear indicator of arbitrary
     action – Another way to assess whether an action complained of
     could be termed as arbitrary is by scrutinizing the reasons assigned
     to such an action – However, the Court is not supposed to delve
     into every minute details of the reasoning assigned, but should
     only see whether the reasons were earnest, genuine and had a
     rationale with the ultimate decision – What is under scrutiny in
     judicial review of an action is the decision-making process and
     whether there is any element of arbitrariness or mala fide – Thus,
     the question to be answered in such situations is whether the
     decision was based on valid considerations. [Paras 65, 67, 69-71]

                              Case Law Cited
     Pimpri Chinchwad New Township Development Authority v.
     Vishnudev Coop. Housing Society [2018] 11 SCR 310 : (2018)
538                                                         [2024] 7 S.C.R.

                      Digital Supreme Court Reports


       8 SCC 215; Shanti Sports Club v. Union of India [2009] 13 SCR
       710 : (2009) 15 SCC 705 – distinguished.
       Radhakrishna Agarwal & Ors. v. State of Bihar & Ors. [1977]
       3 SCR 249 : (1977) 3 SCC 457; Premji Bhai Parmar & Ors. v.
       Delhi Development & Ors. [1980] 2 SCR 704 : (1980) 2 SCC
       129; Divisional Forest Officer v. Bishwanath Tea Co. Ltd. [1981]
       3 SCR 662 : (1981) 3 SCC 238; Bareilly Development Authority
       & Anr. v. Ajai Pal Singh & Ors. [1989] 1 SCR 743 : (1989) 2
       SCC 116; M/s Indian Medicines Pharmaceuticals Corp Ltd. v.
       Kerala Ayurvedic Co-operative Society Ltd. [2023] 1 SCR 473 :
       (2023) SCC OnLine SC 5; M.C. Mehta v. Union of India [1987]
       1 SCR 819 : (1987) 1 SCC 395; Mahabir Auto Stores & Ors. v.
       Indian Oil Corporation [1990] 1 SCR 818 : (1990) 3 SCC 752;
       Dwarkadas Marfatia & Sons v. Board of Trustees of the Port of
       Bombay [1989] 2 SCR 751 : (1989) 3 SCC 293; LIC v. Consumer
       Education & Research Centre [1995] Supp. 1 SCR 349 : (1995)
       5 SCC 482; Shrilekha Vidyarthi (Kumari) v. State of U.P. [1990]
       Supp. 1 SCR 625 : (1991) 1 SCC 212; Verigamto Naveen v.
       Govt. of A.P. & Ors. [2001] Suppl. 3 SCR 112 : (2001) 8 SCC
       344; Binny Ltd. & Anr. v. Sadasivan & Ors. [2005] Supp. 2
       SCR 421 : (2005) 6 SCC 657; ABL International Ltd. v. Export
       Credit Guarantee Corporation of India Ltd. (2004) 3 SCC 553;
       Noble Resources Ltd. v. State of Orissa [2006] Supp. 6 SCR
       53 : (2006) 10 SCC 236; Joshi Technologies International Inc.
       v. Union of India & Ors. [2015] 6 SCR 1042 : (2015) 7 SCC
       728; M.P. Power Management Co. Ltd., Jabalpur v. Sky Power
       Southeast Solar India Pvt. Ltd. & Ors. [2022] 5 SCR 1 : (2023)
       2 SCC 703; Ramana Dauaram Shetty v. The International Airport
       Authority of India & Ors. [1979] 3 SCR 1014 : AIR 1979 SC
       1628; Mahesh Chandra v. Regional Manager, U.P. Financial
       Corporation & Ors. [1992] 1 SCR 616 : (1993) 2 SCC 279;
       Tata Cellular v. UOI [1994] Supp. 2 SCR 122 : (1994) 6 SCC
       651; Bachhittar Singh v. State of Punjab & Anr. [1962] Supp. 3
       SCR 713 : AIR 1963 SC 395; Delhi Development Authority v.
       Hello Home Education Society (2024) 3 SCC 148; Mahadeo &
       Ors. v. Sovan Devi & Ors. [2022] 11 SCR 153 : (2023) 10 SCC
       807; Municipal Committee, Barwala v. Jai Narayan and Co. &
       Anr. [2022] 16 SCR 897 : (2022) SCC OnLine 376; Sethi Auto
[2024] 7 S.C.R.                                                               539

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     Service Station v. DDA [2008] 14 SCR 598 : (2009) 1 SCC 180;
     State of Uttaranchal v. Sunil Kumar Vaish [2011] 13 SCR 754 :
     (2011) 8 SCC 670; State of Bihar v. Kripalu Shankar [1987] 3
     SCR 1 : (1987) 3 SCC 34; Vice Chariman & Managing Director,
     City & Industrial Development Corporation of Maharashtra Ltd.
     & Anr. v. Shishir Realty Pvt. Ltd. & Ors. [2021] 13 SCR 190 :
     (2021) SCC OnLine SC 1141; Vasantkumar Radhakisan Vora
     (Dead) by His Lrs. v. Board of Trustees of the Port of Bombay
     [1990] 3 SCR 825 : (1991) 1 SCC 761; Har Shankar & Ors. v. Dy.
     Excise and Taxation Commr. & Ors. [1975] 3 SCR 254 : (1975) 1
     SCC 737; Nagar Nigam v. Al. Farheem Meat Exporters Pvt. Ltd.
     [2006] Supp. 10 SCR 354 : (2006) 13 SCC 382; Sivanandan
     C.T. v. High Court of Kerala [2023] 11 SCR 674 : (2024) 3 SCC
     799 – referred to.

                                 List of Acts
     Constitution of India.

                              List of Keywords
     Contract/tender disputes; Contractual matters; Operation &
     maintenance of underpasses; Advertisement rights of the
     underpasses; Judicial review; Writ jurisdiction; Amenability to writ
     jurisdiction; Public-Private Partnership basis; Notice of cancellation;
     Tender cancelled/terminated; Tender cancelled at the behest
     of the minister; Administrative actions of the State; Arbitrary;
     Unfair; Unreasonable; Influenced by extraneous considerations;
     Non-application of mind; Capricious exercise of powers; Malice;
     Contractual disputes; Dispute not purely contractual; Public law
     element; Private law element; Right to public law action; Work stop
     notice/order; Handing over of the operation & maintenance of the
     underpasses; Change in policy, License fee in lieu of advertisement
     rights; Technical faults in the tender floated; Cancellation of the
     tender not in public interest; Administrative discretion; Internal
     file notings; Public interest; Potential financial losses; Possibility
     of fetching higher license fees; Arbitrariness; Arbitrariness of
     State actions; Administrative decisions; Test of reasonableness;
     Vice of arbitrariness; Wednesbury principle of reasonableness;
     Public tenders; Principles of natural justice, reasonableness and
     proportionality; Valid considerations; Bona-fide.
540                                                           [2024] 7 S.C.R.

                              Digital Supreme Court Reports


                                       Case Arising From

       CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6741 of 2024
       From the Judgment and Order dated 25.05.2023 of the High Court
       at Calcutta in MAT No. 744 of 2023

                                   Appearances for Parties

       Shyam Divan, Sr. Adv., Ateev Mathur, Ajay Monga, Sanjay Gupta,
       Ms. Varsha Kriplani, Anmol Sharma, Ananta Prasad Mishra, Advs.
       for the Appellant.
       Rakesh Dwivedi, Sr. Adv., Zoheb Hossain, Advs. for the Respondents.

                       Judgment / Order of the Supreme Court

                                             Judgment
       J.B. PARDIWALA, J.
       For the convenience of exposition, this judgment is divided in the
       following parts: -
                                                   INDEX*

        A. FACTUAL MATRIX                                                2

        B. IMPUGNED ORDER                                                7

        C. DEVELOPMENTS THAT OCCURRED DURING THE 10
           PENDENCY OF THE PRESENT APPEAL.

        D. SUBMISSIONS ON BEHALF OF THE APPELLANT                        15

        E. SUBMISSIONS ON BEHALF OF THE RESPONDENT                       17

        F. POINTS FOR DETERMINATION                                      18

        G. ANALYSIS                                                      19

               i.    Scope of Judicial Review of the actions of the 19
                     State in matters relating to Contract / Tender
                     under Writ Jurisdiction.


* Ed. Note: Pagination as per the original Judgment.
[2024] 7 S.C.R.                                                         541

     Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.



                  a. Earlier Position of Law and Misconception of the 19
                     State as a Largesse.

                  b. Concept of ‘Public Law’ Element: Scope of 25
                     Judicial Review in Contractual Matters.

                  c. Meaning and True Import of Arbitrariness of State 47
                     Actions in Contractual Disputes.

             ii. Whether the action of cancelling the tender is 53
                 arbitrary or unfair and in consequence of violation
                 of Article 14 of the Constitution?

                  a. Scrutiny of Internal File-Notings and Deliberations 55
                     of the State.

                  b. Concept of Public Interest in Administrative 69
                     Decisions.

             iii. Sanctity of Public-Private Partnership Tenders        77

        H. FINAL CONCLUSION                                             81


1.      This appeal arises out of the final judgment and order dated
        25.05.2023 passed by the High Court of Calcutta in M.A.T. No.
        744 of 2023 (“Impugned Order”), by which the High Court upheld
        the decision of the respondent to cancel the tender that had been
        awarded to the appellant for the maintenance of two underpasses
        on Public-Private Partnership basis, and thereby dismissed the writ
        appeal filed by the appellant.
        A.   FACTUAL MATRIX
2.      The respondent floated a tender notice dated 12.05.2022 inviting bids
        for the maintenance of two underpasses on the Eastern Metropolitan
        Bypass and its abutting area against a License Fee for Advertisement
        Rights over designated sites at each underpass, for a period of
        10-years. As per the aforesaid tender, the scope of work included
        the regular maintenance of the aforementioned underpasses and
        the upkeep of its garden area and electro-mechanical fittings. The
        relevant portion reads as under: -
542                                                                [2024] 7 S.C.R.

                        Digital Supreme Court Reports



       Sl.   Name of Work        License Fee of the   Earnest       Allotted Time
       No                        Yearly Charge for    Money         Period for
                                 the 1st year (Rs.)   (Rs.)         License & Work

       (1)   (2)                 (3)                  (4)           (5)

             REGULAR
             MAINTENANCE
             OF BELIAGHATA
             UNDERPASS        TO BE QUOTED            5,00,000.00 10 (Ten) Years
             INCLUDING
             UPKEEPING OF                             [Rupees
             UNDERPASS                                Five Lakh
             PROPER, GARDEN                           Only]
             AREA, AT GRADE
             UNDERPASS
             AREA AND                                 Online
             ALL ELECTRO-                             (Net
             MECHANICAL                               Banking/
             FITTINGS AGAINST                         NEFT/
             LICENSE FEE OF                           RTGS)
             ADVERTISEMENT
             RIGHTS OVER (10)
             YEARS.
             Tender ID – 2022_
             KMDS_380215_1

             REGULAR
             MAINTENANCE
             OF SWABHUMI
             UNDERPASS
             INCLUDING
             UPKEEPING OF                             5,00,000.00
             UNDERPASS                                [Rupees
             PROPER, GARDEN                           Five Lakh
             AREA, AT GRADE   TO BE QUOTED                          10 (Ten) Years
                                                      Only]
             UNDERPASS
             AREA AND
             ALL ELECTRO-                             Online
             MECHANICAL
             FITTINGS AGAINST                         (Net
             LICENSE FEE OF                           Banking/
             ADVERTISEMENT                            NEFT/
             RIGHTS OVER (10)                         RTGS)
             YEARS.
             Tender ID – 2022_
             KMDS_380215_1
[2024] 7 S.C.R.                                                               543

     Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


3.      Pursuant to the aforesaid, the tendering process was undertaken
        and the appellant herein on 13.06.2022 submitted his bid with a
        quotation of Rs. 29,55,555/- for the Beliaghata Underpass and Rs.
        23,55,555/- for the Swabhumi Underpass. Out of the total bids
        received, the appellant’s quotations were found to be the highest
        and was classified as ‘H1’ for both the underpasses.
4.      Accordingly, the respondent issued two Letter of Intents dated
        27.06.2022 in favour of the appellant, accepting the quotation
        offered by him and declaring his firm as the successful bidder for
        the aforementioned tender, and a formal Memorandum of Tender
        for Work was executed and issued to the appellant.
5.      As per the Memorandum of Tender for Work, the detailed ‘Scope
        of Work’ inter-alia included (i) the sweeping of floors & cleaning of
        the walls, stairwell, escalators, railings and glass-fixtures, (ii) regular
        emptying of dustbins and removal / processing of waste trash, (iii)
        upkeep of the garden and plants and (iv) the maintenance of light-
        fittings, escalators, water pumps and other electro-mechanical fixtures.
6.      Furthermore, the Special Terms & Conditions of the Memorandum,
        more particularly Clause 35 therein stipulated that the contract would
        be liable to be terminated inter-alia in the event of any failure, breach
        or non-compliance of any of the obligations or terms delineated in
        the tender by the successful bidder.
7.      Upon completion of all the formalities, the Work Orders dated
        18.10.2022 were issued by the Executive Engineer, pursuant to
        which the appellant commenced his work in terms of the contract.
8.      On 01.12.2022, the Urban Development and Municipal Affairs
        Department, Government of West Bengal issued an Order directing
        that the maintenance of the roads and drainage of the E.M. Bypass
        including the two subject underpasses shall be handed over by
        the Kolkata Metropolitan Development Authority (KMDA) i.e., the
        respondent herein to the Kolkata Municipal Corporation (KMC). The
        said order reads as under: -
                     “Government of West Bengal
          Urban Development and Municipal Affairs Department
                      NAGARYAN, DF-8, Sector-I
                      Salt Lake, Kolkata - 700 064
               Memo No. 5783 – UDMA-22012(14)/11/2022
                                                Date : 01.12.2022
544                                                          [2024] 7 S.C.R.

                      Digital Supreme Court Reports


                                     ORDER
           KMDA was the custodian for the maintenance of the E.M
           Bypass connecting the northern and southern part of the
           city and starts from northern hub Ultadanga to Garia in the
           South. The road length is 15.6 Km which runs along the
           eastern ring of the city. After careful consideration it has
           been decided that the maintenance of the road alongwith
           the drainage be handed over from KMDA to KMC with the
           following scope of activities.
           (1)   The defects in carriageway would be maintained and
                 restored by KMC henceforth.
           (2)   The existing carriageway alongwith the surface and
                 underground drainage would be maintained by KMC.
                 The conservancy in and around the Eastern Bypass
                 would also be maintained by KMC.
           (3)   Subject to clearance from KMDA, KMC would issue
                 NOC to all utility and service providers. The cost of
                 road restoration from the charges to be levied is to
                 be paid to KMC by all utility and service providers.
           (4)   The right of collecting revenues from the advertisement
                 displays will remain with KMDA.
           (5)   All the structures, as the new or old Bridges, Culverts,
                 FoBs etc. will be under the custody of KMDA.
           (6)   All development activities along the road except for the
                 Bridges, Culverts, FoBs etc. will be taken up by KMC.
           (7)   KMC would remain custodian for illumination of the
                 Bypass.
           (8)   The green verge along the E.M. Bypass to be
                 maintained by KMC.
           The order is issued in the interest of public service.
                                                                  Sd/-
                                                   Principal Secretary
                                          to the Govt. of West Bengal”
9.     As per the aforesaid Order dated 01.12.2022, the maintenance and
       restoration of carriageway, structures, underground drainage and
[2024] 7 S.C.R.                                                         545

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     development activities of the E.M. Bypass Area was taken over by
     the KMC. However, the Order specifically, clarified that the right of
     collecting revenue from advertisements displayed would continue to
     remain with the KMDA.
10. Thereafter, in light of the aforesaid order, the Executive Engineer,
    KMDA under instructions issued by the competent authorities sent a
    notice dated 24.01.2023 to the appellant herein asking him to stop
    all work in respect of the maintenance of the two underpasses with
    immediate effect in view of the handing over of the maintenance of
    the E.M. Bypass to the KMC.
11. In response to the above, the appellant sent a letter dated 25.01.2023
    inter-alia pointing out that as per the Urban Development and
    Municipal Affairs Department’s Order dated 01.12.2022, the custody
    and rights of revenue of all structures, bridges, culverts etc. including
    the concerned underpasses, continued to remain with the respondent,
    and requested to recall the notice dated 24.01.2023 asking him to
    stop the work.
12. However, on 07.02.2023, the respondent issued one another notice
    to the appellant stating that the tender for work of maintenance has
    been cancelled on account of a technical fault in the tender. It was
    stated therein that the tender was found to be ‘non-specific’ & ‘not
    well defined’ and that had created ambiguity resulting in financial
    losses to the respondent. The said Notice of Cancellation reads
    as under: -
                                                    “Date: 07.02.2023
           To,V.S. Advertising,
           65/268, M.N. Sarkar Road,
           Siliguri, West Bengal 7340001
                       Sub: Cancellation of Work/Tender
           Sir,
           The cited tender is hereby cancelled by the Authority in
           KMDA. We would state with regret that the tender has
           been found having technical fault, non-specific and not
           well defined thus creating ambiguity for obvious reasons.
           By this, the Authority is incurring financial loss as well.
546                                                           [2024] 7 S.C.R.

                       Digital Supreme Court Reports


            We regret for the inconvenience caused to you and are
            ready to reimburse the cost you have so far incurred in
            the work. This has been decided that the license fee
            deposited by you and the cost incurred for construction
            activity and maintenance work would be refunded as per
            actual assessment by the divisional engineers based upon
            the approved drawing and execution.
            This is for your information with kind compliance please.
                                                                  Sd/-
                                            Chief Engineer-II (Bridge)
                                      Roads & Bridges Sector, KMDA”
13. It is pertinent to note from the aforesaid that, no reference was made
    as regards handing over of the maintenance to KMC which was
    previously alluded to, for stopping all work pertaining to the tender.
       B.   IMPUGNED ORDER
14. Aggrieved by the aforesaid, the appellant preferred a writ petition
    being WPA No. 3381 of 2023 before the High Court of Calcutta
    assailing the respondent’s Notice dated 07.02.2023 cancelling the
    tender for work of maintenance of the two underpasses.
15. The aforesaid writ petition referred to above came to be rejected
    by the High Court vide its order dated 24.04.2023, wherein the Ld.
    Single Judge held that the decision to cancel the tender had to be
    taken on account of the administrative exigencies and also due to
    the ‘change in policy’. It was further held that the decision to cancel
    the tender was not borne out of any ulterior motives on the part of
    the respondent. The decision of the learned Single Judge is based
    on two grounds: -
            (i)   First, the High Court took the view that the decision
                  to cancel the tender cannot be termed as an arbitrary
                  action on the part of the respondent. The appellant was
                  put to prior notice as regards the change of hands of the
                  management of the concerned underpasses, much before
                  the ultimate cancellation notice was issued. It further
                  observed that, since the notice of cancellation dated
                  07.02.2023 specifically provided the reasons for cancelling
                  the tender i.e., the technical faults found in the tender that
[2024] 7 S.C.R.                                                            547

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


                was floated, there was no element of arbitrariness in the
                said action. The relevant observations read as under: -
                     “11. [...] The effect of the administrative decision
                     was reiterated in the stop-work request of
                     24.01.2023 where the reason given for the
                     stop-work was also the “changed scenario”
                     of handover of the maintenance work of E.M.
                     Bypass to KMC from KMDA. Hence, the reason
                     for the stop-work and the impugned cancellation
                     is a change of policy for administrative
                     convenience simpliciter.
                                xxx		      xxx		       xxx
                     18. In the present case, the impugned
                     cancellation of 07.02.2023 cannot be described
                     as a bolt from the blue since the petitioner
                     was put on notice of the impending change
                     in circumstance on 24.01.2023 where the
                     reason for the change was also conveyed to
                     the petitioner. The order dated 01.12.2022 of
                     the Urban Development and Municipal Affairs
                     Department stating that the maintenance of
                     the E.M. Bypass would be handed over from
                     the KMDA to KMC provides the rationale
                     for the impugned cancellation. Seen in this
                     backdrop, it cannot be said that the impugned
                     letter of cancellation of the tender /work was
                     issued with an ulterior motive or for extraneous
                     considerations. In fact, the letter of cancellation
                     provides further reasons, namely, that the tender
                     has been found to be non-specific and having
                     technical faults. This would also be borne out
                     from clauses 10 and 14 of the Special Terms
                     and Conditions of the tender document which
                     give rise to conflicting interpretations on the
                     placement of the signboards. Hence, besides
                     the administrative decision to hand over the
                     maintenance of E.M. Bypass from KMDA to
                     KMC, the respondent KMDA as the tendering
548                                                       [2024] 7 S.C.R.

                   Digital Supreme Court Reports


                   authority, has a right to rectify the ambiguities
                   in the bid document by cancelling the same.”
                                               (Emphasis supplied)
       (ii)   Secondly, the appellant could not have redressed his
              grievances by invoking the writ jurisdiction of the High
              Court under Article 226 of the Constitution, as there was
              no failure of any statutory duty or public law element
              involved. Moreover, since the relief sought was essentially
              in the nature of specific performance, it could have been
              prayed for only under ordinary civil law and not by way of
              a writ petition. The relevant observations read as under: -
                   “20. It is well settled that a contractual dispute
                   with a public law element would be amenable
                   to writ jurisdiction. The present dispute however
                   arises out of a private contract for maintenance
                   of underpasses in the E.M. Bypass and
                   advertisement rights over certain spaces within
                   the contracted area. The rights following out of
                   the contract are purely private in nature and
                   there is nothing to show that the performance
                   of the contract or the consequence therefrom
                   would affect the public at large or even a
                   sizeable section of the public. A public law
                   element is generally understood to mean the
                   reach of an obligation to a large section of
                   the public or the obligation affecting the lives
                   and livelihood of the general public by its very
                   nature. M.P. Power sounded a cautionary note
                   in such cases where the State cites monetary
                   gains or losses as reason for termination of
                   a contract. This is also not’ the case at hand
                   since the reasons given for cancellation were
                   on a wholly different plane.”
                   21. The above reasons persuade this Court to
                   hold that the remedy available to the petitioner is
                   in the realm of private law and not under Article·
                   226 of the Constitution which contemplates
                   certain tests including that the dispute must
[2024] 7 S.C.R.                                                        549

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


                     have a public law element. The complaint of
                     the petitioner is essentially for the specific
                     performance of the contractual obligation of the
                     respondent KMDA. Doubtless, the petitioner can
                     avail of appropriate civil remedies for redress
                     which would include damages for breach of the
                     contractual terms.
                                                 (Emphasis supplied)
16. Aggrieved with the aforesaid, the appellant went in appeal before
    a Division Bench of the High Court by way of M.A.T. No. 744 of
    2023, wherein the appeal court finding no fault in the decision of the
    learned Single Judge, dismissed the appeal and thereby affirmed
    the judgment of the learned Single Judge referred to above.
17. In view of the aforesaid, the appellant is here before this Court with
    the present appeal.
     C.    DEVELOPMENTS THAT OCCURRED DURING THE
           PENDENCY OF THE PRESENT APPEAL.
18. During the pendency of the present appeal, the appellant herein
    preferred a RTI seeking further information on the respondent’s
    internal note-file pertaining to the cancellation of the subject tender.
19. The Public Information Officer, KMDA vide its reply dated 18.08.2023
    provided the internal file-notings of the respondent on the aforesaid
    tender. In the internal file-notings of the respondent, the following
    entries / notes are relevant: -
     a)    As per Note #91 dated 30.12.2022, the respondent in view of
           the maintenance of the concerned underpasses being handed
           over to KMC, was contemplating the possibility of cancelling the
           tender for work. The relevant noting reads as under: -
                “Note # 91
                Recently maintenance of EM Bye pass has been
                handed over to KMC. Thus, in this changed scenario
                we may cancel the work order.
                03/01/2023 11:51 AM                FIRHAD HAKIM
                                                   CHRMN (KMDA)”
550                                                            [2024] 7 S.C.R.

                         Digital Supreme Court Reports


       b)   As per Note #95 dated 10.01.2023, the respondent instructed
            that the tender be cancelled in view of the maintenance of the
            concerned underpasses being handed over to KMC. However,
            since the respondent was in doubt as regards the legality &
            validity of such decision, it opined that the opinion of the Legal
            Department may be sought first before any action of cancellation
            is taken. However, as an interim measure, it decided to issue
            a notice to stop all work in respect of the tender. The relevant
            noting reads as under: -
                 “Note # 95
                 [...] Now, as instructed by the competent authority
                 of KMDA keeping in view of the recent changed
                 scenario of handing over of maintenance of E.M.
                 Bypass from KMDA to KMC, cancelling the work order
                 as instructed may require judicious action towards
                 implementing the same and to make it lawful, legal
                 advice from Law-Cell, KMDA may be required so that,
                 KMDA doesn’t fall in any legal obligation. However,
                 for immediate compliance of the order, a notice to
                 stop the works in all respect with regards to the
                 two above-mentioned tenders may be served to the
                 agency for immediately stopping his all activities at
                 site till further notice. As instructed, a draft Letter is
                 attached herewith for his kind perusal and direction
                 in this regard. [...]
                 10/01/2023 02:55 PM PARTHA PROTIM GHOSH
                                        EE (RBBRDG) (KMDA)”
       c)   Again, in Note #96, it was noted that since the competent
            authority of the respondent was desirous to cancel the tender,
            the respondent was of the view that the opinion of its legal
            cell be obtained first before such action is taken. The relevant
            noting reads as under: -
                 “Note # 96
                 [...]
                 As per Note#91¸Competent Authority desires to
                 cancel the Work Order.
[2024] 7 S.C.R.                                                            551

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


                In Note#95¸a draft letter has been attached for
                approval towards issuance to the agency to stop any
                type of work related to this project.

                Considering the Chronological development and
                acceptance by Authority, the matter may kindly be
                viewed lawfully, so that, if it is cancelled by this end,
                no legal action is taken by the Agency.

                Submitted for necessary action.

                13/01/2023 02:13 PM              SANTANU PATRA
                                             SE (RBBRDG) (KMDA)”

     d)    In Note #97 dated 16.01.2023, the respondent has noted that
           since the competent authority had decided to cancel the work
           tender there was no option but to cancel it. However, the
           respondent once again insisted that a legal opinion may be
           sought first, in order to avoid further litigations. The relevant
           noting reads as under: -

                “Note # 97

                    Sub: Cancellation of Work Order of Mainte-
                           nance of two Underpasses

                A concurrence of Law Cell, KMDA may kindly be
                obtained before cancelling the Work Order of the
                existing agency. There is no different opinion than
                to get this cancelled, once this has been decided by
                the Authority but a legal opinion may be sought for
                avoiding further litigations. [...]

                16/01/2023 04:38 PM                 SUBHANKAR
                                                  BHATTACHARYA
                                             CE (RBBRDG) (KMDA)”

     e)    Thereafter, it could be seen from Note #101 dated 19.01.2023,
           that the other officials of the authority also concurred with the
           respondent’s opinion to first seek advice of its legal cell on
           the possible consequences in the event the tender for work is
           cancelled. The relevant observations read as under: -
552                                                           [2024] 7 S.C.R.

                      Digital Supreme Court Reports


                 “Note # 101
                 As concurred by the Authority the legal aspects and
                 the possible consequences may be reviewed and
                 opined back prior to cancelling the Work Order. The
                 draft of order for stopping work further is enclosed,
                 which may kindly be seen and commented.
                 For kind concern of Law Cell with request to revert
                 back with further advice and opinion on above please.
                 19/01/2023 02:28 PM                 SUBHANKAR
                                                   BHATTACHARYA
                                              CE (RBBRDG) (KMDA)”
       f)   However, before the legal cell of the respondent could give
            any definite opinion on the legal implications of cancelling the
            tender, it appears from the records, more particularly Note #108
            dated 24.01.2023 that the concerned minister during his visit
            instructed the officials of the respondent on his own to cancel
            the tender, upon which the respondent undertook the steps to
            duly comply with such instructions. The relevant noting reads
            as under: -
                 “Note # 108
                 For immediate compliance of HMIC’s instruction. This
                 is as per the instruction given during his visit to Un-
                 nanyan Bhavn today in presence of KMDA Officials.
                 24/01/2023 05:16 PM                 SUBHANKAR
                                                   BHATTACHARYA
                                              CE (RBBRDG) (KMDA)”
       g)   Pursuant to the above, as per Note #109 dated 02.02.2023,
            the Tender Committee of the respondent convened a meeting
            wherein the proposal for cancellation of the aforesaid tender
            was finalized and placed for approval. The relevant noting
            reads as under: -
                 “Note # 109
                 As per the discussion held in the 5th meeting of
                 Tender Committee, KMDA, proposal for cancel-
                 lation of this tender, as per the Note #91 for this
[2024] 7 S.C.R.                                                       553

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


                changed scenario vide memo : 5783-UDMA-
                22012(14)/11/2022 Dt. 01-12-2022 maintenance
                of E.M. Bypass has been handed over to KMC
                from KMDA, is placed herewith for approval
                please. [...]
                02/02/2024 02:31 PM    SANTANU PATRA
                                   SE (RBBRDG) (KMDA)”
     h)    Thereafter, as per the last entry in the internal notings – Note
           #110 dated 03.02.2023, the respondent floated one another
           proposal seeking approval to cancel the tender, which culminated
           into the final notice of cancellation dated 07.02.2023 which is
           the subject matter of challenge in the present litigation.
20. During the course of hearing of this appeal, it was brought to the
    notice of this Court that after the work order issued in favour of
    the appellant was cancelled, the respondent floated a fresh tender
    dated 15.05.2023 for the work of maintenance of the very same
    underpasses, the selection process for which stood completed and
    that the tender had been awarded along with the work order(s) to
    one another third-party agency.
21. This Court was further apprised of the order dated 16.09.2023
    passed by the Urban Development and Municipal Affairs Department,
    Government of West Bengal, modifying its earlier order dated
    01.12.2022 to the extent that both i) the operation & maintenance
    of 37 bridges, flyovers, underpasses, etc. including the concerned
    two underpasses along with ii) the right to collect revenue towards
    the advertisement rights for the said structures, shall be taken over
    by KMC from KMDA. The said letter reads as under: -
                         “Government of West Bengal
                    Urban Development and Municipal Affairs
                                 Department
                           NAGARYAN, DF-8, Sector-I
                          Salt Lake, Kolkata - 700 064


           Memo No. 5271 – UDMA-22012(14)/11/2022
                                                  Date : 16.09.2023
554                                                         [2024] 7 S.C.R.

                      Digital Supreme Court Reports


            ORDER
            In continuation with the order issued vide no. 5783-UDMA-
            22012(14)/11/2022 dated 01.12.2022, it has been further
            decided that the operation and maintenance of the 37
            bridges, flyovers, foot over bridges, under pass & culverts
            attached herewith to be taken over by KMC from KMDA.
            In that case the revenues earned from advertisements
            and displays erected on these assets (including the piers
            of the bridges) to be accrued to KMC.
            This order shall take immediate effect.
                                                               Sd/-
                                                Principal Secretary
                                       to the Govt. of West Bengal”
22. In view of the fact that a fresh tender had already been awarded to
    a third-party, coupled with the fact that the right to collect revenue
    from the advertisements for the concerned underpasses had been
    handed over to KMC, the counsel for the respondent submitted that
    the matter had since become infructuous.
       D.   SUBMISSIONS ON BEHALF OF THE APPELLANT
23. Mr. Shyam Divan, the learned Senior Counsel appearing for the
    appellant submitted that the impugned notice of cancellation dated
    07.02.2023 is manifestly arbitrary and tainted with extraneous
    considerations. He submitted that though the impugned notice
    purports to cancel the tender on the ground of being ambiguous and
    non-specific, but in reality the said action was at the behest of the
    concerned Minister-In-Charge who directed such cancellation without
    any justifiable cause. In this regard he placed strong reliance on the
    internal-file notings of the respondent.
24. He submitted that the reasons assigned for cancelling the tender in
    the impugned notice are not to be found in the entire file of notings
    maintained by the respondent. He further pointed out that the file of
    the internal notings indicate that, before the respondent could take
    a judicious call the concerned minister issued a specific direction on
    the basis of which the cancellation was undertaken & that to without
    any application of mind.
[2024] 7 S.C.R.                                                       555

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


25. Mr. Divan also submitted that no orders to stop the work could have
    been issued by the respondent on account of handing over of the
    maintenance to another authority, because even after the handover,
    the respondent continued to operate & maintain the underpasses
    including the licensing rights for advertisements.
26. He further submitted that, although the terms of the contract provided
    for assigning cogent grounds for termination, yet the same was not
    followed and instead the respondent arbitrarily proceeded to cancel
    the tender.
27. In the last, Mr Divan submitted that the contention as regards the
    financial losses being suffered is erroneous, as the respondent
    voluntarily accepted the bid that was submitted by the appellant,
    and even as per the notings in the file the tender was generating
    more revenue than earlier.
     E.    SUBMISSIONS ON BEHALF OF THE RESPONDENT
28. Mr. Rakesh Dwivedi, the learned Senior Counsel appearing for the
    respondent submitted that the present matter being purely a contractual
    dispute was rightly not entertained by the High Court in exercise of
    its writ jurisdiction under Article 226 of the Constitution of India.
29. He further submitted, that the decision to cancel the tender was bona
    fide and had to be taken considering the technical faults in the same.
    He submitted, that there was ambiguity in the tender as regards
    whether it was lawful to put up advertisements at the places outside
    the underpasses, due to which, many interested bidders might not
    have participated in the tender. The respondent was of the view that
    a higher license fee could be fetched by rectifying such ambiguity.
30. Mr. Dwivedi also submitted that the decision to cancel the tender
    had to be taken to enable the respondent to float separate tenders,
    one for the maintenance of the underpasses and the other for the
    licensing advertisement rights. Thus, the decision was taken in
    public interest. He submitted that the decision to cancel the tender
    was on the basis of a change in the policy, and thus cannot be
    said to be arbitrary.
31. He further submitted that no reliance could have been placed on the
    notings in the file maintained by the respondent, as the file notings
556                                                          [2024] 7 S.C.R.

                       Digital Supreme Court Reports


       are only internal deliberations. Such notings cannot be construed
       as decisions of the respondent and thus, creates no right in favour
       of the appellant.
32. In the last, Mr Dwivedi submitted that since during the pendency of
    the present appeal, the operation, maintenance and the licensing
    rights for the advertisements have been taken over by a third party,
    the present appeal has been rendered infructuous.
       F.    POINTS FOR DETERMINATION
33. Having heard the learned counsel appearing for the parties and
    having gone through the materials on record, the two pivotal questions
    that fall for our consideration are as under: -
       I)    What is the scope of judicial review of the actions of the State
             in the matters relating to contract / tender disputes under writ
             jurisdiction?
       II)   Whether the action on the part of the respondent herein in
             cancelling the tender vide its notice dated 07.02.2023 was
             amenable to the writ jurisdiction of the High Court? If so,
             whether the said action could be termed as arbitrary or unfair
             and in consequence of violation of Article 14 of the Constitution
             of India?
       G.    ANALYSIS
       i.    Scope of Judicial Review of the actions of the State in
             matters relating to Contract / Tender under Writ Jurisdiction.
       a.    Earlier Position of Law and Misconception of the State as
             a Largesse.
34. Over the years, the scope of judicial review and the extent to which a
    Court can interfere in disputes arising out of contracts or tenders has
    seen a significant development, marked by a nuanced understanding
    of the critical role of administrative discretion. The judicial quest
    in administrative matters has always been to find a right balance
    between i) allowing leeway to the States in deciding the exercise of
    their administrative discretion in matters pertaining to policy and ii) the
    need to ensure fairness and propriety in such administrative actions.
35. Earlier, the position of law was that any dispute arising out of a
    contract entered into with the State or its instrumentalities could not
[2024] 7 S.C.R.                                                             557

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     be adjudicated by the court under its writ jurisdiction, as in all such
     cases, it could be said that the ‘real grievance’ was essentially only
     one being that of breach of a contract for which the appropriate
     remedy would be an ordinary suit and not a writ petition. One of
     the earliest judicial pronouncements in this regard is the decision
     of this Court in Radhakrishna Agarwal & Ors. v. State of Bihar &
     Ors. reported in (1977) 3 SCC 457 wherein the following relevant
     observations were made: -
           “19. [...] None of these cases lays down that, when the
           State or its officers purport to operate within the contractual
           field and the only grievance of the citizen could be that
           the contract between the parties is broken by the action
           complained of, the appropriate remedy is by way of a
           petition under Article 226 of the Constitution and not an
           ordinary suit. There is a formidable array of authority
           against any such a proposition. [...]”
                                                   (Emphasis supplied)
36. It was further explained by this Court in Radhakrishna Agarwal
    (supra) that once the State or its instrumentalities enter into a
    contract, any dispute arising out of that contract cannot be decided
    in writ jurisdiction as their relations no longer remain governed by the
    constitutional provisions, and it is only the contract which thereafter
    determines the rights and obligations of the parties. Any claim to a
    right flowing from a contract cannot be redressed through the writ
    jurisdiction except where some statute steps in and confers some
    special statutory power or obligation on the State in the contractual
    field or if the agreement is in the nature of a statutory contract. The
    relevant observations read as under: -
           “10. [...] But, after the State or its agents have entered into
           the field of ordinary contract, the relations are no longer
           governed by the constitutional provisions but by the legally
           valid contract which determines rights and obligations
           of the parties inter se. No question arises of violation of
           Article 14 or of any other constitutional provision when
           the State or its agents, purporting to act within this field,
           perform any act. In this sphere, they can only claim rights
           conferred upon them by contract and are bound by the
           terms of the contract only unless some statute steps in
558                                                        [2024] 7 S.C.R.

                     Digital Supreme Court Reports


          and confers some special statutory power or obligation
          on the State in the contractual field which is apart from
          contract.
          11. In the cases before us the contracts do not contain any
          statutory terms or obligations and no statutory power or
          obligation which could attract the application of Article 14
          of the Constitution is involved here. Even in cases where
          the question is of choice or consideration of competing
          claims before an entry into the field of contract facts
          have to be investigated and found before the question
          of a violation of Article 14 could arise. If those facts
          are disputed and require assessment of evidence the
          correctness of which can only be tested satisfactorily
          by talking detailed evidence, involving examination and
          cross-examination of witnesses, the case could not be
          conveniently or satisfactorily decided in proceedings
          under Article 226 of the Constitution. Such proceedings
          are summary proceedings reserved for extraordinary
          cases where the exceptional and what are described as,
          perhaps not quite accurately, “prerogative” powers of the
          Court are invoked. We are certain that the cases before
          us are not such in which powers under Article 226 of the
          Constitution could be invoked.”
                                                 (Emphasis supplied)
37. Similar view as above, was reiterated by this Court in Premji Bhai
    Parmar & Ors. v. Delhi Development & Ors. reported in (1980) 2
    SCC 129 at para 8 and in Divisional Forest Officer v. Bishwanath
    Tea Co. Ltd. reported in (1981) 3 SCC 238 wherein it was held
    that any right to relief flowing from a breach of contract cannot be
    entertained under the extraordinary writ jurisdiction of the court, even
    if the action of the State or its instrumentality was unauthorized in
    law. The relevant observations read as under: -
          “9. Ordinarily, where a breach of contract is complained of,
          a party complaining of such breach may sue for specific
          performance of the contract, if contract is capable of being
          specifically performed, or the party may sue for damages.
          Such a suit would ordinarily be cognizable by the civil
[2024] 7 S.C.R.                                                           559

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           court. The High Court in its extraordinary jurisdiction would
           not entertain a petition either for specific performance of
           contract or for recovering damages. A right to relief flowing
           from a contract has to be claimed in a civil court where a
           suit for specific performance of contract or for damages
           could be filed. This is so well-settled that no authority is
           needed.
           10. In substance, this was a suit for refund of a royalty
           alleged to be unauthorisedly recovered and that could
           hardly be entertained in exercise of the writ jurisdiction
           of the High Court.”
                                                  (Emphasis supplied)
38. We do not propose to dwell any further, on the position of law that
    existed earlier, and leave it at rest with one last reference to the
    decision of this Court in Bareilly Development Authority & Anr. v.
    Ajai Pal Singh & Ors. reported in (1989) 2 SCC 116, wherein this
    Court once again reiterated that no writ can be issued in contractual
    disputes between the State and an aggrieved party where the rights
    or claims arise or stem only from the terms of the contract. The
    relevant observations read as under: -
           “22. There is a line of decisions where the contract entered
           into between the State and the persons aggrieved is non-
           statutory and purely contractual and the rights are governed
           only by the terms of the contract, no writ or order can be
           issued under Article 226 of the Constitution of India so as
           to compel the authorities to remedy a breach of contract
           pure and simple [...]”
                                                  (Emphasis supplied)
39. Thus, for a period of time the courts recognized that there was a clear
    brightline distinction between when a State or its instrumentalities could
    be said to be acting in its executive capacity and when it could be said
    to be acting in its private capacity, with the existence of a ‘contractual
    relation’ inter-se the parties being the determinative factor. Wherever,
    there was a contract, the State’s relations and all its actions were said
    to be within the field of a contract i.e., within the realm of private law,
    and the courts would resile from interfering with the same under their
    writ jurisdiction or embarking upon a judicial review of such actions.
560                                                        [2024] 7 S.C.R.

                     Digital Supreme Court Reports


40. Such reluctance on the part of the courts stemmed from its
    understanding that State or any of its instrumentalities must have
    the flexibility or the discretion to take decisions that are in the best
    interest of the public and efficient governance. Government being the
    decision-maker of the State is said to be the best judge of when a
    contract or an agreement is in its interest and by its extension in the
    interest of the public, and as such the courts should not interfere in
    the State’s discretion to award or terminate contracts. One another
    reason why contractual disputes were precluded from being espoused
    under the writ jurisdiction of the courts was due to the summary nature
    of such proceedings, which do not allow for an exhaustive review
    unlike civil suits. [See: Radhakrishna Agarwal (supra) at para 11]
41. This simplistic approach of the courts in deeming every act and
    action of the State which was complained of as nothing more than a
    ‘contractual dispute’ or a case of ‘breach of contract’ often led to the
    State abusing its position and acting unfairly under the misconceived
    notion, that all its actions such as award of contracts or tenders were
    nothing but a ‘largess’ – a generosity bestowed upon its citizens, which
    it can at its own whims choose to deny, alter, modify, or take away
    without any consequences. This often led to a conflation of power
    with duty, and resulted in every arbitrary exercise of power by the
    State under the guise of a ‘contractual dispute’ to remain unchecked
    and undisputable before the courts and out of the reach of judicial
    review, undermining the rights of the citizen to have their interests
    safeguarded and protected. We may in this regard refer to M/s Indian
    Medicines Pharmaceuticals Corp Ltd. v. Kerala Ayurvedic Co-
    operative Society Ltd. reported in (2023) SCC OnLine SC 5 wherein
    this Court speaking eruditely through one of us, Dr. D.Y. Chandrachud,
    CJI made the following pertinent observations: -
          “11 The welfare State plays a crucial role in aiding
          the realisation of the socioeconomic rights which are
          recognised by the Constitution. Social welfare benefits
          provided by the State under the rubric of its constitutional
          obligations are commonly understood in the language of
          ‘largesse’, a term used to describe a generous donation.
          Terming all actions of government, ranging from social
          security benefits, jobs, occupational licenses, contracts
          and use of public resources – as government largesse
          results in doctrinal misconceptions. The reason is that this
[2024] 7 S.C.R.                                                           561

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           conflates the State’s power with duty. The Constitution
           recognises the pursuit of the well-being of citizens as a
           desirable goal. In doing this the Constitution entrusts the
           State with a duty to ensure the well-being of citizens.
           Government actions aimed at ensuring the well-being
           of citizens cannot be perceived through the lens of
           a ‘largess’. The use of such terminology belittles the
           sanctity of the social contract that the ‘people of India’
           entered into with the State to protect and safeguard
           their interests.
                      xxx			xxx			xxx
           13. In the early 1950s’, judicial review of the process of
           concluding contracts by government was limited. The
           courts allowed the State due deference on the ground of
           governmental policy. In C.K Achuthan v. State of Kerala, AIR
           1959 SC 490 a Constitution Bench of this Court held that
           it is open to the Government ‘to choose a person to their
           liking, to fulfil contracts which they wish to be performed.’
           The Court observed that when one party is chosen over
           another, the aggrieved party cannot claim the protection
           of Article 14 since the government has the discretion to
           choose with whom it will contract.”
                                                 (Emphasis supplied)
42. Before proceeding further to discuss how the scope of judicial review
    came to be evolved, we would like to refer to the observations made
    by this Court in M.C. Mehta v. Union of India reported in (1987) 1
    SCC 395 which are significant, and read as under: -
           “31. [...] Law has to grow in order to satisfy the needs
           of the fast changing society and keep abreast with the
           economic developments taking place in the country. As
           new situations arise the law has to be evolved in order to
           meet the challenge of such new situations. Law cannot
           afford to remain static. We have to evolve new principles
           and lay down new norms which would adequately deal
           with the new problems which arise in a highly industrialised
           economy. [...]”
                                                 (Emphasis supplied)
562                                                          [2024] 7 S.C.R.

                      Digital Supreme Court Reports


       b.   Concept of ‘Public Law’ Element: Scope of Judicial Review
            in Contractual Matters.
43. Over a period of time the courts recognized the crucial role of
    judicial oversight in preventing the abuse of power and maintaining
    public confidence in the administrative process. Courts developed
    various doctrines and principles to guide their review, such as the
    principles of natural justice, reasonableness and proportionality.
    These principles ensured that the administrative actions are not
    arbitrary, discriminatory or capricious. By enforcing such standards,
    the courts also ensured that the rule of law was maintained and the
    individual rights were protected.
44. The interplay between judicial review and administrative discretion
    has been a dynamic process. As new challenges and complexities
    kept on arising before the courts as regards the State’s actions and
    governance, it continued to refine its approach. This ongoing dialogue
    between the courts and the executive branch contributed to the
    development of a more accountable and transparent administrative
    framework, paving the way for the exercise of judicial review even in
    the realm of contractual disputes to achieve a fine balance between
    efficiency and fairness in policy decisions on the one hand and the
    rights of individuals and overall public interest on the other.
45. In Mahabir Auto Stores & Ors. v. Indian Oil Corporation reported in
    (1990) 3 SCC 752, this Court expressed doubts over the correctness
    of the earlier position of law, that actions of the State in the private
    contractual field cannot be questioned in writ jurisdiction. This Court
    further held that even if the inter-se relation of parties with the State
    is governed purely by a contract, the method, motive and decision
    of the State would be subject to judicial review on the grounds of
    relevance and reasonableness, fair play, natural justice, equality
    and non-discrimination. The relevant observations read as under: -
            “12. [...] It appears to us that rule of reason and rule
            against arbitrariness and discrimination, rules of fair play
            and natural justice are part of the rule of law applicable in
            situation or action by State instrumentality in dealing with
            citizens in a situation like the present one. Even though
            the rights of the citizens are in the nature of contractual
            rights, the manner, the method and motive of a decision
            of entering or not entering into a contract, are subject
[2024] 7 S.C.R.                                                              563

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           to judicial review on the touchstone of relevance and
           reasonableness, fair play, natural justice, equality and non-
           discrimination in the type of the transactions and nature
           of the dealing as in the present case.
           13. The existence of the power of judicial review however
           depends upon the nature and right involved in the facts and
           circumstances of the particular case. It is well settled that
           there can be “malice in law”. Existence of such “malice in
           law” is part of the critical apparatus of a particular action
           in administrative law. Indeed “malice in law” is part of the
           dimension of the rule of relevance and reason as well as
           the rule of fair play in action.
                            xxx		      xxx		       xxx
           20. [...] we are of the opinion that it would be appropriate
           to state that in cases where the instrumentality of the
           state enters the contractual field, it should be governed
           by the incidence of the contract. It is true that it may not
           be necessary to give reasons but, in our opinion, in the
           field of this nature fairness must be there to the parties
           concerned, and having regard to the large number or
           the long period and the nature of the dealings between
           the parties, the appellant should have been taken into
           confidence. Equality and fairness at least demands this
           much from an instrumentality of the State dealing with a
           right of the State not to treat the contract as subsisting.
           We must, however, evolve such process which will work.”
                                                   (Emphasis supplied)
     [See also: Dwarkadas Marfatia & Sons v. Board of Trustees of
     the Port of Bombay : (1989) 3 SCC 293 at para 27.]
46. In LIC v. Consumer Education & Research Centre reported in
    (1995) 5 SCC 482, the Court held that the law as it stood earlier
    that a State or its instrumentality whose action is hedged with public
    element cannot be called into question because such action was
    in the field of private law is no longer a good law. The relevant
    observations read as under: -
           “23. Every action of the public authority or the person acting
           in public interest or any act that gives rise to public element,
564                                                           [2024] 7 S.C.R.

                     Digital Supreme Court Reports


          should be guided by public interest. It is the exercise of
          the public power or action hedged with public element
          (sic that) becomes open to challenge. If it is shown that
          the exercise of the power is arbitrary, unjust and unfair,
          it should be no answer for the State, its instrumentality,
          public authority or person whose acts have the insignia of
          public element to say that their actions are in the field of
          private law and they are free to prescribe any conditions
          or limitations in their actions as private citizens, simpliciter
          do in the field of private law. Its actions must be based
          on some rational and relevant principles. It must not be
          guided by irrational or irrelevant considerations. Every
          administrative decision must be hedged by reasons. [...]
                           xxx		      xxx		       xxx
          26. This Court has rejected the contention of an
          instrumentality or the State that its action is in the private
          law field and would be immuned from satisfying the tests
          laid under Article 14. The dichotomy between public law
          and private law rights and remedies, though may not be
          obliterated by any strait-jacket formula, it would depend
          upon the factual matrix. The adjudication of the dispute
          arising out of a contract would, therefore, depend upon
          facts and circumstances in a given case. The distinction
          between public law remedy and private law field cannot
          be demarcated with precision. Each case will be examined
          on its facts and circumstances to find out the nature of
          the activity, scope and nature of the controversy. The
          distinction between public law and private law remedy has
          now become too thin and practicably obliterated.”
                                                  (Emphasis supplied)
47. This Court in Consumer Education & Research Centre (supra)
    further held that the writ jurisdiction of the courts cannot be shackled
    by technicalities and that any action of the State which has a public
    law element or a public character, such actions by their nature are
    required to be just, fair, reasonable & in the interest of public, and as
    such they would be amenable to judicial review. As to what is meant
    by actions bearing insignia of public law element, this Court held that
    wherever the action of a State or its instrumentality in the sphere of
[2024] 7 S.C.R.                                                             565

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     contractual relations is enjoined with a duty or an obligation to the
     public, such actions could be said to bear the insignia of a public
     element. The relevant observation reads as under: -
           “27. In the sphere of contractual relations the State, its
           instrumentality, public authorities or those whose acts
           bear insignia of public element, action to public duty or
           obligation are enjoined to act in a manner i.e. fair, just and
           equitable, after taking objectively all the relevant options
           into consideration and in a manner that is reasonable,
           relevant and germane to effectuate the purpose for public
           good and in general public interest and it must not take
           any irrelevant or irrational factors into consideration or
           appear arbitrary in its decision. Duty to act fairly is part of
           fair procedure envisaged under Articles 14 and 21. Every
           activity of the public authority or those under public duty
           or obligation must be informed by reason and guided by
           the public interest.
                      xxx			xxx			xxx
           29. [...] The arms of the High Court are not shackled with
           technical rules or procedure. The actions of the State,
           its instrumentality, any public authority or person whose
           actions bear insignia of public law element or public
           character are amenable to judicial review and the validity
           of such an action would be tested on the anvil of Article
           14. While exercising the power under Article 226 the
           Court would be circumspect to adjudicate the disputes
           arising out of the contract depending on the facts and
           circumstances in a given case. The distinction between
           the public law remedy and private law field cannot be
           demarcated with precision. Each case has to be examined
           on its own facts and circumstances to find out the nature
           of the activity or scope and nature of the controversy. The
           distinction between public law and private law remedy is
           now narrowed down. [...]”
                                                   (Emphasis supplied)
48. In another decision of this Court in Shrilekha Vidyarthi (Kumari) v.
    State of U.P. reported in (1991) 1 SCC 212 it was held that every
566                                                            [2024] 7 S.C.R.

                       Digital Supreme Court Reports


       action of the State that has some degree of impact on the public
       interest, can be challenged under writ jurisdiction to the extent that
       they are arbitrary, unfair or unreasonable, irrespective of the fact that
       the dispute falls within the domain of contractual obligations. It was
       further held, that it is the nature of a government body’s personality
       which characterizes the action as having a public law element,
       and not the field of law where such action is taken. The relevant
       observation reads as under: -
            “22. There is an obvious difference in the contracts between
            private parties and contracts to which the State is a party.
            Private parties are concerned only with their personal
            interest whereas the State while exercising its powers and
            discharging its functions, acts indubitably, as is expected of
            it, for public good and in public interest. The impact of every
            State action is also on public interest. This factor alone
            is sufficient to import at least the minimal requirements
            of public law obligations and impress with this character
            the contracts made by the State or its instrumentality. It
            is a different matter that the scope of judicial review in
            respect of disputes falling within the domain of contractual
            obligations may be more limited and in doubtful cases the
            parties may be relegated to adjudication of their rights
            by resort to remedies provided for adjudication of purely
            contractual disputes. However, to the extent, challenge is
            made on the ground of violation of Article 14 by alleging
            that the impugned act is arbitrary, unfair or unreasonable,
            the fact that the dispute also falls within the domain of
            contractual obligations would not relieve the State of its
            obligation to comply with the basic requirements of Article
            14. To this extent, the obligation is of a public character
            invariably in every case irrespective of there being any
            other right or obligation in addition thereto. An additional
            contractual obligation cannot divest the claimant of the
            guarantee under Article 14 of non-arbitrariness at the
            hands of the State in any of its actions.
                       xxx			xxx			xxx
            24. The State cannot be attributed the split personality
            of Dr Jekyll and Mr Hyde in the contractual field so as
            to impress on it all the characteristics of the State at the
[2024] 7 S.C.R.                                                            567

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           threshold while making a contract requiring it to fulfil the
           obligation of Article 14 of the Constitution and thereafter
           permitting it to cast off its garb of State to adorn the new
           robe of a private body during the subsistence of the contract
           enabling it to act arbitrarily subject only to the contractual
           obligations and remedies flowing from it. It is really the
           nature of its personality as State which is significant
           and must characterize all its actions, in whatever field,
           and not the nature of function, contractual or otherwise,
           which is decisive of the nature of scrutiny permitted for
           examining the validity of its act. The requirement of Article
           14 being the duty to act fairly, justly and reasonably, there
           is nothing which militates against the concept of requiring
           the State always to so act, even in contractual matters.
           There is a basic difference between the acts of the State
           which must invariably be in pubic interest and those of
           a private individual, engaged in similar activities, being
           primarily for personal gain, which may or may not promote
           public interest. Viewed in this manner, in which we find no
           conceptual difficulty or anachronism, we find no reason
           why the requirement of Article 14 should not extend even
           in the sphere of contractual matters for regulating the
           conduct of the State activity.
                           xxx		       xxx		      xxx
           28. Even assuming that it is necessary to import the concept
           of presence of some public element in a State action to
           attract Article 14 and permit judicial review, we have no
           hesitation in saying that the ultimate impact of all actions
           of the State or a public body being undoubtedly on public
           interest, the requisite public element for this purpose is
           present also in contractual matters. We, therefore, find
           it difficult and unrealistic to exclude the State actions in
           contractual matters, after the contract has been made,
           from the purview of judicial review to test its validity on
           the anvil of Article 14.”
                                                  (Emphasis supplied)
49. In Verigamto Naveen v. Govt. of A.P. & Ors. reported in (2001) 8
    SCC 344 this Court held that where a breach of contract involves
568                                                             [2024] 7 S.C.R.

                        Digital Supreme Court Reports


       the decision-making authority exceeding its power or violating the
       principles of nature justice or its decision being borne out of perversity,
       then such cancellation of contract can certainly be scrutinized under
       the writ jurisdiction. This is because such an exercise of power by
       the authority is apart from the contract. The relevant observation
       reads as under: -
            “21. [...] Though there is one set of cases rendered by this
            Court of the type arising in Radhakrishna Agarwal case
            [(1977) 3 SCC 457 : AIR 1977 SC 1496] much water has
            flown in the stream of judicial review in contractual field.
            In cases where the decision-making authority exceeded its
            statutory power or committed breach of rules or principles
            of natural justice in exercise of such power or its decision
            is perverse or passed an irrational order, this Court has
            interceded even after the contract was entered into between
            the parties and the Government and its agencies. [...]
            Where the breach of contract involves breach of statutory
            obligation when the order complained of was made in
            exercise of statutory power by a statutory authority, though
            cause of action arises out of or pertains to contract,
            brings it within the sphere of public law because the
            power exercised is apart from contract. The freedom
            of the Government to enter into business with anybody
            it likes is subject to the condition of reasonableness and
            fair play as well as public interest. After entering into a
            contract, in cancelling the contract which is subject to
            terms of the statutory provisions, as in the present case, it
            cannot be said that the matter falls purely in a contractual
            field. Therefore, we do not think it would be appropriate to
            suggest that the case on hand is a matter arising purely
            out of a contract and, therefore, interference under Article
            226 of the Constitution is not called for. This contention
            also stands rejected.”
                                                     (Emphasis supplied)
50. Similarly in Binny Ltd. & Anr. v. Sadasivan & Ors. reported in (2005)
    6 SCC 657 this Court in view of the increasing trend of the State
    and its instrumentalities to use contracts as a means for dispensing
    their regulatory functions, held that whenever a contract is used for
[2024] 7 S.C.R.                                                           569

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     a public purpose, it will be amenable to judicial review. The relevant
     observations read as under: -
           “30. A contract would not become statutory simply because
           it is for construction of a public utility and it has been
           awarded by a statutory body. But nevertheless, it may be
           noticed that the Government or government authorities at
           all levels are increasingly employing contractual techniques
           to achieve their regulatory aims. It cannot be said that the
           exercise of those powers are free from the zone of judicial
           review and that there would be no limits to the exercise
           of such powers, but in normal circumstances, judicial
           review principles cannot be used to enforce contractual
           obligations. When that contractual power is being used
           for public purpose, it is certainly amenable to judicial
           review. The power must be used for lawful purposes and
           not unreasonably.”
                                                 (Emphasis supplied)
51. The decision of this Court in ABL International Ltd. v. Export
    Credit Guarantee Corporation of India Ltd. reported in (2004)
    3 SCC 553 is significant and was the turning point in the scope of
    judicial review in contractual matters. In this landmark ruling, this
    Court decisively laid down and approved that a relief against a State
    or its instrumentalities in matters related to contractual obligations
    can be sought under the writ jurisdiction. The relevant observations
    read as under: -
           “23. It is clear from the above observations of this Court,
           once the State or an instrumentality of the State is a
           party of the contract, it has an obligation in law to act
           fairly, justly and reasonably which is the requirement of
           Article 14 of the Constitution of India. Therefore, if by the
           impugned repudiation of the claim of the appellants the first
           respondent as an instrumentality of the State has acted in
           contravention of the abovesaid requirement of Article 14,
           then we have no hesitation in holding that a writ court can
           issue suitable directions to set right the arbitrary actions
           of the first respondent.
                      xxx			xxx			xxx
570                                                          [2024] 7 S.C.R.

                     Digital Supreme Court Reports


          27. From the above discussion of ours, the following legal
          principles emerge as to the maintainability of a writ petition:
          (a)   In an appropriate case, a writ petition as against a
                State or an instrumentality of a State arising out of
                a contractual obligation is maintainable.
          (b)   Merely because some disputed questions of fact
                arise for consideration, same cannot be a ground
                to refuse to entertain a writ petition in all cases as
                a matter of rule.
          (c)   A writ petition involving a consequential relief of
                monetary claim is also maintainable.”
                                                  (Emphasis supplied)
52. At the same time, this Court in ABL (supra) cautioned that the power
    to issue writs under Article 226 being discretionary and plenary,
    the same should only be exercised to set right the arbitrary actions
    of the State or its instrumentality in matters related to contractual
    obligations. The relevant observations read as under: -
          “28. However, while entertaining an objection as to the
          maintainability of a writ petition under Article 226 of the
          Constitution of India, the court should bear in mind the fact
          that the power to issue prerogative writs under Article 226
          of the Constitution is plenary in nature and is not limited
          by any other provisions of the Constitution. The High Court
          having regard to the facts of the case, has a discretion to
          entertain or not to entertain a writ petition. The Court has
          imposed upon itself certain restrictions in the exercise of
          this power. (See Whirlpool Corpn. v. Registrar of Trade
          Marks) And this plenary right of the High Court to issue a
          prerogative writ will not normally be exercised by the Court
          to the exclusion of other available remedies unless such
          action of the State or its instrumentality is arbitrary and
          unreasonable so as to violate the constitutional mandate
          of Article 14 or for other valid and legitimate reasons, for
          which the Court thinks it necessary to exercise the said
          jurisdiction.”
                                                  (Emphasis supplied)
[2024] 7 S.C.R.                                                              571

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


53. In Noble Resources Ltd. v. State of Orissa reported in (2006) 10
    SCC 236 this Court for the purposes of judicial review of contractual
    disputes recognized a distinction between a matter where the contract
    is at the threshold and at the stage of breach. It held that at the
    threshold, the court’s scrutiny is more intrusive & expansive while
    at the stage of breach it is discretionary except where the action is
    found to be arbitrary or unreasonable. The relevant observations
    read as under: -
           “15. It is trite that if an action on the part of the State is
           violative of the equality clause contained in Article 14 of the
           Constitution of India, a writ petition would be maintainable
           even in the contractual field. A distinction indisputably must
           be made between a matter which is at the threshold of a
           contract and a breach of contract; whereas in the former
           the court’s scrutiny would be more intrusive, in the latter
           the court may not ordinarily exercise its discretionary
           jurisdiction of judicial review, unless it is found to be
           violative of Article 14 of the Constitution. While exercising
           contractual powers also, the government bodies may be
           subjected to judicial review in order to prevent arbitrariness
           or favouritism on their part. Indisputably, inherent limitations
           exist, but it would not be correct to opine that under no
           circumstances a writ will lie only because it involves a
           contractual matter.”
                                                   (Emphasis supplied)
54. The law on the subject with which we are dealing was laid down
    exhaustively by this Court in its decision in Joshi Technologies
    International Inc. v. Union of India & Ors. reported in (2015) 7
    SCC 728, and the position was summarised as under: -
           “69. The position thus summarised in the aforesaid
           principles has to be understood in the context of discussion
           that preceded which we have pointed out above. As per
           this, no doubt, there is no absolute bar to the maintainability
           of the writ petition even in contractual matters or where
           there are disputed questions of fact or even when monetary
           claim is raised. At the same time, discretion lies with the
           High Court which under certain circumstances, it can
           refuse to exercise. It also follows that under the following
572                                                      [2024] 7 S.C.R.

                  Digital Supreme Court Reports


       circumstances, “normally”, the Court would not exercise
       such a discretion:
       69.1. The Court may not examine the issue unless the
       action has some public law character attached to it.
       69.2. Whenever a particular mode of settlement of dispute
       is provided in the contract, the High Court would refuse to
       exercise its discretion under Article 226 of the Constitution
       and relegate the party to the said mode of settlement,
       particularly when settlement of disputes is to be resorted
       to through the means of arbitration.
       69.3. If there are very serious disputed questions of fact
       which are of complex nature and require oral evidence
       for their determination.
       69.4. Money claims per se particularly arising out of
       contractual obligations are normally not to be entertained
       except in exceptional circumstances.
       70. Further, the legal position which emerges from various
       judgments of this Court dealing with different situations/
       aspects relating to contracts entered into by the State/
       public authority with private parties, can be summarised
       as under:
       70.1. At the stage of entering into a contract, the State
       acts purely in its executive capacity and is bound by the
       obligations of fairness.
       70.2. State in its executive capacity, even in the contractual
       field, is under obligation to act fairly and cannot practise
       some discriminations.
       70.3. Even in cases where question is of choice or
       consideration of competing claims before entering into
       the field of contract, facts have to be investigated and
       found before the question of a violation of Article 14 of the
       Constitution could arise. If those facts are disputed and
       require assessment of evidence the correctness of which
       can only be tested satisfactorily by taking detailed evidence,
       involving examination and cross-examination of witnesses,
       the case could not be conveniently or satisfactorily decided
[2024] 7 S.C.R.                                                                573

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           in proceedings under Article 226 of the Constitution. In
           such cases the Court can direct the aggrieved party to
           resort to alternate remedy of civil suit, etc.
           70.4. Writ jurisdiction of the High Court under Article 226
           of the Constitution was not intended to facilitate avoidance
           of obligation voluntarily incurred.
           70.5. Writ petition was not maintainable to avoid
           contractual obligation. Occurrence of commercial difficulty,
           inconvenience or hardship in performance of the conditions
           agreed to in the contract can provide no justification in
           not complying with the terms of contract which the parties
           had accepted with open eyes. It cannot ever be that a
           licensee can work out the licence if he finds it profitable
           to do so: and he can challenge the conditions under which
           he agreed to take the licence, if he finds it commercially
           inexpedient to conduct his business.
           70.6. Ordinarily, where a breach of contract is complained
           of, the party complaining of such breach may sue for
           specific performance of the contract, if contract is capable
           of being specifically performed. Otherwise, the party may
           sue for damages.
           70.7. Writ can be issued where there is executive action
           unsupported by law or even in respect of a corporation
           there is denial of equality before law or equal protection of
           law or if it can be shown that action of the public authorities
           was without giving any hearing and violation of principles
           of natural justice after holding that action could not have
           been taken without observing principles of natural justice.
           70.8. If the contract between private party and the State/
           instrumentality and/or agency of the State is under the
           realm of a private law and there is no element of public
           law, the normal course for the aggrieved party, is to invoke
           the remedies provided under ordinary civil law rather
           than approaching the High Court under Article 226 of the
           Constitution of India and invoking its extraordinary jurisdiction.
           70.9. The distinction between public law and private law
           element in the contract with the State is getting blurred.
574                                                         [2024] 7 S.C.R.

                    Digital Supreme Court Reports


         However, it has not been totally obliterated and where
         the matter falls purely in private field of contract, this
         Court has maintained the position that writ petition is not
         maintainable. The dichotomy between public law and
         private law rights and remedies would depend on the
         factual matrix of each case and the distinction between
         the public law remedies and private law field, cannot
         be demarcated with precision. In fact, each case has
         to be examined, on its facts whether the contractual
         relations between the parties bear insignia of public
         element. Once on the facts of a particular case it is
         found that nature of the activity or controversy involves
         public law element, then the matter can be examined
         by the High Court in writ petitions under Article 226 of
         the Constitution of India to see whether action of the
         State and/or instrumentality or agency of the State is
         fair, just and equitable or that relevant factors are taken
         into consideration and irrelevant factors have not gone
         into the decision making process or that the decision is
         not arbitrary.
         70.10. Mere reasonable or legitimate expectation of a
         citizen, in such a situation, may not by itself be a distinct
         enforceable right, but failure to consider and give due
         weight to it may render the decision arbitrary, and this is
         how the requirements of due consideration of a legitimate
         expectation forms part of the principle of non-arbitrariness.
         70.11. The scope of judicial review in respect of disputes
         falling within the domain of contractual obligations may
         be more limited and in doubtful cases the parties may be
         relegated to adjudication of their rights by resort to remedies
         provided for adjudication of purely contractual disputes.”
                                                 (Emphasis supplied)
55. Thereafter, this Court in its decision in M.P. Power Management
    Co. Ltd., Jabalpur v. Sky Power Southeast Solar India Pvt.
    Ltd. & Ors. reported in (2023) 2 SCC 703 exhaustively delineated
    the scope of judicial review of the courts in contractual disputes
    concerning public authorities. The aforesaid decision is in the
    following parts: -
[2024] 7 S.C.R.                                                                575

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     i.    Scope of Judicial Review in matters pertaining to
           Contractual Disputes: -
           This Court held that the earlier position of law that all rights
           against any action of the State in a non-statutory contract would
           be governed by the contract alone and thus not amenable to
           the writ jurisdiction of the courts is no longer a good law in view
           of the subsequent rulings. Although writ jurisdiction is a public
           law remedy, yet a relief would still lie under it if it is sought
           against an arbitrary action or inaction of the State, even if they
           arise from a non-statutory contract. The relevant observations
           read as under: -
                 “53. [...] when the offending party is the State. In
                 other words, the contention is that the law in this
                 field has witnessed an evolution and, what is more, a
                 revolution of sorts and a transformatory change with
                 a growing realisation of the true ambit of Article 14
                 of the Constitution of India. The State, he points out,
                 cannot play the Dr. Jekyll and Hyde game anymore.
                 Its nature is cast in stone. Its character is inflexible.
                 This is irrespective of the activity it indulges in. It will
                 continue to be haunted by the mandate of Article 14
                 to act fairly. There has been a stunning expansion
                 of the frontiers of the Court’s jurisdiction to strike at
                 State action in matters arising out of contract, based,
                 undoubtedly, on the facts of each case. It remains
                 open to the Court to refuse to reject a case, involving
                 State action, on the basis that the action is, per se,
                 arbitrary.
            [...] i.   It is, undoubtedly, true that the writ jurisdiction is
                       a public law remedy. A matter, which lies entirely
                       within a private realm of affairs of public body,
                       may not lend itself for being dealt with under
                       the writ jurisdiction of the Court.
                 ii.   The principle laid down in Bareilly Development
                       Authority (supra) that in the case of a non
                       statutory contract the rights are governed only
                       by the terms of the contract and the decisions,
                       which are purported to be followed, including
576                                                              [2024] 7 S.C.R.

                          Digital Supreme Court Reports


                          Radhakrishna Agarwal (supra), may not continue
                          to hold good, in the light of what has been laid
                          down in ABL (supra) and as followed in the
                          recent judgment in Sudhir Kumar Singh (supra).
                   iii.   The mere fact that relief is sought under a
                          contract which is not statutory, will not entitle
                          the respondent-State in a case by itself to
                          ward-off scrutiny of its action or inaction under
                          the contract, if the complaining party is able
                          to establish that the action/ inaction is, per se,
                          arbitrary.”
                                                      (Emphasis supplied)
       (ii)   Exercise of Writ Jurisdiction in disputes at the stage prior
              to the Award of Contract: -
              An action under a writ will lie even at the stage prior to the
              award of a contract by the State wherever such award of
              contract is imbued with procedural impropriety, arbitrariness,
              favouritism or without any application of mind. In doing so, the
              courts may set-aside the decision which is found to be vitiated
              for the reasons stated above but cannot substitute the same
              with its own decision. The relevant observations read as under: -
                   "iv.   An action will lie, undoubtedly, when the
                          State purports to award any largesse and,
                          undoubtedly, this relates to the stage prior
                          to the contract being entered into [See R.D.
                          Shetty (supra)]. This scrutiny, no doubt, would
                          be undertaken within the nature of the judicial
                          review, which has been declared in the decision
                          in Tata Cellular vs. Union of India.”
                                                      (Emphasis supplied)
       (iii) Exercise of Writ Jurisdiction after the Contract comes into
             Existence: -
              This court held that even after the contract comes into existence
              an action may lie by way of a writ to either (I) obviate an arbitrary
              or unreasonable action on part of the State or (II) to call upon
              it to honour its obligations unless there is a serious or genuine
[2024] 7 S.C.R.                                                              577

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           dispute as regards the liability of the State from honouring such
           obligation. Existence of an alternative remedy or a disputed
           question of fact may be a ground to not entertain the parties in
           a writ as long as it is not being used as smokescreen to defeat
           genuine claims of public law remedy. The relevant observations
           read as under: -
                "v.    After the contract is entered into, there can be
                       a variety of circumstances, which may provide
                       a cause of action to a party to the contract with
                       the State, to seek relief by filing a Writ Petition.
                vi.    Without intending to be exhaustive, it may
                       include the relief of seeking payment of amounts
                       due to the aggrieved party from the State. The
                       State can, indeed, be called upon to honour its
                       obligations of making payment, unless it be that
                       there is a serious and genuine dispute raised
                       relating to the liability of the State to make the
                       payment. Such dispute, ordinarily, would include
                       the contention that the aggrieved party has not
                       fulfilled its obligations and the Court finds that
                       such a contention by the State is not a mere
                       ruse or a pretence.
                vii.   The existence of an alternate remedy, is,
                       undoubtedly, a matter to be borne in mind
                       in declining relief in a Writ Petition in a
                       contractual matter. Again, the question as to
                       whether the Writ Petitioner must be told off the
                       gates, would depend upon the nature of the
                       claim and relief sought by the petitioner, the
                       questions, which would have to be decided,
                       and, most importantly, whether there are
                       disputed questions of fact, resolution of which
                       is necessary, as an indispensable prelude to
                       the grant of the relief sought. Undoubtedly,
                       while there is no prohibition, in the Writ
                       Court even deciding disputed particularly
                       when questions the dispute of fact, surrounds
                       demystifying of documents only, the Court
578                                                         [2024] 7 S.C.R.

                      Digital Supreme Court Reports


                      may relegate the party to the remedy by way
                      of a civil suit.
                viii. The existence of a provision for arbitration,
                      which is a forum intended to quicken the pace
                      of dispute resolution, is viewed as a near bar to
                      the entertainment of a Writ Petition (See in this
                      regard, the view of this Court even in ABL (supra)
                      explaining how it distinguished the decision of
                      this Court in State of U.P. and others v. Bridge
                      & Roof Co., by its observations in paragraph-14
                      in ABL (supra)].
                ix.   The need to deal with disputed questions of fact,
                      cannot be made a smokescreen to guillotine a
                      genuine claim raised in a Writ Petition, when
                      actually the resolution of a disputed question
                      of fact is unnecessary to grant relief to a writ
                      applicant.
                x.    The reach of Article 14 enables a Writ Court
                      to deal with arbitrary State action even after
                      a contract is entered into by the State. A wide
                      variety of circumstances can generate causes
                      of action for invoking Article 14. The Court’s
                      approach in dealing with the same, would be
                      guided by, undoubtedly, the overwhelming need
                      to obviate arbitrary State action, in cases where
                      the Writ remedy provides an effective and fair
                      means of preventing miscarriage of justice arising
                      from palpably unreasonable action by the State.”
                                                 (Emphasis supplied)
       (iv) Exercise of Writ Jurisdiction after Termination or Breach
            of the Contract: -
           A relief by way of a writ under Article 226 of the Constitution
           will also lie against a termination or a breach of a contract,
           wherever such action is found to either be palpably unauthorized
           or arbitrary. Before turning away the parties to the remedy
           of civil suit, the courts must be mindful to see whether such
           termination or breach was within the contractual domain or
[2024] 7 S.C.R.                                                             579

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           whether the State was merely purporting to exercise powers
           under the contract for any ulterior motive. Any action of the
           State to cancel or terminate a contract which is beyond the
           terms agreed thereunder will be amenable to the writ jurisdiction
           to ascertain if such decision is imbued with arbitrariness or
           influenced by any extraneous considerations. The relevant
           observations read as under: -
                "xi. Termination of contract can again arise in a wide
                     variety of situations. If for instance, a contract is
                     terminated, by a person, who is demonstrated,
                     without any need for any argument, to be
                     the person, who is completely unauthorised
                     to cancel the contract, there may not be any
                     necessity to drive the party to the unnecessary
                     ordeal of a prolix and avoidable round of
                     litigation. The intervention by the High Court,
                     in such a case, where there is no dispute to
                     be resolved, would also be conducive in public
                     interest, apart from ensuring the Fundamental
                     Right of the petitioner under Article 14 of the
                     Constitution of India. When it comes to a
                     challenge to the termination of a contract by
                     the State, which is a non-statutory body, which
                     is acting in purported exercise of the powers/
                     rights under such a contract, it would be over
                     simplifying a complex issue to lay down any
                     inflexible Rule in favour of the Court turning away
                     the petitioner to alternate Fora. Ordinarily, the
                     cases of termination of contract by the State,
                     acting within its contractual domain, may not
                     lend itself for appropriate redress by the Writ
                     Court. This is, undoubtedly, so if the Court is
                     duty-bound to arrive at findings, which involve
                     untying knots, which are presented by disputed
                     questions of facts. Undoubtedly, in view of ABL
                     Limited (supra), if resolving the dispute, in a
                     case of repudiation of a contract, involves only
                     appreciating the true scope of documentary
                     material in the light of pleadings, the Court
580                                                  [2024] 7 S.C.R.

              Digital Supreme Court Reports


              may still grant relief to an applicant. We must
              enter a caveat. The Courts are today reeling
              under the weight of a docket explosion, which
              is truly alarming. If a case involves a large body
              of documents and the Court is called upon to
              enter upon findings of facts and involves merely
              the construction of the document, it may not be
              an unsound discretion to relegate the party to
              the alternate remedy. This is not to deprive the
              Court of its constitutional power as laid down
              in ABL (supra). It all depends upon the facts of
              each case as to whether, having regard to the
              scope of the dispute to be resolved, whether
              the Court will still entertain the petition.
       xii.   In a case the State is a party to the contract
              and a breach of a contract is alleged against
              the State, a civil action in the appropriate Forum
              is, undoubtedly, maintainable. But this is not the
              end of the matter. Having regard to the position
              of the State and its duty to act fairly and to
              eschew arbitrariness in all its actions, resort to
              the constitutional remedy on the cause of action,
              that the action is arbitrary, is permissible (See
              in this regard Kumari Shrilekha Vidyarthi and
              others v. State of U.P. and others). However, it
              must be made clear that every case involving
              breach of contract by the State, cannot be
              dressed up and disguised as a case of arbitrary
              State action. While the concept of an arbitrary
              action or inaction cannot be cribbed or confined
              to any immutable mantra, and must be laid bare,
              with reference to the facts of each case, it cannot
              be a mere allegation of breach of contract that
              would suffice. What must be involved in the case
              must be action/inaction, which must be palpably
              unreasonable or absolutely irrational and bereft
              of any principle. An action, which is completely
              malafide, can hardly be described as a fair action
              and may, depending on the facts, amount to
[2024] 7 S.C.R.                                                            581

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


                      arbitrary action. The question must be posed
                      and answered by the Court and all we intend to
                      lay down is that there is a discretion available to
                      the Court to grant relief in appropriate cases.”
                                                  (Emphasis supplied)
     (v)   Other relevant considerations for Exercise of Writ
           Jurisdiction: -
           Lastly, this Court held that the courts may entertain a contractual
           dispute under its writ jurisdiction where (I) there is any violation
           of natural justice or (II) where doing so would serve the public
           interest or (III) where though the facts are convoluted or
           disputed, but the courts have already undertaken an in-depth
           scrutiny of the same provided that the it was pursuant to a
           sound exercise of its writ jurisdiction. The relevant observations
           read as under: -
                "xiii. A lodestar, which may illumine the path of
                       the Court, would be the dimension of public
                       interest subserved by the Court interfering in
                       the matter, rather than relegating the matter to
                       the alternate Forum.
                xiv. Another relevant criteria is, if the Court has
                     entertained the matter, then, while it is not
                     tabooed that the Court should not relegate the
                     party at a later stage, ordinarily, it would be a
                     germane consideration, which may persuade the
                     Court to complete what it had started, provided
                     it is otherwise a sound exercise of jurisdiction to
                     decide the matter on merits in the Writ Petition
                     itself.
                xv.   Violation of natural justice has been recognised
                      as a ground signifying the presence of a public
                      law element and can found a cause of action
                      premised on breach of Article 14. [See Sudhir
                      Kumar Singh and Others (supra)].”
                                                  (Emphasis supplied)
56. What can be discerned from the above is that there has been a
    considerable shift in the scope of judicial review of the court when it
582                                                             [2024] 7 S.C.R.

                        Digital Supreme Court Reports


       comes to contractual disputes where one of the parties is the State
       or its instrumentalities. In view of the law laid down by this Court
       in ABL (supra), Joshi Technologies (supra) and in M.P. Power
       (supra), it is difficult to accept the contention of the respondent that
       the writ petition filed by the appellant before the High Court was not
       maintainable and the relief prayed for was rightly declined by the
       High Court in exercise of its Writ jurisdiction. Where State action is
       challenged on the ground of being arbitrary, unfair or unreasonable,
       the State would be under an obligation to comply with the basic
       requirements of Article 14 of the Constitution and not act in an arbitrary,
       unfair and unreasonable manner. This is the constitutional limit of
       their authority. There is a jural postulate of good faith in business
       relations and undertakings which is given effect to by preventing
       arbitrary exercise of powers by the public functionaries in contractual
       matters with private individuals. With the rise of the Social Service
       State more and more public-private partnerships continue to emerge,
       which makes it all the more imperative for the courts to protect the
       sanctity of such relations.
57. It is needless to state that in matters concerning specific modalities
    of the contract — such as required work, execution methods,
    material quality, timeframe, supervision standards, and other
    aspects impacting the tender’s purpose — the court usually refrains
    from interference. State authorities, like private individuals, have a
    consensual element in contract formation. The stipulations or terms
    in the underlying contract purpose are part of the consensual aspect,
    which need not be entertained by the courts in writ jurisdiction
    and the parties may be relegated to ordinary private law remedy.
    Judicial review does not extend to fixing contract stipulations but
    ensures that the public authorities act within their authority to
    prevent arbitrariness.
58. Thus, the demarcation between a private law element and public
    law element in the context of contractual disputes if any, may be
    assessed by ascertaining whether the dispute or the controversy
    pertains to the consensual aspect of the contract or tender in question
    or not. Judicial review is permissible to prevent arbitrariness of
    public authorities and to ensure that they do not exceed or abuse
    their powers in contractual transactions and requires overseeing
    the administrative power of public authorities to award or cancel
    contracts or any of its stipulations.
[2024] 7 S.C.R.                                                          583

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


59. Therefore, what can be culled out from the above is that although
    disputes arising purely out of contracts are not amenable to writ
    jurisdiction yet keeping in mind the obligation of the State to act fairly
    and not arbitrarily or capriciously, it is now well settled that when
    contractual power is being used for public purpose, it is certainly
    amenable to judicial review.
60. Now coming to the facts of the case at hand, the appellant has
    challenged the cancellation of the tender at the instance of the
    respondent on the ground of being manifestly arbitrary and influenced
    by extraneous considerations. It is evident from the notice of
    cancellation dated 07.02.2023, that the tender was not terminated
    pursuant to any terms of the contract subsisting between the parties,
    rather, the respondent ‘cancelled’ the tender saying that there was
    technical fault in the tender that was floated.
61. Thus, the respondent could be said to have exercised powers in its
    executive capacity as the action to cancel the tender falls outside
    the purview of the terms of the contract. Hence, it cannot be said
    that the present matter is purely a contractual dispute. It is also
    not a breach of contract, as no such breach has been imputed to
    the appellant in terms of the contract, but rather a plain and simple
    exercise of the executive powers.
62. Thus, the present dispute even if related to a tender, cannot be termed
    as a pure contractual dispute, as the dispute involves a public law
    element. Although there is no discharge of a public function by the
    respondent towards the appellant yet there is a right to public law
    action vested in him against the respondent in terms of Article 14
    of the Constitution. This is because the exercise of the executive
    power by it in the contractual domain i.e., the cancelling of the
    tender carries a corresponding public duty to act in a reasonable
    and rationale manner. Thus, we find that the writ petition filed by the
    respondent was maintainable and the relief prayed for could have
    been considered by the High Court in exercise of its writ jurisdiction.
     c.    Meaning and True Import of Arbitrariness of State Actions
           in Contractual Disputes.
63. In Ramana Dauaram Shetty v. The International Airport Authority
    of India & Ors. reported in AIR 1979 SC 1628 this Court held
    that the actions of the State in contractual matters must conform
584                                                          [2024] 7 S.C.R.

                      Digital Supreme Court Reports


       to some standard or norms which is rational, non-discriminatory
       and not guided by extraneous considerations, otherwise the same
       would be in violation of Article 14 of the Constitution. The relevant
       observations read as under: -
            “This rule also flows directly from the doctrine of equality
            embodied in Article 14. It is now well settled as a result
            of the decisions of this Court in E.P. Royappa v. State of
            Tamil Nadu, A.I.R. 1974 S.C. 555 and Maneka Gandhi v.
            Union of India, A.I.R. 1978 S.C. 597 that Article 14 strikes
            at arbitrariness in State action and ensures fairness and
            equality of treatment. It requires that State action must
            not be arbitrary but must be based on some rational and
            relevant principle which is non discriminatory; it must not
            be guided by any extraneous or irrelevant consideration,
            because that would be denial of equality. The principle
            of reasonableness and rationality which is legally as well
            as philosophically an essential element of equality or
            non-arbitrariness is projected by Article 14 and it must
            characterise every State action, whether it be under
            authority of law or in exercise of executive power without
            making of law. The State cannot, therefore, act arbitrarily
            in entering into relationship, contractual or otherwise with
            a third party, but its action must conform to some standard
            or norm which is rational and non-discriminatory.”
                                                  (Emphasis supplied)
64. In Dwarkadas Marfatia & Sons (supra) this Court speaking through
    Sabyasachi Mukherji, CJ. (as the learned Chief Justice then was)
    held that every action of the State or an instrumentality of the State
    must be informed by reason......actions uninformed by reason may be
    questioned as arbitrary. The relevant observations read as under: -
            “22. [...] every action of the State or as instrumentality of
            the State, must be informed by reason. Indubitably, the
            respondent is an organ of the State under Article 12 of
            the Constitution. In appropriate cases, as was observed in
            the last mentioned decision, actions uninformed by reason
            may be questioned as arbitrary in proceedings under
            Article 226 or Article 32 of the Constitution. But it has to
            be remembered that Article 14 cannot be construed as a
[2024] 7 S.C.R.                                                            585

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           charter for judicial review of State action, to call upon the
           State to account for its actions in its manifold activities by
           stating reasons for such actions.”
                                                  (Emphasis supplied)
65. The meaning and true import of arbitrariness is more easily
    visualized than precisely stated or defined. The question, whether
    an impugned action is arbitrary or not, is ultimately to be answered
    on the facts and in the circumstances of a given case. An obvious
    test to apply is to see whether there is any discernible principle
    emerging from the impugned act and if so, does it satisfy the test of
    reasonableness. Where a mode is prescribed for doing an act and
    there is no impediment in following that procedure, the performance
    of the act otherwise and in a manner which does not disclose any
    discernible principle which is reasonable, may itself attract the vice
    of arbitrariness. Every State action must be informed by reason and
    it follows that an act uninformed by reason, is arbitrary. Rule of law
    contemplates governance by laws and not by humour, whims or
    caprices of the men to whom the governance is entrusted for the time
    being. It is trite that be you ever so high, the laws are above you.
66. Control of administrative discretion is an important concern in the
    development of Rule of Law. According to Wade and Forsyth, the
    Rule of Law has four meanings, and one of them is that “government
    should be conducted within a framework of recognized rules and
    principles which restrict discretionary power”.
67. To enthuse efficiency in administration, a balance between
    accountability and autonomy of action should be carefully maintained.
    Overemphasis on either would impinge upon public efficiency. But
    undermining the accountability would give immunity or carte blanche
    power to act as it pleases with the public at whim or vagary. Whether
    the public authority acted bona fide would be gauged from the
    impugned action and attending circumstances. The authority should
    justify the action assailed on the touchstone of justness, fairness and
    reasonableness. Test of reasonableness is more strict. The public
    authorities should be duty conscious rather than power charged.
    Its actions and decisions which touch the common man have to be
    tested on the touchstone of fairness and justice. That which is not
    fair and just is unreasonable. And what is unreasonable is arbitrary.
    An arbitrary action is ultra vires. It does not become bona fide and in
586                                                           [2024] 7 S.C.R.

                       Digital Supreme Court Reports


       good faith merely because no personal gain or benefit to the person
       exercising discretion has been established. An action is mala fide if it
       is contrary to the purpose for which it was authorised to be exercised.
       Dishonesty in discharge of duty vitiates the action without anything
       more. An action is bad even without proof of motive of dishonesty, if
       the authority is found to have acted contrary to reason. [See: Mahesh
       Chandra v. Regional Manager, U.P. Financial Corporation & Ors. :
       (1993) 2 SCC 279]
68. The dictum as laid in Tata Cellular v. UOI reported in (1994) 6 SCC
    651 is that the judicial power of review is exercised to rein in any
    unbridled executive functioning. It was observed that the restraint
    has two contemporary manifestations viz. one is the ambit of judicial
    intervention and the other covers the scope of the court’s ability to
    quash an administrative decision on its merits. These restraints bear
    the hallmarks of judicial control over administrative action. It was
    held that the principle of judicial review is concerned with reviewing
    not the merits of the decision in support of which the application for
    judicial review is made, but the decision-making process itself. It was
    held that the principle of judicial review would apply to the exercise
    of contractual powers by the Government bodies in order to prevent
    arbitrariness or favouritism. It was held that the duty of the court is
    to confine itself to the question of legality and its concern should be
    whether a decision-making authority exceeded its powers; whether
    it committed an error of law or committed a breach of the rules of
    natural justice or reached a decision which no reasonable tribunal
    would have reached or, abused its powers. The grounds upon
    which an administrative action can be subjected to judicial review
    are classified as illegality, irrationality and procedural impropriety. In
    that very decision, while deducing the principles from various cases
    referred, it was held that the modern trend points to judicial restraint in
    administrative action; that the Court does not sit as a court of appeal
    but merely reviews the manner in which the decision was made; that
    the court does not have the expertise to correct the administrative
    decision and if a review of the administrative decision is permitted, it
    will be substituting its own decision, without the necessary expertise
    which itself may be fallible; that the terms of the invitation to tender
    cannot be open to judicial scrutiny because the invitation to tender is
    in the realm of contract; and, that the government must have freedom
    of contract, i.e. a free-play in the joints is a necessary concomitant
[2024] 7 S.C.R.                                                         587

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     for an administrative body functioning in an administrative sphere or
     quasi-administrative sphere. However, the decision must not only be
     tested by the application of Wednesbury principle of reasonableness,
     but must be free from arbitrariness not affected by bias or actuated
     by mala fides. Moreover, quashing decisions may impose heavy
     administrative burden on the administration and lead to increased
     and unbudgeted expenditure.
69. To ascertain whether an act is arbitrary or not, the court must carefully
    attend to the facts and the circumstances of the case. It should find
    out whether the impugned decision is based on any principle. If not,
    it may unerringly point to arbitrariness. If the act betrays caprice or
    the mere exhibition of the whim of the authority it would sufficiently
    bear the insignia of arbitrariness. In this regard supporting an order
    with a rationale which in the circumstances is found to be reasonable
    will go a long way to repel a challenge to State action. No doubt
    the reasons need not in every case be part of the order as such.
    If there is absence of good faith and the action is actuated with an
    oblique motive, it could be characterised as being arbitrary. A total
    non-application of mind without due regard to the rights of the parties
    and public interest may be a clear indicator of arbitrary action.
70. One another way, to assess whether an action complained of could
    be termed as arbitrary is by way of scrutinizing the reasons that have
    been assigned to such an action. It involves overseeing whether
    the reasons which have been cited if at all genuinely formed part
    of the decision-making process or whether they are merely a ruse.
    All decisions that are taken must earnestly be in lieu of the reasons
    and considerations that have been assigned to it. The Court must be
    mindful of the fact that it is not supposed to delve into every minute
    details of the reasoning assigned, it need not to go into a detailed
    exercise of assessing the pros and cons of the reasons itself, but
    should only see whether the reasons were earnest, genuine and
    had a rationale with the ultimate decision. What is under scrutiny
    in judicial review of an action is the decision-making process and
    whether there is any element of arbitrariness or mala fide.
71. Thus, the question to be answered in such situations is whether the
    decision was based on valid considerations. This is undertaken to
    ensure that the reasons assigned were the true motivations behind
    the action and it involves checking for the presence of any ulterior
588                                                             [2024] 7 S.C.R.

                        Digital Supreme Court Reports


       motives or irrelevant considerations that might have influenced the
       decision. The approach of the court must be to respect the expertise
       and discretion of administrative authorities while still protecting against
       arbitrary and capricious actions. Thus, now the only question that
       remains to be considered is whether the action of the respondent
       to cancel the tender could be termed as arbitrary?
       ii.    Whether the action of cancelling the tender is arbitrary or
              unfair and in consequence of violation of Article 14 of the
              Constitution?
72. The principal contention of the appellant is that the notice of
    cancellation dated 07.02.2023 that was issued by the respondent is
    manifestly arbitrary, unreasonable and influenced by mala fide and
    extraneous considerations.
73. Before we proceed to determine whether the cancellation of tender
    could be termed as arbitrary, it is necessary to understand the stance
    of the respondent in the present litigation, as discernible from their
    pleadings, which has left us quite perplexed. The argument of the
    respondent is two-fold: -
       (i)    First, that the tender had to be cancelled as there was a
              technical fault. The tender was found to be ‘non-specific’ &
              ‘not well defined’ as a result it created ambiguity resulting in
              financial losses to the respondent.
       (ii)   Secondly, the cancellation was also on account of a change in
              policy whereby, the operation & maintenance of the concerned
              underpasses had been handed over to another authority.
74. The primary thrust of the respondent’s contention is that the
    decision to cancel the tender was taken in view of the technical
    faults in the same, more particularly the ambiguity as to whether
    the advertisement boards could be put up beyond the area of the
    concerned underpasses.
75. The learned Single Judge of the High Court in its order dated
    24.04.2023 observed that there was an ambiguity in the Special Terms
    & Conditions of the Memorandum of Tender more particularly clauses
    10 and 14 respectively which gave rise to a conflicting interpretation
    as to the placement of the signboards. This in the opinion of the
    High Court was a technical fault, which the respondent sought to
[2024] 7 S.C.R.                                                             589

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     rectify by way of cancelling the tender. The relevant observations
     read as under: -
           “18. [...] In fact, the letter of cancellation provides further
           reasons, namely, that the tender has been found to be
           non-specific and having technical faults. This would also
           be borne out from clauses 10 and 14 of the Special
           Terms and Conditions of the tender document which give
           rise to conflicting interpretations on the placement of the
           signboards. Hence, besides the administrative decision to
           hand over the maintenance of E.M. Bypass from KMDA
           to KMC, the respondent KMDA as the tendering authority,
           has a right to rectify the ambiguities in the bid document
           by cancelling the same.”
                                                   (Emphasis supplied)
76. However, interestingly, the Notice of Cancellation dated 07.02.2023
    that came to be issued by the respondent makes no mention of any
    such lacuna. In fact, there is no reference to the aforementioned
    clauses or any conflict in their interpretation. The aforesaid notice
    only states that the tender was found to be ‘non-specific’ and ‘not
    well defined’ which created ambiguity due to which the respondent is
    incurring losses, and nothing is stated either about the ambiguity in
    putting up the advertisement boards or for that matter which aspect
    of the tender is non-specific.
77. It is also apposite to mention that just a month prior to cancelling
    the tender, the respondent on 24.01.2023 issued a notice to the
    appellant, asking him to stop all work in respect of the tender.
    Remarkably, in the said notice, there is no whisper about there
    being any of the aforementioned technical faults in the tender floated
    by the respondent. In fact, a close reading of the aforesaid notice
    would reveal that the orders to stop the work had been issued for
    an altogether different reason – i.e., handing over of the operation
    & maintenance of the concerned underpasses to another authority
    i.e., KMC.
     a.    Scrutiny of Internal File-Notings and Deliberations of the
           State.
78. The appellant has in particular placed reliance on various notings
    made in the internal file of the respondent in respect of the tender to
590                                                          [2024] 7 S.C.R.

                       Digital Supreme Court Reports


       contend that the cancellation of the same was arbitrary and influenced
       by extraneous considerations. The respondent on the other hand
       submitted that the internal file-notings cannot be used or relied upon
       to impute any ill-motives to the decision of cancelling the tender as
       they only reflect the opinion of a particular individual and cannot be
       construed or interpreted as the decision of the respondent. In this
       regard, reliance has been placed on the following decisions: -
       i.    Pimpri Chinchwad New Township Development Authority
             v. Vishnudev Coop. Housing Society : (2018) 8 SCC 215.
       ii.   Shanti Sports Club v. Union of India : (2009) 15 SCC 705.
79. This Court in its decision in Bachhittar Singh v. State of Punjab &
    Anr. reported in AIR 1963 SC 395 held that merely because something
    was written in the internal files and notesheet does not amount to an
    order, it at best is an expression of opinion which may be changed,
    and it only becomes an order when such opinion is formally made
    into a decision. The relevant observations read as under: -
             “9. The question, therefore, is whether he did in fact make
             such an order. Merely writing something on the file does
             not amount to an order. Before something amounts to an
             order of the State Government two things are necessary.
             The order has to be expressed in the name of the Governor
             as required by clause (1) of Article 166 and then it has to
             be communicated. As already indicated, no formal order
             modifying the decision of the Revenue Secretary was
             ever made. Until such an order is drawn up the State
             Government cannot, in our opinion, be regarded as bound
             by what was stated in the file. [...]
             10. The business of State is a complicated one and has
             necessarily to be conducted through the agency of a
             large number of officials and authorities. The Constitution,
             therefore, requires and so did the Rules of Business framed
             by the Rajpramukh of PEPSU provide, that the action
             must be taken by the authority concerned in the name
             of the Rajpramukh. It is not till this formality is observed
             that the action can be regarded as that of the State or
             here, by the Rajpramukh. [...] Indeed, it is possible that
             after expressing one opinion about a particular matter at
[2024] 7 S.C.R.                                                            591

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           a particular stage a Minister or the Council of Ministers
           may express quite a different opinion, one which may be
           completely opposed to the earlier opinion. Which of them
           can be regarded as the “order” of the State Government?
           Therefore, to make the opinion amount to a decision of
           the Government it must be communicated to the person
           concerned.”
                                                  (Emphasis supplied)
     [See also: Delhi Development Authority v. Hello Home Education
     Society : (2024) 3 SCC 148 at para 17 Mahadeo & Ors. v. Sovan
     Devi & Ors. : (2023) 10 SCC 807 at paras 15-17; Municipal
     Committee, Barwala v. Jai Narayan and Co. & Anr. : (2022) SCC
     OnLine 376 at para 16]
80. In Sethi Auto Service Station v. DDA reported in (2009) 1 SCC 180
    this Court held that notings in a departmental file are nothing more
    than an opinion by an officer for internal use and consideration of
    other officials for the final decision making. The relevant observations
    read as under: -
           “14. It is trite to state that notings in a departmental file
           do not have the sanction of law to be an effective order.
           A noting by an officer is an expression of his viewpoint on
           the subject. It is no more than an opinion by an officer for
           internal use and consideration of the other officials of the
           department and for the benefit of the final decision-making
           authority. Needless to add that internal notings are not
           meant for outside exposure. Notings in the file culminate
           into an executable order, affecting the rights of the parties,
           only when it reaches the final decision-making authority
           in the department, gets his approval and the final order
           is communicated to the person concerned.”
                                                  (Emphasis supplied)
81. In Shanti Sports Club (supra) several representations were made
    by the landowners requesting to release their land from acquisition.
    After considering those representations, the concerned minister
    recorded in the note file that the land should be denotified on suitable
    terms and left the final decision to his successor. The new minister,
    however, rejected the request for denotification. Consequently, writ
592                                                          [2024] 7 S.C.R.

                      Digital Supreme Court Reports


       petitions were filed, seeking the release of the land based on the
       note file. This Court held that the notings recorded in the official
       files do not become decisions and confer no right unless the same
       are sanctified, authenticated and communicated in the prescribed
       manner. It further held that any recording in the note-file can always
       be reviewed, reversed or overruled. The relevant observations read
       as under: -
            “43. A noting recorded in the file is merely a noting
            simpliciter and nothing more. It merely represents
            expression of opinion by the particular individual. By no
            stretch of imagination, such noting can be treated as a
            decision of the Government. Even if the competent authority
            records its opinion in the file on the merits of the matter
            under consideration, the same cannot be termed as a
            decision of the Government unless it is sanctified and acted
            upon by issuing an order in accordance with Articles 77(1)
            and (2) or Articles 166(1) and (2). The noting in the file or
            even a decision gets culminated into an order affecting
            right of the parties only when it is expressed in the name
            of the President or the Governor, as the case may be,
            and authenticated in the manner provided in Article 77(2)
            or Article 166(2). A noting or even a decision recorded
            in the file can always be reviewed/reversed/overruled or
            overturned and the court cannot take cognizance of the
            earlier noting or decision for exercise of the power of
            judicial review.
                       xxx			xxx			xxx
            52. As a result of the above discussion, we hold that the
            notings recorded in the official files by the officers of the
            Government at different levels and even the Ministers do
            not become decisions of the Government unless the same
            is sanctified and acted upon by issuing an order in the
            name of the President or Governor, as the case may be,
            authenticated in the manner provided in Articles 77(2) and
            166(2) and is communicated to the affected persons. The
            notings and/or decisions recorded in the file do not confer
            any right or adversely affect the right of any person and the
            same can neither be challenged in a court nor made basis
[2024] 7 S.C.R.                                                          593

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           for seeking relief. Even if the competent authority records
            a noting in the file, which indicates that some decision
           has been taken by the authority concerned, the same can
           always be reviewed by the same authority or reversed or
           overturned or overruled by higher functionary/authority in
           the Government.”
                                                 (Emphasis supplied)
     [See also: State of Uttaranchal v. Sunil Kumar Vaish : (2011) 8
     SCC 670 at para 24]
82. In Pimpri Chinchwad (supra), a revenue minister passed an order
    for deletion of the land of the respondent therein from acquisition
    proceeding, but the said order was never communicated, however,
    the same was mentioned in the internal note file. Sometime later, the
    government decided to reconsider all uncommunicated orders. As
    a result the respondents therein filed a writ seeking implementation
    of the order as mentioned in the internal note-file. This Court held
    that the notings in official files of the government are an internal
    matter and carry no legal sanctity unless they are approved and
    duly communicated as per the prescribed procedure. It is only when
    such notings are translated into formal decisions, they would create
    some right or claim in favour of a person. The relevant observations
    read as under: -
           “36. [...] first, a mere noting in the official files of the
           Government while dealing with any matter pertaining
           to any person is essentially an internal matter of the
           Government and carries with it no legal sanctity; second,
           once the decision on such issue is taken and approved by
           the competent authority empowered by the Government
           in that behalf, it is required to be communicated to the
           person concerned by the State Government. In other
           words, so long as the decision based on such internal
           deliberation is not approved and communicated by the
           competent authority as per the procedure prescribed in
           that behalf to the person concerned, such noting does
           not create any right in favour of the person concerned nor
           it partake the nature of any legal order so as to enable
           the person concerned to claim any benefit of any such
594                                                         [2024] 7 S.C.R.

                     Digital Supreme Court Reports


          internal deliberation. Such noting(s) or/and deliberation(s)
          are always capable of being changed or/and amended or/
          and withdrawn by the competent authority.”
                                                 (Emphasis supplied)
83. We are of the view that the reliance on the part of the respondent
    on the decisions of this Court in Pimpri Chinchwad (supra) and
    Shanti Sports Club (supra) to assert that no reference could be
    made to the internal-file notings for the purposes of judicial review of
    its decision is completely misplaced. In Shanti Sports Club (supra)
    the question before the Court was as to when an internal noting can
    be used to confer or claim a right. Whereas in Pimpri Chinchwad
    (supra) the issue for consideration before the Court was whether any
    internal-note or deliberation once written in the files was capable of
    being reconsidered, changed, modified or withdrawn.
84. None of the aforementioned decisions lay down that the courts are
    completely precluded from appraising or scrutinizing the internal
    file notings and deliberations for the purposes of judicial review of
    a decision. This Court in Pimpri Chinchwad (supra) and Shanti
    Sports Club (supra) only went so far as to say that as long as the
    deliberations in the internal file notings have not been formalized
    into an official decision, the same cannot be relied upon to claim
    any right.
85. We are of the considered opinion that once a decision has been
    officially made through proper means and channel, any internal
    deliberations or file notings that formed a part of that decision-making
    process can certainly be looked into by the Court for the purposes
    of judicial review in order to satisfy itself of the impeccability of the
    said decision.
86. In the aforesaid context, we may refer to the decision of this Court
    in State of Bihar v. Kripalu Shankar reported in (1987) 3 SCC 34,
    wherein it was held that the internal file notings reflect the views
    and line of thinking of a particular officer. It further held that such
    views would amount to disobedience or contempt of court only when
    they are translated into a formal decision. The relevant observations
    read as under: -
          “11. After this finding, the High Court held some of the
          officers of the government guilty solely on the basis of the
[2024] 7 S.C.R.                                                              595

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           views expressed by them in the files, which were not, in
           fact, accepted by the Government and which were only at
           the stage of suggestions and views. Shri K.K. Venugopal,
           the learned Counsel for the State contended that it would
           be unsafe to initiate action in contempt merely on the
           strength or notings by officials on the files, expressing
           their views and to do so would imperil the working of
           various departments in a Government in a democracy
           and would have far-reaching consequences. Sometimes
           a view expressed by an officer may be incorrect. The view
           so expressed passes through various hands and gets
           translated into action only at the ultimate stage. The views
           so expressed are only for internal use. Such views may
           indicate the line of thinking of a particular officer. Until the
           views so expressed culminate into an executable order,
           the question of disobedience of court’s order does not
           arise. Though the State Government have been found not
           guilty, the State has filed the appeal to protect its officers
           from independent and fearless expression of opinion and
           to see that the order under appeal does not affect the
           proper functioning of the Government.”
                                                   (Emphasis supplied)
87. The above observations of this Court fortify our view that once a
    decision is made, all opinions and deliberations pertaining to the
    said decision in the internal file-notings become a part of the process
    by which the decision is arrived at, and can be looked into for the
    purposes of judicial review. In other words, any internal discussions
    or notings that have been approved and formalized into a decision by
    an authority can be examined to ascertain the reasons and purposes
    behind such decisions for the overall judicial review of such decision-
    making process and whether it conforms to the principles enshrined
    in Article 14 of the Constitution.
88. One another reason why the respondent cannot claim that its internal
    file-notings fall outside the purview of judicial review of the courts
    is in view of the inviolable rule that came to be recognized by this
    Court in Ramana Dayaram Shetty (supra) wherein it was held that
    an executive authority must be rigorously held to the standard by
    which it professes its actions to be judged. The relevant observations
    read as under: -
596                                                          [2024] 7 S.C.R.

                     Digital Supreme Court Reports


          “10. [...] It is a well-settled rule of administrative law that
          an executive authority must be rigorously held to the
          standards by which it professes its actions to be judged
          and it must scrupulously observe those standards on pain
          of invalidation of an act in violation of them. [...]”
                                                  (Emphasis supplied)
89. The aforesaid leaves no manner of doubt in our mind that if the
    purported action of cancelling the tender is claimed to have been
    taken in view of certain technical faults in the same or even a change
    in policy the same ought to be clearly reflected from its internal file
    notings as-well, pursuant to which the purported decision was taken.
90. We have gone through the internal file-notings of the respondent on
    the aforesaid tender wherein the entire internal deliberations of the
    KMDA officials as to the tender for work have been recorded. In the
    entire records – right from the time the Notice Inviting Tender was
    being formulated till the issuance of the final Notice of Cancellation
    dated 07.02.2023, there is no whisper of any particular clauses of
    the tender that was floated nor of any conflict or technical fault in
    the same, as claimed by the respondent.
91. We are in seisin of the fact that although the internal-file notings
    mention about the policy change in the operation and maintenance
    of the concerned underpasses, yet a careful reading of the same
    reveals that the cancellation of the tender for work was neither due to
    any technical fault nor due to the policy change in the operation and
    maintenance of the concerned underpasses but was for altogether
    a different reason.
92. As per Note #91 dated 30.12.2022 of the file-notings, when the
    Order dated 01.12.2022 of the Urban Development and Municipal
    Affairs Department came to be passed whereby the maintenance
    was handed over to KMC, it was the Minister-In-Charge as the
    Chairperson of the respondent authority – who suggested that in view
    of the change in scenario the tender be cancelled. In the aforesaid
    note, the following has been recorded - “Recently maintenance of
    EM Bye pass has been handed over to KMC. Thus, in this changed
    scenario we may cancel the work order”.
93. The words “may cancel the work order” clearly indicate, that the
    respondent at that stage by no means was of the opinion that the
[2024] 7 S.C.R.                                                           597

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     tender was required to be cancelled, as no specific reasons had
     been assigned as to what effect the policy change had impacted
     the feasibility or practicality of the tender. This is especially because,
     none of the officials of the respondent suggested that the tender be
     cancelled, rather it was the concerned minister who did so.
94. In Note #95 dated 10.01.2023 it has been clearly recorded by the
    officials of the respondent that it was the competent authority of the
    KMDA that instructed to cancel the tender in view of the aforesaid
    change in the policy. However, since the officials of the respondent
    were in doubt regarding the legality of such action, it insisted on first
    obtaining the advice or opinion from its legal cell before proceeding
    further. Furthermore, the aforesaid note clearly indicates that the
    work stop order had to be issued only with a view to comply with
    the instructions of the competent authority while it decided upon the
    aspect of cancellation of the tender.
95. In Note #97, the respondent has recorded the following – “There is
    no different opinion than to get this cancelled, once this has been
    decided by the Authority but a legal opinion may be sought for avoiding
    further litigations”. This also clearly indicates that as the competent
    authority had decided that the tender be cancelled, the officials of the
    respondent had no other choice but to cancel the tender. However,
    the respondent continued insisting on first obtaining the opinion from
    its legal cell before cancelling the same.
96. However, thereafter, as per Note #108 dated 24.01.2023 it is
    apparent that the concerned minister during his visit specifically
    instructed the officials of the respondent to cancel the tender.
    Pursuant to which, the respondent as per Note #109 dated
    02.02.2023 immediately convened a meeting to undertake the steps
    for cancellation even though the advice from the legal cell had yet
    to be obtained. It thereafter prepared a proposal for cancellation,
    which culminated into the ultimate notice of cancellation dated
    07.02.2023.
97. From the above narrated sequence of events, it is evident that it
    was none other but the concerned minister who suggested to cancel
    the tender. The respondent was reluctant to immediately cancel the
    tender for work and continued to insist on obtaining the opinion from
    its legal cell. Even though the opinion of the legal cell was yet to be
    obtained, the respondent, despite its initial reluctance, undertook
598                                                       [2024] 7 S.C.R.

                     Digital Supreme Court Reports


       immediate steps to cancel the tender after the concerned minister
       personally instructed the officials to do so.
98. Thus, it is evident that the Notice of Cancellation dated 07.02.2023,
    issued to the appellant, was at the behest of the concerned minister.
    The respondent clearly recorded that, because instructions for
    cancellation had been received from the higher-ups, there was
    no option but to proceed with the cancellation. Even before the
    respondent could properly and thoroughly explore the possibility
    of acceding to such request by consulting its legal cell, the tender
    was cancelled only at the instance and specific instructions of the
    concerned minister.
99. The aforesaid aspect can be looked at from one another angle. The
    concerned Minister-In-Charge had instructed to cancel the tender in
    view of the change in policy whereby the operation & maintenance
    of the underpasses was vested in another authority. To ascertain
    whether the decision of the concerned minister to cancel the tender
    was arbitrary or not, we must first consider whether the reason for
    such cancellation was genuinely on the basis of the aforesaid change
    in policy or whether it was driven by some personal discretion or
    motives. This can be discerned by first understanding the change
    in policy that took place.
100. The Urban Development and Municipal Affairs Department by way
     of its Order dated 01.12.2022 decided that the maintenance of the
     roads and drainage of the E.M. Bypass shall be handed over by
     the respondent to the KMC.
101. As per the Note #91 dated 30.12.2022, the concerned minister
     for the first time proposed cancellation of the tender in view of the
     aforesaid change in scenario as a result of the maintenance of the
     E.M. Bypass being handed over from the respondent to the KMC.
102. However, it is pertinent to note that in the aforesaid order of the
     Urban Development and Municipal Affairs Department it has
     been specifically stated that the right to collect revenue from the
     advertisements as-well as the control of the E.M. Bypass shall
     continue to remain with the respondent herein.
103. Thus, the respondent at the relevant point of time was not only
     in control of the two underpasses, but was also empowered to
     continue collecting revenue from the advertisements displayed at
[2024] 7 S.C.R.                                                            599

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     the underpasses. As such the respondent even after the change in
     policy, remained well within its rights to continue charging license
     fee in lieu of the advertisement rights by way of the aforesaid tender
     that was issued to the appellant.
104. When the respondent issued the work stop orders to the appellant
     on 24.01.2023 in view of the handing over of the maintenance of the
     E.M. Bypass to the KMC, the appellant in response, pointed out that
     the work stop orders were completely misconceived as the respondent
     continued to retain the custody as-well as the advertisement rights
     of the concerned underpasses.
105. It was only after the appellant highlighted why the work stop orders
     were misconceived and uncalled for, that the respondent immediately
     flipped its stance and in its notice of cancellation that was issued
     just 1-month later, it attributed ‘technical faults’ in the tender floated.
106. At the relevant point of time, there could have been no occasion
     for the respondent to cancel the tender on the basis of the Urban
     Development and Municipal Affairs Department’s order dated
     01.12.2022. We say so because:-
     (i)    First, as per the aforesaid order, it was explicitly clarified
            that the respondent would continue to retain the operation
            & maintenance as-well as the advertisement rights of the
            concerned underpasses.
     (ii)   Secondly, only the structural maintenance and restoration of the
            E.M. Bypass’s carriageway, roads, underground drainage etc.
            were to be handed over to the KMC. Indisputably, the tender
            that was issued in favour of the appellant was distinct from
            the maintenance that was handed over to KMC inasmuch as
            the scope of work of tender was limited to cleaning the roads,
            walls, floors etc., maintaining the electric-fixtures and upkeep
            of the gardens.
     (iii) Thirdly, despite the stance of the respondent of “change in
           scenario” due to the handing over of the maintenance, we find
           that after cancelling the tender and during the pendency of the
           present appeal, it was the respondent who floated fresh tender
           for the work of maintenance in respect of the same underpasses
           and not KMC, thus fortifying our view that the aforesaid change
           in policy had no bearing on the cancellation of the tender.
600                                                        [2024] 7 S.C.R.

                      Digital Supreme Court Reports


107. It is only on 16.09.2023 i.e., much after the cancellation of
     the tender that the Urban Development and Municipal Affairs
     Department, Government of West Bengal modified its earlier order
     whereby both, the control along with the right to revenue for the
     said structures were handed over to KMC from the respondent.
     This leaves no manner of doubt in our mind that the concerned
     minister’s decision to cancel the tender on account of purported
     ‘change in policy’ was without any application of mind, capricious
     and influenced by malice.
       b.   Concept of Public Interest in Administrative Decisions.
108. The reluctance on the part of the respondent to cancel the tender
     is also evident from Note #97, wherein the authority expressed
     its concern over the potential consequences of such cancellation.
     The respondent apprehended that in the event the tender for work
     was being cancelled, the routine maintenance of the underpasses
     would be disrupted. Due to this, the underpasses would have to be
     closed until some other agency could take over the maintenance.
     The relevant observations read as under: -
            “Note # 97
            [...] Besides, the underpasses are being maintained by
            the bidder. Once the contract is cancel led, the routine
            maintenance would be an issue till the work is awarded
            thru tender. The E&M Sector may be asked to do the
            maintenance by engaging one of the existing agency from
            their set up. 0therwise, both the underpasses should be
            under the lock and key or police custody.
            16/01/2023 04:38 PM                   SUBHANKAR
                                                BHATTACHARYA
                                          CE (REBBRDG) (KMDA)”
109. From the above it is evident that the cancellation of the tender was
     not in public interest. It may also not be out of place to mention that
     as per the internal file-notings the respondent had itself acknowledged
     that the revenue model of the aforesaid tender for work was far more
     beneficial and was fetching higher rates than the existing models
     of other agencies on the E.M. Bypass. The relevant observations
     read as under: -
[2024] 7 S.C.R.                                                          601

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           “Note # 88
           [...] In this model KMDA is saving Rs. 90.00 Lacs per year
           mentioned in Note#49 and earned Rs.62,67,110/- per year
           with 5% increment for each year. [...]
           So it appears that the rate of this current Revenue model
           tender are receiving much higher rate than any hoarding
           installed on E.M. Bypass. [...]
           29/12/2022 02:52 PM                  SANTANU PATRA
                                            SE (REBBRDG) (KMDA)
           Note # 89
           [...] The cost of revenue generation would be enhanced at
           a rate 5% at the end of each year, whereas, the authority
           need not to bother about the routine annual maintenance
           cost of appurtenances and labours, security force etc. which
           would increase as well. By this way two simultaneous
           benefits go in favour of the Authority. [...]
           30/12/2022 05:54 PM                     SUBHANKAR
                                                 BHATTACHARYA
                                           CE (REBBRDG) (KMDA)”
110. Thus, the respondent’s reasoning in the Notice of Cancellation dated
     07.02.2023 that it was incurring financial losses from the aforesaid
     tender does not hold well either. It has been contended by the
     respondent that due to the ambiguity in tender as regards placement
     of advertisements, many interested bidders might not have been
     able to submit their bids. Thus, the respondent formed the view that
     if the ambiguity is corrected a higher license fee could be fetched.
111. However, we are not impressed with the above submission. As
     discussed in the preceding paragraphs of this judgment, nothing to
     this effect is even remotely indicated from the internal file notings of
     the respondent or the materials on record. There is nothing to suggest
     that there was a technical fault in the tender resulting in financial
     losses or that there was a possibility of fetching higher license fees.
     On the contrary, it can be seen that the respondent itself was of the
     opinion that the tender for work was financially beneficial to it. This
     further undermines the claims of technical faults or potential financial
     losses, and suggests that the decision to cancel the tender was not
602                                                         [2024] 7 S.C.R.

                     Digital Supreme Court Reports


       based on genuine financial concerns but rather on other, possibly
       extraneous factors.
112. Even assuming for a moment that there was a technical fault in
     the tender, which if rectified had the possibility of generating more
     revenue, the same by no stretch could be said to be a cogent reason
     for cancelling an already existing tender. In this regard reference
     may be made to the decision of this Court in Vice Chariman &
     Managing Director, City & Industrial Development Corporation
     of Maharashtra Ltd. & Anr. v. Shishir Realty Pvt. Ltd. & Ors.
     reported in (2021) SCC OnLine SC 1141 wherein it was held that
     mere possibility of more money in public coffers does not in itself
     serve ‘public interest’. A blanket claim by the State claiming loss
     of public money cannot be used to forgo contractual obligations,
     especially when it is not based on any evidence or examination as the
     larger interest of upholding contracts is also in the play. The relevant
     observations read as under: -
           “58. When a contract is being evaluated, the mere
           possibility of more money in the public coffers, does not
           in itself serve public interest. A blanket claim by the State
           claiming loss of public money cannot be used to forgo
           contractual obligations, especially when it is not based on
           any evidence or examination. The larger public interest of
           upholding contracts and the fairness of public authorities is
           also in play. Courts need to have a broader understanding
           of public interest, while reviewing such contracts.”
                                                  (Emphasis supplied)
113. In Vasantkumar Radhakisan Vora (Dead) by His LRs. v. Board
     of Trustees of the Port of Bombay, reported in (1991) 1 SCC 761,
     this Court held that wherever a public authority seeks to resile or
     relive itself from the enforcement of a promise made or obligation
     undertaken in the name of public interest, it is legally bound to first
     show the material or circumstances by which public interest would be
     jeopardised if such enforcement is insisted. The relevant observations
     read as under: -
           “20. When it seeks to relieve itself from its application the
           government or the public authority are bound to place before
           the court the material, the circumstances or grounds on
[2024] 7 S.C.R.                                                              603

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           which it seeks to resile from the promise made or obligation
           undertaken by insistence of enforcing the promise, how the
           public interest would be jeopardised as against the private
           interest. It is well settled legal proposition that the private
           interest would always yield place to the public interest. [...]”
                                                    (Emphasis supplied)
114. We may again refer to the decision of this Court in M.P. Power
     Management Company Ltd. (supra) wherein this Court observed that
     merely because the rates embodied in a contract with the passage
     of time have become less appealing, the same cannot become a
     determinative criterion for either terminating the contract or for the
     courts to decline interference in such contractual disputes. The relevant
     observations read as under: -
           “88. Therefore, on a conspectus of the case law, we find
           that the concept of overwhelming public interest has
           essentially evolved in the context of cases relating to the
           award of contract by the State. It becomes an important
           consideration in the question as to whether then the State
           with whatever free play it has in its joints decides to award
           a contract, to hold up the matter or to interfere with the
           same should be accompanied by a careful consideration
           of the harm to public interest. We do not go on to say
           that consideration of public interest should not at all enter
           the mind of the court when it deals with a case involving
           repudiation of a claim under a contract or for that matter
           in the termination of the contract. However, there is a
           qualitative State enters into the contract, rights are created.
           If the case is brought to the constitutional court and it is
           invited to interfere with State action on the score that its
           action is palpably arbitrary, if the action is so found then
           an appeal to public interest must be viewed depending
           on the facts of each case. If the aspect of public interest
           flows entirely on the basis that the rates embodied in the
           contract which is arbitrarily terminated has with the passage
           of time become less appealing to the State or that because
           of the free play of market forces or other developments,
           there is a fall in the rate of price of the services or goods
           then this cannot become determinative of the question as
604                                                        [2024] 7 S.C.R.

                     Digital Supreme Court Reports


          to whether court should decline jurisdiction. In this case,
          it is noteworthy that the rates were in fact settled on the
          basis of international competitive bidding and in which as
          many as 182 bidders participated and the rate offered by
          the first respondent was undoubtedly the lowest. The fact
          that power has become cheaper in the market subsequently
          by itself should not result in non-suiting of the complaint
          of the first respondent, if it is found that a case of clear
          arbitrariness has been established by the first respondent.
          89. In other words, public interest cannot also be conflated
          with an evaluation of the monetary gain or loss alone.”
                                                 (Emphasis supplied)
115. What can be discerned from the above is that this Court has
     consistently underscored that any decision to terminate a contract
     must be grounded in a real and palpable public interest, duly supported
     by cogent materials and circumstances in order to ensure that State
     actions are fair, transparent, and accountable. Public interest cannot
     be used as a pretext to arbitrarily terminate contracts and there must
     be a clear and demonstrable ramification or detriment on the public
     interest to justify any such action.
116. Considerations of public interest should not be narrowly confined to
     financial aspects. The courts must have a more holistic understanding
     of public interest wherever the fairness of public authorities is in
     question, giving due regard to the broader implications of such
     action on the stability of contractual obligations. Merely because the
     financial terms of a contract are less favourable over a period of time
     does not justify its termination. Such decisions must be based on a
     careful consideration of all relevant factors, including the potential
     harm to the integrity and sanctity of contractual relationships. The
     larger interest of upholding contracts cannot be discarded in the
     name of monetary gain labelled as public interest.
117. We may make a reference to the observations made by this Court
     in Har Shankar & Ors. v. Dy. Excise and Taxation Commr. & Ors.
     reported in (1975) 1 SCC 737, wherein this Court held that those
     who contract with open eyes must accept the burdens of contract
     along with its benefit. It further held that the enforcement of rights
     and obligations arising out of a contract cannot depend on whether
[2024] 7 S.C.R.                                                           605

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


     the contracting party finds it prudent to abide by it. The relevant
     observations read as under: -
           “16. [...] Those who contract with open eyes must accept the
           burdens of the contract along with its benefits. The powers
           of the Financial Commissioner to grant liquor licences by
           auction and to collect licence fees through the medium of
           auctions cannot by writ petitions be questioned by those
           who, had their venture succeeded, would have relied upon
           those very powers to found a legal claim. Reciprocal rights
           and obligations arising out of contract do not depend for
           their enforceability upon whether a contracting party finds
           it prudent to abide by the terms of the contract. By such a
           test no contract could ever have a binding force.”
                                                  (Emphasis supplied)
118. Thus, we are of the view that the respondent’s stance of a mere
     possibility of fetching higher license fees was no ground to cancel
     the tender issued to the appellant for the purposes of rectifying it,
     especially when the respondent completely failed to demonstrate
     as to how there was a technical fault in the tender or how potential
     interested bidders did not participate due to it or how fetching higher
     license fees was more than a mere possibility.
119. At this stage, we may also answer one another submission that
     was canvassed on behalf of the respondent as regards the other
     aspect of public interest besides the monetary gain. It was submitted
     on behalf of the respondent that the decision to cancel the tender
     was also keeping in mind the considerations such as being able
     to engage experts for maintenance of critical public infrastructure.
     It is the case of the respondent that the tender was cancelled in
     order to float separate tenders, one for the maintenance work and
     another for licensing advertisement rights to ensure expertise in
     each respective field.
120. We are not impressed by the above submission either. We need not
     refer to a copious amount of documents in this regard, as just a bare
     perusal of the notice inviting tender shows that the eligibility criterion
     for participating in the tender process prescribed a comprehensive
     threshold of requirement of experience in structural works and
     successful completion of similar natured projects, thus ensuring
606                                                        [2024] 7 S.C.R.

                      Digital Supreme Court Reports


       that the bidders participating in the tender possess the necessary
       expertise for the work of maintenance.
121. Even otherwise, if at all the respondent was very much concerned
     about the maintenance of the underpasses due to lack of expertise of
     the appellant, it was always open to the respondent to terminate the
     contract in terms of the termination clause as envisaged in Clause
     35 of the Special Terms & Conditions of the Memorandum for the
     breach or non-compliance of any of the obligations or terms of the
     tender. Mere apprehension of lack of expertise was no ground for the
     respondent to cancel the tender by taking recourse to its executive
     powers in complete ignorance of the contractual terms that were
     agreed upon by them.
122. From the above discussion, we are of the considered opinion that
     the present lis is nothing but a classic textbook case of an arbitrary
     and capricious exercise of powers by the respondent to cancel the
     tender that was issued to the appellant on the basis of extraneous
     considerations and at the behest of none other but the concerned
     Minister-In-Charge.
       II.   Sanctity of Public-Private Partnership Tenders
123. Before we close this judgment, we must also address one very
     important aspect as regards the importance of maintaining the sanctity
     of tenders in public private procurement processes.
124. Public tenders are a cornerstone of governmental procurement
     processes, ensuring transparency, competition, and fairness in the
     allocation of public resources. It emanates from the Doctrine of Public
     Trust which lays down that all natural resources and public use
     amenities & structures are intended for the benefit and enjoyment of
     the public. The State is not the absolute owner of such resources and
     rather owns it in trust and as such it cannot utilize these resources
     as it pleases. As a trustee of the public resources, the State owes
     i) a duty to ensure that community resources are put to fair and
     proper use that enures to the benefit of the public as-well as ii) an
     obligation to not indulge in any favouritism or discrimination with
     these resources. The State with whatever free play it has in its joints
     decides to award a contract, to hold up the matter or to interfere
     with the same should be accompanied by a careful consideration
     of the harm to public interest.
[2024] 7 S.C.R.                                                            607

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


125. Public tenders are designed to provide a level playing field for all
     potential bidders, fostering an environment where competition thrives,
     and the best value is obtained for public funds. The integrity of this
     process ensures that public projects and services are delivered
     efficiently and effectively, benefiting society at large. The principles
     of transparency and fairness embedded in public tender processes
     also help to prevent corruption and misuse of public resources. In
     this regard we may refer to the observations made by this Court in
     Nagar Nigam v. Al. Farheem Meat Exporters Pvt. Ltd. reported
     in (2006) 13 SCC 382, which reads as under: -
           “16. The law is well settled that contracts by the State,
           its corporations, instrumentalities and agencies must be
           normally granted through public auction/public tender by
           inviting tenders from eligible persons and the notification of
           the public auction or inviting tenders should be advertised
           in well-known dailies having wide circulation in the locality
           with all relevant details such as date, time and place of
           auction, subject-matter of auction, technical specifications,
           estimated cost, earnest money deposit, etc. The award
           of government contracts through public auction/public
           tender is to ensure transparency in the public procurement,
           to maximise economy and efficiency in government
           procurement, to promote healthy competition among the
           tenderers, to provide for fair and equitable treatment of
           all tenderers, and to eliminate irregularities, interference
           and corrupt practices by the authorities concerned. This
           is required by Article 14 of the Constitution.”
                                                    (Emphasis supplied)
126. The sanctity of public tenders lies in their role in upholding the
     principles of equal opportunity and fairness. Once a contract has come
     into existence through a valid tendering process, its termination must
     adhere strictly to the terms of the contract, with the executive powers
     to be exercised only in exceptional cases by the public authorities and
     that too in loathe. The courts are duty bound to zealously protect the
     sanctity of any tender that has been duly conducted and concluded
     by ensuring that the larger public interest of upholding bindingness
     of contracts are not sidelined by a capricious or arbitrary exercise of
     power by the State. It is the duty of the courts to interfere in contractual
608                                                          [2024] 7 S.C.R.

                       Digital Supreme Court Reports


       matters that have fallen prey to an arbitrary action of the authorities
       in the guise of technical faults, policy change or public interest etc.
127. The sanctity of contracts is a fundamental principle that underpins
     the stability and predictability of legal and commercial relationships.
     When public authorities enter into contracts, they create legitimate
     expectations that the State will honour its obligations. Arbitrary or
     unreasonable terminations undermine these expectations and erode
     the trust of private players from the public procurement processes
     and tenders. Once a contract is entered, there is a legitimate
     expectation, that the obligations arising from the contract will be
     honoured and that the rights arising from it will not be arbitrarily
     divested except for a breach or non-compliance of the terms
     agreed thereunder. In this regard we may make a reference to
     the decision of this Court in Sivanandan C.T. v. High Court of
     Kerala reported in (2024) 3 SCC 799 wherein it was held that a
     promise made by a public authority will give rise to a legitimate
     expectation that it will adhere to its assurances. The relevant
     portion reads as under: -
            “18. The basis of the doctrine of legitimate expectation
            in public law is founded on the principles of fairness and
            non-arbitrariness in Government dealings with individuals.
            It recognises that a public authority’s promise or past
            conduct will give rise to a legitimate expectation. The
            doctrine is premised on the notion that public authorities,
            while performing their public duties, ought to honour
            their promises or past practices. The legitimacy of an
            expectation can be inferred if it is rooted in law, custom,
            or established procedure
                       xxx			xxx			xxx
            45. The underlying basis for the application of the doctrine
            of legitimate expectation has expanded and evolved to
            include the principles of good administration. Since citizens
            repose their trust in the State, the actions and policies of
            the State give rise to legitimate expectations that the State
            will adhere to its assurance or past practice by acting in
            a consistent, transparent, and predictable manner. The
            principles of good administration require that the decisions
            of public authorities must withstand the test of consistency,
[2024] 7 S.C.R.                                                          609

  Subodh Kumar Singh Rathour v. The Chief Executive Officer & Ors.


           transparency, and predictability to avoid being regarded as
           arbitrary and therefore violative of Article 14.”
                                                  (Emphasis supplied)
128. Cancellation of a contract deprives a person of his very valuable rights
     and is a very drastic step, often due to significant investments having
     already been made by the parties involved during the subsistence
     of the contract. Failure on the part of the courts to zealously protect
     the binding nature of a lawful and valid tender, would erode public
     faith in contracts and tenders. Arbitrary terminations of contract
     create uncertainty and unpredictability, thereby discouraging public
     participation in the tendering process. When private parties perceive
     that their contractual rights can be easily trampled by the State, they
     would be dissuaded from participating in public procurement processes
     which may have a negative impact on such other public-private
     partnership ventures and ultimately it is the public who would have
     to bear the brunt thereby frustrating the very object of public interest.
129. We caution the public authorities to be circumspect in disturbing or
     wriggling out of its contractual obligations through means beyond the
     terms of the contract in exercise of their executive powers. We do
     not say for a moment that the State has no power to alter or cancel
     a contract that it has entered into. However, if the State deems it
     necessary to alter or cancel a contract on the ground of public interest
     or change in policy then such considerations must be bona-fide and
     should be earnestly reflected in the decision-making process and also
     in the final decision itself. We say so because otherwise, it would have
     a very chilling effect as participating and winning a tender would tend
     to be viewed as a situation worse than losing one at the threshold.
     H.    FINAL CONCLUSION
130. We are of the considered opinion that the litigation at hand is nothing
     but a classic textbook case of an arbitrary exercise of powers by
     the respondent in cancelling the tender that was issued in favour
     of the appellant and that too at the behest of none other than the
     concerned Minister-In-Charge and thereby rendering the Notice of
     Cancellation dated 07.02.2023 illegal.
131. During the course of hearing, we were informed that the appellant
     herein pursuant to the terms of the subject tender had erected
     multiple structures at different sites on the concerned underpasses
610                                                       [2024] 7 S.C.R.

                          Digital Supreme Court Reports


       for displaying advertisements at a huge personal cost. He has made
       significant investments pursuant to the tender.
132. As, we have held the Notice of Cancellation dated 07.02.2023 to be
     non-est, the issuance of a fresh tender to any third-party in respect
     of the same work would not defeat the vested rights that accrued in
     favour of the appellant. Similarly, the handing over of the operation
     and maintenance of the E.M. Bypass to the KMC also would have no
     bearing whatsoever, on the rights that stood vested in the appellant
     as on the date of cancellation of the tender. Such vested rights would
     continue to operate notwithstanding any change in the control and
     maintenance of the underpasses.
133. The order dated 16.09.2023 passed by the Urban Development and
     Municipal Affairs Department, Government of West Bengal merely
     transferred the operation and maintenance of the underpasses
     including the right to receive revenue from KMDA to KMC and
     therefore will have no effect on any rights that accrued in favour
     of the appellant as such rights are independent of the authority in
     control of operations and maintenance.
134. Thus, for all the foregoing reasons, the appeal succeeds and is
     hereby allowed. The notice of cancellation dated 07.02.2023 is
     quashed and the impugned judgment and order passed by the High
     Court is hereby set aside.
135. Pending application(s), if any, also stand disposed of.

       Result of the case: Appeal allowed.



       †
           Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "contract/tender disputes"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

SUBODH KUMAR SINGH RATHOUR versus THE CHIEF EXECUTIVE OFFICER & ORS. — 2024 INSC 486 - Legal Desk AI