Created byFuzzy Cloud

Supreme Court of India

THE STATE OF HIMACHAL PRADESH & ANR.versusJSW HYDRO ENERGY LIMITED & ORS.

Citation
2025 INSC 857
Decided
16 July 2025
Disposal
Appeal(s) allowed

Holding

The CERC Regulations, 2019 do not prohibit the respondent from supplying free power beyond 13% and the Implementation Agreement is not overridden by those Regulations; consequently, the writ petition is not maintainable.

Summary

The Himachal Pradesh government entered into an Implementation Agreement with JSW Hydro Energy Ltd (formerly JIL) to supply 12% free power for the first 12 years and 18% thereafter from a 1045 MW hydro project. When the free‑power obligation rose above the 13% cap prescribed in CERC (Terms and Conditions of Tariff) Regulations, 2019, the generator sought a writ to modify the agreement to conform to the Regulations, which the High Court granted. The Supreme Court held that Note 3 of Regulation 55 merely limits the free‑power considered for tariff calculation and does not prohibit supplying more than 13% under the contract. Consequently, the contract remains enforceable and the High Court’s writ jurisdiction was improper because tariff matters lie exclusively with the CERC and the APTEL. The appeal was allowed, setting aside the High Court order and dismissing the writ petition.

Issues considered

  • The CERC Regulations, 2019, whether they bar the respondent from supplying free power beyond 13% to the State.
  • Whether a writ petition under Article 226 is maintainable to align a pre‑existing Implementation Agreement with the CERC Regulations, 2019.

Legislation cited

Headnote

Issue for Consideration The primary issues arising for consideration are: first, whether the CERC Regulations, 2019 bar respondent no. 1 from supplying free power to the appellant-State beyond 13%; and second, whether respondent no. 1 could have invoked the High for aligning the Implementation Agreement with the CERC Regulations, 2019. Headnotes† Electricity Act, 2003 – CERC (Terms and Conditions of Tariff) Regulations, 2019 – Regulations 44 and 55 – Note 3 of Regulation 55 – Respondent no.1, a generating company,

Subjects

Contractual obligationStatutory regulatorImplementation AgreementConsiderationFree energy for home StateWrit Jurisdiction of High CourtAligning the Implementation AgreementSupplying free power beyond 13%Interpreting cap under Note 3 of Regulation 55Calculation and fixation of tariffCERC as statutory regulator

Judgment

                 [2025] 7 S.C.R. 1104 : 2025 INSC 857

               The State of Himachal Pradesh & Anr.
                                v.
                JSW Hydro Energy Limited & Ors.
                      (Civil Appeal No. 12883 of 2024)
                                 16 July 2025
                [Pamidighantam Sri Narasimha* and
                      Joymalya Bagchi, JJ.]


                           Issue for Consideration
       The primary issues arising for consideration are: first, whether the
       CERC Regulations, 2019 bar respondent no. 1 from supplying
       free power to the appellant-State beyond 13%; and second,
       whether respondent no. 1 could have invoked the High Court’s
       writ jurisdiction for aligning the Implementation Agreement with
       the CERC Regulations, 2019.

                                  Headnotes†
       Electricity Act, 2003 – CERC (Terms and Conditions of
       Tariff) Regulations, 2019 – Regulations 44 and 55 – Note 3
       of Regulation 55 – Respondent no.1, a generating company,
       installed and commissioned a hydroelectric power project
       pursuant to a grant followed by an Implementation Agreement
       with the appellant-State of Himachal Pradesh – Under
       this agreement, respondent no. 1 undertook to supply as
       consideration 18% of net generation free of cost (free power
       supply of 12% of net generation for 12 years and 18% thereafter
       for next 28 years) to the appellant-State – At the commencement
       of the obligation to supply 18% free power, respondent no. 1
       approached the High Court by way of a writ petition to align
       the Implementation Agreement with the CERC (Terms and
       Conditions of Tariff) Regulations, 2019, which provide for a
       maximum of 13% free power to the State Government, on the
       ground that contractual agreements, to the extent that they
       are inconsistent with the applicable regulations, shall stand
       overridden by their operation – The High Court directed for
       modification of the Implementation Agreement – Correctness:
       Held: 1. The purpose and intendment of Note 3 of Regulation 55
       is for the State Commission to determine tariff by assuming that
* Author
[2025] 7 S.C.R.                                                               1105

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

     FEHS is 13%, whenever it is higher in actuality, while calculating
     the energy and capacity charges – Neither the language of Note
     3 nor the context in which it appears in the CERC Regulations,
     2019 supports respondent no. 1’s contention that the legal effect of
     this cap is to override its contractual obligations with the appellant-
     State – On the other hand, use of the term “shall be taken as 13%
     or actual, whichever is less” shows that the Regulations cover a
     situation where the obligation to supply free power is higher than
     13%, and in such an eventuality, allow only a certain portion of free
     supply to be considered for tariff determination and payments by
     beneficiaries for the saleable capacity – Once the Regulation does
     not prohibit the supply of free power beyond 13%, respondent no. 1
     cannot rely on it to wriggle out of its contractual obligations – The
     Regulatory Commissions, APTEL, and the Courts must enforce
     these contractual obligations and ensure that their interpretation
     of regulations does not allow the party to circumvent and breach
     its contractual undertakings when the same is not intended by the
     regulation itself. [Paras 19, 20]
     2. This Court holds that CERC Regulations, 2019 do not prohibit
     respondent no. 1 from supplying free power beyond 13% to the
     appellant-State, and the Implementation Agreement does not stand
     overridden by the operation of these Regulations – Further, a writ
     petition before the High Court for aligning the Implementation
     Agreement with the CERC Regulations, 2019 and the CERC’s order
     dated 17.03.2022 is not maintainable – Once respondent no.1’s
     prayer for relief was rejected by the CERC and it specifically held
     only the PPA and PSAs to stand overridden, which finding was
     not further appealed, it would not be open for respondent no. 1
     to seek modification of the Implementation Agreement by way of
     a writ petition before the High Court. [Para 40]

     Electricity Act, 2003 – Writ Jurisdiction of High Court –
     Whether the writ petition before the High Court for aligning
     the Implementation Agreement with the CERC Regulations,
     2019 and the CERC’s order dated 17.03.2022 is maintainable:
     Held: Under the Electricity Act, the statutory regulator has been
     entrusted with discharging the function of tariff determination,
     including making regulations for the purpose and interpreting
     the same – Constitutional courts must enable the regulator to
     comprehensively regulate all aspects of the sector such that
     remedies are not fragmented and certain issues are not left
1106                                                           [2025] 7 S.C.R.

                         Supreme Court Reports


    outside the regulator’s domain – The regulator has the expertise,
    specialisation, and institutional memory to conduct such an
    interpretative exercise to further the objective of the regulatory
    regime and systematically lay down legal principles – In this light, the
    High Court should not have entered into the domain of interpreting
    these Regulations which deal with tariff determination, as the same
    falls within the exclusive domain of the CERC – The Electricity
    Act itself provides the appellate mechanisms by establishing a
    specialised and permanent tribunal, namely the APTEL, and an
    appeal before this Court, against the CERC’s orders – In view
    of the existence of a statutory regulatory forum, the High Court
    should not have entertained the writ petition by interpreting the
    CERC Regulations, 2019 – Therefore, a writ petition before the
    High Court for aligning the Implementation Agreement with the
    CERC Regulations, 2019 and the CERC’s order dated 17.03.2022
    is not maintainable. [Paras 38, 40]

    Electricity Act, 2003 – A complete and comprehensive code:
    Held: The Electricity Act, 2003 is a complete and comprehensive
    code for regulating the generation, transmission, distribution, trading
    and use of electricity – One of the core features of the Act is that
    it unbundles the functions of electricity generation, transmission,
    and distribution that were erstwhile performed by State Electricity
    Boards into separate utilities, and provides for their regulation
    through independent Regulatory Commissions. [Para 7]

    Electricity Act, 2003 – Electricity Regulatory Commissions Act,
    1998 – Need for an independent and transparent regulatory
    mechanism:
    Held: The need for an independent and transparent regulatory
    mechanism was felt due to the regulatory failures under the erstwhile
    legal regime, wherein SEBs constituted by the State Governments
    were entrusted with regulation – It was experienced that various
    problems plagued the power sector, including lack of rational retail
    tariffs, high level of cross-subsidies, poor planning and operation,
    inadequate capacity, neglect of consumer interest, and limited
    involvement of the private sector’s skills and resources – It is in this
    context that the Electricity Regulatory Commissions Act, 1998 was
    enacted to reform the governance of the sector by establishing an
    independent and transparent regulatory mechanism – Thereafter,
    the Electricity Act, 2003 was enacted as a comprehensive legislation
[2025] 7 S.C.R.                                                            1107

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

     for regulating the sector and it replaced the Electricity Act, 1910,
     Electricity Supply Act, 1948 and the 1998 Act [Para 8]
     Electricity Act, 2003 – Regulation of Electricity Generation
     Under the Electricity Act – Discussed. [Paras 11 to 14]
     Electricity Act, 2003 – CERC Regulations, 2019 – Interpretation
     of – Discussed. [Para 15]

                               Case Law Cited
     PTC India Ltd. v. Central Electricity Regulatory Commission [2010]
     3 SCR 609 : (2010) 4 SCC 603; Transmission Corporation of A.P.
     Ltd. v. Rain Calcining Ltd. [2019] 17 SCR 474 : (2021) 13 SCC
     674; Ganga Retreat and Towers Ltd. v. State of Rajasthan [2003]
     Supp. 6 SCR 1134 : (2003) 12 SCC 91; K.C. Ninan v. Kerala State
     Electricity Board [2023] 9 SCR 637 : (2023) 14 SCC 431; W.B.
     Electricity Regulatory Commission v. CESC Ltd. (2002) 8 SCC
     715; Sesa Sterlite Ltd. v. Orissa Electricity Regulatory Commission
     [2014] 13 SCR 426 : (2014) 8 SCC 444; Dilip v. Satish, 2022 SCC
     OnLine SC 810; Chameli Singh v. State of U.P. [1995] Supp. 6 SCR
     827 : (1996) 2 SCC 549; Tata Power Co. Ltd. v. Reliance Energy
     Ltd. [2009] 9 SCR 625 : (2009) 16 SCC 659; Indsil Hydro Power
     & Manganese Ltd. v. State of Kerala [2021] 13 SCR 136 : (2021)
     10 SCC 165; Reliance Infrastructure Ltd. v. State of Maharashtra
     [2019] 1 SCR 886 : (2019) 3 SCC 352; Cellular Operators Assn. of
     India v. Union of India [2002] Supp. 5 SCR 222 : (2003) 3 SCC 186;
     U.P. Power Corpn. Ltd. v. NTPC Ltd. [2009] 3 SCR 1060 : (2009) 6
     SCC 235; BSES Ltd. v. Tata Power Co. Ltd. [2003] Supp. 4 SCR
     932 : (2004) 1 SCC 195; Maharashtra State Electricity Distribution
     Co. Ltd. v. Adani Power Maharashtra Ltd. [2023] 7 SCR 648 :
     (2023) 7 SCC 401; Jaipur Vidyut Vitran Nigam Ltd. v. MB Power
     (M.P.) Ltd. [2024] 1 SCR 909 : (2024) 8 SCC 513 – referred to.

                         Books and Periodicals Cited
     H.W.R. Wade and C.F. Forsyth, Administrative Law (11th edn,
     Oxford University Press 2014), 116-117 – referred to.

                                 List of Acts
     Electricity Act, 2003; Electricity Regulatory Commissions Act,
     1998; Electricity Act, 1910; Electricity (Supply) Act, 1948; CERC
     Regulations, 2019; CERC (Terms and Conditions of Tariff)
     Regulations, 2014.
1108                                                                                      [2025] 7 S.C.R.

                                     Supreme Court Reports


                                          List of Keywords
       Contractual obligation; Statutory regulator; Implementation
       Agreement; Consideration; Free energy for home State; Writ
       Jurisdiction of High Court; Aligning the Implementation Agreement;
       Supplying free power beyond 13%; Interpreting cap under Note 3
       of Regulation 55; Calculation and fixation of tariff; CERC as
       statutory regulator.

                                         Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal No. 12883 of 2024
       From the Judgment and Order dated 28.05.2024 of the High Court
       of Himachal Pradesh at Shimla in CWP No. 7667 of 2023

                                    Appearances for Parties

       Advs. for the Appellants:
       Vaibhav Srivastava, A.A.G., Kapil Sibal, Parag Tripathi, Anup
       Rattan, Sr. Advs., Ms. Sugandha Anand, Bhargava Ravikumar,
       Puneet Rajta, Ms. Mishika Bajpai.
       Advs. for the Respondents:
       P. Chidambaram, Dr. A.M. Singhvi, Gurminder Singh, Nikhil Nayyar,
       Sr. Advs., Mahesh Agarawal, Aman Anand, Shashwat Singh, Ms.
       Madhavi Agarwal, Chirag Nayak, Ms. Natasha Debroy, Shidharth
       Seem, E. C. Agrawala, Anand K Ganesan, Amal Nair, Shivani
       Verma, Nitin Saluja, Ms. Preetika Dwivedi, Abhisek Mohanty, Nikunj
       Dayal, Jatinder Singh Gill, T. V. S. Raghavendra Sreyas, Siddharth
       Vasudev, Brahma Prakash Soni, Kshitij Maheshwari.

                       Judgment / Order of the Supreme Court

                                                Judgment

       Pamidighantam Sri Narasimha, J.

                                        Table of Contents*

       I.      Introduction ............................................................................       2
       II.     Facts .......................................................................................   4


* Ed. Note: Pagination as per the original Judgment.
[2025] 7 S.C.R.                                                                                        1109

                       The State of Himachal Pradesh & Anr. v.
                         JSW Hydro Energy Limited & Ors.


      III.    Impugned Order .....................................................................          14
      IV.     Submissions ...........................................................................       16
      V.      Issue ....................................................................................... 29
      VI.     Analysis ..................................................................................   29
      VII. Regulation of Electricity Generation Under the Electricity Act ...                               33
      VIII. Legal Effect of Note 3 of Regulation ...................................... 36
              i)    Interpretation of the CERC Regulations, 2019 ................ 36
              ii)   CERC’s Order dated 17.03.2022 ..................................... 41
      IX.     Maintainability of the Writ Petition .......................................... 44
              i)    CERC as an Expert and Specialised Regulator, and Extent 44
                    of Judicial Interference .....................................................
              ii)   Grant of Relief by the High Court ...................................                   50
      X.      Conclusion .............................................................................. 53




      I.      Introduction:
1.    Respondent no. 1, a generating company, installed and commissioned
      a 1045MW hydroelectric power project pursuant to a grant followed
      by an Implementation Agreement with the appellant-State of Himachal
      Pradesh. Under this Agreement, respondent no. 1 undertook to
      supply as consideration 18% of net generation free of cost1 to the
      appellant-State. At the commencement of the obligation to supply
      18% free power, respondent no. 1 approached the High Court by
      way of a writ petition to align the Implementation Agreement with the
      CERC (Terms and Conditions of Tariff) Regulations, 20192, which
      provide for a maximum of 13% free power to the State Government,
      on the ground that contractual agreements, to the extent that they are
      inconsistent with the applicable regulations, shall stand overridden by
      their operation. Accepting the argument, the High Court entertained


1    The obligation to supply free power is 12% of net generation from 12.09.2011 to 12.09.2023, and 18%
     thereafter till 12.09.2051.
2    Hereinafter “CERC Regulations, 2019”.
1110                                                            [2025] 7 S.C.R.

                                      Supreme Court Reports


        the writ petition and directed that the Implementation Agreement
        stood modified.
2.      We have allowed the appeal by the State of Himachal Pradesh by
        interpreting the provisions of the Electricity Act, 20033 and the CERC
        Regulations, 2019 in the context of the subsisting and continuing
        contractual relationship between the parties. We have held that
        the Central Electricity Regulatory Commission4 shall give effect to
        the Regulations and provide a pass-through to the extent of 13%
        free power but the remaining part of the obligation is contractual in
        nature and will be governed by the provisions of the Implementation
        Agreement. On interpreting the cap under Note 3 of Regulation 55 of
        the CERC Regulations, 2019, we have held that it does not restrain
        or prohibit respondent no. 1 from supplying free power beyond 13%
        but it is only meant for the calculation and fixation of tariff. Further,
        considering the expertise and specialisation of the CERC as a
        statutory regulator and the wide-ranging jurisdiction it exercises
        under the Electricity Act, as well as respondent no. 1’s conduct in
        not seeking relief against the appellant before the CERC, we have
        held that the present writ petition was not maintainable before the
        High Court as the interpretation of the Regulations falls within the
        exclusive domain of the regulator.

        II.    Facts:
3.      The facts, to the extent necessary are as follows. By a Memorandum
        of Understanding5 dated 28.08.1993, the appellant-State allotted the
        Karcham Wangtoo Hydroelectric Project for an installed capacity of
        900 MW to one Jaiprakash Industries Limited6, which is a power
        generating company and the predecessor of respondent no. 1.
        Under Clause 6 of the MoU, JIL agreed to supply 12% of the power
        generated to the appellant-State free of cost.
        3.1 Pursuant to the MoU, the appellant entered into an Implementation
            Agreement with JIL for an enhanced capacity of 1000 MW. The
            relevant clauses of the Implementation Agreement are as follows:


3    Hereinafter “Electricity Act”.
4    Hereinafter “CERC”.
5    Hereinafter “MoU”.
6    Hereinafter “JIL”.
[2025] 7 S.C.R.                                                             1111

                     The State of Himachal Pradesh & Anr. v.
                       JSW Hydro Energy Limited & Ors.

             i.     Article 1.2 is the definitions clause that defines “Law” as
                    any Act, rule, regulation, notification, order, or instruction
                    having the force of Law enacted or issued by any competent
                    legislature, government, or statutory authority in India.
             ii.    Further, the Effective Date of the Agreement is defined
                    as the date of signing, and the Scheduled Commercial
                    Operation Date 7 is defined as 120 months from the
                    Effective Date.
             iii.   Article 3.2 stipulates that the Implementation Agreement
                    shall remain in force for a period of 40 years from the
                    Commercial Operation Date8 of the Project (Agreement
                    Period), unless terminated earlier as per its provisions.
                    It reads:
                          “3.2 Agreement Period
                          a) This Agreement shall remain in force up to a
                          period of forty (40) years from the Commercial
                          Operation Date of the Project (Agreement
                          Period), unless terminated earlier in accordance
                          with the provisions of the Agreement.”
             iv.    Article 4 delineates the obligations of the appellant-State
                    under the Agreement, which include the grant of various
                    consents and permissions to JIL to establish, operate,
                    and maintain the Project; to acquire land and prepare a
                    rehabilitation and resettlement plan for local residents;
                    to enter into leases for government land required for the
                    works; to upgrade roads and bridges for the Project; and to
                    provide necessary assistance to JIL as per the Agreement.
             v.     Article 5 deals with the obligations of JIL, of which the
                    most relevant is the supply of power to the appellant-State
                    without any cost or charges under Article 5.1. Sub-clause
                    (a) stipulates the quantum of such supply as 12% of the
                    net generation for the first 12 years from the COD, and
                    18% of the net generation for the next 28 years. Further,



7   Hereinafter “SCOD”.
8   Hereinafter “COD”.
1112                                                             [2025] 7 S.C.R.

                             Supreme Court Reports


                     sub-clause (b) stipulates that JIL shall ensure that any
                     Power Purchase Agreement9 entered into by it shall not be
                     detrimental to the rights of the appellant-State envisaged
                     in this clause. It reads:
                          “5.1 Government Supply
                          (a) The Company shall supply to the Government
                          or its Agent, during the Agreement Period, at
                          the Interconnection Point without any cost or
                          charges to the Government, the quantum of
                          electrical energy generated as specified below
                          (Government Supply):

                          i) Commencing from the date          Twelve (12)
                          of synchronisation of the first      percent of Net
                          Unit and for the first twelve        Generation
                          (12) years from Commercial
                          Operation Date (COD)
                          ii) For the next twenty eight (28)   Eighteen (18)
                          years after expiry of the period     percent of Net
                          specified in (i) above.              Generation

                          This quantum of Government Supply is
                          applicable in case the Project achieves
                          Commercial operation on Scheduled Commercial
                          Operation Date. In the event of early or delayed
                          commissioning of the Project, the same shall
                          be as per provision specified in Clause 5.19
                          and 5.20 respectively.
                          In case the Government levies any duty/tax
                          on generation and supply of power, the same
                          shall be borne by the Government in respect
                          of Government Supply. Further modalities for
                          providing the Government Supply shall be
                          mutually agreed between the Company and
                          the Board.



9   Hereinafter “PPA”.
[2025] 7 S.C.R.                                                              1113

                      The State of Himachal Pradesh & Anr. v.
                        JSW Hydro Energy Limited & Ors.

                            (b) The Company shall ensure that any Power
                            Purchase Agreement entered into by it shall not
                            be detrimental to the rights of the Government
                            envisaged in this Clause.”
              vi.    Article 9 provides that the rights and obligations under
                     or pursuant to the Agreement shall be governed by and
                     construed according to Law.
              vii.   Article 10 provides for dispute resolution through mutual
                     discussions, and in case of failure of the same, arbitration.
      3.2 By an addendum to the Implementation Agreement dated
          24.05.2001, the time-period for commencing construction was
          extended from 36 to 48 months from the Effective Date, but
          the COD was unamended.
      3.3 Subsequently, by a tripartite agreement dated 30.12.2002
          between the appellant, JIL, and one Jaypee Karcham Hydro
          Corporation Limited10 that was incorporated by JIL as per
          Clause 8 of the MoU, the rights and liabilities of the Project
          were transferred from JIL to JKHCL.
      3.4 JKHCL entered into a PPA dated 21.03.2006 with respondent
          no. 4, i.e., PTC India Limited, which is an inter-state trading
          licensee, for sale of 704 MW of power. PTC then entered into
          Power Sale Agreements11 with respondent nos. 5 to 10, which are
          distribution companies in the States of Punjab, Haryana, Uttar
          Pradesh and Rajasthan, to sell the power which it purchased
          from JKHCL. In the PPA as well as the PSAs, “free power” is
          defined in the same manner as Article 5.1 of the Implementation
          Agreement.
      3.5 The appellant and JKHCL entered into a Second Supplementary
          Implementation Agreement on 20.12.2007 to extend the SCOD
          to 144 months from the Effective Date, i.e. 18.11.2011.
      3.6 The Project achieved commercial operation on 12.09.2011,
          i.e., within the extended SCOD. It is relevant to note that
          this is the date from which JKHCL’s obligation to supply free


10   Hereinafter “JKHCL”.
11   Hereinafter “PSAs”.
1114                                                            [2025] 7 S.C.R.

                            Supreme Court Reports


              power to the appellant-State commenced as per Article 5.1
              of the Implementation Agreement. For the first 12 years from
              12.09.2011, the quantum of free power to be supplied is 12%,
              and 18% thereafter for the next 28 years.
        3.7    By a tripartite agreement dated 29.08.2015, the rights and
               liabilities in the Project were transferred from JKHCL to
               Himachal Baspa Power Company Limited12, which is the
               predecessor of respondent no. 1, with effect from 01.09.2015.
               As per clause 3 of this agreement, HBPCL agreed to be bound
               by and liable for the contractual undertakings as specified
               in the Implementation Agreement, Addendum, tripartite
               agreement dated 30.12.2002, and the Second Supplementary
               Implementation Agreement.
        3.8    In 2018, HBPCL changed its name to JSW Hydro Energy
               Limited, which is the present respondent no. 1 company.
               The parties signed the Third Supplementary Implementation
               Agreement dated 21.10.2019 for effecting the change in name
               while also agreeing that the other contractual undertakings
               would remain unamended.
        3.9    During this time, the CERC (Terms and Conditions of Tariff)
               Regulations, 2014 governed the field with respect to tariff
               determination of generating stations, including the specific
               provision with respect to free power supply under Note 3 of
               Regulation 42. This provided that “FEHS = Free energy for
               home State, in percent and shall be taken as 13% or actual
               whichever is less.” Respondent no. 1 sought for relaxation of
               this cap in its tariff petition for the 2014-2019 period. This was
               decided by the CERC’s order dated 30.03.2017, wherein it
               did not consider this issue as the free power supply obligation
               during this period was only 12%, which is below the 13%
               cap prescribed in the CERC Regulations, 2014. However,
               respondent no. 1 was given liberty to claim this relief at an
               appropriate time.
        3.10 In 2019, the CERC framed the CERC Regulations, 2019
             determining tariffs for generating stations and transmission


12   Hereinafter “HBPCL”.
[2025] 7 S.C.R.                                                            1115

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

            units from 01.04.2019 to 31.03.2024. At this stage, it is
            relevant to refer to Note 3 of Regulation 55 that provides that
            free energy to home State (FEHS) shall be taken as 13% or
            actual, whichever is lesser. Further, Regulation 44 deals with
            the computation and payment of capacity and energy charges
            for generating station, and Regulation 55(2) provides for billing
            and payments. The relevant portions of these provisions are
            extracted hereinbelow:
                Regulation 44:
                “44. Computation and Payment of Capacity Charge
                and Energy Charge for Hydro Generating Stations:
                (1) The fixed cost of a hydro generating station shall be
                computed on annual basis, based on norms specified
                under these regulations, and shall be recovered on
                monthly basis under capacity charge (inclusive of
                incentive) and energy charge, which shall be payable
                by the beneficiaries in proportion to their respective
                allocation in the saleable capacity of the generating
                station, i.e., in the capacity excluding the free power
                to the home State:…
                ***
                (4) The energy charge shall be payable by every
                beneficiary for the total energy scheduled to be
                supplied to the beneficiary, excluding free energy,
                if any, during the calendar month, on ex-bus basis,
                at the computed energy charge rate. Total energy
                charge payable to the generating company for a
                month shall be:
                Energy Charges = (Energy charge rate in Rs. / kWh) x
                {Scheduled energy (ex-bus) for the month in kWh} x
                (100 – FEHS) / 100
                (5) Energy charge rate (ECR) in Rupees per kWh on
                ex-power plant basis, for a hydro generating station,
                shall be determined up to three decimal places based
                on the following formula, subject to the provisions of
                clause (7) of this Regulation:
1116                                                           [2025] 7 S.C.R.

                            Supreme Court Reports


                   ECR = AFC X 0.5 x 10 / {DE x (100 – AUX) x (100 –
                   FEHS)}
                   Where,
                   DE = Annual design energy specified for the hydro
                   generating station, in MWh, subject to the provision
                   in clause (6) below.
                   FEHS = Free energy for home State, in per cent, as
                   mentioned in Note 3 under Regulation 55 of these
                   regulations…”
                   Regulation 55:
                   “55. Billing and Payment of charges:
                   ***
                   (2) … Payment of capacity charge and energy charge
                   for a hydro generating station shall be shared by the
                   beneficiaries of the generating station in proportion
                   to their shares (inclusive of any allocation out of
                   the unallocated capacity) in the saleable capacity
                   (to be determined after deducting the capacity
                   corresponding to free energy to home State as per
                   Note 3 herein.
                   ***
                   Note 3 FEHS= Free energy for home State, in percent
                   and shall be taken as 13% or actual whichever is
                   less…”
        3.11 In 2019, respondent no. 1 filed a petition before the CERC for
             approval of its tariff between 2019-2024, as well as truing up
             the tariff for 2014-2019 period. In the tariff petition, respondent
             no. 1 inter alia prayed for relaxation of the 13% cap on free
             power under Note 3 of Regulation 55 of the 2019 Regulations,
             since its free power obligation under the Implementation
             Agreement is 18% of net generation after the completion of
             12 years from COD.
        3.12 This was decided by the CERC’s order dated 17.03.2022
             wherein it rejected the prayer for relaxation of the 13% cap on
             free power supply. The CERC held that it was bound by the
[2025] 7 S.C.R.                                                        1117

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

            CERC Regulations, 2019 while determining the tariff and that
            the regulations will override inconsistent contractual provisions
            in the PPA and PSAs executed by respondent no. 1 in respect
            of free power to the appellant-State. We will be dealing with
            the findings of the CERC in more detail in our analysis.
     3.13 In the meanwhile, the Central Electricity Authority approved an
          increase in the Project capacity from 1000MW to 1091MW in
          two stages by a letter dated 29.04.2021. Pursuant to this, the
          capacity of the Project was enhanced to 1045 MW by the Fourth
          Supplementary Implementation Agreement dated 08.07.2021.
          It was further agreed that respondent no. 1 would be required
          to supply an additional 3% free power to the appellant-State
          on the enhanced 45MW capacity.
     3.14 In 2022, the present dispute arose between the parties as
          respondent no. 1 issued various letters to the appellant that
          Note 3 of Regulation 55 of the CERC Regulations, 2019 caps
          the free power supplied to the State at 13%. Further, that
          the CERC’s order dated 17.03.2022 requires inconsistent
          contractual provisions to be aligned with the Regulations.
          Relying on these, respondent no. 1 requested the appellant
          to align the Implementation Agreement with the CERC
          Regulations, 2019 and the order dated 17.03.2022 such that its
          free power supply obligation is confined to 13%. On the other
          hand, the appellant-State replied that the quantum of free power
          must be determined as per the Implementation Agreement
          and the Supplementary Implementation Agreements, which
          comes to 18.46% commencing from 13.09.2023. The appellant
          also issued a notice to respondent no. 1 dated 13.09.2023 to
          adhere to the contractual terms, failing which consequential
          action would be initiated against it. It also issued a notice dated
          16.09.2023 to the Northern Regional Load Dispatch Centre to
          schedule 18.46% free power to the appellant.
     3.15 This led respondent no. 1 to file the present writ petition before
          the High Court to direct the appellant to align the provisions
          of the Implementation Agreement and Supplementary
          Implementation Agreements on free power with the CERC
          Regulations, 2019 and the CERC’s order dated 17.03.2022,
          as well as to quash the notices issued by the appellant.
1118                                                           [2025] 7 S.C.R.

                            Supreme Court Reports


        III.   Impugned Order:
4.      By the order 28.05.2024, which is impugned before us, the High
        Court allowed the writ petition and directed the appellant to align
        the Implementation Agreement and Supplementary Implementation
        Agreements in respect of the quantum of free power with the
        provisions of the CERC Regulations, 2019 till they remain in force.
        Further, it directed that if respondent no. 1 supplied any free power
        above the maximum ceiling limit under the Regulations, the same
        shall be adjusted. For arriving at this conclusion, the High Court
        adopted the following reasoning:
        4.1 First, it held that the writ petition is maintainable inspite of the
            arbitration clause in Article 10.1 of the Implementation Agreement
            as the issues of whether the CERC Regulations, 2019 will
            override the Implementation Agreement and whether the
            contractual provisions need to be aligned pertain to enforcement
            of statutory regulations. Hence, the arbitration clause does not
            stand in the way of invoking writ jurisdiction.
        4.2 The High Court then took note of various provisions of the
            Electricity Act, the CERC Regulations, 2019, and the CERC’s
            order dated 17.03.2022 and rejected the appellant’s argument
            that these do not affect the obligations under the Implementation
            Agreement and held that the CERC’s order has a direct bearing
            on the supply of free power by respondent no. 1 to the appellant.
            Noting that the appellant-State was a party before the CERC
            and did not contest respondent no. 1’s prayer for relaxing the
            cap on free power, the Court held that such cap is not only to
            determine the tariff but is relevant for every other incidental
            and connected purpose.
        4.3 While the CERC in its order dated 17.03.2022 held that
            inconsistent provisions in the PPA and PSAs stand overridden
            by the Regulations, the High Court observed that these
            provisions are the same as in the Implementation Agreement
            and Supplementary Implementation Agreements. In a composite
            scheme for generation and sale of electricity, it held that there
            cannot be any mismatch in respect of the quantum of supply
            of free electricity. Hence, the corollary of the CERC’s order that
            the PPA and PSAs stand overridden is that the Implementation
            Agreement becomes unworkable and must be aligned with the
            CERC Regulations, 2019.
[2025] 7 S.C.R.                                                        1119

                     The State of Himachal Pradesh & Anr. v.
                       JSW Hydro Energy Limited & Ors.

      4.4 Further, since the appellant-State accepted the CERC’s order,
          respondent no. 1 was within its right to seek alignment of the
          Implementation Agreement with the CERC Regulations, 2019
          and the CERC’s order.
      4.5 The High Court also relied on this Court’s decision in PTC India
          Ltd. v. Central Electricity Regulatory Commission13 where it
          was held that statutory regulations under the Electricity Act will
          override existing contracts between regulated entities. On this
          basis, the High Court concluded that the CERC Regulations,
          2019 will have supremacy over contractual undertakings and
          the provisions of the Implementation Agreement must be aligned
          accordingly.

      IV.    Submissions:
5.    We have heard Mr. Kapil Sibal and Mr. Parag Tripathi, learned
      senior counsel for the appellant, and Mr. P. Chidambaram and
      Dr. A.M. Singhvi, learned senior counsel for respondent nos. 1
      and 2. We also heard Mr. Nikhil Nayyar, learned senior counsel for
      respondent no. 11 (CERC), Ms. Preetika Dwivedi, learned counsel
      for respondent nos. 7-9 (distribution companies operating in the State
      of Rajasthan), and Mr. Gurminder Singh, learned senior counsel for
      respondent no. 10 (distribution company operating in the State of
      Punjab). Their submissions can be recapitulated as follows:
      5.1 Mr. Tripathi and Mr. Sibal appearing for the appellant-State
          have broadly submitted that the quantum of free power to be
          supplied under the Implementation Agreement is not regulated
          or curtailed by the CERC Regulations, 2019 or the CERC’s
          order dated 17.03.2022. While taking us through the sequence
          of events, the following submissions have been made:
             i.     Regulation 2 provides the scope and extent of application
                    of the CERC Regulations, 2019, which is to determine the
                    tariff for generating and transmission companies.
             ii.    The purport of Note 3 of Regulation 55, which stipulates
                    the 13% cap on free power, is for calculating the bill
                    amount that the generating company can recover from


13   (2010) 4 SCC 603.
1120                                                             [2025] 7 S.C.R.

                              Supreme Court Reports


                     beneficiaries. It does not prohibit respondent no. 1 from
                     supplying free power beyond this cap. The effect of the
                     cap is that the CERC Regulations, 2019 provide a pass-
                     through to the extent of 13% free power while determining
                     the tariff. Any further supply of free power must be borne
                     by the generating companies from their resources.
              iii.   Further, that the Regulations govern agreements between
                     the generation and distribution companies but do not
                     extend to the Implementation Agreement, which was
                     executed even prior to the commencement of generation.
                     In the written submissions, it is further submitted that
                     the Implementation Agreement is a contract for natural
                     resources, and not a tariff agreement. It hence falls outside
                     the ambit of the CERC Regulations, 2019.
              iv.    In this vein, the learned senior counsel have also
                     referred us to the relevant portions of the CERC’s order
                     dated 17.03.2022 wherein respondent no. 1 prayed for
                     relaxation of the 13% cap while calculating tariff in view
                     of its contractual obligations under the Implementation
                     Agreement. This was rejected by the CERC and it held
                     that the PPA and PSAs executed by respondent no. 1
                     are overridden by the Regulations. The learned senior
                     counsel submit that respondent no. 1 did not appeal this
                     order before the Appellate Tribunal for Electricity14 and
                     instead filed a writ petition in 2023 seeking amendment
                     of the Implementation Agreement.
              v.     Coming to the impugned order of the High Court, they
                     submit that the High Court has proceeded on the basis
                     that the appellant-State is a regulated entity under the
                     Electricity Act, and thereby relied on PTC (supra) where this
                     Court held that contracts between regulated entities stand
                     overridden by statutory regulations under the Electricity
                     Act. They submitted that this is incorrect as the State
                     Government is not a deemed licensee under the third
                     proviso of Section 14 as it is not engaging in transmission,
                     distribution, or trading of electricity.


14   Hereinafter “APTEL”.
[2025] 7 S.C.R.                                                        1121

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

           vi.    They also submitted that contractual terms could not have
                  been amended in exercise of writ jurisdiction, and the only
                  remedy available to respondent no. 1 was to challenge
                  the validity of the Regulation itself, which it had not
                  done. Regarding the exercise of writ jurisdiction to align
                  the contractual terms with the Regulations, it is further
                  contended in the written submissions that the High Court
                  has rewritten the Implementation Agreement by relying on
                  the PPA and PSAs being overridden as per the CERC’s
                  order dated 17.03.2022. However, the High Court ignored
                  that these agreements are not on the same footing and
                  Article 5.1(b) of the Implementation Agreement provides
                  that it shall not be affected by the PPA.
           vii.   In the written submissions, the appellant submitted that
                  the quantum of free power was arrived after a series of
                  negotiations with JIL, which was awarded the Project
                  through the MoU route rather than through competitive
                  bidding. In order to avoid competitive bidding, JIL agreed
                  to supply 18% free power during a certain portion of the
                  Agreement period.
           viii. The learned senior counsel further submitted that despite
                 a similar cap on free power in the Hydroelectric Policy,
                 1998 @ 12%, respondent no. 1 knowingly agreed to
                 supply 18% free power in the Implementation Agreement
                 that was executed in 1999. Further, this obligation has
                 been reiterated in all the Supplementary Agreements.
                 Moreover, the Fourth Supplementary Implementation
                 Agreement was executed in 2021 for additional free
                 power on the enhanced capacity, which was executed
                 after the CERC Regulations, 2019 came into force.
                 Hence, once respondent no. 1 consented to supplying
                 free power @ 18% despite a similar cap existing all
                 through, the same cannot be avoided by filing a writ
                 petition.
     5.2 Mr. Chidambaram, learned senior counsel for respondent
         no. 1 submitted that the Implementation Agreement, which
         was negotiated prior to the CERC Regulations, 2019 stands
         overridden by the Regulations.
1122                                                                              [2025] 7 S.C.R.

                                  Supreme Court Reports


              i.      Referring to Article 9 of the Implementation Agreement,
                      he submitted that the rights and obligations under the
                      Agreement are subject to “Law”, which has been widely
                      defined as including regulations. The regulations in this
                      case are framed under the Electricity Act, which was
                      enacted in 2003, after the Implementation Agreement
                      was executed. Prior to this, there was no law restricting
                      the quantum of free power at the time of execution of the
                      Implementation Agreement.
              ii.     The State Government is a regulated entity under the
                      Electricity Act as it is a deemed licensee as per the
                      third proviso of Section 14. He referred us to certain
                      portions of the writ petition before the High Court, where
                      respondent no. 1 contended that the appellant-State is a
                      deemed licensee and the same was not denied by the
                      appellant in its reply. He also referred to Section 10(2) of
                      the Electricity Act to submit that generating companies
                      can supply electricity to licensees only. On this basis, he
                      submitted that respondent no. 1 is supplying electricity
                      to the appellant-State as a licensee, albeit free of cost.
              iii.    Relying on the decisions of this Court in PTC (supra) as well
                      as Transmission Corporation of A.P. Ltd. v. Rain Calcining
                      Ltd.15, he submitted that even concluded contracts between
                      regulated entities are overridden by regulations. Since
                      the State Government is a licensee, the Implementation
                      Agreement stands overridden by the Regulations. Further,
                      he submitted that performance of a contract must be in
                      conformity with the law in force at the time.16
              iv.     He then referred us to Regulation 30 of the CERC
                      Regulations, 2019 that provides for Return on Equity17 to
                      hydro-electric generating companies @ 16.5%, which the
                      generating company earns through tariff on saleable power.
                      The tariff is calculated by considering the free power cap
                      @ 13% as per Note 3 of Regulation 55. However, if the


15   (2021) 13 SCC 674.
16   Relied on Ganga Retreat and Towers Ltd. v. State of Rajasthan, (2003) 12 SCC 91.
17   Hereinafter “RoE”.
[2025] 7 S.C.R.                                                           1123

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

                  actual free power supply is 18% as per the Agreement,
                  this will negatively impact the RoE. Further, to ensure that
                  RoE is maintained, respondent no. 1 will be required to
                  sell the remaining 82% of power at a higher rate to PTC
                  and the distribution companies, which will ultimately be
                  passed on to the consumers thereby affecting consumer
                  interest. In the written submissions, respondent no. 1
                  also contended that the cost of generation and supply of
                  electricity must be recovered through tariff as per Section
                  61 of the Electricity Act. However, if it is required to supply
                  18% free power despite the 13% cap in the Regulations, it
                  will not recover revenue for 5% of the power it generates
                  and supplies, and this will negatively impact its RoE.
     5.3 Dr. Singhvi supplemented these submissions with the following
         arguments:
           i.     The consequence of a change in law (i.e., the cap on free
                  power supply) must be borne by both parties, and cannot
                  be unilaterally imposed on the generating company.
           ii.    The State Government is a regulated entity as per the third
                  proviso to Section 14 as well as under Section 10(2) of
                  the Electricity Act. Hence, the CERC Regulations, 2019
                  govern and override the contractual obligations under the
                  Implementation Agreement.
           iii.   Since this is a composite scheme for generation and
                  distribution of electricity, there can be no mismatch on the
                  quantum of free power stipulated in the Implementation
                  Agreement, which is an upstream agreement with the
                  State Government, and the PPA and PSAs, which are
                  downstream agreements with distribution companies.
     5.4 We also heard Mr. Nikhil Nayyar for the CERC, who submitted
         the following:
           i.     The CERC Regulations, 2019 are only concerned with
                  tariff fixation and neither deal with the Implementation
                  Agreement nor impose restrictions on the quantum of free
                  power supply to the appellant-State. The purport of the
                  Regulations is to cap the free power that will be considered
                  while fixing tariff and whose costs can be passed onto
1124                                                          [2025] 7 S.C.R.

                         Supreme Court Reports


                the distribution companies and consumers. Since the
                actual quantum of free power supply is determined by
                contract, respondent no. 1 must use contractual remedies
                to challenge the same.
         ii.    Relying on PTC (supra), he submitted that the CERC is
                bound by its Regulations, including the cap on free power
                supply, while determining the tariff. Any further supply is to
                be met by the generating company from its own resources,
                which is also stipulated in the Hydro Power Policy, 2008
                that forms the basis of the CERC Regulations, 2019.
         iii.   RoE for respondent no. 1 is stipulated as 16.5% under
                Regulation 30(2), which is arrived at after considering
                commercial principles and consumer interest, as per
                Section 61(b) and (d) of the Electricity Act. Referring to
                Regulations 14(4), 15, and 18 of the CERC Regulations,
                2019, he submitted that the RoE is part of the Annual Fixed
                Cost, which is used to derive capacity charges that is in
                turn used to determine the tariff. Hence, RoE forms a part
                of the tariff itself and the tariff is structured on this basis.
                RoE is not the same as the net profit of respondent no. 1.
                In its written submissions, the CERC further submitted that
                RoE is calculated on the equity component of the Project,
                which has been granted in full to respondent no. 1 for the
                2014-19 and 2019-24 periods.
         iv.    The CERC’s order dated 17.03.2022 only directs that the
                PPA and PSAs must be aligned with the Regulations.
                It does not deal with or decide on the Implementation
                Agreement. This order was not challenged by respondent
                no. 1 before the APTEL, and they instead relied on the
                same to file a writ petition before the High Court to seek
                the relief of aligning the Implementation Agreement. The
                filing of the writ petition is a way to avoid the CERC order
                dated 17.03.2022 and an attempt to achieve the same
                result through a different prayer.
    5.5 Mr. Gurminder Singh, learned senior counsel submits that the
        State Government cannot be treated as a deemed licensee in
        the present case. Further, he submits that the CERC’s role of
        tariff determination does not extend to allocating or apportioning
[2025] 7 S.C.R.                                                           1125

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

           the power supplied by the generating company to various
           entities. It only relates to fixation of tariff for such supply, after
           the generating company has decided the allocation.
     5.6 Ms. Preetika Dwivedi submitted that PTC (supra) does not
         apply as tariff regulation is not concerned with a contract
         between the State Government and a generating company.
         When respondent no. 1 consented to supply 18% free power,
         a similar cap of 12% with respect to free power supply was
         provided in the Hydroelectric Policy, 1998. Finally, that the
         burden of free power cannot be passed on to the distribution
         companies or consumers.
     5.7 Finally, Mr. Sibal responded to the submissions made on
         behalf of respondent nos. 1 and 2. He disputed the status of
         the appellant-State as a deemed licensee by contending that
         there is no transmission, distribution, or trading of electricity in
         this case. Specifically referring to Section 2(71) of the Electricity
         Act which defines “trading” as purchase of electricity for resale,
         he submitted that the State Government is not purchasing any
         power as it is supplied free of cost. Since the State Government
         is not a deemed licensee, it does not fall under the CERC’s
         jurisdiction and the terms and conditions of free power supply
         cannot be regulated under the Electricity Act. Second, he
         submitted that the tariff order dated 17.03.2022 provides for
         more than 16.5% RoE to respondent no. 1, and the only impact
         of free power supply beyond 13% is on the net profit, which
         is not guaranteed under the CERC Regulations, 2019. Finally,
         he submitted that the Implementation Agreement falls outside
         the jurisdiction of the Regulatory Commissions constituted
         under the Electricity Act, which deal with tariff determination.
         Rather, this is a case of free supply of electricity to the State
         Government that it can dispose of in a manner it deems fit as
         per the Electricity [Removal of Difficulty] (Third) Order, 2005.
     5.8 Mr. Tripathi also submitted that while RoE is guaranteed by
         the Regulations, net profit is not guaranteed. He submitted
         that this issue was raised by respondent no. 1 in its tariff
         petition and the prayer for relaxation of the cap on free power
         supply was rejected by the CERC, which was not subsequently
         challenged.
1126                                                          [2025] 7 S.C.R.

                           Supreme Court Reports


      5.9 Regarding the status of the State Government as a deemed
          licensee, respondent no. 1 has submitted the following in its
          written submissions: First, although power is supplied free of
          monetary cost, there is purchase as there is non-monetary
          consideration for the power under the Implementation Agreement.
          Second, the State Government undertakes trading of such
          electricity through respondent no. 3, the Himachal Pradesh State
          Electricity Board, which is its agent/instrumentality. Considering
          these factors, the State Government is a regulated entity and
          is governed by the CERC Regulations, 2019. As per PTC
          (supra) as well as Article 9 of the Implementation Agreement,
          the contractual rights and obligations relating to free power are
          subject to the CERC Regulations, 2019.
      5.10 Further, in its written submissions, respondent no. 1 has also
           contended that the policies relied on by the appellant, including
           the Hydro Power Policy 2008, do not apply to it as the Project
           was awarded through MoU and not competitive bidding.

      V.      Issue:
6.    Having considered the sequence of events and the subject-matter of
      the dispute, as well as the extensive oral and written submissions of
      the parties, we find that the primary issues arising for our consideration
      are: first, whether the CERC Regulations, 2019 bar respondent no.
      1 from supplying free power to the appellant-State beyond 13%; and
      second, whether respondent no. 1 could have invoked the High Court’s
      writ jurisdiction for aligning the Implementation Agreement with the
      CERC Regulations, 2019. In this context, we will also examine the
      scope and ambit of the Electricity Act and the rights and liabilities
      of the entities governed thereunder.

      VI.     Analysis:
7.    The Electricity Act, 2003 is a complete and comprehensive code for
      regulating the generation, transmission, distribution, trading and use
      of electricity. One of the core features of the Act is that it unbundles
      the functions of electricity generation, transmission, and distribution
      that were erstwhile performed by State Electricity Boards18 into


18   Hereinafter “SEBs”.
[2025] 7 S.C.R.                                                                                          1127

                        The State of Himachal Pradesh & Anr. v.
                          JSW Hydro Energy Limited & Ors.

       separate utilities, and provides for their regulation through independent
       Regulatory Commissions.19
8.     The need for an independent and transparent regulatory mechanism
       was felt due to the regulatory failures under the erstwhile legal
       regime20, wherein SEBs constituted by the State Governments were
       entrusted with regulation.21 It was experienced that various problems
       plagued the power sector, including lack of rational retail tariffs, high
       level of cross-subsidies, poor planning and operation, inadequate
       capacity, neglect of consumer interest, and limited involvement of
       the private sector’s skills and resources.22 It is in this context that
       the Electricity Regulatory Commissions Act, 199823 was enacted to
       reform the governance of the sector by establishing an independent
       and transparent regulatory mechanism.24
9.     Within a few years thereafter, the Electricity Act, 2003 was enacted as
       a comprehensive legislation for regulating the sector and it replaced
       the 1910 Act, the 1948 Act, and the 1998 Act.25 The following salient
       features emerge from the Preamble26 of the Electricity Act:
       9.1 The Act consolidates laws, and therefore comprehensively deals
           with all aspects of the electricity sector, from production to usage.
       9.2 Electricity being a public good27 and a basic amenity28, it has
           been recognised as a part of the right to shelter and right to



19   PTC (supra), para 17.
20   Electricity Act, 1910 (hereinafter “the 1910 Act”); the Electricity (Supply) Act, 1948 (hereinafter “the 1948
     Act”).
21   K.C. Ninan v. Kerala State Electricity Board, (2023) 14 SCC 431, para 6.
22   Statement of Objects and Reasons of the Electricity Regulatory Commissions Act, 1998.
23   Hereinafter “the 1998 Act”.
24   W.B. Electricity Regulatory Commission v. CESC Ltd., (2002) 8 SCC 715, para 52; PTC (supra), para 17;
     Sesa Sterlite Ltd. v. Orissa Electricity Regulatory Commission, (2014) 8 SCC 444, para 22.
25   Section 185 of the Electricity Act.
26   The Preamble of the Electricity Act reads:
         “An Act to consolidate the laws relating to generation, transmission, distribution, trading and use
         of electricity and generally for taking measures conducive to development of electricity industry,
         promoting competition therein, protecting interest of consumers and supply of electricity to all areas,
         rationalisation of electricity tariff, ensuring transparent policies regarding subsidies, promotion of
         efficient and environmentally benign policies, constitution of Central Electricity Authority, Regulatory
         Commissions and establishment of Appellate Tribunal and for matters connected therewith or
         incidental thereto.”
27   See K.C. Ninan (supra), para 93.
28   Dilip v. Satish, 2022 SCC OnLine SC 810, para 9.
1128                                                               [2025] 7 S.C.R.

                                  Supreme Court Reports


              life29. In this light, the Act covers the entire process of production,
              transfer, and sale of electricity and also deals with the utilisation
              of electricity. These are covered under generation, transmission,
              distribution, trading and use of electricity.
      9.3 The Act is also concerned with the development of the electricity
          sector so as to ensure that there is sufficient amount of electricity
          available to all. In furtherance of this goal of enhancing the
          availability of electricity, the Act envisages private sector
          participation and promotion of competition.
      9.4 These measures are ultimately intended to protect and subserve
          consumer interests by making electricity supply accessible at
          cheaper rates for those who cannot afford it, as well as making
          supply accessible in all areas and regions. In this vein, the Act
          provides for the need for transparent subsidy policies.
      9.5 Taking the ecological impact of the electricity sector’s activities,
          the Act provides for promotion of efficient and environmentally
          benign policies.
      9.6 Finally, the Act provides for the constitution of permanent
          expert bodies, i.e., Central and State Electricity Regulatory
          Commissions, to regulate the production, transfer and use of
          electricity, as well as for the development of the sector through
          private sector participation and competitiveness to subserve
          consumer interests. Considering the specialised nature of
          functions performed by these bodies, the Act also provides
          for an appellate forum to challenge the Central and State
          Commissions’ decisions, i.e., the APTEL, which can appreciate
          the technicalities and nuances of the sector.
10. Since the facts of this case relate to hydro-power generation, we
    will now examine the relevant statutory provisions for its regulation.

      VII. Regulation of Electricity Generation Under the Electricity Act:
11. Part III of the Electricity Act deals with generation of electricity.
    Section 7 of the Electricity Act permits generating companies to
    establish, operate and maintain a generating station without obtaining



29   Chameli Singh v. State of U.P., (1996) 2 SCC 549, para 8.
[2025] 7 S.C.R.                                                                                          1129

                        The State of Himachal Pradesh & Anr. v.
                          JSW Hydro Energy Limited & Ors.

       a license under the Electricity Act.30 However, in cases of hydro-electric
       generation, the concurrence of the Central Electricity Authority is
       required as per Section 8.31
12. Section 10 lays down the duties of generating companies. While
    sub-section (1) requires a generating company to establish, operate
    and maintain generating stations, sub-section (2) provides that
    a generating company may supply electricity to any licensee in
    accordance with the Act and rules and regulations made thereunder,
    and it may supply electricity to any consumer subject to the regulations
    under Section 42(2). Section 10 is extracted hereinbelow for ready
    reference:
               “Section 10. (Duties of generating companies): ---
               (1) Subject to the provisions of this Act, the duties of a
               generating company shall be to establish, operate and
               maintain generating stations, tie-lines, sub-stations and
               dedicated transmission lines connected therewith in
               accordance with the provisions of this Act or the rules or
               regulations made thereunder.
               (2) A generating company may supply electricity to any
               licensee in accordance with this Act and the rules and
               regulations made thereunder and may, subject to the
               regulations made under sub-section (2) of section 42,
               supply electricity to any consumer.
               (3) Every generating company shall –
                       (a) submit technical details regarding its generating
                       stations to the Appropriate Commission and the
                       Authority;



30   Section 7 of the Electricity Act reads:
         “Section 7. (Generating company and requirement for setting up of generating station): Any
         generating company may establish, operate and maintain a generating station without obtaining a
         licence under this Act if it complies with the technical standards relating to connectivity with the grid
         referred to in clause (b) of section 73.”
31   The relevant portion of Section 8 of the Electricity Act reads:
         “Section 8. (Hydro-electric generation): --- (1) Notwithstanding anything contained in section 7,
         any generating company intending to set-up a hydrogenerating station shall prepare and submit to
         the Authority for its concurrence, a scheme estimated to involve a capital expenditure exceeding
         such sum, as may be fixed by the Central Government, from time to time, by notification…”
1130                                                                                    [2025] 7 S.C.R.

                                     Supreme Court Reports


                       (b) co-ordinate with the Central Transmission Utility
                       or the State Transmission Utility, as the case may
                       be, for transmission of the electricity generated by it.”
13. While the Electricity Act has done away with the licensing requirement
    for generating companies, it continues to regulate electricity
    generation as the tariff at which the generating company supplies
    electricity to a distribution licensee is determined by the Central or
    State Commission, as is appropriate, as per Section 62(1)(a) read
    with Section 79 and Section 86 of the Act.32 We will further deal
    with the tariff determination function of the CERC at a later stage.
14. At this juncture, it is also relevant to note this Court’s decision in
    Tata Power Co. Ltd. v. Reliance Energy Ltd.33. It was observed that
    delicensing of generation under the Electricity Act, 2003 marks a
    shift from the position under the 1910 Act, the 1948 Act, and the
    1998 Act.34 The Court held that delicensing electricity generation
    is intended to encourage the setting up of generating stations and
    to promote competition among generating companies. Hence,
    courts must ensure that while interpreting the Electricity Act and
    the regulations made thereunder, they do not bring back licensing
    requirements through the backdoor.35
       14.1 The primary issue before the Court was whether the State
            Commission could have directed a generating company to
            allot additional quantities of power to a particular distribution
            company based on its requirements and number of consumers.
            Answering the question in the negative, this Court held
            that generating companies have the freedom to enter into
            agreements for the sale of generated electricity, including the
            freedom to allocate the quantum of electricity to be sold to


32   Section 62(1)(a) of the Electricity Act reads:
         “Section 62. (Determination of tariff): --- (1) The Appropriate Commission shall determine the tariff
         in accordance with the provisions of this Act for –
         (a) supply of electricity by a generating company to a distribution licensee:
         Provided that the Appropriate Commission may, in case of shortage of supply of electricity, fix
         the minimum and maximum ceiling of tariff for sale or purchase of electricity in pursuance of an
         agreement, entered into between a generating company and a licensee or between licensees, for a
         period not exceeding one year to ensure reasonable prices of electricity;…”
33   (2009) 16 SCC 659.
34   ibid, paras 68-73.
35   ibid, paras 83-84.
[2025] 7 S.C.R.                                                                                       1131

                       The State of Himachal Pradesh & Anr. v.
                         JSW Hydro Energy Limited & Ors.

                each distribution company.36 However, such freedom is not
                entirely unregulated as the generating company is subject to
                tariff determination by the appropriate Regulatory Commission,
                and its agreements with distribution companies are subject to
                the approval of State Commissions under Section 86(1)(b),
                who will examine whether the allocation of power and terms
                and conditions of the agreement are reasonable.37

      VIII. Legal Effect of Note 3 of Regulation 55:
15. Interpretation of the CERC Regulations, 2019: It is a settled position
    of law that a regulation made by the CERC in exercise of its powers
    under Section 178 of the Act will override existing contracts between
    regulated entities. Contractual terms, insofar as where the regulation
    operates, must be aligned or modified such that they are in line with
    the regulation.38 For example, a regulation for determining tariff will
    override inconsistent and contrary provisions in an agreement to that
    extent. The crux of the dispute between the parties in the present
    case is whether Note 3 of Regulation 55 prohibits the generating
    company from supplying free power beyond 13% to the State, and
    consequently, whether it overrides the contractual obligation of
    respondent no. 1 under the Implementation Agreement.
16. The contractual obligation of respondent no. 1 to supply free power
    can be understood as a form of “royalty” payable to the State as


36   ibid, paras 108-109.
37   ibid, paras 77, 108, 110-113. This position has been reiterated in Transmission Corporation of Andhra
     Pradesh Ltd. v. Sai Renewable Power (P) Ltd., (2011) 11 SCC 34, para 64.
38   PTC (supra), paras 58 and 66. This has been consistently followed by the Court. See Gujarat Urja Vikas
     Nigam Ltd. v. Renew Wind Energy (Rajkot) (P) Ltd., 2023 SCC OnLine SC 411, para 48; Haryana Power
     Purchase Centre v. Sasan Power Ltd., (2024) 1 SCC 247, paras 110-111.
     The relevant portions from PTC (supra) are extracted hereinbelow for ready reference:
        “58. … Further, it is important to bear in mind that making of a regulation under Section 178
        became necessary because a regulation made under Section 178 has the effect of interfering
        and overriding the existing contractual relationship between the regulated entities. A regulation
        under Section 178 is in the nature of a subordinate legislation. Such subordinate legislation can
        even override the existing contracts including power purchase agreements which have got to
        be aligned with the regulations under Section 178 and which could not have been done across
        the board by an order of the Central Commission under Section 79(1)(j).
        66. While deciding the nature of an order (decision) vis-à-vis a regulation under the Act,
        one needs to apply the test of general application. On the making of the impugned 2006
        Regulations, even the existing power purchase agreements (PPA) had to be modified and
        aligned with the said Regulations. In other words, the impugned Regulations make an inroad
        into even the existing contracts…”
                                                                                          (emphasis supplied)
1132                                                                                     [2025] 7 S.C.R.

                                    Supreme Court Reports


      compensation, in lieu of being allowed to utilise river water, which
      is a public and commons resource, for undertaking its commercial
      activity of power generation from which it derives benefits through
      sale of power.39 Perusal of Article 4 of the Implementation Agreement
      also shows that the appellant-State fulfilled various other obligations
      like acquiring land, granting permissions, and executing leases in
      favour of respondent no. 1 to enable it to set up its hydropower
      generating station. In return, respondent no. 1 undertook various
      obligations provided in Article 5 of the Implementation Agreement,
      including supplying free power at a certain percentage. Therefore, it
      is clear that the free power supply is a part of the consideration by
      respondent no. 1 under the Implementation Agreement.
17. Now the question is whether such a consideration is impermissible
    or prohibited by virtue of the CERC Regulations, 2019. To answer
    the same, it is necessary to appreciate the context in which Note 3
    of Regulation 55, which stipulates that FEHS shall be taken as
    13% or actual, whichever is less, has been made. Regulation 55
    deals with billing and payment of charges to generating companies.
    While sub-clause (1) deals with raising bills for capacity and energy
    charges and payment, sub-clause (2) is relevant for our purpose. It
    provides that payment of capacity and energy charges for a hydro-
    generating station shall be shared by its beneficiaries40 in proportion
    to their shares in saleable capacity, which is to be determined after
    deducting the capacity corresponding to FEHS as per Note 3. Hence,
    Note 3 of Regulation 55 is relevant for the calculation of saleable
    power, which is in turn relevant for the generating company to raise
    bills and for payments by beneficiaries.



39   See Indsil Hydro Power & Manganese Ltd. v. State of Kerala, (2021) 10 SCC 165, paras 43-43.1; 56-57.
40   “Beneficiary” has been defined in Regulation 3(8) of the CERC Regulations, 2019 as follows:
        “3. Definitions. - In these regulations, unless the context otherwise requires:
        ***
        (8) ‘Beneficiary’ in relation to a generating station covered under clauses (a) or (b) of sub-section 1 of
        section 79 of the Act, means a distribution licensee who is purchasing electricity generated at such
        generating station by entering into a Power Purchase Agreement either directly or through a trading
        licensee on payment of capacity charges and energy charges;
        Provided that where the distribution licensee is procuring power through a trading licensee, the
        arrangement shall be secured by the trading licensee through back to back power purchase
        agreement and power sale agreement.
        Provided further that beneficiary shall also include any person who has been allocated capacity in
        any inter-State generating station by Government of India”
[2025] 7 S.C.R.                                                       1133

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

18. Regulation 44, which deals with the computation and payment of
    capacity and energy charges for hydro-generating stations also
    defines FEHS similarly. Sub-clause (1) provides that the fixed cost of a
    hydro-generating station shall be recovered on a monthly basis under
    capacity and energy charges, which are payable by beneficiaries
    in proportion to their respective allocation in saleable capacity, i.e.,
    capacity excluding FEHS. Further, the formula for calculating energy
    charges is provided in sub-clauses (4) and (5), which also relies on
    FEHS as defined in Note 3 of Regulation 55.
19. Therefore, the purpose and intendment of Note 3 of Regulation 55
    is for the State Commission to determine tariff by assuming that
    FEHS is 13%, whenever it is higher in actuality, while calculating
    the energy and capacity charges. Neither the language of Note 3
    nor the context in which it appears in the CERC Regulations, 2019
    supports respondent no. 1’s contention that the legal effect of this
    cap is to override its contractual obligations with the appellant-State.
    On the other hand, use of the term “shall be taken as 13% or actual,
    whichever is less” shows that the Regulations cover a situation
    where the obligation to supply free power is higher than 13%, and
    in such an eventuality, allow only a certain portion of free supply to
    be considered for tariff determination and payments by beneficiaries
    for the saleable capacity.
20. Once the Regulation does not prohibit the supply of free power
    beyond 13%, respondent no. 1 cannot rely on it to wriggle out of
    its contractual obligations. Such an interpretation is necessary to
    recognise and enforce the generating company’s freedom of contract,
    which includes its choice of business dealings. The Regulatory
    Commissions, APTEL, and the Courts must enforce these contractual
    obligations and ensure that their interpretation of regulations does not
    allow the party to circumvent and breach its contractual undertakings
    when the same is not intended by the regulation itself.
21. Further, the above interpretation of the regulation balances the social
    justice obligation of the Regulatory Commission to ensure that the
    tariff is not increased by allowing pass-through to the extent of only a
    certain portion of free supply while balancing the commercial viability
    and financial position of the generating company. Public interest is
    also subserved since the State can utilise the free power for its own
    purposes. This interpretation balances the twin values of freedom
1134                                                      [2025] 7 S.C.R.

                        Supreme Court Reports


     of business choices and the social justice obligations of the State,
     which the Regulatory Commission channelises towards protecting
     consumer interests and maintaining the health of the sector.
22. CERC’s Order dated 17.03.2022: The relief sought by respondent
    no. 1 in its tariff petition for 2019-2024 before the CERC is relevant
    as it shows that the initial position taken by it was not an attempt to
    wriggle out of the contract by seeking its modification. In contrast to
    claiming that the Implementation Agreement stands overridden and
    must be aligned with the 13% cap, as is the case before the High
    Court and in this appeal, respondent no. 1 sought relaxation of the
    cap itself. In other words, respondent no. 1 sought a pass-through
    for the full extent of 18% free power, rather than 13% as per the
    Regulations, in recognition of its contractual obligations under the
    Implementation Agreement.
23. In the tariff order dated 17.03.2022, the CERC rejected this prayer on
    the following basis. It took note of the free power supply obligation
    under Article 5.1 as being 12% of net generation for the first 12 years
    from the COD, and 18% of net generation for the next 28 years.
    It also noted that the PPA executed with respondent no. 4 defines
    free power in the same manner. Relying on this Court’s decision in
    PTC (supra), it held that the provisions of the agreement must be
    aligned with the Regulations. Hence, the provisions of the PPA and
    PSAs executed by respondent no. 1 in respect of free power are
    inconsistent and stand overridden by Note 3 of Regulation 55 such
    that FEHS is to be considered as 13% only. The relevant portions
    of the CERC’s order are extracted below for ready reference:
          “145. The main contention of the Petitioner is that since
          the quantum of free power to be supplied to the home
          State was based on the agreement between the parties,
          which were executed prior to coming into force of the
          Tariff Regulations notified by the Commission, the same
          may be considered by the Commission in exercise of
          the power to relax/power to remove difficulties. The
          Respondent HPPC has submitted that in terms of the
          judgment of the Hon’ble Supreme Court in PTC v CERC
          & ors. Tariff Regulations override existing contracts. Note
          3 under Regulation 55 of the 2019 Tariff Regulations
          provides as under:
[2025] 7 S.C.R.                                                             1135

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

                Note 3: FEHS = Free energy for home State,
                in percent and shall be taken as 13% or actual
                whichever is less.
           146. The Constitution Bench of the Hon’ble Supreme
           Court in PTC India Ltd Vs CERC & ors (2010 4 SCC
           603) has laid down the principle of law, whereby any
           provision of an agreement, if it falls within the domain
           of the Regulations of subordinate legislation, has to be
           aligned with the Regulations. The relevant portion of the
           judgment is quoted below…
           147. Thus, the provisions of the PPA/PSAs executed by
           the Petitioner in respect of free power to the home State
           is inconsistent and shall accordingly stand overridden by
           Note 3 under Regulation 55 of the 2019 Tariff Regulations.
           We, therefore, find no reason to exercise the power to relax
           and grant relief, as prayed for by the Petitioner. Accordingly,
           the free energy to home state is to be considered as 13%
           in this case.”
24. There are two aspects of the CERC’s reasoning and decision that
    we must note: first, the CERC was made aware of the contractual
    obligation of respondent no. 1 under the Implementation Agreement,
    but it did not hold the same as being overridden by Note 3 of
    Regulation 55. This is in line with the interpretation of the cap that
    we have elaborated hereinabove, i.e., it does not prohibit or restrain
    respondent no. 1 from entering into or performing a contract for
    supplying a higher quantum of free power. Second, the CERC only
    held that the PPA and PSAs stand overridden to the extent that
    they are inconsistent with the Regulation. The effect of this is that
    only 13% of free power would be considered as a pass-through
    for tariff fixation and recovery of charges from the beneficiary
    distribution companies as per the Regulations. Since respondent
    no. 1 did not appeal this order before the APTEL under Section
    111 of the Electricity Act, these findings are now final and binding
    on it.
25. We will now examine whether the High Court could have, in exercise
    of its writ jurisdiction, granted the relief of aligning the Implementation
    Agreement by relying on the CERC’s order dated 17.03.2022.
1136                                                                                [2025] 7 S.C.R.

                                   Supreme Court Reports


       IX.        Maintainability of the Writ Petition:
26. CERC as an Expert and Specialised Regulator, and Extent of Judicial
    Interference: In order to appreciate the issue on maintainability of the
    writ petition, it is necessary to take note that postmodern legislation
    institutionalises governance through regulation. Under the Electricity
    Act, we see such a statutory incorporation of the regulators through
    the CERC and the State Commissions that are expert and specialised
    bodies to perform wide-ranging regulatory functions.41
27. The jurisprudence on regulation is that independent regulators,
    armed with statutory powers and duties, were established to reduce
    the government’s control and interference with the market while
    safeguarding consumer interests, preventing abuse of monopoly, and
    enabling private participation in the sector. Therefore, the regulator
    has socio-economic obligations of ensuring accessibility of goods
    and services, as well as the duties towards the development of the
    industry by promoting efficiency and competition.42 The nature of
    functions and the jurisdiction of these regulatory bodies are wide
    and extensive as they perform a mix of legislative, executive and
    administrative, and judicial functions.43 Concomitantly, they are
    sufficiently empowered under the statute, and legislative, executive
    and adjudicatory powers are telescoped into one institution.
    Regulators have the power to lay down rules and regulations; issue
    licenses; fix prices and scope and areas of operation; investigate
    and prosecute offences, and impose penalties; adjudicate disputes
    and interpret the law; implement and enforce the statute, the rules
    and regulations made thereunder, and their decisions; and exercise
    incidental and ancillary powers to deal with all aspects relating to
    the sector.44
28. Specifically, in the context of the CERC under the Electricity Act,
    Section 79 sets out its functions, including tariff determination. The
    relevant portion is extracted hereinbelow:



41   See PTC (supra), para 17; Sai Renewable (supra), paras 36 and 38; Reliance Infrastructure Ltd. v. State
     of Maharashtra, (2019) 3 SCC 352, para 38.
42   H.W.R. Wade and C.F. Forsyth, Administrative Law (11th edn, Oxford University Press 2014), 116-117.
43   ibid, 124.
44   ibid; Cellular Operators Assn. of India v. Union of India, (2003) 3 SCC 186, para 33; U.P. Power Corpn.
     Ltd. v. NTPC Ltd., (2009) 6 SCC 235, paras 4, 22, 48.
[2025] 7 S.C.R.                                                            1137

                      The State of Himachal Pradesh & Anr. v.
                        JSW Hydro Energy Limited & Ors.

              “Section 79. (Functions of Central Commission): ---
              (1) The Central Commission shall discharge the following
              functions, namely:-
              ***
              (b) to regulate the tariff of generating companies other
              than those owned or controlled by the Central Government
              specified in clause (a), if such generating companies enter
              into or otherwise have a composite scheme for generation
              and sale of electricity in more than one State…”
29. “Tariff” has not been defined under the Electricity Act, but it has been
    interpreted by this Court on several occasions. This Court in PTC
    (supra) held that “tariff” does not only mean fixation of rates but also
    the rules and regulations relating to it45. Further, in Transmission
    Corporation of Andhra Pradesh Ltd. v. Sai Renewable (supra), this
    Court relied on the meaning of the term in general law or common
    parlance, and held its meaning to be as follows:
              “62. Therefore, in the absence of any specific definition
              in any of these Acts we will have to depend upon the
              meaning attached to these expressions under the general
              law or in common parlance. The expression “tariff” has
              been explained in Law Lexicon With Legal Maxims, Latin
              Terms And Words & Phrases (2nd Edn., 1997) as
                     “determination, ascertainment, a table of rates
                     of export and import duties, in which sense the
                     word has been adopted in English and other
                     European languages and as defined by the
                     law dictionaries the word ‘tariff’ is a cartel of
                     commerce; a book of rates; a table or catalogue,
                     drawn usually in alphabetical order, containing
                     the names of several kind of merchandise, with
                     the duties or customs to be paid for the same as
                     settled by the authority or agreed between the
                     several princes and States that hold commerce
                     together.”



45   PTC (supra), para 26.
1138                                                                               [2025] 7 S.C.R.

                                  Supreme Court Reports


              It has also been explained as a schedule, system, or
              scheme of duties imposed by the Government of a country
              upon goods imported or exported; published volume of
              rate schedules and general terms and conditions under
              which a product or service will be supplied; a document
              approved by the responsible regulatory agency listing the
              terms and conditions including a schedule of prices, under
              which utility services will be provided.”46
30. Determination of tariff must be in accordance with Section 61 of the
    Electricity Act, which requires the CERC to specify the terms and
    conditions for the determination of tariff and stipulates the principles
    that shall guide the CERC. These include commercial principles,
    competition, efficiency, economical use of resources, consumer
    interest, and cost-reflective tariffs. The relevant portion of Section
    61 has been extracted hereinbelow:
              “Section 61. (Tariff regulations): The Appropriate
              Commission shall, subject to the provisions of this Act,
              specify the terms and conditions for the determination of
              tariff, and in doing so, shall be guided by the following,
              namely:-
              ***
              (b) the generation, transmission, distribution and supply of
              electricity are conducted on commercial principles;
              (c) the factors which would encourage competition,
              efficiency, economical use of the resources, good
              performance and optimum investments;
              (d) safeguarding of consumers’ interest and at the same
              time, recovery of the cost of electricity in a reasonable
              manner;
              ***
              (g) that the tariff progressively reflects the cost of supply of
              electricity and also, reduces cross-subsidies in the manner
              specified by the Appropriate Commission;…”


46   A similar definition has been adopted by this Court in BSES Ltd. v. Tata Power Co. Ltd., (2004) 1 SCC
     195, para 16.
[2025] 7 S.C.R.                                                                                   1139

                       The State of Himachal Pradesh & Anr. v.
                         JSW Hydro Energy Limited & Ors.

31. The CERC must weigh and balance these competing principles during
    tariff determination, such that interests of various stakeholders and
    the social justice obligation of the State to ensure access to electricity
    are fulfilled. The Act empowers the CERC to make regulations under
    Section 178, including on terms and conditions for the determination of
    tariff. The relevant portions of Section 178 of the Electricity Act read:
              “Section 178. (Powers of Central Commission to make
              regulations): --- (1) The Central Commission may, by
              notification make regulations consistent with this Act and
              the rules generally to carry out the provisions of this Act.
              (2) In particular and without prejudice to the generality of
              the power contained in sub-section (1), such regulations
              may provide for all or any of following matters, namely:-
              ***
              (s) the terms and conditions for the determination of tariff
              under section 61;…”
32. This Court has time and again emphasised that since tariff
    determination, including the power to make regulations for this
    purpose, has been entrusted to a specialised and expert regulator
    constituted under the statute itself, it would not be proper for
    constitutional courts to interfere and assume these functions, or to
    examine tariff fixation on its merits and substitute its own determination
    for the one made by the expert body after duly considering all material
    circumstances.47 We are of the opinion that this is necessary not
    only to ensure that these specialised functions are performed by
    expert regulators but to also facilitate a systematic and consistent
    development of sectoral laws.
33. In this light, when a constitutional court is interpreting statutes, rules,
    or regulations that fall within the regulator’s domain, it must bear in
    mind the need to enable the regulator to exercise comprehensive
    jurisdiction. Courts must not impair the functioning of the regulator
    by taking away certain aspects of the sector outside the regulator’s
    scope, thereby fragmenting regulation and creating plurality of


47   Sai Renewable (supra), paras 38, 40, 41; Reliance Infrastructure Ltd (supra), para 38; Transmission
     Corpn. of A.P. Ltd. v. Rain Calcining Ltd., (2021) 13 SCC 674, para 66; Maharashtra State Electricity
     Distribution Co. Ltd. v. Adani Power Maharashtra Ltd., (2023) 7 SCC 401, paras 118-121.
1140                                                             [2025] 7 S.C.R.

                            Supreme Court Reports


      jurisdictions. It is in the interest of good governance through regulation
      to ensure that there is no proliferation of remedies and there are no
      parallel, multiple remedial forums. Further, this also ensures that the
      sectoral law is developed in a coordinated and systematic fashion
      by the regulator that is equipped to deal with not only legal issues
      but also has specialised knowledge in other areas.
34. The above principles are also reflected in a recent decision of
    this Court in Jaipur Vidyut Vitran Nigam Ltd. v. MB Power (M.P.)
    Ltd.48. Here, the High Court exercised writ jurisdiction and directed
    distribution companies to procure power from bidders, who are
    generating companies, at the prices quoted in their bids till the
    requisite quantum of power was procured. Allowing the appeal
    of the distribution companies, this Court held that the High Court
    was not justified in entertaining the writ petition as the Electricity
    Act is an exhaustive code and all issues dealing with electricity
    must be considered by the expert bodies, i.e., the Regulatory
    Commissions constituted under the Act. The relevant portion is
    extracted hereinbelow:
             “128. We find that the High Court was not justified in
             entertaining the petition. The Constitution Bench of
             this Court in PTC has held that the Electricity Act is an
             exhaustive code on all matters concerning electricity. Under
             the Electricity Act, all issues dealing with electricity have to
             be considered by the authorities constituted under the said
             Act. As held by the Constitution Bench of this Court, the
             State Electricity Commission and the learned APTEL have
             ample powers to adjudicate in the matters with regard
             to electricity. Not only that, these Tribunals are tribunals
             consisting of experts having vast experience in the field
             of electricity. As such, we find that the High Court erred
             in directly entertaining the writ petition when Respondent
             1 i.e. the writ petitioner before the High Court had an
             adequate alternate remedy of approaching the State
             Electricity Commission.
             129. This Court in Reliance Infrastructure Ltd. v. State
             of Maharashtra has held that while exercising its power


48   (2024) 8 SCC 513.
[2025] 7 S.C.R.                                                          1141

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

           of judicial review, the Court can step in where a case of
           manifest unreasonableness or arbitrariness is made out.
           130. In the present case, there is not even an allegation
           with regard to that effect. In such circumstances, recourse
           to a petition under Article 226 of the Constitution of India
           in the availability of efficacious alternate remedy under
           a statute, which is a complete code in itself, in our view,
           was not justified.”
                                                 (emphasis supplied)

35. Grant of Relief by the High Court: Applying these legal principles, we
    will now analyse whether the High Court could have granted relief of
    aligning the Implementation Agreement with the CERC Regulations,
    2019 by exercising writ jurisdiction. The High Court proceeded on the
    basis that: (i) the appellant-State is a deemed licensee; (ii) the CERC
    Regulations, 2019 are relevant not only for determination of tariff
    but also for other purposes and are binding on the appellant-State;
    and (iii) the 13% cap on free power supply under Note 3, Regulation
    55 has the effect of overriding the free power supply clause in the
    Implementation Agreement since a similar clause in the PPA and
    PSAs stands overridden as per the CERC’s order dated 17.03.2022.
36. On the first aspect of whether the appellant-State is a deemed
    licensee, it is clear from the impugned order that the High Court has
    only cited the statutory provisions on licensing but has neither delved
    into this issue nor arrived at any express conclusion regarding the
    same. This is perhaps because the parties did not raise or argue
    the issue before it. However, before us, respondent no. 1 strongly
    contends that the appellant-State is a deemed licensee, and the
    appellant has disputed the same.
37. We are of the opinion that this issue need not be determined on
    merits, but is relevant to show respondent no. 1’s conduct in taking
    contrary positions by filing the writ petition. On the one hand, it is
    claiming that the appellant being a deemed licensee is a regulated
    entity under the Electricity Act. The sequitur of this would be that
    the appellant, and its contractual rights and liabilities, are subject to
    the CERC’s regulatory jurisdiction. However, respondent no. 1 never
    sought relief against the appellant-State before the CERC, as we
    have indicated above, and instead filed a writ petition. Considering
1142                                                           [2025] 7 S.C.R.

                          Supreme Court Reports


     the contradictory positions of respondent no. 1, it cannot be allowed
     to approbate and reprobate, or blow hot and cold at the same time
     to secure relief under the law.
38. The second aspect pertains to the interpretation of CERC Regulations,
    2019 by the High Court. We have already dealt with the interpretation
    of the Regulations hereinabove, and will presently deal with the same
    in the context of maintainability of the writ petition. Under the Electricity
    Act, the statutory regulator has been entrusted with discharging
    the function of tariff determination, including making regulations for
    the purpose and interpreting the same. Constitutional courts must
    enable the regulator to comprehensively regulate all aspects of the
    sector such that remedies are not fragmented and certain issues
    are not left outside the regulator’s domain. The regulator has the
    expertise, specialisation, and institutional memory to conduct such
    an interpretative exercise to further the objective of the regulatory
    regime and systematically lay down legal principles. In this light, the
    High Court should not have entered into the domain of interpreting
    these Regulations which deal with tariff determination, as the same
    falls within the exclusive domain of the CERC. The Electricity Act
    itself provides the appellate mechanisms by establishing a specialised
    and permanent tribunal, namely the APTEL, and an appeal before
    this Court, against the CERC’s orders. In view of the existence of a
    statutory regulatory forum, the High Court should not have entertained
    the writ petition by interpreting the CERC Regulations, 2019.
39. Equally, we are of the opinion that the High Court incorrectly relied
    on the CERC’s order dated 17.03.2022 to grant relief to respondent
    no. 1. As explained above, the CERC’s order only deals with the PPA
    and PSAs despite taking note of Article 5.1 of the Implementation
    Agreement. Upon reading the order, it is clear that its effect is not
    that of restraining respondent no. 1 from supplying free power beyond
    13%. Hence, it does not in any way adversely affect or prejudice
    the contractual rights of the appellant-State. Hence, the High Court
    could not have proceeded on the basis of this order to grant the
    relief of modifying the Implementation Agreement.

     X.    Conclusion:
40. In view of the above reasons, we hold that CERC Regulations, 2019
    do not prohibit respondent no. 1 from supplying free power beyond
[2025] 7 S.C.R.                                                     1143

                    The State of Himachal Pradesh & Anr. v.
                      JSW Hydro Energy Limited & Ors.

     13% to the appellant-State, and the Implementation Agreement does
     not stand overridden by the operation of these Regulations. Further,
     a writ petition before the High Court for aligning the Implementation
     Agreement with the CERC Regulations, 2019 and the CERC’s
     order dated 17.03.2022 is not maintainable. Once respondent no.
     1’s prayer for relief was rejected by the CERC and it specifically
     held only the PPA and PSAs to stand overridden, which finding was
     not further appealed, it would not be open for respondent no. 1 to
     seek modification of the Implementation Agreement by way of a writ
     petition before the High Court.
41. For the reasons stated above, we allow Civil Appeal No. 12883/2024
    and set aside the order and judgment of the High Court in CWP
    7667/2023 dated 28.05.2024.
42. Pending applications, if any, stand disposed of.
43. No order as to costs.

     Result of the case: Appeal allowed.




     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Contractual obligation"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.