Created byFuzzy Cloud

Supreme Court of India

ZENIT MATAPLAST P. LTD.versusSTATE OF MAHARASHTRA AND ORS.

Citation
2009 INSC 1130
Decided
11 September 2009
Disposal
Disposed off

Holding

The Supreme Court held that the High Court was not justified in refusing interim relief; the State's action was arbitrary and violative of Article 14, and interim relief was warranted despite the petitioner's delay.

Summary

Zenit Mataplast Ltd. filed a writ petition challenging the allotment of 17 acres of land to Mahendra & Mahendra Ltd. and another party, alleging that the Maharashtra Industrial Development Corporation acted arbitrarily, with bias and favouritism, violating Article 14 of the Constitution. The Bombay High Court admitted the petition but refused interim relief, prompting an appeal. The Supreme Court examined whether the High Court was justified in denying interim relief in a case involving alleged arbitrariness and fundamental rights, and whether delay on the part of the petitioner could preclude such relief. Relying on principles of prima facie case, balance of convenience, irreparable injury, and the need to prevent a fait accompli, the Court held that the State's action was arbitrary and that interim relief could be granted even at a belated stage. Consequently, the appeal was allowed and the interim order dated 21‑July‑2008 was directed to remain in force until the High Court decides the writ petition.

Issues considered

  • The High Court's refusal to grant interim relief in a writ petition alleging arbitrariness, bias and favouritism under Article 14.
  • Whether interim relief can be granted at a belated stage when the case involves fundamental rights and a risk of irretrievable injury.
  • Whether the delay of the petitioner in approaching the court bars the grant of interim relief.
  • Whether the land allotment by the Maharashtra Industrial Development Corporation complied with the Maharashtra Industrial Development Act, 1961 and its regulations.

Legislation cited

Subjects

interim reliefArticle 14arbitrarinessbiasfavouritismland allotmentfundamental rightstemporary injunctionstate authorityequality before law

Judgment

                 [2009) 14 (ADDL.) S.C.R. 403


                   ZENIT MATAPLAST P. LTD.                         A
                                 v.
             STATE OF MAHARASHTRA AND ORS.
                (Civil Appeal No. 6201 of 2009)

                      ~EPTEMBER 11, 2009
                                                                   B
      [ALTAMAS KABIR AND DR. B. S. CHAUHAN, JJ.]

~       Interlocutory Order:

          Writ petition against State instrumentality - Alleging c
    discrimination, bias and favoritism in allotment of land -
    Interim relief also sought - Petition admitted while interim
    relief refused - On appeal, held: While deciding application
* for interim relief, in a case alleging arbitrariness, bias and
.J. favouritism, the court is required to form a tentative opinion 0
    as to whether there is substance in those a/legations -If facts
    of the case establish that the action of the State authority is
    arbitrary and violative of mandate of Article 14 of the
    Constitution - Interim relief may be granted even at a belated
    stage, if the case is based on fundamental rights - Interim E
    relief was refused by High Court without assigning any reason
 " - Delay on the part of the writ petitioner, in approaching the
 ._ court has also been explained - Writ petitioner deseNes to
    be granted interim protection - Constitution of India, 1950 -
    Article 14.
                                                                    F
         Interim relief - Grant of - When - Discussed.

      Appellant filed a writ petition, alleging arbitrariness,
  bias and favouritism, against respondent-Statutory
  Authority as regards allotment of land. Appellant also G
~ sought interim relief. High Court admitted the petition, but
  refused to grant interim relief. However, it directed to
  expedite the hearing in the matter. Hence, the present
  appeal against refusal of interim relief.
                                403                                H
    404    SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A         Disposing of the appeal, the Court

       HELD: 1.1. Every action of the State or its
  instrumentalities should not only be fair, legitimate and
  above-board' but should be without any affection or
B aversion. It should neither be suggestive of
  discrimination nor even apparently give an impression of
  bias, favouritism and nepotism. The decision should be
  made by the application of known principle and rules and
  in general such decision should be predictable and the
  citizen should know where he stands. However, if a
C decision is taken without any principle or without any
  rule, it is unpredictable and such a decision is antithesis
  to the decision taken in accordance with the rule of law.
  [Para 20] [417-A-C]

o       S. G. Jaisinghani vs. Union of India and Ors. AIR 1967    )..
    SC 1427; Haji T.M. Hassan Rawther vs. Kera/a Financial
    Corporation AIR 1988 SC 157, relied on.

       1.2. The action/order of the State or State
E instrumentality would stand vitiated if it lacks bona fide as
  it wou!d only be a case of colourable exercise of power.
  The Rule of law is the foundation of a democratic society.      -I
  [Para 21] [417-D]

        l.R. Coelho (dead) by LRs vs. State of Tamil Nadu AIR
F   2007 SC 861, relied on.

       1.3. In a case, as in the instant case, when the
  applicant approaches the court complaining against the
  Statutory Authority alleging arbitrariness, bias or
G favouritism, the court, being custodian of law, must
  examine the averments made in the application to form           ~
  a tentative opinion as to whether there is any substance
  in those allegations. Such a course is also required to be
  followed while deciding the application for interim relief.
H [Para 22] [417-G-H; 418-A]
                                                                        I
                                                                        ;
....            ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 405
                                    AND ORS.



          '
                      2.1. Interim order is passed on the basis of prima A
                facie findings, which are tentative. Such order is passed
 """            as a temporary arrangement to preserve the status quo
                till the matter is decided finally, to ensure that the matter
                does not become either infructuous or a fait accompli
                before the final hearing. The object of the interlocutory B
                injunction is, to protect the plaintiff against injury by
       ~·
                violation of his right for which he could not be adequately
                compensated in damages recoverable in the action if the
          "'    uncertainty were resolved in his favour at the trial. [Para
                23] [418-A-C]                                                 c
 ·- ...
                    Anand Prasad Agarwal/a vs. Tarkeshwar Prasad and Ors.
                AIR 2001 SC 2367; State of Assam vs. Barak Upatyaka
                D.U.Karmachari Sanstha (2009) 5 SCC 694; Colgate
          >
                Palmolive (India) Ltd. vs. Hindustan Lever Ltd. AIR 1999 SC
          ...   3105, relied on.                                            D

                     2.2. Grant of an interim relief in regard to the nature
                and extent thereof depends upon the facts and
                circumstances of each case as no strait-jacket formula
                can be laid down. There may be a situation wherein the          E
                defendant/respondent may use the suit property in such
                a manner that the situation becomes irretrievable. In such
          '-·   a fact situation, interim relief should be granted. (Para 24]
                [418-D-E]

                    M. Gurudas and Ors. vs. Rasaranjan and Ors. AIR 2006        F
                SC 3275; Shridevi and Anr. vs. Muralidhar and Anr. (2007)
                14 sec 721, relied on.

                    2.3. Grant of temporary injunction, is governed by
                three basic principles, i.e. prima facie case, balance of G
                convenience, and irreparable injury, which are required
                to be considered in a proper perspective in the facts and
                circumstances of a particular case. But it may not be
                appropriate for any court to hold a mini trial at the stage
                of grant of temporary injunction. [Para 25) (418-F·G]       H
    406   SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.
                                                                      "
A       S.M. Dyechem Ltd. vs. Mis. Cadbury (India) Ltd., AIR    ~
    2000 SC 2114; Anand Prasad Agarwal/a vs. Tarkeshwar                .....
    Prasad and Ors. AIR 2001 SC 2367, relied on.

       2.4. Interim injunction should be granted by the court
  after considering all the pros and cons of the case in a
B
  given set of facts involved therein on the risk and
  responsibility of the party, in case he looses the case, he
  cannot take any advantage of the same. The order can
  be passed on settled principles takiQg into account the       ~

c three  basic grounds i.e. prima facie case, balance of
  convenience and irreparable loss. [Para 32] [421-C-D]               ,~




      Dalpat Kumar and Anr. vs. Prahlad Singh and Ors. AIR
  1993 SC 276; Manohar Lal Chopra vs. Rai Bahadur Rao
  Raja Seth Hira Lal AIR 1962 SC 527; Deoraj vs. State of       ...
D Maharashtra and Ors. AIR 2004 SC 1975; All India Anna         ~
  Dravida · Munnetra Kazhagam vs. Chief Secretary, Govt. of
  Tamil Nadu and Ors. (2009) 5 SCC 452; Bombay Dyeing and
  Manufacturing Co. Ltd. vs. Bombay Environmental Action
  Group and Ors. (2005) 5 sec 61, relied on.
E       2.5. The delay in approaching the court is of course
  a good ground for refusal of interim relief, but in
  exceptional circumstances, where the case of a party is
  based on fundamental rights guaranteed under the
  Constitution and there is an apprehension that suit
F property may be developed in a manner that it acquires
  irretrievable situation, the court may grant relief even at
  a belated stage provided the court is satisfied that the
  applicant has not been negligent in pursuing the case.
  [Para 32] [421-D-E]
G
        2.6. There has been a delay on the part of the          +
    appellant in approaching the court but the Court cannot
    be oblivious of the fact that the appellant had been
    approaching the authorities time and again for allotment
H
        ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 407
I
                            AND ORS.

        of the land. Admittedly, the entire land had not been            A
        developed by the respondent No.4 till this court
        entertained the Special Leave Petition and directed the
        parties to maintain status quo with regard to the land
        measuring 2 acres adjacent to the appellant's plot no.F-
        15 vide order dated 21. 7.2008. Therefore, it is not the         B
        appellant alone, who is to be blamed for the delay. The
        land had been allotted to the respondent No.4 in undue
        haste and no development could take place therein for
        more than two years of taking the possession of the land.
        In such a fact-situation it is not correct to say that interim   c
        stay cannot be granted at a belated stage. [Para 35] [422-
        E-G]

              2.7. Anything done in undue haste can also be
         termed as arbitrary and cannot be condoned in law. In the
         instant case, the whole case of the appellant is based on D
         violation of Article 14 of the Constitution as according to
         the appellant it has been a case of violation of equality
         clause enshrined in Article 14, The facts of the case
        clearly establish that the Corporation and the
        Government proceeded in haste while considering the E
        application of respondent No.4 which tantamount to
        arbitrariness, thus violative of the mandate of Article 14
        of the Constitution. Application of the appellant was
         required to be disposed of by a speaking and reasoned
        order. Admittedly, no reason was assigned for rejecting F
        the same. There is nothing on record to show as on what
        date and under what circumstances, Plot nos.F-16 and
        F-17 stood decarved and became part of the Open Space
        No.9. The respondents could not furnish any explanation
        as in what manner and under what circumstances, the G
    +   Bharat Sanchar Nigam Ltd. has been made allotment of
        land from plot no.F-16, (a part of Open Space No.9),
        without change of user of the land. The respondent no.4
        had not initially asked for 17 acres of land which has
                                                                         H
    408 ·SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.
                                                                        •
A been allotted to it. There is nothing on record to show as    ;.'
  to why the land could not be disposed of by auction. All
  these circumstances provide for basis to form a tentative
  opinion that State and its instrumentalities have acted
  affectionately in the case of respondent No.4. [Paras 33.
B and 34] [421-F-G-H; 422-A-D]
        Madhya Pradesh Hasta Shi/pa Vikas Nigam Ltd. vs.
    Devendra Kumar Jain and Ors. (1995) 1 SCC 638;
    Bahadursinh Lakhubhai Gohil vs. Jagdishbhai M. Kama/ia     >-~
                                                                    -
    and Ors. AIR 2004 SC 1159, relied on
c
                        Case Law Reference:
        AIR 1967 SC 1427       Relied on          Para 20
       AIR 1988 SC 157         Relied on          Para 20       _.
D
       AIR 2007 SC 861         Relied on          Para 21      >.
        (2009) 5 sec 694       Relied on          Para 23
        AIR 2001 SC 2'3t;'?    Relied on          Paras 23
                                                  and 25
E
       AIR 2006 SC 3275        Relied on          Para 24 ·

        (2001) 14 sec 121      Relied on          Para 24 ·    -+     /




        AIR 2000 SC 2114       Relied on          Para 25
F
       AIR 1999 SC 3105        Relied on          Para 26
       AIR 1993 SC 276         Relied on          Para 27
       AIR 1962 SC 527         Relied on          Para 28
G      AIR 2004 SC 1975        Relied on          Para 29
                                                               +
       (2009) 5 sec 452        Relied on          Para 30

        (2005) 5 sec 61        Relied on          Para 31

H
---f


                    ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 409
                                        AND ORS.
       ;.
            A            (1995) 1 sec 638           Relied on              Para 33       A

                         AIR 2004 SC 1159           Relied on              Para 33

                        CIVIL APPELLATE JURISDICTION : Civil Appeal No.
                    6201 of 2009.
                                                                                         B
                        From the Judgment & Order dated 5.2.2008 of the High
                    Court of Judicature at Bombay in Writ Petition No. 7245 of
                ~
                    2006.

                        Dushyant Dave, Udaya Kr. Sagar, Bina Madhavan,
                    Lawyer's Knit & Co., for the Appellant.
                                                                                         c
                        Shyam Divan, Bhaskar P. Gupta, Shruti Chaudhary, Swati
                    Sinha, Jayshree Singh, Asha Gopalan Nair, Fox Mandal & Co.,
       ..           Sanjeev K. Kapoor, Vishal Gupta, Vikram Bajaj, Khaitan & Co.,
        ...         Aniruddha P. Mayee, Sanjeev Kr. Choudhary for the                    D
                    Respondents.

                         The Judgment of the Court was delivered by

                         DR. B.S. CHAUHAN, J. 1. Leave granted.
                                                                                         E
                          2. This appeal has been filed against the order of the
            '
                    Bombay High Court dated 5.2.2008 rejecting the application
  •' ~              for interim relief while admitting the Writ Petition No. 7245/2006
                    and expediting its hearing against the allotment of land by the
                    respondent No.2 in favour of respondents nos.4 and 5.                F
                          3. The facts and circumstances giving rise to this case are
                    that appellant, a Private Ltd. Company, incorporated under the
                    provisions of Companies' Act 1956, is indulged in
                    manufacturing of press components, moulded components, soft
                    luggage, moulded luggage and other travel goods, tools, moulds       G
       -t
                    jigs, dies fixtures and other engineering goods and carrying its
                    business on a land measuring 4050 sq. meters on plot no.F-
                    18 in the Satpur industrial Estate, Nasik. The appellant
                    submitted an application dated 30.11.2005 (Annexure P-3) for
                    allotment of 8000 sq. yards land frcl'Y'I the adjacent vacant land   hi
    410    SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A   on a prescribed form complying with other requirements. The             .)...'
     said application was rejected by the respondent no.2, the
     Maharashtra Industrial Development Corporation (hereinafter
    referred to as 'Corporation'), a Maharashtra Government
     Undertaking constituted under the provisions of Maharashtra
B    Industrial Development Act, 1961 (for short 1961 Act). In fact,
    the Corporation has powers and duties to make allotment of
     land for industrial purposes. It appears that vide letter dated
     14.3.2005 to the Hon'ble Chief Minister of Maharashtra, the
                                                                           )..
     respondent no.4, Mis. Mahendra & Mahendra Ltd., a leading
c    industrial Company, asked for providing pending dues of
     incentives which were extended to it earlier. In the said letter it
    was also pointed out that the respondent no.4 has entered into
    a collaboration with automobile company Renault and intended •
    to set up a joint venture for manufacturing of car, "The Logan"
    into India and the said respondent was locating the project at           "
D                                                                          }:
    Nasik (Maharashtra) or Zahirabad (Andhra Pradesh) or at any
    other new place in Uttranchal. In the said letter, a demand for
    land measuring 5 to 8 acres for parking facilities at Satpur
    Industrial Estate, Nasik and 3 to 4 acres parking plot outside
    the existing factory gate at Nasik was also included. The
E   Government of Maharashtra vide letter dated 10.6.2005
    promised that the respondent no. 2 - Corporation would provide
    maximum possible vacant land in the existing area at the               ~'
    applicable rates and the Corporation would further facilitate
    acquisition of additional land identified by the Corporation for
F   its project as well as for locating the cluster of industrial units
    (Annexure R.4/R.5). The Government of Maharashtra accorded
    the status of "Mega Project" to the forthcoming project of
    respondent no. 4 known as 'Logan Car Project' at Nasik vide
    ietter dated 11.11.2005 (Annexure R.4/R.6). Respondent no. 4
G   submitted an informal application dated 23.11.2005 to the
    Respondent No. 2 to make the allotment of designated Open
    Space, Plot Nos. 8 and 9, in its favour. The user of land was
    changed from open space to Industrial Area vide resolution
    dated 10.2.2006 and plot was renumbered as 126, instead of
H   Open Space No.9, by the respondent-corporation. The formal
             ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 411'
                      AND ORS. [DR. B.S. CHAUHAN, J.]

   .         application was submitted for that purpose by the respondent       A
       -\.   no. 4 on 1.3.2006 to the respondent no. 2 (Annexure R.4/R.9).
             Respondent No. 2, vide letter dated 27.3.2006 (Annexure R.4/
             R.10), allotted the land measuring 17 acres in favour of the
             respondent no. 4 for a total premium of 7,51, 14,600/- after
             changing the user of the land from vacant space to industrial.     B
             On the same date, namely, 27.3.2006, the respondent no. 4
             was put in possession of the said land and an agreement for
 ..,         licence/lease was executed between respondent no. 2 and
             respondent no. 4 on 3.7.2006. A part of open space was also
       ""    converted as a "parking space" and it was allotted in favour of    c
             respondent no.5 for parking of vehicles.

                   4. The appellant made various representations to the
             Respondent No. 2, Corporation particularly, dated 15.3.2006,
             3.4.2006, 25.8.2006, 3.10.2006 and 10.10.2006, pointing out
,. "'        that rejection of its application and allotment of huge area of · D
       J..
             land in favour of respondent Nos .4 and 5 was discriminatory
             and violative of laws and particularly the statutory requirement
             which provided for allotment of land to the neighbouring unit
             holders. The appellant asked that it may be allotted some part
             of the remaining land from the designated vacant land whose E
             land user has been converted from open space to industrial
             Area. As no order was passed on its representations, the
             appellant filed the writ petition in October 2006 before the High
             Court. However, the Court admitted the writ petition, expedited
             the hearing of the writ petition but rejected the application for F
             interim relief. Hence, this appeal.

                  5. Shri Dushyant Dave, learned senior counsel appearing
             for the appellant has submitted that the application of the
             appellant has been rejected without assigning any reason
                                                                                G
             whatsoever and probably the reason may be that on the date
       +     of passing the order the land was merely a designated vacant
             land and not meant for industrial purpose. However, in order
             to favour the respondent No.4, a big industrial house, the State
             authorities passed the directions to the respondent-Corporation
                                                                                H
    412    SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A   to allot open space after change of user. Application of
    respondent no.4 was processed in haste and all consequential         J'
    orders have been passed within a very short span of time. Land
    has been allotted to Respondent No.4 on the direction of the
    higher authorities, which is not permissible in law. Thus, such
B   a course is violative of Article 14 of the Constitution of India.
    The writ petition filed by the appellant would become infructuous,
    if the respondent no.4 is permitted to develop the allotted land.
    The High Court ought to have granted the interim relief.
    Therefore, the appeal deserves to be allowed.
                                                                             ...
                                                                         >
c         6. On the contrary, Shri Bhaskar P. Gupta, learned senior
   counsel appearing for respondent No.4 has submitted that
  there had been large number of offers by various States to
   Respondent No.4 to set up the industry for the purpose of
  production of cars/jeeps and various incentives were offered,
D particularly, by the States of Madhya Pradesh and Andhra               ;..


  Pradesh. However, as it has several units in Maharashtra, the          ~
  respondent No.4 made application to the Hon'ble the Chief
  Minister for allotment of land and after considering_ the facts, it
  was decided to make the allotment of land at Satpur Industrial
E Estate Nasik, as the appellant was having about four other units
  in close vicinity thereof. It is also submitted by Shri Gupta that
  no law has been violated and the authorities proceeded strictly
  in conformity with the statutory requirements. Respondent no.4
  has already invested a huge amount in the project. Appellant
F did not approach the High Court promptly. Thus, the High Court
  has rightly refused to grant the interim relief. Impugned order
  does not require any interference.

        7. Shri Shyam Divan, learned senior counsel appearing for
  the respondent-Corporation has submitted that when the
G
  application of the appellant was rejected, the land in dispute
  was a designated vacant land and therefore, it could not be            ~
  allotted for any industrial purpose. The land was allotted to the
  respondent no.4 after change of user, considering the
  requirement of respondent No.4 and taking into consideration
H
                   ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 413
                            AND ORS. [DR B.S. CHAUHAN, J.]

                  various other factors, particularly, the development of the city         A
         "'~      keeping in mind that the industry of respondent No.4 would
                  provide job to large number of persons and the people of the
-f                local area would be benefitted otherwise also. Appellant cannot
                  be heard complaining against the allotment in dispute, as it is
    i
                  in consonance with all the statutory requirements. Interim relief        8
    '             could not be granted at a belated stage as the appellant had
                  not filed the petition before the High Court immediately after
         .        allotment of the land. Thus, the interim application has rightly
                  been rejected by the High Court.. The appeal has no merit, thus
             -·   liable to be dismissed.                                                  c
_,,                    8. We have considered the rival submissions made by the
    ~
                  learned counsel for the parties and perused the record.


.   '
         "').
                        9. It is evident from the site plan that a large number of plots
                   had been carved out from the huge area of land,and in between,
                   an open vacant space being No.9 was left. It is also evident
                  from the said site plan that after plot Nos. F-13, F-14 and F-
                                                                                           D


                   15, there was a vacant space and then, plot Nos. F-18, F-19
-l                etc. Thus, there must have been/ plot Nos. F-16 and F-17
~                 between plot nos.F-15 and F-18, at one stage. The land in                E
                  dispute was adjacent to said two plots also. The appellant had
                  demanded the land from Plot Nos. F-16 and F-17. However,
             \-   there is nothing on record to show as to how these two plots
    I'
                  bearing Nos. F-16 and F-17 could disappear from the site plan
                  and become part of Open Space No.9.                                      F
                        10. Application of the appellant has been rejected vide
                  order dated 19.12.2005 without assigning any reason and it
                  cannot be said as to whether the application was rejected
                  merely on the ground that the land in dispute, at that time was
                  a designated vacant land and not meant for the industrial                G

             '-   purpose, thus, its application could not be entertained. On the
i                 contrary, admittedly in the year 2004, a part Plot No. F-17
                  (vacant space) measuring about 500 Sq.Mtrs. had been
                  allotted to BSNL without the change of the user. No explanation
                  could be furnished by the respondents as to under what                   H
                                                                                   ,.._
    414   SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A   circumstances such an allotment was permissible.                    ,._,.
       11. So far as the allotment to respondent No.4 is
  concerned, this had been under the directions of the State
                                                                                   i'
  Government to the Corporatic;m. The Corporation changed the                      .'•
B land user and made the allotment of land to the extent of 17
  acres and the possession had been handed over immediately.
  The license deed had been executed and all the proceedings
  had been taken in close proximity of time. Letter written by
  respondent No.4 dated 14th March, 2005 (Annexure R4/4) to
                                                                             ...
                                                                       ,1.
  the Hon'ble Chief Minister suggests that some other States had
c offered the respondent No.4 various incentives for establishing
  an industrial unit. It is evident from the letter dated 10th June,
                                                                                       "°
  2005 (Annexure R4/5) written by ttie Secretary to the Ministry
  of Industries, Energy and Labour Department, Maharashtra to
  the Respondent No.4 that the State Government was willing to           ,,.
D make various concessions and provide incentives including the                    '+-
                                                                       )t-
  allotment of land at Nasik for establishment of LOGAN cars
  project.                                                                             ;.
                                                                                       ;
       12. The allotment of land is governed by the provisions of                      r-

E 1961   Act, Section 14 of which specifies the functions and
                                                                                       r
  powers of the Corporation and the Corporation has, in general
  power to promote and assist in the rapid and orderly
  establishment growth and development of industries in the State
  of Maharashtra. Section 15 thereof provides for general power
                                                                       +           \




F of the Corporation which includes the power to acquire and hold
  the land and to dispose of the same by executing the lease,
  sale deeds, exchange or otherwise transfer any property.
  Section 31 of the 1961 Act, provides for acquisition and
                                                                                       I'-
  disposal of the land.                                                                I



G      13. The Maharashtra Industrial Development Corporation                           ~
  (Disposal of Land) Regulations, 1975 have been framed to give        ~~

  effect to the provisions of 1961 Act. Regulation 4 provides for
                                                                                       f'
  disposal of the land covered by the lay out prepared by the
  Corporation by public auction or by entertaining individual
H applications. Regulation 6 provides for a particular form to be
                ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA415
                         AND ORS. [DR. B.S. CHAUHAN, J.]
    1'~                                                                              A
                filled up where the allotment is to be made by applications and
                deposit of process fee etc. Regulation 10 provides that the
                Land Committee shall consider the application and pass
                appropriate orders for allotment of land.

                     14. Government of Maharashtra had issued a Circular             B
                dated 25th January, 1994 regarding fixation of rate of industrial
                area in which allotment of plot has to be made by inviting
                tenders. Clause 4 thereof provided for "preferential right" of the
       "        unit holder for having allotment of "neighbouring land" for the
                purpose of factory expansion. It also provides that where there
                are more than one application for allotment, the plot may be
                                                                                     c
                disposed of by adopting the tender process.

                      15. There had been claims and counter claims by the
.    ...         parties. The appellant claimed that it had preferential right for
       -,(      allotment of the part of the vacant land for expansion of its        D   ',




                factory. However, its application has been rejected without
                giving any reason whatsoever, though the law requires giving
                the reasons for passing any order and the allotment in favour
                of respondent No.4 was passed in undue haste showing
                favouritism being a big industrial unit. The right of equality       E
                guaranteed under Article 14 of the Constitution stood violated.
          ~     The application of the appellant had been made prior to the
                application made by respondent No.4. The respondent No.4
                instead of making application to the Corporation started
                negotiations with the Government directly for allotment of land      F
                merely by writing a letter in June, 2005 and on 10th June, 2005
                an understanding was arrived in between the Government of
~
                Maharashtra and respondent No.4 of commissioning of the
                Project at Nasik. The informal application was filed by
                respondent No.4 on 23.11.2005 for making allotment of land
                                                                                     G
           ~-   from Open Space No.9. The application of respondent No.4
                was processed by Land Allotment Committee on 22nd
                December, 2005, wherein the observation was made that it was
                an important industry for the city land and its expansion would
                greatly benefit the industrial growth in Nasik.
                                                                                     H
    416    SUPREME COURT REPORTS {2009] 14 (ADDL.) S.C.R.                              ...


A        16. The user of land in Open Space No.9 was converted            ;.."'
    from Open Space to Industrial Area vide order/resolution dated
    10th February, 2006 and it was re-numbered as Plot No.126.
    The first formal application was submitted by the respondent
    no.4 to the respondent-corporation only on 1.3.2006 and the
a   allotment was made in favour of the respondent No.4 on
    27.3.2006. Respondent no.4 was put in possession on
    27.3.2006 itself. The license agreement was executed by the
    respondent corporation in favour of respondent no.4 on July 3,
                                                                      ~
    2006. The demand of respondent No.4 had not been to the
c   extent the area had been allotted.

         In view of the above facts and circumstances, the sole
    question has arisen as to whether the High Court was justified
    in not granting the interim relief in favour of the appellant?
                                                                          ,.
D      17. Records reveal that the appellant had been bargaining      .~              ""
  with the respondent-Corporation making application after
  application for allotment of land from remaining vacant area and
  approached the Court at some belated stage. Even before the
  High Court the matter remained pending for long before it was
E admitted and the application for interim relief was rejected.
          18. The Regulation 1975 provides for allotment of land by
    public auction or by entertaining individual applications.        +           J
                                                                                  '>.---
                                                                                  \
                                                                                  >---
  Therefore, the question does arise as to-whether without taking
  a decision that land is to be settled by negotiation, the process
F of auction or calling the tender can be dispensed with.

      19. In the instant case the appellant had been asking the                   t
  respondent no.2 to grant the lease of plot nos.F-16 and F-17,
  which had earlier not been the part of the Open Space No.9,
G on the basis of being contiguous and adjacent to the
                                                                      ~
  appellant's existing factory at plot no.F-18. It has been
  canvassed on behalf of the appellant that the action of the
  respondent no.2 is arbitrary and unreasonable and not in
  conformity with the statutory provisions.
H
            ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 417
                     AND ORS. [DR. B.S. CHAUHAN, J.j
.   ~            20. Every action of the State or its instrumentalities should A
            not only be fair, legitimate and above-board but should be
            without any affection or aversion. It should neither be suggestive
            of discrimination nor even apparently give an impression of
            bias, favouritism and nepotism. The decision should be made
            by the application of known principle and rules and in general B
            such decision should be predictable and the citizen should know

-   -.),
            where he is, but if a decision is taken without any principle or
            without any rule, it is unpredictable and such a decision is
            antithesis to the decision taken in accordance with the rule of
            law (vide S.G.Jaisinghani vs. Union of India & ors., AIR 1967 'C
            SC 1427; Haji T.M. Hassan Rawther vs. Kera/a Financial
            Corporation, AIR 1988 SC 157).

                 21. In essence, the action/order of the State or State
""'         instrumentality would stand vitiated if it lacks bona fide as it
        J   would only be a case of colourable exercise of power. The Rule        D
            of Law is the foundation of a democratic society. In l.R. Coelho
            (dead) by LRs vs. Sta_te of Tamil Nadu, AIR 2007 SC 861, the
            Apex Court held as under:-

                 "The State is to deny no one equality before the                 E
                 law........ Economic growth and social equity are the two
    ~            pillars of our Constitution which are linked to the right of
                 an individual (right to equal opportunity), rather than in the
                 abstract. ...... Equality, rule of law, judicial review and
                 separation of powers form parts of the basic structure of        F
                 the Constitution. Each of these concepts are intimately
                 connected. There can be no rule of law, if there is no
                 equality before the law. These would be meaningless if the
                 violation was not subject to the judicial review."

        . Court22.complaining
                   In a case like this, when the applicant approaches the G
                                against the Statutory Authority alleging
            arbitrariness, bias or favouritism, the court, being custodian of
            law, must examine the averments made in the application to
            form a tentative opinion as to whether there is any substance
            in those allegations. Such a course is also required to be            H
    418   SUPREME COURT REPORTS [2009) 14 (ADDL.) S.C.R.


A followed while deciding the application for interim relief.               j/'

        23. Interim order is passed on the basis of prima facie
  findings, which are tentative. Such order is passed as a
  temporary arrangement to preserve the status quo till the matter
  is decided finally, to ensure that the matter does not become
B
  either infructuous or a fait accompli before the final hearing. The
  object of the interlocutory injunction is, to protect the plaintiff
  against injury by violation of his right for which he could not be
                                                                                  ...
                                                                        _\;-
  adequately compensated in damages recoverable in the action
  if the uncertainty were resolved in his favour at the trial. (vide
c Anand Prasad Agarwal/a vs. Tarkeshwar Prasad & Ors. AIR
  2001 SC 2367; and State of Assam vs. Barak Upatyaka D.U.
  Karmachari Sanstha (2009) 5 SCC 694)

        24. Grant of an interim relief in regard to the nature and          ,,,
D extent thereof depends upon the facts and circumstances of            ,)...
  each case as no strait-jacket formula can be laid down. There
  may be a situation wherein the defendant/respondent may use
  the suit property in such a manner that the situation becomes
  irretrievable. In such a fact situation, interim relief should be
E granted   (vide M. Gurudas & Ors. vs. Rasaranjan & Ors. AIR
  2006 SC 3275; and Shridevi & Anr. vs. Mura/idhar & Anr.
  (2001) 14 sec 121.
                                                                        +               ,


       25. Grant of temporary injunction, is governed by three
  basic principles, i.e. prima facie case; balance of convenience;
F and irreparable injury, which are required to be considered in
  a proper perspective in the facts and circumstances of a
  particular case. But it may not be appropriate for any court to
  hold a mini trial at the stage of grant of temporary injunction
  (Vide S.M. Dyechem Ltd. vs. Mis. Cadbury (India) Ltd., AIR
G 2000 SC 2114; and Anand Prasad Agarwal/a (supra).
                                                                        ~


      , 26, In Colgate Palmolive (India) Ltd. vs. Hindustan Lever
  Ltd., AIR 1999 SC 3105, this court observed that the other
  considerations which ought to weigh with the Court hearing the
H application or petition for the grant of injunctions are as below:
       ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 419
                AND ORS. [DR. 8.S. CHAUHAN, J.]

           (i) Extent of damages being an adequate remedy;                    A
.. A
           (ii) Protect the plaintiffs interest for violation of his rights
           though however having regard to the injury that may be
           suffered by the defendants by reason therefor ;

           (iii) The court while dealing with the matter ought not to         B
           ignore the factum of strength of one party's case being
           stronger than the others;

           (iv) No fixed rules or notions ought to be had in the matter
           of grant of injunction but on the facts and circumstances          c
           of each case- the relief being kept flexible;

           (v) The issue is to be looked from the point of view as to
           whether on refusal of the injunction the plaintiff would suffer
           irreparable loss ·and injury keeping in view the strength of
           the parties' case;                                        ··       0

           (vi) Balance of convenience or inconvenience ought to be
           considered as an important requirement even if there is a
           serious question or prima facie case in support of the
           grant;                                                             E

           (vii) Whether the grant or refusal of injunction will adversely
   ~i      affect the interest of general public which can or cannot be
           compensated otherwise."

            27. In Dalpat Kumar&Anr. vs. Prah/ad Singh & Ors., AIR            F
       1993 SC 276, the Supreme Court explained the scope of
       aforesaid material circumstances, but observed as under:-

                  "The phrases 'prima facie case', 'balance of
           convenience' and ' irreparable loss' are not rhetoric G
            phrases for incantation, but words of width and elasticity, .
           to meet myriad situations presented by man's ingenuity in
           given facts and circumstances, but always is hedged with
           sound exercise of judicial discretion to meet the ends of
           justice. The facts rest eloquent and speak for themselves. H
    420     SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.


A         It is well nigh impossible to find from facts prima facie case
                                                                                ;.~
          and balance of convenience."
                                                                                      ~

         28. This Court in Manohar Lal Chopra vs. Rai Bahadur
    Rao Raja Seth Hira Lal, AIR 1962 SC 527 held that the civil
    court has a power to grant interim injunction in exercise of its
B
    inherent jurisdiction even if the case does not fall within the ambit
    of provisions of Order 39 Code of Civil Procedure.

        29. In Deoraj vs. State of Maharashtra & Ors. AIR 2004
                                                                            )t-
   SC 1975, this Court considered a case where the courts below
c had refused the grant of interim relief. While dealing with the
   appeal, the Court observed that ordinarily in exercise of its
  jurisdiction under Art.136 of the Constitution, this Court does
  not interfere with the orders of interim nature passed by the
  High Court. However, this rule of discretion followed in practice
                                                                              ,,,.
D is by way of just self-imposed restriction. An irreparable inji:Jry
  which forcibly tilts the balance in favour of the applicant, may          Jr
  persuade the Court even to grant an interim relief though it may
  amount to granting the final relief itself. The Court held as under:-

                 "The Court would grant such an interim relief only if
E
          satisfied that withholding of it would prick the conscience
          of the court and do violence to the sense of justice,
          resulting in injustice being perpetuated throughout the
          hearing, and at the end the court would not be able to
                                                                            -r
          vindicate the cause of justice."
F
       30. Such a course is permissible when the case of the
  applicant is based on his fundamental rights guaranteed by the
  Constitution of India. (vide All India Anna Dravida Munnetra
  Kazhagam vs. Chief Secretary, Govt. of Tamil Nadu & Ors.
G (2009)  5    sec452)
                                                                            ~
         31. In Bombay Dyeing & Manufacturing Co. Ltd. vs.
    Bombay Environmental Action Group & Ors. (200£) 5 SCC
    61, this Court observed as under:-

H         "The courts, however, have to strike a balance between two
..                 ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 421
                            AND ORS. [DR. B.S. CHAUHAN, J.]

                        extreme positions viz. whether the writ petition would itself      A
      ...A              become infructuous if interim order is refused, on the one
 ..                     hand, and the enormity of losses and hardships which may
                        be suffered by others if an interim order is granted,
                        particularly having regard to the fact that in such an event,
                        the losses sustained by the affected parties thereby may           8
                        not be possible to be redeemed."


     -   -i
                         32. Thus, the law on the issue emerges to the effect that
                   interim injunction should be granted by the Court after
                   considering all the pros and cons of the case in a given set of
                                                                                           c
..                 facts involved therein on the risk and responsibility of the party
                   or, in case he looses the case, he cannot take any advantage
                   of the same. The order can be passed on settled principles
                   taking into account the three basic grounds i.e. prima facie
       ..          case, balance of convenience and irreparable loss. The delay
                   in approaching the Court is of course a good ground for refusal         D
            ·~
                   of interim relief, but in exceptional circumstances, where the
                   case of a party is based on fundamental rights guaranteed
                   under the Constitution and there is an apprehension that suit
                   property may be developed in a manner that it acquires
                   irretrievable situation, the Court may grant relief even at a           E
                   belated stage provided the court is satisfied that the applicant
                   has not been negligent in pursuing the case .
        ...i
                        33. Anything done in undue haste can also be termed as
                   arbitrary and cannot be condoned in law. (Vide Madhya                   F
                   Pradesh Hasta Shi/pa Vikas Nigam Ltd. V. Devendra Kumar
                   Jain & Ors. (1995) 1 SCC 638; and Bahadursinh Lakhubhai
                   Gohi/ vs. Jagdishbhai M. Kamalia & Ors. AIR 2004 SC 1159).

                        34. If the instant case is considered, in the light of the above
                   settled legal propositions and admittedly the whole case of the         G
             /r.   appellant is based on violation of Article 14 of the Constitution
                   as according to the appellant it has been a case of violation of
                   equality clause enshrined in Article 14, the fact$ mentioned
                   hereinabove clearly establish that the Corporation and the
                   Government proceeded in haste while considering the                     H
    422    SUPREME COURT REPORTS [2009] 14 (ADDL.) S.C.R.
                                                                                    l
                                                                                        '

A application of respondent No.4 which tantamount to
  arbitrariness, thus violative of the mandate of Article 14 of the ·      A_'"
  Constitution. Application of the appellant was required to be                    ,,
  disposed of by a speaking and reasoned order. Admittedly, no
  reason was assigned for rejecting the same. There is nothing
8 on   record to show as on what date and under what
  circumstances, Plot nos.F-16 and F-17 stood decarved and
  became part of the Open Space No.9. The respondents could
  not furnish any explanation as in what manner and under what
  circumstances, the Bharat Sanchar Nigam Ltd. has been made             ,,,...
                                                                                  .-
c allotment of land from plot no.F-16, (a part of Open Space
  No.9), without change of user of the land. The respondent no.4
  had not initially asked for 17 acres of land which has been
  allotted to it. There is nothing on record to show as to why the
  land could not be disposed of by auction. All these
D
  circumstances provide for basis to form a tentative opinion that            ,.
  State and its instrumentalities have acted affectionately in the       ~·
  case of respondent no.4.

        35. Undoubtedly, there has been a delay on the part of the
  appellant in approaching the court but we cannot be oblivious
E of the fact that the appellant had been approaching the
  authorities time and again for allotment of the land. Admittedly,
  the entire land had not been developed by the respondent no.4
  till this Court entertained the Special Leave Petition and            -.r·
  directed the parties to maintain status quo with regard to the
F land measuring 2 acres adjacent to the appellant's plot no.F-
  15 vide order dated 21.7.2008. Therefore, it is not only the
  appellant who is to be blamed for the delay. The land had been
  allotted to the respondent no.4 in undue haste and no
  development could take place therein for more than two years
G of taking the possession of the land. In such a fact-situation the
  submission made on behalf of the respondents that interim stay
  cannot be granted at a belated.stage or is preposterous.

         36. In view of above, we are of the considered opinion that
    the appeal deserves to be allowed and is hereby allowed. In
H
    ZENIT MATAPLAST P. LTD. v. STATE OF MAHARASHTRA 423
             AND ORS. [DR. B.S. CHAUHAN, J.]
)

    the facts and circumstances of the case, the interim order A
    passed by this Court on 21.7.2008 shall continue in operation
    till the writ petition is decided by the High Court. The Hon'ble
    High Court is requested to dispose of the writ petition
    expeditiously. Needless to say that any observation made
    herein either on facts or on law shall not adversely effect the ·9
    case of either of the parties, for the reason that the only question
    before this Court has been as to whether the appellant
    deserves to be granted interim protection till his writ petition is
    decided by the High Court.

        The appeal stands disposed of accordingly. No costs.
                                                                      c
    K.K.T.                                 . Appeal disposed of.




-


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "interim relief"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.