Created by Fuzzy Cloud

Patna High Court

Rakesh Narayan SinghversusThe State of Bihar

Decided
Disposal
ALLOWED

Holding

The Court held that the acquisition did not lapse and the State must pay compensation calculated at the current MVR.

Summary

The petitioner, Rakesh Narayan Singh, claimed that his ancestral land of 8.10 bighas was acquired in 1976‑77 for the Gogri‑Narayanpur Embankment under the Land Acquisition Act, 1894, but he never received compensation and the relevant records are missing. The State of Bihar argued that compensation had been paid to a co‑coparcener and that the records were unavailable. The Court examined the legal position under the 2013 Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, particularly Section 24, and held that possession had been taken and therefore the acquisition had not lapsed despite non‑payment of compensation. Relying on Supreme Court precedents, the Court affirmed that the State must pay compensation calculated on the current Minimum Value Register. Consequently, the Court directed the authorities to recompute and disburse the compensation and disposed of the writ petition.

Issues considered

  • Whether the land acquisition proceedings have lapsed under Section 24 of the 2013 Act due to non‑payment of compensation.
  • Whether the petitioner is entitled to compensation calculated on the basis of the Minimum Value Register despite the absence of records.
  • Whether the State is liable to pay compensation for land acquired under the 1894 Act after possession has been taken.

Legislation cited

Subjects

  • land acquisition
  • compensation
  • Section 24
  • Right to Fair Compensation Act
  • Article 300-A
  • Minimum Value Register
  • Gogri Dam
  • writ petition

Judgment

         IN THE HIGH COURT OF JUDICATURE AT PATNA
                    Civil Writ Jurisdiction Case No.15767 of 2022
     ======================================================
     Rakesh Narayan Singh Son of Late Kamal Deo Narayan Singh Resident of
     Village and P.O. and P.S.- Parbatta, District- Khagaria at present R/o 410,
     Pandey Mall Complex, Frazer Road, Patna- 800001.
                                                                ... ... Petitioner/s
                                        Versus
1.    The State of Bihar through Chief Secretary, Government of Bihar, Patna.
2.   The Principal Secretary, Water Resources Department, Government of Bihar,
     Patna.
3.   The Principal Secretary, Land and Revenue, Government of Bihar.
4.   The Director, Land Acquisition Department Government of Bihar, Patna.
5.   The Collector, Khagaria.
6.   The Land Acquisition Officer, Khagaria.
7.   The Circle Officer, Parbatta, Khagaria.
                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s    :        Mr.Rakesh Narayansingh, Advocate
     For the Respondent/s    :        Mr.Vikash Kumar, (SC11)
                                      Mr.Piyush Kumar Pandey, AC to SC 11
     ======================================================
     CORAM: HONOURABLE MR. JUSTICE PURNENDU SINGH
                         ORAL JUDGMENT
      Date : 19-02-2026
                  Heard Mr. Rakesh Narayansingh, learned counsel

      appearing on behalf of the petitioner and Mr. Vikash Kumar,

      learned SC11 for the State.

                     2. The petitioner in paragraph no. 1 of the present

      writ petition has sought inter alia the following relief(s), which

      is reproduced hereinafter:-

                                       “1. That this petition is being filed for issuance
                      of an appropriate writ/writs, directing against the respondents
                      for making payment of compensation amount of 8.10 bighas land
                      of the petitioner which was taken by the respondents way back in
                      1976-77 for construction of Gogri-Narayanpur Embankment in
                      different L.A. Case Nos. 76-77.”



                     3. Learned counsel appearing on behalf of the
Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                           2/9




         petitioner submitted that during the year 1974–75, the

         Government decided to construct an embankment along the

         river Ganga, namely the Gogri–Narayanpur Embankment, for

         which large tracts of land were acquired by the State. In the

         course of construction of the said embankment, the petitioner’s

         ancestral lands appertaining to Mauza Harinmar (Thana No.

         376), Khata Nos. 26 and 39, Khesra Nos. 101 and 102, as well

         as, Mauza Timapur and Karari (Thana No. 379), Khata Nos. 300

         and 164, Khesra Nos. 238 and 240, measuring a total area of 8

         Bigha 10 Kattha, were also acquired after due initiation of land

         acquisition proceedings. Notifications under Sections 4 and 9 of

         the Land Acquisition Act, 1894, were issued by the then

         A.D.M., Munger. He further submitted that the said lands were

         ancestral properties which had fallen to the share of the

         petitioner’s father pursuant to Title Suit No. (25/1949)/

         (41/1951), decided by the Court of Sub-Judge-I, Munger.

         Learned counsel submitted that the order sheet relating to

         payment and the records pertaining to compensation are missing

         and, as reported by the record keeper, no information is

         available regarding payment of compensation to the petitioner

         or his ancestors. He further submitted that the acquisition

         proceedings for construction of the Gogri Dam were initiated in
Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                           3/9




         the year 1977–78 in accordance with the provisions of the Land

         Acquisition Act, 1894 and the petitioner having not received the

         requisite amount of compensation till date, finally filed the

         present writ petition. Learned counsel has further submitted that

         the due compensation payable to the petitioner is required to be

         calculated on the basis of the Minimum Value Register (MVR)

         as determined by the State Government for the vicinity in which

         the acquired land is situated. Learned counsel has also placed

         reliance upon the judgment passed by this Court in CWJC No.

         14927 of 2021.

                        4. Per contra, learned counsel appearing on behalf

         of the State submitted that, in cases where compensation has

         been paid to the respective landholders whose lands were

         acquired for the construction of the Gogri Dam, the records

         relating to such landholders are ordinarily maintained in the

         office concerned. However, in the present case, it has been

         informed to this Court by the Land Acquisition Officer, duly

         affirmed in the affidavit dated 21.02.2023, that the records

         pertaining to Land Acquisition Case no.18 of 1967-68 and Land

         Acquisition Case No.76-77 are not available in the office. It has

         further been submitted that one of the petitioner’s coparcener, in

         respect of his share of the acquired land, has already received
Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                           4/9




         compensation. Information to this effect is contained in

         paragraph 7 of the counter affidavit filed by the Executive

         Engineer.

                        5. At this stage, learned counsel for the petitioner

         objected to the aforesaid submission and contended that, on the

         basis of incomplete and incorrect information, the respondents

         are seeking to deny the petitioner his lawful compensation in

         respect of the acquired land. He submitted that the Land

         Acquisition Officer has furnished erroneous information with

         regard to payment of compensation. Learned counsel further

         submitted that the statement contained in paragraph 7 of the

         counter affidavit cannot be relied upon, as the Land Acquisition

         Officer, in his subsequent affidavit has categorically admitted

         that no records relating to the land acquisition cases concerning

         to the petitioner are available in the office.

                        6. Heard the parties.

                        7. Having considered the rival submissions made

         on behalf of the parties, as well as, the information contained in

         the present writ petition, counter affidavit and supplementary

         counter affidavit and other documents on records, it is an

         admitted position that, in Land Acquisition Case no.18 of 1967-

         68 and Land Acquisition Case No.76-77, the lands of the
Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                           5/9




         petitioner were acquired for the construction of the Gogri Dam.

         It is further not disputed that, after acquisition and taking

         possession of the petitioner’s land, the dam was constructed and

         has been completed. It is also admitted that, although the

         acquisition proceedings were undertaken and possession was

         taken, the records relating to the said land acquisition cases are

         presently not available in the office of the Land Acquisition

         Officer. The petitioner contend that the compensation award is

         pending since more than 50 years, seeking payment in terms of

         the applicable Government Resolution. The legal position

         governing such issues is no longer res integra and stands

         authoritatively settled by the Apex Court in the case of Indore

         Development Authority vs. Manoharlal and Others, reported in

         AIR 2020 SC 1496 which is reproduced hereinafter:

                                 “366. In view of the aforesaid discussion, we answer the
                                 questions as under:
                                 366.1. Under the provisions of Section 24(1)(a) in case
                                 the award is not made as on 1-1-2014, the date of
                                 commencement of the 2013 Act, there is no lapse of
                                 proceedings. Compensation has to be determined under
                                 the provisions of the 2013 Act.
                                 366.2. In case the award has been passed within the
                                 window period of five years excluding the period covered
                                 by an interim order of the court, then proceedings shall
                                 continue as provided under Section 24(1)(b) of the 2013
                                 Act under the 1894 Act as if it has not been repealed.
                                 366.3. The word “or” used in Section 24(2) between
                                 possession and compensation has to be read as “nor” or
                                 as “and”. The deemed lapse of land acquisition
                                 proceedings under Section 24(2) of the 2013 Act takes
                                 place where due to inaction of authorities for five years
                                 or more prior to commencement of the said Act, the
                                 possession of land has not been taken nor compensation
                                 has been paid. In other words, in case possession has
                                 been taken, compensation has not been paid then there is
Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                           6/9




                                 no lapse. Similarly, if compensation has been paid,
                                 possession has not been taken then there is no lapse.
                                 366.4. The expression “paid” in the main part of Section
                                 24(2) of the 2013 Act does not include a deposit of
                                 compensation in court. The consequence of non-deposit
                                 is provided in the proviso to Section 24(2) in case it has
                                 not been deposited with respect to majority of
                                 landholdings then all beneficiaries (landowners) as on
                                 the date of notification for land acquisition under Section
                                 4 of the 1894 Act shall be entitled to compensation in
                                 accordance with the provisions of the 2013 Act. In case
                                 the obligation under Section 31 of the Land Acquisition
                                 Act, 1894 has not been fulfilled, interest under Section 34
                                 of the said Act can be granted. Non-deposit of
                                 compensation (in court) does not result in the lapse of
                                 land acquisition proceedings. In case of non-deposit with
                                 respect to the majority of holdings for five years or more,
                                 compensation under the 2013 Act has to be paid to the
                                 “landowners” as on the date of notification for land
                                 acquisition under Section 4 of the 1894 Act.
                                 366.5. In case a person has been tendered the
                                 compensation as provided under Section 31(1) of the
                                 1894 Act, it is not open to him to claim that acquisition
                                 has lapsed under Section 24(2) due to non-payment or
                                 non-deposit of compensation in court. The obligation to
                                 pay is complete by tendering the amount under Section
                                 31(1). The landowners who had refused to accept
                                 compensation or who sought reference for higher
                                 compensation, cannot claim that the acquisition
                                 proceedings had lapsed under Section 24(2) of the 2013
                                 Act.
                                 366.6. The proviso to Section 24(2) of the 2013 Act is to
                                 be treated as part of Section 24(2), not part of Section
                                 24(1)(b).
                                 366.7. The mode of taking possession under the 1894 Act
                                 and as contemplated under Section 24(2) is by drawing
                                 of inquest report/memorandum. Once award has been
                                 passed on taking possession under Section 16 of the 1894
                                 Act, the land vests in State there is no divesting provided
                                 under Section 24(2) of the 2013 Act, as once possession
                                 has been taken there is no lapse under Section 24(2).
                                 366.8. The provisions of Section 24(2) providing for a
                                 deemed lapse of proceedings are applicable in case
                                 authorities have failed due to their inaction to take
                                 possession and pay compensation for five years or more
                                 before the 2013 Act came into force, in a proceeding for
                                 land acquisition pending with the authority concerned as
                                 on 1-1-2014. The period of subsistence of interim orders
                                 passed by court has to be excluded in the computation of
                                 five years.
                                 366.9. Section 24(2) of the 2013 Act does not give rise to
                                 new cause of action to question the legality of concluded
                                 proceedings of land acquisition. Section 24 applies to a
                                 proceeding pending on the date of enforcement of the
                                 2013 Act i.e. 1-1-2014. It does not revive stale and time-
                                 barred claims and does not reopen concluded
                                 proceedings nor allow landowners to question the
Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                           7/9




                                 legality of mode of taking possession to reopen
                                 proceedings or mode of deposit of compensation in the
                                 treasury instead of court to invalidate acquisition.”



                          8. It is also to be taken note of that Article 300-A

         of the Constitution of India, which tends to safeguard the

         invaluable right to property.

                                 “300-A. Persons not to be deprived of property
                                 save by authority of law
                                 No person shall be deprived of his property save by
                                 authority of law.”
                         9. The State cannot disposes a citizen of his

         property except in accordance with law and procedure

         prescribed. The obligation to pay compensation is not

         expressively included in Article 300-A of the Constitution of

         India can be inferred in that Article. The law in this regard is

         well settled by the Apex Court in case of Vidaya Devi Vs. The

         State of Himachal Pradesh & Ors. reported in 2020(2) SCC

         569, I find it proper to quote Para-12.1 and 12.2 of the said

         judgment, which are inter alia reproduced hereinafter;

                                 “12.1. The appellant was forcibly expropriated of her
                                 property in 1967, when the right to property was a
                                 fundamental right guaranteed by Article 31 in Part III of
                                 the Constitution. Article 31 guaranteed the right to
                                 private property [State of W.B. v. Subodh Gopal Bose,
                                 (1953) 2 SCC 688 , which could not be deprived without
                                 due process of law and upon just and fair compensation.
                                 12.2. The right to property ceased to be a fundamental
                                 right by the Constitution (Forty-Fourth Amendment) Act,
                                 1978, however, it continued to be a human right
                                 [Tukaram Kana Joshi v. MIDC, (2013) 1 SCC 353 in a
                                 welfare State, and a constitutional right under Article
                                 300-A of the Constitution. Article 300-A provides that no
                                 person shall be deprived of his property save by
                                 authority of law. The State cannot dispossess a citizen of
Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                            8/9




                                 his property except in accordance with the procedure
                                 established by law. The obligation to pay compensation,
                                 though not expressly included in Article 300-A, can be
                                 inferred in that Article. [K.T. Plantation (P) Ltd. v. State
                                 of Karnataka, (2011) 9 SCC 1”



                     10. The above proposition of law has again been

         reiterated by the Apex Court in the case of Dharnidhar Mishra

         (D) and Another vs. State of Bihar and Others, in Civil Appeal

         No. 6351 of 2024, reported in (2024) 10 Supreme Court Cases

         605, is relevant. The paragraph is reproduced as under:–

                                     “ 16. The right to property ceased to be a
                         fundamental right by the Constitution (Forty-fourth
                         Amendment) Act, 1978, however, it continued to be a human
                         right in a welfare State, and a constitutional right under
                         Article 300-A of the Constitution. Article 300-A provides
                         that no person shall be deprived of his property save by
                         authority of law. The State cannot dispossess a citizen of his
                         property except in accordance with the procedure
                         established by law. The obligation to pay compensation,
                         though not expressly included in Article 300-A, can be
                         inferred in that Article. [See: K.T. Plantation (P) Ltd. v.
                         State of Karnataka [K.T. Plantation (P) Ltd. v. State of
                         Karnataka, (2011) 9 SCC 1.”


                     11. In such circumstances, when the question of right

         to property as per the provision of Article 300 A of the

         Constitution of India comes to the knowledge of this Court and

         also in view of the recorded evidence and the established MVR

         of the area, in which vicinity, petitioner’s land has been

         acquired, this Court has no alternative than to direct the

         concerned authority to give due regard to the same and

         recalculate the amount of compensation at the current rate of
             Patna High Court CWJC No.15767 of 2022 dt.19-02-2026
                                                        9/9




                      MVR so that the petitioner should not be made to suffer

                      financially in any manner. The claim of the petitioner is

                      supported by the judgment of the Apex Court in the case of

                      Indore Development Authority (Supra) and the amendment

                      brought in the Right to Fair Compensation and Transparency

                      in Land Acquisition, Rehabilitation and Resettlement Act,

                      2013 in the year 2018. Admittedly, in the present case, the

                      petitioner has not received the amount of compensation till date.

                                     12. The writ petition is, accordingly, disposed of.


                                                              (Purnendu Singh, J)

Ashishsingh/-
AFR/NAFR                NAFR
CAV DATE                NA
Uploading Date          24.02.2026
Transmission Date       NA


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.