Allahabad High Court
RAMDEVversusSTATE OF U.P. AND 7 OTHERS
- Decided
- Bench
- ANISH KUMAR GUPTA
Holding
The Court directed the Sub‑Divisional Magistrate to reinstall the pillars within two months, notwithstanding the water‑logging issue.
Summary
The petitioner sought re‑installation of demarcation pillars that had been installed under an order passed pursuant to Section 24 of the Uttar Pradesh Revenue Code on 06‑06‑2022, but were later removed by private individuals, leading to an FIR and a final report. The petitioner applied to the Sub‑Divisional Magistrate, Soraon, for reinstatement of the pillars. The magistrate indicated that the land was water‑logged and that the water needed to be subsidized before any re‑installation could occur. The High Court examined whether the water‑logging justified a delay and found that the magistrate should act to reinstall the pillars. Consequently, the Court disposed of the petition, directing the Sub‑Divisional Magistrate to complete the re‑installation within two months of the certified copy of the order.
Issues considered
- Whether the Sub‑Divisional Magistrate is obligated to reinstall the demarcation pillars despite the presence of water‑logging on the land.
- Whether the delay caused by water‑logging is a valid ground to defer compliance with the order under Section 24 of the U.P. Revenue Code.
Legislation cited
- Uttar Pradesh Revenue Code — s. 24
Subjects
- demarcation
- pillars
- Section 24
- U.P. Revenue Code
- water logging
- Sub‑Divisional Magistrate
- writ petition
Judgment
HIGH COURT OF JUDICATURE AT ALLAHABAD
WRIT - C No. - 22407 of 2026
Ramdev
.....Petitioner(s)
Versus
State Of U.P. And 7 Others
.....Respondent(s)
Counsel for Petitioner(s) : Dan Bahadur
Counsel for Respondent(s) : Azad Rai, C.S.C.
Court No. - 34
(Sl.No.342) Transfer of Court No.37
HON'BLE ANISH KUMAR GUPTA, J.
1. Heard Sri Dan Bahadur, learned counsel for the petitioner, Sri
Dhananjay Singh, learned Standing Counsel for the State and Sri Azad
Rai, learned counsel for respondent no.3, Gaon Sabha.
2. The Grievance of the petitioner herein is that on an application filed by
one Ram Kailash and others under Section 24 of the U.P Revnue Code.
On 08.04.2020, an order was passed and in pursuant thereto the
installation of pillars was done on 06.06.2022. Thereafter, it is alleged
that some private persons have removed the demarcation marks and
pillars so installed regarding which an FIR was also lodged on 05.07.2022
in which the final report has been submitted in the court concerned on
01.01.2023. Thereafter, the petitioner filed an application before the Sub-
Divisional Magistrate, Soraon, Prayagraj to re-install the pillars after due
demarcation.
3. In the instructions received by the Sub-Divisional Magistrate, it is
stated that at present there is water logging on the land in question and
after the water is subsidized, necessary exercise of re-installation of the
pillars shall be done.
4. In such view of the matter, the instant petition is disposed of with a
direction to the respondent no.2, Sub-Divisional Magistrate, Soraon,
Prayagraj to do the needful in the matter within a period of two months
WRIC No. 22407 of 2026
2
from the date of production of certified copy of this order.
(Anish Kumar Gupta,J.)
September 11, 2026