Created byFuzzy Cloud

Supreme Court of India

BENGALURU DEVELOPMENT AUTHORITYversusMR. SUDHAKAR HEGDE & ORS.

Citation
2020 INSC 303
Decided
17 March 2020
Disposal
Disposed off

Holding

The Supreme Court held that the PRR project is an expressway within the ambit of the 2006 EIA Notification, the BDA failed to comply with the procedural requirements, and the SEAC’s recommendation of an EC was legally untenable.

Summary

The Bengaluru Development Authority (BDA) sought an environmental clearance (EC) for its Peripheral Ring Road (PRR) project, which was later quashed by the National Green Tribunal (NGT) on the ground that the primary data used in the Environmental Impact Assessment (EIA) report was over three years old and the Terms of Reference (ToR) had expired. The Supreme Court examined whether the PRR project fell within the scope of the 2006 EIA Notification, whether the BDA complied with the procedural requirements, and whether the State Expert Appraisal Committee (SEAC) acted lawfully in recommending the EC. The Court found a failure of due process: the ToR was expired, the primary data were outdated, the SEAC did not provide adequate reasons for its recommendation, and there were material contradictions regarding forest land and tree felling. Consequently, the Court upheld the NGT’s direction and ordered the BDA to conduct a fresh rapid EIA, engage an accredited consultant, obtain all requisite clearances, and submit the new report for SEAC’s assessment before any EC can be granted. The appeal was dismissed with detailed directions under Article 142 of the Constitution.

Issues considered

  • Whether the PRR project commenced before the coming into force of the 2006 EIA Notification and thus escaped its applicability.
  • Whether the PRR project qualifies as a ‘highway/expressway’ within para 7(f) of the Schedule to the 2006 Notification, obligating the proponent to obtain prior EC.
  • Whether the BDA complied with the procedural requirements of the 2006 Notification, including validity of the ToR and freshness of primary data.
  • Whether the SEAC fulfilled its statutory duty to assess the EIA report, provide reasons for its recommendation, and act within the limits of the ToR.

Legislation cited

Subjects

environmental clearanceEIAPeripheral Ring Roadforest clearanceTerms of Referencerapid EIASEACSEIAAsustainable developmentprocedural due processexpresswayhighwayBengaluru Development Authority ActEnvironment (Protection) Act

Judgment

                       [2020] 5 S.C.R. 755                            755


         BENGALURU DEVELOPMENT AUTHORITY                              A
                                 v.
               MR. SUDHAKAR HEGDE & ORS.
                  (Civil Appeal No. 2566 of 2019)
                         MARCH 17, 2020                               B

        [DR. DHANANJAYA Y CHANDRACHUD AND
                 HEMANT GUPTA, JJ.]
       Environment (Protection) Act, 1986 – Environment (Protection)
Rules, 1986 – Bangalore Development Authority Act, 1976 – C
Environment Impact Assessment Notification 2006 – Peripheral Ring
Road Project – National Green Tribunal quashed the Environmental
clearance granted to the appellant for the said PRR project – NGT
was of the view that the primary data upon which the Environment
Impact Assessment report was based was collected more than 3 years
prior to its submission to the State Environment Impact Assessment D
Authority – There was substantial delay in the preparation of the
EIA report – Accordingly, the NGT directed the appellant to conduct
a fresh rapid EIA and clarified the project proponent not to proceed
on the basis of the impugned Environmental clearance – On appeal,
held: In the instant case, there was failure of due process E
commencing from issuance of the Terms of Reference and leading
to the grant of the Environmental clearance for the PRR Project –
The appellant, as project proponent sought to rely on an expired
Terms of Reference and proceeded to prepare the final EIA report
on the basis of outdated primary data – At the same time, the process
leading to the grant of the Environmental clearance was replete F
with contradictions on the existence of forest land to be diverted
for the Project as well as the number of trees required to be felled –
The State Expert Appraisal Committee, as an expert body abdicated
its role and function by relying solely on the responses submitted to
it by the appellant and failing to comply with its obligations under G
the OMs issued by the MOEF-CC from time to time – The State Expert
Appraisal Committee failed in its fundamental duty mandated to do
under the 2006 Notification – Therefore, inter-alia, following
directions issued: (i) The appellant directed to conduct a fresh rapid
EIA for the proposed PRR project; (ii) The appellant, for the purpose
                                                                       H
                                 755
756            SUPREME COURT REPORTS                        [2020] 5 S.C.R.


A     of conducting the rapid EIA, hired a sector-specific accredited EIA
      Consultant; (iii) Appellant to ensure the requisite clearances under
      various enactments submitted to the State Expert Appraisal Committee
      prior to the consideration by it of the information submitted by the
      appellant in accordance with the OMs issued by the MOEF-CC
B     from time to time; (iv) State Expert Appraisal Committee shall
      thereafter assess the rapid EIA report in accordance with the role
      assigned to it under the 2006 Notification and if it is of the opinion
      that the appellant has complied with the 2006 Notification as well
      as the directions issued by the Supreme Court, only then shall it
      recommend to the State Environment Impact Assessment Authority
C     the grant of Environmental clearance for the proposed project –
      The order of the NGT directing the appellant to conduct a rapid
      EIA is upheld.
            Disposing of the appeal, the Court
             HELD: 1. The protection of the environment is premised
D
      not only on the active role of courts, but also on robust
      institutional frameworks within which every stakeholder complies
      with its duty to ensure sustainable development. A framework of
      environmental governance committed to the rule of law requires
      a regime which has effective, accountable and transparent
E     institutions. Equally important is responsive, inclusive,
      participatory and representative decision making. Environmental
      governance is founded on the rule of law and emerges from the
      values of our Constitution. Where the health of the environment
      is key to preserving the right to life as a constitutionally recognized
      value under Article 21 of the Constitution, proper structures for
F     environmental decision making find expression in the guarantee
      against arbitrary action and the affirmative duty of fair treatment
      under Article 14 of the Constitution. Sustainable development is
      premised not merely on the redressal of the failure of democratic
      institutions in the protection of the environment, but ensuring
G     that such failures do not take place. [Para 79][809-F-H; 810-A-
      B]
            2. In the present case, there has been a failure of due
      process commencing from issuance of the Terms of Reference
      and leading to the grant of the Environmental Clearance for the
H     Peripheral Ring Road project. The appellant, as project proponent
           BENGALURU DEVELOPMENT AUTHORITY v.                           757
                  MR. SUDHAKAR HEGDE

sought to rely on an expired ToR and proceeded to prepare the           A
final Environment Impact Assessment report on the basis of
outdated primary data. At the same time, the process leading to
the grant of the EC was replete with contradictions on the
existence of forest land to be diverted for the project as well as
the number of trees required to be felled. [Para 80][810-B-C]
                                                                        B
      3. The State Expert Appraisal Committee, as an expert body
abdicated its role and function by relying solely on the responses
submitted to it by the appellant and failing to comply with its
obligations under the OMs issued by the MoEF-CC from time
to time. In failing to provide adequate reasons for its
recommendation to the State Environment Impact Assessment               C
Authority for the grant of an EC, it failed in its fundamental duty
of ensuring both the application of mind to the materials
presented to it as well as the furnishing of reasons which it is
mandated to do under the 2006 Notification. [Para 81][810-D-E]
      4. In this view of the matter, neither the process of decision    D
making nor the decision itself can pass legal muster. Equally,
this Court must bear in mind the need to balance the development
of infrastructure and the environment. This Court is of the view
that while the need for a road project is factored into the decision-
making calculus, equal emphasis should be placed on the                 E
prevailing state of the environment. The appeal which was filed
before the NGT in 2015, was finally disposed of at a belated stage
only in 2019. [Para 82][810-E-F]
     5. Bearing in mind the need to bring about a requisite
balance, this Court proposes to issue the following directions          F
under Article 142 of the Constitution:
      (i) The appellant is directed to conduct a fresh rapid EIA
for the proposed PRR project;
      (ii) The appellant shall, for the purpose of conducting the
rapid EIA, hire a sector-specific accredited EIA consultant;            G
      (iii) The appellant shall have due regard to the various
deficiencies noted in the present judgment as well as ensure that


                                                                        H
758            SUPREME COURT REPORTS                      [2020] 5 S.C.R.


A     additional precautions are taken to account for the prevailing
      state of the environment;
            (iv) The appellant shall ensure that the requisite clearances
      under various enactments have been obtained and submitted to
      the SEAC prior to the consideration by it of the information
B     submitted by the appellant in accordance with the OMs issued
      by the MoEF-CC from time to time;
             (v) The SEAC shall thereafter assess the rapid EIA report
      and other information submitted to it by the appellant in
      accordance with the role assigned to it under the 2006 Notification.
C     If it is of the opinion that the appellant has complied with the
      2006 Notification as well as the directions issued by this Court,
      only then shall it recommend to the SEIAA the grant of EC for
      the proposed project. The SEAC and the SEIAA would lay down
      appropriate conditions concerning air, water, noise, land, biological
      and socioeconomic environment and other conditions it deems
D     fit; and
            (vi) The appellant shall consult the requisite authority to
      ensure that no potential damage is caused by the project to the
      petroleum pipelines over which the proposed road may be
      constructed. [Para 83][810-D-H; 811-A-E]
E
            State Bank of India v. V. Ramakrishnan (2018) 17 SCC
            394 : [2018] 10 SCR 974; Lafarge Umiam Mining
            Private Limited v. Union of India (2011) 7 SCC 338 :
            [2011] 7 SCR 954 – relied on.

F           Shreeranganathan K P v. Union of India 2014 ALL (I)
            NGT Reporter (1) (SZ) 1 – referred to.
                             Case Law Reference
      [2018 10 SCR 974               relied on               Para 28
      [2011] 7 SCR 954               relied on               Para 75
G
            CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2566
      of 2019.
            From the Judgment and Order dated 08.02.2019 of the National
      Green Tribunal, Principal Bench, New Delhi in Appeal No. 27 of 2015.
H
             BENGALURU DEVELOPMENT AUTHORITY v.                             759
                    MR. SUDHAKAR HEGDE

       Shyam Divan, Sr. Adv., Anand Sanjay M. Nuli, Dharm Singh,            A
Suraj Kaushik, Nanda Kumar K.B., Bhavratan, M/S. Nuli & Nuli, Advs.
for the Appellant.
      Nikhil Nayyar, Sr. Adv., T. V. S. Raghavendra Sreyas, Mrs. Gayatri
Gulati Sreyas, Advs. for the Respondent.
        The Judgment of the Court was delivered by                          B

        DR. DHANANJAYA Y CHANDRACHUD, J.
        Index
        A Introduction
                                                                            C
        B Submissions
        C Issues
        D Date of commencement of the PRR project
        E Applicability of the EIA Notification 2006
                                                                            D
        F Compliance with the procedure under the EIA Notification 2006
        G Deficiencies in the EIA report
          G.1 Accreditation of the EIA consultant
          G.2 Forestland
                                                                            E
          G.3 Trees
          G.4 Pipeline
        H Appraisal by the SEAC
        I Courts and the environment                                        F
        J Directions
        A Introduction
       1. The present appeal arises from a judgment of the Principal
Bench of the National Green Tribunal1 dated 8 February 2019 quashing
                                                                            G
the Environmental Clearance2 granted to the appellant for the development
of an eight lane Peripheral Ring Road3connecting Tumkur Road to Hosur
Road and totaling a length of 65 kilometers. The NGT was of the view
1 NGT
2 EC
3 PRR
                                                                            H
760             SUPREME COURT REPORTS                           [2020] 5 S.C.R.


A     that the primary data upon which the Environment Impact Assessment4
      report was based was collected more than three years prior to its
      submission to the State Environment Impact Assessment Authority5. The
      NGT was of the view that it was not necessary to adjudicate upon the
      other contentions that were urged in support of quashing the EC as
      there was a substantial delay in the preparation of the EIA report.
B
      Accordingly, the NGT directed the appellant to conduct a fresh rapid
      EIA and clarified that the “project proponent will not proceed on the
      basis of the impugned Environmental Clearance.” Assailing the order of
      the NGT, the appellant, as project proponent, is in appeal before this
      Court.
C            2. In a bid to address the growing need for efficient
      commutation,address traffic congestion and connect the Bangalore-
      Mysore Infrastructure Corridor (NICE road) with more access points,
      the appellant formulated the PRR project scheme in 2005. A preliminary
      notification was issued on 27 May 2005 under Section 17(1) and (3) of
D     the Bangalore Development Authority Act 19766 to acquire certain land
      for the execution of the project. The stated purpose of the project was:
            “1) To decongest the traffic in Bangalore City;
            2) To cater intercity connectivity and intercity traffic;
            3) To reduce pollution in the city;
E
            4) To reduce heavy vehicles traffic i.e., Lorry and Trucks; and
            5) To decongest the traffic on outer ring road.”
             3. Another preliminary notification was issued on 23 September
      2005 which concerned the realignment of the proposed road project. A
F     final notification under Section 19(1) of the BDA Act was issued on 29
      June 2007 for the acquisition of the proposed land. The notifications
      were challenged before the High Court of Karnataka in Writ proceedings7
      on the ground that the appellant had no authority to issue the notifications
      and acquire land for the proposed PRR project. By a judgment dated 22
      July 2014, the High Court dismissed the writ petition on the ground that
G     the appellant was authorised under the BDA Act to acquire the land for
      the project in question. The Writ Appeal against this was dismissed on
      the ground of default on 9 February 2017.
      4 EIA
      5 SEIAA
      6 BDA Act

H     7 WP No. 4550/2008
    BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                           761
      HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

       4. The appellant, as project proponent, submitted an application8to    A
the SEIAA on 10 September 2009 under the EIA Notification 20069
seeking an EC for the PRR. The Terms of Reference10 were prepared
by the State Expert Appraisal Committee 11on 21 November 2009.
Primary data was collected between December 2009 and February 2010.
The final EIA report was placed before the SEAC and the SEIAA in
                                                                              B
October 2014. An EC was granted by the SEIAA on 20 November
2014. The first and second respondents filed an appeal to the NGT
challenging the grant of the EC. The NGT, by an interim order dated 15
April 2015 granted an interim stay of the EC. The relevant portion of the
order reads:
      “Pointing to the EIA report which was placed before the 1st             C
      respondent, the counsel for the appellant would submit that the
      first part of the report would clearly indicate that if the road was
      constructed, it would pass through the Reserve Forest and the
      later part it would submit that the Forest clearance is not necessary
      which by itself would suffice to reject the recommendation. The         D
      EIA report would clearly indicate that if the proposed road has
      got to be constructed approximately 200 trees were to be cut
      which is thoroughly inconsistent to the report given by the
      Horticulture and Forest Department. According to their report, it
      would require felling of 16,685 trees. Added further by the counsel
      for the appellant that if the proposed road is allowed to be            E
      constructed it would be above the underground pipe line already
      laid for transporting petroleum from Mangalore to Bangalore and
      if any leakages happens in future it would bring forth serious
      consequence…
      There exists a prima facie case in favour of the appellant for          F
      granting an interim order of stay…”
       The NGT noted the discrepancy between the submission of the
appellant and the existence of a reserved forest through which the
proposed road was to pass. The NGT recorded that while the EIA report
stated that only 200 trees would be cut for the proposed project, the         G


8  No. BDA/EM/TA3/PRR/EIA/T333/09-10
9  2006 notification
10 ToR

11 SEAC
                                                                              H
762                SUPREME COURT REPORTS                         [2020] 5 S.C.R.


A     report given by the Horticulture and Forest Department indicated that
      about 16,685 trees would be required to be felled for the proposed project.
      By its final order dated 8 February 2019, the NGT stayed the operation
      of the EC granted by the SEIAA. The relevant portion of the order
      reads:
B            “The Environmental Clearance was granted on 20.11.2014. Thus,
             the primary data was more than three years prior to the EIA
             report. There are omissions in the EIA report with regard to data
             of forests land as well as the provisions of revised Master Plan,
             2015 prepared by the BDA. Thippagondanahalli Reservoir (TGR)
             catchment area has been suppressed in the EIA report. Green
C            cover particulars have been overlooked. Further objection is that
             there is proximity of the area to the petroleum pipelines and land
             earmarked for petroleum pipelines overlaps the project. According
             to the appellant, Stage-I Forest Clearance was not obtained as
             required…
D            It is not necessary to adjudicate on the contentions raised, having
             regard to the patent fact that there was substantial delay in EIA
             and a period of almost five years passed even thereafter. This
             Tribunal, vide order dated 15.04.2015, considered the issue…It
             will, thus, be in the interest of justice that a fresh rapid EIA is
E            conducted. If the project is found viable after incorporating due
             abatement measures, including the suggestions of the appellant,
             the same can be taken up without further delay…”
             The NGT directed the appellant to conduct a rapid EIA. It was
      further directed that if the project is found to be viable after incorporating
F     abatement measures, “the same can betaken up without delay”. Notice
      was issued by this Court on 15 March 2019.
             B Submissions
            5. Assailing the order of the NGT, Mr. Shyam Divan, learned
      Senior Counsel appearing on behalf of the appellant contended that:
G
             (i)    The 2006 Notification obliges a project proponent to seek
                    prior EC only for projects that are listed in the Schedule to
                    the Notification. Para 7(f) of the Schedule includes only those
                    projects that are either National or State Highways. The PRR
                    project does not fall within the ambit of either the National
H                   Highways Act 1956 or the Karnataka Highways Act 1964.
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                              763
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

            Consequently, the appellant was under no obligation under          A
            the 2006 Notification to seek a prior EC for the PRR project;
      (ii) The 2006 Notification came into effect from the date of its
           publication in the Official Gazette on 14 September 2006. It
           is prospective in its application. The PRR project commenced
           on 23 September 2005 upon the issuance of the preliminary           B
           notification under the BDA Act and as such, on the date of
           the coming into force of the 2006 notification, no obligation
           existed on the appellant to seek a prior EC for the PRR
           project;
      (iii) The appellant executed the EIA process and applied for the         C
            grant of an EC out of abundant caution;
      (iv) The first respondent has challenged the grant of the EC by
           the SEIAA only because his appeal before the Karnataka
           High Court challenging the acquisition of land for the PRR
           project was unsuccessful. The present proceedings are               D
           merely a method of delaying the acquisition proceedings;
      (v) The SEAC acceded to the request of the appellant to not
          forward to the SEIAA a recommendation for the closure of
          the proposal. The SEAC recommended to the SEIAA the
          grant of the EC to the project in question after due                 E
          consideration of the EIA report in its 121st meeting between
          11 and 18 November 2014; and
      (vi) All objections raised by the first respondent concerning
           forests, the cutting of trees and the protection of the reservoir
           were adequately addressed in the EIA report submitted in            F
           2014, on which basis an EC was granted to the PRR project.
      6. On the other hand, Mr. Nikhil Nayyar, learned Senior Counsel
appearing on behalf of the first respondent contended:
      (i)   The term ‘highway’ or ‘expressway’ used in the 2006
            Notification must be given a wide interpretation and not be        G
            restricted to the issuance of a notification under central or
            state enactments;
      (ii) Both the National Highway Act 1956 and the Karnataka
           State Highway Act 1964 concern the acquisition of land, its
           development and permissions concerning the collection of            H
764                SUPREME COURT REPORTS                          [2020] 5 S.C.R.


A                    toll/fee. The statutory framework does not envisage the wide
                     definition to be attributed to the term ‘highway’ in matters
                     concerning the protection of the environment;
                (iii) The appellant itself admitted in its EIA report that the PRR
                      project is a category ‘B’ project falling under the purview of
B                     para 7(f) of the Schedule under the 2006 Notification;
                (iv) The primary data for the PRR project was collected between
                     December 2009 and February 2010. The EAC conducted
                     the appraisal process after a substantial delay of over four
                     years in the year 2014. This defeats the purpose for which
C                    ToRs are issued as the state of the environment is constantly
                     changing;
                (v) An OM dated 22 March 2010 issued by the Ministry of
                    Environment and Forests12 stipulates that EIA reports for
                    projects where the ToRs have been granted prior to the date
D                   of the coming into force of the OM must be based on primary
                    data that is not older than three years. The OM further
                    stipulates that a ToR is valid only for a period of four years.
                    The EIA report was prepared after the expiry of the ToR
                    and is legally unsustainable;
E               (vi) The SEIAA decided to close the file for the PRR project on
                     17 May 2013, which decision was communicated to the
                     appellant on 25 July 2013. A party aggrieved by the action of
                     the SEIAA may only file an appeal under Section 16 of the
                     NGT Act and the SEIAA was not authorised to reopen the
                     file on the request of the appellant;
F
                (vii) There was no collection of additional data in the year 2014.
                      The report which is styled as a rapid EIA report in the year
                      2014 is nothing but the final EIA report under the 2006
                      Notification which was prepared after the public consultation
                      process was conducted in February 2014;and
G
                (viii) There are significant omissions in the EIA report concerning
                       forest land, green cover, number of trees required to be cut,
                       the catchment area in the Thippagondanahalli Reservoir and


H     12   MoEF, later renamed as MoEFCC in 2014
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                            765
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

            proximity of the PRR project to the petroleum pipelines          A
            underneath. Material concealment by the project proponent
            invalidates the EC which was granted by the SEIAA.

      7. The rival submissions fall for our consideration.

      C Issues                                                               B

      8. Essentially this Court is required to decide:

       (i) Whether the PRR project commenced prior to the coming into
force of the 2006 Notification;
                                                                             C
      (ii) Whether the PRR project falls within the scope of para 7(f) of
the Schedule to the 2006 Notification obliging the project proponent to
seek aprior EC; and

       (iii) Whether the appellant has complied with the conditions
stipulated in the 2006 Notification and the OMs issued by the MoEF-CC        D
from time to time.

      D Date of commencement of the PRR project

       9. This Court is required to adjudicate whether it is the issuance
of a preliminary notification under Section 17 of the BDA Act or a final     E
notification under Section 19 of the BDA Act that constituted the
identification of the proposed site for the project and marked its
commencement for the purposes of the 2006 Notification.

       10. On 27 January 1994, the MoEF, in exercise of the powers
conferred by sub-section (1) and clause (v) of sub-section (2) of Section    F
3 of the Environment (Protection) Act 1986 Act read with clause (d) of
sub-rule 3 of rule 5 of the Environment (Protection) Rules, 1986, issued
a notification imposing restrictions and prohibitions on the expansion and
modernisation of any activity or a new project unless a prior EC was
granted in accordance with the procedure stipulated in the notification.     G
On 14 September 2006, the MoEF released the 2006 Notification in
supersession of the previous notification. The 2006 Notification directed
that:


                                                                             H
766             SUPREME COURT REPORTS                            [2020] 5 S.C.R.


A            “…on and from the date of its publication the required
             construction of new projects or activities or the expansion or
             modernization of existing projects or activities listed in the
             Schedule to this notification entailing capacity addition with
             change in process and or technology shall be undertaken in
             any part of India only after the prior environmental clearance
B
             from the Central Government or as the case may be, by the State
             Level Environment Impact Assessment Authority, duly constituted
             by the Central Government under sub-section (3) of section 3 of
             the said Act, in accordance with the procedure specified hereinafter
             in this notification.”
C                                                            (Emphasis supplied)
             11. The 2006 Notification came into force on the date of its
      publication and obliges every project proponent to seek prior EC for the
      projects and activities which are listed in the Schedule to the Notification.
      According to para 2 of the 2006 Notification, all new projects or activities
D     listed in the Schedule to the 2006 Notification shall require a prior EC
      from the concerned regulatory authority:
             “2. Application for Prior Environmental Clearance (EC):- An
             application seeking prior environmental clearance in all cases shall
             be made in the prescribed Form 1 annexed herewith and
E            Supplementary Form 1A, if applicable, as given in Appendix II,
             after the identification of prospective site(s) for the project
             and/or activities to which the application relates, before
             commencing any construction activity, or preparation of
             land, at the site by the applicant. The applicant shall furnish,
             along with the application, a copy of the pre-feasibility project
F            report except that, in case of construction projects or activities
             (item 8 of the Schedule) in addition to Form 1 and the
             Supplementary Form 1A, a copy of the conceptual plan shall be
             provided, instead of the pre-feasibility report.”
                                                             (Emphasis supplied)
G
             Once a prospective site has been identified by the applicant for
      the proposed project, all applications seeking an EC shall be made in the
      prescribed Form 1 and Supplementary Form 1A, if applicable which
      contains a detailed list of the extent and potential impact of the proposed
      project. The application must be submitted after the identification of the
H     prospective site and prior to the commencement of any construction
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                             767
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

activity, or preparation of the land.Thus, the action by the project          A
proponent that is relevant to the obligation to seek a prior EC under the
2006 notification is the identification of the prospective site for the
execution of the proposed project.
       12. Section 2(a) of the BDA Act defines “authority” as the
Bangalore Development Authority constituted under Section 3 of the            B
Act. Chapter III of the Act deals with development schemes and the
procedures that must be complied with in the carrying out of a
development scheme. Under Section 15, the appellant may draw up a
detailed development scheme for the development of the Bangalore
metropolitan area. Section 16(1) mandates that the appellant must also
provide, in the formulation of the scheme, the details of the land proposed   C
to be acquired for the development scheme. Section 17 contemplates
the issuance of a preliminary notification. It reads:
      “17. Procedure on completion of scheme.- (1) When a
      development scheme has been prepared, the Authority shall draw
      up a notification stating the fact of a scheme having been made         D
      and the limits of the area comprised therein, and naming a place
      where particulars of the scheme, a map of the area comprised
      therein, a statement specifying the land which is proposed to be
      acquired and of the land in regard to which a betterment tax may
      be levied may be seen at all reasonable hours.                          E
      (2) A copy of the said notification shall be sent to the Corporation
      which shall, within thirty days from the date of receipt thereof,
      forward to the Authority for transmission to the Government as
      hereinafter provided, any representation which the Corporation
      may think fit to make with regard to the scheme.                        F
      (3) The Authority shall also cause a copy of the said notification
      to be published in [ x xx ] the official Gazette and affixed in some
      conspicuous part of its own office, the Deputy Commissioner’s
      Office, the office of the Corporation and in such other places as
      the Authority may consider necessary.                                   G
      (4) If no representation is received from the Corporation within
      the time specified in sub-section (2), the concurrence of the
      Corporation to the scheme shall be deemed to have been given.
      (5) During the thirty days next following the day on which such
      notification is published in the official Gazette the Authority shall   H
768             SUPREME COURT REPORTS                            [2020] 5 S.C.R.


A            serve a notice on every person whose name appears in the
             assessment list of the local authority or in the land revenue register
             as being primarily liable to pay the property tax or land revenue
             assessment on any building or land which is proposed to be acquired
             in executing the scheme or in regard to which the Authority
             proposes to recover betterment tax requiring such person to show
B
             cause within thirty days from the date of the receipt of the notice
             why such acquisition of the building or land and the recovery of
             betterment tax should not be made.
             (6) The notice shall be signed by or by the order of the
             [Commissioner] and shall be served,-
C            (a) by personal delivery or if such person is absent or cannot be
             found, on his agent, or if no agent can be found, then by leaving
             the same on the land or the building ; or (b) by leaving the same at
             the usual or last known place of abode or business of such person;
             or (c) by registered post addressed to the usual or last known
D            place of abode or business of such person.
             Section 17 stipulates that the appellant shall, upon the preparation
      of a scheme under Section 15, notify that a scheme has been prepared
      along with the specifications of the scheme, a map of the area comprised
      therein and the details of the land proposed to be acquired.The notification
E     is forwarded to the Corporation of the City of Bangalore, which is granted
      thirty days to provide its comments to the appellant authority for
      transmission to the government along with the scheme for sanction.
      Section 17(3) stipulates that a copy of the notification shall be published
      inthe Official Gazette and affixed in conspicuous parts of the offices of
      the appellant and the Corporation. Section 17(5) mandates that the
F     appellant shall serve on every person whose land is proposed to be
      acquired a notice to show-cause within thirty days onwhy the acquisition
      of the building or land must not take place.
             13. Section 18 stipulates that where the procedure stipulated under
      Section 17 is complete, the appellant shall submit the scheme with any
G     modifications, to the Government of Karnataka for sanction subject to
      the conditions stipulated therein. Section 18 reads:
             “18. Sanction of scheme.- (1) After publication of the scheme
             and service of notices as provided in section 17 and after
             consideration of representations, if any, received in respect thereof,
             the Authority shall submit the scheme, making such modifications
H            therein as it may think fit, to the Government for sanction,
             furnishing,-
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                               769
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

           (a) a description with full particulars of the scheme including      A
           the reasons for any modifications inserted therein;
           (b) complete plans and estimates of the cost of executing the
           scheme;
           (c) a statement specifying the land proposed to be acquired;
           (d) any representation received under sub-section (2) of section     B
           17;
           (e) a schedule showing the rateable value, as entered in the
           municipal assessment book on the date of the publication of a
           notification relating to the land under the section 17 or the land
           assessment of all land specified in the statement under              C
           clause(c); and
           (f) such other particulars, if any, as may be prescribed.
       (2) Where any development scheme provides for the construction
       of houses, the Authority shall also submit to the Government plans
       and estimates for the construction of the houses.                        D
       (3) After considering the proposal submitted to it the Government
       may, by order, give sanction to the scheme.”
       Under this provision, the appellant is required to furnish details of
the land proposed to be acquired along with a schedule showing the
rateable value, as entered in the municipal assessment book on the date         E
of the publication of the notification. The appellant furnishes to the
government a description with full particulars of the scheme including
the reasons for any modifications inserted, plans and estimates of costs
and a statement specifying the land proposed to be acquired.Significantly,
if the government is satisfied with the proposed scheme, it may accord
sanction to the scheme under Section 18(3) of the Act. A scheme                 F
formulated under Section 15 may only be carried out where sanction
has been accorded to the scheme by the Government under Section
18(3) of the Act.
       14. Section 19 of the Act reads thus:
           “19. Upon sanction, declaration to be published giving               G
           particulars of land to be acquired.- (1) Upon sanction of the
           scheme, the Government shall publish in the official Gazette a
           declaration stating the fact of such sanction and that the land
           proposed to be acquired by the Authority for the purposes of
           the scheme is required for a public purpose.
                                                                                H
770             SUPREME COURT REPORTS                            [2020] 5 S.C.R.


A               (2) The declaration shall state the limits within which the land
                proposed to be acquired is situated, the purpose for which it is
                needed, its approximate area and the place where a plan of
                the land may be inspected.
                (3) The said declaration shall be conclusive evidence that the
B               land is needed for a public purpose and the Authority shall,
                upon the publication of the said declaration, proceed to execute
                the scheme.
                (4) If at any time it appears to the Authority that an improvement
                can be made in any part of the scheme, the Authority may
C               alter the scheme for the said purpose and shall subject to the
                provisions of sub-sections (5) and (6), forthwith proceed to
                execute the scheme as altered.
                (5) If the estimated cost of executing the scheme as altered
                exceeds, by a greater sum than five per cent the estimated
D               cost of executing the scheme as sanctioned, the Authority shall
                not, without the previous sanction of the Government, proceed
                to execute the scheme as altered.
                (6) If the scheme as altered involves the acquisition otherwise
                than by agreement, of any land other than that specified in the
                schedule referred to in clause (e) of sub-section (1) of section
E
                18, the provisions of sections 17 and 18 and of sub-section (1)
                of this section shall apply to the part of the scheme so altered
                in the same manner as if such altered part were the scheme.”
              Under Section 19, once the Government sanctions the appellant’s
      scheme, a final notification is published by the government in the Official
F     Gazette declaring that sanction has been received and that the land
      proposed to be acquired is required for a public purpose. The final
      notification specifies the limits within which the land proposed to be
      acquired is situated and specifies the place at which people may inspect
      the plan. The appellant is authorised under Section 19(4) to alter the
G     scheme subject to the sub-sections (5) and (6). Section 19(6) stipulates
      that if acquisition of additional land is required over and above the details
      that were furnished by the appellant under Section 18, and otherwise
      than by agreement with the person whose land is proposed to be acquired,
      the procedure stipulated in Section 17 and 18 shall be followed.

H           15. The BDA Act was enacted with the purpose of establishing a
      development authority for the development of the city of Bangalore and
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                                  771
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

adjacent areas. Sections 17, 18 and 19 stipulate the mechanism that                A
must be followed by the appellant leading up to the grant of government
sanction for a scheme formulated under Section 15. The purpose
underlying Section 17 is to grant to both the Corporation and the persons
whose lands are proposed to be acquired an opportunity to file their
objections to the proposed scheme and the acquisition of land required
                                                                                   B
for the execution of the project. Though the land proposed to be acquired
for the scheme is stipulated in the preliminary notification under Section
17, the provision to forward to the Corporation a copy as well as serve
notices to persons whose lands are proposed to be acquired sub-serves
the principles of natural justice where an affected party is extended the
right to object to a proposed scheme.                                              C
        16. Upon the receipt of suggestions and objections, if any, the
appellant may modify the scheme in accordance with the suggestions
received and thereafter forward to the Government the scheme for the
grant of sanction. However, it is only upon the grant of sanction by the
Government under Section 18(3), that a final notification under Section            D
19 is issued. It is only upon the grant of sanction by the Government that
a proposed scheme is deemed to be finalized and carried into effect.
       17. The 2006 Notification stipulates an obligation to commence
the EIA process once a prospective site is identified and before the
commencement of any construction or preparation of land. It may be                 E
possible that following the formulation of a scheme under Section 15
and the issuance of a preliminary notification under Section 17,
government sanction is denied or the appellant drops the proposed
scheme prior to the grant of sanction or the issuance of the final
notification. In such situations, if it were held that it is the issuance of the
preliminary notification identifying the proposed site for the project that        F
marked the commencement of the project for the purposes of the 2006
Notification, the appellant would be under an obligation to carry out the
EIA process for a proposed scheme which may not eventually materialize.
        18. The EIA process under the 2006 Notification serves as a
balance between development and protection of the environment: there               G
is no trade-off between the two. In laying down a detailed procedure for
the grant of an EC, the 2006 notification attempts to bridge the perceived
gap between the protection of the environment and development. The
basic postulate of the 2006 Notification is that the path which is prescribed
for disclosures, studies, gathering data, consultation and appraisal is            H
designed in a manner that would secure decision making which is
772             SUPREME COURT REPORTS                            [2020] 5 S.C.R.


A     transparent, responsive and inclusive. While the BDA Act was enacted
      with the purpose of establishing a development authority for the
      development of the city of Bangalore and adjacent areas, the 2006
      Notification embodies the notion that the development agenda of the
      nation must be carried out in compliance with norms stipulated for the
      protection of the environment and its complexities. The BDA Act and
B
      the 2006 Notification operate in different fields. It cannot be said that a
      site is deemed identified for the purpose of triggering the obligations
      under the 2006 Notification upon the issuance of a preliminary notification
      under Section 17 of the BDA Act. Adopting a contrary interpretation
      would lead to the absurd result where a project proponent is obligated to
C     carry out the EIA process for a scheme even prior to the grant of
      government sanction and a final notification carrying into effect the
      proposed scheme. In this view of the matter, the prospective site is deemed
      to be identified only upon the issuance of the final notification under
      Section 19 after the proposed scheme has received Government sanction
      under Section 18(3).
D
             19. The final notification under Section 19(1) of the BDA Act
      was issued on 29 June 2007 following the grant of government sanction
      for the acquisition of the land. This being after the coming into force of
      the 2006 Notification, the contention urged by the appellant that the project
E     commenced prior to the coming into force of the 2006 Notification cannot
      be accepted.

             E Applicability of the EIA Notification 2006

            20. Essentially, this Court is required to address the contention
F     urged by Mr. Shyam Divan, learned Senior Counsel appearing on behalf
      of the appellant that the PRR project, being neither a project falling
      within Section 2 of the National Highways Act 1956 or Section 3 of the
      Karnataka Highways Act 1964, does not fall within the ambit of the
      Schedule to the 2006 Notification.

G            21. Para 2 of the 2006 Notification reads thus:

             “2. Requirements of prior Environmental Clearance (EC):- The
             following projects or activities shall require prior environmental
             clearance from the concerned regulatory authority, which shall

H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                               773
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

      hereinafter be referred to as the Central Government in the Ministry      A
      of Environment and Forests for matters falling under Category
      ‘A’ in the Schedule and at State level the State Environment Impact
      Assessment Authority (SEIAA) for matters falling under Category
      ‘B’ in the said Schedule, before any construction work, or
      preparation of land by the project management except for securing
                                                                                B
      the land, is started on the project or activity:
      (i) All new projects or activities listed in the Schedule to this
      notification;
      (ii) Expansion and modernization of existing projects or activities
      listed in the Schedule to this notification with addition of capacity     C
      beyond the limits specified for the concerned sector, that is, projects
      or activities which cross the threshold limits given in the Schedule,
      after expansion or modernization;
      (iii) Any change in product - mix in an existing manufacturing unit
      included in Schedule beyond the specified range.”                         D
                                                      (Emphasis supplied)
        Para 2(1) of the 2006 Notification stipulates that only projects
listed in the Schedule must be granted prior EC. Para 7(f) of the Schedule
to the 2006 Notification, as originally enacted reads:
                                                                                E




                                                                                F




                                                                                G




       22. The schedule to the 2006 Notification stipulates that projects
listed in column 3 must be granted prior EC from the MoEF-CC while              H
774              SUPREME COURT REPORTS                                  [2020] 5 S.C.R.


A     projects listed in column 4 must be granted prior EC from the SEIAA.
      The general conditions applicable are listed at the end of the Schedule. 13
      Column 3 of para 7(f) includes new national highways and the expansion
      of existing national highways while column 4 includes new state highways
      and the expansion of existing state highways.Admittedly, in the present
      case, no notification was issued under either the National Highways Act
B
      1956 or the Karnataka Highways Act 1964 notifying the PRR project as
      a highway under those enactments. Initial discussions took place at the
      Government of Karnataka level regarding the transfer of the PRR project
      to the National Highways Authority of India14. On 10 January 2018, the
      Central Road Transport Ministry was informed that the Government of
C     Karnataka had granted its consent to transfer the said project to the
      NHAI on an”as it is” basis. However, the Government of Karnataka,
      by its order dated 24 June 2008, withdrew the proposal to transfer the
      PRR project to the NHAI.
             23. There is however another aspect of the matter that warrants
D     the attention of this Court. Para 7(f) of the Schedule to the 2006
      Notification has been amended15 since the coming into force of the 2006
      Notification.
             24. Prior to the issuance of the 2006 Notification, a draft notification
      was published in the official Gazette on 15 September 2005 stipulating
E     that comments may be sent to the MoEF-CC within sixty days from the
      date on which the notification was published. Para 7(f) of the Schedule
      to the draft notification reads:



F




      13
         “Any project or activity specified in Category ‘B’ will be treated as Category A, if
G     located in whole or in part within 10 km from the boundary of: (i) Protected Areas
      notified under the Wild Life (Protection) Act, 1972, (ii) Critically Polluted areas as
      notified by the Central Pollution Control Board from time to time, (iii) Notified Eco-
      sensitive areas, (iv) inter-State boundaries and international boundaries.”
      14
         NHAI
      15
         Notifications dated 11 November 2007, 1 December 2009, 4 April 2011 and 22
H     August 2013.
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                                             775
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

  S.     Project or   NIC code   ISIC                   Category                    Condit    A
  No.    Activity     (2004)     code                                               ions if
                                        A                 A/B      B                any

  (f)    Roads        45203*            All      new       -       All     State    GC-1
                                        National                   Highway
         Highways                       Highways,                  projects >=
                                        Express                    30 km length
                                        ways      and                                         B
                                        bypasses >=
                                        30        Km
                                        length
                                                                   Or

                                        Or
                                                                   All      State             C
                                                                   Highway
                                        All National               expansion
                                        Highways,                  projects
                                        Express way
                                        expansion
                                        projects                   >= 30 km
                                                                   length and
                                                                   additional
                                                                                              D
                                        >= 30 km                   rights of way
                                        length and                 of more than
                                        additional                 20 m
                                        right of way
                                        of more than
                                        20m
                                                                                              E
      In the draft notification, para 7(f) to the Schedule included the
term ‘expressway’ under category ‘A’ projects. However, in the final
2006 Notification, the word ‘expressway’ was deleted. Absent any
conclusive reason for the deletion from the draft notification prior to it
coming into force, such deletion cannot be used to construe the terms of                      F
the 2006 Notification or subsequent amendments thereto.
       25. In exercise of the powers conferred by sub-section (1) and
clause (v) of sub-section (2) of Section 3 of the Environment (Protection)
Act 1986 read with clause (d) of sub-rule (3) of rule 5 of the Environment
(Protection) Act 1986, the Central Government issued a notification dated
                                                                                              G
1 December 2009 amending, inter alia, para 7(f) of the Schedule to the
2006 Notification. Para (xv) of the amending notification reads:
        “(xv) against item 7(f),
        (a) In column (4), for the entry, the following entry shall be
        substituted namely:-                                                                  H
776            SUPREME COURT REPORTS                              [2020] 5 S.C.R.


A                       “i) All State Highway Projects; and
            ii) State Highway expansion projects in hilly terrain (above 1,000
            m AMSL) and or ecologically sensitive areas”
            (b) in column (5) for existing entry, the following entry shall
            be substituted, namely:-
B
                             “General Conditions shall apply.
                          Note: Highways include expressways.”
             Following the 2009 amendment, column 5 of para 7(f) to the
      Schedule which read “General Condition shall apply” was substituted to
C     stipulate that in addition to the application of the general conditions,
      highways include expressways.
              26. Prior to the amendment, a draft notification was published on
      19 January 2009 seeking comments and objections thereto. The MoEF-
      CC, by its order dated 3 July 2009 constituted a Committee under the
D     Chairmanship of Shri JM Mauskar, Additional Secretary to consider the
      comments received on the draft notification, conduct meetings with the
      various stake holders and make recommendations for the finalization of
      the notification.The Committee held various meetings with concerned
      stakeholders. The MoEF-CC published the report of the Committee titled
      “Report of the Committee constituted under the Chairmanship
E     of Shri JM Mauskar, Additional Secretary to examine the
      comments / suggestions on the Draft Amendments to EIA
      Notification, 2006” in October, 2009. Numerous comments were
      received by the Committee on various aspects of the draft notification
      including the proposed amendment to para 7(f) of the Schedule. The
F     initial draft notification only sought to modify column 4 of para 7(f).
      However, comments were received by the Committee stating that
      aspecific reference to expressways must be made. The Committee
      formulated its analysis in the following terms:
            “Analysis: The main suggestion relates to expansion of the scope
            of the notification by including expressways, bypasses, Major
G
            district roads, tunnelling for roads within city limits, peripheral roads
            around municipal corporation limits. There is also a request for
            expanding the right of way limit from 20 metres to 60 metres.
            BRO has sought exemption of their projects up to 50 kilometres.
            From the comments received, it is perceived that
H           Expressways are different from Highways. However,
     BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                           777
       HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

         keeping in view the objective of the Notification, it needs           A
         to be explicitly clarified in the Notification that Highways
         include Expressways. In regard to other items these may be
         considered separately. In regard to the proposal for enhancing
         the right of way limit from 20 metres to 60 metres, this may not be
         accepted as it would involve significant changes in land use and
                                                                               B
         issues of rehabilitation.”
                                                       (Emphasis supplied)
       27. The analysis of the Committee recorded that the main
suggestions related to the expansion of the scope of the Notification by
including within its ambit expressways, bypasses, major district roads,        C
tunnelling for roads within city limits and peripheral roads around
municipal corporation limits. Significantly, the Committee took note of
the perception that highways and expressways differed from each other.
Though it appeared from the comments that an expansion was sought in
the scope of the 2006 Notification, the Committee explicitly clarified
that the term ‘highways’ includes ‘expressways’.For other items, the           D
Committee stated that they may be considered separately. The
clarification issued for highways and expresswaysdid not amount to an
expansion in the scope of the 2006 Notification but only made clear that
the term highways always included expressways.
       28. Where an amendment is clarificatory in nature, such                 E
amendment is deemed to be retrospective in its application. In State
Bank of India v VRamakrishnan16, the question before a two judge
Bench of this Court concerned whether Section 14 of the Insolvency
and Bankruptcy Code, 2016 which provides for a moratorium for the
limited period mentioned, on admission of an insolvency petition, would        F
apply to a personal guarantor of a corporate debtor. In the judgment of
National Company Law Appellate Tribunal which was under appeal, it
was held that as a Resolution Plan binds personal guarantors as well
under Section 31, the moratorium under Section 14 would apply to personal
guarantors. Assailing this, the appellant relied upon the Insolvency
Committee Law proceedings to contend that an amendment to Section              G
14 which stipulated that the moratorium shall not apply to a surety in a
contract of guarantee to a corporate debtor was clarificatory in nature
and that personal guarantors were always intended to fall outside the

16
     (2018) 17 SCC 394                                                         H
778            SUPREME COURT REPORTS                           [2020] 5 S.C.R.


A     operation of the moratorium. Accepting this contention, Justice RF
      Nariman, speaking for the Court held:
            “31. The Insolvency Law Committee, appointed by the Ministry
            of Corporate Affairs, by its Report dated 26-3-2018, made certain
            key recommendations, one of which was:
B              “(iv) to clear the confusion regarding treatment of assets of
               guarantors of the corporate debtor vis-à-vis the moratorium
               on the assets of the corporate debtor, it has been recommended
               to clarify by way of an explanation that all assets of such
               guarantors to the corporate debtor shall be outside scope
C              of moratorium imposed under the Code;” (Emphasis
               supplied)
               …
               The Committee concluded that Section 14 does not intend to
               bar actions against assets of guarantors to the debts of the
D              corporate debtor and recommended that an explanation to
               clarify this may be inserted in Section 14 of the Code. The
               scope of the moratorium may be restricted to the assets of the
               corporate debtor only.”
            33. The Report of the said Committee makes it clear that the
E           object of the amendment was to clarify and set at rest what the
            Committee thought was an overbroad interpretation of Section
            14.”
            The Court noted that the Committee clarified that it was never
      intended that the moratorium under Section 14 applied to personal
F     guarantors of corporate debtors. Accordingly, an amendment was enacted
      to Section 14. The Court then proceeded to hold, relying on consistent
      precedent of this Court, that a clarificatory amendment has retrospective
      application. A similar position is expounded by G P Singh in his seminal
      work Principles of Statutory Interpretation. He states:
G           “…An amending Act may be purely clarificatory to clear a meaning
            of a provision of the principal Act which was already implicit. A
            clarificatory amendment of this nature will have retrospective effect
            and, therefore, in the principal Act was existing law when the
            amendment came into force, the amending Act also will be part
            of the existing law.”
H
     BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                              779
       HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

       29. An amending provision which clarifies the position of law which        A
was considered to be implicit, is construed to have retrospective effect.
The position of the retrospective application of clarificatory amendments
to notifications is analogous to the position under statutory enactments.In
the present case, the Committee appointed by the MoEF-CC clarified
that the term highways included expressways and suggested that a
                                                                                  B
suitable amendment be issued to that effect. Based on the report of the
Committee, a clarificatory amendment was issued in column 5 of para
7(f) to stipulate that highways include expressways.This being the
position, this Court is required to analyze whether the PRR project
qualifies as an expressway falling within the ambit of para 7(f) of the
Schedule.                                                                         C
        30. Neither the National Highways Act 1956 nor the Karnataka
Highways Act 1964 define the term ‘highway’. The 2009 amendment to
the 2006 Notification is silent on the definition of the term ‘expressway’.It
was submitted by the learned Senior Counsel appearing on behalf of the
respondents that the definition by the Indian Road Congress17 in the              D
Manual of Specifications and Standards for Expressways in instructive
is instructive.
       31. The IRC was set up in 1934 on the recommendation of the
Indian Road Development Committeeconstituted by the Government of
India for the development of roads in the country. An expert group was            E
constituted in 2013 to formulate a Manual of Specifications and Standards
for Expressways. The report, which was released in the same year,
defined an expressway in the following terms:
           “…For this purpose, the Expressway is defined as an arterial
           highway for motorized traffic, with divided carriageways for high      F
           speed travel, with full control of access and provided with grade
           separators at location of intersections. Generally, only fast-moving
           vehicles are allowed access on Expressways…”
       An expressway is defined as an arterial highway designed for
high-speed travel with the objective of reducing traffic and generally            G
involving control of access. Other indicators are the provision of toll
booths, divided carriageways and grade separators located at
intersections. The assessment of whether a road project is an expressway
is to be determined on a case by case basis.
17
     IRC                                                                          H
780               SUPREME COURT REPORTS                          [2020] 5 S.C.R.


A             32. In the present case, the stated purpose of the PRR project is
      thus:
              “1) To decongest the traffic in Bangalore City;
              2) To cater intercity connectivity and intercity traffic;
B             3) To reduce pollution in the city
              4) To reduce heavy vehicles traffic i.e., Lorry and Trucks
              5) To decongest the traffic on outer ring road.”
              The brief note submitted by the appellant to this Court states that:
C             “…the PRR proposed to be implemented by the BDA is an 8 lane
              divided road around Bangalore city is primarily ease the
              vehicular traffic congestion on its city roads. The proposed
              cross-section consists of 4 lane main road in each traffic direction
              and 3 lane service road on either side of the main road for local
              traffic. The main road and the service road will be separated by
D
              access-controlled facility. The engineering designs will be
              carried out in accordance with Indian roads congress
              standards.”
                                                             (Emphasis supplied)
E            The primary purpose of the PRR project is to ease vehicular traffic
      congestion in the city. The main road and the service road are to be
      separated by access-controlled facilities. The engineering designs are to
      be carried out in accordance with the standards laid down by the IRC.
      The EIA report prepared by the appellant describes the PRR project in
      the following terms:
F
              “The proposed Peripheral Ring Road (PRR) project alignment
              starts from – Tumkur Road as CH.17a (distance of 16-20 Km
              from Bangalore city railway station) on NH4 & terminate at Hosur
              Road near Begur CH.64.65 Km (65Km) for a smooth flow of
              traffic, to reduce the traffic congestion, pollution intensity
G             and travel time.”
              …
              Highway Design
              The proposed Peripheral Ring Road (PRR) alignment has been
H             designed for a speed of 100 Kmph where ever possible.
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                            781
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

      However, at a few locations that designs have been carried out         A
      for 80 Kmph owing to restrictions at site. The vertical curves are
      designed as per the guidelines of IRC SP:23.
      …
      Interchanges
                                                                             B
      An interchange is a grade separated intersection with
      connecting roadways for turning traffic between highway and
      approaches. The intersections are designed during the construction
      of Peripheral Ring Road (PRR) after contemplating the guidelines
      and schemes given in AASHTO and IRC: 92 guidelines.
                                                                             C
      …
      Toll Plaza
      …All the traffic passing through the toll plaza section of road will
      have to pay toll. The public bus transport will be exempted from
      paying the toll.                                                       D


      Accessibility
      The Peripheral Ring Road (PRR) is speculated as a toll road.
      Provisions are provided for toll booths for tolling the road system.   E
      Accessibility to Peripheral Ring Road (PRR) is restricted
      to the following categories of roads
      National Highways;
      State Highways;
                                                                             F
      Major District roads.


      “The proposed project being a new state highway having 65 Km
      length with Right of Way of 75m the project falls under category
      “b” in the Schedule of the EIA notification 2006 and requires          G
      environmental clearance from SEIAA”
                                                    (Emphasis supplied)
     33. The PRR project is expected to be an 8 lane main carriageway
highway (4 + 4 bi-directional), along with a 6 lane road service road (3 +
                                                                             H
782            SUPREME COURT REPORTS                           [2020] 5 S.C.R.


A     3 bi-directional) having a right of way of 75 meters and total length of
      63.5 kms. The EIA report stipulates that the PRR project was
      conceptualised with the salient purpose of decongesting the traffic in the
      city and catering to intercity connectivity and intercity traffic. This, it
      was stated, would significantly reduce pollution intensity and travel time.
      The EIA report clarifies that the project is designed to cater to high
B
      speed vehicular traffic with vehicles plying at speeds of 100Kms/hr,
      where possible, and 80Kms/hr in other places.
             34. Moreover, the report stipulates that the project also comprises
      of ten interchanges and sixteen toll booths.It is stated that access to the
      road is restricted only to national highways, state highways and major
C     district roads. In this view of the matter, there is no doubt that the PRR
      project is an expressway falling within the ambit of para 7(f) of the
      Schedule to the 2006 Notification. The PRR project commenced on the
      issuance of the final notification under Section 19(1) of the BDA Act on
      29 June 2007. Having concluded that the PRR project is an expressway,
D     the appellant as project proponent was under an obligation under para
      7(f) of the Schedule to the 2006 Notification to seek a prior EC to
      implement the project.
            F Compliance with the procedure under the EIA
      Notification 2006
E            35. The next question to be analysed is whether the EIA process
      followed by the appellant was in compliance with the procedure stipulated
      under the 2006 Notification. In the written submissions and the rejoinder
      filed by the appellant before this Court, it was contended that the EIA
      process leading upto the preparation and submission of the EIA report to
F     the SEAC was in compliance with the procedure stipulated under the
      2006 Notification. It was contended that the NGT erred in concluding
      that there was a substantial delay in the preparation of the EIA report
      and in suspending the operation of the EC granted to the PRR project.
      On the other hand, in the written submissions filed by the respondents, it
      was contended that the delay in the preparation of the EIA report was in
G     contravention of the OM dated 22 March 2010 issued by the MoEF-CC
      prescribing a validity period of four years for ToRs from the date on
      which they are issued. In assessing the rival contentions, it becomes
      necessary to analyse the EIA process followed by the appellant,leading
      up to the grant of the EC.
H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                            783
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

       36. On 10 September 2009, the appellant filed an application with     A
the SEAC seeking a prior EC for the PRR project as a category ‘B’
project under the 2006 Notification. In accordance with the 2006
Notification, the SEAC at its 46th meeting held on 21 November 2009
formulated and issued the ToR for the PRR project on which basis the
appellant was required to carry out the EIA process. The final EIA
                                                                             B
report was placed before the SEAC and the SEIAA in November 2014.
The SEAC held meetings on 5 April 2013, 9 June 2014, 11-12 August
2014 and 11-18 November 2014. At its final meeting between 11-18
November, the SEAC recommended the grant of an EC for the PRR
project to the SEIAA. The EC was granted on 20 November 2014.
       37. The SEAC, at its 101st meeting dated 5 April 2013 decided to      C
recommend to the SEIAA the closure of the project file since the ToRs
were issued over two years prior to the meeting and there was no
correspondence by the appellant indicating any progress on the EIA
process. Acting upon the letter of the SEAC, the SEIAA, at its 66th
meeting dated 17 May 2013 closed the file relating to the grant of EC for    D
the PRR project and communicated its decision to the appellant on 25
July 2013. By a letter dated 24 August 2013, the appellant requested the
SEIAA to re-open the file. The SEIAA, at its 71st meeting dated
3 September 2013 decided to re-open the file, subject to the payment of
the requisite processing fee. A public hearing was conducted on 6 February
2014. The SEAC, at its 111th meeting dated 9 June 2014, decided to           E
defer the consideration of the appellant’s proposal as the EIA report
was not made available to the Committee members. By a letter dated 2
August 2014, the appellant placed before the SEAC the EIA report which
was prepared after the public hearing was conducted in February
2014.The SEAC, at its 115th meeting dated 11-12 August, 2014 noted           F
numerous deficiencies in the information submitted by the appellant and
decided to obtain additional information which was communicated to the
appellant on 28 August 2014.
      38. The appellant provided to the SEAC a point-wise reply to the
information sought along with additional samples on ground water, surface    G
water and soil. A final EIA report was prepared by the appellant in
October 2014 and submitted to the SEAC. At its 121st meeting between
11th and 18th November 2014, the SEAC recommended to the SEIAA
the grant of EC to the PRR project. The SEIAA issued the EC on 20
November 2014.
                                                                             H
784             SUPREME COURT REPORTS                           [2020] 5 S.C.R.


A            39. Under the 2006 Notification,the process to obtain an EC for
      new projects comprises a maximum of four stages, all of which may not
      apply depending on the specific case stipulated under the Notification:
      screening, scoping, public consultation and appraisal. At the scoping stage,
      the project proponent submits information in Form 1 to the EAC or the
      SEAC, as the case may be, for the preparation of a comprehensive
B
      ToR. Following this, the project proponent prepares a summary EIA for
      the purpose of the public consultation process. The summary EIA is
      presented at the public hearing to invite comments and objections, if any.
      Based on the comments received and after addressing the objections
      raised, a final EIA report is prepared and sent to the concerned regulatory
C     authority. At this stage, the regulatory authority must examine the
      documents “strictly with reference to the ToR” and communicate any
      inadequacy to the EAC or the SEAC, as the case may be, within 30
      days of the receipt of the documents. Within sixty days of the receipt of
      all the documents, the EAC or the SEAC, as the case may be, shall
      complete the appraisal process as prescribed in Appendix V. The appraisal
D
      stage involves detailed scrutiny by the EAC or the SEAC of all the
      documents submitted by the applicant for the grant of EC.The EAC and
      the SEAC are charged with evaluating the information submitted by the
      applicant in Form 1/Form 1A with reference to the ToR which was
      issued for the preparation of the EIA report.
E            40. Significantly, the process of obtaining an EC commences from
      the production of the information stipulated in Form 1/Form 1A.
      Information submitted in Form 1 relies on data and information on an “as
      is” basis at the relevant time of submitting information. Material
      information regarding the particulars of the proposed project as well as
F     the potential impact on the environment is sought to enable the EAC or
      the SEAC to prepare a comprehensive ToR on which basis the applicant
      proceeds to prepare the EIA report. As the information in Form 1 is
      submitted on the basis of prevailing environmental conditions as on the
      date of its preparation, it is necessary to ensure that the EIA process is
      contemporary to the submission of information in Form 1 and the issuance
G     of the ToR. The MoEF-CC, noting situations where some EIA reports
      were prepared belatedly on the basis of outdated ToRs, issued a notification
      on 22 March 2010 prescribing a time limit for the validity of ToRs which
      stated thus:

H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                            785
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

                         “Office Memorandum                                  A
      Sub: Time limit for validity of Terms of Reference (TORs)
      prescribed under EIA Notification, 2006 for undertaking
      detailed EIA studies for developmental projects requiring
      environmental clearance – Regarding.
                                                                             B

      The EIA Notification, 2006 has prescribed a time limit for validity
      environmental clearance granted to a project. However, no time
      limit has been specifically provided under the EIA Notification for
      the TORs prescribed for undertaking detailed EIA studies. As a
      result, the TORs once prescribed would continue to be valid            C
      indefinitely, which is definitely not desirable because the
      TORs are very much site specific and are dynamic to some
      extent depending upon the site features, its land use and
      the nature of development around it. The matter has been
      considered in the Ministry of Environment & Forests.                   D
      It has been decided that from 1.4.2010, the prescribed TORs would
      be valid for a period of two years for submission of the EIA/EMP
      Reports, after public consultation where so required. This period
      will be extendable to the 3rd year, based on proper justification
      and approval of the EAC/SEAC, as the case may be. Thus, an             E
      outer limit of three years has been prescribed for the validity of
      the TORs with effect from 1.4.2010.
      In case of the proposals which has been granted TORs prior
      to the issue of this O.M., the EIA/EMP reports should be
      submitted, after public consultation where so required, no             F
      later that four years from the date of the grant of the TORs,
      with primary data not older that three years.”
                                                    (Emphasis supplied)
       41. The MoEF-CC stated that it was clearly undesirable to
indefinitely continue a ToR. The environment is, by its very nature,         G
dynamic. Soil quality, air characteristics and surrounding flora and fauna
are among the characteristics of the environment which are constantly
in a state of flux. A robust framework of environmental governance
accounts for the dynamic nature of the environment. It is for this reason
that project proponents are also required to ensure the submission of an
                                                                             H
786            SUPREME COURT REPORTS                          [2020] 5 S.C.R.


A     Environmental Management Plan and compliance with the monitoring
      procedures envisaged under the 2006 Notification. An indefinite ToR
      defeats the very purpose which underlies the 2006 Notification for it
      may lead to situations where the state of the environment has changed
      drastically, yet the EIA process is carried out on the basis of outdated
      information. For this reason, the MoEF-CC prescribed a validity period
B
      of two years for TORs, which could be extended by the EAC or the
      SEAC only by another year. Furthermore, extension is to be granted
      only where the project proponent provides adequate justification in
      writing. Relevant to the present case, the notification dated 22 March
      2010 stipulates that where ToRs were granted prior to the issue of the
C     OM, the EIA report must be submitted within four years from the date
      on which the ToR was issued, with primary data not being older than
      three years.
              42. By another notification dated 22 August 2014, the MoEF-CC
      clarified the validity of the ToRs prescribed under the 2006 Notification
D     in the following terms:
            “…2(iv) Extension of validity of TORs beyond the outer limit of
            three years for all projects or activities and four years for River
            Valley and HEP projects shall not be considered by the
            Regulatory Authority. In such cases, the project proponent
            will have to start the process de novo and obtain fresh TORs
E           in case the proponent is still interested in pursuing the
            clearance for the project. Re-use of old baseline data
            (provided it is not more than 3 years old) for the purpose of
            preparation of fresh EIA and EMP report will be considered
            subject to due diligence by the EAC/SEAC which may make
            appropriate recommendations including the need for
F
            revalidation. Baseline data older than 3 years will not be used
            for preparation of EIA/EMP report. In any case, the PH shall
            have to be considered afresh in such cases.”
                                                          (Emphasis supplied)
G            The MoEF-CC clarified that where the time period prescribed
      for the ToR has expired, the regulatory authority “shall not” consider
      any further extension and a project proponent seeking to continue the
      project must initiate the EIA process de novo. This includes the
      submission of fresh information in Form 1 and the prescription of a new
      ToR to guide the preparation of the EIA report. The extraordinary
H     prescription of conducting the EIA process afresh was in keeping with
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                              787
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

the commitment to a framework of environmental governance which                A
accounts for the dynamic nature of the environment.
      43. By another notification dated 7 November 2014, the MoEF-
CC issued a notification clarifying the time limit prescribed for ToRs as
well as the consideration of EIA reports by the SEAC which relied on
primary data older than three years. The notification, in so far as it is      B
relevant reads:
      “2. The matter has been further examined in the Ministry in the
      light of the decision taken as part of clearance reform and it is felt
      that it would not be logical to start the process of environment
      clearance de novo including taking fresh Terms of Reference              C
      (TORs), if the base line data collected for preparation of
      EIA/EMP report and/or public consultation are more than
      three years old.
      3. Thus, it has been decided to substitute para 2(v) of the above
      referred Office Memorandum No. J-110113/41/2006-IA.II(I)                 D
      (part) dated 22.08.2014 with the following:
      “(v) (a) All the projects which have been recommended by the
      Expert Appraisal Committee (EAC) shall be considered by the
      Competent Authority even if data collected has become more
      than three years old as the ToRs itself used to have three               E
      years validity and extendable by one more year.
      (b) All the projects where the project proponent have already
      submitted their EIA/EMP Report for consideration by the EAC
      though the cases have still not been placed before the EAC and
      meanwhile the data has become more than three years old, shall           F
      be considered for the same reasons as given in para (a) above….”
                                                      (Emphasis supplied)
       This notification stipulated that the ‘concerned authority’ shall
consider EIA reports for the grant of EC even where the primary data
relied upon was collected beyond three years from the preparation of           G
the EIA report. This was because the ToR itself was extendable beyond
three years by an additional year. Thus, where the EIA report is prepared
within the prescribed time period for the validity of the ToR, the concerned
authority may consider an EIA report which relies on primary data which
was collected more than three years ago i.e. in the fourth year preceeding
the preparation of the EIA report. The effect of the notification was to       H
788            SUPREME COURT REPORTS                          [2020] 5 S.C.R.


A     prescribe a uniform validity period of four years for both ToRs and the
      primary data collected. However, the stipulation that a fresh EIA process
      must be undertaken where the ToR has expired was retained.
             44. In the present case, the ToR was issued on 21 November
      2009, prior to the issue of the OM dated 22 March 2010. Hence, by
B     virtue of the notification, the appellant was required to submit the EIA
      report within four years from the date of the issuance of the ToR i.e
      before 21 November 2013. The SEAC was under a corresponding
      obligation to refuse the consideration of any EIA report prepared after
      the expiry of the ToR. Public hearing was conducted belatedly only on 6
      February 2014 and the EIA report prepared thereafter was placed before
C     the SEAC only on 2 August 2014, nearly a year after the ToR had expired.
      We cannot gloss over the failure of the project proponent to comply with
      the OMs issued by the MoEF-CC prescribing a time limit for the validity
      of the ToR. The decision of the SEAC to proceed with the EIA report as
      well as seek additional information from the project proponent despite
D     the expiry of the ToR suffers from a non-application of mind and is
      unsustainable.
            45. Moreover, primary data was collected in December 2009 and
      February 2010. The EIA report was prepared after the public hearing
      was conducted in February 2014, nearly a year after the primary data
E     had expired in terms of the OMs issued by the MoEF-CC. In the final
      EIA report prepared in October 2014, it is stated:
            “1.8 Study Period
            To prepare the Rapid Environmental Impact Assessment (REIA)
            report for the proposed project, the data was collected from
F           December to February (2009-2010) in the study area. Micro
            Meteorological parameters were recorded such as wind speed,
            wind direction and relative humidity on hourly basis during the
            study period.”
            “3.5 Monitoring period
G
            Meteorological data was collected for the study area during the
            months of winter (December, January and February (2009-
            2010), Wind Speed, Wind Direction, Temperature and Relative
            Humidity were recorded on hourly basis for the total study period”
                                                          (Emphasis supplied)
H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                               789
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

       46. Admittedly, the EIA reports prepared in August and October           A
2014 relied on primary data which was collected between the months of
December 2009 and February 2010. The EIA report was prepared prior
to the coming into force of the OM dated 7 November 2014 by which
the MoEF-CC extended the validity of primary data collected from a
period of three years to four years. Even if the benefit under the
                                                                                B
notification were extended to the appellant, it was duty bound to collect
fresh primary data upon the expiry of four years from the date of issuance
of the ToR i.e. 21 November 2013. This was evidently not done. This
being the case, there is no manner of doubt that the final EIA report
prepared on the basis of an expired ToR and primary data was in
contravention of the OMs dated 22 March 2010, 22 August 2014 and 7              C
November 2014 issued by the MoEF-CC and could not form the basis
of a validly issued EC.
        47. It is also pertinent to note that a Rapid EIA along with a socio-
economic study was prepared by M/s Ramky Enviro Engineers Ltd.,
the EIA consultantfor the PRR project on behalf of the appellant in             D
November 2010. This EIA report relied on primary data collected between
the months of December 2009 and February 2010 and analysed the
impact of the proposed PRR project on the environment. A perusal of
both the 2010 rapid EIA report and the EIA report prepared in October
2014 reveals that the data as well as the analysis of the impact of the
proposed PRR project on the environment in the 2014 report is similar to        E
that in the 2010 Rapid EIA report. It appears that the EIA consultant has
reproduced verbatim, portions of the Rapid EIA report which was
prepared in the year 2010. No effort was taken by the appellant to ensure
the fresh collection of data in compliance with its obligations under the
OMs issued by the MoEF-CC. In this view of the matter, the contention           F
urged on behalf of the respondents that there was a substantial delay in
the carrying out of the EIA process, vitiating the process commends
itself for our acceptance.
       48. In the rejoinder and brief note of submissions filed before this
Court by the appellant, it was contended that any delay in the collection       G
of primary data was remedied by the collection of fresh samples in reply
to the questions raised by the SEAC in its 115th meeting dated 11-12
August, 2014. The primary data furnished in reply, it was urged, dated to
the year 2014 and not 2010.In assessing this contention, it is necessary
to advert to the questions raised by the SEAC to the appellant. The
                                                                                H
790             SUPREME COURT REPORTS                          [2020] 5 S.C.R.


A     SEAC, at its 115th meeting noted shortfalls in the information submitted
      by the appellant and decided to obtain additional information. This was
      communicated to the appellant on 28 August 2014. The SEAC sought
      additional information on the following:
            “
B           1. EIA accredited consultant for Highway projects was not present
            2. Declaration of experts involved in preparation of EIA report is
            not furnished in the report
            3. Accessibility to all villages on either sides of the proposed road
            has to be preferably through underpasses.
C
            4. Baseline data of hardness of borewell water furnished in the
            report is found to be wrongly analysed.
            5. Surface water analysis report is found to be with wrong results.
            6. All the parameters required to be tested as per NABET
D           guidelines are to be analysed and furnished with lab reports.
            7. Sampling locations are to be marked on maps windrose diagram
            to be superimposed.
            8. In AAQ analysis, CO concentration is reported to be at
            dangerous level and this has to be checked again.
E
            9. EMP to be revised and has to be site specific.
            10. Sensitive location monitoring to be explicitly mentioned in EIA
            report with details of location.
            11. Regarding information on forest land in the EIA report there
F           are contradicting information in the report.
            12. Trees to be planted are to be known in advance to grow
            samplings.
            13. Soil analysis to be revalidated.

G           14. Borrow area of earth to be part of EIA report.
            15. Emergency relief operation to be included.
            16. As per the proposals submitted in page no 10. “No forest land
            is involved in the proposed project. Hence forest clearance is not
            required” whereas in the same proposal page no 21 “the total
H           forest land to be diverted is estimated to be 1.5ha in the jarakbande
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                             791
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

      kaval at Ch. 12.000” to 12.500. The contradictory information to        A
      be explained with documents.
      17. In the same proposal under the head 10.3 afforestation plan :
      “Species proposed for afforestation plan are Avicennia officinalis,
      Avicennia alba, Rhizophora mucronara & Rhizophora aciculate
      etc., they are mangrove-tropical tree growing in shoes ie., they        B
      are endemic in sea shores (coastal area in the Kundapur coast)
      etc.
      18. PP is advised to consult the forest wing under BDA to design
      (1 to 2) rows depending on the availability of the area) the strip
      plantations on either side of the proposed road with suitable native
                                                                              C
      fruit yielding shade bearing & fast growing species (instead of
      this consultant), to improve the micro climate. Committee decide
      to obtain additional information sought above and to recall the
      proposal alter receipt of the information.”
      By its letter dated 12 November 2014, the appellant provided to
the SEAC a point-wise reply to the information sought along with additional   D
samples on ground water, surface water and soil.
       49. The questions framed by the SEAC and responses filed by
the appellant demonstrate that there existed serious deficiencies in the
EIA report which was submitted to the SEAC. This included outdated
data on the AAQ air analysis, soil quality, forest land and the number of     E
trees to be planted. The SEAC noted certain shortfalls which concerned
limited aspects of the EIA report including the baseline data of hardness
of borewell water, soil analysis and forest land. In addition to this, the
SEAC directed that certain samples collected were to be marked on the
map submitted to the SEAC in the EIA Report. Significantly, the SEAC
noted the discrepancy concerning the disclosure of the existence of forest    F
land. This aspect shall be explored in the course of the judgment.
       50. The SEAC framed questions and sought information which
was clarificatory in nature and covered specific substantive aspects of
the data submitted in the EIA report. The EIA report on the other hand
covers a wide range of matters which include terrain, topography, land
                                                                              G
requirements, terrain classification, wind and noise pattern analysis, air
quality analysis, surface and ground water analysis, soil environment
analysis, impact of flora and fauna and environmental monitoring plans.
       51. The submission of additional fresh data on a few points raised
in the form of a query on behalf of the SEAC does not remedy the
general obligation to ensure that the EIA report was prepared within a        H
792            SUPREME COURT REPORTS                           [2020] 5 S.C.R.


A     time period of four years from the date of the issuance of the ToR,
      relying on primary data that was no older than four years. Merely because
      some additional information was sought which required the furnishing of
      additional details and the collection of fresh samples, it cannot be said
      that such an exercise cures the defect arising from the preparation of an
      EIA report outside the time period prescribed by the MoEF-CC.
B
      Significantly, even at the relevant time when information was sought
      from the project proponent, both the ToR as well as the primary data
      upon which the EIA report was prepared was beyond the period of their
      validity. In such a case, the SEAC, by seeking additional information,
      has traversed beyond the power conferred upon it under the 2006
C     Notification.
             52. The SEAC proceeded to recommend to the SEIAA the grant
      of the EC to the PRR project in contravention of the obligations stipulated
      under the OMs issued by the MoEF-CC. Significantly, the SEAC
      considered the final EIA report only at its 121st meeting between 11 –
D     18 November 2014 when the OM dated 22 August 2014 issued by the
      MoEF-CC was in force. The SEAC was under an obligation to direct
      the appellant to conduct the EIA process de novo. The SEAC and the
      project proponent cannot circumvent the obligation to ensure reliance on
      contemporary data by seeking additional information beyond the
      prescribed validity of the ToR and primary data. The SEAC has clearly
E     erred inrecommending to the SEIAA the grant of EC despite the non-
      compliance by the appellant with the prescribed time limit for the
      preparation of the EIA report.
            G Deficiencies in the EIA report

F           G.1 Accreditation of the EIA consultant
             53. In the written submissions submitted by the appellant, it was
      contended that the EIA process was undertaken on behalf of the appellant
      by M/s RamkyEnviro Engineers Pvt. Ltd., a non-accredited EIA
      consultant. This, it was submitted, was in contravention of the OM dated
G     2 December 2009 issued by the MoEF-CC mandating that only sector-
      specific accredited EIA consultants should be engaged to carry out the
      EIA process.
           54. The MoEF-CC, by its notification dated 2 December 2009,
      mandated the registration of EIA consultants under the scheme of
      Accreditation and Registration of the National Accreditation Board of
H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                               793
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

Education and Training/Quality Council of India. The relevant portion of        A
the notification reads:
       “…It has been felt in the Ministry that there is a need to enhance
       the quality of EIA reports as the Consultants generally, undertake
       preparation of EIA/EMP Reports in many sectors and in some
       instances without requisite expertise and supporting facilities like     B
       laboratories for testing of samples, qualified staff etc. The good
       quality EIA Reports are pre-requisites for improved decision
       making.
       …
       3. After detailed consideration of the issued relating to the            C
       accreditation of the Consultants, following decisions have been
       taken:
       · All the Consultants/Public Sector Undertaking (PSUs)
       working in the area of Environmental Impact Assessment
       would be required to get themselves registered under the                 D
       scheme of Accreditation and Registration of the NABET/
       QCI.
       · Consultant would be confined only to the accredited
       sectors and parameters for bringing in more specificity in
       the EIA document.
                                                                                E
       …
       4. It is decided, in the above factual matrix that no EIA/EMP
       Reports prepared by such Consultants who are not registered
       with NABET/QCI shall be considered by the Ministry after 30th
       June, 2010.”
                                                                                F
                                                       (Emphasis supplied)
       55. The MoEF-CC prescribed that it is mandatory for every
consultant or PSU acting as an EIA consultant to get themselves
registered under the accreditation scheme of the NABET/QCI. Moreover,
a consultant would be confined to the sector for which they receive             G
accreditation to ensure expertise and specificity in the carrying out of
the EIA process. This was also to ensure the availability of facilities like
laboratories. It was stated that a good quality EIA report is a pre-condition
for improved decision-making. In the written submissions before this
Court, the appellant urged that M/s Ramky Enviro Engineers Pvt. Ltd.
was hired in November 2009 upon the issuance of the ToRs prior to the           H
794             SUPREME COURT REPORTS                                          [2020] 5 S.C.R.


A     coming into force of the OM dated 2 December 2009. Consequently,
      there was no obligation to engage an accredited consultant for the
      preparation of the EIA report. Be that as it may, Ramky Enviro Engineers
      Pvt. Ltd, Hyderabad was granted the status of a ‘consultant with
      accreditation’ vide OM dated 30 June 2011 issued by the MoEF-CC. At
      the time of the preparation of the EIA report which was submitted to the
B
      SEAC, the EIA consultant had received accreditation. However, the
      learned counsel appearing on behalf of the respondents has also placed
      on record a copy of the minutes of the 4th Accreditation Committee
      Meeting for Re-Accreditation held on 22 November 2013. The case of
      Ramky Enviro Engineers Pvt. Ltd, Hyderabad was considered in the
C     following terms:
            “21. Ramky Enviro Engineers Pvt. Ltd., Hyderabad
            The case of Ramky Enviro Engineers was discussed earlier in
            RAAC meeting dated Oct. 28 2013. Inadequacies with respect
            to a) Variation in names of candidate in list of experts/persons
D           included in EIA b) Implementation of QMS and c) Quality of EIA
            were observed. RamkyEnviro was asked to explain the reasons
            for shortfalls to Accreditation Committee (AC)
            …
            Results of the Re-accreditation (RA) assessment are given below:
E           Ramky Enviro Engineers have scored more than 60% as an
            organization and therefore qualifies for Cat. A EIA projects.
            However, in respect of Completeness and quality of EIA, the
            marks are less that 60% indicating scope of improvement vide
            points mentioned below in relevant section.
            2.1.1 Scope of accreditation
F
                Sl.   Sector No. as NABET   Name of Sector                    Cat.
                No.   Scheme

                1     1                     Mining                             A

                2     40                    Thermal Power plants               A

                3     20                    Petrochemical based processing     A
G
                4     21                    Synthetic organic processing       A

                5     1                     Industrial estate/parks/SEZ        A

                6     32                    TSDF                               A

                7     38                    Building and Large construction    A

                8     39                    Area and Township projects         A
H
    BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                                          795
      HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

       56. The Committee noted the deficiencies in the performance of                        A
M/s Ramky Enviro Engineers Pvt. Ltd. as an EIA consultant and indicated
a scope for improvement. The Committee then proceeded to record the
sectors for which M/s Ramky is granted accreditation. Conspicuous in
its absence is the grant of accreditation for serving as an EIA consultant
for highway projects. When the final EIA report for the PRR project
                                                                                             B
was prepared in August/October2014, M/s Ramky lacked accreditation
to serve as an EIA consultant for highway projects. This aspect shall be
borne in mind in deciding the eventual directions which this Court seeks
to issue.
         G.2 Forest land
                                                                                             C
        57. Essentially, the contention urged on behalf of the respondents
in its written submissions before this Court is that there was a patent and
abject failure on the part of the appellantas project proponent, to disclose
the diversion of forest land for the proposed PRR project. The appellant,
it was contended, concealed material information concerning the diversion
of forest land and absent the requisite forest clearance, the EC granted                     D
for the PRR project stands vitiated.
       58. In the draft EIA report prepared for the PRR project, it was
stated:
         “The Forest (Conservation) Act, 1980                                                E
         …No forest land is involved in the proposed project. Hence, Forest
         clearance is not required.”
       Despite an indication that the proposed PRR project did not involve
the diversion of forest land, the draft EIA report stated:
                                                                                             F
         “…As per the proposed design, the total forest land to be diverted
         is estimated to be 1.5 Ha and the chainage wise details of the
         same are presented as:
      Table 2.2 B. Details of Forest Area proposed to be diverted for
the Project Road
Sl.No.      Proposed    Length   Forest              Village     Survey No.   Area of the
                                                                                             G
            chainage    (Km)                                                  forest to be
                                                                              diverted in
                                                                              HA

1           Ch 12.000   763 M    Jarakabandekavalu   Yelahanka   59           1.5
            to 12.500

                                                                                             H
796              SUPREME COURT REPORTS                                     [2020] 5 S.C.R.


A           The draft EIA report noted that 1.5 hectares of forest land in
      Jarakabande kavalu is proposed to be diverted between linkages Ch
      12.000 and 12.500 for a portion of the proposed road totaling 763 meters.
      A similar contradiction is noted in the final EIA report prepared in October,
      2014:
B             “Initial portion of the Highway is along protected forest areas.
              From the site visits and discussion with officials, it is inferred that
              there are no noticeable habitats or wild or endangered animal
              habitats along close vicinity of the project road…”
             The EIA report affirms at numerous places that 1.5 hectares of
C     forest land will be affected by a part of the project. Despite this, the EIA
      report proceeds to state:
        Sl.    Type of clearance              Statutory     Applicabilit   Project      Respo
        No                                    Authority     y              stage        nsibili
                                                                                        ty

        1      Prior          Environmental   SEIAA         Applicable     Pre          BDA
D              Clearance      under    EIA                                 constructi
               Notification, 2006                                          on

        2      Forest Clearance under         Karnataka     Not            Pre          BDA
               Forest Conservation Act,       S tate and    applicable     construct
               1980                           Forest Dept                  ion
                                              & MoEF
E
             59. The EIA report proceeds on the assumption that no forest
      clearance is required despite the diversion of 1.5 hectares of forest land.
      No explanation has been provided by the appellant either in the EIA
      report or in the written submissions before this Court as to why it was
F     exempt from seeking the requisite forest clearance. The only indication
      of remedying the loss of forest cover provided in the EIA report is thus:
              “10.4 Afforestation Plan
              Affected Area – Around 1.50 Ha.
              Area proposed to be afforested – 4.5 Ha (three times the affected
G             area)
              Afforestation Program will be implemented through the Forest
              Department, BDA and regular monitoring will be ensured.
              Land will be identified in consultation with state Forest Department,
H             Bangalore.”
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                               797
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

        The contradictory stand by the appellant on the forest cover            A
proposed to be diverted for the proposed project was noted by the SEAC
in its 115th meeting dated 11-12 August, 2014. The SEAC sought
additional information from the appellant on numerous grounds, of which
one concerned the potential loss of forest cover. The SEAC, in its letter
to the appellant, noted the contradictory stand of the appellant and stated:
                                                                                B
       “…16. As per the proposals submitted in page no 10. “No forest
       land is involved in the proposed project. Hence forest clearance
       is not required” whereas in the same proposal page no 21 “the
       total forest land to be diverted is estimated to be 1.5ha in the
       jarakbande kaval at Ch. 12.000” to 12.500. The contradictory
       information to be explained with documents.”                             C

       The appellant furnished a pointwise reply to the question raised
by the EAC. It replied to the question concerning forest land by stating:
       “As per the proposed design the total forest land to be diverted is
       estimated to be 1.5 ha in the Jarakbande Kaval at Sh.12.000 to           D
       12.500.
       25 acres of land available in possession with BDA is proposed to
       be given to Forest Department in lieu of 25 acre of Forest Land
       (PRR Chainage between 12th and 13th Km in Survey No. 59 of
       Jarakbande Kaval approved vide by authority Subject No. 80/89            E
       dated 17.03.2009.) needed to PRR.”
       The appellant confirmed that 1.5 hectares of forest land is proposed
to be diverted. It was stated that in lieu of the 25 acres of forest land
required, the appellant shall make available to the Forest Department 25
acres of land available with it.                                                F
        60. We cannot gloss over the patent contradiction of the appellant
as the project proponent in disclosing the existence of forest land to be
diverted for the purposes of the PRR project. Despite a clear indication
that a total 1.5 hectares of forest land is to be diverted for the purpose of
the PRR project, the appellant sought to remedy its failure in seeking the
                                                                                G
requisite clearances in a post facto manner by stipulating that 25 acres
of land available with it is to be given to the forest department in lieu of
the forest cover proposed to be diverted for the project. Post facto
explanations are inadequate to deal with a failure of due process in the
field of environmental governance.While the appellant submitted to the
EAC that it had already obtained the consent of the forest department to        H
798             SUPREME COURT REPORTS                              [2020] 5 S.C.R.


A     divert the proposed forest land, a contradictory stance was taken in the
      written submissions filed by the appellant:
             “It is stated herein that the PRR passes through 25 acres of forest
             land situated in Jarakbande Kaval Forest Area, Yelahanka Hobli,
             Bangalore North Taluk and since the alignment inevitably passed
B            through this, the forest department was requested on 28.08.2018
             to handover the forest land to the Appellant for the purpose of the
             PRR project. Thereafter, the forest department replied on
             12.01.2019 requesting for alternate land of 25 acres.”
               It was stated by the appellant that it was only on 28 August 2018
C     that it sought to remedy its failure in obtaining the requisite forest clearance
      by requesting the forest department to handover the forest area involved
      in the project. The appellant, in its rejoinder filed before this Court states:
             “…It is admitted that the PRR does indeed pass through
             the forest land in Jarakabande Kavalu forest area. It is also
D            pertinent to point out here that the Appellant has also taken
             necessary steps to ensure that land measuring 25 acres have also
             been provided as alternate land for the afforestation plan due to
             the forests to be cleared in the Jarakabande Kavalu forest area
             as shown in pg. 238 of IA. No. 53243. The contradictions
             mentioned in the EIA report have subsequently stood
E            corrected and clarified before the EAC and the SEIAA.”
                                                               (Emphasis supplied)
             In addition to the admission by the appellant of the contradictions
      in the EIA report, it sought to substitute the requisite forest clearance
F     with an agreement with the forest department to provide an alternative
      site for afforestation. This is not sustainable in law. Compliance with the
      2006 Notification and other statutory enactments envisaged in the EIA
      process cannot be reduced to an ad-hoc mechanism where the project
      proponent seeks to remedy its abject failure to disclose material
      information and seek the requisites clearances at a belated stage.
G
             61. The Karnataka SEIAA, in its affidavit before the NGT sought
      to contend that the EC was granted subject to the appellant obtaining the
      required forest clearance. It was stated:
             “Forest Area
H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                              799
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

      (b) Environmental Clearance has been provided by SEIAA is for            A
      the present alignment of the road as submitted to SEIAA and any
      change in the scope of the project requires fresh appraisal. In this
      regard, it may be noted that details of the forest land involved are
      covered in the Environment Impact Assessment Report. The
      proponent has decided to provide 25 acres of land available with
                                                                               B
      them to the Forest Department.
      It may also be noted that as per law, clearances from other statutory
      authorities is not mandatory for consideration of the application
      for Environment Clearance (hereafter, also referred to as “EC”)
      as it is prior Environmental clearance. Nonetheless, specific
      conditions have been imposed in the EC that such permission shall        C
      be obtained by the project proponent.
      …
      It is also important to note that the EC is subject to compliance
      with the conditions requiring obtaining of required clearances from      D
      the competent authority in accordance with the applicable law
      such as prior clearances relating to forests and lakes. Any non-
      compliance will be construed as a violation of the EC conditions
      and will be dealt with in accordance with law.”
       In the view of the Karnataka SEIAA, there was no deficiency in          E
the grant of the EC so long as specific conditions were imposed on the
project proponent to seek the requisite clearance.
       62. Prior to the notification, prior clearance from regulatory bodies
or authorities was not required. The MoEF-CC, by a notification dated
31 March 2011, prescribed the procedure to be followed for projects            F
which involve forest land in the grant of an EC. The relevant portion
reads:
      “…In this regard, reference is also invited to para 8(v) of the EIA
      notification, 2006 which reads as follows:
      “Clearances from other regulatory bodies or authorities shall not        G
      be required prior to receipt of applications or prior environmental
      clearance of projects or activities, or screening, or scoping, or
      appraisal, or decision by the regulatory authority concerned, unless
      any of these is sequentially dependent on such clearance either
      due to a requirement of law, or for necessary technical reasons.
                                                                               H
      …
800              SUPREME COURT REPORTS                           [2020] 5 S.C.R.


A            However, in view of the complexity of the issues involved, the
             matter has been considered further in the Ministry and in
             suppression of the earlier instructions, it has now been decided to
             adopt the following procedure for consideration of such projects.
             …
B            I. (B) Projects for which TORs have already been prescribed
             by the proposal for environmental clearance is yet to be
             submitted:
             In case of the proposals, which involve forestland, in part or it full,
             and for which TORs have already been prescribed, the project
C            proponents are advised to ensure that the requisite stage-I forestry
             clearance has been granted and its copy is submitted along with
             their application/proposal for environmental clearance.
             Alternatively, the proponent should delete from their land
             requirement, the forestland involved in the project and the proposal
D            so amended without any forestland may be submitted for appraisal
             by the EAC.
             In case of projects where forest diversion (Stage I clearance)
             has been approved for part of the total forestland involved in the
             project, the proposal will be considered only for the land for which
E            forest diversion has been approved and the non forestland, if
             any…”
             63. The MoEF-CC stipulated that where ToRs have been issued
      and the EIA report for the grant of EC is yet to be submitted, project
      proponents must ensure that the requisite forest clearance has been
F     granted. A copy of the grant should be submitted along with their
      application for the grant of EC. Alternatively, the project proponent may
      delete from the proposed project any forest land that may be affected
      by the project. The MoEF-CC clarified that where forest clearance has
      been obtained for only a part of the total forestland involved in the project,
      the proposal will be considered only to the extent of the land for which
G     forest diversion has been approved.
            64. By two subsequent notifications dated 9 September 2011 and
      18 May 2012, the procedure concerning the grant of EC for projects
      involving forestland stood amended in the following terms:

H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                            801
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

      “…                                                                     A
      (ii) At the stage of consideration of proposals for EC in respect of
      projects involving forestland, the project proponent would inform
      the respective EACs about the status of their application for
      forestry clearance along with necessary supporting documents
      from the concerned Forest Authorities. It will clearly be informed     B
      to the EAC whether the application is at the State level or at the
      Central level. The EAC will take cognizance of the involvement
      of forestland and its status in terms of forestry clearance and
      make their recommendations on the project on its merits. After
      the EAC has recommended the project for environmental
      clearance, it would be processed on file for obtaining decision of     C
      the Competent Authority for grant of environmental clearance. In
      the cases where the Competent Authority has approved the grant
      of environmental clearance, the proponent will be informed of the
      same and a time limit of 12 months, which may be extended in
      exceptional circumstances to 18 months, a decision on which will       D
      be taken by the Competent Authority, will be given to the proponent
      to submit the requisite stage-I forestry clearance. The formal
      environmental clearance will be issued only after the stage-
      I forestry clearance has been submitted by the proponent.
                                                                             E
      (iii) In the eventuality that the stage-I forestry clearance is not
      submitted by the project proponent within the prescribed time limit
      mentioned at para (ii) above, as and when the stage-I forestry
      clearance is submitted thereafter, such projects would be referred
      to EAC for having a relook on the proposal on case by case             F
      basis depending on the environmental merits of the project
      and the site. In such a situation the EAC may either reiterate its
      earlier recommendations or decide on the need for its reappraisal,
      as the case may be. In the eventuality, a reappraisal is asked for,
      the Committee will simultaneously decide on the requirement of
      documents / information for reappraisal as also the need for a         G
      fresh public hearing.”
                                                    (Emphasis supplied)
       65. Project proponents are duty bound to disclose the existence
of forest land and inform the SEAC of the status of their application for
                                                                             H
802             SUPREME COURT REPORTS                             [2020] 5 S.C.R.


A     forest clearance at the time of submitting the EIA report for the grant of
      the EC. Where the competent authority has granted the EC for a project,
      the project proponent is then duty bound to obtain and submit to the
      competent authority the requisite stage I forest clearance for the proposed
      project within 12 months or 18 months, as the case may be. Where the
      project proponent fails to submit the requisite forest clearance within the
B
      prescribed time, the EAC or the SEAC are authorised to reexamine the
      project and decide whether there is a need for the reappraisal of the
      project. The process envisaged for the disclosure of the forest clearance
      procedure as well as the submission of the grant of forest clearance
      sub-serves the purpose of ensuring timely and adequate protection of
C     forest land. Where the EAC or the SEAC is of the opinion that additional
      documents are required upon the failure of the project proponent to submit
      the requisite forest clearance within the prescribed time, it may direct
      that a fresh public hearing be conducted.
             66. The appellant attempted to remedy its contradictory stand on
D     the forest land proposed to be diverted and its failure to obtain the requisite
      forest clearance by submitting to the SEAC an undertaking to ensure
      afforestation in an alternate plot of land owned by it in collaboration with
      the forest department. Such a procedure is neither envisaged under the
      2006 Notification nor is in compliance with the notifications issued by
      the MoEF-CC from time to time. Similarly, the SEAC was under an
E     obligation to ensure that the project proponent had complied with the
      stipulated procedure for the grant of forest clearance. Instead, the SEAC
      proceeded on the clarification issued by the appellant in contravention of
      the OMs dated 31 March 2011, 9 September 2011 and 18 May 2012.
      Despite the numerous deficiencies that were noted in the minutes of the
F     SEAC meeting, it proceeded to recommend to the SEIAA the grant of
      EC for the PRR project. The decision of the SEAC to recommend to
      the SEIAA the grant of the EC, despite the contradictory stand of the
      appellant as well as its failure to furnish adequate reasons as to why it
      was exempt from seeking forest clearance, suffers from a non-application
      of mind.
G
             G.3 Trees
            67. In the written submissions filed before this Court, it was
      contended by the respondents that there was a material concealment by
      the project proponent of the number of trees proposed to be felled for
H     the PRR project. While the appellant stated that only 200 – 500 trees
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                              803
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

were required to be felled, the number was in fact as high as 16,000           A
trees. The appellant, as project proponent, stated in the 2014 EIA report:
      “Around 519 plants are felled for the project; the minimum of
      three times the number of felled plant will be replanted in the
      nearby areas”
                                                                               B

       The Deputy Conservator of Forests, BDA, in a reply dated 24
April 2009 to a right to information query stated:
      “With respect to the information sought under the Right to
      Information Act, 2005, the number of trees that will be cut for the      C
      formation of the Peripheral Ring Road – Part I have been provided
      below:
         Sl.    Information sought       Information provided
         No.           for

               Here       is    the   The below mentioned trees                D
               information sought     belong to the Horticulture &
               regarding cutting of   Forest Department will be cut
               trees     for    the   for the formation of the
               formation of the       peripheral ring road Part – I
               Peripheral Ring Road
                                         1. Coconut trees: 3837                E
               Part - I
                                         2. Mango trees: 3142
                                         3. Guava trees: 1361
                                         4. Sapota trees: 0818
                                         5. Arecanut trees: 0287
                                         6. Jamun trees: 0084
                                         7. Jackfruit trees: 0059              F
                                         8. Tamarind trees: 0040
                                         9. Teak trees: 0201
                                         10. Silver oak trees: 0028
                                         11. Neem trees: 0028
                                         12. Eucalyptus trees: 7000
                       Total                     16,785                        G

       68. The Deputy Conservator of Forests revealed that around
16,785 trees were proposed to be cut for the purpose of executing the
PRR project. The abject failure of the project proponent in disclosing
the number of trees required to be felled is also evident from the rejoinder
                                                                               H
filed by appellant before this Court. It was submitted:
804            SUPREME COURT REPORTS                          [2020] 5 S.C.R.


A           “13. In reply to Para No. 6: As had been stated earlier, the
            clarifications regarding cutting of trees and the corrections have
            been made subsequently and additionally a further 25 acres of
            land has been provided for the purpose of afforestation in an
            alternate piece of land. The same has been shown in pg. 184 of
            I.A. No. 53243/2019.”
B
             The EIA report prevaricated by recording that the area required
      for the proposed PRR project has only a few trees. Though the
      development of infrastructure may necessitate the felling of trees, the
      process stipulated under the 2006 Notification must be transparent, candid
      and robust. Hiding significant components of the environment from
C     scrutiny cannot be an acceptable method of securing project approvals.
      There was a serious lacuna in regard to disclosures and appraisal on this
      aspect of the controversy.


D           G.4 Pipelines
              69. The EIA process was challenged on the ground that by virtue
      of a notification dated 12 June 1999, the Central Government acquired
      certain lands for laying a petroleum pipeline between Mangalore and
      Bangalore. Petronet MHB Ltd., by its letters dated 7 November 2005
E     and 21 November 2007 sought to inform the appellant of the potential
      crossover of the PRR project over the pipelines. The same was reiterated
      in its meeting with the appellant dated 4 February 2008. Petronet MHB
      Ltd.was of the opinion that as the pipelines contain hazardous material
      which is highly inflammable, care should be taken to either relocate parts
      of the project or ensure that adequate safeguards were put in place.
F
            70. The respondents have placed on record the minutes of the
      meeting dated 2 February 2008 between the appellant authority and the
      representatives of M/S. Petronet MHB Limited. It was noted that the
      proposed PRR project crosses the PETRONET pipeline at three locations
      – PRR CH 7600, PRR CH 29100 to 29500 and CH 31100 to 31800 and
G     PRR CH 39500. It was agreed that a joint-inspection would take place
      for one crossing, while for the other two crossings it was agreed that the
      PRR project would be raised for clearance height. It was stated:
            “The MD, M/S. Petronet MHB Limited agreed that the PRR
            may be taken over at higher level with a clearance of minimum
H           5.20 m from the ground level and the crossing shall be preferably
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                                805
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

       at right angles. He also insisted that no supports shall be constructed   A
       within their Right of user (ROU) of 18.00.”
       In this view of the matter, the appellant sought to take adequate
precautions to ensure that the proposed PRR project did not cross a
pipeline and where it did, it was at a sufficient height without the use of
support pillars. The respondent contended that that the appellant was            B
constrained to revert to the proposed alignment prior to the meeting by
virtue of various orders passed by the High Court of Karnataka. This
shall be dealt with in the directions which this Court seeks to issue.
       H Appraisal by the SEAC
        71. In addition to the finding that the SEAC erred in recommending       C
to the SEIAA the grant of EC on the basis of an expired ToR and primary
data, there is another aspect of the matter that warrants the attention of
this Court. The SEAC, in its 121st meeting between 11 – 18 November
2014 proceeded to recommend to the SEIAA the grant of EC for the
PRR project. Appraisal by the SEAC is structured and defined by the              D
2006 Notification. At this stage, the SEAC is required to conduct “a
detailed scrutiny” of the application and other documents including the
EIA report submitted by the applicant for the grant of an EC. Upon the
completion of the appraisal process, the SEAC makes “categorical
recommendations” to the SEIAA either for: (i) the grant of a prior EC
on stipulated terms and conditions; or (ii) the rejection of the application.    E
Significantly, the recommendations made by the SEAC for the grant of
EC, are normally accepted by the SEIAA and must be based on
“reasons”. At its 121st meeting, the SEAC recorded the following reasons
for its recommendations:
       “PP and environmental consultant were present in the meeting.             F
       PP stated that the project was conceived and the consultant was
       engaged in 2003 prior to 2006 EIA Notification. Now JICA is
       insisting for EC.
       PP have submitted the compliance for the above queries raised
                                                                                 G
       by the committee vide their letter dated 12.11.2014.
       After due deliberations the committee decided to recommend the
       proposal to SEIAA for consideration to issue EC.
       PP has submitted an undertaking on the day of the meeting on the
       following points:                                                         H
806             SUPREME COURT REPORTS                               [2020] 5 S.C.R.


A                1. To provide pedestrian crossings in the utility crossings facility
                    taking all the precautions.
                 2. Adequate CD works
                 3. To maintain Raja Kalave
B                4. To take up afforestation work separately
                 5. Major crossings of NH/SH/MDR/VR
                 6. Accessibility to proposed road from all villages without
                    charging toll.
             Action to be taken: Secretary, SEAC to submit the proposal to
C
             SEIAA accordingly.”
             72. The reasons furnished by the SEAC must be assessed with
      reference to the norm that it is required to submit reasons for its
      recommendation.The analysis by the SEAC is, to say the least, both
      perfunctory and fails to disclose the reasons upon which it recommended
D
      to the SEIAA the grant of EC for the PRR project. The SEAC proceeds
      merely on the reply furnished by the appellant to the queries raised by
      the SEAC at its 115th meeting dated 11-12 August, 2014. In this view,
      the procedure followed by the SEAC suffers from a non-application of
      mind.
E
             73. The SEAC is under an obligation to record the specific reasons
      upon which it recommends the grant of an EC.The requirement that the
      SEAC must record reasons, besides being mandatory under the 2006
      Notification, is of significance for two reasons: (i) The SEAC makes a
      recommendation to the SEIAA in terms of the 2006 Notification. The
F     regulatory authority has to consider the recommendation and convey its
      decision to the project proponent. The regulatory authority, as para 8(ii)
      of the 2006 Notification provides 18, shall normally accept the
      recommendations of the EAC. Thus, the role of the SEAC in the grant
      of the EC for a proposed project is crucial; and (ii) The grant of an EC
      is subject to an appeal before the NGT under Section 16 of the NGT Act
G     2010. The reasons furnished by the SEAC constitute the link upon which
      the SEIAA either grants or rejects the EC. The reasons form the material
      which will be considered by the NGT when it considers a challenge to
      the grant of an EC.
      18
        ‘‘(ii) The regulatory authority shall normally accept the recommendations of the
H     Expert Appraisal Committee or State Level Expert Appraisal Commitee concerned...’’
     BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                                807
       HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

       74. In Shreeranganathan K P v Union of India19, the grant of                 A
an EC to the KGS Aranmula International Airport Project was challenged.
The NGT found fault with the process leading upto the grant of the EC
since sector specific issues had not been dealt with. The NGT extensively
reviewed the information submitted with regard to the construction of
the airport and held thus:
                                                                                    B
          “182. … a duty is cast upon the EAC or SEAC as the case may
          be to apply the cardinal principle of Sustainable Development and
          Principle of Precaution while screening, scoping, and appraisal of
          the projects or activities. While so, it is evident in the instant case
          that the EAC has miserably failed in the performance of its duty
          not only as mandated by the EIA Notification, 2006, but has also          C
          disappointed the legal expectations from the same. For a huge
          project as the one in the instant case, the consideration for
          approval has been done in such a cursory and arbitrary
          manner without taking note of the implication and
          importance of environmental issues. …Thus, the EAC has                    D
          not conducted itself as mandated by the EIA Notification,
          2006 since it has not made proper appraisal by considering
          the available materials and objections in order to make
          proper evaluation of the project before making a
          recommendation for grant of EC.”
                                                                                    E
       The Court held that the EAC had not conducted a proper appraisal
given its failure to consider the available material and objections before
it. The EAC had thus failed to conduct a proper evaluation of the project
prior to forwarding to the regulatory authority its recommendation.
       75. In Lafarge Umiam Mining Private Limited v Union of                       F
India,20 an application was made under the 1994 notification for the
grant of an EC to a proposed limestone mining project at Nongtrai Village,
East Khasi Hills District, Meghalaya. A three judge Bench of this Court
rejected the challenge and upheld the grant of the EC to the proposed
project. Chief Justice S H Kapadia noted that the doctrine of
proportionality must be applied to matters concerning the environment               G
as part of judicial review. The principles of judicial review in
environmental matters have been enunciated thus:

19
     2014 ALL (I) NGT Reporter (1) (SZ) 1
20
     (2011) 7 SCC 338                                                               H
808            SUPREME COURT REPORTS                            [2020] 5 S.C.R.


A           “In the circumstances, barring exceptions, decisions relating to
            utilisation of natural resources have to be tested on the anvil of
            the well-recognised principles of judicial review. Have all the
            relevant factors been taken into account? Have any extraneous
            factors influenced the decision? Is the decision strictly in
            accordance with the legislative policy underlying the law (if any)
B
            that governs the field? Is the decision consistent with the principles
            of sustainable development in the sense that has the decision-
            maker taken into account the said principle and, on the basis of
            relevant considerations, arrived at a balanced decision? Thus, the
            Court should review the decision-making process to ensure that
C           the decision of MoEF is fair and fully informed, based on the
            correct principles, and free from any bias or restraint.”
             76. The SEAC, as an expert body, must speak in the manner of
      an expert. Its remit is to apply itself to every relevant aspect of the
      project bearing upon the environment and scrutinise the document
D     submitted to it. The SEAC is duty bound to analyse the EIA report.
      Apart from its failure to repudiate a process conducted beyond the
      prescribed time period stipulated by the MoEF-CC, the SEAC failed to
      apply its mind to the abject failure of the appellant in conducting the EIA
      process leading upto the submission of the EIA report for the grant of
      EC. The SEAC is not required to accept either the EIA report or any
E     clarification sent to it by the project proponent. In the absence of cogent
      reasons by the SEAC for the recommendation of the grant of EC, the
      process by its very nature, together with the outcome, stands vitiated.
            I Courts and the environment

F            77. Courts today are faced with increasing environmental litigation.
      A development project that was conceptualized as early as in the year
      2005 has surfaced before this Court over 15 years later. The period that
      has led up to the present litigation has involved a myriad of decisions and
      processes, each contributing to the delay of a project that was outlined
      to sub-serve a salient development policy of de-congesting the city. Where
G     project proponents and institutions envisaged under the 2006 Notification
      abdicate their duty, it is not only the environment that suffers a serious
      set-back, but also the development of the nation. In the eventual analysis,
      compliance with the deliberative and streamlined process envisaged for
      the protection of the environment ensures a symbiotic relationship between
H     the development of the nation and the protection of the environment.
     BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                              809
       HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

        78. The adversarial system is, by its nature, rights based. In the        A
quest for justice, it is not uncommon to postulate a winning side and a
losing side. In matters of the environment and development however,
there is no trade-off between the two.The protection of the environment
is an inherent component of development and growth. Professor Charles
E Corker of the University of Washington School of Law said in a speech
                                                                                  B
titled “Litigating the Environment – are we overdoing it?”21:
       “My answer is yes. We are overdoing our litigation of the
       environment. I do not mean that there are necessarily too many
       lawsuits being filed on environmental issues, and that we should
       somehow cut back – I would not know how, in any case – the
       number of those suits by ten percent, twenty percent, or fifty             C
       percent. I do mean that a disproportionately large share of attention,
       effort and environmental concern is being focused on lawsuits.
       Lawsuits cannot accomplish, by themselves, solutions to the most
       pressing of our environmental problems. As a result, we are in
       some danger of leaving the most pressing environmental problems            D
       unsolved –or even made worse – because the commotion of
       litigation has persuaded us that something has been accomplished.”
         Professor Corker draws attention to the idea that the environmental
protection goes beyond lawsuits. Where the state and statutory bodies
fail in their duty to comply with the regulatory framework for the protection     E
of the environment, the courts, acting on actions brought by public spirited
individuals are called to invalidate such actions. Equally important
however, is to be cautious that environmental litigation alone is not the
panacea in the quest to ensure sustainable development.
       79. The protection of the environment is premised not only on the          F
active role of courts, but also on robust institutional frameworks within
which every stakeholder complies with its duty to ensure sustainable
development. A framework of environmental governance committed to
the rule of law requires a regime which has effective, accountable and
transparent institutions. Equally important is responsive, inclusive,
participatory and representative decision making. Environmental                   G
governance is founded on the rule of law and emerges from the values
of our Constitution. Where the health of the environment is key to
preserving the right to life as a constitutionally recognized value under
21
  Speech to the Thirteenth Annual Meeting of the Interstate Conference on Water
Problems, Portland, Oregon delivered on 29 October, 1970.                         H
810               SUPREME COURT REPORTS                         [2020] 5 S.C.R.


A     Article 21 of the Constitution, proper structures for environmental decision
      making find expression in the guarantee against arbitrary action and the
      affirmative duty of fair treatment under Article 14 of the Constitution.
      Sustainable development is premised not merely on the redressal of the
      failure of democratic institutions in the protection of the environment,
      but ensuring that such failures do not take place.
B
            80. In the present case, as our analysis has indicated, there has
      been a failure of due process commencing from issuance of the ToR
      and leading to the grant of the EC for the PRR project. The appellant, as
      project proponent sought to rely on an expired ToR and proceeded to
      prepare the final EIA report on the basis of outdated primary data. At
C     the same time, the process leading to the grant of the EC was replete
      with contradictions on the existence of forest land to be diverted for the
      project as well as the number of trees required to be felled.
             81. The SEAC, as an expert body abdicated its role and function
      by relying solely on the responses submitted to it by the appellant and
D     failing to comply with its obligations under the OMs issued by the MoEF-
      CC from time to time.In failing to provide adequate reasons for its
      recommendation to the SEIAA for the grant of an EC, it failed in its
      fundamental duty of ensuring both the application of mind to the materials
      presented to it as well as the furnishing of reasons which it is mandated
E     to do under the 2006 Notification.
            82. In this view of the matter, neither the process of decision
      making nor the decision itself can pass legal muster. Equally, this Court
      must bear in mind the need to balance the development of infrastructure
      and the environment. We are of the view that while the need for a road
F     project is factored into the decision-making calculus, equal emphasis
      should be placed on the prevailing state of the environment. The appeal
      which was filed before the NGT in 2015, was finally disposed of at a
      belated stage only in 2019.
            J Directions
G           83. Bearing in mind the need to bring about a requisite balance,
      we propose to issue the following directions under Article 142 of the
      Constitution:
            (i)     The appellant is directed to conduct a fresh rapid EIA for
                    the proposed PRR project;
H
  BENGALURU DEVELOPMENT AUTHORITY v. MR. SUDHAKAR                              811
    HEGDE [DR. DHANANJAYA Y CHANDRACHUD, J.]

      (ii)    The appellant shall, for the purpose of conducting the rapid     A
              EIA, hire a sector-specific accredited EIA consultant;
      (iii)   The appellant shall have due regard to the various
              deficiencies noted in the present judgment as well as ensure
              that additional precautions are taken to account for the
              prevailing state of the environment;                             B
      (iv)    The appellant shall ensure that the requisite clearances under
              various enactments have been obtained and submitted to
              the SEAC prior to the consideration by it of the information
              submitted by the appellant in accordance with the OMs
              issued by the MoEF-CC from time to time;                         C
      (v)     The SEAC shall thereafter assess the rapid EIA report and
              other information submitted to it by the appellant in
              accordance with the role assigned to it under the 2006
              Notification. If it is of the opinion that the appellant has
              complied with the 2006 Notification as well as the directions    D
              issued by this Court, only then shall it recommend to the
              SEIAA the grant of EC for the proposed project. The SEAC
              and the SEIAA would lay down appropriate conditions
              concerning air, water, noise, land, biological and socio
              economic environment and other conditions it deems fit;
              and                                                              E

      (vi)    The appellant shall consult the requisite authority to ensure
              that no potential damage is caused by the project to the
              petroleum pipelines over which the proposed road may be
              constructed.
                                                                               F
       84. In moulding the above directions, this Court has factored into
its decision-making calculus the fact that the appeal from the judgment
of the NGT was filed by the project proponent and no appeal was filed
by the respondents. The order of the NGT directing the appellant to
conduct a rapid EIA is upheld, though for the reasons which we have
indicated above. We clarify that no other Court or Tribunal shall entertain    G
any challenge to the ultimate decision of the SEAC or the SEIAA. Liberty
is granted to the parties to approach this Court upon any grievance from
the decision of the SEAC or the SEIAA pursuant to the order of this
Court.
                                                                               H
812                SUPREME COURT REPORTS                      [2020] 5 S.C.R.


A           85. The appeal is disposed of in the above terms. There shall be
      no order as to costs.
            Pending application(s), if any, shall stand disposed of.


B     Ankit Gyan                                               Appeal disposed of.




C




D




E




F




G




H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "environmental clearance"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.