Created byFuzzy Cloud

Supreme Court of India

CHAMUNDESHWARI ELECTRICITY SUPPLY COMPANY LTD. (CESC)versusSAISUDHIR ENERGY (CHITRADURGA) PVT. LTD. & ANR.

Citation
2025 INSC 1034
Decided
25 August 2025
Disposal
Appeal(s) allowed

Holding

The Court held that, in the absence of a valid Force Majeure notice and without seeking an extension under Article 5.7, the appellant was entitled to invoke and encash the performance bank guarantee under Article 4.4 of the PPA.

Summary

The case concerned a 10 MW solar power project where Chamundeshwari Electricity Supply Company Ltd. (CESC) entered into a Power Purchase Agreement (PPA) with Saisudhir Energy (Chitradurga) Pvt. Ltd. (the Developer) and relied on Karnataka Power Transmission Corporation Ltd. (KPTCL) to commission two 220 kV evacuation lines. KPTCL admitted that the lines would be commissioned only in August 2015, well beyond the contractual timelines for conditions precedent and commercial operation date. The Developer failed to meet the conditions precedent and did not obtain an extension under Article 5.7 of the PPA nor issue a Force Majeure notice under Article 14.5, prompting CESC to invoke and encash the performance bank guarantee under Article 4.4. The State Commission and APTEL held the delay to be a Force Majeure event and ordered restoration of the guarantee, extension of timelines and tariff renegotiation, which CESC challenged. The Supreme Court held that the contractual provisions, not an automatic extension, governed the parties’ rights; the lack of a valid Force Majeure notice and failure to seek extension meant CESC was entitled to encash the guarantee. Consequently, the Court set aside the orders of the State Commission and APTEL and allowed the appeal.

Issues considered

  • The effect of Respondent No.2/KPTCL’s delay in commissioning the 220 kV evacuation system on the timelines for fulfilment of the conditions precedent and achievement of COD under the PPA
  • The entitlement of the appellant to invoke and encash the performance bank guarantee
  • The sustainability of the State Commission’s finding of Force Majeure in the absence of a notice under Article 14.5 of the PPA
  • The character of the PPA as a contingent contract
  • The competence of the State Commission and APTEL to direct restoration of the bank guarantee, extension of timelines and renegotiation of tariff

Legislation cited

Headnote

Issue for Consideration The following questions arise for determination: (i) the effect of respondent no.2/KPTCL’s delay in commissioning the 220 kV evacuation system upon the timelines stipulated for fulfilment of the CPs and achievement of (ii) the entitlement of appellant to invoke and encash the performance bank guarantee in the facts of the present case; (iii) the sustainability of the finding of Force Majeure recorded by the State Commission in the absence of the contractual notice contemplated under Article 14.5 of the PPA;

Subjects

Delay in commissioning the 220 kV evacuation systemEncashing the performance bank guaranteeForce MajeureContingent contractRestoration of the bank guaranteePower Purchase AgreementLaw of ContractExplicit terms of contractIntention of partiesJurisdiction of the regulatory bodies

Judgment

                [2025] 8 S.C.R. 1493 : 2025 INSC 1034

Chamundeshwari Electricity Supply Company Ltd. (CESC)
                          v.
    Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.
                        (Civil Appeal No. 6888 of 2018)
                                 25 August 2025
           [Sanjay Kumar and Satish Chandra Sharma,* JJ.]


                             Issue for Consideration
       The following questions arise for determination: (i) the effect of
       respondent no.2/KPTCL’s delay in commissioning the 220 kV
       evacuation system upon the timelines stipulated for fulfilment of the
       CPs and achievement of COD under the PPA; (ii) the entitlement of
       appellant to invoke and encash the performance bank guarantee in
       the facts of the present case; (iii) the sustainability of the finding of
       Force Majeure recorded by the State Commission in the absence
       of the contractual notice contemplated under Article 14.5 of the
       PPA; (iv) the character of the PPA as a contingent contract; and
       (v) the competence of the State Commission and the APTEL to
       direct restoration of the bank guarantee, extension of timelines,
       and renegotiation of tariff.

                                    Headnotes†
       Electricity Act, 2003 – APTEL affirmed the order dated
       28.01.2015 of the Karnataka Electricity Regulatory Commission
       (State Commission/KERC), whereby the State Commission
       directed Chamundeshwari Electricity Supply Corporation
       Limited, the appellant herein, to restore to the Developer
       i.e. respondent no.1 herein, the amount realised from the
       encashment of the performance bank guarantee; extend the
       timelines for fulfilment of contractual obligations; and to
       undertake renegotiation of the tariff under the Power Purchase
       Agreement (PPA) for a solar power project:
       Held: 1. Appellant’s invocation and encashment of the performance
       security was in full conformity with the contractual framework under
       the PPA – The non-fulfilment of the respondent no.1/Developer’s
       obligations within the stipulated time, non-seeking of extension
       under Article 5.7 or valid Force Majeure claim under Article 14,
       necessarily attracted Article 4.4 of the PPA – The impugned

* Author
1494                                                          [2025] 8 S.C.R.

                         Supreme Court Reports


    judgment dated 21.03.2018 of the APTEL passed in Appeal No.176
    of 2015, and the order dated 28.01.2015 of the State Commission
    in O.P. No.24 of 2014 are set aside. [Paras 44-45]
    2. The record discloses beyond dispute that the evacuation system,
    integral for delivery of power, was to be executed by respondent
    no.2/KPTCL through the construction of two 220 kV double-circuit
    lines – By its communication dated 19.08.2014, respondent no.2/
    KPTCL itself acknowledged that the lines would be commissioned
    only in August 2015, well beyond the contractual timelines –
    The respondent no.1/Developer submission that such delay,
    being beyond its control, automatically extended the contractual
    schedule, cannot be accepted – The contractual framework does
    not operate on automaticity – Contractual rights and remedies
    must be asserted within the framework of the agreement, not
    dehors it. [Paras 37-38]
    3. Turning then to the invocation of the performance bank guarantee,
    in the present case, supply did not commence within the agreed
    period; no formal extension was obtained under Article 5.7 of the
    PPA; and no notice of Force Majeure was issued under Article
    14.5 of the PPA – The preconditions for invocation of Article 4.4 of
    the PPA thus stood satisfied – Appellant’s invocation of the bank
    guarantee was, therefore, an exercise of a remedy specifically
    conferred by the contract, and to deny it would be to disregard
    the allocation of risk embodied in the PPA. [Para 39]
    4. The finding of Force Majeure by the State Commission cannot
    be sustained for the reason that Article 14.5 of the PPA stipulates
    that the affected party “shall” issue notice within seven days of
    knowledge of the event – This requirement is not merely directory;
    it is a condition precedent for invoking the clause – Even if the
    delay in completion of the evacuation system was beyond the
    respondent no.1/Developer’s control, the appropriate provision
    for relief was Article 5.7, not Article 14 of the PPA – Significantly,
    Article 14.3.1 of the PPA details the events and circumstances
    which constitute Force Majeure and delay in the readiness of the
    evacuation system, even if attributable to Respondent No.2/KPTCL,
    does not constitute a Force Majeure. [Para 40]
    5. The completion of the evacuation system by respondent no.2/
    KPTCL was indeed an uncertain event outside the respondent
    no.1/Developer’s control, and in a practical sense, supply of
    power was dependent upon it – Yet, the PPA does not treat such
[2025] 8 S.C.R.                                                               1495

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

     completion as a condition precedent in law to the Respondent No.1/
     Developer’s obligations – It instead provides specific contractual
     mechanism(s)-Article 5.7 for delays attributable to the appellant
     and Article 14 for events of Force Majeure – Unless relief is sought
     and secured under those provisions, the time-bound obligations
     under the PPA remain enforceable and the Appellant’s remedies
     for default intact. [Para 41]
     6. Finally, as to the competence of the regulatory fora, appellant
     and respondent no. 2/KPTCL, though both State instrumentalities,
     are parties to a commercial contract concluded through competitive
     bidding – Their relationship is governed not by overarching notions
     of equity but by the terms of the PPA – The jurisdiction of the
     regulatory bodies is to ensure compliance with law and to adjudicate
     disputes within the four corners of the contract. [Para 43]

     Law of Contract – Explicit terms of contract – Intention of
     parties:
     Held: It is settled that the explicit terms of a contract are always
     the final word with regard to the intention of the parties – This Court
     has, in a consistent line of judgements, reiterated that regulatory
     or adjudicatory fora cannot, under the guise of equity or fairness,
     rewrite the contractual framework or superimpose obligations alien
     to the agreement – The PPA, being the product of a competitive
     bidding process and having received regulatory approval, must
     be construed and enforced strictly in accordance with its express
     stipulations – To permit otherwise would be to allow the State
     Commission or the APTEL to override the parties own allocation
     of risk under the contract. [Para 42]

                               Case Law Cited
     Venkataraman Krishnamurthy & Anr. v. Lodha Crown Buildmart
     Pvt. Ltd. (2024) 4 SCC 230 – referred to.

                                 List of Acts
     Electricity Act, 2003.

                              List of Keywords
     Delay in commissioning the 220 kV evacuation system; Encashing
     the performance bank guarantee; Force Majeure; Contingent
1496                                                       [2025] 8 S.C.R.

                        Supreme Court Reports


     contract; Restoration of the bank guarantee; Power Purchase
     Agreement; Law of Contract; Explicit terms of contract; Intention
     of parties; Jurisdiction of the regulatory bodies.

                           Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6888
     of 2018
     From the Judgment and Order dated 21.03.2018 of the Appellate
     Tribunal for Electricity at New Delhi in A No. 176 of 2015

                        Appearances for Parties
     Advs. for the Appellant:
     Dhruv Mehta, Sr. Adv., Ms. Garima Jain, Tushar Kanti Mahindroo,
     Arnav Khanna.
     Advs. for the Respondents:
     C. Mohan Rao, Sr. Adv., Gowtham Polanki, Snehasish Mukherjee.

               Judgment / Order of the Supreme Court

                               Judgment

     Satish Chandra Sharma, J.

     STATEMENT OF FACTS
1.   This appeal is arising from the judgment dated 21.03.2018 of the
     Appellate Tribunal for Electricity, New Delhi (the “APTEL”), whereby
     the APTEL has affirmed the order dated 28.01.2015 of the Karnataka
     Electricity Regulatory Commission (the “State Commission”/“KERC”),
     whereby the State Commission directed Chamundeshwari Electricity
     Supply Corporation Limited, the Appellant herein, to restore to the
     Developer i.e. Respondent No. 1 herein, the amount realised from
     the encashment of the performance bank guarantee; extend the
     timelines for fulfilment of contractual obligations; and to undertake
     renegotiation of the tariff under the Power Purchase Agreement (the
     “PPA”) for a solar power project.
2.   The Appellant, Chamundeshwari Electricity Supply Company Limited
     (“Chamundeshwari”/“CESC”), is a distribution licensee wholly owned
     by the State of Karnataka. The Respondent No. 2, Karnataka
[2025] 8 S.C.R.                                                        1497

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

     Power Transmission Corporation Limited (“KPTCL”), is the State
     transmission utility and a statutory corporation. Both entities are State
     instrumentalities engaged in discharging public functions under the
     Electricity Act, 2003. The Respondent No. 1, M/s Saisudhir Energy
     (Chitradurga) Pvt. Ltd. (the “Developer”) a special purpose vehicle
     promoted and incorporated by M/s Saisudhir Energy Limited, a private
     generating company selected pursuant to a competitive bidding
     process for the establishment of a 10 MW solar power project in
     Chitradurga District.
3.   The lis traces its origin to a request for proposal issued by the
     Karnataka Renewable Energy Development Limited (the “KREDL”)
     inviting bids for selection of Solar Power Developers (the “SPDs”) to
     establish grid-connected solar power plants in the State of Karnataka.
     The bidding process was conducted under the aegis of the State’s
     solar policy to promote renewable energy capacity. Pursuant to
     the competitive bidding process, the Respondent No. 1/Developer
     was selected for development of a 10 MW solar photovoltaic power
     project at Thallaku Village, Challakere Taluk, Chitradurga District,
     Karnataka.
4.   On 30.08.2012, Appellant and the Respondent No. 1/Developer
     executed a PPA for procurement of 10 MW solar power at a tariff of
     Rs. 8.49/kWh, approved by KERC. The PPA envisaged achievement
     of Commercial Operation Date (the “COD”) within 12 months from the
     Effective Date, preceded by satisfaction of “Conditions Precedent”
     (the “CPs”) under Article 4 of the PPA, within 240 days.
5.   On 28.05.2013, the parties executed a supplementary PPA, inter alia,
     aligning the commissioning schedule and other contractual timelines
     with the State Commission’s tariff order and clarifying the delivery
     point and interconnection facilities. It reaffirmed that CPs were to
     be fulfilled within 240 days and COD achieved within 12 months
     thereafter. The CPs obliged the Respondent No. 1/Developer to
     acquire land, secure statutory approvals, achieve financial closure,
     enter into connectivity agreements, and ensure readiness of the
     evacuation system in coordination with Respondent No. 2/KPTCL.
6.   The project site was finalised at Village Thallaku, Challakere Taluk,
     Chitradurga. The Respondent No. 1/Developer obtained permission
     under Section 109 of the Karnataka Land Reforms Act for acquisition
1498                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


     of 49.36 acres by the order of the Deputy Commissioner dated
     19.02.2014.
7.   The evacuation scheme prepared by Respondent No. 2/KPTCL
     envisaged connection of the project to the State grid through the
     commissioning of two specific 220 kV double-circuit transmission
     lines: one between Birenhalli and Thallak; and another between
     Hiriyur and Gowribidnur. The readiness of these lines was, in effect, a
     technical and operational precondition for the grant of synchronisation
     approval as outlined in letter dated 06.02.2014.
8.   On 05.04.2014, the Respondent No. 1/Developer sought Appellant’s
     assistance for securing approvals and requested extension of the
     COD, citing delay in Respondent No. 2/KPTCL’s commissioning of
     the 220 kV lines. Vide letter dated 17.05.2014, Appellant stated that
     extension could be considered only on condition of a reduced tariff
     from Rs. 8.49/kWh to Rs. 2.39/kWh. The Respondent No. 1/Developer
     contested this reduction and approached the State Commission
     by way of O.P. No. 24 of 2014, seeking inter-alia; i) restoration of
     the performance bank guarantee; ii) extension of timelines; and
     iii) consequential direction for tariff renegotiation, thereby retaining
     the original tariff. Pertinently, vide an interim order dated 14.11.2014,
     the State Commission directed Appellant herein not to encash the
     performance security/bank guarantee.
9.   During pendency, the Respondent No. 1/Developer addressed further
     letters seeking extension of time for CPs fulfilment, pointing to the
     dependency on Respondent No. 2/KPTCL’s works. In response to a
     Right to Information application, Respondent No. 2/KPTCL confirmed
     that the 220 kV lines were likely to be commissioned only in August
     2015, well beyond the original CP and COD timelines.
10. Due to the inability to evacuate the contracted power, Appellant
    claims to have procured power from alternate sources at higher rates,
    incurring losses to the tune of Rs. 48.65 crores. The Respondent
    No. 1/Developer, on the other hand, faced encashment of the
    performance bank guarantee to the tune of Rs. 24.9 crores despite
    COD being rendered impossible due to Respondent No. 2/KPTCL’s
    admitted delay.
11. Vide final order dated 28.01.2015, the State Commission held
    that the delay in completion of the evacuation system constituted
[2025] 8 S.C.R.                                                      1499

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

     a Force Majeure event under the PPA and accordingly ordered:
     (i) restoration of the encashed performance security to the Respondent
     No. 1/Developer; (ii) extension of the contractual timelines and
     (iii) renegotiation of the project tariff in the light of the revised
     commissioning schedule.
12. Aggrieved by the orders passed by the State Commission, Appellant
    filed Appeal No. 176 of 2015 before the APTEL and APTEL vide the
    impugned order dismissed the appeal filed by the Appellant thereby
    affirming the findings and directions of the State Commission. It is
    against this concurrent view of the fora below that Appellant has
    approached this Court in the present appeal.

     SUBMISSIONS BY THE APPELLANT
13. Learned Senior Counsel appearing for Appellant submits at the outset
    that the dispute cannot be adjudicated without first appreciating
    the essential character of the agreement between the parties. It is
    urged that the PPA, executed on 30.08.2012 and supplementary
    PPA on 28.05.2013, is in its essence a contingent contract within
    the meaning of the Indian Contract Act, 1872 (the “Contract Act”).
    The PPA is a self-contained commercial arrangement concluded
    through competitive bidding. Its terms allocate risk and provide
    specific remedies.
14. Obligation to achieve the COD within the stipulated period is, by the
    very structure of the PPA, inextricably linked to the readiness of the
    evacuation system - a responsibility that rests squarely on Respondent
    No. 2/KPTCL, the State transmission utility. In the absence of such
    readiness, Respondent No. 1 was aware that synchronisation and
    injection of power into the grid is technically impossible.
15. Inviting our attention to Article(s) 4 and 5 of the PPA, learned Senior
    Counsel submits that while Article 4 sets out the CPs to be duly
    complied with by the Respondent No. 1/Developer within the stipulated
    timelines, Article 5 enumerates the substantive obligations to be
    discharged in furtherance of the contractual scheme. It is urged that
    the framework of these provisions does not contemplate any dilution
    of responsibility on the premise that certain elements may require
    coordination with other agencies, or may otherwise lie beyond the
    control of the Respondent No. 1/Developer. The said Article(s), in
    material part, provide as follows:
1500                                                      [2025] 8 S.C.R.

                      Supreme Court Reports


        “ARTICLE 4: CONDITION PRECEDENT

        4.1 Condition Precedent
        Save and except as expressly provided in Articles 4,
        14, 18, 20 or unless the context otherwise requires, the
        respective rights and obligations of the Parties under this
        Agreement shall be subject to the satisfaction in full of
        the conditions precedent specified in this Clause 4 (the
        “Conditions Precedent”) by the Developer within 240 (two
        hundred and forty) days from the Effective Date, unless
        such completion is affected by any Force Majeure event,
        or if any of the activities is specifically waived in writing
        by CESC Mysore.

        4.2 Conditions Precedent for the Developer
        The Conditions Precedent are required to be satisfied
        by the Developer shall be deemed to have been fulfilled
        when the Developer shall have:
             a) obtained all Consents, Clearances and
             Permits required for supply of power to CESC
             Mysore as per the terms of this Agreement;
             b) not Applicable
             c) achieved Financial Closure and provided a
             certificate to CESC Mysore from the lead banker
             to this effect;
             d) made adequate arrangements to connect the
             Power Project switchyard with the Interconnection
             Facilities at the Delivery Point;
             e) obtained power evacuation approval from
             [Karnataka Power Transmission Company
             Limited (“KPTCL”)/CESC Mysore, as the case
             may be];
             f) produced as per the requirements set out in
             Schedule 1, the documentary evidence of having
             the clear title and possession of the land required
             for the Project in the name of Developer;
[2025] 8 S.C.R.                                                       1501

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

                g) fulfilled Technical Requirements for Solar PV
                Project as per the format provided in Schedule
                2 and also provides the documentary evidence
                for the same;
                h) delivered to CESC Mysore from confirmation,
                in original, of compliance with the equity lock-in
                condition as set out in 5.2; and
                i) delivered to CESC Mysore a legal opinion from
                the legal counsel of the Developer with respect
                to the authority of the Developer to enter into
                this Agreement and the enforceability of the
                provisions thereof.
           4.2.1 Developer shall make all reasonable endeavours
           to satisfy the Conditions Precedent within the time
           stipulated and CESC Mysore shall provide to the
           Developer all the reasonable cooperation as may be
           required to the Developer for satisfying the Conditions
           Precedent.
           4.2.2 The Developer shall notify CESC Mysore in writing
           at least once a month on the progress made in satisfying
           the Conditions Precedent. Developer shall promptly inform
           the CESC Mysore when any Conditions Precedent is
           satisfied by it.

           4.3 Damages for delay by the Developer
           In the event that the Developer does not procure
           fulfillment of any or all of the Conditions Precedent set
           forth in Clause 4.2 within the period of 240 days and the
           delay has not occurred for any reasons attributable to
           CESC Mysore or due to Force Majeure, the Developer
           shall pay to CESC Mysore Damages in an amount
           calculated at the rate of 0.2% (zero point two per cent)
           of the Performance Security for each day’s delay until
           the fulfillment of such Conditions Precedent, subject to
           a maximum period of 30 (thirty) days. On expiry of the
           said 30 (thirty) days, CESC Mysore at its discretion may
           terminate this Agreement.
1502                                                    [2025] 8 S.C.R.

                      Supreme Court Reports


        4.4 Performance Security
        a) For due and punctual performance of its obligations
        under this Agreement, relating to the Project, the Developer
        has delivered to CESC Mysore, simultaneously with the
        execution of this Agreement, an irrevocable and revolving
        bank guarantees from a scheduled bank acceptable to
        CESC Mysore for an amount of Rs. 24,90,00,000/- (Rupees
        Twenty Four Crores Ninety Lakhs only) (“Performance
        Security”). The Performance Security is furnished to CESC
        Mysore in the form of three bank guarantees in favour
        of Managing Director of the CESC Mysore as per the
        format provided in Schedule 3 and having validity up to 1
        year from the Commercial Operation Date. The details of
        the bank guarantees furnished towards the Performance
        Security are given below;
        (i) Bank Guarantee No. 2657BG3652012 dated 24 August,
        2012 for an amount of Rs. 4,98,00,000/- (Rupees Four
        Crores Ninety Eight Lakhs only);
        (ii) Bank Guarantee No. 2657BG3662012 dated 24 August,
        2012 for an amount of Rs. 9,96,00,000/- (Rupees Nine
        Crores Ninety Six Lakhs only); and
        (iii) Bank Guarantee No. 2657BG3672012 dated 24 August
        2012 for an amount of Rs. 9,96,00,000/- (Rupees Nine
        Crores Ninety Six Lakhs only).
        b) Appropriation of Performance Security
        Upon occurrence of a Developer Default or failure
        to meet the Conditions Precedent by the Developer,
        CESC Mysore shall, without prejudice to its other
        rights and remedies hereunder or in law, be entitled to
        encash and appropriate the relevant amounts from the
        Performance Security as Damages for such Developer
        Default or Conditions Precedent. Upon such encashment
        and appropriation from the Performance Security, the
        Developer shall, within 30 (thirty) days thereof, replenish,
        in case of partial appropriation, to its original level the
        Performance Security, and in case of appropriation of the
        entire Performance Security provide a fresh Performance
[2025] 8 S.C.R.                                                        1503

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

           Security, as the case may be, and the Developer shall,
           within the time so granted, replenish or furnish fresh
           Performance Security as aforesaid failing which CESC
           Mysore shall be entitled to terminate this Agreement in
           accordance with Article 16.
           c) Release of Performance Security
           Subject to other provisions of this Agreement, CESC
           Mysore shall release the Performance Security, if any
           within 1 year from the Commercial Operation Date.
           The release of the Performance Security shall be without
           prejudice to other rights of CESC Mysore under this
           Agreement.”

           “ARTICLE 5: OBLIGATION OF THE DEVELOPER
           5.1 Obligations of the Developer
           5.1.1 Subject to and on the terms and conditions of
           this Agreement, the Developer shall at its own cost and
           expense;
           a) procure finance for and undertake the designing,
           constructing, erecting, testing, commissioning and
           completing of the Power Project in accordance with the
           Applicable Law and Grid Code observe, fulfill, comply with
           and perform all its obligations set out in this Agreement
           or arising hereunder;
           b) comply with all Applicable Laws and obtain applicable
           Consents, Clearances and Permits (including renewals
           as required) in the performance of its obligations under
           this Agreement and maintaining all Applicable Permits in
           full force and effect during the Term of this Agreement;
           c) commence supply of power up to the Contracted
           Capacity to CESC Mysore no later than the Scheduled
           Commissioning Date and continue the supply of power
           throughout the term of the Agreement;
           d) connect the Power Project switchyard with the
           Interconnection Facilities at the Delivery Point;
1504                                                      [2025] 8 S.C.R.

                       Supreme Court Reports


        e) own the Power Project throughout the Term of Agreement
        and keep it free and clear of encumbrances, except those
        expressly permitted under Article 19; and
        f) comply with the equity lock-in conditions set out in
        Clause 5.2; and
        g) be responsible for all payments related to any taxes,
        cesses, duties or levies imposed by the Government
        Instrumentalities or competent statutory authority on land,
        equipment, material or works of the project to or on the
        electricity consumed by the Project or by itself or on the
        income or assets owned by it;
        h) be responsible for the construction of additional bays
        in case required;
        i) construct and carry out the maintenance of the
        transmission line up to the Delivery Point, during the
        Agreement Period and pay applicable supervision charges
        to the concerned Government Instrumentality;
        j) make arrangements for auxiliary consumption and bear
        all the related costs for the same.
        5.1.2 The Developer shall discharge its obligations
        in accordance with Good Industry Practice and as a
        reasonable and prudent person.
        5.1.3 The Developer shall, at its own cost and expense, in
        addition to and not in derogation of its obligations elsewhere
        set out in this Agreement:
        a) make, or cause to be made, necessary applications to
        the relevant government agencies with such particulars
        and details, as may be required for obtaining Applicable
        Permits and obtain and keep in force and effect such
        Applicable Permits in conformity with the Applicable Laws;
        b) procure, as required, the appropriate proprietary rights,
        licenses, agreements and permissions for materials,
        methods, processes and systems used or incorporated
        into the Power Project;
        c) make reasonable efforts to maintain harmony and good
        industrial relations among the personnel employed by it
[2025] 8 S.C.R.                                                          1505

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

           or its Contractors in connection with the performance of
           its obligations under this Agreement;
           d) ensure and procure that its Contractors comply with all
           Applicable Permits and Applicable Laws in the performance
           by them of any of the Developer’s obligations under this
           Agreement; and
           e) not do or omit to do any act, deed or thing which may
           in any manner be violative of any of the provisions of this
           Agreement.
           5.7 Extensions of Time
           5.7.1 In the event that the Developer is prevented from
           performing its obligations under Clause 5.1 by the
           Scheduled Commissioning Date due to:
                a) any CESC Mysore Event of Default; or
                b) force Majeure Events affecting CESC Mysore;
                or
                c) force Majeure Events affecting the Developer;
           the Scheduled Commissioning Date and the Expiry Date
           shall be deferred, subject to the limit prescribed in Clause
           5.7.2 and Clause 5.7.3 for a reasonable period but not less
           than ‘day for day’ basis, to permit the Developer or CESC
           Mysore through the use of due diligence, to overcome the
           effects of the Force Majeure Events affecting the Developer
           or CESC Mysore, or till such time such Event of Default
           is rectified by CESC Mysore.
           5.7.2 In case of extension occurring due to reasons
           specified in Clause 5.7.1(a), any of the dates specified
           therein can be extended, subject to the condition that the
           Scheduled Commissioning Date would not be extended
           by more than 6 (six) months.
           5.7.3 In case of extension due to reasons specified in
           Article 5.7.1(b) and (c), and if such Force Majeure Event
           continues even after a maximum period of 3 (three) months,
           any of the Parties may choose to terminate the Agreement
           as per the provisions of Article 16.
1506                                                       [2025] 8 S.C.R.

                         Supreme Court Reports


          If the Parties have not agreed, within 30 (thirty) days after
          the affected Party’s performance has ceased to be affected
          by the relevant circumstance, on the time period by which
          the Scheduled Commissioning Date or the Expiry Date
          should be deferred by, any Party may raise the Dispute
          to be resolved in accordance with Article 18.
          5.7.4 As a result of such extension, the Scheduled
          Commissioning Date and the Expiry Date newly determined
          shall be deemed to be the Scheduled Commissioning Date
          and the Expiry Date for the purposes of this Agreement.”
16. Learned Senior Counsel relies on Article 4.4, which expressly entitles
    the Appellant to encash the performance bank guarantee if supply
    does not commence by the Scheduled COD, subject only to relief
    expressly available under the PPA.
17. On the State Commission’s finding of Force Majeure, learned Senior
    Counsel submits that it is both procedurally and substantively
    untenable. Procedurally, Article 14.5 of the PPA makes notice a
    condition precedent. It requires the affected party to notify the other
    within 7 days, with particulars of the event, its effect, and mitigating
    measures. The said Article, in material part, provide as follows:
                “14.5 Notification of Force Majeure Event
                14.5.1 The Affected Party shall give notice to the
                other Party of any event of Force Majeure as soon
                as reasonably practicable, but not later than seven
                (7) days after the date on which such Party knew or
                should reasonably have known of the commencement
                of the event of Force Majeure. If an event of Force
                Majeure results in a breakdown of communications
                rendering it unreasonable to give notice within the
                applicable time limit specified herein, then the Party
                claiming Force Majeure shall give such notice as
                soon as reasonably practicable after reinstatement
                of communications, but not later than one (1) day
                after such reinstatement.
                Provided that such notice shall be a pre-condition
                to the Affected Party’s entitlement to claim relief
                under this Agreement. Such notice shall include full
[2025] 8 S.C.R.                                                          1507

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

                particulars of the event of Force Majeure, its effects
                on the Party claiming relief and the remedial measures
                proposed. The Affected Party shall give the other
                Party regular (and not less than monthly) reports on
                the progress of those remedial measures and such
                other information as the other Party may reasonably
                request about the Force Majeure Event.
                14.5.2 The Affected Party shall give notice to the
                other Party of (i) the cessation of the relevant event
                of Force Majeure; and (ii) the cessation of the effects
                of such event of Force Majeure on the performance
                of its rights or obligations under this Agreement, as
                soon as practicable after becoming aware of each
                of these cessations.”
     17.1 No such notice is ever issued by the Respondent No. 1/
          Developer; Force Majeure is not even a pleaded defence
          before the State Commission. Substantively, the delay is
          caused by another arm of the State, which falls within the
          contractual provision for extension under Article 5.7, not within
          the exculpatory scope of Force Majeure.
18. It is therefore contended that the Respondent No. 1/Developer
    neither obtained an extension under Article 5.7 nor issued a Force
    Majeure notice under Article 14.5 of the PPA. In such circumstances,
    Article 4.4 of the PPA squarely applies. The State Commission erred
    in treating the delay as Force Majeure in the absence of notice
    and specific plea. The PPA is not rendered inoperative merely
    because both the Appellant and Respondent No. 2/KPTCL are
    State instrumentalities; each has distinct contractual and statutory
    obligations.
19. Learned Senior Counsel further contends that the jurisdiction of
    the regulatory bodies does not extend to modifying the terms of a
    concluded commercial contract or to conferring remedies outside
    the framework of the agreement. The invocation of the performance
    bank guarantee was effected strictly in accordance with Article 4.4
    of the PPA, and the amount realised thereunder cannot be undone
    by directions that alter the contractual allocation of risk. The PPA
    contemplates no automatic extension of timelines; any relief was
    required to be sought and obtained under Article 5.7 or by invoking
1508                                                      [2025] 8 S.C.R.

                        Supreme Court Reports


     Article 14.5 of the PPA. The Respondent No. 1/Developer’s omission
     to pursue such contractual recourse forecloses its claim in law.
20. Learned Counsel lastly addresses the events surrounding the interim
    application filed by the Respondent No. 1/Developer before the State
    Commission, wherein the State Commission, by an interim order,
    expressly restrained Appellant from encashing the performance bank
    guarantee pending adjudication. It is urged that such invocation
    was carried out under a bona fide belief that the Respondent
    No. 1/Developer’s persistent failure to satisfy the CPs, coupled with
    the absence of demonstrable progress on site, had already crystallised
    the Appellant’s contractual right under Article 4.4 of the PPA.

     SUBMISSIONS BY THE RESPONDENT(S)
21. In reply, learned Counsel appearing for the Respondents submit
    that the PPA was consciously entered into with full awareness of the
    prevailing transmission network status and the potential timelines
    for completion of evacuation facilities. The CPs under Article 4 and
    obligations under Article 5 of the PPA are casted in absolute terms,
    to be fulfilled within 240 days from the Effective Date, and the
    Respondent No. 1/Developer assumes the commercial risk of timely
    completion. It must be appreciated that the performance of the PPA is
    inextricably contingent upon the timely completion of the evacuation
    system by Respondent No. 2/KPTCL, without which synchronisation
    and supply of power to the grid is technically impossible.
22. He contends that such delay, being beyond the Respondent No. 1/
    Developer’s control, ought to operate as an automatic ground for
    extension of the timelines for fulfilment of the CPs and achievement
    of COD, thereby precluding invocation of Article 4.4 of the PPA. At
    the same time, counsel stresses that the “reasonable cooperation”
    contemplated under Article 4.2.1 is facilitative and cannot be
    construed as shifting upon the Respondent No. 1/Developer the risk
    of delay in transmission works which the contract itself allocates to
    the Appellant’s sphere of responsibility. To construe otherwise would
    distort the contractual allocation of risk and undermine the very
    structure of the PPA.
23. Learned Counsel stresses that developers such as the present
    Respondent routinely account for external dependencies in
    formulating their bids, and the tariff of Rs. 8.49/kWh reflects this
[2025] 8 S.C.R.                                                      1509

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

     risk assessment. The State Commission, in granting extension and
     ordering restoration of the performance bank guarantee, correctly
     applied the agreement in a manner that avoided unjust enrichment
     of the Appellant.
24. Addressing Force Majeure, learned Counsel submits that the delay
    in commissioning the 220 kV evacuation lines is clearly beyond the
    Respondent No. 1/Developer’s control, arising from delays in large-
    scale transmission works executed by Respondent No. 2/KPTCL.
    While a formal notice under Article 14.5 may not have been issued,
    the factual circumstances, including the correspondence placed on
    record, and the admitted position of Respondent No. 2/KPTCL are
    sufficient for the commission to characterise the event as Force
    Majeure. It is argued that absence of such notice, cannot negate the
    substantive defence where the facts are undisputed, and the delay
    is objectively established.
25. Learned Counsel further relies on the conduct of Appellant itself,
    which, according to him, reflects an implicit acknowledgment of the
    dependency upon Respondent No. 2/KPTCL’s transmission works.
    He submits that Appellant not only entertained successive requests
    for extension of time but also engaged in correspondence suggesting
    revision of tariff from Rs. 8.49/kWh to Rs. 2.39/kWh, and actively
    participated in proceedings before the State Commission without
    ever contesting the position that commissioning of the project was
    contingent upon completion of Respondent No. 2/KPTCL’s evacuation
    infrastructure. He contends that it constitutes tacit admission that the
    delay cannot be attributed solely upon Respondent No. 1/Developer.
26. Learned Counsel further submits that the framework of Article 4
    makes it clear that invocation of the performance bank guarantee is
    envisaged as a remedy for performance failures during the operational
    phase of the project, and not for pre-COD breaches of conditions
    precedent, particularly where such breaches are directly caused by
    the Appellant’s own default or that of another State agency. As to the
    performance bank guarantee, the Respondent(s) maintain that its
    encashment in the face of an express interim restraint order dated
    14.11.2014 of the State Commission is per se unlawful.
27. Learned Counsel concludes by submitting that the remedial directions
    contained in the final order of the State Commission: i) requiring
    restoration of the performance bank guarantee; ii) granting extension
1510                                                         [2025] 8 S.C.R.

                         Supreme Court Reports


     of timelines for fulfillment of conditions precedent; and iii) permitting
     renegotiation of tariff are well within its regulatory powers to balance
     contractual obligations keeping in mind the larger public interest of
     securing timely commissioning of renewable energy capacity for
     integration into the grid. The APTEL, in affirming these directions on
     21.03.2018 has committed no error of law warranting interference
     by this Hon’ble Court.

     FINDINGS OF THE STATE COMMISSION AND APTEL
28. The State Commission, vide its final order dated 28.01.2015 in O.P.
    No. 24 of 2014, records that the Respondent No. 1/Developer’s
    inability to achieve the CPs and COD within the contractual timelines
    is directly linked to the non-completion of the 220 kV evacuation
    lines by Respondent No. 2/KPTCL. The commission notes that
    interconnection of the project to the grid was technically impossible
    until such lines were commissioned.
29. Reliance is placed on the RTI reply dated 19.08.2014 from
    Respondent No. 2/KPTCL, which admits that the evacuation lines
    are likely to be commissioned only in August 2015. This, in the State
    Commission’s view, establishes that the delay is not attributable to
    any act or omission of the Respondent No. 1/Developer. Therefore,
    as per the State Commission, the delay in completion of the
    evacuation system was beyond the control of the Respondent
    No. 1/Developer amounting to Force Majeure, thereby justifying
    extension of timelines.
30. In examining the terms of the PPA, the State Commission places
    emphasis on Article 5.7, which contemplates extension of CPs
    timelines where the delay is for reasons solely attributable to the
    Appellant. It holds that the expression Appellant must, in the present
    context, be construed to encompass the acts or omissions of the State
    transmission utility, given its integrated role in enabling evacuation
    of contracted power.
31. On the invocation of the performance bank guarantee, the State
    Commission finds that Appellant proceeded to encash the security
    notwithstanding the subsistence of its interim restraint order. Such
    invocation, it holds, was contrary both to the contractual scheme
    and to the authority of the State Commission. Article 4, in its view,
    must be harmoniously read with the extension mechanism under
[2025] 8 S.C.R.                                                      1511

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

     Article 5.7 of the PPA and the Force Majeure provisions, such that
     invocation is impermissible where the non-performance flows from
     the default of the Appellant or its instrumentalities.
32. Notedly, the State Commission takes the view that the delay in
    readiness of evacuation facilities falls within the definition of Force
    Majeure under the PPA, being an event beyond the reasonable
    control of the Respondent No. 1/Developer. On these findings, the
    commission directed: i) Restoration of the encashed security to the
    Respondent No. 1/Developer; ii) consideration of an extension of
    time for fulfilment of the CPs; and iii) renegotiation of the project
    tariff considering the revised commissioning schedule.
33. Likewise, the APTEL vide its judgement dated 21.03.2018 in Appeal
    No. 176 of 2015, affirmed the decision of the State Commission in
    its entirety. The APTEL records that there is no dispute about the
    fact that the 220 kV evacuation lines are not commissioned within
    the original CP and COD timelines, and that the delay is attributable
    to Respondent No. 2/KPTCL.
34. The APTEL further observed that where the Appellant’s contractual
    performance is inherently dependent on the completion of transmission
    works by Respondent No. 2/KPTCL, a State instrumentality, delay
    by such entity must, for the purposes of Article 5.7 of the PPA, be
    treated as delays attributable to the Appellant.
35. Qua the performance security, the APTEL concurs with the State
    Commission that the right to invocation of the performance security
    under the PPA is not absolute. It must be exercised in accordance
    with the contract as a whole, including provisions that provide relief
    where non-performance is caused by the Appellant’s own default.
    Although a Force Majeure notice under Article 14.5 was not issued,
    the APTEL held that the State Commission was entitled to take judicial
    notice of the facts on record which show that the delay is beyond the
    Respondent No. 1/Developer’s control. In view thereof, the APTEL
    dismissed Appellant’s appeal, thereby upholding the directions for
    restoring the performance bank guarantee; extension of contractual
    timelines; and renegotiations of the tariff.

     ISSUES FOR DETERMINATION AND ANALYSIS
36. Having heard learned Counsel(s) for the parties and upon close
    consideration of the record, the following questions fall for our
1512                                                      [2025] 8 S.C.R.

                        Supreme Court Reports


     determination: (i) the effect of Respondent No. 2/KPTCL’s delay in
     commissioning the 220 kV evacuation system upon the timelines
     stipulated for fulfilment of the CPs and achievement of COD under
     the PPA; (ii) the entitlement of Appellant to invoke and encash the
     performance bank guarantee in the facts of the present case; (iii) the
     sustainability of the finding of Force Majeure recorded by the State
     Commission in the absence of the contractual notice contemplated
     under Article 14.5 of the PPA; (iv) the character of the PPA as a
     contingent contract; and (v) the competence of the State Commission
     and the APTEL to direct restoration of the bank guarantee, extension
     of timelines, and renegotiation of tariff.
37. Article 5.1 of the PPA casts upon the Respondent No. 1/Developer
    the obligation to complete, at its own risk and cost, all activities
    necessary to enable the supply of power to the Appellant. Article 5.7
    provides for extension where delay is “for reasons solely attributable
    to the Appellant”. The record discloses beyond dispute that the
    evacuation system, integral for delivery of power, was to be executed
    by Respondent No. 2/KPTCL through the construction of two 220
    kV double-circuit lines. By its communication dated 19.08.2014,
    Respondent No. 2/KPTCL itself acknowledged that the lines would
    be commissioned only in August 2015, well beyond the contractual
    timelines.
38. The Respondent No. 1/Developer contends that such delay, being
    beyond its control, automatically extended the contractual schedule.
    That submission cannot be accepted. The contractual framework does
    not operate on automaticity. Relief is conditional upon the Respondent
    No. 1/Developer seeking and obtaining an extension under Article 5.7
    of the PPA, which was never done. In the absence of such recourse,
    the timelines under the PPA remained binding. Respondent No. 2/
    KPTCL and Appellant, being both State instrumentalities does not
    alter the position in law. Contractual rights and remedies must be
    asserted within the framework of the agreement, not dehors it.
39. Turning then to the invocation of the performance bank guarantee,
    Article 4.4 of the PPA confers upon the Appellant the right to encash
    the performance security where the Respondent No. 1/Developer
    fails to commence supply by the Scheduled COD, subject to the
    relief(s) expressly available under the PPA, including those relating
    to Force Majeure. In the present case, supply did not commence
[2025] 8 S.C.R.                                                      1513

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

     within the agreed period; no formal extension was obtained under
     Article 5.7 of the PPA; and no notice of Force Majeure was issued
     under Article 14.5 of the PPA. The preconditions for invocation of
     Article 4.4 of the PPA thus stood satisfied. Appellant’s invocation
     of the bank guarantee was, therefore, an exercise of a remedy
     specifically conferred by the contract, and to deny it would be to
     disregard the allocation of risk embodied in the PPA. Pertinently,
     invocation of the bank guarantee by the Appellant was on 12.11.2014
     and the restraining order was passed by the State Commission only
     on 14.11.2014. As the invocation was before the State Commission’s
     order, the performance security of Rs. 23,40,60,000/- was transferred
     to the account of the Appellant on 06.12.2014, which thereafter
     came to be refunded by the Appellant, pursuant to the order of
     the APTEL.
40. The finding of Force Majeure by the State Commission cannot
    be sustained for the reason that Article 14.5 of the PPA stipulates
    that the affected party “shall” issue notice within seven days of
    knowledge of the event. This requirement is not merely directory; it
    is a condition precedent for invoking the clause. Even if the delay in
    completion of the evacuation system was beyond the Respondent
    No. 1/Developer’s control, the appropriate provision for relief was
    Article 5.7, not Article 14 of the PPA. Significantly, Article 14.3.1 of
    the PPA details the events and circumstances which constitute Force
    Majeure and delay in the readiness of the evacuation system, even if
    attributable to Respondent No. 2/KPTCL, does not constitute a Force
    Majeure event, as defined. The omission to pursue contractual relief
    under the correct clause is fatal; it cannot be remedied by recourse
    to a provision inapplicable on its terms.
41. As regards the submission that the PPA is in the nature of a contingent
    contract under the Contract Act, the contention requires careful
    scrutiny. The completion of the evacuation system by Respondent
    No. 2/KPTCL was indeed an uncertain event outside the Respondent
    No. 1/Developer’s control, and in a practical sense, supply of power
    was dependent upon it. Yet, the PPA does not treat such completion
    as a condition precedent in law to the Respondent No. 1/Developer’s
    obligations. It instead provides specific contractual mechanism(s) -
    Article 5.7 for delays attributable to the Appellant and Article 14 for
    events of Force Majeure. Unless relief is sought and secured under
1514                                                     [2025] 8 S.C.R.

                        Supreme Court Reports


     those provisions, the time-bound obligations under the PPA remain
     enforceable and the Appellant’s remedies for default intact.
42. Reliance was also placed before us on the decision of this Court in
    Venkataraman Krishnamurthy & Anr. v. Lodha Crown Buildmart
    Pvt. Ltd., (2024) 4 SCC 230, wherein it was observed that the
    explicit terms of a contract are always the final word with regard to
    the intention of the parties. We find the principle enunciated therein
    to be apposite to the case at hand. This Court has, in a consistent
    line of judgements, reiterated that regulatory or adjudicatory fora
    cannot, under the guise of equity or fairness, rewrite the contractual
    framework or superimpose obligations alien to the agreement. The
    PPA, being the product of a competitive bidding process and having
    received regulatory approval, must be construed and enforced strictly
    in accordance with its express stipulations. To permit otherwise
    would be to allow the State Commission or the APTEL to override
    the parties own allocation of risk under the contract.
43. Finally, as to the competence of the regulatory fora, Appellant and
    Respondent No. 2/KPTCL, though both State instrumentalities, are
    parties to a commercial contract concluded through competitive
    bidding. Their relationship is governed not by overarching notions
    of equity but by the terms of the PPA. The jurisdiction of the
    regulatory bodies is to ensure compliance with law and to adjudicate
    disputes within the four corners of the contract. It does not extend
    to recasting the contractual framework by directing restitution of
    amount lawfully realised under the PPA, or by mandating alterations
    to tariff and timelines in a manner inconsistent with the agreement.
    The directions of the State Commission, affirmed by the APTEL,
    requiring restoration of the performance security, extension of
    contractual timelines, and renegotiation of tariff, transgress the
    limits of that jurisdiction.

     CONCLUSION AND DIRECTIONS
44. In light of the foregoing analysis, this Court is of the view that
    Appellant’s invocation and encashment of the performance security
    was in full conformity with the contractual framework under the PPA.
    The non-fulfilment of the Respondent No. 1/Developer’s obligations
    within the stipulated time, non-seeking of extension under Article 5.7
    or valid Force Majeure claim under Article 14, necessarily attracted
    Article 4.4 of the PPA.
[2025] 8 S.C.R.                                                     1515

     Chamundeshwari Electricity Supply Company Ltd. (CESC) v.
          Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr.

45. Resultantly, the appeal is allowed and the impugned judgment dated
    21.03.2018 of the APTEL passed in Appeal No. 176 of 2015, and
    the order dated 28.01.2015 of the State Commission in O.P. No. 24
    of 2014 are set aside.
46. Pending application(s), if any, shall also stand disposed of. No order
    as to costs.

     Result of the case: Appeal allowed.




     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Delay in commissioning the 220 kV evacuation system"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

CHAMUNDESHWARI ELECTRICITY SUPPLY COMPANY LTD. (CESC) versus SAISUDHIR ENERGY (CHITRADURGA) PVT. LTD. & ANR. — 2025 INSC 1034 - Legal Desk AI