Created byFuzzy Cloud

Supreme Court of India

HARYANA POWER PURCHASE CENTRE (HPPC) AND OTHERSversusGMR KAMALANGA ENERGY LIMITED AND OTHERS

Citation
2025 INSC 1079
Decided
8 September 2025
Disposal
Dismissed

Holding

The Court held that, in the absence of a substantial question of law and given the concurrent factual findings of the CERC and APTEL, the appeals under Section 125 must be dismissed and the orders of the lower bodies upheld.

Summary

The Supreme Court considered two civil appeals challenging the Appellate Tribunal for Electricity's (APTEL) dismissal of appeals that upheld the Central Electricity Regulatory Commission's (CERC) orders directing Haryana utilities to pay supplementary bills for change‑in‑law adjustments. The disputes centered on whether coal supplied under firm and tapering linkages should be apportioned pro‑rata among three distribution companies (Haryana utilities, GRIDCO, and Bihar utilities) and whether GRIDCO needed to be impleaded in the CERC proceedings. The Court reiterated that expert regulatory bodies' findings of fact are to be respected unless they are arbitrary, illegal, or ignore mandatory statutory provisions, and that appeals under Section 125 of the Electricity Act are permissible only on substantial questions of law under CPC Section 100. Finding no substantial question of law and noting the concurrent factual findings of CERC and APTEL, the Court dismissed both appeals and upheld the lower tribunals' orders. The decision emphasized the need to avoid unnecessary litigation and to maintain the balance between generator profitability and consumer protection.

Issues considered

  • When may an appeal under Section 125 of the Electricity Act, 2003 be entertained under the grounds specified in Section 100 of the CPC?
  • Whether the coal allocation under firm and tapering linkages should be apportioned pro‑rata among all three DISCOMs or can be limited to the Haryana utilities alone?
  • Whether GRIDCO, as a party to a Section 62 PPA, needed to be impleaded in the CERC petitions filed under Section 79/63 concerning change‑in‑law adjustments?

Legislation cited

Headnote

663 : 2025 INSC 1079 Haryana Power Purchase Centre (HPPC) and Others v. GMR Kamalanga Energy Limited and Others (Civil Appeal No. 1929 of 2020) 08 September 2025 [B.R. Gavai,* CJI and K. Vinod Chandran, J.] Issue for Consideration The APTEL dismissed the appeals (Appeal no.135 of 2018 along with – Electricity Appeals – When experts bodies like the CERC, the APTEL and the Central Electricity Authority have taken a particular view: Held: When various expert bodies like the CERC, the APTEL and the Central Electricity Authority after considering the relevant material on record

Subjects

Concurrent findings of CERC and APTELElectricity AppealsSection 100 of Code of Civil Procedure, 1908Priority for supply of powerForce majeure eventsChange in law during the operation periodSubstantial question of lawSecond appealComputing the Energy Charge RateNone of the DISCOMS can claim a priorityPower purchase agreementPro rata allocation of coalSlow in interferingExpert bodies

Judgment

                 [2025] 9 S.C.R. 663 : 2025 INSC 1079

      Haryana Power Purchase Centre (HPPC) and Others
                            v.
         GMR Kamalanga Energy Limited and Others
                        (Civil Appeal No. 1929 of 2020)
                              08 September 2025
           [B.R. Gavai,* CJI and K. Vinod Chandran, J.]


                            Issue for Consideration
       The APTEL dismissed the appeals (Appeal no.135 of 2018 along
       with Appeal no.54 of 2019) and upheld the order dated 20.03.2018
       passed by the Central Electricity Regulatory Commission (CERC)
       in Petition No.105/MP/20173.

                                    Headnotes†
       Electricity Act, 2003 – Electricity Appeals – When experts
       bodies like the CERC, the APTEL and the Central Electricity
       Authority have taken a particular view:
       Held: When various expert bodies like the CERC, the APTEL
       and the Central Electricity Authority after considering the relevant
       material on record have taken a particular view, the Court should
       be slow in interfering with the decisions taken by them – Unless
       the Court finds that the expert bodies have failed to take into
       consideration the mandatory statutory provisions or if their decisions
       are based on extraneous considerations or they are ex facie arbitrary
       and illegal, it will not be appropriate for this Court to substitute its
       views with that of the expert bodies. [Para 20]

       Electricity Act, 2003 – s.125 – Code of Civil Procedure, 1908 –
       s.100 – Appeal u/s.125, when permissible:
       Held: The appeal u/s.125 of the 2003 Act is only permissible on
       any of the grounds as specified in s.100 of the CPC – As such,
       it is permissible only on substantial questions of law. [Para 23]

       Electricity Act, 2003 – ss.79, 125 – The two instant appeals
       challenge the same judgment and final order of the APTEL –
       The first appeal being Civil Appeal No. 1929 of 2020 has been


* Author
664                                                               [2025] 9 S.C.R.

                            Supreme Court Reports


       filed by Haryana Power Purchase Centre and two others
       (HPPC) whereas the second appeal being Civil Appeal No.3429
       of 2020 has been filed by one GRIDCO – Earlier, Petition
       No.79/2013 came to be filed by GKEL-respondent no.1 before
       CERC against the Haryana Utilities for compensation due to
       force majeure events and change in law during the operation
       period – In the said petition, the GKEL-respondent no.1 sought
       adjustment of tariff on account of events of Change in Law
       which affected the power project during the operation period
       in order to restore GKEL to the same economic position that
       it would have been in if the concerned events had never
       occurred – CERC vide order dt. 03.02.2016 disposed of the
       said petition by allowing all such claims which fell within the
       parameters of Change in Law events – GKEL had preferred a
       similar petition being Petition No.112/MP/2015 against Bihar
       Utilities, the CERC vide order dt. 07.04.2017 disposed of the
       petition by allowing all such claims – The CERC vide another
       order dated 20.03.2018 disposed of the Petition No. 105 by
       directing the Haryana Utilities to pay the supplementary bills
       raised by GKEL – Appeals before the APTEL – The APTEL
       vide the common judgment and final order dated 20.12.2019
       dismissed both the appeals and upheld the order of the
       CERC – Correctness:
       Held: In the first Appeal No. 1929 of 2020, there are concurrent
       findings of facts not only in the impugned judgment passed by the
       APTEL and the order passed by the CERC in Petition No.105,
       but also in the order dated 03.02.2016 passed by the CERC in
       Petition No.79 during the first round of litigation – The Court will,
       therefore, have to be very slow in interfering with the said findings
       of fact – Unless it is found that the findings are perverse, arbitrary
       or in violation of the statutory provisions, it will not be permissible
       for this Court to interfere with the same – Also, this Court does
       not find any substantial question of law arises for consideration
       in the present appeal – The petition was filed by GKEL seeking
       relief on account of Change in Law on various grounds – One
       of the grounds was with regard to deviations from the New Coal
       Distribution Policy, 2007 (the NCDP) and changes in coal distribution
       policy of the Government of India and Coal India Limited – The
       perusal of paragraphs 54, 55 and 73 of the order passed by the
       CERC dated 03.02.2016 would reveal that it devised a formula
       for computing the Energy Charge Rate which required pro rata
[2025] 9 S.C.R.                                                            665

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

     allocation of coal among all three DISCOMS – It is pertinent to
     note that the Haryana Utilities did not challenge the said order and
     paid the amounts due – The perusal of the aforesaid judgment and
     orders (CERC and APTEL) would reveal that they are based upon
     interpretation of various documents – Considering the concurrent
     findings of fact by the CERC on two different occasions and
     the APTEL in impugned order and also taking into note of the
     communication dated 02.02.2022 issued by MCL, this Court sees
     no merit in the appeal of Haryana Utilities – In the second appeal
     being Civil Appeal No.3429 of 2020 by GRIDCO is concerned, the
     main contention of GRIDCO is that the order dated 03.02.2016
     in Petition No.79 and order dated 20.03.2018 in Petition No.105
     were passed without impleading GRIDCO – It will be relevant to
     note that the PPA with GRIDCO is u/s.62 of the 2003 Act whereas
     the PPAs with the Haryana Utilities and Bihar Utilities are u/s.63
     of the 2003 Act – As such there was no occasion for GKEL to
     implead GRIDCO as a party to the said petitions – Earlier, while
     considering the appeal of Haryana Utilities, this Court has already
     upheld the concurrent findings of the CERC and the APTEL that
     the coal supply from all the sources has to be apportioned amongst
     all the three DISCOMS in proportion to the energy supplied to
     them – None of the DISCOMS can claim a priority for supply of
     power based either on the prior date of agreement or the recital
     as to the source of coal – There is no merit in the present appeal
     as well – Appeals dismissed. [Paras 24, 28, 31, 34, 40, 41, 45]

                              Case Law Cited
     Maharashtra State Electricity Distribution Company Limited v. Adani
     Power Maharashtra Limited and Others [2023] 7 SCR 648 : (2023)
     7 SCC 401 – relied on.
     GMR Warora Energy Limited v. Central Electricity Regulatory
     Commission (CERC) and Others [2023] 8 SCR 183 : (2023) 10
     SCC 401; Uttar Haryana Bijli Vitran Nigam Ltd. & Another v. Adani
     Power (Mundra) Limited and Others [2023] 5 SCR 468 : (2023)
     14 SCC 736; Energy Watchdog v. Central Electricity Regulatory
     Commission and Others [2017] 3 SCR 153 : (2017) 14 SCC
     80 – referred to.
     GMR-Kamalanga Energy Limited v. Dakshin Haryana Bijli Vitran
     Nigam Ltd., 2016 SCC OnLine CERC 43 – referred to.
666                                                            [2025] 9 S.C.R.

                           Supreme Court Reports


                                  List of Acts
       Electricity Act, 2003; Finance Act 2010; Code of Civil Procedure,
       1908; New Coal Distribution Policy, 2007; CERC (Terms and
       Conditions of Tariff) Regulations, 2009.

                               List of Keywords
       Concurrent findings of CERC and APTEL; Electricity Appeals;
       Section 100 of Code of Civil Procedure, 1908; Priority for supply of
       power; Force majeure events; Change in law during the operation
       period; Substantial question of law; Second appeal; Computing the
       Energy Charge Rate; None of the DISCOMS can claim a priority;
       Power purchase agreement; Pro rata allocation of coal; Slow in
       interfering; Expert bodies.

                              Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1929 of 2020
       From the Judgment and Order dated 20.12.2019 of the Appellate
       Tribunal for Electricity at New Delhi in AN No. 135 of 2018
       With
       Civil Appeal No. 3429 of 2020

                           Appearances for Parties
       Advs. for the Appellants:
       M.G. Ramachandran, C. Aryama Sundaram, Sr. Advs., Ms. Poorva
       Saigal, Shubham Arya, Nikunj Dayal, Ms. Pallavi Saigal, Abhishek
       Gupta, Harshwardhan Singh, Raj Kumar Mehta, Ms. Himanshi
       Andley.
       Advs. for the Respondents:
       Dr. Abhishek Manu Singhvi, Damma Seshadri Naidu, S.B.
       Upadhyay, Sr. Advs., Vishrov Mukerjee, Pukhrambam Ramesh
       Kumar, Yashaswi Kant, Ms. Juhi Senguttuvan, Ms. Priyanka
       Vyas, L. Nidhiram Sharma, Avishkar Singhvi, Karun Sharma,
       Ms. Rajkumari Divyasana, Vishrov Mukerjee, Pukhrambam Ramesh
       Kumar, Yashaswi Kant, Ms. Juhi Senguttuvan, Ms. Priyanka Vyas,
       L. Nidhiram Sharma, Avishkar Singhvi, Karun Sharma,
       Ms. Rajkumari Divyasana, Ms. Prerna Singh, Ravi Kishore, Guntur
       Prabhakar, Raj Kumar Mehta, Ms. Himanshi Andley, Nishant Kumar,
       Abhinav Kathulia, Ms. Anisha Upadhyay.
[2025] 9 S.C.R.                                                           667

            Haryana Power Purchase Centre (HPPC) and Others v.
                GMR Kamalanga Energy Limited and Others

                       Judgment / Order of the Supreme Court

                                               Judgment

       B.R. Gavai, CJI.

       FACTUAL ASPECTS
1.     These appeals take exception to the judgment and final order dated
       20th December 2019 passed by the Appellate Tribunal for Electricity,
       New Delhi1 in Appeal No. 135 of 2018 along with Appeal No. 54
       of 2019, whereby the learned APTEL dismissed the said appeals
       and upheld the order dated 20th March 2018 passed by the Central
       Electricity Regulatory Commission, New Delhi2 in Petition No. 105/
       MP/20173.
2.     We have two appeals before us, both of which challenge the same
       judgment and final order of the learned APTEL. The first appeal
       being Civil Appeal No. 1929 of 2020 has been filed by Haryana
       Power Purchase Centre and two others4 whereas the second appeal
       being Civil Appeal No. 3429 of 2020 has been filed by one GRID
       Corporation of Orissa Limited5. For the sake of clarity and to avoid any
       confusion, the parties will be referred to according to their positions
       in the first of the two civil appeals.
3.     Before we proceed with the facts of the case, it would be apposite
       to give a brief overview of the parties before us.
       3.1 HPCC (Appellant No.1) is the nodal agency for the procurement
           of power on behalf of the distribution licensees in the State of
           Haryana, being Dakshin Haryana Bijli Vitran Nigam Limited
           (Appellant No.2) and Uttar Haryana Bijli Vitran Nigam Limited
           (Appellant No.3). Haryana Power Generation Corporation
           Limited (Proforma Respondent No.6) is the body corporate
           that was responsible for the initiation of the competitive bid
           process on behalf of Appellant Nos. 2 and 3 for procurement


1    Hereinafter referred to as the ‘APTEL’
2    Hereinafter referred to as the ‘CERC’
3    Hereinafter referred to as ‘Petition No. 105’
4    Hereinafter referred to as the ‘HPCC’
5    Hereinafter referred to as ‘GRIDCO’
668                                                          [2025] 9 S.C.R.

                                      Supreme Court Reports


               of power in the State of Haryana. Together, the said parties
               may be referred to as the “Haryana Utilities”.
       3.2 GMR Kamalanga Energy Limited 6 (Respondent No.1) is a
           generating company within the meaning of the Electricity Act,
           20037. Notably, GKEL is a special purpose vehicle of GMR
           Energy Limited8 which was the predecessor-in-interest of the
           Respondent No.1.
       3.3 PTC India Limited9 (Respondent No.2) is a trading licensee
           within the meaning of the 2003 Act. Respondent No. 2 had an
           arrangement with GKEL for the procurement of power.
       3.4 CERC (Respondent No.3) is the regulatory commission under
           the 2003 Act.
       3.5 GRIDCO (Respondent No.4) is a licensee under the 2003 Act
           which is responsible for procuring power for supply within the
           State of Odisha.
       3.6 Similarly, Bihar State Power (Holding) Company10 (Respondent
           No.5) is a licensee under the 2003 Act which is responsible for
           procuring power for supply within the State of Bihar.
4.     Having given a brief overview of the parties in the civil appeals, we
       may now proceed to examine the facts which lead to the present
       appeals. The facts are as follows:-
       4.1 With the intention to set up a thermal power plant of about 1,000
           MW comprising of two units of about 500 MW each at village
           Kamalanga, Dhenkanal in the State of Odisha, GEL entered into
           a Memorandum of Understanding (MoU) with the Government of
           Odisha on 9th June 2006. Per the terms of the MoU, the power
           project as envisaged was to operate with coal as the primary
           fuel, for which purpose the State of Odisha was to either allot
           coal blocks upon receipt of sanction from the Government of
           India or allot long-term coal linkage of such quality and quantity



6    Hereinafter referred to as ‘GKEL’
7    Hereinafter referred to as the ‘2003 Act’
8    Hereinafter referred to as ‘GEL’
9    Hereinafter referred to as ‘PTC’
10   Hereinafter referred to as ‘Bihar Utilities’
[2025] 9 S.C.R.                                                           669

            Haryana Power Purchase Centre (HPPC) and Others v.
                GMR Kamalanga Energy Limited and Others

               as required for the project. The MoU further necessitated that
               a nominated agency authorized by the Government of Odisha
               would have the right to purchase up to 25% of power sent
               out from the thermal power plants. While initially, the MoU
               envisaged the setting up of thermal plants with an aggregate
               capacity of 1,000 MW (500 x 2), by way of alteration carried
               out subsequently, it was decided that GKEL would develop
               four power plants each having a capacity of 350 MW. Three
               out of the four said units have been installed, however, the
               fourth unit of 350 MW is yet to be installed. Subsequently, this
               project was accorded the Mega Power Project status by the
               Ministry of Power, Government of India vide its letter dated 1st
               February 2012.
       4.2 In terms of the MoU, on 28th September 2006, GKEL executed
           a Power Purchase Agreement with GRIDCO (Respondent No.4)
           being the nominated agency of the State of Odisha for the sale
           of 25% of the gross power generated by GKEL to GRIDCO,
           which came to 262.5 MW, upon the installed capacity reaching
           1050 MW (350 MW x 3).
       4.3 Thereafter, on 5th January 2007, GKEL addressed a letter to the
           Government of Odisha requesting the State Government for a
           recommendation to the Ministry of Coal, Government of India
           for the allotment of long-term coal linkage in favour of GKEL.
           Accordingly, the Department of Energy, Government of Odisha
           vide letters dated 19th December 2005 and 12th January 2007
           pursued the matter with the Government of India.
       4.4 While this was underway, on 1st March 2007, the Haryana
           Power Generation Corporation (Respondent No.6) issued a
           Request for Proposal11 on behalf of the Haryana Utilities for
           procurement of 2,000 MW power on a long-term basis. The
           said RfP envisaged the procurement of power by way of a
           tariff-based bidding process as provided for under Section 63
           of the 2003 Act. In order to qualify for the bid, all the bidders
           were required to submit proof of fuel arrangements in terms of
           Clauses 2.1.5 and 2.1.5 A of the RfP which read thus: -



11   Hereinafter referred to as ‘RfP’
670                                                                [2025] 9 S.C.R.

                                   Supreme Court Reports


                      “2.1.5 All Bidders are required to submit copies of
                      one or more of the following :-
                      (a) Linkage letter from the fuel supplier; or
                      (b) Fuel Supply Agreement between the Bidder and
                      Fuel Supplier; or
                      (c) Coal Block Allocation letter/In principle approval
                      for allocation of captive block from Ministry of Coal; or
                      (d) Other details submitted by Bidders subject to
                      acceptance by the Procurer as sufficient proof for
                      demonstration of ability,
                      The above proof of fuel arrangement is not required in
                      case the fuel to be used by the Bidder is imported fuel.
                      2.1.5 A The Successful Bidder is required to show a
                      firm fuel supply agreement/linkage by the time limit
                      specified for fulfilment of Conditions Subsequent as
                      mentioned in the PPA”
       4.5 Subsequently, the Standing Linkage Committee (Long Term)12
           of the Government of India in a meeting dated 2nd August 2007
           approved a firm coal linkage of 2.14 MTPA13 for a 500 MW
           power plant as had been originally envisaged under the 1,000
           MW (500 MW x 2) configuration.
       4.6 In addition to the said approval, the Ministry of Coal, Government
           of India intimated its decision to allocate Rampia and Dip Side
           Rampia coal blocks in Odisha to a consortium of six generating
           companies including GEL. GEL’s share was 4.6 MTPA which
           corresponded to the project capacity of 1,000 MW. The
           approval came to pass when the Ministry of Coal, Government
           of India confirmed the allotment of the said coal blocks to the
           aforementioned consortium vide letter dated 17th January 2008.
       4.7 In the meanwhile, on 31st October 2007, GEL entered into an
           agreement with PTC in order to enable the latter to participate
           in the bidding process initiated by Haryana Power Generation


12   Hereinafter referred to as ‘SLC-LT’
13   Short for ‘million tonnes per annum’
[2025] 9 S.C.R.                                                          671

            Haryana Power Purchase Centre (HPPC) and Others v.
                GMR Kamalanga Energy Limited and Others

               Corporation (Respondent No. 6) by way of the RfP. In pursuit of
               the same, PTC submitted its bid for sale of 300 MW of power
               to the Haryana Utilities and the bid was accepted. Thereafter,
               vide an order dated 31st July 2008, the Haryana Electricity
               Regulatory Commission (HERC) adopted the tariff successful
               bidders including PTC under Section 63 of the 2003 Act.
       4.8 Subsequently, upon the allocation of the Rampia and Dip Side
           Rampia coal blocks to GEL and the remaining allottees of the
           consortium, Mahanadi Coalfields Limited14 issued a Letter of
           Assurance15 dated 25th July 2008 in favour of GEL for providing
           firm linkage of 2.14 MPTA coal, being the normative requirement
           of one of the power plants having capacity of 500 MW.
       4.9 Thereafter, on 7th August 2008, PTC executed two separate
           Power Purchase Agreements16 with the Dakshin Haryana Bijli
           Vitran Nigam Limited (Appellant No.2) and Uttar Haryana Bijli
           Vitran Nigam Limited (Appellant No.3) for supply of 150 MW
           of power to each, aggregating to 300 MW with the Haryana
           STU-Inter Connection Point being the delivery point. Notably, the
           fuel type proposed to be utilized was Coal India Limited (CIL)
           coal linkage and it was proposed to be sourced from the MCL.
     4.10 As the captive coal from Rampia and Dip Side Rampia had not
          become available, on 12th November 2008, the SLC-LT approved
          the tapering coal linkage of 2.384 MTPA for 550 MW of the
          power project, against the coal block allocation to the concerned
          project. In view of the same, on 8th July 2009, MCL issued a
          LoA to GEL providing tapering linkage as aforementioned till
          captive coal blocks became available.
     4.11 Subsequently, as aforementioned, GKEL and GRIDCO executed
          an amended and restated PPA on 4th January 2011 which altered
          the configuration of the thermal power plants and their output
          capacity, while keeping intact the entitlement of GRIDCO to
          25% gross power generated by GKEL.
     4.12 On 9th November 2011, GKEL entered into a PPA with Bihar
          State Electricity Board, being the predecessor to Bihar Utilities


14   Hereinafter referred to as ‘MCL’
15   Hereinafter referred to as ‘LoA’
16   Hereinafter referred to as ‘PPA’
672                                                          [2025] 9 S.C.R.

                                     Supreme Court Reports


               for supply of 260 MW of net power/282 MW of gross power. Per
               the said PPA, the fuel source proposed to be utilized was Coal
               India Limited (CIL) coal linkage and the coal was proposed to
               be sourced from MCL and the Rampia and Dip Side Rampia
               coal blocks allocated to GKEL.
     4.13 Thereafter, on 26th March 2013, MCL signed a Fuel Supply
          Agreement17 with GKEL for supply of coal to the power plants
          (3 x 350 MW) being 500 MW under normal linkage and 425
          MW generation capacity covered under long term PPA i.e., an
          aggregate of 1.819 MTPA/18.19 lakh tonnes. The FSA was
          amended from time to time, initially to increase the quantum
          of coal supplied from 1.819 MTPA to 2.0009 MTPA for the
          same capacity of 425 MW and thereafter, the FSA was further
          amended on 18th September 2014 to increase the quantum of
          coal supplied to 2.14 MTPA on account of operationalization
          of the PPA with Bihar Utilities.
     4.14 Subsequently, on 28th August 2013, GKEL entered into another
          independent FSA with MCL for tapering linkage.
     4.15 In the meanwhile, on 23rd April 2013, GKEL preferred Petition
          No. 79/MP/201318 before the CERC against Haryana Utilities,
          being a petition under Section 79 of the 2003 Act read with the
          statutory framework governing the procurement of power through
          the competitive bidding process and Articles 12, 13 and 17 of
          the PPA dated 7th August 2008 executed between PTC and the
          Haryana Utilities and the back-to-back PPA dated 12th March
          2009 executed between GEL and PTC for compensation due to
          force majeure events and Change in Law during the operation
          period. In the said petition, the GKEL sought adjustment of
          tariff on account of events of Change in Law which affected the
          power project during the operation period in order to restore
          GKEL to the same economic position that it would have been
          in if the concerned events had never occurred. It is notable that
          GRIDCO was not made a party to this petition.
     4.16 Soon thereafter, Unit I of the power project achieved commercial
          operation and GKEL began supplying power to GRIDCO w.e.f.


17   Hereinafter referred to as ‘FSA’
18   Hereinafter referred to as ‘Petition No. 79’
[2025] 9 S.C.R.                                                         673

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

           30th April 2013. Within a few months, Unit II of the power project
           achieved commercial operation and GKEL commenced the
           supply of power to Haryana Utilities w.e.f. 7th February 2014.
           Subsequently, Unit III of the power project achieved commercial
           operation on 25th March 2014 and thereafter GKEL began
           supplying power to Bihar Utilities w.e.f. 1st September 2014.
    4.17 At this stage, it would be apposite to run through the quantum
         of power that was contracted to be delivered under each of the
         long-term PPAs, which are as follows:-
           (a)    Supply of 350 MW of gross power (Stage 1: 262.5 MW
                  and Stage 2: 87.5 MW) to GRIDCO in terms of PPA dated
                  28th September 2006 (as amended on 4th January 2011,
                  with delivery point as Odisha STU Interconnection point).
           (b)    Supply of 350 MW of gross power (300 MW net of
                  transmission losses and auxiliary consumption) to Haryana
                  Utilities based on PPA dated 7th August 2008 and back-
                  to-back PPA dated 12th March 2009 executed between
                  GEL and PTC.
           (c)    Supply of 282 MW of gross power (260 MW net of auxiliary
                  consumption) to Bihar State Electricity Board in term of
                  PPA dated 9th November 2011, with delivery point as the
                  Bihar STU Interconnection point.
    4.18 The CERC vide order dated 3rd February 2016 disposed of the
         Petition No. 79 filed by GKEL in the following terms:-
           (i)    At the time of bid submission, the notified rate of royalty
                  on coal was Rs. 55+5% of ROM price per tonne. This was
                  subsequently increased to an ad-valorem rate of 14% on
                  price of coal. The CERC held that GKEL would be entitled
                  to compensation for the same from Haryana Utilities.
           (ii)   At the time of bid submission, there was no clean energy
                  cess on coal. However, this was subsequently introduced
                  by way of the Finance Act 2010 whereby statutory cess
                  of Rs. 100 per tonne had been levied on coal. This was
                  subsequently reduced to Rs. 50 per tonne. The CERC held
                  that GKEL would be entitled to recover clean energy cess
                  from Haryana Utilities in proportion to the coal consumed
                  for generation and supply of electricity to the appellants.
674                                                              [2025] 9 S.C.R.

                                     Supreme Court Reports


               (iii) At the time of bid submission, there was no excise duty on
                     coal. Excise duty @ 6% on the determined sale price of
                     coal was introduced by the Finance Act 2012. The CERC
                     held that GKEL would be entitled to compensation through
                     adjustment in tariff on account of the freshly applicable
                     excise duty on coal.
               (iv) Owing to shortfall in the linkage coal and also due to
                    transfer of certain quantum of tapering linkage from MCL
                    to Eastern Coalfields Limited, GKEL had to import coal and
                    also source open market coal. This had led to an additional
                    cost of Rs. 46.10 crores in the generation of power for
                    the Haryana Utilities during the months of February and
                    May to July 2014. The CERC held that GKEL would be
                    entitled to compensation for the same and accordingly set
                    out a mechanism for computing the actual additional cost
                    incurred in a month to mitigate the shortfall in linkage coal.
                    The actual compensation payable was to be calculated
                    and certified by the auditor in terms of the method laid
                    down by the CERC.
               (v)     At the time of submission of the bid, the pricing of coal
                       was based on the UHV19 method which was Rs. 400
                       per tonne for F-grade, run-of-mine coal. Thereafter, the
                       Government of India directed a switchover from UHV-
                       based pricing system to GCV20-based pricing system.
                       This led to a significant increase in price. The resultant
                       impact of the change was an increase in cost of Rs. 10.76
                       crores for a full year. The CERC disallowed this claim,
                       holding that any decision affecting the price of inputs for
                       generating electricity including coal could not be covered
                       under Change in Law.
               (vi) GKEL had also raised claims for increase in rail freight
                    charges owing to busy season surcharge and development
                    surcharge. CERC disallowed this claim.



19   Short for ‘Useful Heat Value’
20   Short for ‘Gross Calorific Value’
[2025] 9 S.C.R.                                                             675

            Haryana Power Purchase Centre (HPPC) and Others v.
                GMR Kamalanga Energy Limited and Others

               (vii) GKEL also raised claims towards compensation/payment
                     for increase in MAT21 rate from 11.33% to 20.01% as
                     brought in by the Finance Act, 2012. This claim was also
                     disallowed.
               (viii) A claim was raised by GKEL for payment towards the
                      increase in VAT22 from 4% to 5%. This claim was disallowed.
               (ix) A claim was also raised for payment/compensation owing
                    to increase in water charges, which was disallowed.
     4.19 It is notable that GKEL had preferred a similar petition being
          Petition No. 112/MP/201523 against the Bihar Utilities with regard
          to the PPA executed between the said parties for compensation
          due to Change in Law which impacted revenues and costs
          during the operating period. Vide order dated 7th April 2017,
          the CERC disposed of the petition by allowing all such claims
          which fell within the parameters of Change in Law events.
     4.20 Subsequently, in terms of the order dated 3rd February 2016
          passed in Petition No. 79, GKEL raised supplementary bills
          towards compensation for ‘Change in Law’ events as approved
          by the CERC, by pro-rating coal received from various sources
          for the period commencing from February 2014 onwards. The
          bills were accompanied by Form 15, detailed annexures and
          calculations which clearly showed apportionment of firm linkage
          coal corresponding to respective PPA capacities.
     4.21 Disputing the supplementary bills raised by GKEL, Haryana
          Utilities wrote to PTC on 22nd September 2016 seeking certain
          clarifications as to whether the bills were as per the order of
          the CERC dated 3rd February 2016. GKEL responded to the
          letter on 6th October 2016 wherein it contended that as per
          CERC’s order, it was entitled to claim additional cost incurred
          during a month in respect of imported coal, open market coal
          and tapering coal or any other coal purchased to make up the
          shortfall in the firm linkage coal supplied by MCL.



21   Short for ‘Minimum alternate tax’
22   Short for ‘Value added tax’
23   Hereinafter referred to as ‘Petition No. 112’
676                                                         [2025] 9 S.C.R.

                          Supreme Court Reports


     4.22 Being dissatisfied with the response, Haryana Utilities refused to
          make payments. To resolve the issue, a meeting was held on 25th
          January 2017, however, the matter could not be resolved. In light
          of the same, it was decided by PTC that the supplementary bills
          raised by GKEL for the period between July 2016 to November
          2016 would be considered to be disputed bills.
     4.23 In order to resolve the issue, another meeting was convened
          between the parties on 24th April 2017 wherein it was jointly
          agreed that a clarificatory petition/review petition would be filed
          before the CERC.
     4.24 Thereafter, GKEL preferred Petition No. 105 before the CERC
          under Section 79(1)(b) and (f) of the 2003 Act read with Articles
          11.6 and 17 of the PPA dated 7th August 2008 for the recovery
          of the outstanding amount from the Haryana Utilities raised
          vide supplementary bills.
     4.25 The CERC vide order dated 20th March 2018 disposed of
          the said petition by directing the Haryana Utilities to pay the
          supplementary bills raised by GKEL for the period from July
          2016 to March 2017 along with late payment surcharge as
          per the provisions of the PPA executed between the parties
          within one month. The CERC held, in terms of the previous
          order dated 3rd February 2017 as well as the decision of this
          Court in Energy Watchdog v. Central Electricity Regulatory
          Commission and Others24, GKEL would be eligible for relief for
          any shortfall in the firm linkage and tapering linkage met through
          import and open market coal. To avoid putting GRIDCO and
          Bihar Utilities at a disadvantage, the CERC further directed that
          the firm and tapering linkage coal supplied to GKEL would have
          to be apportioned on a pro rata basis to all the beneficiaries of
          the project and the cost of procurement of coal from alternate
          sources to meet the shortfall would also be apportioned pro
          rata based on power supplied to beneficiaries.
     4.26 Aggrieved thereby, Haryana Utilities preferred Appeal No. 135
          of 2018 before the learned APTEL. Subsequently, GRIDCO
          preferred Appeal No. 54 of 2019 before the learned APTEL.


24   (2017) 14 SCC 80
[2025] 9 S.C.R.                                                         677

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

     4.27 The learned APTEL vide the common judgment and final order
          dated 20th December 2019 dismissed both the appeals and
          upheld the order of the CERC.
     4.28 Hence, these civil appeals under Section 125 of the 2003 Act.

      SUBMISSIONS
5.    We have heard Shri M.G. Ramachandran, learned Senior Counsel
      appearing for the appellants, Dr. Abhishek Manu Singhvi, learned
      Senior Counsel and Shri Vishrov Mukherjee, learned counsel
      appearing for Respondent No.1, Ms. Prerna Singh, learned counsel
      appearing for Respondent No.2, Shri Raj Kumar Mehta, learned
      counsel appearing for Respondent No. 4 and Shri S.B. Upadhyay,
      learned Senior Counsel appearing for Respondent No.5.
6.    Shri Ramchandran, learned Senior Counsel appearing on behalf of
      the Haryana Utilities submitted that from the perusal of the RfP issued
      by Haryana Utilities in March, 2007 and the bid submitted by GKEL
      on 23rd November 2007 through PTC, it is clear that the bidders
      were required to submit the details with regard to fuel arrangement,
      source of fuel among other particulars. It is equally clear that while
      submitting the bid, GKEL had shown the source of fuel to be firm
      linkage granted by way of SLC-LT meeting held on 2nd August 2007.
      It is further submitted that the perusal of PPA dated 7th August 2008
      between Haryana Utilities and PTC would also show that the PPA
      was based on firm linkage coal from MCL. It is submitted that as
      against this, the PPA dated 9th November 2011, entered into by
      GKEL with Bihar Utilities clearly indicated the sources of fuel as
      firm linkage as well as Rampia and Dip Side of Rampia coal block
      allotment (tapering linkage).
7.    Shri Ramchandran further submitted that FSA as well as the LoA in
      favour of GKEL for the first phase was unit specific. It is submitted
      that FSA becomes operational in proportion to the generation covered
      under long term PPAs. It is submitted that at the time when the FSA
      dated 26th March 2013 was signed, even though the linkage was
      for 500 MW, only 425 MW was considered as generation capacity.
      This was so since the PPAs with Haryana Utilities for 300 MW as
      well as with GRIDCO for 125 MW were the only long term PPAs at
      that time. Shri Ramchandran further submitted that subsequently,
      when the Bihar PPA became operational, the capacity under the
678                                                             [2025] 9 S.C.R.

                            Supreme Court Reports


       FSA vis-à-vis firm linkage was modified by specific additional 29.55
       MW (out of a total Bihar PPA capacity of 260 MW).
8.     Shri Ramchandran contended that the Haryana Utilities would be
       entitled to supply of 300 MW of energy from the firm linkage whereas
       GRIDCO would be entitled to supply of 125 MW energy produced
       using the coal available from the firm linkage. It is, therefore, submitted
       that the Haryana Utilities cannot be burdened with the additional cost
       incurred on account of production of coal from the MCL tapering
       linkage. Shri Ramchandran submitted that the difference on account
       of the use of fuel from tapering linkage will have to be borne only
       by the GRIDCO and Bihar Utilities inasmuch as the said coal was
       used for production of power for Unit II of 200 MW and Unit III of 350
       MW. It is, therefore, submitted that both the CERC as well as the
       learned APTEL erred in putting the burden on the Haryana Utilities
       whereas the same should have been apportioned to Bihar Utilities
       and GRIDCO.
9.     Shri Raj Kumar Mehta, learned counsel appearing on behalf of
       GRIDCO submitted that it was the PPA with GRIDCO which came to
       be operationalized first in April 2013. It is submitted that even though
       GRIDCO’s share in the installed capacity of the thermal station of
       GKEL was 25%, the order dated 3rd February 2016 in Petition No. 79
       and order dated 20th March, 2018 in Petition No. 105 were passed
       without impleading GRIDCO. It is submitted that GRIDCO was a
       necessary and proper party as its rights were adversely affected.
       It is submitted that GRIDCO was also not impleaded in the appeal
       being Appeal No. 135 of 2018 filed by the Haryana Utilities before
       the learned APTEL. It is submitted that on account of the order dated
       28th November 2018 of the learned APTEL, GRIDCO came to be
       impleaded in the said appeal.
10. Shri Mehta further submitted that the reasoning given by the learned
    APTEL that since GRIDCO’s PPA was Cost Plus Tariff PPA under
    Section 62 of the 2003 Act whereas the proceedings before the CERC
    and the learned APTEL were initiated seeking compensation on the
    grounds of Change in Law with regard to Haryana Utilities and Bihar
    Utilities which fell under Section 63 of the 2003 Act and therefore,
    GRIDCO was not necessary party, is wholly unsustainable. It is
    submitted that GKEL had specifically prayed for pro rating of linkage
    coal amongst all the three utilities namely GRIDCO, Haryana Utilities
    and Bihar Utilities and as such GRIDCO was a necessary party.
[2025] 9 S.C.R.                                                       679

           Haryana Power Purchase Centre (HPPC) and Others v.
               GMR Kamalanga Energy Limited and Others

11. It is submitted that the project sought to be installed by GKEL was
    at the instance of the Government of Odisha. It is submitted that the
    State of Odisha had provided all the necessary facilities to GKEL
    to install the project. It is therefore submitted that it is the GRIDCO
    which had the first right to the power generated from the coal made
    available from the firm linkage.
12. Dr. Abhishek Manu Singhvi appearing on behalf of the respondent
    No. 1 submitted that the appeals are liable to be dismissed on
    the short ground that they do not raise any substantial question of
    law as is required under Section 125 of the 2003 Act. It is further
    submitted that the order dated 20th March 2018 in Petition No. 105
    is passed by the CERC on the basis of its earlier order dated 3rd
    February, 2016 in Petition No. 79. It is submitted that the CERC in
    Petition No. 79 had clearly held that coal supplied to GKEL under
    linkage by Government of India is to be apportioned on pro rata
    basis to all the three Distribution Companies25 i.e. Haryana Utilities,
    GRIDCO and Bihar Utilities. It is submitted that since the Haryana
    Utilities had not challenged the said order, it was not permissible for
    them to challenge the order passed in Petition No. 105. It is further
    submitted that supply of coal from all the modes of procurement
    has to be considered for the power project inasmuch as allocation
    by Government of India was for the whole project and not specific
    to any particular DISCOM.
13. Dr. Singhvi further submitted that the concurrent orders passed by
    the CERC and the learned APTEL are equitable orders inasmuch
    as it has been held that coal supplied under the linkage is to be
    apportioned on pro rata basis to all the DISCOMS. However, if the
    contentions of the Haryana Utilities are accepted, it will amount to
    burdening the consumers in the State of Odisha and Bihar. It is
    further submitted that if the contentions of both Haryana Utilities and
    GRIDCO are accepted, it will amount to putting the total burden on
    the consumers in the State of Bihar.
14. Dr. Singhvi further contended that the attitude of Haryana Utilities
    is of approbation and reprobation. It is submitted that in the case
    of Uttar Haryana Bijli Vitran Nigam Ltd. & Another v. Adani



25   Hereinafter referred to as ‘DISCOMS’
680                                                         [2025] 9 S.C.R.

                                   Supreme Court Reports


       Power (Mundra) Limited and Others26, this Court noted that after
       accepting before the CERC that they would adopt the methodology
       as given in the case of GMR-Kamalanga Energy Limited v. Dakshin
       Haryana Bijli Vitran Nigam Ltd.27, Haryana Utilities changed their
       stand subsequently.
15. In the totality, Dr. Singhvi submitted that the appeals deserve to be
    dismissed.
16. Shri S.B. Upadhyay, learned Senior Counsel appearing on behalf of
    respondent No. 5 has supported the concurrent orders of the CERC
    and the learned APTEL.

       DISCUSSION AND ANALYSIS
17. At the outset, it can be noticed that all three DISCOMS agree that
    GKEL is entitled to compensation on account of Change in Law
    event. However, the Haryana Utilities and GRIDCO argued that the
    said liability should not come to them but should instead be passed
    on to the other two. It is only the Bihar Utilities which agrees that the
    liability has to be equally shared by all three DISCOMS in proportion
    to the energy supplied to them. We find it appropriate to deal with
    both the appeals separately.

       CIVIL APPEAL NO. 1929 OF 2020
18. Undisputedly, the present appeal filed by Haryana Utilities challenges
    the impugned judgment and final order passed by learned APTEL
    whereby the learned APTEL has upheld the order of the CERC. The
    appeal to this Court has been filed under Section 125 of the 2003
    Act. The perusal of Section 125 shows that the appeal is tenable
    only on the grounds as available under Section 100 of the Code of
    Civil Procedure, 190828, as such, it could be seen that appeal would
    be tenable only on a substantial question of law.
19. One of us (B.R. Gavai, J, as he then was) had an occasion to deal
    with a large batch of electricity appeals pertaining to Change in Law
    event. This Court first decided the common issues involved in the


26   (2023) 14 SCC 736
27   (2016) SCC OnLine CERC 43
28   Hereinafter referred to as “CPC”
[2025] 9 S.C.R.                                                              681

           Haryana Power Purchase Centre (HPPC) and Others v.
               GMR Kamalanga Energy Limited and Others

      said batch of appeals in Maharashtra State Electricity Distribution
      Company Limited v. Adani Power Maharashtra Limited and
      Others29. It would be apposite to refer to following paragraphs of
      the said judgment:
              “118. It could thus be seen that two expert bodies i.e.
              CERC and the learned APTEL have concurrently held, after
              examining the material on record, that the factors of SHR
              and GCV should be considered as per the Regulations or
              actuals, whichever is lower. CERC as well as the State
              Regulatory bodies, after extensive consultation with the
              stakeholders, had specified SHR norms in the respective
              Tariff Regulations. In addition, insofar as GCV is concerned,
              the CEA has opined that the margin of 85-100 kcal/kg
              for a non-pit head station may be considered as a loss
              of GCV measured at wagon top till the point of firing of
              coal in boiler.
              119. In this respect, we may refer to the following
              observations of this Court in Reliance Infrastructure
              Ltd. v. State of Maharashtra [Reliance Infrastructure
              Ltd. v. State of Maharashtra, (2019) 3 SCC 352] : (SCC
              pp. 376-77, paras 38-39)
                     “38. MERC is an expert body which is entrusted
                     with the duty and function to frame regulations,
                     including the terms and conditions for the
                     determination of tariff. The Court, while exercising
                     its power of judicial review, can step in where
                     a case of manifest unreasonableness or
                     arbitrariness is made out. Similarly, where the
                     delegate of the legislature has failed to follow
                     statutory procedures or to take into account
                     factors which it is mandated by the statute to
                     consider or has founded its determination of
                     tariffs on extraneous considerations, the Court
                     in the exercise of its power of judicial review
                     will ensure that the statute is not breached.



29   (2023) 7 SCC 401, hereafter referred to as MSEDCL
682                                                          [2025] 9 S.C.R.

                      Supreme Court Reports


            However, it is no part of the function of the
            Court to substitute its own determination for a
            determination which was made by an expert
            body after due consideration of material
            circumstances.
            39. In Assn. of Industrial Electricity Users v. State of
            A.P. [Assn. of Industrial Electricity Users v. State
            of A.P., (2002) 3 SCC 711] a three-Judge Bench
            of this Court dealt with the fixation of tariffs and
            held thus : (SCC p. 717, para 11)
                  ‘11. We also agree with the High Court
                  [S. Bharat Kumar v. State of A.P., 2000
                  SCC OnLine AP 565 : (2000) 6 ALD 217]
                  that the judicial review in a matter with
                  regard to fixation of tariff has not to be as
                  that of an appellate authority in exercise
                  of its jurisdiction under Article 226 of the
                  Constitution. All that the High Court has to
                  be satisfied with is that the Commission has
                  followed the proper procedure and unless it
                  can be demonstrated that its decision is on
                  the face of it arbitrary or illegal or contrary
                  to the Act, the court will not interfere. Fixing
                  a tariff and providing for cross-subsidy is
                  essentially a matter of policy and normally
                  a court would refrain from interfering with a
                  policy decision unless the power exercised
                  is arbitrary or ex facie bad in law.’ ”

                   ****            ****             ****
       121. Recently, the Constitution Bench of this Court in Vivek
       Narayan Sharma (Demonetisation Case-5 J.) v. Union
       of India [Vivek Narayan Sharma (Demonetisation Case-
       5 J.) v. Union of India, (2023) 3 SCC 1] has held that the
       Courts should be slow in interfering with the decisions
       taken by the experts in the field and unless it is found that
       the expert bodies have failed to take into consideration
       the mandatory statutory provisions or the decisions taken
       are based on extraneous considerations or they are ex
[2025] 9 S.C.R.                                                                683

           Haryana Power Purchase Centre (HPPC) and Others v.
               GMR Kamalanga Energy Limited and Others

             facie arbitrary and illegal, it will not be appropriate for this
             Court to substitute its views with that of the expert bodies.”
20. It can thus be seen that this Court has held that when various
    expert bodies like the CERC, the APTEL and the Central Electricity
    Authority after considering the relevant material on record have
    taken a particular view, the Court should be slow in interfering with
    the decisions taken by them. It has been held that unless the Court
    finds that the expert bodies have failed to take into consideration
    the mandatory statutory provisions or if their decisions are based on
    extraneous considerations or they are ex facie arbitrary and illegal,
    it will not be appropriate for this Court to substitute its views with
    that of the expert bodies.
21. After deciding the common issues involved in the batch of electricity
    appeals in the case of MSEDCL (supra), this Court considered various
    additional issues involved in individual matters pertaining to the
    question of Change in Law event. One such case was GMR Warora
    Energy Limited v. Central Electricity Regulatory Commission
    (CERC) and Others30. This Court in the said case observed thus:
             “VI. Epilogue
             171. Before we part with the judgment, we must note that
             we have come across several appeals in the present batch
             which arise out of concurrent findings of fact arrived at
             by two statutory bodies having expertise in the field. We
             have also found that in some of the matters, the appeals
             have been filed only for the sake of filing the same. We
             also find that several rounds of litigation have taken place
             in some of the proceedings.
             172. Recently, this Court in Maharashtra State Electricity
             Distribution Co. Ltd. v. Adani Power Maharashtra
             Ltd. [Maharashtra State Electricity Distribution Co.
             Ltd. v. Adani Power Maharashtra Ltd., (2023) 7 SCC
             401] has noted that one of the reasons for enacting
             the Electricity Act, 2003 was that the performance of
             the Electricity Boards had deteriorated on account of
             various factors. The Statement of Objects and Reasons


30   (2023) 10 SCC 401
684                                                           [2025] 9 S.C.R.

                         Supreme Court Reports


          of the Electricity Act, 2003 would reveal that one of the
          main features for enactment of the Electricity Act was
          delicensing of generation and freely permitting captive
          generation. In the said judgment, we have recorded the
          statement of the learned Attorney General made in Energy
          Watchdog [Energy Watchdog v. CERC, (2017) 14 SCC 80 :
          (2018) 1 SCC (Civ) 133] that the electricity sector, having
          been privatised, had largely fulfilled the object sought to
          be achieved by the Electricity Act. He had stated that
          delicensed electricity generation resulted in production
          of far greater electricity than was earlier produced. The
          learned Attorney General had further urged the Court not
          to disturb the delicate balance sought to be achieved by
          the Electricity Act i.e. that the producers or generators of
          electricity, in order that they set up power plants, be entitled
          to a reasonable margin of profit and a reasonable return
          on their capital, so that they are induced to set up more
          and more power plants. At the same time, the interests of
          the end-consumers also need to be protected.
          173. However, we find that, in spite of this position,
          litigations after litigations are pursued. Though the
          concurrent orders of statutory expert bodies cannot be
          said to be perverse, arbitrary or in violation of the statutory
          provisions, the same are challenged.”
22. It will also be appropriate to refer to the following observations made
    by this Court in paragraph 181 of the said judgment:
          181. It is further to be noted that the appeal to this Court
          under Section 125 of the Electricity Act, 2003 is only
          permissible on any of the grounds as specified in Section
          100 of the Code of Civil Procedure, 1908. As such, the
          appeal to this Court would be permissible only on substantial
          questions of law. However, as already observed herein,
          even in cases where well-reasoned concurrent orders are
          passed by the Electricity Regulatory Commissions and the
          learned Aptel, the same are challenged by the Discoms as
          well as the generators. On account of pendency of litigation,
          which in some of the cases in this batch has been more
          than 5 years, non-payment of dues would entail paying
[2025] 9 S.C.R.                                                        685

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

           of heavy carrying cost to the generators by the Discoms,
           which, in turn, will be passed over to the end-consumer.
           As a result, it will be the end-consumer who would be at
           sufferance. We are of the opinion that such unnecessary
           and unwarranted litigation needs to be curbed.
23. This Court in clear terms noted that the appeal under Section
    125 of the 2003 Act is only permissible on any of the grounds as
    specified in Section 100 of the CPC. As such, it is permissible only
    on substantial questions of law. This Court observed that even in
    cases where well-reasoned concurrent orders are passed by the
    Electricity Regulatory Commissions and the learned APTEL, the
    same are challenged by DISCOMS as well as the generators. It has
    been observed that on account of pendency of litigation which in
    some of the cases in the said batch had been for more than 5 years,
    non-payment of dues would result in paying of heavy carrying cost
    to the generators by the DISCOMS. It was observed that, in turn,
    this heavy cost is passed over to the end-consumers who are the
    ultimate sufferers. The Court had in unequivocal terms observed that
    such unnecessary and unwarranted litigations need to be curbed. In
    spite of the aforesaid observations, this Court is flooded with such
    kind of litigations.
24. In the present matter, there are concurrent findings of facts not
    only in the impugned judgment passed by the learned APTEL and
    the order passed by the CERC in Petition No. 105, but also in the
    order dated 3rd February 2016 passed by the CERC in Petition No.
    79 during the first round of litigation. The Court will, therefore, have
    to be very slow in interfering with the said findings of fact. Unless
    it is found that the findings are perverse, arbitrary or in violation of
    the statutory provisions, it will not be permissible for this Court to
    interfere with the same.
25. Though, it was sought to be argued on behalf of the appellants
    that in the present case question of interpretation of the documents
    arises and the same question would fall in the category of substantial
    question of law, we do not find that any substantial question of law
    arises for consideration in the present appeal.
26. Be that as it may, since the present appeal is pending since 2020
    having been admitted on 3rd June 2020, we propose to deal with
    the merits of the matter.
686                                                        [2025] 9 S.C.R.

                          Supreme Court Reports


27. It will be relevant to refer to the Petition No. 79 filed by GKEL before
    the CERC. GKEL contended in the said petition that it had entered
    into three long term PPAs as under:
       a)   Supply of 350 MW gross power (Stage 1: 262.5 MW and Stage
            2: 87.5 MW) to Grid Corporation of Odisha Limited (GRIDCO)
            in terms of PPA dated 28th September 2006 (as amended on 4th
            January 2011 with delivery point as Odisha STU interconnection
            point).
       b)   Supply of 282 MW gross power (260 MW net of auxiliary
            consumption) to Bihar State Electricity Board in terms of PPA
            dated 9th November 2011, with delivery point as the Bihar STU
            interconnection point.
       c)   Supply of 350 MW gross power (300 MW net of transmission
            losses and auxiliary consumption) to Haryana Discoms based
            on the competitive bidding through back-to-back arrangements:
            (i)    The PPAs dated 7th August, 2008 entered into between
                   PTC India Limited and Haryana Discoms with delivery
                   point as Haryana STU bus bar;
            (ii)   Back-to-back PPA dated 12th March, 2009 between GMR
                   Energy Limited (holding company of GKEL) and PTC
                   India Limited.
28. The petition was filed by GKEL seeking relief on account of Change
    in Law on various grounds. One of the grounds was with regard to
    deviations from the New Coal Distribution Policy, 2007 (the NCDP)
    and changes in coal distribution policy of the Government of India
    and Coal India Limited.
29. The issue with regard to firm linkage and tapering linkage in favour of
    GKEL and allocation of captive coal mines in favour of a consortium
    of six companies including GKEL also fell for consideration in the said
    petition. It will also be relevant to refer to the following submissions
    of GKEL recorded by the CERC:
            “6…..
            (a) As regards the firm linkage, the Standing Linkage
            Committee (Long Term) (SLC-LT) approved a coal linkage
            for the project on 2.8.2007 which was communicated to
[2025] 9 S.C.R.                                                            687

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

           the petitioner on 24.9.2007. Letter of Assurance (LOA)
           was issued in favour of GEL on 25.7.2008 for 2.14 MTPA
           of coal for 500 MW capacity of the Power Project. LOA
           was transferred in the name of GEKL by Ministry of Coal
           on 17.2.2011.
           (b) On 6.11.2007, Ministry of Coal conveyed its decision
           to allocate Rampia and Dip Side Rampia coal blocks in
           Odisha to a consortium comprising of GEL and five other
           companies (M/s Sterlite Energy Ltd, M/s Mittal Steel India
           Limited, M/s Lanco Group Limited, M/s Navbharat Power
           Private Ltd, and M/s Reliance Energy Ltd). Ministry of Coal
           vide its letter dated 17.1.2008 made the allocation under
           Section 3(3)(a) (iii) of the Coal Mines (Nationalisation) Act,
           1973 for captive use in the specified end use projects by
           the allocatees. A joint venture company in the name of
           Rampia Coal Mine and Energy Private Limited was formed
           by the allocattees to carry out coal mining in early 2008.
           (c) On 12.11.2008, SLC-LT approved tapering coal linkage
           for the power project based on the recommendation of CEA
           that development of coal block allocated to GEL alongwith
           others was likely to take time. On 8.7.2009, LOA was
           issued for tapering coal linkage of 2.384 MTPA for 550
           MW capacity in favour of GEL till coal from Rampia coal
           block was available. LOA was transferred in the name of
           GEKL by Ministry of Coal on 17.2.2011.
           (d) On 26.3.2013, Mahanadi Coalfield Limited (MCL)
           signed the Fuel Supply Agreement with GEKL for supply
           of 1.819 MTPA of coal per annum.
           7. According to the petitioners, the financial closure of
           the power project was achieved on 29.5.2009 and the
           petitioners went ahead with execution of the project with
           the expected COD of Unit 1 as 25.4.2013 as on the date
           of filing the present petition.
30. In the said petition, the Haryana Utilities had raised a preliminary
    objection on the ground that impact of Change in Law can be
    ascertained only during the operation period, i.e. after the power
    project has been declared under commercial operation. The CERC
    with following observations rejected the said preliminary objection:
688                                                           [2025] 9 S.C.R.

                                   Supreme Court Reports


              “17. According to the Haryana Discoms, the present petition
              is premature since the impact of “Change in Law” can be
              ascertained only during the operation period, that is, after
              the power project has been declared under commercial
              operation. In this regard, it is noted that 1st Unit of the
              power project was commissioned on 30.4.2013 and has
              been taken note of by the Haryana Power Purchase Centre
              (which is responsible for purchase of power on behalf
              of the Haryana Discoms) in its letter dated 20.5.2013.
              Subsequently, in its letter dated 8.8.2013, HPCC in
              response to the petitioner’s offer contained in the letter
              dated 4.7.2013, consented for scheduling of power from
              the Project. The 2nd Unit achieved COD on 12.11.2013 and
              supply to the Haryana Discoms commenced on 7.2.2014.
              3rd Unit achieved COD on 25.3.2014. Since all units of the
              power project have achieved COD, the operating period
              has already commenced, making the petitioners eligible for
              compensation under Change in Law during the operating
              period. The objections of Haryana Discoms on this count
              are disposed of accordingly.”
31. The perusal of paragraphs 54, 55 and 73 of the order passed by
    the CERC dated 3rd February 2016 would reveal that it devised a
    formula for computing the Energy Charge Rate31 which required pro
    rata allocation of coal among all three DISCOMS. It is pertinent to
    note that the Haryana Utilities did not challenge the said order and
    paid the amounts due in terms of the said order till June 2016. The
    Haryana Utilities had accepted the bills which were submitted in
    pursuance to the order passed in Petition No. 79 and a total of about
    Rs. 140 crores were paid till June, 2016. However, in September
    2016, the Haryana Utilities raised the issue of pro rata allocation of
    coal. After due deliberations, Haryana Utilities and GKEL agreed that
    the latter would approach the CERC for clarification in this regard.
    As such, GKEL filed Petition No. 105. The argument of Haryana
    Utilities in the said petition was that coal received under FSA dated
    26th March 2013 should be considered for Haryana Utilities only
    and shortfall in supply thereof should be met through imported,
    open market or tapering coal. However, it was submitted on behalf


31   Hereinafter referred to as ‘ECR’
[2025] 9 S.C.R.                                                          689

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

     of GKEL that the allocation of coal was made for the entire plant of
     GKEL and therefore, coal shall be used proportionately for generation
     and supply of power to all beneficiaries namely GRIDCO, Haryana
     Utilities and Bihar Utilities.
32. The CERC vide order dated 20th March 2018 passed in Petition No.
    105 considered the rival submissions as under:
           “31. On perusal of the documents on record, it emerges
           that the Petitioner was granted firm linkage of 500 MW
           and linkage from captive coal mine for 550 MW for its
           plant which was envisaged to have capacity of 1050
           MW(3x350 MW), Subsequently, LOA dated 25.7.2008
           was issued for firm linkage of 2.14 MTPA for 500 MW
           and LOA dated 8.7.2009 was issued for tapering linkage
           of 2.384 MTPA for 550 MW by Ministry of Coal. Perusal
           of the Standing Linkage Committee (SLC) Minutes of
           Meeting dated 14.2.2012 reveals that the tapering linkage
           of 2.384 MTPA was allocated to the Petitioner for all three
           beneficiaries i.e. GRIDCO, Bihar Discoms and Haryana
           Discoms. The Committee noted that in some cases like
           GMR Kamalanga Energy Ltd., two separate LoAs were
           recommended by the SLC (LT) in different meetings, due
           to change in the configuration/capacity of the unit. The 2nd
           LoA was recommended by the SLC (LT) for the remaining
           capacity arising out of the changed configuration. On the
           recommendation of SLC (LT), the LoAs dated 25.7.2008
           and 8.7.2009 were issued to the Petitioner for 500 MW
           and 550 MW respectively to meet the coal requirement
           for the entire capacity of 1050 MW.
           32. FSA dated 26.3.2013 was entered into by the Petitioner
           with Mahanadi Coalfield Limited for 500 MW of firm linkage
           coal. The Tapering Linkage FSA with MCL was signed
           on 20.5.2014 and Tapering linkage FSA with ECL was
           signed on 29.5.2014. Paras 4.1.1 and 4.2 of the FSA
           dated 26.3.2013 provide as under:
                “4.1.1 The Annual Contracted Quantity of
                Coal agreed to be supplied by the Seller and
                undertaken to be purchased by the Purchaser,
                shall be 18.19 lakh Tes. Per Year from the Seller’s
690                                                      [2025] 9 S.C.R.

                     Supreme Court Reports


            mines and/or from import, as per Schedule I.
            For part of Year, the ACQ shall be prorated
            accordingly. The ACQ shall be in proportion of
            the percentage of Generation covered under long
            term Power Purchase Agreements executed by
            the Purchaser with the DISCOMs either directly
            or through PTC(s) who has/have signed the
            back to back long term PPA(s) with DISCOMs.
            Whenever, there is any change in the percentage
            of PPA(s), corresponding change in ACQ shall
            be effected through a side agreement. Such
            changes shall be allowed to be made only once
            in a year and shall be made effective only from
            the beginning of the next quarter. However, in
            no case ACQ should exceed the LOA quantity
            as mentioned in Schedule I.
            4.2. The total quantity of coal supplied pursuant
            to this Agreement is meant for use at Power Plant
            (3X350 MW), 500 MW under Normal Linkage
            (425 MW generation capacity covered under
            long term PPA). Located at Village-Kamalanga,
            Dt. Dhenkanal, Odhisha as listed in Schedule I.
            The Purchaser shall not sell/divert and/or transfer
            the Coal to any third party for any purpose
            whatsoever and the same shall be treated as
            material breach of Agreement, for which the
            Purchaser, shall be fully responsible and each
            act shall warrant suspension of coal supplies by
            the Seller in terms of Clause 14.1 (b).”
       It is evident from the above provisions of the FSA that the
       total quantum of coal supplied pursuant to the FSA is meant
       for use at the power plant (3x350 MW) of the Petitioner.
       Further, ACQ would be in proportion to the percentage
       of generation covered under long term PPAs either with
       the DISCOMs directly or through PTC which have been
       signed by the Petitioner. Therefore, the FSA cannot be
       for a particular PPA as contended by HPPC. As on the
       date of the FSA, only 425 MW were to be operationalised
       under long term PPAs with PTC/Haryana DISCOMs and
[2025] 9 S.C.R.                                                             691

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

           GRIDCO and accordingly, only 425 MW covered under
           the long term PPAs was mentioned in the FSA. The FSA
           further provides that whenever there is any change in the
           percentage of PPAs, corresponding changes in the ACQ
           shall be effected through side agreements. The FSAs for
           the tapering linkage were signed with MCL on 20.5.2014
           and with ECL on 29.5.2014. These FSAs were signed
           before the commencement of supply under Bihar PPA. The
           Petitioner was receiving 2.58 MTPA of coal from both firm
           and tapering linkage to meet the requirement for 618 MW
           and after operationalization of Bihar PPA, the Petitioner
           received 3.63 MTPA of coal to meet the requirement of
           905 MW. Therefore, any shortfall in the firm linkage as well
           as tapering linkage met through import and open market
           coal shall be eligible for relief under the Change in law
           in the light of the order dated 3.2.2016 and the Hon’ble
           Supreme Court’s judgment in Energy Watchdog case.
           33. In the light of the above discussion, it cannot be
           inferred from the language of para 48 of the order dated
           3.2.2016 that the requirement of Haryana PPA shall be
           met from the firm linkage under the FSA dated 26.3.2013
           and shortfall thereof shall be met through import and open
           market coal. Such an interpretation goes against the coal
           allocation by Ministry of Coal to power plant of the Petitioner
           as a whole and will put the GRIDCO PPA and Bihar PPA
           at a disadvantage vis- a-vis Haryana PPA. In fact, the
           Commission in para 73 (b) of the order dated 3.2.2016 in
           Petition No. 79/MP/2013 had observed as under:
                “73……
                (b) The additional cost incurred in a month due
                to shortage of linkage coal shall be computed on
                ex-bus scheduled energy and shall be pro-rated
                corresponding to the scheduled generation for
                Haryana Discoms as per methodology given in
                para 56 above.”
           Therefore, in light of the allocation of firm as well as
           tapering linkage for all three beneficiaries and our order
           dated 3.2.2016 in Petition No. 79/MP/2013, the firm and
692                                                       [2025] 9 S.C.R.

                       Supreme Court Reports


         tapering linkage coal supplied to the Petitioner has to be
         apportioned on pro rata basis to all beneficiaries of the
         project and the cost of procurement of coal from alternate
         sources to meet the shortfall of firm and tapering linkage
         coal has also to be apportioned pro rata based on power
         supplied to these beneficiaries. Accordingly, the contention
         of Haryana Discoms to appropriate the coal supplied under
         firm linkage towards the capacity being supplied to them
         instead of pro-rata apportionment to all the beneficiaries is
         not correct. The order dated 3.2.2016 has to be read in its
         entirety and HPPC is not correct to pick up an observation
         in para 48 of the said order to claim that Its liability is
         limited to imported/open market coal for the shortage
         in firm linkage coal only. In our view, the Petitioner has
         correctly apportioned the linkage coal to Haryana Discoms
         proportionate to the capacity being supplied to them and
         has issued Supplementary Bills in accordance with the
         formula devised in order dated 3.2.2016 in Petition No.
         79/MP/2013. Accordingly, we direct the respondents to
         pay the supplementary bills raised by the Petitioner for
         the period from July, 2016 to March, 2017 along with late
         payment surcharge as per the provisions of the PPA within
         one month from the date of issue of the order.”
33. The said order came to be challenged by the Haryana Utilities.
    However, at the instance of the learned APTEL, GRIDCO came
    to be impleaded as party respondent in the appeal filed by the
    Haryana Utilities. Subsequently, GRIDCO also filed its own appeal
    before the learned APTEL. It was sought to be contended on behalf
    of the Haryana Utilities that the order passed in Petition No. 105
    was beyond the order dated 3rd February 2016. Rejecting the said
    contention, the learned APTEL by a well-reasoned judgment and
    order observed thus:
         “8.16 The Appellants contention that the Impugned Order
         has gone beyond Order dated 03.02.2016 is incorrect. It
         is evident from Paragraph 33 of the Impugned Order that
         CERC has merely reiterated its earlier Order and upheld
         the bills raised by GKEL in terms of Order dated 03.02.2016
         in Petition No. 79/MP/2013.
[2025] 9 S.C.R.                                                           693

         Haryana Power Purchase Centre (HPPC) and Others v.
             GMR Kamalanga Energy Limited and Others

           Coal supply to Plant as whole and not Procurer Specific
           8.17 GKEL had quoted tariff for Haryana PPAs considering
           coal availability for the Project from linkage coal and its
           own Captive Coal blocks based on
           (a) SLC-LT approval dated 02.08.2007 for 500 MW; and
           (b) Ministry of Coal decision dated 06.11.2007 to allocate
           Rampia and Dip side Rampia coal blocks to GKEL.
           8.18 At the time of bid submission for Haryana, the SBD
           did not permit inclusion of different sources of coal -
           linkage, captive etc. Therefore, GKEL had cited linkage
           from CIL/MCL. Use of coal from the Captive Coal block
           was envisaged for the entire Plant as evident from the
           allocation letter dated 17.01.2008 wherein GKEL share of
           coal reserves is 138 MT @ 4.6 MT for 30 years to meet
           coal requirement of the Project as a whole.
           8.19 Coal supply was to the Project as a whole and not
           Procurer Specific is supported by:-
           (a) The SLC minutes dated 14.02.2012 clearly state that
           the tapering linkage coal of 2.384 MTPA is to be utilized for
           all three PPAs with GRIDCO, Haryana and Bihar Discoms.
           (b) Clause 4.2 of the FSA dated 26.03.2013 signed with
           MCL clearly states that:-
                “the total quantity of coal supplied pursuant to
                this Agreement is meant for use at Power Plant
                (3x350 MW), 500 MW under Normal Linkage
                (425 MW generation capacity covered under
                long term PPA).”
           8.20 It is submitted that LoA and FSA are for the station and
           never for a particular PPA as contended by the Appellants.
           Further, the Appellant’s contention that the apportionment
           of coal (from firm linkage) is to be done proportionally
           between the Appellants (300 MW), GRIDCO (150 MW)
           and Bihar (29.55 MW) is erroneous. It is submitted that
           the end-use stated in these documents is for the Station/
           Plant. This was confirmed by MCL in terms of letter dated
694                                                    [2025] 9 S.C.R.

                     Supreme Court Reports


       02.05.2018 which stated that the Coal is released for
       the total PPA capacity and not bifurcated on the basis of
       individual PPAs.
       8.21 In terms of Clause 4.1 of the FSA, the ACQ shall be
       in proportion of the percentage generation covered under
       long term PPAs with Discoms. The relevant portion of
       Clause 4.1 is reproduced below:-
            “4.1.1... The ACQ shall be in proportion of the
            percentage of Generation covered under long
            term Power Purchase Agreements executed by
            the Purchaser with the DISCOMs either directly
            or through PTC(s) who has/ have signed the
            back to back long term PPA(s) with DISCOMS.”
       It is only commencement of supply of coal which is linked
       to commencement of supply under the PPA. For example,
       if supply of power to Bihar commenced before Haryana, the
       ACQ would have been allocated/operationalized similarly.
       8.22 In view of the above, contention of Haryana that the
       tapering linkage granted in relation to coal block cannot
       be linked to 300 MW is wrong. In fact, the linkage coal/
       coal block or tapering linkage are allocated for the station
       and to be utilized for all three PPAs. In fact, allocating
       coal under the FSA to Haryana Discoms to the exclusion
       of Bihar and GRIDCO will be contrary to the provisions
       of the FSA.
       8.23 As brought out above, the allocation of coal was for
       the Project as a whole and not Procurer/PPA wise. This
       is evident from the following:-
       (a) LOAs dated 25.07.2008 and 08.07.2009 were for the
       plant as a whole.
       (b) Allocation letter dated 17.01.2008 for the Captive Coal
       mine is for 4.6 MT which is sufficient for 1050 MW, being
       the installed capacity of the Project.
       (c) Minutes of the SLC-LT dated 14.02.2012 note that the
       entire linkage (firm and tapering) is for all the 3 PPAs.
[2025] 9 S.C.R.                                                               695

            Haryana Power Purchase Centre (HPPC) and Others v.
                GMR Kamalanga Energy Limited and Others

             (d) Letter dated 02.05.2018 issued by Mahanadi Coalfields
             Limited (“MCL”) states that CIL and its subsidiaries had
             allocated coal to the Project on pro-rata basis vis-à-vis the
             operational capacities and not on basis of procurers. The
             letter specifically states that “in case of multiple PPAs, coal
             is released to the IPPs considering the total PPA capacity
             and not bifurcated on the basis of individual PPAs”. The
             aforesaid only confirms the provision of clause 4.1.1 of
             the FSAs which also talks of allocation of coal on pro-rata
             basis to long term PPAs executed by the Discoms directly
             through PTC.
             8.24 If the Appellant’s contention is upheld, it will lead
             to an anomalous situation wherein GRIDCO and Bihar
             Discoms will end up cross-subsidizing supply of power
             to Haryana Discoms. It is submitted that the Ld. Central
             Commission has rightly allowed pro-rata allocation of
             linkage and alternate coal so as to ensure that the impact
             is equally apportioned.
             8.25 Since the allocation is not PPA specific, allocation
             of coal to one procurer to the exclusion of others will be
             contrary to the terms of such allocation.
             8.26 Further, such action will also be contrary to Article
             14 of the Constitution of India since it will result in equals
             being treated unequally.”
34. It could thus be seen that the present appeal challenges the concurrent
    findings arrived at by the CERC on two different occasions and
    the learned APTEL in the impugned judgment. The perusal of the
    aforesaid judgment and orders would reveal that they are based upon
    interpretation of various documents and considering the following
    factual aspects with respect to fuel arrangements for the Project:
     (i)     The original SLC-LT allocation dated 2nd August 2007 for firm
             linkage was made prior to the Haryana PPA;
     (ii)    Letter dated 6th November 2007 issued by Ministry of Coal
             intimating its decision to allocate Rampia and Dip Side Rampia
             coal blocks in Odisha to a consortium comprising of GKEL and
             five other allotees;
696                                                          [2025] 9 S.C.R.

                                Supreme Court Reports


       (iii) Allocation letter dated 17th January 2008 for the captive coal
             mine is for 4.6 MT which is sufficient for 1050 MW, being the
             installed capacity of the Project; and
       (iv) SLC-LT minutes dated 14th February 2012 noted that the firm
            linkage capacity was intended for Odisha, Bihar and Haryana.
35. It will also be relevant to refer to letter dated 7th February 2022 issued
    by MCL in response to the clarification sought by GKEL on the letters
    dated 2nd May 2018 and 22nd June 2021 of MCL with regard to supply
    of coal to GKEL under FSA dated 26th February 2013. The relevant
    extracts of the said letter are as under:
            “As per the provision of FSA dated 26/03/2013, Annual
            Contracted Quantity (ACQ) under FSA is in proportion to
            the percentage of Generation covered under long term
            Power Purchase Agreement(s) executed by the Purchaser
            (IPP) with DISCOMs against the total LOA quantity. In case
            of multiple PPAs, coal is allocated/ released as per the
            ACQ against the total PPA capacity and not segregated
            on the basis of any specific PPA. The same was clarified
            vide MCL’s letter dated 02.05.2018.
            It is pertinent to mention that letter dated of 22/06/2021 of
            MCL was issued to all concerned DISCOMs, with whom
            M/s GKEL has signed PPA, for the purpose of intimating
            the DISCOMs the quantum of coal procured by M/s GKEL
            under FSA from the sources of MCL to ensure proper
            utilization of coal. The said letter indicates the overall,
            quantity of coal supplied for all the PPAs.”
36. As mentioned earlier, after deciding the common issues involved in
    a batch of electricity appeals in the case of MSEDCL (supra), this
    Court decided various individual matters involving additional issues.
    Another such matter was Uttar Haryana Bijli Vitran (supra). It would
    be pertinent to note that the Haryana Utilities had approached this
    Court challenging the concurrent judgment and order passed by
    learned APTEL dated 3rd November 202032 and CERC dated 31st
    May 201833.


32   2020 SCC OnLine APTEL 92
33   2018 SCC OnLine CERC 411
[2025] 9 S.C.R.                                                                 697

            Haryana Power Purchase Centre (HPPC) and Others v.
                GMR Kamalanga Energy Limited and Others

37. In the said proceedings Adani Power (Mundra) Ltd.34 had filed Petition
    No. 97/MP/201735 before the CERC pursuant to the orders passed
    by this court in Energy Watchdog (supra). The CERC vide order
    dated 31st May 2018 had allowed the said petition and directed the
    working out of the relief. It will be relevant to refer to the following
    paragraphs of the Uttar Haryana Bijli Vitran (supra):
               48. The grievance of Haryana Utilities is that the
               methodology for granting benefit on account of the
               change in law adopted by CERC and affirmed by the
               learned Aptel is contrary to the one which was previously
               arrived at in the earlier cases of GMR, DB Power, etc.
               49. Perusal of the order passed by the learned Aptel would
               reveal that AP(M)L had proposed a methodology based
               on the methodology approved by CERC in the GMR-
               Kamalanga Energy Ltd. v. Dakshin Haryana Bijli Vitran
               Nigam Ltd. [GMR-Kamalanga Energy Ltd. v. Dakshin
               Haryana Bijli Vitran Nigam Ltd., 2016 SCC OnLine CERC
               43] considering the quoted tariff under the PPAs as the
               base.
               50. The learned Aptel had referred to the record of
               proceedings of CERC dated 10-8-2017, which read thus :
               (Uttar Haryana Bijli Vitran Nigam case [Uttar Haryana Bijli
               Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd., 2020
               SCC OnLine APTEL 92] , SCC OnLine APTEL para 7.3)
                       “7.3. … (a) … ‘3. In response to the Commission’s
                       query as to whether the methodology adopted by the
                       petitioner in the light of the methodology given in GMR
                       case [GMR-Kamalanga Energy Ltd. v. Dakshin
                       Haryana Bijli Vitran Nigam Ltd., 2016 SCC OnLine
                       CERC 43] is acceptable to Haryana Utilities, learned
                       counsel replied in the positive.’ ”
                                                      (emphasis in original)

               51. The learned Aptel had also referred to the order of
               CERC dated 28-9-2017 [Adani Power Ltd. v. Uttar Haryana


34   Hereinafter referred to as AP(M)L
35   Hereinafter referred to as ‘Petition No. 97’
698                                                     [2025] 9 S.C.R.

                     Supreme Court Reports


       Bijli Vitaran Nigam Ltd., 2017 SCC OnLine CERC 305] in
       IA No. 57 of 2017 in Petition No. 97/MP/2017, which reads
       thus : (Uttar Haryana Bijli Vitran Nigam case [Uttar Haryana
       Bijli Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd., 2020
       SCC OnLine APTEL 92] , SCC OnLine APTEL para 7.3)
            “7.3. … (b) … ‘7. … Haryana Utilities who is the only
            respondent has not objected to the calculation made
            by the applicant.’ ”
                                            (emphasis in original)

       52. The learned Aptel had also referred to the order dated
       3-12-2018 [Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani
       Power (Mundra) Ltd., 2018 SCC OnLine CERC 237] passed
       by CERC in review petition bearing No. 24/RP/2018, which
       reads thus : (Uttar Haryana Bijli Vitran Nigam case [Uttar
       Haryana Bijli Vitran Nigam Ltd. v. Adani Power (Mundra)
       Ltd., 2020 SCC OnLine APTEL 92] , SCC OnLine APTEL
       para 7.4)
            “7.4. … ‘25. … It is apparent from the above
            that the Commission, after due consideration of
            the submissions of the Adani Power and Prayas
            had consciously decided on the methodology for
            computation of relief due to shortage of domestic coal
            under change in law for the period from 1-4-2013 to
            31-3-2017 in para 46 of the impugned order [Adani
            Power (Mundra) Ltd. v. Uttar Haryana Bijli Vitran Nigam
            Ltd., 2018 SCC OnLine CERC 411] . The review
            petitioners had not suggested any methodology of
            calculation of the relief due to shortage of domestic
            coal. On the other hand, the review petitioners in their
            reply dated 28-7-2017 in Petition No. 97/MP/2017 had
            stated that “the reliance to the decision of GMR is
            wholly inappropriate”. The review petitioners are now
            suggesting an alternative formula for computation of
            the relief under change in law. As already reiterated
            in the earlier part of the order, the review cannot be
            used for substitution of a view already taken with a
            new view. Therefore, the review on the ground is not
            maintainable.’ ”
[2025] 9 S.C.R.                                                              699

          Haryana Power Purchase Centre (HPPC) and Others v.
              GMR Kamalanga Energy Limited and Others

             53. We find that Haryana Utilities are indulging into
             approbation and reprobation. They cannot be permitted
             to blow hot and cold at the same time. After accepting
             before CERC that they would adopt the methodology
             as given in GMR-Kamalanga Energy [GMR-Kamalanga
             Energy Ltd. v. Dakshin Haryana Bijli Vitran Nigam Ltd.,
             2016 SCC OnLine CERC 43] , it would not be appropriate,
             in our view, on the part of the appellants, which are, after
             all, instrumentalities of the State, to change its stand after
             final orders are passed by CERC.”
38. It could thus clearly be seen that the learned APTEL had referred
    to the record of proceedings of the CERC dated 10th August 2017
    wherein to the Commission’s query as to whether the methodology
    adopted by the petitioner in the light of the methodology given in
    GMR Kamalanga (supra) was acceptable to Haryana Utilities,
    learned counsel replied in the positive. The learned APTEL also
    referred to the order of the CERC dated 28th September 201736 in IA
    No. 57 of 2017 in Petition No. 97 wherein Haryana Utilities had not
    objected to the calculation made by the applicant. It could further be
    seen that the learned APTEL had also referred to the order dated
    3rd December 201837 passed by the CERC in Review Petition No.
    24/RP/2018 filed by the Haryana Utilities against the order dated
    31st May 2018 of the CERC. The CERC in the said review petition
    referred to the affidavit filed by the Haryana Utilities stating that ‘the
    reliance to the decision of GMR is wholly inappropriate”. The learned
    APTEL, observing that the Review Petitioners are now suggesting
    an alternative formula for computation of the relief under change in
    law, rejected the review petition.
39. This Court in Uttar Haryana Bijli Vitran (supra) had observed that
    the Haryana Utilities are indulging in approbation and reprobation.
    It has been observed that they cannot be permitted to blow hot
    and cold at the same time. It has further been observed that after
    accepting before the CERC that they would adopt the methodology
    as given in GMR Kamalanga (supra), it would not be appropriate


36   (2017) SCC OnLine CERC 305
37   (2018) SCC OnLine CERC 237
700                                                          [2025] 9 S.C.R.

                          Supreme Court Reports


       on the part of Haryana Utilities to change its stand after final orders
       were passed by the CERC. This Court had therefore dismissed the
       appeal of the Haryana Utilities observing that the interference would
       be warranted only if the concurrent findings have failed to take into
       consideration the mandatory statutory provisions or if the decision
       had been taken by them on extraneous consideration or that they
       were ex facie arbitrary and illegal. As a matter of fact, this Court in
       the said case had approved the methodology applied by the CERC
       and affirmed by the learned APTEL which was based on the decision
       of the CERC in the case of GMR Kamalanga (supra).

40. In that view of the matter and considering the concurrent findings
    of fact by the CERC on two different occasions and the learned
    APTEL in impugned order and also taking into note of the
    communication dated 2nd February 2022 issued by MCL, we see
    no merit in the appeal of Haryana Utilities and the same is liable to
    be dismissed.

       Civil Appeal No. 3429 of 2020

41. Insofar as the appeal by GRIDCO is concerned, the main contention
    of GRIDCO is that the order dated 3rd February 2016 in Petition No.
    79 and order dated 20th March 2018 in Petition No. 105 were passed
    without impleading GRIDCO. It will be relevant to note that the PPA
    with GRIDCO is under Section 62 of the 2003 Act whereas the PPAs
    with the Haryana Utilities and Bihar Utilities are under Section 63 of
    the 2003 Act. As such there was no occasion for GKEL to implead
    GRIDCO as a party to the said petitions.

42. It is further to be noted that the petitions filed by GKEL before the
    CERC were filed seeking compensation on account of Change
    in Law events affecting Haryana and Bihar PPAs which were
    concluded by following provisions prescribed under Section 63
    of the 2003 Act. Section 63 of the 2003 Act provides for the
    determination of tariff by bidding process whereas under Section
    62, the tariff is determined on Cost Plus basis. It can thus be seen
    that proceedings under Sections 62 and 63 of the 2003 Act are
    entirely different.
[2025] 9 S.C.R.                                                         701

            Haryana Power Purchase Centre (HPPC) and Others v.
                GMR Kamalanga Energy Limited and Others

43. It is also relevant to note that GKEL had filed a petition being Petition
    No. 77/GT/201338 for approval of the tariff for supply of electricity
    to the GRIDCO. The CERC vide order dated 12th November 2015
    had determined the tariff payable by the GRIDCO to GKEL for the
    period of 1st April 2013 to 1st March 2014. Being aggrieved by the
    said order, GRIDCO filed Appeal No. 45 of 2016 before the learned
    APTEL. The learned APTEL vide judgment and order dated 1st August
    2017 did not find any merit in the methodology adopted by CERC for
    determining the tariff. The learned APTEL found that the CERC had
    calculated ECR in accordance with the CERC (Terms and Conditions
    of Tariff) Regulations, 2009. The methodology adopted by the CERC
    for determining the tariff payable by GRIDCO to GKEL has been
    duly approved by the learned APTEL. In that view of the matter, we
    find that GRIDCO was neither a necessary nor a proper party to the
    proceedings initiated by GKEL by way of Petition Nos. 79 and 105.
44. On merits, it is the contention of the GRIDCO that it was its PPA which
    was executed first on 28th September 2006 and was operationalized
    in April 2013. It is therefore contended that GRIDCO has the first
    right over the firm linkage FSA dated 26th March 2013. GRIDCO
    further contended that allocation under SLC-LT meeting dated 2nd
    August 2007 and LOA dated 25th July 2008 was against long term
    PPAs and the only PPA at that time was with GRIDCO, therefore, the
    firm linkage was for GRIDCO. While considering GRIDCO’s appeal,
    the learned APTEL found that the supply of coal from all modes of
    procurement has to be considered for the power plant as a whole
    and not for specific PPAs as prayed by the appellants.
45. In the foregoing paragraphs, while considering the appeal of Haryana
    Utilities, we have already upheld the concurrent findings of the CERC
    and the learned APTEL that the coal supply from all the sources has
    to be apportioned amongst all the three DISCOMS in proportion to the
    energy supplied to them. None of the DISCOMS can claim a priority
    for supply of power based either on the prior date of agreement or
    the recital as to the source of coal. In view of the findings given by
    us while discussing the appeal of the Haryana DISCOMS, we find
    no merit in the present appeal as well. The same is therefore liable
    to be dismissed.


38   Hereinafter referred to as ‘Petition No. 77’
702                                                          [2025] 9 S.C.R.

                              Supreme Court Reports


       CONCLUSION
46. In the result, we pass the following orders:
       I.      Civil Appeal No. 1929 of 2020 filed by Haryana Utilities and
               Civil Appeal No. 3429 of 2020 filed by GRIDCO are dismissed
               sans merit; and
       II.     The impugned judgment and order dated 20th December 2019
               passed by the Appellate Tribunal for Electricity, New Delhi in
               Appeal No. 135 of 2018 along with Appeal No. 54 of 2019 is
               upheld.
47. Pending application(s), if any, shall stand disposed of.

       Result of the case: Appeals dismissed.




       †
           Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Concurrent findings of CERC and APTEL"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

HARYANA POWER PURCHASE CENTRE (HPPC) AND OTHERS versus GMR KAMALANGA ENERGY LIMITED AND OTHERS — 2025 INSC 1079 - Legal Desk AI