Created byFuzzy Cloud

Supreme Court of India

M/S. JINDAL STEEL AND POWER LIMITEDversusTHE CHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION AND ORS.

Citation
2022 INSC 1036
Decided
29 September 2022
Disposal
Appeal(s) allowed

Holding

The "minimum area of supply" is the area authorised by the licence, which may be a part of a municipal council, corporation or revenue district, and the licence granted to JSPL therefore stands.

Summary

Jindal Steel and Power Ltd. (JSPL) sought a distribution licence for its captive power plant to supply electricity to an industrial park and two villages in Raigarh, Chhattisgarh. The State Electricity Regulatory Commission granted the licence, but the Appellate Tribunal later cancelled it on the ground that JSPL did not satisfy the "minimum area of supply" requirement under the Explanation to Rule 3 of the 2005 Electricity Rules. The Supreme Court examined the meaning of "minimum area of supply" in the sixth proviso to Section 14 of the Electricity Act, 2003 and the related rule, holding that the area authorised by the licence is the minimum area of supply and need not cover an entire municipal council, corporation or revenue district. The Court found that the Tribunal erred in interpreting the rule and that the licence was valid. Consequently, the Court set aside the Tribunal's order and restored the licence. The decision also clarified that the Commission’s grant of licence was made after proper consideration of the statutory requirements.

Issues considered

  • The correct interpretation of the "minimum area of supply" under the Explanation to Rule 3 of the Electricity Rules, 2005 in relation to the sixth proviso of Section 14 of the Electricity Act, 2003.
  • Whether the Appellate Tribunal was empowered to cancel a distribution licence without a hearing to the consumers and in violation of the statutory procedure.
  • Whether the licence granted to JSPL complied with the capital adequacy, creditworthiness and code of conduct requirements under the 2005 Rules.

Legislation cited

Subjects

Electricity Act 2003distribution licenceminimum area of supplysixth provisoExplanation to Rule 3Appellate Tribunalrevocation of licencecaptive power plantindustrial parkChhattisgarh

Judgment

378                      [2022]REPORTS
               SUPREME COURT    7 S.C.R. 378                  [2022] 7 S.C.R.


A               M/S. JINDAL STEEL AND POWER LIMITED
                                         v.
                THE CHHATTISGARH STATE ELECTRICITY
                 REGULATORY COMMISSION AND ORS.
B                     (Civil Appeal Nos. 3607-3610 of 2008)
                              SEPTEMBER 29, 2022
             [AJAY RASTOGI AND B. V. NAGARATHNA, JJ.]
             Electricity Act, 2003: s.14 – Distribution licence/minimum area
      of supply u/s.14 of the 2003 Act granted to appellant-JSPL by the
C
      Chattisgarh State Electricity Regulatory Commission (Commission)
      – Cancellation of, by the Tribunal – Challenge against – Held: s.14
      of the 2003 Act states that appropriate Commission may grant a
      license to any person (a) to transmit electricity as a transmission
      licensee; or (b) to distribute electricity as a distribution licensee; or
D     (c) to undertake trading in electricity as an electricity trader, in any
      area as may be specified in the license – The sixth proviso to s.14
      states that the appropriate Commission may grant a license to two
      or more persons for distribution of electricity through their own
      distribution system within the same area, subject to the applicant
      complying with additional requirements – Explanation to r.3 of 2005
E
      rules prescribes the area falling within a Municipal Council or a
      Municipal Corporation as defined under Art.243 (Q) of the
      Constitution of India or Revenue District – The area of supply
      authorised by the Appropriate Commission shall be the ‘minimum
      area of supply’ – Thus, the expression ‘within the same area’ cannot
F     refer to the entire Municipal Council or a Municipal Corporation
      or a Revenue District but ‘the area falling within’ a Municipal
      Council or a Municipal Corporation or a Revenue District in respect
      of which a distribution licensee is authorised – Hence the authorized
      ‘area of supply’ shall be the ‘minimum area of supply’ – Therefore,
      the contention of respondent no. 2 that the ‘minimum area of supply’
G
      must comprise of the ‘entire’ Municipal Council or a Municipal
      Corporation or a Revenue District is unsustainable – Thus, the area
      in respect of which the license was granted to appellant is the
      minimum area of supply and appellant is bound to supply electricity
      in the said area of supply – Judgment of tribunal set aside –
H     Electricity Rules, 2005 – r.3, explanation.
                                         378
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE              379
             ELECTRICITY REGULATORY COMMISSION


      Allowing the appeals, the Court                                    A
      HELD: 1. The 2003 Act, came into force on 10.06.2003
insofar as Sections 1 to 120 and Sections 122 to 185 are
concerned. The Preamble of the 2003 Act states that it has been
enacted to consolidate the laws relating to generation,
transmission, distribution, trading and use of electricity and           B
generally for taking measures conducive to development of
electricity industry, promoting competition therein, protecting
interest of consumers and supply of electricity to all areas,
rationalization of electricity tariff, ensuring transparent policies
regarding subsidies, promotion of efficient and environmentally
benign policies, constitution of Central Electricity Authority,          C
Regulatory Commissions and establishment of Appellate Tribunal
and for matters connected therewith or incidental thereto. [Para
27][407-B-D]
       2. On a reading of Section 14 of the 2003 Act, it is clear that
the appropriate Commission may, on an application made to it             D
under Section 15 grant a licence to any person (a) to transmit
electricity as a transmission licensee; or (b) to distribute
electricity as a distribution licensee; or (c) to undertake trading
in electricity as an electricity trader, in any area as may be
specified in the licence. The sixth proviso which is under               E
consideration states that the appropriate Commission may grant
a licence to two or more persons for distribution of electricity
through their own distribution system within the same area,
subject to the conditions that the applicant for grant of licence
within the same area, shall, without prejudice to the other
conditions or requirement under the Act comply with the                  F
additional requirements relating to the capital adequacy,
creditworthiness, or code of conduct as may be prescribed by
the Central Government, and no such applicant, who complies
with all the requirements for grant of licence, shall be refused
grant of licence on the ground that there already exists a licensee      G
in the same area for the same purpose. [Paras 32 and 33][412-A-
E]
      3. Within the same area, there could be two or more persons
for distribution of electricity. As to what is the area within which
there could be grant of licence to two or more persons is                H
380            SUPREME COURT REPORTS                      [2022] 7 S.C.R.


A     concerned under the sixth proviso to Section 14, the Explanation
      to Rule 3 prescribes the area falling within a Municipal Council
      or a Municipal Corporation as defined under Article 243 (Q) of
      the Constitution of India or Revenue District. The area of supply
      authorised by the Appropriate Commission shall be the minimum
      area of supply. Thus, the ‘minimum area of supply” would fall
B
      ‘within the area’ which is comprising of a Municipal Council or a
      Municipal Corporation or a Revenue District but it does not imply
      that the licence to supply electricity for an area or an ‘area of
      supply which is the ‘minimum area of supply’ must extend to the
      ‘entire area falling within’ a Municipal Council or a Municipal
C     Corporation or a Revenue District. Thus, the expression ‘within
      the same area’ cannot refer to the entire Municipal Council or a
      Municipal Corporation or a Revenue District but ‘the area falling
      within’ a Municipal Council or a Municipal Corporation or a
      Revenue District in respect of which a distribution licensee is
      authorised by its licence to supply electricity. Therefore, by the
D
      aforesaid interpretation, the authorised ‘area of supply’ shall be
      ‘the minimum area of supply’. [Paras 37, 40, 42][414-A-B, G-H;
      415-A, E-G]
             4. On the other hand, on a reading of the licence granted to
      the appellant, it is clear that respondent No.1 was conscious of
E     the fact that it was granting licence to the appellant JSPL having
      regard to the fact that the said appellant had established an
      industrial park for which it had the responsibility for distribution
      of electricity and in addition, two more villages were added to
      the area comprised in the industrial park for the purpose of
F     distribution of electricity. The area in respect of which the licence
      was granted and thereby authorisation provided to supply
      electricity is the minimum area of supply. The ‘area of supply’ is
      ‘an area falling within’ a Municipal Council or a Municipal
      Corporation or a Revenue District and in the instant case, it is a
      Revenue District. Since, the ‘area of supply’ authorised in the
G     licence granted to the appellant JSPL in the instant case is the
      ‘minimum area of supply’, the said appellant is bound to supply
      electricity in the said area of supply. The licensee cannot resile
      from the condition of supplying electricity as per the authorisation
      of the area of supply indicated in the license. This would also
H     mean that the licensee cannot supply electricity in an area beyond
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE           381
             ELECTRICITY REGULATORY COMMISSION


the area of supply authorised under the license. This is because      A
in respect of an area falling within a Municipal Council or a
Municipal Corporation or a Revenue District, there could be two
or more persons who could be granted licence and authorisation
to distribute electricity in terms of the respective area of supply
specified. [Para 44][416-A-E]
                                                                      B
      S. Sundaram Pillai v. V.R. Pattabiraman (1985) 1 SCC
      591 : [1985] 2 SCR 643; Global Energy Ltd. v. Central
      Electricity Regulatory Commission (2009) 15 SCC 570
      : [2009] 9 SCR 22; Bhaskar Shrachi Alloys Ltd. v.
      Damodar Valley Corporation (2018) 8 SCC 281 :
      [2018] 10 SCR 773; Kerala Samsthana Chethu                      C
      Thozhilali Union v. State of Kerala & Ors. (2006) 4
      SCC 327 : [2006] 3 SCR 420; Bharathidasan University
      & Anr. v. All India Council for Technical Education &
      Ors. (2001) 8 SCC 676 : [2001] 3 Suppl. SCR 253;
      P. Mahendran v. State of Karnataka (1990) 1 SCC 411             D
      : [1989] 2 Suppl. SCR 385; A.A. Calton v. Director of
      Education (1983) 3 SCC 33; Gopal Krushna Rath v.
      M.A.A. Baig (dead) by LRs (1999) 1 SCC 544;
      Federation of Indian Mineral Industries & Ors. v. Union
      of India & Anr. (2017) 16 SCC 186 : [2017] 12 SCR
      724; Hindustan Unilever Ltd. v. State of Madhya                 E
      Pradesh (2020) 10 SCC 751; Gujarat Electricity Board
      v. Shantilal R. Desai [1969] 1 SCR 580; DAV College
      Trust and Management Society & Ors. v. Director of
      Public Instructions & Ors. (2019) 9 SCC 185 : [2019]
      12 SCR 549; C.I.T Andhra Pradesh v. M/s. Taj Mahal              F
      Hotel, Secunderabad (1971) 3 SCC 550 : [1972] 1 SCR
      168; Madhav Rao Jivaji Rao Scindia v. Union of India
      (1971) 1 SCC 85 : [1971] 3 SCR 9; Ramana Dayaram
      Shetty v. International Airport Authority of India (1979)
      3 SCC 489 : [1979] 3 SCR 1014; Energy Watchdog v.
      Central Electricity Regulatory Commission and Others            G
      (2017) 14 SCC 80 : [2017] 3 SCR 153; Thampanoor
      Ravi v. Charupara Ravi (1999) 8 SCC 74 : [1999] 2
      Suppl. SCR 419; Peerless General Finance &
      Investment Co. Ltd. v. Reserve Bank of India (1992) 2
      SCC 343; [1992] 1 SCR 406; Chief Forest Conservator             H
382          SUPREME COURT REPORTS                     [2022] 7 S.C.R.


A          (Wildlife) & Ors. v. Nisar Khan (2003) 4 SCC 595 :
           [2003] 2 SCR 196; Howrah Municipal Corporation and
           Ors. v. Ganges Rope Co. Ltd. and Ors. (2004) 1 SCC
           663 : [2003] 6 Suppl. SCR 1212; Union of India and
           Ors. v. Indian Charge Chrome and Anr. (1999) 7 SCC
           314; M/s. Hiralal Rattanlal Etc. Etc. v. State of U.P.
B
           and Anr. Etc. Etc. (1973) 1 SCC 216 : [1973] 2 SCR
           502; Dattatraya Govind Mahajan v. State of
           Maharashtra (1977) 2 SCC 548 : [1977] 2 SCR 790 –
           referred to.
                           Case Law Reference
C
      [1985] 2 SCR 643              referred to        Para 22.2
      [2009] 9 SCR 22               referred to        Para 22.2
      [2018] 10 SCR 773             referred to        Para 22.4

D     [2006] 3 SCR 420              referred to        Para 22.4
      [2001] 3 Suppl. SCR 253       referred to        Para 22.4
      [1989] 2 Suppl. SCR 385       referred to        Para 22.6
      (1983) 3 SCC 33               referred to        Para 22.6
E     (1999) 1 SCC 544              referred to        Para 22.6
      [2017] 12 SCR 724             referred to        Para 22.6
      (2020) 10 SCC 751             referred to        Para 22.6
      [1969] 1 SCR 580              referred to        Para 22.6
F     [2019] 12 SCR 549             referred to        Para 22.8
      [1972] 1 SCR 168              referred to        Para 22.8
      [1971] 3 SCR 9                referred to        Para 22.8
      [1979] 3 SCR 1014             referred to        Para 22.9
G     [2017] 3 SCR 153              referred to        Para 22.9
      [1999] 2 Suppl. SCR 419       referred to        Para 25.3
      [1992] 1 SCR 406              referred to        Para 25.5
      [2003] 2 SCR 196              referred to        Para 25.5
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                   383
             ELECTRICITY REGULATORY COMMISSION


[2003] 6 Suppl. SCR 1212            referred to         Para 25.10            A
(1999) 7 SCC 314                    referred to         Para 25.10
[1973] 2 SCR 502                    referred to         Para 25.10
[1977] 2 SCR 790                    referred to         Para 25.10
      CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 3607-                   B
3610 of 2008.
      From the Judgment and Order dated 07.05.2008 of the Appellate
Tribunal for Electricity, New Delhi in Appeal Nos. 179, 188 of 2005, 16
and 27 of 2006.
                                                                              C
      With
      Civil Appeal Nos. 4104-4107 of 2008.
      Sanjay Sen, Sr. Adv., Sanjeev K. Kapoor, Ms. Divya C., Saransh
Shaw, Ms. Mandakini Ghosh, Ms. Neha Dabral, Pranav Sood,
M/s Khaitan & Co., Shibashish Misra, Ms. Divya, Ms. Swapna Seshadri,          D
Anand K. Ganesan, Pramod Dayal, Nikunj Dayal, Ms. Kriti Soni, Rakesh
Kumar, Raj Kumar Mehta, Ms. Rashmi Singh, Pukhrambam Ramesh
Kumar, Damodar Solanki, Karun Sharma, W. Immanuel M., Advs. for
the appearing parties.
      The Judgment of the Court was delivered by                              E
      NAGARATHNA, J.
       1. These Civil Appeals filed under Section 125 of the Electricity
Act, 2003 arise out of common impugned Judgment dated 07.05.2008
passed by the Appellate Tribunal for Electricity, New Delhi (‘Appellate
Tribunal’, for short). By the said judgment, the Appellate Tribunal has set   F
aside the order of respondent No.1 dated 29.11.2005 and cancelled the
distribution licence granted to the appellant in C.A. Nos.3607-3610 of
2008. Hence, these appeals.
       2. Since the questions of law and facts which arise in both the
above captioned Civil Appeals are similar, these appeals are being disposed   G
of by this common judgment.
      Re: Civil Appeal Nos. 3607-3610 of 2008:
       3. The appellant-Jindal Steel and Power Ltd. (‘JSPL’, for short)
in this civil appeal established a sponge iron/steel plant at Raigarh,
                                                                              H
384             SUPREME COURT REPORTS                            [2022] 7 S.C.R.


A     Chhattisgarh in the year 1990. A captive power plant was also set up by
      JSPL at a distance of 40 km from the aforesaid steel plant.
             4. Respondent No.1 is Chhattisgarh State Electricity Regulatory
      Commission (‘Commission’, for short), respondent No.2 is Chhattisgarh
      State Electricity Board (‘CSEB’, for short) later became ‘Chhattisgarh
B     State Power Distribution Company’ and respondent No.3 is Chhattisgarh
      Vidyut Mandal Abhiyanta Sangh (‘CVMAS’, for short).
             5. The newly created State of Chhattisgarh formulated its industrial
      policy for 2001-2006 which encouraged the establishment of industrial
      estates in private-public partnership as well as the installation of captive
C     power plant.
             6. A proposal for permission to set up an industrial estate in 500
      acres of land, adjacent to the existing land at Raigarh, was submitted by
      JSPL vide letter dated 28.12.2001. The land was to comprise of villages
      of Kosampali, Dhanagar, Barmuda or at a site in the Tehsil of Gharghoda
D     comprising villages Tarai Mal and Ujjalpur. JSPL, addressed a letter dated
      09.04.2002 to the Department of Mineral Resources, Commerce and
      Industries, Government of Chhattisgarh seeking permission for
      establishing such an industrial estate at Raigarh. A map showing the
      proposed industrial area was annexed with the letter. The Government
      of Chhattisgarh, vide letter dated 26.04.2002 informed JSPL that the
E     Energy Department was taking action to grant permission for sale of
      power and to lay transmission lines to various units in the private industrial
      estate being established by JSPL and requested JSPL to prepare and
      submit a draft of Memorandum of Understanding (‘MoU’, for short) for
      the said purpose for approval. The facilities were to be provided as per
F     the new industrial policy dated 01.11.2001.
              7. JSPL, on 16.07.2002, requested the Chief Minister of
      Chhattisgarh to issue appropriate directions for grant of permission to
      supply power to the units in the proposed industrial estate. The
      Government of Chhattisgarh, on 14.08.2002, sent a reply to the aforesaid
G     request made by JSPL and informed that it shall have to take certain
      actions /steps with regard to the supply of power to the proposed industrial
      units. In compliance of the aforesaid letter on 04.09.2002, JSPL addressed
      a letter requesting for grant of permission under Section 28 of the Indian
      Electricity Act, 1910 (‘1910 Act’, for short) for sale of power to the
      proposed units in the industrial state from its captive power plant and for
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                      385
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


grant of permission to set up transmission and distribution lines/system         A
for supply of power to the industrial units in the proposed industrial estate.
JSPL further stated that they will obtain necessary permission under the
Electricity Supply Act, 1948 (‘1948 Act’, for short) for setting up
transmission and distribution lines from CSEB.
       8. A MoU was signed on 23.10.2002 between Chhattisgarh State              B
Industrial Development Corporation (‘CSIDC’, for short) acting on behalf
of Government of Chhattisgarh and JSPL for setting up the industrial
estate. The Government of Chhattisgarh, on 29.01.2003 granted
permission for supply of power by JSPL to the new industrial units being
set up in the private industrial estate proposed in four villages of Raigarh
District i.e., Punjipathra, Tumdih, Jorapalli and Dhanagarh from its captive     C
power plant and laid down certain terms and conditions. CSEB, on
31.05.2003 granted permission for laying transmission and distribution
lines of 220 KV for supply of power to the prospective units at the
Industrial Estate in Raigarh, Chhattisgarh by tapping 220 KV from the
captive power plant of JSPL.                                                     D
       9. On 06.10.2003, JSPL made a formal application for sanction
under Section 28 of the 1910 Act wherein it provided details of the project
enclosing relevant documents. The Government of Chhattisgarh passed
two orders on 28.02.2004. Vide its first order exercising power under
Sections 68(1) and 68(3) of the Electricity Act, 2003 (‘2003 Act’, for           E
short), the State Government accorded permission for construction of
transmission and distribution lines as recommended by the CSEB on
certain terms and conditions. Vide its second order, relating to the
No-Objection of the State Government regarding direct power supply
by JSPL from their power plant to the industrial units proposed to be set
up in the private industrial estate in Raigarh, Chhattisgarh, the State          F
Government of Chhattisgarh opined that since the 2003 Act was in force
in the State from 09.12.2003 and the 1910 Act stood repealed, no
permission could be granted under the latter Act.
     10. JSPL commenced supply of electricity to the industrial units
which were already setup with effect from 01.03.2004.                            G
        11. Thereafter, on 15.09.2004, JSPL filed an application for grant
of distribution licence before the Commission under Section 14 of the
2003 Act. The same was returned by the Commission on 15.09.2004 for
filing in the prescribed format. On 25.01.2005, JSPL applied for the licence
to the Commission in Form 1-A with all necessary enclosures as per               H
386               SUPREME COURT REPORTS                          [2022] 7 S.C.R.


A     Regulation 3 (1) of the Chhattisgarh State Electricity Regulatory
      Commission (License Regulations), 2004 (‘State License Regulations’,
      for short) along with Demand Draft of Rs.5 Lakhs. In the said application,
      JSPL stated that the area to which supply was to be made was the Jindal
      Industrial Park in the private sector in Punjipathra and Tumdih villages of
      Garghoda Tehsil, Raigarh District having an area of 750 acres and shall
B
      accommodate seventy units. Pursuant to the filing of the said application,
      notices were published in the newspapers and objections were invited
      under Section 15 of the 2003 Act. Three objections were received, one
      each from respondent Nos.2 and 3 and the third objection was from
      Mr. R.K. Aggarwal. The objection of Mr. R.K. Aggarwal was
C     subsequently rejected by the Commission on 27.08.2005 being bereft of
      any locus standi.
            12. Various correspondences and pleadings were exchanged
      between JSPL, CSEB, CVMAS and the Commission and thereafter
      the Commission framed a total of five issues and vide its Order dated
D     29.09.2005, decided to grant distribution licence under Section 14 of the
      2003 Act. The pertinent findings of the Commission can be encapsulated
      as under:
            i.      A harmonious reading of Sections 10(2), 42(2), 2(47) & 12
                    of the 2003 Act, clearly brings out that a generating company
E                   may supply electricity to a consumer under the provisions
                    of Section 10(2) of the 2003 Act only subject to the provisions
                    of open access. The scheme of the Act, particularly Part
                    IV (Licensing) thereof, is such that it cannot authorize a
                    generator to supply electricity to a consumer without a
                    licence. That the present application is not for supply through
F                   open access and the same is for distribution of electricity
                    to a significant number of industries in an industrial area set
                    up under specific permission of the State Government.
            ii.     Section 28 of the 1910 Act is quite clear that supply of
                    electricity to the public mandates the previous sanction of
G                   the State Government. That, by no stretch of the argument,
                    can the letter of the State Government dated 29.01.2003
                    be treated as sanction of the State government. Therefore,
                    the said letter does not confer any right on JSPL under
                    Section 28 of the 1910 Act to supply electricity.
H
M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                   387
 ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


    iii.   No-objection letter dated 28.02.2004 also does not confer         A
           any such right on the applicant. If the said letter conveyed
           any right, either the application for licence would not have
           been made or a claim of existing right should have been
           made. The application of JSPL clearly stated that it had no
           licence. Further, the second letter of the said date, conveying
                                                                             B
           No-objection of the State Government cannot be said to
           be valid since there is no provision for such no objection
           from the State Government. Therefore, as on that date,
           distribution of electricity by JSPL was without any legal
           authority.
    iv.    On the aspect of area for which the licence had been applied      C
           for, it was observed that the present case ought to be treated
           as an exception to Rule 3 of the Distribution License Rules
           and to Para 5.4.7 of the National Electricity Policy since
           effective steps for setting up of the industrial estate herein
           and an understanding with the State Government to the             D
           effect that JSPL would provide electricity from its captive
           power plant were taken much before the National Electrical
           Policy was notified. As per the application, supply of
           electricity commenced with effect from 01.03.2004 to some
           industries on the basis of the letter dated 28.02.2004 and
           therefore, the National Electrical Policy notified subsequently   E
           cannot be invoked to deny distribution licence in this case.
    v.     That if a distribution licence is refused at this stage, which
           is approximately one and half years after supply of electricity
           has commenced, whether with or without legal authority,
           the same shall impact the consumers of JSPL. CSEB also            F
           conveyed its no objection to lay transmission and distribution
           network as early as on 30.05.2003. That JSPL had gone
           way ahead with the industrial estate project in full, including
           distribution of power on the basis of the understanding with
           the State Government. A large investment of Rs.17.79              G
           Crores was made, and there were twenty-four industries,
           most of which were power intensive. If a distribution licence
           was denied, they will have to close down their industries.
           Apart from that, the consumers will be forced to buy power
           from CSEB at a much higher rate than at present. Therefore,
                                                                             H
388               SUPREME COURT REPORTS                           [2022] 7 S.C.R.


A                   the grant of distribution licence in this case may be in the
                    interest of the competition and in the interest of consumers
                    who have already entered into a long-term supply contract
                    with JSPL.
            vi.     Further, in view of the overall position of the case, the balance
B                   of convenience would lie in grant of a distribution licence to
                    JSPL and there was an adequate justification for the same.
                    Moreover, the CSEB could not clarify as to why it was in
                    opposition to a distribution licence in a limited area when
                    CSEB was itself not in a position to supply quality power to
                    their existing industrial consumers.
C
            vii.    In respect of JSPL’s eligibility for grant of such distribution
                    licence, it was observed that JSPL met all the requirements
                    of capital adequacy, creditworthiness and code of conduct
                    as laid down by the Central Government in the Distribution
                    License Rules.
D
            viii. In respect of levy of cross-subsidy charges on the consumer
                  of JSPL, the Commission held that there was no justification
                  in such levy since the same was not a case of open access.
                  The scheme of the 2003 Act is such that a distribution
                  licensee cannot recover cross-subsidy surcharge from
E                 another distribution licensee and that JSPL had undertaken
                  to supply electricity to all its consumers in the area for which
                  licence was proposed to be granted.
            ix.     Lastly, it was held that JSPL was liable to pay a penalty
                    of Rs. One Lakh for contravention of Section 12 of the
F                   2003 Act which mandates licence to be obtained for supply
                    of electricity and violation of the same was punishable under
                    Section 142 of the 2003 Act.
             13. The following conditions, apart from the general and special
      conditions applicable to such licenses under the Regulations, were imposed
G     on JSPL by the Commission for grant of distribution license:
            “(i)    The license will be for the area of the two villages, Tumdih
                    and Punjipathra of Gharghoda Tehsil of Raigarh District.
                    However, the number of industrial consumers in the Jindal
                    Industrial Park shall be limited to 70 and their total demand
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                     389
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


              for electricity not increasing 299 MW, as agreed with the         A
              State Government.
      (ii)    The applicant shall lay necessary distribution lines and put-up
              sub-station at his own cost in the two villages for supply of
              electricity to any person who may apply for it and supply
              electricity at a rate not more than Rs.2.50 per unit or at the    B
              supply rate of the Board for that category of consumer,
              which is lower. This will include domestic, agriculture,
              industrial and other consumers. The option to choose
              between the licensee and the Board shall be with the
              consumer.
                                                                                C
      (iii)   All other general and special conditions applicable to a
              distribution licensee as per the provisions of the License
              Regulations.”
       14. Respondent Nos.2 and 3 on 07.10.2005, filed objections to
the order dated 29.09.2005 before the Commission. Thereafter, respondent        D
No.2 filed Appeal No.179/2005 and respondent No.3 filed Appeal No.188/
2005 before the Appellate Tribunal. The appellant herein challenged the
imposition of penalty of Rs. One Lakh before the Appellate Tribunal in
Appeal No.27/2006.
      15. On hearing the respective parties, the Commission, vide its           E
Order dated 29.11.2005, granted licence to JSPL on the following terms
and conditions:
      “(i)    The distribution license shall be valid for a period of
              twenty-five years from the date of issue, as per the provision
              of Section 15(8) of the Act, unless revoked earlier.              F
      (ii)    The area of the license shall be the geographical area of
              the villages Tumdih and Punjipathra, including the Jindal
              Industrial Park aforementioned, of Gharghoda tahsil of
              Raigarh District of the State as indicated in the map enclosed
              herewith.
                                                                                G
      (iii)   The distribution licensee shall abide by all the relevant
              provisions of the Electricity Act, 2003, the National
              Electricity Policy, i.e. Rules 1956 and Electricity Rules 2005,
              as amended from time to time.
                                                                                H
390         SUPREME COURT REPORTS                          [2022] 7 S.C.R.


A     (iv)    The licensee shall abide by the general conditions of license
              as given in chapter III and the other conditions applicable
              to a distribution licensee as given in chapter V of the CSERC
              (Licence) Regulations 2005, as amended from time to time.
              He shall also comply with the relevant provisions of all the
              regulations issued or as may be issued by the Commission,
B
              as amended from time to time.
      (v)     The licensee shall abide by all the relevant provisions of
              the Chhattisgarh State Electricity Supply Code, 2005.
      (vi)    The licensee shall lay necessary distribution lines and put-up
C             sub-stations at his own cost in the two villages for supply
              of electricity to any person who may apply for it and supply
              electricity at a provisional rate of not more than Rs.2.50
              per unit or at the supply rate of the Board for that category
              of consumer, whichever is lower, till the tariff for supply is
              determined by the Commission. This will include domestic,
D             agriculture, industrial and other consumers.
      (vii)   The consumers of the area other than area of Jindal
              Industrial Park (JIP) shall have the option to choose between
              the licensee and the Chhattisgarh State Electricity Board
              (CSEB) or its successor entity/entities.
E
      (viii) The existing tariff being charged from the industrial
             consumers in the designated area of JIP shall continue to
             be charged by the licensee till the tariff is determined by the
             Commission.

F     (ix)    For determination of tariff in the area of supply, the
              distribution licensee shall file the necessary application under
              Section 64 of the Act and clause 10 of the CSERC (Details
              to be ‘furnished by licensee or generating company for
              determination of tariff and manner of making application)
              Regulations, 2004 before the Commission on or before 31st
G             March 2006, and thereafter in terms of the provisions of
              the same Regulations.
      (x)     The licensee shall abide by the safety rules and safety
              standards issued by the Central Electricity Authority,
              Ministry of Power, Govt. of India and other Government
H             agency/department.
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                     391
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


      (xi)    The licensee shall not transfer or assign, by sale, lease         A
              exchange or otherwise, this license or part thereof to any
              other person without prior approval of the Commission.
      (xii)   The licensee shall undertake electrification of villages Tumdih
              and Punjipathra as per the norms laid down for rural
              electrification within a period of six months, i.e., before       B
              29.05.2006. It shall also provide public lamps in adequate
              number in these two villages on the request of the concerned
              Gram Panchayat and maintain the same.
      (xiii) All issues relating to interpretation of this licence and its
             terms and conditions, shall be a matter for determination by       C
             the Commission and the decision of the Commission on such
             issues shall be final, subject only to the right of appeal.
      (xiii) The conditions of the license may be altered or amended by
              the Commission at any time, if it deems fit in the public
              interest, in terms of Section 18 of the Act.”                     D
      16. Respondent No.2 filed Appeal No.16/2006 before the
Appellate Tribunal challenging the order dated 29.11.2005 passed by the
Commission. The Appellate Tribunal, vide it Order dated 11.05.2006,
upheld the order granting distribution licence dated 29.11.2005 passed by
the Commission. Aggrieved by the order dated 11.05.2006 passed by the           E
Appellate Tribunal, respondent Nos.2 and 3 filed appeals before this Court
being Civil Appeal Nos. 3996 of 2006 and 4268 of 2006. JSPL also
preferred an appeal before this Court being Civil Appeal No.4529 of
2006. This Court, vide its order dated 19.09.2007, allowed the aforesaid
appeals, set-aside the order dated 11.05.2006 passed by the Appellate
Tribunal and remanded the matter to the Appellate Tribunal for fresh            F
determination.
       17. On remand, the Appellate Tribunal reconsidered the matter
and all the aforesaid appeals (Appeal No.179/2005, Appeal No.188/2005,
Appeal No.27/2006 and Appeal No.16/2006) were allowed vide common
impugned order dated 07.05.2008 which is challenged before this Court           G
by way of the present appeals. The pertinent observations and decision
of the Appellate Tribunal are encapsulated as under:
      i.      With respect to JSPL’s argument that the MoU had a specific
              clause that allowed JSPL to directly sell power to the
                                                                                H
392          SUPREME COURT REPORTS                          [2022] 7 S.C.R.


A              industrial units set up in the proposed industrial estate, it
               was held that it was not the correct way to read the MoU.
               The MoU was entered into when the estate had not even
               come into existence and the terms therein only envisioned
               what would happen in the future. Therefore, it was too early
               to grant licence for supply or distribution of electricity by
B
               JSPL. It was further held that JSPL itself did not treat this
               clause in the MoU as grant of license. Had the MoU itself
               meant grant of license, there would have been no occasion
               for the subsequent correspondence between the JSPL and
               the Government of Chhattisgarh. Therefore, neither the
C              State Government nor JSPL was acting under an
               understanding that JSPL had already been granted a license.
      ii.      That the letter dated 29.01.2003 which is a ‘No-Objection’
               from the Government of Chhattisgarh had a clear stipulation
               that JSPL was required to take permission under Section
D              28 of the 1910 Act for direct power supply from its captive
               power plant to the industrial estate and the said letter cannot
               be read as Government’s promise to give license.
      iii.     On examining the two letters dated 28.02.2004, it was found
               by the Appellate Tribunal that the first order accorded
E              permission for construction of power, transmission and
               distribution lines under Sections 68(1) and (3) of the 2003
               Act and the second order dealt with prayer for approval
               under Section 28 of the 1910 Act. Vide the second order, it
               was made sufficiently clear that JSPL will have to get the
               permission/licence from the Commission since Section 28
F              of the 1910 Act stood repealed and no permission thereof
               could be given.
      iv.      That there cannot be an estoppel against the statute. The
               relevant authority at that time was the Commission and the
               licence was to be obtained under Section 14 of the 2003
G              Act from the Commission, after fulfilling the requisite terms
               and conditions. JSPL could not have taken advantage of
               the doctrine of promissory estoppel since, even if the
               aforesaid letters were construed to be a promise, the same
               would only be binding on the Government of the State of
H
M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                    393
 ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


            Chhattisgarh and not the Commission which is not                  A
            subordinate to the Government or its successor or assignee.
    v.      The Appellate Authority, on considering the issue as to
            whether JSPL was entitled to the license/minimum area of
            supply under Section 14 of the 2003 Act observed that on
            the date when the application for licence filed by JSPL under     B
            the 2003 Act was under consideration, the Commission was
            required to apply the regulation in force at that point of time
            which included the rule of minimum area of supply. It was
            observed that the Commission was incorrect in ignoring the
            said rule and granting the licence in violation thereof. No
            exception to the aforesaid rule could have been made out          C
            by the Commission.
    vi.     While interpreting Section 10(2) of the 2003 Act that allowed
            a generating company to supply electricity to any licensee
            or to any consumer, it was held that the JSPL is a captive
            power plant and is governed by Section 9 of the 2003 Act          D
            and not by Section 10 of the said Act.
    vii.    That JSPL had applied for a distribution licence because it
            intended to purchase power from another generating
            company called Jindal Power. JSPL, being a captive power
            plant and not a generating company at the relevant time           E
            could not have made any supply to any third person without
            a license.
    viii.   On considering CSEB’s argument that the supply from a
            captive power plant or even under Section 10(2) of the
            2003 Act is permissible only when the same is made by use         F
            of the grid or the transmission lines of distribution licensee
            or transmission licensee by use of open access and that
            unless open access is availed, the supply cannot be made, it
            was held that open access is an enabling provision that helps
            expansion of the electricity sector and not to limit its          G
            development. If it was the intention of the 2003 Act that no
            sale was possible except by availing open access, it would
            have said so. It was further observed that Section 10(2) of
            the 2003 Act prescribes that the supply to a consumer will
            be subject to Regulations made under sub-section (2) of
                                                                              H
394               SUPREME COURT REPORTS                          [2022] 7 S.C.R.


A                   Section 42 of the 2003 Act. While interpreting the use of
                    the words ‘subject to the rules made under sub-section
                    (2) of Section 42’, it was held that the provision under
                    Section 42(2) of the 2003 Act would only be attracted when
                    the access through the existing distribution was sought; when
                    such access was not sought, the aforesaid provision shall
B
                    not apply.
            ix.     With respect to the Commission’s order imposing penalty
                    of Rs. One Lakh on JSPL, the same was set-aside. This
                    was because, although JSPL did not have a licence when it
                    started supplying electricity to Jindal Industrial Park, a
C                   penalty was not automatically attracted. As per Section 142
                    of the 2003 Act, a person sought to be punished has to be
                    given an opportunity to be heard. Admittedly, the said
                    opportunity was not given to JSPL. It was found that the
                    Commission was merely hearing the application for grant
D                   of distribution license. The issue as to whether JSPL had
                    rendered itself liable to punishment at all was never an issue
                    before the Commission.
            Re: Civil Appeal Nos. 4104-4107 of 2008:
            18. The facts and circumstances in both these appeals are similar
E     and therefore have not been reproduced to avoid repetition except to the
      extent it is necessary to do so.
             19. The appellant in these civil appeals is the consumer of
      electricity in Jindal Industrial Park in Raigarh, Chhattisgarh who is
      aggrieved by the cancellation of distribution licence granted in favour of
F     JSPL and due to unavailability of an alternative distribution licensee. It is
      the grievance of the appellant herein that it was not a party before the
      Appellate Tribunal.
              20. JSPL, on 08.05.2008, by way of its notice, informed the
      appellant in this appeal that since its distribution licence had been
G     cancelled, it had to stop supplying power to all the industries in the Jindal
      Industrial Park whereafter on 09.05.2008, at 1:00 p.m., the electricity
      supply to all the units of the appellant was disconnected. The appellant
      contends that all the units were brought to a standstill and the appellant
      has been facing losses running to crores of rupees. The appellant avers
      that it is a third party and an end consumer of JSPL who is deprived
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                    395
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


of electricity in the absence of any alternative distributor in place. Hence   A
these appeals.
       21. We have heard Sri Sanjay Sen, learned senior counsel for the
appellant in C.A. Nos. 3607-3610 of 2008 and Sri C.S. Vaidyanathan,
learned senior counsel for the appellant in C.A. Nos. 4104-4107 of 2008
duly assisted by their instructing counsel; Ms. Swapna Seshadri, learned       B
counsel for the respondent No.1, Sri Raj Kumar Mehta, learned counsel
for the respondent No.2 and perused the material on record.
      22. The submissions of the learned senior counsel for the
appellant- JSPL in Civil Appeal Nos.3607-3610 of 2008 are epitomised
as under:                                                                      C
      22.1     That the Commission in its order dated 29.11.2005, after
               taking note of the Distribution of Electricity (Additional
               Requirement of Capital and Adequate Creditworthiness
               and Code of Conduct) Rules, 2005 (‘2005 Rules’, for short)
               had proceeded to grant licence keeping in view the              D
               historical background, investment made by the
               appellant-JSPL and the benefits that accrued in favour
               of industrial consumers who had set up their industrial
               plants and had no other source of power supply at the
               relevant time. By its Order dated 29.09.2005, the
               Commission had specifically noticed the inability of CSEB       E
               to provide electricity for want of physical infrastructure
               and unavailability of surplus power. In fact, the State of
               Chhattisgarh was suffering from power shortages and
               was buying power from the captive power plant of this
               appellant-JSPL. On the basis of the permission granted          F
               by the State Government/CSEB, in terms of MoU dated
               23.10.2002, the construction of transmission and
               distribution network was undertaken and completed and
               supply of power on the basis of the long-term agreement
               had commenced on or about 01.03.2004 which was much
               prior to the coming in to existence of the Commission and       G
               the 2005 Rules. Further, the State Government with the
               concurrence of CSEB had acted substantially in terms of
               powers vested under the repealed law i.e., Section 28 of
               the 1910 Act and the State’s Industrial and Energy Policies.
               The original application for grant of licence filed on          H
396     SUPREME COURT REPORTS                           [2022] 7 S.C.R.


A            15.09.2004 and revised application for grant of licence
             filed on 25.01.2005 were both before notification of the
             2005 Rules. However, the Appellate Tribunal has taken a
             narrow and pedantic view solely on the basis of Explanation
             to Rule 3 of the 2005 Rules.
B     22.2   It was contended that an ‘explanation’ to a provision is
             merely meant to explain or clarify certain ambiguities
             and cannot be treated as a substantive provision. In this
             regard, the learned senior counsel appearing on behalf of
             the appellant-JSPL has placed reliance on S. Sundaram
             Pillai v. V.R. Pattabiraman (1985) 1 SCC 591 and
C            Global Energy Ltd. v. Central Electricity Regulatory
             Commission (2009) 15 SCC 570. He further states that
             the Explanation to Rule 3 is not a part of the statute’s
             provisions or primary legislation but is in the context
             of subordinate legislation. From a conjoint reading of
D            Section 2(3), Section 14 and sixth proviso thereof, Section
             86 and Section 176(2)(b) of the 2003 Act, it is clear that
             the Central Government has not been vested with the
             jurisdiction to define the area of supply. It is clear that
             the statute required the Central Government to specify
             conditions only on three subjects namely capital adequacy,
E            credit worthiness and code of conduct. If the Central
             Government indeed had delegated the power to define
             the area of supply of a distribution licensee, it would have
             made a substantive rule and not inserted it through an
             Explanation. According to learned senior counsel,
F            Explanation to Rule 3, at the highest, can act as a guideline
             for discharge of regulatory functions which should be
             generally followed.
      22.3   The position that the Explanation to Rule 3 is in the nature
             of a guideline is strengthened by the fact that Clause 5.4.7
G            of the National Electricity Policy has a similar provision
             relating to minimum area of supply that acts only as a
             guidance in discharge of statutory functions. Sections 61(i)
             and 86(4) of the 2003 Act clearly states that both the
             National Electricity Policy and the Tariff Policy will act
             as a guidance.
H
M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                 397
 ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


    22.4   The learned senior counsel for the appellant-JSPL               A
           reiterated that the Central Government’s power to
           introduce a substantive rule defining the area of licence
           cannot be traced to any provision under the statute. On
           the contrary, the area of supply has to be prescribed in
           the licence issued by the State Government under Sections
                                                                           B
           2(3), 14, 15 and 86(1)(d) of the 2003 Act to each and
           every supplier. Therefore, Explanation to Rule 3 is without
           authority of law. In this behalf, the learned senior counsel
           for the appellant placed reliance on Bhaskar Shrachi
           Alloys Ltd. v. Damodar Valley Corporation (2018) 8
           SCC 281, Kerala Samsthana Chethu Thozhilali Union               C
           v. State of Kerala & Ors. (2006) 4 SCC 327 and
           Bharathidasan University & Anr. v. All India Council
           for Technical Education & Ors. (2001) 8 SCC 676.
    22.5   It was further contended that in the instant case, the
           distribution licence was granted on 29.09.2005 and the          D
           same was confirmed by the Appellate Authority vide order
           dated 11.05.2006 in Appeal No.27 of 2006. Therefore,
           there was no occasion to challenge the vires of 2005
           Rules. Even if the Rules have not been specifically
           challenged, the same cannot be applied if found to violate
           any provision.                                                  E

    22.6   It was submitted that if the Explanation to Rule 3 is applied
           to the present case as a substantive rule, it would result in
           impairment of vested/accrued rights of the appellant-JSPL
           and the consumers of Jindal Industrial Park. At the time
           of making a formal application on 15.09.2004, the 2005          F
           Rules were not in existence. The appellant-JSPL had
           acted bonafide, in terms of concurrence/permission of
           the State Government under the repealed 1910 Act and
           also under the present 2003 Act, the same cannot be now
           made to suffer on account of delay in grant of licence          G
           and introduction of the 2005 Rules. The learned senior
           counsel for the appellant stated that the same cannot be
           done in terms of various judgments passed by this Court
           viz. P. Mahendran v. State of Karnataka (1990) 1 SCC
           411, A.A. Calton v. Director of Education (1983) 3 SCC
                                                                           H
398     SUPREME COURT REPORTS                         [2022] 7 S.C.R.


A            33 and Gopal Krushna Rath v. M.A.A. Baig (dead) by
             LRs (1999) 1 SCC 544. Placing reliance on Federation
             of Indian Mineral Industries & Ors. v. Union of India
             & Anr. (2017) 16 SCC 186, the learned senior counsel
             urged that a subordinate legislation cannot be made to
             have a retrospective effect unless the parent statute,
B
             expressly or by necessary implication authorizes it to do
             so.
      22.7   The next limb of argument was that the exercise of power
             by the State Government in allowing the appellant-JSPL
             in these appeals to proceed with supply of electricity
C            manifests in the form of the terms of the MoU dated
             23.10.2002 as well as letters dated 29.01.2003 and
             28.02.2004. These permissions were no less than a
             sanction contemplated under Section 28 of the 1910 Act
             and thus saved in terms of Section 6 of the General
D            Clauses Act, 1897 and Section 185 of the 2003 Act. In
             this regard, the learned senior counsel for the
             appellant-JSPL banked upon Hindustan Unilever Ltd.
             v. State of Madhya Pradesh (2020) 10 SCC 751 and
             Gujarat Electricity Board v. Shantilal R. Desai (1969)
             1 SCR 580.
E
      22.8   It was further submitted that on the basis of amendment
             that came into effect on 27.01.2004, the legislature
             replaced the word ‘including’ with ‘relating to’ in sixth
             proviso to Section 14 of the 2003 Act. The word ‘including’
             makes the provision expansive as has been held by this
F            Court in the cases of DAV College Trust and
             Management Society & Ors. v. Director of Public
             Instructions & Ors. 2019 (9) SCC 185 and C.I.T
             Andhra Pradesh v. M/s. Taj Mahal Hotel,
             Secunderabad 1971 (3) SCC 550. Further, the
G            Parliament curtailed the power of the Central Government
             and by an amendment removed the word ‘including’ and
             instead used the term ‘relating to’. For something to be
             treated as ‘relating to’ a provision, it has to established
             that ‘the dominant purpose and theme of the provision is
             one and one only’ as was observed in the case of Madhav
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                      399
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


               Rao Jivaji Rao Scindia v. Union of India (1971) 1 SCC             A
               85. Therefore, a restrictive meaning must be given to the
               sixth proviso.
      22.9     Placing reliance on Ramana Dayaram Shetty                v.
               International Airport Authority of India (1979) 3 SCC
               489, it was further urged that the appellant-JSPL has             B
               been supplying electricity to its consumers since
               01.03.2004 and has taken regulatory/contractual/legal steps
               thereof and the decision to deny distribution licence is
               detrimental to the interest of the appellant-JSPL as well
               as the consumers.
                                                                                 C
      23. The submissions of the learned senior counsel Sri
Vaidyanathan for the appellant in Civil Appeal Nos.4104-4107 of 2008
are encapsulated as under:
      23.1 The appellant herein is a consumer of electricity supplied
           by JSPL in Jindal Industrial Park. The judgment of the                D
           Appellate Tribunal in so far as the same sets aside the grant
           of distribution licence by the Commission without appointing
           any alternative distribution licence is ultra vires the 2003
           Act read with the 2005 Rules.
      23.2 The Appellate Tribunal failed to appreciate the scheme of             E
           the 2003 Act that does not permit the Commission or the
           Tribunal to cancel a distribution licence without hearing the
           consumers. The entire purpose and object of the 2003 Act
           was to liberalise the generation, transmission, distribution
           and supply of electricity to prevent monopolies from
           demanding heavy electrical charges from consumers and                 F
           open access was permitted so that any trader or distributor
           could, as of right, distribute and supply electricity to industries
           or consumers who demanded electricity through the
           particular trader or distributor. The sixth proviso to Section
           14 of the 2003 Act makes the aforesaid position even clearer          G
           by providing for more than one licensee distributing and
           supplying power in the same area.
      23.3 The area of supply is defined under Section 2(3) of the
           2003 Act and nowhere, the Act has defined the area of
           supply as restricted to mean an entire district or an entire
                                                                                 H
400      SUPREME COURT REPORTS                          [2022] 7 S.C.R.


A           area of the municipality under Article 243Q of the
            Constitution of India.
      23.4 The Appellate Tribunal failed to note that CSEB was not
           operating in the Jindal Industrial Park and therefore
           cancelling the distribution licence on this ground was
B          incorrect. CSEB itself expressed its inability to supply power
           in the Jindal Industrial Park during the hearing before the
           Appellate Tribunal.
      23.5 Further, Explanation to Rule 3 does not indicate that the
           second licensee must have a minimum area of supply as
C          construed by the Appellate Tribunal. The term ‘same area’
           appearing in the Explanation states what should be the area
           for which the two licensees may be said to be operating
           ‘within the same area’. The term same area has not been
           explained in the 2003 Act or in the 2005 Rules and the
           Explanation, gives the meaning that the overlapping must
D          be at least of an area comprised within a Municipal
           Corporation or a revenue district, etc.
      23.6 The Central Government in making rules under Section 14
           of the 2003 Act has added an Explanation to Rule 3(2) of
           the 2005 Rules by which it has restricted the concept of
E          same area in terms of the sixth proviso to Section 14 of the
           2003 Act to ‘the area comprising a municipal council or a
           municipal corporation as defined in Article 243Q of the
           Constitution of India or a revenue district, which shall be
           the minimum area of supply. The said construction is fully
F          inconsistent and violative of the express provision of sixth
           proviso to Section 14 of the said 2003 Act and goes counter
           to the entire spirit, purpose and object of the 2003 Act.
      23.7 The grant of distribution licence is an administrative
           function of the Commission and the Appellate Tribunal had
G          no jurisdiction to interfere as was rightly held in the earlier
           judgment of the Appellate Tribunal dated 11.05.2006. That
           under the 2003 Act, the Appellate Tribunal is neither
           empowered to grant licence nor to cancel the same.
      23.8 By virtue of Section 19 of the 2003 Act, only the Commission
           is empowered to revoke a license, that too, after complying
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                   401
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


            with the procedural safeguards therein and no such power          A
            has been conferred upon the Appellate Tribunal. Further,
            no appeal can lie from an executive order passed by the
            Commission.
      23.9 There are more than thirty industries that have been set up
           in Jindal Industrial Park by investing more than Rs.600            B
           crores. More than 4000 direct employees are provided
           employment. Therefore, cancelling the said distribution
           licence is opposed to public policy.
      23.10 Learned senior counsel, Sri C.S. Vaidyanathan appearing
            for the appellant in C.A. Nos. 4104-4107 of 2008 contended        C
            that the said appellant was one of the consumers of electricity
            being supplied by JSPL and on account of the cancellation
            of the licence, the appellant had been adversely affected
            and therefore the impugned judgment of Appellate Tribunal
            may be set aside and the Order of the respondent No.1
            may be given effect to.                                           D

       24. The submissions of the learned counsel for respondent No.1
in Civil Appeal Nos.3607-3610 of 2008 are summarised as under:
      24.1 The term ‘within the same area’ appearing in the Explanation
           to Rule 3 of the 2005 Rules has to be read as being an area        E
           comprising of a Municipal Council or a Municipal
           Corporation as defined in Article 243(Q) of the Constitution
           of India or a revenue district. The said Explanation provides
           for a minimum area of supply for grant of a parallel/second
           distribution license. For a minimum area to be provided as a
           qualifying condition for grant of distribution license, an         F
           interpretation that the area should merely fall within a
           revenue district or the municipal council, would negate the
           very provision of a minimum area as a qualifying criterion.
           Thus, the concept of a minimum area would be inherently
           inconsistent or contradictory to the interpretation that the       G
           area needs to fall within and not equivalent to the area
           comprised of a municipal corporation or a revenue district.
      24.2 A distribution licensee has a universal supply obligation under
           Section 43 of the 2003 Act, i.e., to supply electricity to any
           person requiring the same within the area of its operation.
                                                                              H
402            SUPREME COURT REPORTS                          [2022] 7 S.C.R.


A                 It was submitted that Para 5.4.7 of the National Electricity
                  Policy makes clear the intention of Government of India on
                  the minimum area to be provided for grant of a second/
                  parallel distribution license. The purpose of prescription of
                  minimum area as comprising of a municipal corporation/
                  council or a revenue district is that there would be a mix of
B
                  all categories of consumers within the said area. Thus, the
                  second distribution licensee would also be under an obligation
                  to supply electricity to all consumers within such area, and
                  not only to high paying consumers. Hence, cherry picking
                  of the consumers has to be avoided and therefore the
C                 Government of India thought it fit to prescribe a minimum
                  area for which a second distribution licence can be granted.
            24.3 Thus, the minimum area condition specified in Explanation
                 to Rule 3 needs to be fulfilled for grant of the second
                 distribution license. The said distribution licence is neither
D                co-terminus with the existence of the revenue district nor
                 would the distribution licence be amended, revoked or in
                 any manner affected by delimitation or consolidation of
                 revenue districts. Any subsequent change to the area on
                 account of consolidation of revenue district etc. would not
                 affect the area for which the distribution licence has been
E                granted which is the area of minimum supply.
            24.4 That the cancellation of licence granted by the State
                 Commission was not proper in the instant case as the State
                 Commission, after considering the entire factual situation
                 and while making an exception, has already directed that
F                JSPL would be required to supply electricity to two villages,
                 namely, Tumdih and Punjipathra.
            24.5 It was therefore contended that the Appellate Tribunal was
                 not right in setting aside the order of the Commission.

G            25. The submissions of the learned counsel for respondent No.2
      in Civil Appeal Nos.3607-3610 of 2008 are encapsulated as follows:
            25.1 That the National Electricity Policy framed by the
                 Government of India, Ministry of Power, under Section 3 of
                 the 2003 Act stipulates that the area of supply under a
                 distribution licence has necessarily to be a minimum area
H
M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                  403
 ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


          comprising a revenue district, a municipal council for a          A
          smaller urban area or a municipal corporation for a larger
          urban area. By virtue of Section 86(4) of the 2003 Act, the
          State Commission is statutorily bound to be guided by the
          said National Electricity Policy. Placing reliance on the
          judgment of this Court in Energy Watchdog v. Central
                                                                            B
          Electricity Regulatory Commission and Others (2017)
          14 SCC 80, the learned counsel for respondent No.2
          submitted that in the context of Tariff Policy, a tariff policy
          issued under Section 3 of the 2003 Act has the force of
          law. Similarly, the aforesaid provision in National Electricity
          Policy was statutorily embodied in the 2005 Rules.                C
    25.2 Further, a combined reading of the above provisions of the
         Electricity Act, 2003, the National Electricity Policy and
         2005 Rules, the legal position that emerges is that the
         ‘minimum area of supply’ for grant of a distribution licence
         has to comprise the entire area of a municipal council or a        D
         municipal corporation or a revenue district. No distribution
         licence can be granted for a lesser area even though such
         lesser area forms a part of the municipal council or a
         municipal corporation or a revenue district.
    25.3 The interpretation that it can be ‘any area’ which falls within    E
         a municipal council or a municipal corporation or a revenue
         district would defeat the very object sought to be achieved
         by the legislature by providing for universal supply obligation
         of the distribution licence to supply electricity in its area of
         supply read with Explanation 3 of 2005 Rules. Such
         interpretation would render the Explanation nugatory and           F
         redundant and it is a settled principle of interpretation that
         redundancy cannot be attributed to the legislature. Reliance
         in this regard was placed on the judgment in the case of
         Thampanoor Ravi v. Charupara Ravi (1999) 8 SCC
         74.                                                                G
    25.4 The condition of minimum area of supply as mandated by
         sixth proviso to Section 14 of the 2003 Act read with
         Explanation to Rule 3(2) of the 2005 Rules is integral to
         ‘fair competition’ and ‘level playing field’. The same is
         necessary to fulfill the statutory obligations of universal        H
404      SUPREME COURT REPORTS                            [2022] 7 S.C.R.


A            supply stipulated under Section 43 of the 2003 Act. Further,
             in the regime of multiple licenses introduced under the 2003
             Act, insistence upon minimum area of supply prevents any
             form of cherry picking of high end-consumers only in a
             self-chosen area of supply as in the present case.
B     25.5 While relying on the judgment of this Court in Peerless
           General Finance & Investment Co. Ltd. v. Reserve
           Bank of India (1992) 2 SCC 343 and Chief Forest
           Conservator (Wildlife) & Ors. v. Nisar Khan (2003) 4
           SCC 595, it was urged that the Explanation to Rule 3 of the
           2005 Rules was enacted so as to effectuate the working
C          of the 2003 Act and is therefore a part of the said Act.
           Thus, the requirement of minimum area of supply for grant
           of distribution licence is an integral part of the scheme of
           grant of distribution licence under the 2003 Act read with
           2005 Rules.
D     25.6 Therefore, in light of the aforesaid submission, JSPL was
           not entitled to a licence under Section 14 of the 2003 Act as
           it does not satisfy the condition of ‘minimum area of supply’.
      25.7 The Commission, while granting license, vide order dated
           29.09.2005 was well-aware that the appellant JSPL did not
E          satisfy the requirement of the ‘minimum area of supply’ as
           specified in the Explanation to Rule 3 and was not in a
           position to fulfill its statutory duty/universal obligation under
           Section 43 of the 2003 Act. Therefore, the Commission
           imposed a special condition on the appellant by granting
F          distribution licence to JSPL for two villages namely Tumdih
           and Punjipathra of Tehsil Gharghoda, District Raigarh and
           remaining area of these two villages. Even the said special
           condition imposed does not amount to compliance of the
           condition regarding ‘minimum area of supply’ for grant of a
           second licence as mandated in the Explanation to Rule 3(2).
G
      25.8 The appellant was duty bound by the special condition in
           the order granting distribution licence to provide supply of
           power to consumers of the aforesaid two villages. However,
           the appellant- JSPL has been making huge profits by
           supplying electricity only to twenty-five industries in the
H
M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                    405
 ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


           Jindal Industrial Park and has completely failed to fulfill its    A
           obligation to supply power to two villages namely Tumdih
           and Punjigraha of Tehsil Gharghoda, District Raigarh.
    25.9 Due to this gross and flagrant violation by the appellant-JSPL
         of the special condition imposed by the Commission, the
         Distribution Company i.e., the Chhattisgarh State Power              B
         Distribution Company Limited has been deprived of revenue
         to the extent of Crores of rupees per month. Thus, keeping
         in view the above, the licence granted needs to be quashed
         on this ground too.
    25.10 The appellant’s contention that the 2005 Rules were not in          C
          existence at the time of filing of the application for
          distribution licence by the appellant-JSPL and that the grant
          of such licence cannot be faulted with on the ground of
          violation of Rule, is highly misconceived, since, it is a settled
          position of law that the Authority is required to apply the
          Rules and legal provisions in force on the date when the            D
          application is considered. Further, the argument of the
          appellant-JSPL that the Explanation is only in the nature of
          a guideline is also devoid of any merit. In this regard, the
          counsel for respondent No.2 placed reliance on the following
          judgment passed by this Court in Howrah Municipal                   E
          Corporation and Ors. v. Ganges Rope Co. Ltd. and Ors.
          (2004) 1 SCC 663, Union of India and Ors. v. Indian
          Charge Chrome and Anr. (1999) 7 SCC 314, M/s.
          Hiralal Rattanlal etc. etc. v. State of U.P. and Anr. etc.
          etc. (1973) 1 SCC 216 and Dattatraya Govind Mahajan
          v. State of Maharashtra (1977) 2 SCC 548.                           F

    25.11 Explanation to Rule 3 of the 2005 Rules cannot be said to
          have no authority of law. The 2005 Rules have been enacted
          in exercise of power under Section 176(1) and Section
          176(2)(b) of the 2003 Act. Further since the appellant-JSPL
          has not even challenged the vires of the 2005 Rules, the            G
          appellant-JSPL is estopped from raising the contention that
          Explanation to Rule 3 of the 2005 Rules has no authority of
          law.
    25.12 The contention that the appellant-JSPL acted bonafide in
          terms of the concurrence/permission of the State                    H
406            SUPREME COURT REPORTS                            [2022] 7 S.C.R.


A                  Government as the same are saved under Section 6 of the
                   General Clauses Act, 1897 as also Section 185 of the 2003
                   Act is also misconceived and untenable. The counsel for
                   respondent No.2 urged that the Appellate Tribunal in the
                   impugned judgment rightly pointed out that all the permissions
                   given by the State Government and other authorities were
B
                   specifically made subject to and conditional upon the licence
                   being granted by the Commission under the 2003 Act. It is,
                   therefore, incorrect for the appellant to rely on the
                   permissions/concurrences given by the State Government
                   since the appellant does not satisfy the requirement of
C                  minimum area of supply as mandated under Explanation to
                   Rule 3 of 2005 Rules.
            25.13 The submission of the appellant-JSPL that the sixth proviso
                  to Section 14 has been amended to narrow down the scope
                  of Rule-making power is also misconceived. The substitution
D                 of the word ‘relating to’ in place of the word ‘including’
                  does not amount to restricting the scope of the rule-making
                  power. The term ‘relating to’ is of wide amplitude and cannot
                  be restrictive in any manner.
            25.14 Further, the submission of appellant that the grant of
E                 distribution licence was in public interest is devoid of any
                  merit since the appellant has only been furthering its own
                  interest.
            25.15 To sum up, the counsel for respondent No.2 strenuously
                  contended that the ‘minimum area of supply’ as provided in
F                 the Explanation to Rule 3 of 2005 Rules is a mandatory
                  requirement for grant of second or subsequent distribution
                  licence in the area of supply of an existing distribution
                  license. It was thus contended by respondent No.2 that the
                  Tribunal was correct in setting aside the order granting licence
                  to the appellant.
G
            26. Having heard learned senior counsel and counsel for the
      respective parties, it is noted that the appellants in both the appeals are
      challenging the order dated 07.05.2008 whereby the Appellate Tribunal
      allowed the appeals filed by the respondents herein and set-aside the
      order passed by the Commission dated 29.05.2005, thereby, canceling
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                           407
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


the distribution licence granted in favour of the appellant for supply of             A
power by the appellant from its captive power plant to the industrial units
in Jindal Industrial Park.
        27. Before delving further upon the various issues in the present
matter, we shall analyse relevant provisions of the 2003 Act. The 2003
Act, came into force on 10.06.2003 insofar as Sections 1 to 120 and                   B
Sections 122 to 185 are concerned. The Preamble of the 2003 Act states
that it has been enacted to consolidate the laws relating to generation,
transmission, distribution, trading and use of electricity and generally for
taking measures conducive to development of electricity industry,
promoting competition therein, protecting interest of consumers and
supply of electricity to all areas, rationalization of electricity tariff, ensuring   C
transparent policies regarding subsidies, promotion of efficient and
environmentally benign policies, constitution of Central Electricity
Authority, Regulatory Commissions and establishment of Appellate
Tribunal and for matters connected therewith or incidental thereto.
       28. Section 2 of the 2003 Act is the definition clause and the relevant        D
definitions for the purposes of the present cases read as under:
       “Section 2. (Definitions): --- In this Act, unless the context
       otherwise requires, --
                                xxxxxxxxx                                             E
       (3) “area of supply” means the area within which a distribution
       licensee is authorised by his licence to supply electricity;
       (4) “Appropriate Commission” means the Central Regulatory
       Commission referred to in sub-Section (1) of Section 76 or the
       State Regulatory Commission referred to in Section 82 or the                   F
       Joint Commission referred to in Section 83, as the case may be;
                                     xxxxxx
       (38) “licence” means a licence granted under Section 14;
       (39) “licensee” means a person who has been granted a licence                  G
       under Section 14;
                                   xxxxxxxx
       (41) “local authority” means any Nagar Panchayat, Municipal
       Council, Municipal Corporation, Panchayat constituted at the
                                                                                      H
408             SUPREME COURT REPORTS                             [2022] 7 S.C.R.


A           village, intermediate and district levels, Body of Port Commissioners
            or other authority legally entitled to, or entrusted by the Union or
            any State Government with, the control or management of any
            area or local fund;
                                       xxxxxxxx
B           (64) “State Commission” means the State Electricity Regulatory
            Commission constituted under sub-Section (1) of Section 82 and
            includes a Joint Commission constituted under sub- Section (1) of
            Section 83;”
            29. Part II of the 2003 Act deals with National Electricity Policy
C     and Plan. In compliance with section 3 of the 2003 Act, the Central
      Government has notified the National Electricity Policy dated 12th February,
      2005, the relevant portions of which are extracted as under:
            “1.0 INTRODUCTION

D                                       X.X.X.
            1.5 Electricity industry is capital-intensive having long gestation
            period. Resources of power generation are unevenly dispersed
            across the country. Electricity is a commodity that can not be
            stored in the grid where demand and supply have to be continuously
            balanced. The widely distributed and rapidly increasing demand
E
            requirements of the country need to be met in an optimum manner.
            1.6 Electricity Act, 2003 provides an enabling framework for
            accelerated and more efficient development of the power sector.
            The Act seeks to encourage competition with appropriate
            regulatory intervention. Competition is expected to yield efficiency
F
            gains and in turn result in availability of quality supply of electricity
            to consumers at competitive rates.
            1.7 Section 3 (1) of the Electricity Act 2003 requires the Central
            Government to formulate, inter alia, the National Electricity Policy
            in consultation with Central Electricity Authority (CEA) and State
G           Governments. The provision is quoted below:
                “The Central Government shall, from time to time, prepare
                the National Electricity Policy and tariff policy, in
                consultation with the State Governments and the Authority
                for development of the power system based on optimal
H
M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                 409
 ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


       utilization of resources such as coal, natural gas, nuclear         A
       substances or materials, hydro and renewable sources of
       energy”.
    Section 3 (3) of the Act enables the Central Government to review
    or revise the National Electricity Policy from time to time.
    1.8 The National Electricity Policy aims at laying guidelines for      B
    accelerated development of the power sector, providing supply of
    electricity to all areas and protecting interests of consumers and
    other stakeholders keeping in view availability of energy resources,
    technology available to exploit these resources, economics of
    generation using different resources, and energy security issues.      C
                              X.X.X.
    5.4 DISTRIBUTION
                              X.X.X.
    5.4.7 One of the key provisions of the Act on competition in           D
    distribution is the concept of multiple licensees in the same area
    of supply through their independent distribution systems. State
    Governments have full flexibility in carving out distribution zones
    while restructuring the Government utilities. For grant of second
    and subsequent distribution licence within the area of an incumbent
                                                                           E
    distribution licensee, a revenue district, a Municipal Council for a
    smaller urban area or a Municipal Corporation for a larger urban
    area as defined in the Article 243(Q) of Constitution of India
    (74th Amendment) may be considered as the minimum area. The
    Government of India would notify within three months, the
    requirements for compliance by applicant for second and                F
    subsequent distribution licence as envisaged in Section 14 of the
    Act. With a view to provide benefits of competition to all section
    of consumers, the second and subsequent licensee for distribution
    in the same area shall have obligation to supply to all consumers
    in accordance with provisions of section 43 of the Electricity Act,
                                                                           G
    2003. The SERCs are required to regulate the tariff including
    connection charges to be recovered by a distribution licensee under
    the provisions of the Act. This will ensure that second distribution
    licensee does not resort to cherry picking by demanding
    unreasonable connection charges from consumers.”
                                                                           H
410             SUPREME COURT REPORTS                            [2022] 7 S.C.R.


A            30. Part III deals with generation of electricity. Part IV of the
      2003 Act is of relevance to these cases as it concerns licensing. Section
      12 states that no person shall (a) transmit electricity; or (b) distribute
      electricity; or (c) undertake trading in electricity, unless he is authorised
      to do so by a licence issued under Section 14, or is exempt under Section
      13. The power to exempt is prescribed in Section 13. The grant of licence
B
      is as per Section 14 and the procedure for grant of licence is dealt with
      in Section 15 while the conditions of licence are in terms of Section 16.
      Section 18 of the said Act speaks of Amendment of licence while Section
      19 concerns revocation of licence.
            31. Section 14 of the 2003 Act which deals with grant of licence
C     reads as under:
            14. Grant of licence- The Appropriate Commission may, on an
            application made to it under Section 15, grant a licence to any
            person –
            (a) to transmit electricity as a transmission licensee; or
D
            (b) to distribute electricity as a distribution licensee; or
            (c) to undertake trading in electricity as an electricity trader,
            in any area as may be specified in the licence:
            Provided that any person engaged in the business of transmission
E           or supply of electricity under the provisions of the repealed laws
            or any Act specified in the Schedule on or before the appointed
            date shall be deemed to be a licensee under this Act for such
            period as may be stipulated in the licence, clearance or approval
            granted to him under the repealed laws or such Act specified in
F           the Schedule, and the provisions of the repealed laws or such Act
            specified in the Schedule in respect of such licence shall apply for
            a period of one year from the date of commencement of this Act
            or such earlier period as may be specified, at the request of the
            licensee, by the Appropriate Commission and thereafter the
            provisions of this Act shall apply to such business:
G
                   Provided further that the Central Transmission Utility or
            the State Transmission Utility shall be deemed to be a transmission
            licensee under this Act:
            Provided also that in case an Appropriate Government transmits
            electricity or distributes electricity or undertakes trading in
H
M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                  411
 ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


    electricity, whether before or after the commencement of this           A
    Act, such Government shall be deemed to be a licensee under this
    Act, but shall not be required to obtain a licence under this Act:
    Provided also that the Damodar Valley Corporation, established
    under sub-Section (1) of Section 3 of the Damodar Valley
    Corporation Act, 1948, (14 of 1948), shall be deemed to be a            B
    licensee under this Act but shall not be required to obtain a licence
    under this Act and the provisions of the Damodar Valley Corporation
    Act, 1948, in so far as they are not inconsistent with the provisions
    of this Act, shall continue to apply to that Corporation:
           Provided also that the Government company or the company         C
    referred to in sub-Section (2) of Section 131 of this Act and the
    company or companies created in pursuance of the Acts specified
    in the Schedule, shall be deemed to be a licensee under this Act:
    Provided also that the Appropriate Commission may grant a licence
    to two or more persons for distribution of electricity through their    D
    own distribution system within the same area, subject to the
    conditions that the applicant for grant of licence within the same
    area shall, without prejudice to the other conditions or requirements
    under this Act, comply with the additional requirements relating to
    the capital adequacy, credit-worthiness, or code of conduct as
    may be prescribed by the Central Government, and no such                E
    applicant, who complies with all the requirements for grant of
    licence, shall be refused grant of licence on the ground that there
    already exists a licensee in the same area for the same purpose:
    Provided also that in a case where a distribution licensee proposes
    to undertake distribution of electricity for a specified area within    F
    his area of supply through another person, that person shall not be
    required to obtain any separate licence from the concerned State
    Commission and such distribution licensee shall be responsible
    for distribution of electricity in his area of supply:
    Provided also that where a person intends to generate and distribute    G
    electricity in a rural area to be notified by the State Government,
    such person shall not require any licence for such generation and
    distribution of electricity, but he shall comply with the measures
    which may be specified by the Authority under Section 53:
                                                                            H
412             SUPREME COURT REPORTS                              [2022] 7 S.C.R.


A            Provided also that a distribution licensee shall not require a licence
             to undertake trading in electricity.
             32. On a reading of Section 14 of the 2003 Act, it is clear that the
      appropriate Commission may, on an application made to it under Section
      15 grant a licence to any person (a) to transmit electricity as a transmission
B     licensee; or (b) to distribute electricity as a distribution licensee; or (c) to
      undertake trading in electricity as an electricity trader, in any area as
      may be specified in the licence.
             33. The first three provisos to Section 14 of the 2003 Act are in
      the nature of saving clauses. The fourth and fifth provisions are not
C     relevant to these cases. The sixth proviso which is under consideration
      states that the appropriate Commission may grant a licence to two or
      more persons for distribution of electricity through their own distribution
      system within the same area, subject to the conditions that the applicant
      for grant of licence within the same area, shall, without prejudice to the
      other conditions or requirement under the Act comply with the additional
D     requirements relating to the capital adequacy, creditworthiness, or code
      of conduct as may be prescribed by the Central Government, and no
      such applicant, who complies with all the requirements for grant of licence,
      shall be refused grant of licence on the ground that there already exists
      a licensee in the same area for the same purpose.
E           34. The Central Government had enunciated the 2005 Rules w.e.f.
      23.03.2005 as per Section 176 of the 2003 Act. Rule 3 is relevant for the
      purpose of these cases is extracted as under:
             3. Requirements of capital adequacy and creditworthiness.
             — (1) The Appropriate Commission shall, upon receipt of an
F            application for grant of licence for distribution of electricity under
             sub-Section (1) of Section 15 of the Electricity Act, 2003, decide
             the requirement of capital investment for distribution network after
             hearing the applicant and keeping in view the size of the area of
             supply and the service obligation within that area in terms of Section
G            43.
             (2) The applicant for grant of licence shall be required to satisfy
             the Appropriate Commission that on a norm of 30% equity on cost
             of investment as determined under sub-rule (1), he including the
             promoters, in case the applicant is a company, would be in a position
             to make available resources for such equity of the project on the
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                     413
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


      basis of the networth and generation of internal resources of his         A
      business including of promoters in the preceding three years after
      excluding his other committed investments.
      Explanation—For the grant of a licence for distribution of electricity
      within the same area in terms of sixth proviso to Section 14 of the
      Act, the area falling within a Municipal Council or a Municipal           B
      Corporation as defined in the article 243(Q) of the Constitution of
      India or a revenue district shall be the minimum area of supply.
       35. The controversy in these cases surrounds the interpretation
to be given to the Explanation to Rule 3. As already noted, the 2005
Rules, under consideration have been prescribed having regard to the            C
sixth proviso to Section 14 of the Act. The said proviso would apply only
when the appropriate Commission considers it necessary to grant a licence
to two or more persons for distribution of electricity through their own
distribution system within the same area, in which case, there are certain
additional requirements which the applicant must fulfil relating to capital
adequacy, creditworthiness or code of conduct. It is only with regard to        D
the aforesaid three aspects that the 2005 Rules have been prescribed.
       36. In response to the arguments of learned senior counsel for
the appellants, the contention of respondent No.2 herein is that the
appellant-JSPL does not fulfil the condition mentioned in the Explanation
to Rule 3 inasmuch as the said appellant does not fulfil the condition of       E
minimum area of supply as the area that the said appellant is supplying,
is not for an entire Municipal Council or a Municipal Corporation or a
Revenue District. The area of supply as per the licence of the
appellant-JSPL is for the area comprised in the industrial park set up by
the appellant and for two other villages only. Hence, the licence issued        F
to the said appellant is vitiated as the area of supply prescribed in the
licence does not conform to the Explanation to Rule 3 of the 2005 Rules.
       37. In order to answer the aforesaid contention, it would be
necessary to consider the sixth proviso to Rule 14 in light of the definition
of ‘area of supply’ and the Explanation to Rule 3 of the 2005 Rules. On         G
a conjoint reading of the same, it is noted that the sixth proviso to Section
14 applies to a situation where the appropriate Commission may grant a
licence to two or more persons for distribution of electricity through
their own distribution system within the same area subject to the
applicant-JSPL complying with the additional requirements. Therefore,
                                                                                H
414             SUPREME COURT REPORTS                             [2022] 7 S.C.R.


A     it is clear that within the same area, there could be two or more persons
      for distribution of electricity. As to what is the area within which there
      could be grant of licence to two or more persons is concerned under the
      sixth proviso to Section 14, the Explanation to Rule 3 prescribes the
      area falling within a Municipal Council or a Municipal Corporation as
      defined under Article 243 (Q) of the Constitution of India or Revenue
B
      District. The area of supply authorised by the Appropriate Commission
      shall be the minimum area of supply.
             38. The ‘area of supply’ is defined under sub-section 3 of Section
      2 to mean that area within which the distribution licensee is authorised
      by his licence to supply electricity. This ‘area of supply’ must fall ‘within’
C     a Municipal Council or a Municipal Corporation as defined under Article
      243 (Q) of the Constitution of India or a Revenue District. That means
      that the ‘area of supply’ must fall ‘within’ the local authority of a Municipal
      Council or a Municipal Corporation as defined in sub-section 41 of
      Section 2 of the Act or a Revenue District, as the case may be, and
D     within which area of supply, licence is granted for distribution of
      electricity. Therefore, the expression area in the sixth proviso of Section
      14 is explained as the ‘area falling within’ a Municipal Council or a
      Municipal Corporation as defined under Article 243 (Q) of the Constitution
      of India or a Revenue District which shall be the ‘area of supply’. As
      already noted, within such area, there could be two or more persons
E     who are granted a licence to distribute electricity which is in terms of the
      provision granting license. The ‘area within which they are authorised to
      supply electricity’ is the ‘area of supply’ and such ‘area of supply’ in
      respect of which authorisation is granted under the licence is the
      “minimum area of supply”.
F            39. Therefore, when two or more persons are granted licence within
      an area forming a Municipal Council or a Municipal Corporation or a
      Revenue District, the authorisation to supply electricity granted to a
      distribution licensee within the aforesaid area is the actual area of supply
      and the actual area of supply in respect of which the authorisation is
G     granted under the licence is called the minimum area of supply.
             40. Thus, on a conjoint reading of the aforesaid provisions, it
      is clear that the ‘minimum area of supply” would fall ‘within the area’
      which is comprising of a Municipal Council or a Municipal Corporation
      or a Revenue District but it does not imply that the licence to supply
H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                     415
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


electricity for an area or an ‘area of supply which is the ‘minimum area        A
of supply’ must extend to the ‘entire area falling within’ a Municipal
Council or a Municipal Corporation or a Revenue District.
       41. But if the interpretation as suggested by the respondent No.2
is to be accepted, then the expression ‘area falling within’ in the
Explanation would become otiose or redundant. The object of providing           B
a Municipal Council or a Municipal Corporation or a Revenue District
as an area is to provide a standard area, within which area, two or
more persons could distribute electricity. It does not mean that the licensee
must distribute electricity in the entire standard area. The words used
are ‘the area falling within’ a Municipal Council or a Municipal Corporation
or a Revenue District. The same does not mean that the area comprising          C
of or an area equivalent to a Municipal Council or a Municipal Corporation
or a Revenue District. It is only in an ‘area falling within’ a Municipal
Council or a Municipal Corporation or a Revenue District that two or
more persons could be granted licence for distribution of electricity which
interpretation is supported by the use of the expressions ‘within the same      D
area’ used twice in the sixth proviso to Section 14 of the 2003 Act.
Also, the use of the expression ‘within the same area’ in the sixth proviso
as well as in the Explanation to Rule 3 have to carry the same meaning.
       42. Moreover, the expression ‘within the same area’ in the sixth
proviso to Section 14 of the 2003 Act and the Explanation is analogous          E
to the expression ‘the area falling within’ a Municipal Council or a
Municipal Corporation or a Revenue District in the Explanation. Thus,
the expression ‘within the same area’ cannot refer to the entire Municipal
Council or a Municipal Corporation or a Revenue District but ‘the area
falling within’ a Municipal Council or a Municipal Corporation or a
Revenue District in respect of which a distribution licensee is authorised      F
by its licence to supply electricity. Therefore, by the aforesaid
interpretation it is held that the authorised ‘area of supply’ shall be ‘the
minimum area of supply’.
        43. Hence, the contention of respondent No.2 that the ‘minimum
area of supply’ must comprise of the ‘entire’ Municipal Council or a            G
Municipal Corporation or a Revenue District is not correct. The argument
in the instant case is that the appellant-JSPL, not complying with the
prescription in Explanation to Rule 3 of the 2005 Rules as per the terms
of the licence cannot be permitted to supply electricity and therefore, the
                                                                                H
416             SUPREME COURT REPORTS                           [2022] 7 S.C.R.


A     licence was rightly cancelled by the Appellate Tribunal also cannot be
      accepted.
              44. On the other hand, on a reading of the licence granted to the
      appellant, it is clear that the respondent No.1 was conscious of the fact
      that it was granting licence to the appellant-JSPL having regard to the
B     fact that the said appellant had established an industrial park for which it
      had the responsibility for distribution of electricity and in addition, two
      more villages were added to the area comprised in the industrial park
      for the purpose of distribution of electricity. The area in respect of
      which the licence was granted and thereby authorisation provided to
      supply electricity is the minimum area of supply. The ‘area of supply’ is
C     ‘an area falling within’ a Municipal Council or a Municipal Corporation
      or a Revenue District and in the instant case, it is a Revenue District.
      Since, the ‘area of supply’ authorised in the licence granted to the
      appellant-JSPL in the instant case is the ‘minimum area of supply’, the
      said appellant is bound to supply electricity in the said area of supply.
D     The licensee cannot resile from the condition of supplying electricity as
      per the authorisation of the area of supply indicated in the license. This
      would also mean that the licensee cannot supply electricity in an area
      beyond the area of supply authorised under the license. This is because
      in respect of an area falling within a Municipal Council or a Municipal
      Corporation or a Revenue District, there could be two or more persons
E     who could be granted licence and authorisation to distribute electricity in
      terms of the respective area of supply specified.
             45. In view of the aforesaid interpretation, we find no substance
      in the contentions advanced on behalf of the respondent No.2. On the
      other hand, on a reading of the order passed by the respondent No.1-
F     Commission in C.A. Nos. 3607-3610 of 2008, we find that there has
      been an application of mind to the licence that was granted to the
      appellant for distribution of the electricity.
             46. In view of the aforesaid discussion, we find that the Appellate
      Tribunal was not right in cancelling/setting aside the licence granted to
G     the appellant-JSPL and hence, the impugned judgment is liable to be set
      aside.
          47. In the result, the appeals are allowed and the impugned
      common judgment of the Appellate Tribunal is hereby set aside.

H
 M/S. JINDAL STEEL AND POWER LTD. v. THE CHHATTISGARH STATE                  417
  ELECTRICITY REGULATORY COMMISSION [B.V. NAGARATHNA, J.]


       48. Consequently, pending applications stand disposed by              A
reserving liberty to the applicants seeking impleadment to seek remedies
in accordance with law, if so advised.
       49. Parties to bear their respective costs.

Devika Gujral                                             Appeals allowed.
                                                                             B
(Assisted by : Shevali Monga, LCRA)




                                                                             C




                                                                             D




                                                                             E




                                                                             F




                                                                             G




                                                                             H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Electricity Act 2003"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

M/S. JINDAL STEEL AND POWER LIMITED versus THE CHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION AND ORS. — 2022 INSC 1036 - Legal Desk AI