M/S KKK HYDRO POWER LIMITEDversusHIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED AND OTHERS
- Citation
- 2025 INSC 1057
- Decided
- 29 August 2025
- Disposal
- Dismissed
- Bench
- SANJAY KUMAR
Holding
A power purchase agreement and any tariff amendment therein must be reviewed and approved by the State Electricity Regulatory Commission under Section 86(1)(b) of the Electricity Act, 2003; consequently the appellant could not claim the enhanced tariff for the entire project.
Summary
The appellant, KKK Hydro Power Ltd, entered into a 3 MW power purchase agreement (PPA) with HPSEB in 2000 fixing a tariff of ₹2.50/kWh, later augmenting the project to 4.90 MW and attempting to raise the tariff to ₹2.95/kWh through a supplementary PPA in 2010 without the Himachal Pradesh Electricity Regulatory Commission’s (Commission) approval. The Commission rejected the appellant’s claim for arrears at the enhanced tariff, and the Appellate Tribunal for Electricity (APTEL) partially allowed the claim, holding that the additional 1.90 MW capacity could be redetermined under the 2007 Regulations. The Supreme Court examined whether tariff changes in a PPA must be reviewed and approved by the State Commission under Section 86(1)(b) of the Electricity Act, 2003, and whether the supplementary PPA was valid without such approval. It held that fixing electricity purchase price is not a private matter and any amendment to tariff requires Commission approval; consequently the supplementary PPA was invalid and the appellant could not claim the enhanced tariff for the whole project. The Court declined to disturb the Commission’s weighted‑average tariff of ₹2.60/kWh already in force and dismissed the appeal.
Issues considered
- Whether the price of electricity in a power purchase agreement must be reviewed and approved by the State Electricity Regulatory Commission under Section 86(1)(b) of the Electricity Act, 2003.
- Whether the parties may amend the tariff in a PPA by private agreement without Commission approval.
- Whether the supplementary PPA dated 10‑09‑2010 is valid in the absence of Commission’s consent.
- Whether the appellant is entitled to the enhanced tariff of ₹2.95/kWh for the original 3 MW plant.
- Applicability of the Himachal Pradesh Electricity Regulatory Commission (Power Procurement from Renewable Sources and Cogeneration by Distribution Licensee) Regulations, 2007 to the PPA.
Legislation cited
Headnote
Issue for Consideration Himachal Pradesh Electricity Regulatory Commission (Commission) rejected the appellant’s petition for payment of arrears at an enhanced tariff for the electricity supplied by it to the Himachal Pradesh State Electricity Board Limited the appellant’s appeal in part and inter alia held that the tariff for its 3 MW hydel power plant under the PPA dated 30.03.2000 required no redetermination but, the tariff for its additional 1.90 MW hydel power plant required to be redetermined as per the Himachal Pradesh Electricity
Subjects
Judgment
[2025] 8 S.C.R. 2350 : 2025 INSC 1057
M/s KKK Hydro Power Limited
v.
Himachal Pradesh State Electricity Board Limited
and Others
(Civil Appeal No. 3005 of 2015)
29 August 2025
[Sanjay Kumar* and N.V. Anjaria, JJ.]
Issue for Consideration
Himachal Pradesh Electricity Regulatory Commission (Commission)
rejected the appellant’s petition for payment of arrears at an
enhanced tariff for the electricity supplied by it to the Himachal
Pradesh State Electricity Board Limited (HPSEB). APTEL allowed
the appellant’s appeal in part and inter alia held that the tariff for
its 3 MW hydel power plant under the PPA dated 30.03.2000
required no redetermination but, the tariff for its additional 1.90
MW hydel power plant required to be redetermined as per the
Himachal Pradesh Electricity Regulatory Commission (Power
Procurement from Renewable Sources and Cogeneration by
Distribution Licensee) Regulations, 2007; and the Commission was
directed to pass a consequential order. Whether the appellant and
HPSEB were bound to approach the Commission for its approval
before effecting enhancement of the tariff stipulated in the PPA
dated 11.03.2008.
Headnotes†
Electricity Act, 2003 – s.86(1)(b) – Mandate of, binding –
Appellant was to establish a Hydro Electric Power Project
of 3 MW capacity (revised capacity of 4.90 MW) – PPA fixed
the price to be paid by the HPSEB to the appellant at a fixed
rate of 2.50/- per kWh – Under their supplementary PPA dtd.
10.09.2010, the appellant and HPSEB enhanced the tariff from
₹2.50/- per kWh to ₹2.95/- per kWh without the Commission’s
review and approval – Appellant and the HPSEB, if were bound
to approach the Commission for its approval before effecting
enhancement of the tariff stipulated in the PPA dtd. 11.03.2008:
* Author
[2025] 8 S.C.R. 2351
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
Held: 1.1 Yes – Fixing of the price for the purchase of electricity
is not a matter of private negotiation and agreement between a
generating company and a distribution licensee – The price as
well as the agreement, i.e., PPA, incorporating such price and
providing for purchase of electricity at that price necessarily have
to be reviewed and approved by the State Commission u/s.86(1)
(b). [Para 26]
1.2 A generating company and a distribution licensee cannot, by
private agreement, execute a PPA on their own or stipulate tariff
therein as per their choice, for supply of electricity within a State,
without seeking the review and approval of the Electricity Regulatory
Commission u/s.86(1) (b). [Para 31]
1.3 The order dated 09.02.2010 passed by the Commission, without
reference to the appellant’s case, required only those existing PPAs
which stipulated the tariff of ₹2.87/- per kWh to be amended so as
to give effect to the enhancement of tariff from ₹2.87/- per kWh to
₹2.95/- per kWh – This order had no application at all to the case
of the appellant as its PPA dated 11.03.2008 did not stipulate the
tariff of ₹2.87/- per kWh. [Para 26]
1.4 Thus, the appellant and the HPSEB were bound to approach
the Commission to secure its approval before they could effect any
enhancement of the tariff stipulated in the PPA dated 11.03.2008 –
Without doing so, the appellant and the HPSEB on their own and
without the Commission’s review and approval, enhanced the tariff
from ₹2.50/- per kWh to ₹2.95/- per kWh under their supplementary
PPA dated 10.09.2010. [Para 26]
1.5 Thus, the Commission was fully justified in ignoring the
supplementary PPA dated 10.09.2010 and asserting that it could not
enforce it – However, the APTEL overlooked this crucial aspect and
held that, insofar as the additional 1.90 MW plant was concerned,
the supplementary PPA dated 10.09.2010 can be given effect to,
by applying to it the tariff of 2.95/- stipulated therein. [Para 27]
1.6 The observation of the APTEL that no adverse inference could
be drawn against the appellant for not obtaining the approval of
the Commission for the tariff agreed to by the parties under this
supplementary PPA 10.09.2010 overlooked the binding mandate
of s.86(1)(b). [Para 27]
1.7 Appellant was granted relief by the APTEL, ignoring the mandate
of s.86(1)(b) but the HPSEB allowed the same to attain finality
2352 [2025] 8 S.C.R.
Supreme Court Reports
by not filing an appeal – No interference at this late stage – Plea
of the appellant that it should be extended the enhanced tariff
of ₹2.95/- per kWh for the entire project, including the 3 MW
plant covered by the PPA dated 30.03.2000, is bereft of merit.
[Paras 26, 27, 31]
List of Acts
Himachal Pradesh Electricity Regulatory Commission (Power
Procurement from Renewable Sources and Cogeneration by
Distribution Licensee) Regulations, 2007; Electricity Act, 2003;
Electricity Regulatory Commissions Act, 1998.
List of Keywords
Section 86(1)(b) of the Electricity Act, 2003; Fixing of price for
purchase of electricity not a matter of private negotiation; Private
negotiation; Enhancement of tariff in PPA; Review and approval of
Electricity Regulatory Commission under Section 86(1) (b) under
Section 86(1)(b) of the Electricity Act, 2003; Generating company;
Distribution licensee; Payment of arrears at an enhanced tariff;
Tariff; Power Purchase Agreement (PPA); Supplementary PPA;
Baragran Hydro Electric Power Project; 3 MW hydel power plant;
Himachal Pradesh State Electricity Board Limited (HPSEB);
Redetermination of tariff; Enhanced capacity; Private agreement;
Royalty for water usage.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3005 of 2015
From the Judgment and Order dated 17.10.2014 of the Appellate
Tribunal for Electricity at New Delhi in AN No. 198 of 2013
Appearances for Parties
Advs. for the Appellant:
M.G. Ramachandran, Sr. Adv., Raj Kumar Mehta, Ms. Himanshi
Andley, Ms. Srishti Khindaria.
Advs. for the Respondents:
Pradeep Misra, Daleep Dhyani, Suraj Singh, Anand K. Ganesan,
Nikunj Dayal, Amal Nair, Ms. Shivani Verma, Pramod Dayal.
[2025] 8 S.C.R. 2353
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
Judgment / Order of the Supreme Court
Judgment
Sanjay Kumar, J.
1. By way of this appeal filed under Section 125 of the Electricity Act,
20031, M/s. KKK Hydro Power Limited, Faridabad, Haryana, calls
in question the judgment dated 17.10.2014 passed by the Appellate
Tribunal for Electricity, New Delhi2, in Appeal No. 198 of 2013. In turn,
Appeal No. 198 of 2013 was also filed by M/s. KKK Hydro Power
Limited, the appellant herein, against the order dated 05.07.2013 of
the Himachal Pradesh Electricity Regulatory Commission3, rejecting
its petition for payment of arrears at an enhanced tariff for the
electricity supplied by it to the Himachal Pradesh State Electricity
Board Limited4.
2. IA No. 4 of 2016 filed by the Commission seeking to be impleaded
as a party respondent in this appeal is allowed and the Commission
is brought on record as respondent No. 4.
3. By the impugned judgment dated 17.10.2014, the APTEL allowed the
appellant’s appeal in part and held that the tariff for its 3 MW hydel
power plant under the Power Purchase Agreement5 dated 30.03.2000
required no redetermination but the tariff for its additional 1.90 MW
hydel power plant, commissioned on 10.07.2008, required to be
redetermined as per the Himachal Pradesh Electricity Regulatory
Commission (Power Procurement from Renewable Sources and
Cogeneration by Distribution Licensee) Regulations, 20076. The
APTEL further directed that, as the entire capacity of the appellant’s
power project was to be injected and evacuated from the same bus
bars, a common tariff had to be determined for the power project
as a whole and held that the common tariff would be the weighted
average of the respective tariffs for the 3 MW and 1.90 MW plants.
1 for short, ‘the Act of 2003’
2 for short, ‘the APTEL’
3 for short, ‘the Commission’
4 for short, ‘the HPSEB’
5 for short, ‘the PPA’
6 for short, ‘the Regulations of 2007’
2354 [2025] 8 S.C.R.
Supreme Court Reports
The appellant was held entitled to arrears on account of the difference
in tariff for the period for which payment had already been made
as per the existing tariff. The Commission’s order dated 05.07.2013
was set aside to that extent and the Commission was directed to
pass a consequential order within a timeframe.
4. Pursuant to the above direction, the Commission determined the
tariff as per the weighted average and quantified it at ₹2.60/- per
Kilowatt hour (kWh), vide order dated 11.06.2015. In accordance
therewith, the appellant and the HPSEB filed a joint petition, bearing
No. 106 of 2015, seeking approval of the supplementary PPA dated
03.11.2015 entered into by and between them, stipulating the new
tariff as per the weighted average. Reference was made therein
to the orders of the Commission and the APTEL dated 11.06.2015
and 17.10.2014 respectively and the tariff of ₹2.60/- per kWh was
incorporated for the entire project of 4.90 MW capacity with effect
from 14.07.2008. Be that as it may.
5. The factual narrative needs recounting from scratch to properly
gauge the issues raised in this appeal. The Government of Himachal
Pradesh7 and the appellant executed Implementation Agreement8
dated 30.03.2000, whereby the appellant was to establish Baragran
Hydro Electric Power Project of 3 MW capacity on Sanjoin Nallah,
a tributary of River Beas, in District Kullu. Pursuant to this IA, the
appellant and the GoHP executed a PPA on the same day, i.e.,
30.03.2000. Clause 6.2 of the said PPA, titled ‘Tariff for Net Saleable
Energy’, fixed the price to be paid by the HPSEB to the appellant
at a fixed rate of ₹2.50/- per kWh. It was stated therein that ‘this
rate is firm and fixed and shall not be changed due to any reason
whatsoever’. The PPA was to be in force for a period of 40 years
from the synchronization date of the first unit of the project.
6. It was only thereafter, i.e., on 30.12.2000, that the Commission came
to be constituted under the Electricity Regulatory Commissions Act,
1998. The 3 MW hydel power project was commissioned by the
appellant on 05.08.2004. While so, on 05.02.2005, the appellant
sought the approval of the GoHP to augment the capacity of its power
project by increasing it to 4.90 MW. Accepting its request, the GoHP
7 for short, ‘the GoHP’
8 for short, ‘the IA’
[2025] 8 S.C.R. 2355
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
forwarded a draft IA to the appellant under letter dated 06.09.2006,
wherein it proposed that royalty for water usage, in the shape of free
power to be given to GoHP, would continue as per the IA for the
existing 3 MW plant, but it would be waived for the upgraded 1.90
MW plant for 12 years, reckoned from the Commercial Operation Date
of the third turbine, and beyond the period of 12 years, the royalty
would be 12% for the next 18 years and beyond that, 18%. This
proposal was in modification of clause 13.1 of the earlier IA dated
30.03.2000, which stated that royalty for water usage, in the shape
of free power @ 10% of deliverable energy, would be leviable but it
would be waived for 15 years from the Commercial Operation Date.
7. A supplementary IA was then executed by the GoHP and the appellant
on 05.07.2007, wherein both parties agreed that the project for the
revised capacity of 4.90 MW should be implemented, subject to
the terms and conditions mentioned therein. Clauses 13 and 13.1
of this supplementary IA dealt with the GoHP’s rights on water and
stated that royalty for water usage, in the shape of free power,
from the appellant’s 4.90 MW power project would be waived for
12 years, reckoned after 30 months from the date of signing of the
supplementary IA and beyond the period of 12 years, the royalty
would be @ 12% for the next 18 years and beyond that, @ 18%.
This was in alteration of the earlier understanding.
8. Thereafter, on 04.12.2007, on the joint petition of the HPSEB and
the appellant, the Commission conditionally approved the draft PPA
submitted by them in accordance with the supplementary IA dated
05.07.2007 for the revised capacity of 4.90 MW. The relevant portion
of the order reads as follows:
‘The Commission under sub-section (1)(b) of Section 86
of Electricity Act, 2003 grants consent to the said PPA,
subject to the following observations: -
i) The Model PPA approved by the Commission
vide its order dated 24th March, 2003 provides
for Government Guarantee and the same can
only be omitted from the PPA with the approval
of the Commission for which purpose the parties
need to file a joint application within one month
of the date of issue of this order.
2356 [2025] 8 S.C.R.
Supreme Court Reports
ii) The approved model PPA provides that the
Company shall provide to the Board, free of
cost, 10% of the energy generated by the
project as measured at the interconnection point
commencing from the date falling 15 years from
the date on which the Company synchronizes
the first unit of the project. The stipulation made
in this regard in the PPA submitted for approval
is however on the basis of “Hydro Power Policy
2006” notified subsequently by the GoHP in
December, 2006. The deviation can only be
allowed after the parties file a joint application
for necessary approval in this regard with the
Commission.
iii) Construction Schedule attached to the
Implementation Agreement PPA needs to be
got approved as Appendix-B from the competent
authority as per the standard Implementation
Agreement and attached as such with the PPA.
iv) Page 2 of the Implementation Agreement is
missing.
v) Tariff and other terms and conditions of the PPA
shall be subject to the provisions of the Himachal
Pradesh Electricity Regulatory Commission
(Power Procurement from Renewable Sources
and Cogeneration by Distribution Licensee)
Regulations, 2007.’
(emphasis is ours)
9. Pursuant to the conditional approval granted by the Commission,
vide order dated 04.12.2007, the appellant and HPSEB executed
PPA dated 11.03.2008. ‘Project’ was defined therein under clause
2.2.56 to mean Baragran Hydro Electric Project of 4.90 MW (revised)
capacity. Clause 6.2 dealt with the ‘Tariff for the Net Saleable
Energy’ and stated that the HPSEB would pay for the net saleable
energy delivered to it by the appellant at a fixed rate of ₹2.50/- per
kWh. It was further stated that ‘this rate is firm and fixed without
indexation and escalation and shall not be changed due to any
[2025] 8 S.C.R. 2357
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
reason whatsoever’. However, another clause was added thereunder
which reads as follows:
‘Further, the tariff as per clause 6.2 above and other terms
& conditions of the PPA shall be subject to the provisions of
the Himachal Pradesh Electricity Regulatory Commission
(Power Procurement from Renewable Sources and
Cogeneration by Distribution Licensee) Regulations,
2007 and when such regulations are framed as per the
HPERC order dated 04.12.2007 incase no. 241/2007
(Annexure-IV).’
10. Pursuant to the Regulations of 2007, the Commission issued the
Tariff Order for ‘Small Hydel Power Projects not exceeding 5 MW’ on
18.12.2007. Clause 5.35 thereof stated that it would be applicable to
all PPAs (not exceeding 5 MW) already approved by the Commission,
with a specific clause that the tariff and other terms and conditions
of the PPA shall be subject to the provisions of the Regulations of
2007, and also to the PPAs to be approved by the Commission
thereafter. The tariff fixed by the Commission under this Tariff Order
is ₹2.87/- per kWh.
11. Thereafter, the APTEL adjudicated two appeals filed against this
tariff of ₹2.87/- per kWh for small hydel power projects of upto 5
MW and, by order dated 18.09.2009, the APTEL remanded the
matter to the Commission to redetermine the tariff for such projects.
Pursuant thereto, the Commission issued orders dated 09/10.02.2010,
enhancing the tariff to ₹2.95/- per kWh.
12. On the strength of the Commission’s orders dated 09/10.02.2010,
the appellant approached the HPSEB on 01.04.2010 to execute a
supplementary PPA with the enhanced tariff of ₹2.95/- per kWh.
Aggrieved by the lack of response, the appellant filed Petition No. 94
of 2010 before the Commission seeking a direction to the HPSEB to
act upon its plea and execute a supplementary PPA, incorporating
the tariff of ₹2.95/- per kWh. However, supplementary PPA dated
10.09.2010 came to be executed by the appellant and the HPSEB,
without the intervention of the Commission, modifying the tariff from
₹2.50/- per kWh to ₹2.95/- per kWh. Pertinent to note, a caveat
was added therein by the HPSEB that such enhancement would be
without prejudice to its rights as available under law.
2358 [2025] 8 S.C.R.
Supreme Court Reports
13. Pursuant to this supplementary PPA, the HPSEB started paying the
appellant the higher tariff of ₹2.95/- per kWh. As arrears of payment
at this enhanced tariff from April, 2008 to August, 2010 were not
made and payments for that period had only been made at the
initial tariff of ₹2.50/- per kWh, the appellant filed Petition No. 6
of 2011 before the Commission. Its prayer therein was to direct
the HPSEB to pay the arrears of ₹2,77,50,960/- for the period in
question. During the pendency of this petition, the HPSEB cleared
the bill for the aforestated amount and stated that the same would be
released in 5 installments of ₹55,50,192/- each. The first installment
of ₹55,50,192/- was released by the HPSEB on 26.02.2011. According
to the appellant, the only issue that survived thereafter in Petition
No. 6 of 2011 was as to the interest payable on the arrears from
11.03.2008 to 10.09.2010. While so, the HPSEB filed Petition No.
118 of 2012 before the Commission, seeking recall/modification/
clarification of its earlier conditional approval order dated 04.12.2007.
14. By common order dated 05.07.2013, the Commission dismissed
Petition No. 6 of 2011 filed by the appellant for payment of arrears
and also dismissed Petition No. 118 of 2012 filed by the HPSEB.
Perusal of the order reflects that the following issues were framed
for consideration:
1. Whether the Commission has the power to look into the
agreement entered into or concluded prior to its existence?
2. Whether the observation No. (v) of the Commission’s
consent letter on PPA is relevant in the present case and
if it is relevant what is the import of the regulations and the
orders issued thereunder on tariff and other conditions?
3. Whether the provisions in the Model PPA have the binding
force?
4. Whether the parties to the PPA have the power to amend/
modify the PPA and if so does it require Commission’s
approval?
5. Whether the parties have executed the PPA, including
the Supplementary PPA, in conformity with the approval
accorded by the Commission?
6. Whether the petitioner is entitled to seek directions as
prayed for in the petition?
[2025] 8 S.C.R. 2359
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
15. As regards Issue No. 1, the Commission held that PPAs executed/
concluded prior to its existence had to be complied with in accordance
with the stipulations made therein and it lacked the power to look into
such PPAs. It held that neither the Act of 2003 nor the Regulations of
2007 framed thereunder provided for such interference. As regards
Issue No. 2, the Commission held that there was no need to recall
or modify the consent order dated 04.12.2007, the subject matter
of the petition filed by the HPSEB. The Commission noted that the
order dated 04.12.2007 made it clear that the consent conveyed
thereunder for the PPA was subject to certain observations and it
was for the parties to finalize and execute the PPA accordingly. As
per the Commission, instead of proceeding on the basis of mere
assumptions and presumptions, the parties ought to have worked out
the terms and conditions of their PPA after due consideration of the
Regulations of 2007, subject to which it had accorded its approval
on 04.12.2007. The Commission observed that the confusion had
arisen from the wrongful interpretation of the said observations by
the parties and held that the supplementary PPA dated 10.09.2010
was not in conformity with the provisions of the Regulations of 2007,
subject to which it had accorded its approval.
16. With regard to Issue No. 3, the Commission opined that the model
PPA was generic in nature and its amendment would normally
have prospective applicability. It was further observed that if the
same impacted concluded PPAs, the parties would have to adopt
the model PPA with the approval of the Commission on a case-to-
case basis. As regards Issue No. 4, the Commission opined that a
statutory duty is cast on the regulated entities to align their existing
and future contracts with the Regulations of 2007 and the PPA could
be amended/modified only with the consent of both the parties and,
further, whenever such modification involved a change in tariff, such
amendment and modification could be made only with the approval
of the Commission.
17. On Issue No. 5, the Commission observed that neither the Regulations
of 2007 nor the Tariff Order dated 18.12.2007 issued thereunder
contained any express provision to regulate tariff in relation to
enhanced capacities of existing projects. The Commission pointed
out that its order dated 04.12.2007 made it clear that it had conveyed
its consent for the PPA subject to certain observations and it was
for the parties to finalize and execute the PPA accordingly. As the
2360 [2025] 8 S.C.R.
Supreme Court Reports
parties had neither worked out the terms and conditions of their PPA
in conformity with the consent given by it nor did they move a petition
for review of their tariff, they had no power to do so unilaterally.
On the last issue, viz., Issue No.6, with regard to the prayer of the
appellant, the Commission noted that the appellant’s 3 MW project
had been commissioned in the year 2004 at the tariff of ₹2.50/- per
kWh and even thereafter, energy generated from the revised capacity
was also paid for under the PPA dated 11.03.2008 at the same rate.
The Commission noted that the appellant could not take advantage
of its own non-fulfilment of the conditions precedent to the execution
of the supplementary PPA dated 10.09.2010, resulting in additional
revenue of more than ₹1 crore per annum under a PPA, which
was neither firm nor conclusive as it was subject to the HPSEB’s
rights under law. The Commission, therefore, held that it could not
enforce the supplementary PPA. The Commission dismissed both
the petitions accordingly. In effect, the Commission held that the
appellant was entitled to payment @ ₹2.50/- per kWh for the entire
4.90 MW project. Aggrieved by the Commission’s order, the appellant
approached the APTEL, resulting in the passing of the impugned
order dated 17.10.2014.
18. Perusal of the impugned order dated 17.10.2014 indicates that, after
noting the findings of the Commission, the APTEL observed that the IA
dated 30.03.2000 and the supplementary IA dated 05.07.2007 along
with the PPA dated 30.03.2000 and the PPA dated 11.03.2008 dealt
with one single project and there was only a capacity revision, which
came about due to augmentation from 3 MW to 4.90 MW. The APTEL
noted that the consequential PPA, on account of capacity revision, was
signed after the Regulations of 2007 came into force. It also noted
that, as per the proviso to Regulation 6 in the Regulations of 2007,
there was no power to review the PPAs signed prior to existence of
the Commission. As the energy generated from the original 3 MW
plant did not fall within the purview of the Commission’s regulation,
per the APTEL, the only issue was to see how the incremental energy
needed to be regulated for purchase. The APTEL, therefore, found
no mistake on the part of the Commission in including observation
No. (v) in its approval order dated 04.12.2007, which made it clear
that the consent of the Commission was conditional and it was for
the parties to finalize and execute their PPA accordingly. The APTEL
noted that both parties did not work out the terms and conditions of
[2025] 8 S.C.R. 2361
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
their PPA in conformity with the consent given by the Commission and
they also failed to move a petition for review of the tariff thereafter.
19. The APTEL, therefore, opined that the appellant could not seek
release of arrears on the basis of the supplementary PPA dated
10.09.2010, which was not in line with the approval accorded by the
Commission. It noted that the supplementary PPA dated 10.09.2010
was not approved by the Commission at all and it did not meet the
test of law. The APTEL observed that, as the PPA dated 30.03.2000
pertaining to the 3 MW plant was prior to the constitution of the
Commission and as the said plant was commissioned on 05.08.2004
itself, i.e., prior to the notification of the Regulations of 2007, the
appellant was not entitled to claim tariff for the said 3 MW plant on
the basis of the enhanced tariff determined by the Commission under
the Regulations of 2007.
20. The APTEL, however, noted that the augmented 1.90 MW capacity
plant was planned after the commissioning of the 3 MW capacity
plant, as an extension. The APTEL also noted that this 1.90 MW
capacity plant was commissioned on 10.07.2008, i.e., after the
Regulations of 2007 and the Tariff Order dated 18.12.2007 came
into effect. Reference was made to observation No. (v) in the
Commission’s order dated 04.12.2007 and it was pointed out that,
as per the proviso to Regulation 6, as amended on 27.11.2007, the
Commission was empowered to modify PPAs by reason of change
in statutory laws/rules or the State policy. Therefore, in so far as the
1.90 MW plant was concerned, the APTEL opined that it would be
subject to the tariff determined under the Regulations of 2007. The
APTEL, accordingly, disagreed with the Commission’s finding that the
1.90 MW plant would also have to be treated on par with the initial
3 MW plant and be bound by the same tariff of ₹2.50/- per kWh.
21. As regards the failure of the appellant to obtain the approval of
the Commission for the supplementary PPA dated 10.09.2010, the
APTEL opined that the said supplementary PPA was signed with
the mutual consent of both parties, modifying the tariff of ₹2.50/-
per kWh to ₹2.95/- per kWh and as the augmented 1.90 MW plant
would be covered by the tariff determined under the Regulations of
2007, it held that the failure to seek approval of the supplementary
PPA, in so far as the said plant was concerned, could not be held
against the appellant. The APTEL further held that, in so far as the
2362 [2025] 8 S.C.R.
Supreme Court Reports
original 3 MW plant was concerned, in relation to which the PPA
was executed on 30.03.2000, even before the establishment of the
Commission, the tariff thereunder could not have been modified by
the parties even by mutual consent, as it was fixed and, therefore,
the appellant could not seek benefit of the enhanced tariff for the
said plant, notwithstanding the supplementary PPA dated 10.09.2010.
The APTEL opined that, merely because the expanded unit was
commissioned after notification of the Regulations of 2007, it did not
give a right to the appellant to claim the higher tariff for the entire
project.
22. The APTEL, accordingly, concluded that the Commission had
correctly exercised its jurisdiction to examine the validity of the
supplementary PPA dated 10.09.2010 entered into by the parties,
purportedly on the basis of the Commission’s order dated 04.12.2007.
The APTEL held that the tariff for the 3 MW plant which was
commissioned on 05.08.2004 under the PPA dated 30.03.2000,
long prior to the notification of the Regulations of 2007, could not
be redetermined thereunder. As regards the 1.90 MW plant, which
was an extension of the 3 MW plant, the APTEL held that the same
would be governed by the tariff determined as per the Regulations
of 2007. Lastly, as the 1.90 MW capacity plant was also available
at the same project site and the entire capacity of the project is
to be injected and evacuated from the same bus bars, the APTEL
directed that a common tariff be determined for the power project
as a whole. Such tariff, as per the APTEL, would be the weighted
average of the respective tariffs envisaged for the 3 MW and 1.9
MW plants. The appellant was held entitled to payment of arrears
on account of the difference in the tariff for the project as per these
directions.
23. Having given thoughtful consideration to the matter, we are of the
opinion that the APTEL misguided itself on certain crucial aspects.
The Commission’s Tariff Order dated 18.12.2007 worked out the
levelized tariff for small hydel projects of upto 5MW at ₹2.87/- per kWh
but in appeal, the APTEL remitted the matter to the Commission for
reconsideration, vide its order dated 18.09.2009. Pursuant thereto,
the Commission passed orders dated 09/10.02.2010 revising the tariff
for such hydel power projects to ₹2.95/- per kWh. In the concluding
paragraph of its order dated 09.10.2010, the Commission observed
as under:
[2025] 8 S.C.R. 2363
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
‘The Commission is aware that after issuance of the
SHP (Small Hydro Power Projects) Order dated Dec., 18,
2007 and till the issuance of this Order, the hydel power
producers and the Board, have executed and signed the
Power Procurement Agreements with the provision of
the tariff of Rs.2.87/Unit for the power producer by the
SHPs in this State. In order to give the benefit of increase
of tariff of Rs.2.95/unit from Rs.2.87/Unit to the hydel
power producers, who have executed the PPAs with the
stipulation of Rs.2.87/Unit, such hydel power producers
and the Board are directed to modify the clauses in PPAs,
in accordance with law.’
24. Significantly, the appellant’s PPA dated 11.03.2008 did not stipulate
the tariff of ₹2.87/- per kWh, but only ₹2.50/- per kWh. Per se, the
aforestated direction in the concluding paragraph of the Commission’s
order dated 09.02.2010 did not apply to the appellant’s supplementary
PPA. However, by its letter dated 01.04.2010 addressed to the
HPSEB, the appellant straightaway sought amendment of its PPA
and requested for execution of a fresh PPA stipulating the higher
tariff of ₹2.95/- per kWh. Aggrieved by the inaction on the part of
the HPSEB, the appellant thereupon approached the Commission
praying for a direction to the HPSEB to modify the PPA dated
11.03.2008 by enhancing the tariff from ₹2.50/- per kWh to ₹2.95/-
per kWh. This petition was, however, rendered infructuous owing
to the HPSEB addressing letter dated 12.07.2010 to the appellant
requesting it to supply the draft of the amendments to be incorporated
in the existing PPA dated 11.03.2008, so that the Commission’s
order dated 09.02.2010 could be implemented. Pursuant thereto,
the supplementary PPA dated 10.09.2010 came to be executed by
the appellant and the HPSEB. Therein, it was observed as under:
‘The rate of Rs.2.50 per kilowatt hour appearing under
clause 6.2, 6.4 & 16.5 in the PPA referred to above shall be
taken as tariff at Rs.2.95 per kilowatt hour, as per HPERC
Order dated 09.02.2010. This is without prejudice to the
rights of second part as available under law.’
25. Pertinently, after the conditional approval of the initial draft PPA by
the Commission, vide its order dated 04.12.2007, resulting in the
PPA dated 11.03.2008, the subsequent supplementary PPA dated
2364 [2025] 8 S.C.R.
Supreme Court Reports
10.09.2010 was never placed before the Commission for its approval.
The earlier PPA dated 11.03.2008 can be sustained as it was based
on the approval of the draft PPA by the Commission on 04.12.2007
but insofar as the supplementary PPA dated 10.09.2010 is concerned,
no draft PPA was ever submitted to the Commission for its approval
and it appears that the supplementary PPA dated 10.09.2010 was
executed independently and unilaterally by the parties themselves,
incorporating a tariff which was never subjected to the review and
approval of the Commission. In this context, Section 86(1)(b) of the
Act of 2003 assumes great significance. It reads as under:
‘86. Functions of State Commission. – (1) The State
Commission shall discharge the following functions,
namely: -
(a). …..
(b). regulate electricity purchase and procurement process
of distribution licensees including the price at which
electricity shall be procured from the generating companies
or licensees or from other sources through agreements
for purchase of power for distribution and supply within
the State;
(c). ……. .’
26. This provision puts it beyond the pale of doubt that fixing of the price
for the purchase of electricity is not a matter of private negotiation and
agreement between a generating company and a distribution licensee.
The price as well as the agreement, i.e., PPA, incorporating such price
and providing for purchase of electricity at that price necessarily have
to be reviewed and approved by the State Commission under this
provision. The order dated 09.02.2010 passed by the Commission,
without reference to the appellant’s case, required only those existing
PPAs which stipulated the tariff of ₹2.87/- per kWh to be amended so
as to give effect to the enhancement of tariff from ₹2.87/- per kWh to
₹2.95/- per kWh. This order had no application at all to the case of
the appellant as its PPA dated 11.03.2008 did not stipulate the tariff
of ₹2.87/- per kWh. In this scenario, the appellant and the HPSEB
were bound to approach the Commission to secure its approval
before they could effect any enhancement of the tariff stipulated in
the PPA dated 11.03.2008. Without doing so, the appellant and the
[2025] 8 S.C.R. 2365
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
HPSEB, on their own and without the Commission’s review and
approval, enhanced the tariff from ₹2.50/- per kWh to ₹2.95/- per
kWh under their supplementary PPA dated 10.09.2010!
27. Viewed thus, the Commission was fully justified in ignoring the
supplementary PPA dated 10.09.2010 and asserting that it could not
enforce it. However, the APTEL overlooked this crucial aspect and
held that, insofar as the additional 1.90 MW plant was concerned,
the supplementary PPA dated 10.09.2010 can be given effect to, by
applying to it the tariff of ₹2.95/- stipulated therein. The observation
of the APTEL that no adverse inference could be drawn against
the appellant for not obtaining the approval of the Commission for
the tariff agreed to by the parties under this supplementary PPA
10.09.2010 completely overlooked the binding mandate of Section
86(1)(b) of the Act of 2003.
28. However, as the HPSEB did not choose to file an appeal against
the APTEL’s order and mutely accepted the direction therein to go
before the Commission for computation of the weighted average
so as to quantify the tariff for the entire 4.90 MW power project of
the appellant, we choose not to interfere with the same at this late
stage. It may be noted that the revised tariff of ₹2.60/- per kWh, on
the basis of the weighted average computed by the Commission,
stipulated in the supplementary PPA dated 03.11.2015 has been acted
upon for a long time now and we would not wish to upset the apple
cart and start the process all over again. More so, as the HPSEB
did not even choose to file an appeal against the impugned order.
We, however, hasten to clarify the legal position so as to obviate a
similar error being committed in future.
29. Though, the appellant would seek to draw parity with power projects
which entered into PPAs after establishment of the Commission, the
very fact that its PPA was dated 30.03.2000 distinguishes it from
such cases, and there can be no possibility of drawing parity as
sought by it.
30. As regards the issue of royalty on water usage, the change in
the GoHP’s policy in that regard since the PPA dated 30.03.2000
undoubtedly had an adverse impact on the appellant. We may,
however, note that Regulation 6 of the Regulations of 2007, which
dealt with determination of tariff for electricity from renewable sources,
came to be amended by the Commission, vide Notification dated
2366 [2025] 8 S.C.R.
Supreme Court Reports
12.11.2007. The amendment of Regulation 6, to the extent relevant,
reads as under:
‘3. Amendment of regulation 6. – In sub-regulation (1)
of regulation 6 of the said regulations, -
a) …….;
b) …….; and
c) for the second proviso, the following proviso shall be
substituted, namely: -
“Provided further that, -
(i) where the power purchase agreement,
approved prior to the commencement of these
regulations, is not subject to the provisions
of the Commission’s regulations on power
procurement from renewable sources; or
(ii) where, after the approval of the power purchase
agreements, there is change in the statutory
laws, or rules, or the State Govt. Policy;
(iii) the Commission, in order to promote co-
generation or generation of electricity from
renewable sources of energy, may, after
recording reasons, by an order, review or modify
such a power purchase agreement or a class
of such power purchase agreements.’
It would, therefore, be open to the appellant to approach the
Commission for appropriate relief under the amended proviso to
Regulation 6 of the Regulations of 2007. We leave it at that.
31. On the above analysis, we hold that the appellant was granted relief
by the APTEL, ignoring the mandate of Section 86(1)(b) of the Act
of 2003, but the HPSEB allowed the same to attain finality by not
filing an appeal. We, therefore, stay our hand and do not interfere
with the same at this late stage. We, however, clarify and affirm that
a generating company and a distribution licensee cannot, by private
agreement, execute a PPA on their own or stipulate tariff therein as
per their choice, for supply of electricity within a State, without seeking
the review and approval of the Electricity Regulatory Commission
under Section 86(1)(b) of the Act of 2003.
[2025] 8 S.C.R. 2367
M/s KKK Hydro Power Limited v.
Himachal Pradesh State Electricity Board Limited and Others
32. In summation, the plea of the appellant that it should be extended the
enhanced tariff of ₹2.95/- per kWh for the entire project, including the
3 MW plant covered by the PPA dated 30.03.2000, is bereft of merit.
33. The appeal is accordingly dismissed.
I.A. No. 4 of 2016 is allowed.
Registry to carry out necessary amendment in the cause title.
Other pending applications, if any, shall stand dismissed.
Result of the case: Appeal dismissed.
†
Headnotes prepared by: Divya Pandey
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.