Created byFuzzy Cloud

Supreme Court of India

MMTC LIMITEDversusANGLO AMERICAN METALLURGICAL COAL PVT. LIMITED

Citation
2025 INSC 1279
Decided
3 November 2025
Disposal
Dismissed

Holding

The Supreme Court held that the Section 47 objections were not maintainable as there were no prima facie grounds of fraud or breach of fiduciary duty, and the narrow jurisdiction of Section 47 precludes a re‑trial of the award.

Summary

MMTC Limited entered a Long Term Agreement with Anglo American Metallurgical Coal for the supply of coking coal, but a dispute arose over the price and unlifted quantities, leading to an arbitral award in favour of Anglo. MMTC challenged the award under Section 34 of the Arbitration and Conciliation Act, which was rejected, and later succeeded on appeal under Section 37, only for the Supreme Court to restore the award. While the award was being enforced, MMTC filed objections under Section 47 of the CPC claiming fraud and breach of fiduciary duty by its senior officials, and also sought a stay of execution under Order XXI Rule 29. The Delhi High Court dismissed both the Section 47 objections and the stay application. The Supreme Court examined whether the objections were maintainable and whether a prima facie case of fiduciary breach existed, applying the business judgment rule and the narrow scope of Section 47. Finding no substantive evidence of fraud or unreasonable conduct, the Court held the objections untenable and dismissed the appeal.

Issues considered

  • Whether the High Court was justified in dismissing MMTC's objections under Section 47 of the CPC.
  • Whether a prima facie case of breach of fiduciary duty and fraud by MMTC officials was established.
  • Whether Section 47 can be used to challenge the executability of an arbitral award after it has been upheld by the Supreme Court.
  • Whether the application under Order XXI Rule 29 for a stay of execution was maintainable.

Legislation cited

Headnote

Issue for Consideration Issue arose whether the High Court was justified in not entertaining the objections filed by the appellant u/s.47 CPC and in dismissing the same; and whether at least prima facie the case of breach of fiduciary duty has been established Act, 1996 – ss.34, 37 – Code of Civil Procedure, 1908 – s.47 – Objections under – Maintainability – Long Term Agreement-LTA between the petitioner and the respondent – Respondent invoked arbitration clause claiming damages on account of the

Subjects

Prima facie case of breach of fiduciary dutyObjections u/s.47 CPCLong Term AgreementArbitration clauseDamagesUnlifted quantity of coal contractedArbitration awardReview PetitionInterestClarification applicationExecution petitionEnforcement of awardOrd. XXI r.29 CPC applicationStay of executionBusiness judgment rulePostscriptPolicy paralysis

Judgment

                [2025] 11 S.C.R. 327 : 2025 INSC 1279

                          MMTC Limited
                                v.
           Anglo American Metallurgical Coal Pvt. Limited
                      (Civil Appeal No. 13321 of 2025)
                              03 November 2025
             [Sanjay Kumar and K.V. Viswanathan,* JJ.]


                           Issue for Consideration
       Issue arose whether the High Court was justified in not entertaining
       the objections filed by the appellant u/s.47 CPC and in dismissing
       the same; and whether at least prima facie the case of breach of
       fiduciary duty has been established by appellant.

                                  Headnotes†
       Arbitration and Conciliation Act, 1996 – ss.34, 37 – Code of Civil
       Procedure, 1908 – s.47 – Objections under – Maintainability –
       Long Term Agreement-LTA between the petitioner and the
       respondent – Respondent invoked arbitration clause claiming
       damages on account of the unlifted quantity of coal contracted
       by the appellant – Arbitration award passed in favour of
       the respondent – Challenge u/s.34 of the 1996 Act rejected
       by the Single Judge, however, the Division Bench allowed
       appellant’s appeal u/s.37 and set aside the arbitral award – In
       appeal before this Court, the judgment of the Division Bench
       set aside and that of the Single Judge restored as also the
       arbitral award – Review Petition filed by the appellant, admitted
       on the limited issue of interest – Subsequently, clarification
       application by the appellant disposed of – In the meantime,
       the respondent filed execution petition seeking enforcement
       of award and the appellant filed its objections u/s.47 CPC –
       When the Judgment was reserved, the appellant filed a suit
       praying that the award is void and unenforceable, however, the
       said suit was dismissed and the Executing Court dismissed
       the objections u/s.47 CPC as well as Ord. XXI r.29 application,
       seeking stay of execution, pending the suit – Challenge to:
       Held: Objection petition u/s.47 should not invariably be treated
       as a commencement of a new trial – This Court has warned that


* Author
328                                                                [2025] 11 S.C.R.

                             Supreme Court Reports


       there is a steady rise of proceedings akin to a retrial which causes
       failure of realization of the fruits of a decree, unless prima facie
       grounds are made out entertaining objections u/s.47 would be
       an abuse of process – On the material furnished, it cannot be
       said that the Senior Managerial personnel involved at the helm in
       appellant company during the relevant period acted in a manner
       as no reasonable personnel/director in the circumstances would
       have acted – It cannot be concluded that the decisions taken were
       not within the range of reasonableness or that the course adopted
       by them was not one, a reasonably competent personnel/director
       would adopt – Applying the business judgment rule, the course
       adopted by them cannot be said to be one to which a court of
       law would not defer to – Appellants have not been able to even
       prima facie demonstrate that circumstances exist to conclude that
       the personnel of appellant did not act in the best interest of the
       company – Appeal challenges, in the prayer clause, the judgment
       dismissing the objections, though in the prayer clause, no challenge
       to dismissal of the application u/Ord. XXI r.29 filed, in the civil appeal
       the appellants have indicated that they are aggrieved by the said
       order also – Ord. XXI r. 29 provides for stay of execution pending
       suit between decree holder and judgment debtor – However, the
       suit filed itself now stands rejected u/Ord. VII r.11 but a regular first
       appeal was filed – Hence, an occasion for considering an Ord. XXI
       r.29 application does not arise – Objection filed u/s.47 claiming
       that the award as upheld by this Court is inexecutable, is dealt
       with – Jurisdiction lies in a narrow compass – It is the mandate of
       this Court that the object of s.47 is to prevent unwarranted litigation
       and dispose of all objections as expeditiously as possible – No
       merit in the objections filed by the appellant – No good grounds
       to entertain the same. [Paras 95-98, 100]

       Arbitration – Arbitration award – Execution Petition seeking
       enforcement of the Award by the respondent – Appellant-MMTC
       filing its objections u/s.47 CPC and when the Judgment was
       reserved, MMTC filed a suit praying that the award is void
       and unenforceable – However, the said suit was dismissed
       and MMTC filed application u/Ord. XXI r.29 CPC – Executing
       Court dismissed the objections as well as Order XXI Rule 29
       application – Postscript in relation thereto:
       Held: Whether in Government, Public Sector Corporations or even
       in the private sector, the driving force of the entity are the persons
[2025] 11 S.C.R.                                                             329

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     who administer them – Certain play in the joints is inevitable for
     their day-to-day functioning – If they are shackled with the fear
     that, their decisions taken for the day-to-day administration, could
     years later with the benefit of hindsight, be viewed with a jaundiced
     eye, it will create a chilling effect on them – Tendency to play it
     safe will set in – Decision making will be avoided – Policy paralysis
     will descend – All this will in the long run prove detrimental not
     just to that entity but to the nation itself – This Court is not to be
     understood to be condoning decisions taken for improper purposes
     or extraneous considerations – Great caution and circumspection
     have to be exercised before such allegations are brought forward
     and adequate proof must exist to back them – Otherwise for fear
     that carefully built reputations could be casually tarnished, best
     of talent will not be forthcoming, especially for government and
     public sector corporations. [Para 99]

                              Case Law Cited
     Electrosteel Steel Limited (Now M/s ESL Steel Limited) v. ISPAT
     Carrier Private Limited, 2025 INSC 525; Vasudev Dhanjibhai
     Modi v. Rajabhai Abdul Rehman [1971] 1 SCR 66 : (1970) 1
     SCC 670; Ram Preeti Yadav v. U.P. Board of High School and
     Intermediate Education and Ors. [2003] Supp. 3 SCR 352 :
     (2003) 8 SCC 311; S.P. Chengalvaraya Naidu v. Jagannath and
     Ors. [1993] Supp. 3 SCR 422 : (1994) 1 SCC 1; Indian Bank v.
     Satyam Fibres (India) Pvt. Ltd. [1996] Supp. 4 SCR 464 : (1996)
     5 SCC 550; United India Insurance Co. Ltd. v. Rajendra Singh and
     Others [2000] 2 SCR 264 : (2000) 3 SCC 581; Rahul S. Shah v.
     Jinendra Kumar Gandhi and Ors. [2021] 4 SCR 279 : (2021) 6
     SCC 418 – referred to.
     Lazarus Estates Ltd. v. Beasley, (1956) 1 All ER 341; Re Living
     Images Ltd., (1996) 1 BCLC 348; Dovey and The Metropolitan
     Bank (of England and Wales) Limited v. John Cory, 1901 Appeal
     Cases 477; Sharp and Ors. v. Blank and Ors., (2019) EWHC 3096
     (Ch); Maple Leaf Foods Inc. v. Schneider Corp., 42 OR (3d) 177;
     Kerr v. Danier Leather Inc., (2007) 3 SCR 331 Canadian Supreme
     Court Reports – referred to.

                                 List of Acts
     Penal Code, 1860; Prevention of Corruption Act, 1988; Code of
     Civil Procedure, 1908; Arbitration and Conciliation Act, 1996.
330                                                             [2025] 11 S.C.R.

                            Supreme Court Reports


                                List of Keywords
       Prima facie case of breach of fiduciary duty; Objections u/s.47
       CPC; Long Term Agreement; Arbitration clause; Damages; Unlifted
       quantity of coal contracted; Arbitration award; Review Petition;
       Interest; Clarification application; Execution petition; Enforcement of
       award; Ord. XXI r.29 CPC application; Stay of execution; Business
       judgment rule; Postscript; Policy paralysis.

                               Case Arising From
       CIVIL APPELLATE JURISDICTION: Civil Appeal No. 13321
       of 2025
       From the Judgment and Order dated 09.05.2025 of the High Court
       of Delhi at New Delhi in OMP (ENF.) (COMM.) No. 19 of 2018

                            Appearances for Parties
       Advs. for the Appellant:
       Venkataraman, A.S.G., Harish Salve, Sanat Kumar, Sr. Advs. Akhil
       Sachar, Ms. Astha Tyagi, Ms. Sunanda Tulsyan, Ms. Karishma
       Sharma.
       Advs. for the Respondent:
       Neeraj Kishan Kaul, Jayant Mehta, Sr. Advs., Sumeet Kachwaha,
       Samar Singh Kachwaha, Ms. Ankit Khushu, Ms. Garima Bajaj,
       Ms. Akanksha Mohan, Pratyush Khanna, Ms. Ira Mahajan.

                  Judgment / Order of the Supreme Court

                                    Judgment

       K.V. Viswanathan, J.

1.     Leave granted.
2.     The present appeal calls in question the correctness of the judgment
       dated 09.05.2025 passed by a learned Single Judge of the Delhi
       High Court in OMP (ENF.) (COMM.) No. 19 of 2018. By the said
       judgment, the High Court dismissed the objections filed by the
       appellant-MMTC Limited [for short “MMTC”] under Section 47 of
       the Code of Civil Procedure, 1908 [“CPC”] as well as an application
       under Order XXI Rule 29 of CPC seeking stay of the enforcement
[2025] 11 S.C.R.                                                        331

     MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


      proceedings. The High Court further directed that the amount
      deposited by MMTC shall be withdrawn by the decree holder-Anglo
      American Metallurgical Coal Pvt. Limited [for short “the Anglo”]
      along with the interest accrued. Aggrieved, the appellant-MMTC is
      in appeal by way of special leave.

      BRIEF FACTS:-
3.    The respondent-Anglo, on 24.09.2012, invoked the arbitration clause
      in the Long Term Agreement [LTA] dated 07.03.2007 entered into
      between MMTC and Anglo. The claim in the arbitration was for
      damages on account of the unlifted quantity of coal contracted by
      the appellant-MMTC. The damages were computed based on the
      difference in the price between the contracted price of US$ 300 Per
      Metric Tonne [for short “PMT”] and the market price of US$ 126 PMT,
      multiplied by the unlifted quantity. In the arbitration, by an Award
      dated 12.05.2014, Anglo was awarded a sum of US$ 78.720 million
      along with interest and costs by a majority of 2:1.
4.    By a judgment dated 10.07.2015, challenge under Section 34 of the
      Arbitration and Conciliation Act, 1996 [for short ‘the A&C Act’] failed
      before a learned Single Judge of the High Court of Delhi. However,
      the Division Bench, by its judgment dated 02.03.2020, allowed
      MMTC’s appeal under Section 37 of the A&C Act and set aside the
      arbitral Award along with the decision of the learned Single Judge.
      By a judgment of 17.12.2020, this Court allowed the Civil Appeal
      filed by Anglo and after setting aside the judgment of the Division
      Bench restored the judgment of the learned Single Judge and the
      arbitral Award.
5.    On 29.07.2021, a review petition filed by MMTC, which was admitted
      on the limited issue of interest, was disposed of by reducing the
      pendente lite and future interest to 6%. The remaining findings were
      not disturbed. On 19.04.2022, a clarification application filed by
      MMTC was disposed of by clarifying that MMTC would be liable to
      pay interest @ 6% from the date of reference till the date of payment
      and for the period from the date of breach till the date of reference,
      interest was to be paid @ 7.5%.
6.    In the meantime, the respondent filed Execution Petition seeking
      enforcement of the Award. Post the disposal of the clarification
      application, on 20.07.2022, MMTC deposited a sum of Rs.1,087/-
332                                                         [2025] 11 S.C.R.

                          Supreme Court Reports


       crores with the High Court of Delhi at New Delhi. On 28.11.2022,
       E.A. No. 3728 of 2022 in the Execution Petition was filed by MMTC
       seeking to stay the operation and implementation of the Award till
       the Central Bureau of Investigation [CBI] concludes its investigation
       into the matter. It transpires that on 02.09.2022 and 23.11.2022,
       complaints were filed by MMTC against persons including its erstwhile
       employees alleging fraud and collusion with the respondent in relation
       to the price fixed for coal for the 5th Delivery Period. On 09.01.2023,
       the CBI, it transpires registered a preliminary enquiry.
7.     When the matter stood thus, on 10.01.2024, MMTC filed its objections
       under Section 47 of the CPC. In the objections, the primary contentions
       of MMTC were:-
       7.1 Despite having complete knowledge of the recession in the
           market due to the collapse of the Lehman Brothers, the officials
           of MMTC in collusion and conspiracy with the officials of Anglo
           contracted the price of coal for the 5th delivery period at US$ 300
           PMT. This price was 3 times more than the price of US$ 96.40
           PMT which prevailed during the 4th delivery period.
       7.2 Viewed in the background of the fact that Neelachal Ispat Nigam
           Ltd (for short the “NINL”) for whom the coal was sourced did not
           have pressing requirement of the ultimately contracted quantity
           and considering the fact that there was room for negotiation of
           the price, the contention of collusion and conspiracy became
           stark.
       7.3 The fraud could not be discovered earlier since Shri Ved Prakash,
           who was Chief General Manager in 2008, became Director
           (Marketing) in 2010 and ultimately Chairman-cum-Managing
           Director in 2015, remained at the helm of affairs till 29.02.2020.
           The said officer was in control of the arbitral proceedings as
           well as at Section 34 and Section 37 stage.
       7.4 When the Division Bench under Section 37 of the A&C Act
           set aside the Award on 02.03.2020, there was no occasion
           to examine the file to unearth the conspiracy. On 17.12.2020,
           when this Court set aside the judgment of the Division Bench
           and reinstated the Award, the matter was examined and on
           24.02.2021, the then CMD of MMTC issued a confidential note
           requesting the Chief Vigilance Officer to seek permission of the
           Government of India to enquire into the matter.
[2025] 11 S.C.R.                                                          333

     MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


      7.5 It was thereafter that the matter was enquired into, and a decision
          was taken to refer the matter to the CBI and a preliminary enquiry
          came to be registered on 09.01.2023 by the CBI.
8.    A detailed reply was filed by Anglo taking objections on maintainability
      and limitation. Primarily, the reply to the objections on the aspect of
      fraud were set out as under:-
      8.1 Under the LTA entered into on 07.03.2007 between MMTC and
          Anglo, in each of the 5 delivery periods of the contract, Anglo
          was to supply specified quantity of coking coal.
      8.2 After the 3rd delivery period, MMTC had an option to extend the
          Agreement by two years on condition that the option was to be
          exercised latest by 31.01.2007. This was as per Clause 1.3.
          The 3rd delivery period was to expire on 30.06.2007. Clause
          1.3 reads as under: -
                 “1.3 The PURCHASER had the option to extend
                 the duration of the Agreement by two more years,
                 at its sole discretion and the Purchaser to exercise
                 its option for extending the Agreement by two more
                 years or otherwise by 31st January, 2007. In case
                 the PURCHASER decides to exercise such option,
                 at its sole discretion, the Agreement shall have two
                 more Delivery Periods as follows:
                 Fourth Delivery Period: 1st July 2007 to 30th June 2008
                 Fifth Delivery Period: 1st July 2008 to 30th June 2009”
      8.3 The option was indeed exercised before 31.01.2007, on
          30.01.2007, with the execution of the Memorandum of
          Understanding [MoU]. Option once exercised, MMTC was
          obliged to pick up the stipulated quantities at the stipulated
          price during the 4th and 5th delivery periods. The 4th delivery
          period was from 01.07.2007 to 30.06.2008 and the 5th delivery
          period was from 01.07.2008 to 30.06.2009. There could be
          postponement of delivery at the option of the purchaser for a
          period of three months following each delivery period.
      8.4 As per the contract, the price was linked with the price fixed
          for two other Public Sector Undertakings, the Steel Authority
          of India Limited (SAIL) and the Rashtriya Ispat Nigam Limited
334                                                         [2025] 11 S.C.R.

                          Supreme Court Reports


            (RINL). For SAIL and RINL, the prices were negotiated by the
            Government’s Empowered Joint Committee and those contracts
            were long term contracts for purchase up to 2.5 million MT per
            annum as opposed to MMTC’s contracted quantity of 4,66,000
            Metric Tonnes per annum.
       8.5 Addendum No. 2 dated 20.11.2008 to the LTA was only to firm
           up the terms and conditions. Shri Ved Prakash was a junior
           member of the Committee in 2008 and by the time he became
           CMD of MMTC on 14.03.2015 (as mentioned in the objections),
           the Award had been pronounced by the Arbitral Tribunal on
           12.05.2014.
       8.6 The dispute commenced in March 2010 and culminated with
           the judgment of this Court on 17.12.2020 and the allegation of
           fraud is only to escape the liability under the Award.
9.     By 28.10.2024, when the judgment was reserved in the Section 47
       objections, MMTC had filed a Civil Suit praying that the Award
       dated 12.05.2014 is void and unenforceable. It further transpires
       that, on 29.07.2025, the said Civil Suit has been dismissed as not
       maintainable and a Regular First Appeal being RFA (OS) (Comm)
       No. 28 of 2025 is pending before the High Court.
10. On 11.11.2024, MMTC filed an application under Order XXI Rule 29
    CPC. By the impugned judgment, the Executing Court dismissed
    the objections under Section 47 as well as the Order XXI Rule 29
    application seeking stay of execution, pending the suit. Aggrieved,
    MMTC has filed the present Appeal, by way of special leave, and
    this is how the matter presents itself before us.
11. The High Court, by the impugned judgment, though held that the
    objections under Section 47 were not maintainable, made a brief
    observation on merits. It held that on merits that the acts of the Officers
    bind the Corporation as MMTC being a separate legal entity can only
    function through its Officers. Only a preliminary enquiry had been
    registered (when the proceedings were pending in the High Court)
    and, as such, there is no finding of fraud, cheating and collusion
    against the Officers of MMTC with the Officers of the decree-holder.
12. We have heard Mr. N. Venkataraman, learned Additional Solicitor
    General and Mr. Sanat Kumar, learned Senior Advocate, ably
    assisted by Mr. Akhil Sachar, Ms. Astha Tyagi, Ms. Sunanda Tulsyan
[2025] 11 S.C.R.                                                    335

    MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     and Ms. Karishma Sharma, learned counsels for the appellant. We
     have also heard Mr. Neeraj Kishan Kaul and Mr. Jayant Mehta,
     learned Senior Advocates, ably assisted by Mr. Sumeet Kachwaha,
     Mr. Samar Singh Kachwaha, Ms. Ankit Khushu, Ms. Garima Bajaj,
     Ms. Akanksha Mohan, Mr. Pratyush Khanna and Ms. Ira Mahajan,
     learned counsels for the respondent.
13. We have carefully considered the submissions and perused the
    records of the case. Elaborate arguments were heard on 22.05.2025,
    23.05.2025, 24.07.2025, 29.08.2025, 18.09.2025 and 25.09.2025,
    both on maintainability and merits of the Section 47-objections.
14. Before we proceed to consider the contentions, we need to notice
    one additional fact which transpired during the pendency of the
    proceedings. It appears that, on 20.07.2025, MMTC had filed a follow-
    up complaint with the CBI and the CBI, on 21.07.2025, registered an
    FIR. We will deal with the same during the course of the judgment.

     QUESTION FOR CONSIDERATION: -
15. In the above background, the question that arises for consideration
    is – Whether the High Court was justified in not entertaining the
    objections filed by the appellant under Section 47 of CPC and in
    dismissing the same?

     MAINTAINABILITY: -
16. Mr. N. Venkataraman, learned ASG, assailed the impugned judgment
    by first contending that the finding on maintainability is completely
    untenable in view of the judgment of this Court in Civil Appeal No.
    2896 of 2024 [Electrosteel Steel Limited (Now M/s ESL Steel
    Limited) vs. ISPAT Carrier Private Limited1] decided on 21.04.2025.
    According to the learned ASG, this Court has held that the plea of
    nullity qua an Arbitral Award can be raised in a proceeding under
    Section 47 of CPC though the scope was very narrow.
17. Before the High Court, considerable arguments were advanced on
    the question of maintainability of Section 47 objections under the
    CPC, once the award had been challenged and the Section 34
    objection had been dismissed and sustained right up to the highest


1   2025 INSC 525
336                                                         [2025] 11 S.C.R.

                          Supreme Court Reports


       Court. The High Court held that if the objections under Section 47
       are allowed to be entertained during the enforcement proceedings of
       an Award, it would effectively open a second round for challenging
       the Award. According to the High Court, this was not intended by
       the legislature and would defeat the purpose of the A&C Act, apart
       from delaying the finality of disputes.
18. Mr. N. Venkataraman, learned ASG, drew our attention to the judgment
    of this Court in Electrosteel (supra). In Electroteel (supra), certain
    arbitration proceedings between parties therein were commenced
    on 07.06.2017. On 27.06.2017, proceedings commenced under
    Section 7 of the Insolvency and Bankruptcy Code, 2016(IBC) against
    the appellant therein. The arbitration proceedings were kept in
    abeyance, due to the moratorium. The respondent therein filed a
    claim before the resolution professional who partly admitted the claim.
    A resolution plan submitted by the successful resolution applicant
    therein was approved by the Adjudicating Authority on 17.04.2018
    under Section 31 of the IBC. In the plan, ‘nil’ value was provided for
    the operational creditors. The approval of the plan attained finality right
    up to this Court and the challenge made by some other operational
    creditors were not fruitful.
19. The arbitrator, whose proceedings were kept in abeyance, resumed
    proceedings after the lifting of the moratorium and passed an Award on
    06.07.2018 with the appellant therein Electrosteel not even contesting
    the proceedings. An award for a sum of Rs. 1,59,09,214/- along with
    interest was made in terms of Section 16 of the Micro, Small and
    Medium Enterprises Development Act, 2006 (for short ‘MSME Act’).
    No challenge was made under Section 34. Execution came to be
    levied by the respondent therein, when appellant Electrosteel filed
    a petition under Section 47 CPC, contending that the Award was
    a nullity and is not executable. The Executing Court dismissed the
    petition resulting in a challenge under Article 227 before the High
    Court. The High Court dismissed the Article 227-petition primarily
    holding that since arbitral proceedings were initiated prior to the
    insolvency resolution process, the arbitrator was not barred from
    proceeding.
20. Before this Court, apart from arguments on Section 31 of the IBC
    which provided for binding nature of the plan on all the stakeholders,
    Electrosteel also argued that it was not barred from challenging the
[2025] 11 S.C.R.                                                        337

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     award at the execution stage. The contention was that since the
     award was a nullity, even if the appellant had not filed a petition
     under Section 34 of the A&C Act, it would not foreclose them from
     challenging the award in the execution proceedings. It was argued
     therein that the Facilitation Council in the said case inherently lacked
     jurisdiction to arbitrate the claim of the respondent, post the approval
     of the resolution plan. The respondent therein contended that since
     the appellant-Electrosteel did not challenge the award it was not
     open to them to raise a challenge to the award in the Section 47
     proceeding.
21. In answering the issue about the maintainability of the objection under
    Section 47, this Court held that the High Court was correct insofar
    as it stated that plea of nullity qua an Arbitral award can be raised
    in a proceeding under Section 47 of CPC, but such a challenge
    would lie within a very narrow compass. This Court further held that
    in terms of Section 36 of the A&C Act, an Award can be enforced in
    accordance with the provisions of the CPC, in the same manner as if
    it were a decree of the Civil Court. This Court further held as under.
          “48. ………. Execution of decrees and orders is provided for
          in Order XXI CPC. The law is well settled that at the stage
          of execution, an objection as to executability of the decree
          can be raised but such objection is limited to the ground
          of jurisdictional infirmity or voidness. The law laid down
          by this Court in Vasudev Dhanjibhai Modi Vs. Rajabhai
          Abdul Rehman, (1970) 1 SCC 670, is that only a decree
          which is a nullity can be the subject matter of objection
          under Section 47 CPC and not one which is erroneous
          either in law or on facts. The aforesaid proposition of law
          continues to hold the field.”
22. In conclusion, this Court on the said issue, held that objection to
    execution of an award under Section 47 was not dependent or
    contingent upon filing a petition under Section 34. Ultimately insofar
    as Electrosteel (supra) was concerned, the appeal of Electrosteel
    was allowed in view of the provisions of the IBC, particularly, Section
    30 and 31. It was found that the Facilitation Council did not have
    jurisdiction to arbitrate the claim after approval of the plan.
23. Electrosteel (supra) held that any challenge under Section 47 would
    lie within a narrow compass. It has also been held that at the stage
338                                                        [2025] 11 S.C.R.

                          Supreme Court Reports


       of execution, an objection as to executability of the decree can be
       raised, limited to the ground of jurisdictional infirmity or voidness.
       It has been further held that errors of facts and law cannot be the
       subject matter of objection under Section 47.
24. In Vasudev Dhanjibhai Modi vs. Rajabhai Abdul Rehman2, it
    was held that an Executing Court cannot go behind the decree. It
    was also held that where a decree is a nullity like, for example, in
    cases where it is passed without bringing the legal representatives
    on record or made by a Court which inherently lacked jurisdiction,
    objections can be raised at the execution stage.
25. It should be pointed out that, in the present case, the objection is
    not based on the ground of any inherent lack of jurisdiction. What is
    really argued is that the Officials of MMTC committed fraud on MMTC,
    their employer and there was collusion and conspiracy between the
    Officials of MMTC and Anglo in pegging the price at US$ 300 PMT
    for the 5th delivery period. So, the argument on inexecutability of the
    decree was based on fraud committed by the Officials of MMTC on
    MMTC, by collusion and conspiracy resulting in a favourable Award
    for Anglo. It is also argued that fraud was discovered only after the
    Award was upheld by this Court.
26. Mr. Neeraj Kishan Kaul, learned senior counsel for Anglo, argued that
    objections under Section 47 were barred by law; that the A&C Act is
    a complete Code and Section 5 bars any form of judicial intervention
    other than what is expressly provided in the Act. According to the
    learned senior counsel, the A&C Act contains a comprehensive
    mechanism not just for the conduct of arbitral proceedings but also
    for challenge to an execution of an arbitral award. Learned senior
    counsel contended that awards cannot be challenged by a sidewind
    in Section 47-proceedings. Mr. Kaul contended that the fraud alleged
    in the present case is a fraud on itself by the employees (on the
    MMTC) and is not a fraud on the Arbitral Tribunal. According to the
    learned senior counsel, fraud alleged is a fraud on the formation
    and validity of the underlying contract. Learned Senior Counsel also
    submits that these objections were never taken at any point in the
    earlier stage of litigation.



2   (1970) 1 SCC 670
[2025] 11 S.C.R.                                                           339

    MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


27. In response, Mr. N. Venkataraman, learned ASG drew our attention
    to a judgment of the English Court and to the following passage in
    Lazarus Estates Ltd. v. Beasley3, as cited in Ram Preeti Yadav v.
    U.P. Board of High School and Intermediate Education and Ors.4:-
             “I cannot accede to this argument for a moment. No court
             in this land will allow a person to keep an advantage which
             he has obtained by fraud. No judgment of a court, no
             order of a minister, can be allowed to stand if it has been
             obtained by fraud. Fraud unravels everything. The court
             is careful not to find fraud unless it is distinctly pleaded
             and proved; but once it is proved it vitiates judgments,
             contracts and all transactions whatsoever;”
28. Learned ASG also relied on the principle that fraud avoids all judicial
    acts, ecclesiastical or temporal and relied on the judgment in S.P.
    Chengalvaraya Naidu v. Jagannath and Ors.5, as cited in Ram
    Preeti Yadav (supra). Learned ASG further relied on Indian Bank v.
    Satyam Fibres (India) Pvt. Ltd.6, United India Insurance Co.
    Ltd. v. Rajendra Singh and Others7, and judgment of the Delhi
    High Court in National Projects Construction Corporation v.
    Royal Construction Company Private Ltd.8, to contend that fraud
    avoids all judicial acts and that fraud affects the solemnity, regularity
    and orderliness of the proceedings. By relying on Rajendra Singh
    (supra), it was contended that no Court or Tribunal can be regarded
    as powerless to recall its own order if it is convinced that the order
    was wangled due to fraud or misrepresentation of such a dimension
    as would affect the very basis of the claim.
29. In Rajendra Singh (supra), while allowing the appeal of the Insurance
    Company to recall two awards of the Motor Accident claims Tribunal
    and permitting them to resist the claim on the ground of fraud, this
    Court opened the judgment with the following strong words:-
             “2. If what the appellant Insurance Company now says is
             true, then a rank fraud had been played by two claimants


3   (1956) 1 All ER 341
4   (2003) 8 SCC 311
5   (1994) 1 SCC 1
6   (1996) 5 SCC 550
7   (2000) 3 SCC 581
8   2017 SCC Online Del 10944
340                                                        [2025] 11 S.C.R.

                         Supreme Court Reports


          who wangled two separate awards from a Motor Accident
          Claims Tribunal for a bulk sum. But neither the Tribunal nor
          the High Court of Allahabad, before which the Insurance
          Company approached for annulling the awards, opened
          the door but expressed helplessness even to look into the
          matter and hence the Insurance Company has filed these
          appeals by special leave.
          3. “Fraud and justice never dwell together” (fraus et jus
          nunquam cohabitant) is a pristine maxim which has never
          lost its temper over all these centuries. Lord Denning
          observed in a language without equivocation that “no
          judgment of a court, no order of a Minister can be allowed
          to stand if it has been obtained by fraud, for, fraud unravels
          everything” (Lazarus Estates Ltd. v. Beasley : (1956) 1
          All ER 341).
          4. For a High Court in India to say that it has no power
          even to consider the contention that the awards secured
          are the by-products of stark fraud played on a tribunal,
          the plenary power conferred on the High Court by the
          Constitution may become a mirage and people’s faith in
          the efficacy of the High Courts would corrode. We would
          have appreciated if the Tribunal or at least the High Court
          had considered the plea and found them unsustainable
          on merits, if they are meritless. But when the courts pre-
          empted the Insurance Company by slamming the doors
          against them, this Court has to step in and salvage the
          situation.”
30. Faced with this situation, Mr. Kaul submitted that even if the case is
    examined on merits, the MMTC has not made out any case, nor even
    a prima facie case, by establishing any fraud or collusion warranting
    a decision that the Award is inexecutable.
31. In the light of the judicial pronouncements discussed hereinabove,
    we are not inclined to dismiss the objections only on maintainability.
    Elaborate arguments spanning over several days have been heard
    on merits and we set out to examine the objection of the appellants
    on merits to see if any prima facie case of fraud is made out for the
    appellant to contend that the Award is inexecutable.
[2025] 11 S.C.R.                                                         341

    MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     NATURE OF ALLEGATION OF FRAUD – BREACH OF FIDUCIARY
     DUTY: -
32. The fraud that is alleged in this case originates in the grievance
    of MMTC that its employees in senior managerial roles including
    directors on the Board committed a breach of fiduciary duty. According
    to MMTC, there was collusion and criminal conspiracy by them with
    the Officials of Anglo in fixing the contracted price for the 5th delivery
    period at US$ 300 PMT. MMTC contends that the market price was
    only US$ 96.40 PMT for the 4th delivery period. The further contention
    is that the contracted quantity was far in excess of what was in need
    for NINL for whom the coal was being sourced. They also seek to
    explain the delay in unearthing the fraud for the reasons adduced by
    them which have been discussed in the earlier part of the judgment.
33. It is important to recollect here that we are at a stage where the
    award has attained finality in view of the dismissal of the appeal by
    this Court in proceedings arising under Section 34 of the A&C Act.
    The initiation of the dispute was on 04.03.2010 and the judgment
    of this Court was delivered on 17.12.2020.

     LEGAL FRAMEWORK TO DETERMINE BREACH OF FIDUCIARY
     DUTY: -
34. Before we discuss the nitty-gritty of the merits insofar as they are
    essential for adjudication of Section 47-objection to examine whether
    at all even a prima facie case is made out, it is important to set out
    the legal parameters as laid down in judicial precedents in cases
    involving breach of fiduciary duty. The broad framework as to what
    would constitute the breach of fiduciary duty and what are the legal
    parameters for deciding the same have arisen before courts across
    the globe in various fact situations. To understand the principles
    that would govern is even more important in a case like ours where
    parties have litigated for over a period of 15 years and the allegation
    of breach of fiduciary duty has cropped up after the Award has had
    the imprimatur of this Court.
35. As was rightly forewarned in Re Living Images Ltd. 9, the first
    precaution to be taken is not to fall into the trap of being too wise



9   (1996) 1 BCLC 348
342                                                           [2025] 11 S.C.R.

                             Supreme Court Reports


       after the event. In Re Living Images (supra), highlighting the need
       to discount the benefit of hindsight, the Court observed as under:-
             “I should add that the court must also be alert to the dangers
             of hindsight. By the time an application comes before the
             court, the conduct of the directors has to be judged on
             the basis of statements given to the Official Receiver, no
             doubt frequently under stress, and a comparatively small
             collection of documents selected to support the Official
             Receiver’s and the respondents’ respective positions.
             On the basis of this the court has to pass judgment on
             the way in which the directors conducted the affairs of
             the company over a period of days, weeks or, as in this
             case, months. Those statements and documents are
             analysed in the clinical atmosphere of the courtroom.
             They are analysed, for example, with the benefit of
             knowing that the company went into liquidation. It is
             very easy therefore to look at the signals available to
             the directors at the time and to assume that they, or
             any other competent director, would have realised that
             the end was coming. The court must be careful not
             to fall into the trap of being too wise after the event.”
                                                    (Emphasis supplied)

36. It is always useful while adjudicating on alleged breach of fiduciary
    cases to remember the memorable words of Lord Davey in Dovey
    and The Metropolitan Bank (of England and Wales) Limited v.
    John Cory10:-
             “I think the respondent was bound to give his attention
             to and exercise his judgment as a man of business on
             the matters which were brought before the board at
             the meetings which he attended, and it is not proved
             that he did not do so”
                                                    (Emphasis supplied)




10   1901 Appeal Cases 477
[2025] 11 S.C.R.                                                            343

     MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


37. MMTC now launches a ‘no holds barred attack’ on most of the directors
    and senior managerial personnel who were in office from 2008-2009
    right up to those who held office till 2020. The case projected is that
    the senior managerial personnel including the directors operated as
    a cabal to defraud MMTC and that it was only after this Court upheld
    the Award that an enquiry was launched and the fraud unearthed.

      TEST OF A REASONABLY COMPETENT DIRECTOR: -
38. Before we examine the merits, we should also bear in mind the
    principle that in cases like this, a court cannot be swayed by what the
    Court thinks would have been a reasonable course of action for the
    director to adopt but the duty is to enquire whether on the available
    evidence before the Court to consider whether the course adopted
    by the director was one reasonably competent directors could have
    adopted. In Sharp and Ors. v. Blank and Ors,11 a judgment by
    Norris J in Chancery Division in the context of negligence the Court
    observed as under:
             “631. … in testing whether a director has been negligent
             the question is not simply what the Court thinks it would
             be reasonable for the director to have done; rather it is
             what the evidence before the Court establishes were the
             courses open to reasonably competent directors (the
             burden lying on a complainant to establish that the course
             of which complaint is made is not amongst them).
             627. … When embarking upon a transaction a director
             does not guarantee or warrant the success of the venture.
             Risk is an inherent part of any venture (whether it is called
             ‘entrepreneurial’ or not). A director is called upon (in the
             light of the material and the time available) to assess and
             make a judgment upon that risk in determining the future
             course of the company. Where a director honestly holds
             the belief that a particular course is in the best interests
             of the company then a complainant must show that the
             director’s belief is one which no reasonable director in the
             same circumstances could have entertained.”


11   (2019) EWHC 3096 (Ch)
344                                                       [2025] 11 S.C.R.

                          Supreme Court Reports


       RANGE OF REASONABLENESS - TEST
39. Dealing with the aspect of how the Court cannot second guess
    the directors by substituting its opinion and laying down that the
    enquiry should be whether the decision taken was within the range
    of reasonableness, it was held by the Court of appeal for Ontario in
    Maple Leaf Foods Inc. v. Schneider Corp.12, thus:
             “The mandate of the directors is to manage the company
             according to their best judgment; that judgment must be
             an informed judgment; it must have a reasonable basis.
             If there are no reasonable grounds to support an
             assertion by the directors that they have acted in the
             best interests of the company, a court will be justified
             in finding that the directors acted for an improper
             purpose.
             The law as it has evolved in Ontario and Delaware has
             the common requirements that the court must be satisfied
             that the directors have acted reasonably and fairly. The
             court looks to see that the directors made a reasonable
             decision not a perfect decision. Provided the decision
             taken is within a range of reasonableness, the court
             ought not to substitute its opinion for that of the board
             even though subsequent events may have cast doubt
             on the board’s determination. As long as the directors
             have selected one of several reasonable alternatives,
             deference is accorded to the board’s decision…...
             This formulation of deference to the decision of the
             Board is known as the “business judgment rule”.
             The fact that alternative transactions were rejected
             by the directors is irrelevant unless it can be shown
             that a particular alternative was definitely available
             and clearly more beneficial to the company than the
             chosen transaction”
                                                 (Emphasis supplied)



12   42 OR (3d) 177
[2025] 11 S.C.R.                                                              345

     MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


      BUSINESS JUDGMENT RULE: -
40. The above decision also highlights the principle that as long as the
    decision taken falls within the range of options reasonably available,
    Court would defer to the decision of the Board under the “Business
    Judgment Rule”. The said principle was also reiterated by the
    Supreme Court of Canada in Kerr v. Danier Leather Inc.,13 in the
    following words:
             “On the broader legal proposition, however, I agree with
             the appellants that while forecasting is a matter of business
             judgment, disclosure is a matter of legal obligation. The
             Business Judgment Rule is a concept well-developed in
             the context of business decisions but should not be used to
             qualify or undermine the duty of disclosure. The Business
             Judgment Rule was well stated by Weiler J.A. in Maple
             Leaf Foods Inc. v. Schneider Corp. (1998), 42 O.R. (3d)
             177 (C.A.): The court looks to see that the directors made
             a reasonable decision not a perfect decision. Provided the
             decision taken is within a range of reasonableness, the
             court ought not to substitute its opinion for that of the board
             even though subsequent events may have cast doubt on
             the board’s determination. As long as the directors have
             selected one of several reasonable alternatives, deference
             is accorded to the board’s decision ...”

      APPLICATION OF THE LEGAL PRINCIPLES TO THE FACTS AT
      HAND
41. With the above legal principles in mind, it is time to apply the same
    to the facts of the case and consider the contentions raised by the
    respective parties. The dispute revolves around the 5th delivery
    period, i.e., from 01.07.2008 to 30.06.2009, as well as on the status
    and execution of Addendum No.2 dated 20.11.2008, to the LTA of
    07.03.2007. A brief narration of the facts essential for appreciating
    this aspect of the controversy has also been discussed, while dealing
    with the rival contentions.




13   (2007) 3 SCR 331 Canadian Supreme Court Reports
346                                                        [2025] 11 S.C.R.

                         Supreme Court Reports


       LONG TERM AGREEMENT (LTA) OF 07.03.2007
42. Indisputably, on 07.03.2007, an agreement for sale and purchase of
    coking coal was executed between the MMTC and Anglo. This is the
    Long Term Agreement (LTA). Under the LTA, Clauses 1 and 2 are
    crucial for the determination of the case and they are set out hereunder:
          “CLAUSE 1: MATERIAL, QUANTITY, QUALITY AND
          DELIVERY PERIOD:
          1.1    The SELLER shall sell and the PURCHASER shall
                 buy,
          a)     The base quantity during the currency of the contract
                 shall be 466,000 (Four hundred Sixty six thousand)
                 metric tons (of one thousand kilograms each) firm.
          b)     During the First Delivery Period (1 st July, 2004
                 to 30th June, 2005), a quantity of 464,374 (Four
                 Hundred Sixty Four Thousand, Three Hundred
                 and Seventy Four) metric tons (of one thousand
                 kilograms each) firm quantity of freshly mined and
                 washed “Isaac”, “Moranbah North” and “German
                 Creek” coking coals.
          c)     During the Second Delivery Period (1st July, 2005
                 to 30th June, 2006) a quantity of 382,769 (Three
                 Hundred Eighty Two Thousand, Seven Hundred and
                 Sixty Nine) metric tons (of one thousand kilograms
                 each) firm quantity of freshly mined and washed
                 “Isaac”, “Moranbah North” and “German Creek”
                 coking coals.
          d)     During the Third Delivery Period (1st July, 2006 to
                 30th June, 2007) a quantity of 466,000 (Four Hundred
                 Sixty Six Thousand) metric tons (of one thousand
                 kilograms each) firm quantity of freshly mined and
                 washed “Isaac”, “Moranbah North” and “German
                 Creek” coking coals.
          e)     During the subsequent Delivery Periods, in
                 case of the PURCHASER exercising the option
                 to extend the duration of the Agreement by two
                 more years, at its sole discretion, as indicated
                 at Para 1.3 herein below, a quantity of 466,000
[2025] 11 S.C.R.                                                         347

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


                 (Four Hundred Sixty Six Thousand) metric tons
                 (of one thousand kilograms each) of freshly
                 mined and washed “Isaac”, “Moranbah North” and
                 “German Creek” coking coals hereinafter referred to
                 as the MATERIALS, in conformity with the Technical
                 Specifications incorporated in Annexure- IIA
                 (applicable for “Isaac” coking coal) and Annexure-
                 IIB (applicable for “Moranbah North” coking coal)
                 and Annexure IIC (applicable for “German Creek”
                 coking coal) to this Agreement and which shall
                 constitute an integral part of this Agreement, for
                 use of imported coking coals in the coke ovens in
                 its integrated iron and steel works for production of
                 metallurgical coke. The quality of the prime washed
                 coking coals to be supplied under this Agreement
                 shall under no circumstances be inferior to the
                 Technical Specifications as contained in Annexure
                 IIA, Annexure IIB and Annexure IIC to this Agreement
                 as applicable.
          1.1.1 Annual base quantity from 15th July, 2007 to 30th
                June, 2009, in case Purchaser exercises its option to
                extend the Agreement by 2 years, shall be 466,000
                metric tonnes, subject to further discussions at the
                time of contract extension and the logical contract
                specification modifications to reflect the changing
                nature of existing reserves at the Moranbah North
                and German Creek mining operations will be
                mutually agreed.
          1.2    For the purpose of this Agreement, the Delivery
                 Periods shall be reckoned as follows:
                 First Delivery Period: 1st July 2004 to 30th June 2005
                 Second Delivery Period: 1st July 2005 to 30th June
                 2006
                 Third Delivery Period: 1st July 2006 to 30th June 2007
                 The shipments will be evenly spread during each
                 Delivery Period. The PURCHASER reserves the
                 right to prepone shipments against any Delivery
348                                                   [2025] 11 S.C.R.

                    Supreme Court Reports


             Period based on its requirement and subject to
             availability with the SELLER.
             The PURCHASER reserves the right to postpone
             the deliveries to be effected under each Delivery
             Period by upto 3 months i.e. upto the month of
             September following each Delivery Period, without
             any additional financial liability to the PURCHASER.
       1.3   The PURCHASER had the option to extend the
             duration of the Agreement by two more years,
             at its sole discretion and the Purchaser to
             exercise its option for extending the Agreement
             by two more years or otherwise by 31 January,
             2007. In case the PURCHASER decides to
             exercise such option, at its sole discretion, the
             Agreement shall have two more Delivery Periods as
             follows:
             Fourth Delivery Period: 1st July 2007 to 30thJune
             2008
             Fifth Delivery Period: 1st July 2008 to 30thJune 2009

       CLAUSE 2: PRICE:
       2.1   The firm price of the MATERIALS for the First
             Delivery Period 1st July 2004 to 30th June, 2005
             shall be US$ 57.75 (United States Dollars, Fifty
             Seven and Cents Seventy Five only) per metric ton
             (of one thousand kilograms each) Free on Board
             (Trimmed). Port of Loading will be Dalrymple Bay
             Coal Terminal, Queensland, Australia.
             The firm price of the MATERIALS for the Second
             Delivery Period 1st July 2005 to 30th June, 2006 shall
             be US$ 126.75 (United States Dollars One hundred
             twenty six and Cents Seventy Five only) per metric
             ton (of one thousand kilograms each) Free on Board
             (Trimmed). Port of Loading will be Dalrymple Bay
             Coal Terminal, Queensland, Australia.
       2.2   The Price for the delivery of AGREEMENT
             quantity for subsequent Delivery Periods shall
[2025] 11 S.C.R.                                                         349

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


                 be fixed in accordance with Para 1 of Annexure
                 I and shall be firm and shall not be subject to
                 any escalation for any reason, whatsoever, until
                 the completion of delivery of the AGREEMENT
                 quantity due for delivery in the relevant Delivery
                 Period with such extensions as might be
                 mutually agreed upon between the PURCHASER
                 and the SELLER.
          2.3    The payment of the price of the MATERIALS
                 delivered by the SELLER under this Agreement
                 shall be made by the PURCHASER by means of
                 an irrevocable, without recourse to drawer Letter of
                 Credit providing for payment of the full invoice value
                 of the MATERIALS at sight. The Letter of Credit will
                 provide for full payment in US Dollars at Brisbane,
                 Queensland, Australia. The payment shall be made
                 on presentation of the documents mentioned in Para
                 6.2 of Annexure - 1.
          2.3.1 Notwithstanding the method of payment as
                mentioned at 2.3 above, the SELLER may also
                provide Supplier’s credit for 180 days at the terms
                and conditions mutually agreed upon from time
                to time, against an irrevocable, without recourse
                to drawer letter of credit upon presentation of
                documents mentioned at Para 6.2 of Annexure-I.
                 The documents in original and by fax referred to
                 hereinabove should be delivered at the following
                 address.
                 General Manager (Coal & Coke)
                 MMTC Limited,
                 SCOPE Complex, Core-1,
                 7, Institutional Area, Lodi Road,
                 New Delhi-110003
                 India
                 All bank charges at the Seller’s end (outside
                 India) shall be borne and paid for by the SELLER.
                 All bank charges at the PURCHASER’S end
350                                                      [2025] 11 S.C.R.

                        Supreme Court Reports


                 (inside India) shall be borne and paid for by the
                 PURCHASER.”
                                                (Emphasis supplied)

43. It will be noticed that under Clause 1.1 (a), the base quantity of
    4,66,000 MT was fixed for the currency of the contract. For the
    first three delivery periods, the quantity was mentioned along with
    the period. Clause 1.1 (e) dealt with the option of the purchaser to
    extend the duration by two more years, after the third delivery period.
    It further provided that if option is exercised a quantity of 4,66,000
    MT of coal was to be purchased.
44. Clause 1.3 vested the option in the purchaser to extend the contract.
    Clause 2.1 provided the firm price of the materials for subsequent
    delivery periods. As per Clause 2.2, the price was to be fixed in
    accordance with Para 1 of Annexure-I which dealt with General
    Conditions of Agreement. Under Para 1 of Annexure-I, the price for
    delivery of the materials during subsequent delivery periods was
    to be mutually discussed and settled by the purchaser and seller
    prior to the commencement of relevant delivery period at the same
    price as settled between the seller and SAIL/RINL, applicable to the
    relevant delivery period under the LTAs.
45. Clause 1.1 of the General Conditions of Agreement in Annexure-I
    is extracted hereunder:

          “GENERAL CONDITIONS OF AGREEMENT (GCA)
          PARA 1.0: PRICE FIXATION
          1.1 The price for delivery of the MATERIALS during
              subsequent Delivery Periods shall be mutually
              discussed and settled by the PURCHASER
              and SELLER prior to commencement of the
              relevant Delivery Period at the same price
              as settled between the SELLER AND STEEL
              AUTHORITY OF INDIA (SAIL) / RASHTRIYA ISPAT
              NIGAM LTD (RINL), applicable to the relevant
              Delivery Period under their respective Long Term
              Agreements.”
                                                (Emphasis supplied)
[2025] 11 S.C.R.                                                        351

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     It is undisputed that the third delivery period also passed off smoothly
     from 01.07.2006 to 30.06.2007.

     EXECUTION OF THE MoU AND EXERCISE OF OPTION: -
46. One of the questions that arise is whether option was exercised on
    or before 31.01.2007 as required under Clause 1.3 of the LTA. While
    Mr. Venkataraman-learned ASG, contends that it was Addendum No.2
    dated 20.11.2008 which was the real agreement, Mr. Kaul submits
    that, on 30.01.2007, a MoU was executed between MMTC and
    Anglo. Mr. Kaul contends that while the LTA was not formally signed,
    deliveries for the first and second delivery period were completed
    and by 30.01.2007 they were in the process of completing the third
    delivery period which was from 01.07.2006 to 30.06.2007. It was at
    this point that on 30.01.2007, a MoU has been executed with the
    following Clauses:
          “1.   MMTC to execute the long term contract agreed
                between the parties in correspondence and provide
                to Anglo for execution earliest.
          2.    The parties agree to foreclose a quantity of
                a)   1615 MT undelivered against first delivery period
                     July 2004- June 2005 of long term contract @
                     USD 57.75 PMT FOBT and
                b)   83231 MT undelivered against second delivery
                     period July 2005-June 2006 of long term contract
                     @ USD 126.75 PMT FOBT
          2.    Supply of a quantity of 466,000 MT @ USD 114.00
                PMT FOBT for third delivery period July 2006-June
                2007. The delivery period is extended to September
                30,2007.
          3.    Supply of a quantity 466,000 MT at price to be
                finalized by EJC for SAIL and RINL, for fourth
                delivery period July 2007- June 2008. The delivery
                period is extendable up to September 2008.
          4.    The contract is extended by a further two years
                in accordance with clause 1.3 of the long term
                agreement.
352                                                                           [2025] 11 S.C.R.

                                 Supreme Court Reports


                     Fourth delivery period 1st July 2007 to 30th June
                     2008.
                     Fifth delivery period 1st July 2008 to 30th June
                     2009.
                     The price terms & Conditions of coal supply to
                     MMTC for fourth and fifth delivery periods shall
                     be as per Anglo-Agreement UNL/SAIL”
                                                                 (Emphasis supplied)

47. It will be noticed that this MoU was signed on 30.01.2007 and this
    is a fact not disputed by the learned ASG and, in fact, filed by the
    learned ASG as part of his additional documents. This date was one
    day before the deadline of 31.01.2007.#

       DELIVERIES DID NOT AWAIT FORMAL EXECUTION OF
       AGREEMENTS: -
48. As is clear from the MoU, based on the agreement in the
    correspondence, deliveries were taking place and by the time the
    LTA was signed, it was mid-way during the third delivery period.
    As could be seen from the MoU, even the 4th delivery period was
    agreed upon and passed on without any dispute. The 5th delivery
    period was to begin on 01.07.2008, when the 4th delivery period
    stood extended till 30.09.2008.

       PRICES PEGGED TO SAIL/RINL PRICE: -
49. The price for the periods concerned was pegged by what the
    Empowered Joint Committee would fix for the contract with SAIL and
    RINL. This was also reiterated on 30.01.2007, contends Mr. Kaul.
    When matters stood thus, the time for the 4th delivery period which
    was extended to 30.09.2008, however, continued till 30.10.2008.
    In the meantime, as is clear from the internal note of 03.06.2008
    circulated by Shri Suresh Babu of MMTC, SAIL and RINL had fixed
    their price for the delivery period from 01.07.2008 to 30.06.2009.
    On 03.06.2008, the Lehman Brothers’ collapse had not happened.
    It commenced on 15.09.2008, and that is also not in dispute.

# Ed. Note: “This date was one day before the deadline of 31.01.2007” instead of “This date was one
             day before the deadline of 31.01.2007 which came to be signed on 07.03.2007” in terms of
             subsequent corrigendum.
[2025] 11 S.C.R.                                                             353

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     INTERNAL NOTE OF 03.06.2008
50. At this stage, it is relevant to extract the internal note of 03.06.2008
    prepared by Shri Suresh Babu for MMTC, which reads as under:-

                     “COAL & HYDROCARBON DIVISION
          Sub: Finalization of long term price of Coking Coal for
          Delivery Period of 01-07-2008 to 30-06-2009.
          Anglo and BMA had already finalized the price of hard
          coking coal for the above delivery period with Japanese
          Steel Mills and SAIL and RINL. The price of prime hard
          coking coal for the above delivery period is fixed at usd
          300/t and Torrington hard coking coal at usd 292.50/t
          as against usd 96.4/91.5 per ton respectively in the
          previous year. It is understood that BMA had not allowed
          carrying forward the left over quantities for the delivery period
          2007-08 in case of Japanese Steel Mills. So MMTC made
          all out effort to secure the cargo from both BMA and Anglo
          within the delivery period itself. MMTC will not be able to
          lift the entire contracted quantity of Anglo Coal for 07-08
          by 30th June, 2008. Accordingly shipment schedule has
          been obtained from Anglo to complete shipment within the
          extension allowed i.e., upto Sept,’08. However, BMA has to
          give us the schedule for left over quantity for 2007-08. Here
          also every effort is being made to ensure that the entire
          quantity relating to 2007-08 delivery period will be secured
          within the extended delivery period upto 30th Sept., 2008.
          The coal supplied within the extended period will be
          sufficient to take care of NINL requirement upto March’09.
          As per the shipment schedule given by Anglo, two vessels
          have to be nominated in Sept 08 to load coking coal from
          DBCT. These vessels will come up for loading from DBCT
          in Oct 08 and reach Paradip early November 08.
          Both Anglo and BMA are offering Japanese price to Indian
          consumers. The demurrage rate offered by Japanese Steel
          Mills are said to be in the range of US $ 9000-15,000
          per day. So Indian consumers also have been asked to
          accept similar demurrage rates. Despite all these, the
          spot price of hard coking coal has reached US $ 400/t
354                                                       [2025] 11 S.C.R.

                         Supreme Court Reports


           FOB; availability is very-very tight. Since the 2007-08
           contract cargo is to be delivered upto 30.9.09, there
           was a suggestion from Anglo that quantity for 1.7.08
           to 30.6.09 will be proportionately reduced keeping in
           mind 9 months left for the supplies.
           Considering the huge shortage for coking coal and the
           spot premium, it is felt that “we may continue to keep the
           delivery period from 1.7.08 to 30.06.09 and the contracted
           quantity will be 4,66,000 tons with provision for extension
           of delivery period by another three months, i.e., upto
           30.9.09. in case the entire quantity cannot be delivered
           by 30 June 2009, delivery period will be extended upto
           30.9.09.” We may also request Anglo to extend the long
           term agreement for another five years with the terms and
           conditions of Steel Authority of India Ltd.
           For approval ‘A’ please					Sd/-
                                    (SURESH BABU)
           							                   03.06.08
           DIR (HSM)
           Upto March 09, we should try to avoid/ defer US$ 300
           price coal to be finalised for 08-09 pl. ‘X’ app.
                                Sd/-
                                HS Mann
                                04/08.”
                                                  (Emphasis added)

51. As will be noticed, there was a note of Shri H.S. Mann, Director, to
    the effect that MMTC should try to avoid/defer US$ 300 price coal
    to be finalised for 08-09. Learned ASG highlighted this aspect of the
    matter in great detail. The learned ASG contended that even Mr.
    Mann, later was a party consenting to the price of US$ 300 PMT
    and wanted to infer certain sinister conduct in the same.

       EJC – APPROVAL OF SAIL/RINL PRICE AT US$ 300 PMT:
52. On 14.08.2008, Anglo wrote to MMTC about their agreement with
    the Empowered Joint Committee (EJC) on 08th and 9th May, 2008
    for supply of hard coking coal to SAIL and RINL during the delivery
    period from 01.07.2008 to 30.06.2009. They confirmed by the same
[2025] 11 S.C.R.                                                      355

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     mail the supply arrangement for the 5th delivery period with MMTC
     for 4,66,000 MT. Indisputably, the price fixed with SAIL and RINL
     was US$ 300 PMT.
53. On 25.09.2008, a letter was written by Shri Suresh Babu of MMTC
    to Shri SP Padhi, Executive Director of NINL, suggesting that since
    SAIL has already signed the agreement for 2008-2009 and the price
    is also fixed, MMTC may also sign the agreement. In the letter, it
    was suggested that a new brand of hard coking coal “Dawson Valley
    Blend” has been introduced. The letter suggested that “Dawson” coal
    be preferred because “Dawson” coal will be loaded from Gladstone
    where the pre-berthing delay is only around a week as against
    25 to 30 days in port (DBC) where Isaac coking coal was loaded.
    Suggestion was that demurrage can be saved by MMTC.

     AGENDA NOTE OF 29.09.2008
54. In the agenda note dated 29.09.2008 put up by Shri Suresh Babu
    to the Sale/Purchase Committee of Directors [SPCoD] of MMTC,
    it was stated as under:-
          “5. Status Of 2007-08 Contract:
          a) Contracted Quantity: 466,000 Mt: As on today a
          quantity of 417,345 MTs of Hard Coking Coal has already
          been loaded by Anglo and a vessel is already nominated in
          lay can 20-30 October 2008, for loading about 50,000 Mt.

          6. New 5 Year Long Term Agreement by SAIL: RINL/
          SAIL’s LT agreement was valid till 30.6.08. They have
          entered into a new five year long term agreement with
          Anglo Coal for the period of 15th July 2008 to 30th June
          2013. Our LT agreement is valid upto 30.6.09. We may,
          if approved, explore the possibility and enter into a five
          year long term agreement with effect from 01.07.2008 to
          30.06.2013 as in the case of RINL/SAIL.

          B: RECOMMENDATION OF THE DIVISION: -
          7. SPC may please deliberate and accord approval for:-
          i) Inclusion of new coking coal brand “Dawson Valley
          Blend”.
356                                                      [2025] 11 S.C.R.

                        Supreme Court Reports


          ii) Price of US$ 300.00 PMT FOB each for the purchase
          of Isaac and Dawson Valley Blend Brand of Coking Coal
          totaling 466,000 MT from Anglo for the period of 1st July
          2008 to 30th June 2009.
          iii) Subject to acceptance by Anglo Coal for entering
          into five years long term agreement with them w.e.f.
          1.07.2008, incorporating the terms and conditions of
          Anglo’s Agreement/ amendment to Agreement with SAIL
          from time to time with logical changes wherever applicable.
          8. The total value of the proposed purchase for 2008-09
          is about Rs.615 crores (exchange rate US$/Rs. = 1/44).
          9. Authorising Dir (HSM) and Dir (Fin) to sort out deadlock
          issues/make logical changes wherever required.
          10. Associate Finance has concurred the proposal.
          11. Director-HSM has seen and approved for circulation
          to SPCOD.

          C: DECLARATION
          The Division has truly and fairly brought out all material
          information available with the division which is likely to
          influence the decision SPC, in the agenda and no material
          information has been withheld.”

       SPCoD APPROVAL OF 06.10.2008
55. The SPCoD met on 06.10.2008. The SPCoD (including Mr. H.S.
    Mann) granted approval in the following terms:-

          “Item No. 1: Agreement with Anglo coal Australia Pty. Ltd.,
                       for import of Coking Coal for NINL-as per note
                       of GM (SB) dated 29.9.2008
          The Committee after being informed that the proposed
          terms and conditions including deviations are same, as in
          the case of RINL/SAIL approved the proposal subject to
          acceptance of the same by NINL. Possibility of reduction
          of quantity for 2008-09 be explored without affecting
          long-term prospects from the supplier in view of recent
          fall in prices of Pig Iron and Steel products
[2025] 11 S.C.R.                                                         357

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited



           Item No. 2: Import of Coking Coal of NINL-Qty. & Price
                       Fixation as per note of GM (SB) dated 29.9.2008
           The Committee after being informed that the proposed
           terms and conditions including deviations are same, as in
           the case of RINL/SAIL, approved the proposal subject to
           acceptance of the same by NINL. Possibility of reduction
           of quantity for 2008-09 be explored without affecting long-
           term prospects from the supplier in view of recent fall in
           prices of Pig Iron and Steel products.”
                                                  (Emphasis supplied)

     The Minutes of 06.10.2008 mentioned that in view of the recent fall
     in prices of pig iron and steel products possibility of reduction of
     quantity should be explored.
56. Dealing with reference to “approval by NINL” in the Minutes, Mr.
    Kaul sought to explain the same by stating that the LTA was not
    dependent on the approval of NINL and what was meant by the
    Minutes was the approval of the proposed change in the technical
    specifications of coal.

     5TH DELIVERY PERIOD COMMENCED WITH THE LAST SHIPMENT
     UNDER THE FOURTH DELIVERY PERIOD: -
57. During this period, the 4th delivery period was nearing completion
    in view of the extension up to 30.09.2008 which prolonged up to
    30.10.2008. In fact, it was not disputed that with the last shipment
    of the 4th delivery period of 48,655 MT at US$ 96.40 PMT, 2,366 MT
    was loaded on the vessel as part of the 5th delivery period at US$
    300 PMT. This was even before the Addendum No.2 of 20.11.2008
    and on a query by the Court, the learned ASG replied that this was
    a miniscule quantity intended to save dead freight. What is, however,
    significant is even before agreements were entered into, based on the
    agreement on correspondence, deliveries were being executed and
    that is clear from the events that transpired from 2004 onwards. No
    grievance has been raised for any of the shipments till 20.11.2008.

     REPLY OF NINL TO MMTC LETTERS OF 25.09.2008: -
58. In reply, NINL wrote two letters, first a letter was written on 14.10.2008
    giving a go-ahead. Thereafter, a letter dated 16.10.2008 was written
358                                                       [2025] 11 S.C.R.

                           Supreme Court Reports


       in reply to MMTC’s letter dated 25.09.2008. This letter of 16.10.2008
       is strongly relied upon by learned ASG to contend that NINL needed
       only 2.2 Lakh tons of Anglo coal. The letters dated 14.10.2008 and
       16.10.2008 read as under:-

            “Ref.No.NINL/GM(Comml)/2008/1085
                                                     Date: 14.10.2008
            Mr. Suresh Babu,
            GM (Coal & Coke)
            MMTC Ltd.,
            New Delhi
            Dear Sir,
            Please refer to your mail dated 25th September, 2008 for
            procurement of coking coal of 12.66 lakh tons.
            MMTC may please place order for Anglo Coal consisting
            of 80% Dawson and 20% Capricon, since the same is
            approved by SAIL. Other terms and conditions may be
            negotiated and finalized.
            Thanking you,
            Yours faithfully
            For Neelanchal Ispat Nigam Ltd
            Sd/-
            [P.K. Pandey]
            DGM (Commercial)

                               ***             ***                ***
            Ref. No. NINL/CM/24/1103
                                               Dt. 16th October, 2008
            Mr. Suresh Babu,
            General Manager (Coal & Coke)
            MMTC Limited
            Core-1, Scope Complex
            7 Institutional Area, Lodhi Road
            New Delhi-110003
            Dear Sir,
[2025] 11 S.C.R.                                                       359

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


          Please refer to your mail dated 25th September, 2008 for
          procurement of Coking Coal of 12.66 Lakh Tons.
          It may be noted that our annual requirement is 11.80 lakh
          tons. Our present stock of coal is around 3.70 Lakh tons.
          Hence, we need to procure coal around 9.00 Lakh tons
          in a year from now. However, procurement quantity may
          be decided based on the coal supply in pipe line and our
          present stock. Considering, blending of the hard coal and
          soft coal is in 80:20 ratio, coal may be procured as under:

          Hard Coking Coal:

           a) BMA             :   5 Lakh tons approx.
           b) ANGLO           :   2.2 Lakh tons approx.
          Out of 2.2 Lakh tons of ANGLO Coal, 20% may be procured
          from Dawson Valley Blend consisting of 80% Dawson and
          20% Capricorn, since the same is approved by SAIL, at
          the option of MMTC/NINL (to be exercised in a manner
          for minimizing the demurrage)

          Soft Coking Coal
          Black Water: 1.80 Lakh Tons Approx.
          Price, terms and conditions may be negotiated and
          finalized.
          Thanking you,
          Yours faithfully,

          Sd/-
          16/10
          (P.K. Pandey)
          Dy. General Manager (Commercial)
          Encl: Approved copy of Competent Authority for your
          reference and record.”
59. Mr. Kaul contends that the terms of LTA had already fixed the quantity
    and NINL’s correspondence one way or the other can have no bearing
    on the committed quantity which MMTC agreed to procure from Anglo.
360                                                      [2025] 11 S.C.R.

                        Supreme Court Reports


       ADDENDUM NO.2 DATED 20.11.2008 – THE BONE OF
       CONTENTION: -
60. It is in this background that the 20.11.2008-Addendum No.2 to the
    LTA was formally signed. Learned ASG contended that it was by
    the agreement of 20.11.2008 that price and other terms of delivery
    were fixed and relied on the evidence of Mr. John Wilcox who was
    examined in the Arbitration as Anglo’s witness. According to learned
    ASG, the officials of MMTC by entering into Addendum No.2 tied up
    MMTC in knots and no ends were kept loose to ensure that MMTC
    was committed to huge financial amounts due to the fraudulent
    fixation of the price.
61. Learned ASG referred to the news release of Anglo dated 20.02.2009
    to demonstrate that it was within the knowledge of Anglo that the
    price of coking coal has drastically fallen in the second half of 2008.
62. In response, Mr. Kaul contended that Addendum No.2 signed on
    20.11.2008 was only the last in the series of documents to finetune
    the shipping terms, moisture content and the specific variety of coal
    for the 5th delivery period all material terms including the shipping
    period (from 01.07.2008 to 30.09.2009) quantity (4,66,000 MT) and
    price were already fixed in terms of the LTA. The price was to follow
    the SAIL/RINL price which has been duly fixed at US$ 300 PMT for
    the said period.
63. The Addendum of 20.11.2008 is in the form of a letter addressed
    by MMTC to Anglo. It is to the attention of Mr. John B. Wilcox. It
    states that MMTC was pleased to confirm the settlement with Anglo
    and, thereafter, the column below deals with (i) delivery period –
    01.07.2008 to 30.06.2009, (ii) quantity – 4,66,000 MT. Thereafter, it
    deals with coal brands and price (US$ 300 PMT), other terms like
    total moisture, loading terms, vessel sizes, loading rates, demurrage
    rates for different ports, the variation permissible limits and force
    majeure clause. At the end it has the following clause:
          “All other terms and conditions of agreement no. MMTC/
          C&HC/LT/HCC/NINL/ANGLO/585 DATED 7TH MARCH
          2007 shall remain unchanged”.
64. It should be recalled that shipments have happened based on
    correspondence, as stated earlier from 2004 and agreements have
    been entered into post the shipments even for the 5th delivery period.
[2025] 11 S.C.R.                                                        361

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     Admittedly, 2,366 MT were shipped on 30.10.2008 along with the
     last shipment of the 4th delivery period.

     SAME DAY (20.11.2008) LETTER SEEKING PRICE REDUCTION: -
65. On the same day after entering into Addendum No.2, the following
    letter was written by Mr. Ved Prakash, the Chief General Manager
    of MMTC to Anglo:-
          “File No. MMTC/C&HC/08-09/CC/Anglo/798
                                                20th November 2008
          Anglo Coal Australia Pty. Ltd.
          201, Charlotte Street
          Brisbane 4000
          Queensland, Australia
                                           Fax No. 0061-7-3834-1390
          KIND ATTN: MR. JOHN B WILCOX, MARKETING
          MANAGER
          Sub: Addendum to Long Term supply of coking coal
          contract for the
          Delivery Period 2008-09
          Dear Sirs,
          As discussed, we hereby confirm the acceptance of coking
          coal supply during the period 2008-09 vide Addendum No.2
          LT Agreement MMTC/C&HC/LT/HCC/NINL/ANGLO/585
          DATED 7th March 2007
          As you are aware, due to worldwide crisis as financial
          markets, there has been unprecedented fall in prices of
          major commodities including steel Such a steep tall is a
          rare phenomenon and all over there is a feeling that it is a
          beginning of economic recession in the world. It is feared
          that it may continue for long time to come
          The prices of iron and steel products in the international
          market has nose-dived in the month of September and
          October 2008 and pig iron, a finished product manufactured
          by us and being exported is not getting customer on
362                                                       [2025] 11 S.C.R.

                         Supreme Court Reports


          date even at US $100 FOB. Same is the situation in the
          domestic market and we are not able to sell our product.
          Under the circumstances, you will appreciate it has
          become absolutely unviable to produce and sell pig
          iron based on the imported coking coal having price of
          US$ 300 per tonne FOB for hard coking coal. More than
          three-fold increase in the price of coking coal during
          a period when the prices of finished steel including
          pig iron had virtually crashed, will make difficult for us
          to run the plant on sustainable basis. The substantial
          depreciation of Indian rupees to USD has further added
          to our woes and under the circumstances, we have
          already out the production to a bare minimum so as to
          just keep running our coke oven batteries as well as blast
          furnace. In view of unprecedented recessionary trends in
          the economy and consequent abnormal low realization on
          pig iron, we request price reduction of coal for quantities
          finalized for delivery during 1st July 2008 to 30th June 2009
          period to level that was settled for delivery period 1st July
          2007 to 30th June 2008. This only will help us to keep the
          plant running and to produce on consistent basis.
          We look forward for your positive response.
          Yours faithfully
          Sd/-
          MMTC Ltd.
          Ved Prakash
          Chief General Manager”
                                                (Emphasis supplied)

66. The letter was written by Shri Ved Prakash who was then the Chief
    General Manager and the substance of the letter was that since
    pig iron prices have crashed, to purchase coal at US$ 300 PMT to
    produce pig iron could be an unviable option. Hence, a request was
    made for price reduction of coal for the period from 01.07.2008 to
    30.06.2009 to the level which obtained for the delivery period from
    01.07.2007 to 30.06.2008.
67. Elaborate arguments were advanced by the learned ASG about the
    significance of letter being written on the same day after signing the
[2025] 11 S.C.R.                                                   363

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     Addendum No.2. The learned ASG also invited our attention to the
     observations of majority members of the Board of Arbitration about
     the Addendum being executed and the letter being written on the
     same day respectively.

     SUBSEQUENT CORRESPONDENCE – CONCEPT OF “CARRY
     OVER”: -
68. Learned ASG referred to a series of correspondence that ensued
    between MMTC and Anglo pursuant to MMTC lifting only 11,966
    MT out of the contracted 4,66,000 MT. Learned ASG contended
    that the correspondence only reflected a friendly fight between
    erring officials, after having committed to the price of US$ 300 PMT
    while the prevailing market price was US$ 128 PMT. Learned ASG
    submitted that on the one hand Anglo was justifying the fixation of
    prices at US$ 300 PMT on the premise that agreements entered
    into between SAIL and RINL were of the said price, while on the
    other hand Anglo chose to ignore the same analogy for the period
    post the execution of Addendum. According to learned ASG, the
    refusal on the part of Anglo for staggering at the price of US$ 128
    PMT in the same manner as was provided to SAIL was an act of
    arbitrariness on the part of Anglo. Learned ASG lamented that the
    erring officials of MMTC did not even attempt to persuade Anglo to
    provide the same treatment as was given to SAIL and RINL after
    the execution of the Addendum dated 20.11.2008.
69. Learned ASG referred to the letter dated 21.09.2009 of Anglo which
    referred to the earlier letter dated 09.03.2009 (which MMTC claims
    was not received by MMTC) and submitted that Anglo had made
    the following proposal:-
     •    MMTC to perform a total of 38% of the total contracted tonnage
          for the Fifth Delivery Period on the terms and conditions
          (including price) applicable under the Agreement (a further
          172,533 tonnes) by March 31, 2010. This will bring MMTC in
          line with the contract performance of SAIL and RINL for the
          2008/09 Delivery Period.
     •    In addition, MMTC is to perform 18.7% of the remaining
          Carryover (a further 52,641 tons) by March 31, 2010 on the
          terms and conditions of the Agreement (including price) as
          agreed with SAIL and RINL.
364                                                         [2025] 11 S.C.R.

                          Supreme Court Reports


       •   Anglo will enter into a new long term agreement with MMTC
           on the same terms and conditions as the current long term
           agreements with SAIL and RINL (including performance of the
           remaining carryover) for 466,000 tonnes per annum for a period
           of 3 years commencing 1st April, 2010.
       •   Therefore, in summary, MMTC will take delivery of 225,174
           tonnes of coal at 2008 price, terms and conditions between
           now and 31 March 2010 and, under the new 3 year contract,
           perform the remainder of the Carryover evenly spread over the
           first 2 years of the contract.
       •   This proposal is made without prejudice to our rights under
           the Agreement. It will remain open and capable of acceptance
           until 5:00 pm (Brisbane time) on Wednesday 30th Sept 2009.
70. Learned ASG submitted that by letter of 25.09.2009, Shri Suresh
    Babu declined the proposal which the learned ASG stated would
    indicate that the reply strengthened the case of Anglo. Referring to
    the counter proposal in the letter of 25.09.2009, the learned ASG
    referred to the following paragraph in the said letter:-
           “...Keeping these issues in mind, we had approached
           Anglo Coal for a reduction in price vide our letter dated
           20.11.2008. Lifting another 38% implies a further increase
           in loss by another USD 80/t. For the sake of negotiation,
           we hope you will not ignore the economic realities
           completely. Steel Melting Shop of NINL is under
           implementation and the commissioning is expected
           sometime in end 2010. Economy will also come out
           of recession gradually.
           In short we are not denying our obligation. The request
           is only for staggering the time frame for lifting as explained
           in para 1 and para 2. Please review and consider our
           request for allotting at least one shipment of 50,000 MT
           each from October 09 onwards instead of zero stem till
           end of 2009.”
                                                  (Emphasis supplied)

71. Learned ASG also referred to the further proposal of Anglo vide
    their letter dated 25.11.2009, whereby Anglo proposed that MMTC
[2025] 11 S.C.R.                                                       365

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     lifts the remaining quantities of 4,54,034 MT of 2008 contract year
     in line with the agreement with SAIL and RINL at the 2008 price of
     US$ 300 as per the following schedule:-

           “January - March, 2010       85,000         18.7%
           April 2010 - March 2011      1,84,566       40.65%
           April 2011 - March 2012      1,84,566       40.65%
          We trust that this arrangement meets with your approval.
          This proposal is made without prejudice to our rights
          under the Agreement. It will remain open and capable
          of acceptance until 5.00pm (Brisbane time) on Friday 4th
          December 2009.”
72. Learned ASG referred to the reply of Shri Suresh Babu, for MMTC
    dated 27.11.2009 in his letter addressed to Mr. Rod H. Elliott of Anglo
    stating that the said proposal was acceptable to MMTC subject to
    Anglo allocating the left-over quantities pertaining to 2009 contract at
    2009 prices based on the terms and conditions agreed upon in the
    EJC of SAIL and RINL. The learned ASG referred to the following
    para in the said letter.
          “……conditions agreed upon in the EJC of SAIL & RINL.
          To be specific the balance supplies amounting to 4,25,600
          MT at the 2009 price level of US$ 128/125 PMT shall also
          be made in proportion along with the carryover quantities
          of 2008 as proposed above in line with the terms agreed
          upon with SAIL & RINL.”
73. Learned ASG referred to the reply of Anglo dated 01.12.2009 stating
    that it was not possible to make any additional tonnage commitment
    to MMTC over and above what was detailed in the proposal of
    25.11.2009. The above correspondence was characterised by the
    learned ASG as a make believe and friendly fight and only a creation
    of a paper trail to give an impression that there was no collusion.
74. Mr. Kaul, on the other hand, submitted that the offers made by
    Anglo were good faith offers. Explaining the concept of “carry over”
    learned senior counsel, Mr. Kaul, pointed out that “carry over”
    arrangements do not dilute price or quantity and all that happens
    is some more time is given to the purchaser to lift the quantities at
    the contracted price.
366                                                      [2025] 11 S.C.R.

                        Supreme Court Reports


75. Mr. Kaul strongly refuted the contention that Anglo allowed SAIL
    and RINL to lift their 2008-09 quantities at a reduced price. Mr. Kaul
    submitted that SAIL and RINL were in the first delivery period of their
    new LTA and as such could lift coal pertaining to their future delivery
    period alongside their 2008-09 carryover and could thus seek mixed
    price cargo with shipments containing some percentage of 2008-09
    carryover and some percentage of the ongoing delivery period. Mr.
    Kaul submitted that MMTC was in the last delivery period and even
    then they were not treated differently than SAIL or RINL.
76. According to Mr. Kaul, on 15.07.2009, MMTC was offered an ad hoc
    “mixed price shipment” to tide over financial difficulties of MMTC.
    According to the learned senior counsel, what was offered in the
    letter, namely, 40,400 MT at US$ 128.25 PMT was on ad hoc basis
    with a condition that their carry over quantity of 5th delivery period
    will be supplied only at US$ 300 PMT.
77. Mr. Kaul, learned senior counsel for Anglo submitted that the letter of
    21.09.2009 by Anglo offered the same “carry over terms” to MMTC as
    was offered to SAIL/RINL, as is clear from the letter itself. According
    to Mr. Kaul, the attempt of MMTC by its letter of 21.05.2009 was to
    perform the carry-over obligation at the adhoc mixed price, which
    was offered vide letter of 15.07.2009 as a onetime measure and as
    a goodwill gesture.
78. Mr. Kaul submitted that by letter of 21.09.2009, Anglo even agreed
    that MMTC could spread out its contractual performance over the
    next 3 years. The letter of MMTC of 27.11.2009, according to Mr.
    Kaul, purported to accept this offer provided, in parallel, Anglo
    also supplied additional (Adhoc) (coal) @ US$ 128/125 PMT. This
    could not be accommodated by Anglo resulting in the invocation of
    arbitration ultimately.
79. According to Mr. Kaul, MMTC kept asking for reduction of price and
    when Anglo refused to supply at the reduced price a defence was
    taken in the arbitration and in the Court proceedings that Anglo
    was incapable of supplying. According to Mr. Kaul, this submission
    was rejected both by the majority of the arbitral Tribunal and by the
    learned Single-Judge in Section 34 which was restored by this Court
    and a finding was recorded that the stand of MMTC that Anglo was
    incapable of supplying was found to be incorrect.
[2025] 11 S.C.R.                                                          367

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


80. Mr. Kaul invited our attention to the following findings of this Court
    to buttress his submission.
          “…….However, what is missed by Shri Rohatgi is the crucial
          fact that no price for the coal to be lifted was stated in any
          of the emails or letters exchanged during this period. This
          is in fact what the Majority Award adverts to and fills up
          by having recourse to the evidence given by Mr. Wilcox,
          stating that the ambiguity qua price was resolved by the
          fact that no coal was available for lifting at a price lower
          than the contractual price. The Majority Award found, relying
          upon Mr. Wilcox’s evidence, that the supplies that were
          sought to be made in August and September, 2009 were
          therefore, also in the nature of “mixed” supplies, i.e., coal
          at the contractual price, as well as coal at a much lower
          price. This is a finding of fact that cannot be characterised
          as perverse, as it is clear from the evidence led, the factual
          matrix of the setting of there being a slump in the market,
          in which the performance of the contract took place, as
          well as the ambiguity as to whether the correspondence
          referred to contractual price or “mixed” price, and thus, is
          a possible view to take.”

     MMTC’S CONTRACT WITH BMA – SAME PERIOD / SAME PRICE
     (APPROXIMATELY): -
81. Dealing with the aspect of the contracted price, namely, US$ 300 PMT,
    Mr. Kaul highlighted the fact that MMTC had a parallel contract with
    BHP Billiton Mitsubishi Alliance (BMA). Under the said contract, MMTC
    lifted five lakh tons of hard coking coal at US$ 300 PMT (Goonyella
    Middle Seam brand) and US$ 292.5 PMT (Torrington brand) and US$
    270 PMT (soft coking coal) and absolutely no grievance was made
    about the said contract with BMA. Quantities were lifted and price paid
    without demur, contends Mr. Kaul. Mr. Kaul further submitted that in
    fact the price paid to BMA was used as a defence when Anglo sought
    damages pointing to market price at US$ 126 PMT. The argument of
    MMTC before the arbitrators was that there was no scope for damages
    as the market price was what they had paid to BMA.
82. In response to the aspect of supply by BMA, learned ASG submitted
    that the said transaction was vastly different from the one entered
    with MMTC. The learned ASG submitted that
368                                                       [2025] 11 S.C.R.

                         Supreme Court Reports


       a.   The agreement entertained between BMA and MMTC was qua
            5,00,000 MT hard coking coal and 3,00,000 black water soft
            coking coal whereas Addendum 2 with Anglo by MMTC was
            only qua 4,66,000 hard coking coal.
       b.   BMA showed flexibility, commercial wisdom and prudence by
            providing coking coal at the rate agreed that is US$ 292.50
            for Torrington brand coking coal and US$ 270 Black water soft
            coking coal in a staggered manner which commenced from
            25.05.2009 till 23.06.2012.
       c.   BMA continued to supply the much needed hard coking coal
            to the tune of 3,21,410 MT for operating the NINL plan at the
            prevailing market rate that is US$ 122 PMT whereas Anglo
            adopted an extremely hard and uncompromising stand and
            refused to supply coking coal, except for one adhoc quantity of
            40,446 MT of coking coal at US$ 128.25 PMT on 05.08.2009.
       d.   The quality of coking coal supplied by BMA was different from
            the one supplied by Anglo.

       LONG CONTINUANCE OF MR. VED PRAKASH: -
83. Dealing with the contention of the learned ASG that Mr. Ved Prakash,
    being at the helm of affairs in different senior positions from 2008
    to 2020, Mr. Kaul submitted that the arbitration proceedings and the
    Court proceedings were hotly contested and that at no point was
    the issue of fraud and collusion and breach of fiduciary duty in the
    making of the contract ever raised. Mr. Kaul pointed out that Mr.
    Ved Prakash retired on 29.02.2020 when judgment was reserved in
    the Section 37-Appeal of MMTC. The judgment was pronounced on
    02.03.2020 in favour of MMTC and cited this to rebut the contention
    that Mr. Ved Prakash and team played a friendly match. Mr. Kaul
    further submitted that Anglo carried the matter further to this Court
    and by a detailed judgement this Court upheld the award and restored
    the findings of the learned Single Judge.
84. Mr. Kaul invited our attention to the following findings of this Court
    in judgment dated 17.12.2020.
            “3. “Under clause 2 of the LTA, which refers to “Price”,
            for subsequent Delivery Periods, including the “Fifth
            Delivery Period”, with which we are directly concerned,
[2025] 11 S.C.R.                                                         369

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


          it is undisputed that when read with Annexure I of the
          LTA and a letter dated 14.08.2008, setting out the terms
          of the Fifth Delivery Period, the price fixed at $300 per
          metric tonne .... “
          10. “Shri Kapil Sibal, learned Senior Advocate appearing on
          behalf of the Appellant, painstakingly took us through the
          LTA and the entire correspondence that ensued between
          the parties. He argued that all the findings given by the
          Majority Award were findings of fact, there having been
          little dispute on the construction of any term of the LTA; no
          dispute as to the contracted quantity of coal that was to be
          supplied in the Fifth Delivery Period, i.e. 466,000 metric
          tonnes: no dispute as to the price at which such coal was
          to be supplied, i.e., at the rate of $300 per metric tonne;
          and no dispute as to the quantity of coal that remained
          unlifted, i.e., 454,034 metric tonnes. The only issue before
          the Arbitral Tribunal was whether the Appellant was unable
          to supply the contracted quantity of coal at the contractual
          price, or whether the Respondent was unwilling to lift the
          quantity of coal at the contractual price, both being purely
          questions of fact as to the performance of contractual
          obligations stemming from the LTA.”
          14. “Shri Mukul Rohatgi, learned Senior Advocate
          appearing on behalf of the Respondent, supported the
          impugned judgment of the Division Bench ... According to
          him... the Respondent was in a position to take supplies,
          and did in fact demand that supplies of coal be made in
          accordance with the LTA.”
          17. “The first and most important point, therefore, to be
          noted is that this is a case in which there is a finding of
          fact by the Majority Award that the Appellant was able
          to supply the contracted quantity of coal for the Fifth
          Delivery Period, at the contractual price, and that it was
          the Respondent who was unwilling to lift the coal, owing
          to a slump in the market, the Respondent being conscious
          of the fact that mere commercial difficulty in performing a
          contract would not amount to frustration of the contract.
          It was for this reason that the Respondent decided, as an
370                                                        [2025] 11 S.C.R.

                         Supreme Court Reports


          afterthought, in reply to the Appellant’s legal notice dated
          04.03.2010, to attack the Appellant on the ground that it
          was the Appellant that was unable to supply the contracted
          quantity in the Fifth Delivery Period.”

       IMPACT OF THE FIRST INFORMATION REPORT: -
85. Mr. N. Venkataraman, learned ASG, drew attention to the complaints
    filed by MMTC which resulted in the registration of the First Information
    Report on 21.07.2025. The FIR is registered for offences under
    Section 120(B), IPC, and Sections 13(2) read with 13(1)(d) of the
    Prevention of Corruption Act, 1988 [PC Act]. The FIR is lodged by
    Shri Abhay Kumar, General Manager, MMTC, New Delhi. The FIR
    records that the information prima facie disclosed commission of
    offences punishable under the Sections referred to above. The FIR
    is registered against 13 named officials of MMTC, against the Anglo,
    against unknown officials of MMTC and Anglo and other unknown
    persons.
86. FIR refers to the background of the Long Term Agreement (LTA) dated
    07.03.2007 details about the 5th delivery period; the quantity agreed
    to be procured and the price of US$ 300 PMT, labeled as massively
    inflated. The FIR makes reference to Addendum 2 dated 20.11.2008
    having been entered into ignoring NINL letter of 16.10.2008 and
    attributes collusion between MMTC and Anglo officials for execution
    of Addendum 2 at a peak price when the Lehman Brothers collapse
    happened in September 2008.
87. The FIR further mentions that the SPCoD approved Addendum
    2, based on misleading inputs from Mr. Ved Prakash and Suresh
    Babu who failed to disclose the reduced demand and obtained
    approval under false pretences amounting to administrative frauds.
    A reference is also made to the letter of the same dated 20.11.2008
    seeking reduction of price. FIR refers in detail to the subsequent
    correspondence which, according to the complaint, discloses that
    officials did not assert the legal position of MMTC against Anglo. A
    particular reference is made to the use of phrase “we are not denying
    our obligation” in the letter of 25.09.2009 which, according to the
    complaint, weakened the MMTC’s defense in arbitration.
88. The FIR refers to an allegation about Anglo providing reduced price
    US$ 128 PMT and staggered deliveries to SAIL and RINL but refusal
[2025] 11 S.C.R.                                                          371

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     of the same to MMTC/NINL. It alleges that MMTC officials failed to
     invoke parity or renegotiation clauses, indicating deliberate inaction. It
     was stated in the FIR that all this suggested that there was exchange
     of unlawful and illegal consideration between the erring officials of
     MMTC and Anglo.
89. As will be noticed above, the gravamen of the allegations in the
    FIR is similar to the allegations set out in the proceedings before
    us which we have discussed in detail hereinabove.
90. Alluding to the First Information Report, Mr. Kaul submitted that
    the whole attempt to file a criminal complaint and get the FIR
    registered is a malicious attempt to wriggle out of the award and
    mere pendency of the FIR could not render the award inexecutable.
    Mr. Kaul submitted that MMTC filed a criminal complaint with the
    CBI on 02.09.2022 with the follow-up complaint on 23.11.2022. The
    CBI registered the preliminary enquiry on 09.01.2023. MMTC moved
    the CBI Court seeking a direction to register the FIR. The CBI Court
    passed a judgment on 09.05.2024 stating that it did not have power
    to direct the CBI to register the FIR. On 01.03.2025, MMTC filed a
    Revision Petition against CBI Court’s order before the High Court. In
    the meantime, the Executing Court allowed the Enforcement Petition
    and dismissed the MMTC’s objections on 09.05.2025 which is the
    order impugned herein.
91. During the pendency of this Special Leave Petition, and when
    arguments have been heard on 22.05.2025 and 23.05.2025 and
    when the matter was posted after the partial working days i.e., for
    24.07.2025, on 20.07.20205 MMTC filed the follow-up complaint
    with the CBI and the CBI, very promptly, registered the FIR on
    21.07.2025. Mr. Kaul submitted that all this was done when the
    matter was part-heard only to create some support to the allegations
    of fraud. Mr. Kaul made a grievance that no leave of the Court was
    taken and that MMTC had resorted to abuse of the legal process
    of the Court. Mr. Kaul submits that execution of the award cannot
    be kept in abeyance pending an FIR based on a self-serving and
    convenient criminal complaint.
92. The FIR has been filed for the offences punishable under Section
    120B, IPC, read with Section 13(2) and 13(1)(d) of the PC Act,
    against named public servants of MMTC the respondent company,
    unknown officials of MMTC and the respondent.
372                                                           [2025] 11 S.C.R.

                           Supreme Court Reports


93. Mr. Kaul, learned Senior Counsel, submitted that had there been
    criminal conspiracy/fraud, the common course of human conduct of
    recalcitrant parties would be to lift the coal at the agreed price, pay
    the amount, and share the booty. Instead, here was a case where
    not only was the contracted quantity not lifted except to the extent of
    11,966 MT, leaving a huge amount of contracted quantity un-lifted,
    Anglo had to litigate for the last 15 years and have still not seen
    the fruits of the award. To say that there was collusion, submits Mr.
    Kaul, would be completely unjustified.

       ANALYSIS
94. We have set out hereinabove the contentions of both the parties
    to enable us to examine the issue whether at least prima facie the
    case of breach of fiduciary duty has been established by MMTC
    in this appeal. From the analysis of the pros and cons of the case
    advanced by both the parties, the following undisputed facts/irresistible
    deductions emerge:-
       a.   That there was a Long Term Agreement (LTA) between the
            parties on 07.03.2007 which for the first three delivery periods
            clearly prescribed the quantity of 4,66,000 MT as the yearly base
            quantity of which 4,64,374 MT was fixed for the first delivery
            period, 3,82,769 MT was fixed for the 2nd delivery and 4,66,000
            was fixed for 3rd delivery period.
       b.   In clause 2 of the LTA, the price for the 1st and 2nd delivery period
            was prescribed. For the subsequent delivery period, the price
            was fixed in accordance with para 1 of the General Conditions
            of the Agreement (GCA). Para 1.1 of GCA prescribed that the
            price was to be mutually discussed and settled at the same
            price as settled between Anglo and SAIL/RINL.
       c.   Under clause 1.3 of the LTA, the option to extend the duration
            of the agreement was to be exercised by 31.01.2007. It has
            not been disputed before us that a MoU dated 30.01.2007 was
            executed between MMTC and Anglo. Under the MoU read with
            Clause 1.3 of LTA, supply of a quantity of 4,66,000 MT at a price
            to be finalized by the Empowered Joint Committee for SAIL/
            RINL was agreed upon. The contract was extended further for
            2 years, covering the 4th and 5th delivery period.
[2025] 11 S.C.R.                                                         373

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     d.   MoU also indicates that based on correspondence and even
          before the execution of the Long Term Agreement, the first, 2nd
          and part of the 3rd delivery period was even completed. So parties
          had, based on correspondence, discharged their obligations.
     e.   It is not disputed that the 4 delivery periods namely the first,
          second, third and fourth passed on peacefully with no dispute
          between the parties.
     f.   The 5th delivery period was to begin on 01.07.2008. However,
          the 4th delivery period under the 3 month extension clause stood
          extended till 30.09.2008 and in fact was further extended for
          a month to 30.10.2008.
     g.   It is also not disputed that the Empowered Joint Committee on
          8th and 9th May 2008, did approve a price of US$ 300 PMT for
          supply for coal to SAIL/RINL. This is important because the price
          fixed for SAIL/RINL is linked to the price that MMTC was to pay.
     h.   It is also not disputed that with the last shipment of the 4th
          delivery period, 2366 MT pertaining to the 5th delivery period
          was also shipped on 30.10.2010.
     i.   The EJC, fixed the price for the 5th delivery period on 8th and
          9th May 2008. The Lehman brothers fiasco happened in mid-
          September 2008.
     j.   The internal note for the finalization of terms for the 5th delivery
          period is of 03.06.2008 which expressed the concern that the
          spot price for coal was US$ 400 PMT FOB.
     k.   The Addendum signed on 20.11.2008 followed after the quantity
          of 2366 MT as part of the 5th delivery period had already been
          shipped. The explanation of the learned ASG is that this was
          only to save dead freight.
     l.   SPCoD approval Minutes of 06.10.2008 was also signed by Mr.
          H.S. Mann whose initial note of April 2008 was one of the main
          points urged by MMTC before us. The approval also noticed
          the recent fall in prices of pig iron and steel products and did
          in fact suggest exploring possibility of reduction in quantity.
     m.   The explanation of Anglo that NINL had no say in the quantity
          since the quantity was fixed in the LTA and MoU and that in fact,
          NINL’s approval was only for the specification is a plausible one.
374                                                          [2025] 11 S.C.R.

                           Supreme Court Reports


       n.   That MMTC purchased coal from BMA at US$ 300/292 PMT
            which had not been disputed and in fact the argument in the
            proceedings to set aside the award was based on the price paid
            to BMA to contend that no damages occurred to Anglo. Further,
            the stand of the learned ASG insofar as the supply by BMA is
            concerned as dealt with above shows that there was indeed
            supply by BMA at the rate of US$ 292 PMT and US$ 270 PMT,
            though the period of carryover offered may have been different.
       o.   The exercise of writing a letter on 20.11.2008, namely, the
            same day as the Addendum No.2 has been explained as an
            attempt by MMTC to renegotiate the price. Per se on this basis
            and without anything more, nothing sinister could be imputed.
            There has been no convincing explanation from the appellant
            to the argument of Anglo that the common course of human
            conduct of conspiring parties would be to lift the coal at the
            agreed price, pay the amount and share the booty, instead of
            litigating for 15 years.
       p.   The subsequent correspondence and the context in which
            they were written viewed in the background of the findings of
            this Court do not indicate that it was a friendly fight intended
            to commit certain admissions in the correspondence. On the
            concept of carryover also, the explanation by Anglo that there
            was no discrimination between the contract with MMTC and
            contract with SAIL and that a carryover offered in the respective
            contracts have to be viewed in the background of the “delivery
            periods in question” of the respective contracts is a plausible
            explanation borne out from the records.
       q.   A First Information Report by itself is only a document to set in
            motion a legal process. It is the version of one party and by itself
            we are not able to, for the reasons set out above, declare that
            the award upheld by this Court should be rendered inexecutable.
       r.   The argument that Mr. Ved Parkash orchestrated the arbitration
            and the litigation before the High Court of Delhi and facilitated
            success for Anglo is also not convincing because when Mr. Ved
            Prakash was at the helm, the Section 37 proceedings were
            prosecuted by MMTC successfully. While Ved Prakash retired
            on 29.02.2020 the Delhi High Court pronounced its judgement
            in favour of MMTC on 02.03.2020.
[2025] 11 S.C.R.                                                      375

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


     s.   Ultimately, the arbitration was fought over a period of 2 years
          before the arbitrators and the matter was fought in the Delhi
          High Court and this Court for over a period of 6 years till this
          court restored the award and set aside the judgment of the
          Division Bench.
     t.   The only two arguments raised before the arbitrators and Court
          were:-
          i.    Anglo was incapable of supplying the agreed quantity.
          ii.   In any event, there was no loss in the form of damages
                as the market price was in the range of US$ 300 PMT as
                is evident from the supply done by BMA.

     CONCLUSION: -
95. In the light of the above analysis, we are not able to conclude, on the
    material furnished before us, that the Senior Managerial personnel
    involved at the helm in MMTC during the relevant period acted in a
    manner as no reasonable personnel/director in the circumstances
    would have acted. We are also not able to conclude on the material
    furnished that the decisions taken were not within the range of
    reasonableness or that the course adopted by them was not one,
    a reasonably competent personnel/director would adopt. Applying
    the business judgment rule, the course adopted by them cannot
    be said to be one to which a court of law would not defer to. The
    appellants have not been able to even prima facie demonstrate that
    circumstances exist to conclude that the personnel of MMTC did not
    act in the best interest of the company.
96. The appeal challenges, in the prayer clause, the judgment dismissing
    the objections in OMP (ENF.) (COMM.) 19 of 2018. Though in the
    prayer clause, there is no challenge to dismissal of the application
    under Order XXI Rule 29 filed in EX/application (OS) 1806 of 2024,
    in Para 1 of the civil appeal the appellants have indicated that they
    are aggrieved by the said order also. Order XXI Rule 29 provides for
    stay of execution pending suit between decree holder and judgment
    debtor. We were, however, told that the suit filed itself now stands
    rejected under Order VII Rule 11 but a regular first appeal in RFA 28
    of 2025 has been filed. Hence, an occasion for considering an
    Order XXI Rule 29 Application does not arise.
376                                                             [2025] 11 S.C.R.

                            Supreme Court Reports


97. We are dealing with an objection filed under Section 47 claiming
    that the award as upheld by this Court is inexecutable. As held by
    this Court in Electrosteel (Supra) the jurisdiction lies in a narrow
    compass. It is the mandate of this Court that the object of Section 47
    is to prevent unwarranted litigation and dispose of all objections
    as expeditiously as possible. This Court has warned that there is
    a steady rise of proceedings akin to a retrial which causes failure
    of realization of the fruits of a decree, unless prima facie grounds
    are made out entertaining objections under Section 47 would be an
    abuse of process.
98. An objection petition under Section 47 should not invariably be
    treated as a commencement of a new trial. In Rahul S. Shah Vs
    Jinendra Kumar Gandhi and Ors.,14 this Court had the following
    telling observations to make.
             “24. In respect of execution of a decree, Section 47 CPC
             contemplates adjudication of limited nature of issues
             relating to execution i.e. discharge or satisfaction of the
             decree and is aligned with the consequential provisions of
             Order 21 CPC. Section 47 is intended to prevent multiplicity
             of suits. It simply lays down the procedure and the form
             whereby the court reaches a decision. For the applicability
             of the section, two essential requisites have to be kept
             in mind. Firstly, the question must be the one arising
             between the parties and secondly, the dispute relates
             to the execution, discharge or satisfaction of the decree.
             Thus, the objective of Section 47 is to prevent unwanted
             litigation and dispose of all objections as expeditiously
             as possible.
             25. These provisions contemplate that for execution of
             decrees, executing court must not go beyond the decree.
             However, there is steady rise of proceedings akin to a retrial
             at the time of execution causing failure of realisation of fruits
             of decree and relief which the party seeks from the courts
             despite there being a decree in their favour. Experience
             has shown that various objections are filed before the
             executing court and the decree-holder is deprived of the


14   (2021) 6 SCC 418
[2025] 11 S.C.R.                                                        377

   MMTC Limited v. Anglo American Metallurgical Coal Pvt. Limited


          fruits of the litigation and the judgment-debtor, in abuse
          of process of law, is allowed to benefit from the subject-
          matter which he is otherwise not entitled to.
          26. The general practice prevailing in the subordinate
          courts is that invariably in all execution applications, the
          courts first issue show-cause notice asking the judgment-
          debtor as to why the decree should not be executed as is
          given under Order 21 Rule 22 for certain class of cases.
          However, this is often misconstrued as the beginning of
          a new trial. For example, the judgment-debtor sometimes
          misuses the provisions of Order 21 Rule 2 and Order 21
          Rule 11 to set up an oral plea, which invariably leaves no
          option with the court but to record oral evidence which
          may be frivolous. This drags the execution proceedings
          indefinitely.
          27. This is antithesis to the scheme of the Civil Procedure
          Code, which stipulates that in civil suit, all questions and
          issues that may arise, must be decided in one and the
          same trial. Order 1 and Order 2 which relate to parties
          to suits and frame of suits with the object of avoiding
          multiplicity of proceedings, provides for joinder of parties
          and joinder of cause of action so that common questions
          of law and facts could be decided at one go.”

     POSTSCRIPT :-
99. Before we part, a small postscript. Whether in Government, Public
    Sector Corporations or even in the private sector, the driving force
    of the entity are the persons who administer them. A certain play
    in the joints is inevitable for their day-to-day functioning. If they are
    shackled with the fear that, their decisions taken for the day-to-
    day administration, could years later with the benefit of hindsight,
    be viewed with a jaundiced eye, it will create a chilling effect on
    them. A tendency to play it safe will set in. Decision making will
    be avoided. Policy paralysis will descend. All this will in the long
    run prove detrimental not just to that entity but to the nation itself.
    We are not to be understood to be condoning decisions taken for
    improper purposes or extraneous considerations. All that we are at
    pains to drive home is that great caution and circumspection have
    to be exercised before such allegations are brought forward and
378                                                         [2025] 11 S.C.R.

                               Supreme Court Reports


       adequate proof must exist to back them. Otherwise for fear that
       carefully built reputations could be casually tarnished, best of talent
       will not be forthcoming, especially for government and public sector
       corporations.
100. In view of what is stated hereinabove, we find no merit in the
     objections filed by MMTC under Section 47 of the CPC. There are
     no good grounds to entertain the same. The appeal is dismissed.
     No order as to costs.

       Result of the case: Appeal dismissed.




       †
           Headnotes prepared by: Nidhi Jain


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Prima facie case of breach of fiduciary duty"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

MMTC LIMITED versus ANGLO AMERICAN METALLURGICAL COAL PVT. LIMITED — 2025 INSC 1279 - Legal Desk AI