Created byFuzzy Cloud

Supreme Court of India

RAMAYANA ISPAT PVT. LTD. AND ANR.versusSTATE OF RAJASTHAN & ORS.

Citation
2025 INSC 424
Decided
31 March 2025
Disposal
Dismissed

Holding

RERC is constitutionally empowered to regulate intra‑state open access, and the 2016 Regulations, including the penalty regime, 24‑hour notice requirement, and Regulation 21, are valid, reasonable, and do not foreclose the right to open access.

Summary

The appellants, large industrial consumers and captive power generators, challenged the Rajasthan Electricity Regulatory Commission's (RERC) 2016 Open Access Regulations, alleging that they exceeded RERC's jurisdiction over inter‑state open access, imposed unreasonable penalties for drawal variations, required a 24‑hour advance notice that barred urgent procurement, and discriminated against captive generators. The Supreme Court examined the statutory scheme of the Electricity Act, 2003, focusing on sections that allocate powers between the Central Electricity Regulatory Commission (CERC) and State Commissions. It held that RERC retains authority to regulate intra‑state aspects of open access even when electricity originates from another state, and that the regulations' scheduling, penalty, and notice requirements are reasonable measures to ensure grid stability. The Court found no violation of the right to open access, nor any arbitrary or discriminatory treatment of captive generators. Consequently, the Court upheld the validity of the 2016 Regulations and dismissed the appeals.

Issues considered

  • Whether the Rajasthan Electricity Regulatory Commission (RERC) has jurisdiction to regulate inter‑state open access under the Electricity Act, 2003.
  • Whether the imposition of penalties for variations in drawal from contracted demand amounts to an unreasonable restriction on the right to open access under Section 42 of the Act.
  • Whether Regulation 26(7) of the RERC (Terms and Conditions for Open Access) Regulations, 2016, requiring a 24‑hour advance notice, is ultra vires and creates an artificial barrier to open access.
  • Whether Regulation 21 of the 2016 Regulations is arbitrary and discriminatory, discouraging captive power generation.
  • Whether the appellants’ right to open access is foreclosed by the Regulations of 2016.

Legislation cited

Subjects

Rajasthan Electricity Regulatory Commission (RERC)inter‑state open accesspenalties for drawal variationsSection 42 of Electricity Act, 2003Regulation 26(7) advance noticeRegulation 21 captive generationintra‑state regulationgrid stabilityopen access rights

Judgment

                 [2025] 4 S.C.R. 436 : 2025 INSC 424

                  Ramayana Ispat Pvt. Ltd. and Anr.
                                 v.
                     State of Rajasthan & Ors.
                       (Civil Appeal No. 7964 of 2019)
                                 01 April 2025
            [Vikram Nath* and Prasanna B. Varale, JJ.]


                           Issue for Consideration
       i) Whether the Rajasthan Electricity Regulatory Commission
       (RERC) has the jurisdiction to regulate inter-state open access
       under the Electricity Act, 2003; ii) Whether the imposition of
       penalties for variations in drawal from contracted demand amounts
       to an unreasonable restriction on the right to open access under
       Section 42 of the Act of 2003; iii) Whether Regulation 26(7)
       of Rajasthan Electricity Regulatory Commission (Terms and
       Conditions for Open Access) Regulations, 2016 is ultra vires
       for requiring an advance notice of 24 hours a day prior, thereby
       preventing urgent procurement and creating an artificial barrier
       to open access as protected by the Act of 2003; iv) Whether
       Regulation 21 is arbitrary and discriminatory, thereby discouraging
       captive power generation by creating unreasonable distinction
       between captive power plants (CPPs) and state distribution
       companies; v) Whether the appellants’ right to open access is
       foreclosed by the Regulations of 2016.

                                  Headnotes†
       Electricity Act, 2003 – Rajasthan Electricity Regulatory
       Commission (Terms and Conditions for Open Access)
       Regulations, 2016 – Whether the Rajasthan Electricity
       Regulatory Commission (RERC) has the jurisdiction to regulate
       inter-state open access under the Electricity Act, 2003:
       Held: 1. s.79(1)(c) of the Act of 2003, defines the regulatory
       authority of the CERC over inter-state transmission of electricity –
       However, this provision does not strip State Commissions, including
       RERC, of their jurisdiction over intra-state aspects of open
       access – s.42(2) of the Act of 2003 expressly empowers State
       Commissions to regulate open access within their respective states,

* Author
[2025] 4 S.C.R.                                                                437

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     ensuring fair and non-discriminatory access to transmission and
     distribution networks within the state – Further, s.42(3) of the Act
     of 2003 provides that whenever a consumer, with premises within
     the area of supply of a distribution licensee, requires supply of
     electricity from a generating company other than such distribution
     licensee, such transmission and supply shall be in accordance
     with the regulations made by the State Commission. [Para 45]
     2. The key determinant is not the source of power but its delivery,
     end-user, and consumption within Rajasthan's intra-state grid – The
     Act of 2003 provides a framework for demarcating responsibilities
     between CERC and State Commissions, ensuring that intra-state
     aspects of electricity regulation remain within the purview of State
     Commissions – The claim that only CERC has the authority to
     regulate inter-state open access cannot be accepted in light of
     the legislative intent behind the Act of 2003 – Therefore, RERC
     retains jurisdiction over intra-state transactions even if the power
     originates from another state. [Para 47]
     3. Further, s.2(47) of the Act of 2003 defines open access as non-
     discriminatory access to transmission and distribution systems,
     encompassing both interstate and intra-state transactions – The
     respondents argue that the statute does not differentiate between
     them for regulatory purposes, meaning that State Commissions
     naturally retain authority over open access within their jurisdictions –
     This interpretation aligns with s.42, which explicitly grants State
     Commissions the power to regulate open access for consumers
     in their states. [Para 48]
     4. s.181 of the Act of 2003 empowers State Commissions to frame
     regulations necessary for implementing the provisions of the Act of
     2003 – By granting State Commissions the authority to introduce
     and regulate open access, the legislature has clearly vested
     regulatory oversight with RERC in Rajasthan – The omission of
     any reference to CERC’s jurisdiction over open access consumers
     in s.42 of the Act is indicative of the legislature’s intent to keep
     such matters under State Commissions’ oversight, ensuring that
     electricity consumers and distribution networks within a state remain
     subject to state-level regulation. [Para 49]
     5. Thus, the respondents’ argument is well-founded in statutory
     provisions, legislative intent, and the structural framework of the
     Act of 2003 – RERC’s authority to regulate intra-state aspects of
     open access transactions, even when electricity is sourced from
438                                                                  [2025] 4 S.C.R.

                         Digital Supreme Court Reports


       another state, aligns with the Act’s objectives and ensures effective
       regulatory oversight. [Para 50]

       Electricity Act, 2003 – Rajasthan Electricity Regulatory
       Commission (Terms and Conditions for Open Access)
       Regulations, 2016 – Whether the imposition of penalties for
       variations in drawal from contracted demand amounts to an
       unreasonable restriction on the right to open access u/s.42
       of the Act of 2003:
       Held: The electricity grid operates on principles of frequency
       stability and demand-supply balance – Any deviation from scheduled
       drawal or injection can lead to grid instability, potentially affecting all
       consumers – The impugned regulations, therefore, serve a critical
       function in preventing such disruptions by enforcing discipline
       among generators and consumers alike – The penalties imposed
       are a deterrent mechanism to prevent strategic gaming of the
       system and to ensure that all stakeholders adhere to scheduling
       norms – The State Commission’s role is to balance the rights of
       individual market participants with the broader objective of ensuring
       an efficient, reliable, and stable power supply to all consumers in
       the State. [Para 54]

       Electricity Act, 2003 – Rajasthan Electricity Regulatory
       Commission (Terms and Conditions for Open Access)
       Regulations, 2016 – Whether Regulation 26(7) of Rajasthan
       Electricity Regulatory Commission (Terms and Conditions for
       Open Access) Regulations, 2016 is ultra vires for requiring an
       advance notice of 24 hours a day prior, thereby preventing
       urgent procurement and creating an artificial barrier to open
       access as protected by the Act of 2003:
       Held: 1. The requirement of prior notice is a reasonable procedural
       safeguard that aligns with the objectives of the Act of 2003,
       particularly those laid out in Section 42, which envisages a
       structured approach to open access – The 24-hour notice period
       ensures that both transmission and distribution licensees, as well
       as load despatch centres, have adequate time to adjust their
       schedules and prevent system disturbances – Moreover, it prevents
       misuse by entities that may attempt to take advantage of realtime
       price fluctuations, thereby engaging in speculative trading rather
       than genuine demand based procurement – Further, the option
       of purchasing power from the real-time market and day-ahead
[2025] 4 S.C.R.                                                             439

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     market in need of urgent procurement is always available, and is
     not prevented by the impugned regulations. [Para 57]
     2. Furthermore, the regulation does not create an insurmountable
     barrier to open access but rather seeks to bring order and
     predictability to its implementation – The requirement is uniformly
     applicable to all consumers, ensuring that no undue advantage
     is given to any particular category – Considering the technical
     and regulatory imperatives involved, the 24-hour advance notice
     condition under Regulation 26(7) cannot be considered ultra vires,
     as it falls within the regulatory domain of the State Commission
     to establish fair, transparent, and non-disruptive mechanisms for
     open access. [Para 58]

     Electricity Act, 2003 – Rajasthan Electricity Regulatory
     Commission (Terms and Conditions for Open Access)
     Regulations, 2016 – Whether Regulation 21 is arbitrary and
     discriminatory, thereby discouraging captive power generation
     by creating unreasonable distinction between captive power
     plants (CPPs) and state distribution companies:
     Held: 1. The distinction between captive power generators and state
     DISCOMs is not arbitrary but arises from the structural differences
     in their roles and obligations – While captive generators primarily
     generate electricity for self-consumption, distribution companies
     serve a wider consumer base, requiring them to adhere to broader
     regulatory commitments, including universal supply obligations – As
     such, differential treatment based on the nature of their functions
     is legally justified and does not amount to unfair discrimination –
     Moreover, Regulation 21 does not impose undue restrictions on
     captive generators but ensures that their operations align with
     grid discipline, preventing any adverse impact on the larger power
     ecosystem. [Para 61]
     2. Additionally, the principle of non-discrimination under the Act
     of 2003 does not mandate identical treatment for all entities but
     rather requires a rational basis for any differentiation – In this
     case, the regulatory conditions imposed on captive generators
     are aimed at ensuring a level playing field and preventing misuse
     of open access provisions – The regulatory framework ensures
     that captive generators contribute fairly to system stability without
     imposing additional burdens on distribution licensees and other
     grid participants – Thus, Regulation 21 is neither arbitrary nor
440                                                                 [2025] 4 S.C.R.

                         Digital Supreme Court Reports


       discriminatory but rather a necessary and proportionate measure
       to balance the interests of various stakeholders in the electricity
       sector. [Para 62]

       Electricity Act, 2003 – Rajasthan Electricity Regulatory
       Commission (Terms and Conditions for Open Access)
       Regulations, 2016 – Whether the appellants’ right to open
       access is foreclosed by the Regulations of 2016:
       Held: 1. A careful analysis of the Regulations of 2016 indicates that
       they primarily aim at maintaining the reliability of the electricity grid,
       ensuring fair pricing, and preventing speculative misuse of open
       access provisions – The requirement of advance notice for short-term
       open access, penalties for deviations from contracted demand, and
       specific conditions for captive power generators are all designed
       to create a structured and predictable electricity market – These
       provisions do not prevent eligible consumers from availing open
       access but instead ensure that they do so within a framework that
       safeguards the interests of all stakeholders, including distribution
       licensees and other consumers – Moreover, Section 181 of the
       Act of 2003 empowers State Commissions to frame regulations
       necessary for implementing statutory provisions, thereby validating
       the regulatory measures introduced by RERC. [Para 64]
       2. Furthermore, the Act of 2003, envisages a balance between the
       rights of open access consumers and the operational concerns of
       the power sector – The Regulations of 2016, while imposing certain
       conditions, do not outright deny open access but ensure that its
       implementation is equitable and does not jeopardize grid discipline –
       Open access remains available to consumers who comply with
       regulatory prerequisites, including scheduling obligations and
       financial commitments – Thus, the appellants’ assertion that their
       right to open access is foreclosed is misplaced – The Regulations
       of 2016 are consistent with the legislative intent of the Act of 2003,
       ensuring that open access is exercised in a manner that does
       not compromise system stability, fairness, or economic viability –
       Therefore, the regulatory framework does not foreclose open
       access but rather operationalizes it within reasonable constraints
       essential for sustaining the electricity sector. [Para 65]

                                  Case Law Cited
       Energy Watchdog v. Central Electricity Regulatory Commission
       [2017] 3 SCR 153 : (2017) 14 SCC 80; Reliance Infrastructure v.
[2025] 4 S.C.R.                                                          441

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     State of Maharashtra [2019] 1 SCR 886 : (2019) 3 SCC 352;
     Hindustan Zinc v. RERC [2015] 7 SCR 1104 : (2015) 12 SCC
     611 – referred to.

                               List of Acts
     Electricity Act, 2003; Rajasthan Electricity Regulatory Commission
     (Terms and Conditions for Open Access) Regulations, 2016.

                            List of Keywords
     Rajasthan Electricity Regulatory Commission (RERC); Inter-state
     open access; Imposition of penalties; Variations in drawal from
     contracted demand amounts; Section 42 of Electricity Act, 2003;
     Regulation 26(7) of Rajasthan Electricity Regulatory Commission
     (Terms and Conditions for Open Access) Regulations, 2016;
     Advance notice of 24 hours; Regulation 21 of Rajasthan
     Electricity Regulatory Commission (Terms and Conditions for
     Open Access) Regulations, 2016; Jurisdiction to regulate inter-
     state open access; Intra-state aspects of electricity regulation;
     Right to open access; Consumer; Distribution licensee; Inter-
     State transmission system; Captive generation; State Load
     Despatch Centre; Duties of distribution licensee and open
     access; Functions of Central Commission; Functions of State
     Commission; Powers of Central Commission to make regulations;
     Powers of State Commissions to make regulations; Unscheduled
     Interchange Pricing.

                           Case Arising From
     CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7964 of 2019
     From the Judgment and Order dated 06.09.2016 of the High Court
     of Rajasthan at Jaipur in DBCWP No. 4402 of 2016
     With
     C.A Nos. 7966 and 7965 of 2019

                        Appearances for Parties
     Advs. for the Appellants:
     Manu Seshadri, Sahil Manganani, Ms. Aakriti Gupta, Siddhant
     Singh, Nikunj Dayal, Kumar Mihir, Athul Joseph, Gunjan Sharma.
442                                                          [2025] 4 S.C.R.

                            Digital Supreme Court Reports


       Advs. for the Respondents:
       Shiv Mangal Sharma, A.A.G., Milind Kumar, Zoheb Hossain,
       Dr. Rupesh Singh, Guru Prasad Singh, Anshul Suri, Satya Veer
       Singh, Ms. Pratibha Jain, Ms. Christi Jain, Pallav Mongia, Anubhav
       Mishra, Amritesh Krishna.

                      Judgment / Order of the Supreme Court

                                     Judgment

       Vikram Nath, J.

1.     The present appeals challenge two separate orders passed by
       the High Court of Rajasthan—one by the Jodhpur Bench dated
       29.08.2016 and the other by the Jaipur Bench dated 06.09.2016.
       The appeals arise from challenges to the validity of the Rajasthan
       Electricity Regulatory Commission (Terms and Conditions for Open
       Access) Regulations, 20161 framed by the Rajasthan Electricity
       Regulatory Commission2 in the exercise of its powers under Section
       42 read with Section 181 of the Electricity Act, 2003.3 The primary
       grievance of the writ petitioners, appellants herein, before the High
       Court, and now the appellants before this Court, relates to the
       restrictions and conditions imposed by the Regulations of 2016 on
       the exercise of open access for captive power plants4 and other
       large consumers of electricity.
2.     The brief background of the facts giving rise to the challenge before
       us are that the writ petitioners before the High Court are engaged
       in industrial production and have substantial power consumption
       requirements. The facts, as taken by the High Court from one of
       the writ petitions filed by Hindustan Zinc Limited, respondent No.6 in
       Civil Appeal No. 7966 of 2019, for convenience, are that Hindustan
       Zinc Limited is a public limited company incorporated under the
       Companies Act, 1956, and is engaged in the business of mining,
       smelting, and production of non-ferrous metals, including lead and
       zinc. The company operates multiple units at Chanderia, Dariba,


1    Regulations of 2016.
2    RERC.
3    Act of 2003.
4    CPPs.
[2025] 4 S.C.R.                                                        443

      Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


      and Zawar, which are supported by CPPs. In addition to captive
      power generation, the company also has agreements with Ajmer
      Vidhyut Vitran Nigam Limited (respondent No.3 in Civil Appeal No.
      7964 of 2019, respondent No.2 in Civil Appeal No. 7965 of 2019,
      and respondent No.3 in Civil Appeal no. 7966 of 2019) for the supply
      of power to meet its contractual demand. Under these agreements,
      Hindustan Zinc Limited is entitled to draw electricity up to 70 MW
      from the distribution licensee at its Dariba Zinc Smelter Unit at any
      time, as per its operational requirements.
3.    Prior to the introduction of the Regulations of 2016, the appellants
      were availing open access under the Rajasthan Electricity Regulatory
      Commission (Terms and Conditions for Open Access) Regulations,
      2004,5 which permitted them to draw power from both, their captive
      generation and open access sources, without any reduction in the
      contracted demand from the distribution licensee. The open access
      facility under the Regulations of 2004 allowed the appellants to
      schedule their power requirements on a day-ahead basis for each
      15-minute block, with the flexibility to meet shortfalls through their
      contracted demand from the distribution licensee.
4.    RERC issued a draft of the proposed Regulations of 2016 through
      a public notice dated 06.07.2015 and invited comments and
      suggestions. Hindustan Zinc Limited, along with other stakeholders,
      submitted detailed objections, highlighting that certain provisions of
      the draft regulations were inconsistent with the objectives of the Act
      of 2003 and the principle of promoting open access. The Commission
      notified the Regulations of 2016 on 27.01.2016.
5.    The key change introduced by the Regulations of 2016 was the
      imposition of limitations on the simultaneous drawal of power
      through open access and contracted demand from the distribution
      licensee. Under the new regime, if a consumer opted to procure
      power through open access, the contracted demand from the
      distribution licensee would be reduced by the quantum of power
      scheduled through open access. Additionally, the Regulations of
      2016 imposed penalties for over-drawal and under-drawal from the
      contracted demand.



5    Regulations of 2004.
444                                                         [2025] 4 S.C.R.

                      Digital Supreme Court Reports


6.     The appellants before the Jodhpur Bench of the High Court challenged
       several specific provisions of the Regulations of 2016 on the ground
       that they were arbitrary, unreasonable, and contrary to the statutory
       scheme of the Act of 2003. The primary contention was that the
       Regulations of 2016 sought to undermine the statutory right of open
       access guaranteed under Section 42 of the Act of 2003 by imposing
       unreasonable restrictions on the simultaneous use of open access
       and contracted demand. The appellants further contended that the
       imposition of penalties for variations in drawal, even when caused
       by unforeseen breakdowns or operational exigencies, was unjust
       and discriminatory. The appellants argued that the Regulations of
       2016, by reducing the contracted demand by the quantum of power
       scheduled through open access, effectively penalized consumers for
       exercising their statutory right to open access. It was submitted that
       the statutory framework under the Act of 2003 envisaged open access
       as a means to promote competition and efficiency in the electricity
       market, and the Regulations of 2016 were contrary to this objective.
7.     The appellants before the Jaipur Bench of the High Court were inter-
       state consumers, unlike the appellants before the Jodhpur Bench, who
       were intra-state consumers drawing power from their captive plants
       within the State of Rajasthan. The challenge before the Jaipur Bench
       specifically related to Regulations 26(6) and 26(7) of the Regulations
       of 2016, which the appellants contended imposed restrictions on
       inter-state open access, thereby exceeding the Commission’s
       jurisdiction under the Act of 2003. The appellants argued that the
       Regulations of 2016 amounted to an extra-territorial application
       of the RERC’s regulatory power, which was beyond the statutory
       mandate conferred under the Act of 2003. It was contended that the
       Act of 2003 empowered the State Commissions to regulate intra-
       state open access but not inter-state open access, which falls within
       the jurisdiction of the Central Electricity Regulatory Commission.6
       Therefore, the appellants contended that the impugned regulations
       were ultra vires the Act of 2003 and liable to be struck down.
8.     The Jodhpur Bench in the judgment dated 29.08.2016 upheld the
       validity of the Regulations of 2016, holding that the Commission
       was empowered to regulate open access to ensure grid stability and


6    CERC
[2025] 4 S.C.R.                                                         445

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     efficient load distribution. The High Court observed that the impugned
     regulations have been notified with the objective to ensure that the
     consumers do not indulge in any gaming activities on the grid, and
     thus the rationale behind the Regulations of 2016 is to further the
     objectives of the Act of 2003 while ensuring that the interests of
     consumers as well as distribution licensees are balanced. Further,
     rejecting the appellants’ claim that the regulations are violative of
     their rights protected under Part III of the Constitution of India,
     the High Court observed that they had failed to establish that the
     Regulations of 2016 violate their Fundamental Rights, or the RERC
     lacked competence to frame these regulations or that they are
     manifestly arbitrary or unreasonable; and thus merely because the
     Regulations of 2016 are claimed to cause certain inconvenience or
     hardship to the appellants, they cannot be held to be illegal or ultra
     vires the Act of 2003.
9.   The Jaipur Bench also upheld the validity of the Regulations of
     2016 and dismissed the writ petition of the appellants herein in C.A.
     7964 of 2019 herein, holding that their challenge and the issues in
     their petition before the High Court were squarely covered by the
     judgment of the Jodhpur Bench.
10. The appellants in all the three appeals before us are challenging the
    findings of the High Court on the grounds that the Jodhpur Bench failed
    to appreciate that the Regulations of 2016 are discriminatory against
    the CPPs as they impose unreasonable and excessive restrictions
    upon them for availing open access, contrary to the objectives of
    the Act of 2003. Further, the appellants challenging the order of the
    Jaipur Bench further contend that the Bench failed to consider that
    RERC lacked jurisdiction to regulate inter-state open access, which
    falls within the exclusive domain of the CERC under the Act of 2003.
11. The issues for consideration before this Court are as follows:
     i.     Whether the RERC has the jurisdiction to regulate inter-state
            open access under the Act of 2003?
     ii.    Whether the imposition of penalties for variations in drawal from
            contracted demand amounts to an unreasonable restriction on
            the right to open access under Section 42 of the Act of 2003?
     iii.   Whether Regulation 26(7) is ultra vires for requiring an advance
            notice of 24 hours a day prior, thereby preventing urgent
446                                                          [2025] 4 S.C.R.

                        Digital Supreme Court Reports


             procurement and creating an artificial barrier to open access
             as protected by the Act of 2003?
       iv.   Whether Regulation 21 is arbitrary and discriminatory, thereby
             discouraging captive power generation by creating unreasonable
             distinction between CPPs and state distribution companies?
       v.    Whether the appellants’ right to open access is foreclosed by
             the Regulations of 2016?
12. We have heard the learned counsels for the parties at great length.

       ARGUMENTS OF THE APPELLANTS
13. The appellants have raised a comprehensive challenge to the validity
    of the Regulations of 2016. The challenge is primarily directed against
    regulations concerning the levy of additional surcharge, scheduling
    requirement, and penalties for deviations. In Civil Appeal No. 7964 of
    2019, appellants have also contested the jurisdiction of the RERC to
    regulate inter-state open access, arguing that such jurisdiction falls
    exclusively within the domain of the CERC under the Act of 2003.
14. The appellants in Civil Appeal No. 7964 of 2019 have contended
    that the RERC lacked jurisdiction to regulate inter-state open access
    through Regulations of 2016. The appellants submitted that under the
    scheme of the Act of 2003, the authority to regulate inter-state open
    access lies exclusively with the CERC. It is the case of the appellants
    challenging the jurisdiction of the RERC with respect to regulating
    inter-state open access that the Regulation 26(7) essentially forecloses
    the appellants from purchasing powers as it imposes conditions on
    inter-state open access. The appellant argued that these conditions,
    such as requiring a 24-hour scheduling period, advance intimation of
    power usage, and a minimum consumption threshold of 75% of the
    scheduled quantum, exceed the jurisdiction of the State Commission
    and infringe upon the powers vested in the CERC.
15. The appellants referred to Section 2(36) of the Act of 2003, which
    defines “inter-state transmission” as:
             “(36) “ inter-State transmission system” includes –
             (i)   any system for the conveyance of electricity by means
                   of main transmission line from the territory of one
                   State to another State;
[2025] 4 S.C.R.                                                             447

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


           (ii)   the conveyance of electricity across the territory of
                  an intervening State as well as conveyance within
                  the State which is incidental to such inter-State
                  transmission of electricity;
           (iii) the transmission of electricity within the territory of a
                 State on a system built, owned, operated, maintained
                 or controlled by a Central Transmission Utility.”
     In light of the above definition, the appellants argued that merely
     because the transmission lines in the state of Rajasthan are used to
     convey electricity it does not cease to be an inter-state transaction
     as the usage of the said lines is only incidental to the conveyance
     of electricity using inter-state open access.
16. Appellants contended that inter-state open access is a matter falling
    within the exclusive domain of the CERC under Section 79(1)(c) of
    the Act of 2003. The Act of 2003 clearly demarcates the jurisdiction
    between CERC and State Commissions. It was argued that the power
    of the State Commission, RERC in this case, under Section 86(1)(c)
    is confined to regulating intra-state open access, and therefore, any
    attempt to regulate inter-state open access by the RERC is ultra vires
    the Act of 2003. The appellants highlighted that the petitioners in
    Civil Appeal No. 7965 of 2019 and Civil Appeal No. 7966 of 2019 are
    intra-state consumers of captive power from their captive generating
    plants located within Rajasthan. However, the appellants in Civil
    Appeal No. 7964 of 2019 are inter-state consumers, purchasing power
    from sources located outside Rajasthan. Therefore, the challenge to
    Regulation 26(7) by the appellants in Civil Appeal No. 7964 of 2019
    is on a different footing, as it concerns the extra-territorial application
    of the Regulations of 2016 to inter-state transactions, which is beyond
    the legislative competence of the RERC.
17. The appellants while referring to Section 79(1)(c) of the Act of 2003,
    submitted that it explicitly provides that the CERC shall regulate
    the transmission of electricity and determine tariffs for inter-state
    transmission of electricity. Section 2(36) of the Act of 2003 defines
    “inter-state transmission” to mean the conveyance of electricity
    from one state to another. Therefore, any open access transaction
    involving the transmission of electricity across state boundaries would
    qualify as an inter-state transaction, which falls exclusively within
    the regulatory domain of the CERC. The appellants submitted that
448                                                           [2025] 4 S.C.R.

                       Digital Supreme Court Reports


       Section 86(1)(c) of the Act of 2003 empowers the State Commissions
       to facilitate intra-state open access only. The power to regulate intra-
       state open access does not include the authority to regulate inter-
       state open access transactions. The regulatory scheme under the
       Act of 2003 establishes a clear division of jurisdiction between the
       CERC and the State Commissions, with the CERC having exclusive
       authority over inter-state transactions and the State Commissions
       having authority over intra-state transactions.
18. It was the argument of the appellants that any surcharge or regulatory
    requirement imposed by the RERC on such inter-state transactions
    is ultra vires the Act of 2003 and amounts to an extra-territorial
    application of state law. The appellants further submitted that the
    findings of the Jodhpur Bench of the High Court, which upheld the
    validity of Regulations of 2016 with respect to intra-state consumers,
    cannot be applied to inter-state consumers. The challenge before the
    Jaipur Bench of the High Court concerned inter-state consumers,
    whose transactions are governed by the regulatory framework
    established by the CERC, not the RERC, and thus would not be
    covered by the judgment of the Jodhpur Bench.
19. Further, the appellants submitted that the jurisdiction of the RERC
    is circumscribed by Section 86(1)(a) of the Act of 2003, in terms of
    which the State Commission shall determine the tariff for generation,
    supply, transmission and wheeling of electricity, wholesale, bulk or
    retail “within the state”. Thus, the RERC’s powers with respect to
    open access are only within the state and not beyond it. Whereas,
    the CERC has been empowered under Section 79(1)(c) to regulate
    inter-state transmission of electricity.
20. Appellants also made a reference to Section 42 of the Act of 2003
    which provides that the RERC in exercise of its powers under this
    provision may impose cross subsidy surcharge; wheeling charges;
    additional surcharge on wheeling, if any, to meet fixed cost of the
    distribution licensee arising out of its obligation to supply. Thus, the
    RERC is within its power to factor operational costs only. Reference
    was also made to the definition of “open access” provided under
    Section 2(47), which reads as follows:
            “(47) “open access” means the non-discriminatory
            provision for the use of transmission lines or distribution
            system or associated facilities with such lines or system
[2025] 4 S.C.R.                                                            449

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


            by any licensee or consumer or a person engaged in
            generation in accordance with the regulations specified
            by the Appropriate Commission.”
21. Appellants thus submitted that Section 42 of the Act of 2003 only
    refers to the State Commissions whereas the definition of open access
    contained in Section 2(47) refers to the Appropriate Commission which
    includes the CERC. Therefore, the power of the State Commissions
    does not extend to regulating inter-state open access transactions
    which power has been conferred upon the Central Commission.
    A conjoint reading of Sections 42 and 86(1)(a) of the Act of 2003
    makes it clear that the regulations of the State Commissions only
    apply within the state. In the case of inter-state transmission of
    electricity, the governing regulation is the CERC (Connectivity and
    General Network Access to the ‘inter-state’ Transmission System)
    Regulations, 2022.7 All inter-state transactions (including collective
    transactions) on the power exchange are necessarily inter-state
    transactions and governed by the CERC GNA Regulations. In the
    event of transmission of inter-state power from outside the state
    into Rajasthan, it is not the RERC Regulations of 2016 which apply
    within the state but the CERC GNA Regulations.
22. The appellants relied upon the decision of this Court in Energy
    Watchdog v. Central Electricity Regulatory Commission,8 wherein
    it was held that the authority to regulate inter-state transmission
    and inter-state open access vests exclusively with the CERC. The
    appellants argued that the ratio of this judgment squarely applies
    to the present case, rendering the impugned regulation beyond the
    competence of the RERC. The appellants relied upon the following
    findings of this Court in Energy Watchdog (Supra):
            “...24. The scheme that emerges from these sections is
            that whenever there is inter State generation or supply of
            electricity, it is the Central involved, and whenever there
            is intra-State generation or supply of electricity, the State
            Government or the State Commission is involved. This is
            the precise scheme of the entire Act, including Sections
            79 and 86. It will be seen that Section 79(1) itself in


7   CERC GNA Regulations.
8   (2017) 14 SCC 80.
450                                                        [2025] 4 S.C.R.

                     Digital Supreme Court Reports


          clauses (c), (d) and (e) speaks of inter-State transmission
          and inter-State operations. This is to be contrasted
          with Section 86 which deals with functions of the State
          Commission which uses the expression “within the State”
          in clauses (a), (b) and (d), and “intra-State” in clause (c).
          This being the case, it is clear that the PPA, which deals
          with generation and supply of electricity, will either have
          to be governed by the State Commission or the Central
          Commission. The State Commission’s jurisdiction is only
          where generation and supply takes place within the State.
          On the other hand, the moment generation and sale takes
          place in more than one State, the Central Commission
          becomes the appropriate Commission under the Act. What
          is important to remember is that if we were to accept the
          argument on behalf of the appellant, and we were to hold
          in the Adani case that there is no composite scheme for
          generation and sale, as argued by the appellant, it would
          be clear that neither Commission would have jurisdiction,
          something which would lead to absurdity. Since generation
          and sale of electricity is in more than one State obviously
          Section 86 does not get attracted. This being the case, we
          are constrained to observe that the expression “composite
          scheme” does not mean anything more than a scheme for
          generation and sale of electricity in more than one State.”
23. Thus, the appellants submitted that by curtailing the purchase power
    on the exchange by imposing conditions on inter-state open access
    transactions taking place outside the state of Rajasthan, Regulation
    26(7) is ex-facie contrary to the objectives of Act of 2003 and the
    National Tariff Policy, and thus RERC has encroached upon the
    jurisdiction of the CERC in framing these arbitrary regulations. By
    imposing these conditions in excess of its territorial jurisdiction, the
    RERC has essentially banned the purchase of power under real
    time contracts, intraday contracts, and contingency contracts and
    thereby ensured that industrial consumers such as the appellants
    have no option but to purchase power from the Distribution Licensee
    (Jaipur Vidyut Vitran Nigam), contrary to the objectives of promoting
    competition such that consumers can avail quality and cheaper
    power from different sources on the power exchange via the inter-
    state open access mechanism. It was submitted that the impugned
[2025] 4 S.C.R.                                                           451

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     regulation, by interfering with inter-state scheduling, exceeds the
     regulatory authority of the RERC and violates the statutory framework
     established under the Act of 2003.
24. In Civil Appeal Nos. 7965 and 7966 of 2019, the challenge is to the
    vires of the regulation by the captive generators supplying power
    within the state of Rajasthan. Appellants have challenged the
    Regulations of 2016 on the grounds that the Regulations of 2016
    are discriminatory against the CPPs as they put illegal fetters upon
    them for availing open access which is a statutory right of the such
    power generators under Section 9 of the Act of 2003.
25. The appellant submitted that Regulation 21 of the Regulations
    of 2016 is arbitrary and discriminatory against CPPs. Section
    9 of the Act of 2003 recognizes the right of industries to set up
    captive generation plants and ensures non-discriminatory access
    to transmission and distribution networks. However, Regulation 21
    creates an unreasonable distinction between captive generators and
    state distribution companies,9 discouraging captive power generation.
    The appellants contend that the pricing mechanism imposed under
    Regulation 21 unfairly penalizes captive generators while providing
    undue advantages to state DISCOMs. Under the regulation, any
    under-injection by an open access consumer is settled at higher
    rates, whereas over-injection is compensated at lower rates. Further,
    Regulation 21 also provides that any energy injected by the power plant
    but not utilised by its captive units is not paid for at all to the captive
    unit/drawer/buyer. Such a pricing mechanism creates a disincentive
    for captive generators to sell their surplus power through open access
    and effectively forces them to rely on state utilities. The appellants
    further argued that the discriminatory treatment of captive generators
    under Regulation 21 is inconsistent with the intent of the Act of 2003,
    which promotes competition and self-sufficiency in power generation.
    By creating an uneven playing field, the regulation hampers industrial
    consumers’ ability to optimize their power procurement strategies and
    forces them into an unfair dependence on state utilities.
26. The appellants have challenged Regulation 21 on the ground that
    by imposition of heavy penalty in case of under-injection by CPPs
    as provided in Regulation 21 and at the same time exemption of the


9   DISCOMs.
452                                                            [2025] 4 S.C.R.

                       Digital Supreme Court Reports


       State Generators and other generators supplying power to DISCOMS
       on long term basis (by virtue of Regulation 5 and Regulation 6), the
       Regulations of 2016 have created a discriminatory regime detrimental
       to the interest of CPPs which is totally against the spirit of the proviso
       to Section 9(1) of the Act of 2003.
27. It is the argument of the appellants that these regulations discourage
    open access by providing extremely stringent provisions for normal
    and practically uncontrollable deviations from schedule and are
    thereby creating artificial barriers on CPPs and consumers availing
    open access by making the supply from open access non feasible
    and economically unviable by forcing the captive generators and
    consumers to incur very steep payments as well as enriching the
    DISCOMs at the expense of the open access consumers.
28. Appellants further highlighted that the National Electricity Policy 200510
    realises the enormous potential of CPPs and envisages encouraging
    generation from such plants for the overall development of the
    power market in the country. A conjoint reading of the provisions of
    the Act of 2003 and NEP of 2005 establishes that it is the explicit
    intention of the legislature that the CPPs should be encouraged and
    developed as a source of decentralised power generators. Therefore,
    any regulation putting CPPs at a position disadvantageous vis-a-vis
    other generator in the matter of providing open access or regulating
    supply of power from them is in violation of and ultra vires to the
    provisions of Act of 2003 and the NEP of 2005.

       ARGUMENTS OF THE RESPONDENTS
29. The respondents, including the RERC and the distribution licensees
    have strongly defended the validity of the Regulations of 2016,
    contending that the same have been framed well within the jurisdiction
    of the RERC as conferred under the Act of 2003 and are essential for
    maintaining grid discipline, ensuring fair competition, and safeguarding
    the financial viability of the electricity DISCOMs. Further, it has also
    been vehemently submitted that open access cannot be absolutely
    free, untrammelled, un-controlled or unrestricted. The submissions
    of all the respondents defending the validity of the Regulations of
    2016 have been reproduced below.


10   NEP of 2005.
[2025] 4 S.C.R.                                                        453

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


30. At the outset, it is submitted that the regulation of electricity is
    an intricate and highly specialized domain requiring expertise in
    technical, economic, and legal considerations. The Act of 2003,
    entrusts regulatory commissions with the responsibility of ensuring
    an efficient, reliable, and economically viable electricity sector while
    balancing the interests of generators, consumers, and DISCOMs.
    Electricity, being a form of energy that cannot be stored in its raw
    form, necessitates continuous real-time management to maintain
    grid stability. Any mismatch between demand and supply can lead to
    severe disruptions, including grid failure, thereby causing widespread
    economic and social ramifications. To prevent such contingencies,
    electricity regulatory commissions, including RERC, are mandated
    to frame and enforce operating norms that promote efficiency and
    discipline among participants in the electricity sector. The primary
    objective of these norms is to ensure that the benefits derived from
    improved operational efficiency are passed on to consumers while
    simultaneously maintaining grid stability.
31. The respondents submitted that RERC possesses regulatory
    authority over certain aspects of open access transactions, even
    where electricity is procured from outside the state of Rajasthan
    but delivered within Rajasthan. The jurisdiction of CERC is defined
    under Section 79(1) of the Act of 2003 Act, granting it regulatory
    powers over inter-state transmission of electricity. However, this does
    not preclude State Commissions, including RERC, from exercising
    jurisdiction over intra-state aspects of open access. Section 42(2) of
    the Act of 2003 specifically empowers State Commissions to regulate
    intra-state open access, ensuring fair access to transmission and
    distribution networks within the state. While the appellant argues
    that only CERC has the power to regulate inter-state open access,
    this contention is misplaced. RERC retains regulatory oversight over
    intra-state transactions, even if the power originates from another
    state but is ultimately transmitted within Rajasthan’s intra-state grid.
    Thus, while CERC has jurisdiction over inter-state transmission, RERC
    retains regulatory authority over the intra-state aspects of open access
    transactions, even if the power source is located outside the state
    but the power is delivered within the State through the intra-state
    grid. This is in consonance with the framework of the Act of 2003,
    which provides for a clear demarcation of responsibilities between
    central and state regulators without unduly restricting state regulatory
454                                                         [2025] 4 S.C.R.

                      Digital Supreme Court Reports


       authority. Further, Section 42 of the Act of 2003 expressly empowers
       the State Commissions to introduce and regulate open access within
       the state. Nowhere in the parent Act has the legislature conferred the
       power to regulate open access to the Central Government or CERC
       for consumers falling under the purview of Section 42.
32. It is thus the submission of the respondents that the appellant’s
    assertion that only CERC has the power to regulate inter-state open
    access is misleading. While CERC indeed has jurisdiction over
    inter-state transmission under Section 79(1) of the Act of 2003,
    RERC retains regulatory authority over the intra-state aspects
    of open access transactions, even if the power is sourced from
    outside the state. Further, it has been contended that as rightly
    pointed out by the appellants, Section 2(47) of the Act of 2003
    defines open-access as non-discriminatory access to transmission
    or distribution system; but this encompasses in its ambit both,
    inter-state as well as intra-state transactions, without creating
    any distinction between them for regulatory purposes. Therefore,
    it is a natural consequence that State Commissions will retain
    the power to regulate open access within their jurisdictions, even
    if it involves powers sourced from another state. Hence, from
    the plain reading of Section 2(47) with Section 42 of the Act of
    2003, it is clear that the statute treats open access uniformly,
    regardless of the source and the legislature did not intend to create
    any unnecessary distinction. Hence, the power to regulate open
    access, as per Section 42, rests with the RERC, especially since
    the consumer, as defined under Section 2(15) of the Act of 2003,
    is the one who consumes electricity via the distribution licensee,
    which operates within the state. Section 2(15) defines a “consumer”
    as any person who is supplied electricity by a licensee or whose
    premises are connected to a distribution system. Since distribution
    licensees operate within specific states, the regulation of open
    access for consumers naturally falls within the jurisdiction of the
    respective State Commission. Since open access transactions
    ultimately facilitate the supply of electricity to consumers through the
    distribution network of a state licensee, their regulation necessarily
    falls within the purview of the concerned State Commission. This
    reinforces the position that State Commissions, rather than CERC,
    have jurisdiction over open access transactions where power is
    consumed within the state, irrespective of its source.
[2025] 4 S.C.R.                                                        455

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


33. Section 181 of the Act of 2003 grants State Commissions the power
    to frame regulations to implement the provisions of the Act of 2003.
    This includes the power to introduce and regulate open access,
    determine applicable charges, and establish conditions for access
    to intra-state transmission and distribution networks. The ability of
    State Commissions to make rules regarding open access further
    affirms that RERC, in the exercise of its statutory functions, can
    formulate regulations governing open access transactions within
    Rajasthan. Moreover, Section 181 of the Act of 2003 reinforces the
    independent authority of State Commissions by specifying their role
    in electricity regulation at the state level. This provision upholds the
    principle of decentralization in electricity governance and affirms
    the legislative intent to vest regulatory control over intra-state
    electricity transactions with State Commissions, including RERC.
    While, Section 181 of the Act of 2003 specifically grants the State
    Commissions the authority to make regulations concerning the
    classes of consumers falling under Section 42 of the Act of 2003,
    Section 178 of the Act of 2003 grants the CERC broad powers to
    make regulations on a wide range of subjects while intentionally
    withholding powers related to Section 42 of the Act. In furtherance
    of this, Section 79 of the Act of 2003, which outlines the functions
    of the CERC, does not confer any responsibility upon the Central
    Commission regarding he regulation of consumer classes. The
    absence of any such provision is evident of the legislature’s intent
    to not extend the CERC’s role in regulating the supply of power to
    end consumers from distribution licensee, either through intra-state
    transmission or inter-state transmission. Therefore, inter-state open
    access falls within the purview of the State Commissions, RERC
    herein, for regulatory purposes.
34. The respondents further submitted that Regulation 26(7) of
    the Regulations of 2016, which mandates a one-day advance
    scheduling requirement for 24-hour power procurement, serves a
    legitimate regulatory purpose. This is a reasonable and necessary
    provision and is only applicable in the case of ‘short-term inter-state
    open access’. This requirement ensures grid stability, facilitates
    proper load forecasting, and prevents last-minute fluctuations that
    could destabilize the electricity network. The advance scheduling
    requirement is neither arbitrary nor unreasonable but is in line with
    best practices for efficient power system management.
456                                                         [2025] 4 S.C.R.

                     Digital Supreme Court Reports


35. The contention that this requirement forecloses urgent procurement is
    misplaced. The regulations provide alternative mechanisms, including
    short-term market purchases, that allow participants to address
    urgent electricity shortages. Respondents submitted that the real-time
    market and day-ahead market operated under the guidelines of the
    CERC still allow purchase of power for urgent needs. However, the
    scheduling requirement is only applicable to procurement through
    open access within the state of Rajasthan in order to integrate the
    demanded power securely. Thus, such a requirement is a rational
    measure to ensure that the grid operates in a stable and reliable
    manner without the risk of sudden fluctuations, and thus is in no way
    ultra vires the provisions of the Act of 2003 or against the objectives
    of open access. The argument that the scheduling requirement
    creates an artificial barrier to open access is completely misplaced,
    as the intention is to ensure a stable and moderated open access,
    thereby protecting the reliability of the grid. This in no way forecloses
    the access to urgent procurement, which is available through other
    sources, but only ensures that open access consumers follow grid
    discipline, which is imperative to prevent any imbalances. Therefore,
    the imposition of a structured scheduling mechanism is necessary
    for maintaining an efficient and stable grid.
36. It has been further submitted by the respondents that the consistent
    under-utilization of contract demand by such consumers can lead
    to financial losses for the distribution licensees. This is because the
    fixed costs associated with maintaining the infrastructure necessary
    to support higher demand must still be covered, irrespective of
    the actual consumption levels. By allowing only consumers who
    demonstrate genuine demand to access open access, the regulatory
    framework seeks to create a more equitable and efficient system.
    This furthers the aim of the Act of 2003 while ensuring transparency
    and accountability among consumers of open access.
37. The respondents contend that the Regulations of 2016 do not
    arbitrarily foreclose the petitioner’s right to open access, which was
    previously available under the Regulations of 2004. The Regulations
    of 2016 are an evolved framework aimed at aligning open access
    policies with the current realities of electricity distribution and
    transmission. The modifications introduced in the new regulations,
    including changes in scheduling requirement, charges, and penalties,
    are intended to address inefficiencies and ensure a level playing field
[2025] 4 S.C.R.                                                          457

      Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


      for all stakeholders. These changes are well within the regulatory
      domain of RERC and do not constitute an unlawful revocation of
      rights granted under the previous framework.
38. The appellants argued that its transactions qualify as ‘collective
    transactions’ under the CERC GNA Regulations, thereby falling
    outside RERC’s regulatory jurisdiction. The respondents counter this
    argument by asserting that collective transactions, as defined under
    the applicable regulations, pertain to centralized power exchanges
    and structured market transactions. The appellants’ transactions,
    however, involve bilateral arrangements and open access usage
    within Rajasthan’s network. Therefore, they do not automatically
    fall under the exclusive purview of CERC. The respondents submit
    that RERC’s jurisdiction remains intact concerning aspects of the
    transactions that involve intra-state transmission and distribution.
39. The respondents next submitted that Regulation 21 of the Regulations
    of 2016, which imposes penalties for under-injection of power by
    captive power plants, is a necessary regulatory measure designed
    to ensure grid discipline. The contention that Regulation 21 is
    discriminatory against CPPs is unfounded, as the provision applies
    equally to all entities responsible for power injection into the grid. The
    rationale behind this regulation is to prevent deviation from scheduled
    generation, which can disrupt grid stability. Captive generators, unlike
    state generators under long-term power purchase agreements11,
    have greater flexibility in their operations, necessitating stricter
    scheduling norms to maintain system integrity. The imposition of
    penalties is intended to discourage any kind of gaming or foul play
    and ensure that all participants bear the cost of grid imbalances, as
    deviation charges are necessary to discourage under-injection and
    over-drawal, to ensure grid stability. The imposition of penalties for
    under-injection by CPPs is an essential regulatory measure aimed
    at ensuring predictability in electricity scheduling and preventing
    deviations that could jeopardize grid stability. The respondents further
    emphasize that Regulation 21 does not violate the rights of captive
    consumers under Section 9(1) of the Act of 2003. The proviso to
    Section 9(1) merely recognizes the right of captive consumers to
    establish and operate generation plants for self-use. However, this


11   PPAs.
458                                                         [2025] 4 S.C.R.

                            Digital Supreme Court Reports


       right is not absolute and is subject to regulatory oversight to ensure
       that the operation of CPPs does not disrupt grid stability or create
       imbalances in electricity supply. The regulatory measures imposed
       under the Regulations of 2016 are well within the powers conferred
       upon RERC under the Act of 2003, and are consistent with the
       broader objectives of the statute.
40. It is a settled principle of law that courts should exercise judicial
    restraint when reviewing the validity of regulations framed by expert
    regulatory bodies. The respondents argued that this Court has
    consistently recognized that regulatory commissions are vested with
    specialized knowledge and expertise, and their decisions should
    not be lightly interfered with unless they are manifestly arbitrary,
    unreasonable, or in direct contravention of statutory provisions. In
    Reliance Infrastructure v. State of Maharashtra,12 this Court held
    that regulatory decisions should be accorded deference unless it is
    demonstrated that they are wholly irrational, ultra vires the parent
    statute, or violate Fundamental Rights. Similarly, in Hindustan Zinc
    v. RERC,13 this Court reaffirmed the well-established presumption
    of constitutionality that extends to subordinate legislation, including
    regulations framed under statutory authority. The respondents
    submitted that unless a regulation is shown to lack legislative
    competence, be inconsistent with the provisions of the parent
    statute, exceed the authority conferred upon the regulatory body,
    or be manifestly arbitrary and unreasonable, it must be presumed
    to be valid. The burden lies on the party challenging the regulation
    to establish its invalidity, and in the present case, the appellant has
    failed to discharge this burden.
41. The respondents lastly asserted that the Regulations of 2016
    as a whole are justified, necessary, and within the regulatory
    mandate of RERC. The evolution of open access regulations is
    a dynamic process, requiring periodic modifications to address
    emerging challenges in electricity distribution and transmission.
    The Regulations of 2016 aim to enhance grid reliability, ensure
    economic efficiency, and promote non-discriminatory access to the
    power network. Further, regulatory measures such as scheduling


12   (2019) 3 SCC 352, Para 38.
13   (2015) 12 SCC 611, Para 32.
[2025] 4 S.C.R.                                                         459

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     requirements, charges, and penalties are established to prevent
     market manipulation, ensure fair competition, and protect consumer
     interests. The respondents, therefore, submit that the appellants
     have failed to establish any legal infirmity in the Regulations of
     2016 warranting interference by this Court. The respondents further
     submitted that the Regulations of 2016 are framed in alignment
     with national policies and regulatory precedents across various
     states. The objective of open access is to promote competition and
     consumer choice while ensuring grid stability and financial viability
     of distribution licensees. The levy of surcharges and charges under
     the regulations serves this dual purpose. It is further argued that
     the appellants’ interpretation of the Act of 2003, disregards the
     financial impact on state utilities and the broader policy intent. The
     respondents emphasized that regulations framed by RERC are
     based on detailed public consultations and impact assessments,
     taking into account the interests of all stakeholders. The regulations
     are neither arbitrary nor excessive but are necessary for ensuring
     an equitable and sustainable electricity sector.

     ANALYSIS
42. Before delving into the issues before us, the relevant provisions
    referred to are reproduced below:
           42.1. THE ELECTRICITY ACT, 2003
           “Section 2. Definitions: - In this Act, unless the context
           otherwise requires –

                    xxx               xxx                 xxx
           (15) “consumer” means any person who is supplied with
           electricity for his own use by a licensee or the Government
           or by any other person engaged in the business of
           supplying electricity to the public under this Act or any
           other law for the time being in force and includes any
           person whose premises are for the time being connected
           for the purpose of receiving electricity with the works of
           a licensee, the Government or such other person, as the
           case may be;

                    xxx               xxx                 xxx
460                                                       [2025] 4 S.C.R.

                  Digital Supreme Court Reports


       (17) “distribution licensee” means a licensee authorised to
       operate and maintain a distribution system for supplying
       electricity to the consumers in his area of supply;

               xxx                  xxx                  xxx
       (36) “inter-State transmission system” includes -
       (i) any system for the conveyance of electricity by means
       of main transmission line from the territory of one State
       to another State;
       (ii) the conveyance of electricity across the territory of
       an intervening State as well as conveyance within the
       State which is incidental to such inter-State transmission
       of electricity;
       (iii) the transmission of electricity within the territory of a
       State on a system built, owned, operated, maintained or
       controlled by a Central Transmission Utility.

               xxx                  xxx                  xxx
       (47) “open access” means the non-discriminatory provision
       for the use of transmission lines or distribution system
       or associated facilities with such lines or system by any
       licensee or consumer or a person engaged in generation
       in accordance with the regulations specified by the
       Appropriate Commission;

               xxx                  xxx                  xxx

       Section 9. Captive generation:
       (1) Notwithstanding anything contained in this Act, a person
       may construct, maintain or operate a captive generating
       plant and dedicated transmission lines:
       Provided that the supply of electricity from the captive
       generating plant through the grid shall be regulated in the
       same manner as the generating station of a generating
       company.
       [Provided further that no licence shall be required under
       this Act for supply of electricity generated from a captive
[2025] 4 S.C.R.                                                           461

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


           generating plant to any licencee in accordance with the
           provisions of this Act and the rules and regulations made
           thereunder and to any consumer subject to the regulations
           made under sub- section (2) of section 42.]
           (2) Every person, who has constructed a captive generating
           plant and maintains and operates such plant, shall have the
           right to open access for the purposes of carrying electricity
           from his captive generating plant to the destination of his
           use:
           Provided that such open access shall be subject to
           availability of adequate transmission facility and such
           availability of transmission facility shall be determined by
           the Central Transmission Utility or the State Transmission
           Utility, as the case may be:
           Provided further that any dispute regarding the availability
           of transmission facility shall be adjudicated upon by the
           Appropriate Commission.

                    xxx                xxx                 xxx

           Section 32. Functions of State Load Despatch
           Centres: -
           (1) The State Load Despatch Centre shall be the apex
           body to ensure integrated operation of the power system
           in a State.
           (2) The State Load Despatch Centre shall -
                (a) be responsible for optimum scheduling and
                despatch of electricity within a State, in accordance
                with the contracts entered into with the licensees or
                the generating companies operating in that State;
                (b) monitor grid operations;
                (c) keep accounts of the quantity of electricity
                transmitted through the State grid;
                (d) exercise supervision and control over the intra-
                State transmission system; and
462                                                     [2025] 4 S.C.R.

                 Digital Supreme Court Reports


            (e) be responsible for carrying out real time operations
            for grid control and despatch of electricity within the
            State through secure and economic operation of the
            State grid in accordance with the Grid Standards and
            the State Grid Code.
       (3) The State Load Despatch Centre may levy and collect
       such fee and charges from the generating companies and
       licensees engaged in intra-State transmission of electricity
       as may be specified by the State Commission.

       Section 33. Compliance of directions: -
       (1) The State Load Despatch Centre in a State may
       give such directions and exercise such supervision and
       control as may be required for ensuring the integrated grid
       operations and for achieving the maximum economy and
       efficiency in the operation of power system in that State.
       (2) Every licensee, generating company, generating
       station, sub-station and any other person connected with
       the operation of the power system shall comply with the
       directions issued by the State Load Depatch Centre under
       sub-section (1).
       (3) The State Load Despatch Centre shall comply with the
       directions of the Regional Load Despatch Centre.
       (4) If any dispute arises with reference to the quality of
       electricity or safe, secure and integrated operation of the
       State grid or in relation to any direction given under sub-
       section (1), it shall be referred to the State Commission
       for decision:
       Provided that pending the decision of the State Commission,
       the directions of the State Load Despatch Centre shall be
       complied with by the licensee or generating company.
       (5) If any licensee, generating company or any other
       person fails to comply with the directions issued under
       sub-section(1), he shall be liable to a penalty not exceeding
       rupees five lacs.

               xxx                 xxx                 xxx
[2025] 4 S.C.R.                                                            463

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


           Section 42. Duties of distribution licensee and open
           access: -
           (1) It shall be the duty of a distribution licensee to develop
           and maintain an efficient, co-ordinated and economical
           distribution system in his area of supply and to supply
           electricity in accordance with the provisions contained in
           this Act.
           (2) The State Commission shall introduce open access in
           such phases and subject to such conditions, (including the
           cross subsidies, and other operational constraints) as may
           be specified within one year of the appointed date by it
           and in specifying the extent of open access in successive
           phases and in determining the charges for wheeling, it
           shall have due regard to all relevant factors including
           such cross subsidies, and other operational constraints:
           Provided that [such open access shall be allowed on
           payment of a surcharge] in addition to the charges for
           wheeling as may be determined by the State Commission:
           Provided further that such surcharge shall be utilised to
           meet the requirements of current level of cross subsidy
           within the area of supply of the distribution licensee:
           Provided also that such surcharge and cross subsidies
           shall be progressively reduced in the manner as may be
           specified by the State Commission:
           Provided also that such surcharge shall not be leviable
           in case open access is provided to a person who has
           established a captive generating plant for carrying the
           electricity to the destination of his own use:
           [Provided also that the State Commission shall, not later
           than five years from the date of commencement of the
           Electricity (Amendment) Act, 2003, by regulations, provide
           such open access to all consumers who require a supply of
           electricity where the maximum power to be made available
           at any time exceeds one megawatt.]
           (3) Where any person, whose premises are situated
           within the area of supply of a distribution licensee,
464                                                     [2025] 4 S.C.R.

                 Digital Supreme Court Reports


       (not being a local authority engaged in the business
       of distribution of electricity before the appointed date)
       requires a supply of electricity from a generating company
       or any licensee other than such distribution licensee,
       such person may, by notice, require the distribution
       licensee for wheeling such electricity in accordance
       with regulations made by the State Commission and
       the duties of the distribution licensee with respect to
       such supply shall be of a common carrier providing
       non-discriminatory open access .
       (4) Where the State Commission permits a consumer
       or class of consumers to receive supply of electricity
       from a person other than the distribution licensee of his
       area of supply, such consumer shall be liable to pay
       an additional surcharge on the charges of wheeling, as
       may be specified by the State Commission, to meet the
       fixed cost of such distribution licensee arising out of his
       obligation to supply.
       (5) Every distribution licensee shall, within six months from
       the appointed date or date of grant of licence, whichever
       is earlier, establish a forum for redressal of grievances of
       the consumers in accordance with the guidelines as may
       be specified by the State Commission.
       (6) Any consumer, who is aggrieved by non-redressal
       of his grievances under sub-section (5), may make a
       representation for the redressal of his grievance to an
       authority to be known as Ombudsman to be appointed
       or designated by the State Commission.
       (7) The Ombudsman shall settle the grievance of the
       consumer within such time and in such manner as may
       be specified by the State Commission.
       (8) The provisions of sub-sections (5), (6) and (7) shall
       be without prejudice to right which the consumer may
       have apart from the rights conferred upon him by those
       sub-sections.

               xxx                 xxx                 xxx
[2025] 4 S.C.R.                                                           465

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


           Section 79. Functions of Central Commission: -
           (1) The Central Commission shall discharge the following
           functions, namely:-
                (a) to regulate the tariff of generating companies
                owned or controlled by the Central Government;
                (b) to regulate the tariff of generating companies
                other than those owned or controlled by the Central
                Government specified in clause (a), if such generating
                companies enter into or otherwise have a composite
                scheme for generation and sale of electricity in more
                than one State;
                (c) to regulate the inter-State transmission of
                electricity;
                (d) to determine tariff for inter-State transmission of
                electricity;
                (e) to issue licenses to persons to function as
                transmission licensee and electricity trader with
                respect to their inter-State operations;
                (f) to adjudicate upon disputes involving generating
                companies or transmission licensee in regard to
                matters connected with clauses (a) to (d) above and
                to refer any dispute for arbitration;
                (g) to levy fees for the purposes of this Act;
                (h) to specify Grid Code having regard to Grid
                Standards;
                (i) to specify and enforce the standards with respect
                to quality, continuity and reliability of service by
                licensees;
                (j) to fix the trading margin in the inter-State trading
                of electricity, if considered, necessary;
                (k) to discharge such other functions as may be
                assigned under this Act.
           (2) The Central Commission shall advise the Central
           Government on all or any of the following matters, namely :-
466                                                      [2025] 4 S.C.R.

                 Digital Supreme Court Reports


            (i) formulation of National electricity Policy and tariff
            policy;
            (ii) promotion of competition, efficiency and economy
            in activities of the electricity industry;
            (iii) promotion of investment in electricity industry;
            (iv) any other matter referred to the Central
            Commission by that Government.
       (3) The Central Commission shall ensure transparency
       while exercising its powers and discharging its functions.
       (4) In discharge of its functions, the Central Commission
       shall be guided by the National Electricity Policy,
       National Electricity Plan and tariff policy published under
       section 3.

              xxx                  xxx                  xxx

       Section 86. Functions of State Commission: -
       (1) The State Commission shall discharge the following
       functions, namely: -
            (a) determine the tariff for generation, supply,
            transmission and wheeling of electricity, wholesale,
            bulk or retail, as the case may be, within the State:
            Provided that where open access has been permitted
            to a category of consumers under section 42, the
            State Commission shall determine only the wheeling
            charges and surcharge thereon, if any, for the said
            category of consumers;
            (b) regulate electricity purchase and procurement
            process of distribution licensees including the price at
            which electricity shall be procured from the generating
            companies or licensees or from other sources through
            agreements for purchase of power for distribution and
            supply within the State;
            (c) facilitate intra-State transmission and wheeling
            of electricity;
[2025] 4 S.C.R.                                                            467

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


                (d) issue licences to persons seeking to act as
                transmission licensees, distribution licensees and
                electricity traders with respect to their operations
                within the State;
                (e) promote co-generation and generation of electricity
                from renewable sources of energy by providing
                suitable measures for connectivity with the grid and
                sale of electricity to any person, and also specify,
                for purchase of electricity from such sources, a
                percentage of the total consumption of electricity in
                the area of a distribution licensee;
                (f) adjudicate upon the disputes between the
                licensees, and generating companies and to refer
                any dispute for arbitration;
                (g) levy fee for the purposes of this Act;
                (h) specify State Grid Code consistent with the Grid
                Code specified under clause (h) of sub-section (1)
                of section 79;
                (i) specify or enforce standards with respect to quality,
                continuity and reliability of service by licensees;
                (j) fix the trading margin in the intra-State trading of
                electricity, if considered, necessary; and
                (k) discharge such other functions as may be assigned
                to it under this Act.
           (2) The State Commission shall advise the State
           Government on all or any of the following matters, namely:-.
                (i) promotion of competition, efficiency and economy
                in activities of the electricity industry;
                (ii) promotion of investment in electricity industry;
                (iii) reorganization and restructuring of electricity
                industry in the State;
                (iv) matters concerning generation, transmission,
                distribution and trading of electricity or any other
                matter referred to the State Commission by that
                Government.
468                                                     [2025] 4 S.C.R.

                 Digital Supreme Court Reports


       (3) The State Commission shall ensure transparency while
       exercising its powers and discharging its functions.
       (4) In discharge of its functions, the State Commission
       shall be guided by the National Electricity Policy, National
       Electricity Plan and tariff policy published under section 3.

               xxx                 xxx                 xxx

       Section 178. Powers of Central Commission to make
       regulations: -
       (1) The Central Commission may, by notification make
       regulations consistent with this Act and the rules generally
       to carry out the provisions of this Act.
       (2) In particular and without prejudice to the generality of
       the power contained in sub-section (1), such regulations
       may provide for all or any of following matters, namely: -
            (a) period to be specified under the first proviso to
            section 14;
            (b) the form and the manner of the application under
            sub-section (1) of section 15;
            (c) the manner and particulars of notice under sub-
            section (2) of section 15;
            (d) the conditions of licence under section 16;
            (e) the manner and particulars of notice under clause
            (a) of sub- section (2) of section 18;
            (f) publication of alterations or amendments to be
            made in the licence under clause(c) of sub-section
            (2) of section 18;
            (g) Grid Code under sub-section (2) of section 28;
            (h) levy and collection of fees and charge from
            generating companies or transmission utilities or
            licensees under sub-section (4) of section 28;
            (i) rates, charges and terms and conditions in respect
            of intervening transmission facilities under proviso
            to section 36;
[2025] 4 S.C.R.                                                          469

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


                (j) payment of the transmission charges and a
                surcharge under-sub- clause (ii) of clause (d) of sub-
                section (2) of section 38;
                (k) reduction of surcharge and cross subsidies under
                second proviso to sub-clause (ii) of clause (d) of
                sub-section (2) of section 38;
                (l) payment of transmission charges and a surcharge
                under sub-clause (ii) of clause(c) of section 40;
                (m) reduction of surcharge and cross subsidies under
                the second proviso to sub-clause (ii) of clause (c) of
                section 40;
                (n) proportion of revenues from other business to be
                utilised for reducing the transmission and wheeling
                charges under proviso to section 41;
                (o) duties of electricity trader under sub-section (2)
                of section 52;
                (p) standards of performance of a licensee or class
                of licensees under sub-section (1) of section 57;
                (q) the period within which information to be furnished
                by the licensee under sub-section (1) of section 59;
                [(r) the manner of reduction of cross subsidies under
                clause (g) of section 61;]
                (s) the terms and conditions for the determination of
                tariff under section 61;
                (t) details to be furnished by licensee or generating
                company under sub-section (2) of section 62;
                (u) the procedures for calculating the expected
                revenue from tariff and charges under sub-section
                (5) of section 62;
                (v) the manner of making an application before the
                Central Commission and the fee payable therefor
                under sub-section (1) of section 64;
                (w) the manner of publication of application under
                sub-section (2) of section 64;
470                                                       [2025] 4 S.C.R.

                  Digital Supreme Court Reports


            (x) issue of tariff order with modifications or conditions
            under sub-section (3) of section 64;
            (y) the manner by which development of market in
            power including trading specified under section 66;
            (z) the powers and duties of the Secretary of the
            Central Commission under sub-section (1) of section
            91;
            (za) the terms and conditions of service of the
            Secretary, officers and other employees of Central
            Commission under sub-section (3) of section 91;
            (zb) the rules of procedure for transaction of business
            under sub- section (1) of section 92;
            (zc) minimum information to be maintained by a
            licensee or the generating company and the manner of
            such information to be maintained under sub-section
            (8) of section 128;
            (zd) the manner of service and publication of notice
            under section 130;
            (ze) any other matter which is to be, or may be,
            specified by regulations.
       (3) All regulations made by the Central Commission under
       this Act shall be subject to the conditions of previous
       publication.

               xxx                  xxx                  xxx

       Section 181. Powers of State Commissions to make
       regulations: -
       (1) The State Commissions may, by notification, make
       regulations consistent with this Act and the rules generally
       to carry out the provisions of this Act.
       (2) In particular and without prejudice to the generality of
       the power contained in sub-section (1), such regulations
       may provide for all or any of the following matters, namely: -
[2025] 4 S.C.R.                                                         471

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


                (a) period to be specified under the first proviso of
                section 14;
                (b) the form and the manner of application under
                sub-section (1) of section 15;
                (c) the manner and particulars of application for
                licence to be published under sub-section (2) of
                section 15;
                (d) the conditions of licence section 16;
                (e) the manner and particulars of notice under
                clause(a) of sub-section (2) of section 18;
                (f) publication of the alterations or amendments to be
                made in the licence under clause (c) of sub-section
                (2) of section 18;
                (g) levy and collection of fees and charges from
                generating companies or licensees under sub-section
                (3) of section 32;
                (h) rates, charges and the term and conditions in
                respect of intervening transmission facilities under
                proviso to section 36;
                (i) payment of the transmission charges and a
                surcharge under sub-clause (ii) of clause(d) of sub-
                section (2) of section 39;
                (j) reduction of surcharge and cross subsidies under
                second proviso to sub-clause (ii) of clause (d) of
                sub-section (2) of section 39;
                (k) manner and utilisation of payment and surcharge
                under the fourth proviso to sub-clause(ii) of clause
                (d) of sub-section (2) of section 39;
                (l) payment of the transmission charges and a
                surcharge under sub-clause(ii) of clause (c) of
                section 40;
                (m) reduction of surcharge and cross subsidies
                under second proviso to sub-clause (ii) of clause
                (c) of section 40;
472                                                [2025] 4 S.C.R.

            Digital Supreme Court Reports


       (n) the manner of payment of surcharge under the
       fourth proviso to sub-clause (ii) of clause (c) of
       section 40;
       (o) proportion of revenues from other business to be
       utilised for reducing the transmission and wheeling
       charges under proviso to section 41;
       (p) reduction of surcharge and cross-subsidies under
       the third proviso to sub-section (2) of section 42;
       (q) payment of additional charges on charges of
       wheeling under sub-section (4) of section 42;
       (r) guidelines under sub-section (5) of section 42;
       (s) the time and manner for settlement of grievances
       under sub-section (7) of section 42;
       (t) the period to be specified by the State Commission
       for the purposes specified under sub-section (1) of
       section 43;
       (u) methods and principles by which charges for
       electricity shall be fixed under sub-section (2) of
       section 45;
       (v) reasonable security payable to the distribution
       licensee under sub-section (1) of section 47;
       (w) payment of interest on security under sub-section
       (4) of section 47;
       (x) electricity supply code under section 50;
       (y) the proportion of revenues from other business
       to be utilised for reducing wheeling charges under
       proviso to section 51;
       (z) duties of electricity trader under sub-section (2)
       of section 52;
       (za) standards of performance of a licensee or a
       class of licensees under sub-section (1) of section 57;
       (zb) the period within which information to be furnished
       by the licensee under sub-section (1) of section 59;
[2025] 4 S.C.R.                                                         473

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


                [(zc) the manner of reduction of cross-subsidies under
                clause (g) of section 61;]
                (zd) the terms and conditions for the determination
                of tariff under section 61;
                (ze) details to be furnished by licensee or generating
                company under sub-section (2) of section 62;
                (zf) the methodologies and procedures for calculating
                the expected revenue from tariff and charges under
                sub-section (5) of section 62;
                (zg) the manner of making an application before the
                State Commission and the fee payable therefor under
                sub-section (1) of section 64;
                (zh) issue of tariff order with modifications or
                conditions under sub-section(3) of section 64;
                (zi) the manner by which development of market in
                power including trading specified under section 66;
                (zj) the powers and duties of the Secretary of the
                State Commission under sub-section (1) of section 91;
                (zk) the terms and conditions of service of the
                secretary, officers and other employees of the State
                Commission under sub-section (2) of section 91;
                (zl) rules of procedure for transaction of business
                under sub-section (1) of section 92;
                (zm) minimum information to be maintained by a
                licensee or the generating company and the manner of
                such information to be maintained under sub-section
                (8) of section 128;
                (zn) the manner of service and publication of notice
                under section 130;
                (zo) the form of preferring the appeal and the manner
                in which such form shall be verified and the fee
                for preferring the appeal under sub-section (1) of
                section 127;
474                                                       [2025] 4 S.C.R.

                  Digital Supreme Court Reports


            (zp) any other matter which is to be, or may be,
            specified.
       (3) All regulations made by the State Commission under this
       Act shall be subject to the condition of previous publication.”
       42.2. Rajasthan Electricity Regulatory Commission
             (Terms and Conditions for Open Access)
             Regulations, 2016:

              “xxx                  xxx                  xxx

       R.5. Special Provisions for existing Distribution
       Licensees: The Distribution Licensees, using intra-State
       transmission system and the distribution system in the State
       under an existing agreement or arrangement on the date
       of coming into force of the RERC (Terms and Conditions
       for Open Access) Regulations, 2004, shall be entitled to
       continue to avail open access to such transmission and
       distribution system on the same terms and conditions for
       the term of the existing agreement or arrangement on
       payment of transmission charges and wheeling charges
       as may be determined by the Commission.
       R.6. Provisions for existing consumers and generating
       companies: The existing consumer or an existing
       generating company other than the licensees availing open
       access under government policy or under agreements
       entered on the date of coming into force of RERC (Terms
       and Conditions for Open Access) Regulations, 2004 may
       continue to avail open access on terms and conditions laid
       down under these Regulations to the extent they are not
       covered by any policy directive by the State Government
       to the Commission.

               xxx                  xxx                  xxx

       R.21. Unscheduled Interchange Pricing
       The payment settlement for mismatch between the
       schedule and the actual drawal/injection in both intra-State
       and inter-State transactions by customers connected to
[2025] 4 S.C.R.                                                         475

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


           transmission/distribution network of the State licensees
           shall be governed by the pricing mechanism as specified
           below:
                (i) Any under-injection with respect to the schedule
                approved by the SLDC by an open access customer
                shall be settled at higher of the applicable deviation
                rates as notified in CERC Deviation Settlement
                Mechanism Regulations 2014 amended from time to
                time or energy charge at the rate of Temporary Tariff
                applicable for HT (NDS) category as determined by
                the Commission from time to time;
                (ii) Any over-injection upto 5% in a time block of 15
                minutes and averaging upto 1% over a day with
                respect to the schedule approved by the SLDC by
                an open access customer shall be compensated at
                the deviation charge rate at frequency of 50 Hz. or
                applicable deviation charge rate (as notified in CERC
                Deviation Settlement Mechanism Regulations 2014
                amended from time to time) whichever is less;
                (iii) Any underdrawl with respect to the schedule
                approved by the SLDC by an open access consumer
                shall not be compensated and this underdrawl shall
                be considered to be attributable to the consumer;
                (iv) Any over drawl with respect to the schedule
                approved by the SLDC by an open access customer
                who is not a consumer of Distribution Licensee of
                his area of supply shall be settled at higher of the
                applicable deviation rates (as notified in CERC
                Deviation Settlement Mechanism Regulations 2014
                amended from time to time) or energy charge at rate
                of Temporary Tariff applicable for HT (NDS) category
                as determined by the Commission from time to time;
                (v) Any over drawl with respect to the schedule
                approved by the SLDC, by an open access customer
                who is also a consumer of Distribution Licensee of
                his area of supply, shall be considered as the drawal
                from Discom and the open access consumer shall
476                                                    [2025] 4 S.C.R.

                 Digital Supreme Court Reports


            be required to pay charges for the excess capacity
            utilized computed in the manner specified in regulation
            26 for the entire month equal to the same percentage
            of the fixed and energy charges by which percentage
            the excess demand has actually been availed during
            the month on the rates specified in the tariff orders
            in force. However, the excess capacity utilized up to
            5% of capacity allocation occurring to the extent of
            two time blocks of 15 minutes each during a month
            shall be exempted.

               xxx                 xxx                 xxx
       R.26. Compliance and Grid Discipline
       (1) The open access customer shall abide by the Indian
       Electricity Grid Code, the State Grid Code and instructions
       given by State Transmission Utility and State Load Dispatch
       Centre as applicable from time to time.
       (2) The open access customer shall also comply with
       the requirements of the CEA (Technical Standards for
       Connectivity to the Grid) Regulations, 2007 as amended
       from time to time.
       (3) The open access consumer shall restrict the sum of his
       total drawal from all sources including open access and
       Distribution Licensee up to the total sanctioned contract
       demand with the Distribution Licensee.
       Provided that open access may be allowed over and above
       the contract demand to a consumer who sources power
       both by captive generation and Discom to the extent of
       captive power supply subject to availability of transmission
       and/or distribution system as the case may be.
       Provided further that long term open access may be
       allowed over and above the contract demand to the extent
       of sanctioned open access capacity.
       (4) The consumer shall be levied fixed charge based on
       the maximum demand recorded in the ABT meter as per
       tariff applicable from time to time.
[2025] 4 S.C.R.                                                          477

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


           Provided that if the open access is allowed over and above
           the contract demand in terms of proviso to sub regulation
           (3) above, the fixed charges shall be levied based on the
           total demand recorded in the ABT meter less open access
           demand scheduled in terms of proviso of sub regulation
           (3) above.
           (5) The long term/ medium term open access customer
           shall provide the injection schedule at the generator end
           and drawal schedule at the supply end to SLDC, RDPPC,
           supplier end Distribution Licensee and to the consumer end
           Distribution Licensee before 10.00 AM of the day preceding
           the day of scheduling. The Injection schedule shall have the
           open access consumer and supplier identification. Where
           open access is provided to more than one open access
           consumer, supplier shall provide a break up of injection
           schedule as applicable to each open access consumer
           considering that the adjustment of energy in such case
           shall be as per Regulation 25.
           (6) The short term open access customer shall provide the
           injection/drawal schedule for intra-State transactions every
           day to the SLDC, RDPPC and the Distribution Licensee
           before 10:00 AM of the day preceding the day of drawal/
           injection as per the open access capacity sanctioned.
           (7) The power purchase under short term inter-State open
           access including transactions through power exchange
           shall be subject to the following:
                (i) The consumer shall schedule power from open
                access for complete 24 hours of the day.
                (ii) The consumer shall intimate in writing the block
                wise maximum power to be scheduled from inter-
                State open access each day to the SLDC, RDPPC
                and Distribution Licensee before 10:00AM of the day
                preceding the day of drawal.
                (iii) The schedule so given shall be uniform at least
                for a period of eight hours and the minimum schedule
                during the day shall at any time not be less than 75%
                of the maximum schedule of the day.
478                                                         [2025] 4 S.C.R.

                      Digital Supreme Court Reports


                 (iv) The schedule so given shall be used to calculate
                 the block wise maximum admissible drawal from the
                 Discom.
                 (v) If actual schedule approved in inter-State
                 transactions is less, then the admissible drawal shall
                 be reduced to that extent.
            (8) If the actual drawal in a block is higher than the
            admissible drawal, then the percentage excess drawal
            shall be calculated on the admissible drawal and the
            highest percentage of such excess drawal of all blocks
            during a month shall be considered as excess capacity
            (demand) utilized during that month and shall be billed as
            per regulation 21(v).
            (9) Annual maintenance outage, other maintenance outage
            and forced outage shall be subject to the provisions of the
            State Grid Code. Intimation of the forced outage shall be
            sent to SLDC and to the Distribution Licensees, within 30
            minutes of the outage and shall incorporate the estimated
            outage/rectification time. Restoration of unit under outage
            shall be conveyed to SLDC at least 30 minutes prior to
            its synchronization with the State Grid.
            (10) Wherever required, unity power factor shall be
            considered for the purpose of unit conversion from
            MVA/kVA to MW/kW or vice versa.”
43. Upon a judicious and careful consideration of the rival submissions
    made by the parties and perusal of the statutory provisions under
    the Act of 2003 and the Regulations of 2016, we are of the view that
    the contentions raised by the appellants, both inter-state as well as
    intra-state captive generators, cannot be agreed with in light of the
    objectives of the Act of 2003 which the Regulations of 2016 seek
    to achieve.

       I.   Whether the RERC had the jurisdiction to regulate
            inter-state open access under the Act of 2003?
44. The primary contention of the appellants regarding the jurisdiction
    of the RERC to regulate inter-state open access is without any
    merit. The Act of 2003 establishes a clear distinction between the
[2025] 4 S.C.R.                                                         479

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     regulatory functions of the CERC and State Commissions. While
     inter-state transmission falls within the domain of the CERC under
     Section 79(1)(c), the power of the State Commission to regulate
     intra-state transmission and distribution under Section 86(1)(c) is
     well established. Furthermore, the appellants’ argument that the
     Regulations of 2016 have an extraterritorial effect is misplaced. The
     Regulations of 2016 do not seek to regulate inter-state transmission
     per se but rather ensures that transactions impacting the Rajasthan
     grid remain under the oversight of the State Commission.
45. Section 79(1)(c) of the Act of 2003, defines the regulatory authority
    of the CERC over inter-state transmission of electricity. However,
    this provision does not strip State Commissions, including RERC,
    of their jurisdiction over intra-state aspects of open access. Section
    42(2) of the Act of 2003 expressly empowers State Commissions
    to regulate open access within their respective states, ensuring
    fair and non-discriminatory access to transmission and distribution
    networks within the state. Further, Section 42(3) of the Act of 2003
    provides that whenever a consumer, with premises within the area
    of supply of a distribution licensee, requires supply of electricity from
    a generating company other than such distribution licensee, such
    transmission and supply shall be in accordance with the regulations
    made by the State Commission.
46. The respondents have, in their submissions, drawn a relevant and
    appropriate parallel with the regulation of National Highways in the
    country, which also run across state borders. It has been rightly
    analogised by the RERC that even though National Highways falls
    under Entry 23 of List I of the Seventh Schedule of the Constitution
    of India and is a central subject, nevertheless when it passes through
    the respective states it is subject to tolls under the respective state
    laws as per Entry 59 of List II of the Seventh Schedule. Therefore,
    when ‘Electricity’ which is a subject matter of Entry 38, List III is
    wheeled from outside the state and distributed within the state, the
    regulations governing such distribution within the state cannot, by
    any stretch, be termed to be suffering from any excess of jurisdiction.
47. The key determinant is not the source of power but its delivery, end-
    user, and consumption within Rajasthan’s intra-state grid. The Act of
    2003 provides a framework for demarcating responsibilities between
    CERC and State Commissions, ensuring that intra-state aspects of
480                                                         [2025] 4 S.C.R.

                      Digital Supreme Court Reports


       electricity regulation remain within the purview of State Commissions.
       The appellants’ interpretation would render Section 42 redundant
       and contradict the legislative intent behind decentralizing regulatory
       authority to the State Commissions. Thus, the claim that only CERC
       has the authority to regulate inter-state open access cannot be
       accepted in light of the legislative intent behind the Act of 2003.
       Therefore, RERC retains jurisdiction over intra-state transactions
       even if the power originates from another state.
48. Further, Section 2(47) of the Act of 2003 defines open access as
    non-discriminatory access to transmission and distribution systems,
    encompassing both inter-state and intra-state transactions. The
    respondents argue that the statute does not differentiate between
    them for regulatory purposes, meaning that State Commissions
    naturally retain authority over open access within their jurisdictions.
    This interpretation aligns with Section 42, which explicitly grants State
    Commissions the power to regulate open access for consumers in
    their states. Additionally, Section 2(15) of the Act of 2003 defines a
    “consumer” as any person who receives electricity from a licensee
    or whose premises are connected to a distribution system. Since
    distribution licensees operate within state boundaries, the regulation
    of open access for consumers falls squarely within the State
    Commission’s jurisdiction. Section 2(17) further strengthens this
    position by defining a “distribution licensee” as an entity authorized
    to distribute electricity within a specific area, reinforcing the role of
    State Commissions in regulating transactions that ultimately facilitate
    electricity supply to consumers within the state.
49. Section 181 of the Act of 2003 empowers State Commissions to
    frame regulations necessary for implementing the provisions of
    the Act of 2003. This includes establishing conditions for open
    access, determining charges, and ensuring fair access to intra-
    state transmission and distribution networks. By granting State
    Commissions the authority to introduce and regulate open access,
    the legislature has clearly vested regulatory oversight with RERC
    in Rajasthan. The omission of any reference to CERC’s jurisdiction
    over open access consumers in Section 42 of the Act further
    reinforces the respondents’ argument. Section 79, which delineates
    CERC’s functions, does not extend its authority to the regulation of
    end consumers or the supply of power via distribution licensees.
    This omission is indicative of the legislature’s intent to keep such
[2025] 4 S.C.R.                                                         481

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     matters under State Commissions’ oversight, ensuring that electricity
     consumers and distribution networks within a state remain subject
     to state-level regulation.
50. Thus, the respondents’ argument is well-founded in statutory
    provisions, legislative intent, and the structural framework of the
    Act of 2003. RERC’s authority to regulate intra-state aspects of
    open access transactions, even when electricity is sourced from
    another state, aligns with the Act’s objectives and ensures effective
    regulatory oversight.

     II.   Whether the imposition of penalties for variations in drawal
           from contracted demand amounts to an unreasonable
           restriction on the right to open access under Section 42
           of the Act of 2003?
51. The imposition of penalties for variations in drawal from contracted
    demand is a regulatory measure designed to ensure grid stability and
    prevent commercial gaming in the electricity market. The respondents
    contend that such penalties are neither arbitrary nor unreasonable
    but are a necessary mechanism to maintain the reliability of the
    grid. The Act of 2003 guarantees non-discriminatory open access to
    consumers but does not exempt them from complying with regulatory
    conditions essential for the effective functioning of the electricity
    network. Regulation of drawal variations is crucial for balancing power
    supply and demand, particularly in the context of the grid’s technical
    constraints and the need to prevent unscheduled fluctuations that
    may disrupt the system.
52. Further, the penalty mechanism is not an unreasonable restriction
    but rather a measure to ensure that consumers adhere to their
    contractual obligations, preventing undue burden on the system and
    other stakeholders. Uncontrolled variations can lead to deviations
    that may cause frequency imbalances, affecting overall grid security.
    Section 32 and Section 33 of the Act of 2003 empower SLDCs to
    ensure the smooth operation of the power system, which includes
    imposing necessary safeguards against unregulated deviations. The
    penalties, therefore, serve a larger public interest by deterring erratic
    consumption patterns and aligning open access with grid discipline.
53. Additionally, the regulations apply uniformly to all open access
    consumers, ensuring that there is no arbitrary targeting or
482                                                           [2025] 4 S.C.R.

                        Digital Supreme Court Reports


       discrimination. The principle of open access is not absolute and must
       be exercised in a manner that does not compromise the operational
       integrity of the power sector. Therefore, the imposition of penalties
       for variations in drawal is a justifiable regulatory measure that aligns
       with the objectives of the Act of 2003 and does not amount to an
       unreasonable restriction on open access.
54. The electricity grid operates on principles of frequency stability
    and demand-supply balance. Any deviation from scheduled drawal
    or injection can lead to grid instability, potentially affecting all
    consumers. The impugned regulations, therefore, serve a critical
    function in preventing such disruptions by enforcing discipline
    among generators and consumers alike. The penalties imposed are
    a deterrent mechanism to prevent strategic gaming of the system
    and to ensure that all stakeholders adhere to scheduling norms. The
    State Commission’s role is to balance the rights of individual market
    participants with the broader objective of ensuring an efficient, reliable,
    and stable power supply to all consumers in the State.

       III.   Whether Regulation 26(7) is ultra vires for requiring an
              advance notice of 24 hours, thereby preventing urgent
              procurement and creating an artificial barrier to open access
              as protected by the Act of 2003?
55. The Act of 2003 was enacted with the objective of promoting
    competition, efficiency, and consumer interest while ensuring the
    stability of the electricity grid. The RERC’s regulations align with
    these objectives by:
       i.     Ensuring predictability and reliability in power supply through
              scheduling norms,
       ii.    Preventing market distortions by imposing penalties for
              deviations that can destabilize grid operations, and
       iii.   Curtailing gaming practices where open access consumers,
              particularly captive power generators, might manipulate the
              grid to gain an undue advantage.
56. Regulation 26(7), which mandates a 24-hour advance notice for
    availing short-term inter-state open access, serves a critical function
    in maintaining grid stability and ensuring proper scheduling of power.
    The respondents argue that this requirement is not ultra vires but is
[2025] 4 S.C.R.                                                      483

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     in consonance with the broader regulatory framework governing open
     access transactions. The power system operates on a structured
     scheduling mechanism, and unregulated short-term access without
     prior notice could lead to disruptions, frequency imbalances, and
     operational inefficiencies. The Act of 2003 does not provide an
     absolute right to open access but subjects it to conditions necessary
     for the reliability and efficiency of power distribution.
57. The requirement of prior notice is a reasonable procedural safeguard
    that aligns with the objectives of the Act of 2003, particularly those
    laid out in Section 42, which envisages a structured approach
    to open access. The 24-hour notice period ensures that both
    transmission and distribution licensees, as well as load despatch
    centres, have adequate time to adjust their schedules and prevent
    system disturbances. Moreover, it prevents misuse by entities that
    may attempt to take advantage of real-time price fluctuations, thereby
    engaging in speculative trading rather than genuine demand-based
    procurement. Further, the option of purchasing power from the real-
    time market and day-ahead market in need of urgent procurement is
    always available, and is not prevented by the impugned regulations.
58. Furthermore, the regulation does not create an insurmountable barrier
    to open access but rather seeks to bring order and predictability
    to its implementation. The requirement is uniformly applicable
    to all consumers, ensuring that no undue advantage is given to
    any particular category. Considering the technical and regulatory
    imperatives involved, the 24-hour advance notice condition under
    Regulation 26(7) cannot be considered ultra vires, as it falls within
    the regulatory domain of the State Commission to establish fair,
    transparent, and non-disruptive mechanisms for open access.

     IV.   Whether the Regulation 21 is arbitrary and discriminatory,
           thereby discouraging captive power generation by creating
           unreasonable distinction between captive generators and
           state distribution companies?
59. The appellants’ argument that the regulations unfairly burden
    CPPs is misplaced. The impugned regulations apply uniformly to
    all power generators availing open access, whether captive or non-
    captive. Section 9 of the Act of 2003 recognizes the rights of captive
    generators but does not exempt them from compliance with open
484                                                          [2025] 4 S.C.R.

                      Digital Supreme Court Reports


       access regulations framed under Section 42 of the Act of 2003. The
       regulatory measures—such as scheduling, penalties for deviations,
       and drawal limits—are imposed in furtherance of the larger goal of
       grid discipline and market stability. There is no evidence to suggest
       that captive generators are being singled out or subjected to harsher
       conditions compared to other generators.
60. Regulation 21, which governs aspects of scheduling, penalties, and
    compliance for captive power generators, has been challenged on the
    ground that it creates an unreasonable distinction between captive
    generators and state DISCOMs, allegedly discouraging captive
    generation. However, the respondents argue that the regulation is
    neither arbitrary nor discriminatory but rather a necessary framework
    to ensure that all power generators operate under fair and transparent
    rules. The Act of 2003, through Sections 9 and 42, recognizes the rights
    of captive power generators while also subjecting them to regulatory
    oversight to prevent system inefficiencies and inequitable advantages.
61. The distinction between captive power generators and state DISCOMs
    is not arbitrary but arises from the structural differences in their roles
    and obligations. While captive generators primarily generate electricity
    for self-consumption, distribution companies serve a wider consumer
    base, requiring them to adhere to broader regulatory commitments,
    including universal supply obligations. As such, differential treatment
    based on the nature of their functions is legally justified and does
    not amount to unfair discrimination. Moreover, Regulation 21 does
    not impose undue restrictions on captive generators but ensures that
    their operations align with grid discipline, preventing any adverse
    impact on the larger power ecosystem.
62. Additionally, the principle of non-discrimination under the Act of 2003
    does not mandate identical treatment for all entities but rather requires
    a rational basis for any differentiation. In this case, the regulatory
    conditions imposed on captive generators are aimed at ensuring a
    level playing field and preventing misuse of open access provisions.
    The regulatory framework ensures that captive generators contribute
    fairly to system stability without imposing additional burdens on
    distribution licensees and other grid participants. Thus, Regulation
    21 is neither arbitrary nor discriminatory but rather a necessary and
    proportionate measure to balance the interests of various stakeholders
    in the electricity sector.
[2025] 4 S.C.R.                                                         485

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     V.    Whether the appellants’ right of open access is foreclosed
           by the Regulations of 2016?
63. The appellants argue that the Regulations of 2016 impose
    unreasonable restrictions on captive power generators, effectively
    foreclosing their right to open access as guaranteed under Section
    9 of the Act of 2003. However, the respondents contend that the
    Regulations of 2016 do not foreclose open access but rather
    prescribe conditions necessary for its fair and efficient implementation.
    Section 42 of the Act provides for non-discriminatory open access
    but also subjects it to regulations framed by the State Commission
    to ensure grid security, operational discipline, and non-disruptive
    power transactions. The restrictions imposed by the Regulations of
    2016 are thus regulatory safeguards rather than prohibitive barriers.
64. A careful analysis of the Regulations of 2016 indicates that they
    primarily aim at maintaining the reliability of the electricity grid,
    ensuring fair pricing, and preventing speculative misuse of open
    access provisions. The requirement of advance notice for short-term
    open access, penalties for deviations from contracted demand, and
    specific conditions for captive power generators are all designed
    to create a structured and predictable electricity market. These
    provisions do not prevent eligible consumers from availing open
    access but instead ensure that they do so within a framework that
    safeguards the interests of all stakeholders, including distribution
    licensees and other consumers. Moreover, Section 181 of the Act of
    2003 empowers State Commissions to frame regulations necessary
    for implementing statutory provisions, thereby validating the regulatory
    measures introduced by RERC.
65. Furthermore, the Act of 2003, envisages a balance between the
    rights of open access consumers and the operational concerns of
    the power sector. The Regulations of 2016, while imposing certain
    conditions, do not outright deny open access but ensure that its
    implementation is equitable and does not jeopardize grid discipline.
    Open access remains available to consumers who comply with
    regulatory prerequisites, including scheduling obligations and
    financial commitments. Thus, the appellants’ assertion that their
    right to open access is foreclosed is misplaced. The Regulations
    of 2016 are consistent with the legislative intent of the Act of 2003,
    ensuring that open access is exercised in a manner that does not
486                                                            [2025] 4 S.C.R.

                       Digital Supreme Court Reports


       compromise system stability, fairness, or economic viability. Therefore,
       the regulatory framework does not foreclose open access but rather
       operationalizes it within reasonable constraints essential for sustaining
       the electricity sector.

       CONCLUSION
66. The statutory scheme under the Act of 2003 mandates that regulations
    framed by State Commissions must serve the larger public interest.
    The respondents have successfully established that the impugned
    regulations serve this purpose by ensuring equitable treatment of all
    market participants while safeguarding the integrity of the power grid.
67. The RERC derives its authority from the Act of 2003, which vests in
    it the power to frame regulations governing open access, scheduling,
    and penalties. Section 86(1)(c) of the Act of 2003 specifically
    empowers State Commissions to facilitate intra-state transmission
    and wheeling of electricity. Furthermore, Section 181 empowers the
    Commission to make regulations consistent with the Act of 2003
    and its objectives. The impugned regulations have been framed in
    exercise of these statutory powers. The requirement for scheduling,
    imposition of penalties, and limits on drawal are not arbitrary but are
    measures falling within the regulatory ambit of the Commission to
    ensure grid stability and fair competition. The Act of 2003 envisions
    a structured and fair mechanism for open access while ensuring that
    market participants do not engage in practices detrimental to the
    larger consumer base. Moreover, under Section 42 of the Act of 2003,
    the State Commission has the mandate to regulate open access in
    distribution and specify the charges and conditions applicable. The
    respondents have demonstrated that these conditions are necessary
    for maintaining discipline in power scheduling and ensuring that
    open access consumers do not gain an unfair advantage over other
    consumers by evading scheduling norms or penalties.
68. The Jodhpur Bench in common order dated 29.08.2016, which has
    been challenged before us in Civil Appeals No. 7965 of 2019 and
    7966 of 2019, has rightly upheld the validity of the Regulations of
    2016 holding that any inconvenience caused or even some hardship
    faced by the captive power generators shall not make the regulations
    illegal. The High Court also rightly pointed out that the appellants have
    failed to establish that the impugned regulations are in contravention
[2025] 4 S.C.R.                                                        487

     Ramayana Ispat Pvt. Ltd. and Anr. v. State of Rajasthan & Ors.


     of their rights protected under Part-III or any other provision of the
     Constitution of India or that the regulations have been enacted without
     having the competence to do so or they are manifestly arbitrary or
     unreasonable. It has been rightly held by the High Court that the
     Regulations of 2016 are in consonance with the objects of the Act of
     2003 and have been framed as per the competence available under
     Section 181 read with Section 42 of the Act of 2003.
69. The Jaipur Bench in its order dated 06.09.2016, which has been
    challenged before us in Civil Appeal No. 7964 of 2019, has rightly
    held that the issues before it, were squarely covered by the order
    of Jodhpur Bench.
70. In light of the above discussion, the appeals are dismissed, and the
    orders of the High Court are upheld.

     Result of the case: Appeals dismissed.



     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Rajasthan Electricity Regulatory Commission (RERC)"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

RAMAYANA ISPAT PVT. LTD. AND ANR. versus STATE OF RAJASTHAN & ORS. — 2025 INSC 424 - Legal Desk AI