Patna High Court

Surjeet KumarversusThe State of Bihar

Decided
Disposal
DISPOSED

Holding

The acquisition proceedings have not lapsed and the petitioners are entitled to compensation at current market rates under the 2013 Act.

Summary

The petitioners purchased land and were in possession when BSF personnel stopped construction, claiming the land was under acquisition (Case No. 35/2022‑21) for a BSF Vahini Headquarters. They received no notice, possession was not taken, and no compensation was paid despite multiple representations. The petitioners sought a declaration that the acquisition had lapsed, compensation at current market rates, and full details of the proceedings, invoking Article 300A of the Constitution. The Court examined the Supreme Court’s decision in Indore Development Authority v. Manoharlal, interpreting Section 24 of the 2013 Land Acquisition Act, and held that the acquisition has not lapsed because possession was never taken and compensation remains unpaid. Relying on the jurisprudence of Vidaya Devi and Dharnidhar Mishra on Article 300A, the Court directed the authorities to recalculate and pay compensation at the prevailing market rate. The writ petition was disposed with the order to pay compensation.

Issues considered

  • Whether the land acquisition proceedings have lapsed under Section 24 of the Land Acquisition Act, 2013.
  • Whether the petitioners are entitled to compensation despite the absence of possession or notice.
  • Whether the actions of the authorities violate Article 300A of the Constitution of India.

Legislation cited

Subjects

  • land acquisition
  • compensation
  • Article 300A
  • lapse of proceedings
  • Right to Fair Compensation Act
  • property rights
  • procedural due process

Judgment

                     IN THE HIGH COURT OF JUDICATURE AT PATNA
                                Civil Writ Jurisdiction Case No.2233 of 2026
                 ======================================================
           1.     Surjeet Kumar S/o Late Ram Badan Singh, R/o A/3 Vivekanand Park Lane,
                  A.S.E Patliputra Colony, Boring Road, Dist.-Patna.
           2.    Ranjit Kumar, S/o Ramyash Rai, R/o A/3 Vivekanand park lane, A.S.E
                 Patliputra Colony, Boring Road, Dist.- Patna.

                                                                               ... ... Petitioner/s
                                                   Versus
           1.    The State of Bihar through Principal Secretary, Revenue and Land Reforms,
                 Bihar, Patna.
           2.    Principal Secretary, Revenue and Land Reforms, Bihar, Patna.
           3.    District Magistrate-cum-Collector, Patna.
           4.    District Land Acquisition Officer, Patna.
           5.    Circle Officer, Bikram, Patna.

                                                           ... ... Respondent/s
                 ======================================================
                 Appearance :
                 For the Petitioner/s   :         Mr.Parth Gaurav, Advocate.
                 For the Respondent/s   :         Standing Counsel 10
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE PURNENDU SINGH
                                       ORAL ORDER

2   10-02-2026                  Heard learned counsel appearing on behalf of the

                   petitioners and learned counsel for the State.

                               2. The petitioners in paragraph no. 1 of the present

                   writ petition have sought, inter alia, the following relief(s),

                   which is reproduced hereinafter:-

                                              “A. To hold that the Land Acquisition
                                  proceeding with respect to the land in question bearing
                                  Land Acquisition Case No. 35/2022-21 has since elapsed as
                                  the possession still vests with the petitioners.
                                              B. In alternative, direct the Respondent
                                  authorities to grant compensation to the Petitioners for
                                  their acquired land enumerated detailed at Paragraph 4 of
                                  this application at the present market rate when possession
                                  is being taken.
                                              C. Directing the Respondent authorities to
                                  provide the full details of Land Acquisition Proceedings
                                  under which the lands of the Petitioners have been
Patna High Court CWJC No.2233 of 2026(2) dt.10-02-2026
                                            2/8




                          acquired.
                                      D. Directing the Respondent Authorities to pay
                          Rs. 30,00,000/- as compensation besides the compensation
                          for acquisition to each of the Petitioners as the Authorities
                          have acted arbitrarily, depriving the Petitioners of a fair
                          and transparent proceedings and by not providing any
                          information related to the said proceeding thus violating the
                          rights of Petitioners enshrined under Article 300 A of
                          Constitution of India.
                                      E. Any other relief/reliefs for which the
                          petitioner deemed entitled for.”

                      3. Brief facts of the case is that the petitioners, after

          purchasing the land through registered sale deeds and obtaining

          mutation in their favour, were in peaceful possession and

          enjoyment of the land and had also commenced construction

          thereon, which was abruptly stopped by BSF personnel without

          any written order on the ground that the land was under

          acquisition; being unaware of any such acquisition and having

          received neither notice nor compensation, the petitioners

          approached the District Land Acquisition Officer, Patna, who

          vide order dated 13.10.2023 informed that the land has been

          acquired in Land Acquisition Case No. 35 of 2022–21 for

          construction of BSF Vahini Headquarters, allegedly pursuant to

          a declaration published in Hindustan Newspaper dated

          26.06.2020, and advised the petitioners to submit a fresh

          representation for compensation. Accordingly, the petitioners

          submitted       multiple       representations      dated      30.09.2024,

          09.12.2025, 18.12.2025, 30.12.2025, 20.01.2026 and finally
Patna High Court CWJC No.2233 of 2026(2) dt.10-02-2026
                                            3/8




          21.01.2026 seeking information and payment of compensation,

          highlighting that they continued to remain dispossessed in effect

          for more than five years over a substantial area of land

          measuring 199.156 decimals, despite boundary walls and a

          residential      structure       standing      thereon,     but    all   such

          representations were met with complete silence, compelling the

          petitioners to approach this Court due to the arbitrary, and

          unconstitutional action of the respondents.

                      4. Learned counsel appearing on behalf of the

          petitioners submitted that the action of the respondents in

          depriving the petitioners of the use and enjoyment of their land

          without serving any notice, without following due process of

          law and without payment of just and fair compensation is ex

          facie illegal, arbitrary and violative of Article 300A of the

          Constitution      of    India,     rendering     the      entire   acquisition

          proceedings vitiated in law, and therefore the petitioners are

          entitled to appropriate reliefs including protection of their

          property rights and payment of lawful compensation in

          accordance with law.

                      5. Per contra, learned counsel for the State submitted

          that no information has been given in the pleadings made in the

          present writ petition, as to whether, the petitioners approached
Patna High Court CWJC No.2233 of 2026(2) dt.10-02-2026
                                            4/8




          the Land Acquisition Officer, Patna with a prescribed format

          and the petitioners before exercising their right straight away

          filed the present writ petition, which is premature and fit to be

          dismissed by this Court.

                      6. Heard the Parties.

                      7. Having considered the rival submissions made on

          behalf of the parties and upon perusal of the materials available

          on record, it appears that the dispute essentially pertains to the

          determination and payment of compensation under the relevant

          land acquisition         by    the Government           for    BSF Vahini

          Headquarters Project. The petitioners contend that the

          compensation award is pending since 5 years, seeking payment

          in terms of the applicable Government Resolution. The legal

          position governing such issues is no longer res integra and

          stands authoritatively settled by the Apex Court in the case of

          Indore Development Authority vs. Manoharlal and Others,

          reported in AIR 2020 SC 1496 which is reproduced hereinafter:

                                  “366. In view of the aforesaid discussion, we answer the
                                  questions as under:
                                  366.1. Under the provisions of Section 24(1)(a) in case
                                  the award is not made as on 1-1-2014, the date of
                                  commencement of the 2013 Act, there is no lapse of
                                  proceedings. Compensation has to be determined under
                                  the provisions of the 2013 Act.
                                  366.2. In case the award has been passed within the
                                  window period of five years excluding the period covered
                                  by an interim order of the court, then proceedings shall
                                  continue as provided under Section 24(1)(b) of the 2013
                                  Act under the 1894 Act as if it has not been repealed.
                                  366.3. The word “or” used in Section 24(2) between
Patna High Court CWJC No.2233 of 2026(2) dt.10-02-2026
                                            5/8




                                  possession and compensation has to be read as “nor” or
                                  as “and”. The deemed lapse of land acquisition
                                  proceedings under Section 24(2) of the 2013 Act takes
                                  place where due to inaction of authorities for five years
                                  or more prior to commencement of the said Act, the
                                  possession of land has not been taken nor compensation
                                  has been paid. In other words, in case possession has
                                  been taken, compensation has not been paid then there is
                                  no lapse. Similarly, if compensation has been paid,
                                  possession has not been taken then there is no lapse.
                                  366.4. The expression “paid” in the main part of Section
                                  24(2) of the 2013 Act does not include a deposit of
                                  compensation in court. The consequence of non-deposit
                                  is provided in the proviso to Section 24(2) in case it has
                                  not been deposited with respect to majority of
                                  landholdings then all beneficiaries (landowners) as on
                                  the date of notification for land acquisition under Section
                                  4 of the 1894 Act shall be entitled to compensation in
                                  accordance with the provisions of the 2013 Act. In case
                                  the obligation under Section 31 of the Land Acquisition
                                  Act, 1894 has not been fulfilled, interest under Section 34
                                  of the said Act can be granted. Non-deposit of
                                  compensation (in court) does not result in the lapse of
                                  land acquisition proceedings. In case of non-deposit with
                                  respect to the majority of holdings for five years or more,
                                  compensation under the 2013 Act has to be paid to the
                                  “landowners” as on the date of notification for land
                                  acquisition under Section 4 of the 1894 Act.
                                  366.5. In case a person has been tendered the
                                  compensation as provided under Section 31(1) of the
                                  1894 Act, it is not open to him to claim that acquisition
                                  has lapsed under Section 24(2) due to non-payment or
                                  non-deposit of compensation in court. The obligation to
                                  pay is complete by tendering the amount under Section
                                  31(1). The landowners who had refused to accept
                                  compensation or who sought reference for higher
                                  compensation, cannot claim that the acquisition
                                  proceedings had lapsed under Section 24(2) of the 2013
                                  Act.
                                  366.6. The proviso to Section 24(2) of the 2013 Act is to
                                  be treated as part of Section 24(2), not part of Section
                                  24(1)(b).
                                  366.7. The mode of taking possession under the 1894 Act
                                  and as contemplated under Section 24(2) is by drawing
                                  of inquest report/memorandum. Once award has been
                                  passed on taking possession under Section 16 of the 1894
                                  Act, the land vests in State there is no divesting provided
                                  under Section 24(2) of the 2013 Act, as once possession
                                  has been taken there is no lapse under Section 24(2).
                                  366.8. The provisions of Section 24(2) providing for a
                                  deemed lapse of proceedings are applicable in case
                                  authorities have failed due to their inaction to take
                                  possession and pay compensation for five years or more
                                  before the 2013 Act came into force, in a proceeding for
                                  land acquisition pending with the authority concerned as
                                  on 1-1-2014. The period of subsistence of interim orders
                                  passed by court has to be excluded in the computation of
Patna High Court CWJC No.2233 of 2026(2) dt.10-02-2026
                                            6/8




                                  five years.
                                  366.9. Section 24(2) of the 2013 Act does not give rise to
                                  new cause of action to question the legality of concluded
                                  proceedings of land acquisition. Section 24 applies to a
                                  proceeding pending on the date of enforcement of the
                                  2013 Act i.e. 1-1-2014. It does not revive stale and time-
                                  barred claims and does not reopen concluded
                                  proceedings nor allow landowners to question the
                                  legality of mode of taking possession to reopen
                                  proceedings or mode of deposit of compensation in the
                                  treasury instead of court to invalidate acquisition.”



                           8. It is also to be taken note of that Article 300A of

          the Constitution of India, which tends to safeguard the

          invaluable right to property.

                                  “300-A. Persons not to be deprived of property
                                  save by authority of law
                                  No person shall be deprived of his property save by
                                  authority of law.”
                          9. The State cannot disposes a citizen of his

          property except in accordance with law and procedure

          prescribed. The obligation to pay compensation is not

          expressively included in Article 300-A of the Constitution of

          India can be inferred in that Article. The law in this regard is

          well settled by the Apex Court in case of Vidaya Devi Vs. The

          State of Himachal Pradesh & Ors. reported in 2020(2) SCC

          569, I find it proper to quote Para-12.1 and 12.2 of the said

          judgment, which are inter alia reproduced hereinafter;

                                  “12.1. The appellant was forcibly expropriated of her
                                  property in 1967, when the right to property was a
                                  fundamental right guaranteed by Article 31 in Part III of
                                  the Constitution. Article 31 guaranteed the right to
                                  private property [State of W.B. v. Subodh Gopal Bose,
                                  (1953) 2 SCC 688 , which could not be deprived without
                                  due process of law and upon just and fair compensation.
Patna High Court CWJC No.2233 of 2026(2) dt.10-02-2026
                                            7/8




                                  12.2. The right to property ceased to be a fundamental
                                  right by the Constitution (Forty-Fourth Amendment) Act,
                                  1978, however, it continued to be a human right
                                  [Tukaram Kana Joshi v. MIDC, (2013) 1 SCC 353 in a
                                  welfare State, and a constitutional right under Article
                                  300-A of the Constitution. Article 300-A provides that no
                                  person shall be deprived of his property save by
                                  authority of law. The State cannot dispossess a citizen of
                                  his property except in accordance with the procedure
                                  established by law. The obligation to pay compensation,
                                  though not expressly included in Article 300-A, can be
                                  inferred in that Article. [K.T. Plantation (P) Ltd. v. State
                                  of Karnataka, (2011) 9 SCC 1”



                      10. The above proposition of law has again been

          reiterated by the Apex Court in the case of Dharnidhar Mishra

          (D) and Another vs. State of Bihar and Others, in Civil Appeal

          No. 6351 of 2024, reported in (2024) 10 Supreme Court Cases

          605, is relevant. The paragraph is reproduced as under:–

                                      “ 16. The right to property ceased to be a
                          fundamental right by the Constitution (Forty-fourth
                          Amendment) Act, 1978, however, it continued to be a human
                          right in a welfare State, and a constitutional right under
                          Article 300-A of the Constitution. Article 300-A provides
                          that no person shall be deprived of his property save by
                          authority of law. The State cannot dispossess a citizen of his
                          property except in accordance with the procedure
                          established by law. The obligation to pay compensation,
                          though not expressly included in Article 300-A, can be
                          inferred in that Article. [See: K.T. Plantation (P) Ltd. v.
                          State of Karnataka [K.T. Plantation (P) Ltd. v. State of
                          Karnataka, (2011) 9 SCC 1.”


                      11. In such circumstances, when the question of right

          to property as per the provision of Article 300 A of the

          Constitution of India comes to the knowledge of this Court and

          also in view of the recorded evidence and the established MVR

          of the area, in which vicinity, petitioners’ land has been
          Patna High Court CWJC No.2233 of 2026(2) dt.10-02-2026
                                                      8/8




                    acquired, this Court has no alternative than to direct the

                    concerned authority to give due regard to the same and

                    recalculate the amount of compensation at the current rate of

                    MVR so that the petitioners should not be made to suffer

                    financially in any manner. The claim of the petitioners is

                    supported by the judgment of the Apex Court in the case of

                    Indore Development Authority Vs. Manohar Lal & Ors.,

                    reported in AIR 2020 SC 1496 and the amendment brought in

                    the Right to Fair Compensation and Transparency in Land

                    Acquisition, Rehabilitation and Resettlement Act, 2013 in the

                    year 2018. Admittedly, in the present case, the petitioners have

                    not received the amount of compensation till date.

                                12. The writ petition is, accordingly, disposed of.


                                                       (Purnendu Singh, J)

mantreshwar/-

U


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.